prod techniques old

Upload: ragnijethi

Post on 06-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 Prod Techniques Old

    1/582

    PRODUCTIVITY

    TECHNIQUES

  • 8/2/2019 Prod Techniques Old

    2/582

    PRODUCTIVITYTECHNIQUES

  • 8/2/2019 Prod Techniques Old

    3/582

    MEANING OF PRODUCTIVITY

    PRODUCTIVITY IS OFTEN ASSOCIATED WITHPRODUCTION

    HIGHER PRODUCTION IS NOT HIGHER

    PRODUCTIVITY INCREASE IN PRODUCTION CAN BE ACHIEVED

    BY INCREASING QUANTUM OF INPUT BUT THATDOES NOT INCREASE PRODUCTIVITY

    HIGHER PRODUCTIVITY RESULTS IF

    PRODUCTION PER EMPLOYEE OR PER MACHINEINCREASES ALONGSIDE WITH QUALITY

    PRODUCTIVITY IS CREATING SURPLUS THRUPRODUCTIVE OPERATIONS WHERE OUTPUT ISALWAYS GT INPUT

    PRODUCTIVITY IS DEFINED AS OUTPUT WITHINDEFINED TIME AND AS PER QLTY NORMS/INPUT

  • 8/2/2019 Prod Techniques Old

    4/582

    MEANING OF PRODUCTIVITY

    BOTH OUTPUT AND INPUT SHOULD BEQUANTIFIED IN TANGIBLE MONETARYTERMS

    PRODUCTIVITY CAN BE IMPROVED BY-INCREASING OUTPUT WITH SAME INPUT-INCREASING OUTPUT MORE THAN THEINCREASE IN INPUT

    -DECREASING INPUT FOR THE SAMEAMOUNT OF OUTPUT-INCREASING OUTPUT WHILEDECREASING INPUT

    PRODUCTIVITY IMPLIES EFFECTIVENESS

    AND EFFICIENCY IN INDIVIDUAL AND

  • 8/2/2019 Prod Techniques Old

    5/582

    DEFINITION OF

    PRODUCTIVITY PRODUCTIVITY IS THE RATIO BETWEEN OUTPUT

    OF WEALTH TO THE INPUT OF RESOURCES USED

    IN THE PROCESS OF MFG

    PRODUCTIVITY = OUTPUT OF WEALTH/INPUT OF

    RESOURCES

    INPUTS ARE MATERIAL , MONEY , MACHINES ,

    PEOPLE

    ANOTHER PARAMETER OFTEN USED IS

    PERFORMANCE WHICH IS (ACTUAL

    ACHIEVEMENT IN TERMS OF EFFECTIVE WORK

    DONE)/(STANDARD TARGET OF ACHIEVEMENT) *

    100

  • 8/2/2019 Prod Techniques Old

    6/582

    DEFINITION OF

    PRODUCTIVITY PERFORMANCE IS EXPRESSED AS PERFORMANCE INDEX

    WHICH IS % OF STANDARD TARGET OR EFFECTIVENESS OF

    PRODUCTIVITY .PRODUCTIVITY = OUTPUT/INPUT

    = PERFORMANCE ACHIEVED/RESOURCES CONSUMED= EFFECTIVENESS/EFFICIENCY

    PRODUCTIVITY CAN BE APPLIED TO MATERIAL ,

    EQUIPMENT,MEN,CAPITAL

    MATRL = 1 TONNE OF HOT ROLLED STEEL PRODUCES 0.8

    TONNE OF COLD ROLLED STEEL REST IS SCRAP.PRODUCTIVITY WAS 80%. THE ENGINEERS AT TISCO

    STUDIED THE PROCESS AND THRU METHOD STUDY

    INCREASED PRODUCTIVITY TO 90% BY REDUCING SCRAP

  • 8/2/2019 Prod Techniques Old

    7/582

    DEFINITION OF

    PRODUCTIVITY MACHINE = RATED THROUGHPUT OF POWER

    PLANT WAS 100 MWH. ACTUAL

    THROUGHPUT(PLF) WAS 72% WHICH MEANT THE

    POWER PLANT HAD 28% LOSSES.AFTER

    STUDYING HEAT LOSSES AND INSTALLING

    PREHEATERS AND REGENERATORS THE HEAT

    LOSS WAS REDUCED BY 8%.HENCE

    PRODUCTIVITY OF POWER PLANT ROSE TO 80% MAN = STANDARD OUTPUT OF TRAINED 1 YEAR

    EXPERIENCED ORACLE PROGRAMMER IS 80

    DEBUGGED LINES OF CODE PER DAY. ON A

    PARTICULAR DAY MR X PRODUCED 60 LINES. HISPRODUCTIVITY WAS 75%

  • 8/2/2019 Prod Techniques Old

    8/582

    MYTHS IN PRODUCTIVITY

    PRODUCTION IMPROVEMENT MEANS

    PRODUCTIVITY IMPROVEMENT

    EFFICIENCY IMPROVEMENTGUARANTEES PRODUCTIVITY

    IMPROVEMENT

    IMPROVEMENT IN SALES REVENUE

    ENSURES PRODUCTIVITY IMPROVEMENT

    QUALITY IMROVEMENT ENHANCES

    PRODUCTIVTY

  • 8/2/2019 Prod Techniques Old

    9/582

    PARTIAL PRODUCTIVITY

    DEFINED AS RATIO OF TOTAL OUTPUT TO ANY ONE TYPE

    OF INPUT eg MATERIAL , MONEY ,LABOUR , ENERGY

    LABOUR PRODUCTIVITY = TOTAL OUTPUT/LABOUR COST

    eg 1000 cr/300cr = 3.3 MATERIAL PRODUCTIVITY =TOTAL OUTPUT/MATRL COST

    eg 1000cr/200cr 5.0

    CAPITAL PRODUCTIVITY = TOTAL OUTPUT/CAPITAL COST

    eg 1000cr/300 = 3.3

    CAN ALSO BE CALLED FIXED ASSET PRODUCTIVITY ENERGY PRODUCTIVITY =TOTAL OUTPUT/ENERGY COST

    eg 1000cr/100cr = 10

  • 8/2/2019 Prod Techniques Old

    10/582

    PARTIAL PRODUCTIVITY

    PARTIAL PRODUCTIVITY GIVES MEASURE OF

    IMPACT OF TYPE OF INPUT ON OVERALL

    PRODUCTIVITY

    PARTIAL PRODUCTIVITY HELPS IN DETERMINING

    IMPORTANCE OF TYPE OF INPUT ON

    EFFECTIVENESS OF PROCESS

  • 8/2/2019 Prod Techniques Old

    11/582

    ASSET ENERGY

    SUSTAINABILITY INDEX Most companies concentrate on achieving a high degree of

    overall equipment effectiveness

    OEE = UPTIME * EFFICIENCY * QUALITY where

    efficiency is the throughput productivity

    But while doing so how much is the extra energy

    consumed

    Are we achieving higher throughputs but sacrificing

    energy consumption

    Asset Energy Sustainability Index = OEE * (Expected

    energy consumption per unit produced/Actual energy

    consumed per unit)

