Timelines for various projects
• Govt. of NCT of Delhi had earlier demanded funds to the tune of Rs. 1314.40 Crores for improving infrastructure, for example connectivity, traffic management and parking, power, health care, civic amenities and general arrangements in Delhi .
• After meeting with Minister MYAS and Secretary MYAS this amount has been brought down to Rs. 770 Crores.
• The remaining schemes of Rs. 582.20 Crores will be undertaken in the regular Plan Schemes of GNCTD.
• The Planning Commission has given its approval for Rs. 770 Crores.
• The role of private sector participation is being explored in following fields :
i) Radio Taxisii) Parking on BOT basisiii)Improvement of bus fleet operated by private operators
Public Works Department
S.NO Scheme Cost of work (Rs.in Crores)
Present status of work
Date of award of work
Date of completion
Remarks
1. Bypass at Massodpur & Mahipalpur (3.7 Kms.)
30.00 Proposal for both the bypasses submitted to TC-DDA on 1/06 for approval; EFC by 08/06, tender floating 09/06
12/06 12/08
2. Tunnel by pass Connecting NH 24/ Ring Road intersection and Neela Gumbad near Nizummdin (2.2 kms.)
135.00 DPR by 2/07. Reports received from Geometric design consultants & sent to various deptts., designs to be finalized May 07, clearances required from TC, DDA, ASI, DUAC before Oct. 06
May 2007 Dec. 2009
Municipal Corporation of Delhi
S.NO Scheme Cost of work
Present status of work
Date of award of work
Date of completion
Remarks
1. Railway under bridge near Vivek Vihar
40.00 Cleared by technical committee, DDA; estimates finalised
03/07 03/09 To be executed by MCD/ Railways, date of award-March 07
2. Improvement
i) JLN Marg from Ring Road to Thompson Marg
ii) Mehrauli Gurgaon Road
iii) Roads near Siri Fort & Asiad Village Complex
4.55 Already approved by Corporation
04/08
04/09
March 2010
-do-
Municipal Corporation of Delhi
S.NO. Scheme Cost of work
Present status of work
Date of award of work
Date of completion
Remarks
1. Improvement of surrounding of Old and New Delhi Railway Station, improvement of parking area, bus stand
5.00 Already approved by Corporation; estimates finalized
04/08 03/10 -
2. 50 Mechanical sweeper,fancy dustbins, fluorescent overcoats
15.00 Already approved by Corporation
04/08 -09 03/10 -
3. Face lifting and beautification by Horticulture Deptt.
5.00 - 08-09 03/10 -
Transport department
S.NO. Scheme Cost of work
Present status of work
Date of award of work
Date of completion
Remarks
1. 1100 new modern air conditioned /deluxe/mini buses for participants/ managers/officers and for park & ride facility
260.00 Finalization of tender date, details, designs, specifications being done.
2008-09 March 2010
2. Renovation/ dev. of ISBTs .
Dwarka
Kashmiri Gate
Anand Vihar
Narela
Sarai Kale Khan
10.00
Tenders ready
DPR 04/07
DPR 06/07
DPR 06/07
DPR 03/07
10/06
10/07
12/07
12/07
04/08
04/09
07/09
12/09
03/09
Temporary ISBT Sarai Kale Khan is ready (PWD)
Health & Family Welfare
S.NO. Scheme Cost of work
Present status of work
Date of award of work
Date of completion
Remarks
1. Setting up 12 health posts
6.00 - 07/09 March 2010 Setting up of first post at each stadia
2. Poly clinic at Games Village
4.00 Putting up proposal for SFC
04/08 March 2010
3. Ambulance Services 5.00 - 04/09 March 2010 Procurement of ambulances by 2009
4. Upgradation of GTB, LBS,DHAS,Malviya Nagar, AAA Hospital/ Sushruta Trauma centre
31.00 Expecting proposals from different hospitals for upgradation
04/08 March 2010 Target to be fine tuned.
5. Training/disaster preparedness
3.00 Training to trainees Sep.-Oct. 2006; 702 trainees to be trained
Oct. 06 March 2010 Training on basic emergency, disaster management; the trainees will be kept ready.
