power production - grant pud · 4/9/2019 · pp – power production ... • ferc filings by grant...
TRANSCRIPT
Quarterly Commission Update 4/9/19
Powering our way of life.
Power Production
Department Purpose and Goal
Purpose: Provide safe, secure, economical, reliable and compliant power generation under the Priest Rapid Project Federal Energy Regulatory Commission (FERC) License Project No. 2114 while supporting the Wanapum relationship.Goal: Execute the aforementioned tasks while championing a culture of safety and operational excellence with continuous focus on the guiding values of safety, innovation, service, teamwork, respect, integrity, and heritage.
Acronym List
• PP – Power Production• HPI – Human Performance Improvement• AWS – Attraction Water Supply• LB – Left Bank• RPIW – Rapid Process Improvement Workshop• ODSP – Owners Dam Safety Program• PRREIP – Priest Rapids Right Embankment Improvement
Project• JHA – Job Hazard Analysis• FOER – Forced Outage Event Report
2019 Q1 Review
• Safety Update• PP Performance• Budget Review• ODSP Final Report Out• Maximo Update/Electronic Timekeeping• Q2 Forecast• LEAN update
Safety Update
65%
70%
75%
80%
85%
90%
95%
100%
January February March April May June July August September October November
2019 PP Safety Meeting Attendance
Safety Update
• LB AWS work• 2 days to install• No negative impact to
schedule• Gained safety and
efficiencies • No more man basket work
for activity and associated stoppages
Safety UpdatePressurized Equipment
Perform Isolation – LOTO, Pipe Blinding, etc. Depressurize, drain, purge, and ventRelieve trapped pressureAnticipate residual pressure and fluidsAvoid line of fire exposureVerify Pressure is Relieved
Poor Lighting/Visibility - IndoorProvide alternative lighting FlashlightHead lampTemporary Lighting
Poor Lighting/Visibility - OutdoorProvide alternative lighting Wait or defer until visibility improves.FlashlightHead lampTemporary Lighting
Confined Space (Non-Permit Required)Review Confined Space PolicyDiscuss confined space entry safe work practicesConduct atmospheric testing (if required)Monitor access or entry (if required)Do not locate mobile engines near confined spaceProvide observer (if required)I.D. CommunicationRadioEmergency Contact NumbersClearance Tags/LOTOConfirm equipment energy sources are isolatedFlashlightRequired PPEHead LampCell PhoneDistrict PhoneEmergency Contact NumbersConfined Space PermitConfirm Retrieval EquipmentMSDS Review (if applicable)Confined Space Hazard Assessment Form
Confined Space (Hazards eliminated and atmospheric mitigated)Review Confined Space PolicyMSDS Review (if applicable)Discuss confined space entry safe work practicesConduct atmospheric testingRadioRequired PPE
• Hazard and Precaution Table
• Maximo Input ongoing• Conversion of existing
JHA’s into Job Plans• ~1600 job plans
PP Performance
60.00%
65.00%
70.00%
75.00%
80.00%
85.00%
90.00%
January February March April May June July August September October November December
2019 Availability By Month
Priest Wanapum Project Target
PP Performance
0.00%
0.05%
0.10%
0.15%
0.20%
0.25%
0.30%
0.35%
0.40%
0.45%
0.50%
January February March April May June July August September October November December
2019 PP Forced Outage Percentage
Priest Wanapum Project Target
PP Performance 2018 recap
2019 Budget and Actuals
Capital O&M
Budget $25,609,386 Directs $23,189,755
Actual $845,665 $1,374,665
Remain $24,763,731 $21,815,090
Budget $4,226,729 Labor $21,549,431
Actual $695,454 $3,104,455
Remain $3,531,275 $18,444,976
Budget $29,836,115 Total $44,739,186
Actual $1,541,119 $4,479,121
Remain $28,295,006 $1,106,703
ODSP Final Report• Multiple ODSP document updates recommended
• Program roles• Definitions and acronyms• List of references updated to include other documents• Renaming of sections to add clarity• FERC specific guidance versus what we had documented
• “Program so much better than document indicated”• “Heads and tails above others than have seen/saw”• “Well executed dam safety program just not reflected in ODSP”• EAP document• DSSMP
• Program roles• Definitions and acronyms• List of references updated to include other documents• Renaming of sections to add clarity
Electronic Timekeeping
• Priest Rapids Electricians live 3/8• Facilities live on 3/22• Priest Rapids Mechanics live on 4/5• All of PP hourly employees by end of June• Work on ingestion of labor report from Maximo direct in Great Plains
Q2 Forecast• Human Performance Trainings• Plant Manager Hirings• Lessons Learned
P08 GCB RCAWAN W-10 Isophase ExplosionWAN Spillway Gate Left Open on ClearancePR DS Gantry Crane Wire Rope GripPR Spooling wire on drumWAN DT Slip/FallWAN Foot and Cart InjuryWAN Wicket Gate Slip Trip and FallsWAN Oil Spill in DT from left open nose cone valveWAN Powerhouse FirePR Airborne Lead ReleasePR US Gantry Crane Wire Rope FailureQC Penstock Painting Clearance- Final VersionPR Rotor Inspection Contractor deathPR GSU XMFR Fire
LEAN Update
Powering our way of life.
