preliminary design report - iaac-aeic.gc.ca
TRANSCRIPT
PRELIMINARY DESIGN REPORT
HIGHWAY 11 REALIGNMENT
LOCATION:
Highway 11 Realignment – 2.2 km West of Michael Power Boulevard Easterly for 4.7 km
Prepared by TBT Engineering
On Behalf of
Premier Gold – Hard Rock Gold Project
August 25, 2016 TBTE Ref. No. 14-192
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering i
Executive Summary
Premier Gold Mines Limited (Premier) retained TBT Engineering Limited (TBTE) to prepare a
Preliminary Design Report (PDR) for the proposed realignment of provincial and municipal
roadways outside of their Hardrock property gold mine project (Project). The Project is located
approximately 280 km northeast of Thunder Bay, Ontario in the Municipality of Greenstone near
the intersection of Michael Power Boulevard and Highway 11. Geraldton is situated 5 km north
of Highway 11 along Michael Power Boulevard.
The Project is generally anticipated to include an open pit mining operation with an on-site
processing facility, waste rock and tailings disposal sites, water treatment facility, serviced plant
site, and new access road from Highway 11.
King’s Highway 11 is classified as a rural arterial undivided (RAU 110) facility. The primary
function of Highway 11 is to provide access across Northern Ontario as well as a link between
many small communities. Highway 11 traverses the ore body of the Project in an east – west
direction, located in the Ward of Geraldton, in the Townships of Errington and Ashmore,
Municipality of Greenstone, in the District of Thunder Bay. As the ore body is beneath Highway
11, a realignment of the highway and Michael Power Boulevard (secondary Highway 584) will
be necessary to allow surface mining developments.
A Feasible Route Study was completed by Premier in 2013 during their Project Planning Phase.
The route study identified six possible alignment alternatives for Highway 11; five bypassed the
Project to the north and one to the south. Following further Project planning and preliminary
infrastructure design functions, a 500 m safety offset buffer was identified surrounding the
proposed open pit. This requirement removed four of the potential alignments. Premier
completed a Highway Alignment Evaluation Summary Report in 2014 which assessed and
optimized the two remaining alignment options (1 A & 1B) and added a third alternative (1D)
with improved geometry, exceeding the minimum design requirements, and intersects Michael
Power Boulevard at the most favourable angle of the alignment alternatives. Through
consultation with the Ministry of Transportation, it was determined that option 1D is the preferred
alternative as it provides the best horizontal and vertical alignments of the options available.
The length of re-alignment for alternative 1D is 4.7 km.
Alignments 1A, 1B, and 1D all bypass the Project to the north of Highway 11, bordering Mosher
Lake and Kenogamisis Golf Club and cross the existing MacLeod tailing deposits. The MacLeod
tailing deposits include two components; MacLeod Low Tailings (MLT) which is tailings beach
deposited at grade; and, MacLeod High Tailings (MHT) which is a landscaped tailings dump with
heights in the order of 10 m above original ground. All alignments intersect with Michael Power
Boulevard at varying offsets from the current junction.
The realignment of Highway 11 and Michael Power Boulevard will be designed and constructed
to MTO standards. Legal agreements will be required between MTO and Premier; and, the
Municipality of Greenstone and Premier for their respective sections of new roadway. All costs
for the realignment, including utility relocation and establishment, are to be borne by Premier.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering ii
Once construction is complete, the MTO will need to acquire/assume the new alignment and
designate it. Following this, the MTO and the Municipality of Greenstone will have to remove the
designation from the bypassed segments of roadway alignment and dispose of it to Premier.
The existing Highway 11 and Michael Power Boulevard are to remain operational until such time
as the realigned segments are constructed, accepted, and opened. All pre-development access
is to be maintained.
As the MTO will be the ultimate owner of the relocated Highway 11, MTO is expecting that the
detail design and construction of the relocated portions of Highway 11 are undertaken in a
manner consistent with MTO process, standards, and design criteria.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering iii
Attachments
APPENDIX A June 2014 Open House Summary
APPENDIX B Design Criteria
APPENDIX C Preliminary Design Drawings - Highway 11 Realignment
APPENDIX D Preliminary Design Drawings – Mine Site Entrance
APPENDIX E Preliminary Geotechnical Design Report
APPENDIX F Preliminary Foundations Design Report
APPENDIX G MTO Correspondence
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering iv
Table of Content
INTRODUCTION ............................................................................................................. 1 1.0
Project History .............................................................................................................. 1 1.1
Preliminary Design Report............................................................................................ 2 1.2
ENVIRONMENTAL ASSESSMENT PROCESS ............................................................... 3 2.0
Public Consultation Summary .....................................................................................14 2.1
Public Information Session #1 – Federal EA and MTO Class EA .........................14 2.1.1
Public Information Sessions #2 and #3 ................................................................14 2.1.2
EXISTING CONDITIONS ................................................................................................15 3.0
Transportation .............................................................................................................15 3.1
Traffic ...................................................................................................................15 3.1.1
Posted Speed ......................................................................................................16 3.1.2
Horizontal Alignment ............................................................................................16 3.1.3
Vertical Alignment ................................................................................................16 3.1.4
Cross Section .......................................................................................................17 3.1.5
Intersections and Sideroads .................................................................................17 3.1.6
Roadside Safety Hazards .....................................................................................18 3.1.7
Entrances .............................................................................................................18 3.1.8
Illumination ...........................................................................................................18 3.1.9
Geotechnical & Foundations ................................................................................19 3.1.10
Drainage ..............................................................................................................20 3.1.11
Utilities .................................................................................................................20 3.1.12
Environmental Contaminant Screening .......................................................................21 3.2
Mosher Portal Area ..............................................................................................21 3.2.1
Former MacLeod Mine Landfill .............................................................................21 3.2.2
MacLeod High Tailings .........................................................................................22 3.2.3
Highway Maintenance Patrol Yard .......................................................................22 3.2.4
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering v
ALTERNATIVES AND EVALUATION .............................................................................23 4.0
Feasibility Study Report ..............................................................................................23 4.1
Trade-Off Study (TBT Engineering) .............................................................................23 4.2
Preliminary Design ......................................................................................................24 4.3
PROPOSED Design .......................................................................................................29 5.0
Horizontal Alignment ...................................................................................................29 5.1
Vertical Alignment .......................................................................................................29 5.2
Cross Section ..............................................................................................................29 5.3
Intersections and Sideroads ........................................................................................30 5.4
Roadside Safety ..........................................................................................................31 5.5
Traffic Signage and Pavement Markings .....................................................................31 5.6
Drainage .....................................................................................................................31 5.7
Centreline Culverts ...............................................................................................31 5.7.1
Roadside Ditch Design .........................................................................................32 5.7.2
Water Management ..............................................................................................32 5.7.3
Entrances ....................................................................................................................32 5.8
Illumination ..................................................................................................................33 5.9
Snow Plough Turnarounds and Truck Inspection Stations ..........................................33 5.10
MTO Patrol Yard .........................................................................................................33 5.11
Geotechnical Pavement Design ..................................................................................33 5.12
Preliminary Geotechnical Foundation Study ................................................................36 5.13
Materials Management and Aggregate Sources ..........................................................37 5.14
Utilities ........................................................................................................................38 5.15
Property ......................................................................................................................38 5.16
Construction and Traffic Staging .................................................................................38 5.17
ADDITIONAL ConTamiNATED PROPERTY Requirements ...........................................39 6.0
CORRIDOR CONTROL ..................................................................................................40 7.0
PERMITTING .................................................................................................................40 8.0
Corridor Control Permits ..............................................................................................40 8.1
Building and Land Use Permits ............................................................................40 8.1.1
Encroachment Permits .........................................................................................41 8.1.2
Entrance Permits ..................................................................................................41 8.1.3
Construction Permits ...................................................................................................42 8.2
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering vi
LEGAL AGREEMENT.....................................................................................................42 9.0
SCHEDULE ....................................................................................................................42 10.0
CONSTRUCTION COST ESTIMATE .............................................................................43 11.0
CLOSURE ......................................................................................................................43 12.0
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 1
INTRODUCTION 1.0
Premier Gold Mines Limited (Premier) retained TBT Engineering Limited (TBTE) to
prepare a Preliminary Design Report (PDR) for the proposed realignment of provincial
and municipal roadways outside of the Hardrock property gold mine project (Project).
The Project is being located primarily on private, patented lands owned by Premier in the
District of Thunder Bay, within the Municipality of Greenstone, and the Geographical
Townships of Errington and Ashmore in Northwestern Ontario. One of the project
components in developing this mining project is the realignment of Highway 11 and
Michael Power Boulevard outside of the footprint of the proposed mining operations.
Highway 11 is classified as a rural arterial undivided (RAU 110) King’s Highway which
provides access across northern Ontario and links several small communities. The
segment of Highway 11 affected by the proposed realignment is 4.7 km in length in an
east – west direction located south of the community of Geraldton, ON, approximately
280 km northeast of Thunder Bay, ON. The project location is depicted in Figure 1.1.
Figure 1.1 – Project Location
Project History 1.1
A Feasible Route Study was completed by Premier in 2013 during their Project Planning Phase. The route study identified six possible alignment alternatives for Highway 11; five bypassed the Project to the north and one to the south. Following further Project planning and preliminary infrastructure design functions, a 500 m safety offset buffer was introduced surrounding the proposed open pit. This requirement removes four of the
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 2
potential alignments. Premier completed a Highway Alignment Evaluation Summary Report in 2014 which assessed and optimized the two remaining alternatives (1A & 1B) and added a third alternative (1D) with improved geometry, exceeding the minimum design requirements, and intersects Michael Power Boulevard at the most favourable angle of the alignment alternatives. Through consultation with the Ministry of Transportation, it was determined that Alternative 1D provides the best horizontal and vertical alignments of the options available. On the basis of the findings contained within the Feasible Route Study and Highway Alignment Evaluation Summary, and in consideration of the intentions and perspective of both Premier and MTO, Alternative 1D was determined to be the preferred route. Alternative 1D has significant advantages in terms of alignment geometry, changes in travel distances for road users and changes in highway maintenance effort.
Preliminary Design Report 1.2
As the MTO will be the ultimate owner of the relocated Highway 11 and as the MTO is expecting that the detail design and construction of the relocated portions of the Highway 11 alignment are undertaken in a manner consistent with MTO process, standards and design criteria, this Preliminary Design Report has been prepared to provide a concordance between Premier’s EA process and engineering design for development of the Project. This Preliminary Design Report has been prepared to present a preliminary engineering design for the preferred alternative 1D route selected from the planning phases and to document the evaluation of alternative alignments.
Contributors to the PDR are:
Premier Gold Mines Limited
Stantec Consulting Ltd.
TBT Engineering Limited
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 3
ENVIRONMENTAL ASSESSMENT PROCESS 2.0
The Final Environmental Assessment (EA) Report for the Hardrock Project which includes the realignment of Highway 11 will be developed and structured in a manner that follows an Approved Provincial Terms of Reference and the Federal Environmental Impact Statement (EIS) guidelines, as directed by the Ministry of the Environment and Climate Change (MOECC) and the Canadian Environmental Assessment Agency (CEAA). Environmental and socio-economic concerns associated with the design, construction, and maintenance of the recommended Highway 11 realignment are addressed using information obtained from environmental baseline studies that will be incorporated into the EA report for the Project. Table 2.1 is intended to summarize and illustrate concordance between the Hardrock Project EA and the MTO Class EA principles. Table provides an overview of environmental features that may be impacted by highway realignment works, as well as a summary of potential environmental effects, proposed mitigation to minimize adverse effects, and commitments to further work.
In addition to the information supplied in Table 2.1, further details of concordance with the Class EA process are provided in this preliminary design document. More specifically, planning alternatives, from the perspective of the Hardrock Project as a whole, including consideration of the Highway 11 realignment component, are described in Section 4.0 of this Preliminary Design Report (PDR).
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 4
Table 2.1 MTO Class EA Principles within Premier Gold Mines Limited Environmental Assessment
Component MTO Principles Background Conditions Environmental
Concerns Identified
for Proposed Highway
11 realignment
Mitigations and Commitments to
Further Work
Soils Identify soils features that
may be threatened by
Highway 11 realignment
objectives.
Develop environmental
design and mitigation
concepts as necessary for
minimizing erosion and
sedimentation, loss of soils
and soil contamination as a
result of Highway 11
realignment works.
The dominant landforms of the proposed Highway 11 realignment study area are anthropogenic through the Highway Maintenance Patrol Yard, MacLeod High Tailings and in the area of the existing utility corridor and Mosher Portal, with organic, glaciofluvial and till areas throughout the remainder.
The area in the western vicinity of the proposed Highway 11 realignment is generally poorly drained, with small rapid drainage pockets. Drainage in the MacLeod High Tailings area is generally poorly drained, with small well drained areas in the east of the proposed realignment near the Highway Maintenance Patrol Yard.
Native soil types in the proposed Highway 11 realignment study area are classified as developed land through the Highway Maintenance Patrol Yard and MacLeod High Tailings areas, with remaining areas, and primarily Scotia (Eluviated Dystric Brunisol developed on medium-textured morainal (till) deposits, typically well-drained, some surface stoniness, and often thin over bedrock) and Dunbar (Orthic Humic Gleysol developed on medium-textured morainal (till) deposits, typically poorly-drained, some surface stoniness, and often thin over bedrock) with small pockets of Jeannie (Eluviated Dystric Brunisol developed on coarse-textured glaciofluvial deposits, typically rapidly-drained, some surface stoniness, some sites with high gravel content, and often thin over bedrock) to the immediate east of Mosher Lake.
None identified. Premier Gold Mines Limited will
conduct ongoing monitoring
during design and construction
and, using adaptive management
techniques, address any
concerns that may arise.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 5
Component MTO Principles Background Conditions Environmental
Concerns Identified
for Proposed Highway
11 realignment
Mitigations and Commitments to
Further Work
Groundwater Identify groundwater
features (quantity and
quality) that may be
threatened by Highway 11
re-alignment objectives.
Develop environmental
design and mitigation
measures to minimize
impacts to groundwater
quality (increased
pollutants) and quantity
(fluctuation on groundwater
levels), runoff (water
quantity) to groundwater
recharge areas, and well
water levels and quality due
to the proposed design.
Avoid contamination of
groundwater.
Groundwater flow is generally to the east towards
Kenogamisis Lake and topographically controlled,
discharging in low-lying surface waters and
recharging at higher elevations.
The overburden is considered to be hydraulically
connected to the underlying bedrock (shallow).
Groundwater elevations are generally found 1 – 2
meters below ground surface.
During background (considered unaffected by
historic mining activities) groundwater sampling
for baseline studies (Stantec Consulting Limited,
2015), several parameters were found to exceed
Ontario Drinking Water Quality Standards,
ODWQS (Iron, Manganese, Arsenic)
Groundwater sampling within historic mining areas
showed ODWQS exceedances for iron, free
cyanide, manganese and arsenic.
Ground water within the
upper overburden has
been estimated to exist
within 1 - 2 m of ground
surface. The
groundwater levels can
be expected to reach
ground surface and will
vary seasonally and in
response to
precipitation.
Several parameters in
groundwater were found
to exceed ODWQS
guidelines during
Environmental Baseline
studies (iron,
manganese, free
cyanide, arsenic).
Further investigations and testing and preparation of a Geotechnical Design Report will be completed for the recommended alignment.
To prevent groundwater contamination, a spill prevention plan will be developed and implemented, and contingency plans and procedures will be in place to respond to any spills.
Premier Gold Mines Limited will conduct ongoing monitoring during design and construction and, using adaptive management techniques, address any concerns that may arise.
Fisheries and
Aquatic
Habitat
Identify fisheries and
aquatic habitat features that
may be threatened by
Highway 11 re-alignment
objectives.
Develop environmental
design and mitigation
concepts for minimizing
erosion and sedimentation
(including erosion and
sedimentation into
The various watercourses to be crossed by the proposed realignment (WC-C, D, F, and I) of Hwy 11 provide marginal warmwater fish habitat. Fish species sensitivity is considered low, due to the presence of only baitfish. The watercourses are generally low gradient, low energy systems characterized by single channels with the occasional riparian-zone wetland habitat. Habitat sensitivity is considered low, due to the common and widespread nature of the habitat present.
Mosher Lake, located immediately west of the proposed Hwy 11 realignment, is a small and
The proposed route includes crossings of several very small unnamed watercourses. Potential effects are anticipated to be minor, since more sensitive habitats will be avoided and crossings will follow MTO standards. As such, impacts to fish
Best management practices and standard measures will be applied to maintain fish passage and prevent negative impacts to fish and fish habitat. Crossing structures will be sized to accommodate a minimum 50 yr flow unless identified otherwise.
The final detail design will be completed following principles of MTO / DFO / OMNR Fisheries Protocol (MTO / DFO / OMNR
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 6
Component MTO Principles Background Conditions Environmental
Concerns Identified
for Proposed Highway
11 realignment
Mitigations and Commitments to
Further Work
watercourses).
Develop environmental
design and mitigation
measures to minimize direct
or indirect loss of aquatic
habitat, changes to water
quality / quantity, inhibiting
fish passage or reduced fish
productivity.
shallow (5m deep) lake, supporting a coolwater fish community that includes pike, perch, and white sucker. Sensitive habitat near the proposed Hwy 11 realignment includes yellow perch spawning habitat along the east shore, near the outlet of WC-A.
Barton Bay (East & West) of Kenogamisis Lake, is located north of the proposed Hwy 11 realignment and is a shallow (<2m deep) bay of the lake, supporting a coolwater fish community that includes walleye, pike, and perch. Sensitive habitat near the proposed Hwy 11 realignment included northern pike spawning habitat along the south shore, near the outlet of WC-C.
Sampling in the study area between 2013 and 2014 did not provide evidence of any aquatic species at risk either under federal or provincial legislation.
The variability in the benthic invertebrate community data was generally a result of differences in habitat availability (i.e. substrates) as opposed to sediment or water quality impairments.
passage concerns and alteration or destruction of existing fish habitat will be avoided.
No direct or indirect effects are expected to local waterbodies along the remainder of the alignment or those downstream of each watercourse crossed.
Version 2, 2013 and as subsequently amended).
Premier Gold and their sub-consultants will conduct ongoing monitoring during construction, using adaptive management techniques to address any concerns that may arise.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 7
Component MTO Principles Background Conditions Environmental
Concerns Identified
for Proposed Highway
11 realignment
Mitigations and Commitments to
Further Work
Vegetation and
Ecosystems
Identify rare plants or
sensitive ecosystems that
may be threatened by
Highway 11 re-alignment
objectives.
Develop environmental
design and mitigation
concepts as necessary for
minimizing severance of /
encroachment on sensitive
ecosystems.
Develop environmental
design and mitigation
concepts as necessary that
minimize effects on ANSI’s,
ESA’s, Provincially
significant wetlands,
provincially rare species,
NEC “Natural Areas”,
cultural / heritage, social /
economic landscape
features, and woodland
resources.
A unique vegetation community feature in the
form of a sparse treed fen (Ecosite B136) was
noted near the outlet of WC-C during the baseline
surveys.
No plant species at risk were recorded in the
study area during any of the baseline surveys.
The main vegetation cover types associated with
the Hwy 11 realignment are: 1) dry to fresh,
coarse loamy, jack pine-black spruce dominated,
2) rich conifer swamp, and 3) compact gravelled
surface. A significant area of compact gravelled
surface will be traversed due to previous
development activities in the area.
Vegetation removal
will be required along
the planned
realignment. A small
amount (28 ha, max)
of vegetation will need
to be cleared for the
preferred route.
However, potential
effects are anticipated
to be minor, given the
narrow width (~60m)
and short length
(4.7km) of the new
section.
A unique ecosite
(B136 - sparse treed
fen) was noted near
the outlet of WC-C,
and efforts to avoid
fragmentation of the
habitat will be taken to
maintain habitat
functionality.
The unique ecosite (B136 - sparse treed fen) identified in the area of the realignment will not be fragmented by the preferred route, since the northern ROW boundary skirts, only partially, along the southern perimeter of the fen.
Refer to mitigation measures and commitments identified for groundwater, surface water, and fisheries and aquatic habitat.
If necessary, Premier Gold will develop a habitat management program that to address any potential compensation required as a result of the realignment of Hwy 11.
Wildlife Identify wildlife or habitat
features that are threatened
by Highway 11 re-alignment
objectives.
Develop environmental
design and mitigation
concepts as necessary for
Two mammalian species at risk (Little Brown
Myotis and Northern Myotis) were identified during
field investigations. No bat hibernacula or bat
maternity colonies were found during field
investigations, although mature trees suitable for
bat roosting may be found in the vicinity of the
Highway 11 realignment, based on the FRI
vegetation communities identified.
If unavoidable,
impacts to habitat of
SAR species,
protected either
federally (SARA) or
provincially (ESA), will
require a permit and
compensation to offset
If necessary, Premier Gold will develop a habitat management program to address potential impacts to wildlife and wildlife habitat as a result of the realignment of Hwy 11.
Premier Gold is completing permitting under the Species at
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 8
Component MTO Principles Background Conditions Environmental
Concerns Identified
for Proposed Highway
11 realignment
Mitigations and Commitments to
Further Work
minimizing the destruction
of wildlife habitat, barrier
effects on travel corridor(s),
adverse impacts on rare,
threatened or endangered
Species, and wildlife –
vehicle accidents.
The proposed Hwy 11 realignment will include
some minor encroachments within wetland
habitat. Kenogamisis Lake is considered
significant wildlife habitat for waterfowl stopover,
staging, and nesting purposes, including the
associated wetland habitat.
Potential late winter habitat for moose was
identified along the proposed Hwy 11 realignment
just east of Mosher Lake. However, relative
importance was considered low due to the
abundance of similar habitat in the general area.
No moose aquatic feeding areas (MAFA) were
noted within proximity to the proposed Hwy 11
realignment during baseline surveys.
A relatively high level of avian species diversity
was noted in the area, which reflects the variety of
habitats available. The vast majority of bird
species observed in the vicinity are migratory.
Bald eagles have regularly been recorded during
various inventories in proximity to the proposed
realignment of Hwy 11. It is likely that eagles use
Kenogamisis Lake as a feeding area. However,
no bald eagle nest or nests of other raptor species
were identified within close proximity to the
proposed Highway 11 realignment.
Baseline studies and SAR surveys identified five
avian SAR in proximity to the proposed Hwy 11
realignment, including four Threatened species
and one Special Concern species. Two of the
Threatened species (Canada warbler and
common nighthawk) are protected federally under
impacts.
Potential effects of the
realignment on wildlife
existing in the area are
expected to be minor,
given the narrow width
(~60m) and short
length (4.7km) of the
new section, and the
current extent of
residential,
commercial, and
infrastructure
development in the
general area.
Risk Act and Endangered Species Act for the entire
proposed development area, which will include any areas affected by the Hwy 11 realignment.
Permit applications will consider impacts to Species at Risk and their habitat, including impacts that may require compensation.
Premier Gold and their sub-consultants will conduct ongoing monitoring during construction, using adaptive management techniques to address any concerns that may arise.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 9
Component MTO Principles Background Conditions Environmental
Concerns Identified
for Proposed Highway
11 realignment
Mitigations and Commitments to
Further Work
SARA, and the other two (barn swallow and bank
swallow) are protected provincially under the ESA.
The official status of the Special Concern species
(eastern wood pewee), does not yet afford it legal
protection either federally or provincially.
Based on the proposed Hwy 11 realignment,
habitat of SAR species such as Canada warbler,
common nighthawk, and eastern wood pewee
was documented that would be intersected by the
Hwy 11 realignment.
The general use of the area by other SAR species
such as barn swallow and bank swallow should
also be considered when appropriate conditions
are noted for these species.
Air Quality and
Sound
Identify potential
exceedances of relevant air
quality or noise guidelines in
relation to Highway 11 re-
alignment works.
Develop environmental
design and mitigation
concepts as necessary for
minimizing impacts to
sensitive receptors as a
result of air emissions and
noise from road
construction works.
Background air quality is expected to be good,
given the absence of nearby large urban centres
and industrial sources. Local anthropogenic air
emission sources include road traffic, the Town of
Geraldton and drilling associated with exploration
activities.
The primary contaminants of concern are
particulate matter and metals.
The proposed Highway 11 realignment site is
regarded as a Class 2 area – i.e. “urban hum” or
traffic noise dominates the daytime acoustical
environment while sound from natural
environment dominates the night-time
environment.
None identified. Premier Gold Mines Limited will monitor noise levels during highway construction activities in order to minimize acoustic impacts.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 10
Component MTO Principles Background Conditions Environmental
Concerns Identified
for Proposed Highway
11 realignment
Mitigations and Commitments to
Further Work
Surface Water
(Hydrology
and Water
Quality)
Identify surface water
features (quantity and
quality) that may be
threatened by highway
realignment objectives
Develop environmental
design and mitigation
measures as necessary to
avoid increased water
quantity to receiving
watercourses (flood levels
and erosion), surface
erosion / runoff to receiving
watercourses, and / or
pollutants to receiving
watercourse (water quality)
The proposed Highway 11 realignment is located
in the Kenogamisis Lake watershed. This is part
of the Lake Superior watershed due to
hydroelectric power diversion activities.
The proposed Highway 11 realignment is in an
area crossing four small unnamed watercourses
(watercourses C, D, F and I), as well as a low
lying wetland area to the west of the MacLeod
High Tailings, and Mosher Lake to the west of the
alignment.
There are no known municipal water sources
within the proposed Highway 11 realignment area.
The Town of Geraldton takes drinking water from
Cecile Lake.
The climate normal annual precipitation for the
proposed mine area, in which the Highway 11
realignment is located, is 765 mm.
Year to year trend hydrological analysis for three
creeks within the proposed mine study area (but
outside the proposed highway corridor) show
defined sharp peaks in June, low flow through
summer and minor peaks in the autumn months.
Water quality results from Watercourse C in
recent years typical met Provincial Water Quality
Objectives (PWQO); however, arsenic, iron, and
cobalt were consistently present at elevated
concentrations, and did not meet PWQO in
numerous samples. Arsenic exceeded PWQO
objectives in all samples observed.
The preferred route
includes the crossing
of three small
watercourses,
identified as
Watercourses C, D, F
and I.
Drainage associated
with the re-aligned
highway will be
managed by open
ditches and culverts
(as noted in Section
5.7.1 and 5.7.2 of this
PDR).
Arsenic, iron and
cobalt consistently
elevated in waters
from Watercourse C.
Refer to mitigation measures / commitments identified above for fisheries and aquatic habitat.
Best practices will be used to manage stormwater, and a Drainage and Hydrology Report will be completed during Detail Design (as noted in Section 5.7.1 of this PDR).
To prevent surface water contamination, a spill prevention plan will be developed and implemented, and contingency plans and procedures will be in place to respond to any spills.
Premier Gold Mines Limited will conduct ongoing monitoring during design and construction and, using adaptive management techniques, address concerns that may arise.
Aboriginal Identify traditional land use Traditional uses of the area identified through None identified. No concerns were identified
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 11
Component MTO Principles Background Conditions Environmental
Concerns Identified
for Proposed Highway
11 realignment
Mitigations and Commitments to
Further Work
Traditional
Land Use
that may be threatened by
highway realignment
objectives
Develop environmental
design and mitigation
measures as necessary to
minimize impacts from
Highway 11 re-alignment
works on traditional land
uses.
consultation activities include trapping, fishing,
and hunting
– however Premier Gold Mines Limited will undertake additional Stage 2 archaeological assessment in previously identified areas of archaeological potential if necessitated by changes to the layout of the Highway 11 realignment.
Non-
Traditional
Land and
Resource Use
(including
Community
/ Recreation,
Agriculture,
and
Commercial /
Industrial)
Identify non-traditional land
use that may be threatened
by highway realignment
objectives
Develop environmental
design and mitigation
measures as necessary to
minimize impacts from
Highway re-alignment works
on non-traditional land
uses.
The proposed Highway 11 realignment runs
through the back nine and adjacent to the front
nine of the Kenogamisis Golf Club.
The eastern portion of the realignment runs
through a recreational trail that exists on a portion
of the tailings and north along the Lake.
No significant features are identified in the
Highway 11 realignment area in the Greenstone
Official Plan (Appendix F).
No Provincially significant features such as
provincially significant wetlands or protected areas
are located in the Highway 11 realignment study
area.
Use of and access to the
Kenogamisis Golf Club
as a result of the
Highway 11 realignment
may be temporarily
disrupted or eliminated
during re-alignment
construction works.
Premier Gold Mines Limited will continue ongoing stakeholder consultation as part of the EA process.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 12
Component MTO Principles Background Conditions Environmental
Concerns Identified
for Proposed Highway
11 realignment
Mitigations and Commitments to
Further Work
Archaeological
and Cultural
Heritage
Resources
Identify archaeological and
cultural heritage features
that may be threatened by
Highway 11 re-alignment
objectives.
Develop environmental
design and mitigation
measures as necessary to
avoid the loss of
archaeological and cultural
heritage resources.
A Stage 1 Archaeological Assessment undertaken
by Stantec Consulting Limited for Premier Gold
Mines Limited has indicated that the MacLeod
Townsite may contain early 20th
century
settlements, and testpitting in this area is
recommended if affected by the proposal.
The majority of the eastern portion of the
proposed Highway 11 realignment consists of the
MacLeod High Tailings impoundment and
Kenogamisis Golf Club. Any archaeological
potential has been removed and no further
archaeological field work is recommended in this
area.
Little to no archaeological potential was identified
within the proposed Highway 11 realignment area,
with the exception of areas along the limits of
roadways and waterbodies.
A Stage 2 Archaeological Assessment was
completed as recommended by the Stage 1
Assessment. No archaeological resources were
identified during the Stage 2 Assessment found
Small areas of potential
archaeological interest
along roadways and
water bodies identified.
Highway 11 realignment
works are not
associated with any pre-
contact or historic, nor
any built heritage sites.
No archaeological
resources identified
during Stage 2
Archaeological
Assessment.
Premier Gold Mines Limited will conduct ongoing monitoring during design and construction and, using adaptive management techniques, address any concerns that may arise.
Premier Gold Mines Limited will undertake additional Stage 2 archaeological assessment in previously identified areas of archaeological potential if necessitated by changes to the layout of the Highway 11 realignment.
Consultation Consultation will be used to
assist in the identification of
data requirements.
The proponent will
constructively address input
received during the
consultation process.
Premier Gold Mines Limited initiated consultation
in 2008 in advance of the EA process.
A Project website, local office in Geraldton,
regular newsletter, Public Information Centres
(meetings with agencies and stakeholders) and
direct mailing have all been undertaken by
Premier gold Mines Limited to share information.
Specific concerns
raised by interested
stakeholders were
related potential effects
on the Hardrock Project
as a whole are
addressed in the
Project Terms of
Premier Gold Mines Limited will continue ongoing stakeholder consultation as part of the EA process.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 13
Component MTO Principles Background Conditions Environmental
Concerns Identified
for Proposed Highway
11 realignment
Mitigations and Commitments to
Further Work
During later planning and
design phases, the
proponent will show how the
input received in earlier
stages affected the project.
The amount, extent and
timing of consultation will
vary according to the
complexity of a specific
project, the nature of the
specific environmental
issues, and the concerns
expressed by the public and
external agencies.
The proponent will make
reasonable efforts to
resolve concerns.
Premier Gold Mines Limited identified potentially
interested aboriginal groups (listed in the Terms of
Reference documents) as part of the Hardrock
project EA.
Other Stakeholder participants identified in the
Hardrock EA included property owners in the
immediate Project vicinity, residents and business
owners in the municipality of Greenstone, non-
governmental organizations and groups with an
interest in the Undertaking, local land users
including hunters, trappers and fishermen and
agencies including a Government Review Team,
municipal representatives and Planners.
Comments provided by MTO on the Highway 11
realignment Feasibility Report are appended to
this PDR (Appendix G).
Reference (Stantec
Consulting Limited,
December 29, 2014).
*Project information taken from Environmental Baseline reports by Stantec Consulting Limited (January 2015), as well as monitoring data provided by Premier
Gold Mines Limited.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 14
Public Consultation Summary 2.1
Public Information Session #1 – Federal EA and MTO Class EA 2.1.1
The first series of PICs were held in Longlac, Geraldon, Nakina and Long Lake #58 First Nation on June 24 and 25, 2014. Premier was pleased to offer the opportunity to hold an event on-reserve for Ginoogaming First Nation and Aroland First Nation, and in Thunder Bay for Métis members. While Premier followed up on these offers, the groups elected not to follow through on the opportunities. The purpose of the PIC was to introduce the Project, and provide information about Premier, the EA process to be followed, the federal Project Description Report, the Transportation Needs Assessment component of the MTO Class EA, environmental baseline activities, and planned consultation activities. Copies of the draft federal Project Description report were available at the sessions for review and questions from attendees. Participants provided comments on suggested locations for relocation of Highway 11, as well as possible business and employment opportunities in the future. Concerns were expressed regarding potential environmental impacts of the Project as it was known at that time, including:
Potential impacts to water quality, specifically related to Kenogamisis Lake; Potential impacts to Kenogamisis golf course as a result of the pit proximity and highway
realignment; and, Proposed location of the Tailings Management Facility and mine waste rock piles.
Attendees at Long Lake #58 also requested that traditional knowledge be incorporated into project planning.
A summary report detailing the planning and outcomes of this round of PICs is included as Appendix A, including comments received and responses from Premier. Individuals submitting comments at the PIC received a response in writing from Premier.
Public Information Sessions #2 and #3 2.1.2
The second series of PICs were held in Longlac, Geraldon, and Nakina on September 22, 23 and 24, 2014. At each of these sessions, Premier delivered a presentation entitled ‘Hardrock Project Update - Provincial EA Process - Development of Terms of Reference for the EA – Getting Involved in the Process’. Participants were encouraged to ask questions and provide comments related to the presentation content which included a Project overview and update, the EA process, developing the draft ToR, the consultation process and how the public would like to be involved. Overall, there was positive interest in the Project as participants noted that it would bring socio-economic benefits to the Greenstone region. The third series of PICs were held in Longlac, Geraldon, and Nakina on October 28 and 29, 2014. At each of these sessions, Premier delivered a presentation entitled ‘Hardrock Project Update - EA Terms of Reference – What we heard from you – Draft Terms of Reference’. Participants were encouraged to ask questions and provide comments related to the presentation content, which included a description of the Project, the
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 15
purpose of the ToR, and what Premier heard during ToR PIC #2 on how the community wanted to be consulted. The presentation continued with the rationale for the Project, alternatives assessment, the existing environment, potential effects, commitments and monitoring, the consultation plan for the EA and next steps. In addition to the questionnaire typically provided at Premier PICs, a Land and Resource Use (LRU) questionnaire was provided to gather information on traditional and subsistence uses of the land in the area of the Project. This LRU questionnaire was made available at the Geraldton office throughout the EA process. As with previous PICs, there was a positive interest in the Project as it brings socio-economic benefits to the Greenstone region.
EXISTING CONDITIONS 3.0
The following section describes the existing transportation conditions within the study
area and provides an overview of the Environmental Contaminant Screening Report
(ECS).
The existing environmental conditions, aside from those mentioned above, have been
described by environmental baseline studies completed by others and are not included
within this report. Baseline Environmental data will be available in the Hardrock Project
EA Report.
Transportation 3.1
This section documents the existing transportation conditions of the study area. The
study area has been defined in Exhibit 3.1. Highway 11 and Michael Power Boulevard
(MPB) are the two most prominent transportation facilities located in the study area.
Within northwestern Ontario, Highway 11 is classified as a Rural Arterial Undivided
King’s Highway with a design speed of 110 km/hr (RAU 110). MPB is a paved sideroad
providing the community of Geraldton access to Highway 11 and serving as a connecting
link between Highway 11 and Highway 584.
