power system expansion and efficiency improvement ...construction of five 132/33/11kv substations in...
TRANSCRIPT
Semi-annual Environmental Monitoring Report
Project No. 42378-016 June 2019
Power System Expansion and Efficiency Improvement Investment Program - Tranche 2
Construction of Five 132/33/11kV Substations in DESCO Area
This Semi-annual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area.
5th Environmental Monitoring Report
on
Construction of five 132/33/11kV Sub-stations in DESCO Area
Acknowledgements
The Center for Environmental and Geographic Information Services (CEGIS), a public Trust
under the Ministry of Water Resources, expresses its gratitude to the Dhaka Electric Supply
Company Limited (DESCO) for entrusting CEGIS with the responsibility of conducting for
Environmental Monitoring Report (EMR) of “Construction of five 132/33/11kV (Kilo Volt) Grid
Sub-stations in DESCO Area”.
CEGIS is indebted to Brig. General Md. Shahid Sarwar, ndc, psc, (Retd.), Managing Director
of DESCO for giving opportunity to work with DESCO. CEGIS is grateful to Engr. Jagodish
Chandra Mandol, Executive Director (Engineering) DESCO for his contribution of the study
formulation. CEGIS is also grateful to Engr. Md. Rashidur Rahman, Superintending Engineer
and Project Director (Grid), DESCO and Engr. Md. Abdul Latif Miah, Deputy Project Director
(Grid), DESCO for their kind support, co-operation and guidance.
Members of the EMR Team were impressed with the spontaneous response received from
the DESCO concerned office and local people in providing information. Their contribution is
gratefully recognized by CEGIS whole hearted thanks are extended to those people who had
given time to respond to the different types of Consultation Meetings and Group Discussions.
i
ii
Table of Content
Acknow ledgem ents ............................................................................................. i
List of Tables ...................................................................................................... v
List of Figures .................................................................................................... v
Abbreviat ions and Acronym s ............................................................................ vii
Unit Conversion Table ....................................................................................... ix
Execut ive Sum m ary ........................................................................................... x i
I nt roduct ion ................................................................................................ 1
1.1 Background ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Object ives ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Broad Object ive ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . 1
Specific Object ive ......... .. . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . 1
1.3 Proj ect Locat ion ......... .. . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . 2
1.4 Scope of Works ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . 4
1.5 Monitoring Policy Standard ........ ... .. . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . 4
1.6 ADB Loan Covenants with DESCO ........... .. . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
1.7 Im plem entat ion Arrangem ent ......... .. . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . 8
1.8 Environm ent ......... .. . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
1.9 Proj ect Reviews ......... .. . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . 9
Approach and Methodology ....................................................................... 1 1
2.1 I nt roduct ion ......... .. . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . 11
2.2 Overall Approach ......... .. . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . 11
2.3 Study Mobilizat ion ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . 11
2.4 Team Mobilizat ion ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . 12
2.5 Methodology......... .. .. . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Physical Environm ent ......... .. . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . 13
Biological Environm ent ......... .. . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . 13
Monitoring Results .................................................................................... 1 5
3.1 Com pliance status with ADB loan covenants ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . 17
3.2 Physical environm ent ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . 19
Am bient air qualit y ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . 19
Noise level ........ .. . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . 19
Waste m anagem ent ......... .. . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . 20
3.3 Biological Environm ent ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . 26
Ecosystem and Biodiversity ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
iii
I nst itut ional arrangem ent for Monitor ing and com pliance ......................... 3 1
Site Specif ic Environm ental Managem ent Plan .......................................... 3 3
5.1 HSE im plicat ion ......... .. . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . 33
5.2 Training and Meet ing at the Proj ect Site for Safety ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . 33
5.3 Environm ental Protect ion ......... .. .. . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . 33
5.4 I n-house Rules and Regulat ions ........ ... .. . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
5.5 Responsibilit y General Site Safety & Environm ental Guidelines ........ ... .. . . . . . . . . 34
Conclusion and Recom m endat ions ............................................................ 3 5
References ....................................................................................................... 3 7
Appendix 1 : Monitoring Check list ..................................................................... 4 1
Appendix- 2 : Field Photos on June 2 0 1 9 ........................................................... 5 1
Appendix- 3 : Term s of Reference ( ToR) ............................................................ 6 1
Appendix- 4 : Environm ental Clearance Cert ificate ( ECC) .................................. 6 5
Appendix- 5 : Base Map of the study area .......................................................... 6 7
iv
List of Tables
Table 1.1: Location of the Substations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . 2
Table 1.2: Selected I ESCs and Param eters ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Table 2.1: The Com posit ion of the Main Team ......... .. .. . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . 12
Table 2.2: The Com posit ion of the Mult i-disciplinary Field Team ........... .. . . . . . . . . . . . . . . . . . . 12
Table 3.1: Work Progress Status ........ ... .. . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . 15
Table 3.2: Sum m ary of Com pliance status with ADB loan covenants ........ ... . . . . . . . . . . . . . . 18
Table 3.3: Average Noise Level Reading of substat ion locat ions ........ ... .. . . . . . . . . . . . . . . . . . . 20
Table 3.4: Standards of noise levels for different zones of Bangladesh ........ ... .. . . . . . . . . . 20
Table 3.5: Mat rix of Monitoring Results ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 27
List of Figures
Figure 1.1: Map of DESCO Dist r ibut ion Area of Proposed 132/ 33/ 11kV SSs Scope of
Works ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . 3
Figure 2.1: Overall process of the com pliance m onitoring study ........ ... . . . . . . . . . . . . . . . . . . . . . 11
Figure 3.1: Water logging at the const ruct ion site at Banani Sub-stat ion (January) ...... 21
Figure 3.2: Labor accom m odat ion at top floor of Const ruct ion Building at Banani Sub-
stat ion (January) ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 21
Figure 3.3: Kitchen Waste Managem ent at Banani Sub-stat ion (March) ........ ... . . . . . . . . . . . 21
Figure 3.4: Kitchen Waste Managem ent at Banani Sub-stat ion (April) ...... .. .. . . . . . . . . . . . . . . 21
Figure 3.5: Const ruct ion Materials in the m onth of January at Banani Sub-stat ion ....... 21
Figure 3.6: Const ruct ion Materials in the m onth of March at Banani Sub-stat ion ........ .. 21
Figure 3.7: Const ruct ion Materials in the m onth of April at Banani Sub-stat ion ........ ... . 22
Figure 3.8: Const ruct ion Materials in the m onth of May at Banani Sub-stat ion ........ ... . 22
Figure 3.9: Const ruct ion Materials in the m onth of June at Banani Sub-stat ion........... . 22
Figure 3.10: Clean and hygienic lat rine for workers at Banani Sub-stat ion in June ....... 22
Figure 3.11: Kitchen Waste Managem ent at Tongi Sub-stat ion (January) ......... .. . . . . . . . . 23
Figure 3.12: Kitchen Waste Managem ent at Tongi Sub-stat ion (March) ........ ... . . . . . . . . . . . 23
Figure 3.13: Waste Managem ent at Tongi Sub-stat ion (January) ........ ... . . . . . . . . . . . . . . . . . . . . 23
Figure 3.14: Waste Managem ent at Tongi Sub-stat ion (March) ......... .. . . . . . . . . . . . . . . . . . . . . .. 23
Figure 3.15: Waste Managem ent at Tongi Sub-stat ion (April) ...... ... . . . . . . . . . . . . . . . . . . . . . . .. . . 24
Figure 3.16: Waste Managem ent at Tongi Sub-stat ion (May) ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . 24
Figure 3.17: Workers are working without PPEs at Tongi Sub-stat ion (May) ......... .. . . . . . 24
Figure 3.18: Unhygienic and dirty lat rine at Tongi Sub-stat ion (March) ........ ... . . . . . . . . . . . 24
Figure 3.19: Unhygienic and dirty water house for workers at Tongi Sub-stat ion (April) 24
v
Figure 3.20: I nit iat ives taken against fire fight ing at Tongi Sub-stat ion (June) ........ ... . 25
Figure 3.21: Lit t le im provem ent for lat r ine facilit y at Tongi Sub-stat ion (June) ........ ... . 25
Figure 3.22: Waste Managem ent at Tongi Sub-stat ion (June) ......... .. . . . . . . . . . . . . . . . . . . . . .. . . 25
Figure 3.22: Water Facilit y for bath at Tongi Sub-stat ion (June) ........ ... . . . . . . . . . . . . . . . . . . . . . 25
Figure 3.23: Use of PPEs Tongi Sub-stat ion (June) ........ ... . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . 25
Figure 3.24: Vegetat ion at close to the Banani Substat ion during const ruct ion phase .. 26
Figure 3.25: Vegetat ion at close to the Tongi Substat ion during const ruct ion phase .... 26
Figure 4.1: I nst itut ional Arrangem ent for Com pliance Monitoring ......... .. .. . . . . . . . . . . . . . . . . . 31
vi
Abbreviations and Acronyms
ADB Asian Development Bank
ANSI American National Standards Institute
BECR Bangladesh Environmental Conservation Rules
BECA Bangladesh Environmental Conservation Act
BOD Biological Oxygen Demand
CEGIS Center for Environmental and Geographic Information Services
CDA Chattogram Development Authority
CSR Corporate Social Responsibility
DESCO Dhaka Electric Supply Company Limited
DO Dissolved Oxygen
DoE Department of Environment
DPDC Dhaka Power Distribution Company
DPHE Department of Public Health and Engineering
ECA Environmental Conservation Act
ECC Environmental Clearance Certificate
ECR Environmental Conservation Rule
EARF Extractive Area Rehabilitation Fund
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EMR Environmental Monitoring Report
EPC Engineering, Procurement and Construction
ESMPs Environmental and Social Management Plans
FGD Focus Group Discussion
GoB Government of Bangladesh
GIS Gas Insulated Switchgear
GPS Global Positioning System
HSE Health, Safety and Environment
IESC Important Environmental and Social Component
KDA Khulna Development Authority
KII Key Informant Interview
kV Kilo Volt
PAM Project Administration Manual
PAP Project Affected Peoples
pH Potential of Hydrogen
vii
PPE Personal Protective Equipment
P&D Planning & Development
RAJUK Rajdhani Unnyan Kartipakkho
RDA Rajshahi Development Authority
RoW Right of Way
RP Resettlement Plan
RRA Rapid Rural Appraisal
SAE Sub-Assistant Engineer
SCC Site Clearance Certificate
SPM Suspended Particulate Matters
SPS Safeguard Policy Statement
SSs Sub-Stations
ToR Terms of Reference
TL Transmission Line
viii
Unit Conversion Table
General Units
1 meter = 3.28 ft
1 kilometer = 0.621371192 mile
1 square mile = 640 acres = 2.590 km2
1 nautical mile = 1.852 kilometer
1 bigha = 33 decimal
1 katha = 1.65 decimal
Energy Units
1 kV = 1000 Volt
ix
x
Executive Summary
In continuation to the earlier monitoring’s, this fifth monitoring has been conducted in all five
sites based on ADB safeguard’s policy, the laws and the National policies of Bangladesh and
Loan covenants between ADB and Bangladesh in December 2018. Construction work at
Banani and Tongi are in progress. Whereas, in other three sub-stations construction works
have been completed, hence, environmental impacts in these sub-stations are no more
present there. However, the monitoring team has advised the EPC contractor to plant trees
and flower plants in and around the vacant places of all these substations where possible.