Grant PUD Commission Meeting – April 9, 2019
Grant PUD Lands & Recreation 2019 Q2 Business Report
Powering our way of life.
Departmental Purpose and Goal• Purpose: Fulfill certain regulatory obligations under the District’s
FERC license, provide real estate support services for the District, and manage the District’s geographic information system (GIS) program.
• Goal: Execute the aforementioned tasks and services in light of the District’s Strategic Plan objectives related to maintaining a strong financial position, providing long-term low rates, providing excellent customer service, and attaining environmental compliance.
Q1 Business Review• Safety
• Non-recordable incidents = 0• Recordable incidents = 0• Safety meeting attendance = 100%
• Regulatory Review• FERC filings by Grant PUD = 0• Submitted on time = N/A• FERC approvals/orders = 1• Summary/listing of major filings:
• FERC approval of the Recreation Resources Management Plan
2019 Q1 Review• Projects & Work Activities
• SMP consultation and Commission approval
• Commission approval - Central Washington Management Group 3-year contract
• Recruitment for LRM Workers and Aides, LR Tech, Lands Specialist positions
• Campground reservation system overhaul – live March 25!
• Columbia Cliffs Land Use Application and Public Recreation Development Plan
• Crescent Bar Well 1B drilling
• Complete engineering turnover packages for CB water/wastewater systems
• Continued encroachment removal/prep for vegetation management activities
• Continued real estate, vegetation management, and GIS support
2019 Q2 Forecast• Safety Goals
• Non-recordable incidents = 0• Recordable incidents = 0• Safety meeting attendance =
100%• Full review of JHAs• Crew training
• Regulatory Outlook• Anticipated FERC filings = 3• Anticipated FERC approvals = 0 • Any regulatory threats or risks =
none known/anticipated
2019 Q2 Forecast• Projects & Work Activities
• Shoreline Management Plan submittal to FERC
• Onboard/train LRM Workers and Aides, LRM Visitors Center support position
• Prep for recreation season external stakeholder meeting
• Recruit Lands Specialist position, determine coverage for Vanessa’s tasks
• Manage Crescent Bar bio-swales and Teal Rd. crosswalk projects
• Go live with new campground reservation system
• Complete Columbia Cliffs PRDP and Encroachment Removal Plan
• Continued encroachment removal and restoration Project-wide
• Continued real estate, vegetation management, and GIS support
2019 Q2 Forecast
• Potential Management Challenges• Vantage Recreation Area• Denial of land-use applications that lack public access
• Potential Efficiency Opportunities• Succession planning• Crew support for multiple areas of recreation and shoreline
responsibilities - rec site O&M, vegetation management, encroachment removals
YTD budget-to-actuals (through Feb. 28)
2018 BudgetActuals as of 2/28/2019
Budget Remaining
% of Budget Spent Q4 YEP
% Budget to YEP
CAP $37,500 $129,498 ($91,998) 345.33% $825,080 2200.21%
O&M $1,321,606 ($21,435) $1,343,041 -1.62% $1,846,015 139.68%
Labor $1,136,019 $138,810 $997,209 12.22% $1,136,109 100.01%
TOTAL $2,495,125 $246,873 $2,248,252 9.89% $3,807,204 152.59%
Questions?
