power system master plan 2016 - think blue data
TRANSCRIPT
Final Report
Power System Master Plan 2016
Summary
Supported by
Japan International Cooperation Agency (JICA)
Tokyo Electric Power Services Co., Ltd. Tokyo Electric Power Company Holdings, Inc.
Power Division Ministry of Power, Energy and Mineral Resources
Government of the People’s Republic of Bangladesh
September 2016
Power System Master Plan 2016
Final Report
i
Contents
Chapter 1 PSMP2016 Summary ..................................................................................................... 1-1
1.1 Abstract ........................................................................................................................................... 1-1
1.2 Background and Purpose ................................................................................................................ 1-1
1.3 Vision Paper ................................................................................................................................... 1-3
1.4 Policy Vision .................................................................................................................................. 1-4
1.4.1 PSMP2016 Objective .............................................................................................................. 1-4
1.4.2 Five Viewpoints of PSMP2016 ............................................................................................... 1-5
1.4.3 Importance of Contribution and Responsibility to the International Community ................... 1-6
1.5 Practical Vision ............................................................................................................................... 1-8
1.5.1 Relationships between the Five Key Viewpoints and the Master Plan Investigation Items .... 1-8
1.5.2 Methodologies for this Study .................................................................................................. 1-9
1.5.3 Scope of work ........................................................................................................................ 1-12
1.5.4 Survey Implementation Feamework ...................................................................................... 1-14
1.5.5 JICA Study Team ................................................................................................................... 1-16
1.5.6 Past Activities ........................................................................................................................ 1-17
1.6 Focal points .................................................................................................................................. 1-21
1.6.1 PSMP 2010 Review ............................................................................................................... 1-21
1.6.2 Economic Development Policy ............................................................................................. 1-25
1.6.3 Primary Energy ...................................................................................................................... 1-27
1.6.4 Natural Gas (Domestic) ......................................................................................................... 1-30
1.6.5 Natural Gas (LNG Imports) ................................................................................................... 1-33
1.6.6 Coal........................................................................................................................................ 1-35
1.6.7 Oil and LPG ........................................................................................................................... 1-38
1.6.8 Power Development Plan ...................................................................................................... 1-39
1.6.9 Hydropower development ..................................................................................................... 1-57
1.6.10 Renewable Energy ............................................................................................................... 1-61
1.6.11 Power Imports ...................................................................................................................... 1-63
1.6.12 Nuclear Power ..................................................................................................................... 1-66
1.6.13 Power System Plan .............................................................................................................. 1-72
1.6.14 Improvement of Power Quality ........................................................................................... 1-77
1.6.15 O&M Legal Framework ...................................................................................................... 1-84
1.6.16 Thermal Power Plant O&M ................................................................................................. 1-87
1.6.17 Tariff Policy ......................................................................................................................... 1-93
1.7 Road-map ................................................................................................................................... 1-100
Chapter 2 Recommendations on the Implementation & Monitoring of the Master Plan ......... 2-1
2.1 Capacity building for master plan revision .................................................................................... 2-1
2.1.1 Collaboration and Cooperation between Organizations .......................................................... 2-1
2.1.2 Periodical Rolling Revision of the Milestone Plan.................................................................. 2-1
2.1.3 Strengthening of integrated statistical processing functions.................................................... 2-2
2.1.4 Introduction of Key Performance Indicators ........................................................................... 2-2
2.2 Measures to Facilitate Improvement of Investment Climate .......................................................... 2-3
Power System Master Plan 2016
Final Report
ii
2.2.1 Outline ..................................................................................................................................... 2-3
2.2.2 Project Implementation Structure ............................................................................................ 2-3
2.2.3 Risks directly concerned with the Government ....................................................................... 2-4
2.2.4 Risks to be controlled mainly by contractors .......................................................................... 2-5
2.2.5 Recommendations for Improvement ....................................................................................... 2-5
2.3 Economic Development ................................................................................................................. 2-6
2.4 Domestic Natural Gas [Gas] ........................................................................................................... 2-7
2.5 LNG Import [Gas] ........................................................................................................................ 2-10
2.6 Renewable Energy [Introduction of energy storage technology] ................................................. 2-12
2.7 Power System Plan ....................................................................................................................... 2-14
2.8 O&M Legal Framework [O&M] .................................................................................................. 2-15
2.9 Thermal Power Plant O&M [O&M] ............................................................................................ 2-16
2.10 Tariff policy ................................................................................................................................ 2-20
2.11 Realization Of Low Energy Consumption Society .................................................................... 2-20
2.11.1 New Technologies for Power Generation with Different Energy Sources .......................... 2-20
2.11.2 New technologies in the electric power infrastructure sector .............................................. 2-21
2.11.3 Responsible Energy Consumption and Development of Bangladesh .................................. 2-22
Power System Master Plan 2016
Final Report
iii
List of Tables
Page
Table 1-1 Link between PSMP2016 and the SDGs .............................................................................. 1-7
Table 1-2 Contents of the Study ......................................................................................................... 1-12
Table 1-3 PSMP2010 Review (Economic Development) .................................................................. 1-21
Table 1-4 PSMP2010 Review (Coal Supply) ..................................................................................... 1-22
Table 1-5 PSMP2010 Review (Gas Supply) ...................................................................................... 1-23
Table 1-6 Projection of GDP and GDP per capita up to 2041 ............................................................ 1-25
Table 1-7 Projection of Primary Energy Supply – Scenario 3 ............................................................ 1-29
Table 1-8 3E Evaluation Results of Each Power Development Scenario .......................................... 1-53
Table 1-9 3E Evaluation Results of Each Power Development Scenario .......................................... 1-54
Table 1-10 Renewable Energy Potential in Bangladesh ..................................................................... 1-61
Table 1-11 Electrification Rate Calculation Details by Power Division ............................................ 1-73
Table 1-12 Supply Trip Amount and Factors Which Should Be Considered in Each Year ................ 1-82
Table 1-13 Problems in Organizational Resources ............................................................................. 1-88
Table 1-14 Solution Proposals ............................................................................................................ 1-89
Table 1-15 O&M Solution Proposals and Implementation Plans ....................................................... 1-90
Table 1-16 Impacts of Electricity Tariff Increase on Economy (single-year analysis) ....................... 1-94
Table 1-17 Scenarios of Electricity Tariff Increase: Case 1 (cost increase) ....................................... 1-94
Table 1-18 Scenarios of Electricity Tariff Increase: Case 2 (no cost increase) .................................. 1-95
Table 1-19 Impacts of Electricity Tariff Increase on Bangladesh National Economy (Case 1) ......... 1-95
Table 1-20 Impacts of Electricity Tariff Increase on Bangladesh National Economy (Case 2) ......... 1-95
Table 1-21 Impacts of Gas Price Increase on Bangladesh National Economy ................................... 1-96
Table 1-22 Scenarios of Gas Price Increase ....................................................................................... 1-96
Table 1-23 Impacts of Gas Price Increase on Bangladesh National Economy ................................... 1-96
Table 1-24 Example of Scenarios for Electricity Tariff Increase ....................................................... 1-98
Table 1-25 Scenarios of Gas Price Increase ....................................................................................... 1-98
Table 1-26 Roadmap for PSMP2016 ............................................................................................. 1-100
Table 2-1 Items Required in Feasibility Assessment .......................................................................... 2-18
Table 2-2 Areas of research by type of energy ................................................................................... 2-21
Table 2-3Areas of assistance in research in the electric power infrastructure sector ......................... 2-21
Power System Master Plan 2016
Final Report
iv
List of Figures
Page
Figure 1-1 Overall Workflow for This Study ....................................................................................... 1-9
Figure 1-2 Steering Committee and Working Groups ........................................................................ 1-15
Figure 1-3 PSMP2010 Review (Economic Development)................................................................. 1-21
Figure 1-4 PSMP2010 Review (Coal Supply) ................................................................................... 1-22
Figure 1-5 PSMP2010 Review (Gas Supply) ..................................................................................... 1-23
Figure 1-6 PSMP2010 Review (Power Development Plan) ........................................................... 1-24
Figure 1-7 Value Added by Large and Middle Scale Manufacturing Industries ................................ 1-26
Figure 1-8 Illustration of Industrial Development in Bangladesh Toward 2041 ................................ 1-26
Figure 1-9 Stages of Industrial Development and Necessary Policy Measures to Support This ....... 1-27
Figure 1-10 Projection of Final energy Consumption (BAU Scenario) ............................................. 1-27
Figure 1-11 Projection of Final Energy Consumption (Energy Efficiency Scenario) ........................ 1-28
Figure 1-12 Projection of Primary Energy Supply – Scenario 3 ........................................................ 1-29
Figure 1-13 Gas Resource Balance .................................................................................................... 1-30
Figure 1-14 Gas Supply Forecast 2016~2041 .................................................................................... 1-33
Figure 1-15 Forecast of Coal Demand and Supply ............................................................................ 1-35
Figure 1-16 Oil Demand and Supply Balance, 2014 to 2041 ............................................................. 1-38
Figure 1-17 Power Development Planning Flow ............................................................................... 1-40
Figure 1-18 Estimated Composite Daily Load Curve in the Summer in Bangladesh ........................ 1-41
Figure 1-19 Comparision of peak power demand in both models ..................................................... 1-42
Figure 1-20 Relationship between the Time Scale and the Change in PDP ....................................... 1-43
Figure 1-21 Annual Trend of Each Power Plants(MW) ................................................................ 1-45
Figure 1-22 Transition of estimated power demand during 2015-2041 (Unit: MW) ......................... 1-45
Figure 1-23 Reserve Margin ............................................................................................................... 1-46
Figure 1-24 IEACrude Oil Scenario ................................................................................................... 1-47
Figure 1-25 Simulation schem of the supply/demand operation ........................................................ 1-48
Figure 1-26 Generation pattern in 2041 ............................................................................................. 1-49
Figure 1-27 Image for demand and supply simulation ....................................................................... 1-49
Figure 1-28 Annual Trend of Energy Mix in Different Scenarios ...................................................... 1-50
Figure 1-29 Power generation cost under each scenario and Ratio of coal (US cent/kWh) ........ 1-50
Figure 1-30 Scenario-Wise CO2 Emissions(CO2 kg-C/kWh) ...................................................... 1-51
Figure 1-31 Physical Energy Delivery Routes and Risks ................................................................... 1-52
Figure 1-32 An Example of Probability Density of Energy Delivery ................................................ 1-52
Figure 1-33 3E Evaluation Results (Each Value) Figure 1-34 3E Evaluation Results (Total) .. 1-53
Figure 1-35 3E Evaluation Results (Each Value) ............................................................................... 1-54
Figure 1-36 3E Evaluation Results (Total) ......................................................................................... 1-54
Figure 1-37 3E Evaluation Results (Total) ......................................................................................... 1-55
Figure 1-38 Best mix including expansion of renewable enegy ........................................................ 1-56
Power System Master Plan 2016
Final Report
v
Figure 1-39 Location Map of Potential PSPP Sites ............................................................................ 1-58
Figure 1-40 Location Map of Potential Sites for Ordinary and Small Scale Hydropower ................. 1-59
Figure 1-41 Future Power Import Volume and its Share (High Case Scenario) ................................. 1-64
Figure 1-42 Future Power Import Volume and its Share (Low Case Scenario) ................................. 1-65
Figure 1-43 Nuclear Power Development on PSMP2016 .................................................................. 1-66
Figure 1-44 Structure of IAEA Safety Standards ............................................................................... 1-67
Figure 1-45 Nuclear Industry Information Center .............................................................................. 1-69
Figure 1-46 Asian Nuclear Safety Network (ANSN) ......................................................................... 1-70
Figure 1-47 Roadmap for nuclear power development ...................................................................... 1-71
Figure 1-48 The Existing Bulk Power Network System of Bangladesh (2014) ................................. 1-72
Figure 1-49 Development of Access to Electricity (BPDB definition) .............................................. 1-74
Figure 1-50 BREB On-grid Extension Plan Comparison ................................................................... 1-75
Figure 1-51 Number of SHS under IDCOL Program ......................................................................... 1-75
Figure 1-52 Conceptual Map of Locations of Large Scale Power Stations Planned Up to 2035 ....... 1-76
Figure 1-53 Comparison between the Necessary Reserves and the Available Reserves .................... 1-80
Figure 1-54 Trend of Power Frequency Quality Improvement .......................................................... 1-81
Figure 1-55 Schematic Diagram of the Frequency Deviation Immediately ....................................... 1-82
Figure 1-56 Trend of minimum values of frequency immediately ..................................................... 1-82
Figure 1-57 Schedule for Legal Reform ............................................................................................. 1-86
Figure 1-58 Site Selection .................................................................................................................. 1-87
Figure 1-59 Target Site List ................................................................................................................ 1-88
Figure 1-60 O&M Efficiency Improvement Supported by Information Management ...................... 1-91
Figure 1-61 Demand/Supply and Shutdown Planning ....................................................................... 1-91
Figure 1-62 Thermal Power Plant O&M Roadmap............................................................................ 1-92
Figure 2-1 PSMP2010 Review (Power Development Plan) ................................................................ 2-3
Figure 2-2 Organaization of IPP........................................................................................................... 2-4
Figure 2-3 Advanced Electronic Mapping - Object Model System ..................................................... 2-8
Figure 2-4 Introduction of energy storage technology (1).................................................................. 2-12
Figure 2-5 Introduction of energy storage technology (2).................................................................. 2-13
Figure 2-6 Introduction of energy storage technology (3).................................................................. 2-13
Figure 2-7 Steam Turbine Rehabilitation Plan ................................................................................... 2-16
Figure 2-8 Combined Cycle Power Generation Remodeling Plan ..................................................... 2-16
Figure 2-9 Training Course Plan ........................................................................................................ 2-17
Figure 2-10 System Functions and Data Flows for a Power Plant in Bangladesh ............................. 2-19
Power System Master Plan 2016
Final Report
vi
Abbreviations
Abbreviation Full Tytle
ACC American Chamber of Commerce
ADB Asian Development Bank
ADF Asian Development Fund
ADP Annual Development Programme
AGC Automatic Generation Control
AHWR Advanced Heavy Water Reactor
AMD Acid Mine Drainage
API American Petroleum Institute
APSCL Ashuganj Power Station Company
AR5 The Fifth Assessment Report
ASEAN Association of Southeast Asian Nations
ASME American Society of Mechanical Engineers
ASTM American Society for Testing and Materials
ATC Available Transfer Capability
AZEs Alliance for Zero Extinction Sites
Bangladesh the People’s Republic of Bangladesh
BAPEX Bangladesh Petroleum Exploration & Production Company Limited
BAU Business as Usual
bbl Barrel
bpd Barrel per Day
BCMCL Barapukuria Coal Mine Company Limited
BBS Bangladesh Bureau of Statistics
BCBJ Back Contact Back Junction
BCF Billion Cubic Feet
BDT Bangladesh Taka
BERC Bangladesh Energy Regulatory Commission
BGFCL Bangladesh Gas Fields Company Ltd.
BNBC Bangladesh National Building Code
BOP Bottom of Pyramid
BPC Bangladesh Petroleum Corporation
BPDB Bangladesh Power Development Board
BREB Bangladesh Rural Electrification Board
BST Bulk Supply Tariff
BTK Bull’s Trench Kiln
CBM Coal Bed Methane
CBM Condition Based Maintenance
CC Combine Cycle
CCAC Climate and Clean Coalition
CCGT Combined Cycle Gas Turbine
CCPP Combined Cycle Power Plant
CCT Clean Coal Technologies
CEB Ceylon Electricity Board
Power System Master Plan 2016
Final Report
vii
Abbreviation Full Tytle
CGE Computable General Equilibrium
CHT Chittagong Hill Tracts
CLDO Central Load Dispatching Office
CNG Compressed Natural Gas
COD Commercial Operation Day
COD Commercial Operations Date
COP Conference of the Parties
C/P Counterpart
CRT Cathode-Ray Tube
CTT Coal Transshipment terminal
DAC Development Assistance Committee
DESCO Dhaka Electricity Supply Company Limited
DFR Draft Final Report
DOE Department of Environment
DOF Department of Forest
DPDC Dhaka Power Distribution Company Limited
DSM Demand Side Management
EBA Electricity Business Act
ECC Environment Clearance Certificate
ECMP Energy Efficiency and Conservation Master Plan
EDC Economical load Dispatching Control
EEC Energy Efficiency and Conservation
EGAT Electricity Generating Authority of Thailand
EGB Exhaust Gas Boilers
EGCB Electricity Generation Company of Bangladesh
EIA Environmental Impact Assessment
EIA Energy Information Administration, USA
ELBL Eastern Lubricants Blenders Limited
EMRD Energy and Mineral Resources Division
EMS Enegry Management System
EN European Norm (European Standards)
EOI Expression of Interest
EPZ Export Processing Zone
ERD Economic Relation Division
ERL Eastern Refinery Limited
ESMAP Energy Sector Management Assistance Programme
EST Environmentally Sound Technology
EU European Union
FAO Food and Agriculture Organization of the United Nations
FBR Fast Breeder Reactor
FC Frequency Convertor
FCK Fixed Chimney Kiln
FD Finance Division
FDI Foreign Direct Investment
Power System Master Plan 2016
Final Report
viii
Abbreviation Full Tytle
FGMO Free Governor Mode Operation
FIDC Forest Industries Development Corporation
FLEGT Forest Law Enforcement Governance Trade
FR Final Report
F/S Feasibility Study
FSRU Floating Storage Regasification Unit
FY Fiscal Year
GCF Green Climate Fund
GDF Gas Development Fund
GDP Gross Domestic Product
GE General Electric
GEF Global Environment Facility
GHG Greenhouse Gas
GNI Gross National Income
GOB Government of Bangladesh
GPS Ghorasal Thermal Power Station
GSRR Gas Sector Reform Roadmap
GTAP Global Trade Analysis Project
GTCL Gas Transmission Company Limited
ha Hectare
HCU Hydrocarbon Unit
HHI Herfindahl-Hirschman Index
HIES Household Income and Expenditure Survey
HIT Heterojunction with Intrinsic Thin-layer
HRSG Heat Recovery Steam Generator
HSD High Speed Diesel
HVDC High Voltage Direct Current transmission line
Hz Hertz
IAEA International Atomic Energy Agancy
IBRD International Bank for Reconstruction and Development
I&C Instrument & Control
ICI Indonesian Coal Index
IcR Inception Report
ICT Information and Communication Technology
IDCOL Infrastructure Development Company Limited
IEA International Energy Agency
IEE Initial Environmental Examination
IEEE Institute of Electrical and Electronics Engineers
IGCC Integrated Gasifier Combined Cycle
IGFC Integrated Gasifier Fuel Cell
IISD International Institute for Sustainable Development
IMF International Monetary Fund
INDC Intended Nationally Determined Contributions
IOC International Oil Company
Power System Master Plan 2016
Final Report
ix
Abbreviation Full Tytle
ItR Interim Report
IPCC Intergovernmental Panel on Climate Change
IPP Independent Power Producer
IRR Internal Rate of Return
ISO International Organization for Standardization
JETRO Japan External Trade Organization
JICA Japan International Cooperation Agency
JMAR Japan Management Association Research Institute Inc.
JOCL Jamuna Oil Company Limited
JST JICA Survey Team
KBA Key Biodiversity Areas
KPC Kuwait Petroleum Corporation
ktoe Kilo tonne of Oil Equivalent
KV Kilovolt
kWh Kilowatt Hour
LED Light Emitting Diode
LFC Load Frequency Control
LMZ Leningradsky Metallichesky Zavod
LN Natural Logarithm
LNG Liquefied Natural Gas
LOLE Loss of Load Expectation
LOLP Loss of Load Probability
LPG Liquefied Petroleum Gas
LPGL LP Gas Limited
LTCC Longwall Top Coal Caving
LTSA Long Term Service Agreement
MCF Million Cubic Feet
MDGs Millennium Development Goals
METI Ministry of Economy, Trade and Industry
MF Ministry of Finance
MLJPA Ministry of Law, Justice, & Parliamentary Affairs
mm millimeter
MMBTU Million British Thermal Unit
mmcf Million Cubic Feet
mmscfd Million Standard Cubic Feet per Day
MMTPA Million Metric Ton per Annam
MOI Ministry of Industries
MoPEMR Ministry of Power, Energy and Mineral Resources
MPL Meghna Petroleum Limited
MPM&P Management, Production, Maintenance & provisioning Services
MPR Maintenance Period Rate
MRT Mass Rapid Transit
MW Megawatt
MWh Megawatt Hour
Power System Master Plan 2016
Final Report
x
Abbreviation Full Tytle
MWR Ministry of Water Resources
NLDC National Load Dispatching Center
NM Nautical Mile
NOC No Objection Certificate
NRECA National Rural Electrification Cooperative Association
NSAPR II National Strategy for Accelerated Poverty Reduction II
NWPGCL North West Power Generation Company
O&M Operation and Maintenance
OCCTO Organization of Cross-regional Coordination of Transmission Operations
OCR Ordinary Capital Resources
O/C Open Cut
ODA Official Development Assistance
OECD Organization for Economic Co-operation and Development
OICA International Organization of Motor Vehicle Manufacturers
p.a. Per Annum
PAS Protected Area Systems
PBS Palli Bidyuit Samity
PC Power Cell
PCFBC Pressurized Circulating Fluidized Bed Combustion
PCJSS United People's Party of the Chittagong Hill Tracts (Parbatya Chattagram
Jana Sanghati Samiti)
PD Power Division
PDCA Plan, Do, Check, Action
PDP Power Development Plan
PEMFC Polymer Electrolyte Membrane Fuel Cell
PGCB Power Grid Company of Bangladesh Limited
PM Particulate Matter
POCL Padma Oil Company Limited
P/P Power Plant
PPA Power Purchase Agreement
PPP Power Purchasing Parity
PPP Public Private Partnership
PRF Protected Public Forest
PSA Production Sharing Agreements
PSC Product Sharing Contract
PSMP Power System Master Plan
PSPP Pumped Storage Power Plant
PSS/E Power System Simulator for Engineering
PV Photo Voltaic
Q & A Questions & Answers
R&D Research and Development
Re Relaiability
REB Rural Electrification Board
RES Renewable Energy power Source
Power System Master Plan 2016
Final Report
xi
Abbreviation Full Tytle
RF Reserved Forest
RHD Road and Highways Department
RMG Ready-Made Garment
SAOCL Standard Asiatic Oil Company Limited
SARI/EI South Asia Regional Initiative for Energy Integration
SC Steering Committee
SC Super Critical
SCADA Supervisory Control And Data Acquisition
SCC Site Clearance Certificate
SD/VAT Supplementary Duty/Value Added Tax
SDGs Sustainable Development Goals
SEC Specific Energy Consumption
SEZ Special Economic Zone
SGFL Sylhet Gas Fields Limited
SHS Solar Home System
SIPP Small Independent Power Producers
SME Small and Medium Enterprise
SOFC Solid Oxide Fuel Cell
SPM Single Point Mooring
SREDA Sustainable and Renewable Energy Development Authority
SSHP Small Scale Hydropower Plant
ST Steam Turbine
TCF Trillion Cubic Feet
TDS Transmission and Distribution Sector (in General Electricity Utility)
Tk Taka
TEPCO Tokyo Electric Power Company, Inc.
TEPSCO Tokyo Electric Power Services Co., Ltd.
TFC Total Final Consumption
T/D Transmission and Distribution
TNA Technology Needs Assessment
TOR Terms of Reference
TPES Total Primary Energy Supply
UAE United Arab Emirates
UCG Underground Coal Gasification
UCTE Union for the Co-ordination of Transmission of Electricity
UFR Under Frequency Relay
U/G Under Ground
UMIC Upper Middle Income Countries
UNEP United Nations Environment Program
UNFCCC United Nations Framework Convention on Climate Change
UN-REDD United Nations Reducing Emissions from Deforestation and forest
Degradation
USD United States Dollar
USC Ultra Super Critical
Power System Master Plan 2016
Final Report
xii
Abbreviation Full Tytle
WB World Bank
WEO World Energy Outlook
WG3 Working Group 3
WPP World Population Prospects
WZPDCL West Zone Power Distribution Company Limited
YTF Yet to find
η Efficiency
Power System Master Plan 2016
Final Report
1-1
Chapter 1 PSMP2016 Summary
1.1 Abstract
The Power System Master Plan (PSMP) 2016, sponsored by Japan International Cooperation Agency
(JICA), aims at assisting the Bangladesh in formulating an extensive energy and power development
plan up to the year 2041, covering energy balance, power balance, and tariff strategies.
Bangladesh has an aspiration to become a high-income country by 2041. The development of energy
and power infrastructure therefore pursues not only the quantity but also the quality to realize the
long-term economic development.
Since Bangladesh is facing to the depletion of domestic gas supply, various issues such as sustainable
development harmonizing with economic optimization, improvement of power quality for the
forthcoming high-tech industries, and the discipline of operation and maintenance (O&M) for power
plants need to be addressed holistically.
Furthermore, energy subsidy is also a tough challenge, because there’s always a concern that drastic
increase of fuel and electricity prices may trigger another negative effect on the national economy. A
meticulous analysis is required to find the best pathway to attain the sustainability of the energy and
power sectors in balancing with the economic growth.
The new PSMP study covers all the aforementioned challenges comprehensively, and come up with
feasible proposals and action plans for Bangladesh to implement.
1.2 Background and Purpose
The energy source of the People’s Republic of Bangladesh (hereinafter “Bangladesh”) mainly depends
on Domestic Natural Gas. The Government of Bangladesh formulated the Power System Master Plan
2010 (PSMP2010) targeting, among others, for a long term energy diversification due to the foreseen
decrease in the production volume of Natural Gas.
However, energy development is not on track compared with the PSMP2010 plan, because various
assumptions about expected sources for base load energy have subsequently changed. In particular, a
review is needed reflecting namely exponential increasing of oil based rental power plants and
development constraints of domestic primary energy.
Currently, many of power plants in Bangladesh cannot generate electricity as specified in terms of
power, thermal efficiency etc. for each unit. Daily shortage of power does not allow to stop facilities
and to undertake periodical maintenance in a planned way. Legal framework does not stipulate
preventive maintenance works as an obligation for plant owner. Low financial soundness of public
generating companies due to low electricity tariff does not permit to purchase in advance necessary
spare parts. In order to secure a stable electricity supply, we need to find out solutions to all of these
issues and to establish a comprehensive institutional framework. Moreover, hydro power generation
studies (on small scale hydropower plants of 30 kW ~ 5MW and a pumped storage power plant as a
regulator between demand and supply) have become an urgent issue through the government’s
renewable energy promotion policy.
Based on the aid policy of the Government of Japan for Bangladesh, the Japan International
Cooperation Agency (JICA) is considering the power sector as one of priority areas assisting
Bangladesh not only by Yen Loans to the construction of power plants (gas combined cycle,
super-critical using import coal and hydropower), transmission and distribution lines and development
of renewable energy but also by Technical Assistance such as the master plan for energy efficiency.
JICA is thus supporting the entire power and energy sector. It was under such circumstances that JICA
decided to undertake the Power System Master Plan 2016 (PSMP2016) in order to grasp middle to
long term development issues and risks and to formulate a comprehensive and result-oriented aid
strategy for the energy sector by examining effective approaches for each issue.
After the start of this survey, however, the Government of Bangladesh announced, in its new
policy“Vision 2041”, an important target of becoming one of the developed nations by 2041.
Consequently, for the power and energy sector which receives quite dominant development budget, it
has become newly necessary to secure the consistency between the economic development strategy of
Power System Master Plan 2016
Final Report
1-2
the country toward joining the developed countries and the master plan of the power and energy sector
(PSMP). With such consistency only, JICA will be able to make the best use of the result of this survey
as basic information for the future cooperation.
To study consistency between an economic growth strategy and PSMP, an additional survey on
estimated changes of the industrial structure that will be brought by the coming strategy and a precise
forecast of future demand of primary energy and corresponding supply policy must be added to this
survey, since the power sector is one of the largest sectors which consume primary energy. It was
therefore decided to estimate in this survey the most rational and probable demand and supply
scenarios of primary energy for other sectors than power sector such as fertilizer, industry, commerce,
and transportation.
Moreover, the power sector will be required to cope with the changes of industrial structure in line
with the economic growth as expected in order for Bangladesh to join the developed nations.
Specifically, improvement of the quality of electricity is indispensable given the view of the
government that sophistication of industries is generally essential for the nation to become one of the
developed countries.
After the commencement of this survey, Bangladesh started considering also a specific plan to expand
power import from neighbouring countries such as India, Bhutan and Nepal. Usually, international
cooperation in power system is oriented toward direct cooperation by means of alternate current and,
to do so, quality of electricity is required to be equivalent or better than that of counterpart countries. It
is therefore necessary for the promotion of international cooperation to improve the quality of
electricity. Since this issue will be a concern to the entire power sector in revising PSMP, it was also
decided to add to this survey collection of additional basic information and examination of feasible
measures responding to the specific needs of quality improvement.
Therefore, the collection and analysis of the information on the plan for the supply and demand for
primary energy sources and the needs for the improvement of the quality of power supply were
included in this survey that had consisted of the revision of power development plan and the studies on
the institutional reform for the improvement of O&M and the introduction of hydropower generation.
This inclusion of the new survey subject enabled the formulation of a new master plan that covers not
only the power sector but also the energy sector comprehensively and describes the interface between
the two sectors. The new master plan is the output of the first joint survey of the two divisions in the
Ministry of Power, Energy and Mineral Resources (MoPEMR), Power Division and Energy Division,
and this survey is expected to serve as a good precedent of the cooperation between them in the
implementation of policies in the power and energy sectors.
Power System Master Plan 2016 Final Report
1-3
1.3 Vision Paper
Power System Master Plan 2016
Final Report
1-4
Policy Vision
1.4 Policy Vision
The Government of Bangladesh declared its intention to develop the country in order to become one of
the advanced countries by 2041 as the key goal of VISION2041. To achieve the VISION, this master
plan defines the intended goal and “five key viewpoints” that are to be kept in mind by all the
members who are involved in the realization of the goal.
1.4.1 PSMP2016 Objective
To show the targets and approach in the Energy and Power Sectors in order to achieve Bangladesh’s
national goal: to achieve VISION2041 and become a high-income country by 2041
Power System Master Plan 2016
Final Report
1-5
1.4.2 Five Viewpoints of PSMP2016
1 Enhancement of imported energy infrastructure and its flexible operation
For Bangladesh to become one of the high-income nations by 2041, the country needs to achieve
continuous economic growth of 7.4% annually for the period from 2016 to 2020 to initially reach the
standard of the medium to high income nations. Subsequently, its GDP would then grow steadily
although the growth rate may slow down slightly. With this economic growth, the demand for primary
energy, in particular in the industrial sector and the transport sector, is expected to increase sharply
under both the BAU and the energy efficiency scenario.
To meet this rapidly increasing demand for primary energy, the country needs to undergo a major
change from its existing dependency on domestic natural gas to a dependency on various imported
energies. During the period where imported energies are consumed in large quantities, the existing
inefficient energy resource consumption would directly lead to an enormous amount of economic loss.
In the future, the efficient use of energy, its supporting infrastructure and improvements to related
policies and systems will be essential. The infrastructure improvements include the domestic facilities
as well as interaction with neighboring countries. The policy and system improvements include the
strategic positioning of various energy resources and a legal system that promotes efficient use of
energy by revising the current inefficient practices.
2 Efficient development and utilization of domestic natural resources (gas and coal)
While the amount of deposits of natural gas discovered domestically is decreasing, the limited
resources must be utilized to the maximum by developing an efficient development structure.
Achievements in mining and the development of undiscovered resources are limited under the existing
structure and a drastic review is necessary, such as PSC reform and the introduction of technologies
from other countries. In addition, as mentioned in “1”, development of an infrastructure for the
economical and efficient use of gas and development and implementation of the system are necessary.
Since the domestically produced coal is of a high quality and the reserves are abundant, the future
development of an economical domestic coal development structure is important. Since domestic coal
development has a serious impact on the surrounding environment and society and requires a long
period of time, the necessary actions must be taken sufficiently in advance in anticipation of
VISION2041.