Based on the prepared checklist, the monitoring team observed the physical (Waste
management, Noise etc.), ecosystem and biodiversity status of the construction sites (Banani
and Tongi) following both qualitative and quantitative approaches.
According to the air analysis report, enclosed in the 3rd monitoring report, the air quality of
Dhaka is not good as unregulated heavy urbanization activities are more over the entire city,
which cause high level of Suspended Particulate Matters in air. In addition to that, as Tongi
substation is located in an industrial area, the smoke from nearby cotton mills have further
deteriorated the air quality at Tongi. However, this scenario is opposite at Banani substation
as it is located in an enclosed residential area, hence, air quality deteriorates in the
construction period only for crushing of bricks, concrete mixing etc.
The EPC contractor has been advised to cover the construction materials with polythene and
to spray water regularly on the construction sites to avoid SPM spreading by wind. The noise
levels were measured during daytime at the Banani, Tongi, substation sites. The measured
values along with BD and other standard values in tabular form are placed in chapter 3 of this
report for reference.
As construction work is still in progress in Banani and Tongi, noise level was measured at the
entrance and the construction sites in Banani and Tongi substations. The noise level was
observed within the DoE standard at the entrance of both the substations and in the
construction site of the Tongi substation. However, noise level was much higher at the
construction site of the Banani substation.
Construction works at Uttara, Aftabnagar and Purbachal sub-stations are over and waiting for
commissioning, a few workers are present at the site currently, and regular Kitchen are closed
in those sub-stations. Workers manage their food locally; hence, there are no issues for
kitchen wastes at those sites. On the other hand, the major construction activities are over at
Banani and Tongi substation. During the monitoring visits in the last three months, waste
management and use of PPEs for health and safety were found satisfactory at Banani
substation and the management authority took necessary initiatives based on the suggestions
of CEGIS monitoring Team. At Tongi substation, the scenario was quite different.
Kitchen management was satisfactory at this substation. However, in regard of health and
safety issues, workers are unconscious and during the last five visits, each time plastic
packets, wastes, cigarette butts etc. were found here and there in the project area. Workers
are very much unwilling to use PPEs as the PPEs provided by the authority were not of their
size. To them, size is an important factor to work comfortably. Construction materials were
found dumped in a scattered manner, labor accommodation as well as toilet facilities were
found dirty and unhygienic. Monitoring team accordingly has advised the contractor to
xi
Executive Summary
increase the frequency of toilet cleaning, provide additional bins over the area, and advise the
workers to use the bins and not to throw cigarette butts and other materials here and there.
In terms of ecosystem and biodiversity, the monitoring team observed the existing vegetation,
flora and fauna. Other sub-station areas except Banani Substation were covered with grass
and with a few herbs; therefore, occurrence of wildlife was not significant, informed by the
local habitants. As a result, impacts on local wild life and their habitat were found negligible.
As per the findings, there are no more problems due to the project implementation as green
belt will be prepared after the completion of project works. Gardening in empty space, if
available, is also recommended by the CEGIS monitoring Team.
With the few above observations at Banani and Tongi Substations, work in other substations
are satisfactory.
xii
I ntroduction
1.1 Background
Electrical Power is the most useable form of energy as well as one of the major inputs for
development of a country like Bangladesh and not only power generation but also sustainable
power supply is pre-requisite for socio-economic development. In this regard, the Government
of Bangladesh (GoB) has given top most priority in an accelerated manner and took a vision
to develop Bangladesh as middle income country with a commitment of providing electricity to
all by 2021 and as a developed country by 2041 through rapid industrialization, urbanization
etc. Dhaka, the capital of Bangladesh and adjacent areas are currently facing electricity
demand tremendously for the rapid industrialization, urbanization and increased population.
Considering this fact, the Dhaka Electric Supply Company (DESCO), hereinafter called “the
proponent”, has taken an initiative to modernize the existing old distribution system and
intended to construct the 132/33/11kV five (5) grid sub-stations under its command area at
Uttara 3rd Phase, Aftabnagar, Banani, Purbachal and Tongi in Dhaka, Narayanganj and
Gazipur Districts with a total land area of about 489.56 decimals for the proposed five Sub
Stations. The proponent has already obtained Site Clearance Certificate (SCC) and received
necessary approval based on Environmental Impact Assessment (EIA) and EMP reports as
well. Afterwards, DESCO engaged HYOSUNG as EPC contractor for the construction and
Center for Environmental and Geographic Information Services (CEGIS) for conducting the
environmental compliance monitoring as the complementary part of the project regarding EMP
and ADB’s social safeguard policy and the loan covenants between ADB and Bangladesh.
1.2 Objectives
Broad Objective
The broad objective of this project is to monitor whether the work of the EPC Contractor
relating to environment, social and health and safety are in line with the requirements and
guidelines of Department of Environment (DoE), Asian Development Bank (ADB) and the EMP
provided.
Specific Objective
There are some specific objectives in relation to the broad objective of this study. The specific
objectives of the environmental monitoring are to:
• To analyze water and air quality in pre-construction, construction phases as well
as operation stage of the project;
• To analyze Noise level in three stages of the project;
• To explore Land Characteristics in the project sites;
• To analyze the waste management system of concerned authority or EPC
Contractor;
• To monitor working condition and occupational health safety of workers throughout
project life;
1
Introduction
• Provide Environmental Compliance Monitoring Reports at the end of every six
month (Ongoing).
1.3 Project Location
The location of the project is shown in Figure 1.1. The locations of Sub-stations are given in
the Table 1.1.
Table 1.1: Location of the Substations
SI.
No
Proposed
grid name
Location description and
address
Land area
(decimal) Remarks
1
Aftabnagar
132/33/11 kV
sub-station
Plot no -32/M, Road no -17,
Avenue-13, Sectoe-3, Jahurul
Islam City, Aftabnagar, Dhaka
GPS: N 23°46’11.65’’
E 90°27’24.02.’’
60 *Construction work has already
been completed
2
Tongi
132/33/11 kV
sub-station
(Mill gate)
Tongi-3, Sub-station area,
Mill gate, Tongi, Gazipur
GPS: N 23°53’47.22’’
E 90°23’48.23.’’
82 (about)
*DESCO area (Tongi-3,
33/11kV Old sub-station)
*Old sub-station Site cleaning
work is going on,
New Sub station’s
*Construction work has already
been started and 80%
Completed.
3
Purbachal
132/33/11kV
sub-station
Purbachal New city project
area, Sector-2, Road no 210
and 305(close to corner plot),
Rupganj, Narayanganj
GPS: N 23°49’57.01’’
E 90°30’23.49.’’
103.3 *Construction work has already
been completed
4
Uttara third
phase
132/33/11 kV
sub-station
Plot no 103, Avenue-3 and
West avenue, Sector-18,
Uttara third phase, Uttara,
Dhaka
GPS: N 23°51’31.53’’
E 90°20’59.23.’’
198 *Construction work has already
been completed
5
Banani
132/33/11kV
sub-station
Plot no 31, Road no 5, Block
– I, Banani, Dhaka
GPS: N 23°47’18.8’’
E 90°24’17.97.’’
46.26
*The Site cleaning work has
done.
*Construction work has already
been started and 80%
Completed.
Source: PD office, DESCO
2
Introduction
Figure 1.1: Map of DESCO Distribution Area of Proposed 132/ 33/ 11kV SSs
3
Introduction
1.4 Scope of Works
The EIA report provides information on the baseline environmental condition (physical, soil
and agricultural, biological and social environment) of the project area. Following DoE
guidelines, the EIA report identified potential impacts of the proposed project activity on the
environmental components of the project area. It includes the Terms of Reference (ToR)
(Appendix 3) for the EIA and the Environmental Management Plan (EMP) against adverse
impacts. The EMP also includes an Environmental Monitoring Plan, cost and institutional
arrangements for future monitoring.
