profound it park - welcome to...
TRANSCRIPT
ENVIRONMENTAL MANAGEMENT PLAN
PROFOUND IT PARK
(IT park) Sy. No. 66/2, Raidurgam village,
Serilingampally mandal,
Rangareddy district,
Telangana
Prepared by
Flat no: 7-3, Dhruvatara Apartments, Amrutha Estates, Somajiguda,
Hyderabad - 500 082; Ph: 040- 23314270 /271.
Environmental Management Plan PROFOUND IT PARK IT park
1
1.0 INTRODUCTION Shri P. Sarat babu has proposed to construct a IT park under the banner "PROFOUND IT
PARK" at Sy. No. 66/2, Raidurgam village, Serilingampally mandal, Rangareddy district,
Telangana
This report furnishes the details of location of Site, Description of the project, and
Environmental Management Plan to be followed during the Construction and Operation of
the IT park.
2.0 DETAILS ABOUT THE PROJECT SITE
1. The location of the proposed cconstruction of IT park is at Sy. No. 66/2, Raidurgam
village, Serilingampally mandal, Rangareddy district, Telangana
2. The project site for the proposed IT park is located in prime commercial activity area.
3. The site of the proposed IT park is surrounded by the following in all the directions.
North – road
East – private building
South – open land
West – private building 4. The topography of the site is more or less flat without many undulations.
5. Water required for the proposed IT park will be met from Municipality supply and
ground water resources.
6. Total land acquired for the IT park is 3.75 acres (15,198.35 Sq.m.). Net site area after
deducting road effected area 3.67 acres (14,867.30 Sq.m).
7. Borabanda and Hitech city Railway station is situated at a distance of 5 Kms. from the
proposed site.
8. Topographical map showing the location of the Project site is shown in Fig 1.1
Environmental Management Plan PROFOUND IT PARK IT park
2
TOPOGRAPHICAL MAP SHOWING THE LOCATION OF THE PROJECT SITE
Proposed Project site
Environmental Management Plan PROFOUND IT PARK IT park
3 3
3.0 DETAILS OF THE PROJECT
The following are the brief details of the proposed IT park
S.No Details Description
i. Total Land Area Area acquired – 3.75 acres (15,198.35 Sq. m.)
Net area after road widening – 3.67 acres (14,867.30
Sq.m)
ii. Survey nos. Sy. No. 66/2
iii. Expected project cost Rs. 300 Crores
iv. Total built-up area Total Built up area – 1,36,096.02 Sq.m
(which includes a two towers Tower A – 2 cellar + Ground + 3 parking floors + 13
upper floors
Tower B – 1 cellar + Ground + 3 parking floors + 10
upper floors)
v. Built up area statement Total Built up area – 1,36,096.02 Sq.m
Kindly refer to Table 1.1
vi. Water Requirement Total water demand is about 17 KLD during
Construction of IT park & 390 KLD during the
operation of IT park (fresh water – 123 KLD, recycled
water – 267 KLD)
Source of supply : Municipal supply
vii. Waste water generation 279 KLD
viii. STP capacity 300 KLD
ix. Power requirement 8000 kVa (Maximum peak demand)
x. Solid waste generation During operational phase:
Municipal solid waste : 1.8 MT/day
xi. Connectivity The site is well connected by Old Mumbai Highway
xii. Additional facilities DG Sets
Sewage Treatment Plant
Environmental Management Plan PROFOUND IT PARK IT park
4 4
S.No Details Description
xiii. Back up supply 10 x 800 kVA
xiv. Parking facilities Total parking area : 53,302.15 Sq. mts
Total No. of 4 wheelers : 1000 four wheelers
Total No. of 2 wheelers : 2500 Two wheelers
TABLE 1.1
S.NO Tower TOTAL AREA IN SQ.M
1 Tower – A (2 cellar + ground + 3
parking floors + 13 upper floors)
96,933.75
2 Tower – B (1 cellar + ground + 3
parking floors + 10 upper floors)
39,162.27
Total 1,36,096.02
3.1 RAW MATERIALS
Raw materials are required for constructing walls, roofs, openings, panels, super structure
and paving purpose.
