pre- feasibility reportenvironmentclearance.nic.in/writereaddata/online/tor/22...are now several...
TRANSCRIPT
PRE- FEASIBILITY REPORT
TABLE OF CONTENTS
Sr.No. Content Page No.
1.0 Executive Summary 22
2.0 Introduction of Project and Background Information 23
2.1 Identification of project & Project proponent 23
2.2 Copy of mining lease / letter of intent 23
2.3 Nature of the project 24
2.4 Need for the project 24
2.4.1 Importance to the Country & Region 26
2.5 Demand supply Gap 29
2.6 Imports v/s Indigenous Production 29
2.7 Export Possibility 29
2.8 Domestic / Export Markets 29
2.9 Employment Generation 30
3.0 Project Description 30
3.1 Type of the Project 30
3.2 Location 30
3.3 Size & Magnitude of Operation 31
3.4 Project Description 32
3.4.1 Process Description & Flow Diagram 32
3.4.2 Raw Materials 33
3.5 Water Requirement & Distribution 33
3.6 Waste generation 34
3.7 Resource Optimization / Recycling & Reuse Envisaged In
Project, If Any
35
3.8 Power & Fuel requirement 36
3.9 Purpose of EIA 37
4.0 Site Analysis 38
4.1 Connectivity 38
4.2 Land form, land use and land ownership 38
4.3 Topography 38
4.4 Existing Landuse pattern 39
4.5 Existing Infrastructure 40
4.6 Soil / rock classification 40
4.7 Climatic Details 43
4.8 Social Infrastructure 43
5.0 Planning Brief 44
5.1 Planning Concept 44
5.2 Man Power Requirement 44
5.3 Land use Planning 44
5.4 Facilities provided 45
5.4.1 Infrastructure 45
5.4.2 Green Belt Development 45
5.4.3 Health & safety System 45
5.4.4 Disaster Management and risk assessment 46
6.0 Proposed Infrastructure 46
7.0 Rehabilitation & Resettlement 47
8.0 Project Schedule 47
8.1 Proposed schedule and approval for implementation 47
8.2 Project Cost Estimation 47
8.3 Economic Viability 48
9.0 Analysis of Proposal 48
1. EXECUTIVE SUMMARY
Particulars Details
Location New Umrangshu Limestone Area,
Near Village – New Umrangshu, Taluka- Umrangshu,
Distt – Dima Hasao (N.C. Hills), Assam
Latitude 25°31’17.27” to 25°32’40.56” N
Longitude 92°47’54.36” to 92°47’26.39” E
Toposheet No. 83C/NE & 83C/14
Total Mine Lease area 200.0 ha
Mineable Reserves 84.35 MT
Capacity Proposed production – 4,44,500 TPA (ROM)
Life of Mine 188 years
Estimated project cost 260 Lac
EMP Cost 7.5 Lac / annum
Power Requirement NA
Fuel Requirement 1700 lits. /day
DG Set NA
Highest and Lowest Elevation
S. No. Particulars Elevation
(MSL)
1. Highest 445
2. Lowest 315
Land use Non Govt Barren Land
Nearest habitation/ town Umrangshu
Nearest Airport Borjhar (264 km)
Nearest Highway NH -27 and SH 7
Nearest Railway Station Lanka (62 km)
Power supply Umrangshu
Nearest Telephone Umrangshu
Nearest Dispensary and Govt.
Hospital
Umrangshu
Educational facility Umrangshu
Water demand and supply 12 KLD
Nearest tourist places None within the study area
Defense installations None within the study area
Archeological Features None within the study area
Ecological sensitive zones None within the study area
Nearest streams/ rivers/ water
bodies (from mine boundary)
Kopili River – 7.0 km in NW,
Langlai River – 8.0 km in SE,
Langyen River – 3.5 km E,
Mangla River – 8.1 km in NE,
Umrang Dam – 6.7 km in SW.
Seismic zone Seismic zone-V
2. INTRODUCTION OF PROJECT /BACKGROUND INFORMATION
2.1 Identification of the Project and Project Proponent
The Assam Mineral Development Corporation Limited (AMDC) is public limited
company wholly owned by Govt. of Assam. The company was incorporated on 19th
May 1983 under Companies Act 1956. (Certificate of Incorporation of the Company
is attached as Annexure No. 1) having the following aspects:
1. M/s Assam Mineral Development Corporation Limited is planning to excavate
limestone ore.
2. The unit is coming up in New Umrangshu area of Dist. - Dima Hasao (North
Cachar Hills) of Assam state.
3. The mining process to be adopted by M/s Assam Mineral Development
Corporation Ltd will simply be mechanized open cast mining with the use of
Excavator for loading of blasted rock
4. The mineral Limestone which will be excavated at the mine holds good market
in cement industry in India.