3 Construction of a robust, high-quality power network
To meet the rapidly increasing demand for power and to realize its stable supply, large-scale power
supply development and construction of system facilities are necessary. In terms of new issues and
opportunities for power supply development, power imports from neighboring countries (international
cooperation), and nuclear power generation can be considered. System enhancement is essential in
addition to these power supply developments.
In order to realize future rapid economic development, industrial development such as the transition to
higher value-added industries is essential for Bangladesh, necessitating high-quality power to support
such an advancement. Therefore, in the future, Bangladesh requires improvements in its infrastructure
and the development and implementation of a system that provides high-quality power for electrical
frequency stabilization, as well as the development of the power system.
4 Maximization of green energy and promotion of its introduction
For Bangladesh, which is susceptible to climate change, the development of low-carbon energies is
extremely desirable, not simply from the aspect of the international trend, recommending renewable
Power System Master Plan 2016
Final Report
1-6
energies and energy diversification, but from the point of improving energy access for rural people.
Therefore, development of domestic renewable energies is indispensable.
However, there is a limit to the introduction of renewable energies on a large scale in Bangladesh due
to the availability of appropriate land. Importing power from neighboring countries using
hydroelectric power generation has much greater possibility than supplementation programs for the
limited degree of renewable energy introduction in Bangladesh.
5 Improvement of human resources and mechanisms related to the stable supply of energy
To realize advanced utilization and the stable supply of energy and power for Bangladesh,
non-material support such as reform of the existing system, development of a new system, and
development of human resources for their implementation is essential, as well as material support such
as the construction of infrastructure. In particular, to cope with the coming era of mass consumption of
imported energy, efficiency improvement of gas fired power plants, and the development of legal
systems and human resources for its realization, are urgently necessary.
In the same way, significant improvements are required in many aspects of international cooperation
and nuclear power generation from Bangladesh’s existing power supply development and system
operation. Although the development of legal systems and human resources relating to international
cooperation and nuclear power generation is an extremely difficult task for Bangladesh, this task needs
to be achieved.
For power rates, structural reform of the existing below-cost power rates is necessary in terms of the
sustainability of the power sector. In the future, an increase mainly in household power rates is
required, which does not inhibit Bangladesh’s economic growth. In this case, cost reduction measures
must be taken by analyzing the possibility of cost reductions in the power generation, supply, and
distribution sectors prior to the decision-making on an increase in power rates, while alleviating the
impact on the lower socio-economic classes.
1.4.3 Importance of Contribution and Responsibility to the International Community
In 2015, the United Nations adopted the Sustainable Development Goals (SDGs) as the international
development goals. These goals have been established by using the development goals for the period
from 2000 to 2015, Millennium Development Goals (MDGs), as the foundation.
Plainly speaking, the old goals, MDGs, were development goals targeting “developing countries” and
adopted eight goals for poverty countermeasures for the period up to 2015.
The new goals, SDGs, are development goals that are set in 17 fields under “sustainable development”
as cross-cutting themes, including developed countries as well as developing countries. In particular,
the following goals are closely related to the energy and power fields.
Goal 7 “Clean energy for everyone”: Secure access to affordable, reliable, sustainable and modern
energy for everyone
Goal 9 “Industrial and technological innovation and social infrastructure”: By developing robust
infrastructure, promote inclusive and sustainable industrialization and also expand technological
innovation.
Goal 13 “Urgent handling of climate change”: Take urgent countermeasures for climate change and its
impact.
To become one of the advanced countries, proper recognition of contribution to the international
Power System Master Plan 2016
Final Report
1-7
society and its accompanying responsibilities are necessary. To establish this master plan, further
agreement with the major direction of the international society is required. The relationships between
these SDGs and this master plan are shown below.
Table 1-1 Link between PSMP2016 and the SDGs Sustainable
Development Goals: SDGs
Affordable and
clean energy
Industry, innovation,
infrastructure
Climate action
Ensure access to
affordable, reliable,
sustainable and modern
energy for all
Build resilient
infrastructure, promote
sustainable
industrialization and
foster innovation
Take urgent action to
combat climate change
and its impacts
Concept Energy for everyone and
clean energy
Infrastructure for
industries and
technological
innovation
Specific actions for
climate change
Specific contents Secure access to
affordable, reliable,
sustainable and modern
energy for everyone.
By developing robust
infrastructure, promote
inclusive and
sustainable
industrialization and
also expand
technological
innovation.
Take urgent
countermeasures for
climate change and its
impact.
Five key viewpoints
Viewpoint 1
Robust Energy Import Infrastructure
and Flexible Operation ◎
Viewpoint 2
Domestic Resources’ Efficient
Development and Use (Natural Gas
and Coal)
◎
Viewpoint 3
Quality and Robust Power System
Development ◎ ◎ ○
Viewpoint 4
Advanced Use of Green Energy ◎ ○ ◎
Viewpoint 5
Human Resource and System
Development for Stable Energy
Supply
○ ◎ ○
Source: UNDP Website and JICA Survey Team
Power System Master Plan 2016
Final Report
1-8
Practical Vision
1.5 Practical Vision
1.5.1 Relationships between the Five Key Viewpoints and the Master Plan Investigation Items
The table below shows the relationship between “the five key policy viewpoints” mentioned above
and the components of the master plan. The master plan is composed of a policy for the economic
growth, a plan on the primary energy balance, a plan on the power balance mainly based on the power
development plan and a policy on energy prices. The components of the master plan are closely related
to the five key viewpoints required for achieving the vision mentioned in the previous section as
shown in the table below.
Practical V
ision
PSMP Composition
Political Vision
Five Key Viewpoints
Viewpoint 1
Robust Energy
Import
Infrastructure
and Flexible
Operation
Viewpoint 2
Domestic
Resources’
Efficient
Development
and Use
(Natural Gas
and Coal)
Viewpoint 3
Quality and
Robust Power
System
Development
Viewpoint 4
Advanced Use
of Green
Energy
Viewpoint 5
Human
Resource and
System
Development
for Stable
Energy Supply
Economy Economic
Development ◎
Energy
Balance
2. Energy Demand
and Supply ◎
3. Gas ◎ ◎ ◎
4. Coal ◎ ◎ ◎
5. Oil ◎
Power
Balance
6. Power
Development Plan ◎ ◎
7. Hydropower ◎ ◎
8. Renewable
Energy ◎
9. power Import ◎ ◎
10. Nuclear Power ◎
11. Power System
Plan
◎
12. Powr Quality
◎
13. Thermal O&M ◎
Tariff 14. Energy Tariff ◎
Power System Master Plan 2016
Final Report
1-9
1.5.2 Methodologies for this Study
(1) Implementation flow
The overall methodologies and tasks for this study are summarized in the following flow chart.
Source: JICA Survey Team
Figure 1-1 Overall Workflow for This Study
(2) Study on the Future Scenarios of Economic Development
To begin with, this Study considers the future scenarios of economic development in Bangladesh as
the baseline data for energy supply and demand projections.
Taking into account that this study is targeting the period up to 2041, which is considerably long,
structural changes to the Bangladesh economy are expected to occur during its course. That is,
macroeconomic parameters for energy demand forecasts such as GDP and industrial production need
to be projected on the condition that non-linear structural changes to the national economy will take
• Population, GDP
• industrial production etc.
• Projection of sectorial energy demand
based on economic indicators.
Sectorial Energy Demand Projection
• The modes of energy supply to each sector is determined
considering the nature of energy demand.
Energy Supply to Each Sector
Residential
Commercial and public service
Industrial
Transport
Agriculture etc.
Residential
Commercial and public service
Industrial
Transport
Agriculture etc.
Others
OilNatural Gas
Electricity
(Grid)
Macroeconomic Prospects
• Scenarios of long-term
structural changes of
the economy referring
to the experiences of
Asian countries
Economic Development Scenarios
• Necessary volume of energy supply to meet the demand is estimated.
• Insufficient domestic production is supplemented by imports
Primary Energy Balances
Natural GasCrude
oilCoal Others
Imports (LNG, Coal, etc.)
Domestic production
• Production potential of natural gas, crude oil, coal etc.
Availability of Domestic Energy Sources
• The modes of energy supply (especially electricity) is also
determined based on the availability of primary energy sources.
Energy Transfers from Primary Energy Supply
Natural Gas Crude oil Coal Others
Electricity (Grid)
Non-electricity supply
• Optimized set of 3E needs to be considered
- Economic viability
- Environmental quality
- Energy security
Considerations for 3E
Demand-side
Analysis
Supply-side
Analysis
En
erg
y S
up
ply
& D
em
an
d A
naly
sis
Po
wer
Su
pp
ly M
aste
r P
lan
• Necessary CAPEX for forming the infrastructure of energy supply (electricity, natural gas etc.) is formulated from the previous sections, then the costs
of energy supply up to 2041 are estimated.
• The energy tariff in Bangladesh, which is generally set lower than the actual costs of supply with subsidies, needs to be adjusted to be cost-reflective
with the progress of economic development.
2015 2041
Projection of Costs of Energy Supply and Tariff Policy
Costs of energy supply in 2015 (electricity, gas etc.)
Estimated costs of energy supply in 2041
Tariff of energy supply in 2015
1. Cost-reflective tariff to be achieved as early as possible
2. Cost-reflective tariff to be achieved but as a future challenge
3. Tariff remains to be subsidized even in the future
Options of Energy Tariff Policy (example)
Subsidies
• It needs to be noted that raising energy tariff may cause a negative effect on national economy in Bangladesh, such as the competitiveness of the
industrial sector. If a seriously negative effect is expected, policy tools for mitigation (e.g. subsidies) may be justified.
• The impact of energy tariff increase on the national economy is quantitatively analyzed using GTAP (Global Trade Analysis Project) model.
Impact of Energy Tariff Increase on National Economy
En
erg
y S
up
ply
Ta
riff
An
aly
sis
Power System Master Plan 2016
Final Report
1-10
place along with the development of Bangladesh economy.
Though it is hardly possible to determine such structural changes quantitatively, this study considers
the future scenarios of economic development that are likely to occur in Bangladesh, as ascertained
through discussion with local stakeholders. The Government of Bangladesh (GoB) has set an
ambitious target for the country to become a member of the “High-income Countries” by 2041, though
the details to support this have not been provided. This Study also evaluates the feasibility of this
target through the economic development projections and provides policy recommendations for
achieving the economic development target.
(3) Energy Demand Forecast and Projection of Necessary Volume of Primary Energy Supply
Referring to the projection of economic development, this Study formulates the energy demand
forecast and then estimates the necessary supply that meets the energy demand in the future.
It also needs to be noted that the optimized set of energy supply varies among countries depending on
their geographical and geopolitical conditions. Especially for a country like Bangladesh, where the
domestic energy production such as natural gas has mainly satisfied the domestic demand but the
depletion of energy production and increased dependence on imported energy sources are expected in
the future, it is appropriate to develop the energy supply plan by prioritizing the optimized utilization
of domestic energy production and then by incorporating the imported energy sources in the energy
supply system to fill the insufficiency.
Therefore, this study first estimates the total volume of primary energy supply necessary for
Bangladesh based on the energy demand forecast and then estimates the requirement for each energy
source as the combination of domestic energy production and imports.
(4) Power Supply Master Plan
For the meanwhile, this Study also formulates the energy supply and demand balance in terms of the
modes of energy supply to end consumption of energy. Among the various modes of energy supply,
the electricity supply needs more specific considerations for infrastructure development, thus this
study segregates the sections related to power supply and presents the “Power Supply Master Plan”.
In order to determine the optimized set of supply modes, this study takes approaches from both the
demand-side and supply-side. From the demand-side, each mode of energy supply (electricity, natural
gas, oil products etc.) is projected as a part of the aforementioned energy demand projection and the
electricity demand is determined. In Bangladesh, the electrification of unelectrified villages is still in
progress and even in the already electrified villages a shift of energy supply to electricity from other
modes will continue to occur. These transitions need to be considered in an appropriate timeline.
From the supply-side, how to match the primary energy supply sources with the modes of energy
supply is analyzed. Because forming energy supply infrastructure requires a considerably long
lead-time, drastic change of energy supply modes in a short time is not possible. Hence, an appropriate
timeline for infrastructure development also needs to be considered so that the existing energy
infrastructure will be gradually strengthened and modified. For example, the industrial sector, which is
supposed to increase energy demand rapidly in Bangladesh, may consume more electricity from the
grid if sufficient volume of electricity supply from the grid exists. However, because of the limitation
with grid power supply and the considerable capacity of existing captive power generation that has
been installed in the past, it may take time to phase out the use of electricity from captive power
generation, which is generally less efficient than the power supply from the grid.
Then, the analyses from both the demand-side and supply-side are harmonized to determine how to
establish the energy supply to end consumption. The future requirements of the primary energy supply
will be finalized by calculating back from the energy supply to end consumption, considering that the
energy loss from transfer (e.g. power generation), transport and consumption differs among different
modes of energy supply.
(5) Quantitative Evaluation of 3E
Power System Master Plan 2016
Final Report
1-11
For identifying the best energy mix scenario for “Power Supply Master Plan”, 3E (economic viability,
environmental quality, and energy security) evaluation is employed.
Needless to say, for a country like Bangladesh where energy demand is expected to increase rapidly to
sustain the economic development, economic viability, i.e. “assuring that energy supply meets the
energy demand in an economically reasonable way”, needs to be considered as a priority.
However, as the country’s economic development is expected to reach a certain level of maturity by
2041, which coincides with GoB’s national target of the country becoming a member of the
“High-income Countries”, this Study expects that the energy policy will need to assume responsibility
beyond “low-cost supply” and that it will affect the structure of energy supply in Bangladesh. The
country is expected to raise its domestic and international commitments to reduce environmental
burdens such as greenhouse gas emissions. Considering that these environmental commitments can
affect the plan for future energy supply, this study discusses with the stakeholders the policy options
that the country will need to prepare.
In addition, as the Bangladesh economy will continue to be enhanced and modernized, the necessity
for stability of energy supply is expected to gain importance. In order to achieve stability of the energy
supply, not only improving the energy supply infrastructure itself but also improving stability in the
upstream of the supply chain, i.e. stability of quantity and prices to secure primary energy supply, will
gain more importance. There is some literature both in Japan and overseas that has attempted a
quantitative evaluation of energy security, but standardized methodologies have not been established.
It also needs to be noted that the main concerns about energy security may differ among countries.
Therefore, in evaluating the energy security of Bangladesh, these past studies are reviewed but their
methodologies are not strictly followed. An appropriate set of performance indicators is introduced
through discussion with stakeholders in Bangladesh.
This study proposes a future energy supply that is appropriate for Bangladesh as a “responsible”
developed country, taking also into account quantitative evaluations not only from the aspect of
economic viability but also from the aspects of environmental commitments and energy security.
(6) Analysis of the Financial Conditions of the Power Sector and the Costs of Power Supply
Following the results of supply and demand projections for energy and power conducted in the
previous sections, this study analyzes the financial conditions of the power sector in Bangladesh and
the costs of the power supply.
In order to achieve self-contained and sustainable management of the power supply, the power supply
tariff should be set at a level so that these supply costs can be appropriately recovered from
end-consumers. The current status in Bangladesh, however, is that the tariff is set at a low level that
can hardly recover the costs appropriately. This study discusses the direction of power tariff reforms
while ascertaining the overall picture of the power sector’s financial conditions and the costs of power
supply.
(7) Estimation of the Impact of Energy Tariff on National Economy
On the other hand, it is common worldwide that raising energy tariffs is a politically sensitive issue
and that tariff reforms may need to be made gradually. In addition, drastically raising the energy tariff
at the time when the manufacturing sector of a country starts to develop and to be exposed to
international competition may affect the sector’s international competitiveness.
Therefore, the study on the energy supply tariff in Bangladesh up to 2041 needs to analyze how the
“cost-reflective tariff will affect the national economy depending on the timeline to achieve this”,
taking into consideration the level of economic development.
In order to evaluate the effects of raising energy supply tariffs on the national economy quantitatively,
this study runs the simulation model called GTAP (Global Trade Analysis Project). Referring to the
results of this simulation, this study makes a policy recommendation on the future energy supply tariff.
Power System Master Plan 2016
Final Report
1-12
1.5.3 Scope of work
The Survey had been carried out according to the minutes between JICA and the Bangladesh
government. The JICA Survey Team conducted the following items and make reports on the basis of
the survey policy and considerations. The Survey started at the end of October 2014, be carried out as
per following Table, and the Final Report had submitted in September 2016.
Table 1-2 Contents of the Study
Contents of the Study
1 Confirmation of the background
2 Review of PSMP2010 and develop PSMP2016
Primary energy demand and supply scenario
O&M policy
Best Mix of generation power sources
Study of issues related to generation plant and transmission line system development plan
Study of consistency of off-grid renewable energy development and power development plan
Study of economic impact on energy price hike and its countermeasures
Study of JICA’s potential projects in power and energy sector
3 Collect information on O&M
Current O&M situation in national thermal power plants
Collection of basic data for upgrading national power plants to combined cycle
Selection of model thermal power plant among existing plants to consider O&M and upgrading
to combined cycle
Cost-benefit analysis, risk analysis and assistant approach for model power plant
Study of legal framework for sustainable O&M implementation
Concept level plan of the combined cycle to model plant
Arrangement of risks and issues in the application of combined cycle; examination of JICA
approach
Report on the study from legal system examination
4 Collect information on domestic hydropower potential
Review of existing documents about micro hydropower plant and interviews with related
agencies
Site survey, analysis and selection of potential hydropower plant, such as Kaptai Lake
Preparation of the TOR for the required F/S or pre-F/S in the next stage
Preliminary Social and environmental evaluation for the proposed project sites
5 Primary Energy(Fuel)
Study and collect basic information for primary energy demand forecast and making supply
plan
Study of development regarding Seventh five-year plan
Preparation of prospects for economic development and energy demand forecast by 2041
Consideration of exploration of undiscovered domestic natural gas and development plan
Preparation of primary energy supply plan
Calculation of cost required for developing infrastructure for energy supply
Review of price in terms of domestic energy supply
Making financial plan (Future scenario considering price hike for energy supply)
Technical issues related to reviewing introduction of LNG receiving terminal
Confirmation of status of LNG receiving terminal plan in progress
6 Improvement Measures for Power Quality
(1) Proposal for Preparation of a Legal Framework, rules and improvement of work procedures
Propose and support the preparation or amendment of various rules with reference to the rules in
Power System Master Plan 2016
Final Report
1-13
Contents of the Study
Japan (or Europe/America, if necessary) and TEPCO.
Check progress of amendment of the Grid code by BPDB and suggest reinforcement of NLDC’s
orders and generator participation in frequency control.
(2) Draft plan for frequency quality improvement
Evaluate the frequency quality improvement by introducing generators with frequency control
functions.
Propose the development of a future plan for securement of spinning reserve (free governor
mode, LFC) and roadmap for frequency quality improvement for PGCB (NLDC) and BPDB,
and regulating authorities (Energy division and BERC).
(3) SCADA system renewal plan for NLDC
Confirming needs for introducing new functions or adding data to NLDC’s SCADA system, in
order to realize online output instruction orders for power stations.
Possibility study for introducing Japanese SCADA system
7 Holding of the seminars
1st Seminar (November 2014, Dhaka)
Agenda: Explanation of and discussion on the survey plan
2nd Seminar (June 2015, Dhaka)
Agenda: Explanation of and discussion on the interim report
3rd Seminar (December 2015, Dhaka)
Agenda: Explanation of and discussion on the interim report (reflecting survey results after 2nd
Seminar)
4th Seminar (June 2016, Dhaka)
Agenda: Explanation of and discussion on the survey results in the draft final report
8 Reports to be submitted
Inception Report (October 2014)
Interim Report (December 2015)
Draft Final Report (June 2016)
Final Report (September 2016)
Source: JICA Survey Team
Power System Master Plan 2016
Final Report
1-14
1.5.4 Survey Implementation Feamework
Five years have already passed since the latest PSMP2010 was prepared, so the Survey targeted not
only a review of PSMP2010 but also studied the plan up to 2041. The review of the Survey was
discussed and confirmed with the government and relevant agencies in Bangladesh, and also with
JICA.
The Survey was conducted with one steering committee and four subordinate working groups to
facilitate consensus building over a wide area of the relevant organizations. The committee and all
technical discussion meeting were set up on the initiative of the Power Division (PD) of the Ministry
of Power, Energy and Mineral Resources (MPEMR).
(1) PSMP2010 Review Steering Committee
The Steering Committee members include PD of MPEMR, Energy and Mineral Resources Division
(EMRD) of MPEMR, Power Cell (PC) of MPEMR, Bangladesh Power Development Board (BPDB),
Power Grid Company of Bangladesh (PGCB), Secretary, Economic Relations Division (ERD) of
Ministry of Finance (MF), Financial Division (FD) of MF, Ministry of Law, Justice, & Parliamentary
Affairs (MLJPA), Ministry of Water Resources (MWR), and the Prime Minister’s Office. The Steering
Committee is the organization that makes the highest decisions based on the discussions with the 5
subordinate technical discussion meeting.
(2) PSMP2010 Review Technical discussion meeting
The PSMP2010 Review Working Group members include PD of MPEMR, EMRD of MPEMR, PC of
MPEMR, Sustainable and Renewable Energy Development Authority (SREDA), BPDB, generation
corporation, PGCB including National Load Dispatch Centre (NLDC), Infrastructure Development
Company Limited (IDCOL), Petrobangla and its subordinate companies, ERD of MF, and FD of MF.
Technical discussion meeting will discuss the reduction of subsidiaries for energy utilities, the impact
on the amount of LNG imports and the prices of electricity and gas, the coexistence of off-grid
renewable energy and on-grid equipment, and issues across the executing agencies.
(3) Thermal Power Plant O&M Technical discussion meeting
The O&M Working Group members include PD of MPEMR, PC of MPEMR, BPDB, generation
corporation, PGCB including NLDC, Petrobangla and its subordinate companies, and MLJPA.
Technical discussion meeting will discuss the amendment of the Electricity Act, and related laws and
regulations.
(4) Hydropower Development Technical discussion meeting
The Hydropower Development Working Group members include PD of MPEMR, MWR, and BPDB.
Technical discussion meeting will discuss the impacts and countermeasures downstream due to the
planned dam construction, and issues related to the executing agencies.
(5) Primary Energy Technical discussion meeting
The Primary Energy technical discussion meeting was composed as a counterpart agency to PD of
MPEMR, and as a new counterpart agency to the Energy Division (ED).
(6) Improvement Measures for Power Quality Technical discussion meeting
Improvement Measures for Power Quality technical discussion meeting cooperates with the Master
Plan technical discussion meeting and Thermal Power technical discussion meeting. Technical
discussion meeting examines proposals for Preparation of a Legal Framework, rules and
improvements for work procedures, and a draft plan for frequency quality improvement.
Power System Master Plan 2016
Final Report
1-15
Source: JICA Survey Team
Figure 1-2 Implementation framework
Power System Master Plan 2016
Final Report
1-16
1.5.5 JICA Study Team
The JICA Study Team is composed of the following members.
Assignment Name
Team Leader/Power Development Plan (A) Toshiyuki Kobayashi
Adviser to PM/Power Development Plan (B) Kunio Hatanaka
Power System Planning A Masaharu Yogo
Power System Planning B Shinichi Funabashi
Primary Energy Analysis 1A (Coal) Hajime Endo
Primary Energy Analysis 1B (Gas and Oil) Kazuo Koide
Primary Energy Analysis 2A (Energy Balance) Tomoyuki Inoue
Primary Energy Analysis 2B (Energy Balance) Takeshi Aoki
Economic and Financial Analysis A Shigefumi Okumura (Kei Owada)
Economic and Financial Analysis B Dinh Minh Hung
Energy Supply Cost Analysis Satoko Horie
Environmental & Social Considerations A Shigeki Wada
Environmental & Social Considerations B Akiko Urago
Renewable Energy Masaki Kuroiwa
Rural Electrification Toshifumi Watahiki
Transmission and Substation Equipment Osamu Matsuzaki
Sub-team Leader/Thermal Power Plant O&M A Genshiro Kano
Thermal Power Plant O&M B Ken Shimizu
Thermal Fired Power Plant Ability Analysis A Masahiro Ose (Sho Tai)
Thermal Fired Power Plant Ability Analysis B Hiroyuki Sako (Eiji Naraoka)
Thermal Fired Power Plant Ability Analysis C Yusuke Irisawa
Legal Framework Design Katsuhiro Komura
Hydropower Planning Jun Tamagawa
Sub-team leader (Primary energy)/
Energy economic analysis Yasushi Iida
Economic growth strategy Masaya Nakano
Environmental Policy Shunsuke Kawagishi
Energy supply and demand analysis (Commercial) Mari Iwata (Sayaka Okumura)
Energy supply and demand analysis (Industrial) Hideshige Matsumoto
Energy supply and demand analysis (Transportation) Hidenao Tanaka
Energy supply and demand analysis (Energy Model) Yumiko Watanabe
Macroeconomic Analysis Akiko Higashi
Energy supply and demand analysis (Electric Power) Daichi Saito
Power System Master Plan 2016
Final Report
1-17
Assignment Name
Energy development analysis
(LNG gas development A) Hideo Matsushita
Energy development analysis
(LNG gas development B) Uichiro Machida
Energy development analysis
(LNG gas development C) Daihachi Okai
Energy development analysis
(Interior Natural gas development) Masaaki Ebina
Sub-team leader/Power system operation A Shinichi Suganuma
Power system operation B Masafumi Shinozaki
Power system operation C Keisuke Ueda (Hideaki Kuraishi)
Power system facilities A Kazuki Kito
Power system facilities B Hisanori Masuda (Naoto Tokoda)
Power system facilities C Keisuke Kusuhara
Sub-team leader (Energy strategy)/Energy policy Minako Matsukawa (Mochida)
Payment structure (Electric power and Gas) A Masato Muto
Payment structure (Electric power and Gas) B Junji Ueda
1.5.6 Past Activities
(1) 1st Seminar (1
st Steering Committee)
Date: 29 October 2014
Venue: Board Room of BPDB at Buddyut Bhaban, Dhaka
Discussion Point: Explain for Inception Report
Establishment of Steering Committee (SC) and the Working Group (WG) for the Survey.
Explained the survey objectives, methodologies, member, and implementation schedule
(2) 2nd
Seminar (2nd Steering Committee)
Date: 4 Jun 2015
Venue: Board Room of BPDB at Buddyut Bhaban, Dhaka
Discussion Point:
Primary Energy Balance for Power Sector
Power Demand Forecast
Power Development Plan
Power System Master Plan 2016
Final Report
1-18
(3) 3rd
Seminar (3rd Steering Committee)
Date: 15 December 2015
Venue: Board Room of BPDB at Buddyut Bhaban, Dhaka
Discussion Point:
Project Outline
Primary Energy
Power Demand Forecast and Power Development Plan
Power Quality
Operation and Maintenance (O&M)
(4) Pre- High Level Discussion Meeting (Tokyo)
Date: 5 Apr 2016
Venue: TEPCO Headquarter (Tokyo)
Discussion Point:
Economic Development
Primary Energy Balance
Power Balance
Cost and Tariff Balance
(5) High Level Discussion (Dhaka)
Date: 7 April 2016
Venue: Bijoy Hall, Bidyut Bhaban, Power Division, MoPEMR
Discussion Point:
PSMP 2010/2016 comparison
Macroeconomic Projection & Industrial Policy
Power System Master Plan 2016
Final Report
1-19
Energy Balance Strategy
Energy Efficiency Target Setting & Supply-Demand Balance
Power Balance Strategy
A Project Outline and Road Map
(6) 4th Seminar (4th Steering Committee)
Date: 18 June 2016
Venue: Bijoy Hall, Bidyut Bhaban, Power Division, MoPEMR
Discussion Point: Explain for Draft Final Report
Economic Development
Primary Energy Balance
Power Balance
Cost and Tariff Balance
(7) Official comments meeting for Final Report (FR)
Date: 1,2,4 August 2016
Venue: TEPSCO Headquarter (Tokyo)
Discussion Point:
Economic Development
Primary Energy Balance
Power Balance
Cost and Tariff Balance
(8) Official comments meeting for Final Report (FR)
Power System Master Plan 2016
Final Report
1-20
Date: 7 September 2016
Venue: TEPCO Headquarter (Tokyo)
Discussion Point:
Continuous Technical Support for Post-PSMP2016
Power System Master Plan 2016
Final Report
1-21
Technical Focal Poits
1.6 Focal points
1.6.1 PSMP 2010 Review
(1) Economic Development
Table 1-3 and Figure 1-3 compares the actual performance of GDP growth rate with the projected
growth rate in PSMP 2010 and the target of GDP growth rate in the Sixth Five-Year Plan that was set
forth by the GOB in 2011. During the period of the Sixth Five-Year Plan, Bangladesh achieved annual
average of 6.3% growth rate. This was higher than the actual growth rate in each of the past five-year
plans (1st-5
th) and the result implies that the country started taking a path of rapid economic growth.
However, the economic growth rate still underperformed the target of the Sixth Five-Year Plan
(average 7.3% growth) every year and the gap was widened in the later years. The actual growth rate
was also lower than the projection of PSMP2010 that expected the Bangladesh economy to attain 7%
growth. The main factor of this gap is supposed to be the delay of economic reforms for inducing
further economic growth. The country may not be able to fully reap the opportunity of economic
development and the growth rate may continue underperforming the government’s expectation unless
economic policies to promote the development are not in place as planned.
Table 1-3 PSMP2010 Review (Economic Development)
FY
GDP Growth Rate (real price)
PSMP2010
Projection
6th Five-Year
Plan Actual
[%] [%] [%]
2009/10 5.5% - 5.6%
2010/11 6.7% 6.7% 6.5%
2011/12 7.0% 6.9% 6.5%
2012/13 7.0% 7.2% 6.0%
2013/14 7.0% 7.6% 6.1%
2014/15 7.0% 8.0% 6.6%
Average 6.9% 7.3% 6.3% Source: JICA Survey Team
Note: the average in the table is the five-year average from FY2010-2011 to FY2011-2012
Source: JICA Survey Team
Figure 1-3 PSMP2010 Review (Economic Development)
6.7%7.0% 7.0%
7.0% 7.0%7.0%
6.7% 6.9%
7.2%7.6% 8.0%
5.6%
6.5% 6.5%6.0% 6.1%
6.6%
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
2010/11 2011/12 2012/13 2013/14 2014/15 2015/16
GDP Growth Rate (real)
PSMP2010 Projection
6th Five-year Plan
Actual
5.5%
6.7%7.0%
7.0% 7.0%7.0%
6.7%6.9%
7.2%7.6% 8.0%
5.6%6.5% 6.5%
6.0% 6.1%
6.6%
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
2009/10 2010/11 2011/12 2012/13 2013/14 2014/15
GDP Growth Rate (real)
PSMP2010 Projection
6th Five-Year Plan
Actual
5.5%
6.7%7.0%
7.0% 7.0%7.0%
6.7%6.9%
7.2%7.6% 8.0%
5.6%6.5% 6.5%
6.0% 6.1%
6.6%
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
2009/10 2010/11 2011/12 2012/13 2013/14 2014/15
GDP Growth Rate (real)
PSMP2010 Projection
6th Five-Year Plan
Actual
Power System Master Plan 2016
Final Report
1-22
(2) Domestic Coal Production
Table 1-4 shows the performance and the forecast of coal production in PSMP2010 and Figure 1-4
shows them by chart. Annual production of 1 million tones will be possible using existing facilities.
New longwall mining equipment called LTCC (Longwall Top Coal Caving) for thick coal seams was
introduced in May 2013 from China and the mining height was increased from 3 meters to about twice
this. Actual mining height is not clear, but mining efficiency was obviously improved. The coal
production in 2013/14 achieved 0.947 million tons. However, in 2014/15, the figure decreased to
0.676 million tons. The main reason for this was a delay in the withdrawal and installation of the new
equipment on-site. It is normal for people to take time to become skilled in the use of new equipment.
