project management - cpm/pert

111
1 AM ITY G LO BAL BU SIN ESS SC H OOL Bangalore Project Management - CPM/PERT

Upload: senona

Post on 14-Jan-2016

74 views

Category:

Documents


8 download

DESCRIPTION

Project Management - CPM/PERT. For planning, scheduling, monitoring and coordinating large and complex projects comprising a number of activities Defining the entire job to be done Formulating the logical sequence Controlling the progress. Network Analysis. Minimization of total time - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Project Management  - CPM/PERT

1

AMITY GLOBALBUSINESS SCHOOL Bangalore

Project Management - CPM/PERT

Page 2: Project Management  - CPM/PERT

2

AMITY GLOBALBUSINESS SCHOOL BangaloreNetwork Analysis

For planning, scheduling, monitoring and coordinating large and complex projects comprising a number of activities

- Defining the entire job to be done

- Formulating the logical sequence

- Controlling the progress

Page 3: Project Management  - CPM/PERT

3

AMITY GLOBALBUSINESS SCHOOL BangaloreObjectives

• Minimization of total time

• Minimization of total cost

• Mimimize production delays

Page 4: Project Management  - CPM/PERT

4

AMITY GLOBALBUSINESS SCHOOL BangaloreApplications

• Construction of bridges

• Assembly line scheduling

• Installation of complex equipment

• Inventory planning and Control

• Construction of residential complex

Page 5: Project Management  - CPM/PERT

5

AMITY GLOBALBUSINESS SCHOOL BangaloreComponents

• Activity : represented by an arrow, definite starting time, and a point where it ends

- Predecessor Activity : An activity which must be completed before one or more other activities start

- Successor Activity : An activity which started immediately after one or more activities are completed

Page 6: Project Management  - CPM/PERT

6

AMITY GLOBALBUSINESS SCHOOL Bangalore

- Dummy Activity : any activity which does not consume time or resource ( -----)

• Event : represents the start of an activity and the end of an activity

activity i j

Page 7: Project Management  - CPM/PERT

7

AMITY GLOBALBUSINESS SCHOOL BangaloreCritical Path Method

• Ei = earliest start time for activity (i,j)

• Li = latest start time for activity (i,j)

• Ej = earliest finish time for activity (i,j)

• Lj = latest finish time for activity (i,j)

Page 8: Project Management  - CPM/PERT

8

AMITY GLOBALBUSINESS SCHOOL Bangalore Critical Path

• The longest continuous chain of activities through the network starting from the first to last event. ( )

• All activities lying in this critical path are called critical activities as any delay in their execution will lead to a delay in the completion of the entire project.

Page 9: Project Management  - CPM/PERT

9

AMITY GLOBALBUSINESS SCHOOL BangaloreFloat

• Total float :

The amount of time by which an activity can be delayed without delay in the project completion date

• Free Float :

The portion of the total float within which an activity can be manipulated without affecting floats of the subsequent activities

Page 10: Project Management  - CPM/PERT

10

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Independent Float :

That portion of the total float within which an activity can be delayed for start without affecting floats of the preceding activities.

Page 11: Project Management  - CPM/PERT

11

AMITY GLOBALBUSINESS SCHOOL BangalorePERT

programme evaluation and review technique

• Completion time is considered to be unknown

• Probability of activity completion time is estimated

– optimistic time (to or a)

- pessimistic time (tp or b )

- normal time / most likely time (tm or m)

Page 12: Project Management  - CPM/PERT

12

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Expected time te / μ = 1/6 ( to + 4 tm + tp)• Std deviation σ = 1/6 (tp – to)• Variance σ² = ( 1/6 (tp – to))²• Prob of completing the project by

scheduled time (Ts) is given by : Prob ( Z ≤ Ts – μ ) σ

Page 13: Project Management  - CPM/PERT

13

AMITY GLOBALBUSINESS SCHOOL BangaloreQ

For the following PERT diagram : D A 3 4 H 2 B E I K 2 4 5 3 F 7 2 C G 4 J 6

1

2 3

4 7 8 9

5 6

Page 14: Project Management  - CPM/PERT

14

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Compute earliest event time and latest event time

