powell subs tation 21.6 witching modificat roject · 2017. 1. 25. · 4. receive, handle, and...

140
21.6 6kV S V PAGE Po Switc Volum UTILIT 640 H Page, A owell ching me III TY ENT Haul Roa Arizona 8 Subs Mod - Spec In Prof 1145 Ea TERPRI ad 86040 tation dificat cificat termounta fessional E ast South U Midvale ( ISES n tion P tions B Bidder’ Octob ain Consu Engineers, Union Ave e, Utah 84 (801) 255-1 Proje Bid # 2 s Name and A ber 20 umer Inc. enue 4047 1111 ect 207 Address 016

Upload: others

Post on 25-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

21.6

6kV S

V

PAGE

PoSwitc

Volum

UTILIT640 H

Page, A

owell ching

me III

TY ENTHaul Roa

Arizona 8

SubsMod

- Spec

In Prof 1145 Ea

TERPRIad

86040

tationdificat

cificat

termountafessional East South U

Midvale(

ISES

n tion P

tions

B

Bidder’

Octob

ain ConsuEngineers, Union Avee, Utah 84(801) 255-1

Proje

Bid # 2

s Name and A

ber 20

umerInc.

enue40471111

ect

207

Address

016

Page 2: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc. Page Utility Enterprises: Powell Substation 21.6kV Switching Modification Project

Specifications Volume III-00020-i

PAGE UTILITY ENTERPRISES POWELL SUBSTATION

21.6kV SWITCHING MODIFICATION PROJECT

VOLUME III – SPECIFICATIONS

SPECIFICATION INDEX

DOCUMENT/ DIVISION DESCRIPTION

NUMBER OF PAGES

DIVISION 1 GENERAL REQUIREMENTS 1-40 DIVISION 2 SITE WORK 41-55 DIVISION 3 CONCRETE 56-81 DIVISION 5 METALS 82-84 DIVISION 16 ELECTRICAL 85-137

Page 3: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc. Page Utility Enterprises: Powell Substation 21.6kV Switching Modification Project

Specifications Volume III-00020-ii

VOLUME III SPECIFICATIONS

TABLE OF CONTENTS

Division 1 – General Requirements

Section 01110 – Summary of Work ....................................................................................................................... 2 Section 01320 – Project Meetings, Schedules, and Reports ................................................................................... 5 Section 01330 – Submittals .................................................................................................................................. 10 Section 01520 – Field Offices and Sheds ............................................................................................................. 16 Section 01530 – Temporary Barriers and Controls .............................................................................................. 18 Section 01560 – Temporary Utilities and Facilities ............................................................................................. 22 Section 01600 – Equipment and Materials ........................................................................................................... 26 Section 01610 – Owner Furnished Equipment and Materials .............................................................................. 30 Section 01630 – Contractor Furnished Equipment and Materials ........................................................................ 31 Section 01631 – Substitutions .............................................................................................................................. 33 Section 01780 – Contract Closeout ...................................................................................................................... 35 Section 01785 – Warranties .................................................................................................................................. 39

Division 2 – Site Work

Section 02100 – Substation Site Preparation and Grading ................................................................................... 41 Section 02200 – Substation Chain Link Fence ..................................................................................................... 46 Section 02300 – Earthwork and Trenching .......................................................................................................... 50

Division 3 – Concrete

Section 02380 – Drilled Pier Foundations ............................................................................................................ 57 Section 03300 – Cast-in-place Concrete ............................................................................................................... 67

Division 5 – Metals Section 05200 – Substation Structures Erection ................................................................................................... 83

Division 16 – Electrical Section 16110 – Conduit and Accessories ............................................................................................................ 86 Section 16117 – Ductbanks .................................................................................................................................. 97 Section 16120 – Conductors – Control Cables, Low Voltage Cable, Ground Cables and Accessories ............... 99 Section 16126 – Power Cable Installation Method ........................................................................................... 113 Section 16445 – Lighting and Low Voltage Power ........................................................................................... 115 Section 16510 – Installation of Major Substation Equipment ............................................................................ 119 Section 16520 – High Voltage Bus, Insulators, Connectors, Materials, and Hardware ..................................... 124 Section 16610 – Substation Grounding .............................................................................................................. 128 Section 16700 – Field Testing ............................................................................................................................ 131

Page 4: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

DIVISION 1

GENERAL REQUIREMENTS

Page 5: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc. Page Utility Enterprises Powell Substation 21.6kV Switching Modification Project

Summary of Work Volume III-01110-2

DIVISION I - GENERAL REQUIREMENTS

SECTION 01110 - SUMMARY OF WORK PART 1 - GENERAL 1.1 SUMMARY: This Section summarizes the Work of the Project. 1.2 PROJECT DESCRIPTION

A. Project Scope

1. The work required under this project will result in replacement of Existing aerial switches mounted on wood poles with pad mounted switch gear at the Page Utility’s Powell Substation. The work will primarily include demolition of existing facilities, installation of new PME-10 Switchgear and associated bus work, grounding, conduit and 25kV cabling. Both Owner furnished and Contractor furnished materials will be used on the project. The successful contractor will be required to perform and participate in all aspects of the project process, such as material purchase, installation and testing as outlined in the drawings and specifications. Close coordination between the Contractor, the Owner, the Engineer and other Vendors (such as material suppliers) will be required in order for the project to be completed successfully and on schedule.

1.3 Work Covered by Contract Documents:

1. This Contract is entitled “Powell Substation 21.6kV Switching Modification Project” 2. The Project Site is:

(a) 640 Haul Road, Page, Arizona. 

