pre- feasibility reportenvironmentclearance.nic.in/writereaddata/online/tor/08...the mine lease area...
TRANSCRIPT
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
1
PRE- FEASIBILITY
REPORT
July, 2016
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
2
EXECUTIVE SUMMARY
1.0 Introduction
The mine lease area is located at Village- Musyoli Chak Joshigaon, Tehsil & District-Bageshwar,
Uttarakhand. The mining lease area is a Soap Stone Mine. The proposed project of 17.976 ha
area is of Soapstone mining
The project falls under Schedule 1(a) of mining and is a Category- “B2” project as per EIA
notification 14th September 2006 and there amended of 15th January 2016.
Buffer map of 10 km radius is attached as Annexure III.
1.2 Salient features of the project
Project Name MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT
Mining Lease Area 17.976Ha
Location of mine
Village: Musyoli Chak Joshigaon
Tehsil: Bageshwar
District : Bageshwar
State : Uttarakhand
Coordinates
Lattitude Longitude
290 49’12.10”N 790 52’23.16”E
290 49’11.16” N 790 52’28.53” E
290 49’13.51” N 790 52’31.44” E
290 49’15.07” N 790 52’31.73” E
290 49’13.70” N 790 52’33.04” E
290 49’14.34” N 790 52’34.04” E
290 49’14.34” N 790 52’ 34.09” E
290 49’13.99” N 790 52’ 35.16” E
290 49’12.48” N 790 52’ 34.40” E
290 49’10.72” N 790 52’ 33.88” E
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
3
290 49’08.90” N 790 52’ 34.01” E
290 49’10.79” N 790 52’ 35.96” E
290 49’11.82” N 790 52’ 34.48” E
290 49’11.18” N 790 52’ 33.21” E
290 49’10.10” N 790 52’ 32.24” E
290 49’08.79” N 790 52’34.15” E
290 49’07.12” N 790 52’ 31.96” E
290 49’08.65” N 790 52’ 30.36” E
290 49’09.81” N 790 52’ 31.43” E
290 49’09.71” N 790 52’ 32.76” E
290 49’09.97” N 790 52’ 33.67” E
290 49’08.34” N 790 52’ 30.35” E
290 49’08.91” N 790 52’ 29.79” E
290 49’69.34” N 790 52’ 27.90” E
290 49’11.00” N 790 52’ 21.47” E
290 49’11.12”N 790 52’ 22.12” E
290 49’10.90”N 790 52’ 27.00” E
290 49’13.52”N 790 52’ 29.61” E
Land Use Agricultural Land ( Reclaimed in due course of time)
Minerals of mine Soap Stone
Life of mine 10 Years
Total Geological Reserve 32,74,027 Tonnes
Total Mineable Reserve 28,03,449Tonnes
Proposed production of mine 53,275 TPA
Method of mining Opencast Semi Mechanized mining
No of working days 240 days
Water demand 1KLD (Domestic) + 0.5 KLD (Dust Suppression) = 1.5KLD
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
4
Sources of water Water for drinking and dust suppression will be Purchased through
Tanker.
Man power 127
Nearest railway station Kathgodam Railway Station (Approx. 75 km in SSW Direction)
Nearest state/national highway SH 37 (about 10 km in W direction)
Nearest airport Pithoragarh Airport (Approx. 40km in SE direction)
Seismic zone Zone V
2. INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
2.1 Identification of Project and Project Proponent
The project is proposed is for mining of Soapstone Mining. The mine lease has been granted in
the name of Shri. Bhupal Singh Kanwal dated 06-04-2016 term of fifty years (Copy of Lease
deed attached as Annexure IV).
The details of the project are given below:
Name of the applicant Shri. Bhupal Singh Kanwal
Address of applicant Shri. Bhupal Singh Kanwal
H.No. 62, Village- Musyoli, Tehsil & District- Bageshwar,
Uttarakhand
Name of Mine MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT
Mineral Soapstone Mining
Area (ha) 17.976ha
Location of the site Village: Musyoli Chak Joshigaon
Tehsil: Bageshwar
District : Bageshwar
State : Uttarakhand Status of Mine New
2.2 Brief Information about the Project
The proposed project has lease area of 17.976 ha and annual production capacity of 53,275 TPA
of SoapStone mineral. Mining operations will be carried out by Opencast Semi-mechanized
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
5
method. The expected life of the mine is 5years. The soapstone shall be extracted with
deployment of an excavator as well as manually with the help of crow bar; chisels, pickaxe,
hammers, spade and different grade of soapstone will be stacked separately near the mining faces.