• Critical path and total project duration

Page 15: Project Management  - CPM/PERT

15

AMITY GLOBALBUSINESS SCHOOL BangaloreForward pass method

• E1 =0

• E2= E1 + t1,2 = 0 + 3

• E3 = E2 + t2,3 = 3 + 4 = 7

• E4 = E1 + t1,4 = 0 + 2 = 2

• E5 = E1 + t1,5 = 0 + 2 = 2

• E6 = max ( E4 + t4,6 ; E5 + t5,6 )

= max ( 9, 6 ) = 9

Page 16: Project Management  - CPM/PERT

16

AMITY GLOBALBUSINESS SCHOOL Bangalore

• E7 = E4 + t4,7 = 2 + 4 = 6

• E8 = max ( E3 + t3,8 ; E7 + t7,8 )

= max ( 9, 11) = 11

• E9 = max ( E8 + t8,9 ; E6 + t6,9 )

= max ( 14, 15) = 15

Lower left portion

Page 17: Project Management  - CPM/PERT

17

AMITY GLOBALBUSINESS SCHOOL Bangalore Backward Pass

Method• L9= E9 = 15

• L8 = L9 – t8,9 = 15 -3 =12

• L7 = L8 – t7,8 = 12-5 =7

• L6 = L9 – t 6,9 = 15 – 6 = 9

• L 5 = L6 – t5,5 = 9-4 = 5

• L4 = min( L6- t4,6; L7-t4,7)

min( 9-7 ; 7 - 4) = 2

Page 18: Project Management  - CPM/PERT

18

AMITY GLOBALBUSINESS SCHOOL Bangalore

• L3 = L8 – t 3,8 = 12 -2 = 10

• L2= L3- t2,3 = 10 -4 = 6

• L1= min ( L2-t1,2 ; L4- t1,4; L5 – t1,5)

= min ( 6-3; 2-2; 5-2 ) = 0

Page 19: Project Management  - CPM/PERT

19

AMITY GLOBALBUSINESS SCHOOL Bangalore

For the following PERT diagram : D A 3 4 H 2 B E I K 2 4 5 3 F 7 2 C G 4 J 6

1

0 0

23 6

37 10

42 2

76 7

811 12

915 15

52 5

69 9

Page 20: Project Management  - CPM/PERT

20

AMITY GLOBALBUSINESS SCHOOL BangaloreQ

An established company has decided to add a new product to its line. It will buy the product from a mfg concern, package it, and sell it to a number of distributors selected on a geographical basis. Market Research has indicated the volume expected and the size of sales force reqd. the steps in the following table are to be planned :

Page 21: Project Management  - CPM/PERT

21

AMITY GLOBALBUSINESS SCHOOL Bangalore

Activity Description Time(wk)A1-2 B 2-3C 2-4D 2-5E 3-6F 4-7G 5-8H 6-7I 6-8J 6-9

Organize sales officeHire salesmenTrain salesmenSelect advertising agencyPlan advertising campaignConduct advertising campaignDesign packageSet up packaging facilitiesPackage initial stocksOrder stock from manufacturer

24221463334

Page 22: Project Management  - CPM/PERT

22

AMITY GLOBALBUSINESS SCHOOL Bangalore

K7-10L 8-11M 9-12N 10-12

O 11-12P 12-13

Select distributorsSell to distributorsShip stocksCheck inventoryGet customer feedbackRe assess strategy

353233

Page 23: Project Management  - CPM/PERT

23

AMITY GLOBALBUSINESS SCHOOL Bangalore

What is the critical path

Calculate total and free float

Page 24: Project Management  - CPM/PERT

24

AMITY GLOBALBUSINESS SCHOOL Bangalore

6 3

2 3 2 2 4 14 4 3 3

2 3 3

3 5

10 0

2

2 2

36 6

620 20

924 28

1231 31

1334 34

44 20

7

23 26

10

26 29

54 20

823 23

11

28 28

Page 25: Project Management  - CPM/PERT

25

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Total float :