In addition to engineering surveys undertaken by TBT Engineering, MTO Plans
(B&C896-11-2, B&C896-11-3 and B&C895-11-1) were referenced to assist in developing
the description of existing geometric conditions.
Traffic 3.1.1
Previous traffic studies within the project limits were divided into two sections: Hwy 584
Westerly (Section 1) and Hwy 584 Easterly (Section 2). Traffic data for Section 1 was
obtained from MTO’s iCorridor – Transportation Planning & Forecasting online program.
For section 1 the program was limited to observed traffic rates in 2006.
Traffic data for Section 2 was provided by MTO and included Average Annual Daily
Traffic (AADT), Summer Average Daily Traffic (SADT), Design Hour Volume (DHV),
Percent Commercial Traffic and Percent Long Truck traffic observed in 2007. Traffic
volumes are summarized in Table 3.1.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 16
Table 3.1 – Existing Traffic Volumes
LOCATION YEAR AADT SADT DHV % COMM % LT
HWY 11 From Hwy 584 Westerly 2006 1850 - - 29.6 % 25.5 %
HWY 11 From Hwy 584 Easterly* 2007 1500 1750 150 47.3 % 40.9 %
*LHRS 17880 O/S 0.0 km TO Goldfield Rd LHRS 17880 O/S 4.7 km
Posted Speed 3.1.2
The posted speed within the project area ranges from 70 km/h to 90 km/h.
The posted speed on Highway 11 is 90 km/hr and is reduced to 70 km/h within the
vicinity of the Michael Power Boulevard and Highway 11 intersection.
The posted speed on Michael Power Boulevard is 80km/hr. The speed limit is reduced to
70 km/h within the vicinity of the Highway 11 intersection.
Horizontal Alignment 3.1.3
This section of Highway 11 contains three horizontal curves. All curve radii exceed the
design standard for a design speed of 110 km/h. Curve locations and radii are provided
in Table 3.2.
Within the study area Michael Power Boulevard has one horizontal curve with a radius of
250m (80 km/h design speed).
Table 3.2 - Existing Horizontal Curves on Highway 11
P.I. Station Township Radius
(m)
Design Speed
(km/hr)
17+150 Errington 3490 m >120
11+049 Ashmore 1747 m >120
Unavailable* Ashmore 1500 m >120
* B&C Plans unavailable east of 11+900 Ashmore. Radius estimated using TBT survey of existing crown.
Vertical Alignment 3.1.4
The majority of vertical curves meet or exceed the design standard for a design speed of
110 km/hr. The existing vertical curves are summarized in Table 3.3. The maximum
longitudinal grade is 1.3% and extends for approximately 200 meters.
Table 3.3 – Existing Vertical Curves on Highway 11
P.I. Station Township Curve
Type
K Design Speed
(km/hr)
16+642 Errington Crest 100 110
16+801 Errington Crest 70 100
17+054 Errington Sag 240 >120
17+618 Errington Crest 580 >120
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 17
17+965 Errington Sag 240 >120
18+249 Errington Crest 750 >120
18+757 Errington Sag 270 >120
19+163 Errington Crest 130 >120
19+476 Errington Crest 570 >120
19+739 Errington Sag 460 >120
10+471 Ashmore Sag 70 >120
10+685 Ashmore Crest 370 >120
10+847 Ashmore Crest 50 90
11+375 Ashmore Sag 250 >120
11+823 Ashmore Crest 290 >120
Cross Section 3.1.5
Within the project area Highway 11 has the following cross section elements:
Pavement Width: Two 3.5 m through lanes
Shoulder Width: 2.0 m – 2.5 m
0.5 m partial paved shoulder where granular shoulders are present
Rounding Width: 0.5 m
Right-of-Way: 60.96 m
Within the project area Michael Power Boulevard has the following section elements:
Pavement Width: Two 3.5 m through lanes
Shoulder Width: 1.5 m
0.5 m partial paved shoulder where granular shoulders are present
Rounding Width: 0.5 m
Right-of-Way: 30.48 m
Intersections and Sideroads 3.1.6
There are three sideroads located within the project limits which include Midlane Street,
Hard Rock Drive and Michael Power Boulevard.
Midland Street is an unpaved sideroad that forms a ‘T’ intersection with Highway 11. This
intersection consists of a simple open throat design.
The intersection of MPB, Hardrock Drive, and Highway 11 is a partially channelized
intersection. Channelized right turn movements with raised median islands are provided
for Highway 11 westbound traffic turning northbound on Michael Power Boulevard and
southbound Michael Power Boulevard traffic turning westbound onto Highway 11. An
auxiliary left turn lane is provided for Highway 11 eastbound traffic turning north onto
Michael Power Boulevard.
Highway 11
Michael Power Boulevard
Mosher Lake
Kenogamisis Lake
Waterco
urse D
Watercourse F
Watercourse E
Watercourse B Water
cour
seC
WatercourseH
SW ArmTributary
Watercourse G
Watercourse a
Macleod HighTailings
Macleod LowTailings
LittleLonglacTailings
HardrockHistoricTailings
CloutierPit
Mosher Pit(Premier)
0 330 660m
1:15,000
Y:\Pr
ojects
\2014
\14-04
1 Prem
ier G
old G
eraldt
on\G
IS\Pr
emier
Gold
- Mar
25 (F
or GW
) Fig
2.mxd
Revis
ed: 2
015-0
3-31 B
y: cm
itche
llLegend
WatercourseRailwayPower Transmission LineRecreational TrailOpen Pit 500m BufferOpen PitHighway 11Major RoadLocal RoadPit or QuarryWaterbodyGolf CourseHistoric TailingsWetlandSatellite PitStudy Area
Notes1.
2.
3.
Coordinate System: NAD 1983 UTM Zone 16N
Base features produced under license with the Ontario Ministry of Natural Resources © Queen's Printer for Ontario, 2013.
Orthoimagery © Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation, 2014
Exhibit 3.1- Study Area
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 18
Hardrock Drive is a paved sideroad extending southerly from Highway 11 providing
access to the Hardrock townsite. The total cross section width is approximately 11.0
meters.
Within the study area there are two sideroads intersecting Michael Power Boulevard.
Sunset Drive is an unpaved sideroad providing services to the MacLeod community.
Barrick Drive is a paved sideroad providing access to the Discover Geraldton Interpretive
Centre and the Barton Bay Wildlife Trails. Both sideroads have a total cross section
width of approximately 10.0 meters.
Roadside Safety Hazards 3.1.7
There are minimal roadside safety concerns along the existing section of Highway 11
within the study area. The majority of rock cut heights are less than 2 meters have been
relocated beyond a 7 meter clearzone.
There is one three cable guide rail installation addressing a safety hazard associated
with a high embankment and steep fill slope.
Entrances 3.1.8
Within the project limits there are twelve private entrances along Highway 11 and five
private entrance along Michael Power Boulevard.
The O.P.P entrance located at station 19+850 Lt Errington (MTO Plan B-896-11-3)
consist of a westbound right turn lane and taper and eastbound left turn slip around.
There is one truck inspection station (paved partial width) located at station 10+250 Rt
Ashmore (MTO Plan B-895-11-1)
An MTO patrol yard is located at the east limit of the study area. The purpose of this
facility is to provide storage of equipment and materials necessary for highway
maintenance. There are currently two entrances providing access to the facility.
Illumination 3.1.9
Highway 11 has partial illumination at the Michael Power Boulevard intersection. There
are a total of four luminaires with high pressure sodium lamps and drop lenses. The
luminaires are located on Highway 11 at the northwest and southeast corners and
approximately 100m east of the intersection for the channelized right turn movement.
One luminaire is located approximately 50m north of the intersection on Michael Power
Boulevard for the channelized right turn movement.
Within the study area Michael Power Boulevard has illumination throughout. The
luminaires are located along the east side of the road on joint-use poles with Bell and
Hydro.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 19
Geotechnical & Foundations 3.1.10
Geotechnical investigations were completed along the existing and proposed highway
alignments. Results of the preliminary findings are summarized below and further
discussed in the appended Preliminary Foundation Design Report and Preliminary
Geotechnical Design Report.
Pavement Structure
Highway 11 and Michael Power Boulevard are paved rural roadways with open roadside
ditches and corrugated steel culverts at cross-drainage locations. The pavement
structure for Highway 11 includes 100 to 150 mm of hot-mix asphalt, 150 mm crushed
granular base (generally substandard in gradation for Granular ‘A’ due to fineness of
gradation) and 800 mm to 1.3 m of sandy granular subbase (generally substandard in
gradation for Granular ‘B’ due to fineness of gradation and/or excess fines).
In general, Michael Power Boulevard includes 80 – 100 mm of hot-mix asphalt, crushed
granular base and 500 mm to 1.0 m of granular subbase fill. Further investigations are
required to develop the detailed geotechnical / pavement design components for new
Michael Power Boulevard.
General Subsurface Conditions
The subgrade conditions within the project limits can be generalized into three
predominant types.
The western portion of the alignment, approximately 1/3 of the project length,
consists of moderate relief, bedrock controlled terrain with thin, discontinuous
deposits of sand and silt.
The middle segment, approximately 1/3 of the project length includes low-lying
terrain occupied by organic deposits atop undulating bedrock and fine grained
soils.
The eastern portion of the alignment, the remaining 1/3 of the project length,
includes historical mine tailings beaches and mine tailings dump (known as
MacLeod High Tailings see Exhibit 3.1).
The MacLeod tailings deposit consists of a large tailings deposit placed over natural
terrain, dating back to the 1930’s. The perimeter of the deposit consists of shaped
tailings with varying side slopes and configurations. Typically in the areas of this
investigation the side slopes are roughly 2.5 horizontal to 1 vertical. Some sections of
the MHT perimeter have a toe berm/drain while other sections do not. A tailings beach is
also evident along much of the toe of the MHT perimeter. The height of the perimeter
typically varies from 6 to 8 m. Reshaping of the perimeter, plus the construction of the
toe berms (where applicable) was completed circa 2000.
It is understood that the original terrain consisted of a low lying swamp which is still
evident at some locations beyond the perimeter of the MHT.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 20
The subsurface soils along the alignment on top of the MHT typically consist of fill/topsoil
at surface underlain by tailings. The tailings are underlain by organic material followed
by silt. The silt is underlain by a till with occasional cobbles before auger and/or SPT
refusal.
The subsurface soils around the perimeter of the MHT typically consists of organic
material or tailings at surface, followed by silt which are underlain by a till with occasional
cobbles before auger and/or SPT refusal.
The geology of the study area has been taken from the 43-101 Mineral Resource
Estimate Update – Hardrock Project, 2014 which sites work by Lafrance, 2004, and OGS
Maps No. 1951-2 and No. 1951-7. The proposed re-alignment is underlain by the
southern sedimentary unit of the Beardmore-Geraldton Greenstone belt, part of the
Wabigoon Subprovince. The southern sedimentary unit is composed of metasedimentary
pile consisting of thick sequences of sandstone-argillite and minor polymictic
conglomerate with interlayered magnetite-chert banded iron formation.
Based on mapping by F.G. Pye, 1949, the re-alignment is restricted to the Quartz
greywacke (sandstone) with minor intercalated conglomerate sequences that have been
cut by dykes composed of diorite, hornblende diorite, and hornblende gabbro. In the
area of Mosher Lake, the re-alignment will be underlain by iron formation, albite porphyry
and intermediate volcanic tuffs and breccias. Structural fabrics in the area of the re-
alignment include the Ellis Syncline, a regional, west-northwest trending syncline that
plunges shallowly to the west-northwest (280o/35o).
Preliminary investigations indicated the groundwater table is present at or near surface
through low-lying muskeg areas and in the order of 15 - 20 m below the elevated
bedrock grade within the western portion of the alignment.
Drainage 3.1.11
The study area is located within the Kenogamisis Lake watershed. Drainage tends to
flow northerly into Barton Bay; a west leg of Lake Kenogamisis.
Highway drainage is achieved through open ditches and transverse culverts. Catch
basins and sewer pipes provide drainage for the curbed islands, ramps and main lanes
at the Highway 11 and Michael Power Boulevard intersection.
Utilities 3.1.12
In addition to MTO’s infrastructure, the following companies and municipalities have
plants within the study area:
Bell Canada
Hydro One
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 21
Union Gas
Greenstone Municipal Services
Environmental Contaminant Screening 3.2
TBT Engineering (TBTE) completed an Environmental Contaminant Screening (ECS) for
a proposed Highway 11 realignment corridor as part of the preliminary design phase for
the Hardrock Gold Mine Project.
The Study Area for this ECS is the proposed 110 m Right of Way (ROW) for the Highway
11 realignment. The ECS identified four Areas of Potential Environmental Concern
(APECs) based on pre-screening. These APECs are, from west to east, the Mosher
Portal Area, Former MacLeod Mine Landfill, MacLeod Low and High Tailings, and a
Highway Maintenance Patrol Yard.
Individual Findings and Evaluations for each APEC are identified in the ECS report under
a separate cover. A general description of these APECs is outlined below, for sites from
west to east along the proposed highway realignment.
Mosher Portal Area 3.2.1
The Mosher Portal Area is currently vacant, and was formerly the site of the Mosher
Mine and a gravel pit (western section). There are two historic, capped mine shafts in
the Mosher Portal Area. Shaft No. 1 is located in the eastern portion, and shaft No. 2 is
located in the western section of the Mosher Portal Area, north of the gravel pit area and
outside of the study area of the ECS. There is a utility corridor along the northern portion
of the Mosher Portal Area, running from west to east to the south of Mosher Lake.
There is one small unnamed watercourse in the area. Watercourse F (identified as per
Stantec baseline reporting) runs north from the existing Highway 11 corridor to Mosher
Lake.
Contaminants of concern in soils and groundwater at the Mosher Portal Area include but
are not limited to suspected arsenic, copper, lead and polychlorinated biphenyls (PCBs),
based on a review of historic reports, as well as suspected petroleum hydrocarbons
(PHCs), BTEX (benzene, toluene, ethylbenzene, xylenes) and polycyclic aromatic
hydrocarbons (PAHs) due to historic mining and gravel pit activities.
Former MacLeod Mine Landfill 3.2.2
This APEC is a former landfill located east of Highway 584 in Geraldton that exists
beneath the practice fairway and chipping green as part of the Kenogamisis Golf Club.
The Landfill site is currently inactive and closed with cover and exists to the south of the
ECS study area. Site access is from Michael Power Boulevard (Highway 584).
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 22
Historic information indicates that the landfill was active from an undetermined date until
approximately 1965. Groundwater flow in the area is anticipated to be to the northeast
towards the proposed realignment corridor.
Contaminants of concern in soils and groundwater at the Former MacLeod Mine Landfill
include but are not limited to suspected cyanide due to historic disposal activities, as well
as cobalt and iron which regularly exceed Provincial Water Quality Objectives in surface
waters from the adjacent Watercourse C.
Two groundwater monitoring wells were installed by TBTE in 2014 and sampling in
spring/summer 2015 is recommended for cyanide, metals and mercury, PHCs, volatile
organic compounds (VOCs), PAHs, pH, conductivity and hardness to assess existing
conditions.
MacLeod High Tailings 3.2.3
The MacLeod High Tailings site is a large tailings deposit originating from the former
MacLeod-Cockshutt and Mosher Mines. The MacLeod High Tailings (MHT) are located
on the east side of Highway 584, and north of Highway 11. A portion of the proposed
corridor exists across the northeastern section of the MHT.
Groundwater flow in the area is anticipated to be to the northeast towards Kenogamisis
Lake.
Several historic reports as well as Acid-Base accounting on samples taken by TBTE
indicate that the MacLeod High Tailings are considered non-potentially acid generating.
Contaminants of concern in soils and groundwaters in the MacLeod Tailings include but
are not limited to arsenic, cobalt, chromium, and antimony, all of which have been
confirmed in tailings samples (TBTE 2014).
Highway Maintenance Patrol Yard 3.2.4
The Patrol Yard is an MTO property located on Highway 11 in Geraldton and is directly
adjacent to Kenogamisis Lake.
The Patrol Yard property currently has a garage/office building, salt storage dome,
several storage tanks (primarily for fuel) and miscellaneous storage sheds. The site has
a septic field and groundwater well, however the property is supplied with municipal
water supply. The central portion of the Site is paved. The Site is an irregularly shaped
parcel of land with an approximate area of 3.2 hectares (ha). The Site can be accessed
from an entrance on the south side of the property, off of Highway 11. Prior to 2013, the
Site was operated by the Ministry of Transportation (MTO).
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 23
Contaminants of concern in soils at the Highway Maintenance Patrol Yard include but
are not limited to arsenic and chromium (confirmed, TBTE 2015 sampling), as well as
additional metals, xylenes, and ethylbenzene (suspected based on historic reports).
Suspected contaminants of concern in groundwater (based on historic reports) at the
Patrol Yard include but are not limited to arsenic, PHCs, xylenes, and ethylbenzene.
Refer to the Environmental Contaminant Study (TBTE 2015) for detailed Findings and
Evaluation at each of these APECs.
ALTERNATIVES AND EVALUATION 4.0
Route planning for the Highway 11 realignment around the proposed Hardrock Project
site was initiated through the Feasibility Study Report generated by Stantec Consulting
Ltd. (Stantec). Select route alternatives were then further analysed in more detail though
a Trade-Off Study prepared by TBT Engineering. Using the information generated from
these reports and further refinement, the preferred alignment 1D was identified and the
preliminary design phase of the project was initiated.
Several meetings involving Premier, Stantec, TBTE, and MTO were held throughout the
route evaluation process to provide an opportunity to discuss project goals, highway
safety, geometry and other design criteria associated with the Highway 11 realignment.
The meeting minutes are included in Appendix G.
Feasibility Study Report 4.1
Stantec’s Feasibility Study Report (FSR) identified 6 route alternatives (1A, 1B, 2, 3, 4,
and 5) to provide a bypass of the Hardrock Project site. As seen in Exhibit 4.1, five of the
proposed alternatives bypassed the project site to the north and one to the south. After
evaluating highway geometry, safety, environmental impacts (social, cultural and
natural), constructability and cost, Alternative 3 was identified as the ‘base case’
alignment to carry forward for future studies of the Highway 11 realignment.
Trade-Off Study (TBT Engineering) 4.2
The Trade-off Study was initiated to address a critical evaluation criteria that was
unknown and unaccounted for during the FSR phase. The additional criteria was the
requirement of a 500 m safety buffer from the open pit mine operation. Four of the route
alternatives considered during the FSR phase, including Alternative 3, were no longer
viable due to their proximity to the proposed open pit mine operation. Route alternatives
1A and 1B satisfied the pit safety buffer and were carried forward to be examined further
in the Trade-off Study.
""
" " " "
" "
"
"
""
""
"
"
"
"
""
"
"
"
"
"
"
""
""
"
"
"""
"""
""
""
""
"
"
"
"
"
"""
"
" ""
"
""""
" "
""
"
"""
"
"
""
"
"""
""
""
""
"
"
"
"
" "
"
""
"
"
"
"
"
" "
"
"
" """" "
""
"
""
"
""
""
"
"
"
""
"
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ Ñ Ñ Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
ÑÑ
Ñ
ÑÑ
Ñ
Ñ
Ñ
Ñ
ÑÑ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ ÑÑ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
Ñ
ÑÑ
Ñ
Ñ
Ñ
Ñ
Ñ
s
³²
³²
³²
MosherLake
BartonBay
KenogamisisLake
KenogamisisLake
MACLEODPROVINCIAL
PARK
360
350
340
360
350340
370
360
340
330
330
350
350
350
340
340 340
340
340
340
340
340
340
Rosedal eP
oint
Rd
Twilight Cres cent
Sakamoto Road
Sunset Drive
Old Arena Road
Barric k Drive
Laht
i'sR
oad
Hardrock Road
352
356
332
341
341339
353
339
339
349
343
335
335
343
367
349
349
364
344348
339
352
339
344
337
334
337
331
335
323
336
347342
344
341
337
336
337
334
339
335
345
336
332
335
333
339
337
336
338
355
347
342
333
336
331
343 342
335
343
336
338
337
333
334
333
332
332
333
333
333
334
342
345
Alte
rnat
ive
5
Alternative 4
Alternative 3
Alternative 2
Altern
ativ
e 1b
Altern
ativ
e 1a
10+000
10+500
11+00011+500
12+000
13+000
13+500
14+000
14+007
10+000
10+500
11+000
11+50012+000 12+500
10+000
10+500
11+000
11+500
12+000 12+50013+000
13+309
10+000
10+500
11+000
11+500
12+00012+500
13+000
13+473
10+000
10+500
11+000
11+500
12+000
12+500
13+000
13+500
10+00010+500
11+000
11+500
12+000
12+500
13+000
13+500 14+000 14+500
15+000
15+500
16+000
16+245
Exhibit 4.1 - FSR Route AlternativesD Spot Height
" Small Bulding
Large Building
Watercourse
Utility Line
Primary Road
Secondary Road
Tertiary Road
Contour
Provincial Park
Waterbody
Wetland
Wooded Area
§0 200 400 m
Premier GoldHardrock Site
Alternatives
Altern
ative
1a
Altern
ative
1b
Altern
ative
2Alte
rnat
ive 3
Altern
ative
4Alte
rnat
ive 5
Preliminary Proposed Layout
Mill Site & Associated Infrastructure
Water Treatment Facility
Highway 11
Michael Power Boulevard
Mosher Lake
Kenogamisis Lake
Waterco
urse D
Watercourse F
Watercourse E
Watercourse B Waterco
urse
C
WatercourseH
SW ArmTributary
Watercourse G
Watercourse a
Macleod HighTailings
Macleod LowTailings
LittleLonglacTailings
HardrockHistoricTailings
CloutierPit
Mosher Pit(Premier)
10+00010+500
11+000
11+500
12+000
12+500
13+00013+500
14+000
14+500 15+00015+070
10+000
10+500
11+000
11+500
12+000
12+500
13+00013+500 14+000 14+500 15+000
15+500
16+00016+500
16+685
0 330 660m
1:15,000
Y:\Pr
ojects
\2014
\14-04
1 Prem
ier G
old G
eraldt
on\G
IS\Pr
emier
Gold
- Mar
25 (F
or GW
) Fig
1.mxd
Revis
ed: 2
015-0
3-31 B
y: cm
itche
llLegend
WatercourseRailwayPower Transmission LineRecreational TrailOpen Pit 500m BufferOpen PitHighway 11Major RoadLocal RoadPit or QuarryWaterbodyGolf CourseHistoric TailingsWetlandSattelite Pit
Notes1.
2.
3.
Coordinate System: NAD 1983 UTM Zone 16N
Base features produced under license with the Ontario Ministry of Natural Resources © Queen's Printer for Ontario, 2013.
Orthoimagery © Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation, 2014
Alternative AlignmentsAlternative 1AAlternative 1BAlternative 1CAlternative 1D
Exhibit 4.2- Trade-off Study Route Alternatives
Highway 11
Michael Power Boulevard
Mosher Lake
Kenogamisis Lake
Waterco
urse D
Watercourse F
Watercourse E
Watercourse B Water
cour
seC
WatercourseH
SW ArmTributary
Watercourse G
Watercourse a
Macleod HighTailings
Macleod LowTailings
LittleLonglacTailings
HardrockHistoricTailings
CloutierPit
Mosher Pit(Premier)
0 330 660m
1:15,000
Y:\Pr
ojects
\2014
\14-19
2 Prem
ier G
old\G
IS\Pr
emier
Gold
- May
22- P
lan of
High
way 1
1 rea
lignm
ent P
referr
ed Al
terna
tive 1
D.mx
dRe
vised
: 201
5-05-2
2 By:
cmitc
hell
LegendWatercourseRailwayPower Transmission LineRecreational TrailOpen Pit 500m BufferOpen PitHighway 11Major RoadLocal RoadPit or QuarryWaterbodyGolf CourseHistoric TailingsWetlandSattelite Pit
Notes1.
2.
3.
Coordinate System: NAD 1983 UTM Zone 16N
Base features produced under license with the Ontario Ministry of Natural Resources © Queen's Printer for Ontario, 2013.
Orthoimagery © Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation, 2014
Alternative AlignmentsOriginal Alternative 1DPreferred Alignment 1DMicheal Power Blvd Re-Alignment
Exhibit 4.3- Plan of Highway 11 Re-Alignment Preferred Alternative 1D
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 24
During the initial stages of the Trade-off Study and after further consultation with MTO a
new alignment alternative, 1D, was generated and Alternatives 1A and 1B were
modified. The new alternatives were designed with consideration of the new pit safety
limit, environmental constraints and highway geometrics.
The eastern connection between existing Highway 11 and Alternatives 1A and 1B was
modified to incorporate a larger radius curve. These minor variation to Alternatives 1A
and 1B are described by Alternative 1C. The three alternatives are mapped in Exhibit
4.2. An evaluation summary is provided in Table 4.1.
In summary, Alternative 1D was selected as the preferred alternative from the Trade-off
Study based on:
alignment curve geometry exceeding the minimum design stand;
desirable intersection angle between Highway 11 and MPB; and
shortest length (minimizes future maintenance requirements)
Preliminary Design 4.3
The preferred Alternative 1D was carried forward from the Trade-Off Study into
preliminary design. As the alignment was examined in more detail, minor local variations
were made in the alignment to address safety concerns that were encountered as
additional information was gathered for preliminary design. The alignment modifications
are described in Exhibit 4.3.
Mosher Shaft is a historical vertical mine shaft that was in close proximity to the
selected route Alternative 1D. Through consultation with Premier, the alignment
was adjusted to accommodate a 30 m buffer from the south limit of the proposed
MTO Right-of-Way.
The Highway 11 and MPB intersection geometry was further analysed and it was
determined the sight distance for the intersection was sub-standard. To address
the substandard sight distance an additional horizontal curve was introduced to
Alignment 1D and a slight change in the tangent direction at the intersection with
existing MPB. These two changes along with a minor realignment of MPB yielded
a design that provides a 425 m sight distance for the intersection and meets the
MTO Geometric Design Standards for Ontario Highways.
Alternative 1D was shifted to the north-east within the MHT area to accommodate
the 500 m pit safety buffer zone.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 25
Due to the minor alignment changes to Alternate 1D and the availability of additional
baseline environmental data, the three alternatives (1A, 1B and 1D) were re-evaluated
using a ranking system.
Based on the evaluation summarized in Table 4.1 and in consideration of the natural
environment, cultural environment, mine features, socio-economic features, and highway
engineering, Alternative 1D was established as the preferred alignment to carry forward
in the preliminary design.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 26
Table 4.1 – Route Alternative Evaluation
Category Element Alternative 1A Alternative 1B Alternative 1D N
atu
ral
En
vir
on
men
t
Terrestrial -
Vegetation
Fragmented mature conifer and deciduous forest.
Minor wetlands present.
Ranking Acceptable Acceptable Acceptable
Terrestrial – Impact
to Wildlife & SAR Low - Moderate Low - Moderate Low - Moderate
Ranking Acceptable Acceptable Acceptable
Streams Crosses streams WC-A (Permanent); WC-B,
WC-C, WC-D (Intermittent), WC-H & WC-I
Crosses Intermittent Stream WC-C WC-D
WC-F, & WC-I
Crosses Intermittent Stream WC-C, WC-D,
WC-F, & WC-I
Ranking Not Preferred Preferred Preferred
Fisheries WC-A – Permanent Watercourse.
Low Sensitivity Habitat Low Sensitivity Habitat Low Sensitivity Habitat
Ranking Not Preferred Preferred Preferred
Cu
ltu
ral
Heri
tag
e Archaeology &
Cultural Heritage Little or no archaeological potential was identified within the proposed Highway 11 realignment area.
Ranking Acceptable Acceptable Acceptable
Min
e F
eatu
res
Tailings Alignments cross approximately 1200 m of historical mine tailings (MacLeod Low and High Tailings)
Ranking Acceptable
Mine Operations Maintains 500 m offset from proposed open pit
and greatest offset from Mosher Shaft.
Maintains 500 m offset from proposed open
pit and 50 m offset from Mosher Shaft. -
Maintains 500 m offset from proposed
open pit and 50 m offset from Mosher
Shaft.
Ranking Acceptable Acceptable Acceptable
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 27
So
cio
-Eco
no
mic
(D
iffe
ren
ces
) Noise Receptors
Increased traffic volume proximal to property
owners on Barton Bay and Kenogamisis Golf
Club (specifically holes 11&12)
Increased traffic volume proximal to
Kenogamisis Golf Club (specifically holes
4,5,7,11,&12) and Barton Bay.
Increased traffic volume proximal to
Kenogamisis Golf Club (specifically holes
4,5,7,11,&12)
Ranking Acceptable Acceptable Preferred
Recreational
Facilities
Maintains distance (about 400 m) from the
Original 9 Golf Course. Takes up a portion of
snowmobile club trail on Old Arena Rd.
Encroaches on the Original 9 Golf Course
Crosses minimum of 2 holes on Eastern
Portion of the Golf Course and
Encroaches on the Original 9 (west
portion)
Ranking Preferred Acceptable Acceptable
MTO Patrol Yard
Proximity considered likely to require
alterations to MTO yard and impact access
from Highway 11.
Proximity considered likely to require
alterations to MTO yard and impact access
from Highway 11.
Relocation of MTO Patrol Yard required to
favourable location with acceptable site
distance.
Ranking Not Preferred. Not Preferred. Preferred
Utilities
Potential impact to overhead hydroelectric
transmission lines present along south limit of
existing Old Arena Road Corridor for ~ 700 m
where Alignment A parallels existing corridor.
Overhead hydroelectric distribution and
telecommunication lines present along north
limit of Old Arena Road corridor for ~ 2.2 km
where Alignment A parallels existing corridor.
Potential impacts to overhead hydroelectric
transmission line where Alignment crosses
existing hydro corridor ~ 350 m north of
Highway 11 near SE corner of Mosher Lake.
Crosses water line for Golf Course from
Mosher Lake.
Potential impacts to overhead
hydroelectric transmission line where
Alignment crosses existing hydro corridor
~ 350 m north of Highway 11 near SE
corner of Mosher Lake. Crosses water
line for Golf Course from Mosher Lake.
Ranking Not Preferred Acceptable Acceptable
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 28
Hig
hw
ay E
ng
ine
eri
ng
Curve Radii
All horizontal curves meet or exceed minimum
design standard for design speed of 110km/h
All horizontal curves meet or exceed
minimum design standard for design speed
of 110km/h
All horizontal curves exceed minimum
design standard for design speed of
110km/h
Ranking Not Preferred Not Preferred Preferred
HWY 11 and MPD
Intersection Angle
Undesirable intersection angle at MPB & Hwy
11. More impact to existing MPB alignment.
Undesirable intersection angle at MPB &
Hwy 11. More impact to existing MPB
alignment.
Desirable intersection angle at MPB &
Hwy 11. Less impact to existing MPB
alignment.
Ranking Not Preferred Not Preferred Preferred
Constructability
Approximately 1550 m of construction through
deep muskeg deposits (1 – 2m thick). All
alternatives traverse the same length of the
MHT’s.
Approximately 940 m of construction through
deep muskeg deposits (1 – 2m thick). All
alternatives traverse the same length of the
MHT’s.
Approximately 900 m of construction
through deep muskeg deposits (1 – 2m
thick). All alternatives traverse the same
length of the MHT’s.
Ranking Not Preferred Acceptable Preferred
Realignment Length 6.7 Km (1.6 on existing Old Arena Rd.) 5.1 Km 4.7 Km
Ranking Not Preferred Acceptable Preferred
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 29
PROPOSED DESIGN 5.0
This section describes the design of the preferred alignments for Highway 11, Michael
Power Boulevard and associated works. Highway 11 and Michael Power Boulevard will
be designed in accordance to the Geometric Design Standards for Ontario Highways
(GDSOH) and design speed standards of 110 km/h and 80 km/h respectively.
The proposed design standards for Highway 11 are summarized in the Design Criteria
attached in Appendix B. Preliminary plans and profiles are provided in Appendix C.
Horizontal Alignment 5.1
The horizontal alignment for the proposed Highway 11 realignment conforms to a 110
km/h design speed in accordance with the Geometric Design Standards for Ontario
Highways (GDSOH) Table C3-2. Curve length shall be a minimum of 150 m or the
appropriate minimum length for the deflection angle.
During the Trade-Off Study phase, MTO requested that any horizontal curve radii are to
be designed with an 800 m radius or greater. The alignment design consists of three
800 m radius curves and one 900 m radius curve.
Alignment 1D has been designed to provide a 90° intersection on tangent with Michael
Power Boulevard. Due to environmental constraints, Kenogamisis Golf Course, the Pit
Safety Limit and highway geometric standards, approximately 600 m of Michael Power
Boulevard will be re-aligned to achieve the 90° crossing. The section of Michael Power
Boulevard being realigned will be designed using a design speed of 80 km/h and curve
radii of 250 m or greater.
The preferred alignment for Highway 11 is considerate of the possibility the highway may
be upgraded to a four lane facility in the future. Alignment 1D essentially follows the
alignment for the eastbound lanes in a four lane facility.
Vertical Alignment 5.2
The profile grade for the proposed Highway 11 realignment will be considerate of soils
conditions, longitudinal drainage, intersection approaches, freeboard in wetter areas and
depth of cover for drainage features. Where traversing the MacLeod High Tailings the
profile has been set to provide a minimum 2 m separation between profile grade and
original ground. All vertical curves on Highway 11 will meet or exceed the design
standard for a 110km/h design speed.
Cross Section 5.3
The design highway cross section for Highway 11 will be in accordance with GDSOH
Table D2-1& D5-1 and will consist of two 3.75 m lanes, 2.5 m shoulders and 1.0 m
minimum rounding. Auxiliary lanes as detailed elsewhere will be 3.5 m in width.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 30
Pavement widening will be designed in accordance with GDSOH Table D3-3 and a WB-
17.5 design vehicle. Super-elevation will conform to GDSOH Table C3-5 and a design
speed of 110 km/h.
Granular and fill foreslopes shall be at a rate no steeper than 3:1 in shallow fill and cut
sections. In high fill sections where constraints restrict construction of 3:1 foreslopes, the
foreslope between the bottom of the granular base and the toe of the fill may be
steepened up to a maximum of 2:1 in earth fills and 1.25:1 in rock fills.
In cut sections earth backslopes less than 3.0 m in height shall be constructed at rate no
steeper than 3:1 and earth backslopes greater than 3.0 m in height may be steepened to
2:1 as required.
A preliminary foundations investigation and design was completed for rock
embankments traversing and adjacent to the MHT’s. Construction and grading
requirements for these rock embankments are provided within the Preliminary
Geotechnical Foundation Study section of this report and in Appendix F.
The design cross section for the portion of Michael Power Boulevard being realigned will
consist of two 3.5 m lanes, 2.0 m shoulders and 1.0 m minimum rounding. This proposed
platform width is consistent with the existing platform.
Typical cross sections are provided in exhibit 5.1 and 5.2.
Intersections and Sideroads 5.4
The proposed design of the new Highway 11 and Michael Power Boulevard intersection
is very similar to the existing intersection. Channelized turn movements with raised
median islands will be provided for Highway 11 westbound traffic turning northbound on
Michael Power Boulevard (E-N Ramp) and southbound Michael Power Boulevard traffic
turning westbound onto Highway 11(N-W Ramp). The curb and gutter for the E-N and N-
W ramps will consist of barrier curb and standard gutter with offsets designed in
accordance to GDSOH Table E8-7. The ramp alignments will both utilize 80 m radius
curves and spiral parameters of 40.
An auxiliary left turn lane will be provided for Highway 11 eastbound traffic turning north
onto Michael Power Boulevard. Based on the percentage of long trucks turning north
onto Michael Power Boulevard, the design will include a minimum storage length of
15 m.
