presentation tyre lh
TRANSCRIPT
Shop Attachment ProgramAssembly Shop
5th December 2016 – 12th December 2016Redza Bin Amin Suggun
Trainee DEP 4th (Group 6)
719186
Manufacturing Process Flow
Press Shop Body Shop Paint Shop Assembly
Quality Control
Pre-DeliveryDistribution
Dealer & Branch
Customers
Logistic CMK Shop
Assembly Layout A2 Line
Trim Line
Final Line
Chassis Line
S/A Radiator
PBS
Door Line
Quality Inspection
Station 12
Station 13
OK
OK
NG
NG
Mission & Vision
• Mission– Develop professional people which are able to
respecting the rules, sustain the machine, creating effective method and securing the materials.
• Vision– Assemble the car with the highest quality, within
the time period and at a lower cost.
Key Elements
Safety• Wear appropriate
PPE• Use the correct
method or technique (ergonomic)
• Kiken Yochi• Use Stop, Call,
Wait
Quality• Follow the rule
and S.O.P. • PokaYoke –
Mistake Proofing• SIIP• Quality
Classification• Defect Control
Rule• BIQ Forms
Cost• Eliminate or
reduce 7 Muda
Delivery• Deliver OK
products for customers.
• Timely delivery• Ensuring the
sequence are correct
Moral• Follow 9
PERODUA ethic codes
• Obey BEN 10
Person In Charge• Supervisor: Abdul Halim Nyan• Team Leader: Mohd Sharil• Team Member: Mohd Hafeez
Station / Process• Process: Tyre LH• Station : STN – 14
Process Involved
• Myvii. Take and install 4 pcs grommet for upper and lower S/Radiator (SS
no 2, 3 & 4)ii. Detach 4 pcs bolt upper support Radiator (SS no 5)iii. Take and install tyre RR LH (SS no 12 & 13)iv. Install 4 pcs Nut to Tyre RR LH (SS no 14)v. Push Complete button (SS no 18)
• Alzai. Take and install 4 pcs grommet for upper and lower S/Radiator (SS
no 2, 3 & 4)ii. Detach 4 pcs bolt upper support Radiator (SS no 5)iii. Take and install tyre RR LH (SS no 12 & 13)iv. Install 4 pcs Nut to Tyre RR LH (SS no 14)v. Push Complete button (SS no 19)
Abnormalities
• Talking during process• Sign of back painMan• Space between nut runner and conveyor is small• Tyre machine is low • Nut runner wire is not covered properlyMachine• The compartment is too far.• Handling of impact.Material• Method of lifting the tyres.• Did not follow sequence for nuts attachmentMethod
Counter Measure
• Frequent supervision from TL is needed.• Enforcement of wearing back supportMan• Increase platform width for the team member to roam / move.• Increase the height and inclination of the machine• Refurbish the wire cover.Machine• Rearrange the compartment.• Provide mobile impact holder.Material• Follow the correct S.O.P, method and sequence. • Frequent supervision is needed. Method
Conclusion
• Knowledge & Experiences gained through this shop attachment:– Process involved in assembly shop– Qualities demand by assembly shop (SQCDM)– How does TM operate during process.– Abnormalities findings (Observation & Experience)– Presenting ideas & Proposal for countermeasure.