In line with the aforementioned objectives the scope of the services should cover the following:
• Monitoring ambient air quality of the project site and its adjoining area before
construction stage;
• Review of environmental management and environmental monitoring plan
suggested in the EIA report in line with the action plan proposed by ADB;
• Upgrade (if required) the environmental monitoring framework and work plan
specifying the indicators, method, location, time, frequency of monitoring provided
in the EIA that shall be followed by the EPC contractor;
• Monthly monitoring of construction activities to overview their compliance with
national environmental and social regulations, and ADB’s performance standards
on social and environmental sustainability;
• Physical observation (monthly) to assess that all mitigation measures are carried
out or in place in conformity with the EMP and action plan;
• Monthly monitoring of implementation of environmental monitoring activities as
specified in the environmental monitoring plan;
• Monthly monitoring of different activities of EPC contractor regarding analysis of
air quality, water quality, soil texture and quality, soil and land erosion, noise
measurement, waste management, etc. in connection with the environmental
monitoring plan;
• Monthly monitoring of socio-economic issues like community safeguard due to
pollution, hazards and employment opportunity;
• Suggestion of pollution prevention and mitigation measures to ensure
environmental safeguard, to ensure compliance with national environmental and
social regulations;
• Keeping close liaison with the project implementation office (Project Director), and
EPC contractor; and
• Providing a monitoring report at the end of every six (6) months in line with the
reporting requirement of ADB satisfying equator principles.
1.5 Monitoring Policy Standard
The Environment Conservation Rules place construction of substation into the Red category.
The site clearances based on IEE and for environmental clearance certificate have been
obtained from Department of Environment (DoE). As per the Bangladesh Govt. policy
standard, environmental compliance monitoring is one of the important part that would be
initiated following the Environmental compliance monitoring guidelines by DoE and the
4
Introduction
agreement between ADB and Bangladesh Govt. based on the ADB loan covenants. DESCO
has taken initiative to expand its infrastructure of the distribution system through construction
of new lines, installation of new substations and rehabilitation of existing substation in order to
provide new connections to the incoming consumers. Now, the purpose of the environmental
monitoring is to monitor whether the construction activities are performing based on the EMP
or is creating any environmental impacts or any adjustment is required in safeguard measures.
Compliance with National Environmental Laws
The environmental legislation of GoB gives importance to reduce the negative impacts of
infrastructure development projects, and give priority for the enhancement of positive impacts
due to the project implementation. It conforms the National Environmental Policy 1992 based
on the Agenda 21 of Rio Conference and subsequent enactments of the Bangladesh
Environmental Conservation Act (BECA) 1995 and Bangladesh Environmental Conservation
Rules (BECR) 1997.
National Environmental Laws Compliance Requirement Performance of DESCO
Bangladesh Environmental
Conservation Act (BECA) 1995
and Bangladesh Environmental
Conservation Rules (BECR)
1997.
The Construction of Five
132/ 33/ 11 kV Substations
in DESCO Area and require
one site (Banani)
environmental clearance
certificate (ECC).
• The environmental clearance
(valid for 1 year) for the project
was obtained from the DoE on
06.04.14. The processing for
renewal is ongoing as per the
Government rules.
• Banani Substation site has been
relocated and Initial
Environmental Examination
(IEE) study including EMP
report submitted to DoE for
Environmental Clearance
Certificate.
Bangladesh Government Regulation and compliance monitoring
The Bangladesh Environment Conservation Act of 1995 (ECA, 1995) is the key legislation in
relation to environment protection in Bangladesh. Recently, the ECA 1995 has been amended
whereas the project for substation construction is under the orange B category. This Act is
promulgated for environment conservation, standards, development, pollution control, and
abatement. It has repealed the Environment Pollution Control Ordinance of 1977.
The main objectives of the Act are:
• Conservation and improvement of the environment; and
• Control and mitigation of pollution of the environment.
The main strategies of the Act can be summarized as:
• Declaration of ecologically critical areas and restriction on the operations and
processes, which can or cannot be carried/initiated in the ecologically critical areas;
• Regulations in respect of vehicles emitting smoke harmful for the environment;
• Environmental clearance;
• Regulation of the industries and other development activities’ discharge permits;
5
Introduction
• Promulgation of standards for quality of air, water, noise and soil for different areas
for different purposes;
• Promulgation of a standard limit for discharging and emitting waste; and
• Formulation and declaration of environmental guidelines.
The ECA, 1995 specified that no industrial unit or project shall be established or undertaken
without obtaining Environmental Clearance from Director General in a manner prescribed by
the Rules. The project promoter must obtain Environmental Clearance from the Director
General of Department of Environment (DoE). An appeal procedure of DoE exists for those
promoters who fail to obtain clearance. Failure to comply with any part of this Act may result
in punishment of imprisonment or fine or both. The DoE executes the Act under the leadership
of the Director General.
The Bangladesh Environment Conservation Act (Amendment), 2000 focuses on: (1)
ascertaining responsibility for Compensation in cases of damage to ecosystems, (2) increased
provision of punitive measures both for fines and imprisonment and (3) fixing authority on
cognizance of offences.
The Bangladesh Environment Conservation Act (Amendment), 2002 elaborates on: (1)
restriction on polluting automobiles, (2) restriction on the sale and production of
environmentally harmful items like polythene bags, (3) assistance from law enforcement
agencies for environmental actions, (4) break up of punitive measures and (5) authority to try
environmental cases.
The Bangladesh Environment Conservation Act (Amendment), 2010 introduces new rules &
restriction on: a) Ensure proper management of hazardous wastes to prevent environmental
pollution and Health Risk, b) No remarked water body cannot be filled up/changed; in case of
national interest; it can be done after getting clearance from the respective department; and
c) Emitter of any activities/incident will be bound to control emission of environmental
pollutants that exceeds the existing emission standards (d) Government may declare any
ecosystem as “Ecologically critical area” if it appears to be degraded or expected to be
degraded and take all precaution measures to protect that ecosystem. In addition, government
shall stop any ongoing activities and will not allow any new developments in the ecosystem
after declaration of “Ecologically Critical Area”.
The Bangladesh Environment Conservation Rules, 1997 is the first set of rules, promulgated
under the ECA 95 (so far there have been three amendments to this set of rules – February
and August 2002 and April 2003). The Environment Conservation Rules of 1997 has provided
categorization of industries and projects and identified types of environmental assessments
needed against respective categories of industries or projects.
Among other things, these rules set (i) the National Environmental Quality Standards for
ambient air, various types of water, industrial effluent, emission, noise, vehicular exhaust etc.,
(ii) the requirement for and procedures to obtain environmental clearance, and (iii) the
requirement for IEE and EIA’s according to categories of industrial and other development
interventions.
The proposed project, according to the DoE, is considered under the “Red” category of the
Environmental Conservation Rules, 1997.
6
Introduction
Noise Pollution (Control) Rules, 2006 gives the authority to all the Union Councils,
Paurashava, City Corporations, City Development Authority (i.e. RAJUK, CDA, KDA, RDA
etc.) to mark off the areas under their jurisdiction as silent, residential, mixed, commercial or
industrial. They should also put signs to mark those areas. The act also describes the
approved standard limit of sound in the added schedule 1 and 2. In the schedule 1, silent area
means area up-to a radius of 100 meters around hospitals or educational institutions or special
institutions/ establishments identified/to be identified by the government. In the silent area, it
is prohibited to use any kind of horns of vehicles, audio signals and loudspeakers. According
to this act, daytime is counted from 6 am to 9 pm whereas night-time is counted from 9 pm to
6 am.
The Motor Vehicle Ordinance, 1983 stated to impose a penalty of maximum two hundred taka
for those vehicles that are emitting smokes that poses health hazard in the public places. It
also restricts the passenger from smoking in public service vehicles and in any other vehicles
with notice of not smoking. This ordinance is enforced occasionally but a regular enforcement
would be helpful to reduce air pollution in big cities including Dhaka. However, it is to be noted
that amount of the penalty is very low which may be revised as well.
The Environment Court Act, 2000 provides for the establishment of environment courts and
matters incidental thereto. This act also provides the jurisdictions of environment court, penalty
for violating court’s order, trial procedure in special magistrate’s court, power of entry and
search, procedure for investigation, procedure and power of environment court, authority of
environment court to inspect, appeal procedure and formation of environment appeal court.
Compliance with DoE’s Guidelines
As mentioned above, the project activities fall under the ‘red’ category according to the
Environment Conservation Rules, 1997. For projects under this category, it is mandatory to
carry out IEE and subsequently EIA including Environmental Management Plan (EMP) and
where necessary develop a Resettlement Plan for getting environmental clearance from the
DoE. The DoE has issued EIA Guidelines for Industries and addresses the IEE and EIA for
several industrial sectors and activities. Each Project Proponent shall conduct an IEE or EIA
and is expected to consult and follow the DoE guidelines. The provisions of the environment
legislations and the EIA guidelines of the DoE have been reviewed under this study. The DoE
has issued application procedure for obtaining site/environmental clearance.
Environmental quality standards for air quality, noise, odour, sewage discharge, industrial
effluents, and industrial project emissions for Bangladesh.
The Environment Conservation Act, 1995 and the Environment Conservation Rules, 1997 are
the main legislative base in Bangladesh for protection and conservation of natural
environment. The Environment Conservation Rules (1997) place activities of power plant into
the Red category. However, the Safeguard Policy Statement (SPS) of Asian Development
Bank has also been reviewed since ADB is financing the project in partnership with the GoB.
As per the ADB categorization, the sub-station construction activities are under the category
B considering the significance of the project’s potential environmental impacts. Therefore, the
EMP is prepared based on the combination of both the national and the ADB.
The environmental standards are determined in the Environmental Conservation Rules. The
standards for air, water, sound, odour and other components of the environment is started to
monitor in accordance with the standards specified in Schedules - 2, 3, 4, 5, 6, 7 and 8. The
7
Introduction
Bangladesh standards, in general, are less stringent compared to the developed countries.
This is in view to promote and encourage industrialization in the country. The Bangladesh
standards are not for any specific period of time. There is no provision for partial compliance
too. For this reason, monitoring is based on the national standards unless there is absence of
clear standards; only then ADB’s standard is being considered.
Following IESCs and parameters are selected for monitoring in DESCO’s five grid sub-station
areas which have presented in Table 1.2.
