Project Management

Chapter 2Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 -0 1

What is a Project?

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 -0 2

Project

An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of resources.

What is Project Management?

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 03

Project Management

A systemized, phased approach to defining, organizing, planning, monitoring, and controlling projects.

Defining and Organizing Projects

• Defining the Scope and Objectives

• Selecting the Project Manager and Team

• Recognizing Organizational Structure

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 -0 4

Planning Projects

• Defining the Work Breakdown Structure

• Diagramming the network

• Developing the schedule• Analyzing cost-time

trade-offs

• Assessing risks

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 -0 5

Work Breakdown Structure

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 -06

Work Breakdown Structure

A statement of all the work that has to be completed.

Activity

The smallest unit of work effort consuming both time and resources that can be planned and controlled.

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall.

Purchase and deliver equipment

Construct hospital

Develop information system

Install medical equipment

Train nurses and support staff

Work Breakdown Structure

Select administration staff

Site selection and survey

Select medical equipment

Prepare final construction plans

Bring utilities to site

Interview applicants fornursing and support staff

Organizing and Site Preparation Physical Facilities and Infrastructure Level 1

Level 0

Level 2

Relocation of St. John’s Hospital

02 -07

Diagramming the Network

• Program Evaluation and Review Technique (PERT)

• Critical Path Method (CPM)

• Activity-on-Node approach

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 08

Establishing Precedence Relationships

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 09

Precedence RelationshipsDetermining the sequence for undertaking activities.

Example 2.1

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 10

FinishStart

A

B

C

D

E

F

G

H

I

J

K

A

—B

—C

AD

BE

BF

AG

CH

DI

AJ

E,G,HK

F,I,J

Immediate Predecessor

Example 2.1

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 11

The following information is known about a project

Draw the network diagram for this project

Activity Activity Time (days)Immediate

Predecessor(s)

A 7 —

B 2 A

C 4 A

D 4 B, C

E 4 D

F 3 E

G 5 E

Application 2.1

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 12

Finish

G5

F3

E4

D4

Activity Activity Time (days)Immediate

Predecessor(s)

A 7 —

B 2 A

C 4 A

D 4 B, C

E 4 D

F 3 E

G 5 E

B2

C4

StartA7

Application 2.1

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 13

Developing the Schedule

• Path–The sequence of activities between a

project’s start and finish.

• Critical Path – –The sequence of activities between a start

and finish that takes the longest time to complete.

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 14

Developing the Schedule• Earliest start time (ES) - the latest earliest finish time of

any immediately preceding activities

• Earliest finish time (EF) - the earliest start time plus its estimated duration EF = ES + t

• Latest finish time (LF) – the earliest of the latest start times of any of the immediately following activities.

• Latest start time (LS) - the latest finish time minus its estimated duration LS = LF – t

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 15

• Activity Slack - the maximum length of time an activity can be delayed without delaying the entire project

LF-EF or LS-ES

Developing the Schedule

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 16

Latest finish time

Latest start time

Activity

Duration

Earliest start timeEarliest finish time

0

2

12

14

A

12

FinishStart

A

B

C

D

E

F

G

H

I

J

K

Path Time (wks)

A-I-K 33A-F-K 28A-C-G-J-K 67B-D-H-J-K 69B-E-J-K 43

Paths are the sequence of activities between a project’s start and finish.

Example 2.2

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 17

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 18

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

I

15

FinishStart

A

12

F

10

0

Earliest start time

12

Earliest finish time

0 9

9 33

9 19 19 59

22 5712 22

59 63

12 27

12 22 63 69

Example 2.2

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 19

Example 2.2

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

I

15

FinishStart

A

12

F

10

0 9

9 33

9 19 19 59

22 5712 22

59 63

12 27

12 22 63 690 12

The Critical Path takes 69 weeks

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 20

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

I

15

FinishStart

A

12

F

10

0 9

9 33

9 19 19 59

22 5712 22

59 63

12 27

12 22 63 690 12

48 63

53 63

59 63

24 59

19 59

35 59

14 24

9 19

2 14

0 9

63 69

Example 2.2Latest start time

Latest finish time

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 21

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

I

15

FinishStart

A

12

F

10

0 9

9 33

9 19 19 59

22 5712 22

59 63

12 27

12 22 63 690 12

48 63

53 63

59 63

24 59

19 59

35 59

14 24

9 19

2 14

0 9

63 69

Example 2.2

S = 0

S = 2

S = 26

S = 0

S = 36

S = 2

S = 2

S = 41 S = 0

S = 0 S = 0

Developing a Schedule

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 22

Gantt chart

Application 2.2Calculate the four times for each activity in order to determine the critical path and project duration for the diagram in Application Problem 1.