A. Project Schedule

1. The project schedule is as follows:

(a) Bid Due Date: November 2, 2016 (b) Bid Award Date: November 29, 2016 (c) Start Project: December 12, 2016 (d) Complete Project: June 30, 2017

1.4. WORK BY/OWNER AND OTHER ACTIVITIES

A. Materials By Owner Under Other Contracts:

1. The Owner will provide equipment as indicated in the Drawings and as specified in Section 01610 of the specification.

B. Other Activities:

1. Space to receive and stage substation materials is located next to the substation. 2. Space to locate CONTRACTOR’s trailer is available at the project site. 3. Federal, state, and local regulations that affect this Contract are stated in the GENERAL

CONDITIONS of the Contract Documents.

Page 6: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises Powell Substation 21.6kV Switching Modification Project

Summary of Work

Volume III-01110-3

1.5. CONTRACTOR'S USE OF PREMISES:

A. Limited Use:

1. Limit use of the premises for storage and execution of the Work to allow for Work by other

CONTRACTOR(s). Confine operations to areas within Contract limits indicated. Portions of the Site

beyond areas in which construction operations are indicated are not to be disturbed.

2. Coordinate with other separate CONTRACTORs, other parties, and OWNER to avoid interference of

operations.

3. Conduct operations as to ensure the least inconvenience to OWNER, the general public, and agencies

as indicated in the GENERAL CONDITIONS.

1.6. WORK SEQUENCE:

A. General: The Contractor shall work with the Owner to develop a final construction sequence. The Powell

Substation, and out-going distribution circuits, are critical to system operation and maintaining power to

customers. Work Must be sequenced to allow for partial use of the substation during construction.

B. The Contractor is responsible for establishing phase rotation for out-going circuits and maintaining proper

rotation when circuits are reconnected.

C. Construct Work to provide the least possible interference to the activities of OWNER and others.

D. Scheduled Events: Schedule the Work to conform to the events and dates as indicated within this

Contract's activities.

E. Substantially Completed Areas: OWNER intends to place in service, in accordance with the provisions for

use of completed Work set forth in the GENERAL CONDITIONS, the following areas or facilities as soon

as they are Substantially Complete and ready for their intended use.

1. North Town and Gateway Distribution Circuits – April 30, 2017.

1.7. CONTRACTOR FURNISHED MATERIALS:

A. Materials furnished and paid for by OWNER are described in the specification. All other materials not

listed shall be the responsibility of the Contractor.

B. CONTRACTOR's Responsibilities:

1. Be responsible for the cost of repair or replacement of defective contractor supplied materials.

2. Designate delivery date for Materials in the construction schedule.

3. Submit materials cut-sheets to engineer for approval prior to procurement.

4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage.

5. Promptly acknowledge receipt, inspect products; record shortages and damaged or defective items on

Material Receiving Form.

6. Protect products from damage and exposure to elements.

7. Assemble, install, connect, adjust, and finish Materials as stipulated in the respective Sections of the

Specifications.

8. Provide concrete tests utilizing a reputable concrete testing firm.

9. Provide inspections required by public authorities.

1.8. COPIES OF DOCUMENTS:

A. Furnished Copies: After execution of Agreement, CONTRACTOR will be provided at no cost, a

maximum of two (2) sets of full-size Contract Drawings for the Powell Substation 21.6kV Switching

Page 7: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises Powell Substation 21.6kV Switching Modification Project

Summary of Work

Volume III-01110-4

Modification Project including revised drawings (and schedules), and a maximum of two (2) sets of the Bid

Documents in addition to those used in execution of the Agreement.

B. Additional Copies: Additional copies of above documents will be supplied by Engineer upon request at

$300.00 per one set of Drawings and one set of Bid Documents.

1.9. The list of Drawings includes the following drawing types:

A. Contract drawings.

B. Reference drawings.

END OF SECTION 01110

Page 8: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Project Meetings, Schedules, and Reports

Volume III-01320-5

DIVISION I - GENERAL REQUIREMENTS

SECTION 01320 - PROJECT MEETINGS, SCHEDULES, AND REPORTS

PART 1 - GENERAL

1.1 SUMMARY: This Section includes the following administrative and procedural requirements:

A. Project Meetings:

1. Preconstruction conference.

2. Progress meetings.

3. Coordination meetings.

B. Schedules and Reports:

1. Initial coordination submittals.

2. Construction progress schedule.

3. Construction progress reports.

C. Related Work Specified Elsewhere:

1. Submittal Requirements:

1.2 PROJECT MEETINGS

A. Preconstruction Conference:

1. The Owners Representative will administer a meeting within 3 days after the Effective Date of the

Agreement, to review items stated in the following agenda and to establish a working understanding

between the parties as to their relationships during conduct of the Work.

2. Preconstruction conference shall be attended by:

a. Contractor and his superintendent.

b. Engineer and Resident Project Representative.

c. Representative(s) of Owner.

d. At Owner's option, representatives of principal Subcontractors and Suppliers.

e. Other parties.

3. Agenda:

a. Construction schedules.

(1) Completion times.

(2) Requests for extensions of time.

b. Critical Work sequencing.

c. Designation of responsible personnel (including Designated Competent Person(s) and Contractor's

Safety Representative).

d. Subcontracts.

e. Project coordination.

f. Material and Equipment.

(1) Owner furnished.

Page 9: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Project Meetings, Schedules, and Reports

Volume III-01320-6

(2) Contractor furnished.

(3) Storage Areas.

g. Placement of signs and posters.

h. Procedures and Processing of:

(1) Field decisions.

(2) Substitutions.

(3) Submittals.

(4) Change Orders.

(5) Applications for payment.

i. Procedures for testing.

j. Procedures for maintaining record documents.

k. Use of Premises:

(1) Work and storage areas.

(2) Owner's requirements.

l. Construction facilities, controls, and construction aids.

m. Temporary utilities.

n. Safety and first-aid.

o. Security.

p. Permits required for construction.

4. Location of Meeting: Substation site.

5. Reporting:

a. Within 3 working days of the meeting, Engineer will prepare and distribute minutes of the meeting

to Owner and Contractor.

b. Contractor shall provide copies to Subcontractors and major Suppliers.

