prefeasibility study for bishek report_kyrgyzstan.pdf · kara balta, a crossroad to the second...

51
Economic and Social Commission for Asia and the Pacific Promotion of Investment in the selected Asian Highway Routes in four countries (Bangladesh, Kyrgyzstan, Mongolia and Myanmar) Final Report Prefeasibility Study of Upgrading Bishkek Chaldovar Highway (AH5) in Kyrgyzstan

Upload: others

Post on 12-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

Economic and Social Commission for Asia and the Pacific

Promotion of Investment in the selected Asian Highway Routes

in four countries (Bangladesh, Kyrgyzstan, Mongolia and Myanmar)

Final Report

Prefeasibility Study of Upgrading Bishkek – Chaldovar

Highway (AH5) in Kyrgyzstan

Page 2: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

i

This study was undertaken with the financial assistance of

Korea Expressway Corporation

Bangkok

November 2014

Disclaimer

The analyses, findings, views and opinions expressed and arguments employed in the report are those of

the study team members involved with the prefeasibility study, and do not necessarily reflect the official

views of the ESCAP secretariat or of the Government of Kyrgyzstan.

The data and other information, analyses, and findings presented in the report are provided without

warranty of any kind, either express or implied, including their accuracy and completeness for investment

or for any other purpose. The user of the report specifically acknowledges the limitations of the study and

agrees that the use of any materials of the report is at the user’s sole risk.

The designations employed and the presentation of the material including on the maps in this report do

not imply the expression of any opinion whatsoever on the part of the Secretariat of the United Nations

concerning the legal status of any country territory, city or area or of its authorities, or concerning the

delimitation of its frontiers or boundaries.

Mention of firm names and commercial products does not imply the endorsement of the United Nations.

This report has been issued without formal editing.

Page 3: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

ii

Foreword

This prefeasibility study is based primarily on data that were readily available from various

secondary sources, including concerned government departments, and previous studies and reports. The

study itself did not commission any field study to complement data available from secondary sources. A

field trip was however undertaken by the study team mainly to understand the project’s physical and overall

development contexts, and the nature of its likely social and environmental impacts in broad terms. The

available data and information from secondary sources were mostly limited to physical (topographical and

cross-sectional), traffic flow, standard construction costs for different road construction items and some

socio-economic aspects. The study lacks any quantitative assessment of environmental and social impacts

based on surveyed data. However, some initial comments based on observations during the field trip are

included. Given the significance of environmental and social impacts of a road project, any future full-scale

feasibility study of the project should carefully investigate these impacts and consider suitable mitigation

measures through detailed field-level studies.

An attempt was made by the study team to understand the broader development contexts of the

project, including future potential benefits due to improved domestic and cross-border connectivity with the

neighboring countries. However, these understandings were mainly qualitative in nature (and reflected so in

narrative text in the report). A full-scale feasibility study may investigate this aspect further and examine how

the benefits of enhanced cross-border connectivity may be assessed and evaluated for use in a conventional

economic or investment analysis.

Page 4: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

iii

Abbreviations and Acronyms

AADT

AH

ADB

AHN

B/C

BCA

CAS

COS

CPS

CSP

DBST

EIA

EIP

ESCAP

GOK

GMS

IA

IEE

IR

IRR

KEC

MDB

MOTC

NPV

O/D

PCE

PPP

RSDS

SIP

TA

UNESCAP

VOC

WB

Annual Average Daily Traffic

Asian Highway

Asian Development Bank

Asian Highway Network

Benefit/Cost Ratio

Benefit Cost Analysis

Country Assistance Strategy

Country Operational Strategy

Country Partnership Strategy

Country Strategy and Program

Double Bituminous Surface Treatment

Environmental Impact Assessment

Environmental Investment Program

Economic and Social Commission for Asia and the Pacific

Government of Kyrgyzstan

Greater Mekong Sub-region

Implementation Agency

Initial Environmental Examination

Involuntary Resettlement

Internal Rate of Return

Korea Expressway Corporation

Multilateral Development Bank

Ministry of Transport and Communications

Net Present Value

Origin/Destination Survey

Passenger Car Equivalent

Public-Private Partnership

Road Sector Development Strategy

Social Investment Program

Technical Assistant

United Nations Economic and Social Commission for Asia and the Pacific

Vehicle Operating Cost

World Bank

Page 5: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

iv

Table of Contents

Foreword……………………………………………………………………………………….. ii

Abbreviations and Acronyms………………………………………………………………….. iii

Table of Contents……………………………………………………………………………… iv

Section 1 Introduction ......................................................................................................................................................................... 1 1.1 Background ................................................................................................................................................. 1

1.2 Project Description ..................................................................................................................................... 2

1.3 Methodology ............................................................................................................................................... 3

1.4 Study Team ................................................................................................................................................. 4

1.5 Limitation of the study (Recommendations for a formal feasibility study) ................................................ 4

Section 2 Data Survey and Review of Previous Studies ............................................................................................................... 6 2.1 Data Survey................................................................................................................................................. 6

2.2 Review of previous studies ......................................................................................................................... 6

Section 3 Development Plan and Socio-economic Characteristics ............................................................................................ 1 3.1 Development Plan (National and Regional Level) ..................................................................................... 1

3.2 Socio-economic Characteristics .................................................................................................................. 1

3.3 Road System Inventory ............................................................................................................................... 5

3.4 Asian Highway Network ............................................................................................................................. 6

Section 4 Technical Feasibility .......................................................................................................................................................... 8 4.1 Route Assessment ....................................................................................................................................... 8

4.2 Traffic Forecast ......................................................................................................................................... 12

4.3 Improvement Plan ..................................................................................................................................... 15

4.4 Cost Estimation ......................................................................................................................................... 15

Section 5 Economic Analysis ............................................................................................................................................................. 1 5.1 Methodology ............................................................................................................................................... 1

5.2 Benefit/Cost Analysis.................................................................................................................................. 2

5.3 Sensitivity Analysis ..................................................................................................................................... 6

Section 6 Environmental and Social Impact .................................................................................................................................. 7 6.1 Environmental Impact ................................................................................................................................. 7

6.2 Social Impact .............................................................................................................................................. 7

Section 7 Recommendation ................................................................................................................................................................ 8 7.1 Conclusion .................................................................................................................................................. 8

7.2 Recommendation ........................................................................................................................................ 8

7.3 Implementation Plan ................................................................................................................................... 9

Section 8 Alternative Scenario with high Traffic Volume .........................................................................................................10 8.1 Alternate Traffic Volume ........................................................................................................................... 10

8.2 Traffic Forecast ......................................................................................................................................... 10

8.3 Viability of the Project Road ..................................................................................................................... 11

Appendices Appendix A. List of persons met .............................................................................................................................. 13

Appendix B. Implementation Agency ....................................................................................................................... 14

Appendix C. Economic Analysis .............................................................................................................................. 14

Appendix D. Asian Highway Database (UNESCAP, 2010) ..................................................................................... 16

Appendix E. Asian highway Design Standard (1993) .............................................................................................. 19

Appendix F. Data Survey Request ............................................................................................................................ 20

Page 6: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in
Page 7: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

1

Section 1 INTRODUCTION

1.1 Background

Efforts have been made in recent years to assess the current level of investment and to identify

investment needs and priorities for the development, mainly upgrade of Asian Highway (AH) to the

required technical standard, of AH Network (AHN) including:

Priority Investment Needs for the development of the Asian Highway Network (2006,

UNESCAP)

Prefeasibility study of the selected routes (upgrading of priority routes) in Armenia,

Bangladesh, Mongolia and Myanmar (2007, UNESCAP)

Investment Forum (16 November 2007, UNESCAP)

To facilitate the promotion and development of AH investment, a second phase of prefeasibility study

of selected routes in Bangladesh, Kyrgyzstan, Mongolia and Myanmar is being implemented as an

ongoing effort by UNESCAP with the financial support from Korea Expressway Corporation (KEC).

ESCAP decided that study routes should be nominated by recipient countries considering a set of

given criteria reflecting their needs and overall strategic development contexts.

Figure 1. Asian Highway Network

Page 8: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

2

1.2 Project Description

Project Summary

The Ministry of Transport and Communications (MOTC), Kyrgyzstan, has proposed:

Capacity expansion of Bishkek-Kara Balta-Chaldovar section (92km) on AH5; and

Construction of a new PPP expressway (4 lanes) in parallel with the above mentioned project

from Bishkek to Kara Balta additionally during the meeting in Bishkek on July 5, 2012

It was noted that ADB intervention was already underway for the rehabilitation of Bishkek-Kara Balta

section.