If they can master the operation technology of the new facilities, it is surmised that 1,000,000t is quite
possible.
Table 1-4 PSMP2010 Review (Coal Supply)
Source: JICA Survey Team
Source: JICA Survey Team
Figure 1-4 PSMP2010 Review (Coal Supply)
PSMP2010
PlannedActual Gap
[1000tons] [1000tons] [%]
2009/10 705
2010/11 667
2011/12 1,000 835 84%
2012/13 1,000 855 86%
2013/14 1,000 947 95%
2014/15 1,000 676 68%
Average 1,000 781 83%
FY
Coal Supply
Power System Master Plan 2016
Final Report
1-23
(3) Gas Supply
Five year gas supply projection in the PSMP2010 was reviewed against the actual supply records from
2009/10 through to 2014/15. The results show that the actual supply figure is 15 points lower than that
of the projected figures. The projection was made based on the gas reserve data by Hydrocarbon Unit
(HCU) (2011); however, the projection did not reflect the gas field development plan or investment
plan for new and/or existing gas fields after 2010/11. There are also differences in gas reserve data
between Hydrocarbon Unit (HCU) (2011) and USGD/Petrobangla. Hydrocarbon Unit (HCU) (2011)
uses P90/P50/P10 while USGD/Petrobangla uses P95/Mean/P05 for gas reserve assessment, hence the
USGD/Petrobangla gas reserve appears smaller. The difference between the projection and actual is
considered as a combination of all these factors.
Table 1-5 PSMP2010 Review (Gas Supply)
Source: JICA Survey Team, based on the HCU and Petrobangla data
Source: JICA Survey Team, based on the HCU and Petrobangla data
Figure 1-5 PSMP2010 Review (Gas Supply)
PSMP2010
PlannedActual Gap
[mmsfd] [mmsfd] [%]
2009/10 1,995 1,929 97%
2010/11 2,225 1,942 87%
2011/12 2,673 2,038 76%
2012/13 2,636 2,195 83%
2013/14 2,765 2,247 81%
2014/15 2,730 2,441 89%
Average 2,504 2,132 86%
FY
Gas Supply
Power System Master Plan 2016
Final Report
1-24
(4) Power Demand and Power Development Plan
The figure below shows the five-year power demand forecast in PSMP 2010 and the actual power
demand. When PSMP 2010 was formulated five years ago, the demand was estimated to increase to
around 10,000 MW by 2015. However, the actual demand in 2015 was approx. 80% of the estimate,
around 8,000 MW.
The increase in the power demand including potential demand driven by the rapid economic
development in recent years is expected to continue. The shortage of supply is considered to be the
main cause of the continuation of this imbalance between the supply and demand. The figure below
shows that the actual outputs of the gas and coal thermal power generation were only at 40% and 60%
of the outputs described in PSMP 2010, respectively. In the case of the coal thermal power generation,
a very important base load power source in the energy mix, while the output in 2015 was forecast at
1,850 MW in PSMP 2010, even the construction of coal power plants has not been commenced five
years after the formulation of the plan. The lack of integrated planning and implementation of the
construction of large-scale port facilities indispensable for the stable import of fuel and the
construction of the power plants and the increased difficulty in fundraising for such a large-scale
infrastructure development are considered to be major factors for the failure to develop power
generating facilities as planned.
Therefore, it is considered necessary for the Energy Division and the Power Division to develop an
organizational structure and operating system more integrated than before and take concerted
measures to formulate a joint infrastructure development plan, to raise fund in the public-private
partnership and to develop infrastructure systematically for the achievement of the stable energy
supply, a source of the future economic development.
Source: JICA Survey Team
Figure 1-6 PSMP2010 Review (Power Development Plan)
Power System Master Plan 2016
Final Report
1-25
1.6.2 Economic Development Policy
(1) Current Status and Issues
Bangladesh’s economy has seen steady growth since independence was declared in 1971. GDP per
capita has been steadily expanding since the 1990s, when the ready-made garments (RMG) sector
emerged as a major export industry for the country. GDP annual growth rate during the Sixth
Five-Year Plan from 2011 to 2015 averaged 6.3%. According to the Seventh Five-Year Plan
formulated by the Government of Bangladesh, the average GDP growth rate from 2016 to 2020 is
expected to reach 7.4%.
Based on this, the JICA Survey Team conducted Bangladesh’s economic forecasting up to the year
2041 and the result is summarized in the following table. This projection assumes that Bangladesh’s
economy continues to grow as projected in the Seventh Five-Year Plan during the first half of the
2020s, and GDP growth rate is expected to become moderate after the mid-2020s, when the country’s
economic development reaches a certain level of maturity. Bangladesh’s economy will continue to
grow steadily so that its GDP per capita (nominal base) is expected to reach 10,993 US$ in 2041.
According to the income classification by the World Bank, Bangladesh will become a member of the
upper-middle-income economies in the 2020s and will get close to the high-income economies by
2041 if the economic development is achieved as projected.
Table 1-6 Projection of GDP and GDP per capita up to 2041
2010 2015 2020 2025 2030 2035 2041
GDP (million USD) *1
93,236 126,630 181,282 258,598 351,109 453,642 587,665
GDP Growth Rate (p.a.) *1
6.1% 6.3% 7.4% 7.4% 6.3% 5.3% 4.4%
GDP per capita (USD) *1
615 787 1,063 1,444 1,883 2,357 2,970
GDP per capita (USD) *2
760 1,207 1,998 3,270 5,060 7,396 10,993
Note: Average growth rate is a five-year average except in the column for 2041, which is a six-year average.
*1: Real Basis at 2005 price
*2: Nominal Basis
Source: JICA Survey Team
Until now, Bangladesh’s economic growth has been maintained by labor-intensive industries such as
the garment industry. However, heavy dependence on these industries is not sufficient to sustain
further economic growth on a long-term basis. It is necessary to achieve industrial structural changes
in Bangladesh by diversifying industries and to foster high value added industries by implementing
proactive industrial policies.
Present value added by sub-sectors in the manufacturing sector of Bangladesh is shown in the figure
below. The textile industry is the largest in the manufacturing sector and accounts for approximately
60% of the total value added in the sector. In addition, there exist other industries such as “machinery
and parts”, “processed foods”, “plastic products” and “metal products” in the manufacturing sector,
but these industries’ share in value added is still limited. These industries may possibly change the
industrial structure of Bangladesh’s economy.
Power System Master Plan 2016
Final Report
1-26
Note: (p) indicates “provisional”.
Source: Prepared by JICA Survey Team referring to BBS “Bangladesh National Account Statistics: Sources and Methods
2013-14”
Figure 1-7 Value Added by Large and Middle Scale Manufacturing Industries
The following figure is a conceptual illustration of Bangladesh’s future industrial development up to
2041. While Bangladesh’s economy will continue to depend greatly on traditional industries, namely
the RMG, jute and leather industries, until the beginning of the 2020s, new industries will grow
gradually. Export items are expected to become diversified, such as light engineering products,
processed foods and pharmaceutical products. From then on, i.e. toward 2041, this diversification will
expand to higher value added new industries and products such as electronics, information and
technology/software, automobile parts, machinery and shipbuilding.
To achieve such industrial development, it is necessary to implement various industrial policies
including incentives for foreign direct investment, infrastructure development and industrial human
resource development.
Source: JICA Survey Team
Figure 1-8 Illustration of Industrial Development in Bangladesh Toward 2041
(2) Targets to Achieve
Achieve high economic growth rates with an average annual growth rate of 7.4% until 2025 and
become a member of upper-middle-income economies (at a GNI (Gross National Income) per
capita of 4,126 US$ or more) in mid-2020s.
Maintain high economic growth from 2025 onward and achieve GDP per capita equal to that of
high-income economies (at a GNI per capita of 12,736 US$ or more) by 2041.
Food, Beverage, Tobacco
6.6%
Textile60.5%
Foot ware3.1%
Saw Milling, Wood Products and Furniture
& Fixtures1.6%
Paper and its product, Publishing, Printing
1.3%
Petroleum, chemical, Rubber and Plastic
products4.0%
Glass and Non-Metalic Mineral Products
8.0%
Iron, Steel and Non-Ferrus Metal Products
3.1%
General Machine, Electric Machine,
Products and Parts0.5%
Transportation Machine, Parts and
Accessaries10.3%
Jute and Jute Goods(70% of export;1981)
RMG(80% of export;2015)
Diversification of Export
Light EngineeringAgro ProcessingPharmaceuticals
2021 2041
ElectronicsICT/SoftwareAuto PartsMachinesShipbuildingPetrochemical and Steel
Power System Master Plan 2016
Final Report
1-27
Foster high value-added industries and facilitate export-oriented industrialization so as to achieve
high economic growth rates. Toward this end, implement appropriate industrial policies according
to the stage of industrial development.
(3) Roadmap
It is estimated that Bangladesh is currently on the way to Phase 2 of the following industrialization
process and is likely to move toward Phase 3. To maintain long term economic growth without stalling
current favorable economic conditions, it is necessary to implement the following measures for further
advancement of domestic industries.
Short and medium term: incentives for foreign direct investment; various infrastructure
developments such as construction of industrial parks like SEZ, ports, roads, railways and power
plants.
Medium and long term: construction of industrial parks; facilitation of infrastructure
development; industrial human resource development such as development of skilled labor force;
promotion of deregulation and economic liberalization.
Source: JICA Survey Team
Figure 1-9 Stages of Industrial Development and Necessary Policy Measures to Support This
1.6.3 Primary Energy
(1) Current Status and Issues
Based on the aforementioned economic growth outlook, energy consumption outlook by sector until
2041 was studied. Final energy consumption outlook and the sectoral breakdown in the BAU scenario
without considering the effects of energy-saving measures are indicated in the figure below.
Source: JICA Survey Team
Figure 1-10 Projection of Final energy Consumption (BAU Scenario)
With the rapid advancement of industrialization in Bangladesh, it is expected that there will be a shift
Agro Production
Phase 1
Import SubstitutionIndustrialization
(Easy Substitution/Light Industry)(Labor Intensive Industry)
Phase 2
Export OrientedIndustrialization
(Labor Intensive Industry)
Phase 3
Export OrientedIndustrialization(Technology & Capital
Intensive Industry)
Support Policy Support Policy Support Policyinfant industry protection-high tariff-restrictions on imports
Incentives to FDISEZ, EPZDevelop infrastructure
Skilled labor developmentLiberalization & relaxation of regulations
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040
[kto
e]
Residential Industry Commercial and public servises Transport Agriculture etc. Non-energy use
Projection
Power System Master Plan 2016
Final Report
1-28
in the industrial sector from labor-intensive industries like RMG to energy-intensive industries. As a
result, energy consumption in the industrial sector is expected to increase rapidly. In addition, in the
transport sector, as growth in GDP per capita is expected to facilitate vehicle ownership from the
middle of the 2020s onward, it is estimated that energy consumption in the transport sector will
significantly exceed that of the residential sector in the future.
It is estimated that the average annual growth rate of total final energy consumption including the
aforementioned two sectors will be 6.3% between 2014 and 2041. According to this BAU scenario, the
growth in energy consumption will slightly exceed the GDP growth rate (annual average real GDP
growth rate is 6.1%). Though total energy consumption per GDP tends to decrease until the middle of
the 2020s, it is expected to turn upward and, in 2041, reach the same level as the actual figure in 2014
(3.42 toe/million BDT).
For the purpose of relieving rapid growth in energy consumption in Bangladesh in the future, “Energy
Efficiency and Conservation Master Plan up to 2030” (EECMP) was formulated in March 2015,
supported by JICA. In light of the survey results from EECMP and based on the assumption that
measures proposed in the Master Plan will be properly implemented, it is estimated that total energy
consumption per GDP will decrease as follows in the Energy Efficiency Scenario. The difference
between the figure in this Scenario and the target set in the EECMP (energy consumption per GDP in
2030 is -20% compared to 2014) was due to the difference in definition. For example, calculation in
this Scenario considered the transport sector, which was not included in the EECMP’s calculation. If
calculation is carried out on the basis of the same definition, energy consumption per GDP in 2030 is
-20% and that in 2041 is -23% compared to 2014.
2.65 toe/million BDT as of 2030 (decrease of 23% compared to 2014)
2.56 toe/million BDT as of 2041 (decrease of 25% compared to 2014)
Source: JICA Survey Team
Figure 1-11 Projection of Final Energy Consumption (Energy Efficiency Scenario)
The projection of primary energy supply calculated based on this is shown in the following figure and
table (in the case of Scenario 3 among the five scenarios that are discussed in Chapter 12). Average
annual primary energy supply will grow at a moderate rate of 4.8% up to 2041. However, in addition
to significant growth in energy supply from coal and renewable energy, which is mainly used for
power generation, energy supply from oil slightly exceeds the average figure due to increasing demand
in the transport sector.
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040
[kto
e]
Residential Industry Commercial and public servises Transport Agriculture etc. Non-energy use
Projection
Power System Master Plan 2016
Final Report
1-29
Source: JICA Survey Team
Figure 1-12 Projection of Primary Energy Supply – Scenario 3
Table 1-7 Projection of Primary Energy Supply – Scenario 3
Source: JICA Survey Team
(2) Targets to Achieve
Based on the assumption of introducing energy-saving measures proposed in EECMP, GDP
intensity of total energy consumption will decrease by 23% in 2030 compared to 2014 (-20% if
calculated based on the same definition as EECMP) and will decrease by 25% in 2041 compared
to 2014 (-23% if calculated based on the same definition as EECMP).
To attain the above goal, the aim is to achieve reductions in energy consumption of 16% in 2030
and of 28% in 2041 compared to the BAU scenario.
Though energy saving in the transport sector was not taken into consideration in EECMP, it needs
to be noted that motorization will be accelerated significantly due to income growth. As a result,
energy consumption in this sector is expected to expand dramatically. To achieve the above goal,
the aim is to realize a reduction in energy consumption in the transportation sector of 33%
compared to the BAU scenario.
(3) Roadmap
Primary Energy Sources 2014 2041 Annual growth
rate (‘14-’41) ktoe (share) ktoe (share)
Natural gas 20,726 (56%) 50,149 (38%) 3.3% p.a.
Oil (Crude oil + refined
products) 6,263 (17%) 32,153 (25%) 6.2% p.a.
Coal 1,361 (4%) 26,273 (20%) 12.7% p.a.
Nuclear power - - 11,942 (9%) -
Hydro, solar, wind power and
others 36 (0%) 197 (0%) 6.5% p.a.
Biofuel and waste 8,449 (23%) 4,086 (3%) -2.7% p.a.
Power (import) 377 (1%) 6,027 (5%) 10.8% p.a.
Total 36,888 (100%) 130,827 (100%) 4.8% p.a.
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
2000 2005 2010 2015 2020 2025 2030 2035 2040
[kto
e]
Coal
Natural gas
Crude oil & Oil products
Projection
Biofuels and waste
Nuclear
Energy import
Power System Master Plan 2016
Final Report
1-30
To implement the Action Plans proposed in the EECMP.
Energy management system (targeted for demand in the large-scale industrial sector and the
commercial sector)
Performance labeling and minimum performance standards for electrical appliances (mainly
targeting energy demand in the residential sector)
Implementation of energy-saving construction standards (i.e. revised BNBC)
Low-interest loan programs for the installation of EEC equipment
In the transport sector, not only the improvement of fuel consumption efficiency for passenger
vehicles but also the improvement of traffic conditions in urban areas (within Dhaka city), which are
affected by chronic heavy traffic congestion, needs to be considered.
Policy measures for improvement of passenger vehicles’ combustion efficiency (e.g. eco car
program)
Improvement of road network development in urban areas (e.g. road widening, construction of
flyovers)
Development of railway network (e.g. MRT development within Dhaka city, Dhaka-Chittagong
railway network development)
1.6.4 Natural Gas (Domestic)
(1) Current Status and Issues
Natural resources, if used, will run out someday. This also applies to natural gas in Bangladesh.
Recoverable Proven reserve of natural gas in Bangladesh is 20.8 TCF. 12.1 TCF had been produced
and consumed by 2014, and therefore the remaining gas reserve will be 8.7 TCF, corresponding to a
Reserve Production Ratio of 9.5 years.
Source: Field-wise natural gas reserve estimates (Petrobangla, Nov. 2014),
and Draft Five Year Gas Supply Strategy 2015-2019) Figure 1-13 Gas Resource Balance
From an international economic point of view, the people of Bangladesh should recognize the true
value of domestic natural gas. They need to maximize its recovery and use it efficiently.
Power System Master Plan 2016
Final Report
1-31
In the area of oil and gas field development, significant technological advancement has been made
since 1990, and oil and gas recovery has improved significantly. Gas development in Bangladesh
needs to benefit from such advancement and to introduce some mechanism to take advantage of it.
Bangladesh has invited IOCs (International Oil Companies) for offshore development; however, it has
not been particularly interested in working with technologically advanced and financially sound IOCs
for onshore gas field development.
In order to maximize the recovery of gas from onshore fields and develop them more efficiently, it is
important to invite these IOCs for onshore gas development. Existing PSC should be amended to
attract such IOCs. International tenders to be carried out under the revised PSC, and partnerships
between domestic production companies (BAPEX, BGFCL, and SGFL) and IOCs should be
encouraged.
Natural gas will run out someday. The role of BAPEX should be changed to allow it to acquire energy
asset overseas in order to contribute to energy security in future, in a similar manner to that of ONGC
in India.
Gas Use Efficiency is one of the critical issues that needs to be introduced. “Cheap gas” will not be
available in the future and gas users need to enhance their efficiency to save the country’s indigenous
gas resources. Both the Urea Manufacturing Sector and Power Sector are major gas users and have a
significant impact on the overall gas consumption.
Urea is manufactured from natural gas. The world benchmark efficiency for Urea Manufacturing is
25mcf/ton, while average efficiency in Bangladesh was 44 mcf/ton as of 2014 FY, much higher than
that of the international benchmark. Provided that the international benchmark is used in the country,
130 mmscfd of gas would be saved in manufacturing 2,375,000 tons in 2014 and this figure would
translate into the power plant equivalent of 1000 MW.
Gas Consumption for the Power Sector (under BPDB) was 337.4 BCF in FY 2014 while Power
Generation Capacity was 8,340 MW and Generated Power was 42,200 GWh. From these figures, it is
assumed that current power generation efficiency is around 38%. Provided that efficiency can be
raised to 45%, which is considered the international benchmark for a gas based power plant, Energy
gas consumption will be reduced to 285 BCF, and the difference of 52 BCF can be said to be wasted.
This is equivalent to 1,300 MW in power plant annual operation.
In addition, it appears that power generation efficiency of Captive Power is not necessarily high
enough. Further investigation is necessary but low gas efficiency is a waste of resources and some
penalty should be imposed.
It is necessary to enhance the efficiency to the international level and a supporting legal framework
and regulations need to be put in place.
(2) Targets to Achieve
1) In order to attain efficient and economical development of domestic gas resources, introduction of
technologically advanced and financially sound IOCs is considered very important. Policy and
legal framework should be reviewed and changed. A new legal/regulation scheme should be
developed by 2019.
2) Acquisition of energy resources from overseas is necessary in order to maintain and/or increase the
national energy assets belonging to Bangladesh. (Mid/Long Term)
Power System Master Plan 2016
Final Report
1-32
3) Gas Use Efficiency to be enhanced to the international level with the use of the best commercially
available technology (Short/Mid Term).
(3) Roadmap
Amendment of PSC by 2019 to attract IOCs and encourage them to make investments in
Bangladesh
- International Tender based on new PSC
- Encourage forming of partnerships between IOCs and domestic gas production
companies, i.e., BAPEX、BGFCL (Bangladesh Gas Field Company Limited), SGFL
(Sylhet Gas Field Limited)
Role of BAPEX and associated legal framework to be changed by 2019
- Acquisition of Energy resources overseas by 2028
Legal framework to enhance gas efficiency to be in place by 2019
- Efficiency to be enhanced to the international level and discourage the use of
substandard facilities.
Gas Transmission and Distribution infrastructure to be modernized by 2019
- Transmission and Distribution gas Infrastructure should be electronically mapped and
able to introduce advanced monitoring and control systems to support the efficient use of
gas.
Power System Master Plan 2016
Final Report
1-33
1.6.5 Natural Gas (LNG Imports)
(1) Current Status and Issues
Gas Production from the current domestic gas fields in 2015 was 2,500 mmcfd and will reach a peak
production of 2,700 mmscfd in 2017, then start to decline. However, Gas demand in Bangladesh
forecasts a significant increase in future. The demand and supply gap must be filled by gas (LNG)
imports. The first LNG will be introduced in 2019 at the rate of 500 mmscfd, which corresponds to
17% of gas demand. This percentage is forecast to increase to 40% in 2023, 50% in 2028, and 70% in
2041.
Source: JICA Survey Team
Figure 1-14 Gas Supply Forecast 2016~2041
Under these circumstances, gas (LNG) import infrastructure, including an LNG Import and
re-gasification terminal, and connecting pipeline to the existing transmission and distribution
infrastructure, needs to be constructed urgently to fill the supply and demand gap.
Currently, introduction of LNG via FSRU, initiated by Petrobangla, is underway, and concurrently,
construction of a land LNG terminal by Power Cell is also under discussion. It is important to
understand the difference in these systems in view of economics, construction schedule and
operational risk, and it is advisable to prepare in the Master Plan the introduction of LNG to
Bangladesh.
The economics of a land LNG Terminal require large upfront investment for land acquisition and
0
1000
2000
3000
4000
5000
6000
7000
2009 2011 2013 2015 2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041
MM
SCFD
Comparison with PSMP2010 and PSMP2015 Gas Supply Scenario
LNG Import from India
Onshore LNG
FSRU
YTF Offshore
YTF Onshire
Existing Onshore (P1, PSMP2015 survey team projection)
PSMP 2010 Low Case (Existing+YTF Onshore+LNG)
PSMP 2010 Base Case (Existing+YTF Onshore+YTF Offshore+LNG)
PSMP 2010 High Case (Existing+YFT Onshore+YTF Offshore+LNG), esp Block 11 (Netrokona), Chhatak, Two off-shore bid rnds,
Actual Supply (2009-2015)
Power System Master Plan 2016
Final Report
1-34
infrastructure construction; however, gas handling capacity can be increased with the increase in
demand with minimum cost and schedule. Unit operation cost will be lower with the increase of
handling volume. It is also important to note that larger size tankers can be used for LNG delivery and
this will benefit the land LNG Terminal by reducing the unit transportation cost.
In view of the construction schedule, a Land LNG terminal requires 10 years including land
acquisition and the associated re-settlement plan. FSRU requires less than 3 years for commercial
operation.
It should be noted, however, that the current FSRU project in Bangladesh would require more than 60
times’ the LNG delivery using Ship to Ship Transfer, and would be vulnerable to weather conditions.
LNG Terminal Capacity will be expanding and transmission capacity of the pipeline infrastructure
from LNG terminals to the existing distribution infrastructure may need to be studied in advance.
Sending out gas pressure at the terminal should be studied to allow the use of higher pressure for gas
transportation, eliminating booster compressors downstream. Higher pressure in the system will
impact existing gas systems and well head separation performances. The LNG Master Plan should be
prepared to optimize and solve potential operational issues.
Fluidization of LNG supply has started already and the inflexible Take or Pay Contract has been an old
legacy in US and Europe. On the other hand, Asia has suffered from an expensive gas pricing system
known as the Asian Premium. It is important to tie up with other LNG importing Asian nations and
consider the introduction of spot procurement, and discuss product exchange (trading) among the LNG
importing nations. It is advisable to own a slightly larger storage capacity and loading facility for
re-export. Terms of sales/purchase agreements for LNG are not simple. It is important to set up a
strategy taking the above into consideration.
It should be noted that the current LNG price is about ten times higher than that for Bangladesh’s
domestically produced and marketed gas, where the current gas price for the electric power sector is
1.02 USD/Mcf and that for the fertilizer sector is 0.94 USD/Mcf. In the near future the dependence on
LNG over the total gas supply will sharply increase, and the dependency on LNG is projected to
exceed 70% of the total gas supply in the year 2041. Domestic Gas prices need to accommodate the
LNG price. Under these circumstances, existing fertilizer manufacturing facilities will not be able to
produce economically competitive product and the power price from old existing facilities will not be
able to compete economically with higher efficiency facilities. Similarly, more attention should be
given to gas leaks and system loss from gas transmission and distribution infrastructure to prevent
economic loss, i.e., “the lost opportunity cost”.
It is very important to review the integrity of the existing infrastructure, and swiftly introduce an
electronic mapping system with object orientated features as a first step.
(2) Targets to Achieve
1) Land LNG Terminal: Commence 500mmscfd of gas supply in 2027, expanded to 2,000mmscfd in
2041
2) FSRU Phase 1: Commence gas supply of 500 mmscfd in 2019, and additional 500 mmscfd as Phase
2 in 2023
(3) Roadmap
Master Plan for LNG Introduction to be prepared and completed by end of 2017, covering
economic analysis, construction schedule, operational risks, energy security, and international
cooperation (including joint LNG infrastructure operation)
Initial land-based LNG terminal commences operation in 2027, supplying 500mmscfd of natural
gas. The terminal is expanded to supply 3,000 mmscfd gas in 2041.
FSRU Phase 1 and connecting pipeline to be completed and start supplying 500 mmscfd of gas in
2019
Impact of LNG introduction on existing gas infrastructure and gas field facilities to be
investigated and reinforcement plan to be prepared by 2019
LNG Procurement Strategy to be prepared by 2018.
Power System Master Plan 2016
Final Report
1-35
1.6.6 Coal
In this section, the infrastructure for import coal and domestic coal development is considered.
(1) Current Situation and Issues
(a) Infrastructure for import coal
1) As for the quantity of import coal in 2041, 60 million tons is expected.
2) Because the infrastructure for import coal is closely related to handling cost, it is left to the
consideration of each power station plan at present. There are some options such as Coal Center +
Barge Transport, Coal Center + Belt Conveyor Transport and Offshore Unloader + Barge Transport
etc.
3) On the other hand, a Coal Center will be a major solution playing a key role in the future because a
steady coal supply is the most critical issue for a power station.
Source: JICA Survey Team
Figure 1-15 Forecast of Coal Demand and Supply
(b) Domestic coal development
1) Coal will be the cheapest primary energy now and in the future and coal-fired power stations will
increase in Bangladesh.
2) On the other hand, the coal-fired power stations in Southern Asia surrounding Bangladesh are
increasing rapidly. As a result, the supply, the quality and the price of import coal will become very
unstable in the future.
3) From the situation mentioned above, domestic coal development will become more important than
at present in future, because high quality coal is abundant in Bangladesh.
4) The understanding of inhabitants is necessary for domestic coal development, and the government
needs to perform awareness activities in order to gain the understanding of the nation.
5) Despite the high price paid for the coal mined by the Chinese contractor, the technology transfer
from the contractor to Bangladeshi engineers has been limited. If this system of the mining
continues, the increase in coal production with the development of new underground coal mines will
not lead to the reduction in the production cost and, therefore, the stable supply of domestically
produced coal will not be realized.
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040
Coal Supply
Domestic Production Import Total Supply
(1,000t/y)
Power System Master Plan 2016
Final Report
1-36
(2) Targets to Achieve
(a) Infrastructure for import coal
1) Enforcement of F/S for the import coal infrastructure
2) Construction based on the F/S
(b) Domestic coal development
1) Technology acquisition in coal mines for Bangladesh
2) Carrying out pilot operation of open cut mining technology in the Barapukuria coal mine.
3) Development permission for Digipara coal mine and Karaspir coal mine
4) Approval of small scale open cut mining at Phulbari after the pilot operation at Barapukuria coal
mine
(3) Roadmap
(a) Infrastructure of import coal
1) Implementation of import coal infrastructure in the F/S.
- The F/S for the CTT (Coal Transshipment Terminal) planned in the Matarbari area has already
been completed (Source: Preparatory Survey for the Construction and Operation of Imported
Coal Transshipment Terminal Project in Matarbari Area in People's Republic of Bangladesh as a
PPP infrastructure project).
- In this plan, phased development for CTT was recommended to provide sufficient flexibility, i.e.,
to expand the CTT when the power generation program development and realistic commission
operation date (COD) become certain.
- The first phase of the CTT will commence operation in 2025 (planned amount of coal: 10.4
million t/year); the object of the second phase will include those power stations that commence
operation by 2029 (amount of coal: 25.6 million t/year) and use the CTT.
- For the future, with an increase in the development of new coal-thermal power plants there is a
need to implement the F/S for the infrastructure and plan for efficient coal transportation.
- It will be important to conduct a F/S on the possibilities of the construction of CTT in near future
and offshore loading and unloading including an analysis of the actual record of the offshore
loading and unloading in the Bay of Bengal.
2) Based on the F/S Construction
- For CTT (Coal Transshipment Terminal), efficient coal supply operation while ensuring long-term
stability is desired. When planning in Bangladesh, it is important to take into account the natural
characteristics such as the broad expanses of sand, cyclones and high rainfall, and the protection
of precious animals and plants.
- When importing coal over a long period of time, facility planning that can respond to changes in
the type of coal is desirable as, depending on the coal mine reserves, future coal mines and
countries may change.
- The promotion of mechanization and securing of stable supply for offshore loading and unloading
by floating crane; the implementation of early construction of the CTT.
(b) Domestic coal development
1) Because it will take about 10 years to develop a new coal mine and start production, production will
begin in 2025 at the earliest even if it is prepared now. Therefore, it is necessary to carry out the
required preparation from a position of being able to do this now due to as much utilization of the
excellent domestic resources as possible.
Power System Master Plan 2016
Final Report
1-37
2) Unfortunately, the production of Barapukuria coal mines in 2015 was 0.68 million tons and did not
reach 1 million tons as planned, but 1.1 million tons from U/G in 2020 and a total of 3.2 million
tons (1.2 million tons from U/G and 2 million tons from O/C) from 2030 to 2041 are assumed.
3) In addition, it is assumed that total production will be 1.1 million tons by 2020, 5.7 million tons by
2030 and 11.2 million tons by 2041, considering the production scenario in which Dighipara and
Kalaspir coalfields have high development possibility, including the Phulbari coalfield.
4) The acquisition of coal mine technology by Bangladesh
It should be the case that by 2020 systems have been established through which Bangladesh can
learn in technologies such as mining, ventilation and mine safety technology for stable production
in the Barapukuria coal mine, and that Bangladesh can play a key role in developing a new coal
mine.
It is considered necessary to establish an institution for training mining engineers and a third-party
organization for technology transfer, e.g. a mining college, in order to enable Bangladeshi workers
to implement and evaluate the outputs of the programs and extend of the use of transferred
technologies to other mines later in the medium- to long-term.
Power System Master Plan 2016
Final Report
1-38
1.6.7 Oil and LPG
(1) Current Status and Issues
Bangladesh’s current oil annual demand is around 5 million tons, and the self-sufficiency rate is only
5%. However, Bangladesh expects continuous economic development, and the industry sector and
transport sector demand will lead drastic oil demand growth: 6 times higher in 2041 than in 2016
(average growth rate 7.4% p.a.), even under the “Energy Efficient and Conservation Scenario”.
Bangladesh has several plans to extend or newly develop oil refineries; however, if the oil demand
grows as projected, oil imports will be mandatory to meet the demand and keep increasing.
Source: JICA “Southern Chittagong” Survey Team and PSMP2016 Survey Team
Figure 1-16 Oil Demand and Supply Balance, 2014 to 2041
Furthermore, Bangladesh’s LPG demand is only 2% of total oil demand, and less than 0.01% of the
total energy demand. However, LPG consumption is expected to grow drastically as an alternative for
households’ cooking fuel (currently domestic natural gas) and transportation fuel.