5. The promoters of the lease mine are well educated and highly experienced.
2.2 Copy of mining lease/ letter of intent
The AMDC was granted mining lease over an area of 33 hectares for mineral
limestone in the New Umrangshu area, District N.C.Hills, Assam vide letter no.
PEM/22/84/34 dated 21.09.1985, for a period of 20 years. Mining lease was executed
on 30.09.1988 for a period of 20 years. (Refer Annexure No. VI: Copy of Lease
Grant order of 33 ha. Area & Annexure No. VII: Copy of Lease Deed of 33 hect.
area.).
The company was granted another lease over an area of 167 hectares in the adjacent
area in New Umrangshu area vide letter no. PEM/22/84/228 dated 17.06.1992.
Refer Annexure No. VIII: Copy of Lease Grant order of 167 ha. area.
AMDC, applied for renewal of mining lease, on 22.07.2008 in Form J for both the
leases along with request for amalgamation of both the leases. Govt. of Assam
approved the amalgamation of both the leases vide their letter no.
PEM.22/84/Pt.I/11 dated 05.05.2010. Refer Annexure No. X: Copy of Approval
Letter for Amalgamation of leases.
Approval of mining plan along with progressive mine closure plan in respect of
Limestone deposit of M/s Assam Mineral Development corporation Ltd. Over an area
of 200 Ha N/v-Umarngshu in Dima Hasao (N. C. Hills) district of Assam State,
submitted under rules 16(1) of MCR 2016 & 23 (B) of MCDR 1988, vide letter No-
IBM/GHY/AS/DH/LST/MP-78 on dated 01/12/2016.
Refer approval letter of mining plan is attached as Annexure No-XII
The company has applied for Environment Clearance and TOR has been issued by
MoEF, New Delhi vide letter No. J-110015/443/2012-IA.II(M) dtd. 06.12.2013. (Copy
of TOR letter attached as Annexure No. I). Tor has been expiring due to get approved
mining plan. So we have again applied for fresh ToR.
2.3 Nature of the Project
M/s Assam Mineral Development Corporation Limited proposes to renew the
lease area for Limestone mine at Umrangshu area of Dima Hasao (North Cachar
Hills) District, Assam.
2.4 Need for the project
Limestone is an important mineral which is used in the manufacture of cement, as
flux in iron and steel production, and as raw materials for chemical industries. There
are now several cement factories which have come up in Assam due to the availability
of high quality limestone in the region.
2.4.1 Importance to the Country and Region
Limestone deposits of Assam are located in Karbi Anglong and North Cachar Hills
districts. Many limestone beds are interblended with coal-bearing sandstones. The
important areas with excessive limestone eposite in the districts are-Umrangshu in
North Cachar Hills district, Koilajan and Dillai Parbat in Karbi Anglong district.
Limestone (CaCO3) is associated with rocks composed of either calcium carbonate,
carbonate of calcium and magnesium, or mixtures of the two. If magnesium is
present up to 20 per cent it is called magnesium limestone and if it is above 20 per
cent it is known as dolomite limestone. Limestone deposits are of sedimentary
origin and occur in almost all geological formations of the country except
Gondwanas.
Limestone is mainly consumed in cement industry (76%), iron and steel industry
(16%), chemicals (4%), sugar, paper, fertilizer, and ferro-manganese industries
(4%).
The total recoverable reserves of limestone of all categories and grades are placed at
75,679 million tones. The total conditional reserves have been estimated at 701
million tones.
Regional Distribution
More than two-third of India's production of limestone comes from five states of
Madhya Pradesh, Rajasthan, Andhra Pradesh, Gujarat and Chhattisgarh each of
which contribute more than 9 per cent of the country's output of the mineral.
Karnataka, Tamil Nadu, Maharashtra and Himachal Pradesh (each producing over 5
per cent of the country's limestone) account for another 28 per cent of the country's
production of limestone.
Madhya Pradesh-Chhattisgarh-M P. and Chhattisgarh with estimated reserves at
2,126 million tones contribute 26 per cent of the total limestone production of the
country. Here extensive deposits of limestone occur at Katna and Jukehi Keymore
(Jabalpur district), Alaktara (Bilaspur district), Tikaria and Narsinghgarh (Damoh
district) and between Baijnath and Madhupur.(Rewa district) and near Maihar and
Satna areas (Satna district). Deposits of limestone also occur in Rajgarh, Raipur,
Durg, Bastar. Dhar, Betul and Sagar districts.
Andhra Pradesh-Andhra Pradesh, accounting for 15.99 per cent of the total
limestone production in the country, is the third largest producer of limestone in
India. Here important deposits are con- lined to Narji stage of Kurnool system. Main
producers are Vishakhapatnam, Krishna, Guntur, Karimnagar, Kurnool, Nalgonda,
Adilabad, Warangal and Mahbubnagar districts.
