prod techniques old
TRANSCRIPT
-
8/2/2019 Prod Techniques Old
1/582
PRODUCTIVITY
TECHNIQUES
-
8/2/2019 Prod Techniques Old
2/582
PRODUCTIVITYTECHNIQUES
-
8/2/2019 Prod Techniques Old
3/582
MEANING OF PRODUCTIVITY
PRODUCTIVITY IS OFTEN ASSOCIATED WITHPRODUCTION
HIGHER PRODUCTION IS NOT HIGHER
PRODUCTIVITY INCREASE IN PRODUCTION CAN BE ACHIEVED
BY INCREASING QUANTUM OF INPUT BUT THATDOES NOT INCREASE PRODUCTIVITY
HIGHER PRODUCTIVITY RESULTS IF
PRODUCTION PER EMPLOYEE OR PER MACHINEINCREASES ALONGSIDE WITH QUALITY
PRODUCTIVITY IS CREATING SURPLUS THRUPRODUCTIVE OPERATIONS WHERE OUTPUT ISALWAYS GT INPUT
PRODUCTIVITY IS DEFINED AS OUTPUT WITHINDEFINED TIME AND AS PER QLTY NORMS/INPUT
-
8/2/2019 Prod Techniques Old
4/582
MEANING OF PRODUCTIVITY
BOTH OUTPUT AND INPUT SHOULD BEQUANTIFIED IN TANGIBLE MONETARYTERMS
PRODUCTIVITY CAN BE IMPROVED BY-INCREASING OUTPUT WITH SAME INPUT-INCREASING OUTPUT MORE THAN THEINCREASE IN INPUT
-DECREASING INPUT FOR THE SAMEAMOUNT OF OUTPUT-INCREASING OUTPUT WHILEDECREASING INPUT
PRODUCTIVITY IMPLIES EFFECTIVENESS
AND EFFICIENCY IN INDIVIDUAL AND
-
8/2/2019 Prod Techniques Old
5/582
DEFINITION OF
PRODUCTIVITY PRODUCTIVITY IS THE RATIO BETWEEN OUTPUT
OF WEALTH TO THE INPUT OF RESOURCES USED
IN THE PROCESS OF MFG
PRODUCTIVITY = OUTPUT OF WEALTH/INPUT OF
RESOURCES
INPUTS ARE MATERIAL , MONEY , MACHINES ,
PEOPLE
ANOTHER PARAMETER OFTEN USED IS
PERFORMANCE WHICH IS (ACTUAL
ACHIEVEMENT IN TERMS OF EFFECTIVE WORK
DONE)/(STANDARD TARGET OF ACHIEVEMENT) *
100
-
8/2/2019 Prod Techniques Old
6/582
DEFINITION OF
PRODUCTIVITY PERFORMANCE IS EXPRESSED AS PERFORMANCE INDEX
WHICH IS % OF STANDARD TARGET OR EFFECTIVENESS OF
PRODUCTIVITY .PRODUCTIVITY = OUTPUT/INPUT
= PERFORMANCE ACHIEVED/RESOURCES CONSUMED= EFFECTIVENESS/EFFICIENCY
PRODUCTIVITY CAN BE APPLIED TO MATERIAL ,
EQUIPMENT,MEN,CAPITAL
MATRL = 1 TONNE OF HOT ROLLED STEEL PRODUCES 0.8
TONNE OF COLD ROLLED STEEL REST IS SCRAP.PRODUCTIVITY WAS 80%. THE ENGINEERS AT TISCO
STUDIED THE PROCESS AND THRU METHOD STUDY
INCREASED PRODUCTIVITY TO 90% BY REDUCING SCRAP
-
8/2/2019 Prod Techniques Old
7/582
DEFINITION OF
PRODUCTIVITY MACHINE = RATED THROUGHPUT OF POWER
PLANT WAS 100 MWH. ACTUAL
THROUGHPUT(PLF) WAS 72% WHICH MEANT THE
POWER PLANT HAD 28% LOSSES.AFTER
STUDYING HEAT LOSSES AND INSTALLING
PREHEATERS AND REGENERATORS THE HEAT
LOSS WAS REDUCED BY 8%.HENCE
PRODUCTIVITY OF POWER PLANT ROSE TO 80% MAN = STANDARD OUTPUT OF TRAINED 1 YEAR
EXPERIENCED ORACLE PROGRAMMER IS 80
DEBUGGED LINES OF CODE PER DAY. ON A
PARTICULAR DAY MR X PRODUCED 60 LINES. HISPRODUCTIVITY WAS 75%
-
8/2/2019 Prod Techniques Old
8/582
MYTHS IN PRODUCTIVITY
PRODUCTION IMPROVEMENT MEANS
PRODUCTIVITY IMPROVEMENT
EFFICIENCY IMPROVEMENTGUARANTEES PRODUCTIVITY
IMPROVEMENT
IMPROVEMENT IN SALES REVENUE
ENSURES PRODUCTIVITY IMPROVEMENT
QUALITY IMROVEMENT ENHANCES
PRODUCTIVTY
-
8/2/2019 Prod Techniques Old
9/582
PARTIAL PRODUCTIVITY
DEFINED AS RATIO OF TOTAL OUTPUT TO ANY ONE TYPE
OF INPUT eg MATERIAL , MONEY ,LABOUR , ENERGY
LABOUR PRODUCTIVITY = TOTAL OUTPUT/LABOUR COST
eg 1000 cr/300cr = 3.3 MATERIAL PRODUCTIVITY =TOTAL OUTPUT/MATRL COST
eg 1000cr/200cr 5.0
CAPITAL PRODUCTIVITY = TOTAL OUTPUT/CAPITAL COST
eg 1000cr/300 = 3.3
CAN ALSO BE CALLED FIXED ASSET PRODUCTIVITY ENERGY PRODUCTIVITY =TOTAL OUTPUT/ENERGY COST
eg 1000cr/100cr = 10
-
8/2/2019 Prod Techniques Old
10/582
PARTIAL PRODUCTIVITY
PARTIAL PRODUCTIVITY GIVES MEASURE OF
IMPACT OF TYPE OF INPUT ON OVERALL
PRODUCTIVITY
PARTIAL PRODUCTIVITY HELPS IN DETERMINING
IMPORTANCE OF TYPE OF INPUT ON
EFFECTIVENESS OF PROCESS
-
8/2/2019 Prod Techniques Old
11/582
ASSET ENERGY
SUSTAINABILITY INDEX Most companies concentrate on achieving a high degree of
overall equipment effectiveness
OEE = UPTIME * EFFICIENCY * QUALITY where
efficiency is the throughput productivity
But while doing so how much is the extra energy
consumed
Are we achieving higher throughputs but sacrificing
energy consumption
Asset Energy Sustainability Index = OEE * (Expected
energy consumption per unit produced/Actual energy
consumed per unit)
-
8/2/2019 Prod Techniques Old
12/582
COMPARITIVE PLANT FIGURES OF
ENERGY CONSUMPTION PER
VEHICLE IN HERO HONDA PLANTS2009 2010
PLANT VEH KWH/VEH VEH KWH/VEH
GURGAON 15.59L 35.85 15.93L 36.97
DHARUHERA 15.99L 31.12 15.33L 32.09
HARIDWAR 6.30L 24.63 14.04L 17.31
SOURCEANNUAL REPORT OF HERO HONDA 2009-2010
-
8/2/2019 Prod Techniques Old
13/582
PARTIAL PRODUCTIVITY
ADVANTAGES EASY TO UNDERSTAND EFFECT OF
INDIVIDUAL FACTOR OF INPUT ON
OUTPUT EASY TO OBTAIN DATA
EASY TO COMPUTE PRODUCTIVITY
INDICES
EASY TO CONVINCE MGT OF BENEFITS
GOOD DIAGNOSTIC TOOLS AVAILABLE TO
PINPOINT AREAS OF PRODUCTIVITY
IMPROVEMENT
-
8/2/2019 Prod Techniques Old
14/582
PARTIAL PRODUCTIVITY
DISADVANTAGES IF USED ALONE CAN BE MISLEADING
STRESSES ON ONE FACTOR
CANNOT EXPLAIN OVERALL COSTINCREASES
TEND TO SHIFT BLAME ON WRONG AREAS
OF MGT CONTROL
IN THE CASE OF PARTIAL LABOR
PRODUCTIVITY THE CONTRIBUTION OF
INDIRECT LABOR IS NOT TAKEN INTO
CONSIDERATION
-
8/2/2019 Prod Techniques Old
15/582
PROBLEM WITH TRADITIONAL
LABOR PRODUCTIVITY OUTPUT PRODUCED IS A RESULT OF JOINT AND
SIMULTANEOUS IMPACT OF ALL RESOURCES
NOT ONLY LABOR
COMPANIES SHOWING HIGH LABOR
PRODUCTIVITY GROWTH RATES ARE NOT
ALWAYS COMPETITIVE IN THE MARKET
ORGANIZATIONS WITH COLLECTIVE
BARGAINING AGREEMENTS BASED ONLY ONLABOR PRODUCTIVITY TEND TO REDUCE THE
UNIT LABOR COST BUT NOT ALWAYS THE TOTAL
UNIT COST eg COMPUTERIZATION LEADING TO
LABOR REDUCTION
-
8/2/2019 Prod Techniques Old
16/582
PROBLEM WITH TRADITIONAL
LABOR PRODUCTIVITY DIFFICULT TO IMPLEMENT TEAM CONCEPTS OF
MGT WHEN PERFORMANCE MGT IS FOCUSED
ONLY ON LABOR PRODUCTIVITY RATHER THAN
TOTAL PRODUCTIVITY
ORG STRUCTURES TEND TO BE LESS FLEXIBLE
WHEN EMPHASIS IS ON CONTROL OF LABOR
PRODUCTIVITY RATHER THAN TOTAL
PRODUCTIVITY DIFFICULT TO DIRECTLY RELATE LABOR
PRODUCTIVITY TO PROFITS
IN MOST MFG OUTFITS LABOR COST IS NOT A
SIGNIFICANT COMPONENT OF DIRECT COSTS eg
-
8/2/2019 Prod Techniques Old
17/582
TOTAL FACTOR
PRODUCTIVITY DEFINED AS RATIO OF NET OUTPUT TO SUM OF
LABOUR AND CAPITAL INPUTS
NET OUTPUT = TOTAL OUTPUTINTERMEDIATE
GOODS AND SERVICES PURCHASED
INTERMEDIATE GOODS AND SERVICES
PURCHASED INCLUDE RAW
MATRL,COMPONENTS,ENERGY COSTS,FUEL,FEES
FOR SERVICES etc
ALSO CALLED VALUE ADD WHEN COSTS
COMPUTED
-
8/2/2019 Prod Techniques Old
18/582
EXAMPLE OF TOTAL
FACTOR INDEX TOTAL FACTOR PRODUCTIVITY =
OUTPUT/CAPITAL + LABOUR INPUT =
100/(20 + 55) =100/75 = 1.33 VALUE ADD = SALESPROCURE PRICE
SERVICES PRICE = 25001000500 = 1000
VALUE ADD PER EMPLOYEE = 1000/200 = 5
-
8/2/2019 Prod Techniques Old
19/582
ADVANTAGES OF TOTAL
FACTOR PRODUCTIVITY DATA IS EASY TO OBTAIN
APPEALING FROM ECONOMIST
POINT OF VIEW
-
8/2/2019 Prod Techniques Old
20/582
DISADVANTAGES OF TOTAL
FACTOR PRODUCTIVITY VALUE ADDED APPROACH TO DEFINING
OUTPUT IS NOT VERY APPROPRIATE
NOT APPROPRIATE WHEN MATRL COSTFORMS SIZEABLE PORTION OF TOTAL
PRODUCT COST
ONLY LABOR AND CAPITAL INPUTS ARE
CONSIDERED
DATA FOR COMPARISON PURPOSES IS
DIFFICULT TO OBTAIN
-
8/2/2019 Prod Techniques Old
21/582
TOTAL PRODUCTIVITY
TOTAL PRODUCTIVITY IS THE RATIO OF TOTAL
OUTPUT TO THE SUM OF ALLINPUT FACTORS
MEASURE WHICH TAKES INTO CONSIDERATION
THE JOINT IMPACT OF ALL INPUT RESOURCES ON
OUTPUT SUCH AS
MATERIAL,MACHINES,CAPITAL,ENERGY etc
MEASURE VERY POPULAR IN INDUSTRY
-
8/2/2019 Prod Techniques Old
22/582
ADVANTAGES OF TOTAL
PRODUCTIVITY CONSIDERS ALL QUANTIFIABLE OUTPUT AND INPUT FACTORS AND IS
THEREFORE A MORE ACCURATE REPRESENTATION OF THE REAL
ECONOMIC PICTURE OF THE COMPANY
PROFIT CONTROL THRU THE USE OF THESE INDICES IS OF BENEFIT TO THE
MGT IF USED IN CONJUNCTION WITH PARTIAL PRODUCTIVITY CAN DIRECT
MGT ATTENTION IN AN EFFECTIVE MANNER
SENSITIVITY ANALYSIS IS EASIER TO PERFORM
EASILY RELATED TO TOTAL COSTS
MULTIPLE GOALS CAN BE ACHIEVED SIMULTANEOUSLY BY INCREASING
TOTAL PRODUCTIVITY OF A COMPANY USING THE RELATIONSHIP BETWEEN PROFIT AND TOTAL PRODUCTIVITY