GCPUD Enterprise RiskQ2 2019 Update
Agenda• Current Business• Strategic Market Risk• District Wide Risk
Assessment• Work plan – Schedule
Adjustments
GCPUD ERM: Current Business
• 2019 Budget
KEY DETAILSThe Risk Department budget is dominated by insurance premiums.
GCPUD ERM: Current Business
• Completion of Insurance brokerage RFP• Under budget• National firms
• Preparation of CESS Claim• 2-year cross-disciplinary effort• Strategy recommendation
KEY DETAILSCompletion of overhanging work and reorientation of loss control and other programs.
Strategic Market Risk
California Power Demand: California Imports
KEY DETAILS2010 data, in millions of MWH. California imported a quarter of its needs at publication.Graph source: https://www.realclearenergy.org/charticles/2012/01/30/california_must_import_one-quarter_of_its_electricity.html
• Power generally flows north to south, east to west
• Canadian entitlement• California import
demand is a prime mover for western power prices.
California Power Demand: Supply Dynamics
KEY DETAILSHypothetical regional supply stack; the greater the energy demanded from the market, the higher the clearing price.Graph source: https://www.eia.gov/todayinenergy/detail.php?id=7590
California Power Demand: 2007 CAISO Load
KEY DETAILSRegular climb to a broad, wide peak – supports higher HLH prices.Graphic Source: https://www.caiso.com/Documents/2007AnnualReportonMarketIssuesandPerformance.pdf
California Power Demand: 2007 CAISO Load
KEY DETAILSRegular climb to a broad, wide peak – supports higher HLH prices. Graphic Source: https://www.caiso.com/Documents/2007AnnualReportonMarketIssuesandPerformance.pdf
HLH Hours
California Power Demand: Load Dynamics
KEY DETAILSThis load data includes DG (behind-the-meter) solar installations.
California Power Demand: Load Dynamics
KEY DETAILSThis load data includes DG (behind-the-meter) solar installations.
California Power Demand: Load Dynamics
KEY DETAILSThis load data includes DG (behind-the-meter) solar installations.
California Power Demand: Load Dynamics
KEY DETAILSThis load data includes DG (behind-the-meter) solar installations.
California Power: Renewable Generation
KEY DETAILSThis data represents solar, wind, and other wholesale renewable plants within California.
California Power: Renewable Generation
KEY DETAILSThis data represents solar, wind, and other wholesale renewable plants within California.
Wind
California Power: Renewable Generation
KEY DETAILSThis data represents solar, wind, and other wholesale renewable plants within California.
Wind
Solar
California Power Demand: Imports
KEY DETAILSImports are a function of the net load minus the wholesale renewable generation.
California Power Demand: Imports
KEY DETAILSImports are a function of the net load minus the wholesale renewable generation.
California Power Demand: Imports
KEY DETAILSEnergy Efficiency, DG and Wholesale solar within California are causing bulk imports to ebb, placing pressure on western HLH bulk power prices.
• California added 3-4mm people between 2007 and 2018
• >15% Increase in GDP
• Energy Efficiency• Seattle and
Portland reducing load and demand growth
District-Wide Risks
GCPUD Risk ProfileEnterprise Dashboard•All Functional Areas•A key goal is to inform the decision-making with boots-on-the-ground risk information•Warmer colors prone to move
QUADRANT ANALYSISThe center of the grid is a $100,000 impact and 50% likelihood.
GCPUD Risk ProfileEnterprise Dashboard•Functional Areas•Warmer colors prone to move
QUADRANT ANALYSISThe center of the grid is a $100,000 impact and 50% likelihood.
Danger Zone
GCPUD Risk AssessmentData Gathering•Risks are actually causes•321 risks offered•319 chosen across 54 functional areas
RISK CATALOGWe tailored the list of risks for GCPUD through management interviews and industry-specific data supplied by Logic Manager.
GCPUD Risk AssessmentData Gathering•Risks are actually causes•321 risks offered•319 chosen across 54 functional areas
RISK CATALOGWe tailored the list of risks for GCPUD through management interviews and industry-specific data supplied by Logic Manager.
GCPUD Risk AssessmentData Gathering•Risks are actually causes•321 risks offered•303 chosen across 54 functional areas
RISK CATALOGWe tailored the list of risks for GCPUD through management interviews and industry-specific data supplied by Logic Manager.