Walls: Fly ash-based lightweight aerated concrete blocks will be used for construction of
walls and rattrap bond method will be followed. This system of bonding saves 25% of the
total number of bricks and 40% of the mortar
Roof: pre-cast / aerated cellular concrete roofing slabs are proposed for constructing roof
structures. These structures have high rating to fire resistance and provide better
insulation.
Openings: Precast RCC doors and window frames will be used for openings wherever it is
feasible. These are cheaper, stronger, fire resistant, and termite resistant, sustain
temperature and humidity variations and are effective substitutes to timber / wood.
Super structure: Light weight concrete will be made and mixed with conventional mix for
constructing super structure. Aluminum powder when added to lime reacts and form
hydrogen bubbles and light weight cementitious material is formed. This material is high
strength to weight ratio and an insulation value of R-10 in a 20.32 cm thick wall.
Environmental Management Plan PROFOUND IT PARK IT park
5 5
Paving of roads: Grass pavers will be used on the road, parking and pedestrian areas.
Grass pavers will
Reduce heat island effect
Minimize storm water runoff
Beneficial for localized aquifer recharge
Source of Raw materials
All the raw materials required for the IT park will be sourced from in and around Hyderabad
3.2 WATER REQUIREMENT
The total water required for the proposed park will be met from Municipal water supply.
The total water requirement for proposed IT park will be 390 KLD and 17 KLD will be the
water requirement during construction period.
The following is the break-up of the total water consumption for project.
Water Requirement for Domestic and flushing:
Description No. of
Persons
LPCD Water Requirement, KLD
Domestic Flushing Total Domestic Flushing Total
Employees 6510 18 27 45 117.2 175.8 293.0
Visitors 600 9 6 15 5.4 3.6 9.0
Total 122.6 179.4 302.0
Water Requirement for Landscaping:
Landscaping Area : 1,561.07 Sq.m
Total no. of plants : 210
Water required for each plant : 15 liters/plant
Total Water required for landscaping : 3.2 KLD
say 4 KLD
Environmental Management Plan PROFOUND IT PARK IT park
6 6
Break-up of Water Requirement (in KLD)
Requirement Quantity, KLD Source
Domestic 123 Municipal water supply
Flushing 180 Treated wastewater
HVAC 83 Treated wastewater
Greenbelt 4 Treated wastewater
Total Water Demand 390
3.3 WASTEWATER GENERATION
In the proposed project the waste water generated during construction will be sanitary
wastewater which will be treated in septic tank followed by soak pit. During the operation
of the IT park, total wastewater generation will be 279 KLD. The waste water generated
from IT park will be treated in Sewage Treatment Plant and treated waste water will be
utilized partly for flushing operations and greenbelt development.
3.3.1 WATER BALANCE
Input in KLD Output in KLD
Fresh water 123 Treated wastewater will be reused for
non-potable purposes like flushing 180
Recycled water 267 Treated wastewater will be reused for
HVAC purpose 83
Treated wastewater will be reused for
Greenbelt 4
Waste water discharge into the sewer 12
Consumption / Evaporation 111
TOTAL 390 TOTAL 390
Environmental Management Plan PROFOUND IT PARK IT park
7 7
3.4 CONSTRUCTION OF IT PARK In the construction process the following activities will be taken up phase wise manner.
The activities are summarized as below.
S. No. Type of Work
1. Greenbelt Development
2. Leveling of construction area
3. Excavation for Foundations
4. Foundation PCC, Concrete, Plinth Beam
5. Slab laying
6. Electrical works
7. Brick work
8. Plumbing & Drainage work
9. Stair case for all floors
10. Fixing of Doors & windows
11. Water Proofing works
12. Electrical wiring & Fixtures
13. Fixing of sanitary fittings
14. Plastering works
15. Painting work
16. STP Construction
17. Over head & Underground tank construction
18. Miscellaneous works & amenities development
19. Provision of Backup supply
4.0 ENVIRONMENTAL MANAGEMENT PLAN DURING CONSTRUCTION PHASE
Environmental pollution is inevitable during the construction phase. The project proponent
should take appropriate steps to control pollution during construction phase. The following
are the factors requiring control during construction phase.