A FIRM CAN OBJECTIVELY PLAN ITS PROFIT LEVEL BASED ON ITS ABILITY
TO REACH A CERTAIN PRODUCTIVITY LEVEL
USING THE CONCEPT OF BREAK EVEN POINT OF TOTAL PRODUCTIVITY A
FIRM CAN DETERMINE IF ITS TOTAL PRODUCTIVITY LEVEL IS A VALUE
THAT YIELDS PROFITS MGT IS FORCED INTO A LONG TERM ACTION ON QLTY,PROFITABILITY etc
-
8/2/2019 Prod Techniques Old
23/582
DISADVANTAGES OF TOTAL
PRODUCTIVITY DATA FOR COMPUTATION IS DIFFICULT TO
OBTAIN AT PRODUCT AND CUSTOMER LEVEL
LIKE THE PARTIAL AND TOTAL FACTOR
MEASURES THIS ALSO DOES NOT CONSIDER
INTANGIBLE FACTORS OF OUTPUT AND INPUT IN
A DIRECT MANNER
-
8/2/2019 Prod Techniques Old
24/582
AMERICAN PRODUCTIVITY
CENTRE MODEL MODEL DERIVES EQUATION OF PROFITABILITY WITH
PRODUCTIVITY AND PRICE RECOVERYFACTOR
PROFITABILITY = SALES/COST
= OUTPUT QTY * PRICE/INPUT QTY * UNIT COST=OUTPUT QTY/INPUT QTY *UNIT PRICE/UNIT COST
=PRODUCTIVITY * PRICE RECOVERY FACTOR
PRICE RECOVERY FACTOR INDICATES THE INFLATIONARY
EFFECT AND PRODUCTIVITY GIVES THE AMOUNT OF
RESOURCES CONSUMED TO PRODUCE THE DEFINEDOUTPUT. IT IS THE PRICE RATIO OF CURRENT PERIOD TO
THE BASE PERIOD
-
8/2/2019 Prod Techniques Old
25/582
APPLICATIONS OF
PRODUCTIVITY TECHNIQUES APPLIED TO ALL FUNCTIONAL AREAS BOTH IN
MFG AND SERVICES
CONCEPTS OF PRODUCTIVITY VITAL TO
SUCCESS AND SURVIVAL OF ORG IN TODAYS
HIGHLY COMPETITIVE GLOBAL BUSINESS
ENVIRONMENT
ONLY MEASUREMENT OF PRODUCTIVITY
INADEQUATE FOR COMPANY TO SURVIVE
CONTINUOUS IMPROVEMENT IN PRODUCTIVITY
IN ALL FUNCTIONAL AREAS AT A RATE FASTER
THAN COMPETITION IS A DECISIVE BUSINESS
FACTOR FOR SURVIVAL AND SUCCESS OF
-
8/2/2019 Prod Techniques Old
26/582
KEY PARAMETERS
MARKETING
ACCURACY OF DEMAND FORECASTING
-COST LEADERSHIP-SERVICING SPEED AND EFFECTIVENESS
-OPTIMISED PRODUCT MIX
PRODUCTION
-INVENTORY CONTROL-JUST IN TIME
-PROCUREMENT COST
-SAFETY
-
8/2/2019 Prod Techniques Old
27/582
AREAS OF PRODUCTIVITY
TECHNIQUES SUPPLY CHAIN MGT
DEMAND FORECASTING
COST MANAGEMENT LOGISTIC MGT
SERVICING SPEED AND EFFECTIVENESS
METHOD STUDY
PLANT LAYOUT MATERIAL HANDLING
INVENTORY CONTROL (INV TURNOVER RATIO)
WORK MEASUREMENT
-
8/2/2019 Prod Techniques Old
28/582
AREAS OF PRODUCTIVITY
TECHNIQUES MOTION STUDY
MATERIALS MGT AND CONTROL
PRODUCTION PLANNING AND CONTROL INVENTORY MODELS
ERGONOMICS
SAFETY JOB EVALUATION
-
8/2/2019 Prod Techniques Old
29/582
CAUSES OF POOR
PRODUCTIVITY LACK OF PRODUCTIVITY MEASURES BY WAY OF ABSENCE
OF A SYSTEM TO CAPTURE CORRECT AND TIMELY INPUTS
RELEVANT TO PRODUCTIVITY MEASUREMENTS
ESPECIALLY FOR ADMINISTRATIVE STAFF
FAULTY APPRAISAL SYSTEM BASED ON QUALITATIVE
JUDGEMENTS
INADEQUATE WORK ASSIGNMENT
DEMOTIVATED OR UNDER CAPABLE EMPLOYEES
LOW EMPLOYEE INVOLVEMENT HUMAN CONFLICTS
LACK OF TRAINING AND SKILLS UPGRADES
TECHNOLOGICAL CHANGES ESPECIALLY FROM CLIENT
SERVER TO THIN CLIENT
UNBALANCED PRODUCTION LINE OR UNRELIABLE LINE
-
8/2/2019 Prod Techniques Old
30/582
MATERIAL BASED
PRODUCTIVITY TECHNIQUES INVENTORY CONTROL
SUPPLY CHAIN MGT
MATERIAL HANDLING
QUALITY ASSURANCE
JUST IN TIME MFG AND PROCUREMENT
-
8/2/2019 Prod Techniques Old
31/582
PEOPLE BASED PRODUCTIVITY
TECHNIQUES INDIVIDUAL FINANCIAL INITIATIVES
GROUP FINANCIAL INITIATIVES
LIBERAL FRINGE BENEFITS
EMPOWERMENT AND OWNERSHIP
TRAINING AND PERSONAL DEVELOPMENT
JOB ENRICHMENT AND ROTATION
EMPLOYEE PARTICIPATION IN MGT
-
8/2/2019 Prod Techniques Old
32/582
PRODUCT BASED
PRODUCTIVITY TECHNIQUES VALUE ENGINEERING
PRODUCT DIVERSIFICATION
PRODUCT SIMPLIFICATION
PRODUCT FLEXIBILITY AND AGILITY
BENCHMARKING
-
8/2/2019 Prod Techniques Old
33/582
TASK BASED
PRODUCTIVITY
TECHNIQUES WORK MEASUREMENT INCLUDING
METHOD STUDY , TIME STUDY , MOTION
STUDY JOB DESIGN JOB EVALUATION AND JOB
SAFETY
-
8/2/2019 Prod Techniques Old
34/582
ILO APPROACH TO PRODUCTIVITY
IMPROVEMENT ILO APPROACH IS TASK BASED
IT BREAKS MFG TIME INTO BASIC
WORK CONTENT ,ADDED WORKCONTENT AND INEFFECTIVE TIME
APPROACH FOCUSES ON REDUCING
INEFFICIENT TIME IN THE TOTALWORK CONTENT
-
8/2/2019 Prod Techniques Old
35/582
INEFFECTIVE TIME
ALL INTERRUPTIONS WHICH CAUSE
STOPPAGE IN OPERATION IS REGARDED
AS INEFFICIENT TIME BECAUSE NO WORKEFFECTIVE TOWARDS COMPLETION OF
OPERATION IN HAND IS BEING DONE
DURING PERIOD OF INTERRUPTION
INEFFECTIVE TIME DUE TOSHORTCOMINGS BY MGT.TIME DURING
WHICH MAN/MC IS IDLE BECAUSE MGT
FAILED TO PLAN DIRECT OORDINATE OR
CONTROL EFFICIENTLY
-
8/2/2019 Prod Techniques Old
36/582
REDUCTION IN
INEFFECTIVE TIME INEFFECTIVE TIME WITHIN CONTROL OF WORKER CAN BE
REDUCED THRU ADOPTION OF FOLLOWING INITIATIVES
- POOR DESIGN AND FREQUENT DESIGN CHANGES
-WASTE OF MATERIAL
-INCORRECT QUALITY STDS
-POOR LAYOUT AND UTILIZATION OF SPACE
-INADEQUATE MATEIAL HANDLING
-FREQUENT PRODUCTION STOPPAGES
-INEFFECTIVE WORK METHODS
-POOR WORK PLANNING-FREQUENT BREAKDOWNS
-ABSENTEEISM , WRONG ATTITUDES
-POOR WORKMANSHIP
-ACCIDENTS AND SAFETY ISSUES
-
8/2/2019 Prod Techniques Old
37/582
SURVEY RESULTS ON
PRODUCTIVITY TYPICAL 8 HR DAY
-3.5 HRS(44%) PRODUCTIVE TIME
-1.2 HRS(15%) UNAVOIDABLE DELAYS
-3.3 HRS(41%) WASTED TIME
REASONS FOR PRODUCTIVITY LOSS
-POOR PLANNING AND WORK SCHEDULING (35%)
-UNCLEAR INSTRUCTIONS TO EMPLOYEES(25%)
-INABILITY TO ADJUST STAFF SIZE AND DUTIESDURING PEAK LOADS(15%)eg BANK CASH
DISPENSING TELLERS
-POOR COORDINATION OF MATRL FLOW
,UNAVAILABILITY OF MACHINE(25%)
-
8/2/2019 Prod Techniques Old
38/582
COMMON MFG RATIOS
UNITS PRODUCED/LABOR HRS
REWORK HRS REQD/UNITS
PRODUCED
NUMBER DEFECTS/TOTAL UNITS
MACHINE UTILIZATION %
WT OF WASTE/WT OF FINISHED
GOODS
WT OF FINISHED GOODS/RM WEIGHT
-
8/2/2019 Prod Techniques Old
39/582
COMMON SERVICES RATIOS
NUMBER OF CUSTOMER
COMPLAINTS/ORDERS DELIVERED OR
NUMBER OF PRODUCTS SOLD NUMBER OF DATA ENTRY ERRORS /TOTAL
DATA ENTERED
LATE DELIVERIES/TOTAL DELIVERIES
PROJECT PLANNED COST/ACTUAL COST
OVERTIME HRS/REGULAR HRS
CUSTOMER RETURNS%
WARRANTY COSTS/SALES%
-
8/2/2019 Prod Techniques Old
40/582
HARD METRICS IN
PRODUCTIVITY PLANT UTILIZATION
ENERGY EFFECTIVENESS INDEX
NUMBER OF ACCIDENTS AND HRS
LOST DUE TO ACCIDENTS
OVERALL PLANT EFFECTIVENESS
OVERALL PROCUREMENT
EFFECTIVENESS
OVERALL DISTRIBUTION
EFFECTIVESS
-
8/2/2019 Prod Techniques Old
41/582
SOFT METRICS IN
PRODUCTIVITY EMPLOYE MORALE
EMPLOYEE LOYALTY
EMPLOYEE INVOLVEMENT
JOB SATISFACTION
HONESTY
-
8/2/2019 Prod Techniques Old
42/582
SUMANTHS TOTAL
PRODUCTIVITY MODEL MODEL DEFINES TOTAL PRODUCTIVITY
MEASURE WHICH INCLUDES ALL THE OUTPUT
AND INPUT FACTORS
THE TPM IS BASED ON TANGIBLE OUTPUT AND
INPUT ELEMENTS WHICH ARE DIRECTLY
MEASUREABLE AND QUANTIFIABLE
MODEL ALSO REFLECTS THE IMPACT OF
INTANGIBLES DIRECTLY eg IF THE TOTALPRODUCTIVITY LEVEL GOES DOWN IN A PERIOD
IT COULD BE BECAUSE OF POOR QLTY OF RAW
MATRL WHICH INCREASE THE MATRL INPUT OR
REDUCED OUTPUT AS A RESULT OF REWORK
-
8/2/2019 Prod Techniques Old
43/582
IMPLEMENTATION PROCESS FOR
TOTAL PRODUCTIVITY MGT MISSION STATEMENT DEVELOPMENT
TOTAL PRODUCTIVITY MODEL AND COMPREHENSIVE
TOTAL PRODUCTIVITY MODEL ANALYSIS
MGT GOALS DEVELOPMENT FISHBONE ANALYSIS
ACTION PLANS DEVELOPMENT
PRODUCTIVITY QUALITY TEAM TRAINING
IMPLEMENTATION OF ACTION PLANS
ASSESSING THE EXTENT TO WHICH THE MGT GOALS ARE
ACHIEVED
TOTAL PRODUCTIVITY GAINSHARING
NEW GOALS DEVELOPMENT
-
8/2/2019 Prod Techniques Old
44/582
STEP 1 MISSION
STATEMENT AN ENTERPRISE WITHOUT A MISSION STATEMENT IS LIKE
A BUILDING WITHOUT A FOUNDATION
MOST COMPANIES HAVE SO LITTLE SUCCESS WITH NEW
IDEAS BECAUSE THEY DONT HAVE A CENTRAL GUIDINGPHILOSOPHY CAPTURED THRU A VISION AND A MISSION
A VISION REPRESENTS A VERY LONG TERM GOAL
A MISSION REPRESENTS A SHORT TO MEDIUM TERM
STATEMENT OF PURPOSE
A MISSION STRETCHED OVER A RELATIVELY LONG PERIODOF TIME BECOMES A VISION
A CORRECTLY DRAFTED MISSION SHOULD HAVE SEVERAL
CHARACTERISTICS
-
8/2/2019 Prod Techniques Old
45/582
FACTORS TO BE CONSIDERED
IN MISSION STATEMENT HIGHLIGHT MAJOR STRENGTHS
HIGHLIGHT ENVIRONMENTAL FACTORS
SUCH AS ECONOMIC,POLITICAL,SOCIAL) STRATEGY FOR COMBATTING
COMPETITION
QUALITY OF SERVICE
STRATEGY FOR SUPPLIERS
CUSTOMER CHARACTERISTICS
MARKET CHARACTERISTICS
