powering seattle through the 21st century what’s next ... · crews prepare minor avenue n for...
TRANSCRIPT
Powering Seattle through the 21st Century
Denny Substation Program
WHAT’S NEXT? In the second quarter of 2018, crews will complete installation of the substation’s siding and glass and will put the finishing touches on the elevated walkway. Other upcoming work in and around the substation includes restoration of the alley, build-out of the community spaces, and final paving on Minor Avenue N and inside the substation. Installation of the substation artwork will begin in May.
In addition to advancing the Cascade Neighborhood Street Improvements, the Denny Network will continue with duct bank installation and roadway restoration in the South Lake Union area.
CONSTRUCTION SCHEDULE
2016 2017 2018 2019 2020
Denny Substation
Substation Energized
Denny Network Ongoing Network Service Connections
VISIT OUR WEBSITE:www.seattle.gov/light/dennysub
SEND US AN EMAIL:[email protected]
CALL OUR HOTLINE:(206) 257-2142
Denny Substation and Denny Network Construction Map
5
8TH AVE
9TH AVE
BOREN AVE
TERRY AVE
7TH AVE
7TH AVE
6TH AVE
9TH AVE
BOREN AVE
8TH AVE 7TH AVE
6TH AVE 5TH AVE
PINE ST
PIKE ST
STEW
ART ST
VIRGIN
IA ST
BLANCHARD ST
BELL ST
OLIVE WAY
MERCER ST
MERCER ST
REPUBLICAN ST
HARRISON ST
DENNY WAY
THOMAS ST
FAIRVIEW
AVE N
ROY ST
ROY ST
WESTLA
KE AVE N
9TH AVE N
8TH AVE N
TERRY AVE N
BOREN
AVE N
YALE AVE N
MINOR AVE
YALE AVE
DENNY PARK
MIN
OR AVE N
MELRO
SE AVE E
PON
TIUS AVE N
CASCADEPLAYGROUND
CASCADEP-PATCH
HOWELL
ST
JOHN ST
DENNYSUBSTATION
WESTLA
KE AVE
LENORA ST
STEWART ST
Ramps to and from I-5
Key
Planned Duct Bank
Completed Duct Bank
Completed Duct Bank and Roadway Restoration
Completed Duct Bank, Roadway Restoration, and Final Driving Surface
Vault
DENNY NETWORK ONGOING CONSTRUCTION
DV-08
DV-09
DV-10
DV-11
DV-05
DV-06
DV-07
DV-12
HV-02
HV-01
DV-13
DV-21 DV-22 DV-23
DV-40
DV-31
DV-20
DV-33
DV-27 DV-28 DV-29 DV-30
DV-34 DV-35 DV-36
DV-37 DV-39 DV-26
DV-24
DV-25
DV-32
DV-38
DV-41
HV-03
Veer Lofts
Via 6
Larned Apts. Westlake
Hotel
WestinNorth
WestinSouth
StewartCourtHotel
Max
Cosmopolitan
DekkoApts.
Aspira Apts.
BalfourApts.
HarborHouse
JulieApts.
502Minor
CascadeApts.
AMLI
Stack House
AlcyoneApts.
Mirabella
CasaPacifca
LakeviewApts.
Brewster Co
lwell A
pts.
Alley 24 Apts.
Alley 24North
SCCA
215Pontius
219PontiusMinor
AveChildren’s
Metropolitan
Project map showing progress of work for Denny Substation and Denny Network construction.
Powering Seattle through the 21st Century
Denny Substation Program
QUARTERLY REPORT 1 S T Q UA R T E R | 2 0 1 8
WE’RE IN THE HOME STRETCH!
We’re excited to report that both the Denny
Substation and Denny Network projects are
scheduled to be complete in late summer
2018. This year will be packed with major
milestones. Whether or not you’ve stayed up
to date on the project thus far, now’s a good
time to follow closely!
We’re looking forward to energizing the
substation in April, completing John Street
restoration in May, and making neighborhood
improvements around the Cascade Playground
and P-Patch throughout the spring.
What’s energization and why does it matter? Energization is the gradual process of “turning on” the
substation so that it can deliver power to customers.
Since providing power is the substation’s primary
function, energizing it and ensuring everything is working
properly before customers receive electricity are critical
steps toward project completion. The process begins
by bringing high-voltage electricity into the substation’s
three transformers to make sure they can transform high-
voltage electricity into lower voltages that can be used
by customers. The next step involves testing the new
network trunk lines under electrical load. Once this step
is completed, electricity is then distributed through the
feeder lines that will deliver power to customers.
Glass installation on the west side of the substation is nearing completion.
COMMUNITY SPACE PROGRESSOur 2017 year-end report featured the start of construction on the substation’s community and event space. Since then, we’ve framed interior walls and installed the exterior glass. When construction is finished, an outdoor plaza with seating and a food-truck zone will be located just outside the door of the community space on the west side of the substation.
About 4,000 square feet of community space will open onto an outdoor plaza and the off-leash area once the substation is complete.
Denny Substation ProgramPowering Seattle through the 21st Century
ALL ABOUT THE ALLEYWhat’s to come: The alley on the east side of the substation won’t be anything like it is now. As featured in the rendering below, the translucent glass will allow light from the substation to shine through to the alley. The line of concrete seen in the center of the picture at left will form the outer wall of the bioretention planter, which will naturally treat all the stormwater that drains through the alley. These changes, along with new lighting and decorative paving, are designed to create a safer and more pleasant pedestrian experience in the neighborhood.
INSIDE THE SUBSTATION:
PAVING THE WAY You see paving on the streets outside the substation, but did you know that the inside of the substation will also be paved? By the end of April, the entire inside of the substation will be done.
Crews grade the interior yard of the substation in preparation for paving.
OUTSIDE THE SUBSTATION:
A “CROWN” FOR THE ROAD
Crews prepare Minor Avenue N for final paving by adding a layer
of pavement that will give the road a “crown,” which will allow
for proper drainage.
In Seattle, it’s important that we prepare the roads for lots of rain. Adding a “crown”—an outward slope on the road surface—ensures that rainwater will run off to street drains, avoiding flooding.
AROUND THE SUBSTATION: CASCADE NEIGHBORHOOD STREET IMPROVEMENTSAmong the most prominent changes around the substation are the improvements on Thomas Street in the Cascade neighborhood. The new pedestrian street lights and water-permeable sidewalks have been installed! The lighting will help make the neighborhood safer, and the permeable sidewalks and soon-to-be-installed drainage systems and landscaping will make the surrounding area greener and more attractive.
Permeable concrete is highly porous material that reduces the amount of runoff to street drains. When it rains, water infiltrates the sidewalk and seeps slowly into the soil rather than being discharged to storm drains. The soils naturally treat the stormwater and reduce impacts to water quality.
New pedestrian lighting and sidewalks in the Cascade neighborhood are among the improvements being made to make the neighborhood safer and greener.
Permeable concrete sidewalk on Minor Avenue N in the Cascade neighborhood.