The amount of time by which an activity can be delayed without delay in the project completion date

= (Lj – tij) - Ei• Free Float :

The portion of the total float within which an activity can be manipulated without affecting floats of the subsequent activities = (Ej – Ei) - tij

Page 26: Project Management  - CPM/PERT

26

AMITY GLOBALBUSINESS SCHOOL Bangalore Time EstimatesActi Dur

Earliest

Start Fin

Latest

Start Fin

Float

Total Free

A 2 0 2

0 2 0 0

B 4 2 6 2 6 0 0

C 2 2 4 18 20 16 0

D 2 2 4 18 20 16 0

E 14 6 20 6 20 0 0

F 6 4 10 20 26 16 13=23-4-6

G 3 4 7 20 23 16 16 =23-4-3

H 3 20 23 23 26 3 0

Page 27: Project Management  - CPM/PERT

27

AMITY GLOBALBUSINESS SCHOOL Bangalore

Activity Duration

Earliest

Start Finish

Latest

Start Finish

Float

I 3

J 4

K 3

L 5

M 3

N 2

O 3

P 3

20 23

20 24

23 26

23 28

24 27

26 28

28 31

31 34

20 23

24 28

26 29

23 28

28 31

29 31

28 31

31 34

0 0

4 0

3 0

0 0

4 4

3 3

0 0

0 0

Page 28: Project Management  - CPM/PERT

28

AMITY GLOBALBUSINESS SCHOOL Bangalore

Page 29: Project Management  - CPM/PERT

29

AMITY GLOBALBUSINESS SCHOOL BangaloreQ : A project schedule has the

following characteristics :Activity Time(days) Activity Time(days)

1-2 4 5-6 4

1-3 1 5-7 8

2-4 1 6-8 1

3-4 1 7-8 2

3-5 6 8-10 5

4-9 5 9-10 7

Page 30: Project Management  - CPM/PERT

30

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Construct a network diagram

• Compute the total float

• Find the critical path and total project duration

Page 31: Project Management  - CPM/PERT

31

AMITY GLOBALBUSINESS SCHOOL Bangalore

4 1 5 7

1 1 8 2

1

0 0

2

4 9

31 1

4

5 10

57 7

715 15

910 15

611 16

8

17 17

1022 22

Page 32: Project Management  - CPM/PERT

32

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Critical path is 1-3-5-7-8-10 and the project duration is 22 days

• Total Float = ( Lj-tij ) - Ei

Page 33: Project Management  - CPM/PERT

33

AMITY GLOBALBUSINESS SCHOOL Bangalore

Activit Duratio Earliest start

Earliest finish

Latest start

Latest finish

Total float

1-2 4 0 4 5 9 5

1-3 1 0 1 0 1 0

2-4 1 4 5 9 10 5

3-4 1 1 2 11 10 7

3-5 6 1 7 1 7 0

5-7 8 7 15 7 15 0

5-6 4 7 11 12 16 5

Page 34: Project Management  - CPM/PERT

34

AMITY GLOBALBUSINESS SCHOOL Bangalore

7-8 2 15 17 15 17 0

6-8 1 11 12 16 17 5

4-9 5 5 10 12 17 7

9 -10 7 10 17 15 22 5

8-10 5 17 22 17 22 0

Page 35: Project Management  - CPM/PERT

35

AMITY GLOBALBUSINESS SCHOOL Bangalore

Page 36: Project Management  - CPM/PERT

36

AMITY GLOBALBUSINESS SCHOOL Bangalore

steps in developing PERT network• Draw a network diagram

• Time estimates are obtd

- m , a , b

• Calculate te

• Determine the critical path

• Calculate σ²

• Calculate Z

Page 37: Project Management  - CPM/PERT

37

AMITY GLOBALBUSINESS SCHOOL BangaloreQ

Various activities of a small project and other relevant information have been shown in the adjoining table. Using the given info the resulting network is shown in the following figure. Map out the critical path and find the prob of completing the project within 48 days.

