1 A Project Report on Heuristic Methods for Solving the Resource-Constrained Project Scheduling ProblemsBased on Edward W. Davis, James H. Patterson. (1975). A Comparison of Heuristic and Optimum Solutions in Resource Constrained Optimum Scheduling. Management Science, Vol.21, No. 8Submitted By: Amit Kumar 12 Ayanangshu Das 28 Naveen Tiwari 59

Upload: amit15094775

Post on 22-Oct-2014

733 views

Category:

Documents


4 download

DESCRIPTION

A Project Report on“Heuristic Methods for Solving the Resource-Constrained Project Scheduling Problems”Based on“Edward W. Davis, James H. Patterson. (1975). A Comparison of Heuristic and Optimum Solutions in Resource Constrained Optimum Scheduling. Management Science, Vol.21, No. 8”Submitted By: Amit Kumar 12 Ayanangshu Das 28 Naveen Tiwari 591NATIONAL INSTITUTE OF INDUSTRIAL ENGINEERING MUMBAICERTIFICATEThis is to certify that Amit Kumar, Ayanangshu Das & Naveen Tiwari, students

TRANSCRIPT

Page 1: Project Management Heuristics for solving RCPSP

1

A Project Report on

“Heuristic Methods for Solving the Resource-Constrained

Project Scheduling Problems”

Based on

“Edward W. Davis, James H. Patterson. (1975). A Comparison of Heuristic and

Optimum Solutions in Resource Constrained Optimum Scheduling. Management

Science, Vol.21, No. 8”

Submitted By:

Amit Kumar 12

Ayanangshu Das 28

Naveen Tiwari 59

Page 2: Project Management Heuristics for solving RCPSP

2

NATIONAL INSTITUTE OF INDUSTRIAL ENGINEERING

MUMBAI

CERTIFICATE

This is to certify that Amit Kumar, Ayanangshu Das & Naveen Tiwari, students of PGDIE, Batch No.: 40

have successfully completed the project titled “Heuristic Methods for Solving the Resource-Constrained

Project Scheduling Problems” at NITIE, Vihar Lake, Mumbai under guidance of Dr. L. Ganapathy

(Ph.D) Professor, NITIE, Mumbai from July 2011 to August 2011.

Date:

Faculty Guide:

Dr. L. Ganapathy,

(Ph.D) Professor,

NITIE, Mumbai.

Page 3: Project Management Heuristics for solving RCPSP

3

Table of Contents 1. Introduction to RCPSP ................................................................................................................... 4

2. Problem Definition .......................................................................................................................... 4

3. Heuristic Methods for solving RCPSP ........................................................................................... 5

4. Modelling usingMATLAB .............................................................................................................. 8

5. Modelling using RESCON ............................................................................................................ 16

6. Heuristic and Meta-Heuristics Currently in use ........................................................................ 26

List of Figures

Figure 1 : Activity On Node Network ........................................................................................................................... 4

Figure 2 : SPAR 1 based Scheduler Flowchart ............................................................................................................ 7

Figure 3 : Result using GRD Heuristic ....................................................................................................................... 14

Figure 4 : Result using LFT Heuristic ........................................................................................................................ 14

Figure 5 : Result using MINSLK Heuristic ................................................................................................................ 15

Figure 6 : Result using RAN Heuristic ........................................................................................................................ 15

Figure 7 : Result using SIO Heuristic ......................................................................................................................... 16

Figure 8 : RESCON Outputs ....................................................................................................................................... 17

Figure 9 : Activity On Node Diagram Generated by RESCON ............................................................................... 19

Figure 10 : Result using SIO Heuristic in RESCON ................................................................................................. 19

Figure 11 : Result using MINSLK Heuristic in RECON .......................................................................................... 20

Figure 12 : Result using LFT Heuristic in RESCON ................................................................................................. 20

Figure 13 : Result using RAN Heuristic in RESCON ................................................................................................ 21

Figure 14 : Result using the Branch & Bound exact Method ................................................................................... 21

Figure 15 : Resource Skyline of R1 using SIO Heuristic ........................................................................................... 22

Figure 16 : Resource Skyline for R2 using SIO Heuristic ......................................................................................... 22

Figure 17 : Resource Skyline for R3 using SIO Heuristic ......................................................................................... 23

Figure 18 : Performance summary using different heuristics .................................................................................. 25

Page 4: Project Management Heuristics for solving RCPSP

4

1. Introduction to RCPSP

The Resource Constrained Project Scheduling Problem (RCPSP) consists of minimizing the project

duration under fixed resource constraint. When the resources are available in plenty the only determining

factor for the project duration is the duration of each activity and more specifically the duration of activities

in the Critical Path. This non constrained project scheduling problem is the standard Critical Path analysis.