Table 1.2: Selected IESCs and Parameters
IESCs Parameters
Air Suspended Particulate Maters (SPM), Sulphur dioxide, Carbon Monoxide,
Oxides Nitrogen
Waste Waste generation and proper waste disposal
Noise dBA (daytime only)
Water (if any) DO, pH, BOD, Arsenic whether water is usable for irrigation or by fisheries
Biodiversity Habitat conversion and fragmentation
Health & Safety Risk of electrocution, safety measures within the construction site, emergency
plan.
The results of the monitoring are needed to compare the established benchmarks/baseline
and compliance status and help to identify the areas where adverse environmental and social
adverse impacts are still occurring. It would be helpful to formulate the corrective actions
accordingly and in a timely manner.
1.6 ADB Loan Covenants with DESCO
According to the Loan Covenant Article (II), section 2.01, DESCO should carry out the project,
with the due diligence and efficiency and in conformity with sound administrative, financial,
engineering, environmental and power sector practices. For the execution of project following
criteria should be followed.
1.7 Implementation Arrangement
DESCO should ensure the project implementation in accordance with the detailed
arrangements set forth in the PAM. Besides, it is the responsibility of DESCO to ensure their
project management staffs that have the qualification to undertake necessary tasks of
procurement, construction, supervision, inspection, and testing of equipment, payments to
contractors, monitoring, environmental and social safeguards due diligence and reporting of
progress relevant to the components under their responsibility.
1.8 Environment
DESCO should ensure that the preparation, design, construction, implementation, operation,
and decommissioning of the project and all project facilities comply with
• All applicable laws and regulations of the relating to environment, health and safety
• The environmental safeguard
• The EARF
8
Introduction
• All measures and requirements set forth in the respective IEE and EMP and any
corrective or preventive actions set forth in a safeguard monitoring report
1.9 Project Reviews
a. The project progress would be reviewed by the ADB with necessary midcourse
corrections
b. The Assistance should be provided by the Executing Agency (i.e. DESCO).
The environmental monitoring will assess the compliance that has been suggested under the
Bangladesh Govt. laws, policies and national standards (i.e. air, noise and water quality) and
ADB loan covenants. As there is no involuntary resettlement and ethnic minority issues,
therefore, this monitoring assess the environmental and social safeguard issues in accordance
with the Govt. laws and ADB loan covenants like the above-mentioned ways.
The results of the monitoring will be compared with the established benchmarks/baseline and
compliance status and help to identify the areas where adverse environmental and social
adverse impacts are still occurring. It will help to formulate the corrective actions accordingly
and in a timely manner.
9
Introduction
10
Approach and Methodology
2.1 Introduction
This chapter includes methodology following which the environmental compliance monitoring
of various physical, biological, and socio-economic components was carried out. This study
considers five components which are likely to be affected due to construction and operation
of the substations such as water, soil, social and economic issues and ecology. In the following
sections, these components along with indicators, tools and techniques are discussed.
2.2 Overall Approach
The Figure 2.1 shows overall process of environmental monitoring of construction of five
132/33/11kV Sub-Station project. For the monitoring study, a number of activities have been
carried out during the preparation phase of the Project (i.e. information gathering, checklist
preparation, service scoping and bounding, assigning field investigators etc.). Field level data
collection, monitoring of environmental and social compliance have also been carried out.
Figure 2.1: Overall process of the compliance monitoring study
2.3 Study Mobilization
A roadmap for environmental monitoring was prepared with detailed approach and
methodology in the Inception Phase which has been followed by the monitoring team along
with necessary tools for data collection, while visiting the project sites and collect relevant data
for observing the compliance status.
A comprehensive checklist on environmental monitoring such as required guidelines for
construction activities, necessary suggestions for probable hazards and risks at construction
work place etc. has been prepared based on the selected physical and biological indicators
according to the EMP included in the EIA report. Accordingly, the suggested measures have
been ensured for the overall environmental protection and social security. Equator Principles
have been also followed in the preparation of checklist.
11
Approach and Methodology
2.4 Team Mobilization
CEGIS has mobilized a core group of highly skilled professionals as proposed in the technical
proposal. Initiatives have been taken for accomplishing the study within the expected time-
frame through formulating an action plan, setting up of the office in Dhaka, forming the
multidisciplinary field team and providing all necessary logistics and technical supports to
perform required investigations.
The Consultant CEGIS will work under the overall supervision of the Project Director, DESCO
and maintain close liaison with DESCO offices (both field and head offices). The Team Leader
is responsible for direct supervision of the study. He will guide the multidisciplinary team to
achieve the goal of the study. The progress of the study will be reviewed in weekly progress
review meeting. Each report and deliverable shall be reviewed carefully by the team members
and Team Leader.
As per the ToR directives, a multidisciplinary expert team has been formed with suitable
allocation of time for each professional. Table 2.1 presents the composition of the study team
with their designation and Table 2.2 presents the multi-disciplinary team mobilized for
collecting data from the field.
Table 2.1: The Composition of the Main Team
Sl. No. Name of Professional Position Assigned
1. Dr. Kazi Md. Noor Newaz Environmental Expert
2. Engr. Jalal Ahmed Chowdhury Environmental Expert/ Transmission Line (TL)/
Power Plant Expert
3. Dr. Dilruba Ahmed Socio-economic an livelihood expert
4. Mr. Subrata Kumar Mondal Economist
5. Md. Maqb –E- Elahi Geology Specialist
6. Md. Mushfiq Ahmed Ecology Specialist
Table 2.2: The Composition of the Multi-disciplinary Field Team
Sl. No. Name of Professional Position Assigned
1. Md. Shofiqul Islam Sociologist, Project Leader
2. Deeba Farzana Moumita Electrical and Electronics Engineer
3. Bilkish Sultana Electrical Engineer
4. Uzzal Kumar Saha Ecologist
5. Hasin Ahmed Civil Engineer
2.5 Methodology
The compliance monitoring of the project has been carried out following important
Environmental and Social Component during field investigation. Methodology for the
investigation of each component is given below.
12
Approach and Methodology
Physical Environment
Ambient Air Quality
To assess the baseline condition of the ambient air in the project areas, the air has been
sampled and analyzed at spots, using machines and experts. Ambient air quality has been
continuously monitored for CO, SOX, NOX, and particulate matter (PM2.5 and PM10) and
+suspended particulate matters (SPM) following the standard method.
Ambient Noise Level
The ambient noise level has been monitored monthly at nearby sensitive receptors around the
construction site (including substation site) of this project. Noise level was measured at the
day time for each project site. Each time, noise level was recorded for a 15 minutes’ time span
by using portable ANSI Type II noise level meter. Depending on the site condition and acoustic
environment, the noise meter was set up and calibrated each time following the manufacturer’s
instruction manual.
Water quality and Hydrological assessment
Water quality parameters were selected depending on ambient water use and potential
polluting agents from the Project sites. Standard practices were maintained during sampling
and analysis of the collected samples. The water quality parameters included relevant
parameters. All samples were tested through the standard procedure from DPHE as well as
from CEGIS Laboratory.
Waste Management
Waste materials like including garbage, kitchen waste, construction materials, wires etc. are
generated due to construction works as well as development activities which may have the
potential to cause adverse environmental impacts during generation, storage, transportation
and disposal. Waste management procedures based on EMP were suggested in the EIA
Report and are monitored monthly in order to maintain minimal potential impacts to the
environment.
Biological Environment
Ecosystem and Biodiversity Conservation
Proposed substation sites are situated in urban area, so urban ecosystem as well as
vegetation and wildlife are major components for this environmental monitoring.
Terrestrial Vegetation
Project site specific data (i.e. Cocos, Psidium, Cynodon, Scorpia, Croton, Leucas, Cyperus,
Chan grass) were collected through visual observation. Additionally, local people were
interviewed about biodiversity and ecosystem through stakeholder consultation, KII, FGD and
RRA. Currently, ecosystem biodiversity is monitored quarterly through consultation with
stakeholders and local people.
13
Approach and Methodology
Flora and Fauna
Flora and Fauna of all sites were observed through regular field visit. The impact of project
implementation (i.e. Labor and vehicle movement, as well as waste management) on small
mammals, amphibians, reptiles and local urban birds have been identified in depth through
observation and consultation with relevant stakeholders according to the prepared checklist.
14
Monitoring Results
A multi-disciplinary Team of CEGIS has conducted their monthly visit (January 19 to June 19)
to the Tongi and the Banani Substation sites and collected data from the project site and
discussed about the water, noise, ecosystem and biodiversity and occupational health and
safety issues related to the above construction activities with the workers, HYUSONG officials
and DESCO professionals. Other three substation sites were not paid a visit in first five months
of current monitoring session as construction works have been completed and now await for
operational activities. All the monitoring results based on the condition at the substations area
have been placed in Table 3.5.
Based on the prepared checklist, a quantitative and qualitative analysis have been done, and
the synthesis result is also given in the following sections.
The monitoring team found that the construction activities started fully at the five project sites
and following activities are completed and ongoing presented in the following Table 3.1.
Table 3.1: Work Progress Status
Substations
Name Activity details Status
Aftabnagar
Sub-station
Installation of the Gas Insulated
Switchgear (GIS)
Done
MV cable termination work and AC
DC cable laying and termination work
Done
Roof slab and Column casting Done
Transformation bushing installation Done
GIS monitor installation Done
Civil work for installation of electrical
components like transformer.
Done
Other civil works including Building
construction, boundary construction
activities etc.
Done
Setup transformer inside the
substation
132/33/11 kV transformer
installation work is complete
Copping work Done
Purbachal Sub-
station
Installation of the Gas Insulated
Switchgear (GIS)
Done
MV cable termination work and AC
DC cable laying and termination work
Done
Roof slab and Column casting Done
Transformation bushing installation Done
GIS monitor installation Done
Civil work for installation of electrical
components like transformer.
