presentation flare

Upload: mksiocl

Post on 11-Oct-2015

115 views

Category:

Documents


3 download

TRANSCRIPT

  • Basics of Flare Design

    Sandip Lahiri

    Process Design Engineering Cell

    IOCL-RHO, Noida

  • Flare

    Disposal method ofOperational

    &Emergency Relief

    Flammable Substanceto a safe location

    Uses CombustionTo

    ConvertFlammable,Toxic/CorrosiveVapors

    Less Objectionable CompoundsTo

  • Consist of

    Piping

    Vessel

    Stack

    Environmental Control

    Continuous flow of excess gas

    Large surges of gas in emergency

  • Factors affecting Design

    Physical & Chemical Properties of Fluid

    Flash PointFlammable limitsIgnition TempPhase ChangeReactive Chemicals

    Recovery Value

    Costly Solvents

  • Factors affecting Design (Contd..)

    Availability of Space

    EconomicsInitial CostOperating Cost

    Public Relations

    If it is seen from residential area

  • How to determine Flare LoadSafety are used to protect pressure vessels.

    Safety duty are calculated considering following contingencies

    Blocked FlowExternal FireReflux Failure in columnsPower Failure in Units/ColumnsCooling Water Failure/Air Cooler Failure

    Individual unit total flare load is computed considering the exigencies as above.The maximum of them is considered as flare load ex the unit.All units are summed up to compute the flare load.Often cooling water supply, power supply is given from different sources so that controlling flare load is not additive.

  • The controlling load will determine the sizing of

    Flare Header

    Flare Stack

    Seal

    K.O. Drum

    Seal Drum

    API RP 520 & API RP 521

  • Combustion Properties

    FlameSmoke Radiation

    Flame-Rapid self sustaining chemical reaction

    9Diffusion Flame:Occurs on Ignition of Fuel jet issuing into air

    9Aerated Flame:Occurs when fuel & air are premixed beforeignition

  • Generally Flame front is normally at the top of stack

    At low gas velocity back-mixing of air occurs at the top of the stack

    resulting in combustion at a flame front located part of the way

    down the stack creating high stack temperature.

    Flame extinguishment may also occur with subsequent formation

    of an explosive mixture in the stack.

  • Smoke

    HC Flames are luminous Carbon Particles

    Released from Flames

    Smoke

    When the System is Fuel Rich

    Steam

    Reduce Smokeformation

  • Two School of Thoughts

    Steam separates HC molecules Minimizing Polymerization

    Forms O2 compounds that burns at a reduced rate &temp that are not conducive for cracking & polymerization

    Water Vapor + Carbon Particles CO+CO2+H2

    Removing the Carbon before it cools and forms Smoke

  • Suggested Steam Injection Rates

  • In extreme cold climates an internal steam nozzle may causeCondensate to enter flare header, collect and freeze.

    In such cases high pressure air may be used.

    Only disadvantage of air is that it is more expensive than steam

    Air is advantageous in desert and island where water is shortage.

    Steam pr-100-150 psi

    Air pr-100 psi

    Air requirement is approximately 20% more than steam as compressed air does not produce water-gas shift reactionthat occurs with steam.

  • Steam Injected smokeless Flare Tip

  • Radiation

    Effect of Radiation Intensity on Human skin

    Intensity Pain Threshold BurnBtu/hr/sqft Seconds Seconds

    2000 8 207500 - 6

    Intensity Pain Threshold BurnBtu/hr/sqft Seconds Seconds

    250-330 - -

    Solar Radiation

  • As allowable Radiation level is a function of length of exposure,factors involving reaction time & human mobility to be considered.

    In emergency releases a reaction time of 3-5 secs may be considered.

    5 secs for individual to seek cover or depart from the area.

    Total exposure time of 8-10 secs.

    Solar radiation to be added for considering total exposure time.

    Clothing provides some shielding.

    In case of radiation emanating from an elevated point,standard PPElike Hard Hat may reduce thermal exposure.

