Department of Product and Production Development CHALMERS UNIVERSITY OF TECHNOLOGY Gothenburg, Sweden 2015 Prerequisites for an ICT-platform at Volvo Group Trucks Study of the product development and production interface within projects Master’s thesis in Production engineering Johan Korteniemi David Mattsson

Upload: others

Post on 10-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Department of Product and Production Development CHALMERS UNIVERSITY OF TECHNOLOGY Gothenburg, Sweden 2015

Prerequisites for an ICT-platform at

Volvo Group Trucks Study of the product development and production interface within projects Master’s thesis in Production engineering

Johan Korteniemi David Mattsson

Prerequisites for an ICT-platform at

Volvo Group Trucks

Study of the product development and production interface

within projects

Johan Korteniemi

David Mattsson

Supervisor: Atieh Hanna, Pierre Johansson, Magnus Åkerman

Examiner: Åsa Fasth-Berglund

Department of product and production development

CHALMERS UNIVERSITY OF TECHNOLOGY

Göteborg, Sweden 2015

Prerequisites for an ICT-platform at Volvo Group Trucks

Study of the product development and production interface within projects

© JOHAN KORTENIEMI & DAVID MATTSSON, 2015

Departments of Product and Production Development

Chalmers University of Technology

SE-412 96 Göteborg

Sweden

Telephone +46 (0)31-772 1000

Cover:

A picture of collaboration (Pixabay, 2015)

Chalmers Reproservice

Göteborg, Sweden 2015

i

ABSTRACT

This work was conducted at Volvo Group Trucks Operations (GTO) at Lindholmen,

Gothenburg.

Product development projects at Volvo Group Trucks have a tendency of being delayed. One

possible problem causing this effect is the lack of transparency between two departments

handling product development and production. This thesis investigates if an ICT-platform

could facilitate the communication and information flows, the use of IT-tools and project

processes in project work, which otherwise could hinder the collaboration between the two

departments.

The research was first conducted by a pre-study which focused on getting background

information of the different project processes and tools used by the departments. The acquired

knowledge was used to construct interview questions which were asked to employees at

Volvo working with the mentioned areas. The empirical findings from the interviews were

used in the analysis together with theory found in the literature study.

From the analysis several improvement areas were found and categorized as: communication,

documentation, knowledge, resources and gates. Several improvement areas showed that they

could be supported by an ICT-solution, but some areas was found to hinder the

implementation of an ICT-platform. Due to the limitation of the project the authors of this

thesis could not say in what extent the improvement areas were affecting other departments at

the company.

Keywords: ICT, project, standardization, process

ii

SAMMANFATTNING

Det här arbetet genomfördes på Volvo Group Trucks Operations (GTO) på Lindholmen i

Göteborg.

Produktutvecklingsprojekt inom Volvo Group Trucks har en tendens att försenas. Ett möjligt

problem som orsakar den här effekten är bristen på transparens mellan två avdelningar som

hanterar produktutveckling och produktion. Det här examensarbetet undersöker om en ICT-

plattform kan underlätta kommunikationen, informationsflödet, användningen av IT-verktyg

och projektprocesser i projektarbeten, som annars skulle kunna hindra samarbetet mellan de

två avdelningarna.

Undersökningen genomfördes först genom en förstudie som fokuserade på att få

bakgrundsinformation om de olika projektprocesserna och verktygen som används av

avdelningarna. Den förvärvade kunskapen användes för att konstruera intervjufrågor som

ställdes till de anställda på Volvo, som arbetar med de nämnda områdena. De empiriska

resultaten från intervjuerna användes i analysen tillsammans med teorin från litteraturstudien.

Genom analysen kunde flera förbättringsområden konstateras och kategoriseras som:

kommunikation, dokumentation, kunskap, resurser och ”gates”. Flera förbättringsområden

visades att de skulle kunna stödjas av en ICT-lösning, medan det konstaterades att vissa

områden skulle hindra tillämpningen av en ICT-plattform. På grund av arbetets avgränsning

kan författarna till denna studie inte säga i vilken utsträckning förbättringsområdena påverkar

andra avdelningar på företaget.

Nyckelord: ICT, projekt, standardisering, process

iii

PREFACE

This work was partially supported by the Know4Car project, grant agreement number

284602, funded by the EC Seventh Framework Programme theme FoF-ICT-2011.7.4.

ACKNOWLEDGEMENT

There are several people we like to acknowledge that helped us during our thesis work. First

of all, we would like to thank our supervisors at Volvo Group Trucks, Pierre Johansson and

Atieh Hanna, for their supporting roles and all their input and feedback throughout our thesis

work.

We would also like to thank our examiner Åsa Fasth-Berglund and supervisor Magnus

Åkerman at Chalmers University of Technology, who have helped us greatly with structuring

our thesis and given advice on how to proceed with the project.

We are deeply grateful for all eleven anonymous interviewees for have taken the time and

answering our questions. Without them we would never had acquired the knowledge to

complete this thesis.

Last but not least, we would like to thank Volvo Group Truck Operation for the opportunity to

conduct our master thesis within their organization, as well as the whole group at the office

who made us feel welcomed.

Gothenburg, June 2015

Regards,

David and Johan

iv

ABBREVIATIONS

Ad-hoc – “Created or done for a particular purpose” (Oxford dictionary)

CPM – Chief Project Manager

DFA – Design For Assembly

DVP – Develop Product and Aftermarket Product Portfolio

GTO – Group Trucks Operations

GTT – Group Trucks Technology

ICT – Information Communication Technology

ICT-platform – Several ICT-solutions that cooperates

ICT-solution – A function that facilitates one project area

ILG – Industrial Launch Group

JSON – JavaScript Object Notation

K4C – Know4Car

OBS – Organizational Breakdown Structure

PAP – Project Assurance Plan

PGT – Project Governance Tool

PM – Project Manager

PMR – Product Modification Request

PSM – Project Steering Model

PTM – Project Time Management

QDCF – Quality, Delivery, Cost and Feature

RBS – Resource Breakdown Structure

SC – Steering Committee

STP – Standard Time Plan

WBS – Work Breakdown Structure

White-book – Summary of a completed project, including lessons learned

XML – Extensible Markup Language

TABLE OF CONTENTS 1. Introduction .......................................................................................................................... 1

1.1 Background ....................................................................................................................... 1

1.2 Know4Car ......................................................................................................................... 2

1.3 Problem Definition ........................................................................................................... 2

1.4 Purpose ............................................................................................................................. 2

1.5 Research Questions........................................................................................................... 3

1.6 Limitations ........................................................................................................................ 3

2. Method ................................................................................................................................... 4

2.1 Methodology ..................................................................................................................... 4

2.2 Pre-study ........................................................................................................................... 5

2.3 Literature study ................................................................................................................. 5

2.4 Interviews ......................................................................................................................... 6

2.5 Analysis ............................................................................................................................ 8

2.6 Repeatability ..................................................................................................................... 8

2.7 Validation ......................................................................................................................... 8

3. Theory ................................................................................................................................... 9

3.1 Product development and production interface ................................................................ 9

3.2 Project ............................................................................................................................... 9

3.2.1 Project Management ................................................................................................ 10

3.2.2 Stage-Gate ................................................................................................................ 15

3.3 ICT/Collaboration network ............................................................................................. 17

3.4 Change Management ...................................................................................................... 18

4. Empirical Findings ............................................................................................................. 20

4.1 Current Process and Tools at Volvo ............................................................................... 20

4.1.1 DVP .......................................................................................................................... 20

4.1.2 PAP and PGT ........................................................................................................... 21

4.1.3 PSM .......................................................................................................................... 21

4.1.4 Time Plans ............................................................................................................... 22

4.1.5 Communication and Documentation ....................................................................... 22

4.2 A General Concept of Project Work in a Start Cost Project .......................................... 23

4.3 Improvement areas ......................................................................................................... 25

4.3.1 Communication ........................................................................................................ 25

4.3.2 Documentation ......................................................................................................... 26

1

4.3.3 Knowledge ............................................................................................................... 27

4.3.4 Resources ................................................................................................................. 27

4.3.5 Gates ........................................................................................................................ 28

5. Analysis ............................................................................................................................... 29

Communication .................................................................................................................... 29

Documentation...................................................................................................................... 29

Knowledge ............................................................................................................................ 30

Resources .............................................................................................................................. 31

Gates ..................................................................................................................................... 31

6. Discussion ............................................................................................................................ 32

6.1 Further work ................................................................................................................... 34

7. Conclusion ........................................................................................................................... 35

References ............................................................................................................................... 36

Appendix A ................................................................................................................................ I

Communication ....................................................................................................................... I

Documentation...................................................................................................................... III

Knowledge ............................................................................................................................ VI

Resources ........................................................................................................................... VIII

Gates ...................................................................................................................................... X

Appendix B.............................................................................................................................. XI

Appendix C ............................................................................................................................. XI

Appendix D ........................................................................................................................... XII

1

1. INTRODUCTION

The introduction chapter includes a background of the company which includes the current

state at the company and a general description of the theory surrounding the problem

definition. A short background information about the origin of this thesis will be brought up

in chapter 1.2. The problem definition brings up the current problem and then the purpose

chapter describes why the chosen methods have been used. After chapter 1.4, the research

questions narrow down the research field to end up with the aim of this paper. The last

chapter limitation includes both limitations and delimitations.

1.1 Background The project was conducted at Volvo Group Trucks Operations (GTO) at Lindholmen,

Gothenburg. GTO is a department under Volvo Group Global. The Volvo Group employs

around 100,000 people and is a world leader in trucks, busses, industrial and marine engines

and construction equipment. GTO handles the production of engines, transmissions, spare

parts and vehicles for Volvo Group Trucks. This also includes managing the process changes

in the production.

GTO follows a certain flow when working on a project which is called Project Steering Model

(PSM). PSM helps steer the project towards important activities that are executed in the right

order, open gates and complete the project. There are several factors that can activate a

production project; optimization of a process, improvement of work ergonomics and product

changes.

Product development and changes are handled by Group Trucks Technology (GTT). GTT

preforms research in product development, product planning and support products in the

aftermarket. At the moment, GTT has a project model called “Develop Product and

Aftermarket Product Portfolio” (DVP). The process of handling a project in a product development environment is documented in the DVP-Handbook. The handbook describes the

principles and different activities on how to handle product development projects. The cross-

functionality between GTT and GTO is a well discussed subject at Volvo Group Trucks both

concerning projects and assignments. The focus on this thesis is on how the project work at

GTO and GTT is preformed and also the correlation between the two departments in product

development projects.

How well a communication and information flow between the two departments determines

the quality of the product and how fast the product can go into production (Bellgran &

Säfsten, 2010).

One way of supporting the information and communication flow is by using an ICT-platform

(Information Communication Technology), ICT-solutions can help speed up the product

project, increase the efficiency between engineering and design, and increase the

collaboration in an organization (Camarinha-Matos, Afsarmanesh, Ollus 2008).