-
8/2/2019 Prod Techniques Old
46/582
CHARACTERISTICS OF
GOOD MISSION STATEMENT ARTICULATES GUIDING PHILOSOPHY OF
ENTERPRISE WITH A CENTRAL FOCUS
CONCISELY WORDED COMES NATURALLY TO EVERYONE
DEVELOPED CAREFULLY THRU ACTIVE
INVOLVEMENT OF EMPLOYEES
NEEDS TO BE REVISED AS PER THE
TACTICAL AND STRATEGIC PLANS OF THE
COMPANY AND THE THEN PREVAILING
INDUSTRIAL ENVIRONMENTAL OUTLOOK
-
8/2/2019 Prod Techniques Old
47/582
STEP 2 TPM ANALYSIS
TRENDS DISCOVERY IN
-TOTAL PRODUCTIVITY-BREAK EVEN POINT OF TOTAL PRODUCTIVITY
-HUMAN PRODUCTIVITY
-MATERIALS PRODUCTIVITY-FIXED CAPITAL PRODUCTIVITY
-WORKING CAPITAL PRODUCTIVITY
-ENERGY PRODUCTIVITY
-OTHER EXPENSES PRODUCTIVITY
-
8/2/2019 Prod Techniques Old
48/582
STEP 3 MANAGEMENT
GOALS FOUR CRITERIA FOR A GOAL TO QUALIFY AS A MGT GOAL
EVERY MGT GOAL MUST
-ACHIEVE MISSION STATEMENT
-BE VERY SPECIFIC
-BE TIME BASED
-BE VERIFIABLE
IN HMT THE GOALS ESTABLISHED WERE
-INCREASE HUMAN PRODUCTIVITY BY 7% PER YEAR
-INCREASE OTHER EXPENSE PRODUCTIVITY BY 3.5% YRLY
-REDUCE INVENTORIES BY 5% INORDER TO INCREASE
WORKING CAP ITAL PRODUCTIVITY
-
8/2/2019 Prod Techniques Old
49/582
STEP 4 FISHBONE ANALYSIS
WELL ESTABLISHED TOOL TO ANALYZE
THE CAUSES FOR A PROBLEM
FISHBONE ANALYSIS DONE FOR EACH OFMGT GOALS IN STEP 3
IF A COMPANY CAREFULLY ANALYZES
ALL TASKS , PROCESSES AND
TECHNIQUES NEEDED TO ACCOMPLISHEACH MGT GOAL , IT WILL BE BETTER
EQUIPPED TO ALLOCATE RESOURCES
TOGOALS THAT WOULD ATTAIN ITS
MISSION
-
8/2/2019 Prod Techniques Old
50/582
Cause-and-Effect Diagram for
Manufacturing
Exhibit S6.8
-
8/2/2019 Prod Techniques Old
51/582
STEP 5 ACTION PLANS
ACTION PLAN IS DEVELOPED FOR EACH MGT GOAL
ACION PLAN INCLUDES DETAILS OF TASKS ,START AND
END DATES,PEOPLE RESPONSIBLE FOR EACH TASK
ACTION PLAN IS ANOTHER WAY TO CREATE A CAREFULTHOUGHT OUT PLAN OF ACTION TO ACHIEVE A MGT GOAL
TOOL TO ASSIGN PEOPLE TO TASKS WHICH WHEN
ACCOMPLISHED WILL ACHIEVE MGT GOALS WHICH IN
TURN WILL AID ACHIEVEMENT OF VISION AND MISSION
ACTION PLAN HELPS IDENTIFY BOTTLENECKS
-
8/2/2019 Prod Techniques Old
52/582
STEP 6 PRODUCTIVITY
QUALITY TEAM TRAINING TRG IS PROVIDED TO ALL
EMPLOYEES SO THAT THEY HAVE
THE REQUISITE TOOLS TOACCOMPLISH TASKS IN THE ACTION
PLANS IN AN EFFECTIVE AND
EFFICIENT MANNER TRAINING FOCUSES ON PROBLEM
SOLVING
-
8/2/2019 Prod Techniques Old
53/582
STEP 7 IMPLEMENTATION
OF ACTION PLANS IMPLEMENTATION BECOMES MORE
SYSTEMATIC WITH DETAILED
ACTION PLAN ACTION PLANS ARE CONSTANTLY
REVISED AS THE TASKS PROGRESS
THER IS A CONTINUOUS FEEDBACKCONTROL WHICH IS MONITORED
CAREFULLY
-
8/2/2019 Prod Techniques Old
54/582
STEP 8 MGT GOALS
ACHIEVED PROGRESS TOWARDS ACHIEVEMENT OF
GOALS IN STEP 3 ASSESSED ON A
PERIODIC BASIS SAY QUARTERLY
IF A GOAL IS NOT ACHIEVED THE ACTION
PLAN RELATED TO THAT GOAL NEEDS TO
BE REVIEWED AND CORRECTIVE ACTION
INITIATED WHICH INCLUDESDOWNSIZING OF GOAL IF ACHIEVEMENT
IS NOT POSSIBLE DUE TO INTERNAL AND
EXTERNAL ENVIRONMENTAL CAUSES
-
8/2/2019 Prod Techniques Old
55/582
STEP 9 TOTAL PRODUCTIVITY
GAIN SHARING BRAINSTORMING APPROACH BASED ON TOTAL
PRODUCTIVITY
STEP PROVIDES FOR A TANGIBLE MONETARY INCENTIVE
TO ACHIEVE THE MAXIMUM POSSIBLE POTENTIAL OF TPM
REASONS FOR INCLUDING GAIN SHARING IN TPM INCLUDE
-NEED TO SUSTAIN MOTIVATION IN NEW CONCEPTS.
INTANGIBLE MOTIVATION IS A NECCESARY CONDITION
NOT A SUFFICIENT ONE TO SUSTAIN POSITIVE
MOTIVATION
-IT IS FAIR TO SHARE GAINS WITH RESPONSIBLE FOR IT
-RATE OF NEW HIRING CAN BE REDUCED DRAMATICALLY
-
8/2/2019 Prod Techniques Old
56/582
STEP 10 NEW GOALS
SET NEW GOALS WHEN ALL
PREVIOUS GOALS HAVE BEEN
ACHIEVED SET ANNUAL GOALS. THIS LOOKS
OKAY BUT IN A DYNAMICALLY
CHANGING SITUATION ANNUALREVIEW OF GOALS MAY BE A BIT
TOO LATE. NEED TO REVIEW EITHER
ON A QTRLY BASIS OR WHENEVER
-
8/2/2019 Prod Techniques Old
57/582
HOW PRODUCTIVITY CAN
BE IMPROVED INCREASING OUTPUT WITH SAME
INPUT
INCREASING OUTPUT MORE THANTHE INCREASED INPUT
DECREASING INPUT FOR SAME
OUTPUT INCREASING OUTPUT WITH
DECREASED INPUT
-
8/2/2019 Prod Techniques Old
58/582
BENEFITS OF TOTAL
PRODUCTIVITY MGT CUSTOMER RESPONSIVENESS
QUALITY COMPETITIVENESS
TOTAL COST COMPETITIVENESS TEAM BUILDING AND ACCOUNTABILITY
TECHNOLOGY PLANNING
INVESTMENT ANALYSIS ACQUISITION AND MERGER PLANNING
PROFIT TARGETTING
-
8/2/2019 Prod Techniques Old
59/582
WASTE MANAGEMENT
-
8/2/2019 Prod Techniques Old
60/582
Wasteis anything other than
the minimum amount of
equipment, materials, parts,space, and workers time,
which are absolutely
essential to add value to the
product.
Shoichiro Toyoda
President, Toyota 1995 Corel Corp.
Introductory Quotation
-
8/2/2019 Prod Techniques Old
61/582
61
What is WASTE?
Any Activity that DOES NOT increase the Market Form
or Function of the Product or Service based on the
Critical Customer Requirements.
These are things the customer is NOT
willing to pay for.
DEFINITION OF
-
8/2/2019 Prod Techniques Old
62/582
DEFINITION OFWASTE
THE OXFORD DICTIONARY DEFINES WASTEAS UNPURPOSEFUL OR EXTRAVAGANTACTIVITY WHICH RESULTS IN
UNPRODUCTIVE END RESULTS WASTE IS A PRODUCT,ACTIVITY OR
SERVICE FOR WHICH AN EXTERNALCUSTOMER IS UNWILLING TO PAY FOR
CASE OF SECURITY CESS IN RAILWAYS WASTE IS ONLY NUISANCE VALUE TO
CUSTOMER
-
8/2/2019 Prod Techniques Old
63/582
WASTE MANAGEMENT
WASTE EXISTS EVERYWHERE FROMINDUSTRY TO HUMAN ACTIVITIES
IN ANY PROCESS WASTE ACCOUNTS FOR
A VERY LARGE AMOUNT OF NON VALUEADD ACTIVITY
MGT NEEDS TO CONTROL ACTIVITIESBETTER THRU TIGHTER CONTROL
WASTE MGT IMPROVES COSTS ANDPRODUCTIVITY AND REDUCES CYCLETIMES
-
8/2/2019 Prod Techniques Old
64/582
MUDA MURI MURA
3 JAPANESE TERMS USED BY TOYOTA TO
SIGNIFY DIFFERENT TYPES OF WASTES
MUDA IS WASTE. TWO TYPES OF WASTE TYPE 1
MUDA UNAVOIDABLE WASTE OR FORCEDSCRAP(ESSENTIAL NVA);TYPE 2 OR AVOIDABLE
WASTE
MURA IS WASTE OF INCONSISTENCY OR
UNEVENNESS OF FLOW.UNEVENNESS INPRODUCTION FORCES PROCESSES TO DEAL WITH
SPIKES IN DEMAND AND HAS IDLENESS IN
SLACK PERIODS
MURI IS OVERBURDENING OF SYSTEM64
-
8/2/2019 Prod Techniques Old
65/582
65
Eliminate Waste
Mudaanything that does not add value
for the customer
Products in storageProducts being inspected
Products waiting in queues
Defective productsUnnecessary movement of materials or workers
- 2 TYPES OF WASTES TYPE 1 WASTE WHICH ISESSENTIAL NON VALUE ADD ACTIVITIES AND TYPE 2
WASTE WHICH IS ELIMINATABLE eg INSPECTION
-
8/2/2019 Prod Techniques Old
66/582
66
Examples of Waste Idle machine run Waiting for parts
Counting parts
Overproduction Moving parts over long distances
Storing inventory
Looking for tools
Machine breakdown
Rework
-
8/2/2019 Prod Techniques Old
67/582
Common Causes of Waste
Layout (distance)
Long setup time
Incapable processes Poor maintenance
Poor work methods
Lack of training
Inconsistentperformance measures
Ineffective production
planning
Lack of workplaceorganization
Poor supplyquality/reliability
C C f W t
-
8/2/2019 Prod Techniques Old
68/582
Common Causes of Waste Excess Manning
Poor layout and material presentation Rework and extra processes
Inconsistent / inefficient work methods
Excess Downtime
Tooling condition Unreliable equipment
Long changeovers
Incapable process
Defectives - Rework or Replace
Incapable processes or process not compatiblewith customer expectations or design spec (designfor mfg)
Tooling condition
Operator methods and errors
Where is the Waste?
-
8/2/2019 Prod Techniques Old
69/582
69
Where is the Waste?
Defects incomplete or incorrect information
Overproduction releasing work before nextprocess can work on them, unbalanced work loads
Waiting unbalanced work loads, slow system response,incomplete information, approvals
Not Utilizing Employees old guard thinking, politics, high
turnover, low investment in training
Transportation poor layout, poor flow
Inventory large batches, complexity to complete task
Motion poor organization, no standard work
Excess Processing excess communication, lack ofcommunication, unnecessary approvals, customer
requirements are not clearly understood
All processes have waste.