Done
Other civil works including Building
construction, boundary construction
activities etc.
Done
15
Monitoring Results
Substations
Name Activity details Status
Setup transformer inside the
substation
132/33/11 kV transformer
installation work is completed
Uttara 3rd phase
Sub-station
Copping work Done
Installation of the Gas Insulated
Switchgear (GIS)
Done
Civil work for installation of electrical
components like transformer
Done
MV cable termination work and AC
DC cable laying and termination work
Done
Other civil works including Building
construction, boundary construction
activities etc.
Done
Setup transformer inside the
substation
132/33/11 kV transformer
installation done
Installation of the Gas Insulated
Switchgear (GIS)
Done
Roof slab binding Done
Banani Sub-station
Civil work for installation of electrical
components like transformer
Done
Other civil works including building
and boundary wall construction and
other construction activities etc.
In progress
Column and Beam slab and carpeting Finishing work in progress
Piling Completed
Basement preparation and casting
work
Completed
Installation the Gas Insulated
Switchgear (GIS)
Ongoing
In the project area, the safety
activities
Ongoing.
Construction of boundary wall around
project site.
The boundary-wall at the
North-West and the Southern
part will be reconstructed
The Eastern part of the
boundary-wall will remain the
same
Temporary fence is built in
the North and the South side
with tin and iron.
Tongi Sub-station
Civil work for installation of electrical
components like transformer
The Earth Work and the
transformer setup is ongoing
Other civil works including Building
construction, boundary construction
activities etc.
Other civil works are ongoing
Column and Beam slab and carpeting Finishing task is on going
Piling Completed
16
Monitoring Results
Substations
Name Activity details Status
Preparation of the basement and
casting work Completed
Installation of the Gas Insulated
Switchgear (GIS) Ongoing
Safety activities in the Project Area Ongoing
Construction of boundary wall around
project site.
Existing boundary wall is
using now, the boundary-wall
will be reconstructed after the
construction work.
Source: Monthly field visit from January - June 2019
3.1 Compliance status with ADB loan covenants
The compliance status with the ADB loan covenants have been monitored based on indicators
provided in the ADB loan covenants. The findings for compliance status with the ADB loan
covenants presented in Table 3.2. The activity based photos regarding the compliance status
are provided in the Appendix 2.
17
Monitoring Results
Table 3.2: Summary of Compliance status with ADB loan covenants
Indicators Issues Activities
Compliance Status
Complied
No
t
Co
mp
lied
Remarks
Implementation
arrangement
Detailed arrangements set forth in
the PAM
Engage Consultant for environmental
monitoring
Develop a cell for overall inspection,
monitoring of construction activities
Engage procurement committee
Fully
Complied
The implementation
arrangement followed the ADB
and DESCO loan covenant.
Environment All applicable laws and regulations
relating to environment, health and
safety
The environmental safeguard
The EARF
All measures and requirements set
forth in the respective IEE and EMP
and any corrective or preventive
actions set forth in a safeguard
monitoring report
Review of existing laws and
regulation (National and ADB
safeguard policy)
Preparation of monitoring result
based on EMP by the consultant.
Fully
Complied
The Consultant is preparing
the monitoring result based on
EMP and reviewing existing
laws and regulations.
Project Reviews
The project progress would be
reviewed by the ADB with necessary
midcourse correction
All Submitted Report reviewed by
ADB
Fully
Complied
All comments (1st 2nd 3rd and
4th Monitoring report) from the
ADB incorporated and
submitted to DESCO.
Source: EMR findings from January – June, 2019.
18
Monitoring Results
3.2 Physical environment
Ambient air quality
The construction works at Aftabnagar, Purbachal and Uttara 3rd Phase substation sites have
been completed and civil works are ongoing at Banani and Tongi stations. The air quality
analysis report enclosed in 3rd monitoring report reveals that the levels of SPM, PM10 and
PM2.5 exceeded the Bangladesh and World Bank standard both in Banani and Tongi. On the
other hand, SOx and NOx are very low and negligible. The air quality of Dhaka is not good.
Suspended Particulate Matters are high mainly due to the heavy vehicular movement over the
poorly paved roads and unregulated heavy urbanization activity over the entire city.
Furthermore, Banani substation is in an enclosed residential area of Dhaka city where dust
particles has further increased due to crushing of bricks, concrete mixing etc. during
construction period. Tongi is an industrial area adjacent to Dhaka city. In addition to poor air
quality of Dhaka, the smoke from nearby cotton mills have further deteriorated the air quality
at Tongi.
However, during monsoon period no significant dust particle was observed in the air due to
rainfall. On the other hand, dust particles were observed in the dry season because of
construction activities (e.g.: concrete mix, brick crushing, rod cutting etc.). It was, therefore,
suggested to keep the construction materials covered and to spray water in the construction
site and fence the project sites by CI sheet to resist dust flow outside the Project area.
Noise level
The average noise levels were measured at different locations (Tongi and Banani site) in the
project areas during day time. The noise reading was taken at the entrance and near the
construction zone of the project site. The noise reading near the construction zone was un-
steady due to different construction activity. Most of these activities are limited to day time
only.
During this visit, it was noticed that most of the workers were not comfortable in using earmuffs.
The contractors were suggested to provide ear plug to all workers. The construction work in
Uttara 3rd Phase, Purbachal and Aftabnagar project sites are completed and the noise level is
within the DoE standard as shown in the table below. The Banani site is located in a residential
area. Noise at the entrance was within the DoE standard limit but exceeds the standard value
near construction zone which may affect hearing ability of the locals. However, the
construction activities are limited to day time only. Tongi site is located in an industrial area
where the level of noise fluctuates due to industrial activities from the nearby factories.
Vehicular movements around this project site is also a major issue for excessive noise level.
Although there is considerable fluctuation in noise reading, the result shows that the noise
level in Tongi is within the DoE standard. The noise level reduced because the construction
of the main building is almost finished and pile work of the switchyard is over. The average
noise level of the project sites is shown in the below Table 3.3 and Standards of noise levels
for different zones of Bangladesh is shown in the below Table 3.4.
19
Monitoring Results
Table 3.3: Average Noise Level Reading of substation locations
Location Banani Tongi
Construction zone 70.12 dB 67.85 dB
Entrance 54.87 dB 59.45 dB
Source: Monthly field visit from January - June 2019
Table 3.4: Standards of noise levels for different zones of Bangladesh
Serial No. Category of areas Standards determined at dB unit
Day Night
1 Silent zone 50 40
2 Residential area 55 45
3
Mixed area (mainly residential area,
simultaneously used for commercial and
industrial purposes)
60 50
4 Commercial area 70 60
5 Industrial area 75 70
Source: E.C.R. ’2006
Waste management
A few workers are currently present at Uttara, Aftabnagar and Purbachal sub-station sites.
Regular Kitchen is closed in those sub-stations, hence, there will be no issues for kitchen
wastes at those sites. Workers manage their food locally. Construction wastes are also very
minimum major civil works are over.
At Banani substation, during field visit in January management of environmental issues were
found not satisfactory. Water logging was observed around the kitchen, Construction materials
were found dumped in a scattered manner, labour accommodation was found unhygienic.
These are mainly due to the hiring of additional labour to complete the project in time. Banani
has scarcity of space, extended labour accommodation has been arranged in the basement
of the under construction control room building in December. They were shifted on the top
floor of that building. Cigarettes buds and packs were found here and there inside the labour
accommodation. No drinking water facilities were there and no latrine facilities were there as
well, hence, the workers were using open space which caused unbearable odour of urine at
that place. The scenario changed at the month of April. Cleaned and hygienic latrines as well
as bathroom along with water-house were provided to the workers by the authority.
In February, March and April the issues for environmental management were found
satisfactory. However, in April it was observed that, no fire extinguisher and necessary
precautions were available beside the kitchen. Hence, it was advised to keep fire extinguisher
there and very unfortunately, on May 8th, 2019 at night around 8:30 P.M. it caught fire from the
kitchen. However, no loss happened due to that fire as fire brought under control by the
workers. After that occurrence, regular kitchen was closed and workers take their meals from
nearby eateries and some of them go to their house close to the construction areas to have
their meal. The contractor improved sanitation facilities and drinking water facilities. Water
house was clean and hygienic.
As fatal accident may happen at any time, the monitoring team has advised the contractor to
improve the waste management as well as labor accommodation. Construction wastes were
sold out to the proper authority.
20
Monitoring Results
Figure 3.1: Water logging at the
construction site at Banani Sub-station
(January)
Figure 3.2: Labor accommodation at top
floor of Construction Building at Banani
Sub-station (January)
Figure 3.3: Kitchen Waste Management
at Banani Sub-station (March)
Figure 3.4: Kitchen Waste Management
at Banani Sub-station (April)
Figure 3.5: Construction Materials in the
month of January at Banani Sub-station
Figure 3.6: Construction Materials in the
month of March at Banani Sub-station
21
Monitoring Results
Figure 3.7: Construction Materials in the
month of April at Banani Sub-station
Figure 3.8: Construction Materials in the
month of May at Banani Sub-station
Figure 3.9: Construction Materials in the
month of June at Banani Sub-station
Figure 3.10: Clean and hygienic latrine
for workers at Banani Sub-station in
June
At Tongi Substation, kitchen waste management is good. The workers use separate bin for
kitchen wastes. However, construction wastes were kept unorganized manner. The monitoring
team has suggested several times to manage those wastes properly, but very unfortunately
workers are unaware of health and safety issues. On the field visit in April, it was observed
that, one of the workers was smoking near kitchen. Moreover, other two workers informed the
monitoring team that, daily consultation meeting is not done regularly. In addition to that,
during the last five visits, each time plastic packets, wastes, cigarette butts etc. were found
here and there in the project area. Workers should be more encouraged and guided properly
to use dustbins as they show less interest to use them. It has been advised accordingly to
improve the waste management system. The workers also informed that, the PPEs provided
by the authority, are not fit for all workers. According to them size is an important factor for
comfortable working in the construction places. Hence, maximum workers do not like to use
those PPEs. Moreover, the given PPEs get out of order in a very short time. Drinking water
facilities were good. However, the quality of water they use for being freshen was very poor.