  • Permissible Design Total Radiation

  • In most cases, equipment can safely tolerate higher degrees

    of heat intensity than those defined for personnel.

    However, if any items vulnerable to overheating problems

    are involved,such as construction of materials that have low

    melting points (aluminum,plastic),heat sensitive streams,

    flammable vapor space,or electrical equipment then the effect

    of radiant heat on them may be evaluated.

  • Minimum distance from a flare to an object whose exposure to thermal radiation must be limited

    Q = 2.15 x 109 BTU per hrK= 2000 Btu per hr per sq ftF=0.3T= 1.0So D= 160 ft.

    Flare manufacturers have their own proprietary radiation programs based on empirical values.

    The Emissivity (Fraction of heat radiated) values used in these programs are specific to equations used and are not interchangeable.

  • Flame Length vs. Heat release

  • Flame distortion due to wind velocity

  • Gases that have high heating value (200-300 BTU/scf) can sustain

    combustion on their own without any auxiliary fuel additions.

    In some cases addition of auxiliary fuel in the form of fuel gas is necessary.

    Dilute NH3 and high CO2 composition gases with small amounts of

    H2S are common applications.

  • Auxiliary Flaring Equipment

    Liquid Seals-

    Flashback protection- To provide positive protection against Flame propagation into plant piping.

    Maintain +ve header pr- To ensure that a positive pr. is always maintained on the flare header. Any leaks in the flare header will result gas leakage to atmosphere and not air leakagein the header.

    Purge of O2 free gas-

    Prepurge removes any O2 from stack and continuous purge ensures no air enters stack during low flow conditions.To reduce amount of purge gas Diffusion type seal and velocity

    Seal are used.

  • Diffusion type seal- This type of seal uses the difference in molecular weights of the purge gas and infiltrating air to form a gravity seal which prevents the air from entering into the stack. A baffled cylinder arrangement forces the incoming air through two 180 Deg bends (one bend up and one bend down) before it can enter into the flare stack.If the purge gas is lighter than air the purge gas will accumulate in the top of the seal and prevent air from infiltrating the system.If the purge gas is heavier than air the purge gas will accumulate in thebottom of the seal and prevent air from infiltrating the system.

  • Velocity Seal- This seal works under the premise that infiltrating air enters through the flare tip and hugs the inner wall of the flare tip.The velocity seal is cone shaped obstruction with single or multiple baffles, which forces the air away from the wall where it encounters the focused purge gas flow and is swept out of the tip.

  • Purge reduction seals are not flame arrestors ;that is they will

    not stop flashback. They are energy conservation device to

    reduce purge gas flows required to prevent flashback by

    reducing air infiltration in the stack.

  • Flare Type Elevated Flare Ground Flare

    Selection of Flare type is based on

    Available Space Characteristics of the flare gas (composition, quantity and pressure) Economics(investment and operating costs) Public Relations & Regulations.

    Elevated Flare (Most commonly used in Refinery Operation)

    Have larger capacities than ground flares. If adequately elevated, this type of flare has the best dispersion

    characteristics for malodorous and toxic combustion products.

    Due to steam injection / air injection , it introduces a source of noise and cause noise pollution.

    Capital costs are relatively high. Appreciable plant area may be rendered unavailable for plant equipment,

    because of radiant heat considerations.

    Advantage

    Disadvantage

  • Elevated Flare

  • Ground Flare

    A ground flare is where the combustion takes place at ground level.

  • Self Guyed DerrickSupported Supported Supported

    Types of Flare Support

  • Self-supported stacks are more expensive than other design, because it need greater material to ensure structural integrity over the anticipated condition. Normally the stack height for the self-supported design ranges from 200 to 300ft.

    Guy-wire supported is less expensive but it need the largest land due to the

    guy wire radius requirements. The radius of guy-wire is equal to 1.5 of the

    overall stack height.Guyed stacks with heights from 600 to 800 feet have

    been used.

    Derrick supported only used when the stack is large (self-supported not

    practical) and available land area is limited (guy-wire supported not suitable).

