DAERAH ALIRAN SUNGAI CIKERUH

TUGAS BESAR PERANCANGAN INFRASTRUKTUR KEAIRAN 2

Alvina Mayora Nilasari 1206237580Alexander Kevin 1206237284Kasihisa Hervani 1206238002Martha Veraida 1206240133Penny Dwiadhiputri 1206218064Ricky Aristio 1206239415Shabrina Nadhila 1206239440

KELOMPOK 3

Page 2: PPT PIK 2

PEMBAGIAN SUBDAS SUNGAI CIKERUH

SD II SD III

SD IV

SD V

SD I

Page 3: PPT PIK 2

PEMBAGIAN SUBDAS SUNGAI CIKERUH

SD II SD III

SD IV

SD V

SD I

Page 4: PPT PIK 2

SKEMATIK SUBDAS SUNGAI CIKERUH

Page 5: PPT PIK 2

ARC GIS

Page 6: PPT PIK 2

Step 1Add data yang dibutuhkan

(boundary, point of elevation, stream, contour,land use, Admin)

Page 7: PPT PIK 2

Step 2Konversi Satuan meter

ArcToolbox →Data Management Tools →Projection and Transformation →Feature →Project →input data →Output coordinate system →projected coordinate system →UTM →WGS1984 →Southern Hemisphere →Zone 48 S

Page 8: PPT PIK 2

Step 3Membuat DEM

ArcToolbox →Spatial Analyst Tools →Interpolation→Topo to Raster →input data (Boundary utm, Point of elevation utm, contour utm) →Sesuaikan type→Output cell size = 30 →mengganti nama (dem)

Page 9: PPT PIK 2

Step 4Membuat Arah Aliran (Flow Direction)

ArcToolbox →Spatial Analyst Tools →Hydrology→Flow Direction→input data (Dem) → mengganti nama (Flow_dir)

Page 10: PPT PIK 2

Step 5Membuat Akumulasi Aliran (Flow Accumulation)

ArcToolbox →Spatial Analyst Tools →Hydrology→Flow Accumulation→input data (Flow_dir) → mengganti nama (Flow_acc)

Page 11: PPT PIK 2

Step 6Menentukan Point of Origin

• Buka Catalog → klik kanan di folder tempat file disimpan→ new → shapefile → ubah nama(Outlet) → Edit → projected coordinate system → UTM → WGS 1984 → southern → zone 48s

• Editor → Start Editing → Outlet → Ok → Create features → Klik OUTLET dan Point → Pilih Point of Originnya → Stop Editing

Page 12: PPT PIK 2

Step 7Membuat DAS

ArcToolbox → Spatial analyst tool → hydrology → WATERSHED; Input : Flow_dir; Input raster : Outlet;Output : Watershed

Page 13: PPT PIK 2

Step 8Mengubah DAS menjadi polygon

ArcToolbox → conversion tools → from raster → raster to polygon ;Input: watershed; Output: watershed_polygon

Page 14: PPT PIK 2
Page 15: PPT PIK 2

Step 9Menghitung luas DAS

• Table of contents → Klik kanan di layer WATERSHED_POLYGON → Open attribute table → table options → Add field → isi Name, type, precision, dan scale.

• Klik kanan di Cikeruh → Calculate geometry → Units : Square kilometers

Luas DAS = 38671788,3305 m2

Page 16: PPT PIK 2

Step 10Clip Sungai

ArcToolbox → analyst tools → extract → clip ; Input: Sungai_utm; clip feature: watershed dalam bentuk polygon; Output: Sungai_clip

Page 17: PPT PIK 2

Step 11Memasukkan Data Landuse

Page 18: PPT PIK 2

Step 11Clip Landuse

ArcToolbox → analyst tools → extract → clip ; Input: landuse_utm; clip feature: watershed dalam bentuk polygon; Output: Landuse_clip

Page 19: PPT PIK 2
Page 20: PPT PIK 2

Step 12Memunculkan Detail landuse

Klik kanan di landuse_clip → properties → symbology → catagories → unique values → value field: keterangan → add all values → Ok.