It was also observed that, the water house was very dirty. Sanitation facilities were very poor.
Around 60 people are using only two latrines and for last two months, the latrines were not
even cleaned within one or more than a week. Latrines were very dirty and unhygienic and
according to the workers, it is very difficult to stay in the labour shed because of unbearable
bad odour come from the latrines, found in the month of March, April and May. Several times
22
Monitoring Results
it was suggested to the authority to take necessary initiatives to improve their management on
environmental and safety issues but a very few improvements were observed at Tongi site.
No stagnant water was observed in the site.
Figure 3.11: Kitchen Waste
Management at Tongi Sub-station
(January)
Figure 3.12: Kitchen Waste Management
at Tongi Sub-station (March)
Figure 3.13: Waste Management at Tongi Sub-station (January)
Figure 3.14: Waste Management at Tongi Sub-station (March)
23
Monitoring Results
Figure 3.15: Waste Management at Tongi Sub-station (April)
Figure 3.16: Waste Management at Tongi
Sub-station (May)
Figure 3.17: Workers are working
without PPEs at Tongi Sub-station
(May)
Figure 3.18: Unhygienic and dirty latrine
at Tongi Sub-station (March)
Figure 3.19: Unhygienic and dirty water
house for workers at Tongi Sub-station
(April)
24
Monitoring Results
Figure 3.20: Initiatives taken against fire
fighting at Tongi Sub-station (June)
Figure 3.21: Little improvement for
latrine facility at Tongi Sub-station
(June)
Figure 3.22: Waste Management at Tongi Sub-station (June)
Figure 3.22: Water Facility for bath at
Tongi Sub-station (June)
Figure 3.23: Use of PPEs Tongi Sub-
station (June)
25
Monitoring Results
3.3 Biological Environment
Ecosystem and Biodiversity
Each of the site is mainly dominated with local herbs which grow seasonally. Before starting
construction works at the sub-station areas, a number of trees including fruit trees and herbs
especially at Banani were cut down and cleaned the land for construction. The marginal
vegetation of these proposed substations were Ulu, Bonjal, Cyperus, Kakmachi, Kash, Carpet
grass, Thridhara, Busket grass, Guchcha, Katanota, Lajjaboti etc.
Low density of herbs like Vasant (Clerodendrum Viscosum) and shrubslike Henna (Lawsonia
Inermis), Garden Croton (Codiaeum Variegatum) etc. were cut down due to land development
activities. At that time, habitats of some urban birds, (i.e.: House Sparrow, Common Myna,
Bulbuls etc.) small mammals (i.e.: Mongoose and Mouse), amphibians (Common Toad) and
reptiles (Lizards) inside the project site were disturbed. This wildlife was very few in number
and observed occasionally.
Other sub-station areas except Banani Substation were covered with grass and herbs,
therefore, occurrence of wildlife was not significant, informed by the local habitants. As a
result, impacts on local wild life and their habitat were found negligible.
Figure 3.24: Vegetation at close to the Banani Substation during construction phase
Figure 3.25: Vegetation at close to the Tongi Substation during construction phase
26
Monitoring Results
Table 3.5: Matrix of Monitoring Results
Environmental
and Social
Components
Potential
impacts
Monitoring
Measures Status
Corrective Action Plan
(CAP)
Ambient air
quality
Spread of
fugitive dust in
air due to
construction
activities at site.
Spraying water in
the construction
site to control
fugitive dusts
Water spraying
is carried out
once in a day
Water can be sprayed
twice in a day for
controlling fugitive dusts.
Construction site to be
fenced to avoid dust
spreading.
Construction
materials (sand/
soil) to be kept
covered
Complied at all
site
Construction materials
like sand/soil should be
kept covered by
polythene so that strong
wind cannot blow dust
away
Emission of
fugitive gases by
the machines
due to
construction
activities can
accelerate the
air pollution.
Using new/ good
engine quality
machines/vehicle
s to avoid
incomplete
combustion.
Complied in all
sites
Switch off engines that
are not in use
Noise level
Disturbance to
workers at
worksite due to
construction
activities of the
proposed project
site.
Using modern,
low noise
generating
machineries with
silencers.
Complied in all
sites
The contractor has been
advised to cover the
machine with noise proof
hood to make the area
free from noise hazard.
Providing ear
plug/muffler to the
workers
Provided by the
authority but not
being used
Workers should be first
advised followed by
warning and then half day
salary cut for
noncompliance of safety
regulations
Waste
management
An inefficient
municipal waste
management
system may
create serious
negative impacts
like spread of
infectious
diseases, land
and water
pollution,
obstruction of
drains and loss
of bio diversity.
Using bins at
specified
dumping place for
all waste
disposal.
Temporary
sanitary latrine to
be constructed
near worker’s
shed and at work
place. Sweepers
should be
engaged for daily
cleaning.
Provided by the
authority but not
being used
properly
Workers should be first
advised followed by
warning and then half day
salary cut for
noncompliance of waste
management.
Train up the workers how
to use the dustbins
properly.
27
Monitoring Results
Environmental
and Social
Components
Potential
impacts
Monitoring
Measures Status
Corrective Action Plan
(CAP)
The contractor has been
advised to rearrange the
construction waste in
respective specific places
at Tongi site.
Specific waste
management plan should
be ensured
Latrines were
very dirty,
unhealthy and
unhygienic at
Tongi site, the
contractor does
not arrange
cleaners to
wash the toilets.
Labor sheds are
close to the
latrines and
according to the
workers, it is
very difficult to
stay in the shed
due to bad smell
from the latrines
at the Tongi site.
The contractor has been
advised to arrange
cleaners to wash the
latrines daily as only two
latrines are available for
about 50 to 60 people.
Moreover, workers have
been advised also to keep
the latrines clean after
using it.
Safety Issues Explosion
caused due to
poor
maintenance of
oxyacetylene
cylinders or due
to using faulty
cylinders; fire
caused by
mechanical/
electrical failure
of generators,
short circuit or
from kitchen
Keep Fire
Extinguisher,
sand and water
buckets near
kitchen, keep Fire
Extinguisher at
every floor of the
construction
building.
Training on “Fire
extinguisher use”
should be given
to all workers
every three
months.
Kept in some
places by the
authority but all
the workers do
not know how to
use the
extinguisher.
Most of the
extinguishers
were found out
of gas.
The contractor has been
advised to encourage the
workers to learn how to
use the extinguishers at
Tongi site. Sufficient Fire
Extinguisher must be kept
in required places where
fire hazard or explosion
may occur.
28
Monitoring Results
Environmental
and Social
Components
Potential
impacts
Monitoring
Measures Status
Corrective Action Plan
(CAP)
Ecological
resource
Change of
vegetation
coverage
specially for
terrestrial
vegetation at
sub-Station sites
during
construction
phase
Green belt will be
developed once
the construction
activities are over.
Low shrub and
herbs jungles
have been
cleared for land
development
under
construction
phase.
Tree does not
exist.
Plantation of trees inside
and around the project
boundary. Particularly
ornamental tree like Bottle
Brush, Panthapadop,
Jasmine, Radhachura
plant should be planted at
the Substation
(Aftabnagar, Purbachal
and Uttara third phase)
sites.
Source: CEGIS, January - June, 2019
29
Monitoring Results
30
I nstitutional arrangement for Monitoring and compliance
The organogram provided by the DESCO is responsible to monitor environmental compliance
during the project construction. The sub divisional engineer (electrical & civil), assistant
manager, assistant engineer (electrical) and sub assistant engineer are working under
supervision of the deputy project director for the environmental compliance monitoring for the
construction of five 132/33/11 kV grid substation in DESCO area. The project director is
responsible to supervise and guide the whole work of environmental compliance monitoring.
The following Figure 4.1 shows the institutional arrangement of those who are responsible for
ensuring monitoring of compliance in accordance with Govt. laws, rules regulations and ADB’s
loan covenants.
Figure 4.1: Institutional Arrangement for Compliance Monitoring
31
Institutional arrangement for Monitoring and compliance
32
Site Specific Environmental Management Plan
The HYOSUNG CORPORATION has been appointed by the proponent as EPC contractor
who are responsible for Environmental compliance EMP provided in EIA Report and other
safeguard policies relevant to the workplaces. Accordingly, CEGIS has been appointed to
monitor any deviation of work of EPC contractor based on the ESMPs including health and
safety issues. Although the location of the five substations are different, but the nature of work
and the local environments are more or less identical except Tongi and Banani Substations.
Tongi substation is in the industrial area and Banani is in residential area. Therefore, the
ESMPs of all these five substations are homogenous except a few issues of the
aforementioned two substations.
5.1 HSE implication
Safety is a joint venture of all employees, visitors, managers etc. The main target of EPC
contractor is to complete the work without any accident. To achieve the target, it is the
responsibility of the site managers to provide the below mentioned trainings to the workers
and others.
5.2 Training and Meeting at the Project Site for Safety
a) To conduct tool box meeting daily;
b) To arrange monthly discussion meeting;
c) To provide specific safety trainings required for the employees;
d) To arrange Mock Drills for fire and safety and other emergencies at the sites in
every 3-4 months.
5.3 Environmental Protection
Industrial Wastes
a. Only licensed disposal contractor will collect and carry the disposals;
b. All wastes including hazardous materials, liquids or chemicals will be segregated
and kept in designated bins at predetermined place;
c. Hazardous materials will be disposed of as per the DoE regulations;
d. Other wastes will either be sold to the relevant contactors or will be disposed of at
designated municipal places.
