practical configurations for the ska - nrao safe … configurations for the ska rob millenaar spdo...
TRANSCRIPT
Practical Configurations for the SKAPractical Configurations for the SKA
Rob Millenaar
SPDOSPDO
April 2009 1CALIM09 SPDO/RPM
A shifting target
A sobering thought:
We have reached a point in time where the next generation large radio astronomical facility, the SKA, has to consolidate current thoughts on how to lay out
h t d d i th fi tisuch a system, and design these configurations, even when ongoing insight will challenge these designs before the telescope will be builtbefore the telescope will be built…
We have to do the best we canWe have to do the best we can.
April 2009 CALIM09 SPDO/RPM 2
Overview• Introduction
– Setting the scene
– The Configuration Design Task Force
• Configuration DesignReferences– References
– Identification of key issues
– Parameters, figures‐of‐merit
• Real world aspects– Masks
Infrastructure cost– Infrastructure cost
• Final remarks– Status
– The science loopApril 2009 CALIM09 SPDO/RPM 3
Configurations for the SKA
PrepSKA tasks us to do:WP3.5: Optimize the array configuration
“Study the ideal configurations for the SKA for the different Key Science Projects and determine the single configurationKey Science Projects and determine the single configuration that optimises the total return from the Key Science Projects. Match the “ideal” configuration to the geographical realitiesf th t h t li t d it i d t d t i thof the two short‐listed sites in order to determine the
optimum configuration for each site. (...)”
The due date for this is T+18 (end 2009).
April 2009 CALIM09 SPDO/RPM 5
Configurations for the SKASo, in practical terms, by the end of this year the SPDO has to:SPDO has to:• study previous configurations work
• make an inventory of requirements, in relation to the currentmake an inventory of requirements, in relation to the current scientific framework: the Reference Science Plan
• derive figures‐of‐merit that are part of the configurations assessment process
• ensure that the configurations can be realised in the host environments – theMasksenvironments the Masks
• ensure that the developed configurations are economically feasible
• develop and use practical simulation and optimisation toolsApril 2009 CALIM09 SPDO/RPM 6
Configurations for the SKA
In other words:it i ti t t i b t th d i f th• it is now time to get serious about the design of the configurations,
• the results of earlier studies will have to be consolidated into this ‘final’ effort.
And in order to do so:• the science community needs to decide what they want the
SKA to be able to do (and the SWG is doing that),
th i i it d t ith• the engineering community needs to come up with technically and economically realistic scenarios for phase 1 and 2, for SKA‐lo and SKA‐mid (and WP2 and 3 are doing that too).
April 2009 CALIM09 SPDO/RPM 7
Configurations for the SKA
Urgency in designing configurations:g y g g g• We need to do additional high sensitivity RFI monitoring measurements, at the core, but also at a gnumber of ‘representative’ remote stations.
• So, we have to find out which locations will very likely be chosen as remote stations for doing the measurements.
• And these monitoring activities will start in the second half of 2009.
April 2009 CALIM09 SPDO/RPM 8
Configuration Design Task ForceTask Force
• For this configuration design work, a Task Force has been assembled, under the SCWG: – Rosie Bolton (University of Cambridge)
– Mattieu de Villiers (SKA South Africa)
– Sundaram (Jive, NL)( , )
– Rob Millenaar (SPDO, [email protected])
– small number of ‘sounding board’ contributorssmall number of sounding board contributors
• A report with two configurations, one for each host is expected by the end of 2009host, is expected by the end of 2009.
April 2009 CALIM09 SPDO/RPM 9
Configuration Design Task ForceTask Force
• The simulations and optimisations tool that isThe simulations and optimisations tool that is going to be used for that is Mattieu de Villiers’ AntConfig programAntConfig program.
See: http://www.kat.ac.za/public/wiki/AntConfigSee: http://www.kat.ac.za/public/wiki/AntConfigfor the latest Windows version of AntConfig (V1.4), and a preliminary Mac version of iAntConfig.