Rajasthan-Rajasthan occupies second place (16.23%) amongst the limestone
producing states of the country. Here cement grade limestone is obtained from
Ajmer, Banswara, Bikaner, Dungarpur, Jodhpur, Kota, Sirohi, Tonk, Bundi, Alwar,
Sawai Madhopur, Chittaurgarh, Nagaur, Pali, Jhunjhunu and Udaipur districts.
Gujarat-In Gujarat good quality of limestone is found near Pasuval, Diwania and
Khunia in Palanpur taluka of Banaskantha district; near Dari, Veraval, Savni,
Patan/Grokhundi, Sutrapara and Warodra in Junagarh district; near Posina in
Sabarkantha district; near Balasinar in Kheda district; and near Lanawada in
Panchmahals district.
Karnataka-Karnataka accounts for 10 per cent of the reserves and 8.37% of the
total production of limestone in the country. Here limestone deposits are scattered
in Bijapur, Belgaum, Shimoga and Gulbarga districts.
Tamil Nadu-In Tamil Nadu large reserves of limestones are found in
Ramnathapuram, Tirunelveli, Tiruchchirappalli, Salem, Coimbatore, Madurai and
Thanjavur districts. Except from Salem district much of the deposit is of cement
grade limestone.
Others-Other important producers are : Maharashtra-Yavatmal, Chandrapur,
Nanded, Ahmadnagar districts; Himachal Pradesh-Bilaspur Kangra and Chamba
districts; Orissa-Sundargarh (Birmitrapur, Hathibari, Purnapani, Katopuryheria,
Pagposh and Amghat),Sambalpur (near Malkanagiri), and Kalahandi (near
Rostamar, Bomok, Kinerbela and Parkela) districts; Bihar-Shahabad (Baujari-
Rohtas, Baulia-Chunhata-Dhananti and Birki-Chapla areas)district; Jharkhand-
Palamau, Hazaribag, Ranchi and Singhbhum districts; Uttar Pradesh-Mirzapur, Sone-
bhadra, Lucknow and Unnao districts; Uttaranchal; Assam-Nagaon and Sibsagar
districts; Meghalaya-Garo, Khasi and Jaintia hills districts; Haryana-Mahenderagarh
and Ambala districts; Jammu and Kashmir-Anantanag and Jammu districts; West
Bengal-Darjeeling and Jalpaiguri districts; and Punjab-Hoshiarpur district.
The project will provide much needed raw material for infrastructural industries in
the region. It will also generate revenue in terms of royalty, taxes etc. to the state. It
will also bridge the gap between demand and supply of raw material to the
consumers. The project will help in the overall growth of the region and surely
generate employment for local people.
2.5 DEMAND-SUPPLY GAP
The demand for cement mainly depends on the level of development and the rate of
growth of the economy. There are no close substitutes for cement and hence the
demand for cement is price inelastic.
With a goal of speed up the sustaining growth in the cement industry the
government has taken a range of steps in the Union budget 2011-12. The
infrastructure sector has received a momentum in the form of improved funds and
tax related incentives offered to magnetize investors for tapping the infrastructure
opportunities across the country. Introduction of tax free bonds, formation of
infrastructure debt funds and formulating a comprehensive policy for developing
public private partnership projects (PPPs) are some of the steps that will provide
required stimulus for growth of the cement industry in India.
2.6 IMPORTS VS. INDIGENOUS PRODUCTION
There will be no import for the project. There will be indigenous inputs in the entire
mining activity.
2.7 EXPORT POSSIBILITY
The mining activity is not prospecting exports.
2.8 DOMESTIC/EXPORT MARKETS
2.8.1 DOMESTIC MARKET
The demand for Limestone for cement making has been increasing every day. The
mine project aims to cater the raw material requirement of the nearby areas cement
plant.
2.8.2 EXPORT MARKET
All Limestone will be used for the captive purpose.
2.9 Employment Generation (Direct or Indirect due to the project)
Project will create direct & indirect employment opportunities within the
surrounding region. Unit will use good faith efforts to employ local people
from the nearby villages depending upon the availability of skilled & un-
skilled man-power surrounding the project site.
In operation phase, the proposed project would require significant workforce of
non-technical and technical persons. Migration of highly educated and skilled
person will result in increase of literacy in the surrounding villages.
In addition, the proposed project shall enhance the prospects of employment.
3.0 PROJECT DESCRIPTION
3.1 Type of Project
The proposed project is mining unit of Limestone ore. It is a mining project which
will be developed in Dima Hasao (NC Hills) district of Assam.
3.2 Location
M/s Assam Mineral Development Corporation Limited proposes to set up
Limestone Mine near village New Umrangshu, Dist. Dima Hasao (NC Hills), Assam.
Google map is shown in Figure - 1.1.