Soapstone is soft mineral; therefore no drilling & blasting shall be required. The soapstone shall
be dressed manually & stacked separately. No further beneficiation shall be undertaken during
first five years. Water requirement for the proposed project is 1.5 KLD for drinking use and dust
suppression. Green belt development (plantation in completed benches and barrier zone) will be
carried out as a part of reclamation works.
2.3 Need for the Project and Its Importance to the Country or Region
With the rapidly increasing demand of Soapstone raw materials, The Industry's demand for
fine powder is continuously prompting technological advancments to meet this purpose. The
pulverisers/hammer mills developed and manufactured in India are capable of producing up
to 700 mesh powder . The world market prefers fine powder which can be produced by
adopting new processing techniques like micronising and sterilisation of the product. Talc, in
pulverised form, is mostly used as a filler in paper, textile, rubber, insecticides and fertilizer
industries. Pure talc after calcining, called 'Lava', is used in the manufacture of low-loss
ceramic materials essential for radio, radar television, etc. In roofing products, such as, tar
paper, asphalt shingles and roll roofing, talc acts as a fire retardant and increases weather
resistance. Body and face powders (talcum powder) are prepared from the finest quality talc
after adding deodorant and perfumes.
2.4 Demands-Supply Gap
Talc is used mostly in pulverised form as a filler and extender in various industries. The non-
pulverised talc is used in refractory, etc.Total reported consumption of talc/steatite/ soapstone
in the organised sector was at 368 thousand tonnes in 2012-13. About 56% consumption in
2012-13, was in Paper Industry, followed by Paint (20%), Pesticide (11%), Ceramic (8%) and
Cosmetic (4%) industries. Nominal consumption was shared by Fertilizer, Rubber, Textile,
Chemicals and other industries. Consumption of talc/steatite/soapstone during 2010-11 to
2012-13 is given in below Table
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
6
.
Source:
http://ibm.nic.in/writereaddata/files/01192015115341IMYB_2013_Vol%20III_Talc_Soapstone%20and%
20Steatite%202013.pdf
2.5 Imports vs. Indigenous Production
The demand in the domestic market is high for Soapstone. The Industry's demand for fine
powder is continuously prompting technological advancements to meet this purpose. Mineral is
available in abundant quantity in area and can be extracted indigenously.
2.6 Export Possibility
There is no proposal to export the mineral as the minerals extracted cater the indigenous
demand and the development is a never ending process.
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
7
2.7 Domestic/ Export Markets
There is always an ever increasing demand of these minerals in the domestic market. The
finished product will be used for saleable purpose in the local market.
EXPORT MARKET
The proposed mining activity is for indigenous consumption only for Pharmaceutical
Industry, Cosmetic Industry, Textile, Ceramic, Paint, Rubber, Plastic, Detergent etc
2.8 Employment Generation
Owing to the topography of the area, which is a rough terrain, Soap Stone mining activity is
needed as the primary source of income for the locals. The mine will provide
employment to about 127 workers. It will provide employment to the people residing in vicinity
and also indirectly by the development of supporting infrastructure and allied activities.
S.No. Description Numbers
1 Mine Manager 1
2 Geologist 1
3 Skilled Workers 2
4 Unskilled Workers 123
Total Workers 127
3.0 PROJECT DESCRIPTION
3.1 Type of Project Including Interlinked and Interdependent Projects, If Any.
The proposed project for extraction of Soap Stone mining along with associated minor mineral is
an independent project. There are no interlinked or interdependent projects.
