prof. dr. nabil i. el sawalhi

36
Engineering Project Management Prof. Dr. Nabil I. El Sawalhi Professor of Construction Management Chapter 7 Control 1 L7 Control

Upload: others

Post on 27-May-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Prof. Dr. Nabil I. El Sawalhi

Engineering Project Management

Prof. Dr. Nabil I. El SawalhiProfessor of Construction Management

Chapter 7

Control

1 L7 Control

Page 2: Prof. Dr. Nabil I. El Sawalhi

2

Introduction• Monitoring and Control are opposite sides of selection and

planning

– bases for selection dictate what to monitor

– plans identify elements to control

• Monitoring is collection, recording, and reporting of information

• Control uses monitored information to align actual performance with the plan

L7 Control

Page 3: Prof. Dr. Nabil I. El Sawalhi

3

Plan-Monitor-Control Cycle

• Closed loop process

• Planning-monitoring-controlling effort often minimized to spend time on “the real work”

L7 Control

Page 4: Prof. Dr. Nabil I. El Sawalhi

4

Project Authorization and Expenditure Control System Information Flow

L7 Control

Page 5: Prof. Dr. Nabil I. El Sawalhi

5

Designing the Monitoring System

• Identify special characteristics of performance, cost, and time that need to be controlled

– performance characteristics should be set for each level of detail in the project

• Real-time data should be collected and compared against plans

– mechanisms to collect this data must be designed

• Avoid tendency to focus on easily collected data

L7 Control

Page 6: Prof. Dr. Nabil I. El Sawalhi

6

DATA COLLECTION AND REPORTING

L7 Control

Page 7: Prof. Dr. Nabil I. El Sawalhi

7

Formats of Data

• Frequency Counts

• Raw Numbers

• Subjective Numeric Ratings

• Indicators and Surrogates

• Verbal Characterizations

L7 Control

Page 8: Prof. Dr. Nabil I. El Sawalhi

8

Data Analysis• Aggregation Techniques

• Fitting Statistical Distributions

• Curve Fitting

• Quality Management Techniques

L7 Control

Page 9: Prof. Dr. Nabil I. El Sawalhi

Project Control

• The aim of control is to ensure that project’s status is reported in consistent, cost-effective and timely manner to PM to enable any necessary actions can be taken in timely manner.

• The Control Model is “Plan-do-Review”.

• Do will take the following forms:

• Do nothing if work progressing as planned.

• Refer on if the change lies outside control of the project team.

• Change the plan, if there is deviation.

• Change the work, either scope or methods.

L7 Control9

Page 10: Prof. Dr. Nabil I. El Sawalhi

The Role of PM

• Establish the system

• Allocate responsibilities

• Ensure that cost are properly allocated

• Ensure that payments are authorized.

• Purposes of Control

• Stewardship of Organizational Assets

– physical asset control

– human resources

– financial control

• Regulation of Results Through the Alteration of Activities

L7 Control10

Page 11: Prof. Dr. Nabil I. El Sawalhi

PM monitoring

• The PM can Monitor the project by:

• Obtaining regular verbal reports;

• Progress report;

• Internal measurement procedures;

• External audit.

L7 Control11

Page 12: Prof. Dr. Nabil I. El Sawalhi

12

Tools for Control

• Variance Analysis

• Trend Projections

• Earned Value Analysis

• Critical Ratio

cost actual

cost budgeted

progress scheduled

progress actual

L7 Control

Page 13: Prof. Dr. Nabil I. El Sawalhi

13

Trend Projection

L7 Control

Page 14: Prof. Dr. Nabil I. El Sawalhi

14

Critical Ratios with Control Limits

L7 Control

Page 15: Prof. Dr. Nabil I. El Sawalhi

15

Cost Control Chart

L7 Control

Page 16: Prof. Dr. Nabil I. El Sawalhi

16

Reporting• Reports

– Project Status Reports

– Time/Cost Reports

– Variance Reports

• Not all stakeholders need to receive same information

• Avoid periodic reports

• Impact of Electronic Media

• Relationship between project’s information system and overall organization’s information system

L7 Control

Page 17: Prof. Dr. Nabil I. El Sawalhi

17

Report Types

• Routine

• Exception

• Special Analysis

L7 Control

Page 18: Prof. Dr. Nabil I. El Sawalhi

18

Meeting Guidelines

• Meetings should be help primarily for group decision making

– avoid weekly progress report meetings

• Distribute written agenda in advance of meeting

• Ensure everyone is properly prepared for meeting

• Chair of meeting should take minutes

– avoid attributing remarks to individuals in the minutes

• Avoid excessive formality

• If meeting is held to address specific crisis, restrict meeting to this issue alone

L7 Control

Page 19: Prof. Dr. Nabil I. El Sawalhi

19

Virtual Reports, Meetings, and Project Management

• Use of the Internet

• Use of Software Programs

• Virtual Project Teams

L7 Control

Page 20: Prof. Dr. Nabil I. El Sawalhi

Earned Value Analysis

• It is an industry standard way to:

• measure a project’s progress,

• forecast its completion date and final cost, and

• provide schedule and budget variances along the way.