Activity DurationEarliest Start (ES)

Latest Start (LS)

Earliest Finish (EF)

Latest Finish (LF)

Slack (LS-ES)

On the Critical Path?

A 7 0 0 7 7 0-0=0 Yes

B 2

C 4

D 4

E 4

F 3

G 5

The critical path is A–C–D–E–G with a project duration of 24 days.

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 23

Calculate the four times for each activity in order to determine the critical path and project duration.

Activity DurationEarliest Start (ES)

Latest Start (LS)

Earliest Finish (EF)

Latest Finish (LF)

Slack (LS-ES)

On the Critical Path?

A 7 0 0 7 7 0-0=0 Yes

B 2

C 4

D 4

E 4

F 3

G 5

7 9 9 11 9-7=2 No

7 7 11 11 7-7=0 Yes

19 21 22 24 21-19=2 No

19 19 24 24 19-19=0 Yes

11 11 15 15 11-11=0 Yes

15 15 19 19 15-15=0 Yes

Application 2.2

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 24

Application 2.2

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 25

The critical path is A–C–D–E–G with a project duration of 24 days.

Start FinishA7

B2

C4

D4

E4

F3

G5

Analyzing Cost-Time Trade-Offs

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 26

Project CrashingShortening (or expediting) some activities within a project to reduce overall project completion time.

Project Costs• Direct Costs• Indirect Costs• Penalty Costs

Analyzing Cost-Time Trade-Offs

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 27

Project Costs• Normal time (NT) is the time

necessary to complete an activity under normal conditions.

• Normal cost (NC) is the activity cost associated with the normal time.

• Crash time (CT) is the shortest possible time to complete an activity.

• Crash cost (CC) is the activity cost associated with the crash time.

Cost to crash per period =

CC – NCNT – CT

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall.

Cost-Time Relationships

Linear cost assumption

8000 —

7000 —

6000 —

5000 —

4000 —

3000 —

0 —

Dire

ct c

ost (

dolla

rs)

| | | | | |5 6 7 8 9 10 11

Time (weeks)

Crash cost (CC)

Normal cost (NC)

(Crash time) (Normal time)

Estimated costs for a 2-week reduction, from 10 weeks to 8 weeks

5200

Figure 2.602 - 28

Analyzing Cost-Time Trade-Offs

Determining the Minimum Cost Schedule:1. Determine the project’s critical path(s).2. Find the activity or activities on the critical path(s) with

the lowest cost of crashing per week.3. Reduce the time for this activity until…

a. It cannot be further reduced orb. Until another path becomes critical, orc. The increase in direct costs exceeds the savings that

result from shortening the project (which lowers indirect costs).

4. Repeat this procedure until the increase in direct costs is larger than the savings generated by

shortening the project.Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 29

Example 2.3 DIRECT COST AND TIME DATA FOR THE ST. JOHN’S HOSPITAL PROJECT

Activity Normal Time (NT) (weeks)

Normal Cost (NC)($)

Crash Time (CT)(weeks)

Crash Cost (CC)($)

Maximum Time Reduction (week)

Cost of Crashing per Week ($)

A12 $12,000 11 $13,000 1 1,000

B9 50,000

764,000 2 7,000

C10 4,000

57,000 5 600

D10 16,000

820,000 2 2,000

E24 120,000 14 200,000 10 8,000

F10 10,000

616,000 4 1,500

G35 500,000 25 530,000 10 3,000

H40 1,200,000 35 1,260,000 5 12,000

I15 40,000 10 52,500 5 2,500

J4 10,000

113,000 3 1,000

K6 30,000

534,000 1 4,000

Totals$1,992,000 $2,209,500

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 30

Example 2.3Determine the minimum-cost schedule for the St. John’s Hospital project.Project completion time =69 weeks. Project cost = $2,624,000

Direct = $1,992,000 Indirect = 69($8,000) = $552,000 Penalty = (69 – 65)($20,000) = $80,000A–I–K 33 weeks

A–F–K 28 weeks

A–C–G–J–K 67 weeks

B–D–H–J–K 69 weeks

B–E–J–K 43 weeksCopyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 31

Example 2.3

STAGE 1Step 1. The critical path is B–D–H–J–K.