→ Mine Site
The lease area forms a part of Survey of India topo-sheet no. 83C/NE & 83C/14 lying
the co-ordinates Latitudes 25°31’17.27” to 25°32’40.56” N & Longitudes 92°47’54.36”
to 92°47’26.39” E. The deposit can be approached by an all weathered road from
Guwahati via Nangaon, Doboka and Lanka, covering 254 km. except for last 40 km.
which passes through hilly terrain, the road is on flat country. The deposit is 140
km. by road from Shillong via Jowai. Umrongshu is connected with Halflong, the
district H.Q. of N. C. hills, by an all-weather road of 109 km. The nearest railway
station is Lanka 62 km. is on meter gauge section of the N.F. railway. The nearest
civilian airport Borjhar is at a distance of 264 km.
3.3 Size/Magnitude of Operation
M/s Assam Mineral Development Corporation Limited proposes to produce
Limestone @ 4, 44,500 TPA (ROM) in the plot area of 200.0 hectares.
3.4 Project Description
3.4.1 Process Description & Flow Diagrams
The mineral produced here will be sold to nearby industries or buyers. It is
proposed to produce 4,44,568 tonnes of ROM per year.
The area is located in hilly terrain and involves development of access road and
removal of overburden. Being new project ancillary facilities are also required to be
developed.
It is proposed to work the deposit by mechanized open cast method of mining with
the use of excavator for loading of overburden. Following broad design parameters
have been considered.
Bench height of 6.0 m will be developed.
Minimum bench width will be 18-25 m.
Individual bench slope will be 80o from vertical.
100-115 mm dia blast holes using wagon drill.
Excavator of bucket capacity 0.93 cu.m. will be used.
For ore and waste 15 tons tippers are proposed to be used.
Haul roads will be developed at minimum gradient of 1:16.
ANFO with cap sensitive explosive will be used.
Secondary blasting will be carried out as and when required.
Water sprinkler will be used for dust suppression in the mine.
Provisions of MMR 1961 will strictly be adhered.
As per the present scenario the mining will be done mechanically. Mining will be
mechanized opencast mining by forming benches of 6.0 m height. 100-115 mm dia.
holes will be drilled and blasted using ANFO & slurry explosive. Loading of
limestone into trucks will be with the use of excavator. Individual bench slope will
be 80o. At the end of mining plan period about 26.040 hect. area will be covered
under mining, 6.200 ha under waste dump, 1.510 ha under approach road, 15.180
ha. under plantation and 1.500 ha under infrastructure development. On the above
techno-economic as well as environmental consideration, the conceptual mining
plan has been drawn keeping 45° ultimate pit slope angle.
FLOW CHART
MINING OF LIMESTONE ORE
3.4.2 Raw materials
Sr No Raw Material Quantity
1 Explosive 400kg/day
2 Fuel (HSD) 1700 lits. /day
ROM (Run of Mines)
Sorting Waste to
waste dump
Limestone stack Sold to other
buyers
Sold to other Industries
3.5 Water Requirement & Distribution
Umrongshu and neighbouring areas lie in the western extremity of N.C. hills district
and are bordered on west by the Kopili river. The region constitutes the eastern
flank of the Shillong plateau. The drainage system of the area is controlled by river
Kopili that flows in an east – west direction. Streams like Largen, cut across the main
deposit forming ravines.
The Amrang Nalla cuts across the lease area and flows west to east. Very little water
remains in the nalla during eight months period of the year, however the nalla
remains very active during monsoon.
There is no permanent water body or any perennial stream located in the
area/proposed working site. The surface accumulated water body in the area is out
of question, as the sub-surface formation is porous, which allows water to percolate
fast into sub-surface making area dry very soon.
The water requirement for the proposed project will be met from the Dug wells /
Tube wells situated outside the lease area. The daily water requirement is about 12
KLD. Details are shown in table below:
Sr. No. Purpose Total Requirement (KLD)
1 Dust suppression 5.5
2 Drinking 2.0
3 Green belt 4.5
TOTAL 12.0
3.6 Waste Generation
The deposit is exposed on the surface and stratified. The Kopili formation forms
upper most unit of the Jaintia Group and is composed of alternation of gray to
brown splintery shale and yellowish brown sandstone with loose nodules of
ferruginous sandstone. The overburden consists of shale and sandstone.