The intersection of Highway 11 and Michael Power Boulevard has been designed to
provide 425 m of sight distance from the sideroad along the main highway. This
requirement will ensure southbound traffic turning left onto Highway 11 has sufficient
time to accelerate without being overtaken by approaching traffic on Highway 11
traveling at the design speed.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 31
Roadside Safety 5.5
The Ministry of Transportation Roadside Safety Manual, 1993 defines the clear zone
width as “the distance from the edge of the travelled roadway to the face of an
unprotected hazard.” This width, which is dependent on design speed and roadway
geometrics, must be traversable and clear of any hazards such as: rigid sign supports,
light standards, and non-traversable drainage structures.
The applications of clear zone width will be reviewed in accordance with the Roadside
Safety Manual. Obstacles within the clear zone should be treated in the following order
of preference: remove the hazard; relocate the hazard outside the clear zone; minimize
the hazard by making it traversable (i.e., slope flattening) or using breakaway devices;
and shield the hazard.
The minimum required clear zone distance for a 110 km/h design speed and an AADT of
2080 is 7.0 m on tangents and 9.0 m for an 800 m radius curve. The typical design cross
section will locate rock cuts beyond the clearzone.
Where it is not practical to relocate a roadside hazard or to provide traversable
embankment slopes, all hazards that are located within the clear zone will be protected
with guide rail according to current Ministry design standards, practices and procedures.
Ideally, surplus excavation material is utilized for slope flattening to eliminate and/or
minimize the need for guide rail.
Traffic Signage and Pavement Markings 5.6
Pavement markings and signage requirements throughout the project including
cautionary signing at critical locations will be reviewed during detail design.
All recommended permanent signage is to be reviewed and approved by the Ministry.
Approved permanent signage is to be detailed in the contract package. Wording on both
permanent and construction identification signs must be approved. Permanent Signing
and Pavement Marking drawings and a Permanent Signing Table will be prepared. All
permanent signing and pavement markings shall be in accordance with the Ontario
Traffic Manuals, King’s Highway Guide Signing Policy Manual, Ministry standards and
regional guidelines. The Permanent Signing Plan and Permanent Signing Table shall be
submitted to the Ministry for review and approval.
Drainage 5.7
The highway drainage design for surface drainage and water crossings will be in
accordance to the MTO Highway Drainage Standards (2008).
Centreline Culverts 5.7.1
A preliminary design has been undertaken to determine centerline culvert locations.
Since all catchments are estimated to be under 100 hectares, peak flows have been
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 32
estimated using the using the Rational Method. The following data sources have been
referenced to describe the watershed characteristics:
Engineering survey plans and profiles
LIDAR and high resolution ortho-imagery
Aerial photographs (scales: 1:50000)
Ontario Base Maps (scale 1:20000).
The appropriate storm return period and headwater elevation will be used to design
centreline culverts for surface drainage and water crossings. All DFO and MTO protocols
will be implemented to protect designated fisheries. Culvert design will be reviewed
during detail design to determine the impact of changes in adjacent land and topography
resulting from the mine operation and eventual closure.
Gravity pipe design will be completed during detailed design using a 50 year design
service life.
Roadside Ditch Design 5.7.2
It is recommended that standard roadside ditching be provided for 0.5 m below subgrade
in earth and 0.25 m below subgrade in rock with consideration for 1 m flat bottom widths
in flatter and wetter areas. It is recommended that protection of ditches be in the form of
seeding and mulching and/or rock protection depending on the steepness of the highway
grade. Temporary erosion and sediment control measures will be reviewed during detail
design.
Water Management 5.7.3
Highway construction materials and techniques will be optimized along the MacLeod
High Tailings to minimize the infiltration of service water into the tailings. Water
management design alternatives will be further investigated during the detail design
phase.
Entrances 5.8
The MTO Corridor Management Office will be consulted to ensure conformance with
sight distance and permit requirements for both existing and new entrances for Highway
11. See the Permitting section of this report for more details.
A new commercial entrance will be required at station 17+848 Rt Errington Township
(MTO Plan B-896-11-2) to provide access to the mine site. The Traffic Impact Study
recommends an auxiliary westbound left turn lane (minimum 15m storage, parallel lane,
taper, and run-out lane to correspond to the selected design speed) and eastbound right
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 33
turn lane and taper are constructed to accommodate traffic. The traffic impact study also
recommended illumination for the new entrance.
The Municipality of Greenstone will be consulted regarding existing and new entrances
on Michael Power Boulevard.
Illumination 5.9
Illumination will be provided at the decision points for the Highway 11 and Michael Power
Boulevard intersection and at the main entrance for the mine site.
Snow Plough Turnarounds and Truck Inspection Stations 5.10
A new truck inspection station will be provided along the proposed alignment. The
location will be determined during detail design.
A requirement for snow plough turnarounds has not been identified for this project.
MTO Patrol Yard 5.11
Construction of the preferred alignment may require the relocation of the existing MTO
Patrol Yard. Consultation with MTO revealed that if a new patrol yard is required, this
location would require access to the municipal water supply. Based on this requirement a
preliminary relocation site may be available at south of the highway at station 17+850 Rt
Errington Township (MTO Plan B-896-11-2).
Further evaluation of the proposed alignment nearing the eastern tie-in/connecting point
should be completed during detail design phase in attempt to avoid interference or
relocation of the MTO patrol yard.
Geotechnical Pavement Design 5.12
Preliminary Structure Design – Highway 11
The preliminary pavement structure design was carried out utilizing the MTO’s Adaption and Verification of AASHTO Pavement Design Guide for Ontario Conditions (Materials Information Report MI-183) which uses Structural Numbers (SN) derived using standard values for new construction projects. The SN design method references the amount of traffic anticipated over the design life. Based on a forecasted 20 year Equivalent Single Axle Load of 11.6 million and a design subgrade of low plastic clay, the target SN is calculated to be 177 mm. Based on the structural layer coefficients provided in MI – 183 the Structural Number for the proposed Highway 11 realignment pavement structure is provided in the table below:
Highway 11 Proposed Pavement Structure:
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 34
Preliminary Pavement Structure Structural Layer Coefficients
Structural Number
Component Avg. Thickness (mm)
New Asphaltic Concrete 130 0.42 55
New Granular ‘A’ Base 150 0.14 21
New Granular ‘B’ Type II Subbase 850 0.12 102
Theoretical Design Structural Number 178
Target Structural Number 177
Preliminary Design – Michael Power Boulevard Intersection
The forecasted traffic loadings on Michael Power Boulevard extending northerly from proposed Highway 11 is 1.6 M 20 yr ESAL’s which requires a SN of 135 mm using a design subgrade of low plastic clay. As such, the preliminary pavement structures for this segment of Michael Power Boulevard, and associated intersection ramps, are as follows: Michael Power Boulevard North and Intersection Ramps
Preliminary Pavement Structure Structural Layer Coefficients
Structural Number
Component Avg. Thickness (mm)
New Asphaltic Concrete 100 0.42 42
New Granular ‘A’ Base 150 0.14 21
New Granular ‘B’ Type II Subbase 600 0.12 72
Theoretical Design Structural Number 135
Target Structural Number 135
The proposed Michael Power Boulevard extension south of the proposed intersection has a forecasted traffic loading of 10,000 20 yr ESAL’s requiring a SN of 64 mm. The preliminary pavement structure for this segment is as follows: Michael Power Boulevard South
Preliminary Pavement Structure Structural Layer Coefficients
Structural Number
Component Avg. Thickness (mm)
New Asphaltic Concrete 50 0.42 21
New Granular ‘A’ Base 150 0.14 21
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 35
New Granular ‘B’ Type II Subbase 600 0.12 72
Theoretical Design Structural Number 114
Target Structural Number 64
Preliminary Pavement Types
The types and thicknesses of asphaltic concrete for Highway 11 and Michael Power Boulevard are as follows: o Highway 11 Main Lanes: 50 mm SuperPave 12.5 Surface Course
80 mm SuperPave 19.0 Binder Course
o Highway 11 Auxiliary Lanes: 50 mm SuperPave 12.5 Surface Course 80 mm SuperPave 19.0 Binder Course
o Highway 11 Paved Shoulders: 50 mm SuperPave 12.5
o Highway 11 Ramps to 50 mm SuperPave 12.5 Surface Course
Michael Power Boulevard North: 50 mm SuperPave 19.0 Binder Course
o Michael Power Boulevard North: 50 mm SuperPave 12.5 Surface Course 50 mm SuperPave 19.0 Binder Course
o Michael Power Boulevard South: 50 mm SuperPave 12.5 Surface Course
o Hwy 11 Ramps & Michael Power 50 mm SuperPave 12.5 Surface Course Boulevard Paved Shoulders:
SuperPave binder and surface courses should be specified with a Performance Grade Asphalt Cement of 58-34. Highway 11 and Michael Power Boulevard paving courses shall be specified with traffic categories D and B, respectively. Stripping and Muskeg Excavation
All topsoil and organic/muskeg should be removed from the proposed new highway
footprint regardless of the fill height. For design purposes assume an average stripping
depth of 200 mm and that stripping commences at the inner edge of rounding where
widening. Grubbing shall be done in accordance with OPSS 201. For design purposes,
assume a grubbing depth of 300 mm. Grubbing shall not apply for embankments greater
than 2.5 m.
All organic deposits and muskeg should be removed as per OPSD 203.010 for new
construction.
Embankment Fills
New highway embankments will be constructed with rock fill or suitable earth/granular borrow materials. Foreslopes constructed with earth and granular material should be graded at 2:1 or flatter and rock embankments shall be at 1.25:1 or flatter (outside
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 36
foundation areas). Slope flattening opportunities will be reviewed as part of the detailed design process.
Roadway Cuts
New earth cuts will have backslopes graded at 2:1 or flatter (material specific) in conjunction with erosion protection. Erosion protection is anticipated to vary from seed and cover to armouring with granular sheeting or rock protection. The majority of the existing earth along the proposed re-alignment is generally not suitable for re-use as embankment fill due to the fineness of gradation and saturated conditions. New rock cuts should be designed in accordance with MTO’s Northwest Region Rock Cut Guidelines. Rock generated from the cuts within the western portion of the project length will be further evaluated during the detailed design phase to investigate suitability for the production of rock fill, granular materials, and hot-mix stone. Detail Design Phase
The geotechnical components, including field investigations, data analysis, recommendations and reporting shall be carried out as per the MTO’s Pavement Design and Rehabilitation Manual, Second Edition; MTO NWR Geotechnical Investigation Minimum Requirements dated 1998-06-01; and MTO Adaption and Verification of AASHTO Pavement Design Guide for Ontario Conditions (Materials Information Report MI-183).
Preliminary Geotechnical Foundation Study 5.13
The appended Preliminary Foundation Investigation and Design Report address several
roadway embankment design considerations. The report discusses the subsurface
conditions encountered surrounding the MacLeod High Tailings (MHT) and those
encountered within the MHT. Design discussions focus on the stability of the proposed
roadway embankments both on and adjacent to the MHT, and estimated settlement
performance of the roadway embankments for various subsurface conditions. The report
includes a discussion on considerations which will need addressing for the completion of
the detailed design. A brief summary of these three items are provided as follows.
Embankment Stability of the proposed alignment both on the MHT and adjacent to the
MHT was completed. Numerous scenarios were analyzed; from the simple embankment
on top of the MHT, to the highest embankment which crosses the perimeter of the
MHT. For these scenarios, sub-scenarios were further analyzed to determine how far
the embankment could be from the perimeter without effecting it to how to safely
excavate organic material and deleterious soils (such as tailings) from beneath the
embankment footprint without destabilizing the MHT perimeter. From these analyses the
following construction, and design requirements were determined:
Typical rock fill embankment side slope will be 1.5(H) to 1(V).
Rock fill embankments extending “side saddle” over the MHT perimeter will have
side slopes of 1.5(H) to 1(V).
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 37
A zone of organic material and/or tailings will not be able to be excavated at the MHT
perimeter toe (approximately 20 m from the toe).
A flanking berm may be required along the perimeter of the MHT to facilitate the
excavation of organic material and/or tailings for the roadway embankment.
MHT perimeter slope will require reinforcement where the roadway embankment is
within 14 m from the perimeter crest. The reinforcement will include 0.6 m of rock fill
along the face of the perimeter and 15 m wide stepped flanking berm.
Monitoring and instrumentation plans may need to be considered in areas where
construction is over organic material, for construction and stability safety.
Settlement performance has been assessed in reference to the MTO Embankment
Settlement Criteria. This criteria indicates that over the design life of the embankments
that a maximum of 200 mm of settlement can occur post construction of the roadway. In
order for this to be realized either delays in final grading and paving or preloading of the
foundation soils needs to be allowed for. Depending on the area of concern and the
prevailing subsurface conditions delays upwards of three months may be
required. Where estimated delays extend beyond three months preloads may be
considered, the size of the preloads will be dependent on the subsurface conditions and
the allowable delay time.
Further field investigations will be required to obtain additional subsurface data. Water
levels and soil stratigraphy, attempt to locate known subsurface structures, and
considerations for additional design criteria will be investigated. Of the proposed detailed
design considerations two highlighted items are further field investigations and refining
and clarifying the design criteria. Further field investigations are required both on and off
the MHT to obtain more groundwater data, and further subsurface soil stratigraphy. This
will provide more information on the extent of the tailings beach surrounding the MHT,
the condition and variability of the fills above the tailings on the MHT and phreatic
surface data near the perimeter of the MHT. Refining and clarifying the design criteria
will be required to complete the detailed design. In the event that design criteria
becomes more stringent, than those applied within the preliminary report, because of the
state of the MHT, from adjacent structures, or from a regulatory agency the findings of
the preliminary report may no longer be valid.
The above three items (stability, settlement, and detailed design considerations) are
discussed in greater detail in the Preliminary Foundation Investigation and Design Report
provided in Appendix F.
Materials Management and Aggregate Sources 5.14
Excess earth will be generated as the majority of excavated earth material is unsuitable
for roadway construction purposes. The design will be considerate of the “MTO Earth
Best Practices & Recommendations for Design & Construction – June, 2010.” The
responsibility will be placed on the proponent to effectively manage earth that is excess
to the contract requirements outside the right-of-way.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 38
A significant volume of rock fill is required for rock embankment construction of new
Highway 11 across the MacLeod High Tailings. It is anticipated the rock will be supplied
from quarrying additional rock beyond the clearzone in the vicinity of station 10+800
(Highway 11 Realignment).
Utilities 5.15
Utility relocations are anticipated for Bell Canada and Hydro One aerial plant within the
vicinity of the new Highway 11 and MPB intersection.
Bell Canada aerial plant relocates are anticipated at the east limit of the project where
the new Highway 11 alignment ties into existing Highway 11.
There is a Hydro One transmission line that crosses the proposed alignment in the
vicinity of station 10+850. This line will likely require temporary relocation for construction
of the new highway.
Property 5.16
Premier Gold will acquire all lands for the purposes of highway construction. Upon completion of construction and prior to opening to traffic, the new highway right-of-way shall be assumed and designated by the MTO. The right-of-way width will be 110 m throughout the length of the new Highway 11 alignment. A similar process will be required for the transfer of the new MPB alignment to the Municipality of Greenstone.
Construction and Traffic Staging 5.17
In general, on existing highways, construction staging and/or detours are required for
various purposes including safety, traffic control, grading requirements and other related
highway improvements. In areas where geometric improvements are proposed,
temporary delays and/or detours will be required for construction purposes. Detours may
involve temporary shoulder widening and temporary flagging during construction
operations.
As a majority of the new construction is on a new alignment, major traffic impacts on the
existing Highway 11 are not anticipated during construction. During detail design traffic
staging should be reviewed at the following locations:
Highway 11 where the new alignment ties into the existing highway
MPB where the new alignment ties into the existing roadway
MPB and the new channelized intersection
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 39
ADDITIONAL CONTAMINATED PROPERTY REQUIREMENTS 6.0
The Study Area for the ECS is the proposed 110 m Right of Way (ROW) for the Highway
11 realignment. The ECS identified four Areas of Potential Environmental Concern
(APECs) based on pre-screening. These APECs are, from west to east, the Mosher
Portal Area, Former MacLeod Mine Landfill, MacLeod Low and High Tailings, and a
Highway Maintenance Patrol Yard.
MTO’s Contaminated Property Process is divided into six steps as follows:
Contamination Overview Study (Now completed)
Preliminary Site Screening (Now completed)
Phase I ESA (Now completed)
Phase II ESA (Partially completed)
Screening Level Risk Evaluation (to be completed) and
Site management (to be completed).
As the project moves into detailed design, additional Phase II ESA work is required at the
sites to allow the screening level risk evaluations as necessary. Recommendations
associated with each APEC are identified below:
Mosher Portal Area – Soil and groundwater quality testing are recommended in the
area of the Mosher Pit and in the vicinity of the Mosher No. 1 Shaft (including buildings)
to investigate potential contaminants at and adjacent the proposed realigned corridor;
Former Macleod Mine Landfill Area - The groundwater monitoring wells previously
installed in 2014 downgradient of the closed landfill Site (i.e. 14-FL-MW1 and MW2)
should be sampled for water quality to investigate potential landfill leachate migration
towards the proposed realigned corridor;
Macleod Tailings Area – Additional soil quality testing is recommended from
geotechnical boreholes completed for detailed design activity along the proposed
corridor. This will be focused on identifying the presence or absence of the burgundy
coloured tailings in each of the boreholes;
Highway Maintenance Patrol Yard – Additional Soil and groundwater quality testing are
recommended in the yard area to delineate contaminants previously identified.
Based on the additional Phase II ESA information, qualitative risk evaluations shall be
completed (as necessary) to assess the short and long term risk of contamination
identified at each of the APECs to both human and natural environment receptors. From
this point, strategies to mitigate site contamination will be developed. Any contaminant
management strategy would involve site monitoring, or remediation, or possibly the
preparation of a formal risk assessment as per O.Reg. 153/04.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 40
CORRIDOR CONTROL 7.0
The deletion of the portion of the existing Highway 11 being realigned and the addition of
the new alignment into the provincial system will require an Order in Council. The
proponent will prepare all required legal plans with some oversight by MTO Geomatics.
A Municipality of Greenstone Council resolution may be required for acquiring the
realigned section of MPB. Consultation with Municipality of Greenstone will be required
in the next design phase to determine the transfer and closure process.
PERMITTING 8.0
The MTO has permit administration for corridor control with respect to building, land use,
encroachments, entrances and signs etc., within provincial highway right-of-ways and the
ministry’s legislated area of control. Any permit issued by the Ministry shall not relieve
the owner of the necessity of meeting the requirements of local bylaws, local zoning
regulations and/or other legislation. Permitting is under the control of the MTO Corridor
Management Office. All permits must be in place prior to opening of the new highway to
traffic.
Corridor Control Permits 8.1
Building and Land Use, Encroachment, and Entrance Permits will be required prior to
construction taking place within the existing designated MTO controlled area. Permits will
be required along the realigned Highway 11 and are to be coordinated with the legal
agreement and transfer of the realigned portion of Highway 11 to MTO.
Building and Land Use Permits 8.1.1
Building and Land Use Permits will required for any construction or change in use of the
property adjacent to the highway that falls within the MTO controlled area. Relocation of
existing Utility Infrastructure will possibly require permitting depending on the selected
location of the infrastructure and its proximity to the MTO controlled area.
For extraction of aggregates and materials, applicants deal with appropriate authority
(i.e. MNR) and must provide proof of compliance prior to MTO approval. If direct access
to the highway is required, such application for an entrance permit shall be considered
simultaneously. The location of the entrance shall meet Ministry commercial standards.
The Aggregate Resources Act requires that normally no excavation of aggregates may
occur within a 30 m setback bordering a road or road right-of-way.
Where a mining claim adjoins or is adjacent to a highway or road maintained by the
Ministry of Transportation, no surface mining operations shall be carried on within 45 m
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 41
of the limits of the highway or road except with the consent in writing of the Minister.
R.S.O. 1990, Chapter, M. 14, Section 34.
Encroachment Permits 8.1.2
An encroachment includes any installation or work upon, over or under, or within the
limits of a provincial highway right-of-way (excluding entrances).
Encroachments along the Highway 11 bypass will include both the East and West tie in
locations to the existing Highway 11 alignment and the intersection of Michael Power
Boulevard. Utilities within the MTO right-of-way (Hydro One, Union Gas, Greenstone
Municipal Services, and MTO) will be relocated along the new Highway 11 alignment.
The appropriate specifications and standard drawings should be consulted for material
requirements and acceptable construction procedures to be followed during installation
of an encroachment.
All existing utilities and new plants erected within the new highway right-of-way will
require permits with some possible exceptions for Bell Canada per Statutory Authority.
Any utility will normally be expected to adhere to the following:
Confine the utility plant within a 2 m horizontal strip along the highway right-of-way
where possible, but should not take up a width more than 50% of the distance
between the right-of-way and the shoulder rounding and the right-of-way limits. The
accepted tolerance shall mean 0.5 m on either side of the approved 2 m strip.
The 2 m horizontal strip is to be parallel to and immediately adjacent to the right-of-
way, unless that location is already occupied by another utility, trees, or other
obstacles which preclude this location. The 2 m horizontal strip must be as close to
the right-of-way limit as possible, and in all cases not closer to the roadway or
pavement than the centre of the roadside ditch. Any exception must be negotiated
between the parties involved before the start of construction.
Provide appropriate depth of cover for all new roadway crossings
The utility company placing the proposed new facility shall be responsible for locating
any other existing plant as well as resolving any conflicts which could occur.
Any Municipal infrastructure situated within the road allowances or along existing
Highway 11 will require permitting through the new road authority MTO.
Entrance Permits 8.1.3
Entrance permits are required for:
All new entrances along the new Highway 11 alignment. Permits are the
responsibility of the property owner.
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 42
Construction of a temporary entrance or the use of any part of the highway right-of-
way as a means of temporary access sometimes for construction purposes (usually
issued for a 6 month or two year period).
The Municipality of Greenstone will be consulted regarding existing and new entrances
on Michael Power Boulevard.
Construction Permits 8.2
Entrances that will require grading beyond the highway right-of-way will require a
Permission to Enter from the property owner. Entrance plan and profiles will be provided
to the owner.
For all construction upon lands not owned by the proponent, i.e. Municipal road
allowances or provincial, a Permission to Construct will be required.
LEGAL AGREEMENT 9.0
The new Highway 11 realignment will have to be designed and constructed to MTO
standards. A legal agreement will be required between MTO and the proponent to
address responsibilities and obligations.
SCHEDULE 10.0
The schedule for Highway 11 construction is governed by the Premier Gold Hard Rock
Project federal EA. Property acquisition, highway design, utility relocations, highway
construction and highway transfers and designations will be in alignment with the federal
EA. A project schedule is provided below in Figure 9.1.
Figure 9.1 – Highway 11 Realignment Project Schedule
Premier Gold – Hardrock Project TBTE Ref. No. 14-192 Preliminary Design Report - Highway 11 Realignment
TBT Engineering 43
CONSTRUCTION COST ESTIMATE 11.0
The construction cost estimate for the Highway 11 realignment and associated works is
$ 14.9 million. A breakdown of quantity and costs for the major items is provided in Table
10.1. Contingencies have been included for minor items, utilities, engineering and
contract administration.
Table 10.1 – Highway 11 Realignment Cost Estimate
CLOSURE 12.0
Should there be any questions or concerns regarding the information presented in this report,
please do not hesitate to contact Premier Gold Mine Limited or TBT Engineering Limited.
Prepared By: Reviewed By: Approved By:
Don Bowes, P. Eng.,
Project Engineer
TBTE Engineering Limited
Scott Peterson, P.Geo.,
Vice President
TBTE Engineering Limited
Bertho Caron, Ing.
Eng. & Const. Manager
Premier Gold Mines Limited
<Original signed by><Original signed by>
Premier Gold – Hardrock Project TBTE Ref. No.: 14-192 Highway 11 Realignment
APPENDIX A
Preliminary Design Criteria
PRELIMINARY DESIGN CRITERIA
Date: March 2015
HARDROCK GOLD PROJECT HWY NO. 11 TYPE OF PROJECT: [G, D, GB, HMP, ILLUM] WORK PROJECT NO. Highway 11 Realignment LOCATION Hwy 11 – 2.2 km west of Michael Power Boul evard easterly for 4.7 km MUNICIPAL JURISDICTIONS Greenstone Geographic Township(s) of Errington, Ashmore
TRAFFIC
Location Year AADT SADT DHV % Comm % LT
From Hwy 584 LHRS 17880 O/S 0.0 km TO Goldfield Rd LHRS 17880 O/S 4.7 km.
HWY 11 2007 1500 1750 150 47.3 % 40.9 %
2017 1575 1840 155 NA NA
Reference – MTO GWP 6064-09-00 DC
PRESENT
CONDITIONS DESIGN
STANDARDS PROPOSED
STANDARDS RECOMMENDED BY:
HIGHWAY CLASSIFICATION
RAU 110
RAU 110
RAU 110
Signature:
MIN. STOPPING SIGHT DISTANCE (m) 160 215 215 Printed Name:
EQUIVALENT MINIMUM “K” FACTOR
CREST 50 90 90 Date:
SAG 70 50 50 MTO Project Manager / Engineer
GRADES MAXIMUM (%) 1.3 6.0-7.0 3.3 Signature:
RADIUS MINIMUM (m) 1500 525 800 Printed Name:
PAVEMENT WIDTH (m) 3.5 3.75 3.75 Date:
SHOULDER WIDTH (m) 2.0 – 2.5 2.0 2.5 Head, Planning and Design Section
SHOULDER ROUNDING (m) 0.5 1.0 1.0
MEDIAN WIDTH (m) N/A N/A N/A APPROVED BY:
R.O.W. WIDTH (m) 60 N/A 110 Signature:
POSTED SPEED (km/h) 90(a) 90(a) 90(a) Printed Name:
MISCELLANEOUS N/A N/A N/A Date:
Regional Manager, Engineering
PRELIMINARY DESIGN CRITERIA
Date: March 2015
HARDROCK GOLD PROJECT HWY NO. 11 TYPE OF PROJECT: [G, D, GB, HMP, ILLUM] NOTES Vertical and Horizontal Alignment
DESIGN SPEED (km/h)
NUMBER OF CURVES EXISTING ALIGNMENT PROPOSED DESIGN
HORIZ. CREST SAG HORIZ. CREST SAG
≥120 2 4 4 0 3 4 110 0 0 0 4 0 0 100 0 0 0 0 0 0 90 0 1 0 0 0 0
TOTALS 2 5 4 4 3 4
a) The posted speed is reduced to 70km/hr within the vicinity of the Highway 11 and Michael Power Boulevard Intersection. The reduced speed zone shall be applied to the new Highway 11 alignment within the vicinity of the Michael Power Boulevard intersection.
REMARKS: 1. Project Purpose and Scope
The purpose of the project is the construction of a new section of Highway 11 around the Hardrock Gold Project. The proponent, Premier Gold Mines Ltd. will be responsible for all aspects of the project. The highway construction project will include, but is not limited to:
• New alignment beginning 2.2 km west of the existing intersection at Michael Powers Boulevard extending easterly for 4.7 km.
• New alignment includes construction over approximately 1.2 km of existing mine tailings, known as the MacLeod High Tailings (MHT) which currently supports recreational use (golf course).
• New at grade intersection and illumination for Michael Power Boulevard. • Relocation of utility lines and infrastructure • Demolition and re-location of MTO Patrol Yard currently located at the east project limit • Decommissioning of exiting MTO electrical plant
2. Design Year The design year is 2036. Construction is anticipated for 2016.
3. Related Studies and Adjacent Projects MTO GWP 6064-09-00, Highway 11 Resurfacing Contract 2013-6012. 4. Environmental Assessment
The highway construction is considered part of the Individual Federal EA for the mine development project.
PRELIMINARY DESIGN CRITERIA
Date: March 2015
HARDROCK GOLD PROJECT HWY NO. 11 TYPE OF PROJECT: [G, D, GB, HMP, ILLUM] 5. Pavement
The pavement strategy for this project is new construction consisting of a Granular B subbase, Granular ‘A’ base, 80 mm Superpave 19.0 binder course and 50 mm Superpave 12.5 surface coarse.
6. Cross-Fall Cross-fall will meet a 110 km/h design speed standard.
7. Superelevation
Highway 11 superelevation will meet a 110 km/h design speed standard. 8. Drainage
The MTO Gravity Pipe Design Guidelines will assist in designing the gravity pipe systems. Centreline culverts will be designed using a 50 year storm return period and a 50 year design service life. The minimum highway crossing culvert size will be 800 mm diameter.
9. Roadside Safety A clear zone of 7.0 m on tangent will apply. The clear zone will be increased on curves by applying the appropriate curve correlation factor. In rock cut sections, the rock shall be removed to the minimum clear zone offset. Rock cuts should be designed in accordance with the MTO Northwest Region Rock Cut Guidelines. In fill sections the foreslope shall be at a rate no steeper than 3:1. In high fill sections where constraints restrict construction of 3:1 foreslopes, the foreslope between the bottom of the granular base and the toe of the fill may be steepened up to 2:1 in earth fills and 1.25:1 in rock fills. These areas shall be protected with guide rail.
10. Signing
Signing will be replaced, installed, or adjusted where warranted in accordance with current MTO standards.
11. Illumination
Illumination will be provided at the decision points for the Highway 11 and Michael Power Boulevard intersection and the mine site access entrance.
12. Traffic Signals
Not applicable to this project. 13. Commercial Entrances
Commercial entrances will be installed where warranted in accordance with current MTO standards. 14. Intersections
An at-grade intersection will be provided for the new Highway 11 alignment and Michael Power Boulevard. Geometric elements of Michael Power Boulevard will be designed using an 80 km/hr design speed. A portion of Michael Power Boulevard north and south of the new Highway 11 will be realigned to improve the angle of intersection. The intersection will consist of an eastbound auxiliary left turn lane and channelized right turn movements for south bound and westbound traffic.
15. Structures
Not anticipated for this project. 16. Pavement Widening on Curves
PRELIMINARY DESIGN CRITERIA
Date: March 2015
HARDROCK GOLD PROJECT HWY NO. 11 TYPE OF PROJECT: [G, D, GB, HMP, ILLUM]
Pavement widening will be applied based on the requirements of a WB 17.5 (Tractor-Semi-Trailer) vehicle.
17. Passing Lanes / Truck Climbing Lanes Not applicable to this project. 18. Fencing
Not applicable to this project. 19. Active Transportation Infrastructure
Not applicable to this project. 20. Property Requirements
Property acquisition will be required. The property necessary to facilitate the new alignment is the responsibility of the Proponent.
21. Railway Crossings
There are no railway crossings within the project limits. 22. Utilities and Pipelines
Utility relocations will be determined during Detail Design. All costs for relocation will be borne by the Proponent.
23. Construction Staging/Traffic Management
As a majority of the new highway construction is on a new alignment, major traffic impacts on the existing highway are not anticipated. Traffic staging requirements at the new Michael Power Boulevard intersection and the east and west tie-ins for the new highway alignment will be determined during detail design.
24. Legal Agreements and Approvals
A legal agreement will be required between MTO and the Proponent. 25. Highway Closings, Assumptions, Transfers
Once construction is complete and prior to traffic access, the MTO will need to acquire/assume and designate the new alignment. Following this, the MTO will have to remove the designation from the bypassed section and dispose of a portion to the proponent. The Proponent shall prepare a Property Strategy Plan and complete all required legal documents, surveys and plans with some oversight by MTO.
26. Municipal Council Resolution
A Township of Greenstone Council resolution may be required for the transferring of any portions of Michael Power Boulevard bypassed by the new highway.
27. Kenogamisis Golf Club A portion of the golf course, east of Michael Power Boulevard, would be impacted by the proposed alignment, specifically holes 10, 11, and 12 which skirt the northeastern corner of the MacLeod High Tailings.
28. MacLeod High Tailings (MHT)
PRELIMINARY DESIGN CRITERIA
Date: March 2015
HARDROCK GOLD PROJECT HWY NO. 11 TYPE OF PROJECT: [G, D, GB, HMP, ILLUM]
Preliminary explorations indicate the tailings to be 6 to 12 m thick and consist of silt to clay sized particles. Further study of the MHT is recommended to investigate their chemical and physical properties within the proposed highway corridor to assess foundation design requirements.
PRELIMINARY DESIGN CRITERIA
Date: March 2015
HARDROCK GOLD PROJECT HWY NO. 11 TYPE OF PROJECT: [G, D, GB, HMP, ILLUM]
Premier Gold – Hardrock Project TBTE Ref. No.: 14-192 Highway 11 Realignment
APPENDIX B
Preliminary Design Drawings – Highway 11 Realignment
Premier Gold – Hardrock Project TBTE Ref. No.: 14-192 Highway 11 Realignment
APPENDIX C
Preliminary Design Drawings – Mine Site Entrance
Premier Gold – Hardrock Project TBTE Ref. No.: 14-192 Highway 11 Realignment
APPENDIX D
Preliminary Geotechnical Design Report
PAVEMENT ENGINEERING DIVISION
PRELIMINARY GEOTECHNICAL DESIGN
REPORT
LOCATION:
Highway 11 Realignment – 2.2 km West of Michael Power Boulevard Easterly for 4.7 km
Prepared for: Premier Gold Mines Limited
Hardrock Site Geraldton, ON
Prepared by: TBT Engineering Limited
1918 Yonge Street Thunder Bay, ON
P7E 6T9
March 31, 2015 TBTE Ref. No. 14-192-3
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering i
Executive Summary
TBT Engineering Limited (TBTE) was retained by Premier Gold (PG) to assist with
transportation engineering for PG’s Hardrock Mine Project, specifically the completion of a
Preliminary Design Report (PDR) for the relocation of Highway 11 from 2.2 km west of Michael
Power Boulevard easterly for 4.7 km. The proposed realignment runs north of the existing
Highway 11 and will intersect Michael Power Boulevard approximately 1.3 km north of the
current intersection. The realignment will transverse the Townships of Errington and Ashmore,
Municipality of Greenstone within the Provincial district of Thunder Bay, ON.
The western portion of the realignment transverses moderate relief, bedrock controlled terrain
with intermittent pockets of fine grained silts with varying amounts of sand. The eastern portion
of the alignment transverses fine grained soils with discontinuous organic/swamp deposits and a
historical tailings dump, known as McLeod High Tailings (MHT).
Along with the attached report, a set of Preliminary Pavement Structure Treatment Charts
(PPSTC’s) are provided with preliminary geotechnical recommendations for the various
realignment sections addressing site specific conditions. The PPSTC will include pavement
structure thicknesses, frost heaving and erodiblity potential, and drainage recommendations.
Geotechnical investigations and recommendations for the portion of highway bypass traversing
the MHT are addressed by TBTE’s Preliminary Foundation Design Report, under a separate
cover.