Figure 2. Bishkek-Karabalta-Chaldovar section in Kyrgyzstan

Source: Based on AH Network (see Figure.1)

Strategic context of the project

1. Rehabilitation of Bishkek-Kara Balta-Chaldovar section (92km): This east-west corridor is in the

GOK’s top priority as well as north-south Bishkek-Torougart (AH61) and Kara Balta-Osh corridors. It

is one of the main arterials, which connects:

Bishkek, the Capital of Kyrgyzstan;

Kara Balta, a crossroad to the second largest city Osh; and

Chaldovar, a border to Kazakhstan.

It is AH Class I and II in light of AH classification and design standards and the main access to

Kazakhstan from this landlocked country.

The boundaries and names shown and the designations used on this map do not imply official endorsement or acceptance by the United Nations.

Page 9: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

3

2. Construction of a new Bishkek-Kara Balta highway (4 lanes) by PPP: The capacity of Bishkek-

Kara Balta corridor could be enhanced significantly with the new highway.

In 1988, Preliminary Design of the new road was done to enhance the capacity of the corridor as well

as to accommodate demand from neighboring Kazakhstan since it can be a short cut of A2 Highway

in Kazakhstan between the western and the eastern borderline of Kyrgyzstan at that time.

Considering the relatively low traffic volumes of the existing road and intervention made by ADB,

economic and financial viability of the new road, and the capacity expansion of the existing road,

should be explored carefully by a separate formal study. This new road can be listed in the long term

plan based on the level of traffic demand in the future. Three alternatives were identified and reviewed

as below:

Construction of new PPP road in Bishkek~Kara Balta section (MOTC proposal)

Widening of Kara Balta~Chaldovar section from 2 to 4 lanes

Overlay with partial repairs and improvement for Kara Balta~ Chaldovar section.

Due to the limited resources given including the budget of the study, within Bishkek-Kara Balata-

Chaldovar section, improvement of the remaining Kara Balta-Chaldovar section (2 lane, 32km) has

been studied as the main focus of this study.

1.3 Methodology

The overall approach of the prefeasibility study is represented diagrammatically in Figure 3 and

summarized as below. A simple trend analysis has been used for the future traffic forecasting due to

the limited availability of resources.

Figure 3. Prefeasibility Study Process

Page 10: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

4

1.4 Study Team

This prefeasibility study report has been issued by the Transport and Tourism Division, Economic and

Social Commission for Asia and the Pacific (ESCAP). The external consultant, Mr. Woohyun Kwon

has prepared the report with assistance from other consultants and ESCAP officials.

Mr. Hyunha Kwon and Mr. Byungryeol Kim from Naekyung Engineering, Korea, provided additional

assistance with the technical study, traffic forecast and economic evaluation. Mr. Mohammad Nurul

Amin (Deputy Secretary, Roads and Railway Division, MOC) provided relevant data and inputs as the

national expert.

1.5 Limitation of the study (Recommendations for a formal feasibility study)

1. Given the limited resources including the budget, this study has been conducted with the objective

of providing initial evaluation of the candidate route, which was proposed by the Government of

Kyrgyzstan (GOK), to facilitate the interventions from bilateral and/or multilateral donors. In this

regards, the limitation of this study and recommendations for a formal feasibility study are as follows:

The rationale review of the candidate route, which was suggested by the recipient county, and

an exploration of its alternatives have been omitted;

The output of the report is mainly relied on the information and data provided by GOK due to

the limited availability of information in English;

The route assessment for 92km long project was done during one-day site survey only while

thorough investigation of the site should be in place for the efficient planning/design and

estimation of quantities regarding the improvement plan;

Unit cost analysis instead of estimation of BOQ has been used in this study. Cost estimates of

the previous study and CPI, as an inflator, have been used; and

Page 11: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

5

The aerial photos from secondary sources were used for the review since the terrain maps

were not provided due to the national security concerns.

2. In countries with a low traffic demand such as Kyrgyzstan, traditional Benefit Cost Analysis may

not capture the need of infrastructure development properly. By the nature of traffic demand, a derived

secondary function of a variety of socio-economic activities and development plans, the output of the

traffic forecasting and economic analysis in Kyrgyzstan may be insignificant since the initial values of

major indicators including population (5.3million) and number of registered vehicles (318,581) arelow.

A holistic, instead of demand-driven, approach may be appropriate, if a higher priority was given for

the project by the government.

3. The economic viability of the project could have been enhanced considerably by the provision of

following information.

Socio-economic data/statistics including development plan of regions and transport facilities

in the catchments;

Per-unit data for economic analysis in the context of Kyrgyzstan including reduction of

traffic accidents and environmental benefits; and

Traffic survey data including O/D, network, sectional volumes, and travel speed

Page 12: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

6

Section 2 DATA SURVEY AND REVIEW OF PREVIOUS STUDIES

2.1 Data Survey

The project team requested the background materials for data collection in the form of a country

Report (Appendix F). National, regional and project level survey was done by the collection of

country report from project country, internet research, document review and field mission.

Major data collection and survey items are as follows:

A. National (and Regional) Outlook

Area, population, Currency and exchange rate

GDP/GRP, GDP per capita, Economic growth rate, Inflation rate, Employment rate by

sector

Trade (Import, Export), Major trade commodities, Major trade partners (Import, Export)

B. National & Sub-national strategy and priority

Road Master Plan, Regional & sub-regional Planning

Development and upgrading plan of AHN

Strategies and priorities

C. Implementation Agency (Road authority)

Organization

Implementation process including planning, design, construction and maintenance

D. Engineering data

Design specification

Road and bridge inventory

Traffic data (volume, O/D, travel speed, number of accident)

Unit construction cost(road, box & culvert, bridge, T/N)

Maintenance cost (Routine maintenance, periodic overlay)

Toll rate

Geotechnical and hydraulic survey

E. Socio-economic data

Social discount rate (%)

Passenger Car Equivalent (PCE), Vehicle occupancies, Number of registered Vehicles

Time Value, Vehicle Operating Cost (VOC)

GRP/GDP

Land use plan

2.2 Review of previous studies

Previous studies regarding AH were thoroughly reviewed and be incorporated as needed. Major

previous studies are as follows:

1. Priority Investment Needs for the development of the Asian Highway (AH) Network (2006, UNESCAP)

National priorities and intermodal connectivity have been identified as follows:

Status of AH network: Kyrgyzstan has a total 1,695km long AH network, among which

720km is below class III.

Traffic volume in Bishkek-Kara Balta was 20,976 AADT in 2006

Page 13: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

7

Priority investment needs: Bishkek-Torougart (AH61, 539km) and other sections (1,050km)

were identified as priority projects.

Intermodal connectivity: The importance of regional cooperation in improving the

intermodal connections of AH network to landlocked countries including Kyrgyzstan was

addressed.

2. CAREC Corridors (Central Asia Regional Economic Cooperation, ADB)

Four regional transport corridors passing through Kyrgyzstan was identified and prioritized.

CAREC 1: Europe-East Asia(Bishkek-Naryn-Torugart Road)

CAREC 2: The Mediterranean- East Asia (Osh-Sarytash-Irkeshtam Road)

CAREC 3: Russian Federation-Middle East-South Asia (Osh-Sarytash-Karamyk road)

CAREC 5: East Asia- Middle East-South Asia (Irkeshtam- Sarytash-Karamyk road)

3. Interim Strategy Note (ISN) FY 2012-2013 (June 2011, The World Bank)

In response to the internal conflict in 2010, ISN was prepared for the transition period of FY2012-

FY2013.

The ISN aims to partner the transition from recovery (Internal conflict in 2010), via

stabilization, to long-term sectoral development

In road transport, the government’s focus is on rehabilitating six strategic road corridors

Financing road maintenance at the required level remains a challenge

Support for the ongoing Bishkek and Osh Urban Infrastructure project (FY12) for the social

stability in the south.

4. Country Assistance Program Evaluation (CAPE, Aug 2012, ADB)

The CAPE covers three country strategies (i.e., the 1996–2003 COS, the 2004–2006 CSP, and the

2007–2010 JCSS)

The country has to overcome obstacles posed by the difficult topography (mountainous) and

isolation (landlocked) with a small population dispersed over a vast area (small domestic

market).

The importance of road rehabilitation and regional cooperation shall be recognized for rapid

growth.

By improving infrastructure and connectivity in the Bishkek-Osh road, Bishkek-Almaty

road, and Southern Transport Corridor road, regional trade and economic activities are

generated and isolation of the south has been reduced along the roadsides.

Page 14: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

8

Figure 4. ADB supported Road Projects in Kyrgyzstan

Source: Based on UN country map for Kyrgyzstan available at

http://www.un.org/Depts/Cartographic/map/profile/kyrgysta.pdf

The boundaries and names shown and the designations used on this map do not imply official endorsement or acceptance by the United Nations.