B. Progress Meetings:

1. Engineer, or Owners Representative, will schedule and administer on site progress meetings during

the course of the project. Representatives of the Owner, Engineer, and Contractor shall be present at

each meeting. With Engineer’s concurrence, Contractor may request attendance by representatives of

Subcontractors, Suppliers, or other entities concerned with current progress or involved with planning,

coordination, or performance of future activities. All participants in the meeting shall be familiar with

the Project and authorized to conclude matters relating to the Work.

2. Contractor and each Subcontractor represented shall be prepared to discuss the current construction

progress report and any anticipated future changes to the schedule. Each Subcontractor shall comment

on the schedules of Contractor and other Subcontractors and advise if their current progress or

anticipated activities are compatible with that Subcontractor's Work.

3. If one Subcontractor is delaying another, Contractor shall issue such directions as are necessary to

resolve the situation and promote construction progress.

4. Agenda:

a. Safety issues.

b. Review of construction progress since previous meeting.

c. Field observations, interface requirements, conflicts.

d. Defective workmanship.

e. Requests from Owner.

f. Problems which impede construction schedule.

g. Delivery schedules.

Page 10: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Project Meetings, Schedules, and Reports

Volume III-01320-7

h. Submittal schedules and status.

i. Site utilization.

j. Temporary facilities and services.

k. Hours of Work.

l. Hazards and risks.

m. Housekeeping.

n. Quality and Work standards.

o. Change orders.

p. Documentation of information for payment request.

q. Corrective measures and procedures to regain construction schedule if necessary.

r. Revisions to construction schedule.

s. Review of proposed activities for succeeding Work period.

t. Review proposed Contract modifications for:

(1) Effect on construction schedule and on completion date.

(2) Effect on other contracts of the Project.

u. Other business.

5. Location of Meetings: Substation site.

6. Reporting:

a. Within 5 working days of each meeting, Engineer will prepare and distribute minutes of the

meeting to Owner and Contractor.

b. Contractor shall distribute copies to principal Subcontractors and Suppliers.

C. Multiple Contract Coordination Meetings:

1. The Engineer, or Owners representative, may administer coordination meetings to be attended by

Owner or his representative and prime contractors at the Site. Contractor shall participate in such

conferences, accompanied by Subcontractors as requested by Construction Manager.

2. Agenda will be similar to that stated above for Progress Meetings.

3. Location of Meetings: Substation site.

1.3 SCHEDULES AND REPORTS:

A. Initial Coordination Schedules:

1. Within one (1) week after the Effective Date of Agreement, Contractor shall submit to Engineer for

review and acceptance:

a. A preliminary construction progress schedule. The schedule shall show the Work in a horizontal

bar chart or other graphic format, and indicate the times (number of days or dates) for starting and

completing the various stages of the Work including any milestones specified in the Contract

Documents.

b. A preliminary procurement schedule of Equipment and Materials.

c. A preliminary schedule of Submittals, as stated in SECTION 01330.

B. Construction Progress Schedule:

1. After submittal of preliminary construction progress schedule as stated above, submit a detailed

construction progress schedule within 5 days after the Effective Date of Agreement. Base the schedule

on the preliminary construction progress schedule and incorporate review comments and other

feedback. Submit 2 copies to Owners Representative for review and acceptance.

Page 11: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Project Meetings, Schedules, and Reports

Volume III-01320-8

2. The schedule shall show the Work in a horizontal bar chart or other graphic format suitable for

displaying scheduled and actual progress.

a. The schedule shall indicate phase of the Work; starting date, major milestones, and dates of

Substantial Completion and final completion.

b. Breakdown Work phases into separate time bar for each significant construction activity entry,

with dates Work is expected to begin and be completed. Within each time bar, indicate estimated

completion percentage in 10% increments.

c. Scale and spacing shall allow room for notations and revisions.

d. Sheet Size: 11" x 17".

3. Provide sub-schedules to define in more detail critical portions of schedules, if requested.

4. Engineer will review and comment on construction progress schedule and, upon agreement between

Engineer and Contractor on necessary changes:

a. Contractor shall print and distribute 2 copies of the accepted schedule to Owners Representative.

Contractor shall print additional copies for Subcontractors and other parties required to comply

with scheduled dates, one copy to each party.

5. Revise the construction progress schedule after each meeting, event, or activity where revisions have

been recognized and accepted in accordance with the GENERAL CONDITIONS.

6. Update and submit 2 copies to Engineer of the revised schedule at least once every two weeks to show

actual progress compared to the originally accepted schedule and any proposed changes in the schedule

of remaining Work. Include with construction progress report.

C. Construction Progress Schedule with Multiple Prime Contracts:

1. Contractor shall secure time commitments for performing critical construction activities from other

prime contractors. Contractor shall prepare a construction schedule taking into account the required

interfacing with work on other contracts. The schedule shall be a comprehensive, fully developed

schedule. The schedule shall be based on the preliminary construction schedule.

D. Construction Progress Reports:

1. Submit a report on actual construction progress on a weekly basis. More frequent reports may be

required should the Work fall behind the accepted schedule.

2. Construction progress reports shall consist of the revised construction progress schedule and a

narrative report which shall include but not be limited to the following:

a. Comparison of actual progress to planned progress shown on originally accepted schedule.

b. Summary of activities completed since the previous construction progress report.

c. Identification of problem areas.

d. A description of current and anticipated delaying factors, if any.

e. Impact of possible delaying factors.

f. Proposed corrective actions.

3. Submit a construction progress report to Engineer with each application for partial payment. Work

reported complete but not readily apparent to Engineer must be substantiated with supporting data

when requested by Engineer.

4. If a schedule update reveals that, through no fault of Owner, the Work is likely to be completed later

than the Contract completion date, Contractor shall establish a plan for making up lost time and submit

to Owner and Engineer for review before implementing the plan. All actions necessary to get the

Work back on schedule shall be at Contractor's expense.