3.2 Location
The mining lease area is located in Village: Musyoli Chak Joshigaon, Tehsil & District:
Bageshwar, Uttarakhand. The details of location of mining lease area are given below:
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
8
Particulars Details
Location Village: Musyoli Chak Joshigaon, Tehsil & District
Bageshwar, Uttarakhand
Coordinates Lattitude Longitude
290 49’12.10”N 790 52’23.16”E
290 49’11.16” N 790 52’28.53” E
290 49’13.51” N 790 52’31.44” E
290 49’15.07” N 790 52’31.73” E
290 49’13.70” N 790 52’33.04” E
290 49’14.34” N 790 52’34.04” E
290 49’14.34” N 790 52’ 34.09” E
290 49’13.99” N 790 52’ 35.16” E
290 49’12.48” N 790 52’ 34.40” E
290 49’10.72” N 790 52’ 33.88” E
290 49’08.90” N 790 52’ 34.01” E
290 49’10.79” N 790 52’ 35.96” E
290 49’11.82” N 790 52’ 34.48” E
290 49’11.18” N 790 52’ 33.21” E
290 49’10.10” N 790 52’ 32.24” E
290 49’08.79” N 790 52’34.15” E
290 49’07.12” N 790 52’ 31.96” E
290 49’08.65” N 790 52’ 30.36” E
290 49’09.81” N 790 52’ 31.43” E
290 49’09.71” N 790 52’ 32.76” E
290 49’09.97” N 790 52’ 33.67” E
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
9
290 49’08.34” N 790 52’ 30.35” E
290 49’08.91” N 790 52’ 29.79” E
290 49’69.34” N 790 52’ 27.90” E
290 49’11.00” N 790 52’ 21.47” E
290 49’11.12”N 790 52’ 22.12” E
290 49’10.90”N 790 52’ 27.00” E
290 49’13.52”N 790 52’ 29.61” E
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
10
The vicinity map is given below:
3.3 Details of Alternate Sites
Hence no alternative site is examined for mining.
3.4 Size or magnitude of operation
The proposed mine has lease over an area of 17.956 ha and during five year total production of
useable material shall be approximately 53,275 tonnes. The mine will be worked on the day shift
only. The average number of working days in the year would be 240.
Geological and mineable reserves
The reserve has been calculated based on slice level, which is then multiplied with bulk density
2.6t/cum to calculate the reserve in tonnage.
PROJECT SITE
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
11
Table no. 1: RESERVES
Classification UNFC Code
Quantity in million tons
Grade
A. Total Mineral Reserve
Proved Mineral Reserve 111 Nil Cosmetic
paper
Probable mineral Reserve 122 2.803449 Cosmetic
paper
B. Total Remaining Resources
Feasibility mineral Resource 211 Nil Cosmetic
paper
Prefeasibility mineral resource 222 0.470576 Cosmetic
Paper Measured mineral resource 331 Nil Nil Indicated mineral resource 332 Nil Nil Inferred mineral resource 333 Nil Nil
Reconnaissance mineral resource 334 Nil Nil
Total Reserves + Resources 3.274025
Production
The year wise production schedule of soapstone from different benches in different pits are given below:
1ST YEAR (2016-17)
PIT NAME BENCH
(mRL)
FACE LENTH
(m.)
FACE ADVANCEMENT((m.)
BENCH
HEIGHT (m.)
VOLUME (cum)
Saleable
Quantities
of Soapstone (Tones)
PIT-I 1550 146 15 6 13140 20498
Total Geological Reserves (in Tonnes) Total Mineable Reserves (in Tonnes)
32,74,027 28,03,449
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
12
1556 90 21 6 11340 17690
PIT-II 1526 95 8 6 4560 7113
PIT-III 1496 103 7 6 4326 6748
Total 52049
2ND YEAR (2017-18)
PIT NAME BENCH
(mRL)
FACE LENTH
(m.)
FACE ADVANCEMEN
T(m.)
BENCH
HEIGHT (m.)
VOLUME (cum)
Saleable
Quantities
of Soapstone (Tones)
PIT-I 1562 83 18 6 8964 13983
1568 54 9 6 7776 12130
PIT-II 1532 126 13 6 9828 15331
PIT-III 1502 111 11 6 7326 11428
Total 52872
3RD YEAR (2018-19)
PIT NAME BENCH
(mRL)
FACE LENTH
(m.)
