presentation team - acecnjacecnj.org/pdf/acecnj-njdot-fhwa-rm... · presentation team: “risky...
TRANSCRIPT
ACECNJ/NJDOT/FHWA 2013 DESIGN SUMMIT
Presentation Team:
“Risky Business”
• Definition of Risk
• What is Risk Management (RM)
• Constructability
• Risk reviews relationship
• Integration of Risk Management at NJDOT
• Constructability & Risk review
• Route 202 over Passaic
What is Risk?
A risk is defined as a future event, that
can be either an opportunity or threat, that
could occur and has a direct impact on
the success of a program or project
Event
The things that may happen sometime in
the future that will trigger an opportunity
or threat
Opportunity
Benefit to our ability to deliver
the program or project and
achieve an objective
Threat
Detriment to our ability to
deliver the program or project
and achieve an objective
Five Recognized Steps:
1. Plan for Risk
2. Identify Risk
3. Analyze and Prioritize the Risks
4. Plan and Execute Response Strategies
5. Monitor, Evaluate & Adjust
A failure to plan…is a plan to fail!
Identify the context
Product – The Scope Statements will document the
extent of Risk Management on each project
Plan for
Risk
Identify
Risks
Prioritize
Assessed
Risks
Plan and
Execute
Response
Strategies
Monitor,
Evaluate
and Adjust
Communication and Consultation occur at each step
Analyze the Risks
Assess
Risk
Probability
Assess
Risk
Impact
For each identified Risk, ask the following:
• What are the possible risks to the project?
• What are possible benefits to the project?
• What are the challenges/barriers to the project?
Plan for
Risk
Identify
Risks
Prioritize
Assessed
Risks
Plan and
Execute
Response
Strategies
Monitor,
Evaluate
and Adjust
Communication and Consultation occur at each step
Analyze the Risks
Assess
Risk
Probability
Assess
Risk
Impact
Product – Risk Statements are documented within the
Risk Register
What events could affect the project?
• Impacts?
• Likelihood?
Plan for
Risk
Identify
Risks
Prioritize
Assessed
Risks
Plan and
Execute
Response
Strategies
Monitor,
Evaluate
and Adjust
Communication and Consultation occur at each step
Analyze the Risks
Assess
Risk
Probability
Assess
Risk
Impact
Product – Each Risk Statement will be analyzed and
documented within the Risk Register
• Use Matrix on previous slide to determine criticality (or
lack thereof) of risk statements – relative status
• Product – Each Risk Statement, once analyzed, will be
prioritized within the Risk Register
Product – Each Risk Statement, once analyzed, will be
prioritized within the Risk Register
Plan for
Risk
Identify
Risks
Prioritize
Assessed
Risks
Plan and
Execute
Response
Strategies
Monitor,
Evaluate
and Adjust
Communication and Consultation occur at each step
Analyze the Risks
Assess
Risk
Probability
Assess
Risk
Impact
For each threat the response strategy is to:
For each opportunity the response strategy is to:
• Avoid
• Accept
• Mitigate
• Transfer
Plan for
Risk
Identify
Risks
Prioritize
Assessed
Risks
Plan and
Execute
Response
Strategies
Monitor,
Evaluate
and Adjust
Communication and Consultation occur at each step
Analyze the Risks
Assess
Risk
Probability
Assess
Risk
Impact
Product – Response Strategies and Response Plans
are documented within the Risk Register
• Exploit
• Accept
• Enhance
• Share
• Monitor status of risk strategies & response plans
• Document adjusted risk strategies & response plans
• Monitor action plan status performance for lessons
learned and best practices
Plan for
Risk
Identify
Risks
Prioritize
Assessed
Risks
Plan and
Execute
Response
Strategies
Monitor,
Evaluate
and Adjust
Communication and Consultation occur at each step
Analyze the Risks
Assess
Risk
Probability
Assess
Risk
Impact
Product – Response Strategies and Response Plans
are documented within the Risk Register
Constructability &
Risk Relationship
Time-driven Performance
Risks• Agencies controlled by funding and
political commitment deadlines
• Designers judged by performance of
deliverables
• Construction contracts governed by
milestones, performance windows and
time-of-the-essence clauses
Transportation Project
Special Risk Factors
• Cost/Schedule are driven by how something is
constructed versus what is constructed
• Public in, around and through the construction
site
• Restricted work windows and work zones
• Maintenance and protection of traffic – work
zone safety for the public and construction
crews
Risk Management
Tools & Process
Can be performed at any stage, concept thru construction!