-
8/2/2019 Prod Techniques Old
70/582
. 9-70
Types of Waste (Muda)
in Toyota production system Overproduction
Waiting
Transportation
Inventory
Motion
Overprocessing
Defects
-
8/2/2019 Prod Techniques Old
71/582
PRODUCING DEFECTS
DEFECTS IN PRODUCT / SERVICE ARE MAJOR SOURCE OF WASTE
COSTS OF WASTE INCLUDE WARRANTY COSTS,ATTENDINGCOMPLAINTS AS WELL AS REWORK,INSPECTION
CASE OF DELL COMPUTERS
PRODUCT DEFECTS TO BE ELIMINATED BY QUALITY ASSURANCE INDESIGN ELIMINATING NEED TO INSPECT OR REWORK
DEFECTS INCREASE PRODUCTION COSTS AND LEAD TIME OFMANUFACTURE
DEFECTS DUE TO WRONG OPERATING PROCEDURES,VARIATIONS INOPERATIONS RESULTING IN M/C WEAR,DEFECTIVE RAW
MATRL,OPERATOR ERROR etc
TRANSPORTATION AND
-
8/2/2019 Prod Techniques Old
72/582
TRANSPORTATION ANDMATERIAL HANDLING
ITEMS IN MFG MOVED FROM STATION TO STATION TRANSPORTATION WASTES TIME AND IN THE CASE
OF HUMAN BEINGS WHO MAY HAVE TO MOVE FROMSTATION TO STATION TO DO WORK IT IS
FATIGUING AND CAUSES DECLINE INPRODUCTIVITY AND INCREASE IN ERROR RATES OBJECTIVE IS TO MINIMIZE HUMAN EFFORT IN
TRANSPORTATION AND MATERIAL HANDLING BYHAVING CONVEYOR BELTS
CASE STUDY OF AUTOMOBILE ASSEMBLY LINEWHERE AUTOMOBILE MOVES ON THE CONVEYORBELT AND MAN IS STATIONARY.TIME REDUCEDFROM 12HRS/CAR TO 1 HR/ASSEMBLY
-
8/2/2019 Prod Techniques Old
73/582
INVENTORY
INVENTORY AS PER TOYOTA IS ONE OF THE SEVENSINS
INVENTORY REPRESENTS ITEMS WAITING FORSOMETHING TO HAPPEN (JUST IN CASE)
INVENTORY IS CARRIED TO PREEMPT DELAYS INDELIVERY OF PROCESS INPUT OR TO PROVIDE FORCUSHION STOCKS TO TAKE CARE OF MFGREWORK/SCRAP (SOME CUSHIONS ACCOUNT FORAS MUCH AS 5% OF RAW MATERIAL)
WASTES ASSOCIATED WITH HOLDING COSTS,DEPRECIATION, EXPIRY DATES , DETERIORATION.PILFERAGE ETC
JUST IN TIME IS THE REMEDY FOR EFFECTING ZEROINVENTORY
-
8/2/2019 Prod Techniques Old
74/582
OVERPRODUCTION
EXCESS PRODUCTION BECAUSE OFWRONG SALES FORECASTS OR ATTEMPTTO KEEP FACILITIES RUNNING
MFG OF EXCESS PRODUCTION IS WASTE
CASE OF ALL SALES OF READY MADEGARMENTS
WASTE FROM OVERPRODUCTION ISREFLECTED IN UNSOLD STOCKS WHICH
ADD TO FINISHED GOODS INVENTORY
-
8/2/2019 Prod Techniques Old
75/582
WAITING
WASTE OF WAITING IS EASY TO IDENTIFY
WAITING IS A RESULT OF UNBALANCEDPROCESS SEQUENCE OR BREAKDOWN INBOTTLENECK PROCESS
INCLUDES WAITING FOR ORDERS, RAWMATERIAL, POWER, SPARES, LABOUR OR EVENFUNDS TO PROCURE RESOURCES
WAITING ALSO INCLUDES ITEMS FROM
PRECEDING PROCESSES EXAMPLE OF PILE UP OF WIP OR PERISHABLES
AWAITING CUSTOMS CLEARANCE
WAITING
-
8/2/2019 Prod Techniques Old
76/582
WAITING
WAITING MINIMIZED BY BUSINESSPROCESS ACTIVITY IMPROVEMENT ORMINIMIZATION OF LEAD TIME TO
PROCURE THROUGH VENDOR MANAGEDINVENTORY OR OTHER INITIATIVES
WAITING ALSO MINIMIZED BY GOOD
MAINTENANCE PRACTICES SUCH AS CBMRESULTING IN MAXIMIZEDEFFECTIVENESS
PROCESSING
-
8/2/2019 Prod Techniques Old
77/582
PROCESSING
PROCESS MAY CONTAIN ACTIVITIES WHICH AREINEFFECTIVE OR UNNECCESARY
PROCESSING WASTE CAN BE ELIMINATED BYMINIMIZING MOTION REQUIRED TO PERFORM
WORK ACTIVITY ANALYSIS DONE TO DETERMINE
PROCESS UTILISATION TIME AND THEREAFTER
PROCESS IMPROVEMENT DONE TO ELIMINATEDELAYS AND NON VALUE ADDED ACTIVITIES
MOTION
-
8/2/2019 Prod Techniques Old
78/582
MOTION
BEING IN MOTION IS INCORRECTLY CONNOTED TO BE ATWORK
MOTION AND WORK ARE NOT THE SAME
WORK IS CONSIDERED A PARTICULAR KIND OF MOTION THATADDS VALUE
AN APPARENTLY BUSY PERSON MAY ACTUALLY PRODUCEVERY LITTLE WORK
INHERENT HANDICAP AT RIGHT HANDED WORKPLACE FORLEFTHANDERS
MOTION UNREQD TO DO WORK IS WASTE
EXCESSIVE MOTION CAUSES FATIGUE AND LOSS OFPRODUCTIVITY AND INCREASE OF WASTE
CASE OF BEARING LIFETIME INVERSELY PROPORTIONAL TORPM
ROOT CAUSE OF TOYOTA
-
8/2/2019 Prod Techniques Old
79/582
ROOT CAUSE OF TOYOTAWASTES
USAGE OF 5 WHY ANALYSIS
DEFECTS
-INADEQUATE DESIGN POOR MATERIAL
-WRONG PROCESS SPECIFICATIONS
-OPERATOR ERROR -INADEQUATE TESTING
TRANSPORTATION
-WAIT TIME TO TRAVEL -LAYOUT
INVENTORY
-OBSOLETE STOCKSJUST IN CASEWRONGFORECST
CUSTOMER CANCELLATIONSMKT SLUMP
OVERPRODUCTION -WRONG FORECAST
ROOT CAUSE OF TOYOTA
-
8/2/2019 Prod Techniques Old
80/582
OO U O O OWASTES
WAIT TIME
-IMBALANCE IN PROCESS THROUGHPUT ORPROCESS BREAKDOWN
-POOR SCHEDULING -INADEQUATE LABOURSCHEDULING
MOTION
-EXCESS MOTIONEXCESS PAPER DISTRIBUTION
PROCESSING-INEFFECTIVE OR NON VALUE ADDED STEPS
REMEDIESFOR TOYOTA
-
8/2/2019 Prod Techniques Old
81/582
WASTES
WASTE REMEDY
OVERPRODUCTION JIT/PULL PRODUCTIONWAITING PROCESS ACTIVITY STUDY
TRANSPORTATION MOTION STUDYWRONG PROCESSING METHOD STUDYEXTRA INVENTORY JUST IN TIMEEXTRA MOTION MOTION STUDY
DEFECTS ROOT CAUSE ANALYSISAND FMECA
OFFICE WASTES
-
8/2/2019 Prod Techniques Old
82/582
OFFICE WASTES
ERRORS IN DOCUMENTS
DOING UNREQUIRED WORK NOT REQUESTED PROCESS OF GETTING APPROVALS AND NEEDLESS LEVELS OF
APPROVALS BACKLOG OF WORK UNREQUIRED STATIONERY FILES PAPERS AT WORKPLACE UNCLEAR JOB DESCRIPTIONS RESULTING IN UNDEFINED
OUTCOMES EXCESS DEBIT CREDIT NOTES DUE TO ERRONEOUS PO
INVOICE OBSOLETE DATABASES TYPOGRAPHICAL ERRORS UNREQUIRED COMMUNICATION
-
8/2/2019 Prod Techniques Old
83/582
TOTAL WASTE REDUCTION
WASTE MAY EXIST IN PROCEDURES POLICIESSYSTEMS AND IS DIFFICULT TO IDENTIFYHIDDEN WASTES
AUTOMATION IS NOT THE SOLUTION TO WASTE
NEED OF THE HOUR IS TO IDENTIFY REALWASTES THAT AFFECT BOTTOM LINES
WASTE MGT SHOULD BE A CONTINUOUS DRIVEON THE GUIDELINES OF TQM
PERIODIC REVIEW OFPOLICIES,PROCEDURES,PROCESSES TO ENSUREPROCESS IMPROVEMENT AND WASTEREDUCTION
LEVELS OF WASTE
-
8/2/2019 Prod Techniques Old
84/582
LEVELS OF WASTE
FOUR LEVELS OF WASTE-BUSINESS LEVEL WASTES-PLANT LEVEL WASTES
-PROCESS AND METHOD WASTES-OPERATING LEVEL WASTES
LEVEL 1 BUSINESS LEVEL
-
8/2/2019 Prod Techniques Old
85/582
LEVEL 1 BUSINESS LEVELWASTE
LONG TERM AND SHORT TERM GOALS NOT COMMENSURATEWITH CAPABILITIES AND CAPACITY
SHORT TERM GOALS NOT ALIGNED WITH LONG TERMSTRATEGIC GOALS WHICH ENABLE THE REALISATION OF
VISION STRATEGIC OBJECTIVES OF EACH FUNCTION NOT IN UNISON
WITH CORPORATE OBJECTIVES LACK OF COORDINATION AND UNDERSTANDING WITH
STAKEHOLDERS LOP SIDED FINANCING INSTAL OF EXTRA CAPACITY W/O MAXIMISATION OF
CURRENT STRATEGIC DIVERSIFICATION IN AREAS WITHOUT
OPPORTUNITIES AND CORE COMPETENCE INEFFICIENT PRODUCT LIFECYCLE PLANNING AND MGT
LEVEL 2 PLANT LEVEL WASTE
-
8/2/2019 Prod Techniques Old
86/582
LEVEL 2 PLANT LEVEL WASTE
POOR PPC NOT BASED ON MARKETDYNAMICS
HIGH INVENTORIES
LOW PLANT EFFECTIVENESS ANDUNPROFITABLE OPERATIONS
HIGH OVERTIME PAYMENTS BUT LOWEMPLOYEE PRODUCTIVITY
LEVEL 3 PROCESS AND
-
8/2/2019 Prod Techniques Old
87/582
3 OC SSMETHODS LEVEL WASTE
INCORRECT OR INEFFECTIVEPROCESS METHODS
BORNE OUT OF LACK OF SKILLS OR
ATTITUDE
NEED TO MONITOR AND DO PERIODICMETHOD STUDIES TO MAXIMIZE
PROCESS THROUGHPUT WITHMINIMUM EFFORT
LEVEL 4 OPERATIVE LEVEL
-
8/2/2019 Prod Techniques Old
88/582
WASTE
POOR OPERATIVE CONTROLSRESULTING IN HIGH MFG COSTS
HIGH REWORK/REJECT CONTENT eg
.04% value of sales realized thru saleof scrap in 2008-09 and 0.16% valueof sales realized in 2009-10
UNDULY HIGH REACTIVEMAINTENANCE % ie 17.5% ofmaintenance time against 2% world
class (includes 7% breakdown)
-
8/2/2019 Prod Techniques Old
89/582
Root cause of waste
Defects
Inadequate Design - Poor Matrl - Wrong Proc - Oper Error
Inadequate Testing
Over Production
Over enthusiastic incentive - Wrong Forecast
Excess Inventory
Obsolete Stocks - Wrong Forecast - Customer amendments/cancellation
Poor Quality - Market Condition
Unrequired Motions
Over use of paper/distribution - Excess Walking - Excess Motions
Transportation Layout - wait time to travel
Wait Time
Poor Scheduling - Imbalance in prodn line - Inadequate labor resource
-
8/2/2019 Prod Techniques Old
90/582
Root cause of waste
Process
Wrong operations or poor material leading to rework orreject
Poor process control Poor operating specifications
Untrained or de motivated operators
-
8/2/2019 Prod Techniques Old
91/582
NON VALUE ADDED
ACTIVITIES
-
8/2/2019 Prod Techniques Old
92/582
BUSINESS PROCESSES
EVERYTHING WE DO IS A PROCESS AND CONSISTS OF INPUTSPROCESSING AND OUTPUT
PROCESS TAKES INPUT FROM SUPPLIERS,ADDS VALUE ANDDELIVERS OUTPUT TO CUSTOMER
CUSTOMER COULD BE INTERNAL OR EXTERNAL AND SUPPLIER
COULD BE THE SAME AS CUSTOMER PROCESSES ARE SET OF LOGICALLY RELATED ACTIVITIES
LINKED BY RULES WHICH COMBINE TO DELIVER VALUE TOCUSTOMERS ACROSS FUNCTIONAL LINES . THEY USEPREDETERMINED LOGIC RULES TO PROCESS INPUTS
PROCESSES USE INPUTS FROM SUPPLIERS SUCH AS INFORMATIONSKILLS TRAINING PEOPLE,EQUIPMENT,MATERIAL,PROCEDURES
METHODS SPECIFICATIONS SERVICES KNOWLEDGE AND VOICEOF CUSTOMER
PROCESS PROCESSES INPUTS AS PER THE BUSINESS RULES ANDACTIVITY DEPENDENCIES
PROCESSES OUTPUT PRODUCTS SERVICES INFORMATION TOCUSTOMERS
OUTPUTS RESULT IN OUTCOMES WHICH ARE MEASURES
OUTCOMES ARE COMPARED WITH TARGETS AND RESULT IN
PROCESS MECHANICS
-
8/2/2019 Prod Techniques Old
93/582
MATERIALS
PROCEDURES
METHODS DATA
PEOPLE WITH SKILLS
KNOWLEDGE
MANAGEMENT
TRAINING
EQUIPMENT
FINANCE
BUSINESS RULES CONTROLS
ACTIVITIES
DEPENDENCIES
CONSTRAINTS
CAPABILITY
PRODUCTS
SERVICES
INFO
WASTE
INPUTS OUTPUTS CUSTOMER
VOICE OF THE
CUSTOMER
VOICE OF PROCESS
INPUTS PROCESS OUTPUTS
ACTIVITIES IN AN
-
8/2/2019 Prod Techniques Old
94/582
ACTIVITIES IN AN
ORGANIZATION EVERY THING WE DO IN A COMPANY IS A
PART OF A LARGER PROCESS WHICH IS
EXECUTED TO ACHIEVE BUSINESS
RESULTS
PROCESS COMPRISES OF SUB PROCESSES
SUB PROCESS IS DIDIDED INTO
ACTIVITIES WHICH CAN BE // OR INSEQUENCE
ACTIVITIES CAN BE DIVIDED INTO
INDIVISIBLE TASKS
PROCESS DECOMPOSITION INTO ACTIVITIES
ORDER TO
-
8/2/2019 Prod Techniques Old
95/582
ORDER TO
CASH
ORDER
PROCESSING
PLAN TO
PRODUCE
DELIVER
NET MRP
MFG WO
PROCURE
TO PAY
RECEIVE
CASH
ACCEPT
TO
INVOICE
DELY TOACCEPT
TENDER
TO PO OR
PR TO PO
OPTIONAL
PO TO
TENDER
INDENT
TO PR
INVOICE
TO PAY
AWARD TOSUPPLIER
WRITE PROCURE
DETAILS WITH
QTY, RATE, DELVY
SCHEDULE,ETC
MULTI LEVEL
APPROVALAPPROVE PODESPATCH PO