  • 8/2/2019 Prod Techniques Old

    12/582

    COMPARITIVE PLANT FIGURES OF

    ENERGY CONSUMPTION PER

    VEHICLE IN HERO HONDA PLANTS2009 2010

    PLANT VEH KWH/VEH VEH KWH/VEH

    GURGAON 15.59L 35.85 15.93L 36.97

    DHARUHERA 15.99L 31.12 15.33L 32.09

    HARIDWAR 6.30L 24.63 14.04L 17.31

    SOURCEANNUAL REPORT OF HERO HONDA 2009-2010

  • 8/2/2019 Prod Techniques Old

    13/582

    PARTIAL PRODUCTIVITY

    ADVANTAGES EASY TO UNDERSTAND EFFECT OF

    INDIVIDUAL FACTOR OF INPUT ON

    OUTPUT EASY TO OBTAIN DATA

    EASY TO COMPUTE PRODUCTIVITY

    INDICES

    EASY TO CONVINCE MGT OF BENEFITS

    GOOD DIAGNOSTIC TOOLS AVAILABLE TO

    PINPOINT AREAS OF PRODUCTIVITY

    IMPROVEMENT

  • 8/2/2019 Prod Techniques Old

    14/582

    PARTIAL PRODUCTIVITY

    DISADVANTAGES IF USED ALONE CAN BE MISLEADING

    STRESSES ON ONE FACTOR

    CANNOT EXPLAIN OVERALL COSTINCREASES

    TEND TO SHIFT BLAME ON WRONG AREAS

    OF MGT CONTROL

    IN THE CASE OF PARTIAL LABOR

    PRODUCTIVITY THE CONTRIBUTION OF

    INDIRECT LABOR IS NOT TAKEN INTO

    CONSIDERATION

  • 8/2/2019 Prod Techniques Old

    15/582

    PROBLEM WITH TRADITIONAL

    LABOR PRODUCTIVITY OUTPUT PRODUCED IS A RESULT OF JOINT AND

    SIMULTANEOUS IMPACT OF ALL RESOURCES

    NOT ONLY LABOR

    COMPANIES SHOWING HIGH LABOR

    PRODUCTIVITY GROWTH RATES ARE NOT

    ALWAYS COMPETITIVE IN THE MARKET

    ORGANIZATIONS WITH COLLECTIVE

    BARGAINING AGREEMENTS BASED ONLY ONLABOR PRODUCTIVITY TEND TO REDUCE THE

    UNIT LABOR COST BUT NOT ALWAYS THE TOTAL

    UNIT COST eg COMPUTERIZATION LEADING TO

    LABOR REDUCTION

  • 8/2/2019 Prod Techniques Old

    16/582

    PROBLEM WITH TRADITIONAL

    LABOR PRODUCTIVITY DIFFICULT TO IMPLEMENT TEAM CONCEPTS OF

    MGT WHEN PERFORMANCE MGT IS FOCUSED

    ONLY ON LABOR PRODUCTIVITY RATHER THAN

    TOTAL PRODUCTIVITY

    ORG STRUCTURES TEND TO BE LESS FLEXIBLE

    WHEN EMPHASIS IS ON CONTROL OF LABOR

    PRODUCTIVITY RATHER THAN TOTAL

    PRODUCTIVITY DIFFICULT TO DIRECTLY RELATE LABOR

    PRODUCTIVITY TO PROFITS

    IN MOST MFG OUTFITS LABOR COST IS NOT A

    SIGNIFICANT COMPONENT OF DIRECT COSTS eg

  • 8/2/2019 Prod Techniques Old

    17/582

    TOTAL FACTOR

    PRODUCTIVITY DEFINED AS RATIO OF NET OUTPUT TO SUM OF

    LABOUR AND CAPITAL INPUTS

    NET OUTPUT = TOTAL OUTPUTINTERMEDIATE

    GOODS AND SERVICES PURCHASED

    INTERMEDIATE GOODS AND SERVICES

    PURCHASED INCLUDE RAW

    MATRL,COMPONENTS,ENERGY COSTS,FUEL,FEES

    FOR SERVICES etc

    ALSO CALLED VALUE ADD WHEN COSTS

    COMPUTED

  • 8/2/2019 Prod Techniques Old

    18/582

    EXAMPLE OF TOTAL

    FACTOR INDEX TOTAL FACTOR PRODUCTIVITY =

    OUTPUT/CAPITAL + LABOUR INPUT =

    100/(20 + 55) =100/75 = 1.33 VALUE ADD = SALESPROCURE PRICE

    SERVICES PRICE = 25001000500 = 1000

    VALUE ADD PER EMPLOYEE = 1000/200 = 5

  • 8/2/2019 Prod Techniques Old

    19/582

    ADVANTAGES OF TOTAL

    FACTOR PRODUCTIVITY DATA IS EASY TO OBTAIN

    APPEALING FROM ECONOMIST

    POINT OF VIEW

  • 8/2/2019 Prod Techniques Old

    20/582

    DISADVANTAGES OF TOTAL

    FACTOR PRODUCTIVITY VALUE ADDED APPROACH TO DEFINING

    OUTPUT IS NOT VERY APPROPRIATE

    NOT APPROPRIATE WHEN MATRL COSTFORMS SIZEABLE PORTION OF TOTAL

    PRODUCT COST

    ONLY LABOR AND CAPITAL INPUTS ARE

    CONSIDERED

    DATA FOR COMPARISON PURPOSES IS

    DIFFICULT TO OBTAIN

  • 8/2/2019 Prod Techniques Old

    21/582

    TOTAL PRODUCTIVITY

    TOTAL PRODUCTIVITY IS THE RATIO OF TOTAL

    OUTPUT TO THE SUM OF ALLINPUT FACTORS

    MEASURE WHICH TAKES INTO CONSIDERATION

    THE JOINT IMPACT OF ALL INPUT RESOURCES ON

    OUTPUT SUCH AS

    MATERIAL,MACHINES,CAPITAL,ENERGY etc

    MEASURE VERY POPULAR IN INDUSTRY

  • 8/2/2019 Prod Techniques Old

    22/582

    ADVANTAGES OF TOTAL

    PRODUCTIVITY CONSIDERS ALL QUANTIFIABLE OUTPUT AND INPUT FACTORS AND IS

    THEREFORE A MORE ACCURATE REPRESENTATION OF THE REAL

    ECONOMIC PICTURE OF THE COMPANY

    PROFIT CONTROL THRU THE USE OF THESE INDICES IS OF BENEFIT TO THE

    MGT IF USED IN CONJUNCTION WITH PARTIAL PRODUCTIVITY CAN DIRECT

    MGT ATTENTION IN AN EFFECTIVE MANNER

    SENSITIVITY ANALYSIS IS EASIER TO PERFORM

    EASILY RELATED TO TOTAL COSTS

    MULTIPLE GOALS CAN BE ACHIEVED SIMULTANEOUSLY BY INCREASING

    TOTAL PRODUCTIVITY OF A COMPANY USING THE RELATIONSHIP BETWEEN PROFIT AND TOTAL PRODUCTIVITY

    A FIRM CAN OBJECTIVELY PLAN ITS PROFIT LEVEL BASED ON ITS ABILITY

    TO REACH A CERTAIN PRODUCTIVITY LEVEL

    USING THE CONCEPT OF BREAK EVEN POINT OF TOTAL PRODUCTIVITY A

    FIRM CAN DETERMINE IF ITS TOTAL PRODUCTIVITY LEVEL IS A VALUE

    THAT YIELDS PROFITS MGT IS FORCED INTO A LONG TERM ACTION ON QLTY,PROFITABILITY etc

  • 8/2/2019 Prod Techniques Old

    23/582

    DISADVANTAGES OF TOTAL

    PRODUCTIVITY DATA FOR COMPUTATION IS DIFFICULT TO

    OBTAIN AT PRODUCT AND CUSTOMER LEVEL

    LIKE THE PARTIAL AND TOTAL FACTOR

    MEASURES THIS ALSO DOES NOT CONSIDER

    INTANGIBLE FACTORS OF OUTPUT AND INPUT IN

    A DIRECT MANNER

  • 8/2/2019 Prod Techniques Old

    24/582

    AMERICAN PRODUCTIVITY

    CENTRE MODEL MODEL DERIVES EQUATION OF PROFITABILITY WITH

    PRODUCTIVITY AND PRICE RECOVERYFACTOR

    PROFITABILITY = SALES/COST

    = OUTPUT QTY * PRICE/INPUT QTY * UNIT COST=OUTPUT QTY/INPUT QTY *UNIT PRICE/UNIT COST

    =PRODUCTIVITY * PRICE RECOVERY FACTOR

    PRICE RECOVERY FACTOR INDICATES THE INFLATIONARY

    EFFECT AND PRODUCTIVITY GIVES THE AMOUNT OF

    RESOURCES CONSUMED TO PRODUCE THE DEFINEDOUTPUT. IT IS THE PRICE RATIO OF CURRENT PERIOD TO

    THE BASE PERIOD

  • 8/2/2019 Prod Techniques Old

    25/582

    APPLICATIONS OF

    PRODUCTIVITY TECHNIQUES APPLIED TO ALL FUNCTIONAL AREAS BOTH IN

    MFG AND SERVICES

    CONCEPTS OF PRODUCTIVITY VITAL TO

    SUCCESS AND SURVIVAL OF ORG IN TODAYS

    HIGHLY COMPETITIVE GLOBAL BUSINESS

    ENVIRONMENT

    ONLY MEASUREMENT OF PRODUCTIVITY

    INADEQUATE FOR COMPANY TO SURVIVE

    CONTINUOUS IMPROVEMENT IN PRODUCTIVITY

    IN ALL FUNCTIONAL AREAS AT A RATE FASTER

    THAN COMPETITION IS A DECISIVE BUSINESS

    FACTOR FOR SURVIVAL AND SUCCESS OF

  • 8/2/2019 Prod Techniques Old

    26/582

    KEY PARAMETERS

    MARKETING

    ACCURACY OF DEMAND FORECASTING

    -COST LEADERSHIP-SERVICING SPEED AND EFFECTIVENESS

    -OPTIMISED PRODUCT MIX

    PRODUCTION

    -INVENTORY CONTROL-JUST IN TIME

    -PROCUREMENT COST

    -SAFETY

  • 8/2/2019 Prod Techniques Old

    27/582

    AREAS OF PRODUCTIVITY

    TECHNIQUES SUPPLY CHAIN MGT

    DEMAND FORECASTING

    COST MANAGEMENT LOGISTIC MGT

    SERVICING SPEED AND EFFECTIVENESS

    METHOD STUDY

    PLANT LAYOUT MATERIAL HANDLING

    INVENTORY CONTROL (INV TURNOVER RATIO)

    WORK MEASUREMENT

  • 8/2/2019 Prod Techniques Old

    28/582

    AREAS OF PRODUCTIVITY

    TECHNIQUES MOTION STUDY

    MATERIALS MGT AND CONTROL

    PRODUCTION PLANNING AND CONTROL INVENTORY MODELS

    ERGONOMICS

    SAFETY JOB EVALUATION

  • 8/2/2019 Prod Techniques Old

    29/582

    CAUSES OF POOR

    PRODUCTIVITY LACK OF PRODUCTIVITY MEASURES BY WAY OF ABSENCE

    OF A SYSTEM TO CAPTURE CORRECT AND TIMELY INPUTS

    RELEVANT TO PRODUCTIVITY MEASUREMENTS

    ESPECIALLY FOR ADMINISTRATIVE STAFF

    FAULTY APPRAISAL SYSTEM BASED ON QUALITATIVE

    JUDGEMENTS

    INADEQUATE WORK ASSIGNMENT

    DEMOTIVATED OR UNDER CAPABLE EMPLOYEES

    LOW EMPLOYEE INVOLVEMENT HUMAN CONFLICTS

    LACK OF TRAINING AND SKILLS UPGRADES

    TECHNOLOGICAL CHANGES ESPECIALLY FROM CLIENT

    SERVER TO THIN CLIENT

    UNBALANCED PRODUCTION LINE OR UNRELIABLE LINE

  • 8/2/2019 Prod Techniques Old

    30/582

    MATERIAL BASED

    PRODUCTIVITY TECHNIQUES INVENTORY CONTROL

    SUPPLY CHAIN MGT

    MATERIAL HANDLING

    QUALITY ASSURANCE

    JUST IN TIME MFG AND PROCUREMENT

  • 8/2/2019 Prod Techniques Old

    31/582

    PEOPLE BASED PRODUCTIVITY

    TECHNIQUES INDIVIDUAL FINANCIAL INITIATIVES

    GROUP FINANCIAL INITIATIVES

    LIBERAL FRINGE BENEFITS

    EMPOWERMENT AND OWNERSHIP

    TRAINING AND PERSONAL DEVELOPMENT

    JOB ENRICHMENT AND ROTATION

    EMPLOYEE PARTICIPATION IN MGT

  • 8/2/2019 Prod Techniques Old

    32/582

    PRODUCT BASED

    PRODUCTIVITY TECHNIQUES VALUE ENGINEERING

    PRODUCT DIVERSIFICATION

    PRODUCT SIMPLIFICATION

    PRODUCT FLEXIBILITY AND AGILITY

    BENCHMARKING

  • 8/2/2019 Prod Techniques Old

    33/582

    TASK BASED

    PRODUCTIVITY

    TECHNIQUES WORK MEASUREMENT INCLUDING

    METHOD STUDY , TIME STUDY , MOTION

    STUDY JOB DESIGN JOB EVALUATION AND JOB

    SAFETY

  • 8/2/2019 Prod Techniques Old

    34/582

    ILO APPROACH TO PRODUCTIVITY

    IMPROVEMENT ILO APPROACH IS TASK BASED

    IT BREAKS MFG TIME INTO BASIC

    WORK CONTENT ,ADDED WORKCONTENT AND INEFFECTIVE TIME

    APPROACH FOCUSES ON REDUCING

    INEFFICIENT TIME IN THE TOTALWORK CONTENT

  • 8/2/2019 Prod Techniques Old

    35/582

    INEFFECTIVE TIME

    ALL INTERRUPTIONS WHICH CAUSE

    STOPPAGE IN OPERATION IS REGARDED

    AS INEFFICIENT TIME BECAUSE NO WORKEFFECTIVE TOWARDS COMPLETION OF

    OPERATION IN HAND IS BEING DONE

    DURING PERIOD OF INTERRUPTION

    INEFFECTIVE TIME DUE TOSHORTCOMINGS BY MGT.TIME DURING

    WHICH MAN/MC IS IDLE BECAUSE MGT

    FAILED TO PLAN DIRECT OORDINATE OR

    CONTROL EFFICIENTLY

  • 8/2/2019 Prod Techniques Old

    36/582

    REDUCTION IN

    INEFFECTIVE TIME INEFFECTIVE TIME WITHIN CONTROL OF WORKER CAN BE

    REDUCED THRU ADOPTION OF FOLLOWING INITIATIVES

    - POOR DESIGN AND FREQUENT DESIGN CHANGES

    -WASTE OF MATERIAL

    -INCORRECT QUALITY STDS

    -POOR LAYOUT AND UTILIZATION OF SPACE

    -INADEQUATE MATEIAL HANDLING

    -FREQUENT PRODUCTION STOPPAGES

    -INEFFECTIVE WORK METHODS

    -POOR WORK PLANNING-FREQUENT BREAKDOWNS

    -ABSENTEEISM , WRONG ATTITUDES

    -POOR WORKMANSHIP

    -ACCIDENTS AND SAFETY ISSUES

  • 8/2/2019 Prod Techniques Old

    37/582

    SURVEY RESULTS ON

    PRODUCTIVITY TYPICAL 8 HR DAY

    -3.5 HRS(44%) PRODUCTIVE TIME

    -1.2 HRS(15%) UNAVOIDABLE DELAYS

    -3.3 HRS(41%) WASTED TIME

    REASONS FOR PRODUCTIVITY LOSS

    -POOR PLANNING AND WORK SCHEDULING (35%)

    -UNCLEAR INSTRUCTIONS TO EMPLOYEES(25%)

    -INABILITY TO ADJUST STAFF SIZE AND DUTIESDURING PEAK LOADS(15%)eg BANK CASH

    DISPENSING TELLERS

    -POOR COORDINATION OF MATRL FLOW

    ,UNAVAILABILITY OF MACHINE(25%)