FACE ADVANCEMEN
T(m.)
BENCH
HEIGHT (m.)
VOLUME (cum)
Saleable
Quantities
of Soapstone (Tones)
PIT-I 1574 61 9 6 3294 5138
1580 96 23 6 13248 20666
PIT-II 1538 108 11 6 7128 11119
PIT-III 1508 95 18 6 10260 16005
Total 52928
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
13
4TH YEAR (2019-20)
PIT NAME BENCH
(mRL)
FACE LENTH
(m.)
FACE ADVANCEMEN
T(m.)
BENCH
HEIGHT (m.)
VOLUME (cum)
Saleable
Quantities
of Soapstone (Tones)
PIT-I 1586 91 21 6 11466 17886
PIT-II 1544 58 18 6 6264 9771
1550 50 24 6 7200 11232
PIT-III 1514 73 21 6 9198 14348
Total 53237
5TH YEAR (2020-21)
PIT NAME BENCH
(mRL)
FACE LENTH
(m.)
FACE ADVANCEMEN
T(m.)
BENCH
HEIGHT (m.)
VOLUME (cum)
Saleable
Quantities
of Soapstone (Tones)
PIT-I 1592 92 24 6 13248 20666
PIT-II 1556 99 26 6 15444 24092
PIT-III 1520 65 14 6 5460 8517
Total 53275
(Source: Approved Mine Plan)
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
14
The total year wise quantities of soapstone exploited from PIT-I, PIT-II& PIT-III, are tabulated below:
YEAR Quantities of
Soapstone (Tonnes)
I 52049
II 52872
III 52928
IV 53237
V 53275
3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS
3.5.1 Method of Mining
It will be opencast semimechanised mine. The overburden & interburden shall be removed
deployment of an excavator as well as with the help of rock breaker. The soapstone shall be
extracted with deployment of an excavator as well as manually with the help of crow bar; chisels,
pickaxe, hammers, spade and different grade of soapstone will be stacked separately near the
mining faces. Soapstone is soft mineral; therefore no drilling & blasting shall be required. The
soapstone shall be dressed manually & stacked separately. No further beneficiation shall be
undertaken during first five years. The different grade of soapstone will be filled into 50 kg plastic
bags & transported the road side by mules. From road side the soapstone bags will be loaded into
trucks through manually and transported to Haldwani.
The salient points of proposed method of mining are given below:-
Mining shall be carried out in three pits.
It will be open cast semi-mechanized. Average thickness of soil has been considered as 0.50m &
it shall be stacked separately.
Bench height will be kept 6.0m width of benches shall be kept 6.0m with face slope 700 to 75o.
Development work will be construction of approach road to different working benches and no
removal of the top soil. Seasonal nalla & habitation are for away from proposed mining pits.
However wire crated wall having width & height 0.75m & 1.0m shall be provide along the nalla
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
15
for the protection of nalla by mining activities & siltation of waste dump. Habitation is for away
from the proposed mining area, & mined out pit shall be back filled before the commencement of
monsoon therefore there shall be no adverse impact on habitation due to mining activities.
The following mining parameters are proposed for production in 5years:
Type of working : Opencast Semi Mechanised
Bench Height : 6m
Bench Width : 8m
Proposed Year wise Production
YEAR Quantities of Soapstone
(Tonnes)
I 52049
II 52872
III 52928
IV 53237
V 53275
3.6 Raw Material Required Along With Estimated Quantity, Likely Source, Marketing
Area of Final Product/s, Mode of Transport of Raw Material and Finished Product
No raw material will be required in the proposed project. The operation involves the
excavation of Soap stone along with associated minor minerals in its existing form and
transported to the end users/ market.
3.7 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE
Soap Stone is a depleting asset once mined; a scientific approach will be taken up while
excavation of mineral with systematic method.