GCPUD ERM: Company-Wide Risks
Data*Annual Contributory Risk: $10MM Average Assurance: 6Functional Areas: Forecasting/Planning, Bond Compliance, Accounting, Audit, HR, PMO, Records, IT, Distribution Automation, Origination/Contract ManagementMitigation Requests: Data Warehouse/Lake, further leverage existing systems, broaden access, improve data culture/discipline through training
KEY DETAILSInformation Silos, Lack of a Single Source System, Multiple Sources of “Truth”, Inability to Organize/Integrate Data, Lack of Historical Data
GCPUD ERM: Company-Wide Risks
Lack of IT Automation/IntegrationAnnual Contributory Risk: $8MMAverage Assurance: 6Functional Areas: All PMO, Electric Shop, HR Compensation/Benefits, Transportation, Procurement, Records, ITMitigation Requests: Better leverage existing systems, better define what a ‘complete’ IT implementation will do for the team.
KEY DETAILSObsolescence/lagging behind market, Integration difficulties, Lack of adequate automation, Cybersecurity
GCPUD ERM: Company-Wide Risks
Staffing*Annual Contributory Risk: $7MM Average Assurance: 6Functional Areas: Forecasting/Planning, Accounting, Network Operations, Priest Rapids, Power Production Maintenance, Electric Shop, Security Mitigation Requests: Improve automation/data management, cultivate analysis of situations rather than processing through hiring and development
KEY DETAILSLoss of institutional knowledge through attrition (+), Lack of trained backup individuals, Market salaries increasing faster than revenues, Declining employee morale, Overworked staff
GCPUD ERM: Company-Wide Risks
Unreliable EquipmentAnnual Contributory Risk: $6MM Average Assurance: 6Functional Areas: Electric Shop, Wanapum Operations, Priest Rapids Operations, Security, Transportation, Facilities, Distribution AutomationMitigation Requests: Continue reinvestment and better organization of asset management and maintenance.
KEY DETAILSAge and condition – increases noted in Facilities and Distribution
GCPUD ERM: Company-Wide Risks
Business Continuity/RecoveryAnnual Contributory Risk: $6MM Average Assurance: 6Functional Areas: Distribution Automation, IT Network Operations, IT Systems & Programming, Transportation, Facilities, Telecom Engineering Mitigation Requests: Create plan with hierarchies of need and function so all participants are aligned. Consider exercises or stress tests.
KEY DETAILSLack of planning, Cyberattack Risk, Seismic Risk, Terrorism threat. Changes noted in Security and IT.
GCPUD ERM: Company-Wide Risks
Retail Market PressureAnnual Contributory Risk: $6MM Average Assurance: 5Functional Areas: Forecasting/Planning, Power Delivery PMO, Large Customer Care, Origination, Retail Product DevelopmentMitigation Requests: communicate company and customers’ respective positions better to key areas, trigger “Good Profit” culture
KEY DETAILSCustomer needs are not understood and prioritized, Stakeholders unwilling to compromise, Competitive retail markets/customer migration
GCPUD ERM: Company-Wide Risks
Lack of Cooperation**Annual Contributory Risk : $9MM Average Assurance: 5Functional Areas: Project Management, Procurement, Transportation, Safety, Facilities, Electric Shop, Audit, Forecasting Planning/AnalysisMitigation Requests: Clarify functional area alignment with central ownership of corporate roles, Foster inter-unit cooperation and documentation.
KEY DETAILSConflicting priorities or agendas, Ineffective Coordination, Scheduling rigidity, Plans not socialized across disciplines ahead of time, Users not involved in establishing priorities. Improvements in Finance, Safety, Meter Reading.
GCPUD ERM: Company-Wide Risks
Analysis Decision Support Errors*Annual Contributory Risk: $5MM Average Assurance: 5Functional Areas: Safety, Telecom Engineering, Accounting, Forecasting/Planning, Records, all PMOMitigation Requests: Increase delegation of decision making and ownership, Foster culture of analysis rather than processing alone, solve data problems
KEY DETAILSInadequate forecasting and budgeting, Inappropriate use of leading/lagging indicators, Lack of due diligence, Ineffective risk identification, Inadequate Correction for Deficiencies. Moved on improved assurance in financial functions.