Page 38: Project Management  - CPM/PERT

38

AMITY GLOBALBUSINESS SCHOOL Bangalore

activity Most optimistic time ( in days )

Most likely time m

Most pessimistic

time b

1-2 4 8 12

2-3 1 4 7

2-4 8 12 16

3-5 3 5 7

4-5 0 0 0

4-6 3 6 9

5-7 3 6 9

Page 39: Project Management  - CPM/PERT

39

AMITY GLOBALBUSINESS SCHOOL Bangalore

5-8 4 6 8

7-9 4 8 12

8-9 2 5 8

9-10 4 10 16

6-10 4 6 8

Page 40: Project Management  - CPM/PERT

40

AMITY GLOBALBUSINESS SCHOOL Bangalore

Calculate expected time te = a + 4m + b

6

Variance σ² = b-a ²

6

Page 41: Project Management  - CPM/PERT

41

AMITY GLOBALBUSINESS SCHOOL Bangalore

Activity a m b te σ²

1-2 4 8 12 8 1.78

2-3 1 4 7 4 1

2-4 8 12 16 12 1.78

3-5 3 5 7 5 0.44

4-5 0 0 0 0 0

4-6 3 6 9 6 1

Page 42: Project Management  - CPM/PERT

42

AMITY GLOBALBUSINESS SCHOOL Bangalore

5-7 3 6 9 6 1

5-8 4 6 8 6 0.44

7-9 4 8 12 8 1.78

8-9 2 5 8 5 1

9-10 4 10 16 10 4

6-10 4 6 8 6 0.44

Page 43: Project Management  - CPM/PERT

43

AMITY GLOBALBUSINESS SCHOOL BangaloreEarliest

Start Time• E(μ1)= 0

• E(μ2) = 0+8 = 8

• E (μ3) = 8 + 4 = 12

• E(μ4)= 12 + 8 = 20

• E(μ5) = Max(12+5,20+0) = 20

• E(μ6) = 20+6 = 26

Page 44: Project Management  - CPM/PERT

44

AMITY GLOBALBUSINESS SCHOOL Bangalore

• E (μ7) = 20 + 6 = 26

• E(μ8)= 20 + 6 = 26

• E(μ9) = Max(26+8, 26+5) = 34

• E(μ10) =Max(34 + 10, 26 + 6 ) = 44

Page 45: Project Management  - CPM/PERT

45

AMITY GLOBALBUSINESS SCHOOL BangaloreLatest Start

Time• E(L10) = 44

• E(L9) = 44-10 = 34

• E(L8) = 34 – 5 = 29

• E(L7) = 34 – 8 = 26

• E(L6) = 44-10 = 34

• E(L5) = Min (26-6, 29 -6) = 20

Page 46: Project Management  - CPM/PERT

46

AMITY GLOBALBUSINESS SCHOOL Bangalore

• E(L4) = Min(20 – 0, 36 – 6 ) = 20

• E(L3) = 20 – 5 = 15

• E(L2) = Min(15-4, 20 -12) = 8

• E(L1) = 8 – 8 = 0

Draw network diagram and find critical path

Page 47: Project Management  - CPM/PERT

47

AMITY GLOBALBUSINESS SCHOOL Bangalore

10 0

28 8

312 15

420 20

520 20

726 26

934 34

828 29

626 38

1044 44

Page 48: Project Management  - CPM/PERT

48

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Critical path is

1---2---4---5---7----9---10

• Expected time in completing the project

8 + 12 + 0 + 6 + 8 + 10 = 44 days

• Project variance

1.78 + 1.78 + 0 +1 + 1.78 + 4 = 10.34

Page 49: Project Management  - CPM/PERT

49

AMITY GLOBALBUSINESS SCHOOL Bangalore

• To find out the prob of completing the project, within , 48 days

Z = X - X¯ = 48 – 44 = 1.24

σ 3.216

value from normal tables = 0.8925

Hence prob of completing project within 48 days = 89 %

Page 50: Project Management  - CPM/PERT

50

AMITY GLOBALBUSINESS SCHOOL BangaloreQ (Dummy Variable )

A small project consists of seven activities for which the relevant data are given :