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
16
Use of Mineral
The minerals i.e. the Soap stone along with associated minor minerals are used:
Pharmaceutical Industry
Cosmetic Industry
Textile Industry
Ceramic Industry\
Paint Industry
Detergent Industry
Rubber Industry
3.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY/ POWER
REQUIREMENT AND SOURCE
3.8.1 Water Requirement
Water for domestic, dust suppression and plantation is required to be 1.5KLD. It is proposed to
obtain water from nearby villages.
S.No. Description Quantity
1 Domestic 1KLD
2 Dust Suppression 0.5KLD Total 1.5KLD
Source of water: Two seasonal nallas exist within the area and flow direction north to south
and meet to Gadhera exist out of area and flow direction east to west direction. The surrounding
area is characterized by gentle slopes, narrow ridges & forms the mountainous topography & rain
water flows through the slope & meets the drainages & finally meets the main river. The water
catchment of buffer zone is divided into one water shed locally called as Dafot god which is the
main catchment of the area.
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
17
3.8.2 POWER
The operation will be done only from sun rise to sun set hence there is no power requirement for
the project at site.
3.9 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND
SCHEME FOR THEIR MANAGEMENT/ DISPOSAL
3.9.1 Solid Waste Generation & its Disposal
No Solid Waste generated during mine operation. The top soil having average thickness 0.50m
lies all over the lease area. The top soil, interburden from pit will be stacked separately and used
as backfilled material. No mineral reject will be produced during next five years.
The quantity of soil, interburden from pit to be generated during next five years is given below:
YEAR TOTAL
SOIL +INTERBURDEN(cum)
I 13510
II 13723
III 13739
IV 13819
V 13830
TOTAL 68621
Storage and preservation of top soil:
The top soil material to be generated from each pit will be temporarily stacked towards slope side
of working pits. Dumping shall be carried out in single terrace & slope of dump shall be kept 370.
All the quantities shall be used in backfilling before the commencement monsoon period.
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
18
Therefore no proposal has been envisaged for separate stacking of top soil. Before the
commencement of monsoon all the pits shall be backfilled.
The Quantities of soil to be generated to as below:
YEAR TOTAL
SOIL
I 164
II 167
III 168
IV 169
V 170
Total 838
3.9.2 Liquid Effluent
No liquid effluent will be generated from the proposed mining project.
4. Site Analysis
4.1 Connectivity: The lease is well connected to an umettalled road approximately at a distance
of 0.80 m followed by mettalled road which ultimately joins SH-37.
S.NO Other Connectivity Details Distance Direction
1. Kathgodam Railway Station 75 km SSW
2. Pithoragarh Airport 40 km SE
3. SH 37 10km W
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
19
Map I: Evacuation Route
4.2 LANDFORM, LANDUSE AND LAND OWNERSHIP
The Existing land use pattern is agricultural land. The area has a mild slope towards north-east direction. Two seasonal drainage exist within the lease area and flow direction north to south and meat to Gadhera canal,and gadhera canal exist out of lease area and flow direction east to west, the perennial river far away from lease area. 4.2.1 General Geology:
The area forms the part of Calc Zone of Tejam. The stratigraphical sequence of the region as per monumental work (Geology of Lesser Himalayas; 1980 of Prof. K.S. Valdiya is as below:
Berinag Quartzite
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Unconformity ~~~~~~~~~~~~~~~~~~~~~~~~~~~~
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
20
Gangolihat Dolomite Dolomite and dolomitic limestone with algal structures. Magnesite with minor talc/talcose phyllite and dolomite intercalations.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Unconformity ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Sor Slates Shales, Slates and Phyllites
The above sequence as observed in this region is considered to be an inverted one. Soapstone pocket
occur within carbonates of Gangolihat Dolomite.
Topography:
The lease area comprises of terraced agricultural fields showing undulating topography. The area
comprises of a ridge trending north to east having a sinuous shape. Slope in the area varies from low to
moderate. The two seasonal nalas exist within the area and flow direction north to south and meat to
Gadhera and south direction which is perennial and meet to Dafot god. Dafot god main catchment of the
area. The highest level is at 1551.67mrl in between pillar no.74& 75 while the lowest level is at
1496.10mRL towards southern flank in between pillar no.20 & 21.