The current price of LPG is two to three times higher than that of the pipelined gas, and may not be
affordable for average households in Bangladesh. While Bangladesh rural households spend 4-7 % of
their monthly income on traditional solid biomass, LPG at the market price would be 25%. If the
government seriously intends to pursue universal access to modern energy, LPG may not be a good
solution or may need some policy countermeasures. Subsidy of LPG may work to some degree to
increase affordability; however, without sound consideration of the side effects and an exit strategy,
LPG subsidy would create huge pressure on the national coffers, given the projected future demand.
In terms of affordability, biogas could be an alternative to promote universal access to modern energy,
especially in rural areas.
(2) Targets to Achieve
The government should define a strategic position for oil products in its holistic energy policy,
and economic development policy.
The government should develop an exit strategy for oil product subsidy.
(3) Roadmap
A clear strategic positioning for oil products in the energy policy by 2017.
Exit strategy for oil product subsidy by 2017.
-5,000
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040
kto
n
ERL Existing Capacity ERL Capacity Expansion KPC Project
Oil Import Oil Demand
Power System Master Plan 2016
Final Report
1-39
1.6.8 Power Development Plan
(1) Current Status and Issues
As mentioned in Chapter PSMP2010 review, five-year power demand by PSMP2010 and its actual
performance had remained in about 8,000MW which is about 80% level of the plan, because it was
delayed power plant construction which had been planned and necessary infrastructure such as port
which is essential to stable fuel imports has not been established.
Therefore, it is considered necessary for the Energy Division and the Power Division to develop an
organizational structure and operating system more integrated than before. They must also make
concerted efforts to formulate a joint infrastructure development plan, to raise funds in the
public-private partnership and to develop infrastructure systematically in order to achieve a stable
energy supply, a source of future economic development.
(2) Targets to Achieve
The power demand forecast is an important factor in the formulation of a future power development
plan (PDP). However, the accuracy of the actual demand forecast is at such a level that it is difficult to
forecast even the demand for the next day accurately and, in fact, it is almost impossible to accurately
forecast the power demand for several years or longer. Because of this unreliability of the demand
forecast, it is not advisable to formulate a PDP optimal for a certain condition in future and promote
actual power development in accordance with this PDP. In other words, it is very important in
formulating a future PDP to consider all the elements, including the demand variables in the
estimation, conduct a sensitivity analysis while changing these variables within their respective
reasonable ranges for a certain system, and analyze the relationship between power generating
facilities in the system and the economic, environmental and energy security values of the system.
Therefore, a long-term vision for the power source composition created by making a rough estimation
of the future demand based on a scenario of the macro economic growth, simulating a demand/supply
operation somewhat simply using the estimated demand scenario as a variable and formulating the
optimal PDP is presented as a recommendation. The planning flow is as follows.
Power System Master Plan 2016
Final Report
1-40
Source: JICA Survey Team
Figure 1-17 Power Development Planning Flow
1) Peak Power Demand Projection
As for the methodology of peak demand projection for PSMP2016, this study adopted the “GDP
elasticity method”, which is an easier approach and thus easy for technology transfer to local
counterpart agencies who are expected to take over the work in a rolling plan. However, it has to be
noted that this methodology disregards various factors that may also affect the power demand; hence,
the results may differ significantly from other methodologies. This study therefore also tried the peak
demand projection based on the “Sectorial analysis method” to confirm the appropriateness of the
“GDP elasticity method”.
F-4 Long-term Development Plan (Candidate Plan: 2026-41)Sensitive analysis by changing Gas and Coal Power ratio (case1~5)
Supply and Demand Simulation
STEP 1 :Optimization of Emission PowerSTEP 2 :Maximization of Zero-emission Power
A Power Demand Forecasting
A-2 Energy-GDP Elasticity Method
Validation of two methods
A-4 Peak Power Demand Forecasting
A-1 Estimation of the maximum power that includes potential demands (Peak@2016)
Demand Side
A-3 Macro Demand Forecast Method
E-1 Estimation of daily load curve
B PSMP2010 Review
Supply Side (Power)
Daily Load Curve(Peak, Weekday & Holiday)
Supply and Demand Simulation
G Infrastructure and Port Development Plan(JICA’s southern Chittagong MP research)
B-1 Power Development Plan Review
Gas Power Development Plan
Coal Power Development Plan
F-1 Existing Facilities CapacityF-2 Decommissioning Plan
Required Capacity(Peak and Required Reserved Margin)
B-2 Primary Energy Supply Review (Gas & Coal)
G-1 Coal Terminal Development Plan
G-1 LNG Terminal Development Plan
Supply Side (Energy)
Economy EnvironmentEnergy Security
H Quantitative Evaluation of 3E
C Supply Reliability
F Power Development Plan
Existing Facilities Information(Output, Retirement, Efficiency, Property)
New Facilities Information(Output, Retirement, Efficiency, Property, COD)Accumulated Power Development Scenario Fixed Condition
Variable Condition
E Property of Load Factor
D Fuel Price Scenario
D-1 Fuel Price Scenario (Oil, Gas & Coal)
Fuel Price Scenario (Oil, Gas & Coal)
Gas
Oil
Coal
F-3 Government Committed Plan (Committed Plan: 2015-25)
C-2 Supply Reliability Study (Adequate Reserve Margin)
Fuel Consumption
Generation Cost[USD/kWh]
CO2 Emission Cost[USD/kWh]
Study of Energy Security
Possible Supply Loss Cost [USD/kWh]
Risk of sudden shortage in energy supply
Risk of GDP Loss
Minimum 3ECost Scenario [USD/kWh]
VISION2041Desirable Future Direction of Energy Mix
Energy Mix
CO2 Price
Validation
Dem
and
Supply
Renewable Energy
NuclearPowerImport
Hydro
Maximization of Zero-emission
Power
Optimization of Emission Power Fuel-wise CO2
Emission Fuel-wise MW, GWh
Power System Master Plan 2016
Final Report
1-41
(a) Estimation of the maximum power that includes potential demands
Because of the particular situation in Bangladesh whereby rolling blackouts have been used as a
measure to circumvent power shortages at the peak hours, the recorded maximum power consumption
does not include such potential power demand. Therefore, an accurate forecast of the maximum
demand including the potential demand requires a theoretical estimation of load curves from the daily
operational data with particular attention on the characteristics of the seasonal changes in the daily
load curve and the frequency and durations of rolling blackouts.
Because rolling blackouts have been relatively rare on weekends and holidays in the winter (between
November and January), a daily load curve gives an actual peak load (at the hours of the peak power
consumption for lighting) that is quite accurate. A daily load curve in the summer gives estimates of
the base and intermediate loads close to the recorded values.
Therefore, a composite daily load curve representing the peak power demand was created from the
daily load curve in the summer with part of the peak hours replaced by the same part of the daily load
curve in the winter as shown in the figure below. The peak power demand in FY 2014, which was used
as the baseline for the peak demand forecast, was set at 8,039 MW by adding the base and
intermediate load in the summer (5,487 MW and 1,043 MW, respectively) and the peak load in the
winter (1,811 MW) recorded in FY 2015. The peak power demand in FY 2016 was estimated at 8,921
MW in the same way and this value was used as the reference value in the peak power demand
forecast.
Source:JICA Survey Team
Figure 1-18 Estimated Composite Daily Load Curve in the Summer in Bangladesh
(c) Verification of GDP elasticity method by using Sectorial analysis method
In comparing the power demand projection between the “GDP elasticity method” and the “Sectorial
analysis method”, this study concluded that the results are almost identical, though the latter exceeded
the former by about 5%. Therefore, this study adopted a peak demand projection using the "GDP
elasticity method”, which is an easier approach and thus easy for technology transfer to local
counterpart agencies who are expected to take over the work in a rolling plan.
Power System Master Plan 2016
Final Report
1-42
Source: JICA Survey Team
Figure 1-19 Comparision of peak power demand in both models
(d) Integration of Peak Power Demand Projection and Energy Supply-Demand Projection
Following the projection of peak power demand as formulated above, this study calculated the
available electricity supply from the power grid by multiplying the annual load factor, and then
compared this with the projection of total electricity consumption that was discussed in the previous
section in the projection of primary energy supply and demand.
2) Power DevelopmentPlan
Short-term and medium-term power development plans are to be formulated after verifying the
appropriateness of matters with a little short-term uncertainty (the state and retirement plans of the
existing facilities and the plans approved by the Government) in the formulation of a long-term power
development plan. The basic CODs of the gas and coal power plants in the long-term and candidate
plans are to be determined in conformity with the port and fuel depot infrastructure development plan
to be formulated separately in the “Data Collection Survey on Integrated Development for Southern
Chittagong Region (Southern Chittagong MP Survey).”
The optimum power source composition is to be determined in the preparation of the future vision of
the power source composition by conducting a quantitative evaluation of the economic, environmental
and energy security (3E) values of scenarios with different composition ratios for the gas and coal
power generation. Different composition ratios for the gas and coal power generation within ranges
that are consistent with the infrastructure development plan in the Southern Chittagong MP Survey are
to be used in the scenarios, particularly for the highly unpredictable periods for the long-term and
candidate plans.
Power System Master Plan 2016
Final Report
1-43
Source:JICA Survey Team
Figure 1-20 Relationship between the Time Scale and the Change in PDP
(a) Existing plants
The installed capacity of existing plants was determined as described below after discussions with the
organizations concerned in Bangladesh. The installed capacity of existing plants is 10,895MW as of
2015.
(b) Retirement Plan
The lists of the existing power generation facilities above show their outputs, CODs, retirement years
and operation periods. Analysis of these data has revealed that the average operation period for these
power plants is approximately 20 years. It is difficult to improve the efficiency of the existing
inefficient plants significantly because of the large cost required for such improvements. For these
reasons, it has been concluded that the retirement plans prepared by the government are appropriate.
The adoption of a strategy aiming at improving the efficiency of the entire power supply network by
retiring the existing inefficient power plants gradually and replacing them with new, efficient facilities
is considered essential for realizing the maximum use of the limited resources.
(c) Evaluation of the Plans Approved by the Government (Committed Plan)
Power plants with a total output capacity of approximately 14,000 MW are to be constructed in the
next ten years. The current status of each thermal power development plan was confirmed based on the
discussion with related companies, such as BPDB, BIFPCL, CPGCBL, NWPGCL, Orion Group, etc.
(d) Consideration of Consistency with the Southern Chittagong MP Survey
Guarantee of the long-term stability of the fuel supply is a very important factor in the formulation of a
power development plan. The existence of a port infrastructure required for the importing of fuels
including gas and coal during operation has to be a precondition for the decision on the CODs of new
power plants, in particular. Therefore, the infrastructure and port development plan formulated with
the consent of the Government of Bangladesh in the Southern Chittagong MP Survey, implemented by
JICA, was used as reference in this analysis and the CODs of the power supply facilities were set in a
way consistent with the plan.
Power System Master Plan 2016
Final Report
1-44
(e) Evaluationb of the Ultra-long term Power Development Plan (Candidate Plan)
A study on increasing the power sources by changing the ratios of the gas and coal power generation
in accordance with the progress in the infrastructure and port development planned in JICA’s Southern
Chittagong MP Survey is to be conducted for the formulation of the candidate plan. In this section, a
scenario that sets the composition ratios of the gas and coal power generation in 2041 at 35% is to be
used as the basic power development plan.
(f) Summary of Power Development Plan
The figure below shows the power supply plan formulated by adding the capacity of the existing
plants estimated with the retirement plan in the plan for the existing facilities taken into consideration
(existing capacity), the capacity of the plants mentioned in the Committed Plan to be constructed by
2025, the capacity of the plants to be constructed later in the Candidate Plan that is subject to changes
and the capacity required to ensure supply reliability during peak demand.
PowerDevelopment Plan (Base case) Power Development Plan (Base case)
Gas Coal
Oil Hydro
0
10000
20000
30000
40000
50000
60000
2015 2020 2025 2030 2035 2040
(Source: JICA PSMP2015 Team Estimate)
Power Development Plan (MW) @ Scenario3 : Coal 35% Gas 35%
Oil Hydropower
Gas Coal
Power Import Nuclear
Power Demand Required Supply
0
5,000
10,000
15,000
20,000
2015 2020 2025 2030 2035 2040
Gas-based Power Plants (MW)
New Gas-based Power Plants (Candidate)
New Gas-based Power Plants (Committed)
Existing Gas-based Power Plants
0
5,000
10,000
15,000
20,000
2015 2020 2025 2030 2035 2040
Coal-based Power Plants (MW)
Matarbari/Maheshkhali
Rampal/Payra
Other Areas
Barapukria(Domestic Coal)
0
5,000
10,000
15,000
20,000
2015 2020 2025 2030 2035 2040
Oil-based Power Plants (MW)
New Power Plants
Existing Power Plants
0
2,000
4,000
6,000
8,000
10,000
2015 2020 2025 2030 2035 2040
(Source: JICA PSMP2015 Team)
Hydro Power (MW)
New Kaptai PSPP
Existing Kaptai
Power System Master Plan 2016
Final Report
1-45
Power Import Nuclear
Source:JICA Survey Team
Figure 1-21 Annual Trend of Each Power Plants(MW)
3) Simulation of Supply/Demand Operation
(a) Preconditions for the Estimation of the Economic and Environmental Values
(a-1) Daily load curve
The following estimates the daily load curve in Bangladesh during the 2015-2041 period. The
performance records of the daily load curve in Bangladesh in 2015 are represented by a curve having a
power demand peak in the evening, as illustrated below. In the meantime, by 2041, the economic
growth rate in Bangladesh is estimated to reach the daily load curve of advanced countries, where the
peak is found in the daytime and evening, if the growth of the electrification rate is taken into account.
Source: JICA Survey Team
Figure 1-22 Transition of estimated power demand during 2015-2041 (Unit: MW)
(a-2) Power supply reliability
An analysis was conducted on the relationship between the reliability of power supply and the
required capacity based on the power demand forecast (Base Case) and PDP. The relationship between
the reserve margin and LOLE changes from year to year. If the value of LOLE is set at the standard
value for developing countries of 1.0 to 1.5%, the reserve margin theoretically appropriate for the
current state is approximately 25%. If international linkage and nuclear power generation are to be
introduced ca. 2025, the reliability of the power supply shall have to be improved, as mentioned in
detail in the chapter on power quality. A margin of between 8% and 15% will be required in order to
achieve the target of LOLE = 0.3%, which is acknowledged to be a very challenging target. Therefore,
it was assumed that the reserve margin shall be reduced from 25% in 2020 to the target of 10% by
2030 and shall be maintained at this level thereafter.
0
2000
4000
6000
8000
10000
2015 2020 2025 2030 2035 2040
(Source: JICA PSMP2015 Team)
Power Import from Neighboring Countries (MW)
From Bhutan (Rawta)
From Meghalaya (Bibiyana)
From Myanmar(Cox's Bazar)
From AP/Bhutan(Barapukuria Case3)
From AP/Bhutan (Barapukuria Case2)
From Tripura (Comilla)
From WB (Bheramara HVDC)
0
2,000
4,000
6,000
8,000
10,000
2015 2020 2025 2030 2035 2040
(Source: BPDB, JICA PSMP2015 Team Estimate)
Nuclear Power (MW)
South West Nuc 6th Unit
South West Nuc 5th Unit
Roopoor 4th Unit
Roopoor 3rd Unit
Roopoor 2nd Unit
Roopoor 1st Unit
Power System Master Plan 2016
Final Report
1-46
Source:JICA Survey Team
Figure 1-23 Reserve Margin
(a-3) Fuel Price Scenarios
The differences between the prices of fuels in Bangladesh, including the price of domestically
produced gas in particular, and the prices in the international market are large and fuel in Bangladesh
is provided at prices significantly lower than those in the international market. As the future economic
growth will inevitably make it impossible to satisfy the power demand with domestically produced
resources, the proportion of imported fuel in the fuel supply is expected to increase rapidly and the
prices of fuel are expected to increase to close to those in the international market.
In the discussion with the Government of Bangladesh and the IEA, the international organization on
energy, it was decided to use the IEA Scenario for the price of crude oil that projected the price on the
basis of a very long-term projection of the supply/demand balance in this analysis.
However, there is a difference between the market price of crude oil in the IEA scenario and the actual
price in the market in Bangladesh at present. Therefore, an original scenario for this analysis (F5) has
been formulated as the basic scenario for the price of crude oil. In this scenario, the reference price is
set at the average price of crude oil in the domestic market in 2015 and the price is projected to follow
the New Policies Scenario of the IEA (F1) from 2020 onward.
0%
5%
10%
15%
20%
25%
30%
2015 2020 2025 2030 2035 2040
(Source: JProposed by ICA PSMP2015 Team)
Reserve Margin Condition (%)
Power System Master Plan 2016
Final Report
1-47
Source: JICA Survey Team
Figure 1-24 IEACrude Oil Scenario
(b) General description of Supply/Demand Operation Simulation
The estimation with the least cost method was used in the quantitative evaluation of the optimum
power development plan. A good balance of the economic, environmental and energy security values
based on the primary energy supply/demand balance, PDP, power system analysis and power system
operation was taken into account in the evaluation. The results of the evaluation were reflected in PDP.
PDPAT II and WASP IV were used as the tools for the simulation of supply/demand operation in the
formulation of PDP, which was implemented in accordance with the flowchart shown in the figure
below.
The annual fuel cost for a certain year was estimated by finding the most cost-effective operation of
the given power generation facilities to satisfy a given demand of the year concerned in the simulation
of the supply/demand operation. At the same time, a comparison of the fuel cost was conducted, the
annual expenses were estimated as a total of the fixed cost, fuel cost and inter-connected cost, the least
cost operation, the most cost-effective operation of the total power system, was identified in the
simulation and the economic value of the power development plan was evaluated. The optimum
development plan was selected by comparing the estimated annual expenses with those of other
development plans.
0
20
40
60
80
100
120
140
160
2010 2015 2020 2025 2030 2035 2040 2045
USD
per
bar
rel
IEA Crude Oil Scenario
F1 New Policies Scenario (Base Case) F2 Current Policies Scenario (High Case)
F3 450 Scenario (Low Case) F4 Low Oil Price Scenario
F5 PSMP2016 Revised Scenario (F1)
Power System Master Plan 2016
Final Report
1-48
Source: JICA Survey Team
Figure 1-25 Simulation schem of the supply/demand operation
The energy mix should be examined based on the fixed factor and the variable factor as shown in the
figure below. For the fixed factor, nuclear power plants, power imports, hydropower plants, existing
coal-fired power plants, existing oil-fired power plants, and candidate coal, gas and oil-fired plants
that the plan is already in progress should be taken into consideration. For the variable factor,
assuming that 70% of the total energy source that is considered appropriate for the power generation
plan will be covered by coal and gas, in order to study the optimum energy source composition, five
scenarios of energy mix with the share of coal and gas in the energy mix as of 2041 changed from P1
to P5 in the figure below are studied.
In this case, the share of oil and other fuels in the energy mix should not change in each scenario. The
energy mix by fuel type from 2015 to 2041 in each scenario is as shown in the following figure.
Power System Master Plan 2016
Final Report
1-49
Source: JICA Survey Team
Figure 1-26 Generation pattern in 2041
After determining the optimum share of gas and coal in the energy mix, for Step 2, changing the share
of fuels other than thermal power and nuclear power in the energy mix should be considered.
Source: JICA Survey Team
Figure 1-27 Image for demand and supply simulation
Assumptions:
●Fixed Factor: Nuclear, Dom Coal, Dom Gas, Oil, Hydro, and Power Import
●Variable Factor: Imp Coal,
Imp Gas, and Renewable Energy
Nuclear
Domestic
Coal
OilDomestic
Gas
Gas
RE Coal
Variable Factors to be scrutinized for optimum PDP
Hydro
Import
Coal/Gas
RE
STEP 2-1:STEP 1:
(70%) (60%)
Import
Coal/Gas
RE
(50%)
STEP 2-2:
PI PI PI
(15%)
Green Energy
(15%)
Green Energy
(25%)
Import
Coal/Gas
Green Energy
(35%)
(15%) (15%)
Power System Master Plan 2016
Final Report
1-50
Source: JICA Survey Team
Figure 1-28 Annual Trend of Energy Mix in Different Scenarios
(c) Estimation of Economic Value
The following figure shows the trends of five scenarios for generation cost. As the use of coal spreads
in stages, the fuel expense will be slashed, helping curve increases in power generation costs. Thus,
the power generation cost is estimated at 9 to 12 US cents/kWh for 2040. In addition, comparison of
the power generation cost between the five scenarios for energy source ratio (P1 to P5) shows that the
power generation cost becomes higher as the ratio of coal to all the energy sources becomes smaller.
Source: JICA Survey Team
Figure 1-29 Power generation cost under each scenario and Ratio of coal (US cent/kWh)
Power System Master Plan 2016
Final Report
1-51
(d) Estimation of Environmental Value
CO2 emissions in different scenarios are shown in the figure below. The CO2 emissions in 2041 are
the highest (0.82 CO2 kg-C/kWh) in Scenario P1, with a high share of coal in the energy mix, and the
lowest (0.55 CO2 kg-C/kWh) in Scenario P5, with a low share of coal in the energy mix.
Source: JICASurevy Team
Figure 1-30 Scenario-Wise CO2 Emissions(CO2 kg-C/kWh)
As discussed in Chapter 5, which analyzes the environmental policy, climate change is one of the most
critical issues among the environmental impacts of power supply. Bangladesh also submitted INDC to
UNFCCC in 2015 and projected greenhouse gas emission reductions in the power sector by 2030.
Thus, the environmental value of each power development scenario should be evaluated focusing on
CO2 emissions. This study employed CO2 cost per unit of electricity generated to evaluate the
environmental value of each power development scenario. CO2 cost is calculated by multiplying CO2
emissions and CO2 price. In this study, 125 USD/tCO2 is used for the CO2 price, referring to the
assumption in the 450 scenario of IEA World Energy Outlook 2015.
(e) Estimation of Energy Security Value
Energy security covers many concepts and there are no common approaches to evaluate it unlike
previous two values. Here, we focused on risk of sudden shortage in energy supply quantity, which
would directly damage Bangladesh economic activities. The difference ratio of coal and gas among
power development scenarios brings different dependence on supplier countries and delivery routes,
and thus different shortage risks. This energy shortage risk can be quantified in monetary value as
potential loss value of economic production.
Proposed index is calculated using the formula below.
Energy Security Index [USD / kWh]
= GDP [USD] x Possible non-delivery rate [%] / Primary Energy Supply [toe] / Generation Efficiency [kWh/toe]
To calculate “possible non-delivery rate”, we modeled physical energy delivery routes to Bangladesh
and assumed the blockage probability of each point on the routes. The following figure illustrates the
model concept. Among many kinds of risk on the energy delivery routes, we focused on three risks:
export suspension risk, blockage risk on land route, and blockage risk on sea route. We ignored the
risks to deliver domestic energy.
Power System Master Plan 2016
Final Report
1-52
Source: JICA Survey Team
Figure 1-31 Physical Energy Delivery Routes and Risks
With the model, energy delivery rate to Bangladesh can be expressed in the form of probability density
function as shown in Figure 1-31, considering many different combinations of risk realization. This
curve itself reflects the risk situation of the physical energy delivery of the country. Using the
parameter of the expectation () and the standard deviation () of this distribution curve, we can
calculate a value of () which shows minimum delivery rate with 84% confident interval
mathematically. In the other word, 1 () shows maximum non-delivery rate. This number is that
we call “Possible non-delivery rate” here.
Source: JICA Survey Team
Figure 1-32 An Example of Probability Density of Energy Delivery
3) 3E Evaluation Results in Bangladesh
Power supply is closely related with economic activities and environmental issues. For a certain
pattern of energy supply to be sustainable, it has to satisfy the conditions called “3E,” consisting of the
economic value, environmental value and energy security value. The Basic Energy Plan of Japan states
that the energy policy of Japan shall satisfy the “3E” conditions.
A quantitative evaluation of the 3E values in 2041 of each of the power development scenarios
proposed in the previous section conducted for the selection of the most recommendable scenario is
described in this chapter.
Based on the aforementioned methodologies, five scenarios of power development were evaluated
By sea
By land
(railway, truck, pipeline )
Bangladesh
Demand
By land
Supplier country
Physical Energy Flow and Risks
(1)Energy
imported by
land
(2)Energy
imported by sea
(3)Domestic energy
Risk on land route
Risk on sea route
Risk
Risk on supply side
Evaluation using supplier
countries’ risk
Evaluation the risks on
the major chokepoints
on sea route
Evaluation with
assumption that risk
are proportional to
distance
Expectation()
Standard
Deviation
()
100%
Probability
0
Power System Master Plan 2016
Final Report
1-53
using 3E indicators, as shown in the following table. All indicators are expressed in monetary values
and they indicate better performance when the number is small. The sum of these three indicators is
the total score for the 3E evaluation.
Table 1-8 3E Evaluation Results of Each Power Development Scenario
Composition
(MW base) Economy
[US cent/kWh] Environment [US cent/kWh]
Energy Security [US cent/kWh]
Total [US cent/kWh]
Scenario 1 Gas 15%, Coal 55% 11.2 6.6 9.8 27.6
Scenario 2 Gas 25%, Coal 45% 11.6 6.2 8.9 26.7
Scenario 3 Gas 35%, Coal 35% 12.1 5.7 8.2 26.0
Scenario 4 Gas 45%, Coal 25% 12.9 5.0 9.0 26.9
Scenario 5 Gas 55%, Coal 15% 13.7 4.4 10.2 28.2
Source: JICA Survey Team
Source: JICA Survey Team Source: JICA Survey Team
Figure 1-33 3E Evaluation Results (Each Value) Figure 1-34 3E Evaluation Results
(Total)
(g) 3E Evaluation including the Possibility of the Use of Renewable Energy
As mentioned above, after determining the optimum share of gas and coal in the enrgy mix, as Step2,
changing the share of renewable energy in the energy mix should be considered. In this study, RE10
scenario increasing 10% Renewable energy and RE20 scenario increasing 20% reneawable energy is
considered.
Figs. 1-33 and -34 show the 3E values of the scenarios estimated with the “3E” Evaluation Indicator
Estimation Method mentioned above. The introduction of power generation with renewable energy in
RE Scenarios 10 and 20 will lead to a significant increase in the unit power generation cost because of
the increase in the cost for its introduction.
Power System Master Plan 2016
Final Report
1-54
Table 1-9 3E Evaluation Results of Each Power Development Scenario
Composition
(MW base) Economy
[US cent/kWh] Environment [US cent/kWh]
Energy
Security [US cent/kWh]
Total [US cent/kWh]
Composition
(MW base)
Scenario 3 Gas 35%, Coal 35% 12.1 5.7 8.2 26.0
Scenario 3
RE10 Gas 35%, Coal 25% 16.0 5.0 6.9 27.9
Scenario 3
RE20 Gas 25%, Coal 25% 19.2 4.7 6.2 30.2
Source: JICA Survey Team
Source: JICA Survey Team Figure 1-35 3E Evaluation Results (Each Value)
Source: JICA Survey Team Figure 1-36 3E Evaluation Results (Total)
Because the power generation cost is an economic indicator that has a great impact on the 3E
evaluation, a sensitivity analysis was conducted with different costs for the introduction of renewable
energy power generation. Fig. 1-36 shows the result of the comparison of cases in which the
introduction cost is assumed to have been reduced by 50% and 75% with the case of introduction at
the current price.
The 3E evaluation values of the scenarios with the introduction of renewable energy power generation
are lower than those of the scenario without the introduction when the cost of the introduction has
been reduced by at least 5%. Therefore, it is advisable to decide the proportion of the power supply
generated with renewable energy in the total supply with the reduction in the cost of the introduction
to be realized by technical innovation taken into account.
Power System Master Plan 2016
Final Report
1-55
Source: JICA Survey Team
Figure 1-37 3E Evaluation Results (Total)
(3) Roadmap
i) Short term (up to 2020)
Capacity building for MP revision
Collaboration between organizations for power and energy master plan
Periodic rolling revisions for milestone mater plan
Comprehensive statistical work function
Introduction of KPI management
Improvement in the investment climate
Improvement of PPA
Reinforcing tax exemption for FDI
Prompt procedure
Financial credit approval by international organization
Eliminating rolling blackouts
Reform of O&M of power plants and revision of electricity charges
ii) Short- to medium-term (up to 2025)
Breaking away from the dependence on costly petroleum and rental power generation
Promotion of PPP investment in power generation projects
Reform of O&M of power plants and revision of electricity rates
iii) Medium- to very long-term (up to 2041)
Establishment of reliable large-scale base power sources
Promotion of PPP investment in power generation projects
Reform of O&M of power plants and revision of electricity rates
Realization of the best mix of power sources with high 3E values
Regarding acchieve to best energy mix, in order to maximize the 3E value (the total of the economic,
environmental and energy security values) of the power source composition of the energy mix, a
portfolio consisting of well-balanced proportions of gas, coal and other power sources shall be realized.
This shall be done by halving the proportion of gas power generation to depart from the current heavy
reliance on gas, and with the systematic expansion of relatively inexpensive large-scale coal power
generation and international connection with the neighboring countries as an exit strategy from the
reliance on expensive oil-based rental power.
In addition, the investment cost for the use of renewable energy, which is larger than that for the use of
conventional energy sources, is expected to reduce in future with technological advancements and the
Power System Master Plan 2016
Final Report
1-56
extension of its use in society. When this condition has been met, a shift to the active use of renewable
energy and a reduction in the consumption of fossil fuel shall have to be realized, following the global
trend, with the aim of increasing the use of zero-emission power sources.
Source: JICA Survey Team
Figure 1-38 Best mix including expansion of renewable enegy
25%
35%
60%
25%
35%
5%
35%
15%
5%
10%
10%
5%
5%
30%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
2041(P3/RE20)
2041 (P3)
2015
Gas Coal PI/RE Nuc Oil/Hydro/Others
Power System Master Plan 2016
Final Report
1-57
1.6.9 Hydropower development
(1) Current status and issues
1) Current Situation of hydropower development
Bangladesh’s climate is categorized as a subtropical zone monsoonal climate, and its characteristic is
abundant rainfall. As for the topography of Bangladesh, most of the national land is spread over the
delta area along the Bay of Bengal on the Indian subcontinent. Most areas are lower than 9 m above
sea level. In this regard, Bangladesh has relatively limited hydropower potential even though it has
abundant water resources. Only in the Chittagong hilly terrain area are there some potential
hydropower resources.
The existing Karnafuli Hydropower Plant is in the Chittagong area and uses the water of Kaptai Lake.
It is the only hydropower plant in Bangladesh and its total installed capacity is 230 MW. Its No. 1 and
2 units (2 units of 40 MW) and No. 3 unit (50MW) were installed with assistance from the United
States, and operation started in 1962 and 1982 respectively. No. 4 and 5 units were installed with
assistance from Japan, and operation started in 1987. Further, No. 6 and 7 units were planned as a
Japanese Yen Loan Project in order to strengthen the power supply for peak demand. However, since
an Environmental Impact Assessment was not carried out and local consensus was not attained, a
Japanese ODA loan was not provided for the project. The problem was caused by conflicts between
indigenous people and immigrant Bengali people who were living around Kaptai Lake. Compensation
issues during the construction of Kaptai Dam were also one of the causes. Even now, entry to the area
is restricted because of law-and-order problems.
Despite such a situation, the Government of Bangladesh expects further hydropower development for
reduction of CO2 emissions and power system stability.
2) Results and issues
Under this Study, potential hydropower sites for Pumped Storage Power Plants (PSPP) and Ordinary
Hydropower Plants (Ordinary HP) or Small Scale Hydropower Plants (SSHP) were surveyed. The
results of the survey and identified issues are shown as follows:
(a) Potential PSPP Sites
The potential PSPP sites identified in the preliminary map study are shown in Figure 1-39.
Comparison of the potential sites was conducted based on the results of the literature survey and site
reconnaissance. PSPP No. 17 was selected as the most preferable potential site for the first PSPP
project in Bangladesh, and PSPP No. 13 was evaluated as the second potential site. However, it is
judged that realization of the projects will be difficult at this stage because of limited map data,
restrictions on survey activities and difficulties in the acquisition of and compensation for land due to
local sentiments against hydropower development.