Page 15: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

1

Section 3 DEVELOPMENT PLAN AND SOCIO-ECONOMIC CHARACTERISTICS

3.1 Development Plan (National and Regional Level)

Not available

3.2 Socio-economic Characteristics

3.2.1 General

The Kyrgyz Republic is a landlocked country in Central Asia with a multi-ethnic population of 5.5million. It

is surrounded by China, Republic of Tajikistan, Republic of Uzbekistan, and Republic of Kazakhstan.

Figure 5. Location of Kyrgyzstan

Source: Same as in Figure 2.

Over 80% of the country is covered by mountains with the remainder made up of valleys and basins. The

climate varies regionally. The south-western Fergana Valley is subtropical and extremely hot in summer, with

temperatures reaching 40 °C. The northern foothills are temperate and the Tien Shan varies from dry

continental to polar climate, depending on elevation.

Figure 6. Topography of Kyrgyzstan

Source: Same as in Figure 2.

The boundaries and names shown and the designations used on this map do not imply official endorsement or acceptance by the United Nations.

The boundaries and names shown and the designations used on this map do not imply official endorsement or acceptance by the United Nations.

Page 16: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

2

The key Socio-economic indicators of Kyrgyzstan (World Bank, 2010) are as follows:

Surface Area: 200,000㎢

Population: 5.5 million

Population growth: 0.65%

Urban population: 35%

GDP: US $ 4,617 million

GDP growth: -1.4%

GNI: US $ 4.7 billion (Atlas method)

GNI per capita: US $880

Economic growth rate: 5.7% (ADB)

Consumer Price (Annual % change): 8.0%

Export : US $ 1,837 million

Import : US $ 3,354 million

Currency unit: Kyrgyz Som (KGS)

US $1=47.07KGS (effective as of Oct 3, 2012 )

3.2.2 Socio-economic characteristics

Population

The population of Republic of Kyrgyastan is 5.5 million (2010) with very low annual growth rate of 0.65%

since 2001.

Table 1. Population trend in Kyrgyzstan

Year 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011

Growth

Rate

(‘01~‘11)

Population

(thousand

person)

4,893.2 4,911.0 4,927.9 4,959.6 4,994.1 5,018.9 5,049.0 5,062.3 5,093.1 5,163.1 5,222.4 0.65%

Source) Kyrgyzstan Statistics committee Homepage, http://212.42.101.112/pxlocal/Database/STATRU/databasetree.asp

Figure 7. Population trend in Kyrgyzstan

4,700

4,800

4,900

5,000

5,100

5,200

5,300

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011

Population(Thousands)

Page 17: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

3

Regional distribution of Population

Kyrgyzstan’s Topography divides the population into two main segments, the north around Bishkek and the

south, mainly Oshskaya. The capital city Bishkek represents 890 thousand, 17% of the total population,

while Oshskava represents 1,026 thousand, 19.6% of the total population. The Chui region represents total

32.4% including Bishkek, Kara Balta-Chaldovar sections out of total population.

Figure 8. Regional distribution of population

Bishkek, 889.6

Osh, 240.9

Chui, 802.1

Talas, 224.6

Oshskaya area, 1026.2

Naryn, 249.7

Issyk-Kul region, 431.2

Jalal-Abad region, 965.4

Batken, 392.7

Table 2. Regional distribution of population

Region/City

2011 2010 2009

Populaion

(B) B/A

Populaion

(B) B/A

Populaion

(B) B/A

Bishkek 889.6 17.0% 876.3 17.0% 862.3 16.9%

Osh 240.9 4.6% 244.2 4.7% 243.1 4.8%

Chui 802.1 15.4% 795.4 15.4% 788.7 15.5%

Talas 224.6 4.3% 221.8 4.3% 219.1 4.3%

Oshskaya area 1026.2 19.6% 1013.2 19.6% 996.5 19.6%

Naryn 249.7 4.8% 246.9 4.8% 244.8 4.8%

Issyk-Kul region 431.2 8.3% 428 8.3% 424.4 8.3%

Jalal-Abad region 965.4 18.5% 951.9 18.4% 935.5 18.4%

Batken 392.7 7.5% 385.4 7.5% 378.7 7.4%

Total(A) 5,222.4 100.0% 5,163.1 100.0% 5,093.1 100.0%

Page 18: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

4

Number of Registered Vehicles

Kyrgyzstan represents relatively small number of registered vehicles, 315,002, in 2008. It is noted that

annual growth rate has increased sharply since 2007.

Table 3. Number of registered vehicles

Year 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008

Growth

Rate

(‘98~‘08)

# Vehicles 210,273 206,877 208,550 200,630 199,545 198,391 205,037 211,489 227,260 237,589 315,002 4.1%

Source: UNECE Transport Division Database

Figure 9. Number of registered vehicles

GDP

The annual growth rate of GDP represents 4.2% from 2001 to 2011.

(unit : Million 2000 US dollars)

Table 4. GDP trend (2000 Nominal price)

Year 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 Growth Rate

(‘01~‘11)

GDP 1,443 1,442 1,544 1,652 1,649 1,700 1,846 2,001 2,059 2,031 2,173 4.2%

Source: World Bank Data Homepage, http://data.worldbank.org/country/kyrgyz-republic

Page 19: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

5

Figure 10. GDP trend

3.3 Road System Inventory

The road network in the Kyrgyz Republic comprises 34,720 kilometers, 18,810 km of which are public roads

and 15,910 km are other roads.

Table 5. Summary of the Road Network (2007)

By Class International National Local Total

Length (km) 4,163 5,678 8,969 18,810

% 22 30 48 100

By Type Paved Gravel Earth Road Total

Length (km) 7,228 9,961 1,621 18,810

% 38 53 9 100

Source: Ministry of Transport and Communications, the Kyrgyz Republic

The development of road network was primarily done under the former Soviet Union. Due to a backlog in

road maintenance and insufficient funding in the past two decades, roads at all levels are deteriorating. The

Government of the Kyrgyz Republic has made an effort to improve the condition of major arterials through

Road Sector Development Strategy for 2007-2010 (RSDS) and collaboration with donors including CAREC

(Central Asia Regional Economic Cooperation, ADB).

Page 20: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

6

Figure 11. Major Arterials in Kyrgyzstan

Source: Based on UN country map for Kyrgyzstan available at

http://www.un.org/Depts/Cartographic/map/profile/banglade.pdf

Major arterials connect with neighboring countries are as follows:

Bishkek-Naryn-Torugart road connects Republic of Kyrgyz with China

Bishkek-Georgievka and Bishkek-Kara Balta-Chaldovar highways end in the borderline with

Kazakhstan eastward and westward, respectively.

Osh-Sary Tash-Karamyk road connects Tajikistan whereas Sary Tash-Irekstam road ends in the

borderline with China.

Osh-Bakten-Sulukta road connects Tajikistan

There are several roads connecting Uzbekistan.

All the roads are open for international traffic. The railway system, Balykchy-Tokmok-Bishkek-Kara Balta-

Chaldovar, also runs for Kazakhstan.

3.4 Asian Highway Network

The Asian Highway network in Kyrgyzstan consists of four routes, AH5, AH7, AH64, and AH65, as below.

Out of total 1,695km long AH, 309km (part of AH 61 and 65) is below the class Ⅲ standard.

The boundaries and names shown and the designations used on this map do not imply official endorsement or acceptance by the United Nations.

Page 21: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

7

Table 6. Current Status of AH network in Kyrgyzstan (2011)

AH No. AH5 AH7 AH61 AH65 Total (km)

Major cities

Georgievka-

Bishkek-

KaraBalta-

Chaldovar

Kara Balta-

Dzhalal Abad-

Uzghen-Osh

Bishkek-

Naryn-

Torugart

Osh-Sary Tash-

Irkestam

Sary Tash-

Karamyk

Grade Primary - - - - -

Ⅰ 60 - - - 60

Ⅱ 66 432 313 184 995

Ⅲ - 194 115 22 331

Below

Ⅲ - - 111 198 309

Other - - - - -

Total 126 626 539 404 1,695

Source: Asian Highway Database 2011, United Nations ESCAP

Figure 12. Asian Highway Routes in Kyrgyzstan

Source: United Nations, ESCAP

Page 22: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

8

Section 4 TECHNICAL FEASIBILITY

Technical viability of candidate route was assessed in terms of its geometry, alignment, traffic volume,

project cost and cross-border connectivity.

4.1 Route Assessment

4.1.1 Field Mission

A UNESCAP mission comprising Mr. Abdul Quium (UNESCAP), Mr. Woohyun Kwon (KEC), Mr. Hyunha

Kwon and Bongjung Kim (Naekyung Engineering) visited Kyrgyzstan from June 4 to 8, 2012. Meetings

were held with H.E. Abdyldaev Sheraly Itibaevich (Deputy Minister), Mr. Mamaev (Director of Investment

Projects Implementation Groups), Mr. Toktomambetor (Head of Road Management Department),

Mr. Temir Niyazbekov (Head of External Economic Relations Division) in the Ministry of Transportation

and Communication (MOTC).