This thesis will investigate how and if an ICT-platform can support the structured project

work and information flow between GTT and GTO. The aim of this thesis is to see if an ICT-

platform can support process/activities and visualized information channels to increase the

efficiency and transparency of project work. This master thesis originates from the project

2

Know4Car (K4C) which is an EU initiative to increase the collaboration between companies.

The chapter below gives further information about the K4C project.

1.2 Know4Car Know4Car is a project which involves several

companies and institutions, supported by EU,

who are developing an Internet based tool (ICT-

platform) for managing manufacturing

knowledge. Focus lies on collaboration between

product, production and suppliers. The aim of

K4C is to be user friendly where the right

knowledge easily can flow between internal and

external stakeholders. See Figure 1.1.

1.3 Problem Definition The transparency and collaboration between GTT and GTO is known to be a problem when

working in product development projects. These problems sometimes result in product

projects being delayed. This is not supported by the principles that should be followed in a

product project.

One transparency problem is that GTO generally finds that they are getting hands-on

information too late when working in product development projects and that it is hard to get

hold of this information by their own. At the current state, it is the project manager at GTO

that has deeper knowledge on the activities that are being carried out in a product

development project. Employees at GTO need to go through their manager to retrieve this

information. This thesis strives to find a solution to make the interface between GTT and

GTO more transparent and increase the collaboration.

1.4 Purpose The purpose of this thesis is to investigate and document the practical project work, including

communication and data flows. The documentation will then be used to identify improvement

areas. These improvement areas will be the foundation when trying to determine if an ICT-

platform can be implemented and assist project work at Volvo Group Trucks.

Figure 1.1 Know4Car Circle.

(Know4Car consortium, 2015)

3

1.5 Research Questions Three research questions were prepared to help approach the project, they are presented in

Table 1.1. Below each research question is a brief explanation of why the areas were

investigated. The last three columns show how the research questions were answered.

Table 1.1 Research Questions

RQ# Research question Pre-study Interviews Theory

RQ1 How is practical project work carried out at

GTO and GTT?

Due to the size of both GTO and GTT the

research will only result in a general

understanding of how project work is carried

out. Some areas are more researched to find

where and how project information is

communicated.

x

x

RQ2 How is information communicated between

GTO and GTT in project work?

From RQ1 not all communication is

documented, but the documented

communication will be analyzed and compared

with theory to build a firm base that can be

elaborated to support an ICT-solution.

x

x

RQ3 How can an ICT-solution support project

work and collaboration at GTO and GTT?

Theory from the literature study on the

advantages from an ICT-platform will be

compared with the analysis of the improvement

areas at Volvo.

x

1.6 Limitations The total time for the project was 20 weeks. Due to the short time span, a complete

observation of all branches in the organization and interactions within product and production

development could not be documented. Therefore the ICT-solution will cover ad-hoc

functions which help the collaboration between product development and production. We are

aware that product documentation (e.g. CAD files, simulation results, engineering reports,

applicable variant combination, etc.) is an important part of the project work and the

communication between GTT and GTO, but this has been excluded from our scope.

4

2. METHOD

In the method chapter the methodology that was used will be explained, the chapter will also

cover how the different methods were used.

The different method used and in which order is illustrated in Figure 2.1.

2.1 Methodology The chosen methodology was developed over time with the underlying research questions in

mind.

The project was conducted through an inductive qualitative research. Inductive research was

chosen over deductive research to find out if the problem is an anomaly at Volvo. To do this,

the improvement areas were inductively researched. This means that the results were verified

with theory. A deductive approach would do the opposite, verify the theory or a hypothesis if

it is applicable to the real world. The difference is illustrated in the picture below. (Bryman &

Bell, 2003)

Figure 2.2 Difference between inductive and deductive reasoning

A quantitative approach was not chosen because it only answers the problem from an

objective stand point (Bryman & Bell, 2003). This thesis tries to determine how the practical

work is carried out. Therefore a qualitative approach was more suitable.

Figure 2.1 Method precedence chart

Pre-study Literature

Study Interviews Analysis

Comparing

results with

ICT theory

5

The empirical findings from the pre-study and the interviews were analyzed to find patterns

and compared with theoretical findings.

2.2 Pre-study In order to understand the current situation at Volvo Group Trucks a pre-study was conducted

to study the areas which would be or could be affected by implementing an ICT-platform. The

article from (Orlikowski, 1992) argues that a pre-study has to be performed. If a study is

underestimating the current situation at a company, it may result in an incomplete prerequisite

for an implementation of an ICT-platform.

The current project processes at GTT and GTO were studied which are called DVP and PSM

respectively. The study consisted of reading the manuals for both DVP and PSM, this

included research in the Project Assurance Plan (PAP), Project governance tool (PGT) and

Standard time plan (STP). To collect more information and understand the structure of K4C a

presentation was held by the developers of the platform. A project plan was coded with the

JSON format, which is based on XML, partly to obtain practical knowledge on how an ICT-

platform could be used and also how it can be structured. The project plan was then imported

into the K4C-platform. A simulation was done of the project plan preformed from the CPM

(Chief Project Manager) perspective. First, the project plan was implemented and the right

expertise (engineers, reviewers and Project Managers (PM)) was dedicated to each activity in

the project plan. The project plan was then sent out to a virtual PM who appointed resources

to each activity; the resources had to have the right expertise to be appointed to the activity.

2.3 Literature study A literature study was conducted in two phases, in the pre-study and while performing the

analysis. The first of the two can be read in chapter 2.2. The later was made to get up to date

knowledge of the subject investigated and to help with the analysis of the data collected.

6

2.4 Interviews The interviews were conducted through semi-structured interviews. In most cases the

interviews were audio recorded and after each interview the recordings were transcribed.

Semi-structured interviews were chosen over structured interviews, this was made in order to

get more subjective answers and in turn get more information on what the interviewee thought

was important in the surrounding areas of the questions (Bryman & Bell, 2003). A structured

interview was not chosen because it aims only to answer the question asked and the

interviewee is not allowed to talk about other concerns (Bryman & Bell, 2003). This resulted

in two problems. First, the interviews were conducted to get a general understanding of how

project work is carried out at different positions at GTO and GTT, including problems that

concern the interviewees in their daily work. Secondly, when the interviews were constructed

the interviewers did not have enough experience to construct aimed questions. It could be

argued that the last interviews were more tilted towards structured interviews than they were

in the beginning. An explanation of why it was structured like this can be found later in this

chapter.

After the recordings had been transcribed they were deleted according to the agreement set by

the interviewers and the interviewees. A total of eleven persons were interviewed at ten

different occasions. The interviewees’ positions, occupancy and organization can be seen in

Table 2.1.

Table 2.1 Interviewees

Nr. Occupancy Position Organization

1 Quality assurance PM GTT

2 Project PM GTO PM GTO

3 Project PM PM GTO

3 Project Portfolio Coordination Engineer GTO

4 Cross-Functional Coordinator

(Commodity, Product) PM GTT

5 Project (Commodity) PM PM GTT

6 STP – Time Planning PM GTT

7 Tooling PM GTO

8 Intro Engineer PM GTO

9 Technical Designer Engineer GTT

10 Technical Preparation Engineer GTO

11 PTM CPM GTT

7

In Figure 2.3 an organization chart visualizes which departments that were interviewed (red

boxes), the red line is the communication channeled between GTT-chassis and GTO. A more

elaborated chart can be found in Appendix B.

Figure 2.3 Visualization of the interviewed departments

The communication between GTT-design and GTO and the internal communication studied

can be seen in Figure 2.4 below. The red marked communications are external

communications from GTO, The blue and black lines are internal communications that were

documented. The non-filled boxes are departments that have not been interviewed, which

makes the communication path only verified by one partner.

Figure 2.4 Internal communication at GTO including external communication

The interview questions were adapted to the specific occupation and position of the

interviewee. In appendix D the general questions can be found. These were different for

interview sessions six and ten. This was due to the information gathered consisted of

background information and deeper knowledge of how the Standard Time Plans (STP) were

used and how a new Project Time Management (PTM) program worked. After each interview

a walkthrough of the questions were performed to estimate how well they worked, which in

8

some cases lead to minor changes. The alterations mostly consisted of collecting more

information about a specific subject or clarifying the questions. As stated earlier, these

questions could be seen as structured, still the interviews were conducted in a semi-

constructed manner.

2.5 Analysis When all interviews had been conducted two areas were separated: general project work and

improvement areas. General project work is presented in chapter 4.1 and 4.2 in the Empirical

Findings chapter improvement areas can be viewed in chapter 4.3. The general project work is

a combination of the pre-study and information collected in the interviews and answers of

RQ1 and RQ2.

Improvement areas were found through the interviews where problems or concerns was

brought up by interviewees and then put into an excel sheet. Each improvement area was

labeled into five categories and merged into a second excel sheet, see Appendix A. The

categories were: Communication, Documentation, Knowledge, Resources and Gates. In the

chapter 4.3 Improvement Areas in Empirical Findings, improvement areas that resembled

each other or were identical were merged into one single problem. In the analysis the root

causes are investigated with help of the theory found in the literature study. At last, the

improvement areas validated by theory were compared with the advantages of an ICT-

platform, see Figure 2.5. This was done to find out if an ICT-solution was applicable to the

improvement area, which also answers RQ3. In the discussion chapter, comparisons between

applicable ICT-solutions and the prerequisites for an ICT-platform are discussed.

2.6 Repeatability The empirical data collection was performed with interviews and literature studies on the

current state at Volvo. Two concerns are brought up on the repeatability of this thesis results.

Firstly, the system is dynamic, changes are made in the organization and work procedures

may change, which have an effect on the result if the study is to be repeated. Secondly, the

people that were interviewed could have been affected by the interviewers like tone of voice

or follow-up questions. If then another person would have interviewed them the answers

could look different.

2.7 Validation The empirical findings was gathered with scientific methods and then validated with theory

found in the literature study.

Results Analysis ICT

Theory

ompare

ompareup

port

Figure 2.5 Comparing results with the theory of ICT

9

3. THEORY

The theory chapter addresses the necessary theoretical framework to answer the research

questions.

The theory found consists of (in order as they are represented); the interface between product

and production, information about general projects, project management and the affecting

management issues surrounding the improvement areas, the advantages and disadvantages of

having an ICT-platform. The chapter ends with a theoretical chapter about change

management. The project and management theory is from the book (PMI, 2013) which the

DVP is based on.

3.1 Product development and production interface A common characteristic for companies that have product development and production is the

de-coupling of the two areas, which is done to minimize certain risks but may lead to

integration issues. Earlier research has shown that cultural, geographic and organizational

barriers have an impact on the interface between product development and production. This

tends to make projects miss the target time plan where production start-up is pushed forward

in time with other resulting problems i.e. rework of the design. Results from earlier research

show that by improving the formalization, the understanding between product development

and production will gain a smoother production start-up. Formalization may be both

organizational i.e. having clear goals and giving roles and responsibilities to the right person,

as well as having a standardized way of working and the use of formal documents.

