pre-feasibility reportenvironmentclearance.nic.in/writereaddata/online/... · village : bongabari,...
TRANSCRIPT
Pre-Feasibility Report
Project Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Proponent Purulia Metal Casting (P) Ltd.
(Pig Iron Division)
Project Location Village : Bongabari
P.O. : Vivekanandanagar
District : Purulia
Pin : 723147
West Bengal
October 2016
Contents CHAPTER DESCRIPTION PAGE
1 Project Summary 1
2 Background Information 2
2.1 Project Rationale 2
2.2 Justification of the Proposed Project 2
2.3 Project Proponent 3
2.4 Project Site 3
3 Project Description 5
3.1 Project Facilities 5
3.2 Sinter Plant (12m2) 6
3.2.1 Raw Materials (Sinter Plant) 6
3.2.2 Manufacturing Process (Sinter Plant) 7
3.3 Mini Blast Furnace (65 m3) 8
3.3.1 Raw Materials (Mini Blast Furnace) 8
3.3.2 Manufacturing Process (Mini Blast Furnace) 9
3.4 Pig Casting Machine 9
3.5 Utilities & Services 10
3.5.1 Water Re-circulation System 10
3.5.2 Fuel Oil Storage & Distribution System 11
3.5.3 Compressed Air System 11
3.5.4 Laboratories & Quality Assurance System 11
3.5.5 Electrical Power Supply & Distribution System 12
3.5.6 De-dusting System 12
3.5.7 Internal Roads & Drainage 14
3.6 Main Plant & Equipment 14
4 Project Schedule 15
4.1 General 15
4.2 Steps Involved in Implementation 15
4.3 Project Implementation Schedule 15
4.4 Commissioning of Plant 16
4.5 Procurement of Equipment & Installation 16
4.6 Civil Work 16
4.7 Structural Steel Work 16
4.8 Equipment Erection 16
4.9 Wiring, Lighting, Water & Utilities Including Piping Works 17
4.10 Project Management 17
5 Manpower Requirement 18
6 Project Cost & Financial Analysis 19
6.1 Project Cost 19
6.2 Production Cost Estimate of Sinter 20
6.3 Production Cost Estimate of Molten Metal 21
Plant Layout 22
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 1
C H A P T E R 1 Project Summary
PROJECT SUMMARY
Proposed Project Mini Blast Furnace (65 m3) and Sinter Plant (12 m
2)
Project Proponent Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
Latitude : 23°21'1.72" N ; Longitude : 86°22'58.30" E
Main Plant
Unit
Production Capacity
Ton Per Day
Working Days
per Year
Product
Total Production
Ton Per Annum (TPA)
Mini Blast Furnace (65 m
3) 162.5 365 Molten Metal 59,310
Sinter Plant (12 m2) 300.0 170 Iron Ore Sinter 51,000
Product Pig Iron : 59,310 Ton Per Annum (TPA)
Raw Materials
Mini Blast Furnace (TPA) Sinter Plant (TPA)
1. Iron ore 47,450 1. Iron ore fines 40,800
2. Iron ore (Sinter) 50,415 2. Mill scale 6,630
3. Coke 41,518 3. Limestone 5,100
4. Limestone 6,524 4. Coke Breeze 3,060
5. Dolomite 6,524 5. Flue dust 1,530
6. Quartz 2,965 6. Return fines 21,420
Land Area Total Land : 5.0 Acres ; Proposed Greenbelt : 1.65 Acres
Project Cost Rs. 25.50 Crores
Pollution Control Cost
Capital Cost : Rs. 2.0 Crore ; Recurring Cost : Rs. 14.0 Lakhs / Annum
Make-up Water
Consumption Proposed Total : 345 KLD
(Mini Blast Furnace : 260 KLD ; Sinter Plant : 80 KLD : Domestic : 5 KLD)
Source : Supply Water, Borewell & Rain Water Harvesting
Power Requirement Total : 2,050 kVA ; Mini Blast Furnace : 1,500 kVA ; Sinter Plant : 550 kVA
Source : Damodar Valley Corporation (DVC)
D.G. Set : Mini Blast Furnace : 2 X 250 kVA ; Sinter Plant : 2 X 250 kVA
Manpower Proposed Total : 60
Air Pollution Control System
Source Pollution Control System
Mini Blast Furnace Dust Catcher, Dust Cyclone & Bag Filter
Sinter Plant Bag filter
Solid Waste
Blast Furnace Slag : 11,270 TPA will be used in cement plant.
Dust from Air Pollution Control System : 1,530 TPA will be recycled in the process.
Applicability of EIA Notification 2006
Category A [3(a) : Metallurgical Industry (Ferrous & Non Ferrous)]
Environmental Clearance is required from Expert Appraisal Committee (Industrial Projects –1), Ministry of Environment, Forest and Climate Change, Govt. of India, New Delhi.
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 2
C H A P T E R 2 Background Information
2.1 Project Rationale As one of the developing countries of the world, India has taken stride to up lift its industrial status in
multifarious disciplines in parity with the upr ising trend of economic growth rate all through the
world. In STEEL SECTOR all through the world a phenomenon growth is observed in last five years.
India is also in that league and has sustained more than 15% growth rate in this sector.
STEEL SECTOR in Eastern India worth special mention. Being one of the largest reservoirs of iron ore
this part of India has contributed the highest to this growth. In recent years many steel plants have
come up in this region. These helped, in turn, development of steel melting industries in this region.
Furthermore, the massive infra-structural development in the country has further boosted up local
demand of finished steel products. Such scenario attribute to the fact that a lot of entrepreneurs
coming forward to set up mini / midi steel plants of all known methods, continuous casting and rolling is
most effective. With recent growth of the rolling mill sector the gap is widened between demand and
supply. With the growing up of steel Industries in the Country, other supporting ancillary industries like
sponge iron and ferroalloy units are also coming up gradually. Also, with country’s infra-structural
development, requirement of building material like cement and reinforced bar is gaining momentum.