The preliminary pavement structure design is based on the anticipated traffic loadings along with
references to MTO and AASHTO design methods.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering ii
Attachments
Appendix 1 Pavement Structure Treatment Charts
Highway 11 6 Pages
Michael Power Boulevard 4 Pages
Appendix 2 Borehole Logs
Township of Errington 6 Pages
Township of Ashmore 2 Pages
Appendix 3 Laboratory Results
Township of Errington 13 Pages
Township of Ashmore 6 Pages
Appendix 4 MTO Geotechnical Abbreviations 1 Pages
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering iii
Table of Content
INTRODUCTION ............................................................................................................. 1
LOCATION ...................................................................................................................... 1
PROJECT DESCRIPTION ............................................................................................... 2
Highway Alignment Evaluation Study ............................................................................... 3
EXISTING TAILINGS MANAGEMENT FACILITY ............................................................ 4
INVESTIGATION ............................................................................................................. 4
PHYSIOGRAPHY AND SOILS DATA .............................................................................. 5
Subgrade Materials ...................................................................................................... 5 Bedrock Geology .......................................................................................................... 6 Groundwater Table ...................................................................................................... 7 Suitability of Overburden Soils ..................................................................................... 7
TRAFFIC DATA ............................................................................................................... 7
RECOMMENDATIONS AND CONSTRUCTION FEATURES .......................................... 9
Pavement Structure Design .......................................................................................... 9 New Roadway Construction ........................................................................................11
Preliminary Pavement Design ..............................................................................11
Embankment Fill Chart .........................................................................................12
Stripping and Muskeg Excavation ...............................................................................13 Widening and Benching ..............................................................................................13 Drainage .....................................................................................................................14
Drainage Culverts ................................................................................................14
Open Ditches .......................................................................................................14
Foreslope and Backslope Grades ...............................................................................14 Erosion Protection .......................................................................................................14
Seed and Cover ...................................................................................................15
Granular Sheeting ................................................................................................15
Transition Treatments .................................................................................................16 Slope Flattening and Foreslope Construction ..............................................................16
Side Roads and Entrances ..........................................................................................17 Frost Penetration Depth ..............................................................................................17
LIMITATIONS .................................................................................................................17
CLOSURE ......................................................................................................................18
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 1 of 18
INTRODUCTION
TBT Engineering (TBTE) has been retained by Premier Gold Mines Limited (PG) for the
provision of a Preliminary Design Report (PDR) for the relocation of Highway 11 as part of PG’s
Hardrock Gold Project near Geraldton, Ontario. Preliminary studies completed to support the
PDR include topographical engineering surveys, geotechnical investigations studies and field
investigations). The following report describes the findings from the preliminary geotechnical
field investigations and laboratory testing and provides preliminary geotechnical pavement
engineering recommendations.
LOCATION
Premier Gold’s Hardrock site is centralized near the existing intersection of MTO Highway 11
and Michael Power Boulevard located 5.4 km south of the town of Geraldton, Ontario.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 2 of 18
The proposed highway realignment traverses the geographical townships of Errington and
Ashmore.
Chainages for the proposed Highway realignment are as follows:
West Project Limit: STA 10+000 Errington Twp. Michael Power Boulevard Intersection: STA 12+172 Errington Twp. Township Change: STA 12+177 Errington Twp. = 12+177 Ashmore Twp. East Project Limit: STA 14+684.751 Ashmore Twp.
PROJECT DESCRIPTION
King’s Highway 11 is classified as a rural arterial undivided (RAU 110) facility. The segment of
Highway 11 effected by the relocation is running east-west and is located south of the
community of Geraldton, ON. The primary function of Highway 11 is to provide access across
Northern Ontario as well as a link between many small communities. The new bypass will be
designed and constructed to meet MTO standards. Upon designation and transfer of the new
corridor from PG to MTO, the existing bypassed segment will be transferred to PG.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 3 of 18
Currently Michael Power Boulevard connects Highway 11, northerly to Geraldton and MTO
secondary Highway 584 extending northerly.
HIGHWAY ALIGNMENT EVALUATION STUDY
TBTE had previously completed a Highway Alignment Evaluation Study (trade off study) which
evaluated six alignment alternatives, five of which bypassed the Hardrock Project Site to the
north and one to the south. Four of the alignment options were removed from this segment
given there their proximity to the proposed open pit which did not accommodate a 500 m
buffer/setback.
Through consultation and engagement with the MTO, the highlighted alignment (alignment 1D
from the trade off study) was selected as is presents the best vertical and horizontal alignment
and intersects Michael Power Boulevard at the most favorable angle.
Since the trade off study was conducted, minor alterations to the horizontal alignment and
vertical profile have been made during the PDR phase in order to optimize the cut – fill material
quantities, accommodate mine infrastructure planning, and address foundation issues
associated with the McLeod High Tailings.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 4 of 18
EXISTING TAILINGS MANAGEMENT FACILITY
Where the realignment portion of Highway 11 extends easterly from Michael Power Boulevard
the existing ground conditions change from muskeg/swamp to historic tailings, formerly known
as the MacLeod High Tailings (MHT). As part of the PDR assignment, TBTE has investigated
the existing conditions of the MHT facility and will provide preliminary embankment
recommendations for new construction of Highway 11 over the existing Tailings. The results of
the investigations and the preliminary recommendations will be covered under a separate report.
INVESTIGATION
Preliminary geotechnical field investigations to investigate the subsurface conditions along the
proposed alignment options were drilled using hand auger equipment. Explorations east of
Michael Power Boulevard approaching and across the MHT site were completed using TBTE’s
CME 75 and CME 55 drill rigs equipped for geotechnical sampling and testing.
All borehole locations were geospatially referenced using hand held Trimble GeoXT GPS units
and are provided on the attached Borehole Logs in Appendix 2. Hydraulic boreholes completed
for the preliminary geotechnical foundation study were surveyed with Real Time Kinematic
(RTK) equipment.
Representative soil samples were collected for laboratory testing to investigate their engineering
properties and gradations. The lab testing program consisted of natural moisture contents,
grainsize analysis, and liquid and plastic limit determination testing (as appropriate). Laboratory
Reports are attached in Appendix 3 and summarized on the attached Borehole Logs in
Appendix 2.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 5 of 18
PHYSIOGRAPHY AND SOILS DATA
Subgrade Materials
The subgrade conditions within the project limits can be generalized into three predominant types.
The western portion of the alignment, approximately 1/3 of the project length, consists of
moderate relief, bedrock controlled terrain with thin, discontinuous deposits of sand and
silt.
The middle segment, approximately 1/3 of the project length includes low-lying terrain
occupied by organic deposits atop undulating bedrock and fine grained soils.
The eastern portion of the alignment, the remaining 1/3 of the project length, includes
historical mine tailings beaches and mine tailings dump (known as McLeod High Tailings).
The McLeod High Tailings (MHT) consists of a large tailings deposit placed over natural terrain,
dating back to the 1930’s. The perimeter of the deposit consists of shaped tailings with varying
side slopes and configurations. Typically in the areas of this investigation the side slopes are
roughly 2.5 horizontal to 1 vertical. Some sections of the MHT perimeter have a toe berm/drain
while other sections do not. A tailings beach is also evident along much of the toe of the MHT
perimeter. The height of the perimeter typically varies from 6 to 8 m. Reshaping of the perimeter,
plus the construction of the toe berms (where applicable) was completed circa 2000.
It is understood that the original terrain consisted of a low lying swamp which is still evident at
some locations beyond the perimeter of the MHT.
The subsurface soils along the alignment on top of the MHT typically consist of fill/topsoil at
surface underlain by tailings. The tailings are underlain by organic material followed by silt. The
silt is underlain by a till with occasional cobbles before auger and/or SPT refusal.
The subsurface soils around the perimeter of the MHT typically consists of organic material or
tailings at surface, followed by silt which are underlain by a till with occasional cobbles before
auger and/or SPT refusal.
Peat/organic deposits, extending up to 3.0 m are common through lower-lying areas with the
water table generally present at surface.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 6 of 18
Native non cohesive silt and sand deposits were generally found to have moderate frost
susceptibility and moderate to high erosion potential. Field observations indicate the deposits
were typically in a loose to compact condition.
Cohesive deposits are more prevalent within the eastern portion of the alignment. These soils
are considered to be moderately to highly frost susceptible and have high erosion potential.
Typically, fine grained cohesive soils exhibit less erodible characteristics than silty non-cohesive
soils. However the samples taken from the eastern portion of the realignment only contain small
amounts of clay which does not assist in reducing erosion since it reduces soil permeability and
increases runoff. Based on field observations, the majority of the soils were found to have a firm
to stiff consistency.
Bedrock Geology
The geology of the study area has been taken from the 43-101 Mineral Resource Estimate
Update – Hardrock Project, 2014 which sites work by Lafrance, 2004, and OGS Maps No. 1951-
2 and No. 1951-7. The re-alignment of Highway 11 wraps the northern edge of the proposed
open pit outline at the Hardrock Project site. The proposed re-alignment is underlain by the
southern sedimentary unit of the Beardmore-Geraldton Greenstone belt, part of the Wabigoon
Subprovince. The southern sedimentary unit is composed of metasedimentary pile consisting
of thick sequences of sandstone-argillite and minor polymictic conglomerate with interlayered
magnetite-chert banded iron formation.
Based on mapping by F.G. Pye, 1949, the re-alignment is restricted to the Quartz greywacke
(sandstone) with minor intercalated conglomerate sequences that have been cut by dykes
composed of diorite, hornblende diorite, and hornblende gabbro. In the area of Mosher Lake,
the re-alignment will be underlain by iron formation, albite porphyry and intermediate volcanic
tuffs and breccias. Structural fabrics in the area of the re-alignment include the Ellis Syncline, a
regional, west-northwest trending syncline that plunges shallowly to the west-northwest
(280o/35o).
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 7 of 18
Groundwater Table
Preliminary investigations completed along the proposed highway re-alignment indicate that the
water table is present at or near surface through low-lying muskeg areas, within 2.0 m of ground
surface across the MHT, and in the order of 5 to 10 m below the elevated bedrock grade within
the western portion of the project length.
Suitability of Overburden Soils
Organic materials are typically very compressible, have poor load sustaining properties and a
low shear strength. These materials should be excavated as per Section 9.3 of this report and
may be suitable for re-use as landscaping material, mine or aggregate site rehabilitation, cover
over earth slopes or abandoned sections of roadway to aid in crop/vegetation development or
hauled to a suitable disposal site.
The fine grained lacustrine silt and clay soils present are generally situated within lower lying
segments of the highway alignment and will be covered by embankment fill. Where these
materials are excavated, they should be considered waste, not considered suitable for highway
embankment.
Fine to medium grained granular material (sand with gravel and trace silt) is present near the
west limit of the proposed Highway 11 bypass. Preliminary tests indicate that sections of this
deposit may be suitable as subgrade fill although quantities are expected to be limited. Further
investigations are recommended during detailed design to assess the quality and quantity of this
deposit.
TRAFFIC DATA
The preliminary pavement structure design is based on 20 year Equivalent Single Axle Loads
(ESAL’s) derived from previous & forecasted traffic studies.
Previous traffic studies within the project limits were divided into two sections: Michael Power
Boulevard Westerly (Section 1) and Michael Power Boulevard Easterly (Section 2). Traffic data
for Section 1 was provided by MTO and included Average Annual Daily Traffic (AADT) volumes
and percent commercial traffic observed in 2007 and forecasted volumes for 2017. Using the
AADT values provided an annual growth rate of 0.5% was calculated.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 8 of 18
Traffic data, including AADT and commercial traffic information, for Section 2 was obtained from
MTO’s iCorridor – Transportation Planning & Forecasting online program. For Section 2 the
program was limited to observed traffic rates in 2006. For forecasting purposes the annual
growth rate of 0.5% (calculated for Section 1) was applied.
For design purposes the AADT of both sections was calculated for the years 2015 and 2035 (20
year design period). For both sections, the 2035 interpolated AADT includes the additional mine
traffic of 360 and 175 vehicles/day for Sections 1 and 2 respectively.
The forecasted additional mine traffic data was obtained from Stantec’s “Highway 11 Feasible
Route Study” report that was provided to TBTE by Premier Gold.
Table 8.0.1 – Traffic Analysis Summary
Traffic Data
Section 1
Michael Power Boulevard W’ly
Section 2
Michael Power Boulevard E’ly
AADT (2006) - 1850
AADT (2007) 1500 -
AADT (2017) 1575 -
Interpolated AADT (2015) 1560 1933
Interpolated AADT (2035) 2080 2307
Annual Growth Rate 0.5%
Percent Commercial Traffic (%) 47.3 29.6
Percent Long Trucks (%) 40.9 25.5
Design ESAL’s (20 Years) 11,595,182 8,990,059
As shown in Table 8.0.1 the anticipated 20 year ESAL value for Section 1 - Michael Power
Boulevard W’ly is larger than Section 1 and as such will govern the Highway 11 pavement
structure design.
Traffic volumes and ESAL loadings for the components of the Michael Power Boulevard
intersection were derived from traffic data in Stantec’s “Highway 11 Feasibility Route Study”.
The forecasted traffic loadings on Michael Power Boulevard are 1.6 M 20 yr ESAL’s for the
section extending northerly from proposed Highway 11 and 1.6 M 20 yr ESAL’s for proposed
Michael Power extension south of the proposed intersection.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 9 of 18
During the detail design process it is recommended that more recent traffic data be obtained for
additional analysis.
RECOMMENDATIONS AND CONSTRUCTION FEATURES
The following sections provide details specific to the preliminary pavement engineering
recommendations and construction features.
Pavement Structure Design
The preliminary pavement structure design was carried out utilizing MTO Adaption and
Verification of AASHTO Pavement Design Guide for Ontario Conditions (Materials Information
Report MI-183).
Structural Numbers (SN) used in analyses have been derived using standard values for new
construction projects. The following references and guidelines were used for the pavement
design and soil classifications:
MTO’s “Adaption and Verification of AASHTO Pavement Design Guide for Ontario Conditions”, MI-183, March 2008
AASHTO Guide for the Design of Pavement Structures. 1993
MTC Soil Classification Manual
Pavement Design and Rehabilitation Manual, MTO
The following design considerations were addressed in using the AASHTO mechanistic
pavement design approach:
1) Traffic 2) Roadbed Soils 3) Construction Materials 4) Drainage 5) Reliability
The SN design method references the amount of traffic anticipated over the design life, normally
described using Equivalent Single Axle Loads (ESAL’s), a standardized truck axle rating. The
cumulative number of ESAL’s over a design period of 20 years is estimated to be 11.6 M.
A target SN for the highway realignment has been developed using the above design
considerations and is summarized in the table below. A design subgrade of low plastic clay was
utilized for the SN analysis program.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 10 of 18
Table 9.1.1 – AASHTO Design Factors & Target Structural Numbers (SN)
Design Factor Description/Data Remarks
Time Constraint 20 year Design Period
Traffic Data Design lane 20 year ESAL’s 11.6 x 106 (365 day/yr)
Based on 47.3% Commercial Traffic
Design Subgrade
Clay (Low Plasticity) Predicted Resilient Modulus =16 MPa
MI – 183, Table D-8 (20 % reduction to accommodate northern conditions)
Construction Materials AASHTO – Ontario Structural Layer Coefficients (SLC)
New Material Asphaltic Concrete = 0.42 Granular A Base = 0.14 Granular B – Type II Subbase = 0.12
Drainage Coefficient M1,2,3 = 1.0
MI – 183, Table D-9 & D-10
Level of Reliability (R) & Standard Deviation (So)
R = 90 So = 0.47
MI – 183 Table D-7
Serviceability ( PSI) 2 MI – 183, Table D-6
Target Structural Number = 177
Based on the recommended structural layer coefficients provided in Table D-9 of MI – 183
publication and the parameters listed above (Table 9.1.1), the Structural Number (SN) for the
proposed Highway 11 realignment is provided below in Table 9.1.2.
Table 9.1.2 – Proposed Pavement Structure
Type of Structure
Pavement Structure Summary Structural Layer
Coefficients
Structural Number Component Avg. Thickness (mm)
Typical Pavement Structure
New Asphaltic Concrete 130 0.42 55
New Granular ‘A’ 150 0.14 21
New Granular ‘B’ Type II 850 0.12 102
Design Structural Number 178
As illustrated in Table 9.1.2 above, a pavement structure including 130 mm of hot-mix
SuperPave asphalt, 150 mm Granular ‘A’, and 850 mm Granular ‘B’ – Type II meets the
theoretical structural number of 177 mm over a low plastic clay subgrade.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 11 of 18
New Roadway Construction
Preliminary Pavement Design
The preliminary pavement structure for Highway 11 consists of 130 mm of hot-mix asphalt
with a PGAC of 58-34, 150 mm of new Granular ‘A’ and 850 mm Granular ‘B’ Type II
subbase fill. Specific granular depths for earth and rock excavation scenarios are provided in
the Preliminary Pavement Structure Treatment Charts (PPSTC’s).
The pavement types for the main lanes of Highway 11 shall be specified as 80 mm
SuperPave 19.0 binder course and 50 mm SuperPave 12.5 surface course. The main lanes
and auxiliary lanes should be paved with both courses, providing 130 mm HMA and paved
shoulders shall include 50 mm SuperPave 12.5, matching the main lane surface course.
The preliminary pavement structures of both the north and south section of Michall Power
Boulevard includes a granular structure of de=750 mm (150 mm Granular ‘A’ and 600 mm
Granular ‘B’ – Type II). Paving shall include a 50 mm SP 12.5 surface course for both
sections and a 50 mm SuperPave 19.0 binder course for the north section. Paved shoulders
shall include 50 mm SP 12.5, matching the main lane surface course.
Traffic ramps will be provided for Highway 11 westbound traffic turning northbound on
Michael Power Boulevard (E-N Ramp) and southbound Michael Power Boulevard traffic
turning westbound onto Highway 11 (N-W Ramp).
For both ramps, a granular structure of de= 750 mm (150 mm of Granular ‘A’ and 600 mm
Granular ‘B’ - Type II) shall be maintained through all cut sections. Fill sections shall be
constructed as per section 9.2.2.1 of this report. Widening and muskeg excavation shall be
done as per the appropriate section of the PGDR.
Paving of the main ramp lanes shall consist of a 50 mm SuperPave 19.0 binder course and a
50 mm SuperPave 12.5 surface course. Paved shoulders shall include 50 mm SP 12.5,
matching the main lane surface course.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 12 of 18
A summary of the preliminary summary of the types and thicknesses of asphaltic concrete for
Highway 11 and Michael Power Boulevard are as follows:
o Highway 11 Main Lanes: 50 mm SuperPave 12.5 Surface Course 80 mm SuperPave 19.0 Binder Course
o Highway 11 Auxiliary Lanes: 50 mm SuperPave 12.5 Surface Course
80 mm SuperPave 19.0 Binder Course
o Highway 11 Paved Shoulders: 50 mm SuperPave 12.5
o Highway 11 Ramps to 50 mm SuperPave 12.5 Surface Course Michael Power Boulevard North: 50 mm SuperPave 19.0 Binder Course
o Michael Power Boulevard North: 50 mm SuperPave 12.5 Surface Course
50 mm SuperPave 19.0 Binder Course
o Michael Power Boulevard South: 50 mm SuperPave 12.5 Surface Course
o Hwy 11 Ramps & Michael Power 50 mm SuperPave 12.5 Surface Course Boulevard Paved Shoulders:
Table 9.2.1.2 below summarizes the hot mix design criteria to be used for the project.
Table 9.2.1.2 – SuperPave Mix Design Criteria
HMA Type Traffic Category
PGAC Grade ACBID (%)
SuperPave 19.0 D* 58-34 4.8
SuperPave 12.5 D* 58-34 5.2
*Paving courses for Michael Power Boulevard may have a traffic category B.
Embankment Fill Chart
Table 9.2.2.1 is provided for the design team to apply at fill locations. The following minimum
granular depths shall apply to this work project, unless stipulated otherwise in the PPSTC’s
and shall consist of 150 mm of Granular ‘A’ and the remainder of Granular ‘B’ - Type II.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 13 of 18
Table 9.2.2.1 Embankment Fill Granular Thickness Chart
Item Subgrade Material Minimum Granular Fill Thickness (mm)
i) Over Bedrock (shattered surface) 300
ii) Over a minimum 500 mm thickness of Rockfill 300
iii) Over a minimum 500 mm thickness of Select
Subgrade Material (SSM) 850
- Sub-excavation may be required to meet the minimum subgrade fill thicknesses noted above; - Where fill heights are less than 300 mm, construct entirely with Granular ‘A’
Typical unit weights (compacted) are provided below for design purposes only. SuperPave 12.5 and 19.0 Asphaltic Concrete 2460 kg/m3 Granular ‘A’ 2400 kg/m3 Granular ‘B’ – Type II 2200 kg/m3
Stripping and Muskeg Excavation
All topsoil and organic/muskeg should be removed from the proposed new highway footprint
regardless of the fill height. For design purposes assume an average stripping depth of 200 mm
and that stripping commences at the inner edge of rounding where widening. Grubbing shall be
done in accordance with OPSS 201. For design purposes, assume a grubbing depth of 300
mm. Grubbing shall not apply for embankments greater than 2.5 m.
All organic deposits and muskeg should be removed as per OPSD 203.010 for new
construction.
Widening and Benching
Widening is required where Highway 11 and Michael Power Boulevard transition from the
existing alignment to the re-alignment portions. Benching of the fill embankment may be
required at transition / widening areas and should be completed as per OPSD 208.010.
Widening of existing rock embankments should not require benching. Cross sections should be
reviewed prior to completion of detailed design to verify limits and areas of such applications.
End dumping from the top of the existing fill should not be allowed.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 14 of 18
Drainage
Drainage Culverts
All culverts to be placed on this project should be treated as per appropriate section of OPSD
802 and 803 series. In areas of organic material, culverts should be placed in accordance
with OPSD 203.04.
Open Ditches
New ditches associated with the new alignment should be constructed using geodetic control,
ensuring positive drainage of the pavement structure. Ditch inverts should be established a
minimum of 500 mm below the top of subgrade.
Foreslope and Backslope Grades
Rockfill embankments shall be constructed no steeper than 1.25:1. Granular fill embankment
shall be constructed no steeper than 2:1.
Earth foreslopes and backslopes in cut sections will vary depending on the erodibility of the
earth cut material. Where erodibility is low or moderate (k factors < 0.40) foreslopes and
backslopes shall be constructed no steeper than 2:1 and where erodibility is severe (k factor ≥
0.40) no steeper than 3:1. All disturbed earth backslopes and foreslopes should be treated with
seed and cover as per section 9.7. The PPSTC provide specific details regarding erodibility.
Rock cut backslopes shall conform to the Northwestern Ontario Rock Cut Design Guidelines
which generally allow for a vertical cut for faces less than 10 m in height. Rock cuts greater than
10 m in height shall be constructed at 0.25:1. To achieve uniformity, rock cuts less than 10 m
may require similar 0.25:1 backsloping to join up sections greater than 10 m.
Erosion Protection
Erosion factors (k) are reported on the borehole logs. Specific erosion treatments are included
in the PPSTC’s attached as Appendix 1. In general, the predicted soil erodibility is moderate for
the silt and sand subgrade and severe for the low plasticity silty clay subgrade.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 15 of 18
Seed and Cover
All disturbed earth slopes should be treated as per Provincial OPSS 804. Available organic
material meeting OPSS 802 may be applied to earth cut slopes in accordance with OPSS
802.07 prior to seed and cover.
Granular Sheeting
Select locations with severe erodiblity concerns will require additional armouring. Details of
such locations can be found in the PPSTC’s. In general, slope protection will include 300
mm of Granular Sheeting beginning at the top of subgrade on the foreslope and shall extend
1.5 m up the backslope. The remaining earth backslope (from 1.5 m above bottom of ditch to
the top of backslope crest) shall be protected with seed and cover as per section 9.7.1.
Subexcavation will be required to accommodate the 300 mm layer of Granular Sheeting.
Granular sheeting materials shall conform to OPSS 1004. Granular ‘B’ – Type II shall be
used for granular sheeting. As such, the gradation curve of the Granular Sheeting in OPSS
1004 should be adjusted to allow for up to 10% passing the 75 µm sieve. The gradation
curve can be found below in Table 9.7.2.1.
Table 9.7.2.1 Modified Granular Sheeting Gradation
Sieve Size Modified Granular Sheeting Gradation
150 mm 100
26.5 mm 50.0 – 100
13.2 mm 35.0 – 100
4.75 mm 20.0 – 80.0
1.18 mm 10.0 – 50.0
300 µm 5.0 – 25.0
150 µm 0 – 15.0
75 µm 0 – 10.0*
*Adjusted from 8.0% passing in OPSS 1004 to 10.0%
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 16 of 18
Transition Treatments
All transition treatments should be treated as per the appropriate section of OPSD 205. For
design purposes, use a treatment depth of t=1.5 m, granular depth over bedrock dr=300 mm,
depth of organic accumulation da=300 mm. The granular fill depth over earth (de) will be
displayed in the PPSTC and will vary depending on the earth subgrade material.
Slope Flattening and Foreslope Construction
All slope flattening areas should be reviewed for drainage and areas of proposed rock fill should
be designed with drainage gaps as per OPSD 202.020 (or a 1.0 m, full width free draining
drainage layer at the base) where required.
Top of the slope flattening should not extend above 0.5 m below the top of subgrade, or
should be constructed of free draining material
Surplus earth placed adjacent to existing fill should be comprised of acceptable fill
construction materials (Table 9.2.2.1). Materials that have high organic contents and/or
exhibit plasticity (clay) and/or are too wet to place as a stable unit should be considered
as waste or stockpiled to dry or used for landscaping or topsoil (Depending on organic
content) cover to a depth not exceeding 150 mm.
Where modified/ blended embankment construction is required, comprised of a rockfill core and
earth foreslopes, a drainage base layer is required to allow free lateral drainage of the
embankment core fill and subgrade soils. Drainage layers should be constructed of like
materials, matching or exceeding the hydraulic conductivity of the core embankment fill and
should be placed at strategy locations to ensure positive drainage of both embankments.
Drainage layers constructed of rockfill should be covered with Class II non-woven geotextile
(FOS 75-150) to mitigate the migration of the overlying material into the drainage layer. The
drainage layers shall have a minimum width of 5.0 m, thickness of 1.0 m (above original
ground), and spaced at a maximum interval of 75 m (spacing defined by terrain).
Where muskeg excavation is required and drainage layers are to be employed, muskeg should
be removed full depth and width at the drainage locations.
Premier Gold – Hardrock Site TBTE Ref. No. 14-192-3 Preliminary Geotechnical Design Report
TBT Engineering Page 17 of 18
Side Roads and Entrances
New side road and driveway embankments shall be constructed using a de=600 mm and dr=300
mm. New side-road embankments shall be constructed with Granular ‘B’ Type II subbase
capped with 150 mm Granular ‘A’. Pavement side roads and entrances shall be paved with 50
mm of SP 12.5 matching the main lane mix design. Further assessment and design required
during the detailed design phase once proposed uses and traffic loadings are available for new
side road locations.
All topsoil or muskeg should be removed from the proposed new side road / entrance footprint
prior to the placement of granular fill.
Frost Penetration Depth
Based on the MTO’s Pavement Design and Rehabilitation Manual, the estimated frost
penetration depth at the project site is 2.5 m.
LIMITATIONS
Conclusions and preliminary recommendations presented in this report are based on the
analyses of the information available and are intended for the use of the design team as part of
the preliminary design report. Further investigations and analyses should be done prior to detail
design and construction.
Any issues or claims arising from these recommendations, where based on erroneous data
provided by others, shall not be the responsibility of TBT Engineering Limited. Conditions may
become apparent during detail design that was not reflected in the available data. Sub-surface
and groundwater conditions between and beyond test locations may differ from those provided.
If new information is discovered during future work, TBT Engineering shall be allowed to re-
evaluate the conclusions presented in this report and to provide amendments as required.
The information contained within this report in no reflects any environmental aspect of the site or
soil.
<Original signed by><Original signed by>
APPENDIX 1 –
Pavement Structure Treatment Charts
Highway 11 Realignment Preliminary Pavement Structure Treatment Charts TBTE Ref. No.: 14-192-3 March 31, 2015
Page 1 of 6
Preliminary Pavement Structure Treatment Charts
Location Feature Recommended Treatment Comments/ Rationale Highway 11 Realignment STA 10+000 – 14+685
Basic Pavement Strategy: - Pave main lanes, and auxiliary lanes with 80 mm SP 19.0 binder course and 50 mm SP 12.5 surface course - Pave shoulders with 50 mm SP 12.5 matching surface course from main lanes
10+000 – 10+220
Transition from existing Highway 11 to new Highway alignment Fill Widening Lt. (North)
Remove asphalt full depth and width. Reshape with Granular ‘A’ for profile and crossfall correction. For design purposes assume 250 mm of asphalt (200 mm existing plus net increase of 50 mm paved under Contract 2013-6012). Construct a 5 m step joint at 10+000 – 10+005 for the full thickness of the new surface course. Grade granular to ensure a smooth transition (min. 400:1). Bench existing foreslope as per OPSD 208.010 and strip remainder of widening footprint. Ensure that existing north side ditch directs drainage away from new embankment. Ensure a minimum granular structure of de=1.0 m.
Previous Highway 11 investigations done in 2012 indicate the existing highway is constructed with granular depths of 1.7 m overlying a slightly plastic silt and sand subgrade. Asphalt core data conducted under the same assignment indicates the section of Highway 11 requiring widening has between 180 and 220 mm of existing HMA. If the existing highway embankment is constructed with rockfill benching is not required.
10+220 – 10+370 Proposed Earth & Rock Cut
Excavate to provide a minimum of dr= 300 mm in rock and de= 1000 mm in earth. Ensure positive drainage of granular structure and transition treatments. Treat transitions as per appropriate section of OPSD 205. For design purposes use de=1000 mm, t=1.5 m and Y=12 m.
Borehole data indicates ~ 50 mm of organic overburden overlying fine sandy silt with intermittent pockets of F-Med Sand with silt transitioning to bedrock on surface at station 10+324.
Highway 11 Realignment Preliminary Pavement Structure Treatment Charts TBTE Ref. No.: 14-192-3 March 31, 2015
Page 2 of 6
Preliminary Pavement Structure Treatment Charts
Location Feature Recommended Treatment Comments/ Rationale
10+370 – 10+670 Proposed Fill
Construct granular structure in accordance with Granular Thickness Table (Section 9.2.2.1 of PGDR). Grub organics as per GDR where muskeg excavation is not required. 10+435 – 10+460 Excavate muskeg full depth as per OPSD 203.010. Ensure positive drainage.
10+370 – 10+435 Borehole data indicates bedrock on surface. 10+435 – 10+460 Low lying swamp with deep pockets of organics extending to depths up to 2.2 m. Subgrade typically consists of undulating bedrock with clay extending to 2.5 m below OG. 10+470 – 10+610 Borehole data indicates ~ 50 mm of organics overlying ~ 900 mm of sand with varying amounts of silt and overlying a bedrock subgrade. 10+610 – 10+670 Bedrock on surface.
10+670 – 10+990 Proposed Rock Cut
Construct rock cut to allow for a minimum dr= 300 mm in rock. Treat transitions as per appropriate section of OPSD 205. For design purposes, use de=850 mm, t=1.5 m and Y=12.0 m. Ensure positive drainage of granular structure and transition treatments.
Borehole data indicates bedrock on surface.
Highway 11 Realignment Preliminary Pavement Structure Treatment Charts TBTE Ref. No.: 14-192-3 March 31, 2015
Page 3 of 6
Preliminary Pavement Structure Treatment Charts
Location Feature Recommended Treatment Comments/ Rationale
10+990 – 11+150 Proposed Shallow Fill with shallow rock
For fill scenarios, strip and grub as per PGDR recommendations. Construct granular structure in accordance with Granular Thickness Table (Section 9.2.2.1 of PGDR). Ensure a minimum granular structure of de=850 mm in earth and dr= 300 mm in rock. Treat transitions as per appropriate section of OPSD 205. Ensure positive drainage of granular structure and transition treatments. Earth cut material may be suitable for reuse as subgrade fill. Rock cut material may be acceptable to be reused as rock fill.
10+990 – 11+100 Borehole data indicates bedrock on surface. 11+100 – 11+150 Borehole data indicates 50 mm of organics overlying ~ 900 mm of fine sand with varying amounts of gravel and silt overlying a bedrock subgrade.
11+150 – 11+358 Proposed Fill
Construct granular structure in accordance with Granular Thickness Table (Section. 9.2.2.1 of PGDR). 11+165 – 11+358 Excavate muskeg full depth as per OPSD 203.010. Ensure a minimum granular structure of de=1000 mm in earth and dr=300 mm in rock. Ensure positive drainage.
Borehole data indicates organics ranging in depth from 1.1 to 1.6 m overlying fine sand with silt contents varying 35 to 45 %.
Highway 11 Realignment Preliminary Pavement Structure Treatment Charts TBTE Ref. No.: 14-192-3 March 31, 2015
Page 4 of 6
Preliminary Pavement Structure Treatment Charts
Location Feature Recommended Treatment Comments/ Rationale
11+358 – 11+940 Proposed Cut and Shallow Fill
In fill sections where muskeg excavation is not required, strip and grub as per PGDR recommendations. Ensure a minimum granular structure of de=1000 mm in earth and dr=300 mm in rock. 11+556 – 11+720 Excavate muskeg full depth as per OPSD 203.010. 11+700 – 11+940 Grade earth backslopes no steeper than 3:1 and apply granular sheeting as per PDR recommendations. Treat earth cut to rock cut as per OPSD 205.050. For design purposes, use t=1.5 m, de=1000 mm and Y = 10 m. Ensure positive drainage of the granular structure and transition treatments. Earth cut material may be suitable to be reused as embankment fill. Rock cut material may be suitable as rock fill.
Borehole data indicates organics ranging in depth from 700 mm to 3.0 m. Subgrade underlying the organics consists of low plasticity silty clay to silty F-Med sand. Bedrock was encountered on the ridge at station 10+368. Lab data indicates the silty F-Med sand subgrade is moderately susceptible to frost heaving and moderately erodible (0.35). Lab data indicates the silty clay is moderately susceptible to frost heaving and severely erodible (k=0.55).
Highway 11 Realignment Preliminary Pavement Structure Treatment Charts TBTE Ref. No.: 14-192-3 March 31, 2015
Page 5 of 6
Preliminary Pavement Structure Treatment Charts
Location Feature Recommended Treatment Comments/ Rationale
11+940 – 12+700
Proposed Fill
12+025 – 12+180; 12+206 – 12+700 Excavate muskeg full depth as per OPSD 203.010. Where muskeg excavation is not required, grub organics as per GDR recommendations. Ensure a minimum granular structure of de=1000 mm in earth and dr=300 mm in rock. Where new Highway 11 alignment crosses Michael Power Boulevard: Remove existing asphalt full depth. Maintain the granular structure of de= 1000 mm. Ensure the existing drainage features do not drain into the new roadway embankment. Ensure positive drainage of the granular structure and transition treatments.
Borehole Data indicates muskeg depths ranging from 500 mm to 2.1 m. Subgrade underlying organics generally consists of silty clay with varying amounts of fine to medium sand. Lab data indicates the silty clay subgrade is of low plasticity, is moderately to highly susceptibility to frost heaving and severely erodible (0.57< k < 0.63). Existing Michael Power Blvd crosses new Highway alignment at station 12+200 (roughly).
Realignment of Highway 584 (Michael Power Blvd)
12+200 Refer to Preliminary Pavement Structure Treatment Charts for Michael Power Boulevard realignment. See PGDR for the recommendations regarding the East-North and North-West ramps.
12+700 – 14+500
Embankment Fill overriding existing tailings management area.
Refer to Preliminary Geotechnical Foundation Report. Apply granular thickness as per PGDR granular thickness table.
Highway 11 Realignment Preliminary Pavement Structure Treatment Charts TBTE Ref. No.: 14-192-3 March 31, 2015
Page 6 of 6
Preliminary Pavement Structure Treatment Charts
Location Feature Recommended Treatment Comments/ Rationale
14+500 – 14+685 Transition back to existing Highway 11
Remove asphalt full depth and width. Reshape with Granular ‘A’ for profile and crossfall correction. Construct a 5 m step joint at 14+680 – 14+685 for the full thickness of the new surface course. Grade granular to ensure a smooth transition (min. 400:1). Bench existing foreslope as per OPSD 208.010 and strip remainder of widening footprint. Ensure that existing north side ditch directs drainage away from new embankment. Ensure a minimum granular structure of de= 1.0 m.
No borehole investigations of the existing highway have been conducted through this section. If the existing highway embankment is constructed with rockfill benching is not required.