(Vandelvelde, 2003)

3.2 Project The fundamentals of having a project model is to acquire a structured and organized work

flow and by this capture important areas, variables and key functions that otherwise would

have been overlooked. Each project, if finished, results with a unique product or service. A

standardized project model will help achieve higher efficiency with work methods that are

developed to be more effective and still support the flexibility to achieve a unique product.

The flexibility of a project decreases over time where risks and uncertainty are high in the

beginning of the project phase but will later decrease. This correlates with the cost of change,

which increases with the total project time and thus the flexibility. This is illustrated in Figure

3.1. (PMI, 2013)

10

Figure 3.1 How uncertainty correlates with cost of changes (PMI, 2013)

A project can be standardized and efficient but it is also important to standardize how the

handling of project results and how communication with other projects and organizations are

managed. Lack of documentation and communication will result in important parts will

misplaced. It is up to the manager to lead the project to success. The different parts described

in the next chapter will highlight what makes a good project and how it should be managed

(PMI, 2013).

3.2.1 Project Management

Project management is seen as several areas that affect the project, see Figure 3.2 (Rosenau &

Githens, 2005). When a project is failing it is usually because one or several of these areas is

not fully covered.

Figure 3.2 Fundamental areas in project management

(Rosenau, Githens, 2005)

11

(Rosenau & Githens, 2005) mentions three common problems that occur when working in

projects:

Most product failure is at the interface of subsystems, and individual contributors

typically do not pay attention to interfaces until after they have completed most of

their work on their assigned piece of the system.

Time and again, the biggest complaint of people in projects is poor communication.

Senior managers expect project managers to manage projects as if they were a

business, taking a strategic and holistic perspective on the project.

A successful project can be many things from how well deliverables were met, customer

satisfaction amongst other. But what makes a project successful is how the different areas

were handled and balanced between each other. The paragraphs below will bring up

suggestions on how to handle these areas in order to make the project successful, all areas will

not be fully covered such as risk and procurement. (Rosenau & Githens, 2005)

Scope Management

The amount of work that is needed to complete a project is defined in the scope. This also

includes goals, constraints and limitations of the project. With a clearer goal early in the

planning of the scope, it is easier to foresee each activity and the requirements of the project

(PMI, 2013). When the scope has been defined, the deliverables can be described in detail and

visualized as a work breakdown structure (WBS). The WBS can be made in several different

ways, e.g. a precedence diagram can be used to see all deliverables in a logical order or a

hierarchical diagram where activities are portrayed in a top-down approach. A general work

breakdown structure with a top-down approach consists of four levels where the highest level

is the project itself and then is broken down into deliverables of major components. The third

level is more detailed and consists of sub-deliverables and the fourth and last are specific

activities or work packages that needs to be performed, see Figure 3.3.

Figure 3.3 Work breakdown structure (WBS)

12

Communication

Communication is often subjective and a complex process. When working in a project it is

important that the messenger is as objective and neutral as possible, that the receiver can

translate what has been said without the sender’s or receiver’s personal thoughts affecting the

message. (Ying & Pheng, 2014)

When a message is sent, the sender encodes the message and sends it over a medium, the

message will be affected by noise. The noise can corrupt the message and alter its purpose.

Another factor that can affect the message is when the receiver tries to decode the message.

The messages meaning can affect the translation for the receiver, this communication is called

one-way communication and is illustrated in Figure 3.4. (Ying & Pheng, 2014)

Figure 3.4 One-way communication (Ying & Pheng, 2014)

In two-way communication there is a higher chance that the receiver understands the

message. The communication is viewed as a process where sender and receiver are

exchanging information where both are active and receive feedback from each other during

the communication period. The feedback acknowledges that the receiver has understood the

message by communicating back to the sender. The process can be viewed in the Figure 3.5.

In an organization the communication is often restricted to certain formats by the manager,

this has a tendency to form how communication is sent and received. These formats of

communication are debated, they do not take in aspect of how well the sender can distribute

the message. (Ying & Pheng, 2014)

Figure 3.5 Two-way communication (Ying & Pheng, 2014)

13

For an organization to work properly it must be transparent for all stakeholders in the

organization. If this is not the case, different parties will find their own communication

channels, which will make it hard for the organization to effectively monitor the information

flow. Organizations do not generally have a platform for which different stakeholders can

communicate and this makes it even harder for stakeholders with different interest to

collaborate. The effect of this is that the organization will lose control of what information is

sent. Without understanding the information sent through the organization it is hard to control

what is being sent and in turn how this is interpreted. (Ying & Pheng, 2014)

When a project lacks of poor communication it could be for several reasons. As has been

mentioned before, modern technique with people trying to communicate with computers can

be problematic if the message is interpreted differently than what it was intended. Eye-to-eye

contact usually facilitates this issue. Another example may be that people are unwilling to

share their information and sees it as a source of power. It could also depend on people not

knowing the structures within the project or cross-functional problems where technical

language is not perceived properly in other departments. (Pinto, 2007)

Information and Knowledge management

When handling information in projects it could either be structured data or unstructured data.

If the data is structured it can be stored in rows and columns and if it is unstructured it could

be different files like pdf’s or emails. When data is unstructured it cannot be stored in a

database in the same manner as structured data can, which leads to difficulties when trying to

retrieve it due to the complexity of identifying the data itself. Project management data is

usually unstructured and saved on a network based platform. (Eds. Somasundaram &

Shrivastava, 2009)

To make this data easy to find there should be standardized guidelines and work instructions

on how to store this on the platform. During a project, the ability to update documents is a key

feature that will facilitate the work. When a document is updated, a notification system should

be implemented so that all the stakeholders know an update has been made. (PMI, 2013)

The maturity level of the project management shows how standardized and structured a

company is when working in projects. Higher level gives a higher degree of standardization.

This could be used as a measurement for companies that want to benchmark its level of

standardization. (Pinto, 2007)

Knowledge management is a factor in global companies to execute successful projects.

Knowledge could be described as data that has been processed by people with experience and

is useful for others in a company. To make use of the acquired knowledge in later projects, a

knowledge database should be established, known as lessons learned log. Knowledge is

usually divided into explicit knowledge, which is formal knowledge of different subjects.

Tacit knowledge on the other hand is knowledge combined with experience and hard to

transfer between people. According to earlier research, knowledge management can be

described as the four processes seen in Table 3.1. A company that has several projects in its

organization triggers different mechanisms depending on what the project incorporates. The

mechanisms can be facilitated with different technologies as can be seen from Table 3.1.

(Becerra-Fernandez, 2006)

14

Table 3.1 Four processes in knowledge management (Becerra-Fernandez, 2006)

Processes Examples of Mechanisms Examples of Technology

Discover new knowledge -Meetings

-Collaborative creation of

documents.

-Video-conferencing

-Databases

Capture existing knowledge -Prototypes

-Learning by doing.

-Lessons learned log database

-Computer-based

communication

Share knowledge with others -Presentations

-Manuals.

-Expertise locator system

-Web-based access to data

Apply knowledge -Hierarchical relationship

in organizations

-Support centers.

-Resource planning system

-Decision support system

In a cross-functional global company, ICT is competent to share knowledge and information

as long as it is easily accessed and updated regularly. This will be further elaborated in

chapter 3.3. (Coakes, 2006)

Resources

Resource management includes how the project team is managed. People with varied

expertise are assigned roles, authorities, responsibilities and competences and the amount of

time one set off to the project. Resources can be replaced while the project is in progress at

any time, but it is beneficial to have the same team as early and as long as possible during

project execution. When a project team is put together, there needs to be team members with

different background. It is also beneficial to have a project leader that has a certain amount of

experience from earlier projects.

There are different tools available when managing the resources. When planning a project a

hierarchical-type chart could be used. This shows the organization in a structure chart, which

gives a holistic view of the teams and the relationships in between. Each box with several

project members could be seen as a group. When a Work Breakdown Structure (WBS) has

been made to show the project deliverables, an Organizational Breakdown Structure (OBS)

could be made as seen in Figure 3.6. This is used to show the deliverables each department

and teams are responsible for. Then there is a Resource Breakdown Structure (RBS) which is

a hierarchical list of resources including a detailed description of each resource. This can be

connected with the WBS and facilitate planning, monitoring and managing costs. Another

type of chart is the Responsibility Assignment Matrix (RAM). This takes all the activities into

account and connects them to each resource in a matrix based chart. (PMI, 2013)

15

Figure 3.6 Organizational Breakdown Structure (OBS) in a project

Due to people having different chemistry among each other, conflicts are inevitable. How

successful a project manager is when managing the project often depends on their ability to

resolve conflicts. There are five different techniques for resolving conflicts that project

managers or project members could use (PMI, 2013):

Avoid

Accommodate

Reconcile

Force

Collaborate

The conflict may be resolved with the techniques but the core problem may still persist. If

there are personnel problems that cannot be solved with the techniques, the project manager

preferably needs to have argumentation convince top management that some of the personnel

need to be replaced. (Pinto, 2007)

3.2.2 Stage-Gate

Around the late 1980s and the early 1990s a new concept was needed to handle the new

paradigm shift for the commercial product development. Before the 1990s there was no need

of fast development of products, but in the 1990s this changed. The market demanded higher

customization and more variations of products. One model that emerged was the Stage-Gate

model (Cooper, 1990). The Stage-Gate model has different stages were specific activities are

being carried out by all stakeholders, after each stage there is a gate. The purpose of the gates

is to check that all deliverables have been completed and that the project can proceed into a

new development stage, see Figure 3.7. The idea is to include resources in the beginning of

the project to minimize the increased cost of a fundamental change later in the project

(Anderson, 1993). In the earlier phases managers review the progress of the project and at

each gate grant more funds to the project if the criteria’s are fulfilled.

16

One successful adaptation of the Stage-Gate method was done by the companies Corning

Glass and Nortel Networks. Corning Glass had a difficult time during the IT-crash in the

1990s, they did not have continuous product development and had lived on one innovation at

a time. They adapted the Stage-Gate model on top of how they successfully developed

products earlier. The different stages Corning Glass brought forward can be seen in Table 3.2

(Stage-Gate product development, 2012)

Table 3.2 Description of the different stages in the Stage-Gate model

Stage Process

0 Discovery of new opportunities including the development of product ideas by the

project management team.

1

Scoping through a basic evaluation and assessment of the marketability of a new

product idea. Product ideas are assessed based on known competition and the

product's competitive advantage.

2

Developing a business case based on careful research that details why a product

will succeed. During this stage the product is defined, milestones are established

and each department assesses the product's feasibility.

3 Development focuses on the product design and the development of prototypes.

4

Testing and validation, both in house and in the field with consumers. Trial sales

efforts are conducted to measure both the product's functional and market

performance.

5 Product launch.

The Stage-Gate model has since been further developed and implemented in different

companies e.g. Volvo Group Trucks with their product development process, DVP. How

many gates there are and what type of stages depend on the company’s development process

(Anderson, 1993). By adopting the Stage-Gate model, companies aim at lower development

cost and to get products faster on the market (Anderson, 1993).