  • 8/2/2019 Prod Techniques Old

    38/582

    COMMON MFG RATIOS

    UNITS PRODUCED/LABOR HRS

    REWORK HRS REQD/UNITS

    PRODUCED

    NUMBER DEFECTS/TOTAL UNITS

    MACHINE UTILIZATION %

    WT OF WASTE/WT OF FINISHED

    GOODS

    WT OF FINISHED GOODS/RM WEIGHT

  • 8/2/2019 Prod Techniques Old

    39/582

    COMMON SERVICES RATIOS

    NUMBER OF CUSTOMER

    COMPLAINTS/ORDERS DELIVERED OR

    NUMBER OF PRODUCTS SOLD NUMBER OF DATA ENTRY ERRORS /TOTAL

    DATA ENTERED

    LATE DELIVERIES/TOTAL DELIVERIES

    PROJECT PLANNED COST/ACTUAL COST

    OVERTIME HRS/REGULAR HRS

    CUSTOMER RETURNS%

    WARRANTY COSTS/SALES%

  • 8/2/2019 Prod Techniques Old

    40/582

    HARD METRICS IN

    PRODUCTIVITY PLANT UTILIZATION

    ENERGY EFFECTIVENESS INDEX

    NUMBER OF ACCIDENTS AND HRS

    LOST DUE TO ACCIDENTS

    OVERALL PLANT EFFECTIVENESS

    OVERALL PROCUREMENT

    EFFECTIVENESS

    OVERALL DISTRIBUTION

    EFFECTIVESS

  • 8/2/2019 Prod Techniques Old

    41/582

    SOFT METRICS IN

    PRODUCTIVITY EMPLOYE MORALE

    EMPLOYEE LOYALTY

    EMPLOYEE INVOLVEMENT

    JOB SATISFACTION

    HONESTY

  • 8/2/2019 Prod Techniques Old

    42/582

    SUMANTHS TOTAL

    PRODUCTIVITY MODEL MODEL DEFINES TOTAL PRODUCTIVITY

    MEASURE WHICH INCLUDES ALL THE OUTPUT

    AND INPUT FACTORS

    THE TPM IS BASED ON TANGIBLE OUTPUT AND

    INPUT ELEMENTS WHICH ARE DIRECTLY

    MEASUREABLE AND QUANTIFIABLE

    MODEL ALSO REFLECTS THE IMPACT OF

    INTANGIBLES DIRECTLY eg IF THE TOTALPRODUCTIVITY LEVEL GOES DOWN IN A PERIOD

    IT COULD BE BECAUSE OF POOR QLTY OF RAW

    MATRL WHICH INCREASE THE MATRL INPUT OR

    REDUCED OUTPUT AS A RESULT OF REWORK

  • 8/2/2019 Prod Techniques Old

    43/582

    IMPLEMENTATION PROCESS FOR

    TOTAL PRODUCTIVITY MGT MISSION STATEMENT DEVELOPMENT

    TOTAL PRODUCTIVITY MODEL AND COMPREHENSIVE

    TOTAL PRODUCTIVITY MODEL ANALYSIS

    MGT GOALS DEVELOPMENT FISHBONE ANALYSIS

    ACTION PLANS DEVELOPMENT

    PRODUCTIVITY QUALITY TEAM TRAINING

    IMPLEMENTATION OF ACTION PLANS

    ASSESSING THE EXTENT TO WHICH THE MGT GOALS ARE

    ACHIEVED

    TOTAL PRODUCTIVITY GAINSHARING

    NEW GOALS DEVELOPMENT

  • 8/2/2019 Prod Techniques Old

    44/582

    STEP 1 MISSION

    STATEMENT AN ENTERPRISE WITHOUT A MISSION STATEMENT IS LIKE

    A BUILDING WITHOUT A FOUNDATION

    MOST COMPANIES HAVE SO LITTLE SUCCESS WITH NEW

    IDEAS BECAUSE THEY DONT HAVE A CENTRAL GUIDINGPHILOSOPHY CAPTURED THRU A VISION AND A MISSION

    A VISION REPRESENTS A VERY LONG TERM GOAL

    A MISSION REPRESENTS A SHORT TO MEDIUM TERM

    STATEMENT OF PURPOSE

    A MISSION STRETCHED OVER A RELATIVELY LONG PERIODOF TIME BECOMES A VISION

    A CORRECTLY DRAFTED MISSION SHOULD HAVE SEVERAL

    CHARACTERISTICS

  • 8/2/2019 Prod Techniques Old

    45/582

    FACTORS TO BE CONSIDERED

    IN MISSION STATEMENT HIGHLIGHT MAJOR STRENGTHS

    HIGHLIGHT ENVIRONMENTAL FACTORS

    SUCH AS ECONOMIC,POLITICAL,SOCIAL) STRATEGY FOR COMBATTING

    COMPETITION

    QUALITY OF SERVICE

    STRATEGY FOR SUPPLIERS

    CUSTOMER CHARACTERISTICS

    MARKET CHARACTERISTICS

  • 8/2/2019 Prod Techniques Old

    46/582

    CHARACTERISTICS OF

    GOOD MISSION STATEMENT ARTICULATES GUIDING PHILOSOPHY OF

    ENTERPRISE WITH A CENTRAL FOCUS

    CONCISELY WORDED COMES NATURALLY TO EVERYONE

    DEVELOPED CAREFULLY THRU ACTIVE

    INVOLVEMENT OF EMPLOYEES

    NEEDS TO BE REVISED AS PER THE

    TACTICAL AND STRATEGIC PLANS OF THE

    COMPANY AND THE THEN PREVAILING

    INDUSTRIAL ENVIRONMENTAL OUTLOOK

  • 8/2/2019 Prod Techniques Old

    47/582

    STEP 2 TPM ANALYSIS

    TRENDS DISCOVERY IN

    -TOTAL PRODUCTIVITY-BREAK EVEN POINT OF TOTAL PRODUCTIVITY

    -HUMAN PRODUCTIVITY

    -MATERIALS PRODUCTIVITY-FIXED CAPITAL PRODUCTIVITY

    -WORKING CAPITAL PRODUCTIVITY

    -ENERGY PRODUCTIVITY

    -OTHER EXPENSES PRODUCTIVITY

  • 8/2/2019 Prod Techniques Old

    48/582

    STEP 3 MANAGEMENT

    GOALS FOUR CRITERIA FOR A GOAL TO QUALIFY AS A MGT GOAL

    EVERY MGT GOAL MUST

    -ACHIEVE MISSION STATEMENT

    -BE VERY SPECIFIC

    -BE TIME BASED

    -BE VERIFIABLE

    IN HMT THE GOALS ESTABLISHED WERE

    -INCREASE HUMAN PRODUCTIVITY BY 7% PER YEAR

    -INCREASE OTHER EXPENSE PRODUCTIVITY BY 3.5% YRLY

    -REDUCE INVENTORIES BY 5% INORDER TO INCREASE

    WORKING CAP ITAL PRODUCTIVITY

  • 8/2/2019 Prod Techniques Old

    49/582

    STEP 4 FISHBONE ANALYSIS

    WELL ESTABLISHED TOOL TO ANALYZE

    THE CAUSES FOR A PROBLEM

    FISHBONE ANALYSIS DONE FOR EACH OFMGT GOALS IN STEP 3

    IF A COMPANY CAREFULLY ANALYZES

    ALL TASKS , PROCESSES AND

    TECHNIQUES NEEDED TO ACCOMPLISHEACH MGT GOAL , IT WILL BE BETTER

    EQUIPPED TO ALLOCATE RESOURCES

    TOGOALS THAT WOULD ATTAIN ITS

    MISSION

  • 8/2/2019 Prod Techniques Old

    50/582

    Cause-and-Effect Diagram for

    Manufacturing

    Exhibit S6.8

  • 8/2/2019 Prod Techniques Old

    51/582

    STEP 5 ACTION PLANS

    ACTION PLAN IS DEVELOPED FOR EACH MGT GOAL

    ACION PLAN INCLUDES DETAILS OF TASKS ,START AND

    END DATES,PEOPLE RESPONSIBLE FOR EACH TASK

    ACTION PLAN IS ANOTHER WAY TO CREATE A CAREFULTHOUGHT OUT PLAN OF ACTION TO ACHIEVE A MGT GOAL

    TOOL TO ASSIGN PEOPLE TO TASKS WHICH WHEN

    ACCOMPLISHED WILL ACHIEVE MGT GOALS WHICH IN

    TURN WILL AID ACHIEVEMENT OF VISION AND MISSION

    ACTION PLAN HELPS IDENTIFY BOTTLENECKS

  • 8/2/2019 Prod Techniques Old

    52/582

    STEP 6 PRODUCTIVITY

    QUALITY TEAM TRAINING TRG IS PROVIDED TO ALL

    EMPLOYEES SO THAT THEY HAVE

    THE REQUISITE TOOLS TOACCOMPLISH TASKS IN THE ACTION

    PLANS IN AN EFFECTIVE AND

    EFFICIENT MANNER TRAINING FOCUSES ON PROBLEM

    SOLVING

  • 8/2/2019 Prod Techniques Old

    53/582

    STEP 7 IMPLEMENTATION

    OF ACTION PLANS IMPLEMENTATION BECOMES MORE

    SYSTEMATIC WITH DETAILED

    ACTION PLAN ACTION PLANS ARE CONSTANTLY

    REVISED AS THE TASKS PROGRESS

    THER IS A CONTINUOUS FEEDBACKCONTROL WHICH IS MONITORED

    CAREFULLY

  • 8/2/2019 Prod Techniques Old

    54/582

    STEP 8 MGT GOALS

    ACHIEVED PROGRESS TOWARDS ACHIEVEMENT OF

    GOALS IN STEP 3 ASSESSED ON A

    PERIODIC BASIS SAY QUARTERLY

    IF A GOAL IS NOT ACHIEVED THE ACTION

    PLAN RELATED TO THAT GOAL NEEDS TO

    BE REVIEWED AND CORRECTIVE ACTION

    INITIATED WHICH INCLUDESDOWNSIZING OF GOAL IF ACHIEVEMENT

    IS NOT POSSIBLE DUE TO INTERNAL AND

    EXTERNAL ENVIRONMENTAL CAUSES

  • 8/2/2019 Prod Techniques Old

    55/582

    STEP 9 TOTAL PRODUCTIVITY

    GAIN SHARING BRAINSTORMING APPROACH BASED ON TOTAL

    PRODUCTIVITY

    STEP PROVIDES FOR A TANGIBLE MONETARY INCENTIVE

    TO ACHIEVE THE MAXIMUM POSSIBLE POTENTIAL OF TPM

    REASONS FOR INCLUDING GAIN SHARING IN TPM INCLUDE

    -NEED TO SUSTAIN MOTIVATION IN NEW CONCEPTS.

    INTANGIBLE MOTIVATION IS A NECCESARY CONDITION

    NOT A SUFFICIENT ONE TO SUSTAIN POSITIVE

    MOTIVATION

    -IT IS FAIR TO SHARE GAINS WITH RESPONSIBLE FOR IT

    -RATE OF NEW HIRING CAN BE REDUCED DRAMATICALLY

  • 8/2/2019 Prod Techniques Old

    56/582

    STEP 10 NEW GOALS

    SET NEW GOALS WHEN ALL

    PREVIOUS GOALS HAVE BEEN

    ACHIEVED SET ANNUAL GOALS. THIS LOOKS

    OKAY BUT IN A DYNAMICALLY

    CHANGING SITUATION ANNUALREVIEW OF GOALS MAY BE A BIT

    TOO LATE. NEED TO REVIEW EITHER

    ON A QTRLY BASIS OR WHENEVER

  • 8/2/2019 Prod Techniques Old

    57/582

    HOW PRODUCTIVITY CAN

    BE IMPROVED INCREASING OUTPUT WITH SAME

    INPUT

    INCREASING OUTPUT MORE THANTHE INCREASED INPUT

    DECREASING INPUT FOR SAME

    OUTPUT INCREASING OUTPUT WITH

    DECREASED INPUT

  • 8/2/2019 Prod Techniques Old

    58/582

    BENEFITS OF TOTAL

    PRODUCTIVITY MGT CUSTOMER RESPONSIVENESS

    QUALITY COMPETITIVENESS

    TOTAL COST COMPETITIVENESS TEAM BUILDING AND ACCOUNTABILITY

    TECHNOLOGY PLANNING

    INVESTMENT ANALYSIS ACQUISITION AND MERGER PLANNING

    PROFIT TARGETTING

  • 8/2/2019 Prod Techniques Old

    59/582

    WASTE MANAGEMENT

  • 8/2/2019 Prod Techniques Old

    60/582

    Wasteis anything other than

    the minimum amount of

    equipment, materials, parts,space, and workers time,

    which are absolutely

    essential to add value to the

    product.

    Shoichiro Toyoda

    President, Toyota 1995 Corel Corp.

    Introductory Quotation

  • 8/2/2019 Prod Techniques Old

    61/582

    61

    What is WASTE?

    Any Activity that DOES NOT increase the Market Form

    or Function of the Product or Service based on the

    Critical Customer Requirements.

    These are things the customer is NOT

    willing to pay for.

    DEFINITION OF

  • 8/2/2019 Prod Techniques Old

    62/582

    DEFINITION OFWASTE

    THE OXFORD DICTIONARY DEFINES WASTEAS UNPURPOSEFUL OR EXTRAVAGANTACTIVITY WHICH RESULTS IN

    UNPRODUCTIVE END RESULTS WASTE IS A PRODUCT,ACTIVITY OR

    SERVICE FOR WHICH AN EXTERNALCUSTOMER IS UNWILLING TO PAY FOR

    CASE OF SECURITY CESS IN RAILWAYS WASTE IS ONLY NUISANCE VALUE TO

    CUSTOMER

  • 8/2/2019 Prod Techniques Old

    63/582

    WASTE MANAGEMENT

    WASTE EXISTS EVERYWHERE FROMINDUSTRY TO HUMAN ACTIVITIES

    IN ANY PROCESS WASTE ACCOUNTS FOR

    A VERY LARGE AMOUNT OF NON VALUEADD ACTIVITY

    MGT NEEDS TO CONTROL ACTIVITIESBETTER THRU TIGHTER CONTROL

    WASTE MGT IMPROVES COSTS ANDPRODUCTIVITY AND REDUCES CYCLETIMES

  • 8/2/2019 Prod Techniques Old

    64/582

    MUDA MURI MURA

    3 JAPANESE TERMS USED BY TOYOTA TO

    SIGNIFY DIFFERENT TYPES OF WASTES

    MUDA IS WASTE. TWO TYPES OF WASTE TYPE 1

    MUDA UNAVOIDABLE WASTE OR FORCEDSCRAP(ESSENTIAL NVA);TYPE 2 OR AVOIDABLE

    WASTE

    MURA IS WASTE OF INCONSISTENCY OR

    UNEVENNESS OF FLOW.UNEVENNESS INPRODUCTION FORCES PROCESSES TO DEAL WITH

    SPIKES IN DEMAND AND HAS IDLENESS IN

    SLACK PERIODS

    MURI IS OVERBURDENING OF SYSTEM64

  • 8/2/2019 Prod Techniques Old

    65/582

    65

    Eliminate Waste

    Mudaanything that does not add value

    for the customer

    Products in storageProducts being inspected

    Products waiting in queues

    Defective productsUnnecessary movement of materials or workers

    - 2 TYPES OF WASTES TYPE 1 WASTE WHICH ISESSENTIAL NON VALUE ADD ACTIVITIES AND TYPE 2

    WASTE WHICH IS ELIMINATABLE eg INSPECTION

  • 8/2/2019 Prod Techniques Old

    66/582

    66

    Examples of Waste Idle machine run Waiting for parts

    Counting parts

    Overproduction Moving parts over long distances

    Storing inventory

    Looking for tools

    Machine breakdown

    Rework

  • 8/2/2019 Prod Techniques Old

    67/582

    Common Causes of Waste

    Layout (distance)

    Long setup time

    Incapable processes Poor maintenance

    Poor work methods

    Lack of training

    Inconsistentperformance measures

    Ineffective production

    planning

    Lack of workplaceorganization

    Poor supplyquality/reliability

    C C f W t

  • 8/2/2019 Prod Techniques Old

    68/582

    Common Causes of Waste Excess Manning

    Poor layout and material presentation Rework and extra processes

    Inconsistent / inefficient work methods

    Excess Downtime

    Tooling condition Unreliable equipment

    Long changeovers

    Incapable process

    Defectives - Rework or Replace

    Incapable processes or process not compatiblewith customer expectations or design spec (designfor mfg)

    Tooling condition

    Operator methods and errors

    Where is the Waste?

  • 8/2/2019 Prod Techniques Old

    69/582

    69

    Where is the Waste?

    Defects incomplete or incorrect information

    Overproduction releasing work before nextprocess can work on them, unbalanced work loads

    Waiting unbalanced work loads, slow system response,incomplete information, approvals

    Not Utilizing Employees old guard thinking, politics, high

    turnover, low investment in training

    Transportation poor layout, poor flow

    Inventory large batches, complexity to complete task

    Motion poor organization, no standard work

    Excess Processing excess communication, lack ofcommunication, unnecessary approvals, customer

    requirements are not clearly understood

    All processes have waste.

  • 8/2/2019 Prod Techniques Old

    70/582

    . 9-70

    Types of Waste (Muda)

    in Toyota production system Overproduction

    Waiting

    Transportation

    Inventory

    Motion

    Overprocessing

    Defects

  • 8/2/2019 Prod Techniques Old

    71/582

    PRODUCING DEFECTS

    DEFECTS IN PRODUCT / SERVICE ARE MAJOR SOURCE OF WASTE

    COSTS OF WASTE INCLUDE WARRANTY COSTS,ATTENDINGCOMPLAINTS AS WELL AS REWORK,INSPECTION

    CASE OF DELL COMPUTERS

    PRODUCT DEFECTS TO BE ELIMINATED BY QUALITY ASSURANCE INDESIGN ELIMINATING NEED TO INSPECT OR REWORK

    DEFECTS INCREASE PRODUCTION COSTS AND LEAD TIME OFMANUFACTURE

    DEFECTS DUE TO WRONG OPERATING PROCEDURES,VARIATIONS INOPERATIONS RESULTING IN M/C WEAR,DEFECTIVE RAW

    MATRL,OPERATOR ERROR etc

    TRANSPORTATION AND

  • 8/2/2019 Prod Techniques Old

    72/582

    TRANSPORTATION ANDMATERIAL HANDLING

    ITEMS IN MFG MOVED FROM STATION TO STATION TRANSPORTATION WASTES TIME AND IN THE CASE

    OF HUMAN BEINGS WHO MAY HAVE TO MOVE FROMSTATION TO STATION TO DO WORK IT IS

    FATIGUING AND CAUSES DECLINE INPRODUCTIVITY AND INCREASE IN ERROR RATES OBJECTIVE IS TO MINIMIZE HUMAN EFFORT IN

    TRANSPORTATION AND MATERIAL HANDLING BYHAVING CONVEYOR BELTS

    CASE STUDY OF AUTOMOBILE ASSEMBLY LINEWHERE AUTOMOBILE MOVES ON THE CONVEYORBELT AND MAN IS STATIONARY.TIME REDUCEDFROM 12HRS/CAR TO 1 HR/ASSEMBLY

  • 8/2/2019 Prod Techniques Old

    73/582

    INVENTORY

    INVENTORY AS PER TOYOTA IS ONE OF THE SEVENSINS

    INVENTORY REPRESENTS ITEMS WAITING FORSOMETHING TO HAPPEN (JUST IN CASE)

    INVENTORY IS CARRIED TO PREEMPT DELAYS INDELIVERY OF PROCESS INPUT OR TO PROVIDE FORCUSHION STOCKS TO TAKE CARE OF MFGREWORK/SCRAP (SOME CUSHIONS ACCOUNT FORAS MUCH AS 5% OF RAW MATERIAL)