The mission undertook a one day site visit to Bishkek-KaraBalta-Chaldovar (L=92km) on June 7, 2012. Mr.

Alibegashvili Levan Markovichi (Deputy Head of Design Institute, MOTC) and Ms. Yulia Amanbaeva

(Contract Administrator, MOTC) joined the mission.

The objectives of the mission were:

To identify the strategic context of the project;

To assess the road and traffic conditions; and

To identify social and environmental constraints, if any

The mission provided comments to MOTC to assist them with formulating investment proposal including

traffic forecast, economic analysis and safeguard during the meetings and a two day capacity building

workshop from June 5 to 6. The risk management of new PPP road proposal was also discussed in the light

of similar experiences elsewhere. The PPP road will lie parallel to the existing Bishkek-Kara Balta highways

to be widened shortly.

4.1.2 Review of road and traffic conditions

General

Alignment and traffic condition: The Bishkek-Kara Balta-Chaldovar section is 92 kilometers long, and passes

through a level terrain. The alignment is quite straight without steep gradients or sharp curves. The number

of lanes is four to six on Bishkek-Kara Balta section and two on Kara Balta-Chaldovar. The traffic volumes

(AADT) were about 7,198 and 2,650 vehicles per day, respectively in 2010.

Social and Environmental: From Bishkek to Kara Balta, several medium-sized cities are dispersed, and also

many resident buildings and various markets are located alongside of the road.

Geology: The project road was built on the huge alluvial fan from the mountainous region of Tien Shan, the

region forms the extensive rich black soil-belt like other countries in Central Asia. This may cause a uneven

settlement for the new road.

Pavement condition: The road was mostly paved with asphalt concrete and its surface condition of both

Bishkek-Kara Balta and Kara Balta-Chaldovar sections appear to be good except of several short sections. It

is noted that rehabilitation was done in 2007 (Bishkek-Kara Balta) and 1985 (Kara Balta-Chaldovar).

Page 23: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

9

1. Bishkek-Kara Balata section

Review of this 60km section was omitted since rehabilitation of Bishkek-Kara Balta section had already been

arranged by ADB’S CAREC Corridor 3 (Bishkek-Osh Road) Improvement Project, Phase 4.

ADB interventions: ADB is assisting GOK in rehabilitating 130km of Bishkek-Kara Balta (60km) and

Madaniyak to Jalabad (70km), which is a part of CAREC Corridor 3 (Bishkek-Osh Road) with an estimated

cost of $120 million.

PPP road construction: The MOTC expressed its desire to enhance the capacity of Bishkek-Kara Balta

corridor by providing new 4 lane highway during the meeting in Bishkek on July 5, 2012 with the mission.

Based on the preliminary design, which was done in 1988, the new road will run parallel to the project road,

approximately 5km northward. The road will be built on the current location of Chuy stream while the

stream would be relocated into an open concrete culvert to avoid uneven settlement issue. The rationale for

the relocation of the stream and construction of large scale open culvert may be revisited considering its

environmental impact and efficiency of construction.

Figure 13. Typical section of PPP road

Source: MOT, Kyrgyzstan

Preliminary traffic projection in terms of various toll rate and GDP growth is as follows:

The total traffic volume for both PPP road and existing road is less than 23,000 vehicles per day

The maximum traffic volume for each road is less than 20,000 vehicles per day.

It demonstrates that the financial viability of an additional PPP road may be slim in the near

term.

Page 24: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

10

Table 7. Traffic Projection in Bishkek ~ Kara Balta (Year 2044)

Toll rate for PPP road

(Som)

PPP road travel time (%) in

compare to existing road

Traffic Volume (2044, vehicle/day)

PPP road Existing Road

free 75.0% 16,174 6,607

10 84.2% 13,441 9,340

20 93.2% 11,163 11,618

30 102.3% 8,429 14,352

40 113.0% 5,695 17,086

50 120.5% 3,417 19,364

2. Kara Balta-Chaldovar section

The Kara Balta-Chaldovar section is 32km long, 2 lane highway and passes on the level terrain (Asian

Highway Class Ⅱ standard). It starts from a three-leg intersection and ends at Kazakhstan border.

The horizontal and vertical alignment comprises mostly straight without steep gradients or sharp curves. The

ROW is 30 to 50 meters with 7 to 14 meter carriageway and 1 to 2 meter shoulders. The traffic volume is

about 2,500 vehicles per day. No specific constraints were identified for the future widening since it passes a

dispersed settlement and farms mostly.

Road surface condition

It was built in 1955 and the latest rehabilitation was done in 1985. The overall surface condition is fair. Many

potholes and scaling were found and some aggregate separations were also identified. Remedies including

patching and overlay are needed to be done by thorough inspection.

Figure 14. Road surface condition

Page 25: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

11

Source: Study team

Railway crossing

There is an at-grade railway crossing at about 8 km station from Kara Balta. The frequency of the train is

relatively low; the passenger train runs between Bishkek and Lugovaya, Kazakhstan three times a day and

freight train also runs one or two times per day irregularly. Construction of a flyover is not needed.

It is highlighted that the angle of intersection between the road and railway forced to be changed from 25° to

50° just before the railway. Considering the insufficient sight distance due to relatively cute angle and future

development alongside the road, improvement of this at-grade section including better angle (75°) provision

was suggested. Impact of this improvement has been incorporated into the economic analysis by with and

without assessment.

Kara Balta bridge

The Kara Balta Bridge consists of two span slab bridge and one span pre-stressed concrete girder bridge

without any joint devices on the deck. The condition of deck surface pavement is good overall while bearings

need to be replaced based on the thorough investigation. Lots of fungus and stains were found on the surface

of all girders and piers, which need to be cleaned. No severe cracks were identified.

Figure 15. Deck surface pavement and substructure of Kara Balta bridge

Source: Study team

Cross drain pipe

In this region, only a few drain pipes are identified since there is very little precipitation, about 360㎜ a year.

A drain pipe installed on the downstream from a reservoir is shown below. The cross drain pipes are clogged

with soils and gravels due to a slope failure. Addition of wing wall and parapet at the inlet and outlet of pipe

would be beneficial to prevent clogging.

Figure 16. Clogged cross drain pipe

Page 26: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

12

Source: Study team

Safety furniture

Line markings and traffic signals, especially for major intersections and village area, are need to be installed.

Figure 17. Lack of Line marking

Source: Study team

4.2 Traffic Forecast

4.2.1 Current Traffic condition

The Asian Highway Database provides that the traffic volumes of Asian Highway No. 5 Bishkek~Kara Balta

(4 lane) and Kara Balta ~Chaldovar (2 lane) sections are from 7,198 and 2,650 vehicles/day in 2010

respectively. This corridor connects national capital Bishkek and is the main transportation and

communication link between Kyrgyzstan and Kazakhstan. It is also designated as a CAREC (Central Asia

Regional Cooperation) Corridor by ADB.

Table 8. Current traffic volumes in AH5 Bishkek~Kara Balta~Chaldovar (2010)

City/Town

Name at

Start Point

City/Town

Name at

End Point

Traffic Volume by Vehicle Type

Passenger

Car

Pick-up

Bus

Truck

Trailer

Motor-

cycle Total

Georgievka Bishkek 4,132 99 832 1,198 217 0 6,478

Bishkek Kara Balta 4,214 478 307 1,952 123 124 7,198

Kara Balta Chaldovar 1,318 0 354 854 124 0 2,650

Source: UNESCAP Asian Highway DATABASE,

http://www.unescap.org/ttdw/common/tis/ah/Member%20countries.asp

Page 27: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

13

4.2.2 Traffic forecast

Based on the current traffic volumes and traffic projection, widening of the project road was not considered.

Overlay with partial repairs and improvements were explored only.

Simple Trend Analysis

A simple trend analysis has been used for the future traffic forecasting considering the limited budget,

absence of comprehensive traffic database including traffic count and O/D survey and transport network data.

The annual growth rate of nominal GDP during last 7 years from 2001 to 20071 (5% per annum on average)

was used as an independent variable for the regression model of traffic forecasting considering the strong

correlation between traffic growth and GDP growth. The growth rate of registered number of vehicles (4.1%)

and population (0.65%) were also explored.

Traffic Projection of existing road

30 year traffic projection has been provided as below to synchronize the period of economic analysis from

year 2015 to 2044 considering 2-year construction periods from 2013 to 2014.