ACTIVITIES
VALUE AND NON VALUE ADD
-
8/2/2019 Prod Techniques Old
96/582
VALUE AND NON VALUE ADD
ACTIVITIES MANY ACTIVITIES PERFORMED WHILE WORKING AND ARE
THE BUSINESS OUTCOMES OF PROCESSES
VALUE ADD ACTIVITIES ARE THOSE WHICH CUSTOMER ISWILLING TO PAY FOR
NON VALUE ADD ACTIVITIES ARE THOSE ACTIVITIESWHICH THE CUSTOMER WILL NOT PAY FOR
NON VALUE ADD ACTIVITIES MAY BE ESSENTIAL egSAFETY OR NON ESSENTIAL
PROCESS IMPROVEMENT NEEDS TO BE DONE ONESSENTIAL ACTIVITIES TO REDUCE COSTS,TIME ANDRESOURCES
NON VALUE ADD ACTIVITIES NEED TO BE EITHERELIMINATED OR MINIMISED AS THESE ACTIVITIES ONLYADD TO THE COSTS
VALUE ADDED ASSESSMENT
-
8/2/2019 Prod Techniques Old
97/582
ACTIVITY
REQD TO
PRODUC
E O/P
CONTRI
BUTES
TO CUST
REQMT
REQD TO
PRODUC
E O/P
ESSENTIAL NON
VALUE ADD
NON VALUE
ADD
REAL VALUE ADD
Y
NY
N
NY
ACTIVITY
-
8/2/2019 Prod Techniques Old
98/582
MAPPING AS-IS
INDENT TO
PURCHASE
ACTIVITY MAPPING AS-IS
INDENT TO PURCHASE
-
8/2/2019 Prod Techniques Old
99/582
INDENT TO PURCHASE
-
8/2/2019 Prod Techniques Old
100/582
-
8/2/2019 Prod Techniques Old
101/582
ACTIVITY MAPPING
AS-IS INDENT TO
-
8/2/2019 Prod Techniques Old
102/582
S S N N O
PURCHASE
ACTIVITY MAPPING
AS-IS INDENT TO
-
8/2/2019 Prod Techniques Old
103/582
PURCHASE
ACTIVITY MAPPING TO BE TO
BE INDENT TO PURCHASE
-
8/2/2019 Prod Techniques Old
104/582
ACTIVITY MAPPING
TO BE INDENT TO
-
8/2/2019 Prod Techniques Old
105/582
PURCHASE
ACTIVITY MAPPING
TO BE INDENT TO
-
8/2/2019 Prod Techniques Old
106/582
PURCHASE
-
8/2/2019 Prod Techniques Old
107/582
ACTIVITY MAPPING
TO BE INDENT TO
-
8/2/2019 Prod Techniques Old
108/582
PURCHASE
-
8/2/2019 Prod Techniques Old
109/582
PROCESS WASTE
-
8/2/2019 Prod Techniques Old
110/582
WASTE MANAGEMENT
WASTE EXISTS EVERYWHERE FROMINDUSTRY TO HUMAN ACTIVITIES
IN ANY PROCESS WASTE ACCOUNTS FOR
A VERY LARGE AMOUNT OF NON VALUEADD ACTIVITY
MGT NEEDS TO CONTROL ACTIVITIESBETTER THRU TIGHTER CONTROL
WASTE MGT IMPROVES COSTS ANDPRODUCTIVITY AND REDUCES CYCLETIMES
LEVELS OF WASTE
-
8/2/2019 Prod Techniques Old
111/582
LEVELS OF WASTE
FOUR LEVELS OF WASTE-BUSINESS LEVEL WASTES-PLANT LEVEL WASTES
-PROCESS AND METHOD WASTES-OPERATING LEVEL WASTES
-
8/2/2019 Prod Techniques Old
112/582
LEVELS OF WASTE
FOUR LEVELS OF WASTE:-LEVEL 1 refers to business related wastes. It includeswastes due to cross functional issues, poor communicationand coordination between vendors, customers and even
poor investment decisions-LEVEL 2 refers to plant level wastes. It includes faultyproduction planning and control, poor layout resulting inun required movement and WIP It includes poor m/ccapability resulting in rework, scrap and rejection. It alsoincludes poor maintenance policies
-
8/2/2019 Prod Techniques Old
113/582
LEVEL 1 BUSINESS LEVEL
-
8/2/2019 Prod Techniques Old
114/582
LEVEL 1 BUSINESS LEVEL
WASTE
Faulty performance measure
Poor business policies and short sightedness at top
level
Poor communication and coordination between
vendors and customers
Too much emphasis on utilization of resources
Excess production
Poor product and process design
LEVEL 1 BUSINESS LEVELWASTE
-
8/2/2019 Prod Techniques Old
115/582
WASTE
LONG TERM AND SHORT TERM GOALS NOT COMMENSURATEWITH CAPABILITIES AND CAPACITY SHORT TERM GOALS NOT ALIGNED WITH LONG TERM
STRATEGIC GOALS WHICH ENABLE THE REALISATION OFVISION
STRATEGIC OBJECTIVES OF EACH FUNCTION NOT IN UNISON
WITH CORPORATE OBJECTIVES LACK OF COORDINATION AND UNDERSTANDING WITH
STAKEHOLDERS LOP SIDED FINANCING INSTAL OF EXTRA CAPACITY W/O MAXIMISATION OF
CURRENT
STRATEGIC DIVERSIFICATION IN AREAS WITHOUTOPPORTUNITIES AND CORE COMPETENCE
INEFFICIENT PRODUCT LIFECYCLE PLANNING AND MGT
LEVEL 2-PLANT LEVEL
-
8/2/2019 Prod Techniques Old
116/582
LEVEL 2 PLANT LEVEL
WASTES
Play safe tendency
Poor production planning and control
Poor layout resulting in back tracking andexcessive traveling
WIP inventory
Batch size constraints
-
8/2/2019 Prod Techniques Old
117/582
LEVEL 3-PROCESS AND
-
8/2/2019 Prod Techniques Old
118/582
LEVEL 3 PROCESS AND
METHOD WASTES
Poor sequencing of machines and
operations
Long changeover times Poor work place design
Tendency of temporary storage
Incapable and poorly maintained equipment
Unsafe methods
LEVEL 3 PROCESS ANDMETHODS LEVEL WASTE
-
8/2/2019 Prod Techniques Old
119/582
METHODS LEVEL WASTE
INCORRECT OR INEFFECTIVEPROCESS METHODS
BORNE OUT OF LACK OF SKILLS OR
ATTITUDE NEED TO MONITOR AND DO PERIODIC
METHOD STUDIES TO MAXIMIZE
PROCESS THROUGHPUT WITHMINIMUM EFFORT
LEVEL 4-MACHINE/OPERATOR
-
8/2/2019 Prod Techniques Old
120/582
LEVEL 4 MACHINE/OPERATOR
LEVEL WASTES
Poor housekeeping
Excess bending and fatigue
Lack of operator training Operator has to frequently fetch material for
production
LEVEL 4 OPERATIVE LEVELWASTE
-
8/2/2019 Prod Techniques Old
121/582
WASTE
POOR OPERATIVE CONTROLSRESULTING IN HIGH MFG COSTS
HIGH REWORK/REJECT CONTENT
UNDULY HIGH REACTIVEMAINTENANCE %
OFFICE WASTES
-
8/2/2019 Prod Techniques Old
122/582
ERRORS IN DOCUMENTS DOING UNREQUIRED WORK NOT REQUESTED PROCESS OF GETTING APPROVALS AND NEEDLESS LEVELS OF
APPROVALS BACKLOG OF WORK UNREQUIRED STATIONERY FILES PAPERS AT WORKPLACE
UNCLEAR JOB DESCRIPTIONS RESULTING IN UNDEFINEDOUTCOMES EXCESS DEBIT CREDIT NOTES DUE TO ERRONEOUS PO
INVOICE OBSOLETE DATABASES TYPOGRAPHICAL ERRORS UNREQUIRED COMMUNICATION
TOTAL WASTE REDUCTION
-
8/2/2019 Prod Techniques Old
123/582
TOTAL WASTE REDUCTION
STRUCTURED APPROACH TO DEAL WITH
WASTES AND DELAYS WITH VIEW TO
ELIMINATION
APPROACH SEPARATES WASTE(NON
VALUE ADD ACTIVITIES) FROM VALUE
ADDITION AND SCRUTINISES ESSENTIAL
NON VALUE ADD ACTIVITIES FORMINIMISATION OF WASTEFUL ACTIVITIES
PREREQUISITE FOR TQM
TOTAL WASTE REDUCTION
-
8/2/2019 Prod Techniques Old
124/582
TOTAL WASTE REDUCTION
WASTE MAY EXIST IN PROCEDURES POLICIESSYSTEMS AND IS DIFFICULT TO IDENTIFYHIDDEN WASTES
AUTOMATION IS NOT THE SOLUTION TO WASTE
NEED OF THE HOUR IS TO IDENTIFY REALWASTES THAT AFFECT BOTTOM LINES
WASTE MGT SHOULD BE A CONTINUOUS DRIVEON THE GUIDELINES OF TQM
PERIODIC REVIEW OF
POLICIES,PROCEDURES,PROCESSES TO ENSUREPROCESS IMPROVEMENT AND WASTEREDUCTION
TOTAL WASTE REDUCTION
-
8/2/2019 Prod Techniques Old
125/582
TOTAL WASTE REDUCTION
DRASTICALLY IMPROVES QLTY,PRODUCTIVITY,FLEXIBILITY AND SAFETY
REDUCES CYCLE TIME AND IMPROVESRESPONSIVENESS
MAXIMIZES UTILIZATION OF ASSETS ANDPROCESSES
MINIMISES [PROCESS LOSSES AND COST OF NONCONFORMITY
REDUCES PROCESS AND PRODUCT COST AND
IMPROVES CONTRIBUTIONS IMPROVES LIQUIDITY BY FREEING MONEY TIED
UP IN INVENTORIES AND OTHER WASTES
TOYOTA 7 WASTES
-
8/2/2019 Prod Techniques Old
126/582
TOYOTA 7 WASTES
PRODUCTION DEFECTS
TRANSPORTATION
INVENTORY OVER PRODUCTION
WAITING
PROCESSING
MOTIONS AND EFFORT
OTHER( ) WASTES
-
8/2/2019 Prod Techniques Old
127/582
OTHER(canon) WASTES
WASTED CAPACITY
WASTED ENERGY
WASTE FROM LOST OPPORTUNITY
WASTE FROM UNREQD EXPENSES
WASTE FROM UNUTILISED TALENT WASTE FROM LOSSES DUE TOEFFICIENCY,STARTUP,IDLING, BATCH CHANGEOVER
WASTE DUE TO COMMN LOSSES OR INEFFECTIVENESS OFCOMMN
WASTED PLANNING EFFORTS
WASTED INVESTMENTS WASTED OVERSTAFFING
WASTE IN DISPOSAL
ELIMINATION OF 3M
-
8/2/2019 Prod Techniques Old
128/582
ELIMINATION OF 3M
3M STAND FOR MUDA MURA AND MURI
MUDA MEANS WASTES OF ALL KINDSSUCH AS
REWORK,TRANSPORTATION,DELAYS MURA MEANS INCONSISTENCES SUCH ASNON CONFORMANCE TO QLTY AND STDOPERATING PROCEDURES
MURI MEANS NON RATIONALITY ORDISCREPANCY ie UNSCIENTIFIC WAY OFDOING THINGS
ELIMINATION OF 3M
-
8/2/2019 Prod Techniques Old
129/582
ELIMINATION OF 3M
3M EXERCISE DONE TO
-ELIMINATE WHOLE ACTIVITY
-REDUCE STEPS IN ACTIVITY-CHANGE AND SIMPLIFY ACTIVITY
-REDUCE THE TIME COST AND
FATIGUE INVOLVED IN ACTIVITY
MUDA
-
8/2/2019 Prod Techniques Old
130/582
MUDA
MUDA MEANS WASTE
WASTE IS ANY ACTIVITY THAT DOES NOT ADD VALUE
SUCH ACTIVITIES CONTRIBUTE TO COST OF POOR
QUALITY
MUDA IS TOTAL COST OF EXTERNAL PRODUCT/SERVICE
FAILURE PLUS THE COST OF PREVENTIVE MEASURES
MUDA DEFINED IN TOYOTA 7 WASTES AND CANON 9
WASTES
ELIMINATING MUDA REDUCES COST OF PRODN ,
ENHANCES PRODUCTIVITY , REDUCES CYCLE TIME , AND
LEADS TO BETTER CUSTOMER SATISFACTION
8 types of Muda
-
8/2/2019 Prod Techniques Old
131/582
1.Muda of over-production2. Muda of waiting
3. Muda of transport
4. Muda of processing
5. Muda of inventory
6. Muda of motion
7. Muda of repair/rejects
8. Muda of Untapped Human potential
MURI
-
8/2/2019 Prod Techniques Old
132/582
MURI
MURI MEANS UNREASONABLE OR IRRATIONAL
APPROACH TO ANY OPERATION
KAIZEN CHECKLIST TRIES TO LOOK INTO IMPROVEMENT
BY IDENTIFYING AND ELIMINATING THE
UNREASONABLENESS IN AREAS SUCH ASMANPOWER,TECHNIQUE,METHOD,TIME,FACILITIES,TOOLS,
MATERIALS,INVENTORY,PLACE,PRODUCTION,,QUANTITY,
QUALITY, etc
MURI LOOKS FOR IRRATIONALITY WITH FOUR MAJOR
APPROACHES
M ri
-
8/2/2019 Prod Techniques Old
133/582
Muri
Muri = Physical Strain
Bend to work?
Push hard?
Lift weight?
Repeat tiring action?
Wasteful walk?
All this is Muri
4 APPROACHES OF MURI
-
8/2/2019 Prod Techniques Old
134/582
4 APPROACHES OF MURI
THINGS OR ACTIVITIES THAT ARE EXTREMELY DIFFICULT
TO DO AND AT THE MOMENT BEYOND REACH SHOULD BE
IDENTIFIED AND ELIMINATED FROM ACTIVITIES
DO NOT PURSUE ACTIVITIES THAT DO NOT ADD VALUE
IDENTIFY AND REFINE REASONS FOR PERFORMINGACTIVITIES
ELIMINATE IRRATIONAL OPERATIONS THAT CAUSE
FATIGUE
MURA
-
8/2/2019 Prod Techniques Old
135/582
MURA
INCONSISTENCY IN OPERATIONS
DEVIATION FROM STANDARDS
LEADING TO INCONSISTENCY MURA CALLS FOR MINIMUM
DEVIATION BETWEEN BEST AND
WORST PRODUCT BY MINIMIZINGRANGE OF STD DEVIATION USING
SPC
MUDA (WASTE) EXPLAINED OVERPRODUCTION WASTE
-
8/2/2019 Prod Techniques Old
136/582
OCCURS WHEN WE PRODUCE WHAT IS UNNECESSARY, WHEN IT ISUNNECESSARY, AND IN UNNECESSARY AMOUNT.
INVENTORY WASTE
INVENTORY-SYMPTOM OF ILL HEALTH IN FACTORY OPERATIONS. INVENTORYAVOIDS BUT NEVER SOLVES PROBLEMS.
CONVEYANCE WASTE
IS A RESULT OF POOR LAYOUT, HANDLING, OF MATERIAL ETC.