But when the resources are fixed, the scheduling and sequencing of activity becomes more important. The

RCPSP has been shown to be NP hard. Some optimal algorithms exist and the most efficient ones are based

on Branch and Bound approach but for projects with more activities/tasks they become very time

consuming. Heuristic Approaches have become popular over time.

2. Problem Definition

In the selected paper authors have generated fifty seven different computer generated networks having

twenty to twenty seven activities and used eight heuristic methods to solve these and compared the results

with the optimum solution for each of the networks. We have taken only one such network which was

shown in the paper for our simulation purpose.

The objective of this report is to simulate the same results as obtained by the authors in their study.

Figure 1 : Activity On Node Network

Page 5: Project Management Heuristics for solving RCPSP

5

The Activity on Node (AoN) representation is shown in Figure 1. It is clear that the problem consists of

a twenty seven activity project. The precedence relations are as shown in figure. The duration of each

activity is represented at the top of each activity node. There are three resources r1, r2 and r3 that activities

require in different numbers and these numbers are shown at the bottom of each activity node. The three

resources are limited to six units each.

3. Heuristic Methods for solving RCPSP

For modelling any of the heuristic methods first a scheduler has to be programmed. Scheduler is a

program that schedules the ready activities depending on the priority associated with these activities. The

heuristics are used to determine the priority level of these ready activities. The scheduler that we have

programmed is based on the famous Scheduling Program for Allocation of Resources (SPAR 1). The

detailed flowchart of the scheduler is shown in Figure 2. Please note that in this simulation we have assumed

that we are dealing with static RCPSP and hence activities once started are carried on till they are completed

and no pre-empting is allowed. Therefore the pre-emptive part of the SPAR has not been implemented in the

model.

In order to decide priorities among activities the following heuristic rules have been used. In case of a

tie, the activity with the smallest activity number is selected.

Minimum Job Slack (MINSLK)

Priority in resolving conflict is given to the activity with minimum slack. The slack is determined by

finding the difference of Late Start Time (LST) and Early Start Time (EST). The LST and EST are found

out by the usual Critical Path analysis. Slack is continuously updated. Any delayed activity has its slack

reduced by the amount of the delay.

Resource Scheduling Method (RSM)

Activity Priority is calculated as follows: Give precedence to that activity with the minimum value of dij,

where

dij = increase in project duration resulting when activity j follows activity I,

= max[0; (EFTi – LSTj)],

Where: EFTi = Early Finish Time of activity i

LSTj = Late start time of activity j

And the comparison is made on a pairwise basis among all activities in the conflict set.

Minimum Late Finish Time (LFT)

The priorities are assigned on the basis of the LFT of the activities.

Greatest Resource Demand (GRD)

This rule assigns priorities on the basis of total resource unit requirements of all types, with higher

priorities given for greater resource demands. Activity priority is calculated as:

Page 6: Project Management Heuristics for solving RCPSP

6

Priority = dj∑

where, dj = duration of activity j

rij = per period requirement of resource type i by activity j

m = number of different types of resources

Greatest Resource Utilization (GRU)

This rule gives priority to that combination of activities which results in maximum resource utilization in

each scheduling interval. This rule can be implemented by solving a zero one integer programming problem.

Shortest Imminent Operation (SIO)

This is the shortest job first rule and assigns priorities on the basis of activity duration.

Most Jobs Possible (MJP)

This rule gives priority to that combination of activities which results in the greatest number of activities

being scheduled in any interval. It is also implemented by solving a zero one integer programming problem.

Select Jobs Randomly (RAN)

This heuristic assigns priority among competing jobs on a purely random basis.

Page 7: Project Management Heuristics for solving RCPSP

7

Figure 2 : SPAR 1 based Scheduler Flowchart

Page 8: Project Management Heuristics for solving RCPSP

8

4. Modelling using MATLAB

MATLAB is also known as the language of Technical Computing. It is an IDE that provides

programming capability in which data operations in form of matrices can be performed easily. It is sold by a

company named Mathworks Inc. The opensource competition to this software provided by GNU is Scilab.