The product Pig Iron will be used in the Induction Furnaces as one of the raw materials.
2.2 Justification of the Proposed Project
1. The proposed plant will feature a Mini Blast Furnace (65 m3) and a Sinter Plant (12 m2).
2. Iron Ore Sinter will be produced in the Sinter Plant.
3. The feed to the Mini Blast Furnace will be sinter from Sinter Plant & fluxes etc. and liquid metal
will be produced in the Mini Blast Furnace.
4. The liquid metal from Mini Blast Furnace will cast in the Pig Casting Machine to produce Pig
Iron.
5. The major portion of Pig Iron will be used as a raw material to the Induction Furnace of the
existing Secondary Metallurgical Unit of Purulia Metal Casting (P) Ltd.
6. In the existing Secondary Metallurgical Unit the molten metal from induction furnace are being
charged to existing CCM & then to Rolling Mills.
7. The Project because of its nearness to the different industrial areas in Durgapur, Asansol and
Bokaro will benefit from basic infrastructure facilities such as good roads, water supply, power
lines and availability of raw materials for Sinter Plant and Mini Blast Furnace.
8. As the promoters are already established in the field of steel sector, major portion will be
consumed in house and rest of the materials will be sold to the other industries.
9. The process and the equipment will be selected in such a way that the product can meet most
of the international standard. This will help the company to bid for supplying steel to high
valued projects.
10. As the product Pig Iron will be for captive plant so as such there will be no issue of competition
and it will help to gain cost reduction substantially in the production.
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 3
2.3 Project Proponent Purulia Metal Casting (P) Ltd is a Private Limited Company, incorporated under the Companies Act,
1956 with the registrar of Companies, West Bengal. The registered office of the Company is situated at
4D1 & 4D2, 4th Floor, 31, Ganesh Chandra Avenue, Kolkata – 700013, West Bengal. The Directors are
Shri Goutam Kumar Sen and Shri Bhabani Prasad Mukherjee. There will also be very experience
professional those will run the Organization on day-to-day basis.
2.4 Project Site The project site for the proposed project Mini Blast Furnace (65 m3) & Sinter Plant (12 m2) is at Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal.
Purulia is the westernmost district of State of West Bengal. It acts as a gateway between the
developed industrial belts of West Bengal and Jharkhand. Midnapore, Bankura and Burdwan district of
West Bengal and Dhanbad, Bokaro, Hazaribagh, Ranchi, West Singbhum, East Singbhum district of
Jharkhand State bound this district.
The site is in close proximity of the substation within a distance of 2 km from where power shall be
provided at 33 kV to the proposed plant. It is well connected by road with Kolkata and other metropolis
of the country. The site is near to Durgapur, the well-recognized steel city of West Bengal. It can
therefore be seen that the site is ideally situated from the point of view of industrial infrastructure
facilities needed, management control, ancillary support and co-ordination with other unit of the
company.
Project Site : Latitude : 23°21'1.72" N ; Longitude : 86°22'58.30" E
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 4
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 5
C H A P T E R 3 Project Description
3.1 Project Facilities Purulia Metal Casting (P) Ltd. (Pig Iron Division) now have decided to go for setting up a Mini Blast
Furnace with 162.5 TPD capacity along with matching Sinter Plant of 300 TPD Capacity to produce Hot
Metal (i.e. Liquid pig iron). Hot Metal will be casted as solid Pig Iron in the Pig Casting Machine. The
salient feature of the plant capacity, general layout viz. storage and handling of the major input
materials and locations of the Mini Blast Furnace, Sinter Plant, Pig Casting Machine, Product Storage
Yard and De-dusting unit with respect to all the requisite facilities have discussed here. In developing
the plant general layout, the following factors have been taken into consideration:
Economical and uninterrupted receipt of incoming raw materials and supplies including inter
departmental dispatch of in process materials up to finishing stage and disposal of plant wastes with minimum counter flow of materials particularly inside the shops.
Logical location arrangement of production units, plant services and ancillary facilities to ensure minimum capital and operating costs both during the initial stage and future expansion.
Compactness of plant layout minimizing the distance of internal communications and inter plant handling of processing materials without sacrificing operational efficiency.
The plant general layout has been developed with rational disposition of production and auxiliary
facilities, plant utilities, services and ancillary buildings. A properly designed layout is essential for
operational efficiency, economical capital and production cost.
Mini Blast Furnace & Sinter Plant is a material intensive process, employing various plant and
equipment. To ensure an efficient and economically favourable operation, it is essential that the layout
of the shop provide easy access to all operational areas and unimpeded movement of input materials
and manufactured products. Unidirectional flow of materials is of consequence. The major production
facilities are receiving and storage of essential raw materials, such as iron ore, lime stone, dolomite,
coke breeze, fuel oil etc. and miscellaneous supplies.
The manufacturing facility of hot metal comprises of one (1) Mini Blast Furnace of 65 m3 capacity with
blast heating system, blowing system, raw material handling system, slag granulation system, ladle
preparation system, ladle transportation system, pig casting machine & auxiliary services with plant de-
dusting units. The Sinter Plant Comprises of one (1) 12 m2 Sinter machine, Raw material handling
system, Burden preparation unit, Mixer unit, Screening & crushing station, transportation of sinter to
Blast Furnace. This is supported by services and utilities for water and compressed air, electric power,
fuel, ancillary facilities ablution block, drainage, roads, sewerage, de-dusting etc. Taking the above
factors into consideration and major plant equipment involved in the process, general area layout has
been developed. The production facilities including storages of major input materials such as iron ore,
lime stone, dolomite, coke breeze, fuel oil, refractories, fuels etc. have been considered. Sinter shall be
kept in a storage shed for use in the Blast Furnace. The other materials received by trucks / tankers shall
be unloaded at the respective storage area.