Table 9. Traffic projection in Kara Balta~Chaldovar

Section Year Passenger

Car Pick-up Bus Truck Trailer

Motor cycle

Total

Annual Average Growth

Rate

Bishkek- Kara Balta

2015 5,590 634 407 2,589 163 164 9,548

2019 6,691 759 487 3,099 195 197 11,429 4.6%

2024 8,067 915 588 3,737 235 237 13,779 3.8%

2029 9,443 1,071 688 4,374 276 278 16,129 3.2%

2034 10,819 1,227 788 5,011 316 318 18,480 2.8%

2039 12,195 1,383 888 5,649 356 359 20,830 2.4%

2044 13,571 1,539 989 6,286 396 399 23,180 2.2%

Kara Balta-

Chaldovar

2015 1,748 - 470 1,133 164 - 3,515

2019 2,093 - 562 1,356 197 - 4,208 4.6%

2024 2,523 - 678 1,635 237 - 5,073 3.8%

2029 2,953 - 793 1,914 278 - 5,938 3.2%

2034 3,384 - 909 2,192 318 - 6,803 2.8%

2039 3,814 - 1,024 2,471 359 - 7,669 2.4%

2044 4,244 - 1,140 2,750 399 - 8,534 2.2%

1 Year 2008 to 2010 were eliminated due to short term financial distress and internal conflict.

Page 28: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

14

Generalized cost and Diversion Curve

Considering the strong commitment for the new PPP road from MOTC, a diversion curve has been used to

forecast traffic diversion between the project road and new PPP road in the future (year 2044).

Figure 18. Diversion curve

Source) Xinhao Wang, Rainer vom Hofe, (2007) Research Methods in Urban and Regional Planning, Springer, 2007, p.373

Various toll rates were converted into an additional travel time as a penalty (generalized cost) for the traffic

assignment.

Table 10. An estimation of Generalized Cost

Classification Detail

Per capita GNI (US$) 920 (WB, 2011)

Annual workdays(days) 280

Average working hour for a day(hours) 8

Value of Time (US$/hour) 0.4107

(Som/Hour) 18.4815(1US$=45Som, Oct 2011)

Travel speeds for the two roads are used as follows:

Project road: 60km/h

PPP road: 80km/h considering an additional approaching/exiting time and toll collection time

Table 11. Comparison of travel time

Category Travel distance

(km) Travel Time

(minitue)

Toll rate Travel time + Generalized

cost(minutes) Toll rate (Som) Generalized cost (minute)

Project Road 60 60 - - 60

PPP Road 60 45

free - 45

10 5.5 50.5

20 10.9 55.9

30 16.4 61.4

Page 29: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

15

40 22.8 67.8

50 27.3 72.3

Traffic projection in Bishkek ~ Kara Balta section considering PPP road (2044)

Table 12. Traffic projection for both project road and PPP road

Toll rate for PPP road

(Som)

PPP road travel time (%) in

compare to existing road

Traffic Volume (2044, vehicle/day)

PPP road Existing Road

free 75.0% 16,174 6,607

10 84.2% 13,441 9,340

20 93.2% 11,163 11,618

30 102.3% 8,429 14,352

40 113.0% 5,695 17,086

50 120.5% 3,417 19,364

4.3 Improvement Plan

Summary of Current status

Based on the given information, discussion and site survey, major findings are as follows:

The project road represents Asian Highway Class I and II standard and overall alignment doesn’t

need to be improved.

Most sections run through flat terrain.

Rehabilitation of the Bishkek-Kara Balta is underway (ADB)

To address these challenges, upgrading plan was proposed as follows:

Alternative 1: Construction of new PPP road in Bishkek~Kara Balta section (MOTC proposal)

Alternative 2: Widening of Kara Balta~Chaldovar section from 2 to 4 lanes

Alternative 3: Overlay with partial repairs and improvement for Kara Balta~ Chaldovar section.

Economic viability of the 3rd

option (overlay with partial repairs), the lowest cost one, has been explored.

4.4 Cost Estimation

Unit cost estimation

Overall overlay with partial repairs and improvements were proposed considering the road and traffic

conditions and marginal economic viability. Thorough investigation is needed for the implementation. Due to

the absence of cost estimates including unit cost, cost estimates from other ADB projects in Kyrgyzstan were

used mainly as below.

Page 30: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

16

Table 13. Cost estimation

Contents Unit Unit cost

in USD Remarks

a. Pavement (Overlay) Km 168,000 Bishkek-Osh Project

b. Improvement of road Km 457,500 〃

c. Replacement of bearing EA 6,100 Similar project in Korea

d. Installation of wing wall at Pipe EA 1,050 〃

Note: Unit cost for Pavement and Improvement of road quoted Completion Report, "Kyrgyz Republic : Third Road

Rehabilitation Project", October 2008, ADB.

Quantity Estimation

Based on the site survey, the estimated quantities for the improvement of Kara Balta ~ Chaldovar section is

as below.

Table 14. Estimated Quantities

Contents of improvement plans Quantities Remarks

a. Pavement for the whole section 32km

b. Improvement at railway crossing 960m

c. Replacement of bearing of Kara Balta bridge 20EA

d. Installation wing wall and parapet for cross

drain pipe 2EA

Preliminary Cost Estimation

According to the above considerations, the preliminary projects costs are estimated as follows:

Table 15. Preliminary estimation of project cost

Work Name Unit Quantities Unit cost

(US $)

Cost

(US $ in thousand)

A. Base Cost

1. Civil Works

Page 31: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

17

a. Pavement km 32 168,000 5,376.0

b. Improvement of road2 km 0.96 457,500 439.2

c. Replacement of bearing EA 20 6,100 122.0

d. Installation of wing wall at Pipe EA 2 1,050 2.1

2. Consulting Services 36.5

Subtotal (A) 5,975.8

B. Contingencies

1. Physical Contingency 597.6

2. Price Contingency 280.9

Subtotal (B) 878.5

Total 6,854.3

2 Possible Land acquisition and resettlement costs have not been included

Page 32: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

1

Section 5 ECONOMIC ANALYSIS

5.1 Methodology

General

Economic feasibility will be reviewed by Benefit/Cost Analysis (BCA). Benefit Cost Analysis is a

calculation of the stream of both benefits and costs over the lifetime of the facility or strategy. Major indices

of BCA are as follows:

Internal Rate of Return (IRR): The ratio of the total discounted benefit to the total discounted cost

),....2,1(0)1(1

nir

CiBiN

ti

Net Present Value (NPV): The discounted value of the absolute welfare gain minus discounted

value of the investment over the whole life of the project

),....2,1()1(1

nid

CiBiNPV

N

ti

Benefit Cost ratio (B/C): The discount rate that equates the present value of a future stream of

benefits to the investment (Discount rate such that NPV=0)

N

ti

N

ti

nid

Ci

d

BiCB

11

),.....,2,1()1(

/)1(

/

Where, Ci = cost in year i, Bi= benefit in year i, i = year, N = project life, i = discount rate

Figure 19. Economic Analysis Process

Page 33: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

2

Evaluation Criteria

Internal Rate of Return (IRR) > Social Discount Rate

Benefit - Cost Ratio (B/C) > 1 (or 1.2)

Net Present Value (NPV) > 0

5.2 Benefit/Cost Analysis

5.2.1 Economic Analysis Criteria

Basic assumptions for the analysis are as follows:

Project road: Kara Balta – Chaldovar section (32km, 2 lane)

Construction period: 2 years (2013-2014)

Analysis period : 2015 ~ 2044 year (30 years after opening)

Discount rate : 12.0% (proposed value of ADB)

Basic Price: Market price in 2011

(Economic price, converted from market price, was used for the analysis)

5.2.2 Estimation of Costs

Construction (overlay with partial repair), maintenance and land compensation cost were estimated and used

for the analysis. For the economic analysis, the shadow price was calculated by eliminating taxes and

interests from the total costs.

Initial Cost

Construction cost was equally divided into first 2 years as below.

Table 16. Allocation of initial construction cost

Alternative 1: Including the improvement of Railway crossing

Year Initial Cost (US thousand dollars)

2013 3,427.15

2014 3,427.15

Total 6,854.30

Alternative 2: Excluding the improvement of Railway crossing

Year Initial Cost (US thousand dollars)

2013 3,175.25

2014 3,175.25

Total 6,350.50

Page 34: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

3

Maintenance Cost

It is assumed that the periodic maintenance shall be done in every 10 years and the cost of routine

maintenance is estimated as 10% of periodic maintenance work.

Table 17. Estimated Maintenance Cost

Contents Maintenance Cost(US thousand dollars)

Periodic 5,376.0

Routine 537.6

5.2.3 Estimation of Benefits

Vehicle Operation Cost Saving (VOCS)

The costs of operation of a selection of vehicle types, when used under a range of operating conditions can

be estimated by Vehicle Operating Cost models. Due to the absence of relevant data from Government of

Kyrgyzstan, Korean VOC model has been used. Vehicle types are modified in the context of Kyrgyzstan.