The year-wise accretions of overburden are given below:
Year Waste Limestone (ROM) Stripping Ratio Cu.m. Cu.m. Tones Waste: Mineral
Cu.m. Cu.m. First 237,152 127,282 330,932 0.86:1
Second 215,450 145,260 377,675 0.48:1
Third 262,510 162,600 422,760 0.61:1
Fourth 277,402 171,012 444,631 0.62:1
Fifth 266,470 170,990 444,574 0.56:1
Total 1,258,984 777,144 2,020,572
3.7 RESOURCE OPTIMIZATION/RECYCLING AND REUSE ENVISAGED IN THE
PROJECT, IFANY, SHOULD BE BRIEFLY OUTLINED
3.7.1 RESOURCE OPTIMIZATION
Resource optimization has been done quality wise and quantity wise. The geological
cross-sections along section lines 200N to 1800N have been utilized for calculating
the resources in the Measured Mineral Resources category (UNFC 331). The
resources from the remaining area have been assessed on the basis of average
thickness of limestone in the measured category. Remaining resources are classified
under UNFC code 332.
CATEGORY CODE Quantity
Total
Resources
(A+B) 296.895
Reserves (A) Proved (111)
Probable (121)
(122) 84.354
Remaining
Resources (B)
Feasibility Mineral resources (211)
Pre-Feasibility Mineral resources (221)
(222) 10.974
Remaining Measured Mineral Resources (331)
Remaining Indicated Mineral Resources (332)
Inferred Mineral Resources (333) 201.566
Reconnaissance Mineral Resources (334)
Life of Mine;
Mineable Reserves 84.35 million tonnes
Proposed to be mined in MP Period 2.02 million tonnes
Future rate of production 0.45 million tonnes
Remaining Reserves at the end of Plan
Period
82.33 million tonnes
Mine Life after Plan Period 82.33/0.45 = 183 years
Total mine life 183+5 = 188 year 188 years
Summary of Grade:
CaO MgO Fe2O3 Al2O3 SiO2
Limestone 48.02 1.31 2.90 3.01 5.38
3.7.2 PIT OPTIMIZATION
To optimize the excavation of Limestone overall mining limit for the conceptual
mining plan has been fixed at 304 mRL. Based on the present mineable reserve and
conceptual mining plan of the area is prepared, refer plate no. 5.
On the above techno-economic as well as environmental consideration, the
conceptual mining plan has been drawn keeping 45° ultimate pit slope angle. A
7.5 m barrier will be left all along the mining lease boundary. No barrier will be left
along the common lease boundary of other adjacent area of the lessee.
On the basis of Ultimate pit design, Total Minable reserve is established as
121,640,000 tonnes that gives the life of mine 269 years with rated production of
4,44,500 tons per annum (ROM) from sixth year onwards.
3.8 Power and Fuel Requirement
No electricity will be required. Fuel (HSD) will be obtained from authorized public
fuel station & about 1700 lits. /day H.S.D. will be used in machineries during mining.
Mostly mobile equipment’s, so their expected emission will be very less and will
have less impact.
3.9 Purpose of EIA
4 SITE ANALYSIS
4.1 Connectivity
4.2 Land form, land use and land ownership
The lease area is undulating and hilly. Agriculture is the main stay of the tribal
population of the districts. The traditional method of cultivation is the slash & burn
one, commonly known as Jhuming. Whole land in the lease area is Non-Govt. barren
land. Neither, National Park, Archeological monument, etc. or other private land is
within the lease area or in nearby area.
The overall literacy rate in the village of buffer zone area is approximately 24%
while that in Umrangshu town is about 50%. Population of the district is 9131.
There is no habitat with in the core zone. In buffer zone of the study area main
workers are 40.43% and marginal workers are 4.72% resulting into 54.85% non-
workers indicating at chronic unemployment problem. The occupational pattern of
the people is approximately as under Mining - 10%, Trade - 12%, Agriculture - 1% &
Industry - 77%.
Sr.No. Particulars Details
1 Nearest Highway SH - 7 (1.7 km SW) & NH - 27
2 Nearest Railway Station Lanka (62 km)
3 Nearest Airport Borjhar (264 km)
4.3 Topography
The limestone belt of the Kopili valley area constitutes the south eastern flank of the
Shillong plateau and comprises of small flat topped hillocks with elevation varying
from 580 m to about 840 m above mean sea level (MSL). The highest altitude
(837.29 m) in the region has been observed at Khandong, about 12 Km west of New
Umrangshu. The proposed lease area is part of N, NW – S, SE trending ridge in the
hilly terrain of the region.
In the New Umrangshu area the highest altitude of about 445 MSL is located in the
extreme Northeastern part while the lowest altitude of about 360 m is present in the
valley of Amrang nalla flowing west to east in the central part of the area.
The Amrang nalla flows through the central part of the lease area, dividing the area
into two separate zones. The Amrang nalla with its tributaries constituted the
geomorphological disposition of the local terrain.
The drainage of the area is collected through many nallahs discharging in the
Amrang nalla and Langyen nalla. Both side these nalas join in the south eastern side
of the area, near the Langyen basti and flows in a south eastern direction with the
name of langyen nalla, which ultimated flows in the Kopili River. The local nalas
generally carry meager drainage during dry season. While in rainy season their
water level may rise considerable from the bottom for short period of heavy rains.
