project cost estimatingsp.design.transportation.org/documents/projectcostestimatingreport… ·...
TRANSCRIPT
PROJECT COST ESTIMATING A SYNTHESIS OF HIGHWAY PRACTICE
Requested by:
American Association of State Highway and Transportation Officials (AASHTO)
Standing Committee on Highways
Prepared by:
Cliff J. Schexnayder, Ph.D., P.E. Eminent Scholar
Arizona State University
Sandra L. Weber, Ph.D., P.E. Associate Professor
Arizona State University
Christine Fiori, Ph.D., P.E. Assistant Professor
Arizona State University
June 2003 The information contained in this report was prepared as part of NCHRP Project 20-7, Task 152,
National Cooperative Highway Research Program, Transportation Research Board.
PREFACE This report is the contractor’s report requested by the AASHTO Standing Committee Highways and conducted as part of NCHRP Project 20-07. It presents a summary of current project cost estimating practices. It includes detailed information concerning the estimating practices of Departments of Transportation with examples of existing agency processes. Special attention is devoted to conceptual estimates and to the unique challenges of estimating mega projects. The appendices have complete descriptions of unique processes used by some Departments.
ACKNOWLEDGEMENTS
This study was requested by the American Association of State Highway and Transportation Officials (AASHTO), and conducted as part of National Cooperative Highway Research Program (NCHRP) Project 20-07. The NCHRP is supported by annual voluntary contributions from the state Departments of Transportation. Project 20-07 is intended to fund quick response studies on behalf of the AASHTO Standing Committee on Highways.
Cliff J. Schexnayder, Ph.D., P.E., Eminent Scholar, Sandra L. Weber, Ph.D., P.E., Associate Professor, Christine Fiori, Ph.D., P.E., Assistant Professor, and Jonathon Eric Byrnes, graduate student, Arizona State University collected the data and prepared the report.
Valuable assistance in the preparation of this synthesis was provided by the Topic Panel of NCHRP Project 20-07/Task 152, consisting of George Bradfield, Assistant Department Head/Chief Estimator, Georgia Department of Transportation; Byron Coburn, Staunton District Construction Engineer, Virginia Department of Transportation; Shirley Daugherty, Trns*port Systems Manager, Nebraska Department of Roads; Bruce Green, Bidding and Contract Services Engineer, Missouri Department of Transportation; Wayne Kinder, Assistant Chief Road Design Engineer, Nevada Department of Transportation;
Daniel R. McDonald, Senator-48th Legislative District, Washington State Legislature; Don Nelson, Director of Environmental and Engineering Programs, Washington Department of Transportation; Ted Walschleger, Chief, Project Development & Implementation Section, Illinois Department of Transportation; Paul Nishimoto, Highway Engineer, Major Projects Team, Federal Highway Administration
Timothy G. Hess, Senior Program Officer, NCHRP, Transportation Research Board, worked with the consultant and the Project 20-07(152) panel in the development and review of the report.
Information on current practice was provided by all fifty State highway and transportation agencies. Their cooperation and assistance are appreciated.
The opinions and conclusions expressed or implied are those of the research agency that performed the research and are not necessarily those of the Transportation Research Board or its sponsors. This report has not been reviewed or accepted by the Transportation Research Board's Executive Committee or the Governing Board of the National Research Council.
Project Cost Estimating A Synthesis of Highway Practice
SUMMARY Departments of Transportation need a strategic approach to early cost
declarations. Departments must:
¢ Avoid false precision − a big problem is created by early optimism.
¢ Relate contingency to the layman’s everyday experiences with
uncertainty.
¢ Invest in continuous and transparent QA/QC of your estimating
processes.
To have estimate accuracy there needs to be institutional and management
maturity. Poor administration, including overly complex organizational
structures, convoluted contracting practices, and inexperienced personnel will
cause project cost problems stretching from the original estimate to completion
of construction.
Throughout a project’s development estimates are completed to ensure that
sufficient funds have been allocated to complete the proposed work. The
chronological development of a project estimate begins with the conceptual
estimate and evolves through project development until the final pre-bid
estimate is produced.
The actual cost of a project is subject to many variables, which can, and will
significantly influence the range of probable projected cost. Any one cost
number represents only one possible result of the multiple variables and
assumptions. These variables are not all directly controllable or absolutely
quantifiable. Therefore, cost estimating process must consider probabilities in
assessing cost, using a recognized, logical and tested process.
2
At the conceptual stage of project development there is a very large
potential range for ultimate cost of the work. DOTs need to consider:
¢ How are estimates usually done?
¢ What do we need to do to get a valid estimate?
¢ How do we develop a reliable cost estimating and validation process?
¢ The estimating process must evaluate variability and risk using logical,
reasonable statistical (probability) methods.
The traditional approaches to early (conceptual) estimating match poorly
with the public’s intuitive understanding of “what engineers can tell us.” The
meaning of “contingency” in an estimate is not clearly defined in many DOTs
and our use of the term completely mystifies ordinary citizens. The public sees
“development” of an estimate as evidence of doubtful engineering competence
or worse − untrustworthy actions. Engineering skill and judgment invested in
project planning is obscure to the general public, legislators, community
opinion leaders, and the media. Cost busts are easy for the public to
understand. But who wants to appreciate the fine points of route alignment,
difficult geotechnical conditions, or wetlands mitigation analysis?
Many DOTs do not have a set of written estimating procedures to guide
those charged with preparing project estimates. The foundation of a good
estimate is the formats, procedures, and processes used to arrive at the cost.
Estimate documentation must be in a form that can be understood, checked,
verified, and corrected. How inflation is treated in the estimate must be clearly
stated. FHWA recommends the cost estimates be prepared in year-of-
expenditure dollars, inflated to the midpoint of construction, with some
allowance for schedule slippage taken into account. Reporting the costs in
year-of-expenditure dollars will greatly reduce the media and public perception
of “cost growth.” DOTs would benefit greatly by producing an estimating
manual of standard formats, procedures, and processes to be used by both DOT
3
estimators and design consultants retained for estimating purposes.
Estimating takes time, which is expensive, and one should spend it only on
detail that is relevant to decisions. Most states that perform detailed estimates
do so only for major items of work. Major items are defined as those work
items that taken collectively account for 65 - 80% of a project’s cost. The
remaining work items are estimated using historic bid averages. States using
historic bid price estimating systems reported applying these cost factors to all
work items in a project to develop the estimate.
The project estimated early in project development is often not the project
actually built. Scope changes can be defined as any discretionary change in
the size or configuration of a project. Most changes in scope result from a
better understanding of the need for a project. The longer a project takes to get
to field construction, the more room there is for scope changes to be made, and
the more likely they will happen.
In order to ensure that designers are aware of how scope changes will affect
project cost, it is advantageous to require submittal of a cost estimate along
with each design submittal. When large differences between the conceptual
estimate and the design estimate are reported (>10%), approval should be
required from the supervisory level or higher before design proceeds in order
to ensure sufficient funds will be available for construction. If the funds will
not be available then changes will have to be made to reduce the overall
project cost, this may bring about a project scope reduction.
An estimate must be in a form that can be understood, checked, and
verified. After receipt of the bids, the estimator or estimators that estimated a
project should be involved in the bid analysis for that project prior to award.
This will give them an opportunity to spot bidding trends early and also ensure
that someone who is knowledgeable about the estimate is involved in the
decision to award
4
Mega projects have characteristic traits besides cost and size that make
them extremely challenging to estimate and which estimators should always
consider when reviewing costs assumptions. These include:
¢ Mega projects stretch available resources to the limit - labor, material,
management skill, and information systems
¢ Mega projects have a high profile with political subdivisions and the
public
¢ Mega projects are very noticeable by regulators
¢ Mega projects are unusually long duration projects and there is less
likelihood of maintaining continuity of management
The most important predictor of cost growth and schedule slippage in mega
projects is the extent to which the project encounters regulatory constraints in
the following areas:
¢ Protection of the natural environment from the effects of the project
¢ Protection of the public health and safety from the effects of the
project
¢ Controls on the use of labor or procurement
¢ Other government standards or regulations
Unless government regulations are very well understood, the costs for a mega
project will not be well defined.
Virtually any form of technological innovation in a project is likely to result
in cost growth. Measures of innovation are:
¢ Whether or not the project embodied any first-of-a-kind technology.
Whether the project employed any new materials or methods of construction
5
CHAPTER ONE
INTRODUCTION
BACKGROUND
Effective management of transportation projects is critical to this Nation’s economic vitality.
Recently, national publicity about large, high-visibility transportation projects has called into
question the ability of departments of transportation to forecast accurately and to control the final
cost of their projects. This fact is illustrated by the media coverage of bids for major projects
including the Wilson Bridge in Washington, D.C. (1) and the Bay Bridge replacement in San
Francisco, California (2), and the attention of federal and state legislators to transportation
project management because of changes in the announced cost of undertakings like the Central
Artery/Tunnel project in Boston (3 & 4), the Springfield Interchange project in Northern Virginia
(5 & 6), and the Hoover Dam Bypass (7). In most cases, the final cost (or cost projections during
construction) have been significantly higher than the cost estimates prepared and released during
initial planning, preliminary engineering, final design, or even at the start of construction (8).
The ramifications of differences between early project cost estimates and bid prices or the final
cost of a project can be significant. As a result of both higher bids and project cost growth,
estimating for projects over $10 million was recently a topic of review by the Federal House
Subcommittee on Transportation Appropriations.
Over the time span between project initiation (concept development) and the completion of
construction many factors may influence the final project costs. This time span is normally
several years in duration but for the highly complex and technologically challenging mega
projects it can easily exceed 10 years. Over that period major changes to the project scope and
its setting (the macro environment) can occur. Factors that often drive increases in a project’s
final cost include changes in project scope, unforeseen engineering complexities and
constructibility issues, changes in economic and market conditions, lack of organizational
capacity and/or capability, changes in regulatory requirements, local governmental pressures,
and a transformation of community expectations. Additionally when there is a disruption of
management and political continuity coherent strategies for control of scope, schedule, and cost
are often impacted adversely.
6
Large transportation projects are extremely expensive, with costs of individual projects
reaching as high as $14 billion in recent years (4). These mega projects require that a significant
amount of money be obligated early in project development. Estimating the cost of a given
project is the responsibility of the individual state departments of transportation (DOT).
Estimates of a project’s cost are made throughout its development cycle (Figure 1). These
estimates shape allocation decisions, influence long-term spending plans, and serve as a
framework for accounting and control. The estimate is a baseline to measure project
management performance. At the start of a project a conceptual estimate is generated based on
limited information in order to screen projects and work the project into the DOT’s five (5) year
project plan. Once the project is set in the DOT planning cycle, design can begin.
Project Stage
Concept Development Design Advertisement Bid/ Award Construction
Time
Estimate Conceptual Estimate
Design Estimates
Prebid Estimates Bid Analysis Change Orders
FIGURE 1 Estimate Development in Relation to Project Development
Frequently the engineers performing conceptual estimates use only gross historical bidding
data to develop their estimates. As a project progresses from concept to final design more of the
unknown factors can be eliminated from the estimate and numbers that reflect the final design
requirements can be produced. Estimates at final design, prior to bid, are often referred to as the
state’s or engineer’s estimate, and are used to finalize project funding prior to bid solicitation and
construction. In the case of all these estimates the estimator must start with a set of assumptions
that certain factors affecting cost will remain constant or change in predicted ways. Key
assumptions are:
¢ Scope of the project will not change
¢ Inflation has been forecasted appropriately
¢ No unanticipated regulatory changes will occur
¢ The project will not encounter unusually bad luck in the form of strikes, especially
damaging weather, or other uncontrollable events.
7
¢ The project will not be mismanaged.
Many studies of project cost estimation have found that the final total cost incurred in
designing and constructing projects of all types (rail, bridges, road, process plants, refinery,
power plants, mineral extraction) almost always exceeds the amounts estimated (8 & 9). In the
case of one study of process plant estimates it was found that the unreliability and uncertainty
surrounding the accuracy of the cost estimates vastly exceeded any normal range of expected
uncertainty associated with capital cost projections (9).
An estimate is accurate if it is close to the actual final cost of the project. Any single estimate
forms part of a probabilistic distribution that, ideally, clusters around an accurate average. A
“good” cost estimator is one whose estimates are “reasonably” close to the actual costs most of
the time. In statistical terms, this means that a good estimator’s distribution is modally peaked
around actual costs, with a reasonably small average deviation (9). The size of the deviation
depends on the type of estimate and when it is made. For early estimates, the typical average
deviation (confidence range) is larger than in the case of more definite estimates made when
design is complete and the project fully defined. However, because the estimator always lacks
complete information, estimates always incorporate some uncertainty about final project cost.
Uncertainty is greatest during the early project stages, and decreases, as the project is thoroughly
defined. Figure 2 illustrates the typically assumed relationship between estimate accuracy and
the amount of information available at different stages in a project’s development. As the
estimator acquires more definite information, the confidence ranges steadily narrow.
The percentages presented in Figure 2 are conventional estimating expectations and represent
no more than approximate ranges commonly used in the construction industry. They are
presented here only to illustrate the assumptions that estimating error is limited, declines during
project development, and tends on the whole to be unbiased. Very early estimates (conceptual)
exhibit the greatest amount of uncertainty. The plus or minus 40 percent confidence range
typically associated with these estimates reflects the lack of definite project information (9).
Subsequent estimates are made throughout project design as continuing checks on cost
expectations. The later estimates are necessarily assumed to be increasingly accurate cost
predictors and the confidence intervals decline to where the final definitive estimate is expected
to be very close (plus or minus 5 percent) to actual project costs.
8
FIGURE 2 Typical Bounds of Estimate Accuracy vs. Project Development (10).
Some authors seem to imply that all estimates should be expected to fall within the confidence
interval. Others adopt a more probabilistic perspective and assume that the intervals represent a
range of two standard deviations, encompassing about 95 percent of the estimates (11). Still
others have suggested that 80 or 90 percent of the estimates fall within the depicted range (12).
The implied assumption of the figure is that the estimates are symmetrically distributed around
the actual costs.
A study of estimates for process plants revealed a pattern of estimation deviation in sharp
contrast to the usual expectation of actual cost falling symmetrically within established ranges of
estimated cost (9), Figure 3. The points on the figure are developed by dividing each estimated
project cost by the project’s total actual cost. A value of one indicates a perfectly estimated
project. When the estimate is low (estimate < actual cost) produces a ratio value of less than one,
or signifying cost overruns. Figure 3 contrasts the estimation experience of the studied plants
with the typically assumed ranges illustrated in Figure 2. The V-shaped funnel at the top of
Figure 3 approximates the typical assumption that estimates tend on average to equal actual
project cost with uncertainty declining monotonically over the period of project definition. It is
clear that, in the case of process plants, early estimates were much too low. The early estimates
9
(conceptual) averaged less than one-half of actual cost. Based on more recent studies (8), it
appears that a similar tendency is true in the case of transportation projects.
FIGURE 3 Estimate experience of pioneer process plants (9).
Cost estimates are merely predictions and can therefore be wrong. Problems will arise when
contractors submit bid prices that are significantly higher than the estimate prepared by the DOT.
At this point either more money must be allocated or the project scope must be reduced in order
to lower project costs to within budget limits. This frequently necessitates a significant amount
of project reengineering, which adds additional cost to the project while reducing its overall
value.
10
This research examines the estimating practices currently in use by state Departments of
Transportation. It presents a review of DOT estimating practices and discusses actions that can
help agencies produce estimates that are in line with the current challenges of large
transportation reconstruction projects in urban environments. The research involved all aspects
of estimating from the conceptual estimate, to the final engineer’s estimate (which is used for bid
analysis). Additionally, issues such as the decision process for determining whether to award a
project when bids are above the engineer’s estimate and collusion detection are examined.
Data was collected from all fifty DOTs and analyzed based on the size of the DOTs’
construction programs and estimating practices. The two major estimating techniques utilized by
DOTs, detailed estimating and historic bid price estimating, are examined and their performance
compared.
HISTORY – THE HOLLAND TUNNEL
Estimating and managing the cost of complex infrastructure projects has been a universal
challenge for decades. Looking for wisdom by studying the past is a very complicated matter, a
study of the builders who preceded us can provide an appreciation of the difficulties in
estimating and constructing a successful project. The lessons of the past must be heeded if one is
to succeed today. The Holland Tunnel was, when it opened in 1927, the longest underwater
tunnel ever constructed. Additionally, it was the first mechanically ventilated underwater tunnel.
A review of the Holland Tunnel project serves to highlight the critical issues associated with
estimating the costs of mega projects. Most importantly, however, such a review provides
concrete examples of the potential cost escalation factors that are faced even today by engineers.
The construction of the Holland Tunnel, which connects New York City to New Jersey, is a
very enlightening example of a transportation project experiencing cost growth as it moved from
initial conception to completion of construction. Many of the difficulties associated with
estimating the costs of large, long lead-time projects are illustrated by the events that plagued
this historical work.
New York City was in the mist of a severe coal shortage in early 1918. This shortage of coal
was not due to a strike, the lack of production, or even to a lack of supply. Plenty of coal was
11
stockpiled in the storage yards of Jersey City just across the Hudson River from New York City.
In fact, from the upper floors of Manhattan’s buildings, mounds of coal could be seen across the
Hudson on the New Jersey shoreline, but the coal needed to be shipped across the Hudson River.
The only means available at the time to ship the coal was ferryboat, however during the winter of
1918 the Hudson froze over and boats could not cross.
A joint New York and New Jersey commission had been investigating a new means of
transportation across the Hudson since 1906 and the coal shortage of 1918 applied the pressure
necessary to motivate the commission to arrive at a solution for a more efficient and dependable
means of cross river transportation (13 & 14). A tunnel was found to be the most economical
solution. Rail tunnels under bodies of water had long been in use, but this was to be a new type
of tunnel. The automobile was emerging as an increasingly predominate means of transportation
and it was therefore decided that this tunnel should be for vehicular traffic. The tunnel would
have to employ new ventilation technologies in order to purge its air-supply of the deadly
exhaust gases produced as by products of the internal combustion engine. The design for this
tunnel would have to be different from anything built before.
Eleven designs were considered for the tunnel, most notably, one by the engineer responsible
for finishing the Panama Canal, George Washington Goethals. Goethals was a national hero for
having completed the canal and was assigned as a consulting engineer to the Holland project.
Because of his professional status his design received the most publicity. His design called for a
single, bi-level tunnel with each level for opposing directions of traffic. The tunnel was to be
24½ feet wide to allow for three lanes of traffic. His estimate, based on his conceptual design,
was $12 million dollars and three years to construct. World War I consumed much of the
nation’s steel and iron production, so in order to cut costs, Goethals’ design made use of cement
blocks instead of steel or iron to construct the tunnel. This type of design was entirely new and
would require a new construction technique. Goethals’ plan was presented in late February of
1919 and it again appeared to be the front-running plan (15). Goethals however, had
responsibilities elsewhere and as a result he was not named chief engineer for the project.
In June of 1919 Clifford M. Holland was named to head the project along with a board of five
other consulting engineers (16). Holland had vast experience in constructing subways and
12
tunnels in New York. The total cost of engineering would be approximately six percent of the
total cost, which through 1919 was taken at Goethals’ estimate of around $12 million. Holland
produced a report in February of 1920 based on his analysis of the Goethals’ design of the
project as a whole. His findings were not what had been expected. Holland found:
¢ The capacity of the tunnel had been greatly overestimated; a width of 24½ ft would allow
for only two lanes of traffic.
¢ The lining of concrete blocks would neither withstand the external loads exerted on the
tunnel nor would they be dense enough to resist the buoyant forces of the semi-fluid soils
at the bottom of the Hudson River.
¢ The method of construction required for Goethals’ design would increase the difficulties
of construction as it remained undeveloped and was completely untried.
¢ The estimated cost of construction was grossly low.
¢ The time allowed for construction was also far short of what would be actually needed.
The panel of consulting engineers gave unanimous support for Holland’s analysis. Holland
presented a design of his own which was also supported unanimously by the board of consulting
engineers. His design called for twin cast-iron tubes, 29 ft in diameter, with each tunnel to be
used for opposing directions of traffic. Holland’s design would be built using established
methods of tunnel construction that had been implemented under the Thames River in London,
and used for rail tunnels under the East River and further up the Hudson. Holland estimated the
cost at $28,669,000 (17) and the time for construction at three and one-half years. Upon receipt
of Holland’s report and Goethals’ responses, the joint committee of the New York and New
Jersey Bridge and Tunnel Commissions had to decide how to proceed.
Debate about the tunnel design continued for more than a year creating disagreements
between the New York and New Jersey Commissions. The board of consulting engineers’
unanimous support of Holland’s design and analysis convinced the joint commissioners to direct
Holland to devote no more time to Goethals’ design and to proceed with work on the twin cast-
iron tube design. The two state’s commissioners squabbled for a time over recognition of new
13
consulting board engineers appointed by New Jersey and there was a disagreement about
awarding a contract to a newly incorporated company headed by a New Jersey commissioner’s
relative. These delays cost the two states over half of a million dollars. However, in mid-
November of 1921 an agreement (18) was reached that allowed work to proceed. Construction
had started on the New York side in October of 1920 and in late December 1921 the New Jersey
portion of the tunnel was bid (19). The completion date mandated was December 31, 1926. The
construction schedule was now set at five years.
Estimated costs for the project were increased multiple times throughout the early years of
construction. In the same time period forecasted traffic had increased so as to necessitate larger
entrance/exit plazas. By mid 1923 the cost of acquiring new land for entrance and exit plazas
(20) and increases in material and labor expenses were estimated to add another six million
dollars to the project. By the beginning of 1924, the mid-1923 re-estimated costs had been
increased due to several factors. The total of the two increases amounted to $14,000,000 (21).
This was an increase of 49% from Holland’s original estimate. The issues that led to the
increases in price were both functional and aesthetic in nature. A tile lining was selected to cover
the entire interior surface to optimize lighting conditions. The estimated six million tiles added
$750,000 to the cost. More intricate designs for approach sections and the widening of approach
roadways increased the total costs $3,598,822 and $100,000, respectively. An architectural
treatment for the approach sections added $1,160,000. Increases in labor and material costs
came to a total of $3,194,178, and $500,000 in additional contingencies were also included in
these cost escalations. Redesign of the ventilation system was also required due to the findings of
tunnel-gas studies, which had not been completed by the time Holland had produced his original
estimate. The total for this redesign was $4,422,000 which included the following: $1,424,000
for equipment stations, substations for electrical power, ventilation equipment for shafts and
tunnels, buildings for housing emergency equipment, fire extinguishers, telephone systems, and
traffic signals; $1,248,000 for additional equipment; $750,000 to increase the tunnel diameters
by six inches to allow for larger ventilation ducts. Holland also decided to substitute cast-steel
for cast-iron to increase the strength and safety factors of the tunnel at a cost of $575,000.
Lastly, the New Jersey ventilation shafts had to be redesigned along with their corresponding
foundations at a cost of $700,000 due to unknown soil conditions. The preceeding costs, totaling
$14,000,000, increased the total estimate to over $42.5 million dollars.
14
When the appropriations were made for the $14,000,000 in increases, it was believed that the
new funds would be sufficient to complete the project; this proved not to be the case. The
Commission was before the legislatures again, in February of 1926, seeking an additional
$3,200,000 (22). The commission explained that the newfound costs were due to heavy
increases in labor and material costs and to a tube diameter increase. These new costs were
incurred in the same period that Holland died of heart failure. Holland’s assistant, Milton H.
Freeman, took over as chief engineer only to die of pneumonia four months later. Ole Singstad,
the designer of the ventilation system became chief engineer after Freeman’s death and oversaw
the project until completion. In addition to the disorder created by having three different chief
engineers within five months, other factors could have contributed to the increases in expected
costs cited in February of 1926. In April of 1924, three months after the $14 million increase,
water rushed into one of the tunnels from a leak, forcing workers to make a hasty escape. Not
long after this incident there was a workers strike, which delayed the project and increased costs.
There was also growing concern about mounding of the river bottom as a result of tunneling
activities. The mounding was a hazard for large ocean-going vessels that frequented the harbor.