    WASTES ASSOCIATED WITH HOLDING COSTS,DEPRECIATION, EXPIRY DATES , DETERIORATION.PILFERAGE ETC

    JUST IN TIME IS THE REMEDY FOR EFFECTING ZEROINVENTORY

  • 8/2/2019 Prod Techniques Old

    74/582

    OVERPRODUCTION

    EXCESS PRODUCTION BECAUSE OFWRONG SALES FORECASTS OR ATTEMPTTO KEEP FACILITIES RUNNING

    MFG OF EXCESS PRODUCTION IS WASTE

    CASE OF ALL SALES OF READY MADEGARMENTS

    WASTE FROM OVERPRODUCTION ISREFLECTED IN UNSOLD STOCKS WHICH

    ADD TO FINISHED GOODS INVENTORY

  • 8/2/2019 Prod Techniques Old

    75/582

    WAITING

    WASTE OF WAITING IS EASY TO IDENTIFY

    WAITING IS A RESULT OF UNBALANCEDPROCESS SEQUENCE OR BREAKDOWN INBOTTLENECK PROCESS

    INCLUDES WAITING FOR ORDERS, RAWMATERIAL, POWER, SPARES, LABOUR OR EVENFUNDS TO PROCURE RESOURCES

    WAITING ALSO INCLUDES ITEMS FROM

    PRECEDING PROCESSES EXAMPLE OF PILE UP OF WIP OR PERISHABLES

    AWAITING CUSTOMS CLEARANCE

    WAITING

  • 8/2/2019 Prod Techniques Old

    76/582

    WAITING

    WAITING MINIMIZED BY BUSINESSPROCESS ACTIVITY IMPROVEMENT ORMINIMIZATION OF LEAD TIME TO

    PROCURE THROUGH VENDOR MANAGEDINVENTORY OR OTHER INITIATIVES

    WAITING ALSO MINIMIZED BY GOOD

    MAINTENANCE PRACTICES SUCH AS CBMRESULTING IN MAXIMIZEDEFFECTIVENESS

    PROCESSING

  • 8/2/2019 Prod Techniques Old

    77/582

    PROCESSING

    PROCESS MAY CONTAIN ACTIVITIES WHICH AREINEFFECTIVE OR UNNECCESARY

    PROCESSING WASTE CAN BE ELIMINATED BYMINIMIZING MOTION REQUIRED TO PERFORM

    WORK ACTIVITY ANALYSIS DONE TO DETERMINE

    PROCESS UTILISATION TIME AND THEREAFTER

    PROCESS IMPROVEMENT DONE TO ELIMINATEDELAYS AND NON VALUE ADDED ACTIVITIES

    MOTION

  • 8/2/2019 Prod Techniques Old

    78/582

    MOTION

    BEING IN MOTION IS INCORRECTLY CONNOTED TO BE ATWORK

    MOTION AND WORK ARE NOT THE SAME

    WORK IS CONSIDERED A PARTICULAR KIND OF MOTION THATADDS VALUE

    AN APPARENTLY BUSY PERSON MAY ACTUALLY PRODUCEVERY LITTLE WORK

    INHERENT HANDICAP AT RIGHT HANDED WORKPLACE FORLEFTHANDERS

    MOTION UNREQD TO DO WORK IS WASTE

    EXCESSIVE MOTION CAUSES FATIGUE AND LOSS OFPRODUCTIVITY AND INCREASE OF WASTE

    CASE OF BEARING LIFETIME INVERSELY PROPORTIONAL TORPM

    ROOT CAUSE OF TOYOTA

  • 8/2/2019 Prod Techniques Old

    79/582

    ROOT CAUSE OF TOYOTAWASTES

    USAGE OF 5 WHY ANALYSIS

    DEFECTS

    -INADEQUATE DESIGN POOR MATERIAL

    -WRONG PROCESS SPECIFICATIONS

    -OPERATOR ERROR -INADEQUATE TESTING

    TRANSPORTATION

    -WAIT TIME TO TRAVEL -LAYOUT

    INVENTORY

    -OBSOLETE STOCKSJUST IN CASEWRONGFORECST

    CUSTOMER CANCELLATIONSMKT SLUMP

    OVERPRODUCTION -WRONG FORECAST

    ROOT CAUSE OF TOYOTA

  • 8/2/2019 Prod Techniques Old

    80/582

    OO U O O OWASTES

    WAIT TIME

    -IMBALANCE IN PROCESS THROUGHPUT ORPROCESS BREAKDOWN

    -POOR SCHEDULING -INADEQUATE LABOURSCHEDULING

    MOTION

    -EXCESS MOTIONEXCESS PAPER DISTRIBUTION

    PROCESSING-INEFFECTIVE OR NON VALUE ADDED STEPS

    REMEDIESFOR TOYOTA

  • 8/2/2019 Prod Techniques Old

    81/582

    WASTES

    WASTE REMEDY

    OVERPRODUCTION JIT/PULL PRODUCTIONWAITING PROCESS ACTIVITY STUDY

    TRANSPORTATION MOTION STUDYWRONG PROCESSING METHOD STUDYEXTRA INVENTORY JUST IN TIMEEXTRA MOTION MOTION STUDY

    DEFECTS ROOT CAUSE ANALYSISAND FMECA

    OFFICE WASTES

  • 8/2/2019 Prod Techniques Old

    82/582

    OFFICE WASTES

    ERRORS IN DOCUMENTS

    DOING UNREQUIRED WORK NOT REQUESTED PROCESS OF GETTING APPROVALS AND NEEDLESS LEVELS OF

    APPROVALS BACKLOG OF WORK UNREQUIRED STATIONERY FILES PAPERS AT WORKPLACE UNCLEAR JOB DESCRIPTIONS RESULTING IN UNDEFINED

    OUTCOMES EXCESS DEBIT CREDIT NOTES DUE TO ERRONEOUS PO

    INVOICE OBSOLETE DATABASES TYPOGRAPHICAL ERRORS UNREQUIRED COMMUNICATION

  • 8/2/2019 Prod Techniques Old

    83/582

    TOTAL WASTE REDUCTION

    WASTE MAY EXIST IN PROCEDURES POLICIESSYSTEMS AND IS DIFFICULT TO IDENTIFYHIDDEN WASTES

    AUTOMATION IS NOT THE SOLUTION TO WASTE

    NEED OF THE HOUR IS TO IDENTIFY REALWASTES THAT AFFECT BOTTOM LINES

    WASTE MGT SHOULD BE A CONTINUOUS DRIVEON THE GUIDELINES OF TQM

    PERIODIC REVIEW OFPOLICIES,PROCEDURES,PROCESSES TO ENSUREPROCESS IMPROVEMENT AND WASTEREDUCTION

    LEVELS OF WASTE

  • 8/2/2019 Prod Techniques Old

    84/582

    LEVELS OF WASTE

    FOUR LEVELS OF WASTE-BUSINESS LEVEL WASTES-PLANT LEVEL WASTES

    -PROCESS AND METHOD WASTES-OPERATING LEVEL WASTES

    LEVEL 1 BUSINESS LEVEL

  • 8/2/2019 Prod Techniques Old

    85/582

    LEVEL 1 BUSINESS LEVELWASTE

    LONG TERM AND SHORT TERM GOALS NOT COMMENSURATEWITH CAPABILITIES AND CAPACITY

    SHORT TERM GOALS NOT ALIGNED WITH LONG TERMSTRATEGIC GOALS WHICH ENABLE THE REALISATION OF

    VISION STRATEGIC OBJECTIVES OF EACH FUNCTION NOT IN UNISON

    WITH CORPORATE OBJECTIVES LACK OF COORDINATION AND UNDERSTANDING WITH

    STAKEHOLDERS LOP SIDED FINANCING INSTAL OF EXTRA CAPACITY W/O MAXIMISATION OF

    CURRENT STRATEGIC DIVERSIFICATION IN AREAS WITHOUT

    OPPORTUNITIES AND CORE COMPETENCE INEFFICIENT PRODUCT LIFECYCLE PLANNING AND MGT

    LEVEL 2 PLANT LEVEL WASTE

  • 8/2/2019 Prod Techniques Old

    86/582

    LEVEL 2 PLANT LEVEL WASTE

    POOR PPC NOT BASED ON MARKETDYNAMICS

    HIGH INVENTORIES

    LOW PLANT EFFECTIVENESS ANDUNPROFITABLE OPERATIONS

    HIGH OVERTIME PAYMENTS BUT LOWEMPLOYEE PRODUCTIVITY

    LEVEL 3 PROCESS AND

  • 8/2/2019 Prod Techniques Old

    87/582

    3 OC SSMETHODS LEVEL WASTE

    INCORRECT OR INEFFECTIVEPROCESS METHODS

    BORNE OUT OF LACK OF SKILLS OR

    ATTITUDE

    NEED TO MONITOR AND DO PERIODICMETHOD STUDIES TO MAXIMIZE

    PROCESS THROUGHPUT WITHMINIMUM EFFORT

    LEVEL 4 OPERATIVE LEVEL

  • 8/2/2019 Prod Techniques Old

    88/582

    WASTE

    POOR OPERATIVE CONTROLSRESULTING IN HIGH MFG COSTS

    HIGH REWORK/REJECT CONTENT eg

    .04% value of sales realized thru saleof scrap in 2008-09 and 0.16% valueof sales realized in 2009-10

    UNDULY HIGH REACTIVEMAINTENANCE % ie 17.5% ofmaintenance time against 2% world

    class (includes 7% breakdown)

  • 8/2/2019 Prod Techniques Old

    89/582

    Root cause of waste

    Defects

    Inadequate Design - Poor Matrl - Wrong Proc - Oper Error

    Inadequate Testing

    Over Production

    Over enthusiastic incentive - Wrong Forecast

    Excess Inventory

    Obsolete Stocks - Wrong Forecast - Customer amendments/cancellation

    Poor Quality - Market Condition

    Unrequired Motions

    Over use of paper/distribution - Excess Walking - Excess Motions

    Transportation Layout - wait time to travel

    Wait Time

    Poor Scheduling - Imbalance in prodn line - Inadequate labor resource

  • 8/2/2019 Prod Techniques Old

    90/582

    Root cause of waste

    Process

    Wrong operations or poor material leading to rework orreject

    Poor process control Poor operating specifications

    Untrained or de motivated operators

  • 8/2/2019 Prod Techniques Old

    91/582

    NON VALUE ADDED

    ACTIVITIES

  • 8/2/2019 Prod Techniques Old

    92/582

    BUSINESS PROCESSES

    EVERYTHING WE DO IS A PROCESS AND CONSISTS OF INPUTSPROCESSING AND OUTPUT

    PROCESS TAKES INPUT FROM SUPPLIERS,ADDS VALUE ANDDELIVERS OUTPUT TO CUSTOMER

    CUSTOMER COULD BE INTERNAL OR EXTERNAL AND SUPPLIER

    COULD BE THE SAME AS CUSTOMER PROCESSES ARE SET OF LOGICALLY RELATED ACTIVITIES

    LINKED BY RULES WHICH COMBINE TO DELIVER VALUE TOCUSTOMERS ACROSS FUNCTIONAL LINES . THEY USEPREDETERMINED LOGIC RULES TO PROCESS INPUTS

