project management – a lean roadmap management – a lean roadmap plan pre-project reviews (due...

8

Click here to load reader

Upload: vuongdan

Post on 26-Apr-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Management – A Lean Roadmap Management – A Lean Roadmap Plan Pre-Project Reviews (Due Diligence) Initiate Execute Work Breakdown Structure Project Plan Scope Management

Project Management – A Lean Roadmap

Plan

Pre-ProjectReviews

(Due Diligence)Initiate Execute

Work Breakdown StructureProject PlanScope Management Plan

Conceptual ReviewFeasibility AssessmentProfitability MeasuresRisk AssessmentCourse of Action

Statement of Work (SOW)Scope StatementProject CharterAssemble Project FileCommunication PlanAction Register

Change Management PlanRisk PlanQuality PlanClaims Register

Performance Metrics Report

Knowledge Management (Lessons Learned)

Cost & Schedule Status

ControlCourse of ActionPreparation Questionnaire

Action RegisterResponsibility Assignment Matrix (RAM)Project Closure CriteriaInitial Risk Assessment

Cost & Schedule Status (Earned Value Analysis)

Close Project Closure ReportPost mortem MeetingLessons Learned

Michael D. Posdal, MBA, PMP, SSGB [email protected]

Page 2: Project Management – A Lean Roadmap Management – A Lean Roadmap Plan Pre-Project Reviews (Due Diligence) Initiate Execute Work Breakdown Structure Project Plan Scope Management

Project Life Cycle

Plan: Project management endeavors are designed to performPlan: Project management endeavors are designed to perform required outputs from Scope Definition (Initiation) to Final Product hand-off (Close) with management plans in place, have cost profiles and time allotments similar to the following slide.

Michael D. Posdal, MBA, PMP, SSGB [email protected]

Page 3: Project Management – A Lean Roadmap Management – A Lean Roadmap Plan Pre-Project Reviews (Due Diligence) Initiate Execute Work Breakdown Structure Project Plan Scope Management

Project Life Cycle - Plan

PROJECT MANAGEMENT PLAN0 1 yr

(Cumulative) 10% 45% 90% 100%Timeline

$Cost

Profile

$

Project Management Cost

$1.0M

Process Initiation Planning Execution & Control CloseDefinition Document how before start Get it done Monitor & correct Hand-off

Michael D. Posdal, MBA, PMP, SSGB [email protected]

Page 4: Project Management – A Lean Roadmap Management – A Lean Roadmap Plan Pre-Project Reviews (Due Diligence) Initiate Execute Work Breakdown Structure Project Plan Scope Management

Project Life CycleProject Life Cycle

R l ldReal-world: Realization of the Plan in many PM endeavors look more like this Real-world Slide (see next slide). Once the starting guns goes off;

Initiation and Planning phases are squeezed.

At best management plans, critical for a successful seamless objective fulfillment are formedsuccessful, seamless objective fulfillment, are formed during the execution phase, inadequate or, at worst, not at all.

Expediting fast-tracking or crashing tasks areExpediting, fast-tracking or crashing tasks are prevalent throughout to attempt schedule recovery.

Post mortem generally shows a comprehensivePost mortem generally shows a comprehensive, good quality product is delivered, but, late and well over budget.

Michael D. Posdal, MBA, PMP, SSGB [email protected]

Page 5: Project Management – A Lean Roadmap Management – A Lean Roadmap Plan Pre-Project Reviews (Due Diligence) Initiate Execute Work Breakdown Structure Project Plan Scope Management

Project Life Cycle – Real-world

PM Post Mortem

0 Late Delivery 1.2 Yr

Timeline

(Cumulative) 10% 25% 95% 100%

Cost

Profile

$

Project Management CostProfile

Planning

Task

Catch-up Over budget $1.2M

Expedite

Process Initiation Planning Execution & Control CloseDefinition How before start Get it done Monitor & correct Hand-off

Michael D. Posdal, MBA, PMP, SSGB [email protected]

Page 6: Project Management – A Lean Roadmap Management – A Lean Roadmap Plan Pre-Project Reviews (Due Diligence) Initiate Execute Work Breakdown Structure Project Plan Scope Management

Project Life Cycle

Applying Lean principles to Project Management addresses root issues that cause cost overruns and late delivery:

Pull the project manager into the decision making process to address costs and i k t t t th E ti T ( P j t i )risks not apparent to the Executive Team (pre-Project reviews)

Use Initiation Phase as a 2nd Pass opportunity to double-check the decision to launch. Planning tasks are pulled back adding valuable sanity check information allowing reversal with minimal cost and time or, more likely, make mid-stream course corrections to mitigate risks and ill-fated execution moves.

The Plan phase concentrates on determining resources needed and when to execute scope. Risk is continually assessed and any change has a pre-planned response.

Execution and Control phases focus on project execution management and documentation of any variances (positive or negative).

Cl h i t j t h d ff b t iti l t t t dClose phase is not just hand-off, but, a critical post mortem assessment and lessons learned report generator. Although projects are unique, by definition, within each organization new projects have many similarities. Practice Continuous Improvement and assure doing it better the next time.

Michael D. Posdal, MBA, PMP, SSGB [email protected]

Page 7: Project Management – A Lean Roadmap Management – A Lean Roadmap Plan Pre-Project Reviews (Due Diligence) Initiate Execute Work Breakdown Structure Project Plan Scope Management

Project Life Cycle - LeanPROJECT MANAGEMENT – the Lean WayPROJECT MANAGEMENT the Lean Way

0 On-time 1 yr

Timeline

(Cumulative) 25% 45% 90% 100%

Cost$

Profile

Pre-project

$

Project Management Cost

Under budget

$0.8M

Reviews

budget

Process Initiation Planning Execution & Control CloseDefinition How before start Get it done Monitor & correct Hand-off

Michael D. Posdal, MBA, PMP, SSGB [email protected]

Page 8: Project Management – A Lean Roadmap Management – A Lean Roadmap Plan Pre-Project Reviews (Due Diligence) Initiate Execute Work Breakdown Structure Project Plan Scope Management

Why Apply Lean Principles to PM?

•Determine alignment and feasibility before project launch

•Identify and plan risk responses prior to launch

•Confirm financial viability prior to launch

•Ensure important planning tasks are completed

•Minimize probability of schedule creep

•Lower Project management cost

•Lower Project delivery costLower Project delivery cost

•Reduce need for fast-tracking and crashing to maintain schedule (less expediting, staying ahead of the curve)

Michael D. Posdal, MBA, PMP, SSGB [email protected]