Environmental Management Plan PROFOUND IT PARK IT park
8 8
4.1 SITE PREPARATION The following control measures will be followed during the site preparation
Topsoil will be stripped to a depth of 200 mm from areas proposed to be occupied
by buildings, roads, paved areas and external services.
Top soil will be stockpiled to a height of 400 mm in pre - designated areas for
preservation and will be reapplied to site during plantation of the proposed
vegetation.
Measures will be applied to control erosion of preserved top soil.
Top soil will be separated from sub-soil debris and stones larger than 50 mm
diameter.
To keep the damage to topsoil minimum, excavators will be used for construction.
Temporary seeding will be carried out to reduce erosion and sedimentation from
disturbed areas
Temporary seeding will be performed on areas which have been disturbed during
construction and which are likely to be disturbed after a few weeks. For this time
gap the top soil will be preserved from erosion through temporary measures like
temporary seeding.
4.1 AIR ENVIRONMENT
Dust is the major emission during the construction period. The following control
measures will be followed during the construction period
Application of dust suppressants will be done
Locally available gravel will be applied to the roads and lots, to prevent the dust
emanation
Measures will be taken to cover the stored materials to prevent the dust emission
during high winds
Speed of the vehicles in the project area will be limited 20 Kmph
Rescheduling the works during high speedy winds
Inspection will be done for use of covering sheet to prevent dust dispersion at
buildings site
Environmental Management Plan PROFOUND IT PARK IT park
9 9
4.2 WATER ENVIRONMENT Water required during the construction the IT park will be met from the ground water
resources. Total water requirement during construction period will be 17 KLD and
construction period lasts for period of 18 months.
The following control measures will be taken to reduce the reduce the water requirement
during construction
Curing water will be sprayed on concrete structures; free flow of water will not be
done for curing.
After liberal curing on the first day, all concrete structures will be painted with
curing chemical to save water. This will stop daily water curing hence save water.
Concrete structures will be covered with thick cloth/gunny bags and then water
will be sprayed on them. This will avoid water rebound and will ensure sustained
and complete curing.
Ponds will be made using cement and sand mortar to avoid water flowing away
from the flat surface while curing.
Waste water management during construction
Waste water generation will be minimized by following above control measures
Sanitary waste water generated during construction stage will be septic tank
followed by soak pit
4.3 NOISE ENVIRONMENT The main sources of noise in the process of construction activities will be cement concrete
mixing, welding, aluminum channel folding, drilling and DG sets etc.
Diesel generator sets will be provided with integral acoustic enclosure at the
manufacturing stage itself
Equipment like earmuffs, earplugs etc. will be used for hearing protection for
workers.
Environmental Management Plan PROFOUND IT PARK IT park
10 10
4.4 LAND ENVIRONMENT 4.4.1 Solid waste generation & Management
Proper planning and management during construction period is very much vital. We
proposed to implement the following control measures to mitigate the waste generation
Delivery of material on site will be done over a durable, impervious and level
surface, so that first batch of material does not mix with the site surface. Availability
of covered storage will be assured.
The recyclable items like metal, plastic will be sent to recyclable industry, and rest of
this scrap will be stored in a covered area.
Wherever materials (aggregates, sand, etc.) are more likely to generate fine
airborne particles during operations, nominal wetting by water will be practiced.
Workers / labour will be given proper air masks and helmets.
Skilled labour and good workmanship will be employed for judicial utilization of
materials and minimizing the waste.
Proper estimate of material will be done to minimize the undue wastage.
Contaminated runoff from storage will be captured in ditches or ponds with an oil
trap at the outlet.
Materials wasted on site will be reused at the same place.