New Delhi Municipal Council
S.NO. Scheme Cost of work
Present status of work
Date of award of work
Date of completion
Remarks
1. Upgradation of Talkatora Stadium & Shivaji Stadium
14.20 Statutory approval to be applied by 10/06
02/07 03/09 Approval expected by 12/06 & inviting tender bids by 01/07
Consultant appointed & EKS to give detailed technical specification
2. Improvement of major road around stadia
19.55 Proposal to DUAC by 01/07
03/07 03/09 -
-
3. Upgradation of Central Vista and its environs
To be finalized
Proposal to be submitted to DUAC by 01/07
08/07 12/09 Approval expected by 04/07.
Delhi Jal Board
S.NO. Scheme Cost of work
Present status of work
Date of award of work
Date of completion
Remarks
1. Upgradation of water supply at
I.G. Stadium
Ambedkar Stadium
Chattersal Stadium
JLN Stadium
Sirifort Stadium
DLTA Stadium
1 MGD STP
16.50 Clearance received from Technical committee
Tender recd.for consultant
06/2008
06/2009
06/2009
04/2007
06/2008
06/2008
04/2007
9/2008
9/2008
09/2009
01/2008
12/2008
03/2009
03/2009
Additional demand is being received from concerned authority
2. 1 STP 23.50 Apptt. of consultant to be initiated
04/2007 03/2009 Land is yet to be allotted.
Education Department
S.NO. Scheme Cost of work
Present status of work
Date of award of work
Date of completion
Remarks
1. Tyagraj Nagar Sport Complex Net Ball
35.00 Bid for design consultants invited. Consultant to be finalized by 10/2006
March 2007 March 2009 PWD is constructing the stadium.
Details of technical required to be provided by EKS/OC
2. Chhatrasal Stadium (Training venue)
5.00 - - - Decision whether the stadium is to be remodeled or only improvements are required, is to be taken
State Plan Flyovers / Bridges providing connectivity to Games Village / Venues / Hospitals
• 1 (A) Flyovers Cost Connectivity Completion Date (Rs. Cr.)
1 ITO Chungi (underpass) 70 Games Village to IG Stadium 12/08
2 Rao Tula Ram Marg 40 Airport to Village/Venues12/08
3 R.K. Puram / 40 --do— 12/08
Nelson Mandela Marg
4 Africa Avenue / 40 --do— 12/08
Aruna Asaf Ali Road
5 Neela Haus on 50 --do-- 03/08
Aruna Asaf Ali Road
Flyovers at Cost Connectivity Completion Target (Rs. Cr.)
6 Geeta Colony Bridge 130 Games Village to I.G. Stadium, 02/08
7 Raja Ram Kohli Marg 35 Chhatarsal Stadium & Delhi 12/08
8 Shastri Park Pushta 40 University Sports Complex 12/08
(Disused canal)
9 BSZ Marg 150 Games Village /Venues to LNJP & 12/09G.B. Pant Hospital
10 Ring Road bypass 200 Games Village to I.G. Stadium, 03/09
Salimgarh Fort to Chhatarsal Stadium & Delhi
Velodrome Road University Sports Complex
(Shantivan & Rajghat)
11 Elevated East West 325 Games Village to Talkatora 12/09
Corridor from Games & Shivaji Stadium
Village to Rajiv Chowk
Total 1120
All the above flyovers are six lane except Geeta Colony Bridge which is 8 lane corridor.
Contd…
Flyovers / Bridges for intracity connectivity
• Flyovers at Cost
(Rs.Cr.)1. Naraina 1252. Shastri Park 403. Azadpur 1204. Mangolpuri 405. Mukerba Chowk 2006. ISBT Anand Vihar & NH-24 near (Gazipur drain) 907. Shyamlal College 408. Apsara Border 509. U P Link Road on NH-24 crossing 6010.Nangloi 8011.Behra Enclave 3012.Road over bridge on Road no.63 3513.Road under bridge connecting road no. 58 & 64 35
Total 945
These flyovers will be completed progressively by Dec. 2009