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 6
3.2 Sinter Plant (12m2) Sinter Plants agglomerates iron ore fines with other fine materials at high temperature to create a
product that can be used in a Blast Furnace. The final product, a Sinter, is a small, irregular nodule of
iron mixed with small amounts of other minerals. The process, called sintering, causes the constituent
materials to fuse to make a single porous mass with little change in the chemical properties of the
ingredients. The purpose of sinter is to be used for converting iron into steel. The Technical
Parameters of 12 m2 Sinter Plant are :
Sinter Plant (12 m2)
Sl. No. Item Unit Index
1. Design Scale Set X m2 1 X 12 m2
2. Annular Sinter Machine
Effective Sintering Area m2 12
Usage Factor t/m2·hr 1.62
Working Days d 170
3. Working Days of Whole Plant d 170
4. Production per Day T 19.5
5. Working Hours per Day hr 20
6. Production per Day T 390
7. Screening Factor % 23
8. Final Production per Day T 300
9. Annual Production T 51,000
3.2.1 Raw Materials (Sinter Plant) Raw material will be required for sintering are Iron ore, Limestone and Coke Breeze. Apart from this,
Flue dust & Returns fines will be generated in the Sinter Plant itself. The requirement of raw materials
for production of iron ore sinter under the proposed technology are:
Details of Raw Materials for Sinter Plant (12 m2)
Sl. No.
Raw Materials Quantity Ton / Ton
Total Requirement
Ton per Day (TPD)
Total Requirement
Ton per Annum (TPA)
1. Iron Ore Fines 0.80 240 40,800
2. Mill Scale 0.13 39 6,630
3. Limestone 0.10 30 5,100
4. Coke Breeze 0.06 18 3,060
5. Flue Dust 0.03 9 1,530
6. Return Fines 0.42 126 21,420
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 7
3.2.2 Manufacturing Process (Sinter Plant) Iron ore (sinter) is the major raw material required for Blast Furnace. The raw materials (i.e.; Iron ore,
Limestone & Coke Breeze) will be received in the same ground hopper through dumpers. There will be a
Dust Suppression System above the ground hopper. The different raw materials will be received in cyclic
manner to avoid mixing. At the bottom of the hopper there will be a vibro-feeder which will discharge
the material in to a bifurcated chute with a flap gate. Through one leg of the chute Iron ore & Limestone
(flux) will be carried to a belt conveyor through the other leg Coke Breeze will be taken into screen. The
screen under flow will be discharged on a belt conveyor & the other size i.e. (+) 10 mm will be taken into
the Mini Blast Furnace raw material section. This conveyor will discharge into a trifurcated chute with
flap gates. Through one leg of this chute only Iron Ore will be carried to a reversible conveyor & finally
into 2 Raw material storage bin for Iron Ore fines. Through other legs of the chute Limestone & Coke
Breeze will be carried to two (2) dedicated crusher for Lime Stone & Coke Breeze through deflector
gates. Both of the crushed material will be discharged into a common vibrating screen. The undersized
crushed materials (-4mm) will be received in a reversible conveyor to deliver specific materials into their
dedicated storage bunker. The screen over size materials (+4mm) will be recycled through the crusher.
All the storage hoppers/ bunkers will have a weigh feeder at the bottom opening for exact quantity of
raw materials extraction into the conveyor which will discharge the material into a mixer. Little water is
added here to achieve proper micro pelletizing of the raw mix. The raw mix is then transferred to raw
mix bin through a conveyor. There are another two bins for Sinter bedding materials received through a
conveyor & Coke from a hopper. These are fed into the sinter machine through vibro feeder & conveyor.
Bedding materials is initially taken in sinter
machine for protection of machine grates.
Above this bedding raw mix is packed &
leveled. Finally a coke layer is spread
above raw mix for proper & uniform
burning. Burners are initially ignited by
LDO. After burning of raw mix is complete,
the total mix becomes Sinter.
The hot sinter is first crushed & then
conveyed to sinter cooler through
Conveyor. Air is blown to the sinter cooler
through a blower. The hot air passing out
of sinter cooler is de-dusted in a bag filter
before it is let out to atmosphere through
stack & ID fan.
The crushed cooled Sinter is then taken
into a double deck screen. The overflow is the final product which will stored in storage bin at Mini Blast
Furnace (MBF) area through conveyor. The under size of the screen is recycled to return fines bin
through another conveyor. The dust accumulated in the bag filter is also fed to return fines bin through
conveyor.
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 8
3.3 Mini Blast Furnace (65 m3) The purpose of a Mini Blast Furnace is to chemically reduce and physically convert iron oxides into liquid
iron called ‘hot Metal’. The Blast Furnace is a huge, steel stack lined with refractory brick, where raw
material from stock house are dumped into the top and preheated air is blown into the bottom. The raw
materials require 6 to 8 hours to descend to the bottom of the furnace where they become the final
product as liquid slag and liquid iron. These liquid products are drained from the furnace at regular
intervals. The hot air that was blown into the bottom of the furnace ascends to the top in 6 to 8 seconds
after going through numerous chemical reactions.
Purulia Metal Casting (P) Ltd. (Pig Iron Division) has decided to install and commission a 65 m3 Mini
Blast Furnace. Technical Parameters of 65 m3 Mini Blast Furnace are :
Mini Blast Furnace (65 m3)
1. Design Volume of Mini Blast Furnace 65 m3
3. Productivity on working vol. T/d/m3 2.5
4. Available working day in a year 365
5. Annual production T (Hot Metal) 59,310
7. B F Slag generation (TPA) 11,270
8. Hot Blast Flow 13,500 Nm3/ hr
9. Hot Blast Pressure (Bustle Pr.) 1 - 1.1 kg/cm2
10. Hot Blast Temperature 1000 - 1200 oC
11. Furnace Top pressure 0.3 - 0.4 kg/cm2
3.3.1 Raw Materials (Mini Blast Furnace) The raw material required for producing molten metal is iron ore, sinter, limestone, dolomite, coke,
quartz. The requirement of raw-materials for production of steel under the proposed technology are :
Details of Raw Materials for Mini Blast Furnace (65 m3)
Sl. No.