Scilab is freely downloadable from the internet.

The scheduler which is based on the SPAR as stated earlier is programmed in a separate file and the

different priority rules are programmed in separate files. The input to the scheduler is given by an excel file

which contains the precedence relationship, the duration of activities and the resource requirement of

activities and all the relevant data. The data corresponding to the problem under consideration is given in the

excel file and is shown for reference in Table 1:

The MATLAB code for the scheduler and the different priority rules is attached below for reference. The

result of solving the stated problem using the different priority rules is attached below in the form of Gantt

Charts. The charts have been generated in MATLAB. The code for this is also present and is indicated in the

scheduler file by comments.

Page 9: Project Management Heuristics for solving RCPSP

9

Table 1 : Input in form of excel file

Activity Time R1 R2 R3 Pre1 Pre2 Pre3 Pre4

1 0 0 0 0

2 5 3 5 2 1

3 5 5 4 3 1

4 3 5 2 2 1

5 4 4 1 4 2 3 6 1 5 5 4 4

7 6 3 5 2 4

8 2 2 4 4 2 3 9 6 3 2 2 5 8 7

10 3 3 2 4 8 6 7 11 3 3 3 2 6

12 1 4 1 4 5

13 3 1 4 4 9 10 14 6 2 2 2 12

15 3 5 5 4 9

16 4 1 5 4 11

17 4 4 5 4 15 16 18 3 3 2 3 14

19 3 5 3 3 13

20 1 2 4 6 16

21 4 1 6 4 19 18 22 6 3 2 1 17 20 23 4 1 0 4 19

24 1 2 2 1 17

25 3 0 1 3 23 21 24 22

26 3 2 2 2 23

27 0 0 0 0 25 26

%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%

%File Name :rcpm.m

% Resource Constraint Project Management Scheduler % Author: Amit Kumar % Date: 3rd August 2011

clearall; clc;

Input = xlsread('rcpm.xls'); sz = size(Input);

for i = 1:sz(1,1) activity(i).duration = Input(i,2); activity(i).resources = Input(i,3:5); activity(i).precedes = Input(i,6:9); activity(i).iscomplete = 0; activity(i).isrunning = 0; activity(i).isready = 0; activity(i).runtime = 0; activity(i).starttime = -1; activity(i).endtime = -1;

Page 10: Project Management Heuristics for solving RCPSP

10

activity(i).est = -1; activity(i).eft = -1; activity(i).lst = inf; activity(i).lft = inf; end

for i = 1:sz(1,1) for j = 1:4 if (isnan(activity(i).precedes(5-j))) activity(i).precedes(5-j) = []; end end end

running = []; ready = []; completed = []; time = 0;

completed = [1]; activity(1).iscomplete = 1; activity(1).starttime = 0; activity(1).endtime = 0; activity(1).est = 0;

%Critical Path Analysis : Forward Pass to Determine EST and EFT of activities

for i = 1:sz(1,1) for j = 1:length(activity(i).precedes) if activity(i).est< activity(activity(i).precedes(j)).duration +

activity(activity(i).precedes(j)).est activity(i).est = activity(activity(i).precedes(j)).duration +

activity(activity(i).precedes(j)).est; end end end

for i = 1:sz(1,1) activity(i).eft = activity(i).est + activity(i).duration; end

%Critical Path Analysis : Backward Pass to Determine LFT and LST of activities

activity(sz(1,1)).lft = activity(sz(1,1)).eft;

for i = 1:sz(1,1) for j = 1:length(activity(sz(1,1)-i+1).precedes) if activity(activity(sz(1,1)-i+1).precedes(j)).lft> activity(sz(1,1)-i+1).lft -

activity(sz(1,1)-i+1).duration activity(activity(sz(1,1)-i+1).precedes(j)).lft = activity(sz(1,1)-i+1).lft

- activity(sz(1,1)-i+1).duration; end end end

for i = 1:sz(1,1) activity(i).lst = activity(i).lft - activity(i).duration; end

%count = length(completed); r1 = 6; r2 = 6; r3 = 6;

Page 11: Project Management Heuristics for solving RCPSP

11

while(1) %enumerate ready activities for i = 1:sz(1,1) if activity(i).iscomplete == 0 && activity(i).isrunning == 0 && activity(i).isready ==