After the completion of the project the mounding would need to be dredged at an added cost. In
the meantime these large vessels had to be guided carefully through a narrow channel by the
revenue cutter service of the US Coast Guard, also at an added cost. Although costs continued to
grow toward the middle of 1926, the Holland Tunnel was nearing completion.
It was not until the end of 1926 that the final cost of the tunnel would be realized. By the time
the tunnel was nearly completed the $3,200,000 requested in February of 1926 had grown to a
total of $5,741,000 above the 1924 estimate (23). A final appropriation was requested in early
1927 bringing the total cost to $48,400,000. When the engineers were asked to explain these
new costs, they explained that the increases were due solely to the higher costs of labor and
materials. The upward adjustment of the estimate in mid-1926 would prove to be the final cost
increase. On November 13th of 1927 the tunnel officially opened (24).
15
Causes of Holland Tunnel cost increases
1. Scope changes:
¢ From a single 24½ ft wide to a 29 ft diameter
¢ Larger entrance/exit plazas
¢ Tile lining to optimize lighting
¢ Approach roads
¢ Architectural treatment of approaches
¢ Further diameter increases to accommodate ventilation ducts
2. Inflation/escalation over the nine years between initial design and completion of
construction:
¢ Labor costs
¢ Material costs
¢ Labor strikes
3. New Technology:
¢ Lack of knowledge about ventilation systems for the exhaust gases produced by vehicles
with internal combustion engines
4. Technical challenges:
¢ Tunneling methods/risk
¢ Unknown soil conditions – redesign of New Jersey ventilation shaft foundation
¢ Major leak into the tunnel in 1924
¢ Mounding of the river bottom
5. Continuity of senior management:
¢ Goethals
¢ Holland
¢ Freeman
¢ Singstad
What lessons in design and construction can be taken away from the Holland Tunnel project?
The original cost estimate in early 1919 of $12 million dollars grew to $48.4 million when the
final cost was reported. The final cost of $48.4 million was for fully operational twin cast-steel
16
tube tunnels. The work was built by conventional methods, but on a scale never before
attempted. Goethals’ original estimate was significantly beneath what was actually needed for a
project of this nature. Holland’s design was not complete when the first estimate was reported.
Further knowledge about ventilation systems caused additional cost to be incurred because of
necessary design changes. If these tests had been completed before the project design was
produced the estimate would have accurately reflected the necessary construction operations.
Improved forecasting of future traffic would have allowed a more accurate approximation of the
costs for entrance and exit plazas to be included in the initial estimate. It should have been
anticipated that a tunnel of such scale would encounter unexpected circumstances creating the
need for larger contingencies to mitigate the costs of construction problems. These
contingencies could have been used to cover the costs of labor strikes, increases in wages, and in
the prices of material. As with many mega projects the tunnel was a tremendous engineering
achievement that has contributed significantly to New York City’s transportation system even
though it cost four times the amount calculated in the first estimate. The challenges, faced by
Holland in designing and building the tunnel, are similar to those found in every mega project
undertaken today.
SOURCES OF INFORMATION
In order to determine the current state of estimating practice within state DOTs, all fifty DOTs
were contacted and interviewed. Points of contact were generated using an AASHTO committee
member list and by researching state DOT web sites. Once appropriate contacts were identified
they were electronically forwarded an advance copy of the survey and an interview was
scheduled.
The original survey generated by the research team was tested with the Arizona DOT
(ADOT). After discussions with ADOT the initial survey was refined and distributed to the
other 49 states (Appendix A). Most states were interviewed over the phone, however members
of the research team did visit some states at which time interviews were conducted with multiple
personnel. Conducting the interviews either over the phone or in person enabled the team to
expand on comments and ask further questions for clarification. The interviews were used to
collect data in four areas:
17
1. Document estimating practices of state DOTs
2. Ascertain methods for the resolution of discrepancies between DOT estimates and bid
prices
3. Identify problems that remain largely unresolved across the country
4. Determine practices that produce estimates within a + 5% variability between the DOT
estimate and contractor bid.
Data Analysis
While data was requested from all fifty states on projects having engineer estimates of over $10
million, it was determined that to make the data more useful to the reader, project ranges would
have to be established, and some differentiation between DOTs would be required. After
discussions with ADOT, project value ranges were set to give a better idea of how DOTs are
doing business while at the same time capturing useful data from all of the state DOTs. The
number of projects used to determine program size was decided after the data was received from
the DOTs. The data was sorted based on total projects reported with program size breaks based
on clear gaps in the reported project numbers. Additionally, an effort was made to maintain a
sufficient number of DOTs in each category so as to support the validity of conclusions. The
response to the surveys provided practical information concerning specific experiences and
strategies.
19
CHAPTER TWO
LITERATURE REVIEW
Over the last thirty years numerous books were published on the subject of construction
estimating. However, almost all of those books are directed to the building and homebuilding
segments of the construction industry. In the literature there can also be found various articles
on specific construction estimating issues.
BOOKS
The procedures for producing heavy construction estimates are the subject of a very limited
number of books (25 & 26). There are also a few general construction books that devote a
chapter or two to heavy estimating (10). Those books present the beginner with a general
understanding of where to commence with a set of plans in determining the amount of work to
be done and how to apply appropriate cost factors to that work in order to produce an estimate.
Parker (25) and Bartholomew (26) focus on heavy construction projects and the unique
challenges associated with these projects that would not be encountered in smaller scale
operations of the same type.
A list of the steps for estimating a heavy construction project is included in each book along
with some of the special conditions an estimator must consider while preparing an estimate for
heavy/civil projects. These books are written as primers to teach students the mechanics of
project estimating. They do not address the issue of estimating accuracy; they simply lay the
foundation for preparing an estimate. They do provide the base knowledge of where to look for
information and how to assemble it into a useful estimate format.
The Parker book, which was written jointly by Albert D. Parker, Donald S. Barrie and Robert
M. Snyder, primarily addresses estimating for dams, and tunnels. All three of the authors were
practicing construction engineers who had years of contractor experience when the book was
published in 1984. Although Bartholomew’s book was published more recently, it is based on
information from sources, like Parker’s book, that were originally published between ten and
thirty years ago. The Bartholomew book deals with assembling the estimate, quantity takeoff,
pricing labor, indirect costs, and the costs for typical excavation and mass concrete work.
20
There are other books (27, 28, & 29) available that address some of the issues of heavy
construction estimating such as selection of equipment, methods analysis, and calculating crew
productivity. None of these or the aforementioned books specifically address the situations
encountered in constructing a mega transportation project.
TECHNICAL ARTICLES
The problem of estimate accuracy affects all areas of construction and has been studied
repeatedly. Investigations of this sort can be divided into two broad categories of study:
¢ Policies and Procedures of Estimating Entities
¢ Technology for Estimating
The majority of the studies have investigated only a single estimating entity, such as one
highway department; particular estimating procedures; factors that impact project cost; or
technology for estimating. The studies include not only highway and infrastructure projects, but
also building and industrial construction.
Policies and Procedures of Estimating Entities
The process of estimating a construction project begins with the identification of a need and
development of a conceptual estimate, and progresses with the systematic design of the project
from concept to construction documents and development of the final engineer’s estimate. In
order to maintain both the scope and budget of the project it is necessary to manage the design to
insure that all decisions will produce the best value possible for the owner.
Young (30) suggests implementing a “Design to Cost” strategy. This idea involves constantly
managing the design to insure that the construction documents reflect a design that can be
constructed for the budgeted amount. Although this sounds like a simple concept, it often
happens that a design team will have a set of job requirements and a target cost, but then spends
its time and effort in meeting all of the design requirements while ignoring the escalating costs of
the proposed design. The easiest way to control changes to scope, and their tendency toward
cost increases, is through open and honest communication between the designer and owner. This
21
process insures that the owner is aware of any cost increase, beyond the original budget, and the
designer is producing a design that meets the owner’s prescribed needs.
Once design is complete the owner or designer must once again go through the project
carefully to produce the pre-bid or engineer’s estimate based upon the final plans and
specifications. This estimate can be produced by a quick check of the cost drivers that were
tracked throughout the design. However, if the project scope has changed and the resulting costs
were not previously identified, the estimate produced at this point can result in a tremendous
shock when the project cost is finally revealed. If the pre-bid engineer’s estimate is significantly
above the amount of funds budgeted for the project the owner must do one of three things:
¢ Make more funding available.
¢ Direct the designer to make design changes that reduce cost.
¢ Reduce the scope of the project to meet the budget constraints.
In order to increase the accuracy of estimates, De La Garza (31) suggests that the personnel
performing the estimate possess both a strong knowledge of costs as well as implicit design
knowledge. The design knowledge helps to insure all characteristics of a particular building
system are included in the estimate. Without the appropriate design knowledge it is possible that
an estimator may not understand that systems each have their own respective costs and a
particular system can make a significant bottom line difference.
Building construction estimates are commonly created using standardized formats for
delineating individual work items. The most widely used building work classification system is
the Construction Specifications Institute (CSI) Master Format. The sixteen categories (divisions)
of the Master Format allow for easy organization of all aspects of the contract and estimate (32).
By using a cost estimating methodology that follows this format the estimator can easily produce
a detailed accounting to determine exactly what was and was not included in the estimate, as
well as easily cross reference the contract specifications that determine what type and quality of
materials are required for each element in the structure. An additional benefit of using this
method is that contractors can use the same system to produce their estimate, and after bid
opening the owner can directly compare contractor bids to the pre-bid estimate, providing an
easy way to evaluate estimating practices and make changes as necessary.
22
The American Association of State Highway and Transportation Officials (33) has developed
a similar format for use in highway construction. This guide has eight divisions that cover all
aspects of highway construction, while eliminating or consolidating the other CSI categories that
are seldom used for highway work. The AASHTO format is used throughout the United States
as an outline for specification writing and payment monitoring by DOTs. State DOTs either use
the standard numbers supplied by AASHTO or modify them to suit their individual needs.
The methods discussed thus far pertain mainly to owners and designers, the responsible
parties up to the point where bids are solicited. Prior to bidding the project, contractors collect
the bid documents, arrange site visits, and estimate the cost plus mark-up required to complete
the project as designed. A contractor’s estimate is based on completing the work and making a
profit. There are several pitfalls that the contractor can experience during the estimating process
that can lead to financial hardship later if the contractor successfully bids a job on an incomplete
estimate (34). These include: 1) underestimating the time duration of construction, 2) a quantity
takeoff mistake, and/or 3) selecting a construction method that is not allowed by specification.
Even if the material quantities are correct, an underestimate of time (productivity) will lead to
large labor cost overruns, as well as increased overhead to run the project for an extended period
of time. To prevent this from happening the contractor’s estimator must take into account
regional differences in labor productivity and availability that may differ from normally
anticipated production.
Several studies have looked at methods for producing bid estimates. Stern (35) proposes a
methodology based on current market information while downplaying the role of historical data.
He suggests that market influences can alter prices and productivities enough to break an
estimate that is based solely on historical figures that may not reflect current conditions. Shash
and Al-Khaldi (36) agree with this theory, but they also advocate including an evaluation of the
economy as a whole, as a part of the estimate. This allows for adjustments to prices and
predictions as to where overall costs are likely to be throughout the duration of the project.
Market conditions can greatly impact the bids submitted to an owner. Pearl (37) found that
when the market is in decline, contractors would undercut their profit in order to become the low
bidder and secure as much work as possible. As a result, owner estimates done prior to bid in a
23
declining market will have a tendency to be higher than bid prices, while those done during
periods of growth have a greater likelihood of being low. In a growth market contractors
generally have a larger backlog of work available and are, therefore, able to apply their usual
mark-ups to their costs. Thus, owner estimators must increase their estimates during growth
markets, which can widen the gap between an owner’s estimate and the bid amount the next time
the market turns down.
Other market conditions that can effect estimates and bids are: 1) the availability of labor, 2)
location of the project, 3) equipment that requires specially certified sub-contractors to install,
and 4) the overall condition of the economy, such as changes in interest rates that can change the
amount of capitol required to fund a long term project (36).
Technology in Estimating
Since the advent of personal computers and their proliferation into the business environment,
estimators have developed new and innovative techniques to produce estimates faster and better.
Creating a computer program that can simplify the work of estimators requires a substantial
commitment of personnel and resources. This commitment, or investment, can quickly return
large dividends.
Hicks (38) outlines the specifications that an estimating program should adhere to in order to
produce viable estimates. These include: 1) clear definitions of all terms and actions, 2) ease of
use, and 3) some method for tracking each and every part of the estimate, as well as option lists
for each portion of the estimate, such as altering pavement type or thickness. Although there are
many estimating programs currently available from commercial sources Hicks found that no
single program has demonstrated that it is far superior to the others.
Regression Analysis
The Alabama Highway Department (AHD) developed and tested a conceptual estimating
program based on regression analysis. To populate the program model, bid data from a variety
of bridge widening projects were examined and individual line items were compared to
determine average prices that would be used in future estimates. These figures were then
tabulated and used to create the model. This model produced estimates consistently within +
24
20% of the low bid amount, which was the requirement set forth by AHD in creating the
program (39 & 40). This model has limited applicability, as it only addressed estimating bridge
widening projects. However, the methods used to create the model can be applied to other types
of work to create similar models.
Neural Networks
Artificial neural networks have the capacity to perform a large number of calculations and make
decisions with a minimal amount of user input. The estimating neural network is initially
developed by loading historical data, or in the case of highway estimating, line items, into the
network and allowing the network to learn cost relationships. Al-Tabtabai and Tantash (41)
developed such a network for preliminary highway construction estimation. Their network was
able to produce estimates accurate to within + 9% of estimates created by a panel of industry
experts. Use of such a program to perform detailed estimation would require much larger data
sets and longer training periods than were used in their study. However, once completed the
network would be able to produce estimates far more quickly than humans.
Monte Carlo Simulation
In order to address the variability involved with cost estimates Touran (42) developed a
probabilistic cost estimating system. By using Monte Carlo Simulation applied to RSMeans data
for low-rise buildings, he was able to develop an accurate model for predicting the cost of line
items that generally exhibit the greatest amount of variability. His model generated correlated
random numbers from the data, and then applied those numbers to user-defined quantities in
order to develop an estimate.
All of these methods use the power of computers to produce estimates faster, cheaper, and
better than previously thought possible. Technology will definitely play a large role in the future
of highway estimating, but a significant investment will be required to realize the full potential of
computerized estimating systems.
Conclusion
While all of these studies examined estimating and many have made recommendations for
improving the practice, none has made a comprehensive comparison of methods currently in use
25
or the difficulties faced in estimating mega projects. Other articles have made recommendations
for improving performance on individual tasks that are a part of the estimating process, but very
few researchers have actually tested their hypotheses, and therefore they do not have any
empirical data for comparison to other methods for completing the same estimating tasks. While
the experience base for construction cost estimating, both in industry and in government, is quite
large there is comparatively little published on the subject as compared to other areas of
engineering and construction practice. The competitive nature of the low-bid construction
market discourages the free and open exchange of ideas on estimating, as each and every
contractor closely guards any information that provides a competitive advantage when bidding.
As a result, researchers have little support from industry for research that will help other
contractors, even if the research also benefits the company that provides funding.
27
CHAPTER THREE
HOW STATE DOTS ESTIMATE
Throughout a project’s development estimates are completed to ensure that sufficient funds have
been allocated to complete the proposed work. This study is primarily concerned with pre-bid
estimates or what is often termed the engineer’s estimate; however, conceptual estimating
procedures were also examined to determine the extent of estimating procedure standardization
within DOTs. The chronological development of a project estimate begins with the conceptual
estimate and evolves through project development until the final pre-bid estimate is produced.
CONCEPTUAL ESTIMATES
Depending on the policies of the individual DOT conceptual estimates are prepared by project
developers, designers, or estimators. To create a conceptual estimate, 31 DOTs use estimating
cost data that are based solely upon historic lane-mile cost averages for similar projects or for
bridges/structures, they use historical square-foot or square-meter cost data. Eighteen other
states go into greater detail and determine quantities based on the conceptual design and follow
the same procedures that are used for pre-bid estimates, which could be either historic average
unit price estimating or, as is the case in three states, they prepare detailed estimates based on
preliminary design information. One state reported allowing engineers to use whatever method
they thought best to generate conceptual estimates.
While Caltrans uses information derived from old bid numbers to develop average prices for
use in creating conceptual estimates more than simple averages are compiled. The Division of
Structure Design Services & Earthquake Engineering provides cost range analyses of bid data for
use in developing preliminary estimates. Such an analysis of bridge costs is shown in Figure 4.
Note in the Figure 4 that the text clearly states that: “These costs should be used just for
preliminary estimates… .” The Connecticut DOT also analyzes bid data in detail and produces
pricing information for preliminary estimates that can be structured for expected project
conditions, Figure 5.
28
FIGURE 4 Caltrans Comparative Bridge Costs for Preliminary Estimates.
29
FIGURE 5 Connecticut Preliminary Cost Estimating Guidelines.
30
The Connecticut DOT had been having problems with inaccurate construction cost estimates
so in 2002 the Department undertook a review of its preconstruction estimating procedures and
methodology (43). This review was a joint effort of the Department and the FHWA Connecticut
Division office. In the case of preliminary cost estimates the committee issued the following
recommendations.
1. All estimates should be written.
2. All estimates should be based on the “ConnDOT Preliminary Cost Estimating
Guidelines” or actual quantity take-offs.
3. Prime designers should obtain written estimates from all support units: Traffic
Engineering, Environmental Compliance, Bridge Design, etc.
4. Rights-of-way cost estimates should be prepared in consultation with the Office of Rights
of Way. “Place holder” estimates should not be used.
5. At the Project Initiation, the prime designer should confirm that the estimate is consistent
with the project scope. A site visit should be considered an essential part of this effort.
6. Estimates should be updated at each major design milestone: Preliminary Design, Semi-
Final Design, Final Design.
7. The Semi-Final design estimate should be based on actual quantity take-offs.
Preliminary estimating techniques would not be applicable.
8. The “Preliminary Estimating Guidelines” should be updated to include factors for
inflation, unassigned quantities, etc.
9. The “Preliminary Estimating Guidelines” should be updated annually.
10. Project estimates should be updated semi-annually, unless a major milestone has occurred
in the interim, using the techniques appropriate for the given design stage.
These recommendations address preliminary estimates at all stages in the project development
process but several points are particularly applicable to conceptual estimates. Points three and
four concerning interaction with support units are very important. Special emphasis was also
31
placed on point five. This was because a lack of site familiarity by the design team was
identified as a factor that often caused estimating problems. The committee’s report stated:
It is extremely important for all members of the design team to become familiar with the
project site. A formal or “Plans-in-Hand” site review will help refine the project scope early in
the design process and bring forward method and constructability issues often overlooked during
a paper plan review.
The intent of the Plans-in-Hand Review is to determine if other alternative approaches could be used during the design phase to eliminate future costly construction changes, and to analyze these various alternative construction procedures for methods of construction, time saved to complete the work, better customer satisfaction, cost savings, and ease of maintenance after construction (43).
In order to accommodate minor scope changes and account for engineering costs early in the
project, most DOTs add a contingency amount to the conceptual estimate. This is usually a
percentage of the total project cost. The reported range for contingency was 5 - 45% depending
on the type of project and amount of uncertainty prior to design. Overlay projects would
generally be at the low end of the contingency scale, while tunneling would be towards the top
due to the possible variation between subsurface conditions predicted by the geotechnical
investigation and those actually encountered. Table 1 shows the number of DOTs that reported
using set percentages for all projects, as well as how many use a graduated scale (Table 2) based
on estimated project cost, and how many require estimators to perform a cursory analysis of the
risk and unknowns for the project and apply an appropriate percentage to address these
uncertainties.
TABLE 1 ENGINEERING AND CONTINGENCY COSTS APPLIED TO CONCEPTUAL ESTIMATES
Conceptual Contingency
DOTs Practicing
Set Percentage 20
Graduated Scale 15
Engineering Judgment 15
32
TABLE 2 ONE DOT’S GRADUATED CONTINGENCY SCALE
Project Value Conceptual Contingency
$0 - $1,000,000 11.0%
$1,000,000 - $5,000,000 9.5%
$5,000,000 - $25,000,000 7.0%
$25,000,000 + 6.0%
Life cycle
Life cycle cost is an important consideration in project development and if considered at all, it is
generally considered at the conceptual design phase. DOTs reported that life cycle cost analysis
was done in the conceptual stage to determine the materials to be used in the project, as well as
to perform initial value engineering studies. Twenty-seven DOTs consider only pavement type
during life cycle cost analysis and make a decision based upon their previous experience with
facilities in the same general area and construction funds availability. Nine other DOTs reported
they were unaware of any life cycle cost analysis being made during project development.
CRITICAL ISSUE REVIEW MEETINGS
These meetings are intended to focus extra attention on specific projects that are larger or more
complex than those normally undertaken by the DOT. Personnel from all major areas of the
DOT, such as planning, design, construction, traffic, and maintenance, are invited so as to gain
the benefit of having multiple perspectives examine the proposed project. These meetings are
normally held before the project is passed from planning to design. By bringing all of these
perspectives together early the designers are able to reduce conflicts and value engineer the
project upfront, instead of completing a substantial portion of the design before asking anyone to
review the design plan. This process can save time and money as well as provide the public with
a more useful facility. Eight DOTs that have these meetings require them for projects valued
over $25, $30, or $60 million. One of those DOTs also uses this type of meeting for all Design-
Build projects. Two DOTs hold these meetings for projects with extensive urban traffic control
33
requirements, and one DOT uses these meetings to address special environmental, social, or right
of way issues that exist.
DESIGN PHASE COST CONTROL
During the design phase of a project it can be useful to track the programmed (or budgeted) cost
of the project against the anticipated construction cost of the final design. This enables DOTs to
better manage their construction programs by giving supervisors and directors an accurate
overview of the costs associated with projects under design. As design progresses it may
become clear that insufficient funds have been allocated based upon an unknown site condition,
a change in project scope, or changes in the construction market. When this is discovered it must
be reported to managers and either a cost increase approved or design changes made to bring the
cost in line with the budget.
In nine DOTs, approval authority for small cost/scope changes is delegated to the district
engineer responsible for the project. In those same nine states it is required that the Director or
the budget committee approve large cost/scope changes. These reviews encourage designers to
find ways to stay within the project budget, and when that is not possible ensures that the
changes are necessary and make sense within the DOT’s overall construction program.
PRE-BID ESTIMATES
There are basically three approaches to estimating (44). The use of historical data from recently
awarded contracts is the most common approach. Under this approach, bid data are summarized
and adjusted for project conditions (i.e., project location, size, quantities, etc.) and the general
market conditions. This approach requires the least amount of time and personnel to develop and
produces a good estimate, as long as noncompetitive bid prices are excluded from the database
and then appropriately adjusted current data is used to build the estimate. However, this method
is the most susceptible to outside factors such as inflated bid prices from contracts with little or
no competition (44).
The detailed estimate approach based on specific crews, equipment, production rates, and
material costs. This is similar to the way a construction contractor would estimate a project.
This approach requires the estimator to have a good working knowledge of construction methods
34
and equipment. While adjustments for current market conditions may be required, this approach
typically produces an accurate estimate and is useful in estimating unique items of work where
there is insufficient bid history.
The third approach combines the use of historical bid data with actual cost development.
Most projects contain a small number of items that together comprise a significant portion of the
total cost. These major contract items may include Portland cement concrete pavement,
structural concrete, structural steel, asphalt concrete pavement, embankment, or other specialty
items. Prices for these items are estimated using the detailed approach and adjusted for specific
project conditions. The remaining items are estimated based on historical prices and adjusted as
appropriate for the specific project.
It was found that most DOTs that perform detailed estimates do so only for major items of
work. Major items are defined as those work items that account for 65 - 80% of a project’s cost.
The remaining work items are estimated using historic bid averages. States using historic bid
price estimating systems reported applying these cost factors to all work items in a project to
develop the estimate.
DETAILED ESTIMATING
Detailed estimating requires a great deal of knowledge about construction methods, supply
systems, labor markets, and method productivity specific to the area where the work is being
performed. It also requires more time to prepare a detailed estimate than that which is needed for
estimating methods that simply apply bid averages to work items. This is because the estimator
must conceptualize the construction process in order to prepare an accurate estimate. Nineteen
states perform detailed estimates for major work items, using historic databases to track costs
based on crews, equipment, and production, as well as to provide work item costs for minor
items in the estimate. Most state DOTs that do this kind of estimating have dedicated estimating
sections whose personnel have the necessary construction experience.
