prince2 v5
TRANSCRIPT
![Page 1: PRINCE2 V5](https://reader036.vdocuments.mx/reader036/viewer/2022082721/58713bb11a28abf0568b6efb/html5/thumbnails/1.jpg)
Illustrating Project Methodology based on PRINCE2
Ver. 5 - Updated on Dec. 1, 2016
Yuko Soma
(Remarks) This contents were customized based on the following person’s personal perspective and project experiences; however, she tried to follow official textbook for PRINCE2 Practitioner Exam as much as she can so that these help people to use for taking the exam purpose
![Page 2: PRINCE2 V5](https://reader036.vdocuments.mx/reader036/viewer/2022082721/58713bb11a28abf0568b6efb/html5/thumbnails/2.jpg)
1. Basic Structure
Organization Theme
6 Tolerance / Variables
7 Themes (+1 Theme)
7 Principles
7 Processes
Change Theme
Quality Theme
Risk Theme
Business Case Theme Progress Theme
Plan Theme
Quality Benefits Risk Cost Time
Tailoring Theme
Continued BusinessJustification
Learn fromExperience
Defied Roles and Responsibilities
Manage by Stages
Manage byException
Focus onProduct Tailoring
Scope
(SU) Starting up a Project, (DP) Directing a Project, (IP) Initiating a Project, (CS) Controlling a Stage, (MP) Managing Product Delivery, (SB) Managing a Stage Boundary, (CP) Closing a Project
S U D P I P S B M PC S C P
![Page 3: PRINCE2 V5](https://reader036.vdocuments.mx/reader036/viewer/2022082721/58713bb11a28abf0568b6efb/html5/thumbnails/3.jpg)
M P
2. TimelineDe
liver
ing
Man
agem
ent
Dire
ction
Corp
AuthorizePrematureClosure
ExecuteWork Package
CompleteWork Package
Initiation Post-ProjectFinal StageDelivery Stages
Escalate to Corp if exceed tolerance
Pre-Project
Authorize a Project
Project Brief
Project Initiation Document
(PID)
Project ProductDescription (PPD)
Check Point Report
Daily Log
Highlight Report
Draft Closure Notification
Report to Project Board
Follow-on Action Recommendations
Risk Register
Issue Report
Quality Register
(SU) Starting up a Project, (DP) Directing a Project, (IP) Initiating a Project, (CS) Controlling a Stage, (MP) Managing Product Delivery, (SB) Managing a Stage Boundary, (CP) Closing a Project
C P
AuthorizeInitiationOutline
Business Case
I P
C SFinal Stage
C S
Management Product
Product Status
Account
Work Package
ProjectPlan
ExceptionPlan
Communication/Quality/
Configuration/Risk Management Strategy
Accept Work Package
・ ApproveFinalBenefit
Configuration Item Records
AuthorizeWork Package
PM Team Role/Structure
Descriptions
Benefit Review
PlanDetailedBusiness
Case
LessonReport
Additional Work Estimates
Product Breakdown Structure
ProductFlow
Diagram
End StageReport
Lesson Log
Authorize an Exception
TeamPlan
Executive Role
Descriptions
Project Mandate
Project Manager Role
Descriptions
Initiation StagePlan
Exception Report
・ ApproveBenefit
・ ApproveBenefit
S BStage 2-3
S BStage 1-2
End StageReport
Authorize a Stage
・ AssessUpdated Benefit
・ AssessUpdatedBenefit
Project Approach
Project ControlsPD
Issue Register
AuthorizeFinal Stage
Authorize a Stage 2
D P
Stage 2
C SEnd Project
Report
StagePlan
StagePlan
S U
AuthorizeProject Closure
![Page 4: PRINCE2 V5](https://reader036.vdocuments.mx/reader036/viewer/2022082721/58713bb11a28abf0568b6efb/html5/thumbnails/4.jpg)
3. Roles and Responsibilities Corporate/Program Manager0) Appoint only one Executive 1) Set corporate tolerances 2) Produce Project Mandate
Project Board
Customer SupplierSenior User (User)・ Realize post-project benefits・ Specify user requirements then raise RFC if any
Executive (Business)・ Create and verify , responsible for Business Case・ Appoint Project Manager
Project Manager・ Manage the project on a day to day basis・ Appoint the team member・ Create/approve “Exception Plan”, then report this to Project Board・ Assist Executive to create “Outline Business Case”・ Create “Detailed Business Case”, “Daily log”, “Issue Report”, “Project Plan” and other so called “Management Products”
Team Manager・ Admin support for Project Manager to Produce products consistent with “Product Description”・ Manage Team Members・ Issue “Change Request (CRs)”・ Create “Check Point Report”
User Project Assurance (U)
Senior Supplier (Supplier)・ Ensure that products will be delivered as expected in aspect of Timeframe and Cost
Project Managem
ent Team
0) Specify customer’s quality expectations and acceptance criteria 1) Verifying the BC 2) Approve “Exception Plan” then replace “Stage Plan” Escalate the “Exception Report” to higher management as required 3) Approve RFC and off-specification 4) Accountable for project success or failure.
