Need a More Structured Approach – 10,000 Ft view
• Mission Requirements
• Operating Environment
• Component Availability
• Experience and Heritage
Harsh Environment – Getting There
Launch• Acoustic Loading• Vibration• Random and Sine
• Shock • Depressurisation – Venting• Electro Magnetic Interference
Harsh Environment –Operating there
Operation• Temperature• Radiation• Reliability• Long Operating life
• Electro Magnetic Interference
What are some of the Processors are Available
Processor Architecture MIPS Comments
LEON 3 FT ASIC Dual SPARC V8 200 100 MHz
LEON 3 FT AISC Single SPARC V8 75 66 MHz
LEON 3 FT FPGA RTAX SPARC V8 20 25 MHz
RAD 750 Power PC 400 200 MHz
PC 7448 Power PC 3000 1267 MHz
ARM7-TDMI ARM7 36 40 MHz CubesatNot Rad Hard
Mongoose-V MIPS R3000 8 10 - 15 MHz
Processor Selection
PerformancePower
ManagementRedundancy Architecture
PCB Mounting
Operating Systems
Communication IF’s
Debugging Tools
Radiation
• Key Driver for achieving mission requirements
• Million Instructions Per Second
• Number of Instructions per Clock Cycle – Scalar / Vector / Superscalar
• Floating Point Unit
• Multicore
• Hardware Acceleration / Peripherals
• Direct Memory Access
• Memory Bandwidth
Performance
• Drives the thermal management of the payload –Conversion losses
• How many voltage rails are required – this complicates the power architecture - increasing losses and decreasing MTBF, Weight etc.
• Does the processor have low power modes
• Can we reduce the core frequency if desired – Dynamic Power Management
• Voltage scaling
Power Management
• How our equipment communicates externally
• On Chip Peripherals for communication
• Simple UART, SPI, I2C, Ethernet, PCIe
• DMA Provided to reduce load on processor
• Is the bandwidth sufficient for the application requirements
Communication IF’s
• Operating system enables scheduling of processes and processor resources
• Application dependant
• Hard Real Time
• Soft Real Time
• Do we need an operating system – Can it be achieved using a bare metal solution
• Certification – DO178B, Sil3
• Examples in use in space missions
• RTEMS, VxWorks, uC/Osii, eCOS, Linux (RTAI and Xluna)
Operating Systems
• Development Environment
• Can we debug at the system level
• Can we examine the processor state without impacting programme execution
• Can we profile the application
• Can we trace where the processor has been
• Is it possible to analyse communication protocols on communication interfaces
Debugging Tools
• Often the most over looked aspect
• Is it BGA, CGA or QFP
• Impacts reliability – BGA balls fail, Column Crack,
• How it mounts has a large impact on how we perform thermal management.
• Number of IO required
• Is the mounting method currently qualified for your manufacturing facility
PCB Mounting
• Is the device latch up immune
• Can it experience SEUs
• What is the maximum Total Ionising Dose
• Does the processor contain fault tolerant circuits e.g ECC / EDAC to correct for faults
• Is there a watchdog provided for lock ups – often thsneeds to be independent.
Radiation Tolerance
• Is Redundancy required ?
• Inter or Intra module
• Hot or Cold spared
• Cost and Weight driver
• Redundancy approach for SW
• External / internal watchdog provided for SEFI
Redundancy Architecture
• For Space Applications there are some mitigation strategies we can follow
• Redundancy at the Instruction level
• Redundancy at task level
• Redundancy at application level
• ESA Handbook – Techniques for Radiation Effects Mitigation in ASICs and FPGAs is provides a good understanding for all engineers – does include a section on processors.
SW Techniques
Processor Selection
Component CostSW Design
CostsHW Design
Cost
Technical Risks
Schedule Design Reuse Heritage & TRL
Programme Risks
• Goal is meeting mission requirements within the available budget.
• Number of Cost drivers
• Bill of Materials
• Engineering Life Cycle costs – design reviews
• Design / Verification / Integration costs for HW and SW
• Certification programmes
Costs
• Any Programme will have a number of risks technical and programmatic
• Technical risks relate to engineering aspects i.e. Quality
• Programmatic relate to cost and timescale
• Process
• Identify candidate risks
• Identify applicable standards, laws, agreements and company policies
• Analyse Risks / Plan Risk Management / Evaluate
• Risk Profile and Risk Strategy will result
Risks – Technical and Programmatic
• Not necessarily the domain of the project manager but also the Work Package Manager.
• All projects want to deliver
• On Schedule, On Cost, On Quality
• Schedule will define the engineering and programmatic milestones –enables progress to be tracked
• Crucially it will enable past performance to be used as an indicator of future performance
• If you are slipping 6 months in 12 months for example, without addressing the issues via a recovery programme future performance will continue to slip 6 months in 12.
Schedule
• Does the processor have any heritage in the application. Reduces risk of implementation or qualification issues
• Technology Readiness Level
• Determines the readiness level of the technology to be used in your application
• ESA have 9 levels from concept to proven and used on a mission.
• TRL development plan – shows the path taken to prove the system to the required level.
Heritage & TRL
• Enables faster time to market
• Requires a development rules to enable reuse
• Increases quality as it is used across several projects
• Enables the estimation of new projects to be undertaken easier
•
Design Reuse