Page 12: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Project Meetings, Schedules, and Reports

Volume III-01320-9

E. Schedule of Values:

1. Use values as established in Bid. Price will be used as the Schedule of Values.

F. Special Reports:

1. When an event of an unusual and significant nature occurs at the site, prepare and submit a special

report. List the chain of events, persons participating, response by Contractor's personnel, an

evaluation of the results or effects, and similar pertinent information. Advise the Owner in advance

when such events are known or predictable.

2. Submit original report to Owner and copy to Engineer.

END OF SECTION 01320

Page 13: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Submittals

Volume III-01330-10

DIVISION I - GENERAL REQUIREMENTS

SECTION 01330 - SUBMITTALS

PART 1 - GENERAL

1.1 SUMMARY:

A. This Section includes definitions, descriptions, transmittal, and review of Submittals.

B. Related Work Specified Elsewhere:

1. Project Meetings, Schedules and Reports: SECTION 01320.

2. Contract Closeout: SECTION 01780.

1.2 GENERAL INFORMATION:

A. Definitions:

1. Shop Drawings, product data, and Samples are Submittals prepared by Contractor, Subcontractor,

manufacturer, or Supplier and submitted by Contractor to Engineer as a basis for approval of the use of

Equipment and Materials proposed for incorporation in the Work or needed to describe installation,

operation, maintenance, or technical properties.

a. Shop Drawings include custom-prepared data of all types including drawings, diagrams,

performance curves, material schedules, templates, instructions, and similar information not in

standard printed form applicable to other projects.

b. Product data includes standard printed information on materials, products and systems; not

custom-prepared for this Project, other than the designation of selections from available choices.

c. Samples include both fabricated and unfabricated physical examples of materials, products, and

Work; both as complete units and as smaller portions of units of Work; either for limited visual

inspection or (where indicated) for more detailed testing and analysis. Mock-ups are a special

form of Samples which are too large to be handled in the specified manner for transmittal of

Sample Submittals.

2. Informational Submittals are those technical reports, administrative Submittals, certificates, and

guarantees not defined as Shop Drawings, product data, or Samples.

a. Technical reports include laboratory reports, tests, technical procedures, technical records, and

Contractor's design analysis.

b. Administrative Submittals are those nontechnical Submittals required by the Contract Documents

or deemed necessary for administrative records. These Submittals include maintenance

agreements, Bonds, Project photographs, physical work records, statements of applicability, copies

of industry standards, Project record data, security/protection/safety data, and similar type

Submittals.

c. Certificates and guarantees are those Submittals on Equipment and Materials where a written

certificate or guarantee from the manufacturer or Supplier is called for in the Specifications.

3. Refer to ARTICLES 1.3 and 1.4 of this Section for detailed lists of documents and specific

requirements.

Page 14: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Submittals

Volume III-01330-11

B. Quality Requirements:

1. Submittals such as Shop Drawings and product data shall be of the quality for legibility and

reproduction purposes. Every line, character, and letter shall be clearly legible. Drawings such as

reproducibles shall be useable for further reproduction to yield legible hard copy.

2. Documents submitted to Engineer that do not conform to these requirements shall be subject to

rejection by Engineer, and upon request by Engineer, Contractor shall resubmit conforming

documents. If conforming Submittals cannot be obtained, such documents shall be retraced, redrawn,

or photographically restored as may be necessary to meet such requirements. Contractor's (or his

Subcontractor's) failure to initially satisfy the legibility quality requirements will not relieve Contractor

(or his Subcontractors) from meeting the required schedule for Submittal of Shop Drawings and

product data.

C. Language and Dimensions:

1. All words and dimensional units shall be in the English language.

2. Metric dimensional unit equivalents may be stated in addition to the English units.

D. Submittal Completeness:

1. Submittals shall be complete with respect to dimensions, design criteria, materials of construction, and

other information specified to enable Engineer to review the information effectively.

2. Where standard drawings are furnished which cover a number of variations of the general class of

Equipment, each such drawing shall be individually annotated to describe exactly which parts of the

drawing apply to the Equipment being furnished. Use hatch marks to indicate variations that do not

apply to the Submittal. The use of "highlighting markers" is not an acceptable means of annotating

Submittals. Such annotation shall also include proper identification of the Submittal permanently

attached to the drawing.

3. Reproductions or copies of Contract Drawings or portions thereof will not be accepted as complete

fabrication or erection drawings. Contractor may use a reproduction of Engineer prepared Contract

Drawings for erection drawings such as to indicate information on erection or to identify detail

drawing references. Where the drawings are revised to show this additional Contractor information,

Engineer's title block is to be replaced with a Contractor's title block, and Engineer's professional seal

will be removed from the drawing. The Contractor shall revise these erection drawings for subsequent

Engineer revisions to the Contract Drawings.

1.3 COMPLIANCE SUBMITTALS:

A. Items shall include, but not be limited to, the following:

1. Rebar type and material.

2. Anchor bolt type and material.

3. Imbedded grating supports.

4. Water stop type and material.

5. Concrete mix design information.

6. All drawings, catalogs or parts thereof, manufacturer's specifications and data, samples, instructions,

and other information specified or necessary:

a. For Engineer to determine that the Equipment and Materials conform with the design concept and

comply with the intent of the Contract Documents.

B. Schedule of Submittals:

1. Prepare for Engineer's concurrence, a schedule for submission of all Submittals specified or necessary

for Engineer's approval of the use of Equipment and Materials proposed for incorporation in the Work

or needed for proper installation, operation, or maintenance. Submit the schedule with the

Page 15: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Submittals

Volume III-01330-12

procurement schedule and construction progress schedule. Schedule submission of all Submittals to

permit review, fabrication, and delivery in time so as to not cause a delay in the Work of Contractor or

his Subcontractors or any other contractors as described herein.