. DEFECT PRODUCTION WASTE
HUMAN ERRORS CAUSE DEFECTS, DEFECTS ARE WASTE AND ALSO CAUSE
WATE OF DETECTION, CORRECTION, CUSTOMER COMPLAINTS ETC. THEYALSO DISRUPT NORMAL FLOW OF GOODS AND REDUCE PRODUCTIVITY
. PROCESS-RELATED WASTE
EXAMPLES:
I. DRILLING MACHINE SCREW HOLES, EVEN AFTER DESIGN HAS CHANGEDTHE FASTENING METHOD TO WELDING
II. USING SIX SCREWS WHERE FOUR MEET THE PURPOSE.
OPERATION RELATED WASTENOT ALL OF WORKERS MOVEMENT IS WORK OR VALUE-ADDING, SUCHWASTE RESULTS FROM POOR EQUIPMENT LAYOUT OR BY POORLY PLACEDPARTS, JIGS & TOOLS.
IDLE TIME WASTE
INCLUDES HUMAN AS WELL AS MACHINE IDLE TIME. GENERALLY IT IS THETIME OF WAITING FOR SOMETHING.
EFFORTS REQUIRED IN WASTE MGTINITIATIVE
-
8/2/2019 Prod Techniques Old
137/582
ELIMINATING WASTE REQUIRES A COMPANYWIDE
INTEGRATED EFFORT WHICH INCLUDES ALLCORPORATE FUNCTIONS SUCH ASMARKETING,SALES,FINANCE,MANUFACTURING,R&D.
INDUSTRIAL ENGG, QUALITY,CUSTOMER SERVICE,
DISTRIBUTION,HR ETC
WASTE AS SEEN COMPRISES OF MFG AND ADMINWASTES
ADMIN WASTES COULD BE EXCESSIVECOMMUNICATION,UNCONTROLLED DISTRIBUTION OF
INFORMATION, DELAYED INFORMATION ,BREAKDOWNIN ADMIN SERVICES, ERRORS IN COMMERCIALDOCUMENTS,WASTED SALES CALLS,UNPRODUCTIVEMEETINGS ETC
COST OF I.T. /INFRASTRUCTURE DOWNTIME A MAJOR
ISSUE AND NEED FOR BUSINESS CONTINUITY PLAN
Root cause of waste
-
8/2/2019 Prod Techniques Old
138/582
Root cause of waste
Defects
Inadequate Design - Poor Matrl - Wrong Proc - Oper Error
Inadequate Testing
Over Production
Over enthusiastic incentive - Wrong Forecast
Excess Inventory Obsolete Stocks - Wrong Forecast - Customer amendments/cancellation
Poor Quality - Market Condition
Unrequired Motions
Over use of paper/distribution - Excess Walking - Excess Motions
Transportation
Layout - wait time to travel
Wait Time
Poor Scheduling - Imbalance in prodn line - Inadequate labor resource
Root cause of waste
-
8/2/2019 Prod Techniques Old
139/582
Root cause of waste
Process
Wrong operations or poor material leading to rework orreject
Poor process control Poor operating specifications
Untrained or de motivated operators
-
8/2/2019 Prod Techniques Old
140/582
DEFINITION OF VALUE
-
8/2/2019 Prod Techniques Old
141/582
DEFINITION OF VALUE
VALUE IS A WORD USED WITHOUTUNDERSTANDING THE MEANING
DIFFERENT DEPTS OF SAME COMPANYHAVE VARIED MEANING
DESIGNER RELATES VALUE WITHRELIABILITY
MFG RELATES WITH COST OF MFG
PURCHASE RELATES WITH COST OF RM
SALES RELATES TO THE PRICE CUSTOMERIS WILLING TO PAY
DEFINITION OF VALUE
-
8/2/2019 Prod Techniques Old
142/582
DEFINITION OF VALUE
VALUE IS THE RELATIONSHIP BETWEEN COST AND QLTY
VALUE = QUALITY/COST
VALUE IS PLACED FOR VARIOUS ATTRIBUTES MORE POPULARLYKNOWN AS FUNCTIONS OF A PRODUCT
TWO TYPES OF FUNCTIONS
-PRIMARYSECONDARY PRIMARY FUNCTIONS ARE THOSE ATTRIBUTES FOR WHICH APRODUCT IS PURCHASED AND MEANT TO BE USED eg THEPRIMARY FUNCTION OF A CAR IS TO SAFELY TRANSPORT PEOPLEBETWEEN TWO POINTS WITH FUEL ECONOMY
SECONDARY FUNCTIONS ARE THOSE ATTRIBUTES WHICH ARENOT PRIMARY FUNCTIONS BUT WHICH PEOPLE WISH TO SEE AS
ATTRIBUTES OR FUNCTIONSS IN A PRODUCT eg IN A CAR WEALSO WISH TO HAVE A/C AND OTHER ACCESSORIES
-
8/2/2019 Prod Techniques Old
143/582
VALUE ENGG/ANALYSIS
-
8/2/2019 Prod Techniques Old
144/582
VALUE ENGG/ANALYSIS
ENGINEERING IS A PROCESS OF ASSESSMENT OF APRODUCT DURING DESIGN PHASE
ANALYSIS IS ASSESSMENT OF A PRODUCT DURING USAGE
OBJECTIVE IS TO ELIMINATE UNREQD FEATURES ANDFUNCTIONS IN PRODUCT DESIGN
MOST ACTIVITIES PERFORMED IN ANALYSIS PHASE VA TEAM ASSIGNS A VALUE TO EACH FUNCTION AND
FINDS COSTS TO DELIVER FUNCTION AND RATIO OFVALUE TO COST IS CALCULATED
RATIO IMPROVED BY REDUCING COST OF ITEM ORINCREASING WORTH
VALUE ENGG/ANALYSIS
-
8/2/2019 Prod Techniques Old
145/582
VALUE ENGG/ANALYSIS
VALUE ANALYSIS IS A MGT TECHNIQUEFOR REDUCING MFG COSTS AND ///LYIMPROVING QLTY AND RELIABILITY OFPRODUCT
VALUE ENGG IS USED TO COVER THEINITIAL DESIGN STAGE
VALUE MEANS DIFFERENT THINGS TODIFFERENT PEOPLE AT DIFFERENT TIME
VALUE OF AN ITEM DETERMINED ON THEBASIS OF VARIOUS ASPECTS:
FOUR WAYS TO INCREASING
-
8/2/2019 Prod Techniques Old
146/582
VALUE OF FUNCTION
DECREASE COST AND MAINTAIN
PERFORMANCE LEVEL eg NANO
INCREASE PERFORMANCE AT SAME COST
eg TOOTHPASTE/AERATED DRINKS
DECREASE COST AND ENHANCE
PERFORMANCE eg PC HARDWARE
INCREASE BOTH COST ANDPERFORMANCE BUT PERFORMANCE
INCREASE > COST INCREASE eg BUFFETS
TYPES OF VALUE
-
8/2/2019 Prod Techniques Old
147/582
TYPES OF VALUE COST VALUE IS SUM OF ALL COSTS INCURRED IN MFG OF PRODUCT eg
MATRL LABOUR TOOLING O/H USE VALUE IS THE COST INCURRED TO MAKE PRODUCT FUNCTIONAL
eg QLTY COSTS INCURRED TO ENSURE A/C COOLS TO REQDTEMPERATURE
ESTEEM VALUE IS THE COST INCLUDED INTO PRODUCT TO ENHANCECUSTOMER APPEAL
Eg IN SOME CASES THE MOTOR CAR ESTEEM VALUE > USE VALUE INTERMS OF FUEL CONSUMPTION LIKE IN THE CASE OF A MERCEDESBENZ WHICH GIVES ONLY 6 KM/LTR AGAINST THE AVERAGE 15-18KM/LTR IN OTHER BRANDED CARS
EXCHANGE VALUE IS THE VALUE OF PROPERTIES WHICH ENABLESAN ITEM TO BE EXCHANGED FOR SOMETHING ELSE .EXCHANGEVALUE IS GENERALLY RESALE VALUE. Eg REAL ESTATE EXCHANGEVALUE IS INFLATED BY 20% EVERY YEAR
PLACE VALUE IS VALUE OF PROPERTY/EQUIPMENT WHICH VARIES INPRICE WRT LOCATION eg IN MUMBAI REAL ESTATE IS MOREEXPENSIVE IN WESTERN SUBURBS THAN IN EAST
TIME VALUE IS PROPERTY OF PRODUCT/SERVICE RENDERED AT THERIGHT TIME eg THE TIMING OF AN EMERGENCY OPERATION ISCRITICAL FOR SURVIVAL OF THE PATIENT
VALUE ENGG/ANALYSIS
-
8/2/2019 Prod Techniques Old
148/582
VALUE ENGG/ANALYSIS
ECONOMIC WORTH = COST VALUE + EXCHANGEVALUE + USE VALUE + ESTEEM VALUE + PLACEVALUE + TIME VALUE
REAL WORTH = ECONOMIC WORTH/COST VALUE
REAL WORTH = WORTH/LIFE CYCLE COST
FOCUS OF VE TO INCREASE REAL VALUE OFPRODUCT PROCESS OR SERVICE
VE/VA GENERALLY RESULTS IN COST
REDUCTION
QUESTIONS IN VALUE
-
8/2/2019 Prod Techniques Old
149/582
ANALYSIS
CAN WE DO WITHOUT IT
DOES IT DO MORE THAN REQD
DOES IT COST MORE THAN IT IS WORTH
CAN SOMETHING ELSE SUBSTITUTE IT CAN TWO PARTS BE COMBINED OR CAN ONE
COMPONENT BE MADE INTO TWO
CAN IT BE MADE IN A LESS COSTLY METHODWITH LESS COSTLY MATRL
CAN IT BE MADE CHEAPER BETTER OR FASTER
WHAT NEW PROCESSES CAN WE USE
QUESTIONS IN VALUE
-
8/2/2019 Prod Techniques Old
150/582
ANALYSIS
CAN AN ALTERNATIVE MATRL BE USED
CAN ANY DIMENSIONS BR REDUCED TOUSE LESS MATRL
CAN AMOUNT OF WASTE BE REDUCED CAN PARTS BE STANDARDISED
CAN TWO PARTS BE COMBINED
IS BUYING CHEAPER THAN MAKING
WHAT IS THE COST OF ADHERING TOSPECS
WHAT NEW PROCESSES CAN BE USED
WAYS TO INCREASE VALUE
-
8/2/2019 Prod Techniques Old
151/582
BY VE
REDUCE FUNCTIONS WITH CUTCORNERS EXERCISE
KEEP FUNCTIONS UNCHANGED BUTREDUCE COSTS
INCREASE FUNCTIONS BUT RETAINCOSTS
INCREASE FUNCTIONS MORE THANCOST INCREASE
USES OF VALUE ENGINEERING
-
8/2/2019 Prod Techniques Old
152/582
USES OF VALUE ENGINEERING
COST PREVENTION AND ELIMINATIONTECHNIQUE TO REDUCE COST OF PRODUCT
ENABLES BETTER UNDERSTANDING OF EMPLJOBS
BALANCES COST AND PERFORMNCE
PREVENTS OVER DESIGN OF COMPONENTS
MOTIVATES EMPL TO GIVE CREATIVE IDEAS
INCREASES PROFITS AND DEFLATES COSTS
HELPS SATISFY CUSTOMERS WITH PRODUCTS
-
8/2/2019 Prod Techniques Old
153/582
WHEN TO APPLY VA
-
8/2/2019 Prod Techniques Old
154/582
WHEN TO APPLY VA
PRODUCTS ARE LOSING THEIR MKT
SHARE AND THERE IS DECLINE IN SALES
PRODUCTS ARE PRICED HIGHER THAN
COMPETITION IN A PRICE SENSITIVE MKTOR PRODUCT COST IS > SALES PRICE OF
COMPETITION
NEW DESIGNS TO BE UNDERTAKEN RISING MFG COSTS
REASONS FOR UNNECCESARY
-
8/2/2019 Prod Techniques Old
155/582
COSTS
LACK OF RELEVANT INFO LEADS TO
WRONG DECISIONS WHICH
INCREASE COSTS
WRONG BELIEFS FROM ACCEPTING
OPINIONS
LACK OF IDEAS
DIFFERENCE BETWEEN VE
AND OTHER COST REDUCTION
-
8/2/2019 Prod Techniques Old
156/582
AND OTHER COST REDUCTION
TECHNIQUES TRADITIONAL TECHNIQUES ARE POST PRODUCTION ORIENTEDAND CONCENTRATION IS ON THE PART OR ELEMENT INCONTRAST TO VALUE ANALYSIS WHICH IS FUNCTION ORIENTED
OTHER TECHNIQUES TRY TO REDUCE THE COST BY EXISTINGMETHOD WHEREAS VA NEVER CONSIDERS ANY PROCESSMETHOD OR ELEMENT GRANTED AND IT ANALYSES BY
FUNCTION RATHER THAN PART OR ELEMENT COST REDUCTION CAN REDUCE THE COSTS UPTO 10% WHEREAS
VA CAN REDUCE COSTS UPTO 40-50% WITHOUT SACRIFICINGQLTY AND PERFORMANCE
VALUE ANALYSIS QUESTIONS THE VERY EXISTENCE OF PARTSOR PROCESS BY ANALYSIS OF ITS DESIGN SPECIFICATIONS,MATRLS AND PROCESS OF MFG
COST REDUCTION IS COST ORIENTED AND CONCENTRATES ONFINDING THE CHEAPER COST WHEREAS VALUE ANALYSIS ISFUNCTION ORIENTED AND TRY TO PRODUCE THE PRODUCT ATLOWEST COST WITHOUT SACRIFICING QLTY AND PERFORMANCE
STRATEGIC STEPS IN VALUE
ANALYSIS
-
8/2/2019 Prod Techniques Old
157/582
ANALYSIS
DETERMINE FUNCTION AND COST OFEACH ELEMENT IN FINISHED PROD
CONSIDER ALTERNATIVES THAT FULFILFUNCTIONS
SELECT BEST ALTERNATIVE WHICHINCLUDES MATRL,STANDARDISATION OFDIMENSIONS
STRATEGIC CHOICE OF MAKE EXPENSIVE
PRODUCTS OR SUBCONTRACT MODIFY DESIGN TO REDUCE COSTS
VA PROCEDURE
-
8/2/2019 Prod Techniques Old
158/582
VA PROCEDURE
IDENTIFY ITEMS TO BE ANALYSED
DIFFERENTIATE WHETHER ITEM OR PROCESS
IDENTIFY INTERNAL AND EXTERNAL CUSTOMERS
IDENTIFY BASIC FUNCTIONS
IDENTIFY SECONDARY FUNCTIONS WHICH SUPPORT BASIC
TO PRIORITISE DETERMINE VALUE OR IMPERTANCE TOCUSTOMER OF EACH FUNCTION
BREAK ITEM/PROCESS INTO CONSTITUENT COMPONENTSBY USING FLOWCHART
ASSOCIATE COMPONENTS WITH FUNCTIONS
LOOK FOR COMPONENTS WHICH CAN BE MODIFIED ORELIMINATED
OPTIONS IN VA/VE
-
8/2/2019 Prod Techniques Old
159/582
OPTIONS IN VA/VE
MODIFY
INTEGRATE
SUBSTITUTE SIMPLIFY
EXAMPLES OF VALUE
ANALYSIS
-
8/2/2019 Prod Techniques Old
160/582
ANALYSIS
MODIFY-MOTOR CAR ENGINES HAVE BEENMODIFIED TO RUN ON CNG
INTEGRATE-AIR CONDITIONER AND HEAQTERINTEGRATED INTO ONE UNIT
SUBSTITUTE-INHOUSE WIRING HAS BEENCHANGED FROM COPPER TO ALUMINIUM ORCOKE BOTTLES CHANGED FROM GLASS TOPLASTIC
SIMPLIFY-APPLICATION SOFTWARE SIMPLIFIED
BY BEING MADE MODULAR.EARLIER ALLMODULES WERE BUNDLED OR COMPLICATEDEQUIPMENT MADE MODULAR WHICH SIMPLIFIESMAINTENANCE
WHEN TO USE VA/VE
-
8/2/2019 Prod Techniques Old
161/582
WHEN TO USE VA/VE
AIM IS TO EVALUATE REAL VALUE
OF PRODUCT/PROCESS
FOCUS IS ON SAVING COSTS AIM IS ON INCREASING VALUE OF
PROCESS/PRODUCT
BENEFITS OF VALUE
ENGINEERING
-
8/2/2019 Prod Techniques Old
162/582
ENGINEERING
COST REDUCTION/ELIMINATION
TECHNIQUE
BALANCES COSTS AND PERFORMANCE
PREVENTS OVER DESIGN OF PRODUCT
(CUSTOMER FUNCTION DEPLOYMENT)
INCREASES PROFITS AND REDUCES COSTS
INCREASES CUSTOMER SATISFACTION
-
8/2/2019 Prod Techniques Old
163/582
Introduction
D fi iti W k St d i th t ti
-
8/2/2019 Prod Techniques Old
164/582
Definition: Work Study is the systematic
examination of the methods of carrying onactivities so as to improve the effective use ofresources and to set up standards ofperformance for the activities being carried out.