    PROCESSES USE INPUTS FROM SUPPLIERS SUCH AS INFORMATIONSKILLS TRAINING PEOPLE,EQUIPMENT,MATERIAL,PROCEDURES

    METHODS SPECIFICATIONS SERVICES KNOWLEDGE AND VOICEOF CUSTOMER

    PROCESS PROCESSES INPUTS AS PER THE BUSINESS RULES ANDACTIVITY DEPENDENCIES

    PROCESSES OUTPUT PRODUCTS SERVICES INFORMATION TOCUSTOMERS

    OUTPUTS RESULT IN OUTCOMES WHICH ARE MEASURES

    OUTCOMES ARE COMPARED WITH TARGETS AND RESULT IN

    PROCESS MECHANICS

  • 8/2/2019 Prod Techniques Old

    93/582

    MATERIALS

    PROCEDURES

    METHODS DATA

    PEOPLE WITH SKILLS

    KNOWLEDGE

    MANAGEMENT

    TRAINING

    EQUIPMENT

    FINANCE

    BUSINESS RULES CONTROLS

    ACTIVITIES

    DEPENDENCIES

    CONSTRAINTS

    CAPABILITY

    PRODUCTS

    SERVICES

    INFO

    WASTE

    INPUTS OUTPUTS CUSTOMER

    VOICE OF THE

    CUSTOMER

    VOICE OF PROCESS

    INPUTS PROCESS OUTPUTS

    ACTIVITIES IN AN

  • 8/2/2019 Prod Techniques Old

    94/582

    ACTIVITIES IN AN

    ORGANIZATION EVERY THING WE DO IN A COMPANY IS A

    PART OF A LARGER PROCESS WHICH IS

    EXECUTED TO ACHIEVE BUSINESS

    RESULTS

    PROCESS COMPRISES OF SUB PROCESSES

    SUB PROCESS IS DIDIDED INTO

    ACTIVITIES WHICH CAN BE // OR INSEQUENCE

    ACTIVITIES CAN BE DIVIDED INTO

    INDIVISIBLE TASKS

    PROCESS DECOMPOSITION INTO ACTIVITIES

    ORDER TO

  • 8/2/2019 Prod Techniques Old

    95/582

    ORDER TO

    CASH

    ORDER

    PROCESSING

    PLAN TO

    PRODUCE

    DELIVER

    NET MRP

    MFG WO

    PROCURE

    TO PAY

    RECEIVE

    CASH

    ACCEPT

    TO

    INVOICE

    DELY TOACCEPT

    TENDER

    TO PO OR

    PR TO PO

    OPTIONAL

    PO TO

    TENDER

    INDENT

    TO PR

    INVOICE

    TO PAY

    AWARD TOSUPPLIER

    WRITE PROCURE

    DETAILS WITH

    QTY, RATE, DELVY

    SCHEDULE,ETC

    MULTI LEVEL

    APPROVALAPPROVE PODESPATCH PO

    ACTIVITIES

    VALUE AND NON VALUE ADD

  • 8/2/2019 Prod Techniques Old

    96/582

    VALUE AND NON VALUE ADD

    ACTIVITIES MANY ACTIVITIES PERFORMED WHILE WORKING AND ARE

    THE BUSINESS OUTCOMES OF PROCESSES

    VALUE ADD ACTIVITIES ARE THOSE WHICH CUSTOMER ISWILLING TO PAY FOR

    NON VALUE ADD ACTIVITIES ARE THOSE ACTIVITIESWHICH THE CUSTOMER WILL NOT PAY FOR

    NON VALUE ADD ACTIVITIES MAY BE ESSENTIAL egSAFETY OR NON ESSENTIAL

    PROCESS IMPROVEMENT NEEDS TO BE DONE ONESSENTIAL ACTIVITIES TO REDUCE COSTS,TIME ANDRESOURCES

    NON VALUE ADD ACTIVITIES NEED TO BE EITHERELIMINATED OR MINIMISED AS THESE ACTIVITIES ONLYADD TO THE COSTS

    VALUE ADDED ASSESSMENT

  • 8/2/2019 Prod Techniques Old

    97/582

    ACTIVITY

    REQD TO

    PRODUC

    E O/P

    CONTRI

    BUTES

    TO CUST

    REQMT

    REQD TO

    PRODUC

    E O/P

    ESSENTIAL NON

    VALUE ADD

    NON VALUE

    ADD

    REAL VALUE ADD

    Y

    NY

    N

    NY

    ACTIVITY

  • 8/2/2019 Prod Techniques Old

    98/582

    MAPPING AS-IS

    INDENT TO

    PURCHASE

    ACTIVITY MAPPING AS-IS

    INDENT TO PURCHASE

  • 8/2/2019 Prod Techniques Old

    99/582

    INDENT TO PURCHASE

  • 8/2/2019 Prod Techniques Old

    100/582

  • 8/2/2019 Prod Techniques Old

    101/582

    ACTIVITY MAPPING

    AS-IS INDENT TO

  • 8/2/2019 Prod Techniques Old

    102/582

    S S N N O

    PURCHASE

    ACTIVITY MAPPING

    AS-IS INDENT TO

  • 8/2/2019 Prod Techniques Old

    103/582

    PURCHASE

    ACTIVITY MAPPING TO BE TO

    BE INDENT TO PURCHASE

  • 8/2/2019 Prod Techniques Old

    104/582

    ACTIVITY MAPPING

    TO BE INDENT TO

  • 8/2/2019 Prod Techniques Old

    105/582

    PURCHASE

    ACTIVITY MAPPING

    TO BE INDENT TO

  • 8/2/2019 Prod Techniques Old

    106/582

    PURCHASE

  • 8/2/2019 Prod Techniques Old

    107/582

    ACTIVITY MAPPING

    TO BE INDENT TO

  • 8/2/2019 Prod Techniques Old

    108/582

    PURCHASE

  • 8/2/2019 Prod Techniques Old

    109/582

    PROCESS WASTE

  • 8/2/2019 Prod Techniques Old

    110/582

    WASTE MANAGEMENT

    WASTE EXISTS EVERYWHERE FROMINDUSTRY TO HUMAN ACTIVITIES

    IN ANY PROCESS WASTE ACCOUNTS FOR

    A VERY LARGE AMOUNT OF NON VALUEADD ACTIVITY

    MGT NEEDS TO CONTROL ACTIVITIESBETTER THRU TIGHTER CONTROL

    WASTE MGT IMPROVES COSTS ANDPRODUCTIVITY AND REDUCES CYCLETIMES

    LEVELS OF WASTE

  • 8/2/2019 Prod Techniques Old

    111/582

    LEVELS OF WASTE

    FOUR LEVELS OF WASTE-BUSINESS LEVEL WASTES-PLANT LEVEL WASTES

    -PROCESS AND METHOD WASTES-OPERATING LEVEL WASTES

  • 8/2/2019 Prod Techniques Old

    112/582

    LEVELS OF WASTE

    FOUR LEVELS OF WASTE:-LEVEL 1 refers to business related wastes. It includeswastes due to cross functional issues, poor communicationand coordination between vendors, customers and even

    poor investment decisions-LEVEL 2 refers to plant level wastes. It includes faultyproduction planning and control, poor layout resulting inun required movement and WIP It includes poor m/ccapability resulting in rework, scrap and rejection. It alsoincludes poor maintenance policies

  • 8/2/2019 Prod Techniques Old

    113/582

    LEVEL 1 BUSINESS LEVEL

  • 8/2/2019 Prod Techniques Old

    114/582

    LEVEL 1 BUSINESS LEVEL

    WASTE

    Faulty performance measure

    Poor business policies and short sightedness at top

    level

    Poor communication and coordination between

    vendors and customers

    Too much emphasis on utilization of resources

    Excess production

    Poor product and process design

    LEVEL 1 BUSINESS LEVELWASTE

  • 8/2/2019 Prod Techniques Old

    115/582

    WASTE

    LONG TERM AND SHORT TERM GOALS NOT COMMENSURATEWITH CAPABILITIES AND CAPACITY SHORT TERM GOALS NOT ALIGNED WITH LONG TERM

    STRATEGIC GOALS WHICH ENABLE THE REALISATION OFVISION

    STRATEGIC OBJECTIVES OF EACH FUNCTION NOT IN UNISON

    WITH CORPORATE OBJECTIVES LACK OF COORDINATION AND UNDERSTANDING WITH

    STAKEHOLDERS LOP SIDED FINANCING INSTAL OF EXTRA CAPACITY W/O MAXIMISATION OF

    CURRENT

    STRATEGIC DIVERSIFICATION IN AREAS WITHOUTOPPORTUNITIES AND CORE COMPETENCE

    INEFFICIENT PRODUCT LIFECYCLE PLANNING AND MGT

    LEVEL 2-PLANT LEVEL

  • 8/2/2019 Prod Techniques Old

    116/582

    LEVEL 2 PLANT LEVEL

    WASTES

    Play safe tendency

    Poor production planning and control

    Poor layout resulting in back tracking andexcessive traveling

    WIP inventory

    Batch size constraints

  • 8/2/2019 Prod Techniques Old

    117/582

    LEVEL 3-PROCESS AND

  • 8/2/2019 Prod Techniques Old

    118/582

    LEVEL 3 PROCESS AND

    METHOD WASTES

    Poor sequencing of machines and

    operations

    Long changeover times Poor work place design

    Tendency of temporary storage

    Incapable and poorly maintained equipment

    Unsafe methods

    LEVEL 3 PROCESS ANDMETHODS LEVEL WASTE

  • 8/2/2019 Prod Techniques Old

    119/582

    METHODS LEVEL WASTE

    INCORRECT OR INEFFECTIVEPROCESS METHODS

    BORNE OUT OF LACK OF SKILLS OR

    ATTITUDE NEED TO MONITOR AND DO PERIODIC

    METHOD STUDIES TO MAXIMIZE

    PROCESS THROUGHPUT WITHMINIMUM EFFORT

    LEVEL 4-MACHINE/OPERATOR

  • 8/2/2019 Prod Techniques Old

    120/582

    LEVEL 4 MACHINE/OPERATOR

    LEVEL WASTES

    Poor housekeeping

    Excess bending and fatigue

    Lack of operator training Operator has to frequently fetch material for

    production

    LEVEL 4 OPERATIVE LEVELWASTE

  • 8/2/2019 Prod Techniques Old

    121/582

    WASTE

    POOR OPERATIVE CONTROLSRESULTING IN HIGH MFG COSTS

    HIGH REWORK/REJECT CONTENT

    UNDULY HIGH REACTIVEMAINTENANCE %

    OFFICE WASTES

  • 8/2/2019 Prod Techniques Old

    122/582

    ERRORS IN DOCUMENTS DOING UNREQUIRED WORK NOT REQUESTED PROCESS OF GETTING APPROVALS AND NEEDLESS LEVELS OF

    APPROVALS BACKLOG OF WORK UNREQUIRED STATIONERY FILES PAPERS AT WORKPLACE

    UNCLEAR JOB DESCRIPTIONS RESULTING IN UNDEFINEDOUTCOMES EXCESS DEBIT CREDIT NOTES DUE TO ERRONEOUS PO

    INVOICE OBSOLETE DATABASES TYPOGRAPHICAL ERRORS UNREQUIRED COMMUNICATION

    TOTAL WASTE REDUCTION

  • 8/2/2019 Prod Techniques Old

    123/582

    TOTAL WASTE REDUCTION

    STRUCTURED APPROACH TO DEAL WITH

    WASTES AND DELAYS WITH VIEW TO

    ELIMINATION

    APPROACH SEPARATES WASTE(NON

    VALUE ADD ACTIVITIES) FROM VALUE

    ADDITION AND SCRUTINISES ESSENTIAL

    NON VALUE ADD ACTIVITIES FORMINIMISATION OF WASTEFUL ACTIVITIES

    PREREQUISITE FOR TQM

    TOTAL WASTE REDUCTION

  • 8/2/2019 Prod Techniques Old

    124/582

    TOTAL WASTE REDUCTION

    WASTE MAY EXIST IN PROCEDURES POLICIESSYSTEMS AND IS DIFFICULT TO IDENTIFYHIDDEN WASTES

    AUTOMATION IS NOT THE SOLUTION TO WASTE

    NEED OF THE HOUR IS TO IDENTIFY REALWASTES THAT AFFECT BOTTOM LINES

    WASTE MGT SHOULD BE A CONTINUOUS DRIVEON THE GUIDELINES OF TQM

    PERIODIC REVIEW OF

    POLICIES,PROCEDURES,PROCESSES TO ENSUREPROCESS IMPROVEMENT AND WASTEREDUCTION

    TOTAL WASTE REDUCTION

  • 8/2/2019 Prod Techniques Old

    125/582

    TOTAL WASTE REDUCTION

    DRASTICALLY IMPROVES QLTY,PRODUCTIVITY,FLEXIBILITY AND SAFETY

    REDUCES CYCLE TIME AND IMPROVESRESPONSIVENESS

    MAXIMIZES UTILIZATION OF ASSETS ANDPROCESSES

    MINIMISES [PROCESS LOSSES AND COST OF NONCONFORMITY

    REDUCES PROCESS AND PRODUCT COST AND

    IMPROVES CONTRIBUTIONS IMPROVES LIQUIDITY BY FREEING MONEY TIED

    UP IN INVENTORIES AND OTHER WASTES

    TOYOTA 7 WASTES

  • 8/2/2019 Prod Techniques Old

    126/582

    TOYOTA 7 WASTES

    PRODUCTION DEFECTS

    TRANSPORTATION

    INVENTORY OVER PRODUCTION

    WAITING

    PROCESSING

    MOTIONS AND EFFORT

    OTHER( ) WASTES

  • 8/2/2019 Prod Techniques Old

    127/582

    OTHER(canon) WASTES

    WASTED CAPACITY

    WASTED ENERGY

    WASTE FROM LOST OPPORTUNITY

    WASTE FROM UNREQD EXPENSES

    WASTE FROM UNUTILISED TALENT WASTE FROM LOSSES DUE TOEFFICIENCY,STARTUP,IDLING, BATCH CHANGEOVER

    WASTE DUE TO COMMN LOSSES OR INEFFECTIVENESS OFCOMMN

    WASTED PLANNING EFFORTS

    WASTED INVESTMENTS WASTED OVERSTAFFING

    WASTE IN DISPOSAL

    ELIMINATION OF 3M

  • 8/2/2019 Prod Techniques Old

    128/582

    ELIMINATION OF 3M

    3M STAND FOR MUDA MURA AND MURI

    MUDA MEANS WASTES OF ALL KINDSSUCH AS

    REWORK,TRANSPORTATION,DELAYS MURA MEANS INCONSISTENCES SUCH ASNON CONFORMANCE TO QLTY AND STDOPERATING PROCEDURES

    MURI MEANS NON RATIONALITY ORDISCREPANCY ie UNSCIENTIFIC WAY OFDOING THINGS

    ELIMINATION OF 3M

  • 8/2/2019 Prod Techniques Old

    129/582

    ELIMINATION OF 3M

    3M EXERCISE DONE TO

    -ELIMINATE WHOLE ACTIVITY

    -REDUCE STEPS IN ACTIVITY-CHANGE AND SIMPLIFY ACTIVITY

    -REDUCE THE TIME COST AND

    FATIGUE INVOLVED IN ACTIVITY

    MUDA

  • 8/2/2019 Prod Techniques Old

    130/582

    MUDA

    MUDA MEANS WASTE

    WASTE IS ANY ACTIVITY THAT DOES NOT ADD VALUE

    SUCH ACTIVITIES CONTRIBUTE TO COST OF POOR

    QUALITY

    MUDA IS TOTAL COST OF EXTERNAL PRODUCT/SERVICE

    FAILURE PLUS THE COST OF PREVENTIVE MEASURES

    MUDA DEFINED IN TOYOTA 7 WASTES AND CANON 9

    WASTES

    ELIMINATING MUDA REDUCES COST OF PRODN ,

    ENHANCES PRODUCTIVITY , REDUCES CYCLE TIME , AND

    LEADS TO BETTER CUSTOMER SATISFACTION

    8 types of Muda

  • 8/2/2019 Prod Techniques Old

    131/582

    1.Muda of over-production2. Muda of waiting

    3. Muda of transport

    4. Muda of processing

    5. Muda of inventory

    6. Muda of motion

    7. Muda of repair/rejects

    8. Muda of Untapped Human potential

    MURI

  • 8/2/2019 Prod Techniques Old

    132/582

    MURI

    MURI MEANS UNREASONABLE OR IRRATIONAL

    APPROACH TO ANY OPERATION

    KAIZEN CHECKLIST TRIES TO LOOK INTO IMPROVEMENT

    BY IDENTIFYING AND ELIMINATING THE

    UNREASONABLENESS IN AREAS SUCH ASMANPOWER,TECHNIQUE,METHOD,TIME,FACILITIES,TOOLS,

    MATERIALS,INVENTORY,PLACE,PRODUCTION,,QUANTITY,

    QUALITY, etc

    MURI LOOKS FOR IRRATIONALITY WITH FOUR MAJOR

    APPROACHES

    M ri

  • 8/2/2019 Prod Techniques Old

    133/582

    Muri

    Muri = Physical Strain

    Bend to work?

    Push hard?

    Lift weight?

    Repeat tiring action?

    Wasteful walk?

    All this is Muri

    4 APPROACHES OF MURI

  • 8/2/2019 Prod Techniques Old

    134/582

    4 APPROACHES OF MURI

    THINGS OR ACTIVITIES THAT ARE EXTREMELY DIFFICULT

    TO DO AND AT THE MOMENT BEYOND REACH SHOULD BE

    IDENTIFIED AND ELIMINATED FROM ACTIVITIES

    DO NOT PURSUE ACTIVITIES THAT DO NOT ADD VALUE

    IDENTIFY AND REFINE REASONS FOR PERFORMINGACTIVITIES

    ELIMINATE IRRATIONAL OPERATIONS THAT CAUSE

    FATIGUE

    MURA

  • 8/2/2019 Prod Techniques Old

    135/582

    MURA

    INCONSISTENCY IN OPERATIONS

    DEVIATION FROM STANDARDS

    LEADING TO INCONSISTENCY MURA CALLS FOR MINIMUM

    DEVIATION BETWEEN BEST AND

    WORST PRODUCT BY MINIMIZINGRANGE OF STD DEVIATION USING

    SPC

    MUDA (WASTE) EXPLAINED OVERPRODUCTION WASTE

  • 8/2/2019 Prod Techniques Old

    136/582

    OCCURS WHEN WE PRODUCE WHAT IS UNNECESSARY, WHEN IT ISUNNECESSARY, AND IN UNNECESSARY AMOUNT.

    INVENTORY WASTE

    INVENTORY-SYMPTOM OF ILL HEALTH IN FACTORY OPERATIONS. INVENTORYAVOIDS BUT NEVER SOLVES PROBLEMS.

    CONVEYANCE WASTE

    IS A RESULT OF POOR LAYOUT, HANDLING, OF MATERIAL ETC.