4.4.2 Waste management & recycling
The construction waste includes debris, concrete (often recycled and reused at the site),
steel and other metals, pallets, packaging and paper products, fluorescent tubes, wood
beams, joists, studs, baseboards, cabinets and cupboards, railings, brick, doors and
casings, interior windows, bathroom fixtures, light fixtures, ceiling grid and tile, furnishings
etc.
Waste recycling Plan Waste and recycling plans will be developed prior to beginning construction activity. The
plan aims at identifying wastes to be generated, and designate handling, recycling and
disposal method to be followed.
Environmental Management Plan PROFOUND IT PARK IT park
11 11
Handling Handling of waste material requires special precautions such as personal protective
equipment and special procedures to prevent the injury. Safe operating methods will be
developed for waste collection, storage, and disposal operations in a manner to protect the
health and safety of personnel, minimize environmental impact and promote material
recovery and recycling.
Waste Segregation
Gross segregation of construction wastes into roadwork materials, structural building
material, salvaged building parts and site clearance wastes will be done and additional
segregation will be done to facilitate reuse/ recycling.
Storage
Adequate provision will be made for storage of solid waste and for easy access to the
dustbins
• for labours from source to the place of storage, and
• from the place of storage to a collection point specified by the waste
collection authority and/or contractor
Three colours of wheeled bins:
o Dark grey for inert waste,
o Green for wood and ply waste and
o Blue for hazardous waste will be used.
A minimum of 4% of the total site area will be allocated for storage and pretreatment of
the waste. This storage area will be covered to prevent any impact on surrounding.
5.0 ENVIRONMENTAL MANAGEMENT PLAN DURING OPERATION PHASE
5.1 Air Emission Management
During operation of the proposed IT park, the emissions will be mainly from DG Sets which
will be used for backup power supply and vehicles. Emissions will be mainly Particulate
matter, NMHC, CO and Nitrogen dioxide.
The following control measures will be taken up during the operation
Environmental Management Plan PROFOUND IT PARK IT park
12 12
All the internal roads will be grass paved. This will reduce the dust generation due to
the vehicular movement
Stack of adequate height will be provided to the DG Sets as per CPCB guidelines
Green belt will be developed in the premises of IT park which will act as sink for air
emissions
Hence there will not be any impact on surrounding environment due to the air emissions
from the proposed IT park.
BASELINE DATA Baseline data has been monitored at the site for particulate Matter (PM2.5), particulate
Matter (PM10), Sulphur dioxide (SO2) & Nitrogen oxides (NOx) concentrations. The
following table shows the baseline concentrations.
PARAMETER 98th Percentile CONCENTRATION
(g/m3)
PM (2.5) 30.2
PM (10) 43.5
SO2 12.8
NOx 21.6
CO 565
EMISSIONS: The emission data from the stacks is shown in below Table.
Type of Stack Emission Rate (QS) in g/s
PM HC NOx CO
DG Sets (10 x 800 kVA)
0.1 per DG
set
0.3 per DG
set
2.1 per DG
set
0.8 per DG
set
Industrial Source Complex (ISC-3) Model has been applied for prediction of incremental rise
in Ground Level Concentrations of PM10, NOx & CO due to the proposed Project. The
maximum Ground Level Concentrations occur at a distance of 300 m from the stack in the
down wind direction. The emissions due to vehicular traffic are also considered in the
Modeling. The following table shows the Net resultant concentrations of PM10, NOx & CO.
Environmental Management Plan PROFOUND IT PARK IT park
13 13
NET RESULTANT MAXIMUM CONCENTRATIONS DUE TO THE PROJECT
Item PM10
µg/m3 NOx µg/m3
CO µg/m3
Maximum baseline Concentration in the Project area
43.5 21.6 565
Maximum predicted incremental rise in concentration due to the project
0.2 6.8 4.8
Net Resultant concentration after occupancy of complex
43.7 28.4 569.8
National Ambient Air Quality Standards vide order No. S.O. 826 dated 16-11-2009
100 80 2000
The net resultant concentration of PM10, NOx & CO are within the National Ambient Air
Quality Standards. Hence there will not be any adverse impact on air environment due to
the proposed project.