Table 18. Vehicle operating cost for vehicles under various speed (2009)

(Unit: Korean Won/km)

Speed(km/h) Passenger car Pick-up Bus Truck Trailer

10 440.40 384.62 758.41 601.31 856.25

20 356.45 307.64 606.76 463.47 678.65

30 302.56 256.91 498.49 395.27 573.27

40 258.87 222.01 424.54 343.42 505.78

50 227.08 200.79 379.76 314.02 457.58

60 209.93 187.20 353.58 296.70 432.27

70 198.03 179.51 339.52 290.20 419.52

80 186.08 176.21 332.23 292.85 417.90

90 180.47 179.53 330.49 308.11 440.10

100 178.57 190.10 339.93 347.08 465.02

110 179.54 384.62 363.26 - -

120 183.15 - 758.41 - -

Source: Guidelines for Transport project evaluation, 4th

edition (MLTM, 2011)

VOC model for this study was estimated by regression as below.

VOC = a + bV + c/V + d/V2

Where, VOC: VOC for vehicles under ideal conditions (Won/Veh-km)

V: Speed under ideal conditions (km/hr)

a,b,c,d: parameters

Page 35: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

4

Table 19. VOC model parameters

Vehicle type A b c d R2

Passenger car 400.734 -4.68767 1,172.673 0.024462 0.997121

Pick-up 690.8032 -9.26246 2,119.066 0.05802 0.996183

Bus 366.5035 -5.04615 933.398 0.033327 0.998794

Truck 551.848 -7.98578 1,653.167 0.059748 0.998844

Trailer 795.9204 -10.7247 2,215.565 0.075531 0.999495

Travel speed with and without the project were estimated as below.

Alternative 1 (with improvement of railway crossing): 50km/h and 60km/h before and after the

improvement for the whole section

Alternative 2 (without improvement of railway crossing): 50km/h and 60km/h before and after the

improvement for the whole section except the crossing section

Table 20. Per unit cost of VOC

(unit: won/km)

Speed Passenger car Pick-up Bus Truck Trailer Motorcycle3

60km/h 227.08 199.27 379.24 315.35 461.27 45.42

50km/h 250.96 216.18 415.11 334.99 492.82 50.19

VOCS benefit is as follows:

Table 21. VOC saving

(Unit: US thousand dollars/yr)

Year 2015 2024 2034 2044

Alternative 1 873.8 1,261.0 1,691.1 2,121.3

Alternative 2 847.6 1,223.1 1,640.4 2,057.7

Travel Time Saving

Due to lack of proper data in the context of Kyrgyzstan, GNI Per capita was used to estimate the value of

time (VOT) in Kyrgyzstan instead of average wage rate per various types of vehicles, which shall be used in

the Marginal Substitution method to value all activities. Experience demonstrates that approximately 30% of

Travel Time Savings could be used as a production inputs in developing countries. The output of VOT

estimation in Kyrgyzstan is as below.

3 For a per unit cost of motorcycle, 1/5 of passenger car was used considering its fuel efficiency.

Page 36: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

5

Table 22. VOT Calculation by GNI, Annual workdays and Average working hours

Classification Detail

Per capita GNI (USD) 920 (WB, 2011)

Annual workdays(days) 280

Average working hour for a day(hours) 8

% of Travel Time Savings can be used as a

Production inputs 30%

Per capita VOT (USD/hours) 0.1232

Table 23. Time Value of Passenger by Vehicle Types

(Unit: USD/ vehicle·hour)

Classification Passenger

car

Bus Truck Motor-cycle

Small large

Passenger4 2.3 10 18 1 1.5

VOT/vehicle 0.28336

1.232 2.2176 0.1232 0.1848

average VOT/vehicle 1.7248

The output of Travel time saving has been found very low comparing VOCS due to the level of income in

Kyrgyzstan

Table 24. Travel Time Saving

(Unit: US thousand dollars/yr)

Year 2015 2024 2034 2044

Alternative 1 57.0 82.3 110.4 138.5

Alternative 2 55.3 79.9 107.1 134.3

Other Benefits

Given the limited availability of data, only two user benefits including Vehicle Operating Cost (VOC) and

Travel Time Saving are used in this project. Other benefits can be considered are as follows:

Change in Externality Costs: Traffic accident, Environmental costs, Regional developments

Change in system operating costs and revenue

Co-benefits (CO2 emission reduction)

4 VIENTIANE 3'rd RING ROAD FEASIBILITY STUDY, December, 2008, Lao People's Democratic Republic

Page 37: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

6

5.2.4 Results of Economic Analysis

The output of economic analysis represents as below.

Table 25. Economic Analysis

Content Ÿ Alternative 1 Ÿ Alternative 2

B/C 0.746 0.753

NPV (USD 1,000) -2,465.3 -2,302.8

IRR 6.61% 6.59%

In terms of the evaluation criteria, the economic viability of the project is relatively low as below (Alt. 2).

Alternative without the improvement of railway crossing (Alt. 2) was selected as a representative of the

project since it would better to improve the crossing during future widening work.

Internal Rate of Return (IRR) = 6.59% < Social Discount Rate (12%)

Benefit - Cost Ratio (B/C) = 0.753 < 1

Net Present Value (NPV) =-2,302 < 0

5.3 Sensitivity Analysis

The sensitivity of economic analysis will be assessed by re-running B/C, NPV and IRR calculations for:

Total Benefits at +/- 10% and 20%

Total Costs at +/- 10% and 20%

Table 26. Sensitivity Analysis (Alternative 2)

Cost Indicator Benefit

0% -10% -20%

0%

B/C 0.753 0.678 0.603

NPV -2,302.8 -2,684.3 -3,312.6

IRR 6.59% 4.70% 2.60%

10%

B/C 0.685 0.616 0.548

NPV -2,890.0 -3,518.2 -4,146.5

IRR 4.88% 3.00% 0.89%

20%

B/C 0.628 0.565 0.502

NPV -3,723.8 -4,352.1 -4,980.4

IRR 3.32% 1.44% -0.70%

Page 38: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

7

Section 6 ENVIRONMENTAL AND SOCIAL IMPACT

6.1 Environmental Impact

For the project road, Environmental Safeguarding would not be triggered since no alignment change has

been proposed except the railway crossing section. Followings are the Environmental Categorization in

MDB guidelines.

Table 27. Environmental Categorization (ADB)

A

• Environmental Impact Assessment(EIA) report

• Environmental Management Plan including a budget

• Public consultation(at least twice)

• Disclosure 120 days in advance of Board Consideration

B • Initial Environmental Examination(IEE) report

• Public consultation

C • Review of Environmental Implications(No EIA or IEE is required)

FI

• Environmental Management System(Equity Investment)

• EMS including Environmental Assessment and Review Procedures

for Subprojects(Credit Lines)

However, for the PPP road in the future, the Environmental impact is needed to be assessed thoroughly since

it involves wide range of relocation of the stream, construction of open concrete culvert and 4 lane highways.

6.2 Social Impact

Approximately 20 households may need resettlement due to the improvement of railway crossing.

Women’s economic and social empowerment is essential in economic growth and poverty reduction. For

instance, Transport provides access employment, child care, education, health & political processes. Women

tend to make more complex and more trips than men. No specific gender issue has been identified since

connectivity is already there.

Social Safeguarding including Involuntary Resettlement (IR) and Gender Impact shall be assessed in terms

of National, World Bank and ADB guidelines during a formal study.

Page 39: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

8

Section 7 RECOMMENDATION

7.1 Conclusion

1. It is noted that the Bishkek~Kara Balta~Osh corridor is one of the major transport corridors in Kyrgyzstan.

ADB intervention has already been made for Bishkek~Kara Ballta~Osh rehabilitation project (CAREC

Corridor 3). Given this situation, three alternatives could be formulated for the proposed Bishkek~Kara

Balta~Chaldova section as follows:

Construction of new PPP road in Bishkek~Kara Balta section (MOTC proposal)

Widening of Kara Balta~Chaldovar section from 2 to 4 lanes

Overlay with partial repairs and improvement for Kara Balta~ Chaldovar section.

2. Traffic forecasting for 4-lane Bishkek~Kara Balta Corridor represents relatively low to moderate demand,

maximum 23,200 vehicles, in 2044. It means that further capacity enhancement for the Bishkek~Kara Balta

section may not be needed until 2044.

3. Economic viability of the 3rd

option (overlay with partial repairs, Alt. 2), the lowest cost one, has been

explored and its viability was found to be as follows:

Internal Rate of Return (IRR) = 6.59% < Social Discount Rate (12%)

Benefit - Cost Ratio (B/C) = 0.753 < 1

Net Present Value (NPV) = -2,302 < 0

It infers that the economic viability of other two options could be low since significant investments are

needed comparing to the 3rd

option.