• Risk Register
• Constructability Reviews
• Value Engineering Reviews
Risk Constructability
Common Elements
Multidiscipline Teams:
• Architects, Engineers, Construction Managers
• Procurement: Contract options, funding, legal
• Specialists: Environmental, HAZOPS, Police, etc.
• Operations Personnel: Maintenance, plant engineers
• Contractors: Means & Methods, MOT/MPT, etc.
FDOT – Miami Intermodal Center
Example 1
Combined RM/VE Workshop
FDOT MIA-MIC
Example 1
NYSDOT – Work Zone
Safety InitiativeDOT HQ - Review Region Projects
• Tech Design Not Reviewed
• Maintenance of Traffic Only
• Review Work Zone Layouts
• Review Work Windows
• Review Traffic Alternatives
• Review Work Flows
• No Costs Considered
Example 2
NYSDOT – Work Zone Safety
Initiative
Workshop Teams:
• DOT HQ Construction Managers
• FHWA Construction Managers
• State/Local Police
• Contractors
• Specialty Consultants – Traffic, IT, etc.
Example 2
Goal to reduce risk by improving worker and public safety.
Take-Away Points
• Everything involves risk – risk cannot be eliminated, but it can be managed
• RM documents (risk register, etc.) are not end products – they are tools to be used throughout the life of a project. They are tools to help manage risk
• Value Engineering and Constructability Reviews are processes to help manage risk
Example 2
Integration of Risk
Management at NJDOT
Objectives• Identifying risks early = opportunity to manage the
risk
• Reduction in design changes and scope = cost
savings
• Quality contract documents = enhanced project
success
Current Practice
• Project Managers, Designers & SMEs are performing
informal project risk management without consistent
procedures or practices and without consistent
documentation
• Project Managers, Designers & SMEs are performing
project risk management without coordination of effort
• Risks may be identified, but may not actually lead to
implementation of response actions
Formal Risk Management
• Risk Management will occur from Problem
Screening through Construction
• Risk Management will be scalable
• Coordinated effort
• Central and Accessible Repository
• Compatible with the Capital Project Delivery
process and CPD activities
Leverage current best practices:
Interactive Communications
Design Communications Report (DCR)
with
Future State:
Formal and structured process allowing for opportunity to
mitigate threats or embrace opportunities on projects
Formal Risk Management
Benefits
• Risks are formally documented and evaluated so the Project
Team does not manage by crisis when a risk is realized
• Allows for prioritization of high probability and high impact
risks
• Enhances communication between the Project Team and
encourages a robust and diverse exchange of ideas and
solutions
• Strategy can be tracked and monitored for effectiveness
Next Steps
• Risk Management Process Pilot Program
• Monitor the Process for Refinement
• Implementation with Training
Constructability Review
& Risk Management:
Case Study
Route 202 over Passaic River
WEATHER DELAYS
Risk Rank & ID Risk Statement & Category Risk Analysis Matrix Risk Response Strategy & Response Planning
Risk Category Risk Impact
Risk Rank Unique ID # Risk Statement
Initial Risk Owner Risk May Occur In
Risk Probability
Schedule Cost
ScheduleScore
CostScore
FinalScore
Risk Response Strategy
Risk Response Action Plan Final Risk Owner Action Plan Status Risk Last Updated
Final Result Post-Construction
1 1As a result of Weather delays during
construction which may occur, which would lead to schedule delays
Construction Construction 5 - Very High 10 - Very High 4 - Moderate 50 20 70 Accept ThreatHave a contingency of 2 days not shown in the
contract documents that will allow for unforeseen issues such as weather delays.
Contractor and NJDOT Plan Implemented 4/9/2013We were lucky and there were no weather delays. Future jobs can base this risk off of historical weather data.
1 2
As a result of what can be considered a weather delay which may occur, which would
lead to conflict regarding schedule time extensions
Construction Construction 5 - Very High 10 - Very High 4 - Moderate 50 20 70 Accept Threat
Define in the specs that the RE will determine if the project is delayed due to weather. Since it is a 24hr schedule, allow for hourly delays with impacts to working crews. Give additional time to allow mob and demob detailed in the spec.
Contractor and NJDOT Plan Implemented 4/9/2013
Although this was included in the spec and not used, all involved with construction agreed was the best approach to weather delays.
