progress report on magnet m1 desportes...h. desportes difficulties previously reported. on the...
TRANSCRIPT
-
"
. '
)
)
.·
CERN/EF/ EHS-CC/78-57
9 June 1978
PROGRESS REPORT ON MAGNET M1
H. DESPORTES
Difficulties previously reported . on the conductor fabri-, . . cation and on the plastic rings are getting technically solved
but have resulted in considerable delays affecting the whole -
project. Delay on the conductor deliverr has now reached 5 months
and this time cannot be completely recovered during the magnet
fabrication. The overall schedule has been re-examined for possjblc
gains and a new version is attached to the present report. Delivery
of the first coi 1 is s che dule.d on 30 · March 1979 and of the second coi 1
on 30 June 1979. These dates do not leave any freeway for new
supplier delays or for incidents during the fabrication and tests.
CONDUCTOR
At the time of the previous CC meeting, the technical
problems with the conductor soldering appeared to be solved and the
long length production was just starting. Inspection of the first
long length showed again the poor quality experienced previously
and this length was rejected. Development work was resumed with the attendance of two engineers from SACLAY and finally enc.led up
with a fully satisfactpry process. Improvements were obtained by
proper cleaning and degreasing of the copper and of the composite,
by ru~ning the two components into a solder bath, by a better
control of the heating temperatures and by other small changes on -
the line.
I e 1 /
-
. , .
- 2 -
The first acceptable long length was run on May 26.
This length is just been delivered to SACLAY, so that the windin~ is now ready to start.
Two other lengths have been finished since then and are
being shipped. The other lengths should follow at ari adequate puce
provided all the remaining conductor components are ready in time .
SUPPORT RINGS
The design and development work of the plastic rings at
SNIAS have progressed somewhat. Stress analysis has been carriL
out to enable the mechanical structure to be completely defined.
The overall design of the rings, clamp plates and bolting is
completed. The glass fiber weaving pattern of the ring itself·
remains to be decided. This needed some preliminary tests on
unifilamentary composites which could not . be prepared until the
required S-glass was received. All the materials are now on hand
and first tests have been carried out : thermal contraction has
beeri measured both at RUTHERFORD and at GRENOBLE. Inter layer
shear stress measurements are under way at SNIAS. From the results,
the fiber glass structure will be decided and sample plates of tl1e
actual thickness will be made in order to carry out the con1plctc
test program decided upon.
Taking into account the time necessary £or this program
and for the fabrication of the rings, a revised delivery date has
been given by SNIAS : •first !ing at the 'end of November and second
two months later.
. . . I
-
..
)
- 3 -
DOME
After several discussions with CERN, the dome de s i pn
has been completed. This is now on tendering. It is the last
major part of the cryostat to be · ordered.
INSTRUMENTATION
Discussions have taken place with CERN in order to \
specify all the measuring probes which have to be installed within
the magnet and cryostat : temperatures, strain gauges, voltage
taps, etc~ A document will be issued shortly with th~ final speci-
fications as well as interfaces and wiring codes in accordance with EHS standards.
Equipments for the separate tests of the coils at SACLAY
have also been discussed. CERN proposes to bring to SACLAY the
power .supply and protection ~ircuit as a whole, the system hnving
been already tested together at CERN. For the reading and recor-
ding of the numerous measurements, CERN also has available a d11tn
handling system including a 200-channel scanner, a digital voltn1c-
ter, small computcir with read-outs, etc. SACLAY will have to
provide a terminal board t6 interconnect this system with tl1e
magnet instrumentation.
An engineer of CERN has been appointed for the instal-
lation of CERN parts of these equipments and to make the liaison
with SACLAY.
MISCEALLANEOUS WORKS
Practical work has been devoted to perfect the winJing
line and toolings.
Experimental work and tests of internancakc connections
ar still going on, as well as performance tests of the con-
ductor. A small model -coil has just been woun~ in order to test
the stability behaviour of the conductor in similar cooling nnd
field environment as in EHS. This test will be carried out soon.
-
~ ~ ~
("\
i ~
~ ~ :t::.
~ • \..
~ ~ , ,, v
L "')
"' I I
1::::-
. -~ -~- . .c ~
\J \ ~ ~r--
-'.':>---- - · -
').
~ "3 "o!-i ...
-\... ~ \,\ "' ~
I
\..I '[ >
r ~ ...
>... ..._ ~ ~ 'v ' · ~
.,)
" ~ ~ f"b -·
"' -~ ~ · _"'I ~ . ....., " -~ ~. - . ~ -~· ......
'