Work Studysucceeds because it issystematic both in the investigation of theproblem being considered and in thedevelopment of its solution.
164
Continue.
-
8/2/2019 Prod Techniques Old
165/582
If work study results in cutting down the timeof performing a certain activity by 20 per cent
Merely as a result of rearranging the sequenceor simplifying the method of operation
Without additional expenditure
Then productivity will go up by acorresponding value, that is by 20 per cent.
165
WORK STUDY
-
8/2/2019 Prod Techniques Old
166/582
OPERATIONS MGT IS ABOUT ADDING VALUE IN ACTIVITIES
AND PRODUCING RESULTS AS DESIRED BY THE
CUSTOMER.
ACTIVITIES HAVE INPUTS WHICH ARE IN VARIOUS FORMS.
THEY ALSO HAVE BUSINESS RULES AND METHODS BYWHICH THEY HAVE TO BE PERFORMED.THEY ALSO
PRODUCE RESULTS WHICH SHOULD CONFORM TO
CUSTOMERS REQUIREMENT
WORK STUDY DEFINED AS SCIENCE OF EXAMINATION OF
HUMAN WORK IN ALL CONTENTS WHICH LEADS TOSYSTEMATIC INVESTIGATION OF ALL FACTORS WHICH
AFFECT EFFICIENCY
GENERIC FORM OF TECHNIQUES WHICH ARE USED TO
EXAMINE HUMAN WORK IN ALL ASPECTS AND WHICH
SYSTEMATICALLY LEAD TO THE INVESTIGATION OF ALL
WORK STUDY
-
8/2/2019 Prod Techniques Old
167/582
WORK STUDY INVESTIGATES AND
CRITICALLY EXAMINES WORK DONE AND
FINDS THE BEST AND MOST EFFECTIVE
WAY OF USING RESOURCES TO AHIEVEBEST QUALITY RESULTS IN THE LEAST
TIME AND COST
CRUX OF WORK STUDY IS TO OPTIMIZE
USAGE OF INPUT RESOURCES AND TO
MAXIMIZE PRODUCTIVITY
WORK STUDY HELPS IN DECIDING
RESOURCE RE UIREMENTS AT THE
Operational Time
Definition: The time taken by a worker or a machine to carry outan operation or to produce a given quantity of a certain product .
-
8/2/2019 Prod Techniques Old
168/582
p p g q y p
Basic work content of product and/oroperation
Work content added by poor product designor material utilization
Work content added by inefficient methodsof manufacturing or operation.
Ineffective time resulting from humanresources contribution
168
Techniques of work study
-
8/2/2019 Prod Techniques Old
169/582
Method study :The systematic recording and criticalexamination of ways of doing things in order to make
improvements.
Work measurement :The application of techniques
designed to establish the time for a qualified worker
to carry out a task at a defined rate of working.
169
M h d S d
Work Study Relationship
-
8/2/2019 Prod Techniques Old
170/582
Method Study
To simplify the job & develop moreeconomical methods of doing it
Work Measurement
To determine how long it should taketo carry out
Higher Productivity
Work
study
170
ADVANTAGES OF WORK
STUDY
-
8/2/2019 Prod Techniques Old
171/582
STUDY IMPROVED PRODUCTION FLOW
HIGHER PRODUCTIVE EFFICIENCY
REDUCE MANUFACTURING COSTS
FAST AND ACCURATE DELIVERIES
BETTER EMPLOYEE RELATIONS
BETTER SERVICE TO CUSTOMERS
JOB SATISFACTION TO EMPLOYEES
BETTER WORKING CONDITIONS
HIGHER INCENTIVE BASED WAGES BASED ON HIGHERPRODUCTIVITY
ADVANTAGES OF WORK
STUDY
-
8/2/2019 Prod Techniques Old
172/582
STUDY PRODUCTION SMOOTHING DUE TO LINE
BALANCING
REMOVAL OF BOTTLENECKS LEADING TO
REDUCED INVENTORY HIGHER PRODUCTIVE EFFICIENCY
REDUCED MFG COST
ACCURATE DELIVERY DATES TO CUSTOMER AS
PER COMMITMENT BETTER SERVICE TO CUSTOMER
How to apply Work Study
-
8/2/2019 Prod Techniques Old
173/582
Method Study Work Measurement
Analyzing the specific
Methods used in
carrying out an operation
And simplifying job thruEconomical ways
-Determine the time
required to perform
the operation and its
elements-Comprises of Motion and
Time study
-
8/2/2019 Prod Techniques Old
174/582
METHOD STUDY
METHOD STUDY
-
8/2/2019 Prod Techniques Old
175/582
DEFINED AS SYSTEMATIC AND SCIENTIFIC
ANALYSIS OF PROPOSED METHOD OF DOING A
JOB IN ORDER TO DEVELOP A SIMPLE EFFICIENT
EFFECTIVE AND LESS FATIGUING PROCEDURE OF
DOING THE SAME JOB AT A LESSER COST BY
OPTIMIZING INPUT RESOURCES
IT USES DIFFERENT PROCESS MAPPING
TECHNIQUES TO IDENTIFY AND ERADICATE THE
NON VALUE ACTIVITIES
OBJECTIVE OF METHOD STUDY IS TO IMPROVE
PROCESS OF VALUE ADDITION .THIS IS DONE BY
MAXIMIZING VALUE ADDED OPERATIONS AND
MINIMIZING OR ELIMINATING DELAY STORAGE
METHOD STUDY
-
8/2/2019 Prod Techniques Old
176/582
METHOD STUDY INVOLVES THE STUDY
OF HOW ACTIVITIES ARE PERFORMED
AND ATTEMPTS TO REMOVE NON VALUE
ADDED ACTIVITIES AS WELL AS IMPROVETHE PROCEDURE AND WAY IN WHICH THE
ACTIVITY IS PERFORMED SO THAT THE
TIMING TO EXECUTE MAY BE REDUCED
AND THE ACTIVITY IS PERFORMED INLESSER TIME WITH LESSER EFFORT. Eg
DENNIS LILEE BOWLING ACTION AFTER
BACK OPERATION
METHOD STUDY
-
8/2/2019 Prod Techniques Old
177/582
METHOD STUDY IS SYSTEMATIC RECORDING AND
CRITICAL EXAMINATION OF WAYS OF DOING THINGS
OBJECTIVE OF METHOD STUDY IS TO IMPROVE ACTIVITY
ACTIVITY CAN BE IMPROVED THROUGH PROCESS
REENGINEERING BY ELIMINATING NVA ACTIVITIES OR BYREDUCING EXISTING TIMINGS OF ACTIVITIES THROUGH
BETTER WAYS
NEED TO DRAW PROCESS CHARTS AND ACTIVITY CHARTS
WITH
MOVEMENT,STORAGE,DELAY,INSPECTION,ACTIVITY,DECISION ALONG WITH TIMINGS
OBJECTIVES OF METHOD
STUDY
-
8/2/2019 Prod Techniques Old
178/582
STUDY IMPROVED WORK PROCESS LEADING TO ENHANCED
PRODUCTIVITY
STANDARDIZED PROCEDURE LEADIND TO CONSISTENCY
IN ACTIVITY EXECUTION;HENCE GENERALLY
CONSISTENCY IN PERFORMANCE BETTER WORKPLACE LAYOUT
SAFER WORKING CONDITIONS
IMPROVED PRODUCT QUALITY DUE TO HIGHER QUALITY
ASSURANCE
IMPROVED WORK ERGONOMICS LEADING TO HIGHERPRODUCTIVITY
Objective of Method Study
-
8/2/2019 Prod Techniques Old
179/582
Improvement of processes and procedures Improvement in the design of plant and
equipment
Improvement of layout
Improvement in the use of men, materials andmachines
Economy in human effort and reduction ofunnecessary fatigue
Improvement in safety standards Development of better working environment.
179
HUMAN OPERATIONS
ANALYSIS
-
8/2/2019 Prod Techniques Old
180/582
ANALYSIS
DETAILED STUDY OF DIFFERENT
OPERATIONS INVOLVED IN DOING
WORK WITH THE OBJECTIVE TO
FIND DEFECTS IN EXISTING
METHODS AND TO DEVELP
IMPROVED PROCEDURE
AIMS AT OPTIMIZING UTILIZATION
OF RESOURCES AND ESPECIALLY
THOSE PARTS OF HUMAN BODY
METHOD STUDY
PROCEDURE
-
8/2/2019 Prod Techniques Old
181/582
PROCEDURE SELECT WORK TO BE STUDIED AND DEFINE
OBJECTIVES TO BE ACHIEVED
OBJECTIVE MAY BE TO REDUCE COSTS
BOTTLENECKS OR TO REDUCE FATIGUE
INCURRED BY WORKERS AND TO INCREASE
THEIR EFFICIENCY eg CONVEYOR BELT BY FORD
RECORD RELEVANT INFORMATION PERTAINING
TO EXISTING METHOD IN DETAIL AND
DOCUMENT ACTIVITIES BY WAY OF MATERIAL
FLOW CHARTS , PROCESS FLOW CHARTS ,
ACTIVITY FLOW CHARTS,INFORMATION FLOW
CHARTS
METHOD STUDY
PROCEDURE
-
8/2/2019 Prod Techniques Old
182/582
PROCEDURE INSTAL THE BEST DEVELOPED METHOD
MAINTAIN AND CONTINUOUSLY REVIEW AND
IMPROVE THE NEW METHOD (ADLI)
Method Study Procedure
-
8/2/2019 Prod Techniques Old
183/582
1. DEFINE2. RECORD
3. EXAMINE
4. DEVELOP
5. DEFINE NEW METHOD
6. INSTALL7. MAINTAIN
183
ADVANTAGES OF METHOD
STUDY
-
8/2/2019 Prod Techniques Old
184/582
STUDY IMPROVED WORK PROCESS LEADING TO
HIGHER PRODUCTIVITY
STANDARDIZED PROCEDURE LEADING TO
CONSISTENCY IN PERFORMANCE
BETTER WORK PLACE LAYOUT AND
POSITIONING AND ARRANGING FACILITIES AND
MACHINES
NEAT AND CLEAN ENVIRONMENT
REDUCED FATIGUE IN WORKERS
IMPROVES PRODUCT QUALITY
ENSURES SAFETY AND MINIMIZES HEALTH
HAZARDS AT WORKPLACE
-
8/2/2019 Prod Techniques Old
185/582
TIME STUDY
TIME STUDY
-
8/2/2019 Prod Techniques Old
186/582
TIME STUDY CAN BE DEFINED AS THE
APPLICATION OF SCIENTIFIC TECHNIQUES
TO MEASURE WORK CONTENT OF
ACTIVITY IN A NORMAL DEFINEDSITUATION AND ESTABLISH TIME
REQUIRED TO EXECUTE JOB BY VARIOUS
SKILLS AT A DEFINED LEVEL OF
PERFORMANE. FALLACY LIES INDEFINING STD TIME FOR ALL LEVELS OF
CAPABILITY AND EXPERIENCE
TIME STUDY
-
8/2/2019 Prod Techniques Old
187/582
ALSO CALLED WORK MEASUREMENT
IT DETERMINES THE TIME TAKEN TO DO A JOB
DECIDES MANPOWER REQUIRED (QUANTITY VS QUALITY)
DECIDES EQUIPMENT REQUIRED
PROVIDES VALUABLE INFO FOR PRODN PLANNING INTERMS OF TIME ESTIMATION FOR EACH STEP IN THE
ROUTING
INDICATES REALISTIC LABOR BUDGETING
PROVIDES BASE FOR STD COSTING (CHECK CHANGING
PARAMETERS)
RESULTS IN EFFECTIVE LABOUR CONTROL
TIME STUDY
-
8/2/2019 Prod Techniques Old
188/582
CONSISTS OF A WIDE VARIETY OF
PROCEDURES FOR DETERMINING
THE AMOUNT OF TIME REQD UNDER
CERTAIN STD CONDITIONS OF
MEASUREMENT
A TERM WORK MEASUREMENT IS
ALSO USED FOR TIME STUDIES
Objective of Work Measurement
-
8/2/2019 Prod Techniques Old
189/582
To find ineffective time in a process
To set standard for output level
To evaluate worker's performance
To plan work force needs.