0 for j = 1:length(activity(i).precedes) flag = 1; pre = activity(i).precedes(j); if activity(pre).iscomplete == 0 flag = 0; break; end end if flag == 1; ready(length(ready) + 1) = i; activity(i).isready = 1; end end end

%prioritize ready activities %%%%%%GRD%%%%%%%%%%%%%% %ready = grd_priority(activity, ready);

%%%%%%RAN%%%%%%%%%%%%%% %ready = ran_priority(ready);

%%%%%%%SIO%%%%%%%%%%%%% %ready = sio_priority(activity, ready);

%%%%%%%MINSLK%%%%%%%%%% %ready = minslk_priority(activity, ready, time);

%%%%%%%LFT%%%%%%%%%%%%% ready = lft_priority(activity, ready);

%%%%%%%RSM%%%%%%%%%%%%% %ready = rsm_priority(activity, ready);

delfrmready = []; for i = 1:length(ready) if (activity(ready(i)).resources(1) <= r1) && (activity(ready(i)).resources(2) <= r2)

&& (activity(ready(i)).resources(3) <= r3) running(length(running)+1) = ready(i); r1 = r1 - activity(ready(i)).resources(1); r2 = r2 - activity(ready(i)).resources(2); r3 = r3 - activity(ready(i)).resources(3); delfrmready(length(delfrmready)+1) = i; activity(ready(i)).isrunning = 1; activity(ready(i)).isready = 0; activity(ready(i)).starttime = time; end end

for i = 1:length(delfrmready) ready(delfrmready(length(delfrmready) + 1 - i)) = []; end

%run delfrmrunning = []; dur = []; for i = 1:length(running)

Page 12: Project Management Heuristics for solving RCPSP

12

dur(i) = activity(running(i)).duration - activity(running(i)).runtime; end t = min(dur); for i = 1:length(running) activity(running(i)).runtime = activity(running(i)).runtime + t; if activity(running(i)).runtime == activity(running(i)).duration activity(running(i)).isrunning = 0; activity(running(i)).iscomplete = 1; activity(running(i)).endtime = time + t; completed(length(completed)+1) = running(i); r1 = r1 + activity(running(i)).resources(1); r2 = r2 + activity(running(i)).resources(2); r3 = r3 + activity(running(i)).resources(3); delfrmrunning(length(delfrmrunning)+1) = i; end end

for i = 1:length(delfrmrunning) running(delfrmrunning(length(delfrmrunning) + 1 - i)) = []; end

time = time + t;

count = length(completed); if count == sz(1,1) break; end end

disp('Project MakeSpan = '); disp(time);

%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%GANNT CHART%%%%%%%%%%%%%%%%

m = 1; for i = 1:sz(1,1) for j = 1:activity(i).duration p(1,m) = activity(i).starttime + j; m = m + 1; end end

m = 1; for i = 1:sz(1,1) for j = 1:activity(i).duration p(2,m) = i; m = m + 1; end end

figure; scatter(p(1,:), p(2,:), 'marker','s','markerfacecolor',[0,0,1]); gridminor; xlabel('Time'); ylabel('Activity Number'); title('Gantt Chart'); %%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%

%File Name :grd_priority.m – Models the GRD Heuristic

function priority = grd_priority(activity, ready) lnth = length(ready); pr = []; for i = 1:lnth pr(i,1) = activity(ready(i)).duration * sum(activity(ready(i)).resources);

Page 13: Project Management Heuristics for solving RCPSP

13

pr(i,2) = ready(i); end p = sortrows(pr,1); priority = flipud(p(:,2)); %if pr values are equal it will arrange randomly priority = priority'; %%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%

%File Name :lft_priority.m – Models the LFT Heuristic

function priority = lft_priority(activity, ready,time) lnth = length(ready); pr = []; for i = 1:lnth pr(i,1) = activity(ready(i)).lft; pr(i,2) = ready(i); end p = sortrows(pr,1); priority = p(:,2)'; %%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%

%File Name :minslk_priority.m – Models MINSLK Heuristic

function priority = minslk_priority(activity, ready,time)

lnth = length(ready); pr = []; for i = 1:lnth if time > activity(ready(i)).est pr(i,1) = (activity(ready(i)).lst - activity(ready(i)).est) - (time -

activity(ready(i)).est); ifpr(i,1) < 0 pr(i,1) = 0; end else pr(i,1) = activity(ready(i)).lst - activity(ready(i)).est; end pr(i,2) = ready(i); end

p = sortrows(pr,1); priority = p(:,2)'; %%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%