  • Quench is also used at times to condense the less volatile

    components and reduce the release of hot condensable vapors

    to the atmosphere.

  • Drag Coefficient

  • Flare gas recovery

    Flare gas is treated and routed to FG system

    Environmental

    Economic

    Safety Considerations

    Path to flare

    Used for both normal and emergency release.

    Emergency release should always have path to the flare

    Design of flare recovery system should not compromise this path

    Necessary for

  • Safety Considerations (Contd..)

    Back Flow

    FGRS uses compressors which take suction directly from the flare

    header.

    The potential for back flow of air from the flare into the compressors

    at low flare gas loads must be considered.

    Oxygen content of flare gas stream should be measured and

    provisions must be made to shut down the flare gas compressor if

    potentially dangerous condition exist

  • Safety Considerations (Contd..)

    Flare gas characteristicsWidely varying compositionsPotential for materials which are not compatible to treating system must be determined.

    Streams containing acid gases are routed directly to flare bypassing recovery system

    Design Considerations

    SizingSeldom sized for emergency flare loads.Flare loads vary widely over time and the normal rate may be some average flare load or a frequently encountered maximum load.

    Actual loads on these systems will vary widely and they must be designed to operate over a wide range of dynamically changing loads.

  • Design Considerations (Contd..)

    Location

    Typically FGRS are located downstream of all unit header tie-ins

    and at a point where header pressure does not vary substantially with

    load.

    Locations upstream of process unit tie-ins should be carefully

    considered because of the potential for back-flow and high-oxygen

    concentration.

  • Design Considerations (Contd..)

    Flare Tie-inA major consideration in FGRS design is preservation of a path to flare for emergency releases.

    FGRS must be designed as a side stream from the flare header.Main flare flow should not be through a compressor knock out or suction piping.

    The tie-in to the FGRS should come off the top of the flare line to minimize possibility of liquid ingress.

    Most positive and preferred way to prevent air ingress is the installation of a water seal vessel between flare knock out drum and

    flare itself

    Alternate method is to use a fail open control valve

  • Typical Flare Gas Recovery System

  • Typical Flare Gas Recovery Inlet Pressure

  • Diagram for Stack Height Calculation

  • Typical Seal Drum

  • Typical Quench Drum

  • Typical Flare Installation

  • Sizing a Flare Stack:

    Problem:

    Flow rate of HC vapors = 100000 lbs per hr.

    Avg. molecular weight (MW) = 46.1

    Temp (T) = 760 0R (149 0C)

    Compressibility Factor (Z) = 1.0

    Heat of Combustion = 21500 Btu/lb

    Ratio of specific heat of gas (K) = 1.1

    Pr. at Flare tip = 14.7 psia

    Design Wind Velocity = 20 miles /hr

    = 29.3 ft/sec

  • Solution:

    Flare Diameter:

    MACH = (1.702) x (10-5) x (W / P2 D2) x (ZT / K x MW )0.5

    For, MACH = 0.2

    So, 0.2 = (1.702) x (10-5) x (100000/ 14.7 x D2) x ( (1x 760) / (1.1) x (46.1) )0.5

    So, D2 = 2.24

    So, D = 1.5 ft (ID)

    Flame Length:

    Q = (100000) x (21500) = 2.15 x 109 Btu /hr.

    From Graph(Flame Length Vs Heat Release).

    L (Flame Length) = 170 ft.

  • Flame Distortion by Wind Velocity:

    Vapor Flow Rate = (100000 / 3600) x (379.1 / 46.1) x (760 /520)= 334 A ft3 per sec.

    Flame Distortion:

    Ua = Wind Velocity Uj Flare Tip Velocity

    Uj = Flow / {(3.14)xD2/ 4}= 334 / { 3.14 x (1.5)2 / 4} [ For, MACH = 0.2]=189 ft/sec.