Through the years the Stage-Gate model have been modified to help overcome some of the

criticism that has been directed towards it. (Grönlund, et al., 2010) states them as following:

Stage 4 Gate Stage 3 Stage 2 Stage 1 Gate Gate

Figur 3.7 Stage-Gate model

17

Time-consuming, resulting in timewasting activities

Bureaucratic procedures

No provision for focus

Restriction of learning opportunities

The four presented issues could occur in a Stage-Gate model.

3.3 ICT/Collaboration network ICT stands for information communication technology and is a concept on how information

and communication management can be facilitated.

Different concepts are used to achieve more efficient development projects, such as

restructure of the organizations, project models and management tools. The idea with ICT is

that it tries to merge the different concepts. It can be a management tool but also a platform

for other means such as communication and data sharing, for example extend collaboration

between countries and organizations for educational purposes (Khakhar, et al., 2007).

This chapter will highlight the ICT concept adapted for manufacturing companies where great

advantages can be made with a well-functioning ICT-solution. The concept of ICT and what it

tries to accomplish reflects what internet has to offer; collaboration and flexibility with shared

resources (people and data) and openness.

One aspect that differentiates the two areas is the view on communication. Internet is based

on horizontal communication, which means that there is no hierarchical structure, meanwhile

ICT solutions have a tendency to use both horizontal and hierarchical communication (Duque,

et al., 2007).

Manufacturing companies are expecting that they need to develop technologies such as ICT-

platforms in the upcoming future to help them stay competitive on the market. (Marco,

Montorio, 2007)

(Camarinha-Matos, Afsarmanesh, Ollus, 2008) addresses what manufacturing companies can

gain from an ICT-solution with a collaborative network. Customers in the list below can be

interpreted as different stakeholders at different departments in a project:

Business partners can quickly and easily get together to benefit from a business

opportunity, fulfill the need and then disclose the collaboration.

Increasing applications in early stages of product life cycle, speeding up and giving

more efficiency to engineering and design.

Increased customer collaboration and logistics enhance market understanding and

reduce delivery times and times to market.

Customer collaboration in after delivery networks enables new form of support

activities over the life-cycle of the delivered product or service.

Efficiency relies on capability for companies to co-operate despite different

infrastructures, business cultures, organizational forms, and languages, legal or fiscal

systems.

Business networks themselves continuously change.

18

To accomplish the effects mentioned above there are several criterias that need to be met to

build a firm base which an ICT-solution can stand on. Much of the research in ICT has

surrounded areas with ad-hoc solutions, meanwhile the understanding of collaborative

research has been missed. The collaboration is often surrounded by architectural flaws in most

systems, where several different tools or software are used, several different communication

channels and differences between organizations, makes it hard to implement an ICT-platform.

To effectively establish a base for an ICT-platform, the different infrastructure needs to be

customized to fit into a coherent platform. This customization requires highly skilled

engineers who have knowledge in applications. (Camarinha-Matos, Afsarmanesh, Ollus,

2008)

(Rabelo, 2008) states the following three preconditions have to be set to be able to implement

an ICT-platform.

1. Requires collaboration among involved partners that does not only involve sending e-

mail messages.

2. The existence of trust, considering that partners shall rely on each other (at all levels).

3. All (or most) of the activities carried out within a collaborative network organization

should be made via computer networks, i.e. digital transactions should be the routine,

and not an exception.

(Rabelo, 2008) also states that organizations need to be transparent and adaptive to facilitate

the implementation of a communication and information channel in the current state of the

organization. By having all of the mentioned requirements, people using the ICT-platform

will see it as a must have and not as an optional tool. To complement the technology of the

ICT-platform, the platform requires powerful computer power and high internal and external

security.

In chapter 3.2.1 four processes were mentioned and to have the most efficient use of

knowledge in a company, all four of these processes should be managed efficiently. An ICT-

platform would greatly facilitate knowledge management in a company. If the platform has

embraced all four of the processes it will be a more standardized way of working. Explicit

knowledge can be managed with structured databases, and tacit knowledge can be managed

by socialization like meetings and video conferencing. Although a platform that manages tacit

knowledge is hard to implement due to the difficulties of documenting experience. (Becerra-

Fernandez, 2006)

When a company has implemented an ICT-platform there are both positive and negative sides

when it comes to conflict management. A case study (Correia, 2008) has shown that an ICT-

platform facilitated conflict management by having an effective and formal way of

communicating. On the other hand the ICT could also aggravate conflict due to different

personalities of the communication participants, where misinterpretations could occur.

3.4 Change Management If a new work method or technology is implemented in a company, people are the primary

factor in either success or failure in achieving the change. If people are positive to the change

it is easier to implement, but if they do not support the change, it could be due to several

causes.

19

(Suran, 2015) mentions three important factors on how to implement change successfully.

First the company needs to have a clearly defined strategy of why a change is necessary and

that it is understood by all departments and teams. If the strategy is not communicated well

people tend to fear the unknown of what consequence the changes may bring for themselves.

Another factor mentioned is to have an effective organizational structure. If a company has its

organization divided into teams, competitive attitude may grow between them which may

prevent sharing information. The third and last factor mentioned is to have effective processes

and communication processes. This leads to trust among the employees towards the

management because the process assures a consideration of their ideas for different changes.

If a company has met the three factors, the next mission is to get employees to accept the

change. Convincing employees may be hard, but if the right information is communicated in a

way that benefits the company and workers are inspired, the change will be easier to

implement. It is also important to listen to the employees and let them test the new changes in

a real situation and then let them make suggestions on how the change can be more effective

in their daily work. Furthermore it is important that top management shows a specific way of

how the change will be implemented that everyone understands. Factors to successfully

implement change and how to achieve employee acceptance of change, is summarized in the

lists below. (Suran, 2015)

Factors to successfully implement change

1. Clearly defined and communicated strategies.

2. Effective organizational structure.

3. Effective processes, including communication processes.

How to achieve employee acceptance of change

1. Convince employees of the need for change.

2. Listen to employee concerns and needs.

3. Involve employees in the development of the change.

4. Communicate the implementation plan.

20

4. EMPIRICAL FINDINGS

As explained in the method chapter the results will be divided into two groups. The first part

presents the current state at Volvo and the tools used can be found in Appendix C. This

includes how people communicate in projects and a generalized summary of how a product

development project would be carried out at Volvo Group Trucks. The second part of this

chapter consists of improvement areas which are divided into five parts; Communication,

Documentation, Knowledge, Resources and Gates.

4.1 Current Process and Tools at Volvo There is a range of different project types at Volvo besides the product development projects.

Generally a large product development project is called Start cost project.

Start cost projects has four different scales A, B, C and D. Scale A has the longest lead time

and scale C has the shortest. Scale D is called Intro-block. The purpose of an Intro-block is to

bundle and prepare the production for the implementation of new product changes. The

product changes are implemented at specific dates and follow a specific time plan. The major

difference between a Start cost project and an Intro-block project is that the former is used

when developing a whole vehicle or powertrain and the latter is used when bundling a set of

product modification requests. Product Modification Request (PMR) is a project which is

issued by customer request; they are smaller than Start cost projects and are implemented in

the Intro-blocks.

The creation of a Start cost project can have several different triggers. It can either be based

upon customer demand or legislations. A reoccurring phenomenon while forming the project

is that it starts off with a requirement and during the process, new issues occur. New

technology is needed to be able to meet the requirements. Over time more problems are

detected which expands the scope of the project.

There are two kinds of quality notification and assembly systems that handle issues, called

System A and System B, see Appendix C. In general they are not regarded as projects but if

the issues affect the production or product at large they can initiate a project.

4.1.1 DVP

DVP (Develop Product and Aftermarket Product Portfolio) is the project model GTT follows.

This originates from the Stage-Gate model and is adapted for Volvo Group Trucks’s product development. Before the DVP, an older process was used called the GDP (Global

Development Process). Only recently started projects use DVP as a model, while older active

projects still uses the GDP. The DVP comes with a handbook that describes principles that the

management should follow like, quality assurance, cross-functional teams, how to plan the

project and prove the project is feasibility amongst other. The handbook also addresses all

aspects of a product development project like, starting a project, organization, planning, risk

management, decision making etc. The DVP is in close correlation with PGT, PAP and the

Standard Time Plan. A more detailed description of the three will be brought further down.

The amount of gates and stages depends on the particular project, how large it is and what it

21

Figure 4.1 Gate process

contains. A new initiative has been developed to increase resources in earlier stages of the

project. This initiative is called RnD30.

4.1.2 PAP and PGT

Project Assurance Plan (PAP) is a tool in projects that help state and review deliverables for

the gates, plan the next gate and view the project description to see if it meets the QDCF

principles (Quality, Delivery, Cost and Feature). The gate "process" is visualized in Figure

4.1. The deliverables are predefined at each gate in a template by the CPM and PMs, and the

amount deliverables varies with the different sizes of projects. The PAP also includes

documentation of project definition, project time plans and white books.

The Project Governance Tool (PGT) is a web based software connected to PAP and aids the

Steering committee (SC) in taking decision of opening gates or not. It also works like a gate

auditor to view the status of the project and project team where monitoring the progress and

information of what the next deliverable or agenda consists of. Only certain persons have

access to the projects PGT, this access is given by the CPM of the project.

4.1.3 PSM

The Project Steering Model (PSM) is a general project model, which is used for

industrialization changes in process and business projects carried out at Volvo Group Trucks

Operations. The model consists of a couple of different principles for example roles and

responsibility, documents and governance. Another important principle is the PSM Flow,

which is a flow chart showing phases and gates in a project. This helps the project team to

focus on a certain activity and assisting the steering committee to make important decisions at

a certain time. The earlier project process, GDP, had been successfully aligned with the PSM

process. When asked about the issue during the interviews, an example of how the GDP and

PSM could be aligned was showed. This has not been performed for the DVP, where the

explanation is that the DVP model is too new and not enough experience to construct an

alignment model.

22

4.1.4 Time Plans

What time plan to use depends on the grade of the Start cost project: A, B, C or D.

Start cost projects have one main time plan where all stakeholders are included. The time plan

is a template that gives all stakeholders a visualization of the whole project in form of a Gantt

chart. Start and end dates, gates, critical activities and stakeholders are highlighted in the

Gantt chart.

GTT has 4 levels of time plans and different responsibility areas as can be seen in Table 4.1.

Table 4.1 Time plan levels

Level Area Responsibility

1 Main Time Plan CPM

2 Commodity time plan PM

3 System/Module time plan Sub-PM

4 Component/Part time plan Team Leader

GTO does not follow the same levels of time plans as GTT, instead their PM creates a level 2

time plan to suit the main time plan (see chapter 4.1.3). The level 2 time plan is adapted to fit

both the DVP process and the PSM process. The different departments at GTO may construct

more levels of time plans but are not directly connected to the different levels of the main

time plan.