GCPUD ERM: Company-Wide Risks
Regulatory RisksAnnual Contributory Risk: $6MM Average Assurance: 4Functional Areas: Priest Rapids Operations, Power Production Maintenance, Regulatory Affairs, IT Network Operations, Bond Compliance, Audit, OriginationMitigation Requests: proactively engage governmental stakeholders, make realistic promises, steep understanding of the positions through more key areas
KEY DETAILSNew and more expensive NERC/FERC regulatory requirements, new WA state requirements, changing political environment
Work Plans
Work Plan
PROGRESSDemonstrate measurable accomplishment of goals with demonstrable value to the District.
• By end of 2019:Q1• 2018 Major risk analysis
• By end of 2019:Q2• Risk - Middle Office functional framework
• By end of 2019:Q3• Task-based ERM Platform
• By end of 2019• Integration report – Audit, Capital activity
Thank you.Devon WilliamsRisk Manager
[email protected] grantpud.org
2018 Audit ResultsApril 9, 2019
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D
2
Public Utility District No. 2 of Grant County, Washington
Board of Commissioners
Dear Commissioners:
Thank you for your engagement of Moss Adams LLP. We are pleased
to have the opportunity to meet with you to discuss the results of our
audit of the financial statements of the District as of and for the year
ended December 31, 2018.
The accompanying presentation, which is intended solely for the use
of the Board of Commissioners and Management, and not intended to
be and should not be used by anyone other than these specified
parties, presents important information regarding the District’s
financial statements and our audit that we believe will be of interest to
you.
We conducted our audit with the objectivity and independence that
you expect. We received the full support and assistance of District
personnel. We are pleased to serve and be associated with the
District as its independent public accountants and look forward to our
continued relationship.
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D
3
1. Audit Reports Issued
2. Areas of Audit Emphasis
3. Matters Required to be Communicated
4. Upcoming Accounting Pronouncements
5. Acknowledgements and Other Information
Agenda
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D
4
Audit Reports Issued• Unmodified opinions on financial statements of Grant County Public
Utility District, which are presented fairly and in accordance with U.S. Generally Accepted Accounting Principles
• Audit and report on internal control and compliance over financial reporting in accordance with Government Auditing Standards
o No material weaknesses notedo No significant deficiencies identifiedo No compliance findings noted
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D
5
Areas of Audit Emphasis• Capital assets & Construction in Process
o Consideration of capitalization policies and potential impairment, as well as testing of additions, retirements, overhead application, capitalized interest and depreciation
• Bond Activityo Tests of revenue and refunding bonds, debt repayments, discounts and
premiums, capitalized interest, and compliance with covenantso Third-party confirmations with financial institutions
• Power Sales Transactions o Tests of sales to power purchasers, including via third party confirmationso Tests of wholesale power transactions to Shell Energy North America (U.S.), L.P.
and Avangrid Renewables, Inco Review of cash receipts and timing of revenue recognition
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D
6
Areas of Audit Emphasis (continued)• Retail Energy Sales
o Vouching of cash receipts and timing of revenue recognitiono Third-party confirmations with largest commercial power purchasers
• Net Position Classificationo Tests of classification of net investment in capital assets, restricted and
unrestricted
• Information Technology (IT) General Computer Controlso Our IT specialists tested the IT applications and IT general computer controls that
support the various financial reporting systems
• Financial Statement Footnote Disclosureso Review of the footnote disclosures for completeness and accuracy in accordance
with authoritative disclosure checklists and our knowledge of industry best practices
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D
7
Communications with Those Charged with Governance
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D
8
Our Responsibility Under U.S. Generally Accepted Auditing Standards and Government Auditing Standards
To express our opinion on whether the financial statements prepared by management with your oversight are fairly presented, in all material respects, and in accordance with U.S. GAAP. However, our audit does not relieve you or management of your responsibilities.
To consider internal control over financial reportingas a basis for designing audit procedures but not for the purpose of expressing an opinion on its effectiveness or to provide assurance concerning such internal control.
To perform an audit in accordance with generally accepted auditing standards issued by the AICPA and Government Auditing Standards issued by the Comptroller General of the United States, and design the audit to obtain reasonable, rather than absolute, assurance about whether the financial statements are free of material misstatement.
To communicate findings that, in our judgment, are relevant to your responsibilities in overseeing the financial reporting process. However, we are not required to design procedures for the purpose of identifying other matters to communicate to you.