Recommendations
a. All the internal roads shall be paved to reduce the fugitive dust due to vehicle
movement.
b. Greenbelt shall be provided in the site premises.
5.2 WATER POLLUTION MANAGEMENT
Water usage for applications such as flushing and washing will be as high as 93% of water
demand in any building. In view of the above, we proposed to adopt the following measures
to reduce this demand
Water meter conforming to ISO standards will be installed at the inlet point of water
uptake and at the discharge point to monitor the daily water consumption. This would
also enable the user to identify if there are any points of leakages.
Dual flush systems will be installed in order to allow different volume of water for
flushing liquids and solids.
Sensors based fixtures will be fitted which function only in presence of users. These
sensor-operated taps help in reducing water consumption and also result in
maintaining better hygiene
Tap aerators will be installed which facilitate cleaning through increasing the pressure
at which the water is delivered even at low flow rates.
Environmental Management Plan PROFOUND IT PARK IT park
14 14
Pressure reduction device will be installed which will affect the discharge rate and also
to maintain uniform flow at different levels.
Waste water generation
Only source of waste water generation will be sanitary waste water which will be treated in
300 KLD STP with Moving bed bio-reactor. The treated waste water will be utilized for non-
potable purposes like Toilet flushing & gardening. Remaining waste water will be
discharged in to the nearest drain.
During construction of IT park, Dual Plumbing system will be done. Two separate water
tanks will be provided for storingTreated wastewater & another for fresh water. Separate
pipeline system will be provided to treated wastewater tank to pump the water for toilet
flushing & gardening purposes. There by net water withdrawal will be reduced.
The total Water Requirement - 390 KLD
Total Wastewater generated - 279 KLD
The Treated wastewater reused - 267 KLD
The net water requirement after reuse - 123 KLD
The following are the characteristics of Untreated Wastewater
Constituent Unit Range
pH --- 6.5-7.5
Dissolved mg/L 250-850
Volatile mg/L 100-300
Suspended mg/L 100-400
Settelable mg/L 50-200
BOD5 mg/L 100-400
COD mg/L 200-1,000
Total Nitrogen mg/L 15-90
Alkalinity mg/L 50-200
Grease mg/L 50-150
Total Coliform colonies/100 mL 106-108
Environmental Management Plan PROFOUND IT PARK IT park
15 15
5.3 SOLID WASTE Waste generated in IT park will be generally from restaurants, plastic & metal and dusting.
In the proposed IT park, waste segregation will be done at the source by placing two types
of the bins at all the strategic locations.
Green: Bio-degradable waste (tissue paper, food waste etc)
Blue : Non-biodegradable waste (plastic, metal waste etc)
The plastic waste will be disposed off to the waste recyclers and bio-degradable waste will
be disposed to the GHMC bins. Exploration will be done to supply bio-degradable waste to
the agencies undertaking bio-composting activities.
The following will be the solid waste generation during operation of the IT park
S. No SOLID WASTE QUANTITY DISPOSAL
1. Municipal Solid
Waste
1.8 TPD The garbage will be segregated at
source through collection bins into
Bio-degradable waste and Non Bio-
degradable waste. Plastic waste will
be given to the waste recyclers and
bio-degradable waste will be disposed
to the GHMC bins
2. Sludge from STP 27.9 Kg/day Stored in HDPE bags and will be used
as manure / given to farmers.
3. Waste oil 300 Lit /Annum Will be given to SPCB approved
vendors.
4. E-waste 6 T/annum Will be given to SPCB approved
vendors.
5.4 NOISE LEVEL MANAGEMENT
DG sets will be provided with acoustic enclosure, which would restrict the noise level to 75
dB(A) at a distance of l m from the acoustic enclosure. The DG sets would be mounted on
the anti vibration pads to restrict the vibration. There will be slight increase in traffic noise
due to the proposed project. However the Noise levels will be within the standards
Environmental Management Plan PROFOUND IT PARK IT park
16 16
prescribed by CPCB / SPCB. Hence there will not be any impact on Noise environment due
to the proposed project.