In the future, however, it is expected that the selected potential PSPP sites will be developed when the
need for PSPP development increases for stability of the power system, and the above mentioned
limitations regarding the project implementation are solved.
Power System Master Plan 2016
Final Report
1-58
Figure 1-39 Location Map of Potential PSPP Sites
(b) Ordinary HP/SSHP Potential Sites
The locations of the potential sites for ordinary HP and SSHP in this study are shown in Figure 1-40.
Although the number of site visits was limited the JICA Survey Team came to the assumption that
most of the potential sites along the Sangu main river may cause large scale resettlements due to the
relatively gentle slope of the river. Though there are some prospective sites in terms of technical and
economic viability, those sites may not be suitable sites for development in consideration of the
environmental and social impact aspects.
On the other hand, the potential sites on the tributaries of the Sangu River are anticipated to have
limited water flow, particularly in the dry season. Thus, those sites do not seem financially viable.
In this regard, these potential sites seem unattractive for development of hydropower projects.
Power System Master Plan 2016
Final Report
1-59
Figure 1-40 Location Map of Potential Sites for Ordinary and Small Scale Hydropower
(2) Targets to Achieve
Targets to be achieved for realization of hydropower development in the Chittagong hilly area are as
follows:
Topographic maps are required for the initial survey and planning for the development of
infrastructure including hydropower generation facilities. However, the topographic maps of the
Chittagong Hill Tracts that can be used in such a survey and planning are not available.
The government should develop and arrange more detailed (1/25,000 scale) maps required for
further planning and conceptual design.
The implementing agency needs to find a solution to ease the sentiments of local people and to
gain understanding as to the necessity of hydropower plants.
The government should reduce concerns over security in the area.
(3) Roadmap
The road map for development of a PSPP by 2030 is as follows:
Preparation of maps by 2018.
The topographic maps of the Chittagong Hill Tracts shall have to be made available by 2018.
Completion of FS and establishment and capacity building of organizations engaged in the
pumped-storage power generation (PSPG).by 2020.
It is necessary to conduct a pre-FS or FS for the construction of a pumped-storage power plant
(PSPP) at the candidate sites identified in this survey when the topographic maps of the areas
concerned have been created and the residents in the areas have given consent to the
construction.
Human resource development will also be required for the development of PSPG. An
organization engaged in PSPG shall have to acquire the basic knowledge on the functions, roles
and economic characteristics of a PSPP. Persons who are to make decision on the feasibility of a
project for the construction of a PSPP, in particular, must have sufficient knowledge of PSPG.
Power System Master Plan 2016
Final Report
1-60
Therefore, training on PSPG shall have to be provided to not only the staff of an implementing
organization responsible for PSPG but also the decision makers while the above-mentioned
pre-FS or FS is being conducted.
Completion of Detailed Design by 2023.
The training of the power system operators shall also have to be conducted. Stabilization of the
power system is a significant function of PSPPs. Therefore, the training of the system operators
will be required for the effective use of PSPPs.
It is also necessary to establish ancillary services in the electric power market. When the
proportions of coal and renewable energy as the sources of power generation in the power
system in Bangladesh increase, the necessity for not only the power load-leveling but also
ancillary services will increase and the significance of PSPG will increase. The improvement of
the power market including ancillary services will be required for the realization of the optimum
power source balance with proper evaluation of PSPG.
Commencement of Construction of a PSPP by 2024.
A PSPP is a facility contributing to the stabilization of a power system. However, it is not easy
to evaluate its value accurately. It is difficult for a private company to construct a PSPP because
the profitability of operating such a plant is low unless there exists a special market such as an
ancillary service market or a special rate system for PSPG. As the PSPP concerned is the first
PSPP to be constructed in Bangladesh, it is expected to be constructed by a parastatal company.
Therefore, it is recommended that the PSPP be constructed in accordance with the conclusion of
a F/S in an ODA project.
Commissioning of the first unit of a PSPP by 2030.
Power System Master Plan 2016
Final Report
1-61
1.6.10 Renewable Energy
(1) Current Status and Issues
Regardless of the economic status, developing or developed, it is the international trend to promote
renewable energy, as part of energy security as well as greenhouse gas emission reduction. Many
countries have adopted renewable energy promotion policies, such as feed-in-tariffs (FIT) and various
incentives. India in particular has an aggressive plan, where renewable energy shares half of the new
generation capacity to be built by 2040 (while India will also increase coal-fired power plants).
Bangladesh is not an exception to this trend. Its Vision2021 and COP-INDC promise that
Bangladesh’s renewable generation capacity share will become 5% by 2015 and 10% by 2021.
Bangladesh is currently preparing the competitive bidding by IPPs, drafting FIT and providing other
incentives (mainly financial ones) for renewable energy businesses. However, Bangladesh has major
constraints for renewable energy expansion – namely land availability and meteorological conditions –
and the maximum renewable energy (power generation) potential is up to 3,700MW (see the below
Table). Even if the Variable Renewable Energy (VRE), such as solar PV or wind potential, is
developed to the maximum potential and connected to the grid, Bangladesh will gain about 4,200GWh
per year. This amount is quite limited in comparison with the total grid generation energy (estimated at
82,000GWh in 2020, 307,000GWh in 2040), and the IEA points out that the 5-10% of VRE in the
network does not require a major transformation of network development or operation, as such output
variation can occur as a result of load change or unplanned power plant outage.1 Still, as far as
Bangladesh increases the grid-connected renewable generation capacity, network and operation
capacity needs to be improved. In addition, Bangladesh needs to develop technical rules and
regulations for grid-connected renewable energy generation, as they do not exist at this moment.
Table 1-10 Renewable Energy Potential in Bangladesh
Technology Resource Capacity
(MW)
Annual Generation
(GWh)
Solar Park Solar 1400* 2,000
Solar Rooftop Solar 635 860
Solar Home Systems, (SHS) Solar 100 115
Solar Irrigation Solar 545 735
Wind Park Wind 637** 1250
Biomass Generation Rice husk 275 1800
Biogas Generation Animal waste 10 40
Waste to Energy Municipal waste 1 6
Small hydro power plants Hydropower 60 200
Mini-grid, Micro-grid Hybrid 3*** 4
Total 3,666 7,010 * Case 1 (agricultural land excluded) estimate
** Case 1 (flood-prone land excluded) estimate
*** Based on planned projects only, not a theoretical maximum potential, because there is potential
overlap with off-grid solar systems. Either could be used to serve off-grid demand.
Source: SREDA-World Bank Scaling Up Renewable Energy in Low Income Countries (SREP)
Investment Plan for Bangladesh, October 2015
Biogas in Bangladesh, while it has limited potential as a power generation source or for meeting major
gas demand, has great potential as home cooking fuel. Considering LPG’s expensive price, biogas
1 According to the IEA, these variable renewable energies would not create a major technical problem if the share of the
generated renewable energy (GWh) is 5~10% of the total grid generated energy.
Power System Master Plan 2016
Final Report
1-62
could play an important role especially in rural areas in order to realize SDG 7’s “affordable and clean
energy” goal. However, some lead time is required for substantial roll-out of a new type (glass fiber)
of biogas digester by removing duties and developing domestic manufacturers, and addressing the
biogas issue is a mid-term target.
In addition to the “within-the-boundary” renewable energy potential, Bangladesh is in a good position
to exploit the ample regional hydropower potential and import it through the cross-border transmission
network. Another JICA Survey shows the cross-border hydropower potential available to Bangladesh
is 3,500-8,500MW in 2030, mainly from Nepal and north-west India. Details of the cross border status,
issues and countermeasures are discussed in 1.6.11 .
(2) Targets to Achieve
1) Domestic renewable energy power generation (cumulative): 2,470MW (by 2021), and 3,864MW
(by 2041)
2) Domestic biogas production: 790,000m3/day (including additional 600,000m3/day by 2031, 3
million m3/day by 2041)
3) Cross-border Energy Imports: 3,500~8,500MW (by 2031), 9,000MW (by 2041)
4) Cross-border energy import rules and regulations’ set-up, associated with capacity building in this
area (mid to long term)
(3) Roadmap
1) Domestic renewable energy power generation (cumulative): 2,470MW (by 2021), and 3,864MW
(by 2041)
One project utility-scale solar park IPP project on competitive bidding basis, contracted and
operation start (short term)
Wind Resource Assessment completion (short term)
Grid connection technical rules and regulations for renewable energy generation (short term)
Grid connection approval process for utility-scale renewable energy generation (short term)
Grid enhancement planning and implementation for utility-scale renewable energy generation
(short term)
FIT and reverse auction setup (short term)
Network operation to manage renewable energy’s variable output (short term)
FIT revision and application to new projects (mid term)
Utility-scale solar project roll out (short to mid term)
2) Domestic biogas production: 790,000m3/day (including additional 600,000m3/day by 2031, 3
million m3/day by 2041)
Import duty/levy on glass-fiber biogas digester/material removal (short term)
Glass-fiber biogas digester domestic manufacturer development (mid term)
Glass-fiber biogas digester roll-out through IDCOL loan scheme (mid to long term)
3) Cross-border Energy Imports: 3,500~8,500 MW (by 2031), 9,000MW (by 2041)
See 1.6.11
4) Cross-border energy import rules and regulations’ set-up, associated with capacity building in this
area (mid to long term)
See 1.6.11 .
Power System Master Plan 2016
Final Report
1-63
1.6.11 Power Imports
(1) Current Status and Issues
Industrial diversification and advancement are essential in order to achieve further economic
development in Bangladesh. To this end, improvement of the quality of the power supply, such as
stabilization of network voltage and frequency, is a prerequisite. In addition, in anticipation of the
growing share of coal-fired thermal power generation in the medium and long term, the exploitation of
renewable energy resources with low environmental burden under the climate change perspective is
envisaged.
On-grid large-scale hydropower development seems to be an effective measure to overcome the
aforementioned issues. However, due to its flat geographical features, Bangladesh lacks prospective
hydropower potential over 1 MW apart from the existing Kaptai hydro power plant (230MW). In
contrast, there is abundant water power resource potential in the countries surrounding Bangladesh,
namely Bhutan, Nepal, Myanmar, and the Indian States of the North East and West Bengal
(collectively “neighboring countries”). Thus, it is expected that Bangladesh imports electricity out of
such hydropower generation via power interconnections with such neighboring countries for stable
base load supply, energy fuel diversification, and climate change mitigation.
The challenges arising from importing power and their countermeasures are as follows.
(i) Energy Security
In the case of importing power from other countries, the risk of supply interruption caused by adverse
relationships between the two countries needs to be considered. Electric power, which is different from
other types of supply, is technically easy to shut down even in minutes. So it is necessary to avoid
excessive reliance on other countries in order not to place oneself in a serious situation. Specifically,
the capacity of imported power from one country should be within the limit of generating reserve
margin and also 10% of all supply capacity in order to continue the supply in the event of supply
interruption. In the case of Bangladesh, imported power from Bhutan and Nepal has to be transmitted
through India. Therefore, imported power from Bhutan and Nepal should be within 10% of all supply
capacity.
(ii) Compliance with Commissioning Timing of the Transmission Lines in India
The power import plan through India hinges on commercial operation of the Case 2 HVDC (±800kV)
interconnection line or the Case 3 HVAC (765kV) interconnection line. These interconnection lines
shall be constructed in close cooperation with India after fully understanding and confirming India’s
needs.
When hydropower capacity exceeds 3,000MW in Arunachal Pradesh, the ±800kV inter-state
transmission line currently under construction reaches its full transmission capacity, giving rise to a
need for the construction of the Case 2 interconnection line. On the other hand, there seems to be no
reason for India to realize the need for the Case 3 line for the time being. However, need for the Case 3
line’s construction will arise if construction of the Case 2 line is delayed due to a delay in the hydro
power development in Arunachal state, or high construction costs etc.
(iii) Massive blackout due to large scale power loss of supply
It is desirable to import as much power as possible through one connecting point from the viewpoint
of economic efficiency. However, if a huge amount of power is transmitted through one connecting
point, it can lead to the risk of massive blackout, such as blackout across the entire country during the
shutdown of the connecting line. Massive blackout occurred on 1st November 2014, triggered by
500MW power loss of the BTB break down on the inter-connection line from India. In order to avoid
Power System Master Plan 2016
Final Report
1-64
this risk, the limit of the power loss level needs to be worked out, by checking sufficiently continuous
power generators’ operation during frequency drop and the load shedding scheme during large scale
power supply loss. Based on this result, the maximum level of import capacity in one inter-connection
point has to be decided. In concrete terms, it is preferable that the amount of imported power through
one connecting point is within 10% of the demand.
(iv) Mutual Interference due to Grid Accidents
Conducting power trading means transmission lines are connected between two neighboring countries,
which will lead to the threat of mutual interference due to grid accidents. But it is possible to minimize
the influence by connecting DC lines. Current inter-connection lines between India and Bangladesh
apply DC lines or non-connected lines by switching the load. There will be a few mutual interferences
due to grid accidents in these two cases.
(2) Targets to Achieve
(i) High Case Scenario
The High Case Scenario, in which more electric power can be expected due to operation of the Case 2
line and Case 3 line starting on schedule, is shown below.
Source: JICA Survey Team
Figure 1-41 Future Power Import Volume and its Share (High Case Scenario)
The share of power imports against the total supply capacity will be between 20% and 25% within the
permissible range, albeit a little bit large.
(ii) Low Case Scenario
The Low Case Scenario, in which excessive import of electric power from neighboring countries is not
expected, is shown below.
Power System Master Plan 2016
Final Report
1-65
Source: JICA Survey Team
Figure 1-42 Future Power Import Volume and its Share (Low Case Scenario)
The share of power imports against the total supply capacity will be approximately 15% within the
appropriate range after 2025.
(3) Road Map
Agreement acquisition with India is indispensable in order to achieve the plan for power imports from
the neighboring countries that are mentioned above. In particular, it is important to negotiate
tenaciously on the following items.
Advanced development of the Case 3 line
The Case 3 line is more flexible than the Case 2 line, and more effective for Bangladesh.
Because Bangladesh can import electric power from various regions by using the Case 3 line
it is important that it aims to advance development of this line.
Securing power transmission capacity in India
Bhutan and Nepal are positively in favor of electric power exports to Bangladesh. However,
when Bangladesh imports electric power from the two countries, it must pass through the
Indian system. It is especially important to match the system development plan in India and to
advance the plan if necessary in order to secure the power transmission capacity in India.
Direct connection of PSPP in Meghalaya state to Bangladesh system
The PSPP is a very effective tool for stabilizing the system and improving the power quality. It
is necessary to connect the generator directly to the Bangladesh system to enjoy such an effect.
As for the PSPP in Meghalaya state, large-scale development of 1,000MW or more is possible
at each site. Therefore, it is possible to secure economy even if the system is divided into two
parts at the power plant and half of the generators connect with the Bangladesh system
directly.
The existing communication channel suffices for discussions over bilateral power trades between
Bangladesh and India. However, if power trades with Bhutan and Nepal are involved, the use of the
Indian network is inevitable. Bilateral discussions between a seller (Bhutan or Nepal) and a buyer
(Bangladesh) are not enough to facilitate such power trades. A multilateral framework that includes
India is a prerequisite.
To provide a discussions platform of this kind, a group of countries comprising Bangladesh, Bhutan,
India and Nepal (BBIN) has been formulated. BBIN holds Joint Working Groups (JWGs) twice a year.
Therefore, it seems to be most effective to discuss regional power trades and interconnection in JWGs
Power System Master Plan 2016
Final Report
1-66
for the implementation of specific projects.
1.6.12 Nuclear Power
(1) Current Status and Issues
PSMP2016 aims to create a well-balanced power generation environment that maximizes the
respective advantages of different types of power generation methods, including nuclear power,
thermal power, hydropower generation, and power imports from neighboring countries, from the
comprehensive perspective of stable supply, or energy security, environmental performance, and
economic efficiency.
Daily power demand, or load curve varies according to season, temperature, and time of day. Since
electricity cannot be stored, and must be used as it is produced. Gas and oil based thermal power
generation, by virtue of its ability to respond quick flexibly to ever-changing power demand, supplies
middle and peak load. Nuclear power, power import, hydropower, and coal-based thermal power
generations are considered as a base load energy. This combination of different types of power sources
is commonly referred to as the best mix of power sources. In this PSMP2016, nuclear power
generation plays an important role in providing a stable base load.
The following figure shows the PSMP2016 scenario on nuclear power generation, following
discussions with the relevant institutions. It is assumed the first unit 1200MW is to start operations by
2024 and the second 1200MW by 2025 on PSMP2016. These figures are preconditioned in the power
development planning without alternative cases, which means nuclear power is assumed as one of the
Fixed Factors in terms of generation capacity in the simulation, considering the government’s nuclear
power projects planning.
Source: JICA Survey Team
Figure 1-43 Nuclear Power Development on PSMP2016
(2) Targets to Achieve
Realization of development of nuclear generation facilities, many challenges shall be solved.
(i) Meeting IAEA safety standards2
Nuclear safety remains the highest priority for the nuclear sector. Regulators have a major role to play
2 IAEA Safety Standards homepage
Power System Master Plan 2016
Final Report
1-67
to ensure that all operations are carried out with the highest levels of safety. Safety culture must be
promoted at all levels in the nuclear sector (operators and industry, including the supply chain, and
regulators) and especially in newcomer countries (Nuclear energy roadmap actions and milestones,
IEA, 2015) like Bangladesh. Followings are major frameworks to secure the nuclear safety to be
followed and utilize for Bangladsh.
Nuclear safety is a global issue. There are many instruments for achieving high level of nuclear safety
on a global basis, such as IAEA safety standards, safety review services provided by the IAEA. The
IAEA safety standards provide a system of safety fundamentals, Safety Requirements and Safety
Guides for ensuring safety. They reflect an international consensus on what constitutes a high level of
safety for protecting people and the environment from harmful effects of ionizing radiation. The IAEA
safety standards are applicable throughout the entire lifetime of facilities and activities existing and
new utilized for peaceful purposes, and to protective actions to reduce existing radiation risks. For
proceed nuclear power project, all shall follow the IAEA safety standards.
Source: IAEA Safety Standards homepage
Figure 1-44 Structure of IAEA Safety Standards
IAEA recommends some critical issue for strengthen nuclear safety
The regulatory body should be strengthened. The draft Bangladesh Atomic Energy Regulations
Act of 2011 should be promulgated as soon as possible to establish an independent regulatory
body.
Management of the nuclear infrastructure development should be strengthened. Bangladesh
should commit to ensure appointment of leaders (especially in future owner and regulatory body)
with appropriate training and experience for leadership and management of safety. Integrated
management systems (including quality management) should be planned and implemented in
both BAEC and the regulatory body that define the organizational goals and key processes in
sufficient detail.
(ii) Establishment of fuel cycle management3
Based upon the existing nature of the nuclear business worldwide, Bangladesh is considering a
long-term contract and transparent suppliers' arrangements with supplier(s) through backing of the
3 IAEA Country Nuclear Power Profiles, 2016 update
Power System Master Plan 2016
Final Report
1-68
respective government in order to ensure availability of fuel for the nuclear power reactor of the
country. Examples would be fuel leasing and fuel take-back offers, commercial offers to store and
dispose of spent fuel, as well as commercial fuel banks. On the other hand, at present there is no
international market for spent fuel disposal services except for the readiness of the Russian Federation
to receive Russian supplied fuel. Storage facilities for spent fuel are in operation and are being built in
several countries.
Bangladesh is considering accessing detailed technical descriptions of the nuclear fuel assemblies
offered from the supplier side, including physical, thermo-hydraulic, thermodynamic and mechanical
data as well as calculations for batch planning (short term and long term). The supplier shall provide
the QA programme, Handling and inspection methods for new and spent fuel and Tools for fuel and
control rod manipulation and the scope of supply and services. The first core as well as the first reload
should be included in the scope of supply for the plant. The bidders should include the supply of
further reloads as an option.
IEAE points out that the general concerns of Bangladesh about the nuclear fuel cycle are as follows.
The owner/operator of the nuclear plant in Bangladesh needs to ensure availability of fuel for the
NPP from supplier(s) covering its entire life cycle.
The above life cycle supply assurance shall include all services related to the front end of the fuel
cycle. “Fuel leasing-fuel take-back” model (full or partial) is conceivable for Bangladesh.
Alternate sources of services and supply of the front end of fuel cycle should be identified to
accommodate any unforeseen circumstances.
Depending on the size of the nuclear power programme, efforts will be made to acquire the
technology of fabrication of fuel elements based on imported raw materials and enrichment
services in order to ensure security of fuel supply.
Pending a final decision on the back-end of the fuel cycle, the NPPs will have provision for on/
off -site spent fuel storage, the size of which shall be sufficient to store the spent fuel generated
over their respective life cycles.
Sufficient security and physical protection and safety of the fuel storage on-site will be provided
in accordance with the relevant provisions of the non-proliferation regime, as well as national law
and regulations on nuclear safety and radiation control.
Bangladesh will consider any suitable model of nuclear fuel cycle under the responsibility of the IAEA
as the guarantor of service and supplies, e.g. as administrator of a fuel bank.
Bangladesh opines that as far as assurances of supply are concerned, the proposed multilateral
approaches to nuclear fuel cycle could provide the benefits of cost-effectiveness for developing
countries with limited resources. Bangladesh is strongly supporting the Agency’s approach of
developing and implementing international supply guarantees with IAEA participation.
(iii) Proper knowledge about nuclear safety and Public Acceptance
Many kinds of programmes, such as meetings and seminaars with journalists, local people, have been
arranged till now, and Bangladesh has established Nuclear Industry Information Center in 2013. 4
These kind of activities should be continued and enhanced for the public knowledge which will be the
basis for public acceptance.
However, BAEC has conducted survey in 2015 on public acceptance / awareness for nuclear power
project and it is found that still concrete public opinion for nuclear power generation has not yet
formed in Bangladesh since accurate information of nuclear generation technology has not became
widely and correctly known.
Therefore, the government has to do more supporting enlightenment activities to enhance accurate
technical knowledge on nuclear generation with good point and bad point as well as safety issue.
4 Presentation by MoST, “NATIONAL NUCLEAR POWER PROGRAMME OF BANGLADESH”,
https://www.iaea.org/NuclearPower/Downloadable/Meetings/2014/2015-02-03-02-06/D1_S2_Bangladesh_Akbar.pdf
Power System Master Plan 2016
Final Report
1-69
It is also recommended to review other countries’ experience of interactive communication with
public (citizen society) on nuclear technology and its safety, and ask for necessary cooperations.
As for emergency preparedness, several committees have been formed involving relevant stakeholders
to formulate the emergency management system during the operation of Nuclear Power Plant in the
territory of Bangladesh. These committees have already held several meeting with national and
international experts. The Government is also very much eager to develop a standard emergency
preparedness system for the densely populated country.
Source: Ministry of Science and Technology, 2015
Figure 1-45 Nuclear Industry Information Center
In addition, the government is preparing the Multi purpose information center around Rooppur NPP
site to strengthen public communication strategy with public and media. Expected PR-program is as
follows;
Scientific workshops & round tables, discussion clubs
Information center
Social networks/ Social activities
Expert opinions
Televisions (talks shows, documentaries)
Book “100” Facts bout Nuclear Energy
Communication of press releases & organization of interviews
Interaction with neighboring countries…etc
(iv) Participating international framework5
The Asian Nuclear Safety Network (ANSN) was launched in 2002 to pool, analyze and share nuclear
safety information, existing and new knowledge and practical experience among the countries.
Moreover, the ANSN is expected to be a platform for facilitating sustainable regional cooperation and
for creating human networks and cyber communities among the specialists of those countries.
Development of a regional capacity building system composed of knowledge network, regional
cooperation and human networks will serve for enhancement of nuclear safety infrastructures in the
participating countries, and will serve eventually for ensuring and raising the safety levels of nuclear
installations in the region. The ANSN has recently expanded to become a forum for broader safety
strategy among countries in the region.
The current participating countries are Bangladesh, China, Indonesia, Japan, Kazakhstan, Republic of
Korea, Malaysia, the Philippines, Singapore, Thailand and Vietnam. Australia, France, Germany and
the USA are ANSN supporting countries. Pakistan is an associate country in activities related to the
5 Asian Nuclear Safety Network homegage
Power System Master Plan 2016
Final Report
1-70
safety of nuclear power plants and/or strengthening their regulatory frameworks.
For proceed nuclear power project, all shall work with international framework.
Source: Japan Nuclear Energy Safety Organization
Figure 1-46 Asian Nuclear Safety Network (ANSN)
(v) Ratification to the international laws and standards
Bangladesh has not ratified the following critical international laws:
Vienna Convention on Civil Liability for Nuclear Damage
Protocol to Amend the Vienna Convention on Civil Liability for Nuclear Damage
Joint Protocol Relating to the Application of the Vienna Convention and the Paris Convention
Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste
Management, etc.6
For the implementation of RNPP, these international laws and standards should be followerd.
(vi) Other issues
There are many issues such as;
Nuclear power planning integrated into the part of power & energy planning, such as alternative
generation capacity in case of outage of nuclear power plant, reliability of the power supply
system
Development of science technology experience within the country
Emergency planning
Protection of the power plant from natural disaster (e.g. cyclone, flood, earthquake, etc) or outside
human disaster (e.g. terrorist activities, etc)
(3) Road Map
(i) Construction
Consideration of the domestic legal and regulatory conditions to obtain;
required licenses for building NPP,
industrial base to support NPP construction,
availability and competence of human resources for managing the NPP construction project,
national resources as well as its social, economic and environmental condition to support NPP
build.
6 IAEA factsheet: https://ola.iaea.org/ola/FactSheets/CountryDetails.asp?country=BD
Power System Master Plan 2016
Final Report
1-71
Source: Ministry of Science and Technology, 2015
Figure 1-47 Roadmap for nuclear power development
(ii) Legal and implementation framework
All legal and implementation framework shall be established, and even be in an active before a
commissioning of the first nucleare power generation as follows;
Meeting IAEA safety standards
Establishment of fuel cycle management
Propoer knowledge about nuclear safety and public acceptance
Participating international framework
Ratification of the international law and standards
(iii) Comissioning of generation
2024/25: 1st and 2
nd units
2030/31 3rd
and 4th units
2040/41 5th and 6
th units
Power System Master Plan 2016
Final Report
1-72
1.6.13 Power System Plan
(1) Current Situation and Issues
1) Transmission Plan
The operating voltages of the Bangladesh power network system are below 230kV and 132kV, except
for the 500MW HVDC link to India that began to be operated in 2014 at Bheramara. The 400kV
transmission lines and substations have just recently started to be constructed. Many existing power
stations have only a capacity of below 100MW, using domestic gas. They are currently distributed
across the whole of the nation. The following figure shows the current national power network system
of Bangladesh, which consists of 230kV and 132kV, without 400kV, and small-scale power stations
connected to substations distributed across the whole of the nation.
Figure 1-48 The Existing Bulk Power Network System of Bangladesh (2014)
An efficient power network system, including 765kV and 400kV transmission lines, needs to be
studied in consideration with the plan for large scale power stations, the high density of power demand
in and around Dhaka and Chittagong and the characteristics of Bangladesh’s power network system as
shown below.
The rapidly deteriorating and inefficient small-scale power stations with capacity below around
100MW will be phased out in sequence.
The future thermal power units will mainly use imported fuel such as coal or LNG. Because the
locations where suitable seaports can be constructed to receive large scale ships for imported fuel
are limited to south Chittagong and Khulna (Pyra and Patuakhali), the large scale power stations
with a capacity of several thousand MW will be unevenly distributed in those areas.
A nuclear power station with a total capacity of 4,800MW is planned for Rooppur.
In the case of power transmission from hydropower stations located in Bhutan or Nepal through
Power System Master Plan 2016
Final Report
1-73
India, HVDC interconnections with a capacity of around 500–2,000MW will be required in the
north western part of Bangladesh.
The power demand density in Dhaka and Chittagong will increase further due to their rapid
growth ratios.
Although it is required to transmit power of several thousand MW from Chittagong to Dhaka, the
number of circuits in the transmission lines is restricted on the route through Comilla because the
width of the country is narrow and the population density is large in the Comilla region.
The construction of transmission lines crossing between east and west in Bangladesh will incur
much cost because Bangladesh has two large rivers, named Jamuna and Padma, flowing in the
center of the country, with widths of at least around 4.5km to 6km.
2) Rural Electrification
While the government has established “Electricity for all” by 20217, in its Vision Statement, there is
no single internationally-established definition for electricity access.
As of December 2015, the Power Division recognizes the electrification rate of Bangladesh as 77%. In
government policy statements such as the 7th Five Year Plan, the Power Division’s figure is adopted.
Table 1-11 Electrification Rate Calculation Details by Power Division
Source: Power Cell, Power Division
The Electrification rate adopted by BPDB is the ratio of number of access and the whole population.
Access to Electricity is calculated by the below equation.
Source: BPDB System Planning Division
*1 It assumes that the number of people per grid connection (per household) is 7.
Household: Husband, wife, children x 2, father, mother + 1. There are big customers
such as hospitals, so 1 is added.
*2 It assumes that the number of people per off-grid connection (renewable) is 4 (-2014) or
5 (2013-). This is based on the assumption that a household using SHS has fewer family
members than a grid-connected household.
This BPDB definition indicates that the electrification rate improvement has two paths: one is on-grid
connection, the other is off-grid connection (e.g. SHS).
7 In the 7th Five Year Plan adopted in December 2015, the target by 2020 is set as “electricity coverage to be increased to 96
percent with uninterrupted supply to industries”.
BPDB REB DPDC DESCO WZPDCL SHS
No. of Domestic (Residential)
customer2,721,205 12,223,002 910,336 641,978 728,453 4,000,000
Family member parameter 5.5 6.5 4.5 4.5 5.5 4.0
No. of people with electricity
access14,966,628 79,449,513 4,096,512 2,888,901 4,006,492 16,000,000
Total No. of population with
electricity access
Total population of Bangladesh
Access to Electricity
157.8 million
77%
121,408,045
PopulationTotal
SHSofNumberCustomerdElectrifieofNumberyElectricittoAccess
2*1* 47%
Power System Master Plan 2016
Final Report
1-74
The following figure shows the Access to Electricity provided by BPDB. According to this figure,
60% of the population was electrified by grid connection; 8% was electrified by SHS installation. In
total, 68% of Bangladesh was electrified in 2014.
Source: JICA Survey Team, based on the data provided by BPDB
Figure 1-49 Development of Access to Electricity (BPDB definition)
The below Figure shows the BREB’s grid extension projections by 2021, compared with the actual
trend in the past up to 2015. The solid black line shows the actual implementation, and the red solid
line indicates the sum of the individual grid extension projects (as of February 2016).
It should be noted that BREB made a great improvement in grid extension implementation between
2014 and 2015, when it substantially increased the grid extension speed compared with the past
(between 2003 and 2013). The dotted blue line (Projection 1 in the Figure) means that if BREB keeps
the implementation speed as fast as that between 2014 and 2015, it will in theory reach 100% on-grid
extension (in other words, 440,000km distribution line development) by 2021 (it should also be noted,
however, that there is a technical issue with on-grid extension, as described later). On the other hand,
if BREB lowers its grid extension implementation speed to as slow as that between 2003 and 2013, it
would end up far below its target (green dotted line, projection 2 in the Figure).
30% 32% 35% 38%42% 43% 44% 47% 48% 49%
53% 55%60%0%
0%0%
0%0% 0% 0%
0%2% 3%
7%7%
8%
0%
10%
20%
30%
40%
50%
60%
70%
80%
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Ele
ctif
ied
rate
(%)
Electlified Rate by On-Grid Electlified Rate by Off-Grid
Power System Master Plan 2016
Final Report
1-75
Source: JICA Survey Team
Figure 1-50 BREB On-grid Extension Plan Comparison
The SHS installment has been implemented by IDCOL and the progress is at a world-renowned pace
(as seen in the below figure).