Step 2. The cheapest activity to crash per week is J at $1,000, which is much less than the savings in indirect and penalty costs of $28,000 per week.Step 3. Crash activity J by its limit of three weeks because the critical path remains unchanged. The new expected path times are

A–C–G–J–K: 64 weeks B–D–H–J–K: 66 weeks

The net savings are 3($28,000) – 3($1,000) = $81,000. The total project costs are now $2,624,000 - $81,000 = $2,543,000.

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 32

Example 2.3

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 33

Finish

K6

I15

F10

C10

D10

H40

J1

A12

B9

StartG

35

E24

STAGE 1

Example 2.3STAGE 2Step 1. The critical path is still B–D–H–J–K.

Step 2. The cheapest activity to crash per week is now D at $2,000.

Step 3. Crash D by two weeks. • The first week of reduction in activity D saves $28,000 because

it eliminates a week of penalty costs, as well as indirect costs. • Crashing D by a second week saves only $8,000 in indirect costs

because, after week 65, no more penalty costs are incurred. • Updated path times are

A–C–G–J–K: 64 weeks and B–D–H–J–K: 64 weeks• The net savings are $28,000 + $8,000 – 2($2,000) = $32,000. • Total project costs are now $2,543,000 – $32,000 = $2,511,000.

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 34

Example 2.3

Finish

K6

I15

F10

C10

D8

H40

J 1

A12

B9

StartG

35

E24

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 35

STAGE 2

Example 2.3

STAGE 3Step 1. The critical paths are B–D–H–J–K and A-C-G-J-K

Step 2. Activities eligible to be crashed:(A, B); (A, H); (C, B); (C, H); (G, B); (G, H)— or to crash

Activity K• We consider only those alternatives for which the costs of

crashing are less than the potential savings of $8,000 per week. • We choose activity K to crash 1 week at $4,000 per week.

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 36

Step 3.• Updated path times are: A–C–G–J–K: 63 weeks and B–D–H–J–K:

63 weeks• Net savings are $8,000 - $4,000 = $4,000. • Total project costs are $2,511,000 – $4,000 = $2,507,000.

Example 2.3

Finish

K5

I15

F10

C10

D8

H40

J1

A12

B9

StartG

35

E24

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 37

STAGE 3

Example 2.3

STAGE 4Step 1. The critical paths are still B–D–H–J–K and A–C–G–J–K.

Step 2. Activities eligible to be crashed: (B,C) @ $7,600 per week.

Step 3. Crash activities B and C by two weeks.• Updated path times are

• A–C–G–J–K: 61 weeks and B–D–H–J–K: 61 weeks• The net savings are 2($8,000) – 2($7,600) = $800. Total project

costs are now $2,507,000 – $800 = $2,506,200.

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 38

Example 2.3

Finish

K5

I15

F10

C8

D8

H40

J1

A12

B7

StartG

35

E24

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 39

STAGE 4

Example 2.3Stage Crash

ActivityTime Reduction (weeks)

Resulting Critical Path(s)

Project Duration (weeks)

Project Direct Costs, Last Trial ($000)

Crash Cost Added ($000)

Total Indirect Costs ($000)

Total Penalty Costs ($000)

Total Project Costs ($000)

0 — — B-D-H-J-K

69 1,992.0—

552.080.0

2,624.0

1 J 3 B-D-H-J-K

66 1,992.03.0

528.020.0

2,543.0

2 D 2 B-D-H-J-K

A-C-G-J-K

64 1,995.04.0

512.00.0

2,511.0

3 K 1 B-D-H-J-K

A-C-G-J-K

63 1,999.04.0

504.00.0

2,507.0

4 B, C 2 B-D-H-J-K

A-C-G-J-K

61 2,003.015.2

488.00.0

2,506.2

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 40

Indirect project costs = $250 per day Penalty cost = $100 per day past day 14.