Raw Material Quantity Ton per Ton
Total Requirement
Ton per Day (TPD)
Total Requirement
Ton per Annum (TPA)
1. Iron Ore 0.80 T 130 47,450
2. Iron Ore Sinter 0.85 T 138 50,415
3. Coke 0.70 T 114 41,518
4. Limestone 0.11 T 18 6,524
5. Dolomite 0.11 T 18 6,524
6. Quartz 0.05 T 8 2,965
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 9
3.3.2 Manufacturing Process (Mini Blast Furnace) Iron ore, Lime Stone, Dolomite, Coke will be stored in a stockyard and from where the same will be feed
to a ground hopper by pay loader. Below the ground hopper there will be extractor which will discharge
the material to a conveyor. This conveyor will feed to the tripper conveyor in a junction house. Product
sinter from Sinter Plant will feed to the tripper conveyor through sinter conveyor. Over size coke from
Sinter Plant will also feed to this tripper conveyor. The tripper conveyor will discharge material to
twelve numbers day bins (in stock house measuring 25 m X 9 m wide double bay in construction. From
the day bins the same will feed to a conveyor through vibrating screens / vibro feeders. This conveyor
will feed another conveyor which will feed the material to Mini Blast Furnace.
The Fe content of iron ore should
preferably be 30% and 35% iron ore
(sinter) and above with a Laterite content
under 10%, in respect of coke, fixed
carbon should be 75% or higher with ash
not more than 25%. Limestone, which is
used desulfurizing agent should have CaO
contents> 45%. The charge mix is an
important part of the Blast Furnace. The
success of production process in the
furnace mostly depends on it. Another
product of the iron making process, in
addition to molten iron and slag is hot
dirty gas. These gases exit the top of the
Mini Blast Furnace and proceed through
gas cleaning equipment where particulate
matter is removed from the gas and gas is cooled.
This gas has a considerable energy value. So it is burnt as a fuel in the ‘Hot Blat Stoves’ which are used
to preheat the air entering the Mini Blast Furnace to become ‘’Hot Blast’’ and turbo blower that
generates the compressed air known as ‘Cold Blast’ that comes to the stoves. After the hot gas back to
the blast furnace and dirty air out of the stove into a stack. The slag from the Mini Blast Furnace will be
guided to a water pond with a ramp. The guide channel for the slag will be lined with heat resistance
bricks. The hot slag when comes in contact with the water in the pond become granulated. The
granulated slag will be periodically removed mechanically / manually and will be sold to Cement Plant.
3.4 Pig Casting Machine Hot metal produces in the Mini Blast Furnace, whenever not used directly in the steel melting shop is
cast into pig iron in the Pig Casting Machine (PCM) to small pieces. Small sizes of pig iron pieces are
produced in PCM by pouring the hot metal into the mould having small pockets. There the hot metal is
solidified by cooling with air followed by water cooling. The PCM stand is an endless chain carrying the
pig moulds. The strands are placed at an inclination. The level of the inclination is decided on the height
required for receiving the hot metal and for discharging the cast Pig Iron into the car.
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 10
3.5 Utilities & Services The utilities and services comprise the electric power supply and distribution, water supply and re-
circulation system, compressed air and fuel oil storage and distribution system, etc. and these are
suitably located with respect to their storage facilities and specific uses in the shop.
3.5.1 Water Re-circulation System Suitable water circulation system for production units have been duly considered as per requirement.
Water system for Mini Blast Furnace shell cooling, water seal of Sinter Machine, Mixer and Dust
Suppression System comes under one circuit because of water quality as well as terminal pressure also.
One separate circuit has been considered for hydraulic valves, blowers for cooling. A common pump
room measuring 12m X 8m has been planned to accommodate all the pumps, cooling tower necessary to
run the circulation system.
All the reservoirs will be of RCC construction and the pump room will be brick building with R.C. roofing.
One (1) PVC construction overhead reservoir has been considered for feeding water during emergency
to different consuming sectors. Compressors will be housed in a compressor room. While developing the
system design for mechanical utilities and electrical services as mentioned above, various guiding
factors, viz. sources of availability, storage, consumption, terminal condition and losses in circulation as
required by individual services have been duly considered. Water is required for cooling of different equipment and components of the above production units. To
economize consumption of water it is proposed to adopt a re-circulation system for different circuits,
which enables re-use of water in-cycle and replenishing the losses by feeding make up water in the
circuit. Considering operational requirement, duly condition involved in different re-circulation systems
have been proposed as raw water for Mini Blast Furnace shell cooling, Sinter Machine, Mixer & Plant De-
Dusting Unit and soft water for hydraulic valves & blowers. Source of make-up water supply and storage of the same for all the above system have been made
common. Quantity of water in circulation, quality required, terminal pressure related to different service
points are given in the Table.
Equipment Quality
Quantity in Circulation
(m3/hr)
Terminal Pressure
Kg./cm2g
Rate of
Loss
(%)
Make up Feed
(m3/hr)
A. Raw Water Clear suffered 230 4.0 2.83 6.51
B. Soft Water Dematerialized water 285 4.0 1.00 2.85
C. Domestic water Clear & chlorinated 5 - - 5.00
Total 14.36
Total Make-up Water Consumption = 345 KLD
It is apparent from the above table that the continuous supply of make-up water to compensate the
losses will be required at 14.36 m3/ hr. i.e. 345 KLD.