Source: JICA Survey Team
Figure 1-51 Number of SHS under IDCOL Program
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
400,000
450,000
500,000
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
Actual Plan Projection 1 Projection 2
Power System Master Plan 2016
Final Report
1-76
(2) Target of the study
1) Transmission Plan
The power network system is examined by categorizing the study phase into mid-term (2025) and
long-term (2035) through reviews of PSMP2010 in consideration of the application of 400kV and
765kV. The transmission lines and substations are planned in order to fulfill the criteria that are set as
the rules for power network system planning and analysis.
An efficient bulk power transmission network is planned reflecting the results of the power demand
forecast and power generation plan in this MP by recognizing the abovementioned current situation
and issues.
Source: JICA Survey Team
Figure 1-52 Conceptual Map of Locations of Large Scale Power Stations Planned Up to 2035
2) Rural Electrification
Only one definition of electrification rate should be selected. Also, the national census states that
the average family member size is 4.6, while 7 is adopted by BPDB.
Grid extension in the next 5 years requires the same implementation speed as that seen between
2014 and 2015, or twice as fast as the historical pace (average between 2003 and 2015).
BREB and IDCOL coordination and communication should be improved for efficient planning and
implementation. BPDB’s current role as “coordinator” could be reconsidered.
SHS waste recycling needs will drastically increase after the early 2020s. It should be confirmed
whether the current scheme has proven effective and scalable.
Khulna
Import
fuel
Matabari,
Mohesikali
Import fuel
India PSPP
Dhaka
6 GW
8 GW
3.5 GW
1 GW
1 GW
Barapukuria, Jmrpur Interconnection
Bheramara Interconnection
1 GW
Comilla North Interconnection
5 GW Nuclear
Other Gas (distributed) 6.0 GW
Power System Master Plan 2016
Final Report
1-77
1.6.14 Improvement of Power Quality
(1) Current Situation and Issues
1) Necessity of Power Frequency Quality Improvement
In general, the following objectives to improve frequency quality can be mentioned:
To improve the quality of industrial products.
To increase the allowable capacity of PV and wind power sources.
To secure the stable operation of large capacity generation plants (especially, nuclear power
plants).
All of the objectives may have high potential needs, but the methodology for determining the target
value for improvement has not been established yet. And it becomes more difficult than before to
determine the target value because the number of inverter circuits, which are inserted between the
power grid and consumer’s facilities or distributed power sources, is gradually increasing, though,
qualitatively, it can be determined depending on the trade-off relationship between cost and benefit for
consumers.
On the other hand, for stable operation of synchronous machines, such as large capacity generating
units, there is a quantitative requirement that the frequency quality shall be raised to within ±1.0% of
the standard value (50±0.5Hz).
In particular, the equivalent frequency quality is required in order to connect and operate stably the
nuclear power plant planned to be commissioned in 2024. Therefore, ±1.0% can be set as a
short-term target value.
Consequently, we set, in this Study, “±0.5Hz by 2024” as an essential target value, and “±0.2Hz by
2041 at latest” as a tentative value.
2) Current Situation
(a) Current conditions of generating facilities and significant deficiency of power sources
As seen in the results of the survey about the situation of supply-demand balance on days of maximum
peak demand from 2013 to 2015, the load shedding operation is frequently performed, even though the
installed capacity rate has been adequately secured at more than 130% every year.
The major factors involved in this situation are as follows:
The available capacity is chronically insufficient due to decreases in the output and thermal
efficiency and failures of power generators mainly due to the insufficient periodic maintenance,
which results in a decrease of around 30% of installed capacity.
Normally, full authority for preparing, approving and implementing the supply-demand balance
plan should be given to NLDC in order to carry out the balancing operation properly. However,
NLDC has no authority to coordinate the generating plans prepared by BPDB and other
generation companies.
(b) The actual conditions of power frequency control
At present, adjustment of the output of generators is instructed by phone (online instructions from
SCADA are not issued). System frequency deviation from 50 Hz often exceeds ±1.0 Hz even in the
normal operating condition (Grid Code stipulates that the system frequency shall be controlled within
Power System Master Plan 2016
Final Report
1-78
50Hz±1.0Hz under normal conditions.)
The major factors contributing to this situation are as follows:
There is almost no remaining power which can be offered for frequency control due to a
significant deficiency in power sources. That is, all generators have no other choice except to
keep their outputs at the maximum of available capacity.
Grid Code in Bangladesh seems to have most of the necessary and minimum provisions related to
frequency regulation and authority of NLDC. However, unfortunately, these provisions still seem
to have poor effectiveness.
There is no compensation system for the opportunity loss of power selling due to the contribution
to frequency control. There is a strong desire to obtain detailed information about a power system among the
stakeholders, because supply-demand control and frequency regulation should be performed
under fair and transparent circumstances.
3) Issues regarding power quality
(a) Regulatory framework
Regulation by the Electricity Acts
A rough comparative study between the provisions of Electricity Acts in Japan and Bangladesh is
performed.
As shown in the following table, there is only one obligatory provision (④) without penalty in relation
to stable demand/supply operation and frequency control in Bangladesh, while there are five
provisions with penalties in Japan:
Amendment is urgently required regarding several kinds of obligation rules and their penal provisions
in order to enhance effectiveness.
Provisions
Article Penalty Article Penalty
① Obligation to supply 18 Yes None -
② Obligation of endeavor to maintain
voltage/frequency value 26 Yes None -
③ Obligation to prepare a “Supply Plan” 29 Yes None -
④ Obligation to prepare “General Supply
Provisions” 19, 19-2 20, 21 Yes 22 None
⑤ Restrictions on Use of Electricity 27 Yes None -
Regulation by independent regulatory organization
The JICA survey team performed a comparative study of provisions between the two Grid Codes
established by the regulatory commission of each country, BERC (Bangladesh) and OCCTO (Japan),
in relation to the work process for supply-demand operation and frequency control, as shown in the
following table:
From the results of this comparative study, it was found that the necessary minimum provisions for the
supply-demand control process are appropriately stipulated in BERC’s Grid Code. However, there
seem to be no provisions for securing reserves (operating reserves, spinning reserves and so on).
Power System Master Plan 2016
Final Report
1-79
Provisions Details
Supply Plans (Power Plants and Network Development Plan) Yes None
Demand Forecasting
Variety of Forecasting Yes Yes
Responsibility of Forecasting Yes Yes
Post Facto Inspection Yes None
Planned outage schedule
Integration for the Draft Plans Yes Yes
Coordination between Users and Finalization of the Plans Yes Yes
Particular Points to note Yes Yes
Demand/Supply Balance
Schedules
Preparation of the plan and Monitoring the balance Yes Yes
Operating Reserves Yes None
Spinning Reserves Yes None
Margin for lowering Yes None
Measures when supply demand balance worsens Yes Yes
Real-time System
Operation
Frequency Control Yes Yes
Power Quality Analysis Yes None
Information Publication Yes None
(b) Prospect of frequency quality improvement and challenges in the future
Frequency regulation control is usually realized by a combination of FGMO (Free-governor mode
operation) and LFC (Load frequency control).
In this study, the JICA survey team conducted a trial calculation for future frequency improvement
when the regulation control is performed by FGMO only, because:
LFC function in SCADA/EMS is not prepared for use at present.
LFC cannot follow the sudden change in supply-demand balance caused by the trip of a
generating unit or load shedding.
Power frequency quality improvement in the N-0 Case (Normal Conditions)
Unfortunately, there is no globally standardized method to evaluate the frequency improvement.
Therefore, in this study, the JICA survey team calculates the available spinning reserves provided by
generators and the necessary amount of reserves to improve the frequency fluctuation per 0.1Hz, under
certain conditions and assumptions. The trend of future frequency quality can be estimated by finding
the balance point of available reserves and necessary reserves. For details, refer to the full final report.
The following graph shows the available spinning reserves and necessary amount of reserves each
year:
Power System Master Plan 2016
Final Report
1-80
Source: JICA Survey Team
Figure 1-53 Comparison between the Necessary Reserves and the Available Reserves
Solid line in red + Range in green = Available spinning reserves
= [Hydro (100%) + Oil (100%) + Gas (100%) + Coal (50%)] newly installed after June 2015
× 80% (assumption of planned and unplanned outage rate)
× 3 - 7% (assumption of the effective range of adjustment by FGMO)
Dashed lines : ΔP = 0.263 *√P (MW/0.1Hz)
ΔP : Necessary amount of reserves to improve frequency per 0.1Hz
P : Total power demand
(Frequency fluctuation, at present, is assumed to be ±1.5Hz)
The following graph shows the trend of frequency quality improvement from the viewpoint of
fluctuation range. Fluctuation range under normal conditions, at present, is set to ±1.5Hz according
to the chart provided by NLDC.
0
500
1000
1500
2000
2500
20
15
20
16
20
17
20
18
20
19
20
20
20
21
20
22
20
23
20
24
20
25
20
26
20
27
20
28
20
29
20
30
20
31
20
32
20
33
20
34
20
35
20
36
20
37
20
38
20
39
20
40
20
41
Pri
mar
y re
serv
e[M
W]
Necessary Primary Reserves (N-0)
Available FGMO rate 5%
±1.4Hz
±1.2Hz
±1.0Hz
±0.8Hz
±0.6Hz
±0.4Hz
±0.2Hz
Necessary primary reserves
to improve within ±0.2Hz
Necessary primary reserves
to improve within ±0.5Hz
Range of FGMO Regulation (3 - 7%)
Commissioning
Rooppur Nuclear P/S
Power System Master Plan 2016
Final Report
1-81
Source: JICA Survey Team
Figure 1-54 Trend of Power Frequency Quality Improvement
From the results of these analyses, there will be huge potential for appropriate frequency regulation
under normal conditions, if sufficient reserves for FGMO can be prepared in a carefully planned way.
By 2024, when a Rooppur nuclear power generating unit commences to be operated, sufficient
reserves can be prepared so that the frequency fluctuation can be reduced to ±0.5Hz or so, if
effectiveness of FGMO is expected to be 5% of total demand (average level)
By 2041, sufficient reserves can be prepared so that the frequency fluctuation can be improved to
±0.2Hz or lower.
Power frequency quality improvement in the N-1 Case (Emergency Conditions)
Even when a significant frequency deviation occurs due to a sudden trip of large capacity generators,
lowering of frequency should be limited to within a certain level and promptly recovered via sufficient
reserves.
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
1.10
1.20
1.30
1.40
1.50
1.60
1.70
20
15
20
16
20
17
20
18
20
19
20
20
20
21
20
22
20
23
20
24
20
25
20
26
20
27
20
28
20
29
20
30
20
31
20
32
20
33
20
34
20
35
20
36
20
37
20
38
20
39
20
40
20
41
Available FGMO rete 5%
without FGMO
Freq
uen
cy F
luct
uat
ion
: ff
[ 5
0±
ff H
z] Range of FGMO Regulation (3 - 7%)
Commissioning
Rooppur Nuclear P/S
Power System Master Plan 2016
Final Report
1-82
Source: JICA Survey Team
Figure 1-55 Schematic Diagram of the Frequency Deviation Immediately after the Generation
Trip
Overshoot of frequency immediately after the generation trip can be regulated only by FGMO and the
inherent characteristics of the flywheel effect in load. Therefore, urgent preparation for FGMO is
required in Bangladesh. The large capacity generator (power source) trip events which should be taken
into consideration in Bangladesh are as follows:
Table 1-12 Supply Trip Amount and Factors Which Should Be Considered in Each Year
Year Supply trip amounts Factors
2015~2024 500MW Single apparatus fault of HVDC 500MW
2024~2041 1180MW Single unit trip of Rooppur nuclear power plant Source: JICA Survey Team
The following graph shows the assumption for frequency deviation (Δf) using the standard value in
TEPCO, when a sudden trip of a Rooppur nuclear power unit (1180MW) occurs under the minimum
demand conditions each year after 2024.
Source: JICA Survey Team
Figure 1-56 Trend of minimum values of frequency immediately after a sudden trip of a
Rooppur unit
Amount of generator trip is small (Total demand is
Large) and the frequency is restored to 50[Hz]
Amount of generator trip is large (Total demand is small)
and the frequency transiently overshoots.
Bottom of frequency
Power System Master Plan 2016
Final Report
1-83
As shown in the graph above, frequency overshoots below the UFR settings, 48.9Hz, due to the trip of
the Rooppur unit in a low demand season or time zone, which leads to load shedding until 2028.
However, it should be allowed in order to avoid a cascading outage and blackout.
(2) Targets to Achieve
1) Improvement of Electricity Act and Grid Code Framework
(a) The Electricity Act 1910
Amendment to add provisions for various obligations and penalties for improvement of power quality
is urgently required.
(b) The Grid Code 2012
Grid Code in Bangladesh has necessary provisions to a certain extent, but provisions in relation to
preparation of reserves should be enhanced.
2) Improvement of Frequency Quality
Adequate reserves for FGMO should be prepared in a planned way, enough to improve frequency
fluctuation within ± 0.5 [Hz] (1/3 of fluctuation at present) as recommended in IAEA guidelines until
the operation of Rooppur nuclear power plants start in 2024 and 2025.
Adequate reserves for load shedding by UFR should be set in order to prevent a blackout as a tentative
measure.
(3) Roadmap
Key issues
in
PSMP2016
The goal Action Plan Target Prio
rity Short-term
(2016~2021) Medium-term
(2022~2031) Long-term
(2032~2041)
Power
Frequency
Quality
Improvement of
Electricity Act and
Grid Code
Framework
(Provisions for
obligation and
penalty)
Amendment of Electricity Act
Amendment of Grid Code
Improvement of NLDC Operation
Procedures
H
H
H
Improvement of
Frequency Quality
FGMO by newly installed units
- Planning and Designing
- Manufacturing/Conversion
- Testing and simultaneous
commissioning of units
planned from 2015 to 2021
- Promote systematically
according to the installation
plan after 2022
LFC by newly installed units
H
H
H
H
M
Preparation of reserves for load
shedding by UFR
M
Power System Master Plan 2016
Final Report
1-84
1.6.15 O&M Legal Framework
(1) Current Status and Issues
It has not been possible to suspend the operation of power generation facilities and inspect them regularly
because of the permanent shortage of the power supply in Bangladesh. The legal framework for the
preventive maintenance and O&M of these facilities is insufficient. BPDB is financially unsound because
of the low power purchase price. Because of these reasons, the power generation facilities are not
operating at their design performance level (in terms of power output, thermal efficiency, etc.). Therefore,
the establishment of an integrated system for the stable power supply is required. The analysis conducted on solving the problems concerning the preventive maintenance and O&M of the
thermal power plants with the development of a system, or the establishment of a legal framework, is
described in this subsection. In addition, the analysis conducted on solving the same problems with
measures to be taken in the plants is described in the next subsection.
<Issues>
1) Necessity of institutionalization of periodic inspections
Since periodic inspection is not stipulated by law in Bangladesh, periodic inspections tend to be
postponed due to reasons such as budget shortages or tight electricity demand, thus resulting in
unplanned and undesirable shutdown.
2) Necessity of institutionalization of safety audits
Government agencies, as they do not visit power plants to check the inspection situation, do not know
whether the machine conditions allow proper operations or not.
3) Necessity of institutionalization of chief engineer
As the responsibility for technical matters in a power plant is not clear, the organization doesn’t
function properly in the case of trouble.
4) Necessity of institutionalization of Safety regulations
Basic concept of security for operations in power plant is not documented.
5) Necessity of institutionalization of technical standards
National technical standards that would reduce the amount of accidental trouble and disasters are not
regulated.
These five provisions are essential for stable operation in Bangladesh.
(2) Targets to Achieve
Periodic inspections
Purpose
To avoid postponement of inspections due to budget shortages or tight electricity demand, etc.
by securing periodic inspections.
To prevent serious accidents by conducting periodic inspections.
Action
Power System Master Plan 2016
Final Report
1-85
Authorities decide the intervals and inspection items for periodic inspections.
Generators have to conduct the periodic inspections.
Safety audits
Purpose
To audit whether periodic inspections are implemented properly or not.
If there is a defect in the periodic inspection, auditors instruct on its correction.
Action
Authorities decide items for safety audits
Generators undergo periodic safety audits by authorities
Chief engineer
Purpose
To clarify the responsibility for technical matters
To carry out technical management under the chief engineer
Action
Authorities order generators to stipulate the responsibility of chief engineer
Generators select chief engineer from among licensed persons
Safety regulations
Purpose
To establish self-management system by making safety regulations
To establish PDCA cycle of operation independently
Action
Authorities order generators to set up safety regulations
Generators follow their safety regulations
Technical standards
Purpose
To prevent accidents and disasters caused by technical issues
To reduce the amount of forced maintenance work
Action
Authorities make national technical standards
Generators follows the national technical standards
(3) Roadmap
The suggested O&M legal items mentioned above can be divided into three categories as mentioned
below, and these measures are recommended to be taken step by step.
Strengthening of control by government
Periodic inspections
Safety audits
Self-management by Generators
Chief engineer
Safety regulations
Enhancement of technical aspects
Power System Master Plan 2016
Final Report
1-86
Technical standards
Based on the assumption that the preparation time for regulations is 2 years and the starting time for
the respective categories has a 1 year difference, the schedule becomes as follows.
Figure 1-57 Schedule for Legal Reform
Implementation of the regulations
Implementation of the regulations
Implementation of the regulations
STAGE2
Self-
management by
Generators
STAGE3
Enhancement
of technical
aspects
Year6
STAGE1
Strengthening
of control by
government
Year1 Year2 Year3 Year4 Year5
Periodic inspection
Safety audit
Authorities decides the intervals and inspection items
Generators has to conduct the periodic inspection
Authorities decides items of safety audit
Generators undergo safety audit by authority periodically
Chief engineer
Safety regulations
Authorities order generators selects the chief engineers
Authorities order generators makes safety regulations
Generators selects chief engineer among licensed person
Generators follows the safety regulations
Technical standards
Authorities makes technical standards
Generators follows the technical standards
Preparation Action
Preparation Action
Preparation Action
Power System Master Plan 2016
Final Report
1-87
1.6.16 Thermal Power Plant O&M
(1) Current Status and Issues
In Bangladesh, some thermal power stations have a capacity problem due to a lack of O&M practice.
This leads to the power production shortfall. Higher efficiency can be achieved by applying an
appropriate O&M practice with sufficient skills, so that the plant capacity can be recovered. In order to
comprehend the O&M situation in Bangladesh as a whole, the JICA study team carried out screening
with the following selection criteria, and then, selected some target sites for rehabilitation and
conversion to combined cycle as remodeling plans. The screening criteria are shown below.
(a) BPDB owned
Grounds: BPDB is the largest generation public company in Bangladesh
(b) Operation period: more than 10 years, less than 30 years
Grounds: 10 years of experience in O&M is preferable.
A unit older than 30 years may have large-scale malfunctions regardless of the application of the
remodeling plan, therefore, 10-20 year long stable operation may not be expected after the
completion of the remodeling works.
(c) Larger than 100MW
Grounds: There is little to expect from the rehabilitation effect on a small power unit.
(d) Availability higher than 30%
Grounds: This means the plant is very useful, and will continue to be vital in the future.
(e) Lowered output or efficiency
Grounds: A large effect can be expected.
Source: JICA Survey Team
Figure 1-58 Site Selection
Power System Master Plan 2016
Final Report
1-88
Source: JICA Survey Team
Figure 1-59 Target Site List
The study was performed based on interviews with and questionnaires for the representatives of the
target power plants. The results are categorized into Human Resources, Facility, Finance, and,
Information, which are commonly referred to as organizational resources in management of an
enterprise. As shown in the table below, the problems exist across the organizational resources.
Table 1-13 Problems in Organizational Resources
Core Missions
and Areas Human Capital Facility Finance Information
Generation
Capacity - Unit failure.
Aging. - -
Daily Operation Insufficient employee
rotation.
Lack of practical
training equipment.
Insufficient training
facilities.
- - Lack of efficiency
management.
Maintenance &
Repairs
Insufficient employee
rotation.
Lack of practical
training equipment and
material.
Insufficient training
facilities.
- No budget. -
Maintenance
Planning and
Budget Creation
- - No budget.
Absence of
supporting data for
maintenance plan and
shutdown permission.
Lack of evaluation
process.
Source: JICA Survey Team
While solutions to each problem are proposed in (2) Targets to Achieve, in accordance with the
Power System Master Plan 2016
Final Report
1-89
analytical method based on the organizational resources, some of the problems still remain unsolved in
the tree, which are:
Lack of standards for replacement
LTSA does not exist
Lack of standards for maintenance
Absence of legal enforcement
These are firmly connected with the legal framework which should be enacted by the government.
As the development of the legal framework has been examined in detail in the previous subsection, it
is not described in this section. However, it is possible for owners of power generation facilities to
conduct regular inspection without a legal regulation. It is necessary to make them aware that regular
inspection at short intervals will lead to long-term stability of output and the sustainable profitability
of power generators.
(2) Targets to Achieve
As a facility enhancement solution for the capacity problem, this Study proposes rehabilitation and
conversion to combined cycle. It also proposes the following plans to facilitate regular maintenance
which requires information management and plant crew trainings.
Table 1-14 Solution Proposals
Core Missions
and Areas Human Capital Facility Finance Information
Generation
Capacity
-
Steam turbine
rehabilitation &
conversion to
combined cycle.
Scheduled
maintenance.
- -
Daily Operation Training center
equipped with
simulators and hi-tech
training materials.
Work rotation.
- -
Collection of unit data
and fuel data, and
efficiency monitoring.
Maintenance &
Repairs
Training center
equipped with real
machines and hi-tech
training materials.
Work rotation.
- Mid-to long-term
maintenance budget. -
Maintenance
Planning and
Budget Creation - -
Procurement based on
maintenance plan.
Financial efficiency
monitoring and cost
optimization
Database for budgeting,
shutdown planning,
investment decision
making and evaluation.
Source: JICA Survey Team
The study team proposes the following feasible plans to implement the solutions above, which are
considered to be effective in human capital development, facility enhancement and efficiency
improvement in financial decisions.
The human capital development proposal includes a new training facility with a practical training
system (Training Center). The Training Center is purported to provide trainees with:
High-tech education for new power facilities.
Practical training courses and opportunities to experience real operations and maintenance
practices.
Education for certifications in compliance with laws and regulations.
In order to meet the training demand, the study mentions about inviting trainees to Japan during the
construction of the training facility.
Power System Master Plan 2016
Final Report
1-90
The facility enhancement proposal is based on a B&S (build and scrap) unit remodeling plan possibly
applied to Haripur and Fenchuganj. Compared to the other plans, the B&S plan has smaller impacts on
the production level of the power station. The capacity of the combined cycle unit is expected to be
100MW, which is responsive enough to fill the gap in the case where the frequency fluctuation
indicates a gap between peak demand and supply.
A 100MW combined cycle unit has the following advantages:
Quick start, short ramp-up (2 hours to reach the full load capacity).
High efficiency in the low load range.
Cost efficiency.
In order for the authority to improve efficiency in financial decisions, creation of mid-to long-term
plans for procurement in alignment with facility maintenance plans is strongly recommended. The
delays in budget and procurement approval would be reduced or removed, which should encourage
plant managers to create feasible maintenance plans.
Costs for regular maintenance should be allocated over time.
Contingency reserve must be estimated based on failure/repair history.
Spare inventory should be maintained at an optimal level.
The budget process must be integrated across the power plants.
The implementation items of the proposed solutions are shown in the table below.
Table 1-15 O&M Solution Proposals and Implementation Plans SOLUTION ITEM DESCRIPTION
Facility Facility Enhancement
Rehabilitation and
Conversion
Scrap & Build/Build & Scrap remodeling for Fenchuganj and Haripur.
Human Capital Human Capital Development
Education System Technical support from Japan in creation of training curriculum and materials.
Training provided in Japan.
- Education for technological standards.
- Learning about roles of Chief Engineer.
Training Facility Construction of the facility.
Technical support for introduction of facility and equipment such as simulator.
Finance Efficiency Improvement in Financial Decisions
Budget Creation Synchronization with maintenance plans.
- Estimation for maintenance cost.
- Supporting data for budget approval.
- Mid to Long term budget creation in alignment with regular maintenance schedule.
Procurement Process
Optimization
Planning
- Procurement process redesign.
- Spare inventory control.
- Cost reduction planning.
Procurement Efficiency Monitoring
- Budget control and delay management.
- Financial efficiency monitoring.
Source: JICA Survey Team
If BPDB has managed to establish a system for the centralized management of the data on the
operation and the plans and records of repair of all the plants under its control, as a financial measure,
Power System Master Plan 2016
Final Report
1-91
it will be able to estimate the budget for the entire organization and to plan for the suspension of the
plant operation and, thus, the delay in the approval of budget and suspension of the plant operation
will be reduced. The implementation of measures to solve problems in the information sector is
considered to improve the activities in the red rectangles in the figure below. It is considered that the
information can be used effectively in facilitating the solution of various problems in the operation of
power plants in general including problems concerning human resources, facilities and budget and
improving the O&M activities.
Source: JICA Survey Team
Figure 1-60 O&M Efficiency Improvement Supported by Information Management
One of the advantages of information management is that scheduled shut down for maintenance can be
aligned with demand and supply trends. This practice mitigates shutdown impacts on the grid.
Source: JICA Survey Team
Figure 1-61 Demand/Supply and Shutdown Planning
(3) Roadmap
In the area of operations and maintenance, the goal is to achieve efficient use of the enterprise
Power System Master Plan 2016
Final Report
1-92
resources. However, the first step towards practices of operations and maintenance needs to be legally
obliged, which guarantees implementation of regular maintenance. It also facilitates prompt decision
making on shutdown schedules and permissions. In the figure below, an O&M roadmap for
implementation of the proposals is shown along with the implementation plans for the legal
framework.
Source: JICA Survey Team Figure 1-62 Thermal Power Plant O&M Roadmap
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Legal Framework
Strengthen Control by Government Legislation Enforcement
Self-management by Generators Certification Enforcement
Enhancement of Technical Aspects Technical Standards Application
Facility Facility Enhancement
Rehabilitation and Conversion Planning Contract and Construction Operation
Human Capital Human Capital Development
Education System Technical Support from Japan Training in Japan Operation
Training Facility Planning Construction Operation
Finance Efficiency Improvement in Financial Decisions
Budget Creation Synchronization with Maintenance Plan
Procurement Process Optimization Planning Procurement Efficiency Monitoring
Power System Master Plan 2016
Final Report
1-93
1.6.17 Tariff Policy
(1) Current Status and Issues
1) Current Status and Issues
(a) Electricity Tariff
Serious Financial Situation of BPDB caused by the difference between electricity tariff and supply
cost
The current electricity bulk rate is not set high enough to cover the whole electricity supply cost.
Hence, BPDB, as the single buyer, continuously receives a subsidy as a form of long term loan. To
improve this situation, the bulk rate should be increased but this means that the electricity tariff for
final consumers should also be increased. Electricity tariff increase might have a negative impact on
the national economy of Bangladesh.
Electricity tariff menu as measure for supporting low income households
The electricity tariff menu is categorized according to the volume of usage and a lower rate is set for
low income households. When Bangladesh increases the electricity tariff, measures for low income
households should be considered.
(b) Gas price
Difference between international gas price and domestic gas price
Currently, the domestic gas price is set at a lower level. However, if gas demand increases and
Bangladesh starts imports of gas such as LNG, and the gas price is not increased, the gas sector will
require subsidies from the government.
2) Results of analysis and challenges
If the electricity tariff and gas price are increased rapidly in a single year, it will effect a huge negative
impact on the national economy of Bangladesh. It is desirable to increase the electricity tariff and gas
price progressively.
GTAP was used to analyze the impact of electricity tariff increase and gas price increase on the
national economy of Bangladesh. The following model was used for the GTAP analysis.
Area category: Bangladesh, Asian countries, other countries in other regions.
Sector category: Agriculture, coal*, oil*, gas*, electricity, industry, service.
*only for analysis for gas price increase.
(a) Electricity Tariff
To analyze the economic impact of an electricity tariff increase on the national economy of
Bangladesh, impact in the current year only (single-year analysis) was first analyzed. The impact of a
price increase in 2014, the year when the latest data set can be obtained, was analyzed.
The following scenarios were set for the electricity price:
Power System Master Plan 2016
Final Report
1-94
Scenario (a): average electricity price increase of 10% in real USD
Scenario (b): average electricity price increase of 20% in real USD
Scenario (c): average electricity price increase of 30% in real USD
The above-mentioned percentages are increase rates in real USD. If we consider the average inflation
ratio from 2010 to 2014, 7.9%8, the ratios in nominal BDT become 19% in scenario (a), 29% in
scenario (b), and 40% in scenario (c).
In Bangladesh, the electricity price menu for final consumers is different from the size of usage.
However, as a methodological limitation of GTAP analysis, one average price increase ratio was set
for each scenario in the analysis (for example, one “average” 10% electricity tariff increase was used
for scenario (a) instead of different prices for different categories (e.g. 5% electricity increase for low
income households and 15% for high income households)).
The results of the analysis are shown in the following table. A 10% electricity tariff increase produces
a negative effect on real GDP of 0.72%, a 20% increase produces a negative effect on real GDP of
1.45%, and a 30% increase produces a negative effect on real GDP of 2.17%. If the electricity tariff is
increased rapidly, it produces a huge negative effect on real GDP as compared with GDP current
growth.
Table 1-16 Impacts of Electricity Tariff Increase on Bangladesh National Economy (single-year
analysis)
Index (a) 10% increase (b) 20% increase (c) 30% increase
Change ratio
(%)
in real USD
Change
amount
(million
USD)
Change ratio
(%)
in real USD
Change
amount
(million
USD)
Change ratio
(%)
in real USD
Change
amount
(million
USD)
Impact on
real GDP -0.72 -810.7 -1.45 -1618.6 -2.17 -2424.0
Impact on
real exports -0.28 -79.3 -0.56 -157.7 -0.83 -235.1
Impact on
real imports -0.27 -94.7 -0.55 -189.5 -0.82 -284.2
Source: JICA Survey Team
Next, the impact of a progressive increase of electricity tariff was analyzed. Under the assumption that
the cost of the electricity generation supply rises at 1.5% per year in real USD, the following scenarios
were set and the impact on the macro economy of Bangladesh was analyzed. Scenario 1 was set as the
electricity tariff becoming equal to the supply cost by 2021, scenario 2 was by 2031, and scenario 3
was by 2041.
Table 1-17 Scenarios of Electricity Tariff Increase: Case 1 (cost increase) Scenario Annual Increase in real USD
Increase in Cost 1.5%/year
(9.5%/year in nominal BDT in consideration of average inflation rate from
2010 to 2014)
Base Scenario 1.5%/year
(9.5%/year in nominal BDT in consideration of average inflation rate from
2010 to 2014)
1 4.2%/year until 2021
(12.4%/year in nominal BDT in consideration of average inflation rate from
2010 to 2014)
8 Source: World Bank data site
Power System Master Plan 2016
Final Report
1-95
Scenario Annual Increase in real USD
1.5%/year from 2022
(9.5%/year in nominal BDT in consideration of average inflation rate from
2010 to 2014)
2 2.6%/year until 2031
(10.7% in nominal BDT in consideration of average inflation rate from 2010
to 2014)
1.5%/year from 2032
(9.5%/year in nominal BDT in consideration of average inflation rate from
2010 to 2014)
3 2.2%/year until 2041
(10.3%/year in nominal BDT in consideration of average inflation rate from
2010 to 2014) Source: JICA Survey Team
Table 1-18 Scenarios of Electricity Tariff Increase: Case 2 (no cost increase) Scenario Annual Increase in USD
Increase in Cost 0%/year
Base Scenario 0%/year + minor fluctuation in the model calculation
1 2.6%/year until 2021
(10.7%/year in nominal BDT in consideration of average inflation rate from
2010 to 2014)
0%/year + minor fluctuation in the model calculation from 2022
2 1.1%/year until 2031
(9.1%/year in nominal BDT in consideration of average inflation rate from
2010 to 2014)
0%/year + minor fluctuation in the model calculation from 2032
3 0.7%/year until 2041
(8.7%/year in nominal BDT in consideration of average inflation rate from
2010 to 2014) Source: JICA Survey Team
In comparison with the single-year analysis, the increase per year become small and the annual
negative impact will be mitigated. Electricity tariff increase in Case 1 decreases GDP by 0.17%/year in
2014, and 0.26%/year in 2021, in Scenario 1. Electricity tariff increase in Case 1 also decreases GDP
by 0.07%/year in 2014, and 0.17%/year in 2031, in Scenario 2. Electricity tariff increase in Case 1
decreases GDP by 0.04%/year in 2014, and 0.15%/year in 2041, in Scenario 3. In Case 2, similar
impacts are expected. Furthermore, in the long run, negative impact on GDP is mitigated as compared
with a sharp rise in the single-year analysis.