Climatic Condition
Climatically the area falls in temperate zones with pleasant summer and extremely cold in
winters. The area receives moderate snowfalls during winters between Decembers to February.
The maximum temperature goes up to 400C white the average minimum temperature goes above
up to 20C to 30C the months of January & February.
Relative Humidity
The relative humidity shows rise from June to February with highest values in the month of
January and decreases it reaches lowest during April and May. On the basis of past experience
reveals that the maximum average humidity in the month of January is about 96.33% while the
minimum average humidity is about 31.43% during month of April.
Rainfall:
The area receives 70% on an average rainfall in between June end to mid September. Average
rainfall from June to September comes about 1000mm. The maximum rainfall was received
1140mm. during the month of July & August while the minimum rainfall was recorded will
during the months of January & February & it varies 8mm to 15mm.
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
21
4.2.2 Local Geology:
Local Geology:
The area only shows part of carbonates of Gangolihat Dolomite sequence. The local stratigraphy
shows that the mineralized zone lies between upper & lower carbonates as below:
Upper Carbonates: Magnesite sporadic dolomite
Middle Talcose phyllite: Talc in pockets
Lower Carbonates: Dolomite & Dolomite Limestone
As per UNFC, the deposit is lenticular of all dimensions including bodies occurring en-echelon
fashion.
Alluvial Cover:
A thin layer of brownish color of soil exists in the whole area. The average thickness of soil is
0.50m.
Soapstone bearing with Magnesite:
The soapstone mineral in Kumauni Himalaya is an alteration a products magnesium bearing
minerals, Soapstone occurs as pocket type massive and sometimes confined to the upper part of
the magnesium bearing zones. The mineral body occurs in irregular shape & size. The foliation
plane of soapstone trending 3200 N to 3250 N, amount of dip varies 300 to 350 and dip direction
varies 500 to 550 N.
The area was explored with the help of five trial pits. Soapstone bearing with low grade
magnesite was seen in the pit. The pit was dug at different levels in the agricultural field &
soapstone encountered in the pits which is further persists in depth as observed during
prospecting period. The soapstone occurring in this area is weakly foliated, fine grained off white
in color with its characteristic soapy feel.
4.3 Topography
The lease area comprises of terraced agricultural fields showing undulating topography. The area
comprises of a ridge trending north to east having a sinuous shape. Slope in the area varies from
low to moderate. The two seasonal nalas exist within the area and flow direction north to south
and meat to Gadhera and south direction which is perennial and meet to Dafot god. Dafot god
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
22
main catchment of the area. The highest level is at 1551.67mrl in between pillar no.74& 75 while
the lowest level is at 1496.10mRL towards southern flank in between pillar no.20 & 21.
4.4 LAND USE
The Existing land use pattern is agricultural land. The area has a mild slope towards north-east
direction. Two seasonal drainage exist within the lease area and flow direction north to south and
meat to Gadhera canal,and gadhera canal exist out of lease area and flow direction east to west,
the perennial river far away from lease area. The Existing land use pattern indicating the area
already degraded due to quarrying/pitting dumping, roads, processing plants, workshop, township
etc in a tabular form is as below:
Name of land use Benap land Agricultural Land Scrub Land Other
Total
(forest land) (ha) (Ha) (Ha) (Ha) (Ha)
Pits and quarries - - - - 0.041
Waste Dump - - - - -
Backfilled pit - 0.041 - - 0.041
Habitation - Nil - - Nil
Foot track/PWD road - 0.014 - - 0.014
Drainage - - - - -
Remaining
undistrubed area - 17.921 - - 17.921
Total 17.976 - - 17.976
4.5 Climatic data from secondary sources
The climate in Bageshwar district is temperate to sub-humid. The northern part of the district
experiences sub-zero temperature almost throughout the year whereas the central and southern
parts are comparatively warm and humid. Severe winter is the chief climatic feature in the district.
In 8 general, the district experiences a tropical to sub-tropical and sub-humid climate except for
the northern part where a cold temperate climate prevails.