2. In establishing schedule for Submittals, allow 2 days in Engineer's office for reviewing original

Submittals and 2 days in Engineer's office for reviewing resubmittals.

3. The schedule shall indicate the anticipated dates of original submission for each item and Engineer's

approval thereof, and shall be based upon at least one resubmission of each item.

4. Schedule all Submittals required prior to fabrication or manufacture for submission within 3 days of

the Notice to Proceed. Schedule Submittals pertaining to storage, installation and operation at the Site

for Engineer's approval prior to delivery of the Equipment and Materials.

5. Resubmit Submittals the number of times required for Engineer's "Submittal Approved. “However,

any need for resubmittals in excess of the number set forth in the accepted schedule, or any other delay

in obtaining approval of Submittals, will not be grounds for extension of the Contract Times, provided

Engineer completes his reviews within the times stated above.

C. Transmittal of Submittals:

1. All Submittals of Equipment and Materials furnished by Subcontractors, manufacturers, and Suppliers

shall be submitted to Engineer by Contractor.

2. After checking and verifying all field measurements, transmit all Submittals to Engineer for approval

as follows:

a. Affix a Submittal Information Block to all Submittals whether prepared by Contractor,

Subcontractor, or Supplier. Affix transparent decal blocks on all Shop Drawings, and gummed

paper-type blocks on all product data type Submittals. All Submittal Information Blocks needed

for Project will be furnished to Contractor at no charge at the initial coordination conference. A

copy of the Submittal Information Block is included as an appendix to this Section.

b. Identify each Submittal by Project name and number, Contract title and number, and the

Specification Section and Article number marked thereon or in the letter of transmittal.

Unidentifiable Submittals will be returned for proper identification.

c. Check and stamp Submittals of Subcontractors, Suppliers, and manufacturers with Contractor's

approval prior to transmitting them to Engineer. Contractor's stamp of approval shall constitute a

representation to Owner and Engineer that Contractor has either determined and verified all

quantities, dimensions, field construction criteria, materials, catalog numbers, and similar data, or

Contractor assumes full responsibility for doing so, and that Contractor has coordinated each

Submittal with the requirements of the Work and the Contract Documents.

d. At the time of each submission, call to the attention of Engineer in the letter of transmittal any

deviations from the requirements of the Contract Documents.

e. Make all modifications noted or indicated by Engineer and return revised prints, copies, or

Samples until approved. Direct specific attention in writing, or on revised Submittals, to changes

other than the modifications called for by Engineer on previous Submittals. After Submittals have

been approved, submit copies thereof for final distribution. Prints of approved drawings

transmitted for final distribution will not be further reviewed and are not to be revised. If errors

are discovered during manufacture or fabrication, correct the Submittal and resubmit for review.

f. Following completion of the Work and prior to final payment, furnish record documents and

approved Samples and Shop Drawings necessary to indicate "as constructed" conditions, including

field modifications, in the number of copies specified. Furnish additional copies for insertion in

Equipment instruction books and operating manuals as required. All such copies shall be clearly

marked "PROJECT RECORD."

g. Work requiring a Submittal shall not be commenced or shipped until the Submittal has been

stamped "Submittal Approved" or "Submittal Approved as Noted" by Engineer.

h. Keep a copy or sample of each Submittal in good order at the site.

3. Quantity Requirements:

Page 16: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Submittals

Volume III-01330-13

a. Except as otherwise specified, transmit all manufacturer's or fabricator's Shop Drawings in the

quantity as follows:

(1) Initial Submittal: 2 copies to Engineer. One copy will be returned to Contractor.

(2) Resubmittals: One reproducible and 6 copies to Engineer. One copy will be returned to

Contractor.

(3) Submittal for Final Distribution: 12 copies plus the number of copies required by Contractor

to Engineer.

(4) As-Constructed Prints: 6 copies to Engineer.

b. Transmit Submittals of product data as follows:

(1) Initial Submittal: 2 copies to Engineer. One copy will be returned to Contractor.

(2) Resubmittals: 2 copies to Engineer. One copy will be returned to Contractor.

(3) Submittal for Final Distribution: 12 copies plus the number of copies required by Contractor,

to Engineer.

c. Transmit Submittals of material Samples, color charts, and similar items as follows:

(1) Initial Submittal: 2 to Engineer.

(2) Resubmittal: 2 to Engineer.

(3) Upon approval, one sample will be returned to Contractor.

d. Transmit Submittals for Reference Only - 2 copies to Engineer.

e. Owner may copy and use for internal operations and staff training purposes any and all document

Submittals required by this Contract and approved for final distribution, whether or not such

documents are copyrighted, at no additional cost to Owner.

D. Engineer's Review:

1. Engineer will review and return Submittals to Contractor with appropriate notations. Instruction books

and similar Submittals will be reviewed by Engineer for general content but not for detailed substance.

2. Engineer's approval of Submittals will not relieve Contractor from his responsibility as stated in the

General Conditions.

E. Submittal Action Stamp:

1. Engineer's review action stamp, appropriately completed, will appear on all Submittals of Contractor

when returned by Engineer. Review status designations listed on Engineer's action stamp are defined

as follows:

A - SUBMITTAL APPROVED: Signifies Equipment or Material represented by the Submittal

conforms with the design concept and complies with the intent of the Contract Documents and is

approved for incorporation in the Work. Contractor is to proceed with fabrication or procurement

of the items and with related Work. Copies of the Submittal are to be transmitted to Engineer for

final distribution.

B - SUBMITTAL APPROVED AS NOTED (RESUBMIT): Signifies Equipment and Material

represented by the Submittal conforms with the design concept and complies with the intent of the

Contract Documents and is approved for incorporation in the Work in accordance with Engineer's

notations. Contractor is to proceed with fabrication or procurement of the items and with related

Work in accordance with Engineer's notations and is to submit a revised Submittal responsive to

notations marked on the returned Submittal or written in the letter of transmittal.