The Amrang nalla being typical hilly terrain drainage cuts through the high ground
creating gorges.
The master drainage of the region is thus controlled by the Kopili River. Near
Garampani the Kopili river system had been harnessed to create a multipurpose
hydel power project, which generated 150 MW power. Kopili reservoir is the source
of water for agriculture and industrial area.
4.4 Existing Land use Pattern
The lease area is a Non-Govt. Barren land. There is no reserves forest or protected
forest land within the lease area. There is no village or hutments within the lease
area. Existing land use pattern is given as below:-
Table 4.1 Land Use/ Land cover details of study area
Particular Forest
land
Agriculture
land
Grazing
land
Waste
land
Total
Pit/Quarries -- -- -- 6.390 6.390
Waste dump -- -- -- 3.190 3.190
Road &
Building
-- -- -- 2.138 2.138
Plantation -- -- -- 5.180 5.180
Ag. land -- -- -- 0.0 0.0
Mineral stack -- -- -- 0.0 0.0
Remaining
land
-- -- -- 183.102 183.102
Total -- -- -- 200.0 200.0
4.5 Existing Infrastructure
Site services as per Mines Rules 1956 are available in the area. An explosive
magazine and ANFO mixing shed is also in operation in the area. First Aid station,
Toilets as per the provisions of Mines Rules shall be continued to be maintained.
Regular medical checkup of the mine employees will be carried out as per the
provisions of Mines Rules 1956.
4.6 Soil / rock classification
The hill slopes of the zone have red loamy soils and old alluvial soils cover the plains
of North Cachar Hills. The soils are categorized into ferruginous and laterised red
soils which are red to reddish brown/deep reddish brown in color. Due to varying
altitudes and location of hill valleys, temperature remains high during summer and
mild in winter.
4.6.1 Description of the rocks units within the lease area:
The Geological succession of the area is given below:
Table 4.2
LOCAL STRATIGRAPHIC SEQUENCE
Group Formation Lithological units Thickness
Jain
tia
( E
oce
ne
)
Kopili Shale &
Sandstone
Shale & sandstone 0-8 m
Sylhet Limestone
Formation
Top Band limestone 28 – 29 m
Bottom Band limestone 50-52 m
Basal sandstone Sandstone with carbonaceous shale Not Known
Basal Sandstone: The Basal sandstone formation lying unconformably over the
pre-cambrian is mainly made up of whitish to pale brown sandstone, medium to fine
grained, slightly quartzitic with occasional presence of carbonaceous shales and thin
coal seams. It makes its presence along Amrang nala.
Bottom Band limestone: Immediately above the Basal sandstone lies the bottom
band limestone. The contact is a gradual one. This band was encountered in all three
boreholes. It has an average thickness of about 50 m based on physical, chemical
and lithological characters; this band can be classified in to three recognizable sub
horizons as stated below:
(a) Top dirty gray to gray limestone with shale intercalation
(b) Middle gray to high gray massive and compact limestone.
(c) Lower gray limestone with sandy limestone band
The lower unit tends to become arenaceous towards bottom. In fact, the contact
with Basal sandstone formation is more or less gradational. Thickness of sub –
horizons varies from 6 to 8 m.
Thickness of middle unit varies from 20 to 28 m. Limestone of this horizon contains
comparatively higher CaO with lesser Fe2O3, Al2O3 and SiO2. The topmost horizon of
limestone unit is gray in color. It shows comparatively lower CaO content and higher
Fe2O3 and Al2O3 compared to underlying unit. The thickness of this unit varies from
20 to 25 m.
Intermediate shale: The top band and bottom band limestone are separated by a
thin but persistent shale band, thickness of which varies from 5 to 7 m. This shale is
encountered in two boreholes (NU- 12/3) & NU 12/4). In the remaining borehole
AMD-1 it was missed as this borehole was located at a lower level than the shale
band. The shale is dark gray in color with occasional thin shally limestone band.
Top Band Limestone: The top band limestone shows an average thickness of 29 m.
This band was punched through 2 bore holes (NU12/3 & NU 12/4). It is
characterized by highly ferruginous and argillaceous carbonate with low CaO
content. On the basis of physical character and chemical composition, this unit can
be demarcated in to sub units. The lower 20 to 22 m grey to dirty grey in colour,
highly fossiliferous, comparatively less hard and less compact with frequent
presence of shally matter. The top most 8 to 10 m is reddish in colour, highly
ferruginous limestone. It is hard and compact with evenly distributed mega fossils.
