project deliveryproject forecast reports: important terms baseline - data agreed by a recognized...
TRANSCRIPT
PROJECT DELIVERYGuide To Project Management
Moritz Quotschalla, Hana Salihodzic, Armin Rekic
Control Cycle
Plan
provides road map how project will achieve its targets
identifies deliverables
shows to whom work will be delegated
Delegate portfolio management team delegates responsibility to the project steering group
project steering group delegates responsibility to the project manager
project manager delegates responsibility to the project teams
always describe the constraints within which the work must be carried out
both parties must agree upon:
Product description Dependencies
Planned start/finish date Prerequisite products
Planned effort/cost
Delegate delegated work has to be controlled:
timesheet code (charge hours)
skills/experience required
roles (describe responsibilities)
reporting arrangements
escalation conditions
techniques, processes, procedures
arrangement should be set out in the contractual terms of reference
Monitor and report
observation and supervision by those in the management team needs report
each level in the hierarchy needs information without encroaching on the responsibilities of other levels
reports provide the information necessary for decision-making or corrective action
Portfolio management team oversees the wider portfolio of projects must meet every month to evaluate
portfolio
standard agenda for a regular meeting:
prospects
initiated projects
notifications
completions
realisations
project register to know state of portfolio
gives overview of the portfolio
shows how the portfolio is contributing to the organisation‘s strategic imperatives
illustrates how the projects measure upto the balanced scorecard of targets
usually considered quarterly
Project steering group each project steering group directs individual project needs control cycle
project manager has to alert PSG immediately if something exceptional happens
to maintain a level of control PSG can intervene through:
project initiation and closure
holding meetings at different project stages
holding unscheduled meetings
holding scheduled meetings
project forecast reports
Stage meetings – project steering group PSG is required to deliver a successful outcome (benefits > costs)
should schedule a meeting at the beginning of every planned stage agenda:
review of previous stage
review of project plan
review of business case
review of next stage plan
approval of controls
approval to proceed
Unscheduled PSG meetings
necessary only if a breach of the escalation conditions is forecast
agenda similar to stage meeting, but review of previous stage is replaced bypresentation from the project manager:
what has happened to require notifying the PSG
the effect on the plan
the options available to correct the matter
the recmmended solution and its effect on the plan
Scheduled PSG meetings
no news does not always mean good news regular PSG meetings are held (oftenevery month)
not event-based
agenda is based around the review and approval of latest project forecast report
Project manager
is required to plan, monitor and control time, cost and quality
maybe pressure from stakeholders amend aspects of the projects as theirexpectations change
identify problems and risks
motivate project team members to deliver on time, on budget etc.
Project team progress meetings
project manager is responsible for a team of people who must be subjected accordingto the control cycle
usually PSG wants progress reports every two weeks
Agenda – project team progress meetings
delivery highlights during previous period
delivery highlights during next period
timescales
budgets
quality
risks and issues
actions and decisions
Project forecast reports snapshots of the project, taken at regular and frequent intervals throughout its
lifetime
important way to communicate with:
management stakeholders
project steering group
portfolio management team
for members of the project steering group, a summary of key project management information sufficient
for the project manager a detailed information is a must
Project forecast reports: important terms
Baseline - data agreed by a recognized authority used as a stable foundation to track
variances; should not be changed
Actual to Date (ATD) - this should increase as the project progresses
Estimated to Complete (ETC) - latest and most recent estimate
Forecast at Completion (FAC) - the sum of actual to date and estimate to complete
Variance - the difference between the baseline and the forecast at completion
Project forecast report: time forecast
lists every product or milestone from the plan
shows the progress made in achieving targets
shows the extent to which the forecast end date is likely to be met
Project forecast report: cost forecast lists the resource types, including all the people and non-human costs
Project forecast report: cost forecast lists the costs by product; important if earned value analysis is to be carried out
Project forecast report: project quality forecast
identifies the intended success criteria and shows how close the project is to meetingthose expectations
explains what should be done to manage variances
important for the project steering group
Project forecast report: product quality log