7.2 Recommendation

Considering relatively low to moderate demand until year 2044 in Bishkek~Kara Balta~ Chaldovar corridor,

capacity enhancement could be done as follows:

1. AC overlay with partial repairs (Kara Balta-Chaldovar) is found to be the default option as a whole.

2. However, widening of Kara Balta~ Chaldovar section from 2 to 4 lane can be consideredto ensure the

consistency of the corridor

3. Secondly, prepare a new PPP road in Bishkek~Kara Balta section as demand in Bishkek~Kara Balta~Osh

corridor grows in the future.

Page 40: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

9

7.3 Implementation Plan

7.3.1 Preparation and Procurement

The output of this study was presented during an Investment Forum in October 2013 (Bangkok, UNESCAP)

for identification of major donors. Subsequently, project preparation, project appraisal, loan/credit

negotiations, loan/credit approval and signing will take minimum two years depending on the internal

process of multi-lateral or bi-lateral donors. Thereafter the procurement process may follow.

7.3.2 Implementation

The project area around Bishkek represents a humid, continental climate with:

Average 322 clear days per year due to its mountainous terrain

Average precipitation of 440 mm per year

Average daily temperatures range from −3 °C in January to about 25 °C in July.

Pavement works can be done for 7 months, from April to October in this regards.

Table 28. Implementation Plan

Work Item 1st Year 2nd Year

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Road improvement at railway crossing

Installation of concrete wing wall at Pipe

Overlay and partial repairs for the whole section

Cleaning girder and substructure of Kara Balta Bridge

Replacement of bearings of Kara Balta Bridge

Replacement of traffic signal

Line marking

Page 41: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

10

Section 8 ALTERNATIVE SCENARIO WITH HIGH TRAFFIC VOLUME

8.1 Alternate Traffic Volume

During Asian Highway Investment Forum in Bangkok (October 8-9, 2013), the study team was given the

updated traffic data from the concerned official in Kyrgyzstan. The new traffic volume count as of October

2013 is significantly, 5.8 times (Bishkek-Kara Balta), high compared with the previous traffic count data in

2010 which was provided earlier to the study team. It is noted that the change of traffic volume in Kara

Balta- Chaldovar section, the main focus of this study considering the intervention of ADB intervention for

Bishkek-Kara Balta, has been increased 1.33 times, which represents relatively lower than Bishkek-Kara

Balta section.

As per the given updates, the suggested PPP road (Bishkek-Kara Balta) may be financially viable while the

viability of widening (Alternative 1) or overlaying (Alternative 2) for Kara Balta~ Chaldovar section has not

been changed significantly.

However, it is highlighted that this very high increase in traffic volume count may need to be further

validated with reliable traffic studies and any decision on investment required to accommodate such high

volume of traffic may only be taken after further validation of traffic counts.

The results of this alternative traffic growth scenario are presented next.

8.2 Traffic Forecast

8.2.1 Current Traffic condition

Given the updated traffic data as of October 2013, the traffic volume of Bishkek-Kara Balta has significantly

been increased from 7,200 to 41,500, 580% increase within three years, vehicles per day.

Table 29. Current traffic volumes in AH5 Bishkek~Kara Balta~Chaldovar (2013)

City/Town

Name at

Start Point

City/Town

Name at

End Point

Traffic Volume by Vehicle Type

Passenger

Car

Pick-up

Bus

Truck

Trailer

Motor-

cycle Total*

Georgievka Bishkek 5,495 1,202 391 1,374 121 491 9,074

(6,478)

Bishkek Kara Balta 30,224 1,552 1,095 8,050 312 241 41,474

(7,198)

Kara Balta Chaldovar 1,760 978 157 470 0 155 3,520

(2,650)

* ( ): Traffic volume in 2010

Source: Roads and Railway Division, MOTC, Republic of Kyrgyzstan

8.2.2 Traffic forecast

Based on the suggested traffic volume, the traffic projection (year 2044) of Bishkek-Kara Balta has

significantly been increased from 23,180 to 111,682 vehicles per day while the one of Kara Balta-Chaldovar

has been increased, relatively low, from 8,534 to 9,479 vehicles per day.

Page 42: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

11

Table 30. Traffic projection in Bishkek~Kara Balta~Chaldovar

Section Year Passenge

r Car Pick-up Bus Truck Trailer

Motor cycle

Total

Annual Average Growth

Rate

Bishkek- Kara Balta

2015 33,525 1,721 1,215 8,929 346 267 46,004

2019 40,127 2,060 1,454 10,688 414 320 55,063 4.6%

2024 48,379 2,484 1,753 12,885 499 386 66,386 3.8%

2029 56,631 2,908 2,052 15,083 585 452 77,710 3.2%

2034 64,883 3,332 2,351 17,281 670 517 89,034 2.8%

2039 73,135 3,755 2,650 19,479 755 583 100,358 2.4%

2044 81,388 4,179 2,949 21,677 840 649 111,682 2.2%

Kara Balta-

Chaldovar

2015 1,952 1,085 174 521 0 172 3,904

2019 2,337 1,298 208 624 0 206 4,673 4.6%

2024 2,817 1,565 251 752 0 248 5,634 3.8%

2029 3,298 1,832 294 881 0 290 6,595 3.2%

2034 3,778 2,100 337 1,009 0 333 7,557 2.8%

2039 4,259 2,367 380 1,137 0 375 8,518 2.4%

2044 4,739 2,634 423 1,266 0 417 9,479 2.2%

8.3 Viability of the Project Road

New PPP road (Bishkek ~ Kara Balta)

Considering the strong commitment for the new PPP road from MOTC, a diversion curve has been used to

forecast traffic diversion between the project road and new PPP road in the future (year 2044).

Figure 20. Diversion curve

Source) Xinhao Wang, Rainer vom Hofe, (2007) Research Methods in Urban and Regional Planning, Springer, 2007, p.373

Page 43: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

12

The traffic forecast of PPP road represents possible viability based on the level of toll tariffs as below.

Table 31. Traffic projection for both project road and PPP road

Toll rate for PPP road

(Som)

PPP road travel time (%) in compare

to existing road

Traffic Volume (2044, vehicle/day)

PPP road Existing Road

Free 75.0% 79,294 32,388

10 84.2% 65,892 45,790

20 93.2% 54,724 56,958

30 102.3% 41,322 70,360

40 113.0% 27,920 83,762

50 120.5% 16,752 94,930

Project Road (Kara Balta - Chaldovar)

Based on the given updates, the viability of widening (Alternative 1) or overlaying (Alternative 2) for Kara

Balta~ Chaldovar section has slightly decreased. The B/C of Alt 1 and 2 represent 0.704 and 0.710

respectively. This is due party to the portion of Buses, which represents bigger benefits, has been decreased

from 13.4% to 4.5% while the one of Motorcycles has been increased from 0 to 4.4%.

Table 32. VOC saving

(Unit: US thousand dollars/yr)

Year 2015 2024 2034 2044

Alternative 1 835.6 1,205.8 1,617.2 2,028.5

Alternative 2 810.5 1,169.6 1,568.7 1,967.7

Table 33. Travel Time Saving

(Unit: US thousand dollars/yr)

Year 2015 2024 2034 2044

Alternative 1 42.2 60.9 81.6 102.4

Alternative 2 40.9 59.0 79.2 99.3

Table 34. Economic Analysis of Project Road

Content Ÿ Alternative 1 Ÿ Alternative 2

B/C 0.704 0.710

NPV (USD 1,000) -2,879.1 -2,704.2

IRR 5.59% 5.53%

Page 44: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

13

Appendices

Appendix A. List of persons met

MOTC

Mr. Abdyldaev Sheraly Itibaevich (Deputy Minister, MOTC)

Mr. Mamaev (Director of Investment Projects Implementation Groups, MOTC)

Mr. Toktomambetor (Head of Road Management Department, MOTC),

Mr. Temir Niyazbekov (Head of External Economic Relations Div. MOTC)

Ms. Marina S. Asankulova (Chief, Strategic Development and Investment, MOTC)

Mr. Alibegashvili Levan Markovichi (Deputy Head of Design Institute, MOTC)

Ms. Yulia Amanbaeva (Contract Administrator, MOTC)