Table 1-19 Impacts of Electricity Tariff Increase on Bangladesh National Economy (Case 1)
Scenario 2014 2021 2031 2041
Scenario 1 -0.17 -0.26 -0.06 -0.06
Scenario 2 -0.07 -0.09 -0.17 -0.06
Scenario 3 -0.04 -0.06 -0.1 -0.15 Source: JICA Survey Team
Table 1-20 Impacts of Electricity Tariff Increase on Bangladesh National Economy (Case 2)
Scenario 2014 2021 2031 2041
Scenario 1 -0.17 -0.26 -0.04 -0.04
Scenario 2 -0.07 -0.09 -0.15 -0.03
Scenario 3 -0.04 -0.06 -0.09 -0.12 Source: JICA Survey Team
Power System Master Plan 2016
Final Report
1-96
(b) Gas Price
To analyze the economic impact of a gas price increase on the national economy of Bangladesh, the
impact in the current year only (single-year analysis) was first analyzed. The impact of a price increase
in 2014, the year when the latest data set can be obtained, was analyzed.
The following scenarios were set for the gas price:
Scenario (a): average gas price increase of 50% in real USD
Scenario (b): average gas price increase of 100% in real USD
The above-mentioned numbers are rates in real USD. If average inflation ratio from 2010 to 2014 is
considered, 7.9%, the ratios in nominal BDT become 62% in scenario (a), and 116% in scenario (b).
The results of the analysis are shown in the following table. A 50% increase in the gas price produces a
negative effect on real GDP of 1.26%, and a 100% increase produces a negative effect on real GDP of
2.47%. The result shows that the impact of a rapid gas price increase on real GDP is relatively high in
comparison with GDP current growth.
Table 1-21 Impacts of Gas Price Increase on Bangladesh National Economy
(Single-year analysis)
Index (a) 50% increase (b) 100% increase
Change ratio (%)
in real USD
Change amount
(million USD)
Change ratio (%)
in real USD
Change amount
(million USD)
Impact on real GDP -1.26 -1407.9 -2.47 -2759.1
Impact on real exports -0.72 -204.7 -1.35 -382.8
Impact on real imports -1.36 -472.6 -2.70 -937.7
Source: JICA Survey Team Next, the impact of a progressive gas price increase on the national economy of Bangladesh was
analyzed. The following scenarios were set for the analysis. Scenario 1 was set as a progressive gas
price increase to the desirable level considering the international price by 2021, scenario 2 was by
2031, and scenario 3 was by 2041.
Table 1-22 Scenarios of Gas Price Increase
Scenario Annual Increase of Gas Price in real USD
Base
Scenario
0%/year
1
47.2%/year until 2021
(58.8% in nominal BDT in consideration of average inflation rate from 2010 to
2014)
0%/year from 2022
2
17.3%/year until 2031
(26.6%/year in nominal BDT in consideration of average inflation rate from 2010 to
2014)
0%/year from 2032
3
10.6%/year until 2041
(19.3%/year in nominal BDT in consideration of average inflation rate from 2010 to
2014) Source: JICA Survey Team
The result shows that the negative impact is mitigated by retarding the speed of increase.
Gas price increase decreases GDP by 0.33%/year in 2014, and 5.13%/year in 2021, in Scenario 1. Gas
price increase decreases GDP by 0.02%/year in 2014, and 2.82%/year in 2031, in Scenario 2. Gas
Power System Master Plan 2016
Final Report
1-97
price increase produces a positive impact in 2014, and a decrease of 1.08%/year in 2031, in Scenario 3.
Negative impact on GDP in the current situation (e.g. in 2014) is mitigated as compared with a sharp
rise in the single-year analysis.
Table 1-23 Impacts of Gas Price Increase on Bangladesh National Economy
Scenario 2014 2021 2031 2041
Scenario 1 -0.33 -5.13 0.52 0.18
Scenario 2 -0.02 -0.43 -2.82 0.09
Scenario 3 0.04 0.19 -1.08 -0.32 Source: JICA Survey Team
(2) Targets to Achieve
1) Electricity tariff reform
(a) Increase of household electricity price
Bangladesh should increase the domestic electricity tariff. BPDB should decrease subsidies and
increase the electricity bulk rate and electricity tariff to cover the whole supply cost. Due to concerns
regarding low income households, the category for lower income households should not be increased.
The electricity tariff menu is categorized according to the volume of usage. A lower rate is set for low
income households. When Bangladesh increases the electricity tariff, measures for low income
households should be considered.
(b) Discussion among stakeholders
An appropriate scenario for increasing the electricity price should be set in consideration of the
negative impact on GDP. Therefore, the related ministries should discuss this. It is recommended for
Bangladesh to organize meetings with related ministries and develop a plan for the electricity tariff
increase.
2) Capacity building of human resources for financial review
Public acceptance of an electricity tariff increase will not be achieved without sufficient effort to
increase the supply cost. Therefore, chances to reduce the supply cost should be identified and an
increase in tariff should be proposed with the reduction of supply cost.
It is difficult for third parties to get involved in the cost reduction process because much information is
confidential within companies. First, it is recommended for BPDB to launch a special team to
determine processes that are inefficient in terms of cost. It is difficult to change the conditions of a
signed contract, so it is recommended to establish a structure to check cost efficiency when BPDB
makes new contracts. Support from donors such as JICA for capacity building is beneficial.
3) Gas Price Reform
Increase of gas price
In line with the importing of natural gas, the gas price in Bangladesh should also be increased.
However, the price in the category for minimum usage should be maintained as a measure to support
low income households. The gas price menu is categorized according to the volume of usage. A lower
rate is set for low income households. When Bangladesh increases the gas price, measures for low
income households should be considered.
(3) Road Map
1) Electricity price reform
Power System Master Plan 2016
Final Report
1-98
The draft ideas for scenarios for increasing the electricity tariff are the ones used in the analysis. It is
recommended to set the average increase of electricity price until 2021, 2031, and 2041 according to
the scenarios in Table 1-24.
Table 1-24 Example of Scenarios for Electricity Tariff Increase
Scenario Annual Increase in USD
1
4.2%/year until 2021
(12.4%/year in nominal BDT in consideration of average inflation rate from 2010 to 2014)
1.5%/year from 2022
(9.5%/year in nominal BDT in consideration of average inflation rate from 2010 to 2014)
2
2.6%/year until 2031
(10.7%/year in nominal BDT in consideration of average inflation rate from 2010 to 2014)
1.5%/year from 2032
(9.5%/year in nominal BDT in consideration of average inflation rate from 2010 to 2014)
3 2.2%/year until 2041
(10.3%/year in nominal BDT in consideration of average inflation rate from 2010 to 2014)
Source: JICA Survey Team
2) Development of Cost Reduction Plan
BPDB should launch a special team for cost reduction as soon as possible. Preferably by 2017 or 2018
the special team should be ready to start analysis.
3) Gas Price Reform
It is recommended to increase the gas price in line with scenarios such as those proposed in the
analysis. However, in consideration of the supply cost increase, in Scenario 1, a 1.5%/year increase
should be applied after 2022, and in Scenario 2, a 1.5%/year increase should be applied after 2032 to
make them more realistic.
Table 1-25 Scenarios of Gas Price Increase
Scenario Annual Increase of Gas Price in real USD
1
47.2%/year until 2021
(58.8%/year in nominal BDT in consideration of average inflation rate from 2010 to 2014)
1.5%/year from 2022
2
17.3%/year until 2031
(26.6%/year in nominal BDT in consideration of average inflation rate from 2010 to 2014)
1.5%/year from 2032
3 10.6%/year until 2041
(19.3%/year in nominal BDT in consideration of average inflation rate from 2010 to 2014)
Source: JICA Survey Team
Power System Master Plan 2016
Final Report
1-99
1.7 Road-map
To achieve VISION 2041, a road map has been prepared as Bangladesh’s long term strategic power
and energy development planning. The road map, classifiying into three timeline; short, mid to long,
and super long, states specific targets to be achieved, and also shows by when, what items that the
government of the Bangladesh shall implement. It is strongly desided that all indicated items on road
map shall be implemented for certain to achieve VISON 2041.
Power System Master Plan 2016
Final Report
1-100
Table 1-26 Roadmap for PSMP2016
Target Action Plan
Incentive for promoting foreign direct investment (Preferential Taxation)Other,
Deregulation (Abolishment of entry regulation)
Implementation of program for improving skill
Construction of industrial complex and SEZ
Other, Transportation infrastructure improvement(Port, Road, Railway)
Implementation of recommendation by EECMP
A-Appliance-labeling
B-Energy management (reporting)
C-Energy-saving building code
D-Low interest loan program for EEC equipment
Program of Ecologically friendly car
Improvement of road network
Improvement of railway network
Revised PSC to attract IOCs
International Tender for new onshore and offshore acreage
Partnership between foreign investor and BAPEX、BGFCL、SGFFL
Revise the role of BAPEX
Transform the capacity of BAPEX
Acquisition of oversea energy asset
Development of legal framework regarding efficient use of gas
Improve efficiency towards international standard and decommission of
inefficient facilities
Introduce electronic mapping system for gas transmission and distribution system
Introduce gas flow monitoring and safety management system
Import duty/levy on glass-fiber biogas digester/material removal
Glass-fiber biogas digester domestic manufacture development
Glass-fiber biogas digester roll-out through IDCOL loan scheme
Introduction of LNG LNG F/S, FEED, EIA and Land Acquisition
Construction of onshore LNG Terminal (3 sets of tank) to be operational from
2027. Additional tank will be installed after COD of 1st Phase.
Prepare strategy for LNG procurement
Construction of pipeline to connect into onshore pipeline
Commencement of commercial operation
Impact study of LNG introduction to existing gas infrastructure and gas
processing facilities
Construction of FSRU and related infrastructure of 1st and 2nd Phase
Commencement of commercial operation
Implementation of F/S Imported Coal infrastructure
CTT (Phase1~2)FY2025, FY2029
Construction based on F/S
CTT (Phase1)commencement of operation in 2025
CTT (Phase2)commencement of operation in 2029
Establishing technology acquisition system for Bangladesh in order to secure
stable production at Barapukuria Mine
Establishing a system in order to proceed to new mining development mainly in
Bangladesh
To be crystallized after 2017
Commercial Operation in 2021
Commencement of Construction after 2022
Commencement of production after 2027
Review the result of pilot operation of Barapukuria Mine and commencement of
small scale open-cut mining of Phulbari Mine after 2021
Commencement of construction after 2025
Analysis b/w domestic refinery and oil product import completed and decision
made
Exit strategy on oil subsidy established and implemented
Oil import facility (storage tank or domestic refinery) developed to meet
increased oil demand
Energy mix: 3E-Value(Economy/Environment/Energy Security)
Capacity building for MP revision
-Collaboration between organizations for MP
-Periodical rolling revision for milestoned-MP
-Strengthen comprehensive statistical work function
-Introduction of KPI management
Improvement in the investment climate
-PPA improvement
-FDI improvement
-Prompt procedure of invenstment application
-Introduction of financial credit approval by Int'l Organization
No load shedding
Exiting from high cost rental power
Securing low cost power supply for baseload
Integrated energy infrastructure (Port facility for fuel terminal)
Tariff reform
O&M reform
4. LNG Supply
Contents of PSMP2016Sort Term
FY2016~2020
Mid-Long Term
FY2021~2025/ 2026-2035
Acqsition of energy assets in
overseas
Efficient use of Gas
Introduction of advanced
operation and infrastrucure
management system
Domestic biogas
production: 790,000m3/day
(including additional
600,000m3/day by 2031
and 3 million m3/day by
2041
6. Oil Supply Oil imprt 30 million tons/yr
Onshore LNG Terminal to
Supply 3,000 mmscfd of
Gas by 2041
FSRU to Supply 500 mmscf
of Gas by 2019
5. Coal Supply
Super Long Term
FY2036~2041
Economy1. Economic
Development
High-income country by
2041
Introduction of IOCs which
has technological and
financial advantages
Energy Balance
2. Primary Energy
Demand
Reduction of energy
intensity by more than 20%
3. Domestic Gas Supply
Optimized energy mix7. Power Development
Plan
60 million ton to be
expected imported Coal by
2041
Mining technology
acquisition for Bangladeshi
Commencement of
construction for pilot site at
Barapukuria Mine based on
open-cut mining technology
Development Permission
for Digipara Mince,
Karaspir Mine
Small scale open-cut mining
of Phulbari Mine
Commencement of Construction
Barapukuria Mine
open -cut mining (2025)
Initial Phase Terminal Expansion
TransmissionDistribution
Initial phase completed and
commercial operation started (2027)
1st phase of FSRU completed and commercial
operation started (2019)
GDP per capita
11,000 USD (2041)
Energy intensity
3.42-->2.56 million USD/toe
Oil import: 5 --> 30 million tons/yr
Power for all
2nd 2023 start operation
1st 2018-19 start operation
Well-organized investment climate
Well-organized planning climate
Energy Mix-Min 3E
Power System Master Plan 2016
Final Report
1-101
Source: JICA Survey Team
Target Action Plan
Preparation of maps by 2018
Completion of Feasibility Study for a PSPP by 2020
Completion of Detailed Design by 2023
Commencement of Construction of a PSPP by 2024
Commissioning of the first unit of a PSPP by 2030
Transparent and competitive bidding process for utility-scale RE generation
project (1 project)
Completion of wind resource assessment
Technical standards and regulation/rules for RE grid-connection
Transparent and competitive bidding process
FIT and reverse auction system
Utility-scale solar project roll out
Removal of import duty and levy on high-quality glass-fiber biogas digester
Nurture of domestic glass-fiber biogas digester manufactures and dealers
Cost competitiveness of biogas over LPG maximized
Advanced development of the Case 3 line
Securing power transmission capacity in India
Direct connection of PSPP in Meghalaya state to Bangladesh system
Establishment of legal and implementation framework
Meeting IAEA safety standards
Establishment of fuel cycle management
Propoer knowledge about nuclear safety and public acceptance
Operation of nuclear power plants
Direct connection of Dhakka - Chittagong
Strengthening trunk lines for regional development
Transmission facility developed to meet increased power demand
Electrificaion for All by 2021
SHS waste management process established
Amendment of Electricity Act
Amendment of Grid Code
Amendment of NLDC's operational rule
Governor-free operation of new installed generator
- Engineering
- Construction
Commissioning and commencement of operation new installed plant from Jun
2015 to 2021
Implement plan based on the review of new installed plant After 2022
Fulfillment of new installed generator of LFC control
Strengthen monitoring by government
Strengthen utilities' self-management
Technology enhancement
Upgraded combined cycle thermal power plant
Building information management system
Establishment of traning center
Power tarrif increase
Gas tarrif increase
Energy Balance
Contents of PSMP2016Sort Term
FY2016~2020
Development of laws
Mid-Long Term
FY2021~2025/ 2026-2035
Super Long Term
FY2036~2041
9. Renewable Energy
Renewable Energy :
Maximizng generation
potential under the limited
land availability
Biogas production: 62
mmcfd by 2041
8. Hydropower
To be achieved for
realization of hydropower
development in the
Chittagong hilly area
Thermal power plant O&M
[Nuclear Power]
Development of nuclear
power up to 7,200 MW
Energy Cost and
Tarrif Balance15. Energy Tarrif Policy
No gap between tarrif and
supply cost
Power Balance
10. Power Import/
Nuclear Power
[Import Power]
Increase power import from
neighboring counties up to
9,000 MW
11. Power Transmission
Planning
Robust power system
development
12. Distribution
(Rural electrification)
13. Improving Power
Quality
Development of laws and
rules (obligation and penalty
etc.)
Implement ensuring
frequency adjustment
margin and control
14. Thermal O&M
2.6%/year 1.5%/year
10-20%/year 1.5%/year
Biogas production : 4 --> 62 mmcfd
Maximising RE
generation potential
under limited land
H: 5,500 MW
L: 3,000 MW
H: 8,500 MW
L: 5,000 MW
H: 8,500 MW
L: 7,000 MW
1&2 Units 5&6 Units3&4 Units
Power System Master Plan 2016
Final Report
2-1
Chapter 2 Recommendations on the Implementation & Monitoring of the
Master Plan
The issues required to be addressed with a scope wider than the scopes of subject-specific
development plans and those of individual sectors in the implementation of this master plan in future
and the monitoring of its progress, including some recommendations made in the preceding chapters,
are described in this chapter. The issues that were not considered to be the preconditions for the
formulation of this master plan, but which have to be considered in the monitoring of its
implementation and its revision in future are also described in this chapter.
2.1 Capacity building for master plan revision
2.1.1 Collaboration and Cooperation between Organizations involved in the Formulation of MP
In Bangladesh, the Power Division under the Ministry of Power, Energy and Mineral Resources
(MoPEMR) is responsible for developing power development plan, and the practical works are done
by the Bangladesh Power Development Board (BPDB). In the meanwhile, the Energy and Mineral
Resource Division under MoPEMR is responsible for the energy supply plan other than electricity and
the practical works are done by Petrobangla, Bangladesh Petroleum Corporation (BPC) and so on.
This study observed that, because of the separated administration between electricity and other energy
sources, there is no organizational structure that supervises the overall energy supply and demand in
Bangladesh comprehensively. As the domestic production of natural gas in Bangladesh is expected to
deplete whereas the energy demand will continue to increase rapidly, the country will need to depend
more on imported energy sources.
Considering this situation, the importance of developing an energy supply plan from a comprehensive
viewpoint is expected to gain importance for determining how to appropriate the limited domestic
energy production among various sectors and which energy sources to import for supplying to which
sector and how much.
In developing the aforementioned power development plan and energy supply plan, a systematic
relation among stakeholders is needed so that the responsibility of various data necessary for making
future projection such as the actual operational data and facility development plan is identified and
that these data are administrated in unity. Current status is that, as observed by the JICA Study Team,
relations among the organizations responsible for administrating these data are not sufficiently
established.
These power development plan and energy supply plan need to be updated regularly by reflecting the
conditional changes. Therefore establishing an institutional framework is necessary to develop and
implement both plans comprehensively by involving all the relevant stakeholders for these plans to
share information.
2.1.2 Periodical Rolling Revision of the Milestone Plan Although a PSMP has been formulated every five years as a milestone plan, its periodical revision based on
a rolling plan has not been conducted appropriately. In principle, a power supply plan in a power
development plan is formulated on the basis of demand projection and appropriate standards for ensuring
the reliability of supply. However, as the proportions of the projects mentioned in power development plans
that have reached the operation stage have been small, a list of prospective projects for investment tends to
be included in a power development plan as it is. In principle, a power development plan has to be revised
in accordance with power demand and the supply reliability standards as the planning and preparation for
projects progress. It is also necessary to revise the power development plan and the energy supply plan
formulated in this survey periodically, at least once a year, with changes in the situation including the state
of the economy, supply/demand balance of energy sources including domestically-produced natural gas and
power supply/demand balance taken into consideration.
Power System Master Plan 2016
Final Report
2-2
2.1.3 Strengthening of integrated statistical processing functions
BPDB has a record of electricity sales to its customers and those wholesaling to other distributing
companies. The total sum of them is the total volume of electricity sold by BPDB, but is not identical
with the total volume of electricity that is sold by distribution companies including BPDB and used by
end consumers. For analyzing the trend of electricity consumption in Bangladesh more specifically,
grasping the electricity sales of all distribution companies to end-consumers with sectorial breakdown,
such as residential, commercial, industrial etc., is more important. Power Division and/or BPDB is
suggested to take an initiative to develop a database of nationwide electricity consumption uniformly
as a routine.
The JICA Study Team also observed that there is no government agency responsible for grasping how
each sector (residential, commercial, industrial, transport etc.) utilizes energy as the combination of
various sources of energy supply such as electricity, natural gas, LPG, oil products, non-commercial
fuel (bio fuel) etc. When the JICA Study Team interviewed with various organizations, there were
some opinions that, in order to mitigate the increase of natural gas demand, new supply of natural gas
to residential sector and transport sector should be restricted and these sectors should be induced to use
LPG instead. However, if this idea is actually implemented without long-term perspective of energy
supply and demand, it may result in the rapid increase of LPG procurement that is apt to be costlier
than LNG, and the burden of nationwide energy cost may become heavier. In order to realize the
long-term optimization of nationwide energy balances, GoB needs to strengthen the function to
consider and coordinate the national energy policy comprehensively. Although it should be the Government of Bangladesh that decides which organization is to be responsible
for performing these integrated statistic processing functions, the Survey Team recommends the
establishment of Integrated Statistics Bureau in MoPEMR for the centralized management of all the data
from the organizations under the jurisdiction of the Power Division and the Energy Division with the need
to revise the power and energy master plan periodically taken into consideration.
2.1.4 Introduction of Key Performance Indicators
Furthermore, GoB is suggested to set appropriate KPIs (key performance indicators) in the process of
planning and to set quantitative target based on this, in order to indicate clearly the directions of
energy policy of Bangladesh. Above all, as the country’s energy demand is expected to increase
rapidly, target setting for rationalizing energy supply and demand (energy efficiency) is indispensable.
In addition, strengthening the capacity to analyze the effect of conditional changes on these KPIs and,
if necessary, to adjust the targets and plans flexibly to reflect the changes is also required.
Examples of KPIs that serve for target-setting for the power and energy sectors are as follows.
Energy efficiency: energy intensity per GDP (toe/million BDT), GDP elasticity of energy
consumption etc.;
Economy: cost per unit of energy supply (BDT/kWh) etc.;
Environmental consideration: emission factor of greenhouse gas etc.;
Stable supply of energy: energy security index (dependence on energy import, diversification of
energy sources), average frequency and duration of power interruption (SAIFI, SAIDI) etc.;
Optimized supply of energy: balance of aforementioned 3E (integrated indicator), composition of
energy source mix etc.;
Currently the main stakeholder agencies in Bangladesh do not have sufficient organizational and staff
capacity to deal with these new challenges and international support for improving the capacity of
planning, policy implementation and monitoring/evaluation is also needed. Japan has also provided
various kinds of assistance such as the dispatch of policy advisors, training programmes and capacity
development support programmes. These kinds of assistance will still be needed for Bangladesh.
2.2 Measures to Facilitate Improvement of Investment Climate
Power System Master Plan 2016
Final Report
2-3
2.2.1 Outline
As a rapid economic growth is expected in Bangladesh, a power development plan has been
formulated to reinforce power generation facilities to meet the increasing power demand. However, as
the construction of power generation facilities has not been progressing as planned in reality, as
mentioned in detail in the chapter of the power development plan, the demand has been suppressed
due to the limited supply and, therefore, the difference between the actual demand and the demand
projection including potential demand has been large. This fact may have undeniably had negative
impact on the economic growth in Bangladesh.
It is obvious that the milestones in a power development plan, however theoretically the plan may
have been formulated, will be just empty theories in the current state in which various factors impede
the construction of power source facilities.
Therefore, a discussion conducted on the way to create a climate that makes investment in power
development attractive with opinions of investors taken into account is described in the following.
Source: JICA Survey Team
Figure 2-1 PSMP2010 Review (Power Development Plan)
2.2.2 Project Implementation Structure
In addition to conventional loan projects implemented with public financing from international
organizations, projects with PPP investment that utilize the technological capacity and capital of the
private sector more than the loan projects are considered a promising means of power development in
Bangladesh. The figure below shows a possible project implementation structure assumed for the
implementation of IPP projects in Bangladesh.
Sponsors
Government of Bangladesh
Power Purchase Agreement
BOT Contract
Investment Certificate
Fuel Supply Agreement
EPC Contract
Special Purpose Company (SPC)
Gov. Guarantee
BPDB Power Cell BIDAPower Div.
EPC
EPC Contractors
Fuel Supply
Fuel Suppliers
Sponsor
Equity
Lender
Debt
Lenders
Power System Master Plan 2016
Final Report
2-4
Source: JICA Survey Team
Figure 2-2 Organaization of IPP
The sponsor of a project consisting of a contractor and an investor usually minimizes the project risk
by establishing a special purpose company (SPC) and concluding contracts with various organizations
to be involved in it through the SPC. The major project risks are summarized in the following.
Risks directly concerned with the Government
Risks associated with power sales agreements and payment of electricity charges
Foreign exchange and remittance risks
Country and political risks
Risks to be controlled mainly by contractors
Risks of delay and cost overrun
Risks in fuel procurement
O&M risks (including risks in the construction of power transmission, transforming and
distribution facilities)
2.2.3 Risks directly concerned with the Government
In Bangladesh, an SPC and BPDP conclude a power purchase agreement (PPA) and the SPC becomes
the only off-taker of the power under the PPA. Because this agreement provides long-term security, in
principle, investors consider it an important agreement that promises profitability of their investment
in the project life. Investors prefer a large proportion of the payment for electric power to be made in
foreign currencies, while the investee prefers a large proportion of it to be made in the local currency,
as they collect electricity charges from users in the local currency. This proportion of the payment in
foreign currency has significant influence on investors’ decision on investment. If there is a restriction
on foreign exchange applicable to a case in which a SPC exchanges the profit from a project after
deducting the local costs that it has saved in the local currency in a foreign currency and remits it to
the country of the investor, such a restriction will also be an obstacle to the investment.
Power Division applies for the licenses and permits for the establishment of SPCs and construction of
facilities with a consent of Power Cell and applies for a government guarantee with a consent of the
Ministry of Finance. All the permission and licensing for investment in foreign currencies used to be
controlled by the Board of Investment, Bangladesh, (BOI). However, it is currently controlled by
Bangladesh Investment Development Authority, which was established recently as a one-stop center
for foreign investors. The government’s efforts in reorganizing itself in accordance with the needs of
investors such as the case mentioned above should be highly appreciated. A contractor for the
implementation of a project with foreign investment is required to be established as a joint venture
(JV) of a foreign investor and a local partner, and a foreign investor is not allowed to participate in
such a project as its sole investor in many countries, including Bangladesh, in order to facilitate the
development of domestic and local industries.
Successful project implementation naturally requires strict compliance with agreed rules and
provisions of the agreement, which requires minimization of the country and political risks as the
major precondition. These are the risk factors in the agreement directly concerned with the
Government.
2.2.4 Risks to be controlled mainly by contractors
The risk of delay and cost overrun is a risk to be hedged by contractors. The conclusion of an EPC
agreement between a SPC and an EPC contractor is a means to hedge such risk. The risk in fuel
procurement, which may emerge in different forms in different projects, is considered a risk to be
controlled by contractors. The O&M risk is also considered a risk to be controlled by contractors.
There is a risk that power may not be transmitted as planned when the power source facilities have
been constructed and put in use as planned, if a project for constructing transmission lines and
substations is delayed by various factors. If such a project is not in the scope of the investment in the
power source development of an investor, it is considered extremely difficult for the investor to control
the project concerned. Therefore, a mechanism that places the responsibility for the consequence of
the delay of the project to its contractor has to be established.
Power System Master Plan 2016
Final Report
2-5
2.2.5 Recommendations for Improvement
PPA
A PPA will stipulate the standards of tariffs that sufficiently accommodate various risks associated
with foreign exchange and international remittance. The privileges to receive electricity tariffs in US
dollars and transfer the revenue in dollars received from the sale of electricity overseas without
restriction will be granted to investors.
Tax exemption for FDI
The tax exemption to be granted will include exemption from the customs duties on all the imported
materials and equipment required for the plant construction, exemption from the corporate and
personal income taxes for a certain period of time and exemption from the import tax on vehicles and
heavy and specialized equipment to be used by contractors.
Streamlining of procedures
It is not sufficient just to establish better rules. It is also necessary to reduce the time required for the
issuance of licenses and permits.
Credit enhancement to local enterprises by international organizations A tripartite relationship of the political system, bureaucracy and private sector led by a local
large-scale company has been formed in many of the successfully implemented IPP projects in
Bangladesh. A foreign investor must form a JV with a local investor if the foreign investor intends to
implement such a project because there is a law that does not allow purchase of land solely with a
foreign currency in Bangladesh. Therefore, such a project will be implemented as a long-term joint
investment project with a local company to ensure steady cash flow into the project and the financial
credibility of such a local company may have significant influence on the decision of a foreign
investor. For example, an international organization will enhance credit limit of a local company as a
guarantor of its credit in order to improve its credibility in the local industry sector in a scheme to
implement large-scale IPP project as a “model PPP project.” In practice, a mechanism that guarantees
the payment of fees by guarantor in the case of breech of a provision in a PPA and fully covers damage
to a developer will be established.
Power System Master Plan 2016
Final Report
2-6
2.3 Economic Development
It has to be noted that the aforementioned economic projection is based on the assumption that the
Government of Bangladesh (GoB) will implement appropriate policy measures for economic
development. Currently, the economic development in Bangladesh is mainly driven by the steadily
increasing export of ready-made garment (RMG) industry that takes advantage of low cost of labour.
For achieving mid- and long-term economic development, it is indispensable that the national
economy will shift from labour-intensive industries like RMG to more value-added industries, and it is
necessary that policy support to promote these new industries.
Examples of policy support are the provision of incentives for promoting foreign direct investment
(FDI) from overseas and the development of infrastructure like special economic zones. An example
of soft measures to promote the development of high value-added industries is a capacity development
programme for human resources in the industrial sector to help advanced technologies to take root in
Bangladesh industries.
Following these observations, policy recommendations about economic development policy is
summarized as follows.
(1) Infrastructure Development
1) Short term
In order to promote the high value-added of manufacturing, especially the advancement of industries
through the attraction of FDI, development of fundamental infrastructure is indispensable, such as the
utility structure like electricity, gas and water, and the public transport infrastructure for distributing
materials and products. And the development and integration of production base that is equipped with
these infrastructures is supposed to be the key factor of success. In addition, provision of incentives
such as the waiver of tax and duty for mitigating the financial burden of huge amount of capital
investment is also an effective tool. Development of production bases to promote these industries,
such as EPZs (Export Processing Zones), SEZs (Special Economic Zones) and industrial parks is
strongly desired.
In Bangladesh, development of PEZs started from 1980s for promoting export industries and currently
right PEZs are in operation under the supervision of Bangladesh Export Processing Zones Authority
(BEPZA). In addition, Bangladesh Economic Zones Authority (BEZA) was established in 2010 for
fostering the development of SEZs eyeing for the diversification of Bangladesh industries. According
to the JICA Survey Team’s interview on BEZA in February 2016, there exist about 60 project plans of
SEZs and BEZA has a target of developing 100 SEZs in 15 years. In order to realize these plans and
targets effectively, this study suggests that a programme to develop the capacity of planning and policy
implementation for government agencies like BEZA is also needed, which shall be discussed more in
detail in the next section.
2) Mid/long term
Development of fundamental infrastructure for promoting industrial development may have
limitations only with the “point-wise” development like SEZs, PEZs and industrial parks. Connecting
these points into a trunk line, and then into a wide area, will enhance its effectiveness. Furthermore,
improving the convenience of connection among production bases will also help improving the
efficiency of supply chain in a manufacturing process and contribute to the “Banglazation” of supply
chain of export industries (self-containment of value chain from material to final product).
From this point of view, it is strongly recommended to prepare plans of comprehensive wide-area
infrastructure development that cover seaports, roads, railway, and energy supply and etc., and to
implement these plans steadily.