Page 21: PPT PIK 2

Hasil Watershed

Page 22: PPT PIK 2

Data Titik Tinggi, Sungai, dan Kontur

Page 23: PPT PIK 2

SUBDAS AWAL

Page 24: PPT PIK 2

SUBDAS AKHIR

Page 25: PPT PIK 2

Step 13Perhitungan CN

Page 26: PPT PIK 2

Step 14Perhitungan Panjang Sungai

Page 27: PPT PIK 2

WINTR - 20

Page 28: PPT PIK 2

Step 1Membuat File baru WinTR - 20

Page 29: PPT PIK 2

Parameter SUBAREA SUNGAI Cikeruh

Page 30: PPT PIK 2

Step 2Input Parameter SUBAREA pada ‘Sub-Area’ WinTr - 20

SD I

Page 31: PPT PIK 2

SD II

Step 2Input Parameter SUBAREA pada ‘Sub-Area’ WinTr - 20

Page 32: PPT PIK 2

SD III

Step 2Input Parameter SUBAREA pada ‘Sub-Area’ WinTr - 20

Page 33: PPT PIK 2

SD IV

Step 2Input Parameter SUBAREA pada ‘Sub-Area’ WinTr - 20

Page 34: PPT PIK 2

SD V

Step 2Input Parameter SUBAREA pada ‘Sub-Area’ WinTr - 20

Page 35: PPT PIK 2

Parameter REACH SUNGAI Cikeruh

Page 36: PPT PIK 2

REACH 1

Step 3Input Parameter REACH pada ‘Stream Reach’ WinTr - 20

Page 37: PPT PIK 2

REACH 2

Step 3Input Parameter REACH pada ‘Stream Reach’ WinTr - 20

Page 38: PPT PIK 2

DESAIN SALURAN

Page 39: PPT PIK 2

Dimensi Saluran pada Reach 1

Diket:• Q = 44.45 m3/s• Slope = 0.0043

Q

𝑅=𝐴𝑃

𝑃=𝑏+2 𝑦 √1+𝑠2

y s

b

T = b + 2x

Page 40: PPT PIK 2

Dimensi Saluran pada Reach 1

Asumsi• b = 3ym• x = 2ym• T = b + 2x m= 7y m• s = y m• A = 5y2

• n = 0.025(pasangan batu ) v maks = 2 m/s

Q

Q

44.45= 10.025

𝑥5 𝑦 2𝑥 ( 5 𝑦 2

3 𝑦+2 𝑦 √5)2/3

𝑥 0.00431 /2

y

y s

b

T = b + 2x

Page 41: PPT PIK 2

Dimensi Saluran pada Reach 1

Sehingga :• b = 3y m = 5.25• x = 2y m = 3.5 m• T = b + 2x m = 7y m = 12.25 m• S = y = 1.75m• A = 5y2 = 15.3125 m2

• n = 0.025 (PasanganBatu)• v maks = 2 m/s

Karena V desainmelebihi V maks literature (2 m/s), makaperludilakukandesainulangdenganmemperbesar y menjadi1.25 kali

= = 𝑄

V  desain    >   2𝑚/ 𝑠

y s

b

T = b + 2x

Page 42: PPT PIK 2

Dimensi Saluran pada Reach 1

Sehingga :• b = 6.6 m • x = 4.4 m• T = b + 2x m = 7y m = 15.4 m • y = 2.2 m • S = 2.2m• A = 24.05 m2

= = 𝑄

V  desain      <   2𝑚 /𝑠

y s

b

T = b + 2x

Page 43: PPT PIK 2

Data Saluran pada Reach 1

Elevation (m) Discharge (cu m/s)

Area (m2)

Top Width (m)

Slope

475.00 0.00 0.00 6.60 0.0043

475.550 2.17 4.24 8.80 0.0043

476.100 8.11 9.68 11.00 0.0043

476.650 18.39 16.34 13.20 0.0043

477.200 44.45 24.20 15.40 0.0043

Page 44: PPT PIK 2

Dimensi Saluran pada Reach 2

Diket:• Q = 48.28 m3/s• Slope = 0.0025

Q

𝑅=𝐴𝑃

𝑃=𝑏+2 𝑦 √1+𝑠2

y s

b

T = b + 2x

Page 45: PPT PIK 2

Dimensi Saluran pada Reach 2

Asumsi• b = 3ym• x = 2ym• T = b + 2x m= 7y m• s = y m• A = 5y2

• n = 0.025(pasangan batu ) v maks = 2 m/s

Q

Q

48.28= 10.025

𝑥5 𝑦 2𝑥 ( 5 𝑦 2

3 𝑦+2 𝑦 √5)2/3

𝑥 0.00251 /2

y

y s

b

T = b + 2x

Page 46: PPT PIK 2

Dimensi Saluran pada Reach 2

Sehingga :• b = 3y m = 6 m• x = 2y m = 4 m• T = b + 2x m = 7y m = 14 m• S = y = 2m• A = 5y2 = 20 m2

• n = 0.025 (PasanganBatu)• v maks = 2 m/s

Karena V desainmelebihi V maks literature (2 m/s), makaperludilakukandesainulangdenganmemperbesar y menjadi1.15 kali