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 11
System Description : The water system will have two circuits, one for cooling of hydraulic valve system
& other for Blower House. This closed circuit will require soft water. The other circuit for MBF shell
cooling with raw water. Raw water will also be required for Dust suppression, Sinter mixer & water seal
of Sinter Machine. Raw water at the battery limit will be collected in raw water reservoir. There will be
two pumps (1W+1S) with valves, reducers etc. which pump water from this reservoir. The pumped out
water will be distributed to the circuit 1 & 2.
Circuit-1 for Soft Water : The raw water will be fed to a RO Plant for softening & the soft water will be
collected in water tank. Two pumps each with valves & reducers are connected to the soft water tank.
The pumps (1W+1S) will pump soft water to Hydraulic Station & House, all for cooling purpose. The hot
water outlet from Hydraulic Station & Blower House will be collected in hot water tank from where the
hot water will be pumped to the cooling tower tank & back to soft water tank.
Circuit-2 for Raw Water : The raw water by pump will be taken to hot water tank in circuit 2 (as make
up after initial filling). From here raw water will be pumped to the cooling tower in this circuit. The cold
water from cooling tower basin will be pumped (1W+1S) for MBF shell cooling & hot water will be
collected back in the hot water tank. One pump will be pumping water to emergency overhead tank.
Another part of raw water will be directly given for dust suppression in Sinter Mixer Machine & Sinter
Machine. Blow down from RO Plant, soft water tank, circuit-2, cold water tank & hot water tank will all
be collected in the slag granulation pond.
Emergency Supply of Cooling Water : With a view to maintain continuity in supply of water during
power failure, an overhead tank has been provided in the system design to combat the emergency
situation. Certain important zones of Mini Blast Furnace shell cooling system comes under purview of
such emergency feeding of cooling water under gravity from the overhead water tank.
Drinking & Sanitary Water System : Drinking and sanitary water system has been separately considered
in this project. For this purpose water of required quantity will be supplied from raw water reservoir to
the Iron removal Filter and will by-pass softening plant. The filtered water will thereafter be supplied
the tip of overhead tank through chlorination Plant. From the overhead tank drinking and sanitary water
will be supplied to different service terminals under gravity.
3.5.2 Fuel Oil Storage & Distribution System LDO will be required for Sinter Machine Burners in Sinter Plant and Stove Burners in Mini Blast Furnace. The LDO system will comprise of fuel tank, dual fuel burners, pumps, storage tank, distribution pipelines, valves, fittings, instruments, pressure regulations at service terminals and accessories.
3.5.3 Compressed Air System Compressed air shall be required for the pneumatic systems used in Sinter Plant & Mini Blast Furnace
area and general cleaning purposes. To meet the requirement of compressed air, two air compressors of
100 cfm at 100 psig complete with after cooler and a common air receiver has been considered.
3.5.4 Laboratories & Quality Assurance System Equipment in Chemical & Physical Laboratory will be provided for Quality Assurance System.
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 12
3.5.5 Electrical Power Supply & Distribution System The power supply at 33 kV, 50 Hz. 3 phase overhead supply will be available from utility. 33 kV power
will receive by 2.5 MVA, 33/0.433 kV power transformer. Diesel Generator set of 2 X 250 kVA for Mini
Blast Furnace and 2 X 250 kVA for Sinter Plant are intended to cater to emergency loads during power
failure/ restricted periods. 33 kV supply from utility substation will be received to the blast furnace &
stove unit. Power Transformer of rating 33/0.433 kV, 2.5 MVA will convert power to 433 Volt level &
feed to Main LT panel via LT bus duct.
3.5.6 De-dusting System
Sinter Plant
Bag Filter : There will be suction hoods in all transfer points of conveyors, hoppers, chutes in stock
house building, mixing building, sinter machine building and junction houses. The dust generated in all
transfer points will be sucked by suction hoods and will transfer to the filter bags, so they are remained
on the surface of the bags and then the clean flue gas sent to stack of 30 meter height through ID fan.
With the procession of the dust remover, dust remained on the surface of the filter bags become more
and more, the resistance of the bags increases, when the resistance of the bags reaches upper
threshold, the system will open the purge-valve automatically in order to send the cleaning gas into the
pressure static box, which makes the filter bags changed from a state of deflated to a state of expansion
so that the dust absorbed on the surface of the filter bags will fall into the dust hopper at the bottom of
the box and the dust in the hopper will be cleaned by the ash valve. When the resistance of the filter
bags reaches down threshold, the system will close the purge-valve to stop cleaning, as so the dust
remover works again. Maximum filtering rate is 1.0 - 1.5 m3/minute and the gas temperature is 50 OC.
The dust content in the flue gas through the stack will be < 50 mg/Nm3. Service life of fabric bags is
generally up to two years.
Mini Blast Furnace
Dust Catcher : Gas cleaning is based on the gravity separation principle and is used for the removal of
large particles of the dust. It is the dry separation of dust particles in the Mini Blast Furnace top gas
before Bag Filter and is commonly done by a gravity dust catcher. In this stage all the coarser particles
are removed. The objective is to remove as much dust as possible in a dry condition for reuse and
recycling. The dust removal efficiency of the separator is dependent on the particle size distribution, on
the separation mechanism (i.e. gravitational or centrifugal force) and, to a lesser degree, on the inlet
dust loading. The separated dust is normally of size greater than 10 micrometers and is collected in the
dust storage hopper, which is usually sized for one and half days of dust accumulation, and emptied via
a dust discharge system. The dust catcher is a large cylindrical structure normally with a large diameter
and with the required height. It is usually lined to insulate it and prevent the condensation of moisture
in MBF gas so that the dust remains dry and does not ball up and flow freely into the conical portion of
the dust catcher at its bottom for its periodical removal.
The gas is sent to the dust catcher by a single down comer and enters through the top by a vertical pipe
that carries the gas downward inside the dust catcher. This pipe flares at its lower extremity like an
inverted funnel, so that as the gas passes downward its velocity (and thus its dust carrying potential)
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 13
decreases, and most of the coarser dust drops out of the gas stream and is deposited in the cone at the
bottom of the dust catcher. Since the bottom of the dust catcher is closed, and the gas outlet is near the
top, the direction of the travel of the gas must reverse 180 OC. This sudden reversal in the direction of
flow causes more of the dust to get settle down.