Power System Master Plan 2016
Final Report
2-7
In addition, reforms of economic structure will be indispensable for achieving long-term economic
development, such as further deregulation and liberalization of industries for simplifying the licensing
process and for enhancing the mobility of human resources and capital funds.
(2) Capacity Development
1) Short term
In order to promote the development of manufacturing bases for the advancement of manufacturing in
Bangladesh, such as SEZs, EPZs and industrial parks, it is necessary to make effective and realistic
plans of development and to implement them steadily.
Because the skills and experience of government agencies responsible for that may not be sufficient to
fulfill this, capacity development programmes to support this are also considered to be necessary.
Japan has provided assistance to Bangladesh in this field, such as “The Project for Development Study
and Capacity Enhancement of Bangladesh Economic Zone Development Plan Authority” (2015-2016)
and “Study and Verification Survey on the Comprehensive Development of Southern Chittagong
Region in Bangladesh” (2015-2016) that are sponsored by JICA. Technical support from abroad like
that will help enhancing the capacity development of government administration.
2) Mid/long term
For the long-term sustainable development of Bangladesh economy through the advancement of
industries, an overall bottom-up of human capacity in the industrial sector is essential. Examples of
supporting programmes are the establishment of facilities for technology education/training and the
project to assist the efficient acquisition of technologies through OJT (on-the-job training).
2.4 Domestic Natural Gas [Gas]
(1) Infrastructure
Gas production from existing gas field will be peaking out in 2017-18 and declining, while gas import
in a form of LNG is forecast to increase significantly in near future. Under the circumstances issues in
terms of infrastructure development to be reviewed and studied are as follows:
Domestic gas price will be linked with international gas price and more strict control and
monitoring of gas in/out flow will be required to avoid “lost profit opportunities”, and system loss
and/or leakage from the system should be minimized.
Gas flow will be changed from the east-west current to the south-to the rest of the nation, The
large amount of imported gas will be coming from Maheshkhali and/or Payra. Gas transmission
infrastructure will need to be reinforced and existing distribution system will also need to be
reinforced and re-constructed.
Operation mode will be shifting from “Gas Allocation” basis to “Customer Demand” basis, and
required to supply gas to meet the profile of each customer’s demand. Current supply system
needs to be reviewed.
Currently the three layers organizations are involved in gas supply, i.e., Gas Production Companies
(BAPEX, BGFCL, SGFL etc.), Gas Transmission Company (GTCL), and Gas Distribution Companies
(TGTDCL, BGDCL, JGTDSL, PGCL, KGDCL, SGCL). There is no integrated operation system
since there is no necessity under gas allocation system at this stage
In order to solve the above listed issues the well-planned and systematic approach will be required.
Power System Master Plan 2016
Final Report
2-8
Industrial structure and lifestyle of people will be changing with development of economy. Role of gas
based electric power generators will be changing from base load generation to middle/peak shaving
generation, and numbers of new gas power plants will be constructed near metropolitan area (Dhaka).
Gas infrastructure should be planned and installed to coincide with those power plant installation
plans.
The most important is that Gas Sector and Power Sector should work together by organizing working
group jointly and share issues and determine exact location of the power plant, and associated power
grid and gas supply infrastructure.
On completion of gas and/or power infrastructure, more sophisticated operation system need to be in
place and trained operator and maintenance personnel need to be ready for work. However, this
capacity building task might not be easy. Assistance from Japan could be constructing and operating
an “electronic gas infrastructure” which supports operation and maintenance of the infrastructure
facilities, and transfer the system to the operating company at later stage (BOT). With this approach,
project schedule will be shortened and more time can be used to train the staffs.
1) Short term
Most part of gas infrastructure will not be visible from surface because they are buried underground.
Location of each gas piping components need to be identified by linking with GPS. First of all,
object orientated advanced electronic mapping system need to be introduced, combined with
appropriate SCADA (Supervisory Control and Data Acquisition) System. By this arrangement,
Advanced Control, Preventive Maintenance, Operation Safety, Emergency Transaction, and Asset
Management, will be attainable. Such system can be constructed and operated by Japanese entities and
transferred at later stage (build-own-transfer: BOT). Technology transfer will be easily implemented
under this proposed scheme.
Source: JICA Survey Team
Figure 2-3 Advanced Electronic Mapping - Object Model System
2) Mid term
As the imbalance of demand-supply situation improves with the increase of import LNG, operation
mode is changing from “Gas Allocation” to “Customer Demand” basis. Gas supplier is required to
supply gas to meet the demand profile of each customer. Gas supply source will be diversified. In
addition to domestic gas, introduction of LNG via FSRU and/or Land LNG terminal and pipeline gas
from India will be starting shortly. Gas customers will also be diversified with development of the
economy. In order to manage such changes integrated supply system and central operation unit will
Power System Master Plan 2016
Final Report
2-9
need to be constructed. Current gas supply organization may need to be reviewed and re-organized.
Introduction of IT is accelerated in future and operation system will be improved and need to be more
flexible based on advanced data acquisition, processing and control system. JICA has assisted in
introducing pre-paid gas meter to domestic users as part of yen-loan financed project. This system
would be integrated into part of IT system in future.
(2) Human capital development and supporting organization (capacity building)
1) Short term
Currently, it is understood that the numbers of gas leak incidents are reported daily (details are not
precisely understood at a gas distribution company). Most of which presumably are caused by poor
maintenance, use of low grade materials, and/or poor construction practice. To enhance the reliability
and integrity of the gas infrastructure system, it is necessary to set up design standard (such include
piping material standard, standard construction drawings), construction work procedure and
maintenance/safety procedures.
In order to bring up staffs who are able to manage advanced operation and maintenance of gas
infrastructure, knowledge and skill based qualification system should be introduced. Personnel system
may also need to be reformed.
2) Mid/long term
In addition to manage advanced operation and maintenance of gas infrastructure, managers are
required to promote efficient use of gas. Wide range of knowledge and practical skills are required to
be a manager. It is important to bring up internationally recognized professional engineers in the
organization. Professional engineers will take such responsibility as they are seen in major oil
companies and utility sector of advanced countries. Chartered Professional Institution in UK may be
able to support the education and training programs.
Responsibility of such engineers will be extended to prepare operation and maintenance manuals to
suit by themselves.
Power System Master Plan 2016
Final Report
2-10
2.5 LNG Import [Gas]
FSRU Project is under progress and study of land based LNG terminal project has also started.
However, each has its own characteristics and need to understand the differences. Prior to develop
LNG project, following matters need to be taken into consideration:
Price formula of LNG Long term Take or Pay contract
Use of LNG spot market
LNG Freight and tanker size
Storage/gasification service fee
Construction schedule and risk
Operational risk and energy supply security
Construction schedule of FSRU is 3years at the most and construction risk is considered low, and
therefore FSRU is considered reliable source of supply. LNG supply to FSRU will be based on “take
or pay” and risk of “quantity” should be beard by Bangladesh. FSRU require more than 60 times of
LNG delivery by shuttle tankers. Operation of FSRU is vulnerable to Cyclone and/or rough wave
conditions because of ship to ship transfer operation of LNG.
Land based LNG terminal will play a role of supply optimization between supply and demand. It also
plays important role in securing energy supply if it is used as a strategic storage, and considered
inevitable energy infrastructure in Bangladesh. Compared with FSRU, freight unit cost will be lower
since larger vessel such as Q-Flex and Q-Max class can be used to deliver LNG. Initial storage and
gasification service fee is higher since it should support the initial infrastructure investment cost,
however the fee will be lower and competitive with the expansion of storage capacity to meet the
increasing demand. Construction will take 7-10 years to complete before commencement of
commercial operation.
LNG terminal operation will be assigned to RPGCL (CNG & LPG Company), if it is planned by
Petrobangla (a LNG terminal project under Power Cell and BPDB supported by IFC would be
operated by different scheme. Further detail is described in the “LNG” Chapter). Gas produced at the
LNG terminal will be handed over to GTCL (Transmission Company) and transmitted and handed
over to Distribution Companies for supplying to customers. Gas allocation system worked under such
system for long time.
Once large amount of gas is started to be delivered from LNG Terminal, gas allocation system will
need to be changed to new delivery system, i.e., customer demand based supply system. This new
supply system will work under integrated operation system connecting among LNG terminals,
transmission lines, and gas distribution systems. Central operation unit with the task of controlling and
monitoring all the in/out gas flow will need to be constructed. Current organization may need to be
reviewed and restructured.
(1) Infrastructure
1) Short term
Industry of Bangladesh has suffered from shortage of gas supply and adversely affected economic
growth of the country. The first FSRU should be constructed soonest and associated transmission line t
as well. Design of current transmission line under construction is 90 km long, 30 inch diameter with
pressure rating of #600, capable of transmitting 500-700 mmcfd at normal operating pressure of 900
psig. However, this pipeline is considered too small to accommodate further future gas delivery. New
transmission system should be studied by the working group organized jointly between Gas Sector and
Power System Master Plan 2016
Final Report
2-11
Power Sector, and share issues and determine future delivery plan.
Advanced gas supply system can work only under the sophisticated pressure/flow control system.
Changing pressure of the transmission pipeline system may adversely affect performance of
condensate recovery unit at gas field, as well as the operation performance in the downstream
distribution. This potential impact needs to be investigated further.
2) Mid/long term
Land LNG terminal require 7-10 years to construct. It will play a role of supply optimization between
supply and demand. It also plays important role in securing energy supply if it is used as a strategic
storage, and considered inevitable energy infrastructure in Bangladesh. LNG storage capacity will
continue to increase with the increase of demand. Gas transmission and distribution infrastructure will
also be reinforced and expanded. Mid/long term plan should be prepared to minimize future cost and
avoid duplication of works. Joint working group between power and energy sector to be organized for
this purpose also.
(2) Human capital development and supporting organization (capacity building)
1) Short term
On completion of gas infrastructure, operation system needs to be in place and trained operator and
maintenance personnel need to be ready for work. Assistance from Japan could be constructing and
operating an “electronic infrastructure” which supports operation and maintenance of the
infrastructure facilities, and transfer the system to the operating company at later stage (BOT). With
this approach, project schedule will be shortened and more time will be used to train the staffs.
2) Mid/long term
As stated in the previous paragraph, it is important to bring up internationally recognized professional
engineers in the organization. Professional Engineers will take responsibility of managing advanced
operation and maintenance of gas infrastructure, and promote efficient use of gas. Major oil companies
and utility sector of advanced countries relies on their operation on this type of people. Chartered
Professional Institution in UK may be able to support the education and training programs.
Responsibility of such people will be extended to prepare operation and maintenance manuals to suit
by themselves.
Power System Master Plan 2016
Final Report
2-12
2.6 Renewable Energy [Introduction of energy storage technology]
(1) Infrastructure
Integrating intermittent renewable energy resources, such as PV and Wind generation, to achieve CO2
emission reduction is a priority task for most countries worldwide. However, such renewable
resources have high initial cost, low utilization rate and intermittent generation. Therefore, when
integrated into the grid in large scale, they could put system frequency and voltage stability in
jeopardy and cause technical problem.
On the other hand, in parts that have no access to the grid (off-grid areas), Solar Home System (SHS)
or small-scale diesel generation provide electricity. However, SHS are expensive and cannot supply
more than 3 to 4kW, also small-scale diesel generators have fuel running cost in addition to the initial
cost. Therefore, off-grids areas have not only high failure rate but also a very high electricity cost.
To address such issues, increasing renewable energy integration while maintaining electricity supply
stability, large-scale and safe energy storage technology is proposed as a supporting measure, and a
practical introduction is highly expected.
Source: JICA Survey Team
Figure 2-4 Introduction of energy storage technology (1)
1) Short term
Improved grid stability through integration of large scale and safe energy storage system
As mentioned above, in case of integrating large scale intermittent renewable energy sources
in power system, frequency and voltage fluctuations are anticipated.
Up to now, hydro pumped-storage units have been utilized to solve the above issues, however
considering required construction cost, time and area, large scale energy storage systems have
superior characteristics for absorbing power system fluctuation by electrical energy charge and
discharge. Therefore, such solutions are being closely focused in North-America. A pivotal
point in realizing large scale energy storage systems is its safety.
Considering above mentioned conditions, it is proposed to have a demonstration project F/S in
order to connect safe large scale energy storage system to grid, develop operation and control
technology and evaluate the integration effect.
Realizing safe, low cost and environment-friendly Off-Grid energy supply system through
integration of large scale energy storage system In remote areas that don’t have access to grid (off-grid), energy storage can be used to replace
SHS and diesel generators through community energy schemes instead of providing energy
system for each individual house. (Medium to large scale solar systems + large scale energy
storage system for community). Using such scheme, it might be possible to addressee above
mentioned issues. Therefore, F/S for evaluating the system integration effects is proposed.
50/60Hz Thermal &
Nuclear
Power
Home → Smart home Building → Zero Energy Building Factory → Smard Factory
EV Battery Fuel cell
RE
Increasing RE integration
< Frequency Fluctuation Image > < Solar Home System (SHS) >
Power System Master Plan 2016
Final Report
2-13
Redox Flow battery is one of the most well-known large-scale and safe energy storage technologies.
Some of the application samples can be shown as follows.
[1] Improved grid stability
METI’s demonstration project from FY 2013 to FY2018
Installation site : Minami-Hayakita Substation at Hokkaido Electric Power Co., Ltd
Sytem : Redox Flow battery system 15 MW / 60 MWh
Application : Frequency regulation (Short duration)
Surplus power adjustment (Long duration)
Source: JICA Survey Team
Figure 2-5 Introduction of energy storage technology (2)
[2] PV + Large-scale energy storage
Sytem : Redox Flow battery system 1 MW / 5 MWh
Application: Storage of PV surplus generation, PV output stabilization, etc.
Sysytem appearance
Source: JICA Survey Team
Figure 2-6 Introduction of energy storage technology (3)
PV output
Battery output
Total output
PV output
Battery output Scheduled output
< System appearance > < Demonstration image >
WF output
Redox Flow battery
PV output
Dispatch Center
Dispatch
Freq. Discharge
Charge
Power System Master Plan 2016
Final Report
2-14
2) Medium term
Introducing large scale energy storage based on the F/S results
(2) Human capital development and supporting organization (capacity building)
1) Short term
Training for operators and creating operational manuals
It is important for the large scale energy storage operator to have a sound knowledge about functions,
responsibilities, operation and maintenance, economics of the systems and etc. Together with the
above mentioned F/S study, there would be a training for the large scale energy storage operators and a
manual would be provided form the achieved operation know-how. This will layout foundation for
safe and low cost energy supply as well as suitable O&M support in Bangladesh.
2) Medium term
Creating ancillary service market foundation The need for ancillary services and large scale energy storage systems would be increased due to the
expansion in renewable energy resources. To correctly evaluate this value and realize suitable balance of
energy resources, creation of an ancillary service market would be necessary.
2.7 Power System Plan
(1) Infrastructure Arrangement
1) Transmission Plan
The projects listed in the table of on-going projects made by PGCB will be steadily implemented.
The funding sources should be identified soon for the projects that have not yet been funded, such as
the expansion and strengthening of the network in DESCO’s management area (400kV GIS
substations and 230kV substations). Regarding the projects for the bulk power transmission system
related to interconnections, such as Barapukuria, their funding sources should also be identified in
adequate time, in cooperation with the progress of the discussions with the related neighboring
countries. Regarding the projects for the transmission lines for power transmission from the large scale
power stations in south Chittagong and Khulna that are identified in this MP, their FSs are
implemented accordingly at suitable timings in order to match the construction schedule and urgent
selection of the routes for transmission lines.
2) Rural Electrification
The projects listed in the table of on-going projects made by BREB will be steadily implemented. In
the process, it is important that a distribution system which aims at high reliability in the future is
constructed efficiently.
(2) Strong Institutional Arrangements
1) Transmission Plan
PGCB takes on the role of making plans for bulk power transmission lines and substations. Although
consistency among the bulk power network plans and power demand forecasts, power generation
plans and power distribution plans should be ensured, these plans and conditions are set by
organizations other than PGCB. The power demand forecast for the whole of the nation is made by
BPDB and the regional ones are made by power distribution companies. Power generation
development plans are made by BPDB under the management of Power Division in MoPEMR. The
power distribution plans are made by distribution companies such as DSCO and DPDC.
The results of the plan for the bulk power transmission system made by PGCB are reflected in the
power transmission and distribution plans made by distribution companies and become the conditions
for planning the 132kV system. The appropriate feedback should also be given to BPDB and Power
Power System Master Plan 2016
Final Report
2-15
Division in MoPEMR on the power network plan made by PGCB, in order to reflect its results and
correct information in the Government to Government projects. The following countermeasures
should be implemented.
The institutional frameworks should be established among BPDB, Power Division, Distribution
Companies and PGCB to share the necessary information periodically in order to make the power
network system plan.
The reports on the power network system plan are published periodically (every half-year or
annually) to share information on the status of making the plan among the abovementioned
related organizations. PGCB reports on the future projects for transmission lines and substations
required, from its technical viewpoint, to BPDB, Power Division and distribution companies.
The rules for power network system planning should be clarified, published and open to the
public as a part of the Grid Code.
2) Rural Electrification
In this sense, a good communication and coordination between BREB and IDCOL is required;
however, it is observed that such communication or coordination is not taking place. IDCOL is
communicating to BPDB for project planning, but BPDB seems not liaising with BREB properly. If
the Government seriously pursue the achievement of “Electrification for All” by 2021, the good
communication and coordination between BREB and IDCOL must be taken, and both parties (and
BPDB as a coordinator too) need to improve in this area.
2.8 O&M Legal Framework [O&M]
(1) Human capital development and supporting organization (capacity building)
1) Short term
The Bangladeshi government would organize a specialized committee which legislate some act related
O&M.
In terms of short term, the suitable method of bringing up talented person in specialized committee
would be that they study to development some laws related to O&M under the specialist's instruction
after the specialist for making O&M act in developed country, like Japan, invited from overseas to
Bangladesh.
It is highly likely to be difficult to enact laws and regulations mandating regular inspection and to
establish a system for the supervision of the facility maintenance by authorities in a short period of
time. It is worth studying the feasibility of taking proactive measures such as introduction of various
regulations and technical standards for the maintenance of power generation facilities used in Japan as
the standards for the maintenance of power plants in Bangladesh and maintaining the plants using the
introduced standards before the enactment of all the required laws and regulations. It is recommended
that the power plants to be constructed, in particular, be operated in accordance with a schedule that
includes the schedule for the maintenance from the beginning of their operation.
2) Mid/long term
In terms of mid-long term, one of solutions developing human resources is that the members of
legislation committee would be dispatched to developed foreign country to learn the real O&M legal
framework and actual situation of O&M in a power plant, and the members might bring back
knowledge of the useful laws to Bangladesh. In addition that is better to continuous study the
operation status of power plant in developed nation, and also research the history of O&M act
reformation, that would become to good samples for Bangladeshi O&M act.
Power System Master Plan 2016
Final Report
2-16
2.9 Thermal Power Plant O&M [O&M]
(1) Infrastructure
1) Short term
In the short term, we consider that enhancement of power generation capacity is a priority in order to
meet the demand growth and requirements from the industrial sectors. In particular, some of the aging
power facilities need to be replaced with, or converted into higher efficient units. The study team
proposes two plans as power plant remodeling plans. One is a rehabilitation plan for old steam
turbines which were built by Russia. The other consists of three different levels of conversion into
combined cycle units. Those plans can be implemented with proven technologies of Japanese
engineers.
Source: JICA Survey Team
Figure 2-7 Steam Turbine Rehabilitation Plan
Source: JICA Survey Team
Figure 2-8 Combined Cycle Power Generation Remodeling Plan
Power System Master Plan 2016
Final Report
2-17
2) Mid/long term
Those proposals mentioned above can be a quick solution to the power shortage problem of Bangladesh for
a short time period. After the completion of the remodeling works, application of proper maintenance is a
key to successful capacity enhancement.
(2) Human Capital Development (capacity building)
1) Short term
In addition to measures to reinforce the capacities of power generation facilities, preventive
maintenance of these facilities was considered important for the maintenance of their capacities and
the maintenance and improvement of their operational efficiency in this survey. It is necessary to train
maintenance engineers for the appropriate implementation of regular inspection as part of preventive
maintenance. A study will be conducted on the possibility of establishing an independent organization
specialized in the maintenance and repair of the facilities and using the human resource development
service of this organization as a measure to cope with the problems of the shortage of the maintenance
personnel and budget at the state-owned power generation facilities.
In general, the scarcity of skilled engineers undermines operational efficiency and lack of maintenance
of facilities. To cope with this problem, the survey team suggests a training facility with equipment
and materials which are actually used in power facilities, like a power plant silulator. While most of
the trainings are carried out in a traditional classroom setting in Bangladesh, the proposal puts an
emphasis on the practical exercises by using effective training materials. The proposed training has
two main courses, one of which is a course for plant operators, and the other is a course for
maintenance engineers. Both courses lead to certifications in the respective areas of the education. The
proposals include the facility and training items described below.
A further study will be required before deciding whether such training will be provided by an
independent organization to be established or by each power company.
Source: JICA Survey Team
Figure 2-9 Training Course Plan
Power System Master Plan 2016
Final Report
2-18
2) Mid/long term
The training courses should be extended to higher levels of education for instructors. In the short term,
instructors can be provided from other organizations; however, a scarcity of instructors will be the
biggest problem in the future. In order to fill the gap between training demands and instructors
provided, skilled workers at operating facilities can be utilized. A workforce rotation program should
be introduced to enable new employees to learn from the skilled workers who have experiences with
the actual equipment, while the career development plan for the instructors motivates them to take a
leave from their positions at their power facilities. The introduction of job rotation is recommended as
a measure to provide new employees with the opportunities both at power plants and at training
centers to learn the practical work performed in power plants from engineers who have ample practical
working experience.
(3) Thermal Power Plant O&M Information Management
1) Short term
After the completion of the development or enhancement works of power facilities, it is important to
maintain their capacity and efficiency. The objective of the organization-wide information
management system is to facilitate maintenance planning, budget control and procurement
optimization. The functions of the system include the following.
Maintenance Planning - To encourage plant managers to make feasible plans for maintenance.
Budget Management - For prompt decision making on financial matters and reduction/removal of
delay in maintenance activities.
Maintenance Work Management - To keep maintenance projects within budget and timeframes.
Failure History Management - To provide supporting data for budget and plans.
Expected results (Quantitative Effects) are:
Reduction of maintenance cost
Reduction of frequency of forced outage
Reduction of forced outage hours
In order to maximize the effectiveness of implementation of information management, a feasibility
study is expected to be carried out in pursuit of the following information items.
Table 2-1 Items Required in Feasibility Assessment
Category Item Details
Computer
System and
Network
Infrastructure
Plant LAN Local Area Network availability in power plants
Enterprise network Network availability, connectivity among business units and
multiple locations, and its security, reliability and capacity.
Data repository Data center location, storage capacity and scalability
Legacy systems
and data integration
Legacy systems and legacy data.
Management Business process Business processes in Maintenance Planning, Budget Creation,
Procurement, Work Planning, and their business requirements.
Regulations and
standards
Regulations, standards, public authority reporting guidelines.
Target
Selection
Facility
Requirement
Facility type/age/capacity, location, future plans for
enhancement or replacement
Connectivity between facility and data acquisition devices
Source: JICA Survey Team
Power System Master Plan 2016
Final Report
2-19
The Information Management System connects the head office with power facilities and other related
organizations such as Maintenance Center and Training Center. These organizations share facility
information for analytical use which brings the power facility higher efficiency and reliability based
on accumulation of historical data.
Source: JICA Survey Team
Figure 2-10 System Functions and Data Flows for a Power Plant in Bangladesh
2) Mid/long term
The scope of the Information Management System can be extended to Facility Management and
Environmental Management. The functions of the system may contain:
Facility Assessment - To optimize maintenance cost based on physical state of facilities.
Procurement Management - To maintain spare inventory levels while reducing procurement cost.
Tariff Management - To provide an accurate cost basis for appropriate pricing of electricity.
Environmental Management - To ensure regulatory compliance while managing environment
related cost.
Expected results (Quantitative Effects) are:
Reduction of Total Ownership Cost of facilities
Reduction of fuel cost
Reduction of emissions, effluents and waste products
Contribution to effective tariff setting
(4) Organization (capacity building)
1) Short term
To perform facility maintenance activities in compliance with laws and regulations, auditability of the
work processes and work results, such as facility inspection reports, must be achieved. Maintenance
crew must be familiar with the designated documentation and records, which need to be prepared in an
accurate and timely manner when requested by the authority.
The maintenance planning processes require some knowledge in project management. Maintenance
managers will be advised to learn work process management and budget control.
Apart from the above, the information assets need to be properly maintained and protected. IT/ICT
Power System Master Plan 2016
Final Report
2-20
engineers are expected to keep the system fully operational; therefore, IT/ICT education is also
important.
2) Mid/long term
As described in Chapter 19, the goal of this Study is to achieve a best practice in O&M in the power
sector. Major power producers in Japan make use of a wide variety of software applications in daily
operations of their facilities; however, their common focus is to maintain reliability of the facility with
optimal cost. In the future, the education for plant workers may cover wider area which is more
management oriented in terms of efficient use of organizational resources.
2.10 Tariff policy
(1) Human capital development and supporting organization (capacity building)
1) Short term
For implementing appropriate tariff policy including electricity tariff increase and gas price increase,
capacity building for appropriate decision making of price level in consideration of accurate supply
cost is required. Therefore donors are expected to provide capacity building support for BERC. In fact,
ADB is considering to support BERC for capacity building. In addition, for grasping accurate supply
cost, support of capacity building for each organization to develop sophisticated management plan is
also important. Hence for enabling organizations such as BPDB to develop more sophisticated
management plan and implement it, donors should support corporate management capacity building in
them. Donors are expected to support BPDB, etc. to analyze financial situation in more detail, identify
inefficient points, and remedy them.
2) Mid/long term
Above-mentioned support is expected to be continued until appropriate tariff level and ideal financial
situation of BPDB, etc. are achieved.
2.11 Realization Of Low Energy Consumption Society
The target of energy projects in the developing countries is “stable supply of energy and electric power
that meets the increasing demand for energy for the economic growth.” Therefore, they will need
continuous power development. Meanwhile, the results of the analysis of the relationship between the
economic and social activities and energy consumption was used for the projection of energy demand
in the formulation of the supply plan in this master plan. The use of the technologies considered to be
highly reliable in 2016 was assumed in the formulation of the supply plan. However, the validity of
these assumptions is likely to change because the energy demand may not increase as projected and
more advanced power generation technologies may be developed in future. These changes will be
important factors to be investigated in the rolling monitoring of this master plan in future.
2.11.1 New Technologies for Power Generation with Different Energy Sources
The technological innovation in the energy and power sectors is advancing at a remarkable pace. A
technology in the research stage at the time of the formulation of this master plan may become
available for use in Bangladesh by 2041 with the progress of R&D in these sectors. The projects using
such new technologies are classified into the two groups mentioned below and explained in the
following.
(1) Energy Efficiency Project: EE
(2) Renewable Energy Project: RE
Table 2-2 Areas of research by type of energy
Power System Master Plan 2016
Final Report
2-21
EE
Projects for the improvement of energy efficiency (EE)
Power generation Power generation with the integrated coal gasification combined
cycle, etc.
Improvement and rehabilitation of
power generation facilities
Renewal of the facilities for the improvement of power generation
efficiency
Power transmission and
distribution
Establishment of power transmission and distribution facilities for
the improvement of energy efficiency
Activities for reducing power
transmission and distribution
losses
Renewal of the existing facilities for the improvement of energy
efficiency
Rural electrification
Conversion from the power generation with internal-combustion
engines to more energy-efficient power generation, transmission
and distribution facilities
Demand side management (DSM)
activities in the electric power
industry
Introduction of energy-saving systems for the reduction of power
consumption
ESCO activities Introduction of facilities and services for the improvement of
energy efficiency through the ESCO activities
Improvement of energy efficiency Research for the improvement of energy efficiency and the
development of energy-saving technologies
RE
Projects for power generation with renewable energy (RE)
Power generation activities
(use of renewable energy)
Implantation of power plants using solar, wind, hydro, and
geothermal energy and biofuel
Hybrid power generation activities Implantation of power plants that can be operated with both
renewable energy and conventional energy sources
Bio-energy activities Implantation of power plants using bioenergy including biomass,
biogas and biofuel for power generation
Decentralized Energy Production
& Distribution
Implantation of decentralized energy production systems using
renewable energy
Energy conservation Research on the energy conservation technology
Source: JICA Survey Team
2.11.2 New technologies in the electric power infrastructure sector
Table 2-3Areas of assistance in research in the electric power infrastructure sector
Classification Technology
Thermal power generation Integrated coal gasification combined cycle (IGCC) power generation
Renewable energy Biomass gasification power generation
Power generation using the methane gas generated by fermenting biomass
Power transmission and
transformation
Improvement of the power factor
Improvement of the power flow (increasing the number of transmission lines)
Increasing the diameter of power cables
Introduction of an upper level voltage (increasing the transmission voltage)
Superconducting cables
Superconducting transformers
Insulated strand cables
Use of low loss transmission cables
Power System Master Plan 2016
Final Report
2-22
Classification Technology
Power distribution
Distribution loss reduction technology (improvement of power factors:
reduction of lagging power factors)
Distribution loss reduction technology (low-loss distribution transformers, “Top
Runner Transformers”)
Distribution loss reduction technology (amorphous core transformers)
Distribution loss reduction technology (improvement of measuring equipment)
Distribution loss reduction technology (increasing the diameters of power
cables)
DSM
Heat pump technology (Heat pump hot water supply systems with CO2 natural
refrigerant)
Thermal storage air conditioning systems
Electric automobiles
Cogeneration systems (combined with thermoelectric systems)
Fuel cells (polymer electrolyte fuel cells: PEFCs)
Fuel cells (solid oxide fuel cells: SOFCs)
Energy conservation in
storage batteries
Power storage technology (load-levelling)
Energy conservation in battery cells
Superconducting magnetic energy storage system (SMES)
Source: JICA Survey Team
2.11.3 Responsible Energy Consumption and Development of Bangladesh into a “Developed
Country”
The record of energy consumption in Bangladesh in the past and the relationship between the
economic development and energy consumption in the countries in Southeast Asia, especially the
relationship in Thailand, in the past were used for the long-term projection of the energy demand in
Bangladesh in the formulation of this master plan.
There is no doubt that Bangladesh has to develop its economy further in future. On the other hand, it is
required to achieve the economic growth while saving the energy consumption (or, to achieve both
development and environmental conservation simultaneously). In the formulation of this master plan,
the 3E evaluation, more specifically, an analysis using the CO2 emission as a variable, of the power
development plan was used for the quantitative evaluation of its commitment to the environmental
conservation. If the environmental regulations in the international community become stricter and
more diversified, Bangladesh will have to endeavor to comply with them as a responsible member.
In addition, a “developed country” in 2041 may not be a large energy consumer like the developed
countries at present in 2016. Large energy demand has already been a condition for a developed
countrysation in the past. In fact, as mentioned in Chapter 5, the per capita energy consumption of
Bangladesh is smaller than those of Thailand, Indonesia and Vietnam. Meanwhile, the differences in
the per capita energy consumption between Bangladesh and the three countries are larger than the
difference in the per capita energy consumption per GDP between them. This observation indicates
that Bangladesh consumes a smaller amount of energy than the other three countries to create the same
economic value and that the economy in Bangladesh has grown with relatively small energy input.
Although the changes in the industrial structure expected in future are predicted to increase the energy
demand rapidly, Bangladesh can be proud of its more energy-efficient economic growth than the other
Asian countries.
Furthermore, the government and the people of Bangladesh to develop their country into a developed
country is to create an image of a “developed country” in 2041 including the scale of economy and the
lifestyle of people that they aim at, prepare an ideal way to use energy resource for economic
development that is efficient and energy-saving in the way like they have, as mentioned above, by
themselves and realize the ideal way in a responsible manner.