Michael Power Blvd Realignment Preliminary Pavement Structure Treatment Charts TBTE Ref. No.: 14-192-3 March 31, 2015
Page 1 of 4
Preliminary Pavement Structure Treatment Charts
Location Feature Recommended Treatment Comments/ Rationale Michael Power Blvd Realignment (MPB) STA 9+648.684 – 10+421.671
Basic Pavement Strategy for MPB North of new Highway 11: - Pave main lanes and widening sections with 50 mm SP 12.5 surface course and 50 mm SP 19.0 binder course. - Pave shoulders with 50 mm SP 12.5 surface course matching main lane surface course
9+648 – 9+720
9+648 North Paving Limit
9+648 – 9+651 Construct a 3 m step joint at 9+648 and 9+651 for the full thickness of the new surface course.
Rehabilitation of existing Roadway
9+651 – 9+720 Remove existing asphalt full depth and full width. Reshape with Granular ‘A’ for profile and crossfall correction. Ensure Positive drainage.
9+720 – 9+820 Transition to new MPB alignment Rt.
Remove asphalt full depth and width, allowing for cross-fall and grade correction. Re-shape with Granular ‘A’. For widening, excavate existing Rt shoulder from inner edge of rounding to a depth of 750 mm and extend laterally to foreslope. Bench remainder of foreslope as per OPSD 208.010 (as necessary). Extend excavated ditch grade laterally to proposed toe of slope, ensuring that ditch drainage is directed away from the new embankment. Strip organics as per PGDR recommendations. Where required, excavate muskeg full depth as per OPSD 203.010. Provide a minimum granular structure of 750mm (150 mm of Granular ‘A’ and 600 mm Granular ‘B’ Type II). Ensure positive drainage for de=750 mm.
Michael Power Blvd Realignment Preliminary Pavement Structure Treatment Charts TBTE Ref. No.: 14-192-3 March 31, 2015
Page 2 of 4
Preliminary Pavement Structure Treatment Charts
Location Feature Recommended Treatment Comments/ Rationale
9+820 – 9+988 Proposed Shallow Fill/ Cut
Grub roadway footprint as per PGDR regardless of fill height. Where required, excavate muskeg full depth as per OPSD 203.010. Provide a minimum granular structure of de= 750 mm – 150 mm Granular ‘A’ and 650 mm Granular ‘B’ – Type II. Where fill heights exceed 750 mm, construct granular structure in accordance with Granular Thickness Table (Section 9.2.2.1 of PGDR). Where fill heights are less than 300 mm below profile grade, construct entirely of Granular ‘A’. Earth backslopes shall be graded no steeper than 3:1 and apply granular sheeting as per GPDR recommendations. Ensure positive drainage for de= 750 mm.
Borehole data indicates the subgrade soils outside the existing MPB consist of a deep pocket of organics ranging in depth from 1.4 to 1.7 m overlying firm to stiff silty clay. Lab data indicates the silty clay is moderately to highly susceptible to frost heaving and severely erodible.
9+988 – 10+010 New Highway 11 Intersection
Refer to the Preliminary PSTC for details regarding Highway 11.
Michael Power Blvd Realignment Preliminary Pavement Structure Treatment Charts TBTE Ref. No.: 14-192-3 March 31, 2015
Page 3 of 4
Preliminary Pavement Structure Treatment Charts
Location Feature Recommended Treatment Comments/ Rationale Basic Pavement Strategy for MPB South of new Highway 11:
- Pave main lanes, widening sections and paved shoulders with 50 mm SP 12.5 surface course
10+010 – 10+260 Proposed Shallow Fill/Cut
Grub roadway footprint as per PGDR regardless of fill height. Where required, excavate muskeg full depth as per OPSD 203.010. Provide a minimum granular structure of de= 750 mm – 150 mm Granular ‘A’ and 650 mm Granular ‘B’ – Type II. Where fill heights exceed 750 mm, construct granular structure in accordance with Granular Thickness Table (Section 9.2.2.1 of PGDR). Where fill heights are less than 300 mm below profile grade, construct entirely of Granular ‘A’. Grade earth backslopes no steeper than 3:1 and apply granular sheeting as per PGDR recommendations. Ensure positive drainage for de= 750 mm.
Borehole data indicates the subsurface conditions outside the existing MPB consist of a deep pocket of organics ranging in depth from 1.7 to 2.1 m overlying silty clay. The consistency of the silty clay ranges from Wet & Firm to Moist & Soft. Lab data indicates the silty clay is moderately to highly susceptible to frost heaving and severely erodible.
Michael Power Blvd Realignment Preliminary Pavement Structure Treatment Charts TBTE Ref. No.: 14-192-3 March 31, 2015
Page 4 of 4
Preliminary Pavement Structure Treatment Charts
Location Feature Recommended Treatment Comments/ Rationale
10+260 – 10+361 Transition new alignment to existing MPB Lt.
Remove existing asphalt full depth and full width. Reshape with Granular ‘A’ for profile and crossfall correction. For widening, excavate existing Rt shoulder from inner edge of rounding to a depth of 750 mm and extend laterally to foreslope. Bench remainder of foreslope as per OPSD 208.010. Extend excavated ditch grade laterally to proposed toe of slope, ensuring that ditch drainage is directed away from the new embankment. Where required, excavate muskeg full depth as per OPSD 203.010. Provide a minimum granular structure of 750 mm (150 mm of Granular ‘A’ and 600 mm Granular ‘B’ - Type II). Ensure positive drainage.
10+361 - 10+412
Rehabilitation of existing Roadway
10+361 – 10+409 Remove existing asphalt full depth and full width. Reshape with Granular ‘A’ for profile and crossfall correction. Ensure Positive drainage.
10+412 South Paving Limit
Construct a 3 m step joint at 10+409 – 10+412 for the full thickness of the new surface course.
APPENDIX 2 –
Borehole Logs
TBT Engineering Hwy. 11 Realignment
Premier Gold Mines Ltd. TBTE 14-192-3
Hwy. 11 Realignment – Twp. Errington
Page 1 of 6
HIGHWAY 11 REALIGNMENT
ERRINGTON TOWNSHIP
Station 9+540 13.7 Lt 14-HA-500
15UTM 5502778 N 501558 E
BR on Surf
Station 9+926 24.7 Lt 14-HA-501
15UTM 5502798 N 501642 E
0 - 100 Blk Org (Co Fib) with F-Co Sa &
Gr (Moist)
100 - 300 Br F-Co Sa with Gr (Moist & L)
300 - 1.0 Br F-Co Sa Tr Si (Moist & L)
1.0 NFP Prob Bld Poss BR
Station 9+710 16.9 Lt 14-HA-502
15UTM 5502800 N 501726 E
0 - 100 Blk Org (Co Fib) (Wet)
100 - 500 Br F-Co Sa with Gr (Wet & L)
500 - 1.0 Br F-Co Sa with Si (Wet & L)
1.0 - 1.7 Blk Org (Co Fib) (Wet)
1.7 - 2.0 Gry Si(y) F Sa (Wet & Comp)
2.0 EOH
Station 9+803 19.1 Lt 14-HA-503
15UTM 5502813 N 501818 E
0 - 500 Br F-Co Sa(y) Gr (Moist & Comp)
500 - 1.0 Br Gr with F-Co Sa Tr Si
(Moist & D)
1.0 NFP Sloughing
Station 9+960 36.0 Lt 14-HA-504
15UTM 5502848 N 501972 E
0 - 50 Blk Org (F Fib) (Moist)
50 - 500 Br F-Med Sa & Gr Tr Si
(Moist & Comp)
500 - 800 Br F-Co Sa Tr Gr & Si
(Moist & Comp)
800 NFP Sloughing
Station 9+960 36.0 Lt 14-HA-504
Sample No. 14-SM-100 (100 – 300)
% Passing 4.75 mm 53.9 %
% Passing 75 um 6.5 %
FMC @ 300 6.8 %
Group Symbol SP-SM
Station 9+975 37.2 Lt 14-HA-505
15UTM 5502851 N 501987 E
0 - 50 Blk Org (Co Fib) (Moist)
50 - 1.0 Br F Sa & Si (Moist & Comp)
1.0 - 1.5 Br F Sa with Si (Moist & Comp)
1.5 - 2.5 Br F Sa & Si (Moist & Comp)
2.5 EOH
Station 9+975 37.2 Lt 14-HA-505
Sample No. 14-SM-110 (100 – 300)
% Passing 4.75 mm 100.0 %
% Passing 75 um 50.8 %
% Passing 5 um 2.9 %
% Passing 2 um 2.0 %
FMC @ 300 10.5 %
Group Symbol ML
MSFH
'K' Factor = 0.39
Station 9+975 37.2 Lt 14-HA-505
Sample No. 14-SM-111 (1.0 – 1.4)
% Passing 4.75 mm 100.0 %
% Passing 75 um 14.8 %
FMC @ 1.4 3.8 %
Group Symbol SM
Station 10+004 40.9 Lt 14-HA-506
15UTM 5502858 N 502015 E
0 - 50 Blk Org (Co Fib) (Moist)
50 - 1.0 Br F Sa with Si (Moist & Comp)
1.0 - 1.5 Br F Sa with Si (Moist & Comp)
1.5 EOH
Station 10+039 43.7 Lt 14-HA-507
15UTM 5502865 N 502049 E
0 - 50 Blk Org (Co Fib) (Moist)
50 - 1.0 Br Si(y) F-Med Sa Tr Gr
(Moist & Comp)
1.0 - 1.5 Br F Sa with Si (Moist & Comp)
1.5 EOH
Station 10+039 43.7 Lt 14-HA-507
Sample No. 14-SM-112 (100 – 400)
% Passing 4.75 mm 93.3 %
% Passing 75 um 22.9 %
FMC @ 400 9.8 %
Group Symbol SM
TBT Engineering Hwy. 11 Realignment
Premier Gold Mines Ltd. TBTE 14-192-3
Hwy. 11 Realignment – Twp. Errington
Page 2 of 6
Station 10+065 44.2 Lt 14-HA-508
15UTM 5502869 N 502074 E
0 - 50 Blk Org (Co Fib) (Moist)
50 - 600 Br F Sa with Si (Moist & L)
600 - 1.5 Gry Si with F Sa (Moist & Comp)
1.5 EOH
Station 10+065 44.2 Lt 14-HA-508
Sample No. 14-SM-101 (100 – 400)
% Passing 4.75 mm 96.6 %
% Passing 75 um 16.4 %
FMC @ 400 7.9 %
Group Symbol SM
Station 10+210 44.9 Lt 14-HA-509
15UTM 5502901 N 502208 E
0 - 50 Blk Org (Co Fib) (Moist)
50 - 1.0 Br F Sa(y) Si (Moist & Comp)
1.0 - 1.2 Br F-Med Sa with Si
(Moist & Comp)
1.2 - 1.5 Br F Sa(y) Si (Wet & Comp)
1.5 EOH
Station 10+324 31.0 Lt 14-HA-510
15UTM 5502927 N 502315 E
BR on Surf
Station 10+409 15.7 Lt 14-HA-511
15UTM 5502951 N 502396 E
BR on Surf
Station 10+435 13.6 Lt 14-HA-512
15UTM 5502962 N 502419 E
0 - 1.5 Blk Org (Co Fib) (Wet)
1.5 NFP BR
Station 10+435 0.8 Rt 14-HA-513
15UTM 5502966 N 502418 E
0 - 1.5 Blk Org (Co Fib) (Wet)
1.5 NFP BR
Station 10+436 17.5 Lt 14-HA-514
15UTM 5502950 N 502427 E
0 - 700 Blk Org (Co Fib) (Wet)
700 NFP BR
Station 10+438 2.1 Lt 14-HA-515
15UTM 5502954 N 502428 E
0 - 1.8 Blk Org (Co Fib) (Wet)
1.8 - 2.6 Br F Sa & Si with Gr
(Wet & Comp)
2.6 NFP Sloughing
Station 10+438 2.1 Lt 14-HA-515
Sample No. 14-SM-109 (2.0 – 2.3)
% Passing 4.75 mm 88.7 %
% Passing 75 um 36.9 %
FMC @ 2.3 21.9 %
Group Symbol SM
Station 10+442 6.7 Lt 14-HA-516
15UTM 5502960 N 502429 E
0 - 50 Wat
50 - 2.2 Blk Org (F Fib) (Wet)
2.2 - 2.5 Gry Cl(y) Si (Wet & Stiff)
2.5 EOH
Station 10+448 3.0 Lt 14-HA-517
15UTM 5502960 N 502436 E
0 - 1.0 Blk Org (Co Fib) (Wet)
1.0 - 1.2 Blk Si(y) F-Med Sa (Wet & Comp)
1.2 - 1.4 Blk Si(y) F-Med Sa with Org
(Wet & Comp)
1.4 - 1.8 Blk Si(y) F-Med Sa (Wet & Comp)
1.8 NFP BR
Station 10+460 10.0 Lt 14-HA-518
15UTM 5502972 N 502442 E
BR on Surf
Station 10+545 3.1 Lt 14-HA-519
15UTM 5503015 N 502515 E
0 - 50 Blk Org (F Fib) (Moist)
50 - 500 Br Si(y) F Sa (Moist & Comp)
500 - 900 Br F-Co Sa with Gr Tr Si
(Moist & Comp) (Wet from 800)
900 NFP BR
Station 10+610 2.9 Rt 14-HA-520
15UTM 5503052 N 502569 E
BR on Surf
TBT Engineering Hwy. 11 Realignment
Premier Gold Mines Ltd. TBTE 14-192-3
Hwy. 11 Realignment – Twp. Errington
Page 3 of 6
Station 10+761 49.4 Rt 14-HA-521
15UTM 5503133 N 502656 E
BR on Surf
Station 10+844 15.4 Rt 14-HA-522
15UTM 5503221 N 502734 E
BR on Surf
Station 10+886 17.8 Rt 14-HA-523
15UTM 5503255 N 502759 E
BR on Surf
Station 10+965 19.2 Rt 14-HA-524
15UTM 5503325 N 502800 E
0 - 100 Blk Org (Co Fib) (Moist)
100 NFP BR
Station 11+034 16.4 Rt 14-HA-525
15UTM 5503389 N 502827 E
0 - 50 Blk Org (Co Fib) (Moist)
50 - 700 Br F-Med Sa with Si
(Moist & Comp)
700 - 900 Br F-Med Sa with Gr & Si
(Moist & D)
900 NFP BR
Station 11+141 14.6 Rt 14-HA-526
15UTM 5503488 N 502869 E
BR on Surf
Station 11+178 16.7 Rt 14-HA-527
15UTM 5503521 N 502886 E
0 - 800 Blk Org (Co Fib) (Wet)
800 - 1.3 Gry F-Med Sa(y) Si (Wet & L)
1.3 - 2.3 Gry F-Med Sa with Si (Moist & L)
2.3 NFP Sloughing
Station 11+272 6.7 Rt 14-HA-528
15UTM 5503611 N 502915 E
0 - 1.1 Blk Org (Co Fib) (Wet)
1.1 - 1.5 Gry Si & F-Med Sa (Wet & Comp)
1.5 EOH
Station 11+272 6.7 Rt 14-HA-528
Sample No. 14-SM-102 (1.2 – 1.5)
% Passing 4.75 mm 97.4 %
% Passing 75 um 51.0 %
% Passing 5 um 5.0 %
% Passing 2 um 3.3 %
FMC @ 1.5 27.1 %
Group Symbol ML
MSFH
'K' Factor = 0.35
Station 11+368 2.1 Rt 14-HA-529
15UTM 5503697 N 502956 E
0 - 1.6 Blk Org (Co Fib) (Wet)
1.6 - 2.1 Br Si(y) F-Co Sa Tr Gr
(Wet & Comp)
2.1 EOH
Station 11+368 8.8 Rt 14-HA-530
15UTM 5503700 N 502950 E
0 - 150 Blk Org (Co Fib) (Moist)
150 NFP BR
Station 11+457 6.6 Rt 14-HA-531
15UTM 5503776 N 502996 E
0 - 50 Blk Org (Co Fib) (Moist)
50 - 800 Br Gr(ly) Sa Tr Si (Moist & Comp)
800 NFP Sloughing
Station 11+556 6.5 Rt 14-HA-532
15UTM 5503856 N 503052 E
0 - 3.0 Blk Org (Co Fib) (Wet)
3.0 - 3.5 Gry Si(y) Cl (Moist & Firm)
3.5 EOH
Station 11+658 7.1 Rt 14-HA-533
15UTM 5503931 N 503121 E
0 - 700 Blk Org (Co Fib) (Wet)
700 - 1.2 Br Si(y) F-Co Sa Tr Gr
(Wet & Comp)
1.2 NFP Cob
TBT Engineering Hwy. 11 Realignment
Premier Gold Mines Ltd. TBTE 14-192-3
Hwy. 11 Realignment – Twp. Errington
Page 4 of 6
Station 11+751 0.5 Lt 14-HA-534
15UTM 5503997 N 503186 E
0 - 100 Blk Org (Co Fib) (Moist)
100 - 500 Br Si(y) F Sa (Moist & Comp)
500 - 1.5 Br Si(y) Cl (Moist & Firm)
1.5 EOH
Station 11+751 0.5 Lt 14-HA-534
Sample No. 14-SM-103 (700 – 1.0)
% Passing 4.75 mm 100.0 %
% Passing 75 um 97.4 %
% Passing 5 um 54.0 %
% Passing 2 um 22.0 %
FMC @ 1.0 24.3 %
WL 27 %
Wp 19 %
Ip 8
Group Symbol CL
MSFH
'K' Factor = 0.54
Station 11+881 3.2 Rt 14-HA-535
15UTM 5504064 N 503297 E
0 - 50 Blk Org (Co Fib) (Moist)
50 - 500 Br Si(y) F Sa (Moist & Comp)
500 - 1.5 Br Si(y) Cl (Moist & Firm)
1.5 EOH
Station 11+881 3.2 Rt 14-HA-535
Sample No. 14-SM-104 (1.0 – 1.3)
% Passing 4.75 mm 100.0 %
% Passing 75 um 94.9 %
% Passing 5 um 54.4 %
% Passing 2 um 25.0 %
FMC @ 1.3 24.6 %
WL 27 %
Wp 20 %
Ip 8
Group Symbol CL
MSFH
'K' Factor = 0.53
Station 12+024 3.0 Rt 14-HA-536
15UTM 5504120 N 503428 E
0 - 1.8 Blk Org (Co Fib) (Wet)
1.8 - 2.4 Gry Si(y) F Sa (Wet & Comp)
2.4 EOH
Station 12+100 7.9 Rt 14-HA-537
15UTM 5504139 N 503501 E
0 - 1.6 Blk Org (Co Fib) (Wet)
1.6 - 2.1 Gry Si(y) F Sa (Wet & Comp)
2.1 EOH
Station 12+163 19.7 Lt 14-HA-538
15UTM 5504185 N 503552 E
0 - 1.7 Blk Org (Co Fib) (Wet)
1.7 - 2.5 Gry Si(y) Cl (Wet & Firm)
2.5 EOH
Station 12+172 14.1 Rt 14-HA-539
15UTM 5504156 N 503572 E
0 - 1.7 Blk Org (Co Fib) (Wet)
1.7 - 2.3 Gry Si(y) Cl (Wet & Firm)
2.3 EOH
Station 12+172 14.1 Rt 14-HA-539
Sample No. 14-SM-105 (1.7 – 2.0)
% Passing 4.75 mm 99.0 %
% Passing 75 um 93.2 %
% Passing 5 um 37.0 %
% Passing 2 um 18.0 %
FMC @ 2.0 25.3 %
WL 26 %
Wp 18 %
Ip 8
Group Symbol CL
HSFH
'K' Factor = 0.57
Station 12+178 6.1 Lt 14-HA-540
15UTM 5504177 N 503571 E
0 - 1.8 Blk Org (Co Fib) (Wet)
1.8 - 2.3 Gry Si(y) Cl (Wet & Firm)
2.3 EOH
Station 12+206 25.2 Lt 14-HA-541
15UTM 5504204 N 503592 E
0 - 2.1 Blk Org (Co Fib) (Wet)
2.1 - 2.8 Gry Si(y) Cl (Moist & Soft)
2.8 EOH
TBT Engineering Hwy. 11 Realignment
Premier Gold Mines Ltd. TBTE 14-192-3
Hwy. 11 Realignment – Twp. Errington
Page 5 of 6
Station 12+211 4.6 Lt 14-HA-542
15UTM 5504186 N 503603 E
0 - 1.8 Blk Org (Co Fib) (Wet)
1.8 - 2.3 Gry Si(y) Cl (Moist & Stiff)
2.3 EOH
Station 12+218 19.7 Rt 14-HA-543
15UTM 5504165 N 503617 E
0 - 1.4 Blk Org (Co Fib) (Wet)
1.4 - 2.0 Gry Si(y) Cl (Moist & Stiff)
2.0 EOH
Station 12+257 3.1 Lt 14-HA-544
15UTM 5504199 N 503647 E
0 - 1.5 Blk Org (Co Fib) (Wet)
1.5 - 2.0 Gry Si(y) Cl with F-Med Sa
(Moist & Stiff)
2.0 EOH
Station 12+257 3.1 Lt 14-HA-544
Sample No. 14-SM-106 (1.5 – 1.8)
% Passing 4.75 mm 99.9 %
% Passing 75 um 83.7 %
% Passing 5 um 30.5 %
% Passing 2 um 16.5 %
FMC @ 1.8 19.5 %
WL 21 %
Wp 14 %
Ip 7
Group Symbol CL-ML
MSFH
'K' Factor = 0.57
Station 12+354 0.5 Rt 14-HA-545
15UTM 5504226 N 503740 E
0 - 500 Blk Org (Co Fib) (Moist)
500 - 1.5 Br Si(y) Cl with F-Med Sa
(Moist & Stiff)
(Very Stiff from 700)
1.5 EOH
Station 12+441 0.2 Lt 14-HA-546
15UTM 5504252 N 503823 E
0 - 1.0 Blk Org (Co Fib) (Moist)
1.0 - 1.5 Gry SP Si
(Moist & Very Stiff)
1.5 EOH
Station 12+441 0.2 Lt 14-HA-546
Sample No. 14-SM-107 (1.1 – 1.4)
% Passing 4.75 mm 100.0 %
% Passing 75 um 98.3 %
% Passing 5 um 24.6 %
% Passing 2 um 13.8 %
FMC @ 1.4 28.8 %
WL 26 %
Wp 23 %
Ip 3
Group Symbol ML
HSFH
'K' Factor = 0.63
Station 12+524 3.3 Rt 14-HA-547
15UTM 5504265 N 503905 E
0 - 800 Blk Org (Co Fib) (Wet)
800 - 1.5 Gry Si(y) Cl with F Sa
(Moist & Very Stiff)
1.5 EOH
Station 12+603 2.0 Lt 14-HA-548
15UTM 5504278 N 503983 E
0 - 1.0 Blk Org (Co Fib) (Wet)
1.0 - 1.5 Gry Si(y) Cl with F Sa
(Moist & Stiff)
1.5 EOH
Station 12+700 0.2 Lt 14-HA-549
15UTM 5504275 N 504080 E
0 - 1.3 Blk Org (F Fib) (Wet)
1.3 - 1.6 Gry Si(y) Cl (Moist & Firm)
1.6 - 2.0 Gry Si(y) Cl with F Sa
(Moist & Firm)
2.0 EOH
Station 12+799 0.5 Lt 14-HA-550
15UTM 5504262 N 504178 E
0 - 800 Gry F-Med Sa(y) Si (Wet & L)
800 - 1.7 Blk Org (F Fib) (Wet)
1.7 - 2.5 Gry Si(y) Cl (Wet & Firm)
2.5 EOH
TBT Engineering Hwy. 11 Realignment
Premier Gold Mines Ltd. TBTE 14-192-3
Hwy. 11 Realignment – Twp. Errington
Page 6 of 6
Station 12+799 0.5 Lt 14-HA-550
Sample No. 14-SM-108 (1.7 – 2.1)
% Passing 4.75 mm 100.0 %
% Passing 75 um 98.5 %
% Passing 5 um 31.0 %
% Passing 2 um 15.6 %
FMC @ 2.1 24.0 %
WL 23 %
Wp 16 %
Ip 7
Group Symbol CL-ML
HSFH
'K' Factor = 0.58
Station 12+838 1.0 Lt 14-HA-551
15UTM 5504254 N 504216 E
0 - 1.0 Gry F-Med Sa(y) Si (Wet & L)
1.0 - 2.0 Blk Org (Co Fib) (Wet)
2.0 - 3.0 Gry Si(y) Cl with F-Med Sa
(Wet & Firm)
3.0 EOH
12+177 ERRINGTON TOWNSHIP =
12+177 ASHMORE TOWNSHIP
TBT Engineering Hwy. 11 Realignment
Premier Gold Mines Ltd. TBTE 14-192-3
Hwy. 11 Realignment – Twp. Ashmore
Page 1 of 2
HIGHWAY 11 REALIGNMENT
ASHMORE TOWNSHIP
12+177 ERRINGTON TOWNSHIP =
12+177 ASHMORE TOWNSHIP
Station 12+178 6.1 Lt 14-HA-540
15UTM 5504177 N 503571 E
0 - 1.8 Blk Org (Co Fib) (Wet)
1.8 - 2.3 Gry Si(y) Cl (Wet & Firm)
2.3 EOH
Station 12+206 25.2 Lt 14-HA-541
15UTM 5504204 N 503592 E
0 - 2.1 Blk Org (Co Fib) (Wet)
2.1 - 2.8 Gry Si(y) Cl (Moist & Soft)
2.8 EOH
Station 12+211 4.6 Lt 14-HA-542
15UTM 5504186 N 503603 E
0 - 1.8 Blk Org (Co Fib) (Wet)
1.8 - 2.3 Gry Si(y) Cl (Moist & Stiff)
2.3 EOH
Station 12+218 19.7 Rt 14-HA-543
15UTM 5504165 N 503617 E
0 - 1.4 Blk Org (Co Fib) (Wet)
1.4 - 2.0 Gry Si(y) Cl (Moist & Stiff)
2.0 EOH
Station 12+257 3.1 Lt 14-HA-544
15UTM 5504199 N 503647 E
0 - 1.5 Blk Org (Co Fib) (Wet)
1.5 - 2.0 Gry Si(y) Cl with F-Med Sa
(Moist & Stiff)
2.0 EOH
Station 12+257 3.1 Lt 14-HA-544
Sample No. 14-SM-106 (1.5 – 1.8)
% Passing 4.75 mm 99.9 %
% Passing 75 um 83.7 %
% Passing 5 um 30.5 %
% Passing 2 um 16.5 %
FMC @ 1.8 19.5 %
WL 21 %
Wp 14 %
Ip 7
Group Symbol CL-ML
MSFH
'K' Factor = 0.57
Station 12+354 0.5 Rt 14-HA-545
15UTM 5504226 N 503740 E
0 - 500 Blk Org (Co Fib) (Moist)
500 - 1.5 Br Si(y) Cl with F-Med Sa
(Moist & Stiff)
(Very Stiff from 700)
1.5 EOH
Station 12+441 0.2 Lt 14-HA-546
15UTM 5504252 N 503823 E
0 - 1.0 Blk Org (Co Fib) (Moist)
1.0 - 1.5 Gry SP Si
(Moist & Very Stiff)
1.5 EOH
Station 12+441 0.2 Lt 14-HA-546
Sample No. 14-SM-107 (1.1 – 1.4)
% Passing 4.75 mm 100.0 %
% Passing 75 um 98.3 %
% Passing 5 um 24.6 %
% Passing 2 um 13.8 %
FMC @ 1.4 28.8 %
WL 26 %
Wp 23 %
Ip 3
Group Symbol ML
HSFH
'K' Factor = 0.63
TBT Engineering Hwy. 11 Realignment
Premier Gold Mines Ltd. TBTE 14-192-3
Hwy. 11 Realignment – Twp. Ashmore
Page 2 of 2
Station 12+524 3.3 Rt 14-HA-547
15UTM 5504265 N 503905 E
0 - 800 Blk Org (Co Fib) (Wet)
800 - 1.5 Gry Si(y) Cl with F Sa
(Moist & Very Stiff)
1.5 EOH
Station 12+603 2.0 Lt 14-HA-548
15UTM 5504278 N 503983 E
0 - 1.0 Blk Org (Co Fib) (Wet)
1.0 - 1.5 Gry Si(y) Cl with F Sa
(Moist & Stiff)
1.5 EOH
Station 12+700 0.2 Lt 14-HA-549
15UTM 5504275 N 504080 E
0 - 1.3 Blk Org (F Fib) (Wet)
1.3 - 1.6 Gry Si(y) Cl (Moist & Firm)
1.6 - 2.0 Gry Si(y) Cl with F Sa
(Moist & Firm)
2.0 EOH
Station 12+799 0.5 Lt 14-HA-550
15UTM 5504262 N 504178 E
0 - 800 Gry F-Med Sa(y) Si (Wet & L)
800 - 1.7 Blk Org (F Fib) (Wet)
1.7 - 2.5 Gry Si(y) Cl (Wet & Firm)
2.5 EOH
Station 12+799 0.5 Lt 14-HA-550
Sample No. 14-SM-108 (1.7 – 2.1)
% Passing 4.75 mm 100.0 %
% Passing 75 um 98.5 %
% Passing 5 um 31.0 %
% Passing 2 um 15.6 %
FMC @ 2.1 24.0 %
WL 23 %
Wp 16 %
Ip 7
Group Symbol CL-ML
HSFH
'K' Factor = 0.58
Station 12+838 1.0 Lt 14-HA-551
15UTM 5504254 N 504216 E
0 - 1.0 Gry F-Med Sa(y) Si (Wet & L)
1.0 - 2.0 Blk Org (Co Fib) (Wet)
2.0 - 3.0 Gry Si(y) Cl with F-Med Sa
(Wet & Firm)
3.0 EOH
APPENDIX 3 –
Laboratory Results
TBT Engineering Limited
LABORATORY 711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23001
Location: Hwy 11 Geraldton, ON Field No. 14-SM-100
Station: 9+960
Twp Errington Offset (m): 36.0 Lt
Reported To: Scott Peterson Depth: 100 mm - 300 mm
Sampled By/Date: Sam Molendijk/Nov. 4, 2014 Tested By/Date: F.Valela / November 12, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Size Percent Passing 75 mm 50 mm37.5 mm25.0 mm19.0 mm 100.016.0 mm 95.613.2 mm 88.9 9.5 mm 80.84.75 mm 53.92.00 mm 39.0.850 mm 32.1.425 mm 23.8.250 mm 16.9.106 mm 8.5.075 mm 6.5
Remarks: Test Method LS 602, 701, ASTM C136, D2216 Soil Classification - SP-SM
Natural Moisture Content:6.8% @ 300 mm depth
CCIL Certified
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10521-Rev.1112
TBT Engineering Limited
LABORATORY711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis of Soil By Hydrometer
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23011
Location: Hwy 11 Geraldton, ON Field No. 14-SM-110
Station: 9+975
Twp Errington Offset (m): 37.2 Lt
Reported To: Scott Peterson Depth: 100 mm - 300 mm
Sampled By/Date: Sam Molendijk/November 5, 2014 Tested By/Date: F.Valela G.Homac/Nov. 14, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Analysis Hydrometer Analysis
Sieve (mm) % Passing Diameter (mm) % Finer
50.0 100.0
37.5 100.0 23.9
25.0 100.0 15.6
19.0 100.0 10.0
13.2 100.0 5.6
9.5 100.0 3.9
4.75 100.0 3.3
2.00 100.0 2.2
0.850 100.0 1.7
0.425 99.9
0.250 99.1 2.9
0.106 68.5 2.0
0.075 50.8
%Gravel 0.0 % Silt 47.9 % NMC 10.5 MSFH NAGM
% Sand 49.2 % Clay 2.9 PI NP 0.39 ML
Remarks: Test Method LS 701, 702, ASTM D2216, D4318
5 µm
2 µm
CCIL & CSA Certified
Material Suitability
Soil Classification
Frost Heave Susc.
Erodibility (k)
0.009675
0.006859
0.003378
0.001411
0.047988
0.035550
0.023141
0.013656
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10501-Rev.0103
TBT Engineering Limited
LABORATORY 711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23012
Location: Hwy 11 Geraldton, ON Field No. 14-SM-111
Station: 9+975
Twp Errington Offset (m): 37.2 Lt
Reported To: Scott Peterson Depth: 1.0 m - 1.4 m
Sampled By/Date: Sam Molendijk/Nov. 7, 2014 Tested By/Date: F.Valela / November 12, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Size Percent Passing 75 mm 50 mm37.5 mm25.0 mm19.0 mm16.0 mm13.2 mm 9.5 mm4.75 mm 100.02.00 mm 100.0.850 mm 99.9.425 mm 99.0.250 mm 75.8.106 mm 24.1.075 mm 14.8
Remarks: Test Method LS 602, 701, ASTM C136, D2216 Soil Classification - SM
Natural Moisture Content:3.8% @ 1.4 m depth
CCIL Certified
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10521-Rev.1112
TBT Engineering Limited
LABORATORY 711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23013
Location: Hwy 11 Geraldton, ON Field No. 14-SM-112
Station: 10+039
Twp Errington Offset (m): 43.7 Lt
Reported To: Scott Peterson Depth: 100 mm - 400 mm
Sampled By/Date: Sam Molendijk/Nov. 7, 2014 Tested By/Date: F.Valela / November 12, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Size Percent Passing 75 mm 50 mm37.5 mm25.0 mm19.0 mm16.0 mm 100.013.2 mm 99.8 9.5 mm 97.74.75 mm 93.32.00 mm 88.2.850 mm 83.1.425 mm 66.3.250 mm 51.1.106 mm 28.2.075 mm 22.9
Remarks: Test Method LS 602, 701, ASTM C136, D2216 Soil Classification - SM
Natural Moisture Content:9.8% @ 400 mm depth
CCIL Certified
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10521-Rev.1112
TBT Engineering Limited
LABORATORY 711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23002
Location: Hwy 11 Geraldton, ON Field No. 14-SM-101
Station: 10+065
Twp Errington Offset (m): 44.2 Lt
Reported To: Scott Peterson Depth: 100 mm - 400 mm
Sampled By/Date: Sam Molendijk/Nov. 4, 2014 Tested By/Date: F.Valela / November 12, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Size Percent Passing 75 mm 50 mm37.5 mm25.0 mm19.0 mm16.0 mm13.2 mm 100.0 9.5 mm 99.24.75 mm 96.62.00 mm 92.7.850 mm 88.2.425 mm 82.2.250 mm 72.9.106 mm 32.2.075 mm 16.4
Remarks: Test Method LS 602, 701, ASTM C136, D2216 Soil Classification - SM
Natural Moisture Content:7.9% @ 400 mm depth
CCIL Certified
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10521-Rev.1112
TBT Engineering Limited
LABORATORY 711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23010
Location: Hwy 11 Geraldton, ON Field No. 14-SM-109
Station: 10+438
Twp Errington Offset (m): 2.1 Lt
Reported To: Scott Peterson Depth: 2.0 m - 2.3 m
Sampled By/Date: Sam Molendijk/Nov. 7, 2014 Tested By/Date: F.Valela / November 12, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Size Percent Passing 75 mm 50 mm37.5 mm25.0 mm19.0 mm 100.016.0 mm 98.513.2 mm 96.7 9.5 mm 94.14.75 mm 88.72.00 mm 83.9.850 mm 80.8.425 mm 75.5.250 mm 65.4.106 mm 45.5.075 mm 36.9
Remarks: Test Method LS 602, 701, ASTM C136, D2216 Soil Classification - SM
Natural Moisture Content:21.9% @ 2.3 m depth
CCIL Certified
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10521-Rev.1112
TBT Engineering Limited
LABORATORY711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis of Soil By Hydrometer
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23003
Location: Hwy 11 Geraldton, ON Field No. 14-SM-102
Station: 11+272
Twp Errington Offset (m): 6.7 Rt
Reported To: Scott Peterson Depth: 1.2 m - 1.5 m
Sampled By/Date: Sam Molendijk/November 4, 2014 Tested By/Date: F.Valela G.Homac/Nov. 14, 2014
Reported By: Premier Gold Mines Limited Reviewed By: Tim Fummerton
Sieve Analysis Hydrometer Analysis
Sieve (mm) % Passing Diameter (mm) % Finer
50.0 100.0
37.5 100.0 31.9
25.0 100.0 24.2
19.0 100.0 16.5
13.2 100.0 9.8
9.5 98.8 7.7
4.75 97.4 5.7
2.00 95.9 4.1
0.850 93.0 2.6
0.425 84.2
0.250 75.3 5.0
0.106 59.1 3.3
0.075 51.0
%Gravel 2.6 % Silt 46.0 % NMC 27.1 MSFH NAGM
% Sand 46.4 % Clay 5.0 PI NP 0.35 ML
Remarks: Test Method LS 701, 702, ASTM D2216, D4318
0.009515
0.006761
0.003339
0.001402
0.044856
0.033443
0.022188
0.013307
5 µm
2 µm
CCIL & CSA Certified
Material Suitability
Soil Classification
Frost Heave Susc.