By integrating three measurements, it provides consistent, numerical indicators with which you can evaluate and compare projects.

• Knowing where you are on schedule?

• Knowing where you are on budget?

• Knowing where you are on work accomplished

L7 Control20

Page 21: Prof. Dr. Nabil I. El Sawalhi

• It compares the PLANNED amount of work with what has actually been COMPLETED, to determine if COST , SCHEDULE, and WORK ACCOMPLISHED are progressing as planned.

• Work is “Earned” or credited as it is completed.

L7 Control21

Page 22: Prof. Dr. Nabil I. El Sawalhi

Earned Value• Earned Value analysis (EVA) compare the value of work done

with the value of work that should have been done.

• Budget cost of work scheduled(BCWS) is the value of work that should have been done at a given point of time. This take the work planned to have been done and the budget for each task and indicates the portion of the budget planned to have been used.

• Budget cost of work performed (BCWP)is the value of the work done at a given point of time. This take the work that has been done and the budget for each task and indicate what portion of the budget ought to have been used to achieve it.

• Actual Cost of work performed (ACWP)

• Productivity factor (PF) is the ratio of estimated man-hours to the actual man-hours.

L7 Control22

Page 23: Prof. Dr. Nabil I. El Sawalhi

• SV = schedule variance= (BCWP-BCWS). Negative number imply that the work is behind schedule.

• CV= Cost Variance= (BCWP-ACWP) negative number implies a current budget overrun.

• Variance at completion is the budget at completion (BAC) minus the estimate at completion.

L7 Control23

Page 24: Prof. Dr. Nabil I. El Sawalhi

Typical S Curve

L7 Control24

Page 25: Prof. Dr. Nabil I. El Sawalhi

25

Variances

• Cost/Spending Variance

EV (Earned Value) – AC (Actual Value)

• Schedule Variance

EV – PV (Planed Value)

• CPI (Cost Performance Index). value under 100 means that project is over budget

EV/AC= BCWP/ACWP

• SPI (Schedule Performance Index). value under 100 means that project is over budget or behind

• EV/PV= BCWP/BCWS

L7 Control

Page 26: Prof. Dr. Nabil I. El Sawalhi

26

Additional Items of Interest

• Estimated (Remaining Cost) to Completion

ETC = (BAC - EV)/CPI

• (Total Cost) Estimated at Completion

EAC = ETC + AC•CSI: Cost Schedule Index (CSI=CPI x SPI)

The further CSI is from 1.0, the less likely project recovery becomes.

L7 Control

Page 27: Prof. Dr. Nabil I. El Sawalhi

Example on EVA

L7 Control27

Page 28: Prof. Dr. Nabil I. El Sawalhi

S-Curve analysis

L7 Control28

Page 29: Prof. Dr. Nabil I. El Sawalhi

Example

L7 Control29

On Day X:

PLANNED VALUE (Budgeted cost of the work scheduled, BCWS) =

18 + 10 + 16 + 6 = 50

EARNED VALUE (Budgeted cost of the work performed, BCWP) =

18 + 8 + 14 + 0 = 40

ACTUAL COST (of the work performed , ACWP) =

45 (from your project tracking - not evident in above chart)

Page 30: Prof. Dr. Nabil I. El Sawalhi

Example Project

• Plans to spend $100K in each of first 4 weeks (baseline budget, per documented plan)

• Actuals at end of week 4: $325K– BCWS = $400K ($100K x 4)

– ACWP = $325K

• What conclusions can you draw?

• Under budget?

• Is project on schedule?

L7 Control30

Page 31: Prof. Dr. Nabil I. El Sawalhi

• Suppose BCWP is $300K

– How is this determined?

• What conclusions now?

– SV = BCWP – BCWS

– SV = $300k - $400K = -$100K

• Behind schedule, but what does the $100K in variance really mean?

– CV = BCWP – ACWP = $300K - $325K

• Over budget by $25K

L7 Control31

Page 32: Prof. Dr. Nabil I. El Sawalhi

• How can you use this information?

– Careful analysis of variance and trends

– Resetting schedule or budget, when appropriate

• Variance Analysis Questions

– What is the problem causing the variance?

– What is the impact on time, cost and performance?

– What is the impact on other efforts, if any?

– What corrective action is planned or under way?

– What are the expected results of the corrective action?

L7 Control32

Page 33: Prof. Dr. Nabil I. El Sawalhi

• Extraordinary variance or alarming trends may be cause for reset or cancellation of a project, but where do you draw the line?

• How much variance to allow depends on a number of factors:

– Life-cycle phase

– Length of life-cycle phase

– Length of project

– Type of estimate

– Accuracy of estimate

L7 Control33

Page 34: Prof. Dr. Nabil I. El Sawalhi

L7 Control34

Page 35: Prof. Dr. Nabil I. El Sawalhi

Performance Index Trends

L7 Control35

Page 36: Prof. Dr. Nabil I. El Sawalhi

Ideal Performance Index

L7 Control36