• Draw the network and find the project completion time

Page 51: Project Management  - CPM/PERT

51

AMITY GLOBALBUSINESS SCHOOL Bangalore

Activity Preceding activity

Activity duration ( days )

A - 4

B - 7

C - 6

D A,B 5

E A,B 7

F C,D,E 6

G C,D,E 5

Page 52: Project Management  - CPM/PERT

52

AMITY GLOBALBUSINESS SCHOOL Bangalore

A D1 G D3

B E F

C D D2

10 0

24 7

37 7

46 14

514 14

614 20

720 20

Page 53: Project Management  - CPM/PERT

53

AMITY GLOBALBUSINESS SCHOOL Bangalore

CRITICAL PATH IS 1-3-5-7

Page 54: Project Management  - CPM/PERT

54

AMITY GLOBALBUSINESS SCHOOL BangaloreQ

• Q has been commissioned by the food manufacturer Z to carry out market research in a new product development project, prior to a test market launch. The table below lists required activities and their duration in weeks

• Draw the new product development network. State and explain the critical path and its duration

Page 55: Project Management  - CPM/PERT

55

AMITY GLOBALBUSINESS SCHOOL Bangalore

Prepare a table of the earliest start and finish times, the latest start and finish times and the total and free float

Page 56: Project Management  - CPM/PERT

56

AMITY GLOBALBUSINESS SCHOOL Bangalore

Activity Immediate predecessor

duration

A - 6

B - 4

C A 20

D B 12

E B 11

F C 5

G C,D,E 4

Page 57: Project Management  - CPM/PERT

57

AMITY GLOBALBUSINESS SCHOOL Bangalore

H E 30

I G 8

J G 10

K F,I 7

L H,J,K 6

M H,J,K 4

N L 10

P M,N 3

Page 58: Project Management  - CPM/PERT

58

AMITY GLOBALBUSINESS SCHOOL Bangalore

Use only 2 dummy variables

Page 59: Project Management  - CPM/PERT

59

AMITY GLOBALBUSINESS SCHOOL Bangalore

• F P C A R I K M N

B D G J L S E H

10 0

26 6

34 4

426 26

838 38

626 26

515 15

730 30 9

45 4510

51 51

1161 61

12

64 64

Page 60: Project Management  - CPM/PERT

60

AMITY GLOBALBUSINESS SCHOOL Bangalore

Activity

duration

ES EF LS LF Tot F Free

A 6 0 6 0 6 0 0

B 4 0 4 0 4 0 0

C 20 6 26 6 26 0 0

D 12 4 16 14 26 10 10

E 11 4 15 4 15 0 0

F 5 26 31 33 38 7 7

G 4 26 30 26 30 0 0

Page 61: Project Management  - CPM/PERT

61

AMITY GLOBALBUSINESS SCHOOL Bangalore

H 30 15 45 15 45 0 0

I 8 30 38 30 38 0 0

J 10 30 40 35 45 5 5

K 7 38 45 38 45 0 0

L 6 45 51 45 51 0 0

M 4 45 49 57 61 12 12

N 10 51 61 51 61 0 0

P 3 61 64 61 64 0 0

Page 62: Project Management  - CPM/PERT

62

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Floats are useful to management as they indicate how much an activity can be delayed without delaying the entire project. Resources can be redeployed from an activity with slack to be used elsewhere

• Slack --- events

• Head slack = Lj - Ej

Page 63: Project Management  - CPM/PERT

63

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Tail Slack = Li – Ei

• Total float = Lj – Ei - tij

• Free float = total float – head slack

• Independent float = free float – tail slack

Page 64: Project Management  - CPM/PERT

64

AMITY GLOBALBUSINESS SCHOOL BangaloreQ

Activity Preceding activity

to tm tp

A Nil 4 7 16

B Nil 1 5 15

C A 6 12 30

D A 2 5 8

E C 5 11 17

F D 3 6 15

G B 3 9 27

H E , F 1 4 7

I G,H 4 19 28

Page 65: Project Management  - CPM/PERT

65

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Draw the PERT network diagram• Identify the critical path• Find the expected duration and variance for each

activity. What is expected project length ?• What is the prob that the project is completed

between 35 and 40 weeks ?