To create time plans, different tools are used depending on personal preferences. CPMs can

require PMs to use a specific scheduling tool for their level two and three time plan. Either

Microsoft Project or Excel is used. A new tool has been developed for handling standard time

plans and is called PTM (Project Time Management). This is an ICT-tool where each time

plan is linked, and when one is updated the other ones get notified. The one responsible for

the time plan can accept or decline the update. It is also supposed to help people in projects

that are not CPM or PM to have access to a web based visualization of the time plans and

their status.

4.1.5 Communication and Documentation

The communication at both GTO and GTT are performed through PGT, e-mail, Microsoft

Share Point, Lync, meetings and by phone. PGT is used in direct correlation with deliverables

and gates, where templates are stored at each activity that has to be done before certain dates.

E-mails are regularly sent for different reasons, often with unstructured data, where it can

vary from new emerging problems to sending new documents. Microsoft Share Point is the

main platform to store all the important project documents like project description, time plans

and organization charts. Lync is used both in online meetings and to send messages to

concerned people. How people interact and what tools people prefer to use for communicating

are up to each person or group. Closed projects and their descriptions, including white books

are saved in a database called System C, see Appendix C. Product changes are sent through

23

System F and affected production changes is sent through System E, see Appendix C. The

data is of structured nature in both systems.

At GTT Chassis, there is an ad-hoc manual for how to work in different roles and what

knowledge is needed for a role, but it has not been updated for years.

4.2 A General Concept of Project Work in a Start Cost Project This paragraph will highlight certain parts of a Start cost project. The whole organization or

all information in such project is not presented. What includes is the information about project

work gathered from the interviewees. Each of the interviewees has different tasks and method

while working. This concept has merged all interviews to try to visualize how the different

interviewees are connected. Figure 4.2 gives a general illustration of how the different

information and communication flows between GTT and GTO are connected.

Figure 4.2 Information and communication flows between GTT and GTO

Product planning generates a Start cost project based on customer demand. Product planning

then sends out prerequisites of the product to the CPM. The CPM then gathers PMs on the

different departments that are affected by the project and a concept is developed to meet the

specifications of the product. Each department then creates a business case, to calculate the

cost and then sends it to the finance department. If the product change is financially viable the

request is accepted.

24

The business case results in demands from the stakeholders e.g. production (GTO) and

aftermarket. The demands are distributed via PGT and are discussed through meetings. The

demands defines the product's shape and attributes, this is necessary for different reasons and

depends on who the demands originate from. It could be GTO who wants the product to be

easy to assemble, it is then up to the GTO PM to collect information from relevant actors

within GTO and bring it to the CPM of the Start cost project. Each factory does not have the

same production requirement which leads to different demands. This is where intro engineers’ helps with the merging of the demands to fit a common tool and production system.

The CPM structures the standard time plan to fit this particular project and in turn sends the

time plan to affected PMs, who then create a level 2 time plan. The time plans are discussed at

meetings, in some cases a physical time plan is saved on a whiteboard. In the earlier stages of

the project all PM’s meet every two weeks to discuss deliverables and how the project is

going compared to the standard time plan. It is up to the individual PMs to choose what the

time plan is based on and what tools they use, for example Microsoft Project or Excel. At

GTO, PSM has to be adapted to fit the gates with the product project.

The product matures during the development loops, which have been added in the DVP to

increase time and resources in the earlier phases of the project. There are a total of eight

development loops, where each loop begins with the same prerequisites and demands as the

previous ended with. Development loops help departments to have similar understanding of

the product and ensures that they all are on the same level of knowledge in the product

specification. The different departments are generally in different stages in their own

development process, where development loops help their own development to be more

aligned with the standard time plan.

When a loop is completed the product is “frozen” and no more changes are allowed until the

next loop. Designer and technical preparation has to have a meeting if a change is made to a

product. If a change is made it will be noted by changing the article number of the product in

System F. Intro engineers then implement the changes into the master structure System E.

They are sent to the factories through target structure System E which they in turn alter to fit

into their production system. All factories have an Industrial Launch Group (ILG) which

through meetings verifies that all activities have been performed in all local departments and

suppliers.

The first gate the project needs to pass is the feasibility gate, during the feasibility and concept

phase the product is developed during the previous named development loops. After the

concept gate it is no longer allowed to change the products specifications. GTO gradually gets

more involved the further the project proceeds, primarily based on the maturity level of the

product. Technical preparation is the main actor from GTO in the earlier loops, intro

engineering takes on a larger role after the concept gate and tooling and equipment gets more

involved when a production change is under development. The sooner information about the

product reaches GTO-regional and local, the earlier they can plan and change the production,

for example contact suppliers for tools and equipment, give assembly instruction that the

factories can implement into their production.

GTO gathers information from the project in two ways. Firstly, communication between

designers and technical preparation consists of updates on the design and information

surrounding the demands from GTO, the information is not new but more detail and specific.

25

Secondly, technical preparation distribute information to tooling and intro engineering on

which updates are ongoing and they also take notes from mentioned departments on how the

production will be affected by the changes.

New vital information is gathered by the GTO PM who shares it with GTO local and regional

departments via Microsoft share point. This is done regularly each week with included

meetings. A Start cost project does not always affect the whole production. In the beginning

of the project it is usually small, but grows larger over time with new information, and due to

this it can go from a line organization problem to a project at GTO-regional.

The Final Industrialization Gate (FIG) is an important gate; it verifies all aspect of the

production instruction, assembly sequences, lead times etc. The verification of the product has

been performed at Final Development Gate (FDG) and is GTT’s responsibility. The

verification is primarily done at the Pilot Plant (PP), where the product's manufacturability is

tested. Simulations of the assembly sequence are also done but only around 80% of all

variations can be verified, this is primarily because of the large amount of variants. When the

project has gone through the Release Gate (RG) the series production can start and the

responsibility of the product is handed over to GTO-local with support from intro engineering

if needed.

4.3 Improvement areas The improvement areas are concerns mentioned at the interviews, see Appendix A. Under

each part a summary of the reoccurring improvement areas that were mentioned and the

highlighted words in the chapters is the subject of each paragraph.

4.3.1 Communication

There is no group management to secure that all e-mails are sent to the right people. When

PM or CPM sends out important emails to all stakeholders there are usually a lot of e-mail

addresses to handle manually. This could sometimes lead to emails not getting to the

concerned persons who then can miss important information, meetings, etc. (see Appendix A,

C1.1, C1.2, C1.3)

The project management can sometimes be time consuming when the project grows and

changes line organization or when several projects are merged. The communication between

all stakeholders is crucial for the different departments so that delays can be minimized. (see

Appendix A, C2.1, C2.2)

When it comes to the communication between GTO and GTT it is important that information

between product development and production is transparent. This is not always the case

which may lead to time plans getting out of sync between departments and projects might be

delayed. Also when departments are isolated due to holding information within its walls, time

consuming activities appears and may cause frustration and less value adding work time.

When concepts are changed late it is important that all stake holders get the information fast,

otherwise project costs may increase due to expensive long lead time tool development. At the

moment there is only one person that tries to extract information from the product

26

development to maintain a fast response to changes. (see Appendix A, C3.1, C3.2, C3.3, C3.4,

C3.5, C3.6, C3.7, C3.8, C3.9, C3.10)

The performance of the project has a lot of factors, where one could be people chemistry and

how the interaction between persons may be carried out. (see Appendix A, C4.1, C4.2, C4.3)

4.3.2 Documentation

There are several inconsistencies when handling project files like storing data, updating data

and where to find manuals (see Appendix A, D1.1, D1.2, D1.3, D1.4, D1.5, D1.6, D1.7). This

could lead to confusion and time consuming activities due to people having to search for the

right documents for their project. Although some CPM’s set rules in the beginning of a project to get more consistency (see Appendix A, D1.8). There are also problem with the

structure of the project files, how the files are stored and their naming convention. There is

also lacking gates alignment between DVP and PSM. (see Appendix A, D2.1, D2.2, D2.3,

D2.4)

Project management is lacking when smaller projects are merged into a larger project, which

takes time and resources, and people at GTO must contact the GTO PM to obtain the latest

information about what product the project includes (see Appendix A, D3.1, D3.2).

It is hard to visualize the project plan and get a holistic view of the whole project (see

Appendix A, D4.1, D4.2). It is important to have all stakeholders understanding the scope of

the project and make it as clear as possible.

Having no transparency is a problem that usually occurs in projects spanning over several

departments. It is especially problematic between the product development at GTT and

production at GTO. When GTO does not participate in the development loops as they should

and GTT does not have an understanding of the production, the departments may suffer from

isolation that causes important information to be locked up. Due to long lead time tools that

need to be ordered in time, an employee from GTO tries to obtain the information that is

needed and thus break the isolation. It is also very hard to interpret the project in the

beginning which makes it hard to start working with the production of the product (see

Appendix A, D5.1, D5.2, D5.3, D5.4, D5.5).

There are no guidelines for a PM as to which tools to use, which makes the time plans in

projects, end up in a lot of different formats. Moreover when files are in different formats it

takes time to convert them into a convenient format which any program can use (see

Appendix A, D6.1, D6.2).

When project members are replaced a lot of project experience may be lost, but it also makes

it hard, if not impossible, to document experience. Intro engineers have a lot of correlated

projects and they have to search for the connected impacts when a certain product change has

been made. If a key project member is replaced it will cause problems due to the lost

experience (see Appendix A, D7.1, D7.2).

When working in projects there are some administrative activities that are waste of time due

to tedious way of working (see Appendix A, D8.1). Other time related issues are the Intro

blocks. These are for the most parts movable if a problem occur, but there are some

exceptions that are not moveable due to i.e. legal requirements like safety issues (see

Appendix A, D8.2, D8.3).

27

There are ways to measure project quality and it is not that comprehensive, which means that

the cost of the project is discarded, hence priority amongst the projects cannot be obtained.

The ILG is responsible to verify and assure that all activities in a project have been

performed and saves a status file at the Microsoft Share Point storage (see Appendix A, D9.1,

D9.2).

4.3.3 Knowledge

An important factor when introducing new work methods is to educate people of why the

change is necessary. If the information about the change has not been communicated as well

as it should, people tend to fall back on the old and practiced way of working or use of tools.

(see Appendix A, E1.1, E1.2, E1.3)

When it comes to the awareness of new project models, some project managers are not aware

of the high workload in the beginning of a project. This leads to a time pressure throughout

the project and may delay deliveries. (see Appendix A, E2.1, E2.2)

There is no clear information on why or how to use project tools like PGT or processes like

DFA or PSM, which makes it hard to follow them. (see Appendix A, E2.3, E2.4, E2.5)

Project managers may choose how the document structure should look like or how to follow

a process which could lead to misunderstandings between stakeholders. (see Appendix A,

E3.1, E3.2, E3.3, E3.4)

4.3.4 Resources

The project group members are usually dismantled after a project is finished. Reusing

resources from a project that has worked well would facilitate the next project. When

working with new project models it can be difficult to estimate the time it takes for each

deliverable before each gate which leads to delayed projects. Searching for resources is

usually time consuming and hard to find new resources when a team member has left a

project. Solving a problem can be done faster if the right expertise is found as fast as possible.

