project activities and tasks - the enterprise program ... · pdf file6/15/2010 7 graphic...

9
6/15/2010 1 Project Activities and Tasks Project Activities and Tasks Module 4 Module Objectives Module Objectives After completing the Project Activities and Task Section, ii ill b bl participants will be able to: y learn the difference between an activity and a task. y define Work Breakdown Structure (WBS). y describe the difference between summary and detailed (c)2010 Competitive Advantage activities. y describe the different formatting approaches for a WBS. 5-2 2

Upload: dongoc

Post on 02-Feb-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Activities and Tasks - The Enterprise Program ... · PDF file6/15/2010 7 Graphic Graphic --WBS WBS --LevelsLevels Level 1 WBS Chunkof Level 2 Work Deliverable Phase Element

6/15/2010

1

Project Activities and TasksProject Activities and Tasks

Module 4

Module ObjectivesModule Objectives

After completing the Project Activities and Task Section,

i i ill b bl participants will be able to:

learn the difference between an activity and a task.

define Work Breakdown Structure (WBS).

describe the difference between summary and detailed

(c)2010 Competitive Advantage

activities.

describe the different formatting approaches for a WBS.

5-22

Page 2: Project Activities and Tasks - The Enterprise Program ... · PDF file6/15/2010 7 Graphic Graphic --WBS WBS --LevelsLevels Level 1 WBS Chunkof Level 2 Work Deliverable Phase Element

6/15/2010

2

Activities versus TasksActivities versus Tasks

An activity is generally a higher level of work or an element of the project. In some organizations, the term “activity” is used to describe a particular function such as design activity, purchasing activity, etc. If this is true of your organization, it may be more appropriate and less confusing to use the term “tasks”.

Tasks and subtasks describe what needs to be accomplished in the project. This is the actual work to be done by the

(c)2010 Competitive Advantage

people supporting the project. Time, cost, and resources can be assigned at the task level.

5-3A3

Tasks (or Activities)Tasks (or Activities)

Represent action or work and should begin with a VERBwith a VERB

Assign resources - accountability and responsibility

Determine duration and work

Identify cost

(c)2010 Competitive Advantage

Identify cost

Track progress

5-3B4

Page 3: Project Activities and Tasks - The Enterprise Program ... · PDF file6/15/2010 7 Graphic Graphic --WBS WBS --LevelsLevels Level 1 WBS Chunkof Level 2 Work Deliverable Phase Element

6/15/2010

3

Formatting InformationFormatting Information

After the Statement of Work has been completed, the next step is to identify all the elements (activities), tasks, and subtasks associated with the project.

The initial identification of tasks is a draft of what the project team thinks needs to be accomplished. When more structure is added to the Project Plan, the team may identify additional tasks, change tasks, or delete

(c)2010 Competitive Advantage

tasks altogether.

5-4A5

Work Breakdown Structure Work Breakdown Structure (WBS)(WBS)

Graphically depicts the elements and tasks to be

l d i hi j h d i d j completed within a project to meet the desired project

goals and objectives.

The Work Breakdown Structure (WBS):

shows the different levels of a project.

(c)2010 Competitive Advantage

does not take into consideration order of tasks or time.

can be presented in several different formats.

5-4B6

Page 4: Project Activities and Tasks - The Enterprise Program ... · PDF file6/15/2010 7 Graphic Graphic --WBS WBS --LevelsLevels Level 1 WBS Chunkof Level 2 Work Deliverable Phase Element

6/15/2010

4

Work Breakdown Structure Work Breakdown Structure (WBS)(WBS)

Phase Element Segment Deliverable

Level I

Level II

T k

Project

(c)2010 Competitive Advantage

Level III

Tasks

Subtasks

Subtasks

5-57

Work Breakdown Structure Work Breakdown Structure ApproachesApproaches

Top Down Approach

Bottom Up Approach

Outlining Format

Work Order or Numeric Format

(c)2010 Competitive Advantage 5-6A8

Page 5: Project Activities and Tasks - The Enterprise Program ... · PDF file6/15/2010 7 Graphic Graphic --WBS WBS --LevelsLevels Level 1 WBS Chunkof Level 2 Work Deliverable Phase Element

6/15/2010

5

Top Down FormatTop Down FormatIn the top down format, it is assumed that the project team

knows the major elements. The team identifies the tasks and knows the major elements. The team identifies the tasks and subtasks associated with each element. For example, building a garage would include:

Build a Garage

Administration Cement Garage ElectricityProject 

ManagementPreliminary

9(c)2010 Competitive Advantage

Bottom Up FormatBottom Up Format

The bottom up format is useful when the project team is

able to determine the tasks and subtasks that need to

be completed. Once this step is completed, then

several common elements can be defined and the tasks

grouped by elements.