Erodibility (k)
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10501-Rev.0103
TBT Engineering Limited
LABORATORY711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis of Soil By Hydrometer
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23004
Location: Hwy 11 Geraldton ON Field No. 14-SM-103
Station: 11+751
Twp Errington Offset (m): 0.5 Lt
Reported To: Scott Peterson Depth: 700 mm - 1.0 m
Sampled By/Date: Sam Molendijk/Nov. 4, 2014 Tested By/Date: F.Valela G.Homac/Nov. 14, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Analysis Hydrometer Analysis
Sieve (mm) % Passing Diameter (mm) % Finer
50.0 100.0
37.5 100.0 90.5
25.0 100.0 87.3
19.0 100.0 81.6
13.2 100.0 74.4
9.5 100.0 65.5
4.75 100.0 56.6
2.00 100.0 31.5
0.850 100.0 12.9
0.425 100.0
0.250 99.7 54.0
0.106 98.7 22.0
0.075 97.4
%Gravel 0.0 % Silt 43.4 % NMC 24.3 MSFH NAGM
% Sand 2.6 % Clay 54.0 PI 8 0.54 CL
Remarks: Test Method LS 701, 702, ASTM D2216, D4318
2 µm
CCIL & CSA Certified
Material Suitability
Soil Classification
Frost Heave Susc.
Erodibility (k)
5 µm
0.007267
0.005396
0.002971
0.001330
0.033550
0.024339
0.016052
0.009735
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10501-Rev.0103
TBT Engineering Limited
LABORATORY711 Harold Crescent
Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 Fax (807) 624-5163
E-Mail: [email protected]
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23004
Location: Errington Field No.: 14-SM-103
Station: 11+751
Twp Errington Offset: 0.5 Lt
Reported To: Scott Peterson Depth: 700 mm - 1.0 m
Sampled By/Date: Sam Molendijk/Nov. 4, 2014 Tested By/Date: G.Homac / Nov 11, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Liquid Limit Determination
Dish No.: K Z A Liquid Limit
Wet Soil + Dish: 38.072 37.693 39.613 25 Blows
Dry Soil + Dish: 34.423 34.086 35.673
Moisture: 3.649 3.607 3.94
Dish: 20.742 20.858 21.675
Dry Soil: 13.681 13.228 13.998
% Moisture: 26.67 27.27 28.15
No. of Blows: 29 25 19
Liquid Limits: 27 27 27 27
Liquid Limit, %: 27
Plastic Limit, %: 19
Plasticity Index: 8
Plastic Limit Determination Natural Moisture
Dish No.: 1 2
Wet Soil + Dish: 27.356 27.315 927.6
Dry Soil + Dish: 26.145 26.048 792.9
Moisture: 1.211 1.267 134.7
Dish: 19.902 19.491 237.6
Dry Soil: 6.243 6.557 555.3
% Moisture: 19.40 19.32 24.3
Average: 19
Test Method : ASTM: D4318, D2216
CCIL & CSA Certified
Atterberg Limits
22.00
23.00
24.00
25.00
26.00
27.00
28.00
29.00
30.00
31.00
32.00
10 100
Liquid Limit
TBT Engineering Limited
LABORATORY711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis of Soil By Hydrometer
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23005
Location: Hwy 11 Geraldton ON Field No. 14-SM-104
Station: 11+881
Twp Errington Offset (m): 3.2 Rt
Reported To: Scott Peterson Depth: 1.0 m - 1.3 m
Sampled By/Date: Sam Molendijk/Nov. 4, 2014 Tested By/Date: F.Valela G.Homac/Nov. 13, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Analysis Hydrometer Analysis
Sieve (mm) % Passing Diameter (mm) % Finer
50.0 100.0
37.5 100.0 91.9
25.0 100.0 89.1
19.0 100.0 84.3
13.2 100.0 77.7
9.5 100.0 69.2
4.75 100.0 58.7
2.00 100.0 36.0
0.850 99.8 15.2
0.425 98.8
0.250 97.9 54.4
0.106 96.0 25.0
0.075 94.9
%Gravel 0.0 % Silt 40.5 % NMC 24.6 MSFH NAGM
% Sand 5.1 % Clay 54.4 PI 8 0.53 CL
Remarks: Test Method LS 701, 702, ASTM D2216, D4318
5 µm
0.007527
0.005571
0.002978
0.001329
0.036665
0.026351
0.017104
0.010219
2 µm
CCIL & CSA Certified
Material Suitability
Soil Classification
Frost Heave Susc.
Erodibility (k)
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10501-Rev.0103
TBT Engineering Limited
LABORATORY711 Harold Crescent
Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 Fax (807) 624-5163
E-Mail: [email protected]
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23005
Location: Errington Field No.: 14-SM-104
Station: 11+881
Twp Errington Offset: 3.2 Rt
Reported To: Scott Peterson Depth: 1.0 m - 1.3 m
Sampled By/Date: Sam Molendijk/Nov. 4, 2014 Tested By/Date: G.Homac / Nov 11, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Liquid Limit Determination
Dish No.: Q G 18 Liquid Limit
Wet Soil + Dish: 33.856 36.718 36.863 25 Blows
Dry Soil + Dish: 31.044 33.155 33.297
Moisture: 2.812 3.563 3.566
Dish: 20.88 20.771 21.401
Dry Soil: 10.164 12.384 11.896
% Moisture: 27.67 28.77 29.98
No. of Blows: 30 20 15
Liquid Limits: 28 28 28 28
Liquid Limit, %: 28
Plastic Limit, %: 20
Plasticity Index: 8
Plastic Limit Determination Natural Moisture
Dish No.: 4 5
Wet Soil + Dish: 27.78 26.891 1150.4
Dry Soil + Dish: 26.538 25.607 970.9
Moisture: 1.242 1.284 179.5
Dish: 20.241 19.104 242.1
Dry Soil: 6.297 6.503 728.8
% Moisture: 19.72 19.74 24.6
Average: 20
Test Method : ASTM: D4318, D2216
Atterberg Limits
CCIL & CSA Certified
23.00
24.00
25.00
26.00
27.00
28.00
29.00
30.00
31.00
32.00
33.00
10 100
Liquid Limit
TBT Engineering Limited
LABORATORY711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis of Soil By Hydrometer
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23006
Location: Hwy 11 Geraldton ON Field No. 14-SM-105
Station: 12+172
Twp Errington Offset (m): 14.1 Rt
Reported To: Scott Peterson Depth: 1.7 m - 2.0 m
Sampled By/Date: Sam Molendijk/Nov. 4, 2014 Tested By/Date: F.Valela G.Homac/Nov. 13, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Analysis Hydrometer Analysis
Sieve (mm) % Passing Diameter (mm) % Finer
50.0 100.0
37.5 100.0 85.2
25.0 100.0 80.5
19.0 100.0 71.2
13.2 99.1 59.9
9.5 99.1 52.4
4.75 99.0 42.1
2.00 99.0 25.3
0.850 98.8 12.2
0.425 98.8
0.250 97.5 37.0
0.106 95.2 18.0
0.075 93.2
%Gravel 1.0 % Silt 56.2 % NMC 25.3 HSFH NAGM
% Sand 5.8 % Clay 37.0 PI 8 0.57 CL
Remarks: Test Method LS 701, 702, ASTM D2216, D4318
2 µm
CCIL & CSA Certified
Material Suitability
Soil Classification
Frost Heave Susc.
Erodibility (k)
5 µm
0.008070
0.005939
0.003087
0.001341
0.037892
0.027475
0.018209
0.011062
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10501-Rev.0103
TBT Engineering Limited
LABORATORY711 Harold Crescent
Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 Fax (807) 624-5163
E-Mail: [email protected]
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23006
Location: Hwy 11 Geraldton ON Field No.: 14-SM-105
Station: 12+172
Twp Errington Offset: 14.1 Rt
Reported To: Scott Peterson Depth: 1.7 m - 2.0 m
Sampled By/Date: Sam Molendijk/Nov. 4, 2014 Tested By/Date: G.Homac / Nov 11, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Liquid Limit Determination
Dish No.: 12 5 38 Liquid Limit
Wet Soil + Dish: 36.712 35.361 33.302 25 Blows
Dry Soil + Dish: 33.991 32.308 31.025
Moisture: 2.721 3.053 2.277
Dish: 22.625 20.758 22.788
Dry Soil: 11.366 11.55 8.237
% Moisture: 23.94 26.43 27.64
No. of Blows: 35 20 16
Liquid Limits: 25 26 26 26
Liquid Limit, %: 26
Plastic Limit, %: 18
Plasticity Index: 8
Plastic Limit Determination Natural Moisture
Dish No.: 6 7
Wet Soil + Dish: 27.399 27.388 1175.8
Dry Soil + Dish: 26.257 26.202 985.2
Moisture: 1.142 1.186 190.6
Dish: 19.998 19.722 230.4
Dry Soil: 6.259 6.48 754.8
% Moisture: 18.25 18.30 25.3
Average: 18
Test Method : ASTM: D4318, D2216
CCIL & CSA Certified
Atterberg Limits
21.00
22.00
23.00
24.00
25.00
26.00
27.00
28.00
29.00
30.00
31.00
10 100
Liquid Limit
TBT Engineering Limited
LABORATORY711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis of Soil By Hydrometer
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23007
Location: Hwy 11 Geraldton ON Field No. 14-SM-106
Station: 12+257
Twp Ashmore Offset (m): 3.1 Lt
Reported To: Scott Peterson Depth: 1.5 m - 1.8 m
Sampled By/Date: Sam Molendijk/Nov. 5, 2014 Tested By/Date: F.Valela G.Homac/Nov. 13, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Analysis Hydrometer Analysis
Sieve (mm) % Passing Diameter (mm) % Finer
50.0 100.0
37.5 100.0 69.4
25.0 100.0 63.0
19.0 100.0 55.1
13.2 100.0 46.3
9.5 100.0 39.9
4.75 99.9 33.5
2.00 98.9 22.3
0.850 96.8 11.2
0.425 93.8
0.250 91.8 30.5
0.106 86.9 16.5
0.075 83.7
%Gravel 0.1 % Silt 53.2 % NMC 19.5 MSFH NAGM
% Sand 16.2 % Clay 30.5 PI 7 0.57 CL-ML
Remarks: Test Method LS 701, 702, ASTM D2216, D4318
2 µm
CCIL & CSA Certified
Material Suitability
Soil Classification
Frost Heave Susc.
Erodibility (k)
5 µm
0.008248
0.005999
0.003077
0.001337
0.038640
0.028385
0.018759
0.011320
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10501-Rev.0103
TBT Engineering Limited
LABORATORY711 Harold Crescent
Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 Fax (807) 624-5163
E-Mail: [email protected]
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23007
Location: Hwy 11 Geraldton ON Field No.: 14-SM-106
Station: 12+257
Twp Ashmore Offset: 3.1 Lt
Reported To: Scott Peterson Depth: 1.5 m - 1.8 m
Sampled By/Date: Sam Molendijk/Nov. 5, 2014 Tested By/Date: G.Homac / Nov 11, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Liquid Limit Determination
Dish No.: 32 21 5 Liquid Limit
Wet Soil + Dish: 38.688 35.946 35.942 25 Blows
Dry Soil + Dish: 35.954 33.587 33.572
Moisture: 2.734 2.359 2.37
Dish: 22.393 22.522 22.783
Dry Soil: 13.561 11.065 10.789
% Moisture: 20.16 21.32 21.97
No. of Blows: 29 21 17
Liquid Limits: 21 21 21 21
Liquid Limit, %: 21
Plastic Limit, %: 14
Plasticity Index: 7
Plastic Limit Determination Natural Moisture
Dish No.: 8 9
Wet Soil + Dish: 27.882 27.657 1030.6
Dry Soil + Dish: 26.891 26.647 902.3
Moisture: 0.991 1.01 128.3
Dish: 20.044 19.667 243.8
Dry Soil: 6.847 6.98 658.5
% Moisture: 14.47 14.47 19.5
Average: 14
Test Method : ASTM: D4318, D2216
CCIL & CSA Certified
Atterberg Limits
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
25.00
26.00
10 100
Liquid Limit
TBT Engineering Limited
LABORATORY711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis of Soil By Hydrometer
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23008
Location: Hwy 11 Geraldton ON Field No. 14-SM-107
Station: 12+441
Twp Ashmore Offset (m): 0.2 Lt
Reported To: Scott Peterson Depth: 1.1 m - 1.4 m
Sampled By/Date: Sam Molendijk/Nov. 5, 2014 Tested By/Date: F.Valela G.Homac/Nov. 13, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Analysis Hydrometer Analysis
Sieve (mm) % Passing Diameter (mm) % Finer
50.0 100.0
37.5 100.0 84.7
25.0 100.0 77.1
19.0 100.0 66.6
13.2 100.0 50.4
9.5 100.0 39.0
4.75 100.0 29.5
2.00 100.0 17.1
0.850 100.0 10.5
0.425 99.8
0.250 99.4 24.6
0.106 99.0 13.8
0.075 98.3
%Gravel % Silt 73.7 % NMC 28.8 HSFH NAGM
% Sand 1.7 % Clay 24.6 PI 3 0.63 ML
Remarks: Test Method LS 701, 702, ASTM D2216, D4318
5 µm
0.008532
0.006234
0.003178
0.001351
0.038386
0.028205
0.018733
0.011565
2 µm
CCIL & CSA Certified
Material Suitability
Soil Classification
Frost Heave Susc.
Erodibility (k)
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10501-Rev.0103
TBT Engineering Limited
LABORATORY711 Harold Crescent
Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 Fax (807) 624-5163
E-Mail: [email protected]
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23008
Location: Hwy 11 Geraldton ON Field No.: 14-SM-107
Station: 12+441
Twp Ashmore Offset: 0.2 Lt
Reported To: Scott Peterson Depth: 1.1 m - 1.4 m
Sampled By/Date: Sam Molendijk/Nov. 5, 2014 Tested By/Date: G.Homac / Nov 11, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Liquid Limit Determination
Dish No.: K Z H Liquid Limit
Wet Soil + Dish: 35.691 33.812 34.676 25 Blows
Dry Soil + Dish: 32.64 31.095 31.864
Moisture: 3.051 2.717 2.812
Dish: 20.759 20.888 21.685
Dry Soil: 11.881 10.207 10.179
% Moisture: 25.68 26.62 27.63
No. of Blows: 32 23 17
Liquid Limits: 26 26 26 26
Liquid Limit, %: 26
Plastic Limit, %: 23
Plasticity Index: 3
Plastic Limit Determination Natural Moisture
Dish No.: 1 2
Wet Soil + Dish: 27.59 27.369 916.1
Dry Soil + Dish: 26.164 25.911 768.5
Moisture: 1.426 1.458 147.6
Dish: 19.902 19.492 255.6
Dry Soil: 6.262 6.419 512.9
% Moisture: 22.77 22.71 28.8
Average: 23
Test Method : ASTM: D4318, D2216
Atterberg Limits
CCIL & CSA Certified
21.00
22.00
23.00
24.00
25.00
26.00
27.00
28.00
29.00
30.00
31.00
10 100
Liquid Limit
TBT Engineering Limited
LABORATORY711 Harold Cres.,Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 FAX: (807) 624-5163
E-Mail: [email protected]
Grain Size Analysis of Soil By Hydrometer
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23009
Location: Hwy 11 Geraldton ON Field No. 14-SM-108
Station: 12+799
Twp Ashmore Offset (m): 0.5 Lt
Reported To: Scott Peterson Depth: 1.7 m - 2.1 m
Sampled By/Date: Sam Molendijk/Nov. 5, 2014 Tested By/Date: F.Valela G.Homac/Nov. 13, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Sieve Analysis Hydrometer Analysis
Sieve (mm) % Passing Diameter (mm) % Finer
50.0 100.0
37.5 100.0 87.4
25.0 100.0 81.8
19.0 100.0 71.6
13.2 100.0 55.8
9.5 100.0 45.5
4.75 100.0 35.3
2.00 100.0 21.4
0.850 99.8 11.2
0.425 99.4
0.250 99.1 31.0
0.106 98.7 15.6
0.075 98.5
%Gravel 0.0 % Silt 67.5 % NMC 24.0 HSFH NAGM
% Sand 1.5 % Clay 31.0 PI 7 0.58 CL-ML
Remarks: Test Method LS 701, 702, ASTM D2216, D4318
2 µm
CCIL & CSA Certified
Material Suitability
Soil Classification
Frost Heave Susc.
Erodibility (k)
5 µm
0.008276
0.006079
0.003124
0.001344
0.037266
0.027180
0.018113
0.011231
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100 1000
%
P
a
s
s
i
n
g
Grain Size Analysis
Material GradationSieve Size
R10501-Rev.0103
TBT Engineering Limited
LABORATORY711 Harold Crescent
Thunder Bay, ON P7C 5H8
PH: (807) 624-5162 Fax (807) 624-5163
E-Mail: [email protected]
Client: Premier Gold Mines Limited TBTE Project No.: 14-192
Project: Hwy 11 Realignment Lab No.: 23009
Location: Hwy 11 Geraldton ON Field No.: 14-SM-108
Station: 12+799
Twp Ashmore Offset: 0.5 Lt
Reported To: Scott Peterson Depth: 1.7 m - 2.1 m
Sampled By/Date: Sam Molendijk/Nov. 5, 2014 Tested By/Date: G.Homac / Nov 11, 2014
Reported By: Forch Valela Reviewed By: Tim Fummerton
Liquid Limit Determination
Dish No.: Q G 18 Liquid Limit
Wet Soil + Dish: 36.993 35.413 33.246 25 Blows
Dry Soil + Dish: 34.075 32.727 30.993
Moisture: 2.918 2.686 2.253
Dish: 20.759 20.888 21.685
Dry Soil: 13.316 11.839 9.308
% Moisture: 21.91 22.69 24.20
No. of Blows: 27 22 17
Liquid Limits: 22 22 23 23
Liquid Limit, %: 23
Plastic Limit, %: 16
Plasticity Index: 7
Plastic Limit Determination Natural Moisture
Dish No.: 10 11
Wet Soil + Dish: 27.832 28.281 1100.2
Dry Soil + Dish: 26.731 27.163 931.5
Moisture: 1.101 1.118 168.7
Dish: 19.977 20.331 227.9
Dry Soil: 6.754 6.832 703.6
% Moisture: 16.30 16.36 24.0
Average: 16
Test Method : ASTM: D4318, D2216
CCIL & CSA Certified
Atterberg Limits
18.00
19.00
20.00
21.00
22.00
23.00
24.00
25.00
26.00
27.00
28.00
10 100
Liquid Limit
APPENDIX 4 –
MTO Geotechnical Abbreviations
Premier Gold – Hardrock Project TBTE Ref. No.: 14-192 Highway 11 Realignment
APPENDIX E
Preliminary Foundations Report
Preliminary Foundation Investigation and Design Report
Highway 11 Relocation MacLeod High Tailings Geraldton, Ontario
SUBMITTED TO:
Premier Gold Mines Hardrock Inc. 1100 Russel Street, Suite 200 Thunder Bay, ON P7B 5N2
SUBMITTED BY: TBT ENGINEERING LIMITED 1918 Yonge Street Thunder Bay, On P7E 6T9 CONTACT PERSON: Gordon Maki, P.Eng. Steven Seller, P.Eng Phone: (807) 624-5160 SUBMISSION DATE: March 30, 2015 REFERENCE NO.: 14-192-2
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page i
Table of Contents
PART A - FOUNDATION INVESTIGATION REPORT Draft Preliminary Foundation Investigation and Design Report................................................. 1 Highway 11 Relocation ............................................................................................................ 1 1 Introduction ....................................................................................................................... 1 2 Site Description ................................................................................................................. 2 3 Surficial Geology ............................................................................................................... 3 4 Investigation Procedures ................................................................................................... 3 5 Laboratory Testing ............................................................................................................ 4 6 Sub-Surface Conditions .................................................................................................... 4
6.1 Topsoil ....................................................................................................................... 4 6.2 Fill .............................................................................................................................. 4 6.3 Organic Material ......................................................................................................... 5 6.4 Silt .............................................................................................................................. 5 6.5 Tailings ...................................................................................................................... 6 6.6 Till .............................................................................................................................. 7 6.7 Ground Water ............................................................................................................ 7 6.8 Refusal ...................................................................................................................... 8
7 Miscellaneous ................................................................................................................... 8 PART B - FOUNDATION DESIGN RECOMMENDATIONS 8 Introduction ..................................................................................................................... 10 9 Roadway Embankment Analyses .................................................................................... 11 9.1 Geotechnical Model ........................................................................................................ 11
9.2 Roadway Embankment Stability ............................................................................... 11 10 Settlement Performance.................................................................................................. 15
10.1 Roadway Embankment on Top of MHT.................................................................... 16 10.2 Roadway Embankment Constructed Adjacent to the Perimeter of the MHT ............. 17 10.3 Embankments Constructed Off of MHT .................................................................... 18
11 Scope of Detailed Investigation and Future Considerations ............................................ 18 12 Limitations ....................................................................................................................... 21 13 Closure ........................................................................................................................... 22
APPENDICIES
Appendix A, Borehole Logs Appendix B, Laboratory Test Data Appendix C, Borehole Locations, and Soil Strata Drawing Appendix D, Stability Models
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 1
Part A - FOUNDATION INVESTIGATION REPORT 1 Introduction
TBT Engineering Limited (TBTE) has been retained by Premier Gold (PG) to provide a
preliminary foundation investigation and design report for the proposed realignment of Highway
11 as it crosses over the MacLeod High Tailings (MHT). The MHT is located south of
Geraldton, Ontario near the intersection of Highway 11 and 584. The preliminary foundation
investigations were conducted along the proposed new highway alignment with particular
attention to areas where the alignment crosses the tailings pile. The proposed alignment
crosses the perimeter of the tailings pile at four locations at the approximate Stations of
13+015, 13+340, 13+575, and 14+035.
This investigation consisted of twelve boreholes drilled along the proposed alignment. Six
boreholes were drilled off the MHT (at approaches to the raised pile), four boreholes were
advanced near the crests of the MHT perimeter and the remaining two were advanced at mid
points between the perimeter crossings on the MHT. The boreholes are labeled from BH 500 to
BH 511.
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 2
2 Site Description
The preliminary foundation investigations were completed to investigate subsurface conditions
for the four MHT perimeter crossings, located at stations 13+015, 13+340, 13+575, and
14+035, and provide some data for areas between the crossings.
The MHT consists of a large tailings deposit placed over natural terrain, dating back to the
1930’s. The perimeter of the deposit consists of shaped tailings with varying side slopes and
configurations. Typically in the areas of this investigation the side slopes are roughly 2.5
horizontal to 1 vertical. Some sections of the MHT perimeter have a toe berm/drain while other
sections do not. A tailings beach is also evident along much of the toe of the MHT perimeter.
The height of the perimeter typically varies from 6 to 8 m. Reshaping of the perimeter, plus the
construction of the toe berms (where applicable) was completed circa 2000
It is understood that the original terrain consisted of a low lying swamp which is still evident at
some locations beyond the perimeter of the MHT.
Photo 2.1 – Looking North Easterly Towards Station 13+015
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 3
3 Surficial Geology
Available surficial geology mapping (OGS NOEGTS Map 5078 – Longlac) indicates the site is
located in a terrain unit comprised of a peat veneer (organic terrain) over a sand (outwash
plain); the area may also include a till (ground moraine) beneath the sand. The surrounding
terrain is a low local relief plain.
4 Investigation Procedures
A geotechnical site investigation was undertaken from December 16, 2014 to February 4, 2015.
The borehole locations are illustrated on the Borehole Location and Soil Strata Drawing found in
Appendix D.
The borehole locations were identified in the field by TBTE personnel and service clearances
were completed prior to mobilizing the drill rig to site. Numerous drill set ups were used to
complete the boreholes and associated Standard Penetration Testing (SPT), as indicated
below:
Table 4.1: Boreholes and Associated Drill Equipment
Drill Equipment
SPT Delivery Mechanism (Efficiency)
Borehole
CME 55 Automatic Hammer (0.73) 500, 501, 502, 505, 506, 507, 509, 511
CME 750 Automatic Hammer (0.67) 503, 504, 508
Tripod Safety Hammer (0.6)* 510
*Based on published data.
SPT “N” values reported on the borehole logs and referenced in Section 6 (Sub-Surface
Conditions) are uncorrected field values.
Drilling methods applied to all boreholes consisted of keeping the hollow stem augers or casing
filled with water (to ground level) to reduce the possibility of the soils being “blown up” within the
boreholes. Soil samples were obtained from the auger flights and using a split spoon sampler
as a part of the Standard Penetration Testing . Refusal material was sampled not sampled.
Borehole locations were surveyed by TBTE and were based on North American Datum 1983,
UTM CSRS CBNV6-2010 Zone 16. Control was established from existing published Horizontal
Control Monuments and a Geodetic Benchmark using the Canadian Geodetic Vertical Datum
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 4
1928. The following horizontal control points and vertical control points were utilized throughout
this project:
HCM 00119753139, HCM 0011984U045
VCM 0011984U045 VCM 00819728155
5 Laboratory Testing
Samples which were obtained during the field investigation were subjected to laboratory testing
consisting of moisture content, grain size analysis (mechanical sieves and hydrometers),
consolidation testing and drained direct shear testing. The results of this testing are shown on
the Borehole Logs (Appendix A) and on the laboratory data reports (Appendix B).
6 Sub-Surface Conditions
Details of the subsurface conditions are provided on the borehole (Appendix A), laboratory
reports (Appendix B) and on the Soil Strata Drawing (Appendix C).
The subsurface soils along the alignment on top of the MHT typically consist of fill/topsoil at
surface underlain by tailings. The tailings are underlain by organic material followed by silt.
The silt is underlain by a till with occasional cobbles before auger and/or SPT refusal.
The subsurface soils around the perimeter of the MHT typically consists of organic material or
tailings at surface, followed by silt which is underlain by a till with occasional cobbles before
auger and/or SPT refusal.
6.1 Topsoil
Topsoil was encountered within the MHT at the ground surface of Boreholes 503, 504, and 508.
The topsoil’s thickness varied from 1.4 to 1.8 m.
6.2 Fill
Fill was encountered at ground surface at boreholes both outside and within the MHT.
Within the MHT (BH 503, 505 and 507) fill was encountered at elevation 336.1, 338.5 and 336.8
and extended to elevations 335.3, 333.0 and 335.5 m, respectively. The fill ranges from sandy
gravel with silt with trace sand to silt with trace sand. The test results indicate a grain size
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 5
distribution of 0 to 53 % gravel, 1 to 27 % sand, and 18 to 99 % silt/clay sized particles. The
presence of cobbles was noted within the fill at Borehole 505. The fill is very loose to dense as
indicated by “N” values ranging from 3 to 34 blows/0.3 m.
Outside of the MHT (BH 510 and 511) fill was encountered at elevation 331.1 and 332.6 and
extended to elevations 330.4 at both locations. Based on a single grain size analysis this fill
consists of sandy silt. The test results indicate a grain size distribution of 0 % gravel, 29 %
sand, and 72 % silt/clay sized particles. The fill is very loose to compact as indicated by “N”
values ranging from 2 to 13 blows/0.3 m.
6.3 Organic Material
Organic matter was encountered at all boreholes with the exception of Boreholes 508, 509, and
511. The organic material varies from being on surface to be being below topsoil or tailings.
For boreholes located outside of the MHT organic material was encountered at ground surface
at Boreholes 500 and 501, beneath tailings at Boreholes 502 and 506, and beneath fill at
Borehole 510. The material was encountered at elevations ranging 328.8 to 330.6 and varied in
thickness from 0.8 to 2.1 m with natural moisture contents ranging from 119 to 685 %.
A consolidation test was conducted on a disturbed sample of the organic material from
Borehole 505 at a depth of 10.5 m. The results of this consolidation test indicate a drained
constrained modulus in the range of 0.1 to 0.9 MPa within the normal effective stress range of
the test (5 to 150 kPa). The coefficient of consolidation, Cv, varied from 9.5 to 2.5 mm2/min.
The organic material within the MHT was encountered beneath tailings at Boreholes 503, 504,
505 and 507 at elevations ranging from 328.3 to 330.0 and varied in thickness from 0.3 to 1.4
m, with natural moisture contents ranging from 119 to 325 %.
6.4 Silt
Native silt was present at all the borehole locations with the exception of Boreholes 508, 510
and 511. The native silt was encountered beneath the organics at all the boreholes with the
exception of Borehole 509, where it was encountered directly beneath the tailings. The silt was
encountered at elevations ranging between 327.0 to 330.6 m.
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 6
Within the MHT (BH 503, 504, 505, 507 and 509) the native silt was encountered at elevations
327.0 to 330.6 m and varied in thickness from 2.4 to 5.2 m, with Borehole 505 terminating within
the silt. Based on four grain size analysis the material consists of silt with trace sand as
indicate by a grain size distribution of 0 % gravel, 3 to 8 % sand, and 92 to 97 % silt/clay sized
particles. The silt is loose to dense as indicated by “N” values ranging from 4 to 31 blows/0.3
m.
Outside of the MHT (BH 500, 501, 502 and 506) the native silt was encountered at elevation
327.6 and 329.6 and varied in thickness from 3.3 to 3.9 m, with Borehole 506 terminating within
the silt. Based on a three grain size analysis the material consists of gravelly sandy silt to silt
with trace sand. The test results indicate a grain size distribution of 0 to 30 % gravel, 3 to 24 %
sand, and 47 to 97 % silt/clay sized particles. The presence of cobbles was noted within the fill
at Borehole 500, 502 and 506. The silt is typically very loose to compact as indicated by “N”
values ranging from 3 to 29 blows/0.3 m. The silt was very dense at a depth of 9.1 m in
Borehole 506 with an “N” value of 42 blows/0.3 m
6.5 Tailings
Tailings was present at all the borehole locations with the exception of Boreholes 500, 501, 510
and 511.
Within the MHT tailings were encountered at surface (BH 509), beneath topsoil (BH 504 and
508) and beneath fill (BH 503, 505, and 507) at elevations 333.0 to 336.3 m and varied in
thickness from 3.7 to 7.9 m. Based on fourteen grain size analysis the material consists of
gravelly sandy silt, silt and sand with trace gravel to silt. The grain size analysis typically
indicates a grain size distribution of 0 to 4 % gravel, 0 to 38 % sand, and 58 to 99 % silt/clay
sized particles. A single sample from Borehole 508 has a grain size distribution of 32 % gravel,
22 % sand, and 45 % silt/clay sized particles at a depth of 4.4 m. The tailings is typically very
loose, with a few instances of it being compact as indicated by “N” values ranging from 1 to 25
blows/0.3 m.
A consolidation test was conducted on a disturbed sample of the tailings material from Borehole
504 at a depth of 3.0 m. This sample consists of 5% sand and 95% silt and clay sized particles.
The results of this consolidation test indicate a drained constrained modulus in the range of 6 to
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 7
17 MPa within the normal effective stress range of the test (15 to 200 kPa). The coefficient of
consolidation, Cv, varied from 47 to 157 mm2/min.
Consolidated drained direct shear testing was conducted on a sample from Borehole 504 at a
depth of 3.0 m to estimate the effective stress strength parameters of the tailings. The lower
bound of the shear strength points developed at low horizontal shear strain level of 2% is
represented by effective stress strength parameters of c’ = 0 kPa and ϕ’ = 31°.
Outside of the MHT (BH 502 and 506) the tailings was encountered at ground surface at
elevation 331.7 and varied in thickness from 1.2 to 3.0 m. Based on a two grain size analysis
the material consists of sandy silt to silt with trace sand. The test results indicate a grain size
distribution of 0 % gravel, 5 to 32 % sand, and 68 to 95 % silt/clay sized particles. The tailings
is very loose to loose as indicated by “N” values ranging from 2 to 7 blows/0.3 m.
6.6 Till
Till consisting of a heterogeneous mixture of gravel, sand, silt and cobbles is encountered
beneath the silt at Boreholes 500 to 504, 507, and 509, beneath the tailings at Borehole 508,
beneath organic material at Borehole 510 and beneath fill at Borehole 511. Till was not
encountered at Boreholes 505 and 506. The till was encountered at elevations ranging from
323.9 to 330.9 m. It should be noted that all boreholes where till was encountered, terminated
within the till. The till can range from sand with trace gravel and trace silt to sandy silty gravel.
Grain size analysis conducted on seven samples of the indicate the layer consist of 4 to 49 %
gravel , 25 to 92 % sand and 4 to 29 % silt/clay size particles. Occasional cobbles were noted
within several boreholes. The till is compact to dense as indicated by an “N” values ranging
from 10 to 46 blows/0.3m.
6.7 Ground Water
The ground water levels are based on the pre-existing well data collected from 1996, 2012,
2013 and 2014. The wells reviewed are situated in close proximity to the proposed highway
right of way. The wells reviewed are provided in the following table with a summation of their
data from 1996, 2012, 2013, and 2014 data for all years may not have been present for all
wells.
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 8
Table 6.1: Ground Water Level (elevations m)
Well ID Average Level Max. Level Min. Level
96-03 331.4 332.7 330.5
96-04 330.0 337.6 324.8
96-09A1 335.4 338.3 333.3
96-09A4 335.3 338.3 333.1
96-12A 330.3 331.4 329.6
6.8 Refusal
Auger refusal and “N” values of 100+ blows/0.3 m was encountered at all borehole with the
exception of Borehole 505 which extend to a maximum depth of 15 m. The following table
indicates the recorded refusal depths at each borehole. Refusals may be on cobbles, boulders,
or bedrock. Refusal material was not sampled.
Table 6-2: Borehole Refusal Site 3
Test hole Number
Refusal Depth (m)
Refusal Elevation (m)
500 7.8 322.8
501 8.6 322.5
502 6.3 325.4
503 12.6 324.9
504 14.6 323.0
506 10.0 321.7
507 13.7 323.1
508 9.0 327.4
509 13.5 322.8
510 3.2 327.9
511 5.9 326.7
7 Miscellaneous
Laboratory testing was carried out at the TBT Engineering Limited laboratory in Thunder Bay.
The drill equipment for this investigation was operated by TBT Engineering. The field operations
were supervised by Alan Finke. Laboratory testing was supervised by T. Fummerton C.E.T.
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 9
This report was prepared by Steven Seller, P.Eng and Gordon Maki, P.Eng., and reviewed by
W. Hurley, P.Eng (TBTE designated principal contact identified for MTO Foundation
Engineering projects).
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 10
Part B - FOUNDATION DESIGN RECOMMENDATIONS
8 Introduction
TBT Engineering Limited (TBTE) has been retained by Premier Gold (PG) to provide
preliminary foundation investigation and design services for the proposed Highway 11
relocation over the MacLeod High Tailings. The preliminary foundation investigations were
conducted along the proposed new highway alignment particularly attention was paid to the
areas where the alignment crossed the tailings pile perimeter, with some investigation along the
tailings pile. The proposed alignment crosses the perimeter of the tailings pile at four locations
at the approximate Stations of 13+015, 13+340, 13+575, and 14+035.