= = 𝑄

V  desain    >   2𝑚/ 𝑠

y s

b

T = b + 2x

Page 47: PPT PIK 2

Dimensi Saluran pada Reach 2

Sehingga :• b = 6.9 m • x = 4.6 m• T = b + 2x m = 7y m = 16.1 m • y = 2.3 m • S = 2.3m• A = 26.45 m2

= = 𝑄

V  desain      <   2𝑚 /𝑠

y s

b

T = b + 2x

Page 48: PPT PIK 2

Data Saluran pada Reach 2

Elevation (m) Discharge (cu m/s)

Area(m2)

Top Width (m)

Slope

375.00 0.00 0.00 6.90 0.0025

375.58 2.36 4.63 9.20 0.0025

376.15 9.35 10.58 11.50 0.0025

376.73 22.37 17.85 13.80 0.0025

377.30 48.57 26.45 16.10 0.0025

Page 49: PPT PIK 2

WINTR - 20

Page 50: PPT PIK 2

REACH 1Channel menghubungkan Reach 1 dengan Outlet

Step 4Input Data Saluran pada ‘Stream Cross Section Reach’ WinTr - 20

Page 51: PPT PIK 2

REACH 2X Section1 menghubungkan Reach 2 dengan Outlet

Step 4Input Data Saluran pada ‘Stream Cross Section Reach’ WinTr - 20

Page 52: PPT PIK 2

Step 5Input ‘Rainfall Distribution’ pada WinTr - 20

Page 53: PPT PIK 2

5 tahunan

Step 6Input ‘Storm Analysis’ pada WinTr - 20

Page 54: PPT PIK 2

10 tahunan

Step 6Input ‘Storm Analysis’ pada WinTr - 20

Page 55: PPT PIK 2

15 tahunan

Step 6Input ‘Storm Analysis’ pada WinTr - 20

Page 56: PPT PIK 2

25 tahunan

Step 6Input ‘Storm Analysis’ pada WinTr - 20

Page 57: PPT PIK 2

50 tahunan

Step 6Input ‘Storm Analysis’ pada WinTr - 20

Page 58: PPT PIK 2

100 tahunan

Step 6Input ‘Storm Analysis’ pada WinTr - 20

Page 59: PPT PIK 2

Step 7Setting ‘Global Output’ pada WinTr - 20

Page 60: PPT PIK 2

Step 8Setting ‘Verification’ pada WinTr - 20

Page 61: PPT PIK 2

Running WinTR-20

Page 62: PPT PIK 2
Page 63: PPT PIK 2

GRAPHIC OUTPUT

SUBAREA 1

Page 64: PPT PIK 2

GRAPHIC OUTPUT

SUBAREA 2

Page 65: PPT PIK 2

GRAPHIC OUTPUT

SUBAREA 3

Page 66: PPT PIK 2

GRAPHIC OUTPUT

SUBAREA 4

Page 67: PPT PIK 2

GRAPHIC OUTPUT

SUBAREA 5

Page 68: PPT PIK 2

GRAPHIC OUTPUT

REACH 1

Page 69: PPT PIK 2

GRAPHIC OUTPUT

REACH 2

Page 70: PPT PIK 2

GRAPHIC OUTPUT

CROSS SECTION

Page 71: PPT PIK 2

TATA GUNA LAHAN

Page 72: PPT PIK 2
Page 73: PPT PIK 2
Page 74: PPT PIK 2
Page 75: PPT PIK 2

PERDA RTRW KABUPATEN BOGOR• Pasal 24b kawasan resapan air• Pasal 27 kawasan taman wisata• Pasal 35 (4) kawasan tanaman tahunan• Pasal 35 (6) kawasan peternakan• Pasal 27 kawasan industri estate• Pasal 37 pengembangan jaringan jalan baru, jalan

lingkar kabupaten

Page 76: PPT PIK 2

Tata Guna Lahan

Page 77: PPT PIK 2
Page 78: PPT PIK 2
Page 79: PPT PIK 2
Page 80: PPT PIK 2

Koefisien Tata Guna Lahan DAS Cikeruh

Page 81: PPT PIK 2

Kecamatan Babakan Madang - Bogor

• Desa Babakan Madang• Desa Bojong Koneng• Desa Cijayanti• Desa Cipambuan• Desa Citaringin• Desa Kadunmangu

• Total Penduduk = 106524 Jiwa• Total Luas = 9219.71 ha• Kepadatan Penduduk = 1155.4 jiwa/km2

Sumber = bogorkab.go.id

Page 82: PPT PIK 2

NERACA AIR

Page 83: PPT PIK 2

Perhitungan Kebutuhan Air Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

R andalan mm 213 299.1304 269.3043 289.5652 78.13043 31.47826 44.95652 45.91304 38.95652 50.65217 255.6087 323.1739

R andalan m2 0.213 0.29913 0.269304 0.289565 0.07813 0.031478 0.044957 0.045913 0.038957 0.050652 0.255609 0.323174