(see Appendix A, R1.1, R1.2, R1.3, R1.4, R1.5, R1.6)

Due to the amount of people in projects that span over several departments, the CPM or Intro

engineer could miss contacting all the stakeholders within the project group. The organization

charts are made in a PowerPoint-file and has no connection to the e-mail client which is one

potential improvement area. (see Appendix A, R2.1, R2.2, R2.3)

When it comes to different roles in a project the people chemistry is usually a performance

factor that is hard to estimate before a project start. (see Appendix A, R3.1, R3.2)

It is also hard to get a holistic view of the project and all its stakeholders and when a project

is late everyone needs to be informed. (see Appendix A, R4.1, R4.2)

28

4.3.5 Gates

Gates are an important part of project work. Since each project looks different from the other,

the PM needs to have an opportunity to merge gates or adapt project plans when late product

changes have been made. The cross-functionality in a project is important when different

departments need to adapt gates with their process so that delays are easier to handle. (see

Appendix A, G1.1, G1.2, G1.3, G1.4, G1.5)

29

5. ANALYSIS

This chapter includes an analysis to find differences between the theory chapter and the

results chapter. A summary is presented in each improvement chapter in a form of a table. An

analysis of the improvement areas and the correlating ICT advantages will also be brought up.

The project management and the different processes used currently at Volvo Group Trucks

are a reflection of the presented theory; much of the theory is based upon the book (PMI,

2013), which in turn is regulated by the ANSI standard ANSI/PMI 08-001-2012. The DVP

follows the Stage-Gate principle, though using their own concept of the method, and with

RnD30 it also aims for more resources at early stages. Time plans are used throughout the

organization in projects with the help of WBS and RBS. Inconsistencies concerning different

kinds of communication and data handling has been detected, where there are no structured

process, there are directives on how people should carry out the process but not all PM or

CPM are consistent with following or demanding that they are followed.

Communication As could be seen in the theory chapters there were a lot of different areas that needs to work

to have a successful project. Communication is a complex part of the project work as can be

seen in the theory. This also states that there are virtual communication methods that will

facilitate at global companies. When comparing the theory with the result chapter it can be

seen that there are some improvement areas standing out, like emails getting to the right

people, transparency between departments and people chemistry. The areas and their

correlation to theory are presented in Table 5.1. According to the theory it is important to

have good communication between all the stakeholders when the project scope grows, which

is discussed in the next chapter.

Table 5.1 Communication results validated by theory

Results Theory

E-mails not getting to the right

people.

People not knowing the structure of the project

(Ying & Pheng, 2014)

Transparency leads to essential

information not being communicated

When the organization is not transparent it has

problem with distributing information (Ying &

Pheng, 2014)

People chemistry leads to conflicts. People having different personalities, conflicts are

inevitable. (PMI, 2013)

As can be seen from the ICT chapter in the theory, an ICT may help with the two first issues.

The first can be solved due to the hierarchical communication structure where people may be

able to send e-mails to whole groups. The second could be solved as a result of the

implementation of the ICT, where collaboration will be facilitated (Rabelo, 2008). The third is

ambiguous due to there are both positive and negative sides with an ICT (Correia, 2008).

Documentation When it comes to information storage the theory states that data can be either structured or

unstructured. Most project data is unstructured and hence it is more convenient to be stored on

30

a network based storage platform. This can be confirmed by the results that the data is stored

on Microsoft share point. Although, according to the results there are inconsistencies when

storing data and what tools to use and does not comply with the theory. This states that the

data should have standardized guidelines and work instructions in how to store it.

The theory states that it is important to have a holistic view of the whole project that helps all

stakeholders understanding the scope. This is not the case according to the results, which

shows that it is usually hard to have a visualization of the whole project. Transparency

between departments is also an area that differs. The theory states that it is important for

global companies to have a transparent organization, but the results shows that the production

department may feel isolated due to the product development department not sharing

important information in time.

Furthermore the theory mentions that when people are replaced in projects experience may

disappear and this knowledge can for instance be saved in a lessons learned log. The results

confirm that it can be problematic but also that it is difficult to document experience.

Table 5.2 Documentation results validated by theory

Results Theory

Inconsistencies in naming conventions, file

structure when storing project files and

tools.

To make data easy to find there should be

standardized guidelines and work instructions.

(PMI, 2013)

Visualization of the project plan is hard. It is important that all stakeholders understand

the scope. (Pinto, 2007)

Isolation leads to less transparency

between departments.

Important that global companies are

transparent. (Pinto, 2007)

When people in projects are replaced

experience may be lost.

Important to have a lesson learned log to

document experience. (Becerra-Fernandez,

2006)

The theory states that a standardized document structure is vital for having an effective

project work. ICT may facilitate all four issues but there is some interference that needs to be

solved in advance which will be discussed in the next chapter. (Coakes, 2006) (Camarinha-

Matos, Afsarmanesh, Ollus, 2008) (Rabelo, 2008)

Knowledge Knowledge improvements in most cases revolve around methods not fully being implemented

and enforced. Inexperience in project work and clear initiatives from CPM and PMs makes it

hard for people to structure their work.

Table 5.3 Knowledge results validated by theory

Results Theory

People are not aware of why a work

method change is necessary. Change management (Suran, 2015)

There is no clear information on how to

use project tools.

There should be standardized guidelines and

work instructions. (PMI, 2013)

31

When it comes to knowledge the theory mentions four processes that can be facilitated with

an ICT (Becerra-Fernandez, 2006). The first issue in Table 5.3 is a change management type,

where the next issue is of a kind that could be included into one of the processes.

Resources The theory states that keeping resources throughout the project is beneficial. The result shows

that when someone in the team leaves the project it is hard to find new resources and it takes

time. The theory also states that when managing the resources several tools can be used for

visualization of the organization or having an expertise locator system. PowerPoint is used

according to the results to visualize the organization, but does not have a connection between

the resource and e-mail client. This may lead to excessive work.

Table 5.4 Resources results validated by theory

Results Theory

Project is dismantled after a project is finished

and people can leave in the middle of a project.

Having the same team throughout the

project is beneficial. (PMI, 2013)

When someone leaves the project it is hard to

find new resources.

It would help to have an expertise

locator system (Becerra-Fernandez,

2006).

As could be seen in the theory chapter 3.3, an ICT-solution could facilitate both resource

planning and expertise locator system that could be used to find the right resources (Becerra-

Fernandez, 2006). This will be further discussed in the next chapter.

Gates The empirical findings show that gates are not always followed. They can be moved ahead in

time and some deliverables can be moved to the next gate. There is also an improvement area

connected to fit the different time plans for each department.

Table 5.5 Gates results validated by theory

Results Theory

No alignment of the different time plans

for each department

Time consuming, resulting in unnecessary

activities. (Grönlund, et al., 2010)

Gates are not always followed Bureaucratic procedures. (Grönlund, et al., 2010)

The first improvement area is primarily a result of lack of knowledge, for instance during the

interviews the connection between PSM and DVP could not be found. An ICT-solution helps

this alignment for companies to cooperate despite different organizational forms (Camarinha-

Matos, Afsarmanesh, Ollus, 2008). The second area could not be supported by an ICT,

bureaucratic procedures needs to be standardized to be able to be supported.

32

6. DISCUSSION

The discussion focuses on the improvement areas from the empirical findings and the

supporting theory. The first paragraph discusses the problem defined in the problem definition

and how it is affected by the improvement areas. Second paragraph mentions if an ICT-

function is applicable to the improvement areas. The third paragraph states if an ICT-platform

can be implemented at Volvo Group Trucks. The last paragraphs discusses how an ICT-

platform could be implemented and how the general response could be expressed.

As could be seen from the analysis there are correlations between the current state and the

theory. The theory consists of chapters that highlight how a general project and a product

development project should be managed to successfully develop a product with high quality

and in time. In the analysis several cases are shown that the improvement areas does not

coincide with the standards of a well-functioning project process, as mentioned in the theory.

From the problem definition it is stated that projects at Volvo Group Trucks are delayed and

that they are not following the principles set when working in product development projects.

The authors do not think these improvement areas are solely responsible for the delays in

product development projects, and this thesis cannot answer in what extent the improvement

areas affect projects because of the small research scope. However the authors can assume

from the interviews that they do affect the collaboration between the chassis department at

GTT and GTO when working in such projects. The theory states that ineffective collaboration

makes project ends up being delayed (Vandelvelde, 2003), with this the authors can say that

the improvement areas are delaying product development projects, but as said earlier the

authors cannot say to what extent the improvement areas are affecting a product development

project. The authors also assume that the improvement areas look similar between other GTT

departments and GTO. This assumption is made on the basis from the interviews with GTO

employees.

According to the analysis several areas were found where an ICT-solution could help support

the project work at Volvo. (Becerra-Fernandez, 2006) also gives examples on how ICT-

solutions could facilitate the improvement areas. This leads to ad-hoc solutions, which does

not fully incorporate the complete project infrastructure as mentioned in the theory

(Camarinha-Matos, Afsarmanesh, Ollus, 2008). An organization needs an ICT-platform that

incorporates all aspects of project work.

Table 6.1 Prerequisites not fulfilled

Improvement areas Theory

Easy access to data and regular updates (Coakes, 2006)

Transparency (Rabelo, 2008)

Several different software’s and tools (Camarinha-Matos, Afsarmanesh, Ollus,

2008)

Several and unstructured communication

channels (Camarinha-Matos, Afsarmanesh, Ollus,

2008)

33

The mentioned improvement areas in Table 6.1 are prerequisites that need to be managed in

advance of implementation of a fully functional ICT-platform. The theory states that it can

support some of these areas, i.e. increased collaboration will increase the transparency. The

authors’ thinks that the transparency with for example not knowing who to contact; is an

unstructured transparency and it needs to be structured before an ICT-platform can support it.

Other issues that need to be mentioned are the amount of different software tools used. By

having that amount of tools it is difficult to construct a coherent ICT-platform. Also a more

general issue is the different personalities among people which are both difficult to estimate

and to solve. That being said, GTO and GTT incorporate the three preconditions that were

stated by (Rabelo, 2008).

1. Requires collaboration among involved partners that does not only involve sending e-

mail messages.

2. The existence of trust, considering that partners shall rely on each other (at all levels).

3. All (or most of) the activities carried out within a collaborative network organization

should be made via computer networks, i.e. digital transactions should be the routine,

and not an exception

By having the three preconditions the authors argues that it justifies that Volvo is ready to

start investigating on how an ICT-platform should be implemented.