April 2009 CALIM09 SPDO/RPM 10
Kick‐off meeting
In March 2009 a kick‐off meeting for the work of h T k F h ld i M hthe Task Force was held in Manchester. The 2.5 day workshop established what the SKA
i id b hcommunity considers to be the:
• scientific and engineering boundary conditions,
• requirements of the configurations, q g
• physically and economically feasible targets,
• appropriate methods and tools• appropriate methods and tools.
April 2009 CALIM09 SPDO/RPM 11
Kick‐off meeting
The outcome of this meeting was that:
h T k F d d h i d f• the Task Force understands what is expected of them, to be delivered by the end of 2009;
th SKA it d t d th t th T k F• the SKA community understands that the Task Force is working towards “final” configurations, which will go into the costed design for the SKA phase 1 thego into the costed design for the SKA phase 1, the PrepSKA main deliverable, and phase 2.
• Nevertheless, there are a number of open issues that the two host countries and the SPDO have to get agreement on.
April 2009 CALIM09 SPDO/RPM 12
References
Apart from drawing information from previous and ongoing work (EVLA ALMA ATA LOFAR LWA SKADSongoing work (EVLA, ALMA, ATA, LOFAR, LWA, SKADS, the precursor telescopes, etc), two baseline documents are used:are used:
1. Memo 100: Preliminary Specifications for the Square Kilometre Array (last issue 12/2007)q y ( / )
2. The Square Kilometre Array Reference Science Plan: SKA‐mid and SKA‐lo of the SWG. A work in progress: current draft March 6, 2009 and the final version should be ready by 2010.
April 2009 CALIM09 SPDO/RPM 14
References3. Information available from the site bids of 2005
4. RFP, CSTF Guidelines: CSTF=C fi ti Si l ti T k F
4. RFP, CSTF Guidelines:• Max angular resolution
• axial ratio of PSF
if i d i l i f
Configuration Simulation Task Forcechair Steven Tingay(2006)
• uniformity and circularity of uv coverage
• PSF sidelobe levels
– evaluated for:• long integration obs
• short integration obs (snapshots)
• continuum multi freq synthesis (MSF) observations• continuum multi‐freq synthesis (MSF) observations
• spectral line (narrow band, single channel) observations
Note that the RFP specified that min elevation for any station should be 30° Thi b id d30°. This must be reconsidered…
April 2009 CALIM09 SPDO/RPM 15
References5. From the CSTF, the evaluation of the LNSD
configurations report, example:
• uv coverage and psf calculations, done for:– 4 h obs for northern vis limit (4 h obs time available for all stations) for MFS (25% frac bw) and sp. line (single channel)
4 h obs for southern vis limit MFS+sp line– 4 h obs for southern vis limit, MFS+sp. line
–max duration at declination of pk vis, MFS+sp. line
– snapshot (5 mins) for northern vis limit, MFS+sp. linep ( ) , p
– snapshot for southern vis limit, MFS+sp. line
– snapshot at declination of pk vis, MFS+sp. line
April 2009 CALIM09 SPDO/RPM 16
Reference Science Plan• Purpose
Is an assembly of science component studies to be used to define the requirements (SKA‐low and mid only)
• Structureh f h ’ hFor each of the KSP’s one or more components, with
summary of scientific and technical requirements per component.p
• StatusBeing written by the SWG. Latest draft March 09, not released. Final version expected by 2010.
• The RSP is used for configuration designStarting assumptions performance parametersStarting assumptions, performance parameters.
April 2009 CALIM09 SPDO/RPM 19
Reference Science PlanScience Case
Reference Science Plan (Requirements)
Case StudiesEng. Simulations
Technical R&DPrototypesPathfinders
ConfigurationCostingCosting
Readiness
Engineering Design
April 2009 CALIM09 SPDO/RPM 20CALIM09 SPDO/RPM
& Cost
ParametersFrom Memo 100 and later AA studies:
• Gross distribution of collecting area for phase• Gross distribution of collecting area for phase 1 and 2. Memo 100 specifies in table 1:
dish Memo 100
diameter (km) phase 1 phase 2
provisional AA
AA‐hi AA‐lo
core 1 50% 20%
central 5 75% 50%
30% ~5‐7%
66% 50%
mid 180 100% 75%
outer 3000 100%
100% 100%
April 2009 CALIM09 SPDO/RPM 21
Parameters
From RSP:
• Frequency and baseline range (angular resolution) per receptor technology type: for WBSPF and PAF in dishes, sparse and dense AA.