FABRICATION
Risk Rank & ID Risk Statement & Category Risk Analysis Matrix Risk Response Strategy & Response Planning
Risk Category Risk Impact
Risk Rank Unique ID # Risk Statement
Initial Risk Owner Risk May Occur In
Risk Probability
Schedule Cost
ScheduleScore
CostScore
FinalScore
Risk Response Strategy Risk Response Action Plan Final Risk Owner Action Plan Status Risk Last Updated
Final Result Post-Construction
2 14
As a result of the prefabricator requiring more than the 5.5 months allotted in the schedule for fabrication due to unforeseen delays in material deliveries or backlog in orders which may occur,
which would lead to project schedule delays
Construction Construction 5 - Very High 10 - Very High 1 - Very Low 50 5 55 Accept ThreatHave a contingency of 2 days not shown in the
contract documents that will allow for unforeseen issues.
Contractor and Designer
Plan Implemented 4/9/2013
This risk almost delayed construction and proved to be critical. There is little control over the fabricator's schedule. If KK didn't push to get the job out to bid, this would have definitely delayed the schedule.
CRANE MALFUNCTION
Risk Rank & ID Risk Statement & Category Risk Analysis Matrix Risk Response Strategy & Response Planning
Risk Category Risk Impact
Risk Rank Unique ID # Risk Statement
Initial Risk Owner Risk May Occur In
Risk Probability
Schedule Cost
ScheduleScore
CostScore
FinalScore
Risk Response Strategy
Risk Response Action Plan Final Risk Owner Action Plan Status Risk Last Updated
Final Result Post-Construction
4 12
As a result of the on site cranes malfunction requiring new cranes to be brought in which
may occur, which would lead to schedule delays
Construction Construction 3 - Moderate 10 - Very High 1 - Very Low 30 3 33 Mitigate Threat
Identify if a backup crane is available and the mobilization time required prior to bridge
demolition. Prepare a design that allows for a standard size crane to be used so a replacement can readily be found.
Contractor Plan Implemented 4/10/2013
We did have a crane breakdown on the project. The contractor was able to find an alternate crane, get it delivered and still construct within schedule.
UTILITY INTERFERENCE
Risk Rank & ID Risk Statement & Category Risk Analysis Matrix Risk Response Strategy & Response Planning
Risk Category Risk Impact
Risk Rank Unique ID # Risk StatementInitial Risk Owner Risk May Occur In
Risk ProbabilitySchedule Cost
ScheduleScore
CostScore
FinalScore
Risk Response Strategy
Risk Response Action Plan Final Risk Owner Action Plan Status Risk Last Updated
Final Result Post-Construction
4 16As a result of Utilities not moved in adequate time for construction which may occur, which
would lead to schedule delaysConstruction Construction 3 - Moderate 10 - Very High 1 - Very Low 30 3 33 Mitigate Threat
Have advance utility relocations take place removing this item from the critical path
Designer and NJDOT Plan Implemented 4/9/2013Utilities were moved through advance construction through direction and coordination by Amercom
PLACEMENT OF UNITS
Risk Rank & ID Risk Statement & Category Risk Analysis Matrix Risk Response Strategy & Response Planning
Risk Category Risk Impact
Risk Rank Unique ID # Risk StatementInitial Risk Owner Risk May Occur In
Risk ProbabilitySchedule Cost
ScheduleScore
CostScore
FinalScore
Risk Response Strategy
Risk Response Action Plan Final Risk Owner Action Plan Status Risk Last Updated
Final Result Post-Construction
11 10
As a result of Precast abutments being out of alignment when placed on piles which may
occur, which would lead to improper construction and delays
Construction Construction 2 - Low 4 - Moderate 2 - Low 8 4 12 Mitigate ThreatAllow the design of the bearing seat to be slightly oversized to compensate for the
misaligned abutments.
Contractor and Designer
Plan Implemented 4/10/2013Abutments needed some adjustment in the field but it did not impact the schedule or final outcome.
11 11
As a result of Prefabricated superstructure units being out of alignment when placed on bridge which may occur, which would lead to
improper construction and delays
Construction Construction 2 - Low 4 - Moderate 2 - Low 8 4 12 Mitigate ThreatAllow the design of the bearing seat to be slightly oversized to compensate for the
misaligned abutments.
Contractor and Designer
Plan Implemented 4/10/2013Final placement of superstructure lined up very well