DOTs that do perform detailed estimates typically use computer software that supports
estimate development, but the software is not critical to the estimating process itself. The
software may be used to track cost trends or simply allow the estimator to report the estimate to
35
other sections of the DOT more efficiently. The basic information that is necessary to perform a
detailed estimate such as crew sizes, equipment types, production rates, and labor and material
costs can be derived from a variety of resources. It is important that the estimator be familiar
with available resources, how to find the resources, and most importantly has a competent
knowledge of construction processes. All of these elements are necessary in order to develop an
accurate cost estimate.
HISTORIC BID PRICE ESTIMATING
Creating cost estimates from historic bid prices is a relatively straightforward and quick process.
After determining the quantities from the project plans, the estimators simply matches those
quantities to the appropriate historical unit-bid prices or average historic unit-bid prices. To
generate unit price data departments systematically compile bid data from past project lettings.
This data is broken down by bid line item. Average prices can also be calculated for the
estimator’s use. DOTs reported several different methods for sorting the data collected from bid
documents.
The first decision is how many bids from each project should be included in the data. There is
significant variance as to how DOTs approach this issue. All 50 DOTs responded to this
question as even those DOTs that use a detailed estimating procedure track historical bid average
costs for minor work items.
¢ Low bid only - 20 DOTs
¢ Low and second bid - 1 DOT
¢ Three lowest bids - 15 DOTs
¢ All bids (but may exclude single bids that are very high or low) - 11 DOTs
¢ All bids except high and low - 2 DOTs
¢ Bid analysis to determine a reasonable bid amount for each line item - 1 DOT
Table 3 summarizes the estimating performance for each of the above practices and includes
data from both historic bid price estimating DOTs and detailed estimating states that track costs
for minor work items. The two DOTs that use all bids except high and low, and the one using a
36
reasonable price reported the best performance. However, there was insufficient data to compare
these two systems on a larger scale to other systems. The one DOT that used reasonable price to
create it’s estimates did not have any experience using the approach for projects valued at greater
than $100 million. The one state that uses the low and second low bids prices to create the
database does not provoke as much interest as the results are the worse of any DOT using
historic bid price estimating.
TABLE 3 NUMBER OF BIDS USED FOR HISTORIC BID PRICE ESTIMATING
Number of bids used Number of DOTs
Reported Projects
Number reported more than 5% over Estimate %
Low only 20 755 169 22.4
Low and Second 1 24 13 54.2
Three Lowest 15 497 88 17.7
All 11 260 74 28.5
All Except High and Low 2 64 3 4.7
Reasonable Price 1 24 1 4.2
A closer examination of the two DOTs using all bid prices except high and low to create the
estimating database did reveal that one DOT had very limited experience with the approach and
a very bad record. Specifically, only five projects had been estimated with the database and the
estimates for three of those five had a variance from the contractor bid price of more than five
percent. The other DOT which has a dedicated estimating section staffed with personnel having
on average 18 years of experience had extremely good results. That DOT’s except high and low
bid price database had been used, in the last five years, to estimate over 50 projects that had
initial contract prices of from $10 to $100 million. Additionally the database had been used to
estimate five projects that had initial contract prices greater than $200 million. In all cases the
estimate was within five percent of the low bid price for the work.
Of the remaining practices, using the three low bids for each item was found to produce the
best results, while using all bids produces the worst. This is most likely due to the fact that if a
37
single bidder uses greatly unbalanced prices it can skew up or down the individual item averages
in the database.
After it is decided which bid prices will be used to create the average price, a timetable must
be established that specifies the frequency of data updates. Databases can be refreshed and
updated after each letting, or on an annual or on some other recurring basis.
In addition to these two factors, how many bids to use and how often to make system updates,
the department must decide for what period of time data will be retained in the database and how
far back price data should be considered to determine average prices used in estimates. Typical
look back periods are 1 year, 18 months, or two years for use in averages. Nine DOTs retain
data for as long as records exist. Estimators can examine and use this data for items that are not
frequently encountered or items that have seasonal price swings. An averaging of data would
obscure seasonal pricing.
Estimators should know exactly how the prices they are using were created, as there are
multiple mathematical methods to arrive at an index value. Three common methods of deriving
an index value are
Index value (average) = n
Cn
1ii∑
=
Index value (inverse) =
∑=
n
1i iC1
n
Index value (root of the product) = ( ) n1
n321 C...CCC ××××
where
C = the individual costs elements
n = the numbers of cost elements
Such information should be part of the DOT’s estimating manual, Figure 6. Connecticut has
several different sets of bid data information that the estimator can use as the situation dictates.
38
A three low bid printout is created for each project bid. At the end of each calendar year average
prices are computed and every two years weighted unit prices are prepared.
FIGURE 6 Connecticut Price Cost Data Guidance.
COMPUTER USE
Computer software gives DOTs the ability to manage large data sets that cover all project types.
The most widely used DOT estimating software is Estimator™ by InfoTech. Estimator is a
module of TRNS*PORT. TRNS*PORT is owned by Info Tech, Inc. and fully licensed by
39
AASHTO under the name. Using this software DOTs can prepare parametric or item level
project cost estimates. Parametric estimates are based on project work types and their major cost
drivers. Item level estimates are derived from bid histories and cost-based estimating techniques.
Cost-based estimates use material, equipment and labor costs.
The TRNS*PORT Estimator module is used (8/7/02) by 22 DOTs. Historic bid price
databases can be created using the BAMS/DDS module of TRNS*PORT. BAMS/DDS is the
Decision Support System module of the construction contract information historical database.
Another commercially available system that is used by several DOTs is “Bid Tabs” by OMAN
systems. It is used either as a stand-alone or in conjunction with “TRNS*PORT” by seven
DOTs. Two other DOTs are in the process of testing this software. One DOT uses HCSS Heavy
Bid, which is a program, used by many contractors and was originally developed to facilitate
detailed estimating by a large contracting organization. One DOT uses AutoCAD to perform
quantity takeoff for project estimates, by combining plan views of the project area with elevation
information to get a three dimensional view of the project.
Eighteen DOTs are using programs that were developed within the DOT. These are not
commercially available and are used either as stand-alone systems or in conjunction with other
software. These programs generally have limited capabilities and were designed to run on
mainframe computer systems. Legacy programs like these are difficult to update or modify.
PERSONNEL
Estimating experience of DOT personnel charged with developing estimates ranged from less
than one year to more than 40 years across the fifty DOTs. Several DOTs that reported having
estimators with minimal experience stated that they had in recent years lost their most
experienced personnel to retirement and they had not retained mid-level personnel to ensure that
the overall experience level in estimating would remain high. Similarly, DOTs with high levels
of experience among estimating personnel acknowledged that they might have difficulty
replacing their highly experienced personnel with sufficiently skilled personnel when their
current estimators retire. A few states have recognized the benefit of having personnel at all
stages of professional development in their department and have recruited in such a way as to
ensure continuity as members retire over the next ten to twenty years.
40
Estimators come from many different specialties within the DOT including engineering,
construction, contracting, and occasionally from the operations and maintenance areas. In
twenty-six DOTs, estimating personnel are consolidated in a dedicated estimating section where
their primary responsibility is the production of estimates. In the other twenty-four DOTs
personnel prepare estimates as an ancillary duty while their primary responsibilities are likely to
be either design or contract preparation.
Design consultants are used by all DOTs to produce project documents. This situation is
caused either by a lack of DOT manpower or a need for specialized design knowledge. When
consultants are used to prepare project documents they are usually required to submit a project
estimate to the DOT for use in contract preparation. In sixteen states this estimate is then
reviewed by the DOT project manager who makes required changes before the official estimate
for bid evaluation purposes is created. In another twenty-six states, this estimate is not used
except to cross check the DOT estimate after the DOT estimate has been prepared. The
remaining eight states reported using consultant estimates without modification or substantial
checking.
Training
To ensure all estimators have current estimating knowledge, a training program is vital. This can
be either a formal set of classes for all estimators, mentoring among the estimators in the section,
or support for estimators to attend off-site conferences, seminars, or classes pertinent to their
work. Ten DOTs reported having formal estimator training programs in place or under
development. Mentoring and on the job training (OJT) are used extensively by all DOTs.
Additionally most DOTs reported that the personnel preparing estimates have had experience
either in design or construction prior to becoming estimators, and it is assumed that their
personnel will have gained the necessary estimating knowledge and understanding either in
school or in previous jobs. This previous experience, gained either from school or on the job
imparts a better understanding of the construction process, and helps the estimator develop
accurate estimates.
Whichever system is used, it is necessary for the personnel preparing estimates to understand
how and why the system works. This is done either by having an estimating manual, or through
41
OJT and familiarization with office policy. Currently sixteen DOTs have manuals, either a
separate estimating manual or a section within a design or other manual, that cover estimate
preparation. Two other DOTs are in the process of developing estimating manuals. The
remaining 32 DOTs do not have formal written guidance for estimate preparation that can be
referenced by the estimator. If the experience level of personnel preparing estimates is not
sufficient it will take extra OJT to bring them up to the appropriate level of understanding.
Without a manual of practice or formal training program it is difficult for any DOT to produce
consistent, accurate estimates, unless they are able to attract and retain personnel who have been
trained elsewhere.
TIME FRAMES
The time from completion of the DOT estimate to contract advertisement ranges from two days
to three months. The majority of DOTs have a six to eight week range to allow sufficient time
for internal estimate review. The reported DOT practice for completion of the final estimate is
tabulated in Table 4.
TABLE 4 TIME FROM COMPLETION OF ESTIMATE TO ADVERTISEMENT
DOTs Practicing Time Frame prior to
Advertisement Detailed Estimating
Historic Bid Average Total
Within one week 2 3 5 One week to one month 6 5 11
One to two months 9 15 24 Two to three months 1 4 5 Three to five months 0 3 3 More than six months 1 1 2
Total 19 31 50
Advertisement periods range from 10 days to three months depending on project complexity
and whether the project is being undertaken for emergency work. Thirty DOTs have three to
four week advertisement periods with provisions for longer periods at the discretion of the
contracting section. Five states were found to have three or four week firm advertisement
42
periods that are not exceeded for any project. This policy is based on the idea that if a contractor
cannot prepare a bid in the required time, chances are they do not have sufficient capacity to
complete the project.
ESTIMATE ITEMS
Overhead
Project overhead is estimated almost exclusively by assuming that historic bid prices include the
necessary mark up for overhead and profit. In DOTs that perform detailed estimates, unit prices
are adjusted to account for overhead. Ten DOTs reported estimating overhead and profit directly
based on individual line items, enabling them to more accurately account for special project
requirements that vary from job to job.
Contractor Mobilization
Twenty DOTs limit the mobilization pay item to a predetermined percentage of the contract
amount. In these states the percentage varied from a low of 3% in two DOTs to a high of 12% in
one DOT. In twenty-six other DOTs, mobilization cost is determined based on historic average
percentages after analyzing the project location, type of work, and schedule limitations. Other
methods used for estimating mobilization are a sliding percentage scale based upon project dollar
value where a set percentage is used for projects in different cost ranges, or a graduated amount
that adjusts as project value increases up to a maximum amount (Table 5). Graduated or sliding
percentage scales are used in four states.
Demolition Work
DOTs estimate demolition work either as an individual line item, or assume it will be included in
other pay items depending upon the specific type of demolition work. Ten DOTs prefer to have
a separate contract for major demolition work prior to the construction contract. The decision to
perform demolition under a separate contract is usually made based upon schedule constraints
for the alignment or right of way, and whether there is sufficient time to perform required
demolition before construction begins in an area.
43
TABLE 5 SAMPLE GRADUATED MOBILIZATION PAY ITEM
Project Value Mobilization
$0 - $500,000 8.0%
$500,000 - $2,500,000 $40,000 + 3% of amount over $500,000
$2,500,000 + $100,000 + 1% of amount over $2,500,000
Traffic Control
Traffic control is a difficult item to estimate, as it requires a great deal of effort to properly
conceptualize how the project work will be sequenced. Ten DOTs reported that they estimate
traffic control cost as a predetermined percentage of the project’s total cost. Several of those
DOTs allowed that the percentage applied was based on the project size and the type of work
involved. In searching the literature the researchers could fine no basis for assuming that there is
a relationship between total project cost and traffic control cost. There was a study in South
Carolina that explored the relationship between traffic control cost and the lane miles of a project
using regression analysis (45). That study reported that in the case of the South Carolina data
there was no correlation strong enough to be useful as a means of cost forecasting. Therefore, it
should be noted that using a percentage of project cost to estimate traffic control cost is not a
good practice.
The other predominant method for estimating traffic control is to analyze the project documents
in detail and calculate total signage, temporary striping, flagging personnel, police, barriers, and
other necessary items, each of which is multiplied by the appropriate number of project days to
complete the work. This method, which is used by thirty DOTs, may or may not include an
additional pay item for maintenance of traffic to cover other minor incidental expenses
associated with traffic control.
The remaining DOTs reported specialized techniques such as using historic bid data from
similar projects, five DOTs, and project schedule, one DOT, or they did not specifically respond.
DOT Supplied Materials
Twenty-three DOTs supply materials for contractor use. The most common material items
supplied are permanent signs, signalization, and light poles. These are usually supplied to reduce
44
the contract time, as these can be extremely long lead-time items for a contractor to procure.
Additionally, a DOT can often save money on these items by purchasing large quantities when
individual projects may only require a few of each. Other items sometimes supplied by DOTs
were aggregate from state owned quarries, excess fill retained from other projects, and reclaimed
asphalt material (RAP) or rubblized pavement from other projects. These are generally supplied
only if readily available and more economical than using contractor furnished material. DOT
owned traffic barriers are made available by some DOTs. When these are provided the
contractor is responsible to pick up and return the barriers to a central storage facility.
Unique and Specialty Items
Most DOTs estimate these items similarly by calling suppliers, contractors, or other DOTs that
are familiar with the work and asking for installed cost information. They then estimate the
expected cost by adjusting the information they receive based on project location and current
market conditions.
In some states talking to contractors about a specific job is prohibited. The concern is that
such conversations would give the contacted contractor an unfair bidding advantage over the
other bidders. Specifically it is though that the contacted contractor would have more time to
research the issue and find alternatives before bidding. Such rules limit the DOT’s ability to
gather information directly from contractors. This may force the estimator to create a detailed
estimate for that single item or rely on information from another agency that may not have the
same contract requirements and may have a lower cost than that DOT will realize at bid time.
OTHER ESTIMATING CONSIDERATIONS
There are several other project considerations that must be taken into account to prepare an
accurate cost estimate for any project. These factors are part of the overall project but are not
always captured by a single item of work, or may be in addition to standard specifications
normally used by DOTs. All of these items can have significant costs associated directly with
them or may significantly alter the costs of other items in the project.
45
Incentives
Incentives are used by many DOTs as a means to encourage contractors to perform above the
minimum contract requirements. Currently the most common type of incentive is for early
project or phase completion. An incentive notice is included in the advertisement and may
compel contractors to bid lower if they feel they can complete the project in less than the allotted
time. Early completion incentive clauses are often accompanied by disincentives for failure to
complete the project on time. A disincentive is more punitive than the liquidated damages that
would normally be assessed by the owner for late completion. Disincentives are structured in
such a way that the contractor would be far worse off to complete the project late than to pay
additional overtime or a premium for material in order to complete the project on time.
Incentives for pavement smoothness are also being used by some DOTs as a way to link
quality directly to profit. This incentive is based on the construction specifications with any
surface that exceeds the specified smoothness resulting in an incentive payment to the contractor.
This can also be coupled with a disincentive to help motivate the contractor to meet
specifications.
Funding of Incentives
The funds that are needed to make incentive payments must come from somewhere in the DOT
budget before they can be paid to a contractor. The following practices were reported by DOTs
using incentives:
¢ Incentive funds programmed in the construction estimate - 26 DOTs
This practice ensures adequate money is available to pay any incentive that is earned.
This is based on the assumption that the contractor intends to earn the incentive. If the
contractor fails to earn the incentive, or is subjected to a disincentive, the money that was
set aside can then be used to fund other projects.
¢ Incentive funds come from other projects that were below budget - 9 DOTs
These DOTs plan on having funds available from projects that under run their allocated
budgets. This can cause problems within the DOT when a contractor earns an incentive
but no other projects under ran sufficiently to provide the extra money. In order to
46
compensate for any resulting funding shortfalls, future projects will have to be reduced in
scope, delayed, or cancelled to provide the necessary incentive monies.
¢ Incentives paid out of project contingency fund- 10 DOTs
These DOTs feel that budgeted contingency funds are sufficient to make incentive
payments and do not budget any other funds solely for that purpose. In order for
incentive payment to be made in these states a change order must be processed and
approved for the incentive amount that was set forth in the original contract.
¢ No incentive program - 5 DOTs
Contingency
Contingency budgeting is done in order to provide funds for minor change orders, without
forcing the DOT to request additional funds or reallocate funds from other projects. A
contingency amount can be planned for and budgeted at project award. The reported range for
contingency set asides was 3 - 19%. These additional funds are reserved within the DOT budget
in a contingency fund to pay for minor project changes that arise during construction. These
changes can result in additional cost to the DOT in payment for contractor work or to others (e.g.
requirement to purchase additional right of way). This amount is not part of the estimate, and is
generally not publicized outside of the DOT. Twenty-three DOTs use some contingency amount
for project budgeting, while the remaining 27 states do not. DOTs that do not budget a
contingency amount propose to complete projects that overrun their budgets by drawing funds
available from other projects.
Schedule
Schedule can effect project cost and force modifications to estimates. This is generally driven by
the owner requiring the project to be delivered very quickly, limiting contractor work times due
to environmental or social goals, or requiring work during unusual times such as at night or only
on weekends. These requirements increase project cost by forcing a contractor to either pay
overtime to regular employees, or pay a premium to pull labor into the project area, or away
from other contractors already in the area. Thirty-three DOTs consider this factor and examine
47
project schedules when preparing estimates to ensure they adjust the estimate appropriately. The
Nebraska Department of Roads, Roadway Design Manual, Chapter Fifteen Cost Estimating,
states:
15.5.8.2 Construction Schedule
The construction schedule may also affect the cost of construction. Complicated work sequences can increase the cost of a project. Economies of scale may reduce the construction cost if projects in close proximity are combined. Wintering a project can also affect the cost.
DOTs that do not analyze the schedule when preparing the estimate, assume that sufficient time
has been allotted for the project based on previous experience in the project area.
Project Conditions
Project conditions such as restricted work areas, geographically separated staging areas, long
haul routes, and site drainage problems as well as any number of other problems that are realized
during design can significantly increase project costs above standard unit prices. When these
factors are considered in advance, appropriate adjustments can be made to the estimate to
eliminate surprises at the project letting. Thirty-eight states attempt to adjust estimate prices
when they believe that there will be unusual project conditions that will cause the contractor to
incur additional costs.
Project Location
Another major consideration for estimating is project location within the state. Thirty-eight
states reported wide variation of bid prices within their states and adjust their prices accordingly
for the geographic location of the project.
Table 6 is a summary of factors DOTs consider when preparing their estimates.
48
TABLE 6 ESTIMATING CONSIDERATIONS
Factor Considered Number of DOTs that Consider
Incentive Funds - Programmed in the construction estimate 26 - Come from other projects that are below budget 9 - Paid out of project contingency fund 10 - No incentives program in place 5
Contingency Budgeting - DOTs with contingency budgets 23 - DOTs without contingency budgets 27
Schedule - Estimate adjusted based on schedule 33 - Estimate not adjusted based on schedule 17
Project Conditions - Estimate adjusted based on special conditions 38 - Estimate not adjusted based on special conditions 12
Project Location - Estimate adjusted based on location within state 38 - Estimate not adjusted based on location within state 12
Project Award
After advertisement each DOT conducts a letting where all bids are received. After the letting,
all bids are compiled and an award decision is made. A decision must be made as to the
maximum difference between the DOT estimate and the low bid that is acceptable in terms of an
award decision. For bids that are below the DOT estimate, regardless of the percent difference,
twenty-six states require no action for award. Twelve DOTs require justification in order to
award the project if it is more than 10 - 30% below the DOT estimate depending on the
individual state’s laws. The most common requirement to justify is a review to determine cause
of difference and to ascertain that there is not a problem with unbalancing.
49
Bids that are above the DOT estimate by 5 - 25%, depending on the individual state’s laws,
must be reviewed and may be rejected or awarded based upon an estimate review and/or a
discussion with the contractor to determine why the difference occurred. Eight DOTs require all
projects be reviewed prior to award regardless of percent difference (Table 7).
TABLE 7 ACTION REQUIRED FOR PROJECT AWARD
Percent difference between DOT estimate and Low Bid
DOTs taking other action if percentage exceeded
No lower limit reported 26 Up to -30 1 Up to -25 2 Up to -20 2 Up to -15 2 Up to -10 5 Up to -5 2
All Projects Reviewed 8
Percentages Unknown/Unreported 2
Up to +5 3 Up to +10 31 Up to +15 2 Up to +20 2 Up to +25 2
The decision to award in some DOTs is left to the discretion of the contracting office, while
most states require approval from a director, senior manager, or award committee before any
project can be awarded, with special attention being paid to projects that are outside of the
acceptable range, either over or under the DOT estimate. Bids are rejected when a project is
outside of the acceptable range and there is no justification that the estimator or project manager
can find for the price difference. The project will then be re-advertised at a later date with or
without changes. If the award committee knows of other factors that are separate from
estimating that require the project be awarded, no matter what the cost, they can decide to award
at the higher price, or enter into negotiations with the low bidder to bring the project to an
acceptable budget amount.
50
Collusion
Collusion detection is the ability of the DOT to identify and track trends in bidding that would be
considered criminal. The 1981 AASHTO Suggested Guidelines for Strengthening Bidding and
Contract Procedures and the 1983 Justice/Transportation interdepartmental guidance,
Suggestions for the Detection and Prevention of Construction Contract Bid Rigging, are key
reference documents for bid rigging detection.
Bid collusion or rigging is a conspiracy to disrupt or circumvent the competitive bidding
environment by establishing a competitive advantage for certain bidders (Table 8).
TABLE 8 COMMON BID COLLUSION ACTIVITIES (46)
Name Description
Complementary Bids A pattern of consistently high bids, or non-response of bidders (e.g., unqualified bidders or incorrectly submitted bids) made to give the "appearance" of competition in order to influence the decision to award the project to a predetermined bidder.
Territorial Allocation A pattern of consistent wins by a bidder within a specific area (e.g., county or multi-county area).
Joint Ventures Submission of a "complementary bid" or other noncompetitive behavior by an eventual partner (i.e., subcontractors, suppliers, etc.) to the successful bidder.
Bid Rotation Coordinated patterns of win and lose bid responses to assure that a predetermined bidder submits the lowest bid.
In seven states little is done to actively detect/deter collusion based upon the idea that the
construction industry is sufficiently competitive, fragmented, and distrustful of one another that
contractors would not be willing to share the information that would be required for bid rigging.
Eleven other DOTs make contractors sign a form that is submitted with the bid. The form is a
certification that there is no collusion and it makes contractors aware of the consequences should
collusion be found. The most common method for performing collusion detection, which is used
by 34 DOTs, is to run a bid history for each project and for each contractor to see if there is a
pattern among winning contractors in a particular area. In DOTs that use TRNS*PORT, eight
51
reported using the BAMS/DSS module to aid in this task. Info Tech reports that 35 agencies
hold licensees for the BAMS/DSS module (8/7/02). BAMS/DSS provides a complete set of
analysis models, and the capability for ad hoc query and analysis. Other DOTs either
do this manually or use their own software.
One other method for collusion detection that was reported is bid analysis by either the state
Attorney General’s office or the DOT Inspector General. With this method estimators are not
involved in or have little knowledge of the exact procedures being used. This is done in seven
states.
Release of Information
The release of state estimate information to the general public and contractors varies from state
to state depending on the Freedom of Information Act (FOIA) provisions under state law.