Source: http://cgwb.gov.in/District_Profile/Uttarakhand/Bageshwar.pdf
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
23
5. PLANNING BRIEF
It will be opencast semi mechanised mine. The overburden & interburden shall be removed deployment of
an excavator as well as with the help of rock breaker. The soapstone shall be extracted with deployment of
an excavator as well as manually with the help of crow bar; chisels, pickaxe, hammers, spade and different
grade of soapstone will be stacked separately near the mining faces. Soapstone is soft mineral; therefore no
drilling & blasting shall be required. The soapstone shall be dressed manually & stacked separately. No
further beneficiation shall be undertaken during first five years. The different grade of soapstone will be
filled into 50 kg plastic bags & transported the road side by mules. From road side the soapstone bags will
be loaded into trucks through manually and transported to Haldwani.
The salient points of proposed method of mining are given below:-
Mining shall be carried out in three pits.
It will be open cast semi-mechanized. Average thickness of soil has been considered as 0.50m & it shall be
stacked separately.
Bench height will be kept 6.0m width of benches shall be kept 6.0m with face slope 700 to 75o.
Proposal for reclamation of land affected by mining activities:
The mining has been proposed in such a way that land will be reclaimed concurrently from end of first
year onward in each pit to restore its maximum original topography. The backfilled area shall be leveled &
it is use for agriculture. The average depression with respect to original topography after backfilling will
be 2.0 m.
The quantities of interburden & soil to be generated, space available for backfilling, quantities of
interburden & soil to be filled back and balance quantity of interburden & soil during next five years is
given below:
Year Quantities of soil +
interburden to be generated & dumped (Cum)
Space available for backfilling
(Cum)
Quantities of soil+ interburden to be used in backfilling
(Cum)
Balance quantities to be dumped
(Cum)
2016-17 13510 33366 13510 0
2017-18 13723 33894 13723 0
2018-19 13739 33930 13739 0
2019-20 13819 34128 13819 0
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
24
2020-21 13830 34152 13830 0
Total 68621 169470 68621 0
Source: Mine Plan
5.2 Population projection
The project will employ most of the workers from nearby villages except for supervisory staff.
Thus there will no increase in population due to the project. However, few people from other
area may migrate in this area for employment directly and indirectly for business
opportunities.
5.3 Amenities/Facilities
Temporary rest room shelter will be provided near project site.
First-Aid facilities (along with anti-venom) & Government Hospital is available at Bageshwar.
Safe drinking water
Facilities for sanitation-community toilets.
Direct and indirect Employment, most of which most will be from nearby villages.
Arrangements for safe and healthy working conditions.
Provision of safety equipments like ear-muffs, gloves, etc. Conducting medical camps for workers and nearby villagers at regular interval.
6. PROPOSED INFRASTRUCTURE
6.1 Industrial Area (Processing Area)
No infrastructure is proposed.
6.2 Residential Area (Non Processing Area)
As the local people will be given employment, no residential area/ housing are
proposed.
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
25
6.3 Green Belt
The Existing land use pattern is agricultural land. The area has a mild slope towards north-east direction. Two seasonal drainage exist within the lease area and flow direction north to south and meat to Gadhera canal,and gadhera canal exist out of lease area and flow direction east to west, the perennial river far away from lease area. The Existing land use pattern indicating the area already degraded due to quarrying/pitting dumping, roads, processing plants, workshop, township etc in a tabular form is as below:
Name of land use Benap land Agricultural Land Scrub Land Other Total (forest land) (ha) (Ha) (Ha) (Ha) (Ha) Pits and quarries - - - - 0.041 Waste Dump - - - - - Backfilled pit - 0.041 - - 0.041 Habitation - Nil - - Nil Foot track/PWD road - 0.014 - - 0.014 Drainage - - - - - Remaining undistrubed area - 17.921 - - 17.921
Total 17.976 - - 17.976
Flora:
The area is basically agricultural. It is therefore deficient in trees. Fruits tree exits surrounding of
habitation. The mining activities will be concentrated on cultivated fields. Therefore no flora shall be
disturbed due to mining & allied activities.
Shrubs:Ghingaru with a few Jhitalu, Kilmora and Hisalu etc. occurs in the depressions.