Kopili Sandstone & Shale: The Kopili formation forms the upper most unit of the
Jaintia Group and is composed of alternation of gray to brown splintery shale and
yellowish brown sandstone with loose nodules of ferruginous sandstone. Thin
bands of calcareous shale and impure limestone are also seen at places. This
formation is encountered in two boreholes. The kopili formation generally occupies
the ridge top. The sandstone is medium to fine grained well sorted , whitish to
brown in colour. It is soft and sometime friable. The shale is dark gray to brownish
in colour and splintery in nature. The limestone band shows the following chemical
composition in totality:
Radicals (%) Lime Grade Cement Grade
SiO2 2.40 5.38
CaO 49.50 43.02
MgO 0.47 1.31
Al2O3 0.95 3.01
Fe2O3 1.95 2.90
4.7 Climatic Details
The climate of the district of N.C. Hills is fairly diverse climate with an average
annual precipitation of around 1500 mm to 2000 mm with average of 1673 mm and
40 to 90% relative humidity. The rainfall is mostly distributed between the months
of July and September. About 90 percent of the annual rainfall is received during the
period June to September, July and August being the rainiest months. The variation
in annual rainfall from year to year is very large. During the North-East monsoon
season, the relative humidity is generally over 90 percent. The coldest month is
January and the hottest month is May.
The micro meteorological conditions at the mine site determine the transport
diffusion pattern of air pollutants released into atmosphere. The principle variables
include horizontal connective transport (average wind speed and direction) vertical
convective transport (atmospheric stability) and topography of the area.
Based on the Meteorological data such as wind speed, wind direction, temperature,
and relative humidity from IMD station summarized as below:-
TABLE 4.3: MICRO-METEOROLOGY
SUMMER SEASON
Temperature
°C
Relative humidity
%
Wind Speed(km/hr) & Direction
8.30 Hrs. 17.30 Hrs.
Max. Min. 8.30 Hrs. 17.30 Hrs. Direction Speed Direction Speed
32.2 18.5 70 34 NE 04 SW 04
4.8 Social Infrastructure
The infrastructure that exists within the lease area is an explosive magazine and
ANFO mixing shed, toilets, first aid stations etc.
The nearest village is Umrangshu, there educational facilities are available in the
form of primary and secondary schools.
Medical facilities, Primary Health Centre are there in the area, imparting services,
for advance medical facilities. In each village one health worker has been appointed
by the Govt. to provide primary health facilities.
Village people are availing drinking water facilities generally from the Hand pump,
open well and tube well. The water supply is also supplied through tanker in few
villages. During summer scarcity of water has been noticed.
Communication services like post office and telephones are available in the nearby
village. Some of the villagers are having mobile phones.
5. PLANNING BRIEF
5.1 Planning Concept
M/s Assam Mineral Development Corporation Limited proposes the renewal of a
mining lease to produce 4,44,500 TPA (ROM) of Limestone mineral. It is situated in
Dima Hasao (NC Hills) District of Assam.
5.2 Man Power requirement:
Man power requirement for mining is estimated to be 36 Nos. Most of the
employees will be recruited from neighboring village.
5.3 Land use Planning:
Land use pattern (Hects.)
S.
No. Activity Present
At the end of
5th year
At the end of
lease period
1 Pits 6.390 26.040 90.720
2 Waste Dump 3.190 6.200 10.000
3 Road & building 2.138 3.010 4.000
4 Plantation 5.180 15.180 27.800*
5 Agriculture land 0.0 0.0 0.0
6 Mineral stack 0.0 0.0 0.0
7 Remaining Land 183.102 149.570 67.480
Total area 200.0 200.0 200.0
Note: - *Plantation along lease boundary & barren land – 27.80 ha and on the dump site –
10.0 ha.
5.4 Facilities Provided:
5.4.1 Infrastructure
The infrastructure required is office, store, and shelter for workers and these will be
provided at the mine site. For drinking, water will be brought from the well
outside the lease area & this water is potable. Most workers will be from nearby
villages so no accommodation at mine site will be required.
5.4.2 Landscaping and Green Belt Development
It is proposed to plant a total no. 4000 trees per year during five year plan period.
An effort will be made in the first three years to cover the entire green belt area
along the statutory lease barrier. By the end of lease period about 27.8 ha. area will
be covered under plantation. Year wise plantation is shown on the layout plan
(Refer plate no. 6). The total proposed area for afforestation is 10.0 hectares and
expected survival rate is 90%.
A number of species will be planted suitable to this area of climate conditions
like Neem, Sagwan, Banyan, Pilu, Baval etc. The afforested area will be encircled
by a barbed wire fence to protect it from cattle’s and regular watering thrice a
week (except monsoon) and maturing as required will be done.
YEAR’S NO. OF PLANTS AREA (IN Hect.) SURVIVAL RATE FIRST 4000 2.0
90% SECOND 4000 2.0 THIRD 4000 2.0
FOURTH 4000 2.0 FIFTH 4000 2.0
5.4.3 Health and safety System
During the opencast working, and allied activities, all the precautionary measures
shall be taken into account as per Reg. 106, 181, 182 & 183 of MMR 1961 and Rules
31, 35, 37, 38 & 39 of MCDR 1988 for safety and security.