Twenty DOTs were found to release, during project planning, only an anticipated project cost
range.
Ranging information gives contractors an idea of project size and lets them know which jobs
are within their bonding capacity. This is the only DOT information released in these states.
After an award has been made, the low-bidder or all bidder information, along with the total
project amount, can be found in the bid tabs that twenty-two DOTs post on their web pages
(Appendix B). Ten DOTs go one step further and after all bids have been read release the total
amount of the DOT estimate at the letting. This lets the contractors know right away whether the
job will be awarded immediately or if there will be justification required prior to award.
Nineteen DOTs also release a complete copy of the DOT’s estimate including quantities and
unit prices along with the contractor bid tabs either after the bid opening or following award.
One DOT announces the DOT’s total estimate amount at advertisement. Two DOTs were found
to have such extensive state FOIA requirements that all project documents, including the full
DOT estimate, must be made available to anyone requesting it at any stage of project
development. To help accommodate this one of these DOTs announces the DOT estimate in the
advertisement and contractors may request copies of the entire estimate to consult during their
own estimate preparation.
52
PROJECT DATA
In order to compare the estimating performance of individual DOTs, data was gathered on all
projects bid having a value greater than $10 million over the last five years. Project data was
aggregated into four ranges: between $10 and $25, $25 and $100, $100 and $200, and in excess
of $200 million. Additionally, the number of these projects that exceeded the DOT estimate by
5% or more, at the time of the bid letting, was recorded to help determine the efficacy of DOT
estimating procedures.
It should be understood that comparing a DOT estimate to the low bid is not a measure of the
estimate’s accuracy in relation to absolute value of the work assuming a reasonable profit. The
magnitude of a contractor’s project bid represents the sum of both the contractor’s estimate of
the cost to actually perform the work and the impact of other factors. Two important factors that
impact a contractor’s bid price are:
Perceived risk – contract imposed risk and performance risk
Economic environment – competition (assumed number of bidders), need to employ assets,
and opportunity for future returns.
A DOT pre-bid estimate, the type of estimate reviewed in this section, should be a benchmark of
the fair and reasonable cost of a project. The issue of appropriate action by the DOT if the low
bid is significantly above the DOT estimate is discussed later in the “Project Award” section of
this chapter.
DOTs were separated into three groups for analysis based on the number of projects they
reported in response to the survey. DOTs that reported fewer than 20 projects greater then $10
million were classified as having small programs. Those that reported between 21 and 75
projects greater then $10 million were classified as having medium sized programs and those that
reported more than 75 projects greater then $10 million were classified as having large programs
(Table 9, Figure 7). Four DOTs were unable to provide historical project letting data.
53
TABLE 9 PROJECT ESTIMATE - BID COMPARISON DATA, ALL DOTS
Number % DOT 5 Year Construction Program Size
No. of DOTs
Total No. Reported Projects
No. of DOTs w/ complete
Data
No. Complete Data Proj.
more than 5% over Estimate
Small (< 20 projects) 14 109 13 107 29 27.1
Medium (21-75 projects) 20 893 16 686 138 20.1
Large (76+ projects) 12 1362 9 1021 193 18.9
States not providing data 4 0 0 0 0 0
Overall 50 2364 36 1814 360 19.8
29107
686
1021
193138
0
150
300
450
600
750
900
1050
Small Medium Large DOT 5 Year Construction Program Size
Nu
mb
er o
f P
roje
cts
Complete Data Reported Projects
Number more than 5% over Estimate
FIGURE 7 Project estimate - Bid comparison data, all DOTs
The two estimating methods exhibited about the same level of performance for projects
valued over $10 million. Detailed estimating DOTs reported that 19.6% of their estimates were
exceeded by 5% or more (Table 10, Figure 8) and historic bid price estimating DOTs reported
that 20.1% of their estimates were exceeded by 5% or more (Table 11, Figure 9).
54
TABLE 10 DOTS USING DETAILED ESTIMATING - BID COMPARISON
Number % DOT 5 Year Construction Program Size
Number of DOTs with
complete Data
Reported Projects more than 5% over
Estimate
Small (< 20 projects) 3 31 7 22.6
Medium (21-75 projects) 3 193 34 17.6
Large (76+ projects) 7 648 130 20.1
Overall 13 872 171 19.6
7
648
193
31
130
34
0
100
200
300
400
500
600
700
Small Medium Large
DOT 5 Year Construction Program Size
Nu
mb
er o
f P
roje
cts
Reported Projects
Number reported more than 5% over Estimate
FIGURE 8 DOTs using detailed estimating - bid comparison
55
TABLE 11 DOTS USING HISTORIC BID PRICE ESTIMATING - BID COMPARISON
Number % DOT 5 Year Construction Program
Size
Number of DOTs with complete
Data
Reported Projects more than 5% over Estimate
Small (< 20 projects) 10 76 22 28.9
Medium (21-75 projects) 13 493 104 21.1
Large (76+ projects) 3 373 63 16.9
Overall 26 942 189 20.1
22
76
493
373
63104
0
100
200
300
400
500
600
700
Small Medium Large
DOT 5 Year Construction Program Size
Nu
mb
er o
f P
roje
cts
Reported Projects
Number reported morethan 5% over Estimate
FIGURE 9 DOTs using historic bid price estimating - bid comparison
Estimate Comparison - $10 - $25 million projects
The data was broken down further, within each estimating type, to determine which size program
had the best performance in each project cost range. Table 11 and Figure 9 summarize the
project estimating performance for projects valued between $10,000,000 and $25,000,000.
56
Overall, DOT’s with large 5 year construction programs, using either detailed or historic bid
price estimating, and DOTs with medium sized construction programs using detailed estimating
were the top performers in this project value range, all within 2% of one another. These DOTs
have a great deal of experience estimating projects, and whether they prepare detailed or historic
bid price estimates, are able to accurately capture the costs of construction for this project cost
range. The worst reported performance (28.9%) was among small programs preparing historic
bid price estimates. It appears that these DOTs have little experience or data for effectively
estimating projects in this cost range. One possible reason for the lack of accuracy is that the
historic bid prices they are using are for much smaller projects that do not require the same
commitment of resources. As these DOTs complete more projects in this range their historic bid
prices should come in line and their estimating accuracy improve.
TABLE 12 BID COMPARISON, PROJECTS VALUED BETWEEN $10,000,000 AND $25,000,000
DOT 5 Year Estimating Number of Reported Projects Number %
Construction Program Size Method DOTs with
complete Data more than 5% over
Estimate
Small (< 20 projects) Detailed 3 30 30 7 23.3
Historic Bid Price 10 72 72 21 29.2
Medium (21-75 projects) Detailed 3 149 149 25 16.8
Historic Bid Price 12 327 327 66 20.2
Large (76+ projects) Detailed 7 491 491 81 16.5
Historic Bid Price 3 251 251 38 15.1
57
7 2581
327251
14972
30
491
3866
21
0
100
200
300
400
500
Detailed Historic BidPrice
Detailed Historic BidPrice
Detailed Historic BidPrice
Small Medium Large
DOT 5 Year Construction Program Size
Nu
mb
er o
f P
roje
cts Reported Projects
Number reported morethan 5% over Estimate
FIGURE 10 Bid comparison, projects valued between $10,000,000 and $25,000,000
Estimate Comparison - $25 - $100 million projects
Projects valued between $25,000,000 and $100,000,000 (Table 13, Figure 11) are less common
than those in the previous range. DOTs with small 5-year construction programs reported fewer
than ten projects in this category. This number was insufficient for analysis. In this project
range DOTs with medium sized construction programs performed similarly, no matter which
estimating approach was used, detailed or historic bid price. Large historic bid price estimating
DOTs in this category outperformed detailed estimating DOTs.
The two estimating systems are however much more closely aligned than the data would
suggest as Florida, a historic bid price estimating state, had the best performance in this category
with only 11.1% of their projects exceeding the DOT estimate by 5% or more. When Florida is
excluded from the analysis, the large historic bid price estimating DOTs percentage for estimates
over 5% above the DOT estimate rises to 26.8%.
58
TABLE 13 BID COMPARISON, PROJECTS VALUED BETWEEN $25,000,000 AND $100,000,000
DOT 5 Year Estimating Number of Reported Number %
Construction Program Size Method DOTs with
complete Data Projects more than 5% over
Estimate
Small (< 20 projects) Insufficient data for analysis (fewer than ten projects)
Medium (21-75 projects) Detailed 3 37 7 18.9
Historic Bid Price
12 107 20 18.7
Large (76+ projects) Detailed 7 149 43 28.9
Historic Bid Price
3 116 24 20.7
116
7
4337
107149
20 24
0
40
80
120
160
Detailed Historic Bid Price Detailed Historic Bid Price
Medium LargeDOT 5 Year Construction Program Size
Nu
mb
er o
f P
roje
cts
Reported Projects
Number reportedmore than 5% overEstimate
FIGURE 11 Bid comparison, projects valued between $25,000,000 and $100,000,000
One possible reason for the difference between the medium and large DOTs is that larger
program DOTs possibly have more projects at the high end of the range and it is much more
difficult to accurately estimating the larger projects as discussed in the next chapter.
Additionally, several states in this group reported great difficulty in estimating Design-Build
59
projects accurately prior to bid. One DOT reported eleven projects in this project range, five of
which were design build. Of the eleven, six were over the DOT estimate by 5% or more, and all
five of the design-build projects were among the six that were over. The reason these DOTs
cited for this estimating problem is estimators must create complete project estimates based upon
0 - 30% design documents. The contractors base their bids upon a complete study of all project
issues as outlined in their own proposals, which includes much more detailed and possibly
different design information. Depending on the project, the contractor may specify higher
quality or different type materials than the state design standards, particularly if a project
warranty is required. These changes can provide the state with a better facility and a usable
facility in less time, both of which are goals of design-build projects. However, these attributes
sometimes add significant costs. As a result, an estimate based on the early design documents
may only be as accurate as a conceptual estimate would be for another project.
Insufficient data was available for analysis on the two larger project categories by estimating
type and DOT construction program size. For projects valued between $100,000,000 and
$200,000,000 a total of 26 projects were reported with no more than eight in any single category.
Of these 26 reported projects, 10 were reported as being more than 5% over the DOT estimate,
or 38.5%. This extremely high percentage of projects is most likely a result of a lack of DOT
experience in estimating projects this large (Table 14).
TABLE 14: BID COMPARISON, PROJECTS VALUED BETWEEN $100,000,000 AND $200,000,000
Estimating Method No. of DOTs w/ complete Data
Reported Projects
Number %
more than 5% over Estimate
Detailed 4 12 7 58.3
Historic Bid Price 8 14 3 21.4
Overall 12 26 10 38.5
Only eleven projects were reported in the $200,000,000+ project category and data was
available for only eight of those. Of those eight, two or 25.0% were reported over the DOT
estimate by 5% or more (Table 15). While this is better than the percentage for the next lower
project range it is still a very high number when it is considered that these differences all
60
involved at least $10,000,000. Projects of this size are not likely to be typical to any DOT
anytime in the near future, however they are becoming more common across the country. DOTs
should gather as much data as possible when preparing estimates for a project of this size,
including talking to DOTs that have executed projects of this magnitude, particularly those that
received bids far above their estimates.
TABLE 15 BID COMPARISON, PROJECTS VALUED OVER $200,000,000
Estimating Method Number %
Number of DOTs with complete Data
Reported Projects more than 5% over Estimate
Detailed 3 3 1 33.3
Historic Bid Price 3 5 1 20.0
Overall 6 8 2 25.0
Anticipated Changes
Thirty-two DOTs currently have no near-term plans to make any changes to their estimating
practices. Eight DOTs are considering implementing TRNS*PORT, either by converting to the
system, or adding additional modules to their current system. Other DOTs are considering
upgrading current in-house programs to perform better on today’s computers, and the few DOTs
that do not currently use computers for estimating are considering adoption of some computer
system.
61
CHAPTER 4
THE CHALLENGES OF MAJOR PROJECTS
There appears to be no universal definitions for terms such as mega, major, and large-dollar
projects. Yet all of these terms are found in the literature if reference to projects that because of
their physical magnitude require greater amounts of funding and attract rabid proponents and
opponents. The GAO stated in its report Federal-Aid Highways Cost and Oversight of Major
Highway and Bridge Projects – Issues and Options (47) that there is currently no standard
definition of what constitutes a “major project.” GAO has nevertheless applied the term “major
project” to those projects ranging from as little as $10 million to those estimated to cost $1
billion or more. A Senate subcommittee used the term “large-dollar projects” in reference to
projects with a total estimated cost of over $100 million (48). While the FHWA tracks projects
expected to cost more than $1 billion it does not maintain a national database of active federal-
aid projects with a total estimated cost of between $100 million and less than $1 billion (49).
The FHWA in its Resource Manual for Oversight Managers (50) states, “Major (or Mega)
projects are defined as projects with an estimated total cost greater than $1.0 billion or projects
approaching $1.0 billion with a high level of interest by the public.” Hence it is clear that
between government agencies there is not a consistent definition of the term “major project.”
Even researchers have not used the term “mega projects” with any consistency. Merrow applies
the term Megaprojects to those ranging in cost from $500 million to over $10 billion (51).
DOTs in responding to the survey that was conducted for this synthesis reported experience
with only a limited number of projects costing over $100 million so the data for evaluating their
ability to estimate such projects permits only very general conclusions. The data does suggest
that the quality of estimates, for projects costing over $100 million, could be substantially
improved. At the same time DOTs are expected to be challenged by a greater number of these
large projects in the future. At the end of 2002 the FHWA reported there were 14 active Mega
projects base on their $1 billion definition. The FHWA defines active as projects in which the
Record of Decision (ROD) has been issued and design or construction has begun. These projects
are being pursued by 11 different State DOTs. In the case of the new Mississippi River Bridge
between Illinois and Missouri, and the Wilson Bridge between Virginia and Maryland some of
62
these projects are joint efforts. Additionally, the FHWA has identified 13 other mega projects
that should become active in the next three to four years. These projects will involve eight
additional DOTs.
GAO STUDIES OF PROJECT COST
GAO in 1997 examined 30 active highway and bridge projects that were estimated to cost
between $101 and $695 million. Twenty-three of those projects had experienced cost growth,
Figure 12, from their initial estimates. About half of the projects had cost growth of more than
25 percent. The cost of the other 7 projects had either decreased of remained the same.
FIGURE 12 GAO Analysis of DOT Projects Costing over $100 million, 1988-1993 (48)
The GAO report specifically stated:
Most of the cost growth that occurs on a project happens before construction begins. For example, costs on the nearly complete I-595 project in Maryland have increased by over $200 million from the initial cost estimate—from about $188 million to about $390 million. State officials provided data showing that about $160 million of that $200 million increase—around 80 percent—occurred before the construction stage (48).
63
GAO found that there were many factors that caused costs to increase, but noted three specific
factors that worked together to increase costs beyond the initial project estimates (48).
1. Initial estimates are preliminary and not designed to be reliable predictors of a project’s
cost.
2. Initial estimates are modified to reflect more detailed plans and specifications as a project is
designed.
3. A project’s costs are affected by, among other things, inflation and changes in scope to
accommodate economic development that occurs over time as a project is designed and built.
Other researchers have found similar results. As one engineer stated, “To our despair
(megaprojects) often develop lives of their own and their lives sometimes defy control by us
mere mortals (52).” In the June 15, 2002 issue of ENR there was an article “Megaprojects Need
More Study Up Front to Avoid Cost Overruns (8).” The reporters, using information from a
study by Bent Flyvbjerg (53) a Danish professor, asserted that cost overruns were found in 90%
of the mega projects studied.
THE FLYVBJERG STUDY
Flyvbjerg sought to establish how common and how large are the differences between actual and
estimated costs in transportation infrastructure projects. This was a statistical study of 258
transportation infrastructure projects having a total value of $90 billion. Actual costs were
defined as real, accounted construction costs determined at the time of project completion.
Estimated costs were defined as budgeted or forecasted construction costs at the time of the
decision to build.
The researchers hypothesized that if inaccuracy of early cost estimates were simply a matter
of incomplete information and difficulties in predicting the distant future then the expected
inaccuracies should be close to random. The results of the study are summarized in Figure 13
and Table 16. If errors in estimating costs were small, the Figure 12 histogram would be
narrowly concentrated around zero. If errors in overestimating costs were of the same magnitude
and frequency as errors in underestimating costs, the histogram would be symmetrically
distributed around zero. Neither is the case.
64
FIGURE 13 Inaccuracy of Cost Estimates in Transportation Infrastructure Projects (53)
TABLE 16 INACCURACY OF TRANSPORTATION PROJECT COST ESTIMATES BY TYPE OF PROJECT (53)
Project Type Number of Cases (N)
Average Cost Escalation (%)
Standard Deviation
Rail 58 44.7 38.4
Bridges/Tunnels 33 33.8 62.4
Road 167 20.4 29.9
All Projects 258 27.6 38.7 Flyvbjerg made the following observations regarding the distribution of inaccuracies of
construction cost estimates.
¢ Costs are underestimated in almost 9 out of 10 projects. For a randomly selected project,
the likelihood of actual costs being greater than estimated costs is 86%
¢ Actual costs are on average 28% higher than estimated costs.
65
This study of transportation projects mirrors Merrow’s 1981 findings concerning process plant
estimates (9).
Considering projects by type, Table 16, road projects estimates exhibit “average cost
escalation” costs that are less than the aggregate average while bridge estimates are a little more
than 5% above the aggregate average.
Another disturbing fact demonstrated by the study was that cost predictions have not
improved as more sophisticated estimating methods have been developed and experience with
planning and implementing such projects has grown. “Underestimation today is in the same
order of magnitude as it was 10, 30, and 70 years ago. If techniques and skills for estimating and
forecasting costs of transportation infrastructure projects have improved over time, this does not
show in the data.” These comments by Flyvbjerg are illustrated in Figure 14.
FIGURE 14 Inaccuracy of Transportation Project Cost Estimates Over Time, 1910-1998 (53)
66
Explanations of Underestimation
The researchers reviewed the literature for explanations why estimates tend to be low and offered
four broad classes of rationale: technical, economic, psychological, and political. The discussion
of technical explanations is the most interesting.
We may agree with proponents of technical explanations that it is, for example, impossible to predict for the individual project exactly which geological, environmental, or safety problems will appear and make costs soar. But we maintain that it is possible to predict the risk, based on experience from other projects, that some such problems will haunt a project and how this will affect costs. We also maintain that such risk can and should be accounted for in forecasts of costs, but typically is not (53).
This statement brings each DOT’s experience with mega project risk into sharp focus and
highlights needed efforts to predict their potential cost prior to estimating a mega project. It
explains why the Washington DOT has instituted its Cost Estimate Validation Process
(CEVP). With the CEVP process, WSDOT is specifically trying to capture project
uncertainties by critically examining the project estimate to identify risk items. The final CEVP
restructured estimate uses a Monte Carlo simulation technique to provide planners with a range
of costs and a probability for obtaining a specific cost number. A comprehensive discussion of
the WSDOT CEVP process is given in Appendix E.
Washington’s CEVP also drew the attention of the National Academies Committee for
Review of the Project Management Practices Employed on the Boston Central Artery/Tunnel
Project. The Committee stated:
The CA/T could have benefited from a CEVP-type process when it began in 1982, and although options are now limited such a process could still help the IPO (integrated project organization) to control cost and schedule for completing the project (54).
Big Decisions, Big Risk
Mega projects cannot be approached in the same manner as conventional projects. Bruzelius,
Flyvbjerg, and Rothergatter published a study in 1998 (55) that deals with some of the other
issues facing those charged with executing mega projects. In the case of most conventional
projects, engineers focus on technical solutions with little attention to community interest or
concerns. Though this has been changing in some cases where DOTs are experimenting with
67
Context Sensitive design and construction (56 & 57). Their assumption is correct, technical
alternatives are generally discussed at the early stage before community outreach efforts are
undertaken. Concerns related to the external effects of projects are not addressed until later in
the project cycle. Such an approach in the case of a mega project can “… lead to project changes
at a stage when such changes are particularly costly (55).”
“Lack of public involvement also tends to generate a situation in which those groups who feel
concern about the project … are inclined to act destructively…(55).” The Bruzelius-Flyvbjerg
research team counsel that: “It is therefore important to develop a planning process which is less
concerned with technical solutions and information about these, and has more focus in the early
stages on requirements with respect to economic performance, environmental sustainability, and
safety performance of the project.”
COST OVERRUNS
“Large cost overruns on public projects make good newspaper copy. Journalists appear duly
horrified and the world seems to continue as before (58).” John E. Sawyer (59), in a survey of
historical cost experience, declared that if the true costs were known in advance many projects
would not have been commenced to the country’s economic detriment. The Hoosac tunnel
project (1851-1873) cost ten times what was originally projected. The Panama Canal (French
construction period 1881 to 1903, American construction period 1904 to 1914) cost twice its
original estimate and 1.7 times its first U. S. estimate.
Leonard Merewitz’s study (58), in the late 1960’s and early 1970’s, of the Bay Area Rapid
Transit (BART) project in San Francisco provide some very good insight into the problems that
are experienced when a mega project is attempted. The total cost of the original system was
projected at $996 million in 1962. It the time it was the largest single public works project ever
undertaken in the U.S. by the local citizenry. BART construction officially began on June 19,
1964. Delays and inflation sapped capital reserves, and pressures from public and governmental
groups resulted in the relocation of 15 miles of right-of-way and 15 stations, as well as a general
upgrading of station plans. Stations were also substantially altered during construction to include
elevators and other facilities for the handicapped and elderly at an added cost of $10 million.
The cost of the transbay tube rose to $180 million from an original estimate of $133 million.
68
Eliminating design "bugs" from the newly designed train control equipment was a problem Rohr
Industries, Inc. could not deal with. Rohr had suffered a nine-week strike, which, added to
previous delays, had put the car builder one year behind in its car delivery schedules. Another
serious problem arose on June on 1972, when the state imposed a hiring freeze on the District
until 1,100 applicants from other local transportation lines were interviewed for BART jobs on a
priority basis. The first segment of the system opened in September 1972.
Merwitz found that cost overruns were positively related to:
¢ Size of the project
¢ Project scope enlargement
¢ Inflation
¢ Length of time to complete the project
¢ Incompleteness of preliminary engineering and quantity surveys
¢ Engineering uncertainty
¢ Exogenous delays (caused by outside influences)
¢ Complexity of administrative structure
¢ Inexperience of the administrative personnel
California Legislative Analysis
A letter to California State Senator McAteer in 1966 documented a California Legislative
Analyst’s of major factors driving the BART cost overrun. In addition to inflation the letter cited
the following:
¢ Delays
¢ Poor community cooperation
¢ Inadequate assessment of the bidding climate for contract size
¢ Misspecification
Researchers have continually confirmed the presence of such factors when studying the quality
of early project estimates. The builders of the Holland Tunnel experienced cost overruns related
69
to these same factors. Merewitz’s study analyzed the causes of construction cost exceeding the
project authorization estimate.
UNCONTROLLABLE AND CONTROLLABLE REASONS
Estimators and managers should think of cost changes in terms of those that are uncontrollable
and those that are controllable.
Uncontrollable
In the case of BART and the Central Artery/Tunnel project (54), inflation was the critical factor
impacting cost overruns.
Inflation
While inflation is uncontrollable, it is usually a foreseeable factor. Inflation engendered by the
Vietnam War greatly affected the BART system’s cost. The original estimates provided for 3%
per annum inflation, but the actual rate was 6.5% (60). This was a little above the twenty major
American city’s average. There are many indexes available that can aid the estimator in
establishing inflation adjustments to an estimate. Construction costs indexes are published in
both the Architectural Record and Engineering News Record, and these publications include
geographical differentiation factors. Many times it is difficult to tell if an estimate is expressed
in terms of constant or current dollars. In the case of long duration mega projects it is important
to properly account for inflation.
A study of urban rail transit projects in 1990 found that planners have been doing better in
accounting for inflation (61). Planners of the Washington DC rail system substantially
underestimated the rate of construction cost inflation that would occur during completion of its
initial phases, while in the case of six other projects, where explicit forecast were reported,
planners overestimated the inflation percentage, Table 17.