Grasses:Kumaria, Doob, Shishoona, Gria and Bhawaria.
YEAR TOTAL NO. OF SAPLING
I 68 II 150 III 200 IV 250 V 300
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
26
TOTAL 968
6.5 Water Management
The total water of about 1.5KLD will be supplied from the nearby sources in the village. further water stored in existing pits will also be used for Domestic & dust suppression purposes.
6.6 Sewerage System
No sewerage system is proposed.
6.7 Industrial Waste Management
Not applicable
6.8 Solid Waste management
No solid waste is envisaged. The soil will only be generated which will be used for green
belt development. In addition small amount of domestic waste will be generated by the
workers which will be disposed off through proper municipal way.
6.9 Power Requirement & Supply/Source
The operation will be done only from sun rise to sun set hence there is no power
requirement for the project at site. Machines used will run on diesel.
6.10 Social Infrastructure
The Applicant shall spend 5% of project cost for the development of the area i.e. treatment of
poor, schools, temples and other social work
Budget for Corporate Social Responsibility (CSR)
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
27
SI. No. Activity Capital Cost (in
Rs.)
1 Provide drinking water facility in surrounding villages and
schools by constructing water tanks at schools and
50,000/-
2 Solar lamp distribution 50,000/-
3 Construction of Toilets with hand pumps 30,000/-
4 Plantation of trees with tree guards 20,000/-
TOTAL (in life time) 1,50,000/-
6.11 Environmental Management Plan
The environmental management plan consists of the set of mitigation, management, monitoring
and institutional measures to be taken during the implementation and operation of the project, to
eliminate adverse environmental impacts or reduce them to acceptable levels. The present
environmental management plan addresses the components of environment, which are likely to be
affected by the different operations in the mine area.
Budget Allotted for the Environmental Management Plan:
S.No. Measures Capital Cost (In Rs.) Recurring Cost (In Rs.)
1 Pollution Control Dust Suppression
20,000
20,000/-
2 Pollution Monitoring i) Air pollution ii) Water pollution iii) Soil Pollution iv) Noise Pollution
-- --
10,000/- 10,000/- 10,000/- 10,000/-
3 Plantation/ Green belt 10,000 10,000/- 4 Reclamation of mined out area
(pisciculture , irrigation purpose)5,000 10,000/-
5 Occupational Health 5,000 20,000/- Total 40,000/- 1,00,000
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
28
7. REHABILITATION AND RESETTLEMENT (R&R) PLAN
Not Applicable
8 PROJECT SCHEDULE & COST ESTIMATES
8.1 Likely date of start of construction and likely date of completion.
The project will commence once Environmental Clearance and other necessary
certificates are obtained from the respective departments.
8.2 Estimated project cost along with analysis in terms of economic viability of the project
The project will commence after getting the Environmental Clearance and other necessary
certificates from respective departments.
S. Description Cost in Rs.
1. Land cost expenditure Nil
2. Cost of Equipment, infrastructure site facilities (worker & office purposes).
7,00,000
3. Environmental Protection & implementation cost 1,00,000
4. Socio-economic condition of local, population, physical survey
1,00,000
TOTAL 9,00,000
The total project cost is Rs. 9,00,000/-
9. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
The proposed mine will bring economical benefits to the state by the way of Royalty for mineral
and to the local people by way of direct and secondary employment opportunities. The
mining activities as proposed are the backbone of all construction and infrastructure projects
as the raw material for construction is available only from such mining activities. The stone
extracted is in high demand at the local market for building, construction of dams, roads, paves,
etc. This project operation will provide livelihood to the poorest section of the
society/economically backward population in the area. It provides employment to the people
residing in vicinity directly or indirectly. The mine management will also help nearby villages
PROJECT: MUSYOLI CHAK JOSHIGAON SOAPSTONE MINING PROJECT PFR
APPLICANT: Shri BHUPAL SINGH KANWAL
29
by providing aid to school, conducting medical and social awareness camps, helping in
formation of self help groups, etc as a part of corporate social responsibility. Thus the
project will bring socio-economic improvement of the area and will prove beneficial to the area.
*************