Following Safety & security measures will be enforced;
Moving front of the quarry shall have temporary fencing.
Permanent fencing will be provided where quarry has reached the ultimate
pit limit.
Mine entrance will have a permanent check post and record shall be
maintained of all persons / vehicles entering the mine area.
Round the clock security arrangement shall be provided to prevent
inadvertent entry of persons.
5.4.4 Disaster Management and risk assessment
The mining activities will involve accident like landslides, fall of material or
equipment from benches and failure of dump retaining wall. The company will
prepare a detailed emergency plan in consultation with DGMS. During heavy rain
mining activities will be closed.
6. PROPOSED INFRASTRUCTURE
S.NO Details
1 Mining Area 200 hectares.
2 Residential Area Not Applicable
3 Connectivity Nearest Highway: Highway NH 27
Nearest Road: Umrangso road SH 7 (1.7 km
SW)
Nearest Railway Station: Lanka Railway
Station (62 km)
4 Green Belt 27.80 hectare will be reserved for green belt
development in the proposed facility.
5 Water Management 12.0 KLD Source: Dug wells / tube wells
6 Power Management N.A.
7 Waste Water Domestic Effluent treated in soak pits and
overflow used for gardening
8 Solid Waste
Management
Over burden disposed at proposed site
9 Hazardous waste
Management
N.A.
7. REHABILITATION & RESETTLEMENT PLAN
Since the project site is a Non-Govt. waste land, there is no reserves forest or
protected forest land within the lease area. There is no village or hutments within
the lease area. R&R is not applicable to this project.
8. PROJECT SCHEDULE
8.1 Proposed Schedule and Approval for Implementation
The Proposed project shall be established after getting the Environmental Clearance
from MoEF.
8.2 Project Cost Estimation
Estimated Project Cost for the proposed project is 260 lakhs.
(A) Capital investment
A site office, store & rest shelter = Rs. 5,00,000/-
Machinery & Tools = Rs 21,000,000/-
Bank Guarantee (Financial assurance) = Rs. 12,60,750/-
Approach road = Rs. 1,557,000/-
PMCP first year = Rs. 1,499,000/-
Social fund & activities = Rs. 2,00,000/-
Total cost = Rs. 26,016,750 /-(say 260 Lac.)
(B) Operational cost-
The mineral will be mined from the lease area, the cost of per ton mining will be
app. Rs. 301.11/- per tonne
8.3 Economic Viability
The anticipated cost of mining is Rs. 301.11/- per ton cost. Average sale value is
assumed at Rs. 1000/- ton of Cement. Hence the project will be viable.
9. ANALYSIS OF PROPOSAL
Project will create direct & indirect employment opportunities within the
surrounding region. Unit will use good faith efforts to employ local people from
the nearby villages depending upon the availability of skilled & un-skilled man-
power surrounding the project site.
In operation phase, the proposed project would require significant workforce of
non-technical and technical persons. Migration of highly education and skilled
experience will result in increase of literacy in the surrounding villages.
In addition, the proposed expansion of project shall enhance the prospects of
employment.
Assessment of the potential socioeconomic benefits during mining
focused primarily on work force requirements, acquisition of supplies, and the
temporary increased demand for services related to the mining project like
food, housing, communications, law enforcement, medical care, local transportation
etc. Due to these, additional revenue to local suppliers for required products and
services related to the construction and operation phases of the project will generate.
Thus, mining activities will provide numerous new, although temporary, work
opportunities for both skilled and unskilled labor, as well as contribute
significantly to the local economy.
Additional government revenue expected from royalty, taxes, duties and other fees.
An added benefit to the proposed project will result in considerable growth of
stimulating the industrial and commercial activities in the state. Small and
medium scale industries may be further developed as a consequence.
----------*************------------
ANNEXURES
Annexure No. I Copy Of Tor Letter
Annexure No.II Copy Of Certificate Of Incorporation Of The Company
Annexure No. III Copy Of Board Resolution In Favor Of Nominated Owner
Annexure No. IV Copy Of List Of Board Of Directors
Annexure No. V Copy Of Photo Id And Address Proof Of The Nominated Owner
Annexure No. VI Copy Of Lease Grant Order Of 33 Ha. Land
Annexure No. VII Copy Of Lease Deed For 33 Ha.
Annexure No. VIII Copy Of Lease Grant Order Of 167 Ha. Land
Annexure No. IX Copy Of Lease Deed For 167 Ha.
Annexure No. X Copy Of Approval Letter For Amalgamation Of Leases
Annexure No. XI DOC
Annexure-XII approval letter of mining plan