C - SUBMITTAL RETURNED FOR REVISION (RESUBMIT): Signifies Equipment and

Material represented by the Submittal appears to conform with the design concept and comply

Page 17: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Submittals

Volume III-01330-14

with the intent of the Contract Documents but information is either insufficient in detail or

contains discrepancies which prevent Engineer from completing his review. Contractor is to

resubmit revised information responsive to Engineer's annotations on the returned Submittal or

written in the letter of transmittal. Fabrication or procurement of items represented by the

Submittal and related Work is not to proceed until the Submittal is approved.

D - SUBMITTAL NOT APPROVED (SUBMIT ANEW): Signifies Equipment and Material

represented by the Submittal does not conform with the design concept or comply with the intent

of the Contract Documents and is disapproved for use in the Work. Contractor is to provide

Submittals responsive to the Contract Documents.

E - PRELIMINARY SUBMITTAL: Signifies Submittals of such preliminary nature that a

determination of conformance with the design concept or compliance with the intent of the

Contract Documents must be deferred until additional information is furnished. Contractor is to

submit such additional information to permit layout and related activities to proceed.

F - FOR REFERENCE, NO APPROVAL REQUIRED: Signifies Submittals which are for

supplementary information only; pamphlets, general information sheets, catalog cuts, standard

sheets, bulletins and similar data, all of which are useful to Engineer or Owner in design,

operation, or maintenance, but which by their nature do not constitute a basis for determining that

items represented thereby conform with the design concept or comply with the intent of the

Contract Documents. Engineer reviews such Submittals for general content but not for substance.

G - DISTRIBUTION COPY (PREVIOUSLY APPROVED): Signifies Submittals which have

been previously approved and are being distributed to Contractor, Owner, Resident Project

Representative, and others for coordination and construction purposes.

1.4 INFORMATIONAL SUBMITTALS:

A. Informational Submittals are comprised of technical reports, administrative Submittals, and guarantees

which relate to the Work, but do not require Engineer approval prior to proceeding with the Work.

Informational Submittals include:

1. Field test reports.

2. Concrete cylinder test reports.

3. Certification on Materials:

a. Cement tests.

4. Warranties and guarantees.

B. Transmittal of Informational Submittals:

1. All informational Submittals furnished by Subcontractors, manufacturers, and Suppliers shall be

submitted to Engineer by Contractor unless otherwise specified.

a. Identify each informational Submittal by Project name and number, Contract title and number, and

the Specification Section and Article number marked thereon or in the letter of transmittal.

Unidentifiable Submittals will be returned for proper identification.

b. At the time of each submission, call to the attention of Engineer in the letter of transmittal any

deviations from the requirements of the Contract Documents.

2. Quantity Requirements:

a. Technical reports and administrative Submittals except as otherwise specified:

Page 18: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Submittals

Volume III-01330-15

(1) Engineer: Two copies.

b. Written Certificates and Guarantees:

(1) Engineer: 6 copies.

3. Test Reports:

a. Responsibilities of Contractor, Owner, and Engineer regarding tests and inspections of Equipment

and Materials and completed Work are set forth elsewhere in these Contract Documents.

b. The party specified responsible for testing or inspection shall in each case, unless otherwise

specified, arrange for the testing laboratory or reporting agency to distribute test reports as

follows:

(1) Owner: Two copies.

(2) Engineer: One copy.

(3) Contractor: Two copies.

C. Engineer's Review:

1. Engineer will review informational Submittals for indications of Work or Material deficiencies.

2. Engineer will respond to Contractor on those informational Submittals which indicate Work or

Material deficiency.

END OF SECTION 01330

Page 19: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises— Powell Substation 21.6kV Switching Modification Project

Field Offices and Sheds

Volume III-01520-16

DIVISION I - GENERAL REQUIREMENTS

SECTION 01520 - FIELD OFFICES AND SHEDS

PART 1 - GENERAL

1.1 SUMMARY:

A. This Section includes requirements for temporary field offices and other structures required for office and

storage space required by Contractor.

B. Related Work Specified Elsewhere:

1. Temporary Utilities and Facilities: SECTION 01560.

C. Use of Powell Substation Control Building:

1. Control Building shall not be used for field offices, lunchrooms, or for storage.

2. When permanent facilities are enclosed and habitable, provide vermin control.

PART 2 - PRODUCTS

2.1 FIELD OFFICES:

A. General:

1. Provide trailers, mobile buildings, or buildings constructed with floors raised aboveground, with steps,

landings, and railings at entrance doors.

2. Buildings shall be structurally sound, secure, and weathertight.

3. Provide appropriate type fire extinguishers at each office and storage area.

4. Maintain offices during progress of the Work.

5. Install office spaces ready for occupancy 14 days after Notice to Proceed.

B. Contractor's Office:

1. Provide field office(s) for Contractor's superintendent(s) on the Site.

2. It shall be of size required for general use, with lights, heat, cooling, furnishings, telephone service,

and other necessary facilities and utilities required by Contractor's operations.

2.2 STORAGE SHEDS AND TRAILERS:

A. On Site:

1. Provide temporary buildings or trailers required for storage of Equipment and Materials installed under

this Contract (and those furnished by Owner or others under separate contract).

2. Provide ventilation and heating as required by Equipment and Material stored.

B. Off Site:

1. Advise Engineer of any arrangements made for storage of Equipment and Materials in a place other

than Owner's Site. Furnish evidence of insurance coverage in conformance with the GENERAL

CONDITIONS.

Page 20: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises— Powell Substation 21.6kV Switching Modification Project

Field Offices and Sheds

Volume III-01520-17

PART 3 - EXECUTION

3.1 LOCATION, INSTALLATION AND MAINTENANCE:

A. General:

1. Place temporary buildings, trailers and stored materials in locations acceptable to Owner or Engineer.

2. Install field offices and sheds to resist winds and elements of the locality where installed.

3. Remove when no longer needed at the Site or when Work is completed.

4. Keep approach walks free of dust and debris.

5. At completion of Work, remove temporary buildings and trailers, foundations (if any), utility services,

and debris.