is a simple report that follows the life cycle of each product, showing to what extent each of the product’s steps have been successfully achieved. These steps are:
draft complete;
review complete;
changes completed;
approved fit for purpose (ffp);
Project forecast report: benefits forecast limited value in reporting progress in achieving benefits during the life of the project
Project forecast report: risk register helps the project manager to review the project
Timesheet best way to gather the data
Earned value analysis measures performance against the time, cost and quality targets
planned value: budgeted cost of work schedule
earned value: budgeted cost of work performed
Earned value analysis: third measure needed
actual cost of work performed: the cost of work completed to date
Calculations
cost variation: the budgeted cost of work scheduled minus the actual cost of workplanned
schedule variation: the budgeted cost of work performed minus the budgeted cost ofwork scheduled
schedule delay: when the budgeted cost of work scheduled is the same as thebudgeted cost of work performed, less the date when the data was captured, measured in days
Earned Value Summary: Conclusions underspent: the actual cost of work performed is less than the budgeted cost of work
performed
behind schedule: the budgeted cost of work scheduled is greater than the budgetedcost of work performed
Quality reviews
earned value analysis depends on being able to measure the completeness of a product
successful execution of the plan depends on managing quality as well as time and cost
Different forms of quality reviews
Testing: where a physical test is necessary
Inspection: where a product or service is scrutinised to determine its fitness
Demonstration: where the potential errors are identified by a display
Formal quality review: where a group of carefully identified reviewers are invited tochallenge a product’s ability
Informal quality review: a less structured version of a formal quality review
Quality review: preparation
the quality plan will contain all product descriptions, together with a list of qualityresponsibilities identifying who will be responsible for reviewing and approving eachproduct:
chair: to ensure that a clear conclusion is drawn
scribe: to record the actions and decisions
author: to offer insight into the product and its construction
reviewers: to identify errors
Quality review: review
starts with an introduction of the participants and an explanation of the purpose ofthe review:
significant errors are identified as a priority
reviewers present and describe their error lists in turn
each reviewer has an equal opportunity to contribute
each quality criterion in the product description is considered in turn
Quality review: conlusion
approved: the product can be accepted
approved subject to amendments
product not ready
product needs significant change
insufficient reviewers
unqualified reviewers
unprepared reviewers
Informal quality review
common form of product appraisal which, if managed well, has many of the benefitsof the formal quality review but is cheaper to implement
How to make sure that the informal quality review is as effective as possible:
identify a balanced selection of reviewers to represent commercial, customer and developerviewpoints
set a time by which reviewers should return their identified errors
provide a budget within which reviewers should work and a cost code
provide a product description against which the reviewers will compare the product
Control
important for monitoring and reporting
the project might easily find itself in a worse position, if the wrong decision is made ortaken by someone without the appropriate authority.
This process makes sure that, if the project’s parameters have to change, it is a conscious, intended management control
Control: change / analysis
change:
must be managed, so anyone may raise a change request or an issue on a freely availableform
change log needed to give an overview of every change request made and issue raised
analysis:
what are the reasons for the issue or CR?
the project manager should oversee the analysis to make sure the background is clearlyexplained
Control: impact assessment
an actual or potential change can be significant and expensive and therefore needs tobe evaluated:
business case: to assess the effect on benefits
user requirements document: to assess the effect on scope
solution design document: to assess the effect on the solution’s robustness
project plan: to assess the effect on timescale, costs and quality
risk register: to assess the effect on the riskiness of the project
Control: solution proposal keeping fixed deadline:
more/faster resources
reduce quality (checks)
working within a fixed budget:
cheaper/ fewer resources, less overtime work
delivery day delayed, reduce quality / quality checks
meeting the original quality and content expectations:
more/“better“ resources
improved quality checks
Control: decision/amend plan
decision:
important to determine who should decide whether to accept the proposed solution
Red, amber and green escalation conditions
amend plan:
change significant – additional changes to project plan and/or business case
change requests earlier or more often
Importance of effective control
many small changes significant effect on project
effective control mitigates the risk of a project failing one day at a time
Thank you for your Attention!