Cr 0.484 0.484 0.484 0.484 0.484 0.484 0.484 0.484 0.484 0.484 0.484 0.484

A m2 38300000 38300000 38300000 38300000 38300000 38300000 38300000 38300000 38300000 38300000 38300000 38300000

Q m3 3948424 5545041 4992149 5367728 1448319 583518.8 833368 851099.3 722144.8 938949.5 4738270 5990739

Keb air m3 4421.35 4421.35 4421.35 4421.35 4421.35 4421.35 4421.35 4421.35 4421.35 4421.35 4421.35 4421.35

Jumlah hari hari 31 28 31 30 31 30 31 31 30 31 30 31

Keb air m3 137061.9 123797.8 137061.9 132640.5 137061.9 132640.5 137061.9 137061.9 132640.5 137061.9 132640.5 137061.9

Kum. Ketersediaan m3 3948424 9493464 14485613 19853341 21301661 21885180 22718548 23569647 24291792 25230741 29969011 35959750

Kum. Kebutuhan m3 137061.9 260859.7 397921.5 530562 667623.9 800264.4 937326.2 1074388 1207029 1344090 1476731 1613793

Faktor Irigasi 3.22272 3.22272 3.22272 3.22272 3.22272 3.22272 3.22272 3.22272 3.22272 3.22272 3.22272 3.22272

Keb. Irigasi m3 441712 398965.6 441712 427463.2 441712 427463.2 441712 441712 427463.2 441712 427463.2 441712

Kum. Keb irigasi m3 441712 840677.6 1282390 1709853 2151565 2579028 3020740 3462452 3889915 4331627 4759090 5200802

Kum tot keb air m3 578773.8 1101537 1680311 2240415 2819189 3379292 3958066 4536840 5096944 5675717 6235821 6814595

Keb air tot m3 578773.8 522763.4 578773.8 560103.7 578773.8 560103.7 578773.8 578773.8 560103.7 578773.8 560103.7 578773.8

Page 84: PPT PIK 2

Perbandingan Ketersediaan dan Kebutuhan per Bulan

1 2 3 4 5 6 7 8 9 10 11 120

1000000

2000000

3000000

4000000

5000000

6000000

7000000

Series1Series2

Page 85: PPT PIK 2

Perbandingan Ketersediaan dan Kebutuhan

0.0000 2.0000 4.0000 6.0000 8.0000 10.0000 12.0000 14.00000

5000000

10000000

15000000

20000000

25000000

30000000

35000000

40000000

Series1Series3

Page 86: PPT PIK 2

Fungsi Waduk

1. Mengalirkan air ke sebuah Pembangkit Listrik Tenaga Air (PLTA) sehingga dapat menghasilkan listrik.

2. Sebagai penyedia air bersih.3. Untuk irigasi yang diperlukan untuk mengairi sawah dan

ladang.4. Sebagai tempat rekreasi.5. Tempat hidup habitat untuk ikan dan hewan lainnya.6. Sebagai pengendali banjir.

Page 87: PPT PIK 2

Butuh Waduk Untuk Penampungan Air

BUKAN sebagai Supplier air

Page 88: PPT PIK 2

DESAIN WADUK

Page 89: PPT PIK 2

Desain Waduk

Surplus Maksimal = 5.411.965,646 m3 Rencana Letak Waduk = Reach 1 Kedalaman Waduk = 6 m Luas Waduk = 901.994 m2 = 90.19 Ha Elevasi DasarWaduk = +272 m Elevasi Bibir = +278 m Tinggi Pelimpah = 2 m Lebar Saluran Reach 1 = 12.25 m

Page 90: PPT PIK 2
Page 91: PPT PIK 2

3.95

P = 6 mH0 = 2 m

Page 92: PPT PIK 2

Data Structure Rating Pelimpah

Page 93: PPT PIK 2

WINTR - 20

Page 94: PPT PIK 2

Step 10Setting ‘Stream Reach’ pada WinTr – 20 untuk membuat struktur Waduk

Page 95: PPT PIK 2

Step 11Input data ‘Structure Rating’ pada WinTr – 20 untuk Waduk

Page 96: PPT PIK 2

Grafik hubungan Flow dan Storage

Page 97: PPT PIK 2

Membandingkan Sebelum dan Setelah dibangunnya Waduk

Page 98: PPT PIK 2

Membandingkan Sebelum dan Setelah dibangunnya Waduk

Page 99: PPT PIK 2

Membandingkan Sebelum dan Setelah dibangunnya Waduk

Page 100: PPT PIK 2

Membandingkan Sebelum dan Setelah dibangunnya Waduk

Page 101: PPT PIK 2

TERIMA KASIH