5.5 LAND ENVIRONMENT
All the pavements in the site area will be grass paved, which will mitigate the dust
generation from the vehicles. Vehicle speed in the IT park area will be reduced which will
reduce the emissions. Greenbelt will be developed in the IT park area which will acts as
sink for the emissions.
Hence there will not be any deposition of pollutants in the surrounding area.
The sanitary waste water generated from the IT park will be treated in Moving Bed Bio Film
reactor and treated waste water will be reused for non-potable purposes like flushing and
greenbelt development. No wastewater will be disposed to the outside. Hence zero
discharge system will be implemented.
The solid waste generated from the IT park will be disposed as per norms.
Hence there will not be any impact on land environment due to the proposed IT park.
Recommendations
a) Land scaping will be done along the periphery of the compound wall.
5.6 GREEN BELT DEVELOPMENT Greenbelt will be developed all around the periphery of the compound wall along with some
part of the Greenbelt will be developed in Open spaces. The greenbelt shall be developed
simultaneously with the plant construction. This will further mitigate the pollution impacts.
Greenbelt plantation
Greenbelt is developed in a set of rows of trees planted in such a way that they form an
effective barrier between the plant and the surroundings. The main purpose of greenbelt
development is to contribute to the following factors.
To maintain the ecological homeostatus.
To attenuate the dust emissions and lower SO2 levels
To prevent the soil erosion.
To attenuate the noise levels.
To utilize the treated effluents.
Environmental Management Plan PROFOUND IT PARK IT park
17 17
Selection of species
The following main criteria will be followed for selection of plants:
• Trees, shrubs having dense foliage with a large surface area, as leaves absorb
pollutants.
• Evergreen trees as they are found to be more effective.
• The species resistant to pollutants, particularly in the early stages of their growth.
The following species are planned to be selected for greenbelt development in the IT park
premises
Botanical name Common name
Delonix regia Gulmohar
Saraca asoca Ashoka tree
Muntingia calabura Singapore Cherry
Jacaranda mimosifolia Jacaranda
Terminalia catapa Indian almond
Mangifera indica Mango
Azadirachta indica Neem
Greenbelt development plan
Green belt will be developed all around the IT park
Out of the total site area 10.5% of area will be allocated for greenbelt development
The tree species to be selected for the plantation are pollutant tolerant, fast
growing, wind firm, deep rooted.
Environmental Management Plan PROFOUND IT PARK IT park
18 18
5.7. RAINWATER HARVESTING In the proposed IT park rain water harvesting pits will be constructed to augment the
precious rain water. Due to this impact on groundwater table will be recharged.
Measures to ensure water quality
To ensure the good quality of rain water the following control measures are proposed
o Catchments such as roofs will be made accessible for regular cleaning and ensuring
no dead animals etc are present on the surface.
o The roof will be made of non- toxic material, having smooth, hard and dense surface
o All gutter ends will be fitted with a wire mesh screen and a first flush device will be
installed. Most of the debris carried by the water from the rooftop like leaves, plastic
bags and paper pieces will be arrested by the mesh at the terrace outlet and
contamination will be prevented to a large extent by ensuring that the runoff from the
first 10-20 minutes of rainfall is flushed off. Remaining contaminants like silt and blow
dirt will be removed by installing appropriate filters.
o No sewage or wastewater will be admitted into the system.
o For runoff from parking lots and roads, grease filters etc. will be arranged to prevent
risk of contamination from chemical spillage.
Total Harvested Rainwater Site is proposed to have rain water storage of 5 Cum. Excess rain water will be diverted to
recharging pits. A total 30 no's of recharging pits, each with 3 cum/day capacity will be
provided.
Total Harvested Rainwater
Rain water harvesting structures will be constructed to harvest the run-off water from roof
tops by laying a separate storm water drainage system for recharging of ground water.