Page 66: Project Management  - CPM/PERT

66

AMITY GLOBALBUSINESS SCHOOL Bangalore

activity to tm tp te σ²

Time estimates(wks)

A 1-2 4 7 16 8 4

B 1-3 1 5 15 6 49 / 4

C 2-4 6 12 30 14 16

D 2-5 2 5 8 5 1

E 4-6 5 11 17 11 4

F 5-6 3 6 15 7 4

G 3-7 3 9 27 11 16

H 6-8 1 4 7 4 1

I 7-8 4 19 28 18 16

Page 67: Project Management  - CPM/PERT

67

AMITY GLOBALBUSINESS SCHOOL Bangalore

10 0

28 8

36 8

422 22

633 33

513 26

717 19

8

37 3755 55

Page 68: Project Management  - CPM/PERT

68

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Critical path

1---2 ---4 –6---7----8---9

• Expected project length

8 + 14 + 11 + 4 = 55 weeks

• Variance

Page 69: Project Management  - CPM/PERT

69

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Prob that the project will be completed between 35 and 40 weeks

prob { 35 - 55 ≤ Z = Ts – Te ≤ 40 – 55 }

σ σ e σ

= p ( - ≤ Z ≤ )

= P ( - ≤ Z ≤ 0 ) + P ( 0 ≤ Z ≤ 0.6 )

=

Page 70: Project Management  - CPM/PERT

70

AMITY GLOBALBUSINESS SCHOOL BangaloreCrashing

The process of reducing an activity time by putting extra effort is called crashing the activity. It is the process of shortening a project and is usually achieved by adding extra resources to an activity.

Page 71: Project Management  - CPM/PERT

71

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Direct costs are the costs directly associated with each activity such as machine costs, labor costs and so on.

• Indirect costs are the costs due to management services, rentals, insurance etc.

Page 72: Project Management  - CPM/PERT

72

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Duration of any activity cannot be reduced indefinitely

• Crash time represents minimum activity duration time that is possible.

• Activity cost corresponding to the crash time is called the crash cost.

Page 73: Project Management  - CPM/PERT

73

AMITY GLOBALBUSINESS SCHOOL BangaloreActivity crashing

Act

ivit

y co

st

Activity time

Crashing activity

Crash time

Crash cost

Normal Activity

Normal time

Normal cost

Slope = crash cost per unit time

Page 74: Project Management  - CPM/PERT

74

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Crashing costs increase as project duration decreases

• Indirect costs increase as project duration increases

• Reduce project length as long as crashing costs are less than indirect costs

Time-Cost Relationship

Page 75: Project Management  - CPM/PERT

75

AMITY GLOBALBUSINESS SCHOOL Bangalore

Time-Cost Tradeoff

cost

time

Direct cost

Indirect cost

Total project costMin total cost = optimal project time

Page 76: Project Management  - CPM/PERT

76

AMITY GLOBALBUSINESS SCHOOL Bangalore

Cost slope =

Crash cost – normal cost

Normal time – crash time

Page 77: Project Management  - CPM/PERT

77

AMITY GLOBALBUSINESS SCHOOL BangaloreQ

The following table gives the activities in a construction project and other relevant information

Page 78: Project Management  - CPM/PERT

78

AMITY GLOBALBUSINESS SCHOOL Bangalore

Activity Predecessor

Time Direct Costs

Normal Crash Normal Crash

A - 4 3 60 90

B - 6 4 150 250

C - 2 1 38 60

D A 5 3 150 250

E C 2 2 100 100

F A 7 5 115 175

G D,B,E 4 2 100 240

Total 713

Page 79: Project Management  - CPM/PERT

79

AMITY GLOBALBUSINESS SCHOOL Bangalore

Indirect costs vary as follows :

Days 15 14 13 12 11 10 9 8 7 6

Cost-Rs 600 500 400 250 175 100 75 50 35 25

Page 80: Project Management  - CPM/PERT

80

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Draw an arrow diagram of the network

• Determine the project duration which will result in minimum total cost.