The preliminary foundation investigations as described in Part A, was completed to investigate
subsurface conditions at these sites. These investigations consisted of twelve boreholes drilled
near the proposed centerline, laboratory testing and geotechnical analysis of the data. The Part
A report describes the subsurface conditions encountered during the investigation. The test
holes are labeled from Borehole 500 to 511.
The foundation soils at these sites typically consist of organics, tailings, topsoil, or fill at surface
which overlie silt, with till to termination. Cobbles are present within the native soils at
numerous locations. All boreholes extended to practical refusal (100+ “N” values as
determined from the Standard Penetration Test), or extend to a maximum depth of 15 m.
The purpose of this section of the report (Part B) is to provide preliminary embankment design
recommendations for various embankment configurations. These are based on the conditions
encountered at the test hole locations, TBTE’s interpretation of the subsurface conditions at the
site and analyses of embankment stability.
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 11
9 Roadway Embankment Analyses 9.1 Geotechnical Model
Stability modeling was completed using Slope/W software and limit equilibrium analysis using
the Morgenstern-Price method.
The preliminary soil properties established for the embankment and foundation soils are
presented below. The preliminary strength properties of the native soils have been based on
published correlations with index tests. The preliminary strength properties of the tailings has
been determined through direct shear testing, and index tests. Typical preliminary strength
properties have been selected for the various potential fill materials.
Table 9-1: Assumed Soil Properties for Stability Analyses
Soil
Effective Stress Strength Properties
Unit Weight γ
(kN/m3)
Effective Angle of Internal Friction,
φ’ (degrees)
Effective Cohesion
Intercept, C’ (kPa)
Rock Fill 45 0 18
Compacted Granular Fill 35 0 20
Filter Material 35 0 18
Tailings 31 0 20
Organic material 28 0 11-12
Native Silts 32 0 20
Till 35 0 20
A tailings beach overlying organic material exists along the toe of the MHT perimeter. The
thickness and extent of the tailings beach is likely variable. While the added weight of the
tailings beach can significantly improve stability of the perimeter, for this assessment its
potential presence was conservatively ignored. This would also cover a scenario where some
or all of the tailings beach material is either eroded or removed in the future.
9.2 Roadway Embankment Stability
Stability analyses have been completed to investigate stability of the proposed roadway
embankment crossing the MHT. For this preliminary assessment stability analyses was
completed for embankment sections off the MHT, adjacent to the MHT perimeter, and for the
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 12
embankment constructed on the MHT independent of the MHT perimeter. The following factors
of safety (FoS) were applied as follows:
FoS 1.5 - For areas along the MHT perimeter both during and after construction.
FoS 1.3 - For areas where the embankment does not influence the stability of the MHT
perimeter.
Stability analyses were conducted under static long term steady state seepage conditions and
under short term construction loading conditions. During construction, it is expected that
porewater pressures within the existing tailings and organic subgrade will likely increase. For
this preliminary assessment the increase in porewater pressure was modelled with a Bbar of
0.3 for the tailings and 0.4 for organic material. The actual increase in porewater pressures
should be investigated for detailed design and/or construction (fill placement) should be
controlled (with staged and monitored fill placement) to ensure porewater pressures do not
exceed the assumed Bbar values.
A uniformly distributed traffic load of 20 kPa was utilized during analysis.
Seismic parameters for the stability models was not consider based on the Canadian Highway
Design Bridge Code (CHBDC). The subject site has a Zonal acceleration Ratio of 0, as
provided in Table A3 of the CHBDC. Assuming the roadway embankment is considered an
“Emergency rout and other bridges”, the site is located in a Seismic Performance Zone 1, in
accordance with Table 1 of Section 4.4.4. As per Section 4.4.5.1, structures within Seismic
Performance Zone 1s do not required seismic analyses.
It is understood that the highway embankments will be constructed with rock fill with a 300 mm
thick pavement structure consisting of granular fills. Where rock fill is placed along the perimeter
slope of the tailing pile, a zone of filter material between the MHT and the rock fill should be
considered. The design of the filter material should retain the tailings soils while not restricting
seepage.
A description of the analyzed configurations and the results of the stability assessment are
provided below for the various configurations. All slope models (Figures 1 to 7) are provided in
Appendix D:
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 13
1. High fill embankments off the MHT:
a. At areas where the embankment will be constructed with full removal of all
existing organic material and/or tailings, the following
recommendations/comments apply (Refer to Figure 1):
i. The embankments shall be constructed with side slopes no steeper than
1.5H:1V through the rock fill and 2H:1V through the granular fills.
ii. Since all the organic material and tailings will be removed there are no
requirements for staged filling operations.
iii. The use of mid slope benches shall be used for rock fills heights in
excess of 10 m.
b. At areas of high fill embankments off the MHT that must be constructed over
existing tailings and organic material (to maintain stability of the MHT perimeter)
it was assumed the tailings beach thickness is insignificant and a total thickness
of 2 m of organic material exists (conservative) the following
recommendations/comments apply (Refer to Figure 2):
i. The embankments shall be constructed with side slopes no steeper than
1.5H:1V through the rock fill and 2H:1V through the granular fills.
ii. A stepped flanking berm will be required on both sides of the
embankment. The stepped flanking berm may consist of a 3.0 m thick
5.5 m wide step followed by a 1.0 m thick 4.0 m wide step.
iii. To ensure stability during construction, staging with delays for excess
porewater pressure dissipation will likely be required.
iv. A monitoring and instrumentation plan to monitor stability and excess
porewater pressures within the organic material subgrade should be
considered.
v. Staging requirements must be addressed during detailed design.
vi. The use of mid slope benches shall be used for rock fills in excess of 10
m in height.
2. Embankments constructed on the MHT that do not influence the stability of the MHT
perimeter:
For embankments that are constructed on the MHT but away from the MHT perimeter
(14 m or further) the following recommendations/comments apply (Refer to Figure 3 and
Figure 4):
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 14
i. The proposed highway embankment is not expected to have a significant
impact on the stability of the MHT perimeter where the embankment is
located at least 14 m away
ii. The embankments shall be constructed with side slopes no steeper than
1.5H:1V through the rock fill and 2H:1V through the granular fills.
iii. During detailed design confirmation that a Bbar of 0.3 for the tailings is
suitable. Should additional porewater pressures be realized, staged
construction and/or the use of flanking berm may be required to improve
stability during construction.
3. Embankments crossing the MHT perimeter:
a. To facilitate excavation of the existing tailings and organic material below the
proposed embankment adjacent to the toe of the MHT perimeter, a steeped rock
fill berm is required along the MHT perimeter toe. The berm will be constructed
over organic material, removal of this organic material would destabilize the MHT
perimeter. The rock fill berm must be constructed prior to the excavation of the
organic material. The following recommendations/comments apply (Refer to
Figure 5):
i. The stepped flanking berm may consist of a 3 m thick 11 m wide step
followed by a 1.0 m thick 4.0 m wide step. This provides a FoS of 1.5
during construction (assuming excess porewater pressures).
ii. To ensure stability during construction, staging with delays for excess
porewater pressure dissipation may be required. A monitoring and
instrumentation plan to monitor stability and excess porewater pressures
within the organic material subgrade should be considered.
iii. Staging requirements must be addressed during detailed design. Refer
to Figure 5.
b. After the construction of the stepped rock fill flanking berm excavation of the
organic material and tailings from the beneath the proposed embankment can
begin. For this assessment it was assumed that that the excavation would be
constructed in the “wet” without dewatering of the excavation. The following
recommendations/comments apply (Refer to Figure 6):
i. The porewater pressures induced from the construction of the stepped
rock fill flanking berm must dissipate, prior to excavation.
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 15
ii. The excavation of the organic material cannot be within 4 m of the toe of
the steeped rock fill flanking berm. This provides a calculated FoS of 1.3
for the first step of the flanking berm and an overall FoS > 1.5 for global
stability of the MHT perimeter.
c. Stability perpendicular to the MHT perimeter of the tailings or parallel to the
highway alignment:
The stability for potential slope failures longitudinally along the highway
alignment was analized and found to be in excess of 1.5.
4. Embankments constructed on the MHT that do influence the stability of the MHT
perimeter:
For embankments that are constructed on the MHT but within 14 m of the MHT
perimeter the a minimum factor of safety of 1.5 for both long term steady state and short
term construction conditions were considered. The following
recommendations/comments apply (Refer to Figure 7 and Figure 8):
i. As a minimum, the existing tailings slope should be covered with at least
0.6 m of filter material / rock fill.
ii. The rock fill slopes may be constructed at grades of 2H:1V. In addition, a
stepped flanking berm (as described in 3 a) will be required and may
consist of a 3 m thick 11 m wide step followed by a 1.0 m thick 4.0 m
wide step.
iii. To ensure stability during construction, staging with delays for excess
porewater pressure dissipation may be required.
iv. A monitoring and instrumentation plan to monitor stability and excess
porewater pressures within the organic material subgrade should be
considered.
v. Staging requirements must be addressed during detailed design.
vi. The use of mid slope benches must be considered.
10 Settlement Performance
Settlement analyses have been completed for three distinct sections along the proposed
alignment. The three sections include:
Roadway embankment constructed on top of MHT,
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 16
Roadway embankment constructed at toe of MHT perimeter over tailings and organics,
and
Roadway embankment beyond MHT perimeter toe with all tailings and organics
removed
For this preliminary assessment, embankment settlements have been estimated on primary
consolidation of the tailings, native silt and till subgrade, and the primary and secondary
consolidation of the organics. In addition, short and long term settlement associated with rock
fill construction (assuming dumped rock fill) have been included.
As per MTO Embankment Settlement Criteria (July 2, 2010), the design life established for
settlement criteria for King’s highways is 20 years following construction of the pavement
structures. The settlement criteria over the design life for embankments on compressible soils
is 200 mm total with a differential settlement rate of 100:1.
10.1 Roadway Embankment on Top of MHT
It is anticipated that the roadway embankment height will be in the order of 3.5 m in height on
top of the MHT. Preliminary settlement analyses indicates the following:
Table 11-1: Estimated Settlement for Roadway Embankment on MHT
Material Total Settlement After Construction (mm)
1 month 3 months 6 months 1 year 21 years
Tailings 40 55 60 70 80
Organic Material 55 90 110 130 185
Native Silt and Till 5 20 45 50 50
Rock Fill 5 20 35 40 50
Estimated Total 105 185 250 290 365
Remaining Settlement from 21 Year Estimate
260 180 115 75 0
Remaining Settlement meet MTO Criteria
No Yes Yes Yes Yes
In order to meet the MTO settlement performance criteria for total settlements, the embankment
would need to be constructed with a delay in the order of 3 months for final grading and paving.
A small preload surcharge in the order of 10 kPa (approximately 0.5 m of fill) may also be
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 17
considered to expedite settlements. Deferential settlement performance should be assessed
during detailed design.
10.2 Roadway Embankment Constructed Adjacent to the Perimeter of the MHT
Where the embankment crosses the perimeter of the MHT, it is expected that settlements will
be most significant near the toe of the MHT perimeter where fill heights of up to 9 m are
expected and the foundation soils are expected to include up to 2 m of loose tailings and
organic material. For this assessment it has been assumed that 2 m of organic material exists
(no tailings). Preliminary settlement analyses indicates the following.
Table 11-2: Estimated Settlement for Roadway Embankment at Perimeter of MHT
Material
Total Settlement After Construction (mm)
1 month 3 months 6 months 1 year 3 years 21 years
Organic Material 210 415 545 675 875 1030
Native Silt 30 95 190 210 210 210
Rock Fill 20 60 120 135 140 155
Total 260 570 855 1020 1225 1395
Remaining Settlement from 21 Year Estimate
1135 825 540 375 170 0
Remaining Settlement meet MTO Criteria
No No No No Yes Yes
In order to meet the MTO settlement performance criteria for total settlements, the embankment
would need to be constructed with a delay in the order of 3 years for final grading and paving.
In order to expedite settlements, a preload will be required. A preliminary assessment of
preloading options was assessed to expedite primary and secondary consolidation within the
organic material. Based on this assessment, post construction settlements are expected to
meet design, with either an 18 month preload with a 20 kPa (approximately 1 m of fill)
surcharge, or a 12 month preload with a 40 kPa (approximately 2 m of fill) surcharge. Where
surcharge fills are considered, stability analyses should be reassessed to consider the
additional fill height. Deferential settlement performance should be assessed during detailed
design.
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 18
10.3 Embankments Constructed Off of MHT
Where the embankments are constructed well beyond the toe of the perimeter of the MHT, it
has been assumed that any existing tailings and/or organic material will be excavated to expose
native silt or till. For embankments up to 9 m in height, settlements within the native (non-
organic) subgrade and within the rock fill are expected to be in the order of 360 mm. In order to
meet MTO settlement criteria for total maximum settlements, a delay in the order of 3 months
for final grading and paving should be considered for embankments up to 9 m in height. No
delay in final grading and paving is expected for embankments 4 m in height and less.
11 Scope of Detailed Investigation and Future Considerations
The following items should be considered for detailed foundation design of the proposed
highway relocation over the MHT.
Design Criteria:
The design of the highway must consider standard design and performance criteria for
the highway as well as design criteria for the MHT. Currently, the design criterial for the
existing tailings facility is not well defined. The last design report (“Tailings Area
Preliminary Investigations Report (Draft)”, issued July 1996) does not clearly identify the
design criteria for the facility and/or demonstrate the existing facility meets the
suggested levels of stability. The hazard potential classification and subsequent design
criteria for the existing tailings facility should also be reviewed in light of the proposed
change in conditions (as the facility will now support a public road). Consultation with
the appropriate regulatory authorities is recommended. The current state of stability of
the existing tailings facility may also need to be reassessed and upgraded, if required.
Seismic Considerations:
As per the Canadian Highway Design Bridge Code, seismic analyses is not required for
the design of the highway embankment. However, design requirements for the MHT will
likely require seismic analysis which will be dependent on the design criteria established
for the existing facility. Any future analyses for the tailings facility should consider any
potential effects associated with the proposed new highway. Depending on the design
criteria established, further investigations may be required to more accurately identify
and address potential liquefaction and/or stability issues.
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 19
Stability During Construction:
The stability of the highway embankment and perimeter of the tailings facility during
construction (filling operations) will be highly dependent on the porewater pressures
response within the existing tailings and organic material subgrade soils. Further study
consisting of laboratory and/or field studies (eg. CPTU testing, or instrumented test fills),
may be considered to identify expected porewater pressure response and dissipation
properties. Additional strength testing under both drained and undrained conditions may
also be considered. Based on the results of new testing data, the stability analyses
should be reassessed to determine requirements for staging including instrumentation
and monitoring, if required.
Phreatic Surface Along Perimeter of Tailings Facility:
The groundwater conditions within the perimeter of the tailings facility can have a
significant impact on global stability and potential for instability due to piping. Currently,
there is little data to identify the current state or fluctuations of the groundwater level
through the perimeter of the existing tailings facility. A monitoring program consisting of
the installation of piezometers along the perimeter of the tailings facility and the
associated toe berm should be considered.
Tailings Beach:
The existing tailings beach beyond the toe of the MHT can have a significant impact on
stability. If the existing tailings beach has a relatively consistent thickness throughout
the areas of concern, stability of the existing MHT perimeter is improved. However,
should the tailings beach be removed at some future time, or be highly variable in terms
of thickness and extent, it may not be reliable in terms of its contribution towards
stability. Further investigation to study the variability, extent and condition of the tailings
beach may be considered.
Fills On Top of Tailings Facility:
Further investigation should be completed to identify the extent, quality and conditions of
the fills on top of the tailings facility along the proposed highway alignment.
Tailings and Organic material:
Additional Investigation and laboratory testing should be considered to address
variability within the tailings and organic material subgrade in terms of strength and
consolidation properties.
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 20
Existing Structures:
It is understood that a buried splitter dyke, abandoned decant structures and drainage
pipes may exist within the MHT along the proposed highway alignment. Additional
investigation should be completed to locate and inspect these structures to identify any
potential future long term settlement issues exist.
Future Structures:
It is understood that a future waste rock pile is planned to be constructed on the MHTs.
The impacts of this structure on the roadway embankments will need to be determined
and design adjustments may be required.
Filter Material:
The design of the filter material will need to be determined.
Preliminary Foundation Investigation and Design TBTE Ref. No. 14-192-2 Highway 11 Relocation Premier Gold
Page 21
12 Limitations
Conclusions and recommendations presented in this report are based on the information
determined at the borehole locations. Subsurface and groundwater conditions between and
beyond these locations may differ from those encountered. Conditions may become apparent
during construction that were not detected and could not be anticipated at the time of the site
investigation.
The comments given in this report on potential construction problems and possible methods of
construction are intended only for the guidance of the designer.
Groundwater levels indicated are based on the information described within the report. The
presence of all conditions that could affect the type and scope of dewatering procedures which
may be considered cannot readily be determined from boreholes. These include local and
seasonal fluctuations of the groundwater level, changes in soil conditions between test
locations, thin and/or discontinuous layers of highly permeable soils, etc.
The information contained within this report in no way reflects any environmental aspect of the
site or soil.
<Original signed by>
<Original signed by><Original signed by>
TBTE REF No.:14-192
Page 23
APPENDIX A Borehole Logs
(97)
(27)
AS
SS
SS
SS
SS
SS
SS
SS
329.1
325.2
322.8
3
25
Water onsurface.
ORGANICS - black, very loose
SILT - trace sand, grey, loose tocompact
- - - - -- numerous cobbles & bouldersTILL - GRAVEL - Sandy, Silty,grey, compact to very dense
End of Borehole @ 7.8 m.Auger Refusal.
1
4
8
13
18
13
100+
1.5
5.4
7.8
685.4
457.4
0
49
>>
1
2
3
4
5
6
7
8
2015 February 3 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
330.6
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
330
329
328
327
326
325
324
323
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-500
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 12+764 o/s 1.8 Rt N5504265.729, E504143.806
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
(47)
(29)
AS
SS
SS
SS
SS
SS
SS
SS
SS
329.0
325.7
322.5
24
38
Water @ surface.ORGANICS - black, some greytailings to 75 mm
- - - - -- brown
- - - - -- blackSILT - Gravelly, Sandy, grey,loose to compact
TILL - SAND - Gravelly, Silty,grey, compact to dense
- - - - -- numerous cobbles & bouldersEnd of Borehole @ 8.6 m.Auger Refusal.
1
1
10
9
6
23
43
100+
2.1
5.4
8.6
279.4
422.4
30
32
>>
1
2
3
4
5
6
7
8
9
2015 February 3 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
331.1
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
331
330
329
328
327
326
325
324
323
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-501
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 12+867 o/s 3.6 Rt N5504242.045, E504242.767
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
(68)
AS
SS
SS
SS
SS
SS
SS
330.5
329.6
326.3
325.4
32
Water @ surface.TAILINGS - SILT - Sandy, someorganics, grey, loose
ORGANICS - black, very loose
SILT - Sandy, grey, loose tocompact
- - - - -- numerous cobbles & bouldersTILL - SAND & GRAVEL - grey,very dense
End of Borehole @ 6.3 m.Auger Refusal.
7
2
7
13
19
100+
1.2
2.1
5.4
6.3
325.7
0
>>
1
2
3
4
5
6
7
2015 February 4 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
331.7
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
331
330
329
328
327
326
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-502
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 12+969 o/s 4.7 Rt N5504206.698, E504337.855
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
(99)
(87)
(26)
AS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
51
336.1
335.3
330.0329.7
327.3
324.9
1
0
13
54
TOPSOIL - SAND - brown
FILL - SILT - trace sand, grey,very loose
TAILINGS - SILT - trace tosome sand, grey, very loose toloose
ORGANICSSILT - grey, compact to dense
TILL - SAND - Silty, Gravelly,occasional cobbles, grey, dense
End of Borehole @ 12.6 m.
4
3
6
4
3
5
31
12
35
100+
48
1.4
2.2
7.57.8
10.2
12.6
280
0
0
0
21
>>
1
2
3
4
5
6
7
8
9
10
11
2014 December 16 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger
P.P.
S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
337.5
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
337
336
335
334
333
332
331
330
329
328
327
326
325
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-503
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 13+041 o/s 4.7 Rt N5504175.869, E504403.445
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
(64)
(93)
AS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
72
76
336.2
328.3
327.1
324.7
323.0
8
5
36
8
Frost to 150 mm.TOPSOIL - SAND - brown
- - - - -- trace tailingsTAILINGS - SILT - trace sand,grey, very loose to loose
- - - - -- SILT & SAND
ORGANICS - brown
SILT - trace sand, loose tocompact
TILL - SAND - Silty, Gravelly,grey
End of Borehole @ 14.6 m.
3
3
2
1
3
4
5
13
28
9
46
100+
20
19
1.4
9.3
10.5
12.9
14.6
289.3
0
0
0
0
>>
1
2
3
4
5
6
7
8
9
10
11
12
13
2014 December 17 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger
P.P.
S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
337.6
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
337
336
335
334
333
332
331
330
329
328
327
326
325
324
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-504
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 13+176 o/s 1.3 Rt N5504120.356, E504525.853
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
(18)
(97)
AS
AS
AS
AS
AS
AS
AS
AS
AS
AS
AS
AS
35
333.0
328.4
327.0
323.5
29
38
3
On cobbles
FILL - GRAVEL - Sandy, somesilt, occasional cobbles, brown,compact to very dense
- - - - - -- grey
TAILINGS - SILT & SAND -trace gravel, grey, loose tocompact
- - - - -- burgundy
ORGANICS - black
SILT - trace sand, loose tocompact
End of Borehole @ 15.0 m.
11
34
32
28
100+
12
8
5
15
18
5
16
23
5.5
10.1
11.5
15.0
306.2
53
4
0
>>
1
2
3
4
5
6
7
8
9
10
11
12
2015 January 14 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger
T.P.
S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
338.5
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
338
337
336
335
334
333
332
331
330
329
328
327
326
325
324
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-505
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 13+323 o/s 0.6 Rt N5504056.903, E504658.373
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
(95)
(89)
(95)
AS
SS
SS
SS
SS
SS
SS
SS
SS
SS
328.8
327.6
321.7
5
11
4
TAILINGS - SILT, trace sand,grey, some organics, brown,very loose to loose
- - - - -- burgundy
ORGANICS - black
SILT - trace to some sand, grey,loose to very dense
- - - - -- numerous cobbles & boulders
End of Borehole @ 10.0 m.Auger Refusal.
6
4
2
2
3
10
4
42
100+
3.0
4.1
10.0
119.4
0
0
0
>>
1
2
3
4
5
6
7
8
9
10
2015 February 4 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
331.7
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
331
330
329
328
327
326
325
324
323
322
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-506
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 13+454 o/s 0.1 Rt N5504000.158, E504776.767
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
(75)
(97)
(96)
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
66
335.5
329.4329.1
323.9
323.1
25
3
4
4
FILL - SILT - Sandy, brown,loose
TAILINGS - SILT - trace sand,grey, very loose
ORGANICS - blackSILT - trace sand, grey, loose tocompact
TILL - SAND & GRAVEL
End of Borehole @ 13.7 m.Auger Refusal.
7
2
1
1
1
4
15
13
9
14
100+
31
1.3
7.47.7
12.9
13.7
119
0
0
0
0
>>
1
2
3
4
5
6
7
8
9
10
11
2015 January 17 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger
T.P.
S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
336.8
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
336
335
334
333
332
331
330
329
328
327
326
325
324
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-507
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 13+603 o/s 6.6 Rt N5503929.485, E504907.652
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
(94)
(45)
(8)
(4)
AS
SS
SS
SS
SS
SS
SS
SS
SS
334.6
330.9
327.4
6
22
81
92
Frost to 300 mm.
On cobbles
TOPSOIL - brown
TAILINGS - SILT, trace sand toSandy, very loose
- - - - -- Gravelly, compact
TILL - SAND - trace silt, trace tosome gravel, occasionalcobbles, very dense
End of Borehole @ 9.0 m.
7
9
1
1
25
100+
100+
100+
1.8
5.5
9.0
0
32
12
4
>>
>>
>>
1
2
3
4
5
6
7
8
9
2014 December 21 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger
P.P.
S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
336.4
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
336
335
334
333
332
331
330
329
328
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-508
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 13+823 o/s 5.6 Lt N5503847.034, E505112.597
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
(94)
(91)
(93)
(15)
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
69
330.6
326.5
322.8
6
9
16
7
49
TAILINGS - SILT, trace to somesand, grey, very loose tocompact
SILT - some gravel, trace sand,grey, compact
TILL - SAND & GRAVEL - somesilt, grey, dense
End of Borehole @ 13.5 m.Auger Refusal.
11
2
1
2
2
17
13
11
34
22
100+
15
5.7
9.8
13.5
0
0
0
0
36
>>
1
2
3
4
5
6
7
8
9
10
11
2015 January 13 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger
T.P.
S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
336.3
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
336
335
334
333
332
331
330
329
328
327
326
325
324
323
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-509
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 14+017 o/s 21.7 Rt N5503772.957, E505295.367
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
(72)SS
SS
SS
SS
SS
330.4
329.6
327.9
29FILL - SILT - Sandy, grey
ORGANICS - black
TILL - SAND & GRAVEL - grey,compact to very dense
- - - - -- GRAVEL & COBBLES - Silty
End of Borehole @ 3.2 m.Auger Refusal.
5
10
18
100+
0.7
1.5
3.2
463.9
0
>>
1
2
3
4
5
2015 February 5 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
331.1
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
331
330
329
328
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-510
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 14+098 o/s 13.5 Rt N5503774.878, E505378.041
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
(3)
AS
SS
SS
SS
SS
SS
SS
330.4
326.7
74
FILL - SAND - very loose tocompact- - - - -- grey
- - - - -- Silty, some organics, blackTILL - SAND - Gravelly, tracesilt, grey, compact to dense
End of Borehole @ 5.9 m.Auger Refusal.
13
2
27
13
32
100+
2.2
5.9
23
>>
1
2
3
4
5
6
7
2015 January 19 DATUM
0.0
SOIL PROFILE
Numbers refer toSensitivity
STRAIN AT FAILURE
20 40 60 80 100
GEOCRES No
kN/m3
BOREHOLE TYPE
LOCATION
PROJECT
Hollow Stem Auger
T.P.
S.S.
CL
ELEVwP
SA
LIQUIDLIMIT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
UN
ITW
EIG
HT
COMPILED BY
3%
wL
DATE
GR20 40 60 SI
"N"
VA
LUE
S
Realignment of Hwy 11
DEPTHDESCRIPTION
w
CHECKED BY
61
PLASTICLIMIT
T.B.
N/A
HWY
332.6
SHEAR STRENGTH kPa
METRIC
REMARKS&
GRAIN SIZEDISTRIBUTION
(%)
TBTE JOB#
SPT (N)
ST
RA
T P
LOT
332
331
330
329
328
327
Ministry ofTransportation
Ontario
ELE
VA
TIO
N S
CA
LE
DIST
20 40 60 80 100
NU
MB
ER
TY
PE
TBT Engineering Consulting Group
Foundation Design
NATURALMOISTURECONTENT
ORIGINATED BY
:
RECORD OF Borehole No 15-BH-511
GR
OU
ND
WA
TE
RC
ON
DIT
ION
S
11
SAMPLES
NP Non Plastic
1 OF 1
WATER CONTENT (%)UNDRAINEDDIRECT SHEAR
3
UNCONFINED FIELD VANE
N/A
14-192-2
Geodetic
UTM Sta. 14+139 o/s 16.7 Rt N5503771.72, E505420.353
W O
ON
_MT
O_B
H_U
TM
14-
192
FD
TN
GE
RA
LTO
N.G
PJ
ON
_MO
T.G
DT
15/
3/30
TBTE REF No.:14-192
Page 24
APPENDIX B Laboratory Test Data
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
0.001 0.01 0.1 1 10 100
coarsefine
PE
RC
EN
T F
INE
R B
Y W
EIG
HT
coarsefine
99.317.674.671.5
D6015-BH-50315-BH-50515-BH-50715-BH-510
%Clay0.053.10.00.0
SAND
TBT Engineering Ltd.1918 Yonge StreetThunder Bay, Ontario P7E 6T9PH: 807-624-5160FX: 807-624-5161Email: [email protected]: www.tbte.ca
1.502.300.600.30
0.729.325.428.5
0.2537.54.75
2
12.899 0.917
D30
GRAIN SIZE DISTRIBUTION
GRAIN SIZE IN MILLIMETERS
%Sand
Project: Realignment of Hwy 11
W P: N/A
DIST: 61 HWY: 11
D100
GRAVELmedium
%SiltTest Hole Depth %Gravel
COBBLES
D10
SILT OR CLAY
Remarks:FILL
MT
O_G
S 1
4-19
2 F
DT
N G
ER
ALT
ON
.GP
J O
N_M
OT
.GD
T 1
5/3/
27
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
0.001 0.01 0.1 1 10 100
coarsefine
PE
RC
EN
T F
INE
R B
Y W
EIG
HT
coarsefine
68.499.886.891.795.3
D6015-BH-50215-BH-50315-BH-50315-BH-50415-BH-504
%Clay
0.001
0.0020.003
0.00.00.00.00.0
SAND
TBT Engineering Ltd.1918 Yonge StreetThunder Bay, Ontario P7E 6T9PH: 807-624-5160FX: 807-624-5161Email: [email protected]: www.tbte.ca
0.753.004.602.303.00
31.60.213.28.34.7
20.1060.25
20.425
0.007
0.0260.022
0.003
0.0080.008
D30
GRAIN SIZE DISTRIBUTION
GRAIN SIZE IN MILLIMETERS
%Sand
Project: Realignment of Hwy 11
W P: N/A
DIST: 61 HWY: 11
D100
GRAVELmedium
%SiltTest Hole Depth %Gravel
COBBLES
D10
SILT OR CLAY
Remarks:TAILINGS
MT
O_G
S 1
4-19
2 F
DT
N G
ER
ALT
ON
.GP
J O
N_M
OT
.GD
T 1
5/3/
27
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
0.001 0.01 0.1 1 10 100
coarsefine
PE
RC
EN
T F
INE
R B
Y W
EIG
HT
coarsefine
63.758.194.697.296.5
D6015-BH-50415-BH-50515-BH-50615-BH-50715-BH-507
%Clay
0.001
0.002
0.04.20.00.00.0
SAND
TBT Engineering Ltd.1918 Yonge StreetThunder Bay, Ontario P7E 6T9PH: 807-624-5160FX: 807-624-5161Email: [email protected]: www.tbte.ca
7.506.001.502.303.00
36.337.75.42.83.5
0.259.5
0.4250.25
2
0.083
0.012
0.009
0.005
D30
GRAIN SIZE DISTRIBUTION
GRAIN SIZE IN MILLIMETERS
%Sand
Project: Realignment of Hwy 11
W P: N/A
DIST: 61 HWY: 11
D100
GRAVELmedium
%SiltTest Hole Depth %Gravel
COBBLES
D10
SILT OR CLAY
Remarks:TAILINGS
MT
O_G
S 1
4-19
2 F
DT
N G
ER
ALT
ON
.GP
J O
N_M
OT
.GD
T 1
5/3/
27
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
0.001 0.01 0.1 1 10 100
coarsefine
PE
RC
EN
T F
INE
R B
Y W
EIG
HT
coarsefine
93.845.393.890.783.6
D6015-BH-50815-BH-50815-BH-50915-BH-50915-BH-509
%Clay
0.003
0.032.40.00.00.0
SAND
TBT Engineering Ltd.1918 Yonge StreetThunder Bay, Ontario P7E 6T9PH: 807-624-5160FX: 807-624-5161Email: [email protected]: www.tbte.ca
3.004.501.503.004.50
6.222.36.29.316.4
0.8537.54.750.850.425
0.417
0.033 0.012
D30
GRAIN SIZE DISTRIBUTION
GRAIN SIZE IN MILLIMETERS
%Sand
Project: Realignment of Hwy 11
W P: N/A
DIST: 61 HWY: 11
D100
GRAVELmedium
%SiltTest Hole Depth %Gravel
COBBLES
D10
SILT OR CLAY
Remarks:TAILINGS
MT
O_G
S 1
4-19
2 F
DT
N G
ER
ALT
ON
.GP
J O
N_M
OT
.GD
T 1
5/3/
27
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
0.001 0.01 0.1 1 10 100
coarsefine
PE
RC
EN
T F
INE
R B
Y W
EIG
HT
coarsefine
97.146.592.596.789.3
D6015-BH-50015-BH-50115-BH-50415-BH-50515-BH-506
%Clay0.029.80.00.00.0
SAND
TBT Engineering Ltd.1918 Yonge StreetThunder Bay, Ontario P7E 6T9PH: 807-624-5160FX: 807-624-5161Email: [email protected]: www.tbte.ca
3.004.60
10.5013.506.10
2.923.77.53.310.7
0.8537.50.850.25
2
0.352
D30
GRAIN SIZE DISTRIBUTION
GRAIN SIZE IN MILLIMETERS
%Sand
Project: Realignment of Hwy 11
W P: N/A
DIST: 61 HWY: 11
D100
GRAVELmedium
%SiltTest Hole Depth %Gravel
COBBLES
Remarks:SILT
D10
SILT OR CLAY
MT
O_G
S 1
4-19
2 F
DT
N G
ER
ALT
ON
.GP
J O
N_M
OT
.GD
T 1
5/3/
27
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
0.001 0.01 0.1 1 10 100
coarsefine
PE
RC
EN
T F
INE
R B
Y W
EIG
HT
coarsefine
95.495.793.0
D6015-BH-50615-BH-50715-BH-509
%Clay0.20.00.0
SAND
TBT Engineering Ltd.1918 Yonge StreetThunder Bay, Ontario P7E 6T9PH: 807-624-5160FX: 807-624-5161Email: [email protected]: www.tbte.ca
9.109.007.50
4.44.37.0
9.522
D30
GRAIN SIZE DISTRIBUTION
GRAIN SIZE IN MILLIMETERS
%Sand
Project: Realignment of Hwy 11
W P: N/A
DIST: 61 HWY: 11
D100
GRAVELmedium
%SiltTest Hole Depth %Gravel
COBBLES
Remarks:SILT
D10
SILT OR CLAY
MT
O_G
S 1
4-19
2 F
DT
N G
ER
ALT
ON
.GP
J O
N_M
OT
.GD
T 1
5/3/
27
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
0.001 0.01 0.1 1 10 100
coarsefine
PE
RC
EN
T F
INE
R B
Y W
EIG
HT
coarsefine
26.529.125.87.84.0
D6015-BH-50015-BH-50115-BH-50315-BH-50815-BH-508
%Clay
0.1140.161
49.032.420.611.74.3
SAND
TBT Engineering Ltd.1918 Yonge StreetThunder Bay, Ontario P7E 6T9PH: 807-624-5160FX: 807-624-5161Email: [email protected]: www.tbte.ca
6.006.10
10.506.007.50
24.538.553.680.591.7
37.537.525
13.29.5
7.4172.9291.0881.4640.831
0.1610.080.1070.4690.346
D30
GRAIN SIZE DISTRIBUTION
GRAIN SIZE IN MILLIMETERS
%Sand
Project: Realignment of Hwy 11
W P: N/A
DIST: 61 HWY: 11
D100
GRAVELmedium
%SiltTest Hole Depth %Gravel
COBBLES
D10
SILT OR CLAY
Remarks:TILL
MT
O_G
S 1
4-19
2 F
DT
N G
ER
ALT
ON
.GP
J O
N_M
OT
.GD
T 1
5/3/
27
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
0.001 0.01 0.1 1 10 100
coarsefine
PE
RC
EN
T F
INE
R B
Y W
EIG
HT
coarsefine
14.82.9
D6015-BH-50915-BH-511
%Clay
0.336.223.4
SAND
TBT Engineering Ltd.1918 Yonge StreetThunder Bay, Ontario P7E 6T9PH: 807-624-5160FX: 807-624-5161Email: [email protected]: www.tbte.ca
10.503.00
49.073.7
37.525
3.9062.443
0.7980.764
D30
GRAIN SIZE DISTRIBUTION
GRAIN SIZE IN MILLIMETERS
%Sand
Project: Realignment of Hwy 11
W P: N/A
DIST: 61 HWY: 11
D100
GRAVELmedium
%SiltTest Hole Depth %Gravel
COBBLES
D10
SILT OR CLAY
Remarks:TILL
MT
O_G
S 1
4-19
2 F
DT
N G
ER
ALT
ON
.GP
J O
N_M
OT
.GD
T 1
5/3/
27
14-192-2
Peat
Borehole 505 Depth: 10.5 Lab No.: 23044
CONSOLIDATION TEST Project No.:
0123456789
10
1 10 100 1000
Cv (
mm
^2/m
in.)