Dust Cyclone : In the cyclone dust catcher the raw Mini Blast Furnace gas is introduced by one or two
tangential inlets with a velocity to force the dust particles to the wall and separate them from the gas
stream. The cyclone dust catcher can have different type of internal construction. One type of cyclone is
completely empty, while other type has a complicated inlet dome and replaceable guide vanes. The
higher separation of dust inside the cyclone is linked to the centrifugal forces and high circumferential
velocities inside the cyclone. The higher velocities inside the vessel require a special protection of the
surfaces inside the vessel. A dust catcher is very often operated without any protection of the inner
surfaces due to the low gas velocity, but the cyclone technology requires a protection of these surfaces
in order to avoid wear.
The cyclone dust catcher is usually with vortex finder, apex, flow cone and a dust collection hopper with
a dual dust outlet. The collection efficiency of the cyclone depends very much on particle size
distribution. Particles below 5 micrometers are not removed due to their small mass; Particles between
5 micrometers to 30 micrometers are partially separated and particles larger than 30 micrometers are
completely separated in the cone dust catcher. Overall separation efficiency of cyclone dust catcher is
better than the gravity dust catcher.
Bag Filter : The gas that after initial separation get into the dust catcher and dust cyclone from the
bottom of the dust remover, and larger particles fall on the ash bucket by their own weight, and the
smaller particles dispersion in the room of the filter bags, so they are remained on the surface of the
bags and then the clean gas is sent to the users. With the procession of the dust remover, dust
remained on the surface of the filter bags become more and more, the resistance of the bags increases,
when the resistance of the bags reaches upper threshold, the system will open the purge-valve
automatically in order to send the cleaning gas into the pressure static box, which makes the filter bags
changed from a state of deflated to a state of expansion so that the dust absorbed on the surface of the
filter bags will fall into the dust hopper at the bottom of the box and the dust in the hopper will be
cleaned by the ash valve. When the resistance of the filter bags reaches down threshold, the system will
close the purge-valve to stop cleaning, as so the dust remover works again. Maximum filtering rate is 1.0
to 1.5 m3/minute and the gas temperature is 50 OC to 280 OC (the system can also operate stably
(reliably) for 2 hours at gas temperature of 300 OC). The normal dust content of Mini Blast Furnace gas
after cleaning is usually not more than 3 mg/ Nm3. Service life of fabric bags is generally up to two years.
Set of bag filter with ID Fan & Stack will be provided to control the air pollution to comply with the
emission norm. The amount of dust will be sucked by hoods from different material handling facilities &
through bag filter it will be released to the atmosphere through stack. The flue gases from furnace will
be sucked through an interconnecting ductwork by induced draft fan & exhaust to the chimney. The
system will meet the emission standards during operation of the plant and ensure clean plant operation.
The fume exhaust hood with duct will be provided around the furnace circumference to capture the
fumes generated during operation. The cleaning will be off line & will take place after tapping operation
is over. Emission level at the outlet of Bag House through stack will be less than 50 mg/ Nm3.
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 14
3.5.7 Internal Roads & Drainage The Internal roads will be 6m wide. A drainage system will be provided along the roads and buildings for
disposal of plant and storm water. Brief details of factory and other buildings are given in Plant Layout.
3.6 Main Plant & Equipment
List of Main Plant & Equipment
Sl. No. Description
Blast Furnace : 65 m3
1. Ground Hopper
2. Day Bins
3. Conveyors
4. Tripper Conveyor
5. Vibrating Screen
6. Vibro Feeder
7. Blast Furnace, 65 m3
8. Dust Catcher
9. Dust Cyclone with Hopper
10. Bag Filter
11. Stove
12. Blower
13. Multi Stage Blower
14. Pig Casting Machine
15. Water Circulation System
16. Air System with Accessories
17. Hydraulic Power Pack with Motor
Sinter Plant : 12 m2 1. Ground Hopper
2. Day Bins
3. Conveyors
4. Screens
5. Crushers
6. Mixer Machine
7. Sinter Machine, 12 m2
8. Sinter Cooler
9. Water Circulation System
10. Air System With Accessories
11. Thickener & Flocculator
12. Gas Cleaning Station
General 1. De-dusting Unit for Sinter Plant & Mini Blast Furnace
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 15
C H A P T E R 4 Project Schedule
4.1 General Considering the delivery period of major equipment and time required for construction of
buildings and miscellaneous items as well as for installation of machinery and equipment, a project
implementation schedule has been developed. The factors involved in the execution of this schedule are
as follows :
4.2 Steps Involved in Implementation The major steps involved in the implementation of the proposed plant are :
Arrangement of the requisite financing for the project.
Finalization of the layout for the proposed plant.
Design of all plant buildings, auxiliary and ancillary buildings, utilities and services.
Issue of tender documents and specifications for all equipment, selection of equipment suppliers and placement of orders.
Finalization of arrangements for the construction of the substation for the electric power supply system / gas distribution system. For the construction and commissioning of the plant the following major steps are needed :
Setting up an organization for the execution of the job.
Arrangement of all construction facilities at the plant site.
Procurement of bulk of steel, cement and other constructional materials and their progressive delivery in accordance with the construction schedule.
Obtaining foundation load and other relevant data of furnace, gas generator etc.
Preparation of tender documents for construction.
Issue of tender documents and selection of contractors for handling civil, structural, mechanical and electrical jobs and equipment installation.
Erection of equipment, power supply & distribution system, water system and other utilities.
Securing staff for the operation of the plant.
Arranging for the necessary raw materials and services.
Trial runs and commissioning of the individual units and finally the entire plant.