6. Prepare ground or paved areas as specified in applicable Sections.

END OF SECTION 01520

Page 21: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Temporary Barriers and Controls

Volume III-01530-18

DIVISION I - GENERAL REQUIREMENTS

SECTION 01530 - TEMPORARY BARRIERS AND CONTROLS

PART 1 - GENERAL

1.1 SUMMARY:

A. This Section includes General Requirements for:

1. Safety and protection of Work.

2. Safety and protection of existing property.

3. Barriers.

4. Security.

5. Environmental controls.

6. Access roads and parking areas.

7. Traffic control and use of roadways.

B. Related Work Specified Elsewhere:

1. Temporary Utilities and Facilities: SECTION 01560.

PART 2 - PRODUCTS - Not Applicable.

PART 3 - EXECUTION

3.1 SAFETY AND PROTECTION OF WORK AND PROPERTY:

A. General:

1. Provide for the safety and protection of the Work as set forth in GENERAL CONDITIONS. Provide

protection at all times against wind, dust, or heat so as to maintain all Work and Equipment and

Materials free from injury or damage. At the end of each day, all new Work likely to be damaged shall

be appropriately protected.

2. Notify Engineer immediately at any time operations are stopped due to conditions which make it

impossible to continue operations safely or to obtain proper results.

B. Property Other than Owners:

1. Provide for the safety and protection of property as set forth in the GENERAL CONDITIONS. Report

immediately to the owners thereof and promptly repair damage to existing facilities resulting from

construction operations.

2. The applicable requirements specified for protection of the Work shall also apply to the protection of

existing property of others.

3. Before acceptance of the Work by Owner, restore all property affected by Contractor's operations to

the original or better condition.

3.2 BARRIERS:

A. General:

Page 22: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Temporary Barriers and Controls

Volume III-01530-19

1. Furnish, install, and maintain suitable barriers as required to prevent public entry, protect the public,

and to protect the Work, existing facilities, and wildlife from construction operations. Remove when

no longer needed or at completion of Work.

2. Materials may be new or used, suitable for the intended purpose, but must not violate requirements of

applicable codes and standards or regulatory agencies.

3. Barriers shall be of a neat and reasonable uniform appearance, structurally adequate for the required

purposes.

4. Maintain barriers in good repair and clean condition for adequate visibility.

5. Relocate barriers as required by progress of Work.

6. Repair damage caused by installation and restore area to original or better condition. Clean the area.

7. Provide traffic control during construction on/ near public roads.

3.3 SECURITY:

A. Contractor shall initiate a security program at mobilization and maintain the security program throughout

the construction period until Owner’s occupancy.

B. Contractor shall be responsible for:

1. Protecting the interest of the Contractor and the Owner.

2. Keeping unauthorized personnel away from the construction area.

3.4 ENVIRONMENTAL CONTROLS:

A. Dust Control:

1. Contractor shall furnish all labor, equipment, and means required and shall carry out effective

measures as required to comply with permits and wherever and as often as necessary to prevent its

operation from producing dust in amounts damaging to property, cultivated vegetation, or domestic

animals, or causing a nuisance to persons living in or occupying buildings in the vicinity. Contractor

shall be responsible for any damage resulting from any dust originating from its operations. The dust

abatement measures shall be continued until the Contractor is relieved of further responsibility by the

Engineer.

2. Contractor shall apply non-toxic soil stabilizers according to manufacturers' specifications to all

inactive construction areas, or water at least twice daily, as needed to maintain adequate dust control.

3. Contractor shall enclose, cover, water (at least twice daily, or more frequently as needed), or apply

non-toxic soil binders according to manufacturers' specifications on all exposed piles (i.e. gravel, sand,

dirt) with a silt content of 5 percent or greater.

4. Contractor shall water active construction sites and unpaved roads at least twice daily, or more

frequently as needed.

5. If Contractor cannot maintain effective dust control under windy conditions, the Contractor shall

temporarily suspend all excavating and grading operations.

6. Contractor shall cover or maintain at least two feet of freeboard (minimum vertical distance between

the top of the load and the top of the trailer) on all trucks hauling dirt, sand, soil, or other loose

materials outside of the construction site.

7. When there is visible track-out from an unpaved road onto a paved public road, Contractor shall, as

directed, install wheel washers where the vehicles exit and enter onto the paved roads, wash the

undercarriage of trucks and any equipment leaving the Site on each trip, or sweep the paved street at

the end of each shift with a Mobil Athey or similar water spray pick-up broom-type street sweeper.

The Engineer will notify Contractor as to which measure to use to remove visible track-out.

8. The Contractor shall maintain a maximum speed limit of 15 miles per hour (mph) while on the Site and

access roads. If watering of unpaved roads is not sufficient to control dust, the Contractor shall reduce

vehicle speeds to 10 mph or less on unpaved roads.

9. Contractor shall pave or seal construction roads which have traffic volumes for sustained periods of

time of more than 50 daily trips by construction equipment, or 150 total daily trips for all vehicles, at

least 100 feet onto the site from the main road.

Page 23: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Temporary Barriers and Controls

Volume III-01530-20

B. Air Quality Control: Contractor shall maintain all vehicles and equipment in proper tune, use Best

Available Control Technology on construction equipment, including a timing retardation, use natural-gas

powered construction equipment where possible, and encourage employee car-pooling.

C. Noise Control:

1. Contractor shall comply with the hours of work as allowed by the local jurisdiction or land

management agency.

2. Noise limits on construction equipment will comply with the noise limits of the local jurisdiction or

land management agency.