1 2
3 4
8
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D
• Our audit was performed according to the planned scope
• Significant accounting policies are summarized in Note 1 to the financial statements o There were no changes to significant accounting policies for the year ended
December 31, 2018
o Implementation of Governmental Accounting Standards Board (GASB) Statement No. 75, Accounting and Financial Reporting for Postemployment Benefits Other Than Pensions
• No difficulties were encountered during the performance of our audit
• Financial statement disclosures were consistent, clear and understandable
• During the audit, there were no adjusting journal entries proposed or posted
Required Communications
9
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D
• Potential Effect on the Financial Statements of Significant Risks, Exposures & Uncertaintieso The District is subject to potential legal proceedings and claims that arise in the
ordinary course of business, which are disclosed in the notes to the financial statements in Note 10
• There were no disagreements with managemento Weekly meetings were held between Moss Adams and District management and
staff throughout the audit term
• Ability to continue as a going concern (no disclosure deemed necessary)• Consideration of fraud in a financial statement audit
o We are not aware of any instances of fraud or noncompliance with laws and regulations.
• Moss Adams is independent with respect to the District
Required Communications (continued)
10
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D Upcoming Accounting Pronouncements
11
• Addresses accounting and financial reporting for certain asset retirement obligations.
• Effective for 2019 financial statements
GASB 83 –Asset
Retirement Obligations
• Addresses accounting and financial reporting for leases recognizing that leases are financings of the right to use an underlying asset.
• Effective for 2020 financial statements
GASB 87 -Leases
• The audit progressed on time and in an orderly fashion; requested schedules and draft financial statements were received on a timely basis.
• All District personnel across all departments were courteous, responsive, and fulfilled all of our requests in a timely manner.
• ‘Tone at the Top’ and attitude from management was one of helpfulness and openness in response to audit requests and discussion points.
Thank you!
Acknowledgements
12
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D
Bet
ter
Toge
ther
: M
oss
Ada
ms
& G
CPU
D
13
Contact Us
Reliability Compliance Program 2019 – 2020
Gene AustinCompliance ManagerApril 09, 2019
O v e r v i e w
•RC Program Assessment•How we Manage Risk Today•Risk-Based Reliability Initiative•How we Manage Risk Tomorrow •Budget to Actual
April 09, 2019
Reliability Compliance Program
2
RC Program Assessment• Review of Policy, & Program Documentation• Interviews with Staff, Management, Owners, SMEs
• 98% strong culture of compliance • Registrations – WECC, NERC, Peak-RC• Organizational Structure
oEHQ – RnC, Engineering, IT, ServiceDesk, Internal AuditoPower ProductionoPower Delivery
• NERC Reliability Programs beyond Standards
April 09, 2019
Reliability Compliance Program
3
How we Manage Risk Today
• Strict Compliance Audit Approacho100% Review of documentation & Evidence
~650 Level 1 Requirements (~ 1,300 Total Reqmts)
oDetailed Review of 23 Self-Certification Requirementso80/20 Initial Review of Balance – 1st Review
• Detailed Review of Balance – 2nd Review on-going• 5 Self-Reported PNC’s – Open Enforcement Actions
(2) new (1) Q4-2018 (2) 2017 Audit
April 09, 2019
Reliability Compliance Program
4
Risk-Based Approach to Reliability
April 09, 2019
Reliability Compliance Program
5
How we Manage Risk Tomorrow• 2019 – Work Plan, Reliability Compliance
o Risk-Based Internal Compliance Program o Policies, Tools, Train, Tech. Forums, Streamline & Simplifyo Ancillary District Programs to Reliability Compliance
Internal Controls, Root Cause Analysis
o Close OEAs; Audit Recommendations
• 2020 - Audit Readiness• Inherent Risk Assessment• WECC ‘ICE’ Review • Consistency in Documentation & Evidence• Zero Findings of Non-Compliance – Audit and beyond
April 09, 2019
Reliability Compliance Program
5
2019 Budget and Actual 3/21/2019
$998,314
$550,448
$83,600
$333,766
$30,500 $78,537
$0 $10,402 $67,410
$725
Total CAP O&M Labor Travel and Training
April 09, 2019
Reliability Compliance Program
6