Project Activity and Cost Data

ActivityNormal Time (days)

Normal Cost ($)

Crash Time (days)

Crash Cost ($)

Immediate Predecessor(s)

A 51,000

41,200

B 5800

32,000

C 2600

1900

A, B

D 31,500

22,000

B

E 5900

31,200

C, D

F 21,300

11,400

E

G 3900

3900

E

H 5500

3900

G

Application 2.3

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 41

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 42

13

19

F

2

15

21

13

13

G

3

16

16

5

5

D

3

8

8

8

8

E

5

13

13

5

6

C

2

7

8

0

0

B

5

5

5

0

1

A

5

5

6

Start

ES

LS

ID

DUR

EF

LF

16

16

H

5

21

21

Finish

Application 2.3

Project Activity and Cost DataActivity Crash Cost/Day Maximum Crash Time (days)

A 200 1B 600 2C 300 1D 500 1E 150 2F 100 1G 0 0H 200 2

Normal Total Costs = Total Indirect Costs = Penalty Cost = Total Project Costs =

$7,500$250 per day 21 days = $5,250

$100 per day 7 days = $700$13,450

Application 2.3

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 43

Step 1: The critical path is , and the project duration is

B–D–E–G–H21 days.

Step 2: Activity E on the critical path has the lowest cost of crashing ($150 per day). Note that activity G cannot be crashed.

Step 3: Reduce the time (crashing 2 days will reduce the project duration to 19 days) and re-calculate costs:

Normal Costs Last Trial = Crash Cost Added = Total Indirect Costs = Penalty Cost = Total Project Cost =

$7,500$150 2 days = $300$250 per day 19 days = $4,750$100 per day 5 days = $500$13,050

Application 2.3

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 44

Step 4: Repeat until direct costs greater than savings

(step 2) Activity H on the critical path has the next lowest cost of crashing ($200 per day).

(step 3) Reduce the time (crashing 2 days will reduce the project duration to 17 days) and re-calculate costs:

Costs Last Trial = Crash Cost Added = Total Indirect Costs = Penalty Cost = Total Project Cost =

$7,500 + $300 (the added crash costs) = $7,800$200 2 days = $400

$250 per day 17 days = $4,250$100 per day 3 days = $300

$12,750

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 45

Application 2.3

(step 4) Repeat

(step 2) Activity D on the critical path has the next lowest crashing cost ($500 per day).

(step 3) Reduce the time (crashing 1 day will reduce the project duration to 16 days) and re-calculate costs:

Costs Last Trial = Crash Cost Added = Total Indirect Costs = Penalty Cost = Total Project Cost =

$7,800 + $400 (the added crash costs) = $8,200$500 1 day = $500

$250 per day 16 days = $4,000$100 per day 2 days = $200

$12,900 which is greater than the last trial. Hence we stop the crashing process.

Application 2.3

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 46

The recommended completion date is day 17.

TrialCrash

Activity

Resulting Critical Paths

Reduction (days)

Project Duration

(days)

Costs Last Trial

Crash Cost

Added

Total Indirect

Costs

Total Penalty Costs

Total Project Costs

0 — B-D-E-G-H — 21 $7,500 — $5,250 $700 $13,450

1 E B-D-E-G-H 2 19 $7,500 $300 $4,750 $500 $13,050

2 H B-D-E-G-H 2 17 $7,800 $400 $4,250 $300 $12,750

Further reductions will cost more than the savings in indirect costs and penalties.

The critical path is B – D – E – G – H and the duration is 17 days.