    . DEFECT PRODUCTION WASTE

    HUMAN ERRORS CAUSE DEFECTS, DEFECTS ARE WASTE AND ALSO CAUSE

    WATE OF DETECTION, CORRECTION, CUSTOMER COMPLAINTS ETC. THEYALSO DISRUPT NORMAL FLOW OF GOODS AND REDUCE PRODUCTIVITY

    . PROCESS-RELATED WASTE

    EXAMPLES:

    I. DRILLING MACHINE SCREW HOLES, EVEN AFTER DESIGN HAS CHANGEDTHE FASTENING METHOD TO WELDING

    II. USING SIX SCREWS WHERE FOUR MEET THE PURPOSE.

    OPERATION RELATED WASTENOT ALL OF WORKERS MOVEMENT IS WORK OR VALUE-ADDING, SUCHWASTE RESULTS FROM POOR EQUIPMENT LAYOUT OR BY POORLY PLACEDPARTS, JIGS & TOOLS.

    IDLE TIME WASTE

    INCLUDES HUMAN AS WELL AS MACHINE IDLE TIME. GENERALLY IT IS THETIME OF WAITING FOR SOMETHING.

    EFFORTS REQUIRED IN WASTE MGTINITIATIVE

  • 8/2/2019 Prod Techniques Old

    137/582

    ELIMINATING WASTE REQUIRES A COMPANYWIDE

    INTEGRATED EFFORT WHICH INCLUDES ALLCORPORATE FUNCTIONS SUCH ASMARKETING,SALES,FINANCE,MANUFACTURING,R&D.

    INDUSTRIAL ENGG, QUALITY,CUSTOMER SERVICE,

    DISTRIBUTION,HR ETC

    WASTE AS SEEN COMPRISES OF MFG AND ADMINWASTES

    ADMIN WASTES COULD BE EXCESSIVECOMMUNICATION,UNCONTROLLED DISTRIBUTION OF

    INFORMATION, DELAYED INFORMATION ,BREAKDOWNIN ADMIN SERVICES, ERRORS IN COMMERCIALDOCUMENTS,WASTED SALES CALLS,UNPRODUCTIVEMEETINGS ETC

    COST OF I.T. /INFRASTRUCTURE DOWNTIME A MAJOR

    ISSUE AND NEED FOR BUSINESS CONTINUITY PLAN

    Root cause of waste

  • 8/2/2019 Prod Techniques Old

    138/582

    Root cause of waste

    Defects

    Inadequate Design - Poor Matrl - Wrong Proc - Oper Error

    Inadequate Testing

    Over Production

    Over enthusiastic incentive - Wrong Forecast

    Excess Inventory Obsolete Stocks - Wrong Forecast - Customer amendments/cancellation

    Poor Quality - Market Condition

    Unrequired Motions

    Over use of paper/distribution - Excess Walking - Excess Motions

    Transportation

    Layout - wait time to travel

    Wait Time

    Poor Scheduling - Imbalance in prodn line - Inadequate labor resource

    Root cause of waste

  • 8/2/2019 Prod Techniques Old

    139/582

    Root cause of waste

    Process

    Wrong operations or poor material leading to rework orreject

    Poor process control Poor operating specifications

    Untrained or de motivated operators

  • 8/2/2019 Prod Techniques Old

    140/582

    DEFINITION OF VALUE

  • 8/2/2019 Prod Techniques Old

    141/582

    DEFINITION OF VALUE

    VALUE IS A WORD USED WITHOUTUNDERSTANDING THE MEANING

    DIFFERENT DEPTS OF SAME COMPANYHAVE VARIED MEANING

    DESIGNER RELATES VALUE WITHRELIABILITY

    MFG RELATES WITH COST OF MFG

    PURCHASE RELATES WITH COST OF RM

    SALES RELATES TO THE PRICE CUSTOMERIS WILLING TO PAY

    DEFINITION OF VALUE

  • 8/2/2019 Prod Techniques Old

    142/582

    DEFINITION OF VALUE

    VALUE IS THE RELATIONSHIP BETWEEN COST AND QLTY

    VALUE = QUALITY/COST

    VALUE IS PLACED FOR VARIOUS ATTRIBUTES MORE POPULARLYKNOWN AS FUNCTIONS OF A PRODUCT

    TWO TYPES OF FUNCTIONS

    -PRIMARYSECONDARY PRIMARY FUNCTIONS ARE THOSE ATTRIBUTES FOR WHICH APRODUCT IS PURCHASED AND MEANT TO BE USED eg THEPRIMARY FUNCTION OF A CAR IS TO SAFELY TRANSPORT PEOPLEBETWEEN TWO POINTS WITH FUEL ECONOMY

    SECONDARY FUNCTIONS ARE THOSE ATTRIBUTES WHICH ARENOT PRIMARY FUNCTIONS BUT WHICH PEOPLE WISH TO SEE AS

    ATTRIBUTES OR FUNCTIONSS IN A PRODUCT eg IN A CAR WEALSO WISH TO HAVE A/C AND OTHER ACCESSORIES

  • 8/2/2019 Prod Techniques Old

    143/582

    VALUE ENGG/ANALYSIS

  • 8/2/2019 Prod Techniques Old

    144/582

    VALUE ENGG/ANALYSIS

    ENGINEERING IS A PROCESS OF ASSESSMENT OF APRODUCT DURING DESIGN PHASE

    ANALYSIS IS ASSESSMENT OF A PRODUCT DURING USAGE

    OBJECTIVE IS TO ELIMINATE UNREQD FEATURES ANDFUNCTIONS IN PRODUCT DESIGN

    MOST ACTIVITIES PERFORMED IN ANALYSIS PHASE VA TEAM ASSIGNS A VALUE TO EACH FUNCTION AND

    FINDS COSTS TO DELIVER FUNCTION AND RATIO OFVALUE TO COST IS CALCULATED

    RATIO IMPROVED BY REDUCING COST OF ITEM ORINCREASING WORTH

    VALUE ENGG/ANALYSIS

  • 8/2/2019 Prod Techniques Old

    145/582

    VALUE ENGG/ANALYSIS

    VALUE ANALYSIS IS A MGT TECHNIQUEFOR REDUCING MFG COSTS AND ///LYIMPROVING QLTY AND RELIABILITY OFPRODUCT

    VALUE ENGG IS USED TO COVER THEINITIAL DESIGN STAGE

    VALUE MEANS DIFFERENT THINGS TODIFFERENT PEOPLE AT DIFFERENT TIME

    VALUE OF AN ITEM DETERMINED ON THEBASIS OF VARIOUS ASPECTS:

    FOUR WAYS TO INCREASING

  • 8/2/2019 Prod Techniques Old

    146/582

    VALUE OF FUNCTION

    DECREASE COST AND MAINTAIN

    PERFORMANCE LEVEL eg NANO

    INCREASE PERFORMANCE AT SAME COST

    eg TOOTHPASTE/AERATED DRINKS

    DECREASE COST AND ENHANCE

    PERFORMANCE eg PC HARDWARE

    INCREASE BOTH COST ANDPERFORMANCE BUT PERFORMANCE

    INCREASE > COST INCREASE eg BUFFETS

    TYPES OF VALUE

  • 8/2/2019 Prod Techniques Old

    147/582

    TYPES OF VALUE COST VALUE IS SUM OF ALL COSTS INCURRED IN MFG OF PRODUCT eg

    MATRL LABOUR TOOLING O/H USE VALUE IS THE COST INCURRED TO MAKE PRODUCT FUNCTIONAL

    eg QLTY COSTS INCURRED TO ENSURE A/C COOLS TO REQDTEMPERATURE

    ESTEEM VALUE IS THE COST INCLUDED INTO PRODUCT TO ENHANCECUSTOMER APPEAL

    Eg IN SOME CASES THE MOTOR CAR ESTEEM VALUE > USE VALUE INTERMS OF FUEL CONSUMPTION LIKE IN THE CASE OF A MERCEDESBENZ WHICH GIVES ONLY 6 KM/LTR AGAINST THE AVERAGE 15-18KM/LTR IN OTHER BRANDED CARS

    EXCHANGE VALUE IS THE VALUE OF PROPERTIES WHICH ENABLESAN ITEM TO BE EXCHANGED FOR SOMETHING ELSE .EXCHANGEVALUE IS GENERALLY RESALE VALUE. Eg REAL ESTATE EXCHANGEVALUE IS INFLATED BY 20% EVERY YEAR

    PLACE VALUE IS VALUE OF PROPERTY/EQUIPMENT WHICH VARIES INPRICE WRT LOCATION eg IN MUMBAI REAL ESTATE IS MOREEXPENSIVE IN WESTERN SUBURBS THAN IN EAST

    TIME VALUE IS PROPERTY OF PRODUCT/SERVICE RENDERED AT THERIGHT TIME eg THE TIMING OF AN EMERGENCY OPERATION ISCRITICAL FOR SURVIVAL OF THE PATIENT

    VALUE ENGG/ANALYSIS

  • 8/2/2019 Prod Techniques Old

    148/582

    VALUE ENGG/ANALYSIS

    ECONOMIC WORTH = COST VALUE + EXCHANGEVALUE + USE VALUE + ESTEEM VALUE + PLACEVALUE + TIME VALUE

    REAL WORTH = ECONOMIC WORTH/COST VALUE

    REAL WORTH = WORTH/LIFE CYCLE COST

    FOCUS OF VE TO INCREASE REAL VALUE OFPRODUCT PROCESS OR SERVICE

    VE/VA GENERALLY RESULTS IN COST

    REDUCTION

    QUESTIONS IN VALUE

  • 8/2/2019 Prod Techniques Old

    149/582

    ANALYSIS

    CAN WE DO WITHOUT IT

    DOES IT DO MORE THAN REQD

    DOES IT COST MORE THAN IT IS WORTH

    CAN SOMETHING ELSE SUBSTITUTE IT CAN TWO PARTS BE COMBINED OR CAN ONE

    COMPONENT BE MADE INTO TWO

    CAN IT BE MADE IN A LESS COSTLY METHODWITH LESS COSTLY MATRL

    CAN IT BE MADE CHEAPER BETTER OR FASTER

    WHAT NEW PROCESSES CAN WE USE

    QUESTIONS IN VALUE

  • 8/2/2019 Prod Techniques Old

    150/582

    ANALYSIS

    CAN AN ALTERNATIVE MATRL BE USED

    CAN ANY DIMENSIONS BR REDUCED TOUSE LESS MATRL

    CAN AMOUNT OF WASTE BE REDUCED CAN PARTS BE STANDARDISED

    CAN TWO PARTS BE COMBINED

    IS BUYING CHEAPER THAN MAKING

    WHAT IS THE COST OF ADHERING TOSPECS

    WHAT NEW PROCESSES CAN BE USED

    WAYS TO INCREASE VALUE

  • 8/2/2019 Prod Techniques Old

    151/582

    BY VE

    REDUCE FUNCTIONS WITH CUTCORNERS EXERCISE

    KEEP FUNCTIONS UNCHANGED BUTREDUCE COSTS

    INCREASE FUNCTIONS BUT RETAINCOSTS

    INCREASE FUNCTIONS MORE THANCOST INCREASE

    USES OF VALUE ENGINEERING

  • 8/2/2019 Prod Techniques Old

    152/582

    USES OF VALUE ENGINEERING

    COST PREVENTION AND ELIMINATIONTECHNIQUE TO REDUCE COST OF PRODUCT

    ENABLES BETTER UNDERSTANDING OF EMPLJOBS

    BALANCES COST AND PERFORMNCE

    PREVENTS OVER DESIGN OF COMPONENTS

    MOTIVATES EMPL TO GIVE CREATIVE IDEAS

    INCREASES PROFITS AND DEFLATES COSTS

    HELPS SATISFY CUSTOMERS WITH PRODUCTS

  • 8/2/2019 Prod Techniques Old

    153/582

    WHEN TO APPLY VA

  • 8/2/2019 Prod Techniques Old

    154/582

    WHEN TO APPLY VA

    PRODUCTS ARE LOSING THEIR MKT

    SHARE AND THERE IS DECLINE IN SALES

    PRODUCTS ARE PRICED HIGHER THAN

    COMPETITION IN A PRICE SENSITIVE MKTOR PRODUCT COST IS > SALES PRICE OF

    COMPETITION

    NEW DESIGNS TO BE UNDERTAKEN RISING MFG COSTS

    REASONS FOR UNNECCESARY

  • 8/2/2019 Prod Techniques Old

    155/582

    COSTS

    LACK OF RELEVANT INFO LEADS TO

    WRONG DECISIONS WHICH

    INCREASE COSTS

    WRONG BELIEFS FROM ACCEPTING

    OPINIONS

    LACK OF IDEAS

    DIFFERENCE BETWEEN VE

    AND OTHER COST REDUCTION

  • 8/2/2019 Prod Techniques Old

    156/582

    AND OTHER COST REDUCTION

    TECHNIQUES TRADITIONAL TECHNIQUES ARE POST PRODUCTION ORIENTEDAND CONCENTRATION IS ON THE PART OR ELEMENT INCONTRAST TO VALUE ANALYSIS WHICH IS FUNCTION ORIENTED

    OTHER TECHNIQUES TRY TO REDUCE THE COST BY EXISTINGMETHOD WHEREAS VA NEVER CONSIDERS ANY PROCESSMETHOD OR ELEMENT GRANTED AND IT ANALYSES BY

    FUNCTION RATHER THAN PART OR ELEMENT COST REDUCTION CAN REDUCE THE COSTS UPTO 10% WHEREAS

    VA CAN REDUCE COSTS UPTO 40-50% WITHOUT SACRIFICINGQLTY AND PERFORMANCE

    VALUE ANALYSIS QUESTIONS THE VERY EXISTENCE OF PARTSOR PROCESS BY ANALYSIS OF ITS DESIGN SPECIFICATIONS,MATRLS AND PROCESS OF MFG

    COST REDUCTION IS COST ORIENTED AND CONCENTRATES ONFINDING THE CHEAPER COST WHEREAS VALUE ANALYSIS ISFUNCTION ORIENTED AND TRY TO PRODUCE THE PRODUCT ATLOWEST COST WITHOUT SACRIFICING QLTY AND PERFORMANCE