    Ua = 29.3 Uj 189

    = 0.155

    From GraphDy / L = 0.35Dx / L = 0.85So, Dy = (0.35) x 170

    = 59.5 ft.So,Dx = (0.85) x 170

    = 144.5 ft.

  • Calculation of Stack Height:

    D = (TFQ / 4 x 3.14x K)0.5 [ F=0.3, T =1 The max. allowable radiation at 150ft from Flare Stack = 2000 (Btr /hr) / sqft]

    So, D = (1x (0.3) x (2.15x 109) / 4 x (3.14 )x (2000))0.5= 160.2 ft .

    Flare Stack Height:

    H = H + DyR = R - DxDx = 144.5 ftDy = 59.5 ftR = R- x (144.5)

    =150 x (144.5) = 78 ft.

    D2 = R 2 + H 2H 2 = D 2 - R 2

    = (160)2 (78)2= 19516 ft2.

    So, H = 140 ft. So, H = 140 D y

    = 140 (59.5) = 110 ft.

  • Sizing a Knock out Drum: -

    Problem:

    Single Contingency results in the flow of 200000 lbs/hr of a fluid

    Liquid density of 31 lbs /ft3 & vapor density of 0.18 lb /ft3.

    Pr = 2 psi.

    Viscosity of Vapor = 0.01 Cp

    Fluid Equilibrium results in 31000 lbs per hr of liquid & 169000 lbs per hr of vapor.

    In addition 500 gallous of storage for miscellaneous draining from the units is desired.

    The droplet size selected as allowable is 0.000984 ft in diameter.

  • Solution: Vapor Rate (Rv) = 169000 lbs / hr (3600 sec. /hr) x (0.18 lbs/ft3) = 261 ft3 /sec PV PL Drag Coefficient (C) from graph D PV C (RC)2 = 0.95 x 108 x (0.18 )x (0.000984)3 (31-0.18) (0.01)2 = 5021. So, C from graph = 1.3

  • Drop Out Velocity (VC): UC = { (gD (L - V) / V x C )0.5}x 1.15 = {((32.2) x(0.000984)x(31-0.18) / (0.18)x(1.3))0.5 } x 1.15 = 2.35 A horizontal vessel with an inside diameter Di and a cylindrical length L should be assumed, At (Cross Section Area) = /4 (Di)2 AL1 = ((500 gallous) /(7.48 gallous per ft3)) x (1/L) Considering liquid hold up of 30 minutes during emergency, A L2 = (31000 lbs per hr / 31 lbs per ft3) x (30 minutes / 60 min per hr) x (1/L) The cross sectional area for the remaining vapor flow, A V = A T - (A L1 + A L2). h L1 = Depth of slops & Drains. h L1+ h L2 = Depth of all liquid accumulator. hV = Remaining metrical space for the vapor flow. ht = Total drum diameter = hL1 + h L2 +hr (Liquid Dropout time, in seconds) = (hV / 12 inches per ft) x (1/ VL ft per sec.) UV (Vapor Velocity in ft per sec) = (260 ft3 per sec / A V ft2) DRUM LENGTH (LMIN) = (UV ft /sec) x ( secs.) LMIN should be less than or equal to the assumed drum length L. Other wise the calculation must be repeated with a newly assumed cylinder length. Assume dMIN inside dia = 8 ft Assumed dMIN length = 19 ft AT = 50.26 ft2 AL1 = 3.25 ft2 h L1 = 11.25 inches. A L2 = 26.32 ft2 h L1 + h L2 = 55 inches. AV = 20. 69 ft2 hV = 41 inches. ht = 96 inches. Liquid dropout time (sec) = 1.45. Vapor velocity UV (ft/sec) = 12.73. Require Drum Length LMIN (ft) = 18.5

  • Modes of Flare Failure

    Flow Restriction

    Failure to burn

    Mechanical Failure

  • Modes of Flare Failure (Contd..)

    Failure to burn can be caused by loss of pilot functioning.Pilot failure can often be traced to a failure of the pilot gas Supply system rather than pilot itself.

  • Modes of Flare Failure (Contd..)