11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 1
HUNTER VALLEY MAJOR WORKSPresentation to Capacity Improvement Forum
March 2008
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 2
Completed Projects
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 3
Sandgate Flyover
• $80M Project
• Commissioned on Time in November 2006
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 4
Sandgate Flyover
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 5
Sandgate Flyover
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 6
Sandgate Flyover
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 7
Muswellbrook Loop Extension
• $11.02M Project
• Completed early, in May 2007
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 8
Muswellbrook Loop Extension
Up train on the Muswellbrook Loop Extension
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 9
Muswellbrook Loop Extension
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 10
Gunnedah Loop
• $10M Project
• Completed on time in December 2007
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 11
Gunnedah Loop
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 12
Gunnedah Loop
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 13
Train Control Consolidation
• Amalgamation of Area Controllers, Signaller and Train Controller
• Reduction of staff from 250 to 100
• Closure of signal boxes. Remoting functions to single point at Broadmeadow
• Upgrade of significant signalling systems
• Removal of old unreliable equipment with new equipment
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 14
Ulan CTC
• $13.5M Project
• Stages 1 and 2
commissioned January 2008
• Final stages forecast
for completion April 2008
• Strategy Required by
Q1 2008
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 15
More Completed Projects;
• 80km/hr running on Minimbah and Nundah Banks, a $1.2M Project completed on time in November 2006 (stage 1)
• Togar Loop Extension, a $4.0M project completed on time in May 2007
• Murulla Loop Extension, a $4.8M project completed on time in May2007
• Werris Creek Loop Extension, completed on time as part of the Main Line TCC project in December 2007
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 16
Projects That Have Commenced Construction (incl those at tender);
• Antiene to Grasstree Duplication – target completion of August 2008 – early per strategy
• St Heliers to Muswellbrook Duplication – target completion of March 2009 – early per strategy
• Bi-Directional Signalling Grasstree to St Heliers – target March 2009 –early per strategy
• Mangoola Loop – target June 2008 – early per strategy
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 17
• Wollar Loop – target May 2008 – early per strategy
• Ardglen Loop Extension – Target June 2008 – 3 months late per strategy
• Willow Tree – Target May 2008 – 4 months late per strategy
• Curlewis Loop Extension – target July 2008 – On time per strategy
• Breeza Loop Extension – target July 2008 – On time per strategy
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 18
• Emerald Hill Loop Extension – target August 2008 – early per strategy
• Werris Creek to Gunnedah CTC – Target July 2008 – on time per strategy
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 19
Projects that are currently at detailed design phase, include;
• Bi-Directional Signalling Maitland to Branxton – target March 2009 –early per strategy
• Minimbah Bank 3rd Road – target March 2010 – 2 months late per strategy (may come forward if it can be commissioned under traffic)
• Newdell Junction – target June 2010 – early per strategy
• Bylong Loop – Target Q4 2008 – on time
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 20
HUNTER VALLEY CORRIDOR 2007-2012 CAPACITY STRATEGY – PROGRESS
Prepared by: G WithfordDate: 3 March 2008
2006-2011 STRATEGY
TIMING
2007-2012 STRATEGY
TIMING
Commissioned Cost ($M)
Scheduled Delivery Date Performance; (Note; 'On time' is within 3 months of strategy date given the inflexible nature of the possession
regime, ie 4 x possessions per year)
Newcastle – Muswellbrook
Sandgate Grade Separation By 1st half 2007 Completed $80.00 Completed Nov 2006 Early
80km/hr approaching Minimbah Bank By 1st half 2007 Completed $0.60 Completed Nov 2006 - st 1 Early
Muswellbrook Loop & Junction By 2nd half 2007 Completed $11.02 Completed May 2007 Early
Minimbah Bank 10 min headway By 2nd half 2007 Deleted $0.00 Deleted Deleted
80km/hr approaching Nundah Bank By 1st half 2007 Completed $0.60 Completed Nov 2006 - st 1 Early
Nundah Bank 10 min headway By 2nd half 2007 Deleted $0.00 Deleted Deleted
Antiene to Grasstree Duplication By 2008 By Q1 2009 Target August 2008 Early
Bidirectional Signalling Maitland to Branxton By 2009 By Q3 2009 Target June 2009 Early
Bidirectional Signalling Whittingham to Newdell By 2008 Deleted Deleted Deleted
Minimbah Bank 3rd Road By 2010 By Q4 2009 Target March 2010 On time
Newdell Junction By 2009 By Q1 2010 Target Q1 2010 Early
St Heliers – Muswellbrook Duplication By 2009 By Q3 2009 Target March 2009 Early
Nundah Bank 3rd Road By 2011 Deleted Deleted Deleted