Inflation’s effect must be accounted for both in terms of a rate and a time interval. The report
documented that although the rate predicted was less than that actually experienced, delays in
starting projects (Table 17) and the lengthening of their construction schedules actually caused
inflation to be a significant cost growth factor. The National Academy report (54) on the CA/T
70
project stated; “… the CA/T project management team indicated that about half of the cost
growth was caused by inflation (the original estimates were in 1982 dollars, as required by
FHWA) and that a portion of this could be attributed to the extended schedule.” Exposing
capital outlays to a more prolonged period of inflation contributed to the cost overruns
experienced.
TABLE 17 ERRORS IN FINANCIAL PLANNING TRANSIT PROJECTS (61)
Washington, DC Atlanta Miami Buffalo Portland Sacramento Detroit
Annual Inflation Rate in construction Costs
Forecast 3.1% 6.2% 7.0% 7.8% 8.5% 6.0% 9.0%
Actual* 7.3% 6.1% 4.3% 6.0% 2.7% 2.8% 3.3%
Start of Construction
Forecast 1969 1972 1978 1978 1981 1982 1981
Actual 1971 1975 1979 1979 1982 1983 1983
Years to Reach Scope Studied
Forecast 8 6 6 5 5 3 3
Actual 15 12 7 8 6 5 5
* Actual measure is the average annual rate of increase in the McGraw-Hill Construction Cost index for urban area over the period extending from forecast start year through actual completion year.
Scope
The second cause for overruns was unforeseen scope changes after the authorization of the
project. In many cases scope changes were due to technical problems that had not been foreseen,
while others were in response to demands for the use of “state-of-the-art” technology. The
history of almost every project that pushed the frontier of engineering experience shows that cost
overruns and sometimes-even disaster resulted. Similar events are found in all mega projects.
Examples of technology caused cost overruns include the ventilation system for the Holland
Tunnel, a technical problem of greater impact than originally believed; and, more recently, the
cost effect of the cracks on Amtrak’s Acela Express trains, the use of state-of-the-art technology
71
(62). While these may be uncontrollable analogous to inflation, they should be anticipated and
included for in the project estimate.
Controllable
Large projects are more difficult to manage than smaller ones. Poor administration of mega
projects, starting with incomplete engineering surveys, is often a major escalation cost driver.
Poor administration may also include overly complex organizational structures for planning and
construction, poor contracting practices, and simply inexperienced personnel. Merewitz stated,
“The most significant fact is that the longer the project continues the greater is there likely to be
cost overruns.” Project delays allow inflation to have a greater impact on project cost.
Additionally, delay creates greater time opportunity for increases in scope. Studies of the
estimates prepared by the Corps of Engineers, the Tennessee Valley Authority (TVA), and the
Bureau of Reclamation found that exogenous factors caused large cost increases (63). In the
case of the TVA 80% of the deviations could be characterized as exogenous.
The magnitude of estimation error will vary with project administration. Tighter engineering
and schedule control create better estimates. Some researchers (64) have flatly stated that to
have estimate accuracy there needs to be institutional and management maturity. In 1970
Hufschmidt and Gerin suggested presenting cost estimates in ranges when only preliminary
information available (63). This is how WSDOT is now handling their early cost estimates
(Appendix E).
A STATISTICAL STUDY
Mega projects have characteristic traits besides cost and size that make them extremely
challenging to estimate and which estimators should always consider when reviewing costs
assumptions. These will include:
¢ Mega projects stretch available resources to the limit - financial, labor, equipment,
material, management skill, and information systems
¢ Mega projects have a high profile garnering both political and public scrutiny
¢ Mega projects are very noticeable by regulators
72
¢ Mega projects are unusually long duration projects and there is less likelihood of
maintaining continuity of management
Twenty years before Flyvbjerg’s accusations about agencies purposefully underestimating
project cost independent researchers at The Rand Corporation investigated some 52 projects
ranging in cost from $500 million to over $10 billion (1984 dollars). Their study specifically
sought to address the question of what steps could be taken to minimize cost and schedule risks
(51). Although only six of the projects were civil projects (11%), with similar construction
requirements to what DOTs traditionally build, the results are significant because the research
team was seeking to identify correlations to cost increases. In the Rand study over a third of the
projects took more than five years to go from the beginning of detailed engineering to
completion of construction, while the average total duration was approximately seven years. The
base estimate that the Rand researchers used for their analyses was the project estimate that was
prepared closest to the beginning of detailed engineering.
Faulty Estimates
In the absence of specific information, estimating methods usually fix a zero cost to requirements
that are not perceptible and while contingency allowances are common practice they are not
designed to adjust for major changes in project requirements. It is believed that the causes of
faulty estimates include:
¢ Poor project definition at the time an estimate is made
¢ Project complexity adds to the tendency to underestimate costs. It makes interactions
between different facets of a project more likely to go unnoticed and therefore
unestimated.
¢ Faulty economic assumptions for long duration projects involving mega cost have large
dollar effects
Faulty Execution
Project execution consists of the detailed engineering, construction, and cost/schedule/quality
control of a project. The Rand researchers investigated whether blunders in the execution of a
73
project could lead to significant cost increases. Merrow reports (51), however, that no
systematic analysis of capital projects has ever concluded that blunders by project managers in
executing the project were an important source of cost growth. He cites his own studies in 1981
and 1986 (65 & 66) and studies by Meyers (67 & 68).
Merrow (51) suggests that the sub-management categories, such as labor productivity, have
sometimes caused problems. But he tempers even that allowance by stating: “While inept day-
to-day labor supervision might lead to poor labor productivity we strongly suspect that other
factors are underlying causes ? factors such as remote sites, failure to plan for adequate
manpower training programs, poor understanding of local labor practices, changing or unclear
labor regulations, and the like (51).” He admits that poor management will cause cost growth
but stresses that poor project execution caused by management deficiencies is usually not the
primary driver of project cost growth.
Project Scope Changes
The project estimated early in the project development process is often not the project actually
built. Scope changes can be defined as any discretionary change in the size or configuration of a
project. Most changes in scope result from an improved understanding of project need and
outcome requirements. The longer a project takes to get to field construction, the more likely
scope changes will occur. Here we are speaking strictly of discretionary scope changes that add
features to the project.
Technological innovation was grouped together with scope change in the Rand research. This
seems to be a result of considering that most scope changes were driven by a desire to use the
very latest technology. The Rand researchers used the terminology “high technology” – on the
cutting edge of the transition of science into practice. Technological innovation in construction
operations would be defined as the use of new equipment and/or methods that have had limited
prior application such that estimators have difficulty predicting costs, just as field personnel will
have difficulty in its use. Doing something in a different way reduces the amount of information
available to the estimator to use in predicting cost.
74
Macroenvironment
Every project is executed in the context of a particular political, economic, and cultural
environment. The legal system, labor practices, attitudes and regulations concerning worker
health and safety, and environmental concerns and constraints are manifestations of the
macroenvironment of mega projects. The macroenvironment can affect cost growth in two
ways: 1) by being unknown to some degree to estimators and managers, and 2) by changes in the
environment. Unlike other aspects of project planning and estimating, understanding the
macroenvironment has never been standardized as a part of project estimating. Mega projects
are more likely to have problems stemming from the macroenvironment because they often spark
new regulations, political opposition, and the need for new technology to overcome engineering
challenges. Examples of cutting edge technology that were used to meet engineering challenges
on the Boston Central Artery/Tunnel mega project and which made successful execution of the
project possible include (54):
¢ Use of new and specialized equipment from Europe to construct the deep slurry walls.
This was the largest use of slurry wall construction in North America.
¢ Construction of the tunnel under active railroad tracks by the jack tunneling through
unstable solids with the use of extensive soil freezing.
¢ Erection of the widest cable-stayed bridge in the world.
Identified Correlations
Morrow’s study (59) found that cost growth was not correlated to project size. His statistical
approach found positive correlations between cost growth and:
1. Problems between the project and government ? regulatory disputes
2. Innovation in the project
Regulations
The most important predictor of cost growth and schedule slippage in mega projects is the extent
to which the project encounters regulatory constraints in the following areas (51):
¢ Protection of the natural environment from the effects of the project
75
¢ Protection of the public health and safety from the effects of the project
¢ Controls on the use of labor or procurement
¢ Other government standards or regulations
In and of themselves, regulations should not cause either cost growth or schedule slippage. These things occurred in our database projects because the effects of regulations on cost and schedule were not factored into the cost and schedule estimates. In particular, regulatory cost effects associated with environmental problems and health and safety issues were not accounted for (51).
The GAO report Managing the Costs of Highway Projects (48) also called attention to the
impact efforts to protect the environment have on project cost. GAO noted that initial cost
estimates usually identify and include environmental mitigation costs, but the extent and
therefore the true cost of the mitigation work is typically not known until testing for the detailed
design has been completed.
On the reconstruction of I-880 in California, the state’s EIS had identified the need to clean up hazardous material sites along the highway’s alignment. However, drilling and testing for hazardous materials during the design stage revealed the presence of more contaminated soil and groundwater than had been expected. The costs of controlling and disposing of these contaminants increased the cost of this project by about $40 million. In Maryland, a noise study was performed for the EIS to estimate the need for and costs of soundwalls for the I-595 reconstruction project. However, more detailed noise readings taken during the design stage affected the size and length of the required soundwalls and added $2.6 million to the project’s costs (48).
From Merrow’s analysis it is clear that in order to properly ascertain the cost of a mega
project, estimators must have a very good understanding of how government regulations can
directly impact the cost of many individual work items and can add a significant number of work
items to the project.
Innovation
“Virtually any form of technological innovation in a project is likely to result in cost growth
(51).” Indicators of innovation are:
¢ Whether or not the project embodied any first-of-a-kind technology.
76
¢ Whether the project employed any new materials or methods of construction.
¢ Whether the project was the largest project of its kind when constructed.
A positive correlation was found between cost growth and the first two indicators. No
correlation was found between being the largest project of its kind and cost growth.
Merrow’s Conclusions
The larger the project, the more important is the accuracy of early estimates. This is because the
absolute amount of money is so large that even minor percentage overruns involve large sums of
money. In the conclusion of his study, Merrow offers good advice, which is supported by other
researchers.
1. It is essential that all aspects of each and every government regulations be analyzed with
respect to every element of the project during estimate preparation.
2. Mega projects may foster regulatory rule changes because new information is generated,
problems become visible, or because political pressures dictate change. Estimators must
consider the likelihood and cost of regulatory changes.
3. Estimators must consider that political concerns and the desire of individual politicians to
be re-elected may over shadow and impede the progress and success of the project.
4. Estimators must understand that mega projects employing new technology have a far
higher risk of catastrophic problems during project execution and these can result in large
cost increases.
Estimating a mega project is not the usual procedure of summing the costs of accomplishing
items of work; it is also about appropriately accounting for the many non-performance of work
factors that add cost to the undertaking.
WOODROW WILSON BRIDGE SUPERSTRUCTURE CONTRACT
On December 13, 2001, the Maryland State Highway Administration opened bids for the
Woodrow Wilson Bridge superstructure contract. A single $860 million bid was received. That
amount was more than 75% higher than the engineer’s estimate for the contract (1). Maryland
77
formally rejected the bid since it far exceeded the project’s budget. An independent review
committee was organized to identify and evaluate the reasons for the large discrepancy between
the engineer’s estimate and the bid submitted. Thomas Warne, former Executive Director for the
Utah Transportation department, chaired the committee made up of engineering and construction
consultants from across the country.
The committee interviewed contractors to determine the reasons they chose not to bid on the
contract and what might serve as an incentive to make them compete for the project in any re-bid
scenario (69). The committee concluded that an agency or owner’s hired consultant cannot
produce a good estimate unless it has an appreciation for how contractors perceive risk. In the
case of mega projects, the amount of risk that even the largest contracting organizations can
tolerate is exceeded. Therefore, contracting firms must develop strategies to minimize their
risks. Some of these strategies involve increased cost to the project owner. In the case of risks
that cannot be quantified, that cost increase can be significant. Additionally, if the contractor
perceives that an owner is seeking through the contract language to shift risk to the builder
sufficient additional cost will be included in the bid to cover that added financial exposure.
Points raised by contractors to the review committee concerning the Wilson Bridge
superstructure contract illustrate these concerns.
¢ Project schedule – Jointly the project duration constraints with associated cost impacts for
late delivery and the fact that there was no compensating incentive to deliver the project
on time or ahead of schedule were viewed as a disincentive. Incentives provide the funds
necessary to attempt extraordinary construction methods that can accelerate project
delivery.
¢ Constructability – The new Wilson Bridge is a unique design that created some unknown
factors that could impact the cost of the project. Additionally, several large cranes and
barges would be needed; some actually would need to be constructed specifically for the
project.
¢ Government oversight – The variety of government entities involved and the political
sensitivity of this unique project raised concerns as to who would be ultimately
78
accountable and empowered to make quick decisions. Delays decision-making by an
owner causes a contractor to incur non-compensated additional costs.
¢ Other Major Projects – Bidding was underway for the $1.04 billion Oakland Bay Bridge
project at the same time. Even major contractors have limited estimating capability; to
estimate more than one mega projects during the same time frame is often not possible.
The independent review committee (IRC) determined that the owner estimate produced was
technically solid based on the tangible factors like the cost of steel, concrete, and other materials,
but certain significant factors, particularly for large construction projects, are difficult to quantify
in an estimate (70). The IRC went on to state that the estimate did not sufficiently take into
account the intangibles of market factors, specifically:
¢ Due to recent experiences on other mega projects and to associated project risks
contractors capable of bidding a project of that size are seeking larger margins to protect
themselves.
¢ Lack of competition as there were several other large bridge projects bidding in the same
time period.
¢ Equipment demands on projects of this size are substantial.
There are only a small number of contractors in the world who have the ability to take on
mega projects. The size of such projects necessitates that joint venture teams be formed in order
to generate adequate bonding capacity and reasonable risk. The consequence of fewer
competitors is higher bid prices. When material demands are great, producers may also have to
team, thus further reducing second tier competition. In the case of the Wilson Bridge the steel
demand was so significant that fabricators needed to team together to meet the requirements
(71).
Acting on these factors, which that the review committee noted, Maryland officials decided to
re-package the superstructure work into three contracts. Those contracts were bid in late 2002
and early 2003 (72, 73, & 74). The first package came in 11% above the DOT estimate, but the
second package came in 28% below, and the third 25% below. By packaging the work into three
smaller contracts, eliminating the union-only project labor agreement, and a design change
79
substituting plate girders for box girders allowed the DOT to achieve a total price for the bridge
only slightly above the 2001 DOT estimate and about $360 million below the single mega
project bid of 2001.
Some would argue now, that all of the contracts have been bid, that the original estimate was
not the problem. That is not a valid conclusion if the estimate was suppose to represent the cost
of doing the work under the conditions of the offered contract. A contract that placed greater
risk on the bidders. The original contract and scope of work, and what was bid in the three
separate contract do not represent the same conditions. What can be argued and what this
synthesis strives to point out is that DOTs can receive better valued by carefully considering
upfront how best to package contracts, by utilizing constructability reviews, and by
understanding the impact of the macro-environment of the cost of projects.
Innovation
As reported by many other researchers (51, 58, & 62), innovation causes cost growth. The IRC
noted:
The bridge V-piers, which are the defining signature element of this project, represent a construction technique that has never previously been attempted on such a magnitude. As a result, it is very difficult to estimate the premium associated with the risk and complexity of these piers (70).
Innovation adds risk to the building process. Maybe the worse case was the Sydney Opera
House which was originally estimated to cost $7,000,000 Australian dollars. The original design
proved so bad that the structure could not be constructed as designed and the entire internal
design was changed. The final cost was $102,000,000 Australian dollars and the structure does
not even function as the major opera house that was its principle raison d’être (60).
Inflation
Inflation is a concern to both owner and contractors, and it influences bid prices. The long
construction duration of the Wilson Bridge superstructure contract (more than 5 years) was
appreciably greater than most projects. Therefore, contractors had to forecast economic
80
conditions and calculate anticipated prices for materials, equipment, and labor far into the future.
Most contractors will approach this situation very conservatively and include generous
contingencies consistent with that uncertainty (70).
Macroenvironment
The work being preformed on the previous contract for the bridge demonstrated the difficulties
in dealing with the local jurisdictions and regulatory agencies (70). In addition uncertainty
surrounding the proposed project labor agreement (PLA) abounded. These added risk factors
were likely compensated for by the contractor inflating the bid price.
81
CHAPTER 5
RECOMMENDATIONS
Significant differences exist among the estimating practices of individual DOTs. Although
consistency might have been expected among agencies based on program size or regional
location, none was found. Instead, it appears that the estimating practices of any DOT are
determined solely by the experience of the personnel in charge of estimating, usually the head of
the estimating section or the chief of design. Because DOTs do not share bidding and pricing
information with their neighboring state DOTs, some potentially valuable insights are lost. It
seems that the DOTs would benefit from collaborative discussions of bidding trends, habits of
bidders that are in common bidder pools, and potentially on estimating practices for mega
projects.
The following sections of this chapter discuss practices that could help DOTs improve their
project estimating capability. Many of these practices are being used by a limited number of
DOTs. Some of the practices are derived from studies of contractor estimating procedures.
ESTIMATING GUIDANCE
Estimate documentation must be in a form that can be understood, checked, verified, and
corrected (74). The foundation of a good estimate is the formats, procedures, and processes used
to arrive at the cost. Every DOT that does not currently have a published estimating manual
would benefit greatly by producing its own manual of standard formats, procedures, and
processes to be used by both DOT estimators and design consultants retained for estimating
purposes. This guidance document should be specifically written for those responsible for
preparing the State’s estimates. How inflation is treated in the estimate must be clearly stated.
FHWA recommends the cost estimates be prepared in year-of-expenditure dollars, inflated to the
midpoint of construction, with some allowance for schedule slippage taken into account.
Reporting the costs in year-of-expenditure dollars will greatly reduce the media and public
perception of “cost growth.”
82
FHWA has distributed information on lessons learned from major (Mega) projects. Two
important points that should be considered in addition to inflation are contingencies and a
project’s economic impact on the local economy.
Reasonable contingencies should be built into the total project cost estimate. It is suggested
that the following contingencies be included: 1) a Construction contingency for cost growth
during construction; 2) a Design contingency based on different levels of design completion; 3)
an overall Management contingency for third-party and other unanticipated changes; and 4) other
contingencies for areas that may show a high potential for risk and change, i.e., environmental
mitigation, utilities, highly specialized designs, etc.
Cost estimates should consider the economic impact of major project on the local
geographical area. For example, material manufacturers that would normally compete with one
another may be “forced” to team together in order to meet the demand of a major project.
Extremely large construction packages also have the potential to reduce the amount of
contractors that have the capability of bidding on the project, and may need to be broken up into
smaller contracts to attract additional competition. Bid options (simultaneous procurements of
similar scopes with options to award) should also be considered for potential cost savings
resulting from economies of scale and reduced mobilization. A value analysis should be
performed on the project to determine the most economical and advantageous way of packaging
the contracts for advertisement.
In preparing an estimating manual, members of the States heavy/highway construction
industry should be asked to share with the Department their knowledge of production rates,
estimating techniques, and factors that increase project risk. Advice from local contractors
should specifically be sought in regard to factors that they consider to be important cost drivers.
Some considerations that are often made by contractors include (75):
¢ Is this a labor-intensive project (76)?
¢ Does the project depend heavily on certain pieces of equipment?
¢ Is there a danger of material price increases?
¢ What is the cash flow of the project?
83
The availability of an easy to use guide, that prescribes the standard estimate format for the
DOT, will greatly assist estimators in preparing estimates in less time, as many of their questions
can be addressed simply by reading the manual and following standard procedures. The benefits
of standardized procedures clearly explained in a manual should outweigh the cost of initial
production and periodic updates. In order to reduce production costs and make changes less
expensively, the manual could be published and maintained electronically.
CONCEPTUAL ESTIMATES
A conceptual estimate should use the highest level of detail available for quantity takeoff and
project scoping combined with recent bid information to set the project cost. By incorporating
proper risk and contingency amounts into this estimate, the estimator can greatly improve the
accuracy of the estimate. The DOT must develop clear definitions of what constitutes a
contingency and how contingency amounts are determined.
Contingency means an event that may occur but is not likely or intended. It is a possibility,
condition of chance, for which there must be a plan of action (or additional money). Risk is a
possibility of suffering harm or loss. Think of contingency and risk in terms of quantifiable and
non-quantifiable outcomes, Table 18. Contractors will add cost to their bid to cover both
contingencies and risks.
TABLE 18 CONTINGENCY - RISK EVALUATION
Issue Cost Coverage in the Estimate
Identified issue Known Direct cost
Identified issue that will occur Unknown Contingency
Identified issue that may occur Unknown Risk
Issue that has not been identified Unknown Risk The use of historic bid prices is a relatively straightforward process and can yield good results
if properly applied. The use of historic bid averages however does not release the estimator from
personal responsibility to insure that the averages are representative of the conditions of the
84
project being estimated. If a DOT is, by means of bid data, creating line item averages to be
used in preparing its estimates, the estimator must be trained to recognize the validity of such
unit prices. The use of data without knowledge of its similarity to the work being estimated
produces an inaccurate estimate. The analysis of historic bid data and the use of that data in the
creation of a unit price guide is valuable. Caltrans (see Appendix F) provides an annual guide
giving average cost data, cost range data, and average cost per unit of work data. Their guide
also includes indices for cost adjustments based on location, quantity, traffic conditions, and
other factors.
Conceptual estimates for mega projects are another matter and such estimates must account
for the macroenvironment of the project. Because these projects are of such long duration there
is a greater chance that the conditions affecting cost will change. The certainty of prevailing
conditions declines as the length of the forecast (estimate) period increases (77). In the case of
such situations estimators must identify not only the most likely course of events but also those
events that could possibly impact the project. Estimators should employ risk analysis techniques
such as the CEVP process that WSDOT is using (Appendix E).
DESIGN PHASE COST CONTROL
Many DOTs reported that during the design phase of project development they do have standard
procedures for identifying scope changes that cause project cost increases. In order to ensure
designers are aware of how design changes will affect project cost, it is advantageous to require
submittal of a cost estimate along with each design submittal. When large differences between
the conceptual estimate and the design estimate are reported (>10%), approval should be
required from the supervisory level or higher before design proceeds in order to ensure sufficient
funds will be available for construction. If the funds cannot be obtained, changes must be
required to reduce the overall project cost; this may cause a reduction in project scope.
PRE BID ESTIMATES
A dedicated estimating section with personnel knowledgeable in the areas of design,
construction, and estimating can best conceptualize and model all elements that are required for
an accurate estimate. These personnel should be trained to use available estimating software.
85
Preparing detailed estimates of major work items gives the DOT a strong footing for rejecting
bids that are over their internal estimate, while performing historic average cost estimates of
minor items reduces the overall workload of estimators and requires fewer personnel to complete
more estimates.
In DOTs that use historic bid price averages, the more information the estimators have about
both the project and pricing of items, the more likely they are to produce an accurate estimate. In
California cost sheets are generated for major work items detailed by item quantity ranges.
Additionally, adjustment factors based on project conditions that may be encountered on any
given project are provided. These factors are the result of extensive bid data analyses. Appendix
F is a Caltrans Unit Price Factor sheet for Structural Concrete for Bridges. While this sheet
cannot address all possible project conditions, nor can it tell the estimator exactly how much to
add for any specific condition, it is a quick and concise tool for developing costs based on project
conditions. In order for an estimator to determine how much to increase or decrease prices they
must examine the work closely and not rely on a simple quantity takeoff from the plan sheets.
Consideration of all project conditions that effect price, such as location within the state,
schedule constraints, and site issues is necessary to accurately estimate a project. The estimator
must also know if any incentives are in the contract, and anticipate that the contractor will
perform to the required standard, when creating the estimate.
AWARD
After receipt of the bids, the estimator or estimators that estimated a project should be involved
in the bid analysis for that project prior to award. This will give them an opportunity to spot
bidding trends early, and also ensure that someone that is knowledgeable about the estimate is
involved in the decision to award. Projects that exceed DOT estimate limits for automatic award
generally receive this additional inspection, but to maximize the benefit of this process the same
estimator that prepared the DOT estimate should be involved in both the bid analysis and award
decision.