Team MemberTeam Member
Project Assurance0) Monitors performance & Quality of the PROJECT (NOT Product) 1) Help Project Manager to create Risk/Quality Management Strategy
Business Assurance (Business)User Assurance (User) Supplier Assurance (Supplier)・ Ensure that “Team Plan” is viable
Project Support・ Create/Update “CI Records” including master data copies, “Risk Register”, Issue Register”, “Product Status Account” and “Quality Register” with actual to “Work package”
0) Covers User, Business and Supplier’s interests 1) Control Change Requests (CRs), RFC, and off-specifications then make a decision if Project Board delegates2) Approve change budget according to severity rating level 3) Project Manager could take this role
Change Authority
Independent from Any Team
![Page 5: PRINCE2 V5](https://reader036.vdocuments.mx/reader036/viewer/2022082721/58713bb11a28abf0568b6efb/html5/thumbnails/5.jpg)
4. Business Case
Heading Description
1. Executive Summary Install new ERP applications on new public cloud services rather than on-premised inside of the office then restructure Internal IT organization to improve Profit and Loss.
2. Reasons ・ Boise Potato Firm needs to deal with the increasing pressure to cut costs.・ The inadequate controls and outdated technology must be addressed.
3. Business Options(address the business problem to be solved)
Option 1. Do nothing Option 2. Do minimum Option 3. Do something・ The contracting of an external supplier to deliver selected business functions would not provide the required outcome.・ The reduction of staff and the updating of technology used means a re-engineering of existing services will deliver the performance improvements required.
4. Expected Benefits ・ There is an expected saving of 10m over 5 years
・ 20m sales increase from 2nd year after the project endROI : 2000 - (300+500+1000)/1100 = 0.18 for the first year. 2000 - (300+500)/100 = 1992 for the 2nd year.
5. Expected Dis-benefits ・ Internal IT staff morale will be negatively affected:
・ New software may require enhancement after go-live then require to use 2 software for a while to keep data correctly
6. Timescale ・ The expected benefits will be realized over a 5 years period. ・ The expected benefits will be realized as soon as the new software package become BAU at the end of stage 3
7. Cost Project Cost: 1000 USD Maintenance Cost: 100 USD/ year
8. Investment Appraisal
9. Major risks ・ Due to 2 months later market conditions, a suitable external supplier may not be found, which may lead to premature closure of the project (Probability 30% x Impact 1000 USD = 300 USD)・ Due to Internal IT staff’s resistance for the change, the progress of this project may be delayed (Probability 10% x Impact 2000 USD = 200 USD)
Output:New Oracle EBS packageson New clouds service( now in on-premised)
Outcome :Restructuring internal IT Organization and its servicesTo make our business faster
Benefit :Saving of 10m over 5 years and 20m sales increase
![Page 6: PRINCE2 V5](https://reader036.vdocuments.mx/reader036/viewer/2022082721/58713bb11a28abf0568b6efb/html5/thumbnails/6.jpg)
6
5. ReferencesBooks:
Murray, Andy and AXELOS, Managing Successful Projects with PRINCE2, United Kingdom, 2009
Bentley, Colin, PRINCE 2 for Beginners, New York: Routledge, 2015
PRINCE2 Templates:
on Management Plaza Site
http://mplaza.pm/prince2-templates/ and
on APMG International Site
https://www.apmg-businessbooks.com/free-resources?f[0]=field_qualification%3A7
PRINCE2 Case Studies:
Konica Minolta on AXELOS site
https://www.axelos.com/CMSPages/GetFile.aspx?guid=f6d2e4cb-61c4-4184-8c99-5de1bf63411e
PRINCE2 Exam Sample:
For Foundation: https://youtu.be/w-F1WlsFpbY
For Practitioner: http://www.bestpracticelms.com/content/lessons/7/SCORM-P2Passport-931_EP/sharableassets/sm/P2_Practitioner_Sample_Papers.pdf