• Activity F & G end at the same time.

Page 81: Project Management  - CPM/PERT

81

AMITY GLOBALBUSINESS SCHOOL Bangalore

3

24 4

513 13

• 2 4

C 2 E 2

B 4 G

6 9 9 4

A 4 D 5 F 7

10 0

Page 82: Project Management  - CPM/PERT

82

AMITY GLOBALBUSINESS SCHOOL Bangalore

The critical path is 1-2-4-5.

Critical activities are 1-2, 2-4 and 4-5

Project duration is 13 days

Page 83: Project Management  - CPM/PERT

83

AMITY GLOBALBUSINESS SCHOOL Bangalore

Activity A B C D E F G

1-2 1-4 1-3 2-4 3-4 2-5 4-5

Cost slope

30 50 22 50 - 30 70

Page 84: Project Management  - CPM/PERT

84

AMITY GLOBALBUSINESS SCHOOL Bangalore

Among the critical activities, choose activity with least cost slope

i.e A (1-2)

Crash activity A by 4-3 = 1 day.

Project duration reduces by 1 day

= 13-1 = 12days

Page 85: Project Management  - CPM/PERT

85

AMITY GLOBALBUSINESS SCHOOL Bangalore

Total project cost = total direct cost + increased direct cost due to crashing +

indirect cost for 12 days

= 713 + 1 * 30(cost slope) + 250

= 993

Page 86: Project Management  - CPM/PERT

86

AMITY GLOBALBUSINESS SCHOOL BangaloreNew network

Page 87: Project Management  - CPM/PERT

87

AMITY GLOBALBUSINESS SCHOOL Bangalore

23 3

512 12

C 2 E 2

1 6 4 4

0 0 B 8 G

A 3 D 5 F 7

Page 88: Project Management  - CPM/PERT

88

AMITY GLOBALBUSINESS SCHOOL Bangalore

The critical path is 1-2-4-5 Total time = 12 days;

The critical activities are 1-2, 2-4, 4-5

The first one A 1-2 has already been crashed

From the other two choose the one with the smallest cost slope and crash it.

Page 89: Project Management  - CPM/PERT

89

AMITY GLOBALBUSINESS SCHOOL Bangalore

Activity D(2-4) is crashed by 5-3=2 days.

Page 90: Project Management  - CPM/PERT

90

AMITY GLOBALBUSINESS SCHOOL Bangalore

3

23 3

510 10

2 2

C 2 E 2

B 4 G

6 6 6 4

A 3 D 3 F 7

10 0

Page 91: Project Management  - CPM/PERT

91

AMITY GLOBALBUSINESS SCHOOL Bangalore

There are 3 critical paths

1-2-5

1-4-5

1-2-4-5

Each with 10 days

Page 92: Project Management  - CPM/PERT

92

AMITY GLOBALBUSINESS SCHOOL Bangalore

Total cost = 743 +2*50 +100 = Rs. 943

since there are more than one parallel critical path, crashing must be performed.

As A & D are crashed, crash activities F & G by 2 days each to reduce the project duration by 2 days.

Page 93: Project Management  - CPM/PERT

93

AMITY GLOBALBUSINESS SCHOOL Bangalore

3

23 3

58 8

2 2

C 2 E 2

B 4 G

6 6 6 2

A 3 D 3 F 5

10 0

Page 94: Project Management  - CPM/PERT

94

AMITY GLOBALBUSINESS SCHOOL Bangalore

There are 3 critical paths1-4-51-2-51-2-4-5Each with 8 days

Page 95: Project Management  - CPM/PERT

95

AMITY GLOBALBUSINESS SCHOOL Bangalore

• Total cost = 843 +(2*30 +2*70) +50

= Rs. 1093

Since all the activities in the critical path 1-2-5 are crashed , further crashing is not possible.

Decision : minimum total cost is Rs. 943 and the optimum duration is 10 days.

Page 96: Project Management  - CPM/PERT

96

AMITY GLOBALBUSINESS SCHOOL Bangalore

Q

Page 97: Project Management  - CPM/PERT

97

AMITY GLOBALBUSINESS SCHOOL Bangalore

The following table gives data on normal time, and cost and crash time and cost for a project.