5.4 In-house Rules and Regulations
In-house rules and regulations are
a. Smoking is only allowed at designated Smoking Points;
b. Use of any band items is fully prohibited;
c. Photography within the prohibited areas are not allowed without permission from
the competent authority.
33
Site Specific Environmental Management Plan
Always Be Proactive:
a. To manage the risk during operations;
b. To identify and eliminate hazards before they become a HSE problem.
c. To upgrade employee and contractors’ work competency.
5.5 Responsibility General Site Safety & Environmental Guidelines
a. The Code of Practices according to the rules and regulations of the Government of
Bangladesh should be strictly followed;
b. Emergency assembly points for evacuation and immediate contact numbers for
respective authorities should be marked at the workplaces;
c. Emergency First Aid box should be kept at the designated places and the location
should be displayed;
d. First Aider should have medical background;
e. Safety Awareness including tool box talk should be provided to all the workers;
f. Caution boards like "NO SMOKING" etc. should be displayed;
g. Firefighting facilities like sand bucket, fire extinguisher should be provided at the
workplaces;
h. Nobody is allowed to work without PPEs;
i. Ambulance facility should be provided for emergency use;
j. Adequate lighting facilities such as hand lights and area lighting should be provided
at the worksite.
k. Daily manpower report, accident reports should be submitted to the authority;
l. Medical Report or Fitness certificate along with national ID should be kept before
engaging any worker;
m. Safety audit compliance should be prepared by contractor regularly.
34
Conclusion and Recommendations
The overall performance of EPC contractor in relation to compliance of environmental issues
detailed in EMP of the EIA report of the five substation projects are satisfactory. All work in
three out of five substations are completed and waiting for commissioning. Civil works in the
remaining two substations, Tongi substation at Tongi industrial area and Banani substation at
Banani residential area are ongoing. Based on the time to time observations and suggestions
of CEGIS monitoring team, the EPC contractor has taken necessary steps like providing
hygienic accommodations to workers, fire extinguishers in fire vulnerable places, displaying
government regulations like smoking in designated areas only, providing drinking water
facilities adjacent to worker’s shed and work place etc. EPC contractor has been advised to
provide filters in the drinking water tank. Since there is no firing of fossil fuel in these project
areas, issue of air pollution other than generation of SPM during construction period is
redundant, EPC has taken rightful action of water spraying to reduce the fugitive dust. As the
construction work is limited to day time activity only, noise generated in the Banani substation
is not a big issue for the residents of Banani. Waste management is another major
environmental issue which is not satisfactory particularly in Tongi. The monitoring team has
explained the importance of the issues and actions to be taken in detail to workers and the
EPC personals. The outcome will be observed in the next monthly monitoring. With all these
the overall performance of the EPC contractor on environmental issues can be commented
as Satisfactory.
The environmental and social monitoring team recommended following the guidelines for
Environmental Management System, and Occupational Health and Safety, which should be
strictly followed by the workers and the EPC contractors.
• The management should develop emergency preparedness and response plan for
fire and natural and manmade disasters prevention;
• The sanitation system for the workers must be improved at the Tongi site.
• Daily toolbox meetings in construction sites on health and safety, as well as the
other governing environmental and social issues should be maintained.
• An integrated drainage network should be planned for maintaining the runoff of the
rainfall;
• All Safety measures for potential risk associated with the substations including the
health, safety and environment should be adopted and implemented;
• The project proponent may provide some social services under corporate social
responsibility (CSR) to the local community in the form of subsidized medical
service, drinking water supply;
• Gardening in empty space, if available, should be done;
• Involvement of local people in terms of classified job opportunities should be
ensured.
35
Conclusion and Recommendations
36
References
Yearbook of Agricultural Statistics 2017, Bangladesh Bureau of Statistics (BBS) 2017.
Ministry of Planning, Agriculture Wing, Parishankhyan Bhaban, E-27/A, Agargaon,
Dhaka-1207.
SRDI (Soil Resource and Development Institute), 1997. Guideline for Land and Soil
Resources Utilization. Thana Nirdeshika, Farmgate, Dhaka-1212.
37
References
38
Appendix
Appendix 1: Monitoring Checklist
Category Description of
potential impact
Measures /Indicators
Due Diligence
Uttara third phase Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Monitoring Component: Physical Environment
Noise Level
Disturbance to local communities, ecosystem and workers at worksite due to construction activities of the proposed plant site.
Use modern low noise producing machineries.
✓ ✓ ✓
Partially
80%
Partially
80%
Switching off machines which are not in use.
✓ ✓ ✓ ✓ ✓
Provide hearing protection for the workers
✓ ✓ ✓ Partially
20%
Partially
20%
Follow mandatory regulations in case of night shift operations.
✓ ✓ ✓ ✓ ✓
Marinating noise level 45 dBA at the residential area and 55 dBA at day light hour
✓ ✓ ✓
Partially
20%
Partially
20%
Maximize the offset distance between noisy plant items and nearby sensitive receivers
✓ ✓ ✓
✓
✓
41
Appendix
Category Description of
potential impact
Measures /Indicators
Due Diligence Uttara third phase Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Employ effective silencing measures for equipment and other abatement techniques to minimize construction site noise.
✓ ✓ ✓
Partially
50%
Partially
50%
Ensure that all equipment is in good repair and operated in the correct manner.
✓ ✓ ✓
✓ ✓
Consult with local people /residents and building owners to address community concerns
Not applicable
for the project sites
Not applicable
for the project sites
Not applicable for
the project sites
Partially
90%
Partially
50%
Air Quality
Emission of particulate matter, SOx and NOx due to construction activity and from construction machineries.
Water spraying system to control fugitive dusts
✓ ✓ ✓ Partially
75%
Partially
75%
Restricting excavation activities such as top soil removal during period of high winds
✓ ✓ ✓ ✓ ✓
Locating stockpiles away from the sensitive receptors
✓ ✓ ✓
Partially
50%
Partially
50%
42
Appendix
Category Description of
potential impact
Measures /Indicators
Due Diligence Uttara third phase Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Carrying out progressive rehabilitation of cleared land
✓ ✓ ✓
Partially
50%
Partially
50%
Locating contractor’s compounds away from residential areas
✓ ✓ ✓
✓
Not applicable
for the project sites
Restricting the burning of waste ✓ ✓
✓ ✓ ✓
Minimize exhaust emissions from construction equipment through the regular maintenance of all construction machinery and vehicles
✓ ✓ ✓
✓ Partially
70%
Construction materials (sand/soil) to be kept covered with polythene
✓ ✓ ✓ Partially
60%
Partially
60%
Provide broad fence/ barrier to restrict wind current
✓ ✓ ✓ ✓
✓
Introduce vehicle speed limit
Not
applicable for the
Not
applicable for the
Not applicable for
Not
applicable for the
✓
43
Appendix
Category Description of
potential impact
Measures /Indicators
Due Diligence Uttara third phase Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
project sites
project sites
the project sites
project sites
Use good engine quality machines/vehicles
✓ ✓ ✓
Partially
70%
Partially
60%
Ensure that emissions from on-road and off-road vehicles should comply with Schedule 6 (Standards for emissions from motor vehicles) of ECR 1997
✓ ✓ ✓
✓
✓
Soil Characteristics
The soils of the project areas have clay loam/ silty loam to loamy texture. The area under the project would be filled up with external soils having sandy materials. Then the existing soil might turn into sandy soil in the proposed Sub-station sites.
Top soil that is to be removed should be stockpiled for site rehabilitation and landscaping works.
✓ ✓ ✓ ✓
✓
Soil-erosion and sedimentation-control measures should be undertaken in stages to minimize the area of unstable or unprotected soil surfaces
✓ ✓ ✓ ✓ ✓
Wherever possible, vegetation is to be left undisturbed
Not
applicable for the
Not
applicable for the
Not applicable for
Not
applicable for the
Not
applicable for the
44
Appendix
Category Description of
potential impact
Measures /Indicators
Due Diligence Uttara third phase Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
and retained as soil cover. If vegetation cover is not available, spread mulches over the surface to reduce dust and rainfall impact.
project sites
project sites
the project sites
project sites
project sites
All fuel storage areas and refueling vehicles are to be provided with spill –containment kits
✓ ✓ ✓ ✓ ✓
An emergency Spill Contingency plan shall be prepared by the contractor as part of the SEMP
✓ ✓ ✓ ✓ ✓
Proper deposition of loose soil and construction materials to avoid water logging
✓ ✓ ✓ Partially
70%
Partially
70%
Waste Management
An efficient municipal solid waste management system may create serious negative impacts like infectious diseases, land
Specific sites for waste disposal
✓ ✓ ✓ Partially
85%
Partially
75%
Quantification of solid wastes
✓ ✓ ✓ ✓ ✓
Location of backfilling stockpile in safe area
✓ ✓ ✓ ✓ ✓
45
Appendix
Category Description of
potential impact
Measures /Indicators
Due Diligence Uttara third phase Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
and water, pollution, obstruction of drains and loss of bio diversity.
Measures to control odour problems
✓ ✓ ✓ Partially
95%
Partially
70%
Excavated material unsuitable for fill should be disposed in an environmentally safe manner.