    STRATEGIC STEPS IN VALUE

    ANALYSIS

  • 8/2/2019 Prod Techniques Old

    157/582

    ANALYSIS

    DETERMINE FUNCTION AND COST OFEACH ELEMENT IN FINISHED PROD

    CONSIDER ALTERNATIVES THAT FULFILFUNCTIONS

    SELECT BEST ALTERNATIVE WHICHINCLUDES MATRL,STANDARDISATION OFDIMENSIONS

    STRATEGIC CHOICE OF MAKE EXPENSIVE

    PRODUCTS OR SUBCONTRACT MODIFY DESIGN TO REDUCE COSTS

    VA PROCEDURE

  • 8/2/2019 Prod Techniques Old

    158/582

    VA PROCEDURE

    IDENTIFY ITEMS TO BE ANALYSED

    DIFFERENTIATE WHETHER ITEM OR PROCESS

    IDENTIFY INTERNAL AND EXTERNAL CUSTOMERS

    IDENTIFY BASIC FUNCTIONS

    IDENTIFY SECONDARY FUNCTIONS WHICH SUPPORT BASIC

    TO PRIORITISE DETERMINE VALUE OR IMPERTANCE TOCUSTOMER OF EACH FUNCTION

    BREAK ITEM/PROCESS INTO CONSTITUENT COMPONENTSBY USING FLOWCHART

    ASSOCIATE COMPONENTS WITH FUNCTIONS

    LOOK FOR COMPONENTS WHICH CAN BE MODIFIED ORELIMINATED

    OPTIONS IN VA/VE

  • 8/2/2019 Prod Techniques Old

    159/582

    OPTIONS IN VA/VE

    MODIFY

    INTEGRATE

    SUBSTITUTE SIMPLIFY

    EXAMPLES OF VALUE

    ANALYSIS

  • 8/2/2019 Prod Techniques Old

    160/582

    ANALYSIS

    MODIFY-MOTOR CAR ENGINES HAVE BEENMODIFIED TO RUN ON CNG

    INTEGRATE-AIR CONDITIONER AND HEAQTERINTEGRATED INTO ONE UNIT

    SUBSTITUTE-INHOUSE WIRING HAS BEENCHANGED FROM COPPER TO ALUMINIUM ORCOKE BOTTLES CHANGED FROM GLASS TOPLASTIC

    SIMPLIFY-APPLICATION SOFTWARE SIMPLIFIED

    BY BEING MADE MODULAR.EARLIER ALLMODULES WERE BUNDLED OR COMPLICATEDEQUIPMENT MADE MODULAR WHICH SIMPLIFIESMAINTENANCE

    WHEN TO USE VA/VE

  • 8/2/2019 Prod Techniques Old

    161/582

    WHEN TO USE VA/VE

    AIM IS TO EVALUATE REAL VALUE

    OF PRODUCT/PROCESS

    FOCUS IS ON SAVING COSTS AIM IS ON INCREASING VALUE OF

    PROCESS/PRODUCT

    BENEFITS OF VALUE

    ENGINEERING

  • 8/2/2019 Prod Techniques Old

    162/582

    ENGINEERING

    COST REDUCTION/ELIMINATION

    TECHNIQUE

    BALANCES COSTS AND PERFORMANCE

    PREVENTS OVER DESIGN OF PRODUCT

    (CUSTOMER FUNCTION DEPLOYMENT)

    INCREASES PROFITS AND REDUCES COSTS

    INCREASES CUSTOMER SATISFACTION

  • 8/2/2019 Prod Techniques Old

    163/582

    Introduction

    D fi iti W k St d i th t ti

  • 8/2/2019 Prod Techniques Old

    164/582

    Definition: Work Study is the systematic

    examination of the methods of carrying onactivities so as to improve the effective use ofresources and to set up standards ofperformance for the activities being carried out.

    Work Studysucceeds because it issystematic both in the investigation of theproblem being considered and in thedevelopment of its solution.

    164

    Continue.

  • 8/2/2019 Prod Techniques Old

    165/582

    If work study results in cutting down the timeof performing a certain activity by 20 per cent

    Merely as a result of rearranging the sequenceor simplifying the method of operation

    Without additional expenditure

    Then productivity will go up by acorresponding value, that is by 20 per cent.

    165

    WORK STUDY

  • 8/2/2019 Prod Techniques Old

    166/582

    OPERATIONS MGT IS ABOUT ADDING VALUE IN ACTIVITIES

    AND PRODUCING RESULTS AS DESIRED BY THE

    CUSTOMER.

    ACTIVITIES HAVE INPUTS WHICH ARE IN VARIOUS FORMS.

    THEY ALSO HAVE BUSINESS RULES AND METHODS BYWHICH THEY HAVE TO BE PERFORMED.THEY ALSO

    PRODUCE RESULTS WHICH SHOULD CONFORM TO

    CUSTOMERS REQUIREMENT

    WORK STUDY DEFINED AS SCIENCE OF EXAMINATION OF

    HUMAN WORK IN ALL CONTENTS WHICH LEADS TOSYSTEMATIC INVESTIGATION OF ALL FACTORS WHICH

    AFFECT EFFICIENCY

    GENERIC FORM OF TECHNIQUES WHICH ARE USED TO

    EXAMINE HUMAN WORK IN ALL ASPECTS AND WHICH

    SYSTEMATICALLY LEAD TO THE INVESTIGATION OF ALL

    WORK STUDY

  • 8/2/2019 Prod Techniques Old

    167/582

    WORK STUDY INVESTIGATES AND

    CRITICALLY EXAMINES WORK DONE AND

    FINDS THE BEST AND MOST EFFECTIVE

    WAY OF USING RESOURCES TO AHIEVEBEST QUALITY RESULTS IN THE LEAST

    TIME AND COST

    CRUX OF WORK STUDY IS TO OPTIMIZE

    USAGE OF INPUT RESOURCES AND TO

    MAXIMIZE PRODUCTIVITY

    WORK STUDY HELPS IN DECIDING

    RESOURCE RE UIREMENTS AT THE

    Operational Time

    Definition: The time taken by a worker or a machine to carry outan operation or to produce a given quantity of a certain product .

  • 8/2/2019 Prod Techniques Old

    168/582

    p p g q y p

    Basic work content of product and/oroperation

    Work content added by poor product designor material utilization

    Work content added by inefficient methodsof manufacturing or operation.

    Ineffective time resulting from humanresources contribution

    168

    Techniques of work study

  • 8/2/2019 Prod Techniques Old

    169/582

    Method study :The systematic recording and criticalexamination of ways of doing things in order to make

    improvements.

    Work measurement :The application of techniques

    designed to establish the time for a qualified worker

    to carry out a task at a defined rate of working.

    169

    M h d S d

    Work Study Relationship

  • 8/2/2019 Prod Techniques Old

    170/582

    Method Study

    To simplify the job & develop moreeconomical methods of doing it

    Work Measurement

    To determine how long it should taketo carry out

    Higher Productivity

    Work

    study

    170

    ADVANTAGES OF WORK

    STUDY

  • 8/2/2019 Prod Techniques Old

    171/582

    STUDY IMPROVED PRODUCTION FLOW

    HIGHER PRODUCTIVE EFFICIENCY

    REDUCE MANUFACTURING COSTS

    FAST AND ACCURATE DELIVERIES

    BETTER EMPLOYEE RELATIONS

    BETTER SERVICE TO CUSTOMERS

    JOB SATISFACTION TO EMPLOYEES

    BETTER WORKING CONDITIONS

    HIGHER INCENTIVE BASED WAGES BASED ON HIGHERPRODUCTIVITY

    ADVANTAGES OF WORK

    STUDY

  • 8/2/2019 Prod Techniques Old

    172/582

    STUDY PRODUCTION SMOOTHING DUE TO LINE

    BALANCING

    REMOVAL OF BOTTLENECKS LEADING TO

    REDUCED INVENTORY HIGHER PRODUCTIVE EFFICIENCY

    REDUCED MFG COST

    ACCURATE DELIVERY DATES TO CUSTOMER AS

    PER COMMITMENT BETTER SERVICE TO CUSTOMER

    How to apply Work Study

  • 8/2/2019 Prod Techniques Old

    173/582

    Method Study Work Measurement

    Analyzing the specific

    Methods used in

    carrying out an operation

    And simplifying job thruEconomical ways

    -Determine the time

    required to perform

    the operation and its

    elements-Comprises of Motion and

    Time study

  • 8/2/2019 Prod Techniques Old

    174/582

    METHOD STUDY

    METHOD STUDY

  • 8/2/2019 Prod Techniques Old

    175/582

    DEFINED AS SYSTEMATIC AND SCIENTIFIC

    ANALYSIS OF PROPOSED METHOD OF DOING A

    JOB IN ORDER TO DEVELOP A SIMPLE EFFICIENT

    EFFECTIVE AND LESS FATIGUING PROCEDURE OF

    DOING THE SAME JOB AT A LESSER COST BY

    OPTIMIZING INPUT RESOURCES

    IT USES DIFFERENT PROCESS MAPPING

    TECHNIQUES TO IDENTIFY AND ERADICATE THE

    NON VALUE ACTIVITIES

    OBJECTIVE OF METHOD STUDY IS TO IMPROVE

    PROCESS OF VALUE ADDITION .THIS IS DONE BY

    MAXIMIZING VALUE ADDED OPERATIONS AND

    MINIMIZING OR ELIMINATING DELAY STORAGE

    METHOD STUDY

  • 8/2/2019 Prod Techniques Old

    176/582

    METHOD STUDY INVOLVES THE STUDY

    OF HOW ACTIVITIES ARE PERFORMED

    AND ATTEMPTS TO REMOVE NON VALUE

    ADDED ACTIVITIES AS WELL AS IMPROVETHE PROCEDURE AND WAY IN WHICH THE

    ACTIVITY IS PERFORMED SO THAT THE

    TIMING TO EXECUTE MAY BE REDUCED

    AND THE ACTIVITY IS PERFORMED INLESSER TIME WITH LESSER EFFORT. Eg

    DENNIS LILEE BOWLING ACTION AFTER

    BACK OPERATION

    METHOD STUDY

  • 8/2/2019 Prod Techniques Old

    177/582

    METHOD STUDY IS SYSTEMATIC RECORDING AND

    CRITICAL EXAMINATION OF WAYS OF DOING THINGS

    OBJECTIVE OF METHOD STUDY IS TO IMPROVE ACTIVITY

    ACTIVITY CAN BE IMPROVED THROUGH PROCESS

    REENGINEERING BY ELIMINATING NVA ACTIVITIES OR BYREDUCING EXISTING TIMINGS OF ACTIVITIES THROUGH

    BETTER WAYS

    NEED TO DRAW PROCESS CHARTS AND ACTIVITY CHARTS

    WITH

    MOVEMENT,STORAGE,DELAY,INSPECTION,ACTIVITY,DECISION ALONG WITH TIMINGS

    OBJECTIVES OF METHOD

    STUDY

  • 8/2/2019 Prod Techniques Old

    178/582

    STUDY IMPROVED WORK PROCESS LEADING TO ENHANCED

    PRODUCTIVITY

    STANDARDIZED PROCEDURE LEADIND TO CONSISTENCY

    IN ACTIVITY EXECUTION;HENCE GENERALLY

    CONSISTENCY IN PERFORMANCE BETTER WORKPLACE LAYOUT

    SAFER WORKING CONDITIONS

    IMPROVED PRODUCT QUALITY DUE TO HIGHER QUALITY

    ASSURANCE

    IMPROVED WORK ERGONOMICS LEADING TO HIGHERPRODUCTIVITY

    Objective of Method Study

  • 8/2/2019 Prod Techniques Old

    179/582

    Improvement of processes and procedures Improvement in the design of plant and

    equipment

    Improvement of layout

    Improvement in the use of men, materials andmachines

    Economy in human effort and reduction ofunnecessary fatigue

    Improvement in safety standards Development of better working environment.

    179

    HUMAN OPERATIONS

    ANALYSIS

  • 8/2/2019 Prod Techniques Old

    180/582

    ANALYSIS

    DETAILED STUDY OF DIFFERENT

    OPERATIONS INVOLVED IN DOING

    WORK WITH THE OBJECTIVE TO

    FIND DEFECTS IN EXISTING

    METHODS AND TO DEVELP

    IMPROVED PROCEDURE

    AIMS AT OPTIMIZING UTILIZATION

    OF RESOURCES AND ESPECIALLY

    THOSE PARTS OF HUMAN BODY

    METHOD STUDY

    PROCEDURE

  • 8/2/2019 Prod Techniques Old

    181/582

    PROCEDURE SELECT WORK TO BE STUDIED AND DEFINE

    OBJECTIVES TO BE ACHIEVED

    OBJECTIVE MAY BE TO REDUCE COSTS

    BOTTLENECKS OR TO REDUCE FATIGUE

    INCURRED BY WORKERS AND TO INCREASE

    THEIR EFFICIENCY eg CONVEYOR BELT BY FORD

    RECORD RELEVANT INFORMATION PERTAINING

    TO EXISTING METHOD IN DETAIL AND

    DOCUMENT ACTIVITIES BY WAY OF MATERIAL

    FLOW CHARTS , PROCESS FLOW CHARTS ,

    ACTIVITY FLOW CHARTS,INFORMATION FLOW

    CHARTS

    METHOD STUDY

    PROCEDURE

  • 8/2/2019 Prod Techniques Old

    182/582

    PROCEDURE INSTAL THE BEST DEVELOPED METHOD

    MAINTAIN AND CONTINUOUSLY REVIEW AND

    IMPROVE THE NEW METHOD (ADLI)

    Method Study Procedure

  • 8/2/2019 Prod Techniques Old

    183/582

    1. DEFINE2. RECORD

    3. EXAMINE

    4. DEVELOP

    5. DEFINE NEW METHOD

    6. INSTALL7. MAINTAIN

    183

    ADVANTAGES OF METHOD

    STUDY

  • 8/2/2019 Prod Techniques Old

    184/582

    STUDY IMPROVED WORK PROCESS LEADING TO

    HIGHER PRODUCTIVITY

    STANDARDIZED PROCEDURE LEADING TO

    CONSISTENCY IN PERFORMANCE

    BETTER WORK PLACE LAYOUT AND

    POSITIONING AND ARRANGING FACILITIES AND

    MACHINES

    NEAT AND CLEAN ENVIRONMENT

    REDUCED FATIGUE IN WORKERS

    IMPROVES PRODUCT QUALITY

    ENSURES SAFETY AND MINIMIZES HEALTH

    HAZARDS AT WORKPLACE

  • 8/2/2019 Prod Techniques Old

    185/582

    TIME STUDY

    TIME STUDY

  • 8/2/2019 Prod Techniques Old

    186/582

    TIME STUDY CAN BE DEFINED AS THE

    APPLICATION OF SCIENTIFIC TECHNIQUES

    TO MEASURE WORK CONTENT OF

    ACTIVITY IN A NORMAL DEFINEDSITUATION AND ESTABLISH TIME

    REQUIRED TO EXECUTE JOB BY VARIOUS

    SKILLS AT A DEFINED LEVEL OF

    PERFORMANE. FALLACY LIES INDEFINING STD TIME FOR ALL LEVELS OF

    CAPABILITY AND EXPERIENCE

    TIME STUDY

  • 8/2/2019 Prod Techniques Old

    187/582

    ALSO CALLED WORK MEASUREMENT

    IT DETERMINES THE TIME TAKEN TO DO A JOB

    DECIDES MANPOWER REQUIRED (QUANTITY VS QUALITY)

    DECIDES EQUIPMENT REQUIRED

    PROVIDES VALUABLE INFO FOR PRODN PLANNING INTERMS OF TIME ESTIMATION FOR EACH STEP IN THE

    ROUTING

    INDICATES REALISTIC LABOR BUDGETING

    PROVIDES BASE FOR STD COSTING (CHECK CHANGING

    PARAMETERS)

    RESULTS IN EFFECTIVE LABOUR CONTROL

    TIME STUDY

  • 8/2/2019 Prod Techniques Old

    188/582

    CONSISTS OF A WIDE VARIETY OF

    PROCEDURES FOR DETERMINING

    THE AMOUNT OF TIME REQD UNDER

    CERTAIN STD CONDITIONS OF

    MEASUREMENT

    A TERM WORK MEASUREMENT IS

    ALSO USED FOR TIME STUDIES

    Objective of Work Measurement

  • 8/2/2019 Prod Techniques Old

    189/582

    To find ineffective time in a process

    To set standard for output level

    To evaluate worker's performance

    To plan work force needs.