Page 98: Project Management  - CPM/PERT

98

AMITY GLOBALBUSINESS SCHOOL BangaloreActivity Normal Crash

Time(weeks) Cost (INR) Time(weeks) Cost (INR)

1-2 3 300 2 400

2-3 3 30 3 30

2-4 7 420 5 580

2-5 9 720 7 810

3-5 5 250 4 300

4-5 0 0 0 0

5-6 6 320 4 410

6-7 4 400 3 470

6-8 13 780 10 900

7-8 10 1000 9 1200

Page 99: Project Management  - CPM/PERT

99

AMITY GLOBALBUSINESS SCHOOL Bangalore

Indirect cost is Rs. 50 per week.

1. Draw the network for the project and identify the critical path

2. What are the normal project duration and associated cost

3. Crash the relevant activities systematically and determine the optimal project completion time and cost.

Page 100: Project Management  - CPM/PERT

100

AMITY GLOBALBUSINESS SCHOOL Bangalore

10 0

2

3 3

4

10 12

36 7

512 12

618 18

722 22

832 32

Page 101: Project Management  - CPM/PERT

101

AMITY GLOBALBUSINESS SCHOOL Bangalore

The critical path is

1-2-5-6-7-8

Project duration is 32 weeks and associated cost is as follows :

= direct normal cost +indirect cost for 32 weeks

= 4220 + 50*32 = Rs. 5820

Page 102: Project Management  - CPM/PERT

102

AMITY GLOBALBUSINESS SCHOOL BangaloreCrash cost slope for critical

activities are 1-2 400-300 = 100

3-2

2-5 810 – 720 = 45

9-7

5-6 45

6-7 70

7-8 200

Page 103: Project Management  - CPM/PERT

103

AMITY GLOBALBUSINESS SCHOOL Bangalore

The minimum crash cost per week is for activity 2-5 & 5-6.

Hence, crash activity 2-5 by 2 weeks.

But, the activity should b reduced only by 1 week – so that another critical path be raised

Page 104: Project Management  - CPM/PERT

104

AMITY GLOBALBUSINESS SCHOOL Bangalore

• 81

0 0

2

3 3

4

10 11

36 6

511 11

617 17

721 21

831 31

Page 105: Project Management  - CPM/PERT

105

AMITY GLOBALBUSINESS SCHOOL Bangalore

Network is as shown in previous slide.

New project time is 31 weeks

The critical paths are

1-2-5-6-7-8

1-2-3-5-6-7-8

Page 106: Project Management  - CPM/PERT

106

AMITY GLOBALBUSINESS SCHOOL Bangalore

The new total cost

= total direct normal cost + increased direct cost due to crashing + indirect cost for 31 weeks.

= (4220 + 1*45) + 31 * 50 = Rs. 5815

Page 107: Project Management  - CPM/PERT

107

AMITY GLOBALBUSINESS SCHOOL BangaloreWrt new network

Crashed Activity Slope

1-2 100

2-5 Crashed

2-3 No need(not in first path)

3-5 50

5-6 45

6-7 70

7-8 200

Page 108: Project Management  - CPM/PERT

108

AMITY GLOBALBUSINESS SCHOOL Bangalore

Crash 5-6 by 2 weeks.

Page 109: Project Management  - CPM/PERT

109

AMITY GLOBALBUSINESS SCHOOL Bangalore

• 8 41

0 0

2

3 3

4

10 11

36 6

511 11

615 15

719 19

829 29

Page 110: Project Management  - CPM/PERT

110

AMITY GLOBALBUSINESS SCHOOL Bangalore

The new total cost

= total direct normal cost + increased direct cost due to crashing of 5-6 + indirect cost for 29 weeks.

= (4220 + 1*45 + 2 *45) + 29 * 50 = Rs. 5805

Page 111: Project Management  - CPM/PERT

111

AMITY GLOBALBUSINESS SCHOOL Bangalore

If we go in for further crashing the project cost wil;l go up (Rs.5825), hence stop here.