%File Name :ran_priority.m – Models RAN Heuristic

function priority = ran_priority(ready) lnth = length(ready); ran = randperm(lnth); pr = []; for i = 1:lnth pr(i) = ready(ran(i)); end priority = pr'; %%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%

%File Name :sio_priority – Models SIO Heuristic

function priority = sio_priority(activity, ready)

lnth = length(ready); pr = []; for i = 1:lnth pr(i,1) = activity(ready(i)).duration; pr(i,2) = ready(i);

Page 14: Project Management Heuristics for solving RCPSP

14

end p = sortrows(pr,1); priority = p(:,2)';

%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%

------------------------------------------------------------RESULTS---------------------------------------------------------

Figure 3 : Result using GRD Heuristic

Figure 4 : Result using LFT Heuristic

0 10 20 30 40 50 60 70 800

5

10

15

20

25

30

Time

Activity N

um

ber

Gantt Chart

0 10 20 30 40 50 60 700

5

10

15

20

25

30

Time

Activity N

um

ber

Gantt Chart

Page 15: Project Management Heuristics for solving RCPSP

15

Figure 5 : Result using MINSLK Heuristic

Figure 6 : Result using RAN Heuristic

0 10 20 30 40 50 60 70 800

5

10

15

20

25

30

Time

Activity N

um

ber

Gantt Chart

0 10 20 30 40 50 60 70 800

5

10

15

20

25

30

Time

Activity N

um

ber

Gantt Chart

Page 16: Project Management Heuristics for solving RCPSP

16

Figure 7 : Result using SIO Heuristic

5. Modelling using RESCON

RESCON is educational software for the resource-constrained project scheduling problem. It is

programmed in Visual C++ 6.0. The main features of RESCON are:

Activity-on-the-node representation

Exact and heuristic scheduling procedures

Multiple resource profiles

Gantt chart

Comparative analysis of algorithms

Project metrics "What-if" analysis

DLL support for custom-made scheduling routines

Support for robust scheduling

The outputs are displayed as the following:

0 10 20 30 40 50 60 70 800

5

10

15

20

25

30

Time

Activity N

um

ber

Gantt Chart

Page 17: Project Management Heuristics for solving RCPSP

17

Figure 8 : RESCON Outputs

The input is given in a .rcp file in the following manner:

Table 2 : Format for Inputting Data in RESCON

N R R1 R2 R3

D1 R11 R12 R13 S11 S12 S13

D2 R21 R22 R23 S21 S22 S23

D3 R31 R32 R33 S31 S32 S33

D4 R41 R42 R43 S41 S42 S43

N : Number of activities in the Network

R : The number of different type of resources required for completing activities

Rj : The available number of resources for each type of resource j, j = 1 to R

Di : The duration of activity I, I =1to number of activities

Rij : The number of units of resource j required by activity i

Sij : Denotes the successors of activity I, j = 1 to number of successors

Page 18: Project Management Heuristics for solving RCPSP

18

Therefore for the given network problem we can form the .rcp file by inputting data as shown below:

Table 3 : Input data for the Network Problem

27 3

6 6 6 0 0 0 0 3 2 3 4

5 3 5 2 2 5 8

5 5 4 3 2 5 8

3 5 2 2 2 6 7

4 4 1 4 2 9 12

1 5 5 4 2 10 11

6 3 5 2 2 9 10

2 2 4 4 2 9 10

6 3 2 2 2 13 15

3 3 2 4 1 13

3 3 3 2 1 16

1 4 1 4 1 14

3 1 4 4 1 19

6 2 2 2 1 18

3 5 5 4 1 17

4 1 5 4 2 17 20

4 4 5 4 2 22 24

3 3 2 3 1 21

3 5 3 3 2 21 23

1 2 4 6 1 22

4 1 6 2 1 25

6 3 2 1 1 25

4 1 0 4 2 25 26

1 2 2 1 1 25

3 0 1 3 1 27

3 2 2 2 1 27

0 0 0 0 0

Page 19: Project Management Heuristics for solving RCPSP

19

The above input, when fed in RESCON, will generate the following network diagram:

Figure 9 : Activity On Node Diagram Generated by RESCON

The various heuristic methods used for solving the RCPSP have been discussed earlier. Now we show the

results of using these heuristics to solve the stated problem in RESCON. Results have been shown using

Gantt Charts.