How an implementation of an ICT-platform would succeed and how it will be accepted

depends on the preconditions. As had been said earlier there are a lot of tools at Volvo, this

could be discussed to be several ad-hoc solutions. As stated from the interviews, some

software are seldom used because of lack of knowledge of the software or that they are too

complex to use. An example is the database with completed projects; the inconsistent naming

convention makes it hard for people to find the projects they are looking for. This is a case of

software being implemented or managed wrong. If employees could give feedback on the

system before implementation the authors thinks that a more general acceptance would help

the implementation of an ICT-platform.

If all these underlying issues are not taken into account when developing an ICT-platform, it

will probably not work as intended even if the platform itself is working as it should.

34

6.1 Further work For the first paragraphs in the discussion, it is stated that the scope of this research is only

applicable to the research area. To be able to find out if the results of this thesis can be

applicable to all stakeholders involved in product development projects and their respective

interfaces, all departments at Volvo needs to be researched.

The prerequisites for an ICT-platform are not fully met, which means that further research

needs to be conducted on how standardized project work can be managed at Volvo. Not only

to give a more detailed analysis of the subject, but also to create a foundation for the

architecture of the ICT-platform. It would also be interesting to see if and how the PTM

system could be implemented into the final ICT-platform.

If an ICT-platform would be implemented, a research on the current technical knowledge at

Volvo needs to be performed. This to find out if they have the expertise to translate the

practical project work into a complete ICT-platform.

35

7. CONCLUSION

The conclusion addresses how and where in the thesis the research questions were answered.

The purpose of this master thesis was to find out if an ICT-platform can be implemented and

help project work at Volvo. The results from the discussion show that an ICT-solution can be

implanted but to implement an ICT-platform further work is needed.

How is practical project work carried out at GTO and GTT?

How practical project work is carried out is answered in the empirical findings, chapter 4.2. It

is evident that for product development projects a Stage-Gate model is used which is designed

for product development projects. Meanwhile GTO uses a project process called PSM, which

is used primarily for production changes and not product changes. At the moment the two

different project models are not completely aligned.

How is information communicated between GTO and GTT in project work?

This is answered in the empirical findings chapter 4.1. Several different tools and

communication channels are used when sending information, where unstructured data is often

sent through e-mail and Microsoft Share Point, and structured data is sent via System E and

System F. The communication, information and transparency mentioned in the problem

definition were found during the interviews, which resulted in several potential improvement

areas. The scope of this research limits the field of how well the different improvement areas

cohere with other departments at Volvo and is suggested as further work.

How can an ICT-platform support project work and collaboration at GTO and GTT?

This is answered in chapter 5 and elaborated in chapter 6. Several ad-hoc solutions could be

found to increase the collaboration between GTT and GTO. As mentioned in the discussion

the ad-hoc solutions will only resolve one issue. Moreover it was stated that the company is

not ready for a complete implementation of an ICT-platform, which has been suggested for

further work.

ICT-solutions could be implemented but only to solve specific problems. To be able to

implement an ICT-platform the prerequisites need to be solved.

36

REFERENCES

Anderson, R. E., 1993. Can stage-gate systems deliver the goods?, Financial Executive, vol 9

no 6 pp. 1-34.

Becerra-Fernandez, I., 2006, ICT and Knowledge Management Systems in Encyclopedia of

Knowledge Management, ed D. G., Schwartz, IGI Global, Pennsylvania, pp. 230 - 236.

Bellgran, M., Säfsten, K., 2010. Production Development. 1st ed. London: Springer.

Bryman, A., Bell, E., 2003. Business Research Methods. 3rd ed: Oxford University Press.

Camarinha-Matos, L. M., Afsarmanesh, H., Ollus, M., 2008. Ecolead and cno base concepts

in Methods and tools for collaborative networked organizations, eds L. M. Camarinha-Matos,

H. Afsarmanesh, M. Ollus, Springer, US pp.8-21.

Coakes, E., 2006. Storing and sharing knowledge: Supporting the management of knowledge

made explicit in transnational organisations. The Learning Organization, vol. 13 no. 6, pp.

579-593.

Cooper, R. G., 1990. Stage-gate sytemes: a new tool for managing new products. Business

Horizons, vol. 33 no. 3, pp. 44-54

Correia, A.-P., 2008. Team conflict in ICT-rich environments: Roles of technologies in

conflict management, British Journal of Educational Technology, vol. 39 no. 1, pp. 18–35.

Duque, R., Collins, M., Abbate, J., Azambuja, C. C., Snaprud, M., 2007. History of ICT in

Past, Present and Future of Research in the Information Society, eds W. Shrum, K.R.

Benson, W.E. Bijker, K. Brunnstein, Springer, US pp 33-45.

Grönlund, J., Sjödin, D. R., Frishammar, J., 2010. Open Innovation and the Stage-Gate

Process: A revised model for new product development, California Management Review, Vol.

52, 3, pp. 106 –131.

Khakhar, D., Cornu, B., Wibe, J., Brunello, P., 2007. ICT and Development in Past, Present

and Future of Research in the Information Society, eds W.Shrum, K.R. Benson, W.E.

Bijker, K.Brunnstein, Springer, US pp 47-62.

Know4Car consortium, Circle, 2015. Available from: <

http://www.know4car.eu/public/pictures/temp.png/view>. [1 June 2015]

Marco, T., Montorio, M., 2007. The future of manufacturing: Survey of international

technology foresight initiatives in Advanced Manufacturing. An ICT and Systems

Perspective, eds M. Montorio , M. Taisch , K-D. Thoben, Taylor & Francis, pp. 1-12.

Pixabay, 2015. Available from: < http://pixabay.com/sv/sociala-medier-personlig-581783/>.

[1 June 2015]

Rabelo, R. J., 2008. Advanced Collaborative business ICT infrastructures in Methods and

tools for collaborative networked organizations, eds L. M. Camarinha-Matos, H.

Afsarmanesh, M. Ollus, Springer, US pp. 8-21.

37

Rosenau, M., Githens, G., 2005. Successful Project Management: A Step-by-Step Approach

with Practical Examples. 4th ed. New Jersey: John Wiley and Sons, Inc.

Pinto, J., 2007. Project Management, Achieving Competitive Advantage Global Edition. 1st

ed. Harlow: Pearson Education Limited.

Project Management Institute, PMI, 2013. A Guide to the Project Management Body of

Knowledge (PMBOK Guide). 5th ed. Newtown Square: Project Management Institute, Inc

Somasundaram, G., Shrivastava, A. (eds) 2009. Information Storage and Management:

Storing Managing and Protecting Digital Information, Wiley Publishing, Indianapolis.

Stage-Gate product development, Idaho State Journal, 2012. Available from:

http://search.proquest.com/docview/942991869 [1 June 2015]

Suran, S., 2015. How to Effectively Implement Change, Journal of Corporate Accounting &

Finance,vol. 26, no. 4, pp 5–12

Vandevelde, A., Van Dierdonck, R., 2003. Managing the design-manufacturing interface.

International Journal of Operations & Production Management, vol. 23 no. 11/12, pp. 1326-

1348.

Orlikowski, W. J., 1992. Learning from Notes: organizational issues in groupware

implementation. In Proceedings of the 1992 ACM conference on Computer-supported

cooperative work (CSCW '92). ACM, New York, NY, USA, pp. 362-369.

Ying, Z., Pheng, L. S., 2014. Project Communication Management in Complex Environments.

1st ed. Singapore: Springer.

.

I

APPENDIX A

Communication Subject

Nr.

Interview

Nr. Specific Issues General Issues Proposed Solution

C1.1 2 Send email to concerned

PMs

Group

management

Automated within ICT

C1.2 2

Communication GTT-

GTO enclosed,

sometimes CPM missed

contacting stake holders

Group

management

Improved cross

functionality with

direct messages to all

stake holders within a

group

C2.1 3

The size of the project is

not determined, it can

grow and switch from

one line organization to

another (said by GTO)

Project maturity More information

about the project to all

stake holders

C2.2 3 Merging projects takes

time and resources

Project

management

Standardized way of

grouping projects

C3.1 3

GTO-local needs info

about the product, GTO

PM needs info about the

production

Transparency Good communication

between product

designer and technical

preparation

C3.2 3

GTO doesn’t find the organization

transparent. GTO needs

to ask for information.

Transparency Better communication,

right information

should flow to the

right people

C3.3 3

Product development is

isolated within GTT

(said by GTO)

Transparency Invite GTO to have

better understanding in

product development

C3.4 3

There are three

communication

interfaces (said by

GTO), GTT-GTO PM,

GTO Regional-GTO

Local, GTO Regional

Transparency Merge communication

C3.5 3

Delayed Start cost

project usually result in

shorter lead time for

GTO. GTO works

harder, may cause bad

quality

Transparency

Communication or hint

in time so GTO may

have a chance to

handle it

C3.6 3

Tools are developed and

suddenly the concept is

changed and the tool is

outdated, this leads to

high costs

Transparency Better communication

at the right time

II

Communication Subject

Nr.

Interview

Nr. Specific Issues General Issues Proposed Solution

C4.1 4, 10

The performance of the

project is based on the

chemistry between

people and also how

older projects worked

out (the “best” solution is not always the best

solution)

Neutralize people

chemistry

Standardized

communication

approaches

C3.7 4

GTO is not a part of the

development loops as

they want and should be

Transparency Better cross-

functionality

C4.2 4

The technical

preparation team and

people involved in the

industrialization phase

do sometimes have

divided opinions

Communication

and

standardization

Better communication

within GTO

C3.8 4

GTT only sees a

fraction of the

production development

Transparency Better cross-

functionality

C1.3 5

Everyone needs to be

informed when a project

is late

Transparency Group communication

C4.3 5

GTO may have to

deliver a concern to

GTT that first was not a

demand but when they

got challenged it turns

out into a demand

(GTT: Sometimes the

cost of fixing the issue

is more than just leaving

it as it is)

Neutralize people

chemistry

Due to different

personalities.

Standardized

communication

approaches

C3.9 7

One person tries to get

out information from a

project on GTT due to

long lead time tools

Transparency GTO needs

information early

C3.10 10

GTT can change the

whole concept of a

product from what we

were working on.

Transparency GTO needs fast

updates so they don’t work on outdated data

III

Documentation Subject

Nr.

Interview

Nr. Specific Issues General Issues Proposed Solution

D1.1 1

Product change leads to

not all IDs are updated

through the chain

Inconsistency

when updating

data

D1.2 1 Documents need to be

updated

Old documents Notification system for

stake holders

D1.3 1, 2, 10

Same document are

stored on different

places, templates are

hard to find

Inconsistency

when storing files

Documents needs to be

stored on same place,

template database

D8.1 1

Quality status reporting

takes time, needs to be

reported to the manager

No flexible status

system

Quality reporting

system

D1.4 2

Hard to find

documentation on how

to use different tools

Inconsistency on

which database to

use for how-to

documents

Knowledge database

D2.1 2

The structure on

Microsoft Share Point

looks different

depending on the PM

Inconsistency in

structure

Standardized structure

(names and place of

files and folders)

D1.5 2

Small product changes

(GTT) does not lead to

a new article number

which may affect other

departments later

No alert system

through the whole

stake holder chain

Visualize/educate the

importance in how a

decision may cause

problems later. Fail

proof when changing

product.