Application 2.3

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 47

Assessing Risks

• Risk-management Plans– Strategic Fit

– Service/Product Attributes

– Project Team Capability

– Operations

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 48

Assessing Risks

• Statistical Analysis

– Optimistic time (a)

– Most likely time (m)

– Pessimistic time (b)

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 49

Statistical Analysis

a m bMean

Time

Beta distribution

a m bMeanTime

3σ 3σ

Area under curve between a and b is 99.74%

Normal distributionCopyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 50

Statistical Analysis• The mean of the beta distribution can be

estimated by

te =a + 4m + b

6

• The variance of the beta distribution for each activity is

σ2 =b – a

6

2

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 51

Example 2.4

Suppose that the project team has arrived at the following time estimates for activity B (site selection and survey) of the St. John’s Hospital project:

a = 7 weeks, m = 8 weeks, and b = 15 weeks

a. Calculate the expected time and variance for activity B.

b. Calculate the expected time and variance for the other activities in the project.

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 52

Example 2.4

a. The expected time for activity B is

The variance for activity B is

te = = = 9 weeks7 + 4(8) + 15

6

54

6

σ2 = = = 1.7815 – 7

6

28

6

2

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 53

Example 2.4b. The following table shows the expected activity times and

variances for this project.Time Estimates (week) Activity Statistics

Activity Optimistic (a)

Most Likely (m)

Pessimistic (b)

Expected Time (te)

Variance (σ2)

A 11 12 13 12 0.11

B 7 8 15 9 1.78

C 5 10 15 10 2.78

D 8 9 16 10 1.78

E 14 25 30 24 7.11

F 6 9 18 10 4.00

G 25 36 41 35 7.11

H 35 40 45 40 2.78

I 10 13 28 15 9.00

J 1 2 15 4 5.44

K 5 6 7 6 0.11

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 54

Application 2.4

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 55

The director of continuing education at Bluebird University just approved the planning for a sales training seminar. Her administrative assistant identified the various activities that must be done and their relationships to each other:

Application 2.4

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 56

Start

A

B

C

D

FinishE

F

G J

H

I

The Network Diagram is:

ActivityImmediate

Predecessor(s)Optimistic

(a)

Most Likely

(m)Pessimistic

(b)Expected Time (t)

Variance (σ)

A —5 7 8

B —6 8 12

C —3 4 5

D A11 17 25

E B8 10 12

F C, E3 4 5

G D4 8 9

H F5 7 9

I G, H8 11 17

J G4 4 4

For the Bluebird University sales training seminar activities, calculate the means and variances for each activity.

Application 2.4

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 57

ActivityImmediate

Predecessor(s)Optimistic

(a)

Most Likely

(m)Pessimistic

(b)Expected Time (t)

Variance (σ)

A —5 7 8

B —6 8 12

C —3 4 5

D A11 17 25

E B8 10 12

F C, E3 4 5

G D4 8 9

H F5 7 9

I G, H8 11 17

J G4 4 4

For the Bluebird University sales training seminar activities, calculate the means and variances for each activity.

6.830.25

8.331.00

4.000.11

17.335.44

10.000.44

4.000.11

7.500.69

7.000.44

11.502.25

4.000.00

Application 2.4

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 58

Analyzing Probabilities

TE = =Expected activity times

on the critical path Mean of normal distribution

• Because the activity times are independent

σp2 = (Variances of activities on the critical path)

z =T – TE

σp

• Using the z-transformation

where

T = due date for the project

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 59

• Because the central limit theorem can be applied, the mean of the distribution is the earliest expected finish time for the project

Example 2.5Calculate the probability that St. John’s Hospital will become operational in 72 weeks, using (a) the critical path and (b) path A–C–G–J–K.

a. The critical path B–D–H–J–K has a length of 69 weeks. From the table in Example 2.4, we obtain the variance of path B–D–H–J–K: σ2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89 Next, we calculate the z-value:

0.873.45

311.89

6972 z

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 60

Example 2.5Using the Normal Distribution appendix, we find a value of 0.8078. Thus the probability is about 0.81 the length of path B–D–H–J–K will be no greater than 72 weeks.

Length of critical path

Probability of meeting the schedule is 0.8078

Normal distribution:Mean = 69 weeks;σ = 3.45 weeks

Probability of exceeding 72 weeks is 0.1922

Project duration (weeks)

69 72

Because this is the critical path, there is a 19 percent probability that the project will take longer than 72 weeks.

