progress report on magnet m1 desportes...h. desportes difficulties previously reported. on the...

4
" . ' ) ) CER N /EF/ E HS-CC/78-57 9 June 1978 PROGRESS REPORT ON MAGNET M1 H. DESPORTES Difficulties previously reported . on the conductor fabri- , . . cation and on the plastic rings are getting technically solved but have resulted in considerable delays affecting the whole - project. Delay on the conductor deliverr has now reached 5 months and this time cannot be completely recovered during the magnet fabrication. The overall schedule has been re-examined for possjblc gains and a new version is attached to the present report. Delivery of the first coi 1 is s che dule.d on 30 · March 1979 and of the second coi 1 on 30 June 1979. These dates do not leave any freeway for new supplier delays or for incidents during the fabrication and tests. CONDUCTOR At the time of the previous CC meeting, the technical problems with the conductor soldering appeared to be solved and the long length production was just starting. Inspection of the first long length showed again the poor quality experienced previously and this length was rejected. Development work was resumed with the attendance of two engineers from SACLAY and finally enc.led up with a fully satisfactpry process. Improvements were obtained by proper cleaning and degreasing of the copper and of the composite, by the two components into a solder bath, by a better control of the heating temperatures and by other small changes on - the line. I e 1 /

Upload: others

Post on 28-Jan-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

  • "

    . '

    )

    )

    CERN/EF/ EHS-CC/78-57

    9 June 1978

    PROGRESS REPORT ON MAGNET M1

    H. DESPORTES

    Difficulties previously reported . on the conductor fabri-, . . cation and on the plastic rings are getting technically solved

    but have resulted in considerable delays affecting the whole -

    project. Delay on the conductor deliverr has now reached 5 months

    and this time cannot be completely recovered during the magnet

    fabrication. The overall schedule has been re-examined for possjblc

    gains and a new version is attached to the present report. Delivery

    of the first coi 1 is s che dule.d on 30 · March 1979 and of the second coi 1

    on 30 June 1979. These dates do not leave any freeway for new

    supplier delays or for incidents during the fabrication and tests.

    CONDUCTOR

    At the time of the previous CC meeting, the technical

    problems with the conductor soldering appeared to be solved and the

    long length production was just starting. Inspection of the first

    long length showed again the poor quality experienced previously

    and this length was rejected. Development work was resumed with the attendance of two engineers from SACLAY and finally enc.led up

    with a fully satisfactpry process. Improvements were obtained by

    proper cleaning and degreasing of the copper and of the composite,

    by ru~ning the two components into a solder bath, by a better

    control of the heating temperatures and by other small changes on -

    the line.

    I e 1 /

  • . , .

    - 2 -

    The first acceptable long length was run on May 26.

    This length is just been delivered to SACLAY, so that the windin~ is now ready to start.

    Two other lengths have been finished since then and are

    being shipped. The other lengths should follow at ari adequate puce

    provided all the remaining conductor components are ready in time .

    SUPPORT RINGS

    The design and development work of the plastic rings at

    SNIAS have progressed somewhat. Stress analysis has been carriL

    out to enable the mechanical structure to be completely defined.

    The overall design of the rings, clamp plates and bolting is

    completed. The glass fiber weaving pattern of the ring itself·

    remains to be decided. This needed some preliminary tests on

    unifilamentary composites which could not . be prepared until the

    required S-glass was received. All the materials are now on hand

    and first tests have been carried out : thermal contraction has

    beeri measured both at RUTHERFORD and at GRENOBLE. Inter layer

    shear stress measurements are under way at SNIAS. From the results,

    the fiber glass structure will be decided and sample plates of tl1e

    actual thickness will be made in order to carry out the con1plctc

    test program decided upon.

    Taking into account the time necessary £or this program

    and for the fabrication of the rings, a revised delivery date has

    been given by SNIAS : •first !ing at the 'end of November and second

    two months later.

    . . . I

  • ..

    )

    - 3 -

    DOME

    After several discussions with CERN, the dome de s i pn

    has been completed. This is now on tendering. It is the last

    major part of the cryostat to be · ordered.

    INSTRUMENTATION

    Discussions have taken place with CERN in order to \

    specify all the measuring probes which have to be installed within

    the magnet and cryostat : temperatures, strain gauges, voltage

    taps, etc~ A document will be issued shortly with th~ final speci-

    fications as well as interfaces and wiring codes in accordance with EHS standards.

    Equipments for the separate tests of the coils at SACLAY

    have also been discussed. CERN proposes to bring to SACLAY the

    power .supply and protection ~ircuit as a whole, the system hnving

    been already tested together at CERN. For the reading and recor-

    ding of the numerous measurements, CERN also has available a d11tn

    handling system including a 200-channel scanner, a digital voltn1c-

    ter, small computcir with read-outs, etc. SACLAY will have to

    provide a terminal board t6 interconnect this system with tl1e

    magnet instrumentation.

    An engineer of CERN has been appointed for the instal-

    lation of CERN parts of these equipments and to make the liaison

    with SACLAY.

    MISCEALLANEOUS WORKS

    Practical work has been devoted to perfect the winJing

    line and toolings.

    Experimental work and tests of internancakc connections

    ar still going on, as well as performance tests of the con-

    ductor. A small model -coil has just been woun~ in order to test

    the stability behaviour of the conductor in similar cooling nnd

    field environment as in EHS. This test will be carried out soon.

  • ~ ~ ~

    ("\

    i ~

    ~ ~ :t::.

    ~ • \..

    ~ ~ , ,, v

    L "')

    "' I I

    1::::-

    . -~ -~- . .c ~

    \J \ ~ ~r--

    -'.':>---- - · -

    ').

    ~ "3 "o!-i ...

    -\... ~ \,\ "' ~

    I

    \..I '[ >

    r ~ ...

    >... ..._ ~ ~ 'v ' · ~

    .,)

    " ~ ~ f"b -·

    "' -~ ~ · _"'I ~ . ....., " -~ ~. - . ~ -~· ......

    '