• Imaging Dynamic Range ‐> 77dB
• Array filling factorArray filling factor
• Sky coverage
April 2009 CALIM09 SPDO/RPM 22
Separate cores• Considering 3 receptor technologies: AA‐low (sparse), AA‐high (dense), dishes
• All want large filling factor in the core
• Need to separate in the core, because of:p ,– mutual shadowing
– sub‐optimal filling possibilities if all combined
– accessibility
– inter‐RFI/EMI arguments
• Extra complication: presence of precursor telescopes
• Note: Remote stations, up to a certain baseline, will d l f l lneed real estate for multiple receptor stations.
April 2009 CALIM09 SPDO/RPM 23
Overall SKA ConfigurationComms links
Dishes in stations spread along spiral
S i
Core ~5km dia
StationCentral ProcessingFacility 200km
Dishes
AA-hi
AA-lo
April 2009 24CALIM09 SPDO/RPM
courtesy A. Faulkner
Key Issues
Some more items to (re)consider:• In many studies so far symmetrical log spirals have been investigated. We have the practical need to come up with highly asymmetrical configurations forcome up with highly asymmetrical configurations for the longest baselines.
• In a densely packed core shadowing becomes a• In a densely packed core, shadowing becomes a serious issue.
• To what baseline range do we consider PAFsTo what baseline range do we consider PAFs.
April 2009 CALIM09 SPDO/RPM 25
Key Parameters
Initial design assumptions:
Th b f i h d i f 150• The number of stations that we design for 150
• of which 70 equivalent stations in inner 5 km
• the number of antennas per station 20
• bring back all signals from stations to the correlator f b li 180k b d h b f dfor baselines <180km, beyond that beamformed data.
P ti l ti t h d fit th• Practical question to answer: how do we fit the required baseline range on the two continents in a scientifically useful fashionscientifically useful fashion.
April 2009 CALIM09 SPDO/RPM 26
Figures‐of‐merit
Prime FoM for imaging will be the rms side lobe l l f h PSF l i f hlevel of the PSF, resulting from the uv coverage for:
• snapshot observations
• spectral line imaging observationsp g g
• for multi frequency synthesis (MFS)
• Being programmed into AntConfig now.
April 2009 CALIM09 SPDO/RPM 27
PSF rms side lobe level1. Ambition is to have 77 dB of DR
2 Wide field of view and >50x increase in array2. Wide field of view and >50x increase in array sensitivity will place enormous amount of sources in the field; of which the stronger ~1000s can bein the field; of which the stronger 1000s can be removed for calibration ‐> sky model, but will leave:
3. ex. ~1 million 1 sigma sources in the field, andg ,
4. side lobe confusion will increase noise, 1st order estimate, by factor sqrt(nr sources)/side lobe level, y q ( )so for this example…
5. side lobe level 0.1% would still double the noise.
April 2009 CALIM09 SPDO/RPM 28
Log spiralsThe very demanding imaging FoM is likely best realised by a smooth log spiral configuration:realised by a smooth log spiral configuration:
• many short spacings (for high brightness )sensitivity)
• enough long spacings (to minimize confusion)
• comparable sensitivity at all scales
• aiming to prevent holes in the uv plane foraiming to prevent holes in the uv plane, for continuum work through MFS…
April 2009 CALIM09 SPDO/RPM 29
Multi Frequency Synthesis
• Holes in uv plane can be filled up by using l i f h imulti frequency synthesis
• Needs assumptions on the frequency dependance, spectral index
• Works till what fractional bw– Urvashi Rau’s thesis work very relevant
• uv ‐‘holiness’ metric to be worked intouv holiness metric to be worked into AntConfig, MdVs method and possibly Lobanov’s uvgap metricLobanov s uvgap metric.