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 61

Example 2.5

b. The sum of the expected activity times on path A–C–G–J–K is 67 weeks and that σ2 = 0.11 + 2.78 + 7.11 + 5.44 + 0.11 = 15.55. The z-value is

1.273.94

515.55

6772 z

The probability is about 0.90 that the length of path A–C–G–J–K will be no greater than 72 weeks.

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 62

The director of the continuing education at Bluebird University wants to conduct the seminar in 47 working days from now. Using the activity data from Application 2.4, what is the probability that everything will be ready in time?

The critical path isand the expected completion time is

T =

TE is:

A–D–G–I,

43.16 days.

47 days

43.16 days

(0.25 + 5.44 + 0.69 + 2.25) = 8.63And the sum of the variances for the critical activities is:

Application 2.5

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 63

Application 2.5

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 64

Start

A

B

C

D

FinishE

F

G J

H

I

The Network Diagram is:

The critical path is A-D-G-I

= = = 1.313.84

2.94

47 – 43.16

8.63

T = 47 days

TE = 43.16 daysAnd the sum of the variances for the critical activities is: 8.63

z = T – TE

σ2

Assuming the normal distribution applies, we use the table for the normal probability distribution. Given z = 1.30, the probability that activities A–D–G–I can be completed in 47 days or less is 0.9049.

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 65

Application 2.5

Monitoring and Controlling Projects

• Monitoring Project Status– Open Issues and Risks– Schedule Status

• Monitoring Project Resources

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 66

Solved Problem 2.1

Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the thirteenth day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedent relationships are given in Table 2.2.

a. Draw the project network diagram.b. What completion date would you recommend?

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 67

Solved Problem 2.1

ELECTRIC MOTOR PROJECT DATAActivity

Normal Time (days)

Normal Cost ($)

Crash Time (days)

Crash Cost ($)

Immediate Predecessor(s)

A 4 1,000 3 1,300 None

B 7 1,400 4 2,000 None

C 5 2,000 4 2,700 None

D 6 1,200 5 1,400 A

E 3 900 2 1,100 B

F 11 2,500 6 3,750 C

G 4 800 3 1,450 D, E

H 3 300 1 500 F, G

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 68

Solved Problem 2.1a. The network diagram is shown in Figure 2.10. Keep the

following points in mind while constructing a network diagram.

Start

Finish

A4

B7

C5

D6

E3

F11

G4

H3

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 69

Solved Problem 2.1b. With these activity times, the project will be completed in 19

days and incur a $700 penalty. Using the data in Table 2.2, you can determine the maximum crash-time reduction and crash cost per day for each activity. For activity A

Maximum crash time = Normal time – Crash time =4 days – 3 days = 1 day

Crash cost per day

= = Crash cost – Normal costNormal time – Crash time

CC – NCNT – CT

= = $300$1,300 – $1,0004 days – 3 days

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 70

Solved Problem 2.1

Activity Crash Cost per Day ($)

Maximum Time Reduction (days)

A 300 1

B 200 3

C 700 1

D 200 1

E 200 1

F 250 5

G 650 1

H 100 2

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 71

Solved Problem 2.1

PROJECT COST ANALYSISStage Crash

ActivityTime Reduction (days)

Resulting Critical Path(s)

Project Duration (days)

Project Direct Costs, Last Trial ($)

Crash Cost Added ($)

Total Indirect Costs ($)

Total Penalty Costs ($)

Total Project Costs ($)

0 — — C-F-H 19 10,100 — 3,800 700 14,600

1 H 2 C-F-H 17 10,100 200 3,400 500 14,200

2 F 2 A-D-G-H 15 10,300 500 3,000 300 14,100

B-E-G-H

C-F-H

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 72

Solved Problem 2.1The critical path is C–F–H at 19 days, which is the longest path in the network.

The cheapest activity to crash is H which, when combined with reduced penalty costs, saves $300 per day.

Crashing this activity for two days gives

A–D–G–H: 15 days, B–E–G–H: 15 days, and C–F–H: 17 days

Crash activity F next. This makes all activities critical and no more crashing should be done as the cost of crashing exceeds the savings.