Environmental Management Plan PROFOUND IT PARK IT park
19 19
Ground rainwater harvesting system:
Artificial recharge or ground water rainwater harvesting is a process by which the rain
water from paved areas will be collected through a storm water network. And will be
connected to Rainwater harvesting pit.
Rooftop rainwater harvesting system:
In rooftop harvesting, the roof becomes the catchments, and the rainwater will be collected
from the roof of the each building. Rainwater from roof or terrace will transported using
PVC gutters. Rainwater harvesting pits collect all the rainwater. So that groundwater table
will be recharged and utilized for future use.
5.8 FIRE PROTECTION SYSTEM
As per the provisions of the Fire Service Act, 1999, we will obtain permission from
Telangana State Disasters Response & Fire Services Department from fire safety point of
view.
5.9 COST FOR ENVIRONMENTAL PROTECTION The following will be the cost for Environmental protection.
S. NO PURPOSE CAPITAL COST (in Rs. Lakhs)
RECURRING COST (in Rs. Lakhs/annum)
1. Air emission management
Paving of internal roads 63.68 5
Chimney for DG sets 12.00 0.1
Greenbelt development 1.68 0.4
2. Water & waste water management
Water meters 0.45 0.03
Dual plumbing system 15.00 0.1
STP 90.00 6
3. Rain water harvesting system
Rain water harvesting pits 3.00 0.3
Rain water storage tank 10.00 --
Environmental Management Plan PROFOUND IT PARK IT park
20 20
S. NO PURPOSE CAPITAL COST (in Rs. Lakhs)
RECURRING COST (in Rs. Lakhs/annum)
4 Solid waste management
Two bins at every 750 Sq.m 1.50 2
4 no. chutes 0.60 0.1
5 Environmental monitoring -- 0.5
6 Other energy conservation measures like Solar panels, LED etc
25.00 0
Total 222.91 14.53
The in charge who is experienced in environmental aspects will look after monitoring
schedules and will coordinate with the Govt. authorities.
6.0 POST PROJECT MONITORING STRATEGY
The monitoring of various environmental parameters is necessary which forms part of the
environmental protection measures. Monitoring is an important feature because the
efficiency of control measures can only be determined by monitoring. A comprehensive
monitoring program is given under. Locations and frequency of monitoring as per the
guidelines of SPCB and MOEF are tabulated below.
MONITORING SCHEDULE FOR ENVIRONMENTAL PARAMETERS
S. No. Particulars Frequency of Monitoring
Duration of sampling
Parameters required to be
monitored
1. Water quality
A. Ground Water
quality in the
site
Once in a month
except for heavy
metals.
Grab sampling
(24 hourly)
As per IS: 10500
B. Wastewater Once in a month Grab sampling As per IS: 2490
2. Air Quality
A. Stack
Monitoring
Once in a month PM, NMHC, CO & NOX
Environmental Management Plan PROFOUND IT PARK IT park
21 21
CONCLUSIONS
1. Dust curtains will be used to reduce the dust emissions during construction of proposed
project.
2. The flue gases from the D.G. Set will be let out through a stack of adequate height for
effective dispersion of emissions into the atmosphere. The resultant Ground Level
Concentrations of PM, NMHC, NOX & CO in the post project scenario are within the
National Ambient Air Quality Standards (NAAQS). Hence there will not be any adverse
impact on air environment due to the proposed project.
3. All Driveways & internal roads will be paved.
4. Wastewater generated from the apartment will be treated in sewage treatment plant
and will be utilized for non-potable purposes like Toilet flushing and gardening.
Remaining treated waste water will be discharged into the nearest drain
5. Rain Water Harvesting pits will be provided to augment the precious rain water and
ground water recharge
6. The Solid waste in the form of garbage will be segregated at source into bio-degradable
and non-bio-degradable waste. Plastic waste will be given to the authorized recyclers
and bio-degradable waste will be sent to GHMC.
7. Greenbelt of 1,561.07 Sq.m will be developed in the project site premises.
8. Adequate firefighting equipment’s will be implemented as per the National Building
Code.