Drayton Junction Upgrade By 2011 By 2011 Target by 2011 Not Commenced
Bidirectional Signalling Newdell to Drayton By 2010 Deleted Deleted Deleted
Bidirectional Signalling Grasstree – St Heliers By 2009 By Q3 2009 Target March 2009 Early
Allandale Resignalling for 8-minute headways New By Q3 2009 Target March 2009 Early
Minimbah – Maitland 3rd Road New By 2012 By 2012 Not Commenced
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 21
Muswellbrook – Ulan
Ulan Line CTC By 2nd half 2007 By Q1 2008 tba Stage 1 and Stage 2, commissioned January 2008, Completion targeted for April 2008
Late
Mangoola (304km) Loop By 2008 By Q4 2008 Target June 2008 Early
Rylestone Rd (381km) Loop By 2008 By Q4 2008 Target November 2008 On Time
Wollar (410km) Loop By 2009 By Q4 2008 Target May 2008 Early
Aerosol Valley (370km) Loop By 2010 By 2010 Target 2010 On Time
Worondi (348km) Loop By 2010 By 2010 Target 2010 On Time
Radio Hut (319km) Loop New By 2012 Target 2012 On Time
Muswellbrook – Bengalla Duplication New By 2012 Target 2012 Not Commenced
Muswellbrook – Narrabri
Togar Loop Extension By 2nd half 2007 Completed $4.00 Completed May 07 On Time
Murulla Loop Extension By 2nd half 2007 Completed $4.80 Completed May 07 On Time
Gunnedah Loop (RIC) By 2nd half 2007 By Q1 2008 $10.00 Completed December 2007 On Time
Werris Creek – Narrabri Power Operation (RIC) By 2nd half 2007 Deleted Deleted Deleted
Ardglen Loop Extension By 2008 By Q2 2008 Target for Jun 2008 On Time
Willow Tree Loop Extension By 2008 By Q1 2008 Target for May 2008 Late
Werris Creek Loop Extension By 2008 Completed tba Completed December 2007 On Time
Werris Creek Bypass New By 2011 Target 2011 Not Commenced
Quirindi Loop Extension By 2009 Deleted Deleted Deleted
Ardglen – Kankool Duplication By 2009 Deleted Deleted Deleted
Parkville Loop Extension By 2009 By 2011 Target 2011 Not Commenced
Curlewis Loop Extension (RIC) By 2009 By Q3 2008 Target July 2008 On time
Werris Creek to Gunnedah CTC (RIC) By 2009 By Q3 2008 Target July 2008 On time
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 22
Muswellbrook – Narrabri - continued
Gunnedah – Narrabri CTC (RIC) By 2010 By 2010 Target March 2009 - tbc by RIC Early
Koolbury Passing Loop By 2010 Deleted Deleted Deleted
Murrurundi Loop Extension By 2010 By 2011 Target 2011 Not Commenced
Burilda Loop Extension (422.360km) By 2010 By 2012 Target 2012 Not Commenced
Emerald Hill Loop Extension (RIC) By 2010 By 2010 Target August 2008 Early
Boggabri Loop Extension (RIC) New By 2010 Target Novemeber 2008 - tbc by RIC Early
Breeza Loop Extension (RIC) (433.900km) New By Q3 2008 Target July 2008 On time
Quipolly Passing Loop (402.014km) New By 2011 Target 2011 On Time
Braefield Passing Loop (386.010km) New By 2010 Target 2010 Not Commenced
Watermark Passing Loop (RIC) (455.600km) New By 2011 Target 2011 Not Commenced
Wingen Passing Loop New By 2012 Target 2012 Not Commenced
South Gunnedah Passing Loop New By 2012 Target 2012 Not Commenced
Muswellbrook – Koolbury Duplication New By 2011 Target 2011 Not Commenced
New Liverpool Range Alignment New By 2012 Target 2012 Not Commenced
Scone Reconfiguration New By 2011 Target 2011 Not Commenced
Completed ProjectsConstruction Has Commenced or tenders calledDeleted ProjectsLate Projects
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 23
Conclusion
• Resource Constrained environment
• 4 x 2 day Possession per year of which projects can be completed/commissioned without adverse impact of throughput
• Unprecedented on time completion by the Hunter Valley Major Works Team
• Total value of commissioned projects to date is $126M
• Value of work currently under construction or at tender is $122M
• Value of work at final design with construction to commence within 6-12 months is $141M
• Value of next 5 year spend is $988M
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 24
Forecast Outlook
Gunnedah Basin
Theoretical Capacity 11.6mtpa
95mtpa notional allocation 5.0mt
113mtpa notional allocation 7.5mt
145mtpa notional allocation 25mt
West of Muswellbrook
Theoretical Capacity 17.63/25.5/35.8
95mtpa notional allocation 12.2mt
113mtpa notional allocation 15mt
145mtpa notional allocation 24mt
Muswellbrook - Antiene
Theoretical Capacity 52.88/146.07
95mtpa notional allocation 17.2mt
113mtpa notional allocation 22.5mt
145mtpa notional allocation 49mt
Antiene to Singleton
Theoretical Capacity 146.07mtpa
95mtpa notional allocation 58.1mt
113mtpa notional allocation 67.9mt
145mtpa notional allocation 113mt
Singleton - Port
Theoretical Capacity 188.88/209
95mtpa notional allocation 90.6mt
113mtpa notional allocation 109.5mt
145mtpa notional allocation 141mt
11/03/2008 Coal Capacity Forum - Project Update 5 March 2008 25
FORECAST OUTLOOK
95mtpa Notional Allocation
5.0mt
12.2mt
17.2mt
58.1mt
90.6mt
145 mtpa Notional Allocation
25mt
24mt
49mt
113mt
141mt
113mtpa Notional Allocation
7.5mt
15mt
22.5
67.9mt
109.5mt
Unconstrained Rail Theoretical Capacity
11.6mtp
17.63mtpa/25.5mt/35.8mt
52.88mtpa/146.07mt
146.07mtpa
188.88mtpa/209mtpa
Gunnedah Basin
West of Muswellbrook
Muswellbrook - Antiene
Antiene – Singleton
Singleton - Port