An additional responsibility of estimators is the detection of bid rigging or collusion.
Enforcement of the Federal Sherman Act is the responsibility of the Antitrust Division of the
86
U.S. Department of Justice. However, those that are charged with review of project bids should
be the first to notice the signs of complementary bidding or bid rotation. With proper training
and adequate technological and legal support, estimators can include this step in normal bid
analysis without appreciably increasing their workload. Estimators are the personnel in the DOT
most familiar with pricing information from past projects and are most likely to notice when a
group of contractors have suddenly changed their bidding habits. Additionally, by making
estimators responsible for this portion of project development they will be forced to examine all
projects to determine how contractors are bidding, aiding the estimator in determining the best
unit price for any estimate item.
RELEASE OF ESTIMATE
The DOT’s estimate should be available after award as a project total amount. This gives both
the general public and contractors a chance to see the original projected project cost. However,
the release of detailed unit prices may compromise future DOT estimates. What is allowable is
usually defined by State statute and, in many cases, out of the DOT’s control.
DESIGN BUILD PROJECTS
In order to accommodate the cost difference between contractor proposals and the DOT's pre-bid
estimate for Design-Build projects, the DOT can make appropriate adjustments. Since the pre-
bid estimate is based on conceptual design information, the estimate can be treated like a
conceptual estimate and a proper contingency amount can be added. The contingency amount
can be determined by an estimator's review of the Request for Proposals and should attempt to
determine areas where the contractor may exceed the DOT standards for the purpose of making
the proposal more appealing to the award committee or for satisfying warranty requirements.
Bid items can be adjusted upward to reflect contingencies or incomplete design or a range of
values can be used for each item. As agencies have more experience and cost data for design-
build projects, separate price lists or estimating guides can be developed.
Additionally, the DOT should assign estimators to the award team for these projects. These
estimators would be responsible for examining the project cost proposal based on the
information in the technical proposal. Since the technical proposal is likely to differ from DOT
87
standard designs the estimator will have to ensure any costs they use in analyzing the cost
proposal are valid based on the proposal requirements for time and quality.
PROJECTS VALUED OVER $100 MILLION
From a risk perspective, mega projects are more than the simple ballooning of the size of
conventional projects. With increased size and complexity, and, many times, new technology
comes exponentially large risk (78). This is a lesson that many estimators have not yet learned.
Projects valued over $100 million require special consideration of project risk and complexity in
order to produce an accurate estimate. The most experienced estimating personnel should be
assigned to estimate these large projects. It may be necessary to retain a construction consultant
with the necessary experience to help the DOT estimators or even to prepare the estimate. This
will help the estimators account for all of the complexities of the large project while at the same
time giving them the necessary experience to prepare accurate estimates for mega projects in the
future.
89
CHAPTER 6
CONCLUSIONS
The core assumptions underlying an estimate can be major determinants of forecast accuracy.
This has proved particularly true in the case of mega projects. It does not matter if the estimating
methodology is detail or historic bid price. In the case of projects valued at over $25 million,
approximately 20% of the time the bid price is greater than 5% over the DOT estimate. In the
case of projects costing over $100 million, approximately 40% of the time the bid price is greater
than 5% over the DOT estimate. When the core assumptions of the estimating process are wrong
it makes little difference what methodology is used to prepare the estimate (77).
Departments of Transportation must develop and implement strategic project and program
management systems to improve on − time, on − budget delivery of projects. To do so, DOTs
must develop and test cost estimating/validation processes to determine that cost estimates are
reasonable, defendable, and sustainable.
A COST ESTIMATE IS NOT A SINGLE NUMBER (79 & 80)
The actual cost of a project is subject to many variables, which can, and will significantly
influence the range of probable projected costs. Similarly, the Census Bureau does not present a
single forecast population growth; it offers projections based on different assumptions of
fertility, mortality, and migration rates (77). In the case of DOT estimates, any one cost number
represents only one possible result of the multiple variables and assumptions. These variables
are not all directly controllable or absolutely quantifiable. Therefore, cost estimating and the
validation process must consider probabilities in assessing cost, using a recognized, logical and
tested process.
In the beginning there is a very large potential range for a project’s ultimate cost. We need to
consider:
¢ How estimates are usually done?
¢ What we need to do to get a valid estimate?
¢ How we develop a reliable cost estimating and validation process?
90
¢ How the estimating process can accurately evaluate variability and risk using logical,
reasonable statistical (probability) methods.
The traditional approaches to early estimating match poorly with the public’s intuitive
understanding of “what engineers can tell us.” The meaning of “contingency” in an estimate is
not clearly defined in many DOTs and how DOTs use of the term completely mystifies ordinary
citizens. The public sees “development” of an estimate as evidence of doubtful engineering
competence or worse − untrustworthy actions.
GROWTH IN PROJECT COST
The Boston Central Artery/Tunnel Project has received scalding condemnation because of
supposed cost growth. The initial cost estimate for the project was $2.6 billion in 1982. That
was a preliminary concept developed by state officials. It covered only a small fraction of what
would eventually be built and excluded key factors such as inflation over the 20 plus year life of
the project, environmental permitting requirements, and many unforeseen community mitigation
measures (81). The same factors that caused the difference between the initial cost estimate and
actual cost are to be found on every mega project. Table 19 presents information from three
specific projects, and the results of Merewitz’s and Rand studies of multiple mega projects.
TABLE 19 FACTORS THAT INCREASE MEGA PROJECT COST
Factors Project Researcher
Holland Tunnel BART CA/T Merewitz (59) Rand (65)
Scope Changes Yes Yes Yes Yes Yes
Inflation Yes Yes Yes Yes Yes
New Technology
Yes Yes Yes Yes Yes
Technical challenges
Yes Yes Yes Yes Yes
Duration Yes Yes Yes Yes
Exogenous factors
Yes Yes Yes Yes
Management Yes Yes Yes
91
In Boston 55% of the cost growth was attributable to inflation. The next major cost impact
factor was macroenvironment mitigation which added 15% to the cost. Public pressure forced a
one billion dollar redesign of the Charles River crossing. Changes in project scope added
another 13% to the cost. DOTs must be very conscious that estimating a mega projects is not the
simply about summing the costs of work items; it is very much about appropriately accounting
for the many external factors that add cost and risk to the undertaking. Stretching out a project
means that there is more time for land costs to increase, planned economic development to occur,
and the passage of environmental or other laws or regulations that could increase the project’s
costs (48).
KEYS TO SUCCESS
Engineering skill and judgment invested in project planning is obscure to the general public,
legislators, community opinion leaders, and the media. Cost busts are easy for the public to
understand. But who wants to appreciate the fine points of route alignment, difficult
geotechnical conditions, or wetlands mitigation analysis?
Departments need a strategic approach to early cost declarations.
¢ Avoid false precision − a big problem is created by early optimism.
¢ Relate contingency to the layman’s everyday experiences with uncertainty.
¢ Invest in continuous and transparent QA/QC of your estimating processes.
93
REFERENCES
1. “Lone Woodrow Wilson Bridge Bid Comes in 70% above Estimate,” ENR, p. 13, Dec. 24,
2001.
2. “Bay Bridge Replacement Comes in Above Estimate,” ENR, p. 5, Dec. 31, 2001.
3. “Heat Rises Over Central Artery,” ENR, p. 15, May 15, 2002.
4. Murphy, S., “Big Dig Review to Target Cost Overruns,” The Boston Globe, 23 November
2002, A1, 2003.
5. “Interchange’s Cost Overrun Draws Congressional Fire,” ENR, p. 9, July 17, 2000.
6. “Virginia’s Big ‘Mixing Bowl’ is 180% Over Budget, Late,” ENR, p. 7, Dec. 2, 2002.
7. “Steep Slopes Mean Steepened Costs for Hoover Dam Bypass,” ENR, p. 15, June 24, 2002.
8. “Megaprojests Need More Study Up Front to Avoid Cost Overruns,” ENR, p. 11, June 15,
2002.
9. Merrow, Edward W., Phillips, Kenneth E., and Myers, Christopher W., Understanding Cost
Growth and Performance Shortfalls in Pioneer Process Plants, Rand, Santa Monica, CA,
Sept. 1981.
10. Schexnayder, Clifford J. and Mayo, Richard E., Construction Management Fundamentals,
McGraw-Hill Higher Education, Boston, MA, 2003.
11. Hackney, J. W., Control and Management of Capital Projects, John Wiley & Sons, Inc.,
New York, 1965.
12. Clark, Forrest D., “Cost Control for Process Plants from the Owner’s View,” Chemical
Engineering, July 7, 1975, pp. 76-77.
13. “Urges New Tunnel Under the Hudson”. New York Times: Mar. 18, 1918; pp 18.
14. “Ask Nation to Share in Tunnel to Jersey”. New York Times: Jun. 29, 1918; pp 15.
94
15. “Hudson Vehicle Tube”. New York Times: Feb. 25, 1919; pp 11.
16. “Name Interstate Tunnel Engineers”. New York Times: Jun. 15, 1919; pp 28.
17. “Asks $28,669,000 for Jersey Tube”. New York Times: Feb. 15, 1920; pp 17
18. “Reach Tunnel Agreement”. New York Times: Nov. 16, 1921 pp 10.
19. “Way All Cleared for Jersey Tunnel”. New York Times: Dec. 28, 1921; pp 4.
20. “Vehicular Tube is Growing”. New York Times: Jul. 1, 1923; VIII pp. 1
21. “Vehicular Tunnel Cost Up $14,000,000”. New York Times: Jan. 15, 1924; pp. 23.
22. “$3,200,000 More Asked for Tunnel”. New York Times: Feb. 10, 1926; pp 2.
23. “Holland Tunnels to Cost $48,400,000”, New York Times: Dec. 27, 1926; pp. 11.
24. “Work on Tunnel Began 7 Years Ago”. New York Times: Nov. 13, 1927; pp. 26.
25. Parker, A., Barrie, D., Snyder, R., Planning and Estimating Heavy Construction. McGraw-
Hill, New York, NY, 1984.
26. Bartholomew, S., Estimating and Bidding for Heavy Construction. Prentice-Hall, Upper
Saddle River, NJ., 2000.
27. Church, Horace K. Excavation Handbook, McGraw-Hill, Inc., New York, NY, 1981.
28. O’Brien, James J., Havers, John A., and Stubbs, Frank W. Jr., Standard Handbook of Heavy
Construction, 3rd ed., The McGraw-Hill Companies, Inc., New York, NY, 1996.
29. Peurifoy, Robert L., and Schexnayder, Clifford J., Construction Planning, Equipment, and
Methods, The McGraw-Hill Companies, Inc., New York, NY, 2002.
30. Young, J., “Design Phase Cost Control,” 1997 AACE International Transactions,
Association for the Advancement of Cost Engineering International, Morgantown, WV,
1997.
31. De La Garza, J., and Oralkan, G., “Implicit Design Knowledge and its Impact on Cost
Estimating,” Construction Congress Proceedings: Preparing for Construction in the 21st
Century, American Society of Civil Engineers, New York, NY, 1991.
95
32. Uman, D., “Is a Standard Needed for Estimating Building Design and Construction Cost?”
Cost Engineering, Association for the Advancement of Cost Engineering International,
Morgantown, WV, 32(8), 7-11, 1990.
33. Guide Specifications for Highway Construction. American Association of State Highway and
Transportation Officials, Washington, D.C., 1998.
34. Paek, J., “Common Mistakes in Construction Cost Estimation and Their Lessons,” Cost
Engineering, Morgantown, WV, 35(6), 29-33, 1993.
35. Stern, A., “The Best Estimating Methodology for Project Owners,” 1994 AACE
Transactions, Association for the Advancement of Cost Engineering International,
Morgantown, WV, 1994.
36. Shash, A., and Al-Khaldi, Z., “The Production of Accurate Construction Cost Estimates in
Saudi Arabia,” Cost Engineering, Association for the Advancement of Cost Engineering
International, Morgantown, WV, 34(8), 15-24, 1992.
37. Pearl, R., “The Effect of Market Conditions on Tendering and Forecasting,” 1994 AACE
Transactions, Association for the Advancement of Cost Engineering International,
Morgantown, WV, 1994.
38. Hicks, J., “Heavy Construction Estimates with and without Computers,” Journal of
Construction Engineering and Management, 118(3), 545-560. American Society of Civil
Engineers, New York, NY, 1992.
39. Sanders, S., and Maxwell, R., Glagola, C., “Preliminary Estimating Models for Infrastructure
Projects,” Cost Engineering, Association for the Advancement of Cost Engineering
International, Morgantown, WV, 34(8), 7-13, 1992.
40. Sanders, S., and Maxwell, R., “Preliminary Estimating for Heavy Construction,” 1992 AACE
Transactions, Association for the Advancement of Cost Engineering International,
Morgantown, WV, 1992.
96
41. Al-Tabtabai, H., Alex, A., and Tantash, M., “Preliminary Cost Estimation of Highway
Construction Using Neural Networks,” Cost Engineering, Association for the Advancement
of Cost Engineering, Morgantown, WV. 41(3), 19-24, 1999.
42. Touran, A., “Probabilistic Cost Estimating with Subjective Correlations,” Journal of
Construction Engineering and Management, American Society of Civil Engineers, New
York, NY, 119(1), 58-71, 1993.
43. Preconstruction Estimating Procedures/Methodology, A Joint FHWA/ConnDOT Process
Review, State of Connecticut, Department of Transportation, Newington, Conn., Sept. 2002.
44. Contract Administration Core Curriculum Participant's Manual and Reference Guide 2001,
Chapter III A, U. S. Department of Transportation, Federal Highway Administration,
www.fhwa.dot.gov/programadmin/contracts/cor_IIIA.htm#IIIA2
45. Skipper, Charles O. and Bell, Lansford C., Long Range Program Cost Estimating
Methodology for SCDOT, Department of Civil Engineering, Clemson University, April 2003.
46. Contract Administration Core Curriculum Participant's Manual and Reference Guide 2001,
Chapter III B, U. S. Department of Transportation, Federal Highway Administration,
www.fhwa.dot.gov/programadmin/contracts/cor_IIIB.htm#IIIB1
47. Federal-Aid Highways Cost and Oversight of Major Highway and Bridge Project – Issues
and Options, GAO-03-764T, Washington, D.C., May 8, 2003.
48. Transportation Infrastructure Managing the Costs of Large-dollar Highway Projects,
GAO/RCED-97-47, Washington, D.C., February, 1997.
49. Transportation Infrastructure Cost and Oversight Issues on Major Highway and Bridge
Projects, GAO-02-702T, Washington, D.C., May 1, 2002.
50. FHWA Major Projects, Resource Manual for Oversight Managers, United States Department
of Transportation - Federal Highway Administration, Washington, D. C.,
www.fhwa.dot.gov/programadmin/mega/mega.htm, last modified on April 28, 2003.
51. Merrow, Edward W., Understanding the Outcomes of Megaprojects: a Quantitative Analysis
of Very Large Civilian Projects, The Rand Corporation, Santa Monica, CA, 1988.
97
52. Engesser, D. E., “Management of Large Projects,” Proceedings of the American Institute of
Chemical Engineering Conference on Engineering and Construction Contracting, Sept. 20,
1982.
53. Flyvbjerg, Bent, Holm, Mette Skamris, and Buhl, Søren, “Underestimating Costs in Public
Works Projects, Error or Lie,” Journal of the American Planning Association, Vol. 68, No.
3, 279-292, Summer 2002
54. Completing the Big Dig, Managing the Final Stages of Boston’s Central Artery/Tunnel
Project, (prepublication copy), The National Academies Press, Washington, D. C., 2003.
55. Bruzelius, Nils, Flyvbjerg, Bert, and Rothergatter, Werner, “Big Decisions, Big Risk:
Improving Accountability in Mega Projects,” International Review of Administrative
Science, Vol. 64, 423-440, (1998)
56. A Guide to Best Practices for Achieving Context Sensitive Solutions, NCHRP Report 480,
Transportation Research Board, Washington, D. C., 2002.
57. Werkmeister, Raymond F., Jr. and Hancher, Donn E., “Paris-Lexington Road Project, Project
Report,” Transportation Research Record, Journal of the Transportation Research Board,
NO 1761, Construction 2001, National Research Council, 2001, pp. 130-136.
58. Merewitz, L., “Cost Overruns in Public Works.” in Benefit Cost and Policy Analysis (pp 227-
297), Chicago, Aldine. (1973).
59. Sawyer, John E., “Entrepreneurial Error and Economic Growth,” Explorations in
Entrepreneurial History, Vol. IV:4, pp. 199-204, 1951-52.
60. Hall, Peter, Great Planning Disasters, University of California Press, 1980.
61. Pickrell, Don H., Urban Rail Transit Projects: Forecast Versus Actual Ridership and Costs,
DOT-T-91-04, U.S. Department of Transportation, Oct. 1990.
62. Norquist, John O., “Get Back on Track,” The Wall Street Journal, 21 August 2002.
98
63. Hufschmidt, Maynard M. and Gerin, Jacques, “Systematic Errors in Cost Estimates for
Public Investment Projects,” The Analysis of Public Output, Columbia University Press,
1970.
64. Healey, J. M., “Errors in Project Cost Estimates,” Indian Economic Journal, Vol. 12, July-
Sept. 1964.
65. Merrow, Edward W., Phillips, Kenneth E., and Myers, Christopher W., Understanding Cost
Growth and Performance Shortfalls in Pioneer Process Plants, The Rand Corporation, Sept.
1981.
66. Merrow, Edward W., A Quantitative Assessment of R&D Requirements for Solids Processing
Technology Process Plants, The Rand Corporation, July 1986.
67. Meyers, C. W. and Shangraw, R. F., Understanding Process Plant Schedule Slippage and
Startup Costs, The Rand Corporation, June 1986.
68. Meyers, C. W. and Dewey, M., How Management Practices Can Affect Project Outcomes:
An Exploration of the PPS Database, The Rand Corporation, Aug. 1984.
69. Summary of Independent Review Committee Findings Regarding the Woodrow Wilson
Bridge Superstructure Contract, March 1, 2002.
70. Woodrow Wilson Bridge Project Bridge Superstructure Contract (BR-3): Review of the
Engineer’s Estimate vs. the Single Bid, February 28, 2002.
71. “Revised Wilson Bridge Contract Draws a “Workable’ Low Bid,” ENR, p. 13, Nov. 18,
2002.
72. “Act Two of Woodrow Wilson Play is 28% Below Engineer Estimate,” ENR, p. 11, Feb. 24,
2003.
73. “Bids Stay Low on Wilson Bridge,” ENR, p. 14, May 12, 2003.
74. Carr, Robert I., “Cost-Estimating Principles,” Journal of Construction Engineering and
Management, ASCE, Vol. 115, No. 4, 545-551, Dec. 1989.
99
75. Estimating Guidelines, Arizona Department of Transportation, Phoenix, AZ, 1989.
76. Schexnayder, Cliff, “Construction Forum,” Practice Periodical on Structural Design and
Construction, ASCE, Vol. 6, No. 1, Feb. 2001.
77. Ascher, William, Forecasting an Appraisal for Policy-Makers and Planners, The John
Hopkins University Press, Baltimore, MD, 1978.
78. Warrack, Allan, Megaproject Decision Making Lessons and Strategies, Western Centre for
Economic Research, University of Alberta, Edmonton, Canada, No. 16/May 1993.
79. MacDonald, Doug and Mullen, Linda, CEVP Process and Results, Washington State
Department of Transportation, press and public release, June 3, 2002.
80. Reilly, John J., McBride, Michael, Dye, David, and Mansfield, Cliff, Cost Estimate
Validation Process (CEVP), guideline procedure, Washington State Department of
Transportation, January 2002.
81. The Big Dig: Key Facts about Cost, Scope, Schedule, and Management, Bechtel/Parsons
Brinckerhoff, 20 Feb. 2003.
100
101
APPENDIX A
BEST PRACTICES & GUIDELINES OF PROJECT COST ESTIMATING SURVEY Contact: J. B. Byrnes at [email protected]
The questions refer to estimates prepared immediately prior to bid letting unless otherwise stated.
1. Does your department have a dedicated estimating section or do personnel who also perform other duties prepare estimates? Are estimates prepared by design consultants?
2. What is the experience level of personnel performing estimates?
3. Is there a formal training program for new personnel in estimating?
4. Does the department, during the design phase of a project, impose a strict methodology to control the cost of construction? Yes ____ No ____.
If yes would you describe? If there is a written protocol would you provide a copy?
5. Are there standard operating procedures for all DOT estimating departments? If so, how are they distributed and used?
6. Is the same system or set of procedures used for conceptual estimates and pre-bid estimates? If not, how do they differ?
7. During project design (as the project is developed) is it a requirement that changes resulting in cost variances from the original conceptual estimate be reported and approved?
Yes ____ No ____ If yes at what level in the department is there approval authority?
8. Is there a formal review within the DOT of the estimate? Yes ____ No ____.
a. Are personnel outside of the estimating section involved in the review? Yes ___ No___.
b. Does the review include a discussion of schedule? Yes ____ No ____.
c. Does the review include a discussion of project conditions (night work, required/ necessary weekend work, etc.)? Yes ____ No ____.
d. Does the review include a discussion of site conditions affecting operations? Yes___ No___.
e. Does the review include a discussion of required sequencing of work/traffic control? Yes ____ No ____.
9. Does any project value trigger additional reviews, or a critical issues review meeting?
10. How many jobs in each of the following categories has your department executed in the last five years, and how many are planned in the next five years?
102
a. $10,000,000 - $25M: Last five years:_________ Next five years _________
b. $25M - $100M Last five years:_________ Next five years _________
c. $100M - $200M Last five years:_________ Next five years _________
d. $200M+ Last five years:_________ Next five years _________
11. How many of those jobs actually bid in each category were over the DOT estimate by 5% or more?
12. Does your state use a computer-based system for estimating, other than a supporting project tracking database? If so, what is the program; is it commercially available; and how is it used?
13. What units of measure or items of work are typically used in performing conceptual estimates? For example, is total sf of pavement used or is a more detailed estimate completed?
14. Are prices in this system updated based on bid data to develop historical average prices?
15. Is the system based on historical low bid cost data? If not, what is the basis for pricing?
16. Are neighboring state DOTs consulted when setting prices? About what issues?
17. Are contractors ever consulted about cost before a project estimate is prepared?
18. Are factors such as market conditions, anticipated time before execution, or geographic area of the state considered when preparing conceptual estimates?
19. Do you attempt to make a detailed estimate of project costs? (Detailed – means calculating production based on specific crews, equipment, and methods.)
20. Do you attempt of make a detailed estimate of major work items?
21. Do you attempt to make an estimate of project overhead costs (those project related costs that cannot be attributed to specific work items – required safety staffing, quality control staffing, temporary facilities, etc.)
22. How are mobilization and traffic control costs estimated?
23. Does your DOT ever provide materials for contractors such as aggregate, concrete, or asphalt? If so, when and why?
24. How are unique/specialty items priced? Those items for which historic costs are not available. Is there a review of the additional costs required to meet social goals?
MBE/WBE/DBE Yes ____ No ____. Project agreements. Yes ____ No ____. Noise control Yes ____ No ____.
103
Limited work times. Yes ____ No ____. Other ___________ Yes ____ No ____.
25. Is the cost of demolition identified separately? Yes ____ No ____.
26. Are the costs of detours identified separately or included with traffic control?
27. Are state estimates ever released to the general public? If so, when and at what level of detail?
28. Are all projects awarded to a single general contractor or will specialty portions, such as bridges, be awarded separately? And at what economic level?
29. Are alternative project delivery methods allowed for use by state law? If so, how are these projects estimated differently than traditional design-bid-build projects? Additionally, what methods are you using and for what size and type of projects?
30. Does your DOT use A + B bidding? If yes, how are the two values used to determine a low bidder?
31. Is life cycle cost considered at any stage of project development?
32. How much time typically lapses between the department’s estimate calculation and the bid opening?
33. What steps are taken when estimates are not close to bid prices? At what percent difference are these steps taken?
34. Is there a contingency amount incorporated into each project estimate? If so how is this amount determined?
35. For a conceptual estimate, what percentage (%) is used for engineering and contingency?
36. Are incentives used for early project completion, roadway smoothness or other items? If so, where does this money come from and is it set aside and planned for during estimating?