April 2009 CALIM09 SPDO/RPM 30
The Mask
The mask defines where stations can or cannot be located as determined by a range of aspectsbe located, as determined by a range of aspects.Example no‐go areas:• Geographically constrained areas• Geographically constrained areas• RFI constrained areas
• The mask is thought to have the most i t f l i t ti ithi thimportance for placing stations within the range of ~30‐~300km.
April 2009 32CALIM09 SPDO/RPM
Mask, Geographical• Bodies of water
• Roads This is the ‘easy’ part, even though f l id ti fRoads
– small, single‐lane
– multi‐lane
careful consideration for:
• buffer zones• seasonal influences
– rail
• Slopes
• seasonal influences• climate zones• historic data• future projections
• Mountains
• Floodplains
future projections• slope data• geology aspects• plateaus
• Environmental– Parks
• data sources• common criteria• integration in AntConfig
– Cultural exclusion areasApril 2009 33CALIM09 SPDO/RPM
Mask, RFI considerations
Criteria
• RA769‐2 continuum for the central area
• RA769‐2 VLBI for the longer baselinesg• Bottom line: given the unavoidable sources of RFI anywhere in the array (aircraft, satellites), the levels of RFI should be less than the level where cost&performance would be affected by having to:– design in more receiver headroom
– use more signal bits
April 2009 CALIM09 SPDO/RPM 34
Mask, format• Mask generated as a GIS ESRI shapefile, to be used within AntConfigwithin AntConfig
• ESRI shapefile is standard data format for the compilation and distribution of ‘geographical’ information– Hydrology, topography, meteorology, demography, geology etcetc.
• Data sources– Common data source, where possible: use of satellite , pdatasets, eg. landsat.org, SRTM‐90
April 2009 35CALIM09 SPDO/RPM
Masks and AntConfig
• The masks will be supplied by the two hostThe masks will be supplied by the two host countries
• Will be read into AntConfig to constrain the• Will be read into AntConfig, to constrain the placement of stations during manual antenna shuffling and during automated optimisationsshuffling and during automated optimisations.
April 2009 CALIM09 SPDO/RPM 37
Infrastructure cost
• Cost of infrastructure must be considered while designing configurationsdesigning configurations
• Proximity of services and accessibilityfibre– fibre
– power
– roadsroads
– support base
– Tools to evaluate infrastructure cost:• SKADS costing tool
• Routing optimiser for fibre
• Costing ‘layer’ in AntConfigCosting layer in AntConfig
April 2009 CALIM09 SPDO/RPM 38
Costing layer
• Engineering consultancy for input parametersEngineering consultancy for input parameters, common for SA and AUS
• Pre process costing and generate site specific• Pre‐process costing and generate site specific costing layer – f(x,y,cost)
• Components• Components– Site establishment cost– Bulk infrastructure costBulk infrastructure cost
April 2009 CALIM09 SPDO/RPM 39
Costing layer
courtesy A. Tiplady
• Establishment + infrastructure costing (illustrative only)only)
April 2009 40CALIM09 SPDO/RPM
Status
• Reaching agreement on methods (ongoing)– masks
• specification to be completed
d i f h k• production of the masks
– costingifi ti• specification
• consultancy
April 2009 CALIM09 SPDO/RPM 42
Status
• Development work on AntConfig (ongoing)– functionality for mask and costing layer
– developing and implementing FoMs
– additional analysis functionality
– add multi‐computing node functionality
– the tool is intended to evolve into a general configuration research and education platform.
– mid May first release of iAntConfig (Mac edition)
April 2009 CALIM09 SPDO/RPM 43
Feedback and iterations
• A set of developed configurations will be presented to the SWGto the SWG
• Iterations will narrow down the options and can possibly also cause the RSP to be modifiedpossibly also cause the RSP to be modified
• Configurations that are deemed to be suitable will be presented to SSEC who will make final selection ofpresented to SSEC, who will make final selection of one preferred configuration per host country.
• These will be used in further planning and costing ofThese will be used in further planning and costing of the array, also in PrepSKA WP2.
April 2009 CALIM09 SPDO/RPM 44