4.3 Project Implementation Schedule Based on the delivery schedule of major equipment and volume of all construction jobs, construction
planning has been made on the basis of a total time of completion of the proposed plant as 18 month
from the go-ahead signal. A construction schedule broadly indicating the sequence of major activities
such as preparation of specification / drawing, issue of tenders, placement of orders, delivery schedule
of the major items of equipment, civil and structural construction of all buildings, test trial runs of
various items of equipment and commissioning of the plant is shown in a Bar chart.
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 16
4.4 Commissioning of Plant It has been planned to complete the installation and commissioning of the entire plant within 18
months of go-ahead. The construction schedule has been prepared on the basis of the delivery periods
of the major items of equipment and the volume of civil, mechanical and constructional jobs involved.
In view of long delivery period of some of the major items, it is imperative to finalize the orders for all
such equipment at the initial stage of the project. Completion of the project on time can concern, in
accordance with delivery of plant and equipment.
4.5 Procurement of Equipment & Installation The equipment comprises one Mini Blast Furnace and Sinter Plant, the delivery period of which is
normally 4-5 months. The order for it should be placed. The delivery period of the crane, electrical
equipment, etc. will be about 3-4 months. Therefore, pending the delivery of the Sinter Plant, all
necessary electrical jobs and water supply arrangement should be executed as far as practicable. The
arrangements for installation of the Mini Blast Furnace, Stock House, Stoves and Sinter Plant should be
initiated along with structural jobs for the project to facilitate easy installation of Mini Blast Furnace.
The entire water circulation system should be ready by the time the test / trial run commence.
4.6 Civil Work The drawings for foundations of the columns for production buildings should be started immediately
after the go-ahead signal and action taken for the procurement of cement and reinforcement rods.
The construction of production sheds can proceed simultaneously. On receipt of foundation load and
other data, lying of foundations for the Mini Blast Furnace, transformer and all other equipment can
be taken up simultaneously before the equipment arrive at the site. The laying of internal roads and
drainage system should be completed expeditiously to facilitate transportation of structural materials,
equipment, raw materials, etc. Work on the construction of ancillary buildings and facilities should
proceed simultaneously.
4.7 Structural Steel Work
An appropriate and economic structural design of plant buildings will be developed and the required
quantity of structural steel and other building materials should be procured in stages after the go-
ahead decision has been taken. Adequate steel materials should be made available by the time
structural fabrication commences and the drawings should be released in stages. A contractor should
be fixed. The fabrication of columns, roof trusses, etc. can be started along with the civil work. The
fabrication and erection of structural steel work including roofing and cladding should be completed
within the allocated time.
4.8 Equipment Erection Arrangements for procuring the equipment should commence immediately after the go-ahead signal
has been given. Equipment data (foundation, electrical, utilities, etc.) have to be taken from the
suppliers. The erection of the induction furnaces should preferably be carried out under the guidance
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 17
and supervision of the personnel deputed by the equipment supplier, who will also be responsible for
commissioning the equipment and demonstrating the fulfillment of the performance guarantee. In the
case of staggered delivery of the components of an individual item of equipment, the erection should
follow the schedule. Piping, electrical work and lying of refractory have to be kept in view. As cooling
water of the desired specification will be necessary, the jobs relating to water treatment and its
cooling should be completed in time.
4.9 Wiring, Lighting, Water & Utilities Including Piping Works
Preparation of specification for these facilities should be taken up after the data from the equipment
suppliers received and it is to be so planned that these are installed at the sight will in advance of
commissioning of the equipment. Permanent power and water supplies will have to be arranged
before the test trial commences. The source of water and its analysis should also be available to
enable selection of the proper water treatment facilities.
4.10 Project Management It will be necessary to fix the responsibility for project management on suitable persons headed by a
Chief of the project who will monitor the progress of work and apply midterm correction to ensure its
timely implementation.
Project Implementation Bar Chart
Sl. No. Activity Time In Month
1. Land Development and Road Construction, Drainage etc. 1 to 2
2. Finalization of Master Plan 1 to 1
3. Road and Sewerage Construction 2 to 2
4. Civil and Structural Drawings 2 to 6
5. Piling Earth Cutting etc. for the Shed and Civil 3 to 6
6. Structural Construction of Sheds 3 to 9
7. Preparation of Tender Documents for Main Equipment 2 to 5
8. Design of Utilities on the Basis of Main Equipment 9 to 12
9. Selection and Procurement of the Equipment 6 to 12
10. Preparation of Drawings Mechanical and Electrical Utilities 9 to 12
11. Erection of Equipment 9 to 14
12. Selection of Manpower for Different Activity 9 to 12
13. Commissioning of the Plant 14 to 16
14. Performance Test and Commencement of Regular Production 16 to 18
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 18
C H A P T E R 5 Manpower Requirement
Sl. No.