37. What is the time duration that contractors have for preparing their project estimates? Does this change based of the size ($) of the project?
38. How does your DOT prevent contractor bid collusion?
39. What system changes are you considering and why?
104
105
APPENDIX B
STATES WITH WEB BASED BID TABS
State Bid Tab Web Sites
CA www.dot.ca.gov/hq/esc/oe/awards/bidsum/
CO www.dot.state.co.us/bidding
GA www.dot.state.ga.us/DOT/construction/contractsadm/
ID www2.state.id.us/itd/design/contractors/contrinfo.htm
IL www.dot.state.il.us/deserv/dearch.html
KS www.ink.org/public/kdot/business/hwycont.html
MD www.sha.state.md.us/doingbiz.htm
ME www.state.me.us/mdot/project/design/bidtabarchive.htm
MN www.dot.state.mn.us/bidlet
MO www.modot.state.mo.us/bids/bidtabs.asp
MT www.mdt.state.mt.us/cntrct/contract.htm
NA doroads.nol.org/letting/past-lettings.htm
NC www.doh.dot.state.nc.us/preconstruct/highway/dsn_srvc/contracts/bidaverages/
ND www.state.nd.us/dot/pacer/bidopenrtpindex.html
NV gis.nevadadot.com/contractor/business/contall.asp
OH www.dot.state.oh.us/contract/estimating/files%20&%20info/files_and_information.htm
OR www.odot.state.or.us/techserv/progsrv/costestm/
SC www.dot.state.sc.us/doing/default.html
TN www.tdot.state.tn.us/construction/
TX www.dot.state.tx.us/business/business.htm
VA virginiadot.org/business/const/resources-bidtabs.asp
WI www.dot.state.wi.us/dbm/business.html
WV www.wvdot.com/10_contractors/10a_lettings.htm
WY dot.state.wy.us/web/business/contractor.html
106
107
APPENDIX C
UNIT PRICE FACTOR SAMPLE COST SHEET
STRUCTURAL CONCRETE, BRIDGE
UNIT PRICE FACTORS BASE PRICE = $270/CUBIC YARD CONCRETE IN PROJECT
20,000 CY+ 7,000 CY+ 2,500 CY + 600 CY+ 300 CY+
-15 0 +30 +80 +130
PROJECT LOCATION Urban Area Small Urban/City Rural/Town Distant Rural Isolated
0 +25 +50 +75 +150
TRAFFIC WATER Over Traveled Way Heavy Traffic/Congestion Over Water
+20 +10 to +80 +10 to +150 (depending on permit restrictions)
FALSEWORK HEIGHT
20’+ 40’+ 60’+ 80’+ 100’+ 120’+
0 +20 +45 +70 +100 +130
WIDENING/STAGED CONSTRUCTION 60’+ 40’+ 30’+ 20’+ 15’+ 10’+ 5’+
+10 +30 +75 +110 +150 +210 +300
OTHER FACTORS Work Schedule (permit restrictions/ limited night hours/night work/expedited schedule) Increase $20 to $400/CY
Restricted Access Increase $20 to $150/CY
Arch Construction/Variable superstructure Increase $20 to $60/CY
Rugged Terrain Increase $20 to $150/CY
Slab Construction Reduce $20 to $40/CY
108
109
APPENDIX D
SURVEY DATA
1. Does your department have a dedicated estimating section or do personnel who also perform
other duties prepare estimates? Are estimates prepared by design consultants?
No. of DOTs Response
19 Dedicated section prepares all final estimates.
1 Dedicated section prepares all final estimates as well as bid analyses.
1 Dedicated section prepares all final estimates as well as bid analyses. 8 districts, each does own estimating, decentralizing estimating to the district level
1 Dedicated section prepares all final estimates as well as construction schedules.
1 Dedicated section prepares all final estimates as well as contract prep and letting
1 Dedicated section prepares all final estimates as well as the letting documents and bid analysis.
1 Dedicated section prepares all final estimates as well as programming estimates
1 Dedicated section prepares all final estimates. Each district has an in-house estimator to assist HQ section with field investigations
11 No, designers prepare estimates, consultant estimates reviewed by PM
8 No, designers or consultants prepare final estimates
1 No, Contracts & Estimates prepares all final estimates as well as other contracting responsibilities
1 No, Contracts & Specs prepares all final estimates as well as other contracting responsibilities
1 No, designers prepare estimates, then supervisor reviews
1 No, designers prepare estimates. One reviewer reviews all estimates as requested, this is his only duty
1 No, eliminated and merged with QA this year, now perform plan review and spec check as well, get involved at problem statement
110
2. What is the experience level of personnel performing estimates?
No. of DOTs Response
2 Unknown 15 Less than 10 years 19 10-20 years 10 20-30 years 4 30+ years
3. Is there a formal training program for new personnel in estimating?
No. of DOTs Response
40 OJT only
1 NO, all DOT employees eligible to bid for estimating job with no training requirements prior to or once in job
1 Design engineer training program includes a class on estimating, and use of estimator software
1 Project estimating guide 1 Supervisor tailors training to prior experience of new personnel 1 2 manuals outline procedures and methods, one for conceptual, one for final
1 Cost estimating procedure not available outside department, provided to all engineers as guidance
1 Developed course and offered once but have not repeated in last two years 1 Developing plans review class
1 Estimating manual is under production but has not been approved yet, will outline policy and procedures for completing estimates
1 Individual one-on-one training 4. Does the department, during the design phase of a project, impose a strict methodology to
control the cost of construction? Yes ____ No ____.
If yes would you describe? If there is a written protocol would you provide a copy?
No. of DOTs Response
35 NO
1 NO, but overall construction program budget may not be exceeded
12 YES, Estimate reviewed throughout design submission process by multiple divisions
2 YES, engineer responsible to deliver design within programmed amount
111
5. Are there standard operating procedures for all DOT estimating departments? If so, how
are they distributed and used?
No. of DOTs Response
20 YES, procedures are outlined in policy manual
4 YES, computer system users guide
26 NO
6. Is the same system or set of procedures used for conceptual estimates and pre-bid
estimates? If not, how do they differ?
No. of DOTs Response
11 YES
20 NO, Rough quantity takeoff done using lane miles or SF for structures
12 NO, Conceptual Estimates done in separate section
4 NO, use highest level of detail available
1 NO, Conceptual estimates have no standard procedures
1 NO, concept based on historic project data for similar size project, but not itemized
1 NO, concept focuses on big ticket items then add % to cover all other items
7. During project design (as the project is developed) is it a requirement that changes
resulting in cost variances from the original conceptual estimate be reported and
approved? Yes ____ No ____ If
yes at what level in the department is there approval authority?
No. of DOTs Response
16 NO
24 YES, Headquarters management must approve changes
10 YES, District management responsible for own changes
112
8. Is there a formal review within the DOT of the estimate? Yes ____ No ____.
No. of DOTs Response
21 NO
16 YES
7 YES, each estimate is reviewed by a PM or supervisor
5 YES, within estimating section
1 YES, chief execs of 6 divisions w/in DOT make up an estimating committee which reviews all estimates
a. Are personnel outside of the estimating section involved in the review?
b. Does the review include a discussion of schedule?
c. Does the review include a discussion of project conditions (night work, required/
necessary weekend work, etc.)?
d. Does the review include a discussion of site conditions affecting operations?
e. Does the review include a discussion of required sequencing of work/traffic control?
Number of DOTs
a b c d e Response
31 14 12 15 15 NO
19 36 38 35 35 YES
9. Does any project value trigger additional reviews, or a critical issues review meeting?
No. of DOTs Response
37 NO
8 YES, Large complex projects over a preset $ amount
2 YES
2 Projects with extensive urban TC requirements
1 Special environmental, right of way, or social issues
113
10. How many jobs in each of the following categories has your department executed in the
last five years, and how many are planned in the next five years?
The totals for the 47 states that reported data for this item.
a. $10,000,000 - $25M: Last five years: 1825 Next five years: 1217
b. $25M - $100M Last five years: 530 Next five years: 479
c. $100M - $200M Last five years: 26 Next five years: 60
d. $200M+ Last five years: 11 Next five years: 27
11. How many of those jobs actually bid in each category were over the DOT estimate by 5%
or more?
Number % DOT 5 Year Constr.
Program Size
No. of DOTs
Total Reported Projects
No. of DOTs with complete
Data
Complete Data
Reported Projects
more than 5% over Estimate
Small (< 20 projects) 14 109 13 107 29 27.1
Medium (21-75 projects) 20 893 16 686 138 20.1
Large (76+ projects) 12 1362 9 1021 193 18.9
States not providing data 4 0 0 0 0 0
Overall 50 2364 36 1814 360 19.8
114
12. Does your state use a computer-based system for estimating, other than a supporting
project tracking database? If so, what is the program; is it commercially available; and
how is it used?
No. of DOTs Response
18 TRNS*PORT
7 TRNS*PORT and in-house software
1 TRNS*PORT and OMAN Bid-Tabs Professional
2 OMAN Bid Tabs Professional
2 OMAN Bid Tabs Professional and in-house software
1 OMAN light Estimating, in-house for asphalt resurfacing
9 In-house
1 HCSS Heavy-Bid
1 AutoCAD quantity takeoff
8 NO
13. What units of measure or items of work are typically used in performing conceptual
estimates? For example, is total sf of pavement used or is a more detailed estimate
completed?
No. of DOTs Response
31 Lane-mile/kM, SF/SM for bridges
18 Use as much detail is available
1 Engineers dicretion
14. Are prices in this system updated based on bid data to develop historical average prices?
No. of DOTs Response
5 NO
45 YES
115
15. Is the system based on historical low bid cost data? If not, what is the basis for pricing?
No. of DOTs Response
20 Low only
1 Low and Second
15 Three Lowest
11 All
2 All Except High and Low
1 Reasonable Price
16. Are neighboring state DOTs consulted when setting prices? About what issues?
No. of DOTs Response
37 NO
13 YES
17. Are contractors ever consulted about cost before a project estimate is prepared?
No. of DOTs Response
17 NO
33 YES
18. Are factors such as market conditions, anticipated time before execution, or geographic
area of the state considered when preparing conceptual estimates?
No. of DOTs Response
12 NO
38 YES
116
19. Do you attempt to make a detailed estimate of project costs? (Detailed – means
calculating production based on specific crews, equipment, and methods.)
No. of DOTs Response
36 NO
14 YES
20. Do you attempt of make a detailed estimate of major work items?
No. of DOTs Response
31 NO
19 YES
21. Do you attempt to make an estimate of project overhead costs (those project related costs
that cannot be attributed to specific work items – required safety staffing, quality control
staffing, temporary facilities, etc.)
No. of DOTs Response
39 NO
11 YES
22. How are mobilization and traffic control costs estimated?
No. of DOTs Response
20 Mobilization: Set % for all contracts
26 Mobilization: Historic average % based on project analysis
4 Mobilization: Graduated or sliding % scale
20 Traffic Control: Set %
30 Traffic Control: Individual line items
117
23. Does your DOT ever provide materials for contractors such as aggregate, concrete, or
asphalt? If so, when and why?
No. of DOTs Response
27 NO
23 YES
24. How are unique/specialty items priced? Those items for which historic costs are not
available. Is there a review of the additional costs required to meet social goals?
a. MBE/WBE/DBE Yes ____ No ____.
b. Project agreements. Yes ____ No ____.
c. Noise control Yes ____ No ____.
d. Limited work times. Yes ____ No ____.
e. Other ___________ Yes ____ No ____.
Number of DOTs
a. b. c. d. e. Response
42 35 37 20 45 NO
8 15 13 30 5 YES
25. Is the cost of demolition identified separately? Yes ____ No ____.
No. of DOTs Response
4 NO
46 YES
118
26. Are the costs of detours identified separately or included with traffic control?
No. of DOTs Response
21 Separate detour pay item
11 Included with traffic control
3 Depends on size of detour
13 Included in other estimate items
2 No response
27. Are state estimates ever released to the general public? If so, when and at what level of
detail?
No. of DOTs Response
20 Project ranging only
10 DOT estimate total announced at letting
19 Entire DOT estimate with bid tabs
1 Entire DOT estimate available at advertisement
28. Are all projects awarded to a single general contractor or will specialty portions, such as
bridges, be awarded separately? And at what economic level?
No. of DOTs Response
48 Single GC
1 Separate contracts for individual work types
1 No Response
119
29. Are alternative project delivery methods allowed for use by state law? If so, how are
these projects estimated differently than traditional design-bid-build projects?
Additionally, what methods are you using and for what size and type of projects?
No. of DOTs Response
18 NO
30 YES
2 No Response
30. Does your DOT use A + B bidding? If yes, how are the two values used to determine a
low bidder?
Number of DOTs Response
12 NO
37 YES
1 No Response
31. Is life cycle cost considered at any stage of project development?
No. of DOTs Response
9 NO
37 YES
4 No Response/Unknown
120
32. How much time typically lapses between the department’s estimate calculation and the
bid opening?
No. of DOTs Response
5 Within one week
11 One week to one month
24 One to two months
5 Two to three months
3 Three to five months
2 More than six months
33. What steps are taken when estimates are not close to bid prices? At what percent
difference are these steps taken?
Percent difference between DOT estimate and Low Bid
DOTs taking other action if percentage exceeded
No lower limit reported 26
Up to -30 1
Up to -25 2
Up to -20 2
Up to -15 2
Up to -10 5
Up to -5 2
All Projects Reviewed 8
Percentages Unknown/Unreported 2
Up to +5 3
Up to +10 31
Up to +15 2
Up to +20 2
Up to +25 2
121
34. Is there a contingency amount incorporated into each project estimate? If so how is this
amount determined?
No. of DOTs Response
27 NO
23 YES
35. For a conceptual estimate, what percentage (%) is used for engineering and contingency?
No. of DOTs Conceptual Contingency
20 Set Percentage
15 Graduated Scale
15 Engineering Judgment
36. Are incentives used for early project completion, roadway smoothness or other items? If
so, where does this money come from and is it set aside and planned for during
estimating?
No. of DOTs Response
26 Programmed in the construction estimate
9 Come from other projects that are below budget
10 Paid out of project contingency fund
5 No incentive program in place
37. What is the time duration that contractors have for preparing their project estimates?
Does this change based of the size ($) of the project?
No. of DOTs Response
30 3 to 4 weeks may extend if needed
5 3 to 4 weeks no extensions
15 4 weeks to three months
122
38. How does your DOT prevent contractor bid collusion?
No. of DOTs Response
7 No active program
11 Contractors must sign non-collusion form with bid
34 Run bid histories and perform bid analysis
7 Separate entity responsible for this
39. What system changes are you considering and why?
No. of DOTs Response
32 No planned changes
8 Implement TRNS*PORT to a greater degree
10 Other minor changes
123
APPENDIX E
WSDOT COST ESTIMATING VALIDATION PROCESS (CEVP) Washington State Department of Transportation
The information presented in this appendix is taken for the Cost Estimating Validation Process
(CEVP) Initiation Report (July 2002). The initiators of the Washington State Department of
Transportation CEVP process were:
Direction: Doug MacDonald, Secretary of Transportation
Sponsor: David Dye, Urban Corridors Administrator
Concept: John Reilly, Michael McBride, David Dye, and Cliff Mansfield
Implementation: Cliff Mansfield
WSDOT Manager: Jennifer Brown
Key consultants to the effort were:
John Reilly, Core Team Advisor, John Reilly Assoc. Int’l.
Dwight Sangrey and Bill Roberds, Risk and Uncertainty Analysis, Golder Associates.
Keith Sabol, Cost Validation, Parsons Corporation.
Art Jones, Base Cost Information, KJM Associates.
National Constructors Group.
John Reilly, Michael McBride, David Dye, and Cliff Mansfield developed the specific CEVP
guidelines in January 2002. However, it should be noted that John Reilly had been making
international presentations and leading discussions on the idea and related topics since 1997.
The primary author of the Cost Estimating Validation Process (CEVP) Initiation Report is
Dr. Keith Molenaar of the University of Colorado, but many people contributed significantly to
the report’s development. Much of the documentation contained within was developed by
WSDOT employees and consultants involved in the CEVP process. Contributors to the report
include:
Adam Brown WSDOT Technical Writer Jennifer Brown WSDOT CEVP Facilitator Jeff Carpenter WSDOT Alternative Project Delivery Manager James Diekmann University of Colorado, Construction Engineering & Management
124
David Dye WSDOT Deputy Regional Administrator Bill Elliott Engineering Manager, Urban Corridors, WSDOT Art Jones KJM Associates Keith Molenaar University of Colorado, Construction Engineering & Management Cliff Mansfield WSDOT Engineering Director, Urban Corridors Office Mike McBride McBride Consulting Travis McGrath Golder Associates, Decision and Risk Analysis Richard Rast Azimuth Group, Ltd John Reilly John Reilly Associates International William (Bill) Roberds Golder Associates, Decision and Risk Analysis Keith Sabol Parsons Corporation Dwight Sangrey Golder Associates Schaftlein, Shari WSDOT Environmental Affairs Office Greg Selstead WSDOT Programming George Xu WSDOT Environmental Affairs Office
WHAT IS CEVP?
The Cost Estimating Validation Procedure (CEVP) is a peer-level review or “due diligence”
analysis on the scope, schedule and cost estimate for transportation projects throughout the State
of Washington. The objective of the CEVP process is to evaluate the quality and completeness,
including anticipated uncertainty and variability, of the projected cost and schedule. The CVEP
process has been successfully implemented on the WSDOT Urban Corridors Mega Projects
during March through June of 2002 in a series of intensive one-week workshops. CEVP is a tool
to:
1. Evaluate the quality and completeness of the current project cost estimate;
2. Assist in developing a higher level of confidence in the estimate; and,
3. Identify major areas of variability and uncertainty in the defined project that significantly
influence the cost estimate.
The process cannot create a project estimate where none exists.
125
HOW IS CEVP ACCOMPLISHED?
CEVP involves two primary tasks: 1) a due diligence review of the project “base” cost estimate,
and 2) a modeling of uncertainty to more accurately define contingencies and allowances as
ranges of cost that can be influenced by design development or major risk and opportunity
events.
The project development team, or “Project Team”, accomplishes these two tasks with the
assistance of a “CEVP Team” of specialists. After the Project Team compiles the project data,
the CEVP Team assists the Project Team in reviewing the current project estimate. Next, the
CEVP Team removes the contingencies from the base estimate, models their uncertainty, and
provides a project cost range for the Project Team to verify and utilize for planning and
engineering throughout the development of the project.
WHAT OUTCOMES CAN BE EXPECTED?
The outcomes of the CEVP process are directly tied to the objectives and performance measures
established at the beginning of each CEVP Workshop. Outcomes include:
1. An estimate validation statement in the form of a CEVP Project Summary Sheet that
more accurately represents the project cost ranges and the uncertainty involved.
2. Findings and recommendations that allow WSDOT Project Teams and Senior
Management to better understand the basis, content, and variability of cost estimates.
3. Identification and characterization of the high risk project elements, which will enable
Project Teams to address appropriate mitigation strategies.
4. Recommendations for WSDOT management to consider in regards to the group of
projects that have been subject to CEVP review.
WHAT DATA IS NEEDED TO CONDUCT A CEVP WORKSHOP?
The Spring 2002 CEVP Mega-Project Workshops involved projects at design levels of less than
1% and more than 30%. The outcomes of these workshops were quite different. The projects
with less than 1% design provided a clear identification of major risks but were not as useful in
the cost validation objective due to the lack of information. Those projects with greater than
126
30% design development achieved excellent cost validation but many of the risks were already
being mitigated through the course of sound engineering. At a minimum the following items are
required to conduct the most rudimentary CEVP workshop:
1. Project plans and engineering documents that describe the scope, character and timeframe
of the project.
2. Project estimate that includes a summary, detailed backup of quantities and prices, and a
detailed identification of contingencies and allowances included in cost estimate.
3. Project schedule in a bar chart with precedence relationships and/or flow diagram.
4. List of major assumptions and constraints.
5. List of major risks and concerns.
The CEVP workshop appears to provide the most benefit in the range of 5% to 30% design or
somewhere between project scoping and detailed design. When the project is at less than 5%
design, there is typically not enough cost information to validate and there are often too many
alternatives to explore within the workshop time allotment. The CEVP process can be
performed at this conceptual design level, but the process should focus on risk identification and
scoping exercise rather than a cost validation exercise.
PROJECT AND CEVP TEAM MEMBER IDENTIFICATION
One of the primary strengths of the CEVP process revolves around a peer review by an
interdisciplinary team of recognized experts. There are three primary groups of individuals that
must be assembled for the CEVP workshop: the Project Team, the CEVP Team and the CEVP
Administrative Team. The importance of the CEVP Administrative Team must not be
underestimated for maximum benefit of the workshop.
Project Team
The Project Team assembles the project data, participates in the workshop, and is the ultimate
beneficiary of the CEVP workshop. Team makeup may vary greatly depending upon the nature
of the project. Table E -1 is divided into critical team members that should be present in every
CEVP exercise and other project dependent team members that can be added when the CEVP
workshops are of significant size and scope.
127
TABLE E-1 SUGGESTED CEVP PROJECT TEAM MEMBERS
Critical Team Members Project Dependent Team Members CEVP Team Leader Assistant Project Engineer Project Manager Project Development Engineer Project Engineer Program Management Engineer Design Team Leader Designers Environmental Coordinator Construction Engineer Scheduler Bridge Design Supervisor Cost Estimator* Engineering Geologist Foundations Engineer Materials Engineer Biologist Other Project and Support Office Team Members
* The project cost estimate will most likely be done under a engineer’s job description. The project estimator’s participation is absolutely essential to the CEVP process. A majority of the CEVP workshop time will be spent reviewing, validating, and reorganizing
the most current project estimate. It is critical that the lead estimator is present to answer any
questions regarding the quantities, pricing, and assumptions that were developed for the estimate.
The Project Manager is a critical member because questions of project scope will arise and
management decisions will be made throughout the workshop. Lead designers and project
engineers are also essential because they typically have the most intimate knowledge of the
design.
CEVP Team
The CEVP Team (Table E-2) has the responsibility to perform a peer evaluation or due-diligence
on the project’s estimate and scope. The CEVP Team is a core group of experts that is not
involved in the day-to-day planning of the project. It can be made up of WSDOT employees,
standing order consultants, or national experts depending upon the size and scope of the project
being explored. The CEVP Team Leader is included in both the Project Team and the CEVP
Team because this individual must perform functions on both teams, and more importantly,
create a unified working group. The Project Team and the CEVP Team must function as one
group.
128
TABLE E -2 SUGGESTED CEVP TEAM MEMBERS
Critical Team Members Project Dependent Team Members CEVP Team Leader Construction Manager Certified Cost Engineer General Contractor Decision and Risk Analyst Lead Designer Risk Modeler Environmental Economist Technical Writer Other Department Leaders
The CEVP Team has the dual functions of validating the project estimate and modeling the
risk and opportunities into a range estimate. The two most critical CEVP Team members are the
Certified Cost Engineer and the Decision and Risk Analyst. These two individuals typically lead
“cost” and “risk” breakout groups made up of both Project Team and CEVP project team
members.
Administrative Team
The Administrative Team is the final group of professionals that is essential to a successful
CEVP workshop. The administrative burden of this exercise cannot be underestimated. At a
minimum, the following roles must be accounted for:
u Facilitator,
u Technical Writer(s), and
u Logistics Planner.
Technical writers are employed to document and disseminate the workshop results in a
number of formats.
PROJECT TEAM DATA COMPILATION
Prior to the CEVP workshop, a summary of the project data must be compiled. There should be
project plans and project documents that generally describe the scope, character, and timeframe
of the project. Additionally, major internal and external factors that could influence the project
cost and scope should be identified.
Items required from the Project Team prior to the workshop for a major project:
129
1. A team organizational chart. Contact information of workshop participants.
2. Project Informational Map.
3. Project Definition Documents including scope element descriptions.
4. Summary or overview plan(s) that indicate project elements at the type, size, location, and
configuration level. This may include, concept plans, cross-sections, illustrations, public
information documents, MOU, etc.