Figure 10 : Result using SIO Heuristic in RESCON

Page 20: Project Management Heuristics for solving RCPSP

20

Figure 11 : Result using MINSLK Heuristic in RECON

Figure 12 : Result using LFT Heuristic in RESCON

Page 21: Project Management Heuristics for solving RCPSP

21

Figure 13 : Result using RAN Heuristic in RESCON

RESCON is also able to solve the RCPSP optimally using a Branch and Bound Approach. The Gantt

chart for the optimal scheduling is shown below.

Figure 14 : Result using the Branch & Bound exact Method

Page 22: Project Management Heuristics for solving RCPSP

22

RESCON also generates the resource skyline for the different types of resources. The resource skyline

for one of the heuristics is shown below. The allocation chart of resource 1(skyline) over the project lifetime

using Shortest Imminent Operation heuristic is as follows:

Figure 15 : Resource Skyline of R1 using SIO Heuristic

Figure 16 : Resource Skyline for R2 using SIO Heuristic

Page 23: Project Management Heuristics for solving RCPSP

23

Figure 17 : Resource Skyline for R3 using SIO Heuristic

In addition to the available heuristic methods preprogramed in RESCON we can also write our own

heuristic method in C++. As an example the code for simulating Shortest Imminent Operation (SIO)

heuristic is given below:

SIO.cpp

#include "myDLL.h"

extern "C"

{

DLL_EXPORT void getSchedule(int act, int res, int *avail, int *dur, int **req,

int *nrpr, int **pred, int **su, int *nrsu, int **_bestSchedule){

int *bestSchedule = *_bestSchedule;

int i, k, t;

int horizon = 0;

for (i=0; i!=act; i++){

horizon += dur[i];

}

int **profile = new int * [res];

for (k=0; k!=res; k++){

profile[k] = new int[horizon];

for (t=0; t!=horizon; t++){

profile[k][t] = 0;

}

}

bestSchedule[0] = 0;

for (i=1; i!=act; i++){

int minStart = 0;

for (int p=0; p!=nrpr[i]; p++){

int pr = pred[i][p];

if (bestSchedule[pr] + dur[pr] > minStart){

minStart = bestSchedule[pr] + dur[pr];

}

}

bool slotFound = true;

while (true){

Page 24: Project Management Heuristics for solving RCPSP

24

for (t=minStart; t!=(minStart + dur[i]); t++){

for (k=0; k!=res; k++){

if (profile[k][t] + req[i][k] > avail[k]){

slotFound = false; break;

}

}

if (!slotFound) break;

}

if (!slotFound){

minStart = t+1;

slotFound = true;

}else break;

}

for (t=minStart; t!=(minStart + dur[i]); t++){

for (k=0; k!=res; k++){

profile[k][t] += req[i][k];

}

}

bestSchedule[i] = minStart;

}

for (k=0; k!=res; k++){

delete profile[k];

}

delete profile;

}

}

SIO.h

#ifndef _FLUPPE_MYDLL_INCLUDED

#define _FLUPPE_MYDLL_INCLUDED

#define DLL_EXPORT __declspec(dllexport)

#define DLL_IMPORT __declspec(dllimport)

extern "C"

{

DLL_EXPORT void getSchedule(int act, int res, int *avail, int *dur, int **req, int

*nrpr, int **pred,

int **su, int *nrsu, int **_bestSchedule);

}

#endif

Page 25: Project Management Heuristics for solving RCPSP

25

Figure 18 : Performance summary using different heuristics

Page 26: Project Management Heuristics for solving RCPSP

26

6. Heuristic and Meta-Heuristics Currently in use

Apart from the heuristics discussed in this report there are many other heuristic techniques currently in

use. Many of them are being used in software packages both such as RESCON and MS Project and many

others. It has been found that certain heuristic techniques outperform others depending on the class and type

of RCPSP.

Many Meta Heuristic techniques such as Simulated Annealing, Genetic Algorithms, Ant Colony

Optimization and Tabu Search algorithm and their variants have been used to solve the RCPSP.

Researchers solve and publish report on an accepted set of problems for the sake of comparison of

performance of different algorithms. The PSPLIB is an online library of such Project Scheduling Problems.

One can Google “PSPLIB” and download problems for purpose of research.