Section & Trade Shifts
Extra Total Grade G A B C
1 PLANT OPERATION
1.1 General
a. Works Manager 1 - - - - 1 Executive
Total of Item 1.1 1
1.2 Mini Blast Furnace Area
a. Shift Foreman - 1 1 1 - 3 Jr. Manager
b. Furnace Operator - 2 1 1 - 4 Highly Skilled
c. Assistant - 2 1 1 - 4 Skilled
d. Helper - 1 1 1 - 3 Un-skilled
e. Charging Crane Operator - 1 1 1 - 3 Skilled
f. Sling Man - 2 2 2 2 8 Un-skilled
g. Labour - 2 1 1 - 4 Un-skilled
Total of Item 1.2 29
1.3 Blast Furnace Stock House Area
a. Shift Foreman - 1 1 - - 2 Jr. Manager
b. Operator - 1 1 1 - 3 Highly Skilled
c. Helper - 2 2 1 - 5 Semi-skilled
Total of Item 1.3 10
1.4 Sinter Plant Area
a. Shift Foreman - 1 1 - - 2 Jr. Manager
b. Sinter Machine Operator - 1 1 1 - 3 Highly Skilled
c. Helper - 1 1 1 1 4 Semi-skilled
d. Gas Cutter - 1 1 - - 2 Skilled
e. Crane Operator - 1 1 - - 2 Skilled
Total of Item 1.4 13
2. SERVICE AND MAINTENANCE
a. Chief Engineer 1 - - - - 1 Sr. Manager
b. Shift Supervisor (Mech. & Elec.) - 1 1 1 - 3 Supervisor
c. Electrical Engineering 1 - - - - 1 Jr. Manager
d. Electrician - 1 - - - 1 Skilled
e. Helper - 1 - - - 1 Semiskilled
Total of Item 1.4 7
Total Manpower Requirement = 1 + 29 + 10 + 13 + 7 = 60 Additional unskilled labour on contract basis = 80
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 19
C H A P T E R 6 Project Cost & Financial Analysis
6.1 Project Cost
Indian steel demand rose 4.5 per cent in the financial year 2015-16, a slightly better growth rate than in
the previous year. Accordingly, even though challenges remain, the steel sector’s fundamentals have
started to improve. Purulia Metal Casting (P) Ltd. is presently operating Secondary Metallurgical Unit
having Induction Furnaces, Continuous Casting Machine and Rolling Mill producing finished steel
products. To make finished steel products even more economically viable in the present fluctuating
market, Purulia Metal Casting (P) Ltd. has decided to go for a Mini Blast Furnace (65 m3) and Sinter Plant
(12 m2) to produce Pig Iron which will be used as one of the raw materials in its existing Secondary
Metallurgical Unit to withstand the present market situations.
The technology involved in the proposed project is well recognised and reliable. Such types of plants are
successfully operating all over the country. The combination of dynamic management and experienced
professionals is quite capable of managing the business. Regarding operation and maintenance of the
plant, well experienced professional manpower are available in this region. The proposed project will
have good financial and social benefits to the local people by way of direct & indirect employment.
Preference will be given to the local people considering the requisite skill and qualification criteria. The
unit does CSR activities in the area like supply of drinking water during summer, help to pour peoples,
financial aid to local schools, clubs etc. In future, after commissioning of the proposed project, the unit
will carry out different CSR activities also.
There will be complete integration right from the beginning to finished products. The feasibility of
proposed project has been examined from 3 angles, which are backbone of any sustainable project i.e.,
Commercial and Financial Feasibility, Pre and Post Project scenario in which company will operate and
Environmental feasibility and the results show positive feasibility.
The total Project Cost will be Rs. 25.50 Crores. The following is the breakup of the proposed project cost.
Capital Cost for Pollution Control System will be Rs. 2.0 Crores. The Recurring Cost for Pollution Control
System has been considered as Rs. 14.00 Lakhs / annum. Also there will be an adequate fund towards
Corporate Social Responsibility.
Sl. No. Item Total Cost
(Rs. In Crores)
1. Land & Site Development 3.00
2. Mini Blast Furnace 7.00
3. Sinter Plant 3.75
4. Refractory & Other Initial Requirement 3.00
5. Civil & Structural 3.50
6. Erection & Commissioning 3.25
7. Pollution Control System 2.00
Total 25.50
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 20
6.2 Production Cost Estimate of Sinter
Basis : One Sinter Plant for 170 Days of Operation in a Year Producing 51,000 T of Sinter
Sl. No.
Items Rate / Price / T
(Rs.)
Consumption / T
(kg)
Cost / T of Sinter (Rs.)
A Raw Materials
1. Iron Ore Fines 800.00 800.00 640.00
2. Mill Scale 0.00 130.00 0.00
3. Limestone 3500.00 100.00 350.00
4. Coke Breeze 12000.00 60.00 720.00
Total 1710.00
5. Flue Dust 0.00 30.00 0.00
6. Return Fines 0.00 420.00 0.00
Total 0.00
Total of A 1710.00
B Utilities & Consumables
1. Power (Kwh) 4.18 60.00 250.80
2. Fuel Oil (L) 25.00 1.00 25.00
3. Refractories & Consumables for Sinter Machine
100.00
4. Miscellaneous consumable 25.00
Total of B 400.80
C Indirect Expenses
1. Labour & Supervision 200.00
2. Repair & Maintenance 40.00
3. Administrative Expenses 50.00
4. Miscellaneous Factory Expenses 50.00
Total of C 340.00
Cost per Ton of Sinter Production = (A+B+C) 2450.80
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 21
6.3 Production Cost Estimate of Molten Metal
Basis: One Mini Blast Furnace for 365 of Days Operation in a Year Producing 59310 T of Molten Metal
Sl. No.
Items Rate / Price / T
(Rs.)
Consumption / T
(kg)
Cost / T of Sinter (Rs.)
A Raw Materials
1. Iron Ore 3300.00 850.00 2805.00
2. Iron Ore Sinter 2554.00 850.00 2170.90
3. Coke 12000.00 700.00 8400.00
4. Limestone / Dolomite / Quartz
l
3500.00 225.00 787.50
Total of A 14163.40
B Utilities & Consumables
1. Power (Kwh) 4.18 60.00 250.80
2. Refractories & Consumables for MBF Machine
100.00
3. Miscellaneous consumable 25.00
Total of B 375.80
C Indirect Expenses
1. Labour & Supervision 216.00
2. Repair & Maintenance 40.00
3. Administrative Expenses 50.00
4. Miscellaneous Factory Expenses 50.00
Total of C 356.00
Cost per Ton of Molten Metal Production = (A+B+C) 14895.20
Pre-Feasibility Report
Mini Blast Furnace (65 m3) & Sinter Plant (12 m2)
Project Location Village : Bongabari, P.O. : Vivekanandanagar, District : Purulia, Pin : 723147, West Bengal
October 2016
Purulia Metal Casting (P) Ltd. (Pig Iron Division)
Page 22