Page 45: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

14

Appendix B. Implementation Agency

Appendix C. Economic Analysis

Alternative 1

discount rate 12.0% B/C 0.746

Page 46: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

15

Base Year 2011 NPV -2,465.3

IRR 6.61%

Unit:1,000US $

Year

Cost Benefit

CV PV VOCS Time saving VOCS+Time

saving PV

2013 3,427.2 2,732.1

2014 3,427.2 2,439.4

2015 537.6 341.7 873.8 57.0 930.9 591.6

2016 537.6 305.0 916.8 59.9 976.7 554.2

2017 537.6 272.4 959.8 62.7 1,022.5 518.0

2018 537.6 243.2 1,002.9 65.5 1,068.3 483.3

2019 537.6 217.1 1,045.9 68.3 1,114.2 450.0

2020 537.6 193.9 1,088.9 71.1 1,160.0 418.3

2021 537.6 173.1 1,131.9 73.9 1,205.8 388.2

2022 537.6 154.5 1,174.9 76.7 1,251.6 359.8

2023 537.6 138.0 1,217.9 79.5 1,297.5 333.0

2024 5,376.0 1,232.0 1,261.0 82.3 1,343.3 307.8

2025 537.6 110.0 1,304.0 85.1 1,389.1 284.2

2026 537.6 98.2 1,347.0 87.9 1,434.9 262.2

2027 537.6 87.7 1,390.0 90.7 1,480.8 241.5

2028 537.6 78.3 1,433.0 93.6 1,526.6 222.3

2029 537.6 69.9 1,476.1 96.4 1,572.4 204.5

2030 537.6 62.4 1,519.1 99.2 1,618.2 187.9

2031 537.6 55.7 1,562.1 102.0 1,664.1 172.5

2032 537.6 49.8 1,605.1 104.8 1,709.9 158.3

2033 537.6 44.4 1,648.1 107.6 1,755.7 145.1

2034 5,376.0 396.7 1,691.1 110.4 1,801.5 132.9

2035 537.6 35.4 1,734.2 113.2 1,847.4 121.7

2036 537.6 31.6 1,777.2 116.0 1,893.2 111.4

2037 537.6 28.2 1,820.2 118.8 1,939.0 101.8

2038 537.6 25.2 1,863.2 121.6 1,984.8 93.1

2039 537.6 22.5 1,906.2 124.4 2,030.7 85.0

2040 537.6 20.1 1,949.2 127.3 2,076.5 77.6

2041 537.6 17.9 1,992.3 130.1 2,122.3 70.8

2042 537.6 16.0 2,035.3 132.9 2,168.2 64.6

2043 537.6 14.3 2,078.3 135.7 2,214.0 58.9

2044 537.6 12.8 2,121.3 138.5 2,259.8 53.7

Total 32,659.1 9,719.7 44,926.8 2,933.0 47,859.8 7,254.4

Alternative 2

discount rate 12.0% B/C 0.753

Base Year 2011 NPV -2,302.8

IRR 6.59%

Unit:1,000US $

Page 47: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

16

Year

Cost Benefit

CV PV VOCS Time saving VOCS+Time

saving PV

2013 3,175.3 2,531.3

2014 3,175.3 2,260.1

2015 537.6 341.7 847.6 55.3 902.9 573.8

2016 537.6 305.0 889.3 58.1 947.4 537.6

2017 537.6 272.4 931.0 60.8 991.8 502.5

2018 537.6 243.2 972.8 63.5 1,036.3 468.8

2019 537.6 217.1 1,014.5 66.2 1,080.7 436.5

2020 537.6 193.9 1,056.2 69.0 1,125.2 405.8

2021 537.6 173.1 1,098.0 71.7 1,169.6 376.6

2022 537.6 154.5 1,139.7 74.4 1,214.1 349.0

2023 537.6 138.0 1,181.4 77.1 1,258.5 323.0

2024 5,376.0 1,232.0 1,223.1 79.9 1,303.0 298.6

2025 537.6 110.0 1,264.9 82.6 1,347.4 275.7

2026 537.6 98.2 1,306.6 85.3 1,391.9 254.3

2027 537.6 87.7 1,348.3 88.0 1,436.3 234.3

2028 537.6 78.3 1,390.0 90.7 1,480.8 215.7

2029 537.6 69.9 1,431.8 93.5 1,525.2 198.3

2030 537.6 62.4 1,473.5 96.2 1,569.7 182.3

2031 537.6 55.7 1,515.2 98.9 1,614.1 167.3

2032 537.6 49.8 1,557.0 101.6 1,658.6 153.5

2033 537.6 44.4 1,598.7 104.4 1,703.0 140.7

2034 5,376.0 396.7 1,640.4 107.1 1,747.5 128.9

2035 537.6 35.4 1,682.1 109.8 1,791.9 118.1

2036 537.6 31.6 1,723.9 112.5 1,836.4 108.0

2037 537.6 28.2 1,765.6 115.3 1,880.9 98.8

2038 537.6 25.2 1,807.3 118.0 1,925.3 90.3

2039 537.6 22.5 1,849.0 120.7 1,969.8 82.5

2040 537.6 20.1 1,890.8 123.4 2,014.2 75.3

2041 537.6 17.9 1,932.5 126.2 2,058.7 68.7

2042 537.6 16.0 1,974.2 128.9 2,103.1 62.7

2043 537.6 14.3 2,016.0 131.6 2,147.6 57.1

2044 537.6 12.8 2,057.7 134.3 2,192.0 52.1

Total 32,155.3 9,339.6 43,579.0 2,845.0 46,424.0 7,036.8

Appendix D. Asian Highway Database (UNESCAP, 2010)

1. Geometry and pavement type

Section Bishkek-Kara Balta Kara Balta-Chaldovar

Number of Lanes 2 - 32km

Page 48: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

17

4 53km -

6 7km -

Surface Type Asphalt Concrete 60km 26km

PM DB SB - 6km

Surface

Condition

Good 60km 32km

Bad - -

Terrain Flat Flat

Number of Major Intersections 3 5

Bridges Total No. 7 2

Total Length 96m 47m

Vertical Clearance < 4.5m No No

Design Load Below HS 20-44 No No

AH Design Standard Ⅰ, Ⅱ Ⅱ

Section Bishkek-Kara Balta Kara Balta-Chaldovar

Row Width 30-50m 60km 32km

Carriageway Width 7-14m - 32km

14m ≤ 60km -

Width of Median ≥1m 2km 0

1m < 8km 0

Type of Shoulder Hard 60km 32km

Shoulder Width ≥1m 0 0

(One Side) 1-2m 23km 32km

<2m 37km 0

Side Walk With 29km 18km

Without 31km 14km

Page 49: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

18

2. Traffic data

Section Bishkek-Kara Balta Kara Balta-Chaldovar

Year of Construction 1964 1955

Year of Rehabilitation Improvement 2007 1985

Traffic Volume Passenger Car 4,214 1,318

by Vehicle Types Pick-up 478 0

Bus 307 354

Truck 1,952 854

Trailer 123 124

Motor Cycle 37 0

Other 87 0

Non-Motorized 0 0

Traffic Accident No. of Accidents 15 -

No. of Fatalities 5 -

Number of Rest Areas 2 0

Number of Refueling Points 23 7

Remarks CAREC Corridor 1 CAREC Corridor 1, 3

Page 50: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

19

Appendix E. Asian highway Design Standard (1993)

Notes: Figures bracket are desirable values

Minimum horizontal curve shall be determined in conjunction with super-elevation

Page 51: Prefeasibility Study for Bishek Report_Kyrgyzstan.pdf · Kara Balta, a crossroad to the second largest city Osh; and Chaldovar, a border to Kazakhstan. It is AH Class I and II in

20

Appendix F. Data Survey Request

Section 1. General Information

1.1 National/Regional Outlook

Area, Population

Currency and exchange rate:

GDP/GRP/GNI, GDP/GNI per capita:

Economic growth rate, Inflation rate, Employment rate by sector

Trade (Import, Export), Major trade commodities, Major trade partners (Import, Export)

1.2 Traffic related information

Driving style: Left-hand side drive

International border crossing points (example)

Maximum gross weight and axle load permissible

Major Tourism spot

Section 2. Data Collection and Survey

2.1 Implementation Agency (Road authority)

Organization

Implementation process including planning, design, construction and maintenance

2.2 National & Sub-national strategy and priority, Guidelines

Road Master Plan

Regional & sub-regional Planning

Development and upgrading plan of AHN

Strategies and priorities

Design specification

2.3 Asian Highway Database – Any update of AHDB 2011(draft, Appendix 1) including:

Traffic data (volume, accident, etc.)

Road and bridge inventory

Toll rate

2.4 Other Engineering and Socio-economic data (Appendix 2) including

Social Discount Rate

Travel speed, Time value, Value of Time

O/D

Number of registered Vehicles

Land use plan

Unit construction cost(road, box & culvert, bridge, T/N)

Maintenance cost (Routine maintenance, periodic overlay)

Geotechnical and hydraulic survey

Appendices

Appendix 1. AHDB 2011(draft version to UNESCAP)

Appendix 2. Engineering & Socio-economic Data (attached)