5. If multiple alternatives are active, description of status and relationships sufficient for the
Core Team to understand options and to plan workshop priorities.
6. The basis of cost estimate including estimating assumptions and qualifications.
7. A preliminary listing of the Project Team’s issues of concern (technical, political, etc.).
8. A preliminary listing of identified risks (unresolved issues),
9. A preliminary Project Flowchart showing key tasks and interrelationships, from the
current status through completion of construction and operation and, maintenance.
10. Design and Construction Schedule, including description of how durations were
determined.
11. Current Estimates and their Basis (unit prices, parametric estimates), including an overall
“Program rollup estimate.” Please note the base year of the estimate.
12. Identify Costs associated with developing PS&E and getting to bid, including:
12.1. Engineering.
12.2. Mapping and Surveys.
12.3. Geotechnical Investigation.
12.4. Environmental Mitigation Design/Administrative Cost.
12.5. Right of Way Acquisition Services (administrative, not including cost of the
property).
12.6. Hazmat Remediation Design.
13. Identify Cost to Construct including:
13.1. Direct cost items using unit pricing if available.
13.2. Utility Relocation Cost.
13.3. Hazmat Remediation Cost.
13.4. Right of Way Cost (cost of property).
130
13.5. Environmental Mitigation cost to construct.
13.6. Construction Management.
13.7. Lump Sum Items (e.g. weigh station, maintenance facility/equipment, Park and
Ride lot).
13.8. Miscellaneous add-ons as a percent of construction (e.g. Lighting, Signing, striping,
SC&DI, etc.) with an explanation as to what items are covered and justification for
percent used.
Items required from the Project Team in the workshop for a major project:
1. Engineering drawings, models, cross-sections, and aerial maps, etc.
2. Definition/justification for construction segmenting/phasing.
3. Data used to develop designs in summary format (e.g. general descriptions of soil
conditions, not soil borings).
4. Communication related to discussion of risk issues, development of alternatives, and
stakeholder input.
5. Environmental Reports that cover contentious or risk issues.
6. Complete Cost Estimate Assessment Questionnaire.
7. Complete Cost Estimate Risk Questionnaire.
8. A description of the design criteria used for the current estimate, including a listing of
anticipated variances to design criteria and discussion of how they were accounted for in
their estimate, and any level of participation with approving agencies.
9. The schedule for construction - that was assumed in the estimate.
10. The methodology of the schedule (listing of constraints and qualifications).
11. The basis of any percentage line elements and, what is included in each.
12. The rational for contingencies used in the estimate, including, but not limited to:
12.1. Design.
12.2. Construction.
12.3. Scope elements.
13. A copy of the escalation/inflation analysis including:
13.1. Yearly cash flow schedule with tabulate annualized costs, if available.
13.2. Basis of factor used including the schedule that was assumed.
131
14. Additional materials that the Project Team feels are relevant.
The Project Team preparation is extremely comprehensive. On large and complex projects all
of the data requested should be sought. However, for smaller projects or CEVP workshops with
limited objectives, the following items can be used as a minimum:
1. Project Description
u One paragraph project description
u One-two page project description with project map
2. Project Estimate
u Summary level project estimate
u Detailed estimate backup describing unit quantities and cost basis
u Detailed identification of contingencies and allowances included in cost estimate
u Completed Estimate Basis Questionnaire
3. Project Schedule in a Bar Chart and/or Flowchart
4. List of Major Assumptions and Constraints
5. List of Major Risks and Concerns (risk questionnaire)
Depending upon the level of project development, the minimum project data described above
should be readily accessible. The CEVP workshop should not be conducted if this minimum
data is not available.
There are three items listed in the minimum requirements that the Project Team will be
required to generate prior to the CEVP workshop: the cost estimate basis questionnaire, the risk
questionnaire, and the project flowchart. The estimate basis questionnaire is essential for the
cost validation or due diligence portion of the CEVP. A project flowchart and a risk
questionnaire or list of risks and concerns are essential to risk modeling portion of the CEVP.
Cost Estimate Basis Questionnaire
The results of this Project Estimate Basis Questionnaire (Table E-3) are used by the CEVP Team
to ascertain the level of project estimate development. It gives the CEVP Team a “level of
confidence” with the project team estimate and it helps in identifying missing items in the most
current estimate.
132
TABLE E-3 ESTIMATE BASIS QUESTIONNAIRE
Questions Inclusion Comments
Has the project begun the NEPA/SEPA process? __ Yes __ No __N/A Has a preferred alternative been selected? __ Yes __ No __N/A Have any environmental mitigation measures been defined and included in the estimate?
__ Yes __ No __N/A
Has an alignment been established? __ Yes __ No __N/A Has a grade been established? __ Yes __ No __N/A Have right of way requirements been researched and priced?
__ Yes __ No __N/A
Has a typical section been established? __ Yes __ No __N/A Have the geotechnical site conditions been researched?
__ Yes __ No __N/A
Have potential geotechnical cost issues been factored into the estimate?
__ Yes __ No __N/A
Has a drainage report and concept plan been prepared? __ Yes __ No __N/A Has a noise analysis been performed? __ Yes __ No __N/A Are sound walls included in the estimate? __ Yes __ No __N/A Have retaining wall types been defined? __ Yes __ No __N/A Has a traffic analysis (modeling, HCM, LOS, etc,) been performed?
__ Yes __ No __N/A
Have pavement design reports been reviewed? __ Yes __ No __N/A Has a pavement life cycle cost analysis been performed?
__ Yes __ No __N/A
Has a preliminary construction phasing strategy been developed to help estimate traffic control, detours, temporary structures, temporary construction easements, lanes, etc.?
__ Yes __ No __N/A
Were potential detours evaluated for traffic volumes and vehicle classifications?
__ Yes __ No __N/A
Have any investigations been done in regards to potential major utility impacts?
__ Yes __ No __N/A
Has a conceptual landscaping and aesthetics plan been developed?
__ Yes __ No __N/A
Are there any design deviations that are or expected to be of concern?
__ Yes __ No __N/A
Were other projects used as metrics of comparison for the estimate? If so, please list projects.
__ Yes __ No __N/A
133
Project Flowchart
The project flowchart (Figure E-1) graphically depicts the project scope and schedule at a
summary level. The flowchart should contain the major activities, milestones, and decision
points for the project. It forms the basis for the risk model. The format of the project flowchart
can be a graphical flowchart or critical path method schedule depending upon the risk analyst’s
and team’s preference, but either format must describe the precedence relationships between
milestones and activities.
FIGURE E-1 EXAMPLE PROJECT FLOWCHART Risk Questionnaire/Issues and Concerns
The Project Team begins the CEVP risk identification and analysis through the generation of
issues and concerns. The issues and concerns are quantified in terms of their probability of
occurrence and their magnitude, but the Project Team should complete the initial identification
of the issues prior to the commencement of the CEVP workshop. In its simplest form, this can
be a bulleted list of major issues that the project team generates through a brainstorming session.
A portion of the issues generated for one project is shown in Table E-4.
134
TABLE E-4 PROJECT ISSUES AND CONCERNS
u Recent Changes on the City of Des Moines City Council
u Port of Seattle/City of SeaTac Land Trade
u South Access Road Commitment
u Part 150 Funds and Right-of-Way Acquisition
u Local Agency Funding Requirements
u Designation of Project of Statewide Significance
u Environmental Documentation
u East Marginal Way Connection
u The Clean Water Act and Stormwater Treatment Requirements
u Endangered Species Act (ESA)
u Business Relocations
u Environmental Mitigation Credit
u Magnitude of Relocations and R/W
u Local (Sensitive Area) Permit Requirements
u Noise Mitigation
u Maintenance of Traffic on I-5 During Construction
u Inflation of Real Estate Cost
u HOV Staging
u South 272 and Street Interchange
u Midway Landfill As seen in Table E-4, project the issues and concerns include political, environmental,
engineering, construction, and others.
WORKSHOP GOALS
The outcomes of the CEVP workshop can range from a simple estimate validation statement in
the form of a CEVP project summary sheet to a voluminous engineering report that documents
risk and mitigation plans for multiple project scenarios. The CEVP process can deteriorate into a
value engineering exercise or a simple design review if the CEVP Team is not consistently
reminded of the workshop objectives.
135
Possible workshop objectives may include:
u Perform a cost validation of the existing cost estimate;
u Identify major risks or opportunities which could effect the project cost; or
u Perform a cost-benefit analysis for various risk mitigation strategies and alternative
project designs.
After the CEVP Team Leader has set the goals for the workshop, the Project Team takes the
lead in the workshop and presents their project. As the Project Team presents the project, the
CEVP team should be asking questions that relate to major cost items and major risks. The
project presentation should not be rushed. The project team should focus on delivering:
u The project scope constraints stemming from political, environmental, or technical issues.
u The project opportunities and benefits that could result in cost or time savings.
PRESENTATION OF COST ESTIMATE
After the CEVP team has an adequate understanding of the project scope, the Project Team
presents the details of the estimate. The goal of the Project Team is to present the project
estimate thoroughly, starting from a summary level and ending with a detailed description of
their basis of quantities and pricing.
The estimating peer reviewers should be looking for overlaps and gaps in the estimate and use
their expert judgment to ask questions about the reasonableness of quantity and pricing
assumptions. The team should use the estimate basis questionnaire as a checklist for asking
questions during this presentation. The risk experts on the CEVP team should be looking for
design contingencies and allowances in the project cost estimate that will later be modeled as
ranges in the final CEVP workshop estimate.
The project cost estimate presentation should focus on:
u The basis of major cost item quantities and prices.
u The identification and explanation of contingencies and design allowances.
136
The outcome of the cost estimate presentation should be:
u A clear understanding of the basis for the cost estimate.
u An appropriate level of confidence for the CEVP cost validation team.
u A list of tasks and objectives for the Cost Team Breakout.
PRESENTATION OF ISSUES AND CONCERNS
The presentation of major project issues and concerns forms the basis for the CEVP risk team
breakout tasks and also serves as the primer for the uncertainty modeling.
COST VALIDATION AND RISK IDENTIFICATION
The CEVP team breaks the estimate into two major categories:
1. Base Cost Estimate: The sum of base costs excluding contingencies and risk events.
2. Risk-based Estimate: The base estimate plus contingencies and the probable cost of risk
events.
At this point in the workshop the CEVP team typically breaks into at least two teams – a Cost
Team and a Risk Team.
The primary goals are to 1) validate the project cost through peer review of the existing
estimate and 2) perform an uncertainty analysis on major project events. To accomplish these
goals, four main tasks must be accomplished:
1. The existing Project Team estimate must be validated
2. The environmental issues must be identified and assigned costs
3. The risks and opportunities must be identified and quantified
4. The uncertainty model must be designed
Identification of Contingencies and Allowances
Even when there is a firm policy on the percentage to include for allowances and contingency
(i.e. 15% for Engineering and Contingencies), the individual project teams make differing
assumptions on what line items are included in these percentages. It is essential that the all
teams have common definitions of contingencies and allowances as discussed throughout the
remainder of the workshop.
137
The contingencies must be identified and accounted for as either a “base cost” item or as a
“risk cost” item early in the cost validation and risk identification process. In general,
contingencies (undefined and as-yet unknown requirements) are included in the risk costs and
allowances (known but undefined requirements) are included in the base costs. Environmental
costs are a subset of both base and risk costs.
The Risk Team will identify risk and opportunity events at this stage of the workshop. These
risk and opportunity events must be quantified in terms of their probability of occurrence and
their magnitude.
COST TEAM BREAKOUT
The CEVP and Project Teams break out into a minimum of two groups: the Cost Team and Risk
Team. Depending upon the size and scope of the CEVP workshop, the Environmental Costing
Team may be contained in the Cost Team, or they may be a separate team. In either case, the
Cost Team’s primary objectives are to validated the existing project team estimate and organize
the CEVP estimate to support the range modeling function without overlaps or gaps between
base costs and risk or opportunity events.
Estimate Quality - Control/Validation of Unit Costs
The Cost Team begins the estimate validation process through a systematic examination of the
estimate. The initial focus of the process will be determined by the response to the Estimate
Basis Questionnaire. Primarily this is a validation of unit costs used in the project estimate. The
conceptual nature of project estimates at the scoping and environmental stages requires that the
estimates employ large parametric quantities and unit costs.
A CEVP estimate segmented into elements that support the Risk Team’s range estimate
model is now created. The CEVP process quantifies estimate contingency through a
probabilistic analysis of risk and opportunity events. Current WSDOT estimating processes
quantify contingency through a series of fixed percentages. The Cost Team must remove the
contingencies from the existing project estimate/base costs and communicate the contingencies
to Risk Team for modeling in the range estimate. For example, a 10-15% line item labeled
“contingency” may be included at the end of the existing project estimate for undefined and as-
138
yet unknown requirements at time of the estimate. The CEVP process includes contingencies in
risk cost – not in the base costs. The Cost Team focuses on the base costs.
The CEVP process includes the majority of design allowances (known but undefined
requirements) in the base costs. Design allowances involve items that the project team is certain
will be in the final project scope, but has not designed to a point that they can be quantified. The
cost for these allowances is typically based on a percentage of historical costs. An example of a
design allowance is a lump sum amount that is included for landscaping, which has not been
designed but will be required in the final scope. The Cost Team should identify these allowances
and validate the reasonableness of their costs.
The final major task of the Cost Team is to validate the amounts and proper application of the
markups added to the end of the estimate. Common estimate markups or add-ons include tax,
engineering and construction allowance, escalation, and bonds.
ENVIRONMENTAL COST TEAM BREAKOUT
The task of the Environmental Cost Team is to define and quantify the environmental mitigation
costs that are associated with the project cost. This information may not be required in all CEVP
workshops. The motivation for detailing these costs is to assess the impact that environmental
mitigation issues and resource agency requests have on project cost. The information is
extremely useful for negotiating with resource agencies because the costs of their requirements
can now be identified easily through the CEVP process.
RISK TEAM BREAKOUT
The Risk Team’s goal is to model the uncertainty in the project cost and schedule. The
objectives of the breakout session are 1) to assess the project uncertainties and 2) to evaluate the
related consequences. This information will be the data for a structured model of project
uncertainty used to develop a range cost estimate.
Uncertainties are often difficult to identify and even harder to quantify. This step requires a
multi-disciplinary team for accurate results. The identification and quantification of
139
uncertainties requires a balance of project knowledge, program knowledge, risk analysis
expertise, cost estimating expertise, and objectivity.
Project cost and schedule uncertainty can be divided into two categories: risk events and
opportunity events. Risk events are defined as potentially adverse events that negatively affect
the defined project. Opportunity events are potentially beneficial events that positively affect the
project. After the uncertainties are identified, they must be quantified. The Risk Team
quantifies uncertainty in terms of both likelihood and magnitude of occurrence. An event’s
likelihood and magnitude constitute the data required to generate the cost range model.
Risks and Opportunities
The Risk Team should start its analysis with the Project Team’s list of issues and concerns. Two
key issues must be kept in mind during the risk identification step are: 1) all risks and
opportunities should be considered and 2) all risks and opportunities must be independent. Once
identified, the consequences or “impact” of the uncertainties must be quantified. Quantification
involves an assessment of the likelihood and magnitude of occurrence. Likelihood can be
expressed directly (0-100%) or initially adjectivally as:
Category Very likely Likely Unlikely Very unlikely
range in probability 50-100% 10-50% 1-10% <1%
An example risk summary is shown in Table E-5.
Before a detailed quantification is made, an initial quantification should be done to filter out
minor or inconsequential risks using an order-of-magnitude assessment of conditional expected
consequences. The filtering is accomplished by creating baseline criteria for the assessment and
inclusion of risks and opportunities. Different values (for example, > 1% and > $ 1 million or 1
month) based on the cost of the project and the sensitivity of the risk models will be used to
accomplish the filtering. The inconsequential risks need not be neglected. They can be grouped
into a category of “other” and treated as one risk event. If workshop time and budget allows, an
attempt at capturing possible risk mitigation plans should be made.
140
TABLE E-5 EXAMPLE RISK SUMMARY TABLE FROM SR 509 CEVP
Potential Problem Likelihood Additional Cost ($M)
Delay (months)
T1. Storm water collection and treatment 40% 27 (50%) -- T2. Temp. Water Pollution Control/Compliance 50% 1.5 1 T3. ESA 10% 1 3 T4. Marine View Drive Bridge 25% -- 3 T5. Permitting 30% -- 6 T6. ROD 25% -- 6 T7. FAA Approvals 25% 5 6 T8. I-509 ROW 15% -- 6 T9. I-5 ROW 15% -- 6 T10. Utility and Drainage Easements NA <1 <1 T11. Property Development 15% 8 -- T12. Land Transfer NA <1 <1 T13. Utilities 50% 3 12 T14. Relinquishment 25% 5 -- T15. Seismic Criteria 50% 9 1 T16. 516 Structure 10% 6.2 12 T17. Water Tank Wall 10% 7 3 T18. Traffic Control / Staging 25% 10 --
MODELING TEAM BREAKOUT
The Modeling Team breakout process will vary significantly on the basis of CEVP workshop
objectives. The goal of the Modeling Team is to generate a range cost estimate that includes the
base cost estimate and the probable cost of risk and opportunity events. The objectives are to 1)
allocate the base costs accurately into the risk-based model and 2) model the risk and opportunity
events in a probabilistic fashion.
The first task for the Modeling Team is to build a spreadsheet model that represents the
elements of the flowchart and coincides with the cost groupings from the Cost Team. WSDOT
141
was use @Risk software. @Risk is one of a number of commercially available Monte Carlo
simulation software packages.
Construct Range Cost Model
The modeling team constructs the range cost model. WSDOT has always used a consultant to
handle the modeling, as the WSDOT CEVP program grows, the modeling may be done with
WSDOT staff. The tools to the build the models are commercially available, but the skills of
probabilistic modeling are developed over years of training and experience.
WSDOT conducted a first order analysis was using Monte Carlo simulation software to
generate the range cost models. A first order analysis is defined as a risk assessment technique
that incorporates contingency and risk but does not model variability and correlation of base
costs. In other words, the individual line items in the base cost estimate are dealt with
deterministically and independently. Only the risk and opportunity events are modeled
stochastically. If an individual line item in the estimate contains a large variation in quantity or
unit cost, the modeler may choose to include it as a risk or opportunity event rather than a base
costs. Monte Carlo simulation is a risk analysis technique that incorporates multiple simulations
of outcomes with the variability of individual elements to produce a range of potential results.
The results can be presented in a number of fashions. Table E-6 is a sample tabular
presentation of the simulation results formatted as a summary reference. Figure E-2 is a
graphical presentation of the information that was commonly used in the executive summary of
the CEVP Workshop reports.
SUMMARY OF COST ELEMENTS
Concurrently with the range model construction and the preparation of risk element summary,
the Cost Team should develop a cost summary table and document all of their assumptions and
clarifications.
142
TABLE E-6 TABULAR PRESENTATION OF RESULTS FROM SR 90 CEVP
Risk Profile – Partial Funding Scenario
Statistics – The percentages below indicate the probability that the Project will cost less than the Estimate amount shown and the probability that it can be completed in less time than the Overall Project Duration shown - for each percentage.
Estimate in 2002 Dollars
($M)
Estimate in “year of
expenditure” dollars ($M)
Overall Project
Duration
(months)
CEVP Base Cost estimate $645 $755 125 50% $668 $791 136 80% $683 $821 143 90% $693 $837 148 For example, “…there is a 90% probability that the Cost will be less than $693 million.”
FIGURE E-2 GRAPHICAL PRESENTATION OF SIMULATION RESULTS SHOWING RANGE OF PROBABLE COSTS Presentation of CEVP Results
An oral presentation of the CEVP results at the workshop allows for immediate feedback from
the Project and CEVP Teams. The oral presentation objective is to provide an overview of the
results for the Project Team and WSDOT upper management.
143
CEVP Workshop Report
The CEVP Workshop Report is the archival document that presents the findings of the
workshop. Two primary CEVP report formats are generated by WSDOT. The first is a one-
page summary format for WSDOT executive and public use, Figure E-3. The second is the full
CEVP Workshop Report intended for Project Team and public use. The one-page Summary
format is generated as a tool to communicate the overall results to WSDOT management, State
Legislators, and the general public. The purpose of the One-Page Summary is to provide a single
resource for programming and public communication.
The critical information for the CEVP One-Page Summary Report is:
u Brief Project Description
u Design and Construction Schedule
u CEVP Results in Graphical Format (Probability Density Function)
u CEVP Results in Projected Cost Range (10th., 50th.,and 90th. percentile confidence levels)
u Benefits of the Project
u Risk Issues that Could Impact Project Cost or Schedule
u Level of Project Design
The full CEVP workshop final report represents a “snapshot” of the project scope and results.
It is likely that many alternatives will be generated after the initial workshop but the integrity of
the original workshop results must be preserved as a baseline for generating these alternatives.
The CEVP workshop generates a review of the existing project estimate, produces a new range
cost estimate, and provides suggestions for mitigating potential risks or capitalizing on
substantial opportunities. The project team must validate the results generated in the workshop.
The Project Team should begin to create a plan to mitigate risks that have been identified in the
CEVP workshop.
GENERATION OF ALTERNATIVES
In addition to providing a cost estimate validation statement, the CEVP workshop provides a
wealth of baseline data that can be explored to generate engineering and project scooping
alternatives. If used correctly, the baseline data produced in the initial CEVP workshop will
provide better information for engineering and political decisions.
144
FIGURE E-3 GRAPHICAL PRESENTATION OF SIMULATION RESULTS SHOWING RANGE OF PROBABLE COSTS
The SR 99 Alaskan Way Viaduct CEVP workshop provides an excellent example of how the
data from the initial workshop can be used to model alternatives for engineering decision-making
purposes. Due to the low level of design development and workshop time constraints, the initial
145
SR 99 Alaskan Way Viaduct CEVP Team modeled the project as one fully funded project using
a hybrid of construction methods (tunnels, bridges, and seawalls). The workshop served to
validate the existing estimate on the project and even created unit quantities and cost where none
previously existed. However, the final estimate did not reflect one optimal solution. After the
initial CEVP Workshop Report was complete (in draft form), the CEVP and Project Teams met
again to generate a series of alternative project estimates based on a number of designs and
funding scenarios. In the end, the CEVP process generated nine alternative range cost estimates
with separate associated lists of risks and concerns to be considered in design development. The
generation of alternatives can prove to be very beneficial.
The CEVP process is still being developed by WSDOT. It is recognized that CEVP
summaries are not a warranty that estimates are perfect, as you only know the final cost when a
project is finally completed. But risk areas that could significantly increase project costs can be
communicated fairly to the public. Additionally, early identification of a risk area creates
management opportunities to minimize the potential of projects costs associated with some of the
risk issues.
146
147
APPENDIX F
CALTRANS CONSTRUCTION STATISTICS California Department of Transportation
The California Department of Transportation, Division of Engineering Services publishes
Construction Statistics Based on Bid Openings each year, Figures E-1 through E-4.
FIGURE F-1 CONTENTS PAGE, CALTRANS CONSTRUCTION STATISTICS FOR 2001
148
FIGURE F-2 BRIDGE SQUARE FOOT COST SUMMARY CALTRANS CONSTRUCTION STATISTICS 2001
149
FIGURE F-3 WEIGHTED AVG UNIT PRICES CALTRANS CONSTRUCTION STATISTICS 2001
150
FIGURE F-4 DECK AREA, CALTRANS CONSTRUCTION STATISTICS 2001
151
Caltrans then analyses their bid data and prepares guidance sheets to help estimators properly
apply units prices when creating estimates, Figures F-5 through F-8.
FIGURE F-5 CALTRAN’S BRIDGE ITEM PRICE GUIDANCE SHEET, PAGE 1
152
FIGURE F-6 CALTRAN’S BRIDGE ITEM PRICE GUIDANCE SHEET, PAGE 2
153
FIGURE F-7 CALTRAN’S BRIDGE ITEM PRICES
154
FIGURE F-8 CALTRAN’S DETAILED ANALYSIS OF STRUCTURAL CONCRETE, BRIDGE