Load (kPa)
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
1 10 100 1000
Str
ain
Load (kPa)
14-192-2
Tailings
Borehole 504 Depth: 3 Lab No.:
CONSOLIDATION TEST Project No.:
020406080
100120140160180
10 100 1000
Cv (
mm
^2/m
in.)
Load (kPa)
0.0%
0.5%
1.0%
1.5%
2.0%
2.5%
3.0%
3.5%
10 100 1000
Str
ain
Load (kPa)
Ref
. No
.: 1
4-1
92
-2
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
01
02
03
04
05
06
07
08
09
01
00
11
01
20
13
01
40
15
01
60
17
01
80
19
02
00
21
02
20
23
02
40
25
02
60
Shear Stress (kPa)
No
rmal
Str
ess (
kP
a)
Dra
ine
d D
ire
ct
Sh
ea
r Te
st
-Ta
ilin
gs
BH
50
4, D
ep
th 3
.0 m
10
0 kP
a @
2 %
Str
ain
50
kP
a @
2 %
Str
ain
20
0 kP
a @
2 %
Str
ain
c' =
0 k
Pa,
Ph
i' =
31
º
TBTE REF No.:14-192
Page 25
APPENDIX C Borehole Locations, and Soil Strata Drawing
TBTE REF No.:14-192
Page 26
APPENDIX D Stability Models
Nat
ive
Silt
s
Till
Roc
k F
ill
Fill
1.58
DN
NS
Roa
d on
Exi
stin
g G
roun
d N
o P
eat o
r T
ailin
gs.g
szY
:\Pro
ject
s\20
14\1
4-19
2 P
rem
ier
Gol
d -
PD
R\1
4-19
2-2
Pre
lim F
ND
N\A
naly
sis\
Slo
pe\F
or P
relim
inar
y\M
orge
nste
rn-P
rice
26/0
3/20
15F
OS
: 1.5
8N
ame:
Fill
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 35
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
No
Nam
e: T
ill
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
5 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: N
o
N
ame:
Nat
ive
Silt
s
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 30
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
No
Nam
e: R
ock
Fill
Uni
t Wei
ght:
18 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 45
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
No
1.5H
:1V
Fig
ure
1
20 k
Pa
Dis
tanc
e
-80
-75
-70
-65
-60
-55
-50
-45
-40
-35
-30
-25
-20
-15
-10
-50
510
1520
Elevation
310
315
320
325
330
335
340
345
350
355
360
Pea
t
Nat
ive
Silt
s
Till
Roc
k F
ill
Fill
Roc
k F
illR
ock
Fill
1.39
DN
NS
Roa
d on
Exi
stin
g G
roun
d -
No
Ex
with
BB
ar lo
wer
che
ck.g
szY
:\Pro
ject
s\20
14\1
4-19
2 P
rem
ier
Gol
d -
PD
R\1
4-19
2-2
Pre
lim F
ND
N\A
naly
sis\
Slo
pe\F
or P
relim
inar
y\M
orge
nste
rn-P
rice
26/0
3/20
15F
OS
: 1.3
9N
ame:
Fill
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 35
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
Yes
Nam
e: P
eat
U
nit W
eigh
t: 12
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 2
8 °
P
iezo
met
ric L
ine:
1
B
-bar
: 0.4
Add
Wei
ght:
No
Nam
e: T
ill
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
5 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: N
o
N
ame:
Nat
ive
Silt
s
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 30
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
No
Nam
e: R
ock
Fill
Uni
t Wei
ght:
18 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 45
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
Yes
1.5H
:1V
2H:1
V
5.5
m F
lank
ing
Ber
m3
m T
hick
20 k
Pa
4 m
Fla
nkin
g B
erm
1 m
Thi
ck
Fig
ure
2
Dis
tanc
e
-90
-85
-80
-75
-70
-65
-60
-55
-50
-45
-40
-35
-30
-25
-20
-15
-10
-50
510
1520
Elevation
310
315
320
325
330
335
340
345
350
355
360
1.51
DN
NS
slo
pe w
ith N
o B
ench
Slo
pe o
n to
p.gs
zY
:\Pro
ject
s\20
14\1
4-19
2 P
rem
ier
Gol
d -
PD
R\1
4-19
2-2
Pre
lim F
ND
N\A
naly
sis\
Slo
pe\F
or P
relim
inar
y\M
orge
nste
rn-P
rice
26/0
3/20
15F
OS
: 1.5
1N
ame:
Fill
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 32
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
Yes
Nam
e: T
ailin
gs
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
1 °
P
iezo
met
ric L
ine:
1
B
-bar
: 0.3
Add
Wei
ght:
No
Nam
e: P
eat
U
nit W
eigh
t: 12
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 2
8 °
P
iezo
met
ric L
ine:
1
B
-bar
: 0.4
Add
Wei
ght:
No
Nam
e: T
ill
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
5 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: N
o
N
ame:
Nat
ive
Silt
s
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 30
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
No
Nam
e: R
ock
Fill
Uni
t Wei
ght:
18 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 45
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
Yes
20 k
Pa
1.5H
:1V
Fig
ure
3
Dis
tanc
e
-30
-25
-20
-15
-10
-50
510
1520
2530
3540
4550
5560
6570
7580
85
Elevation
310
315
320
325
330
335
340
345
350
355
360
2.01
DN
NS
Roa
d on
Tai
lings
, NO
Slo
pe in
fluen
ce w
ith B
Bar
.gsz
Y:\P
roje
cts\
2014
\14-
192
Pre
mie
r G
old
- P
DR
\14-
192-
2 P
relim
FN
DN
\Ana
lysi
s\S
lope
\For
Pre
limin
ary\
Mor
gens
tern
-Pric
e26
/03/
2015
FO
S: 2
.01
Nam
e: F
ill
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
5 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: Y
es
N
ame:
Tai
lings
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 31
°
Pie
zom
etric
Lin
e: 1
B-b
ar: 0
.3
A
dd W
eigh
t: N
o
N
ame:
Pea
t
Uni
t Wei
ght:
12 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 28
°
Pie
zom
etric
Lin
e: 1
B-b
ar: 0
.4
A
dd W
eigh
t: N
o
N
ame:
Till
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 35
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
No
Nam
e: N
ativ
e S
ilts
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
0 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: N
o
N
ame:
Roc
k F
ill
U
nit W
eigh
t: 18
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 4
5 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: Y
es
20 k
Pa
1.5H
:1V
Fig
ure
4
Dis
tanc
e
-50
-45
-40
-35
-30
-25
-20
-15
-10
-50
510
1520
2530
3540
4550
Elevation
310
315
320
325
330
335
340
345
350
355
360
Tai
lings
Nat
ive
Silt
s
Till
Pea
tRoc
k F
ill
1.51
DN
NS
slo
pe w
ith N
o B
ench
Exc
avat
ion
with
BB
ar.g
szY
:\Pro
ject
s\20
14\1
4-19
2 P
rem
ier
Gol
d -
PD
R\1
4-19
2-2
Pre
lim F
ND
N\A
naly
sis\
Slo
pe\F
or P
relim
inar
y\M
orge
nste
rn-P
rice
26/0
3/20
15F
OS
: 1.5
1N
ame:
Tai
lings
Mod
el: M
ohr-
Cou
lom
b
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 31
°
Phi
-B: 0
°
Pie
zom
etric
Lin
e: 1
B-b
ar: 0
.3
A
dd W
eigh
t: N
o
N
ame:
Pea
t
Mod
el: M
ohr-
Cou
lom
b
Uni
t Wei
ght:
12 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 28
°
Phi
-B: 0
°
Pie
zom
etric
Lin
e: 1
B-b
ar: 0
.4
A
dd W
eigh
t: N
o
N
ame:
Till
Mod
el: M
ohr-
Cou
lom
b
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 35
°
Phi
-B: 0
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
No
Nam
e: N
ativ
e S
ilts
M
odel
: Moh
r-C
oulo
mb
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
0 °
P
hi-B
: 0 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: N
o
N
ame:
Roc
k F
ill
M
odel
: Moh
r-C
oulo
mb
U
nit W
eigh
t: 18
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 4
5 °
P
hi-B
: 0 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: Y
es
4 m
Fig
ure
5
10.9
m2H
:1V
Dis
tanc
e
-50
-45
-40
-35
-30
-25
-20
-15
-10
-50
510
1520
2530
3540
4550
5560
Elevation
310
315
320
325
330
335
340
345
350
355
360
Tai
lings
Nat
ive
Silt
s
Till
Pea
tR
ock
Fill
1.30
DN
NS
slo
pe w
ith N
o B
ench
Exc
avat
ion.
gsz
Y:\P
roje
cts\
2014
\14-
192
Pre
mie
r G
old
- P
DR
\14-
192-
2 P
relim
FN
DN
\Ana
lysi
s\S
lope
\For
Pre
limin
ary\
Mor
gens
tern
-Pric
e26
/03/
2015
FO
S: 1
.30
Nam
e: T
ailin
gs
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
1 °
P
iezo
met
ric L
ine:
1
B
-bar
: 0
A
dd W
eigh
t: N
o
N
ame:
Pea
t
Uni
t Wei
ght:
12 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 28
°
Pie
zom
etric
Lin
e: 1
B-b
ar: 0
Add
Wei
ght:
No
Nam
e: T
ill
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
5 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: N
o
N
ame:
Nat
ive
Silt
s
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 30
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
No
Nam
e: R
ock
Fill
Uni
t Wei
ght:
18 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 45
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
No
4 m
4 m
11 m
2H:1
V
Fig
ure
6D
ista
nce
-50
-45
-40
-35
-30
-25
-20
-15
-10
-50
510
1520
2530
3540
4550
5560
Elevation
310
315
320
325
330
335
340
345
350
355
360
Pea
t
Tai
lings
Nat
ive
Silt
s
Till
Fill
Roc
k F
ill
Roc
k F
illF
ilter
Mat
eria
l
1.50
DN
NS
slo
pe w
ith N
o B
ench
Roa
d on
top
with
bba
r.gs
zY
:\Pro
ject
s\20
14\1
4-19
2 P
rem
ier
Gol
d -
PD
R\1
4-19
2-2
Pre
lim F
ND
N\A
naly
sis\
Slo
pe\F
or P
relim
inar
y\M
orge
nste
rn-P
rice
26/0
3/20
15F
OS
: 1.5
0N
ame:
Fill
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 35
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
Yes
Nam
e: T
ailin
gs
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
1 °
P
iezo
met
ric L
ine:
1
B
-bar
: 0.3
Add
Wei
ght:
No
Nam
e: P
eat
U
nit W
eigh
t: 12
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 2
8 °
P
iezo
met
ric L
ine:
1
B
-bar
: 0.4
Add
Wei
ght:
No
Nam
e: T
ill
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
5 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: N
o
N
ame:
Nat
ive
Silt
s
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 30
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
No
Nam
e: R
ock
Fill
Uni
t Wei
ght:
18 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 45
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
Yes
Nam
e: F
ilter
Mat
eria
l
Uni
t Wei
ght:
18 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 35
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
Yes
20 k
Pa
1.5H
:1V
4 m
10.4
m
2H:1
V
0.6
m T
hick
Fig
ure
7D
ista
nce
-30
-25
-20
-15
-10
-50
510
1520
2530
3540
4550
5560
6570
75
Elevation
310
315
320
325
330
335
340
345
350
355
360
Pea
t
Tai
lings
Nat
ive
Silt
s
Till
Fill
Filt
er M
ater
ial
Roc
k F
ill
1.51
DN
NS
slo
pe w
ith N
o B
ench
Roa
d on
slo
pe (
ii) w
ith b
bar.
gsz
Y:\P
roje
cts\
2014
\14-
192
Pre
mie
r G
old
- P
DR
\14-
192-
2 P
relim
FN
DN
\Ana
lysi
s\S
lope
\For
Pre
limin
ary\
Mor
gens
tern
-Pric
e26
/03/
2015
FO
S: 1
.51
Nam
e: F
ill
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
5 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: Y
es
N
ame:
Tai
lings
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 31
°
Pie
zom
etric
Lin
e: 1
B-b
ar: 0
.3
A
dd W
eigh
t: N
o
N
ame:
Pea
t
Uni
t Wei
ght:
12 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 28
°
Pie
zom
etric
Lin
e: 1
B-b
ar: 0
.4
A
dd W
eigh
t: N
o
N
ame:
Till
Uni
t Wei
ght:
20 k
N/m
³
Coh
esio
n: 0
kP
a
Phi
: 35
°
Pie
zom
etric
Lin
e: 1
Add
Wei
ght:
No
Nam
e: N
ativ
e S
ilts
U
nit W
eigh
t: 20
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
0 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: N
o
N
ame:
Roc
k F
ill
U
nit W
eigh
t: 18
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 4
5 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: Y
es
N
ame:
Filt
er M
ater
ial
U
nit W
eigh
t: 18
kN
/m³
C
ohes
ion:
0 k
Pa
P
hi: 3
5 °
P
iezo
met
ric L
ine:
1
A
dd W
eigh
t: Y
es
20 k
Pa
1.5H
:1V
10.9
m
4 m
Fig
ure
8
2H:1
V
Dis
tanc
e
-30
-25
-20
-15
-10
-50
510
1520
2530
3540
4550
5560
6570
75
Elevation
310
315
320
325
330
335
340
345
350
355
360
Premier Gold – Hardrock Project TBTE Ref. No.: 14-192 Highway 11 Realignment
APPENDIX F
MTO Correspondence
Premier Gold/Stantec/MTO Meeting Minutes – January 30, 2014
Premier Gold/TBTE/MTO Meeting Minutes – Progress Meetings 1- 3
Meeting Minutes
fc c:\users\fchristiansen\appdata\local\microsoft\windows\temporary internet files\content.outlook\uwwpnn0a\not_premier_mto_jan30_14_dft.docx
Ministry of Transportation (MTO) Meeting # 1
Highway 11 Realignment – Premier Gold Hardrock Mine Development / 160960900
Date/Time: January 30, 2014 / 2:00 PM
Place: Ministry of Transportation
Northwestern Region
615 South James Street
Thunder Bay
Next Meeting: TBD
Attendees: Amiel Blajchman Premier Gold, Director, Environment, Aboriginal, and
Community Affairs
Fiona Christiansen Stantec, Project Manager (Teleconference)
Gregg Cooke Stantec, Managing Principal, Transportation
Maya Caron Stantec, Senior Environmental Planner (Teleconference)
Absentees: N/A
Distribution: Internal
Item: Action:
1. The purpose of this meeting was to discuss the possible realignment of Highway 11 to accommodate the Premier Gold Hardrock Mine Development in Geraldton, Ontario, including the proposed environmental assessment process. Any issues discussed during that meeting that are anticipated to result in potential Project delays are highlighted in bold below.
2. Amiel Blajchman provided a brief overview of the overall study, and noted that Premier has elected to approach the study by following the relevant Class Environmental Assessment (EA) processes, including the MTO Class EA for Provincial Transportation Facilities. Ultimately a Federal EA will be completed to include the entire study, including the results of the highway realignment EA study. The MNR and MNDM Class EA processes will also be followed where relevant.
3. MTO noted that “recent” projects completed in the Region followed a voluntary individual EA process. MTO questioned if the Class EA process was “supported” by MOE. Premier confirmed that discussions with MOE are ongoing, however the choice of process is proponent driven.
4. A copy of the feasibility study route alternatives and the preliminary site plan for the mine (including the Mill and Open Pit areas) were provided for discussion. Premier has met with MTO previously to discuss the overall study. A Feasibility Study Report for the realignment of Highway 11 was previously provided to MTO.
January 30, 2014
Ministry of Transportation (MTO) Meeting # 1
Page 2 of 5
fc c:\users\fchristiansen\appdata\local\microsoft\windows\temporary internet files\content.outlook\uwwpnn0a\not_premier_mto_jan30_14_dft.docx
5. Gregg Cooke Provided a brief overview of the highway realignment feasibility study, and proposed MTO Class EA process.
6. Gregg Cooke noted that the scope of the proposed realignment would fall under the Group B MTO Class EA process. Generally Group A studies have more significant impacts (i.e. bypass communities). It is likely that this study would be considered to be a “significant” Group B project that would warrant the submission of a Study Design Report.
MTO noted that it is up to the proponent to determine the appropriate Class that should be followed under the MTO Class EA. MTO also confirmed that as they are not the proponent for this EA they will not formally “approve” the Class EA. The EA sign-off will generally occur at the end of the 30-day public review of the TESR. MTO’s input on the EA will be obtained through stakeholder consultation.
7. It was discussed that the EA study would be required to develop and evaluate a range of feasible route alternatives, with consideration for public and agency input, including the development of a range of preliminary evaluation criteria that will be reviewed by the public and agencies.
8. A separate process will be required to transfer the existing highway to the proponent, and to transfer the new highway to MTO. This process could be initiated in parallel with construction; however, will not be completed until construction is complete to MTO’s satisfaction, and the legal agreement has been executed. MTO noted that the acquisition process for the new highway and closure/transfer of the new highway could be lengthy. MNR may also need to be involved in the process associated with the old highway as the land was formerly Crown. Premier noted that the old highway is within the open pit footprint. This process will need to be confirmed by MTO.
9. An Order in Council will be required for both the closure of the existing highway and the designation of the new highway. This process could take 6 months, optimistically.
10. MTO noted that utility relocations can affect the construction schedule. Premier will be contacting utilities as part of the study to confirm impacts and relocation requirements.
11. Maya Caron noted that environmental specialist work would be completed to meet MTO Standards and Practices documents, similar to previous route planning studies.
12. Gregg Cooke requested input into the level of design requested by MTO to complete the EA, and noted that the alignment, profile, and cross-sections will be developed to a preliminary design level of detail to identify the grading footprint and the property requirements. Geotechnical and foundations work would generally be deferred to preliminary design, although some boreholes may be required to
January 30, 2014
Ministry of Transportation (MTO) Meeting # 1
Page 3 of 5
fc c:\users\fchristiansen\appdata\local\microsoft\windows\temporary internet files\content.outlook\uwwpnn0a\not_premier_mto_jan30_14_dft.docx
evaluate the alignment alternatives.
13. MTO noted that a Preliminary Design Report would be expected, including Design Criteria
14. MTO will confirm the scope required for the Traffic Impact Study
15. There was a discussion about the need to relocate the existing OPP Station. MTO noted that this process may be significant and OPP and IO will have a significant interest.
16. The following additional comments were provided by MTO during the meeting:
a. MTO will not approve the final results of the MTO Class EA Study (Transportation Environmental Study Report) since a Recommended Plan is ultimately approved if the process is followed – elements for MTO approval will include a legal agreement and design standards.
b. This region would not provide comments on the study process (unless a red flag issue is identified) but would participate as a key stakeholder.
c. The Recommended Plan must be designed and constructed in accordance with MTO standards.
d. A traffic impact study and drainage study will be required.
e. MTO may have a responsibility as the Crown to consult with first nation / aboriginal groups – MNDM may be the lead on behalf of the Crown for this element of the study. MTO noted that aboriginal consultation would be important during the Project; “inadequate” consultation could result in Project delays.
f. Generally there are no specific concerns with relocating the highway. However MTO noted potential concerns with regard to the Project schedule. They raised concerns with regard to the likely hood of a new highway being constructed and the old highway been closed by 2016.
g. Entrance permits for the mine and local road closures will be required.
h. A legal survey will ultimately be required for the new corridor.
17. During the meeting, the following questions were answered and responses were provided.
January 30, 2014
Ministry of Transportation (MTO) Meeting # 1
Page 4 of 5
fc c:\users\fchristiansen\appdata\local\microsoft\windows\temporary internet files\content.outlook\uwwpnn0a\not_premier_mto_jan30_14_dft.docx
Q. Did MOE agree to the proposed Class EA processes?
A. MOE has not indicated which process it prefers and noted that either the Individual EA or Class EA route could be followed. They have indicated that specific guidance will not be provided and that ultimately, Premier Gold should confirm that they are following the appropriate process. It was discussed that the risk with the Class EA route is that there is the potential for Part II Order requests, but that this process has general timelines associated within it (e.g. MOE has agreed to provide responses within 45 days). For a similar study, the Individual EA Terms of Reference (ToR) process lasted for approximately one year.
Q. How was the preliminary Preferred Route identified?
A. The identified route was based on a preliminary feasibility study and has not been vetted through the EA process. It considered geology, geography, cost, quantity estimates, and MTO design standards, at a conceptual level of detail. Environmental, public, and stakeholder input will be key components of the MTO Class EA.
Q. Will the proponent have any more discussions with MNR / MOE?
A. Ongoing meetings will be held.
Q. Is the Municipality of Geraldton aware of the study?
A. The proponent is meeting with the town next week.
Q. Is the land required for a future highway Crown Land?
A. This will be confirmed as part of the study.
Q. Will the highway be relocated to the identified tailings area?
A. A Contamination Overview Study will be conducted to identify potential contamination and materials testing will be required to determine suitability for highway construction. Arsenic may be a concern in this area. MTO noted that a plan would have to be in place to ensure that contamination would not enter the future highway right-of-way. MTO confirmed that they will likely not want to take ownership of a new highway built on historic tailings. Remediation should be considered. Premier noted that the current highway is already located on the historic tailings. It was noted that the existing highway was constructed on tailings.
January 30, 2014
Ministry of Transportation (MTO) Meeting # 1
Page 5 of 5
fc c:\users\fchristiansen\appdata\local\microsoft\windows\temporary internet files\content.outlook\uwwpnn0a\not_premier_mto_jan30_14_dft.docx
The meeting adjourned at 3:30 PM
The foregoing is considered to be a true and accurate record of all items discussed. If any discrepancies or inconsistencies are noted, please contact the writer immediately.
Stantec Consulting Ltd.
Maya Caron, B.Sc., MCIP, RPP, AVS Senior Environmental Planner Phone: 416-598-7162 Fax: 416- 596-6680
Page 1 of 3
TBT Engineering Limited 1918 Yonge Street., Thunder Bay, ON P7E 6T9 807-624-5160
MINUTES OF PROGRESS MEETING # 1
Premier Gold Mines Limited Highway 11 Realignment - Hardrock Mine Development
June 13, 2014 at 9:30 AM. EST – MTO Boardroom 2A
Teleconference Information Participant Code: 0587023
Dial-in Number: 1-866-384-4004 Attendees : Jim McKever MTO
Steve Sutch MTO Cindy Brown MTO Dick Dykstra MTO
Linda Kaszuba MTO Mike Satten MTO Matt Leavitt MTO
Patricia DeCal MTO Amiel Blajchman PG (Telecon)
Rob Frenette TBTE Doug Steele TBTE
Scott Peterson TBTE 1.0 Introductions and Roles
TBT Engineering chaired the meeting. An agenda was issued in advance of the meeting and identified the main topics of discussion. Three handouts were included for discussion purposes (Draft Map of Proposed Highway Realignment and Mine Infrastructure; a copy of the Initial Public Notice and a copy of the Group A MTO Class EA Study Stages and Phases). Introductions were made and Amiel Blajchman provided a brief overview of the Hardrock Gold Mine project and current status of the Federal and Provincial environmental assessments. Amiel indicated that Premier had just learned that a Federal Standard EA will be conducted. The draft EIS guidelines were expected to be ready by the current day (June 13) and finalized within 60 days.
i) Project Team
• Premier Gold Mines Limited (PG) is the Hardrock Gold Mine project proponent who will be undertaking and funding the necessary
Meeting Minutes – Progress Meeting No. 1 TBTE Ref. No.: 14-041 Highway 11 Realignment
Page 2 of 3
TBT Engineering Limited 1918 Yonge Street., Thunder Bay, ON P7E 6T9 807-624-5160
environmental assessments, design initiatives, and ultimately the construction of the mine site and proposed realignment of Highway 11.
• Stantec Consulting has been retained to complete the Federal Mine EA
and Provincial Class EA’s with the Ministry of Natural Resources (MNR) and Ministry of Northern Development of Mines and Forestry (MNDMF).
• TBT Engineering has been retained to complete the Ontario Ministry of
Transportation (MTO) Class EA. • G Mining is PG’s mine feasibility consultant.
ii) Stakeholders • MTO is the primary stakeholder for the proposed highway realignment
component of the mining study. • Municipality of Greenstone will be consulted as part of the MTO Class
EA.
2.0 Environmental i) EA Process
• The highway realignment portion of the mining study has been identified as a Group A Project for the MTO Class EA. MTO agreed with the designation level. TBTE and PG are in the process of finalizing the Study Design Report which will formalize the first stage of the planning phase for this Group A project. Action: TBTE
• A Notice of Study Commencement and Public Information Centre (PIC) advertisement was initially issued June 4, 2014 for the first of three planned open house consultations. The first round of PIC’s will be held within the Municipality of Greenstone in the communities of Geraldton, Longlac, and Nakina extending from June 24 to 26th.
• PG noted that the Ontario Ministry of the Environment (MOE) has provided comment in regards to their expectation of MTO’s involvement for the MTO Class EA process (reference to recent PG/STANTEC/MOE meeting). PG will share minutes of this meeting to MTO for review and follow-up with MOE.
Action: PG • MTO will advise of their understanding and level of engagement
for the MTO Class EA upon further internal review. Following which, a meeting with the MOE will be arranged. Action: MTO
ii) Study Stages and Phases
• PG and TBTE will follow the study stages as outlined by the MTO Class EA process for a Group A project.
Meeting Minutes – Progress Meeting No. 1 TBTE Ref. No.: 14-041 Highway 11 Realignment
Page 3 of 3
TBT Engineering Limited 1918 Yonge Street., Thunder Bay, ON P7E 6T9 807-624-5160
3.0 Engineering i) Highway Corridor
• The existing Highway 11 corridor/right-of-way (ROW) is 60 m in width. This should be the minimum acceptable width for realignment planning purposes, however; this is dependent upon MTO senior management approval.
ii) Highway Design Speed
• A design speed of 110 km/h was agreed to be appropriate for realignment planning studies, however; this also must be approved by MTO senior management.
iii) Aggregate Sources • PG indicated that they will have their own sources for aggregate
during construction activity.
4.0 Schedule • PG provided a general overview of the mine development
schedule, anticipating that Provincial EA’s would be complete by the end of 2014, detailed design activities would extend through 2015, with construction of the mine and new highway to begin mid 2016.
5.0 Action Items
• MTO provided a hardcopy of the property easement plan illustrating the location of the municipal water line which services MTO’s Patrol Yard on Highway 11, east of the intersection with Michael Powers Boulevard.
• It was confirmed that Cindy Brown will continue to be the principle point of contact for MTO.
• MTO requested that a meeting be arranged to present the proposed alignment options once available. Attendance would include MTO’s NWR senior management level. Action: PG & TBTE
• Consultation with First Nations – MTO will review roles and responsibilities with MNDMF. Action: MTO
6.0 New Business
Minutes Prepared By: Doug Steele/Scott Peterson TBTE
Page 1 of 3
TBT Engineering Limited 1918 Yonge Street., Thunder Bay, ON P7E 6T9 807-624-5160
DRAFT MINUTES OF PROGRESS MEETING # 2
Premier Gold Mines Limited Highway 11 Realignment - Hardrock Mine Development
July 10, 2014 at 1:30 PM. EST – MTO Boardroom 2A
Teleconference Information Participant Code: 0587023
Dial-in Number: 1-866-384-4004 Attendees : Jim McKever MTO
Steve Sutch MTO Cindy Brown MTO Dick Dykstra MTO
Patricia DeCal MTO Mike Grant MNDM Amiel Blajchman PG
Fiona Christiansen Stantec (Telecon) Rob Frenette TBTE Doug Steele TBTE
Scott Peterson TBTE 1.0 Introductions and Project Update
TBT Engineering chaired the meeting. An agenda was issued in advance of the meeting and identified the main topics of discussion. Two handouts were included for discussion purposes (Draft Map of Proposed Highway Realignment and Mine Infrastructure; a copy of the Draft PM#1 Meeting Minutes). In addition, two large size preliminary plans (one with aerial background) of the potential routes were brought for common viewing and left with MTO at the end of the meeting. Introductions were made and Amiel Blajchman provided a brief overview of the Hardrock Gold Mine project.
2.0 Environmental
i) MTO Involvement on EA Process • General discussion commenced around the current EA strategy
and MTO re-asserted that they are only a stakeholder and not the
Meeting Minutes – Progress Meeting No. 2 TBTE Ref. No.: 14-041 Highway 11 Realignment
Page 2 of 3
TBT Engineering Limited 1918 Yonge Street., Thunder Bay, ON P7E 6T9 807-624-5160
proponent of the highway realignment. The MOE and MTO have differing opinions on this issue and additional inter-agency meetings are forthcoming.
• At this point, MTO is not planning to issue any approval on the Class EA documentation provided, however; will review for comment as a stakeholder.
• MTO indicated that PG is taking a risk proceeding on the Class
EA as the agencies continue discussions on the MTO role. The MTO cannot confirm that the Class EA would not be re-commenced if at some point the MTO becomes the proponent of the highway project.
• The MTO indicated that PG may proceed to construct a “road” to
MTO design standard at their risk. MTO would not accept the proposed highway transfer until the other project EAs are completed and the transfer would require a legal agreement. MTO is to provide a template of this agreement to PG for review.
Action: JM at MTO
ii) MNDM Involvement • Mike Grant indicated that a Closure Plan may not be required for
the highway realignment, however; this would have to be discussed with the Director (Gordon Mackay). In any case, the Director would have to provide permission of some form regarding work on rehabilitated works (i.e. re-graded Macleod High Tailings). In addition, any rehabilitation work now would have to be completed to the current standards which changed in 2000. He acknowledges that they did not know much about the tailings and additional details about the tailings and work plan are required. He indicated that First Nations in the area will be concerned about environmental impacts associated with the construction and the historic tailings. There needs to be an up-to-date Tailings Characterization Report for agencies and stakeholders to utilize in upcoming decisions.
Action: PG
3.0 Engineering i) MTO Involvement on the Engineering
• MTO will actively participate in review of all engineering related documentation to ensure that design standards of the “road” will be acceptable for potential transfer to highway designation in the future.
ii) Highway Corridor
• The existing Highway 11 corridor/right-of-way (ROW) is 60 m in width. This is likely the acceptable width for realignment planning purposes, however; a 110 m corridor may be requested by MTO
Meeting Minutes – Progress Meeting No. 2 TBTE Ref. No.: 14-041 Highway 11 Realignment
Page 3 of 3
TBT Engineering Limited 1918 Yonge Street., Thunder Bay, ON P7E 6T9 807-624-5160
senior management. This would be discussed at an executive presentation.
iii) Presentation to MTO Senior Management
• PG requested when a presentation of the potential realignments could be made to MTO senior management. MTO subsequently confirmed that a meeting could be scheduled for the 21st of July.
iv) Construction Date • PG confirmed that that they would like to construct in 2016 if legal
transfer proceeds as anticipated (transfer estimated to take approximately 6 months).
4.0 Action Items
• MTO provided email and verbal comments on the Draft Minutes for PM#1 to TBTE. TBTE will await clarification of one point from MTO Geotech sent via email from Jim prior to finalizing the minutes.
Action:TBTE 5.0 New Business
Minutes Prepared By: Doug Steele/Scott Peterson TBTE
Page 1 of 3
TBT Engineering Limited 1918 Yonge Street., Thunder Bay, ON P7E 6T9 807-624-5160
MINUTES OF PROGRESS MEETING # 3
Premier Gold Mines Limited
Highway 11 Realignment - Hardrock Mine Development
July 21, 2014 at 10:30 AM. EST – MTO Millennium Boardroom
Teleconference Information Participant Code: 0587023
Dial-in Number: 1-866-384-4004 Attendees : Dan Schutte MTO
Doug Cooper MTO Michelle McGrath MTO Jim McKever MTO Wes Mound MTO Steve Sutch MTO
Iain Galloway MTO Marvin McNabb MTO Shawn Nickerson MTO Bertho Caron PG Rob Frenette TBTE Scott Peterson TBTE An executive summary was issued at the start of the meeting and TBTE provided an
overview of the past and present mine plans, transportation planning activities, and
engineering / design considerations for the proposed realignment of Highway 11. Large
size plans and profiles of the potential routes were brought for common viewing. Copies
of the executive summary and the presentation are attached.
The following summarizes discussion points and questions/comments raised during the
presentation.
1. MTO questioned the requirement / purpose for the 500 m buffer zone
surrounding the open pit. PG confirmed that a 500 m safety buffer zone is
required for open pit blasting operations.
Meeting Agenda – Progress Meeting No. 3 TBTE Ref. No.: 14-041 Highway 11 Realignment
Page 2 of 3
TBT Engineering Limited 1918 Yonge Street., Thunder Bay, ON P7E 6T9 807-624-5160
2. MTO questioned the limits reviewed for re-alignment options, more specifically
options available to the south. Given the natural features (lakes, rivers), nearby
community infrastructure, and historic mine workings in the area, no feasible
options were available to the south. A high level option to the north was
considered however resulted in a re-alignment length > 40 km.
3. Along the proposed alignments, each intersect some portion of muskeg / swamp
terrain. Preliminary boreholes indicate swamp depths in the order of 1 – 2 m.
4. All proposed alignment options transverse some length of existing MacLeod High
Tailings (MHT) which generally consist of silt and clay sized particles and are in a
loose to very loose condition. Option A & B traverse both of unconfined confined
tailings. Option D traverses primarily confined tailings. Subsequent stages of the
design process will require a detailed foundation study to investigate the in-situ
properties, design options, and evaluate ground improvement requirements for
the proposed surface infrastructure.
5. PG noted that impacted residential properties will be purchased by PG and there
are discussions in place regarding a new residential development.
6. All of the alignment options have some impact on the MTO Patrol Yard property
situated near the east connection limit. MTO will provide guidance as to a
preferred new Patrol Yard location. Action – MTO
7. MTO noted that the new Patrol Yard location would ideally have access to a
municipal water supply. PG noted that options may be available depending on
proximity to the municipal service line to the mine site.
8. MTO questioned whether the portion of new highway corridor which traverses the
MHT could have a reduced /limited ownership depth. Requires further
discussion.
9. MTO questioned the arrangement of recreational property (golf course) and if the
new highway would sever the property requiring access across the highway,
alternatively an underpass crossing may be considered. Requires further
discussion once the mine site plan is further developed.
10. All of the alignment options intersect Michael Powers Boulevard. MTO will
advise on intersection requirements. Action – MTO
Meeting Agenda – Progress Meeting No. 3 TBTE Ref. No.: 14-041 Highway 11 Realignment
Page 3 of 3
TBT Engineering Limited 1918 Yonge Street., Thunder Bay, ON P7E 6T9 807-624-5160
11. It was agreed by all parties that Alignment Option D has no fundamental
objections and could be carried forward to the next stages of preliminary design
and planning.
Meeting adjourned at 12:00 pm. Minutes Prepared By:
Scott Peterson TBTE Engineering Limited Distribution: All in attendance.
<Original signed by>