    To determine available capacity

    To compare work methods To facilitate operations scheduling

    To establish wage incentive schemes 189

    USE OF STANDARD TIME

  • 8/2/2019 Prod Techniques Old

    190/582

    STANDARD TIME IS USED AS A NUMERICAL COEFFICIENT

    FOR CONVERTING A QUANTITATIVE STATEMENT OF THE

    WORKLOAD TO A QUANTITATIVE STATEMENT OF THE

    REQUIRED RESOURCES

    PLANNED COSTS ARE DERIVED FROM STANDARD TIMESBECAUSE BUDGETS ARE DERIVED FROM THE ACTIVITIES

    PERFORMED IN STANDARD TIME WHICH REQUIRE MONEY

    MATERIAL MEN etc.

    STANDARD TIME IS USED TO DETERMINE LABOR AND

    EQUIPMENT REQUIREMENTS ESPECIALLY OUTSOURCED

    EQUIPMENT .IN CERTAIN JOBS STANDARD TIME IS OF

    CRITICAL IMPORTANCE BECAUSE OF RESTRICTIONS IN

    DOWN TIME eg AN OIL AND GAS PRODUCTION WELL CAN

    BE DOWN FOR ONLY 120 HOURS IN A YEAR AND ALSO

    THEY NEED TO OUTPUT A MINIMUM FLOW OF GAS FAILING

    USE OF STANDARD TIME

  • 8/2/2019 Prod Techniques Old

    191/582

    TO ASSIST IN DEVELOPING EFFECTIVE METHODS

    TO DETERMINE THE NUMBER OF EQUIPMENT A PERSON

    CAN MANAGE AT A TIME eg WEAVERS 8/16 LOOMS.

    TIME VALUES SHOULD BE SET IN SUCH A WAY TAKING

    INTO ACCOUNT AN AVERAGE WORKER WITH A CERTAINMINIMUM LEVEL OF SKILLS.TODAY THE STD TIMES ARE

    ERRONEOUSLY CALCULATED ON EITHER VERY HIGH SIDE

    LEADING TO LOW PRODUCTIVITY FIGURES OR LOW SIDE

    LEADING TO MISLEADING HIGH PRODUCTIVITY FIGURES.

    Eg STD TIME 20 MIN ACTUAL TIME 10 MIN PRODUCTIVITY

    200%

    DISTRIBUTION OF WORK AMONG CREW

    COMPARE METHODS

    TO SET SCHEDULES

    USE OF STANDARD TIME

  • 8/2/2019 Prod Techniques Old

    192/582

    TO SET SUPERVISORY OBJECTIVES

    TO ASSIST IN COMPARING PLANS

    WITH ACHIEVEMENT WITH RESPECT

    TO WORKLOAD AND RESOURCE

    USAGE

    FOR TOTAL PRODUCTIVITY

    MEASUREMENT

    ALLOWANCES

  • 8/2/2019 Prod Techniques Old

    193/582

    ALLOWANCES ARE ADDED TO NORMAL TIME TO ARRIVE

    AT STANDARD TIME

    TYPES OF ALLOWANCES INCLUDE PROCESS ALLOWANCE

    AND PERSONAL ALLOWANCE

    PROCESS ALLOWANCE ARE ALLOCATED TO COVERENFORCED IDLE TIME OR SPECIAL CASES WHICH ARE NOT

    PART OF WORK CYCLE BUT ARE ESSENTIAL FOR

    PERFORMING WORK eg BEAM CHANGE IN WEAVING OR

    MACHINE SET UP TIME OR INTERFERENCE ALLOWANCE

    WHEN WORKER HANDLES MORE THAN ONE MACHINE eg

    WEAVER HANDLES 8/16 MACHINES

    PERSONAL ALLOWANCES INCLUDE TIME ALLOWED FOR

    FATIGUE , CALLS OF NATURE , DIFFICULT WORKING

    CONDITIONS etc. VARIES FROM 15% TO 30% DEPENDING ON

    SITUATIONS

  • 8/2/2019 Prod Techniques Old

    194/582

  • 8/2/2019 Prod Techniques Old

    195/582

    ADVANTAGES OF TIME

    STUDY

  • 8/2/2019 Prod Techniques Old

    196/582

    STUDY DECIDES MANPOWER SKILLS (AND SHOULD

    ALSO DECIDE CAPABILITIES) REQUIRED TO DO

    THE JOB

    DECIDE EQUIPMENT REQUIRED

    PROVIDES INFORMATION FOR EFFECTIVE

    PRODUCTION PLANNING AND MAINTENANCE

    PROCEDURES

    AIDS AT CALCULATING REALISTIC DE3LIVERY

    DATES AND DOES REALISTIC LABOR BUDGETING

    PROVIDES BASIS FOR STANDARD COSTING

    FORMS THE BASE FOR INCENTIVE SYSTEMS

  • 8/2/2019 Prod Techniques Old

    197/582

    MOTION STUDY

  • 8/2/2019 Prod Techniques Old

    198/582

  • 8/2/2019 Prod Techniques Old

    199/582

    ANALYSIS OF MOTION

  • 8/2/2019 Prod Techniques Old

    200/582

    ANALYSIS OF AN OPERATION FOR ATTAINMENT

    OF END OBJECTIVE IS CARRIED OUT IN TERMS OF

    INDIVIDUAL MOTIONS OF A PERSON AS WELL AS

    THE WORK PLACE LAYOUT AND ERGONOMICS

    FOR ATTAINMENT OF HIGHEST LEVEL OFPRODUCTIVITY

    PURPOSE OF MOTION ANALYSIS IS TO

    ELIMINATE UNNECESSARY MOTIONS TO REDUCE

    FATIGUE AND EFFORT AND MAKE HUMANEFFORT MORE PRODUCTIVE eg WEIGHT LIFTING

    STEPS FOR MOTION STUDY

  • 8/2/2019 Prod Techniques Old

    201/582

    CHART VARIOUS MOTIONS PERFORMED BY OPERATORS

    IDENTIFY LABORIOUS AND IDLE MOTIONS.ALSO IDENTIFY

    COMPLEX MOTIONS WHICH ARE DIFFICULT TO

    PERFORM.OCCASIONALLY PERFORMER EXAGGERATES

    COMPLEXITY OF MOTION eg SIMPLE CATCH IS MADE TO

    LOOK DIFFICULT

    IDENTIFY PRODUCTIVE ,NON VALUE ADD AND IDLE

    MOTIONS

    ELIMINATE NON PRODUCTIVE AND UNREQUIRED MOTIONS

    OR SIMPLIFY COMPLEX MOTIONS eg WEIGHT LIFTING REDESIGN EXISTING OPERATING PROCEDURE BY

    IMPROVING THE MOTIONS INVOLVED IN WORK TAKING

    INTO ACCOUNT THE ABOVE OBSERVATIONS

    IMPART REQUIRED INSTRUCTIONS AND TRAINING TO

    OPERATORS

  • 8/2/2019 Prod Techniques Old

    202/582

  • 8/2/2019 Prod Techniques Old

    203/582

    PRIMARY OBJECTIVES OF

    MOTION STUDY

  • 8/2/2019 Prod Techniques Old

    204/582

    MAXIMIZE FINANCIAL ADVANTAGE THRU

    -LESS DIRECT LABOR EFFORT AND TIME

    -FEWER STEPS IN PROCESS

    -MORE PRODUCTIVE LABOR

    -LESS EQUIPMENT USAGE

    -LESS SPACE USAGE

    -LESS SCRAP GENERATED

    -LOWER OVERALL COSTS

    -LESSER IDLE TIME AND LESSER FATIGUE

    -FEWER HAZARDS IN OPERATIONS

    -

  • 8/2/2019 Prod Techniques Old

    205/582

  • 8/2/2019 Prod Techniques Old

    206/582

    Facility Design

  • 8/2/2019 Prod Techniques Old

    207/582

    Facility layout: Arrangement of machines, storage areas,

    and/or work areas usually within the confines of a

    physical structure, such as a retail store, an office, a

    warehouse, or a manufacturing facility.

    Factors that influence layout

    Volume, weight of items to be produced.

    Nature of the service to be provided.

    Cost of the building to house the operation.

    The product mix that must have a facility.

    The fragility of the product or component.

    What Is Layout Planning

  • 8/2/2019 Prod Techniques Old

    208/582

    Layout planning is determining the best physical arrangement of

    resources within a facility

    Facility resource arrangement can significantly affect productivity

    Two broad categories of operations:

    Intermittent processing systemslow volume of many different

    products

    Continuous processing systemshigh volume of a few

    standardized products

  • 8/2/2019 Prod Techniques Old

    209/582

    INTRODUCTION

  • 8/2/2019 Prod Techniques Old

    210/582

    To make a decision about layout planning, 4 different

    questions must have an answer:

    Which centers do we have to consider?

    How much space and capacity is required for each center?

    If there is not enough space, productivity may be reduced.

    Too much space is expensive and may also reduce

    productivity.

    How must the space be configured at each center?

    Space quantity, shape and the elements of the work center arerelated to each other.

    Where should each center be located at within the facility?

    The allocation of the different centers may affect productivity.

    INTRODUCTION

  • 8/2/2019 Prod Techniques Old

    211/582

    The plant layout process starts at an aggregate

    level, taking into account the different

    departments. As soon as we get into the details,

    the different issues arise, and the originalconfiguration may be changed through a feedback

    process.

    Most (if not all of them) layouts are designed

    properly for the initial conditions of the business,although as long as the company grows and has to

    be adapted to internal and external changes, a re-

    layout is necessary.

    INTRODUCTION

  • 8/2/2019 Prod Techniques Old

    212/582

    The reasons for a re-layout are based on 3 types of

    changes:

    Changes in production volumes. Changes in processes and technology.

    Changes in the product.

    The frequency of the re-layout will depend on the

    requirements of the process.

  • 8/2/2019 Prod Techniques Old

    213/582

    A Good Layout ...

  • 8/2/2019 Prod Techniques Old

    214/582

    Reduces bottlenecks in moving people or material.

    Minimizes materials-handling costs and material inprocess

    Reduces hazards to personnel.

    Utilizes labor efficiently.

    Increases morale.

    Utilizes available space effectively and efficiently.

    Provides flexibility.

    Provides ease of supervision.

    Facilitates coordination and face-to-face communicationwhere appropriate.

    Implements safety measures

    Lay Out

  • 8/2/2019 Prod Techniques Old

    215/582

    Types of Plant Layout

    Product Layout

    Process Layout

    Fixed Position Layout

    Cellular Layout

    Layout for Services

    Objectives of Plant Layout

  • 8/2/2019 Prod Techniques Old

    216/582

    These main objectives are reached through the attainment of the followingfacts:

    Congestion reduction.

    Elimination of unnecessary occupied areas.

    Reduction of administrative and indirect work.

    Improvement on control and supervision.

    Better adjustment to changing conditions.

    Better utilization of the workforce, equipment and services.

    Reduction of material handling activities and stock in process.

    Reduction on parts and quality risks.

    Reduction on health risks and increase on workers safety. Moral and workers satisfaction increase.

    Reduction on delays and manufacturing time, as well as increase in productioncapacity.

    All these factors will not be reached simultaneosly, so the best solution willbe a balance among them.

    Factors affecting Plant Layout The final solution for a Plant Layout has to take into account a

    balance among the characteristics and considerations of all factorsaffecting plant layout, in order to get the maximum advantages.

  • 8/2/2019 Prod Techniques Old

    217/582

    affecting plant layout, in order to get the maximum advantages.

    The factors affecting plant layout can be grouped into 8 categories:

    Materials

    Machinery

    Labor

    Material Handling

    Waiting Time

    Auxiliary Services

    The building

    Future Changes

    Factors affecting Plant Layout

  • 8/2/2019 Prod Techniques Old

    218/582

    The factors affecting plant layout can be grouped into 8categories:

    Materials

    The layout of the productive equipment will depend on the

    characteristics of the product to be managed at the facility, as well as

    the different parts and materials to work on.

    Main factors to be considered: size, shape, volume, weight, and the

    physical-chemical characteristics, since they influence the

    manufacturing methods and storage and material handling processes.

    The sequence and order of the operations will affect plant layout as

    well, taking into account the variety and quantity to produce.

    Factors affecting Plant Layout

  • 8/2/2019 Prod Techniques Old

    219/582

    The factors affecting plant layout can be grouped into 8categories:

    Machinery

    Having information about the processes, machinery, tools and

    necessary equipment, as well as their use and requirements isessential to design a correct layout.

    The methods and time studies to improve the processes are closely

    linked to the plant layout.

    Regarding machinery, we have to consider the type, total available

    for each type, as well as type and quantity of tools and equipment. Its essential as well to know about space required, shape, height,

    weight, quantity and type of workers required, risks for the personnel,

    requirements of auxiliary services, etc.

    Factors affecting Plant Layout

  • 8/2/2019 Prod Techniques Old

    220/582

    The factors affecting plant layout can be grouped into 8categories:

    Labor

    Labor has to be organized in the production process (direct labor,

    supervision and auxiliary services). Environment considerations: employees safety, light conditions,

    ventilation, temperature, noise, etc.

    Process considerations: personnel qualifications, flexibility, numberof workers required at a given time as well as the type of work to beperformed by them.

    Material Handling

    Material handling does not add value to the product; its just waste.

    Objective: Minimize material handling as well as combining withother operations when possible, eliminating unnecessary and costlymovements.

    Factors affecting Plant Layout

    The factors affecting plant layout can be grouped into 8

  • 8/2/2019 Prod Techniques Old

    221/582

    g p y g p

    categories:

    Waiting time - Stock

    Objective: Continuous Material Flow through the facility, avoiding

    the cost of waiting time and demurrages that happen when the flow

    stops. On the other hand, the material waiting to flow through the facility

    not always represents a cost to avoid. As stock sometimes provides

    safety to protect production, improving customer service, allowing

    more economic batches, etc.

    Its necessary then to consider space for the required stock at the facilitywhen designing the layout.