D1.6 2

Few people read white

books

Inconvenient to

find

documentation

Lessons learned log

D1.7 2

Structured work flow

plan is not updated

Inconvenient to

update project

plan

Easier accessible and

updated structured

work flow (process

handler)

D3.1 3 Merging projects takes

time and resources

Project

management

Standardized way of

grouping projects

D3.2 3

Needs to contact GTO

PM for information

about the product

project portfolio

Project

management

Easy access to the

portfolio

D4.1 4

It’s more important to be able to visualize the

project plan than what

tool to use. Microsoft

Project is hard to

visualize.

Visualization Visualize project plan

in ICT

IV

Documentation Subject

Nr.

Interview

Nr. Specific Issues General Issues Proposed Solution

D5.1 4

GTO isn’t a part of the development loops as

they want and should be

Transparency Better cross-

functionality

D4.2 4

One hard aspect is to

get a good picture of the

whole project

Holistic view Visualization and

connect stake holders

within ICT

D5.2 4

GTT only sees a

fraction of the

production development

Transparency Better cross-

functionality

D7.1 4

Experience is the most

important input to a

project, can’t be replaced with systems

Experience

Management

Capture relevant

experience (Serena).

Tag cloud where

common activity names

and time consumption

from earlier projects

are saved

D6.1 4

GTT and GTO uses

different tools which

leads to time consuming

formatting

Tools Common tools

D1.8 5

When starting a project

CPM can set the rules

for the project, i.e. what

project planning tool to

use or the structure in

Microsoft Share Point

Rules

management

The rules is included

when starting a project

so all PMs can see

D5.3 7

One person tries to

obtain information from

a project on GTT due to

long lead time tools

Transparency GTO needs information

early

D6.2 7

People use tools of their

own choice (i.e. project

planning) due to

different knowledge

Tools Standardized way of

working

D2.2 7

People doesn’t always save files in a structured

way on Microsoft Share

Point

Standardization Standardize structure

and way of working

D2.3 7

Project info should be at

Microsoft Share Point,

this is not always the

case

Standardization Standardize structure

and way of working

V

Documentation Subject

Nr.

Interview

Nr. Specific Issues General Issues Proposed Solution

D8.2 8

8 intro block per year, 4

small, 4 large. Usually

System A and System

B, see Appendix C. The

larger is PMR and Start

Cost. Specific dates.

Time Calendar or similar

D9.1 8

Measurement of project

quality in terms of

faults or no faults. Not

accounting the money

each project costs leads

to no priority

Project priority If money was included

the problematic

projects could have a

better priority order

D8.3 8

Some intro blocks can’t be delayed due to legal

requirements i.e. air bag

Time Importance system

D9.2 8

ILG – Industrial Launch

Group. Local at each

factory where they look

through all departments

and suppliers to see if

all activities have been

done. Work saved in an

Excel sheet in Microsoft

Share Point

Project assurance The work of ILG could

be facilitated in an ICT

D7.2 8

There is a designated

Intro Engineer that

takes care of PMR,

System A and System B

(see Appendix C) in

their respective area,

where they need to

investigate how

different changes

impact each other

Project correlation Correlation between

changes and connect

impacts

D2.4 10

Aligned gates between

DVP and PSM is under

construction. PSM is

great for in-house

projects but only use the

tools for product

projects

Official structure Official structure

removes the need of

doing a local solution

D5.4 10

GTT can change the

whole concept of a

product from what we

were working on.

Transparency GTO needs fast updates

so they don’t work on outdated data

VI

Documentation Subject

Nr.

Interview

Nr. Specific Issues General Issues Proposed Solution

D5.5 10

In the beginning of a

project it is really hard

to interpret the project

Project maturity

Transparency

All stake holders needs

to know their part and

task as soon as possible

Knowledge Subject

Nr.

Interview

Nr. Specific Issues General Issues Solution

E1.1 1 ”Why change a fully working GDP”

Change

management

Information and

education

E2.1 2, 3

Some people are not

aware of high

workload in the

beginning of a project

and changes the way of

working (front end

loading)

Awareness Educate on how to

execute a DVP project

E2.2 2

Not enough resources

when using DVP leads

to late deliveries

Awareness Information the

workload in a certain

type of project leads to

easier planning of

resources

E4.1 3

GTT PMs has good

information about

GTO, designers have

not

Transparency Information/education

to the right people

E3.1 3

PSM can be followed

in different ways:

-Experience of PM

-General experience of

the project group

-How mature the

project is

Standardization Educate/inform how a

project model should be

followed

E1.2 4

RnD30 and other new

improvements needs to

have set goals that

people understand

Change

management

Educate why

E2.3 4 PGT and PAP is hard

to follow

Awareness Education of tools

E2.4 5

GTO says no to a lot of

issues regarding DFA.

(Impression from GTT

is that they don’t understand DFA)

Awareness

Educate/inform why a

certain task is important

VII

Knowledge Subject

Nr.

Interview

Nr. Specific Issues General Issues Solution

E3.2 7

People use tools of

their own choice (i.e.

project planning) due

to different knowledge

Standardization Standardized way of

working

E3.3 8

Different conditions

between factories, not

only technical but

language and cultural

as well

Standardization Standardization that

accounts for different

causes

E1.3 9

The hard part is to get

people to use new

products and tools

Change

management

Educate and show the

benefits

E2.5 10

Educate people in PSM

so they know what

tools that are available

Awareness Education will decrease

the scattering on how a

project should be

executed

E3.4 10

Assembly simulations

are done but can’t cover all parts, designs,

variations and models.

GTT and GTO are not

in an agreement on

who should handle the

assembly simulations.

Standardization Everybody knows who

should do what

VIII

Resources Subject

Nr.

Interview

Nr. Specific Issues General Issues Proposed Solution

R1.1 1 Different organizations

on every project

Resource problem Visualize organization

and hierarchy

R1.2 2

Not enough resources

when using DVP leads

to late deliveries

High workload,

Resource problem

Database on the

workload connected to

each role

R2.1 2

Communication GTT-

GTO enclosed,

sometimes CPM missed

contacting stakeholders

Group

management

Improved cross

functionality with

direct messages to all

stake holders within a

group

R1.3 2

Takes time to search for

resources

Resource problem Resource pool, system

to see how many and

what projects people

are part of

R1.4 2 People are being

replaced

Resource problem Resource assurance

R3.1 4

The performance of the

project is based on the

chemistry between

people and also how

older projects worked

out (the “best” solution is not always the best

solution)

Neutralize people

chemistry

Standardized

communication

approaches

R1.5 4

It is important to have

capable people in the

project

Resource problem Resource assurance

R4.1 4

One hard aspect is to get

a good picture of the

whole project

Holistic view Visualization and

connect stake holders

within ICT

R4.2 5

Everyone needs to be

informed when a project

is late

Transparency Group communication

R3.2 5

GTO may have to

deliver a concern to

GTT that first is not a

demand but when they

got challenged turns out

into a demand (GTT:

Sometimes the cost of

fixing the issue is more

than just leaving it as it

is)

Neutralize people

chemistry

Due to different

personalities.

Standardized

communication

approaches

IX

Resources Subject

Nr.

Interview

Nr. Specific Issues General Issues Proposed Solution

R2.2 8

12 technical areas where

intro engineering has

one person at each area.

Local engineering is

divided into layout and

Technical Preparation

into modules. Have to

talk to several, not only

one local engineer when

the layout is changed.

Group

management

ICT should have the

responsibilities of each

engineer divided in

both modules and

layout and then group

the affected people

R2.3 8

It is important to be

effective on meetings

and that they follow an

agenda and structure.

GTO PM has a list on

who to invite on

meetings

Group

management

The right people on

meetings and stick to

the agenda

R1.6 10

Experience and contacts

has a huge impact on

how fast a problem can

be solved

Resource and

experience

management

Right people know

how to solve problems

R1.7 10

Organization charts are

used but not always

updated, takes time to

find your resource

Resource problem ICT can be updated

automatic when people

leave projects or new

one arrives

X

Gates Subject

Nr.

Interview

Nr. Specific Issues General Issues Solution

G1.1 1

Late changes on product

make production less

adaptable

Transparency

G1.2 1 Gates can sometimes be

merged

Dynamic platform

G1.3 3

PSM gates needs to be

adapted to fit into DVP

gates

Is done internally at

GTO right now

G1.4 4 Delays in a Start Cost

project spreads

G1.5 6

Departments have

different lead times and

cannot always follow

time plan

Time plan Dynamic platform

XI

APPENDIX B

APPENDIX C

Tools and IT-Tools

There is a range of different tools available in both project work, assignments and line work,

where each tool usually has one specific purpose. Below is a list of specific and general tools

used in projects.

System A - Quality issues notification system

System B - Product modification notification system

System C - Closed projects database

System D - Resource management system

System E - Production database

System F - Product database

System G - Tolerance tool

PGT - Project governance system

Microsoft Share Point

Lync

Intranet

Microsoft Project

Excel

XII

APPENDIX D

Introduction of ourselves

Explaining why we are conducting this interview.

Can we record this interview?

Questions of introduction

Would you like to tell us about your education and career?

What role do you have in the organization?

Can you tell us briefly about what you are working on and what kind of projects?

The organization of the project

What roles are there, what is the interaction are their between the different roles?

Main Questions

Type of project

Do you follow any project model?

How easy is the PSM/DVP followed?

How do you find this project model? (Does it fulfill its purpose?)

If you follow the PSM differently depending on the project?

What tools do you use to create and manage projects?

Manual and IT tools

How do you delegate tasks and how do you follow up?

What tools do you use to control the project?

Is there documentation on how to work with these tools?

We have heard that the startup cost project will be delayed, how are you affected by it?

What do you think is the reason?

Internal Data Management & Communication

How do you process value adding data? (Recycled / stored data)

What internal communication tools do you use?

External Data Management & Communication

How does the data being exchanged between the other departments? How to check that the

data has been received?

How do you share with you of your output from a value creation process to other

departments?

XIII

What communication has taken place before data is exchanged?

Collaboration GTO-GTT

In which phase of the project will the collaboration the with the GTT/GTO increase?

Is it in any particular phase of the project which is working?

If there is a change of a product how do you notice it and vice versa?

Are there limitations or directives on how data is supposed to be communicated between

departments?

Do you perceive the organization as transparent?

Suppliers

Do you communicate with suppliers? How is the communication?

How are the data between you and supplier? Are there limitations or directives for the flow of

information?

How are things generally going when working in projects?

Does project work well?

What are the strengths / weaknesses?

Some special things that you think are missing?

Concluding questions

What do you have and what do they expect in the future?

If there was a tool that could facilitate projects, would it be used, or does it feel like one in the

crowd? What would be needed for PM and other users to feel it is a necessity in their daily

work?