To determine available capacity
To compare work methods To facilitate operations scheduling
To establish wage incentive schemes 189
USE OF STANDARD TIME
-
8/2/2019 Prod Techniques Old
190/582
STANDARD TIME IS USED AS A NUMERICAL COEFFICIENT
FOR CONVERTING A QUANTITATIVE STATEMENT OF THE
WORKLOAD TO A QUANTITATIVE STATEMENT OF THE
REQUIRED RESOURCES
PLANNED COSTS ARE DERIVED FROM STANDARD TIMESBECAUSE BUDGETS ARE DERIVED FROM THE ACTIVITIES
PERFORMED IN STANDARD TIME WHICH REQUIRE MONEY
MATERIAL MEN etc.
STANDARD TIME IS USED TO DETERMINE LABOR AND
EQUIPMENT REQUIREMENTS ESPECIALLY OUTSOURCED
EQUIPMENT .IN CERTAIN JOBS STANDARD TIME IS OF
CRITICAL IMPORTANCE BECAUSE OF RESTRICTIONS IN
DOWN TIME eg AN OIL AND GAS PRODUCTION WELL CAN
BE DOWN FOR ONLY 120 HOURS IN A YEAR AND ALSO
THEY NEED TO OUTPUT A MINIMUM FLOW OF GAS FAILING
USE OF STANDARD TIME
-
8/2/2019 Prod Techniques Old
191/582
TO ASSIST IN DEVELOPING EFFECTIVE METHODS
TO DETERMINE THE NUMBER OF EQUIPMENT A PERSON
CAN MANAGE AT A TIME eg WEAVERS 8/16 LOOMS.
TIME VALUES SHOULD BE SET IN SUCH A WAY TAKING
INTO ACCOUNT AN AVERAGE WORKER WITH A CERTAINMINIMUM LEVEL OF SKILLS.TODAY THE STD TIMES ARE
ERRONEOUSLY CALCULATED ON EITHER VERY HIGH SIDE
LEADING TO LOW PRODUCTIVITY FIGURES OR LOW SIDE
LEADING TO MISLEADING HIGH PRODUCTIVITY FIGURES.
Eg STD TIME 20 MIN ACTUAL TIME 10 MIN PRODUCTIVITY
200%
DISTRIBUTION OF WORK AMONG CREW
COMPARE METHODS
TO SET SCHEDULES
USE OF STANDARD TIME
-
8/2/2019 Prod Techniques Old
192/582
TO SET SUPERVISORY OBJECTIVES
TO ASSIST IN COMPARING PLANS
WITH ACHIEVEMENT WITH RESPECT
TO WORKLOAD AND RESOURCE
USAGE
FOR TOTAL PRODUCTIVITY
MEASUREMENT
ALLOWANCES
-
8/2/2019 Prod Techniques Old
193/582
ALLOWANCES ARE ADDED TO NORMAL TIME TO ARRIVE
AT STANDARD TIME
TYPES OF ALLOWANCES INCLUDE PROCESS ALLOWANCE
AND PERSONAL ALLOWANCE
PROCESS ALLOWANCE ARE ALLOCATED TO COVERENFORCED IDLE TIME OR SPECIAL CASES WHICH ARE NOT
PART OF WORK CYCLE BUT ARE ESSENTIAL FOR
PERFORMING WORK eg BEAM CHANGE IN WEAVING OR
MACHINE SET UP TIME OR INTERFERENCE ALLOWANCE
WHEN WORKER HANDLES MORE THAN ONE MACHINE eg
WEAVER HANDLES 8/16 MACHINES
PERSONAL ALLOWANCES INCLUDE TIME ALLOWED FOR
FATIGUE , CALLS OF NATURE , DIFFICULT WORKING
CONDITIONS etc. VARIES FROM 15% TO 30% DEPENDING ON
SITUATIONS
-
8/2/2019 Prod Techniques Old
194/582
-
8/2/2019 Prod Techniques Old
195/582
ADVANTAGES OF TIME
STUDY
-
8/2/2019 Prod Techniques Old
196/582
STUDY DECIDES MANPOWER SKILLS (AND SHOULD
ALSO DECIDE CAPABILITIES) REQUIRED TO DO
THE JOB
DECIDE EQUIPMENT REQUIRED
PROVIDES INFORMATION FOR EFFECTIVE
PRODUCTION PLANNING AND MAINTENANCE
PROCEDURES
AIDS AT CALCULATING REALISTIC DE3LIVERY
DATES AND DOES REALISTIC LABOR BUDGETING
PROVIDES BASIS FOR STANDARD COSTING
FORMS THE BASE FOR INCENTIVE SYSTEMS
-
8/2/2019 Prod Techniques Old
197/582
MOTION STUDY
-
8/2/2019 Prod Techniques Old
198/582
-
8/2/2019 Prod Techniques Old
199/582
ANALYSIS OF MOTION
-
8/2/2019 Prod Techniques Old
200/582
ANALYSIS OF AN OPERATION FOR ATTAINMENT
OF END OBJECTIVE IS CARRIED OUT IN TERMS OF
INDIVIDUAL MOTIONS OF A PERSON AS WELL AS
THE WORK PLACE LAYOUT AND ERGONOMICS
FOR ATTAINMENT OF HIGHEST LEVEL OFPRODUCTIVITY
PURPOSE OF MOTION ANALYSIS IS TO
ELIMINATE UNNECESSARY MOTIONS TO REDUCE
FATIGUE AND EFFORT AND MAKE HUMANEFFORT MORE PRODUCTIVE eg WEIGHT LIFTING
STEPS FOR MOTION STUDY
-
8/2/2019 Prod Techniques Old
201/582
CHART VARIOUS MOTIONS PERFORMED BY OPERATORS
IDENTIFY LABORIOUS AND IDLE MOTIONS.ALSO IDENTIFY
COMPLEX MOTIONS WHICH ARE DIFFICULT TO
PERFORM.OCCASIONALLY PERFORMER EXAGGERATES
COMPLEXITY OF MOTION eg SIMPLE CATCH IS MADE TO
LOOK DIFFICULT
IDENTIFY PRODUCTIVE ,NON VALUE ADD AND IDLE
MOTIONS
ELIMINATE NON PRODUCTIVE AND UNREQUIRED MOTIONS
OR SIMPLIFY COMPLEX MOTIONS eg WEIGHT LIFTING REDESIGN EXISTING OPERATING PROCEDURE BY
IMPROVING THE MOTIONS INVOLVED IN WORK TAKING
INTO ACCOUNT THE ABOVE OBSERVATIONS
IMPART REQUIRED INSTRUCTIONS AND TRAINING TO
OPERATORS
-
8/2/2019 Prod Techniques Old
202/582
-
8/2/2019 Prod Techniques Old
203/582
PRIMARY OBJECTIVES OF
MOTION STUDY
-
8/2/2019 Prod Techniques Old
204/582
MAXIMIZE FINANCIAL ADVANTAGE THRU
-LESS DIRECT LABOR EFFORT AND TIME
-FEWER STEPS IN PROCESS
-MORE PRODUCTIVE LABOR
-LESS EQUIPMENT USAGE
-LESS SPACE USAGE
-LESS SCRAP GENERATED
-LOWER OVERALL COSTS
-LESSER IDLE TIME AND LESSER FATIGUE
-FEWER HAZARDS IN OPERATIONS
-
-
8/2/2019 Prod Techniques Old
205/582
-
8/2/2019 Prod Techniques Old
206/582
Facility Design
-
8/2/2019 Prod Techniques Old
207/582
Facility layout: Arrangement of machines, storage areas,
and/or work areas usually within the confines of a
physical structure, such as a retail store, an office, a
warehouse, or a manufacturing facility.
Factors that influence layout
Volume, weight of items to be produced.
Nature of the service to be provided.
Cost of the building to house the operation.
The product mix that must have a facility.
The fragility of the product or component.
What Is Layout Planning
-
8/2/2019 Prod Techniques Old
208/582
Layout planning is determining the best physical arrangement of
resources within a facility
Facility resource arrangement can significantly affect productivity
Two broad categories of operations:
Intermittent processing systemslow volume of many different
products
Continuous processing systemshigh volume of a few
standardized products
-
8/2/2019 Prod Techniques Old
209/582
INTRODUCTION
-
8/2/2019 Prod Techniques Old
210/582
To make a decision about layout planning, 4 different
questions must have an answer:
Which centers do we have to consider?
How much space and capacity is required for each center?
If there is not enough space, productivity may be reduced.
Too much space is expensive and may also reduce
productivity.
How must the space be configured at each center?
Space quantity, shape and the elements of the work center arerelated to each other.
Where should each center be located at within the facility?
The allocation of the different centers may affect productivity.
INTRODUCTION
-
8/2/2019 Prod Techniques Old
211/582
The plant layout process starts at an aggregate
level, taking into account the different
departments. As soon as we get into the details,
the different issues arise, and the originalconfiguration may be changed through a feedback
process.
Most (if not all of them) layouts are designed
properly for the initial conditions of the business,although as long as the company grows and has to
be adapted to internal and external changes, a re-
layout is necessary.
INTRODUCTION
-
8/2/2019 Prod Techniques Old
212/582
The reasons for a re-layout are based on 3 types of
changes:
Changes in production volumes. Changes in processes and technology.
Changes in the product.
The frequency of the re-layout will depend on the
requirements of the process.
-
8/2/2019 Prod Techniques Old
213/582
A Good Layout ...
-
8/2/2019 Prod Techniques Old
214/582
Reduces bottlenecks in moving people or material.
Minimizes materials-handling costs and material inprocess
Reduces hazards to personnel.
Utilizes labor efficiently.
Increases morale.
Utilizes available space effectively and efficiently.
Provides flexibility.
Provides ease of supervision.
Facilitates coordination and face-to-face communicationwhere appropriate.
Implements safety measures
Lay Out
-
8/2/2019 Prod Techniques Old
215/582
Types of Plant Layout
Product Layout
Process Layout
Fixed Position Layout
Cellular Layout
Layout for Services
Objectives of Plant Layout
-
8/2/2019 Prod Techniques Old
216/582
These main objectives are reached through the attainment of the followingfacts:
Congestion reduction.
Elimination of unnecessary occupied areas.
Reduction of administrative and indirect work.
Improvement on control and supervision.
Better adjustment to changing conditions.
Better utilization of the workforce, equipment and services.
Reduction of material handling activities and stock in process.
Reduction on parts and quality risks.
Reduction on health risks and increase on workers safety. Moral and workers satisfaction increase.
Reduction on delays and manufacturing time, as well as increase in productioncapacity.
All these factors will not be reached simultaneosly, so the best solution willbe a balance among them.
Factors affecting Plant Layout The final solution for a Plant Layout has to take into account a
balance among the characteristics and considerations of all factorsaffecting plant layout, in order to get the maximum advantages.
-
8/2/2019 Prod Techniques Old
217/582
affecting plant layout, in order to get the maximum advantages.
The factors affecting plant layout can be grouped into 8 categories:
Materials
Machinery
Labor
Material Handling
Waiting Time
Auxiliary Services
The building
Future Changes
Factors affecting Plant Layout
-
8/2/2019 Prod Techniques Old
218/582
The factors affecting plant layout can be grouped into 8categories:
Materials
The layout of the productive equipment will depend on the
characteristics of the product to be managed at the facility, as well as
the different parts and materials to work on.
Main factors to be considered: size, shape, volume, weight, and the
physical-chemical characteristics, since they influence the
manufacturing methods and storage and material handling processes.
The sequence and order of the operations will affect plant layout as
well, taking into account the variety and quantity to produce.
Factors affecting Plant Layout
-
8/2/2019 Prod Techniques Old
219/582
The factors affecting plant layout can be grouped into 8categories:
Machinery
Having information about the processes, machinery, tools and
necessary equipment, as well as their use and requirements isessential to design a correct layout.
The methods and time studies to improve the processes are closely
linked to the plant layout.
Regarding machinery, we have to consider the type, total available
for each type, as well as type and quantity of tools and equipment. Its essential as well to know about space required, shape, height,
weight, quantity and type of workers required, risks for the personnel,
requirements of auxiliary services, etc.
Factors affecting Plant Layout
-
8/2/2019 Prod Techniques Old
220/582
The factors affecting plant layout can be grouped into 8categories:
Labor
Labor has to be organized in the production process (direct labor,
supervision and auxiliary services). Environment considerations: employees safety, light conditions,
ventilation, temperature, noise, etc.
Process considerations: personnel qualifications, flexibility, numberof workers required at a given time as well as the type of work to beperformed by them.
Material Handling
Material handling does not add value to the product; its just waste.
Objective: Minimize material handling as well as combining withother operations when possible, eliminating unnecessary and costlymovements.
Factors affecting Plant Layout
The factors affecting plant layout can be grouped into 8
-
8/2/2019 Prod Techniques Old
221/582
g p y g p
categories:
Waiting time - Stock
Objective: Continuous Material Flow through the facility, avoiding
the cost of waiting time and demurrages that happen when the flow
stops. On the other hand, the material waiting to flow through the facility
not always represents a cost to avoid. As stock sometimes provides
safety to protect production, improving customer service, allowing
more economic batches, etc.
Its necessary then to consider space for the required stock at the facilitywhen designing the layout.