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 73

Solved Problem 2.2An advertising project manager developed the network diagram in Figure 2.11 for a new advertising campaign. In addition, the manager gathered the time information for each activity, as shown in the accompanying table.

a. Calculate the expected time and variance for each activity.

b. Calculate the activity slacks and determine the critical path, using the expected activity times.

c. What is the probability of completing the project within 23 weeks?

Start

Finish

A

B

C

D

E

F

G

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 74

Solved Problem 2.2

Time Estimate (weeks)

Activity Optimistic Most Likely Pessimistic Immediate Predecessor(s)

A 1 4 7 —

B 2 6 7 —

C 3 3 6 B

D 6 13 14 A

E 3 6 12 A, C

F 6 8 16 B

G 1 5 6 E, F

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 75

Solved Problem 2.2

a. The expected time and variance for each activity are calculated as follows

te =a + 4m + b

6

Activity Expected Time (weeks) Variance

A 4.0 1.00

B 5.5 0.69

C 3.5 0.25

D 12.0 1.78

E 6.5 2.25

F 9.0 2.78

G 4.5 0.69

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 76

Solved Problem 2.2b. We need to calculate the earliest start, latest start, earliest finish,

and latest finish times for each activity. Starting with activities A and B, we proceed from the beginning of the network and move to the end, calculating the earliest start and finish times.

Activity Earliest Start (weeks) Earliest Finish (weeks)

A 0 0 + 4.0 =4.0

B 0 0 + 5.5 =5.5

C 5.5 5.5 + 3.5 =9.0

D 4.0 4.0 + 12.0 =16.0

E 9.0 9.0 + 6.5 =15.5

F 5.5 5.5 + 9.0 =14.5

G 15.5 15.5 + 4.5 =20.0

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 77

Solved Problem 2.2

Based on expected times, the earliest finish date for the project is week 20, when activity G has been completed. Using that as a target date, we can work backward through the network, calculating the latest start and finish times

Activity Latest Start (weeks) Latest Finish (weeks)

G 15.5 20.0

F 6.5 15.5

E 9.0 15.5

D 8.0 20.0

C 5.5 9.0

B 0.0 5.5

A 4.0 8.0

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 78

Solved Problem 2.2

A

4.0

0.0

4.0

4.0

8.0

D

12.0

4.0

8.0

16.0

20.0

E

6.5

9.0

9.0

15.5

15.5

G

4.5

15.5

15.5

20.0

20.0

C

3.5

5.5

5.5

9.0

9.0

F

9.0

5.5

6.5

14.5

15.5

B

5.5

0.0

0.0

5.5

5.5

Finish

Start

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 79

Solved Problem 2.2Start (weeks) Finish (weeks)

Activity Earliest Latest Earliest Latest Slack Critical Path

A 0 4.0 4.0 8.0 4.0 No

B 0 0.0 5.5 5.5 0.0 Yes

C 5.5 5.5 9.0 9.0 0.0 Yes

D 4.0 8.0 16.0 20.0 4.0 No

E 9.0 9.0 15.5 15.5 0.0 Yes

F 5.5 6.5 14.5 15.5 1.0 No

G 15.5 15.5 20.0 20.0 0.0 Yes

Path Total Expected Time (weeks) Total Variance

A–D 4 + 12 = 16 1.00 + 1.78 = 2.78

A–E–G 4 + 6.5 + 4.5 = 15 1.00 + 2.25 + 0.69 = 3.94

B–C–E–G 5.5 + 3.5 + 6.5 + 4.5 = 20

0.69 + 0.25 + 2.25 + 0.69 = 3.88

B–F–G 5.5 + 9 + 4.5 = 19 0.69 + 2.78 + 0.69 = 4.16

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 80

Solved Problem 2.2The critical path is B–C–E–G with a total expected time of 20 weeks. However, path B–F–G is 19 weeks and has a large variance.

c. We first calculate the z-value:

z = = = 1.52T – TE

σ223 – 20

3.88

Using the Normal Distribution Appendix, we find the probability of completing the project in 23 weeks or less is 0.9357. Because the length of path B–F–G is close to that of the critical path and has a large variance, it might well become the critical path during the project

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 81

Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 02 - 82

All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any

means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of the publisher.

Printed in the United States of America.