✓ ✓ ✓ ✓ ✓
Ensure that the waste management measures (collection, sorting, and disposal) are correctly implemented on the project site
✓ ✓ ✓
Partially
85%
Partially
60%
Ensure that correctly signed waste containers are available at convenient locations for the disposal of wastes
✓ ✓ ✓
Partially
90%
Partially
80%
Dispose of all used oil and fuel filters in a secure landfill, unless they can be recycled
✓ ✓
✓ ✓ ✓
Ensure that an adequately sized area is made available for the
✓ ✓
✓ Partially 35%
Lack of available space in the site
✓
46
Appendix
Category Description of
potential impact
Measures /Indicators
Due Diligence Uttara third phase Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
safe storage of wastes prior to collection
Ensure that all on-site wastes are suitably contained and prevented from escaping into
✓ ✓ ✓
Partially
80%
Partially
70%
Neighboring fields, properties, and waterways, and that the waste contained DoEs not contaminate soil, surface, or groundwater, or create unpleasant odours for neighbors or workers
✓ ✓ ✓
✓ ✓
Ensure the site is regularly cleaned and waste material appropriately removed, i.e., to a landfill in accordance with regulations
✓ ✓ ✓ Partially
75%
Partially
60%
Biological Environment
Bird’s habitat loss, damages of herbs, shrubs
Disturbance on wildlife movement
✓ ✓ ✓ Not
applicable for the
Not
applicable for the
47
Appendix
Category Description of
potential impact
Measures /Indicators
Due Diligence Uttara third phase Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Ecosystem and Biodiversity
Conservation
and degradation of ecosystem and biodiversity’s due to construction works.
project sites
project sites
Limiting the use of night light
✓ ✓ ✓ ✓ ✓
No plantation of non-native species
✓ ✓ ✓ ✓ ✓
The removal of vegetation shall be restricted to the development footprint, which should encompass areas that are already relatively disturbed in preference to clearing vegetation
✓ ✓ ✓ ✓ ✓
Any additional clearing for construction will compound the impacts, so ancillary facilities outside the footprint shall be avoided
✓ ✓ ✓
Not applicable
for the project sites
Not applicable
for the project sites
The construction footprint shall be clearly demarcated. The clearing boundaries are to be shown to machinery
✓ ✓ ✓
Not applicable
for the project sites
48
Appendix
Category Description of
potential impact
Measures /Indicators
Due Diligence Uttara third phase Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
operators with the instruction that machinery is not allowed to operate outside the boundaries. The area is then cleared to minimize disturbance to adjacent areas
Not applicable
for the project sites
The boundary will be fenced and the area cleared in such a way that the footprint shall not be extended during clearing works.
✓ ✓ ✓ Partially
80%
Partially
80%
If the area is to be vegetated, preference should be given to naturally occurring species that are recognized as non-invasive species.
Not yet started related initiative
Not yet started related initiative
Not yet started related initiative
Not yet started related
initiative
Not yet started related
initiative
LEGENDS:
1 = Same as Baseline
2 = Not Applicable at this stage
3 = EPC contractors hired a water spraying car, but it DoEs not spray water into the area regularly
49
Appendix
4 = In progress
5 = About 5~6 people did not receive compensation due to lack of ownership transparency
6 = Directly paid by DC office to the incumbent
7 = Some impacts are caused which are intangible
8 = EPC contractors displayed presentation only, but no document is yet available
9 = No water car was required as it was raining during this season
Complied = ✓ Partially complied= ✓ Not complied= ✓
50
Appendix-2: Field Photos on June 2019
Photo: Purbachal 132/33/11 kV Sub-Station in the study area
51
Appendix
Photo: Uttara third Phase 132/33/11 kV Substation in the study area
52
Appendix
53
Appendix
Photo: Aftabnagar 132/33/11 kV Substation in the study area
54
Appendix
55
Appendix
Photo: Banani 132/33/11 kV Sub-Station in the study area
56
Appendix
Photo: Tongi 132/33/11 kV Sub-Station in the study area
57
Appendix
58
Appendix
59
Appendix
60
Appendix-3: Terms of Reference (ToR)
Terms of Reference
For
Environmental Compliance Monitoring of “Construction of Five 132/ 33/11kV Grid Sub-
Stations”.
A. Background
The Government of Bangladesh has given top priority to the development of power sector
considering its importance in overall development of the country. In that regards Government
has made a vision and policy statement for power sector development and set the goal of
providing access to affordable and reliable electricity to all by 2021. Dhaka is the capital of
the country and its demand of electricity at present is 900 MW, considering 12% load growth
it will be 1130 MW during 2015. But as per Government vision, DESCO shall have to provide
1500 MW of electricity during 2015 and 2000 MW by 2020. To meet up this increasing demand
and government vision DESCO has taken an initiative to expand its infrastructure of the
distribution system through construction of new line, installation of new substations and
rehabilitation of existing substation in order to provide new connections to the incoming
consumers. The ongoing DESCO project is one of the steps towards achieving the goal. The
project has already obtained the site clearance certificate and the approval from DoE and has
started its construction work.
As per the ECR 1997 and the requirement of loan provider, Asian Development bank (ADB),
the project should be constructed in compliance with all the applicable Environmental and
Social Rules and Regulations of Bangladesh as well as the Environmental and Social
Management Plan and Monitoring plan described in the EIA report. The proponent has
engaged CEGIS as environmental Consultant for environmental compliance monitoring of the
project under construction.
B. Objective
The environmental monitoring program will show the path for taking precautions during and
after the contractions of the transmission line and sub-stations so that necessary steps can
be taken to rectify defects or deficiencies. The Overall objective of the monitoring consulting
service includes:
Monitoring the environmental compliance of the project construction activities to:
• Environmental and Social Safeguarding Laws and policies of Bangladesh
• Environmental and Social Management, and Monitoring Plan described in the EIA
reports as well as in the action plan ( schedule-5) in line with ADB’s requirements
and the applicable IFC’s performance standards on social and environmental
sustainability
• Provide environmental compliance monitoring report
61
Appendix
C. Location
The proposed Sub-Stations are located in the DESCO area in Bangladesh. The location is
shown in the following Map 1.1.
Map 1.1: Proposed DESCO distribution area 132/33/11kV Grid Sub-stations Location
D. Scope of Work
In line with the aforementioned objectives the scope of the services should cover the following:
i. Monitoring ambient air quality of the project site and its adjoining area before
construction stage;
ii. Review of environmental management plan and environmental monitoring plan
suggested in the EIA report in line with the action plan proposed by ADB;
iii. Upgrade (if required) the environmental monitoring framework and work plan
specifying the indicators, method, location, time, frequency of monitoring provided in
the EIA that shall be followed by the EPC contractor;
iv. Monthly monitoring of construction activities to see their compliance with national
environmental and social regulations, and IFC’s performance standards on social
and environmental sustainability;
v. Physical observation (monthly) and assess that all mitigation measures are carried
out or in place in conformity with the EMP and action plan;
vi. Monthly monitoring of implementation of environmental monitoring activities as
specified in the environmental monitoring plan
vii. Monthly monitoring of different activities of EPC contractor regarding analysis of air
quality, water quality, soil texture and quality, soil and land erosion, noise
measurement, waste management, etc. in connection with the environmental
monitoring plan;
62
Appendix
viii. Monthly monitoring of socio-economic issues like community safeguard due to
pollution, hazards and employment;
ix. Suggestion of pollution prevention and mitigation measures to ensure environmental
safeguard, to ensure compliance with national environmental and social regulations;
x. Keep close liaison with the project implementation office (Project Director), and EPC
contractor;
xi. Provide a monitoring report at the end of every six (06) months in line with the
reporting requirement of ADB satisfying equator principles.
E. Methods of Monitoring
The monitoring activities shall be carried out once in a month for a period of 36 months. At
each month the monitoring team will visit the construction site to monitor environmental
compliances through in-depth observation and Key Informant Interview (KII). If the
construction activities would extend over the 30 months’ period, the monitoring activities would
be extended as per requirement of ADB and subjected to both parties’ negotiation.
F. Monitoring Study Period
The duration of the overall study shall be 30 months. However, if the construction activities
take time longer than 30 months the study period shall also be extended.
G. Stuff Requirements and responsibilities
The environmental compliance monitoring team should consist of multidisciplinary
environmental professionals to ensure the standard of the monitoring as per the requirements
of equator principle. The team should include a team leader (Environmental Specialist), an
occupational health and safety specialist, and one environmental compliance officers (for field
activities). However, the total man-months should not exceed 50 man-months which will be
finally decided during the evaluation. The specific tasks of the individuals are briefly mentioned
below:
Sl. No. Position Responsibilities
1. Environmental
Expert/Power Plant
Expert/Team
Leader
The Specialist will prepare monitoring methodology, and
monitoring checklist in line with the requirement of ADB.
The specialist will be responsible for overseeing the monitoring
activities of the environmental compliance officers.
The specialist will keep close communication with the project
director.
The specialist will responsible for providing monitoring report to
ADB quarterly on the basis of monthly monitoring of
environmental compliance officers.
2. Occupational
health and Safety
Specialist (OHS)
The OHS specialist will be responsible to prepare checklist and
methodology for OHS monitoring in line with the IFC’s
environmental performance standard and environmental action
plan that will be followed by the environmental compliance
officers.
3. Environmental
Inspector/Environ
mental Compliance
Officers
The environmental compliance officers shall be responsible for
physical monitoring of activities with the aim of environmental
compliance monitoring.
The environmental compliance officers will visit field once in a
month.
63
Appendix
Sl. No. Position Responsibilities
4 Research
Associate (s)
Junior team for respective discipline will be needed for the
monitoring activities
D. Reporting requirements and Deliverable
The compliance monitoring reports should be prepared on the basis of monthly monitoring
and submitted to the project director at the end of six months (Half yearly). However an interim
report will be submitted at the end of every three months. An inception report within one month
from the date of signing the contract. Submission of monitoring report of first quarter at the
end of three (3) months from the date of signing contract;
• Submission of 1stmonitoring report (1st month) from the date of signing contract;
• Submission of 2nd monitoring report (6th month) from the date of signing contract;
• Submission of 3rd monitoring report (12th month) from the date of signing contract;
• Submission of 4thmonitoring report (18th month) from the date of signing contract;
• Submission of 5th monitoring report (24th month) from the date of signing contract;
• Submission of 6th monitoring report (30th month) from the date of signing contract;
All report shall be submitted to the project director in five (5) hard copies and a soft copy on
CD.
64
Appendix-4: Environmental Clearance Certificate (ECC)
65
Appendix
66
Appendix-5: Base Map of the study area
67
Appendix
68