10(c)2010 Competitive Advantage

Page 6: Project Activities and Tasks - The Enterprise Program ... · PDF file6/15/2010 7 Graphic Graphic --WBS WBS --LevelsLevels Level 1 WBS Chunkof Level 2 Work Deliverable Phase Element

6/15/2010

6

Bottom Up Format ExampleBottom Up Format ExampleBuild a Garage

Administration Cement Garage ElectricityProject 

ManagementPreliminary

♦ Get permit ♦ Developlayout

♦ Prepare &level  area

♦ Routeelectrical

♦ Install theswitches

♦ Track costs

♦ Obtainsignedcontract

♦ Developblueprint ofgarage

♦ Dig footingsfor thegarage

♦ Rough inthe walls

♦ Getinspection(electrical)

♦ Monitorhoursworked

♦ Contactmaterialsuppliers

♦ Post permit ♦ Lay formsin ground

♦ Completewith texturesheathing

♦ Install theelectricity &outlets

♦ Prepareweekly cashflow report

♦ Developquote andestimate

♦ Getinspection(cement)

♦ Hang thegarage door

♦ Connectelectricity tothe door

♦ Preparescheduletrackingreport

♦ Contact ♦ Pour the ♦ Hang the ♦ Prepare♦ Contactinspector

♦ Pour thecement

♦ Hang the36” door

♦ Prepareresourcetrackingreport

♦ Set trusses♦ Get final

inspection♦ Sheath the

roof &shingle

♦ Prepareinvoice

♦ Getinspection

♦ Paint thegarage

11(c)2010 Competitive Advantage

Outline FormatOutline FormatThis format is most common in many project

management software packages. This method is often used in management consulting and engineering projects. The number scheme is usually determined by your organization.

I. Project TitleA. Element I

A 1 Complete task 1A.1 Complete task 1A.2 Complete task 2

A.2.1 Complete subtask 2.1A.2.2 Complete subtask 2.2

12(c)2010 Competitive Advantage

Page 7: Project Activities and Tasks - The Enterprise Program ... · PDF file6/15/2010 7 Graphic Graphic --WBS WBS --LevelsLevels Level 1 WBS Chunkof Level 2 Work Deliverable Phase Element

6/15/2010

7

Graphic Graphic -- WBS WBS -- LevelsLevels

WBSLevel 1

Chunk ofWork Deliverable Phase ElementLevel 2

SUMMARY ACTIVITIES

Level 3

Detailed Activities

13(c)2010 Competitive Advantage

Outlining Format Outlining Format -- ExampleExampleID Task Name1 1 Preliminary2 1.1 Develop Layout3 1.2 Develop Blueprint of Garage3 e e op uep o Ga age4 1.3 Post the Permit5 2 Administration6 2.1 Develop Quote and Estimate7 2.2 Get Permit8 2.3 Obtain Signed Contract9 2.4 Contact Material Supplier

10 2.5 Contact Inspector11 3 Cement12 3.1 Prepare & Level Area13 3.2 Dig Footings for Garage14 3.3 Lay Forms in Ground3 3 ay o s G ou d15 3.4 Get Inspection (Cement)16 3.5 Pour the Cement17 4 Garage18 4.1 Route Electrical Conduit19 4.2 Rough in Walls20 4.3 Complete with Texture Sheathing21 4.4 Set Trusses22 4.5 Sheath Roof & Shingle

14(c)2010 Competitive Advantage

Page 8: Project Activities and Tasks - The Enterprise Program ... · PDF file6/15/2010 7 Graphic Graphic --WBS WBS --LevelsLevels Level 1 WBS Chunkof Level 2 Work Deliverable Phase Element

6/15/2010

8

Sample WBS in MS ProjectSample WBS in MS Project

(c)2010 Competitive Advantage 15

Project Exercise: Work Project Exercise: Work Breakdown StructureBreakdown Structure

Instructions:brainstorm a list of tasks and subtasksalthough your projects may be very detailed, do not go below Level III; develop at a macro leveluse the Top Down or Bottom Up Approach to develop your WBSuse the next page to develop your draftt f fi l WBS t fli h t

(c)2010 Competitive Advantage

transfer your final WBS to flipchart paperTime Limit: 60 minutes

5-1216

Page 9: Project Activities and Tasks - The Enterprise Program ... · PDF file6/15/2010 7 Graphic Graphic --WBS WBS --LevelsLevels Level 1 WBS Chunkof Level 2 Work Deliverable Phase Element

6/15/2010

9

Project Exercise: WBS FormProject Exercise: WBS Form

(c)2010 Competitive Advantage5-13

17

Module Module ReviewReview

This section covered the following topics:activitiestasks and subtaskselementsWork Breakdown Structure (WBS)Top Down WBSBottom Up WBS

(c)2010 Competitive Advantage

Outline WBS

5-1418