D. Debris Control and Clean-Up:

1. Keep the premises free at all times from accumulations of debris, waste materials, and rubbish caused

by construction operations and employees. Responsibilities shall include:

a. Adequate trash receptacles about the Site, emptied promptly when filled.

b. Periodic cleanup to avoid hazards or interference with operations at the Site and to maintain the

Site in a reasonably neat condition.

c. The keeping of construction materials such as forms and scaffolding neatly stacked.

2. Prohibit overloading of trucks to prevent spillages on access and haul routes. Provide periodic

inspection of traffic areas to enforce requirements.

3. Final cleanup is specified in SECTION 01780 - CONTRACT CLOSEOUT.

E. Chemical Use and Pollution Control:

1. All chemicals used during project construction or furnished for project operation, whether soil

sterilant, pesticide, disinfectant, polymer, reactant or of other classification, shall show approval of

either the U.S. Environmental Protection Agency or the U.S. Department of Agriculture. Use of all

such chemicals and disposal of residues shall be in strict accordance with the printed instructions of the

manufacturer.

2. Herbicides shall not be used unless prior approval is obtained. If Contractor decides that herbicides are

needed, the Contractor shall submit a written request specifying the type of herbicide to be used to the

Engineer. The Engineer will notify the Contractor if approval has been obtained.

3. Provide methods, means, and facilities required to prevent contamination of soil, water, or atmosphere

by the discharge of hazardous or toxic substances from construction operations.

4. Provide equipment and personnel, perform emergency measures required to contain any spillages, and

remove contaminated soils or liquids. Excavate and dispose of any contaminated earth off-Site in

approved locations, and replace with suitable compacted fill and topsoil.

5. Take special measures to prevent harmful substances from entering public waters, sanitary, or storm

sewers.

F. Rodent Control:

1. Provide rodent control as necessary to prevent infestation of construction or storage areas.

2. Employ methods and use materials which will not adversely affect conditions at the Site or adjoining

properties.

3. Should the use of rodenticides be considered necessary, submit an informational copy of the proposed

program to Owner with a copy to Engineer. Clearly indicate:

a. The area or areas to be treated.

b. The rodenticides to be used, with a copy of the manufacturer's printed instructions.

c. The pollution preventive measures to be employed.

Page 24: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Temporary Barriers and Controls

Volume III-01530-21

4. The use of any rodenticide shall be in accordance with the manufacturer's printed instructions and

regulatory agencies.

3.5 ACCESS ROADS AND PARKING AREAS:

A. On-Site Roads:

1. Contractor will use existing access roads as indicated.

2. Contractor shall be responsible to construct and maintain any additional access roads required for its

construction operations. Locations of additional roads are subject to approval by Engineer and agency

having jurisdiction.

3. Contractor shall be responsible to provide safe, unobstructed, and adequate vehicular and pedestrian

access along existing roads.

B. Parking Areas:

1. Contractor shall utilize designated parking areas in locations approved by the Owner.

2. Do not allow parking in areas used for construction traffic or equipment and material storage.

3. Do not allow heavy vehicles or construction equipment in parking areas.

C. Maintenance:

1. Contractor shall maintain access roads and parking areas and restore to original, better, or specified

condition at completion of Work.

2. All temporary roads and parking areas shall be restored to their original condition, including drainage

and placement of topsoil, native surface rock and boulders, at completion of Work.

3.6 USE OF ROADWAYS:

A. Contractor’s Operations:

1. Contractor shall investigate the condition of available public and private roads and of clearances,

restrictions, bridge load limits, and other limitations affecting transportation and ingress and egress to

the site of the Work.

2. Contractor shall coordinate and pay for all agency, utility, or contractor services required for, or

associated with, hauling on public or private roads.

3. All operations shall meet the approval of owners or agencies having jurisdiction.

4. Keep traffic areas as free as possible of excavated materials and maintain in a manner to eliminate

dust, mud, and hazardous conditions.

B. Maintenance of Roadways:

1. Repair roads, walkways, and other traffic areas damaged by Contractor’s activities.

2. All repairs shall meet the approval of owners or agencies having jurisdiction.

3.7 Contractor shall comply with all of the Owner’s safety and security requirements at the project site.

END OF SECTION 01530

Page 25: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Temporary Utilities and Facilities

Volume III-01560-22

DIVISION I - GENERAL REQUIREMENTS

SECTION 01560 - TEMPORARY UTILITIES AND FACILITIES

PART 1 - GENERAL

1.1 SUMMARY:

A. This Section includes requirements of a temporary nature not normally incorporated into final Work. It

includes the following:

1. Utility services.

2. Construction and support facilities.

3. Construction aids.

4. Safety and health.

5. Fire protection.

B. Related Work Specified Elsewhere:

1. Temporary Barriers and Controls: SECTION 01530.

2. Field Offices and Sheds: SECTION 01520.

3. Summary of Work: SECTION 01110.

1.2 REFERENCES:

A. American National Standards Association (ANSI):

1. A10 Series - Safety Requirements for Construction and Demolition.

B. National Electrical Contractors Association (NECA):

1. Electrical Design Library - Temporary Electrical Facilities.

C. National Fire Protection Association (NFPA):

1. 10 - Portable Fire Extinguishers.

2. 70 - National Electrical Code.

3. 241 - Safeguarding Construction, Alterations, and Demolition Operations.

D. National Electrical Manufacturers Association (NEMA).

E. Underwriters Laboratories (UL).

1.3 QUALITY ASSURANCE:

A. Regulations: Comply with industry standards and applicable laws and regulations of authorities having

jurisdiction, including but not limited to:

1. Building Code requirements.

2. Health and safety regulations.

3. Utility company regulations.

4. Police, Fire Department, and rescue squad rules.

5. Environmental protection regulations.

Page 26: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Temporary Utilities and Facilities

Volume III-01560-23

B. Standards:

1. Comply with NFPA 10 and 241, and ANSI A10 Series standards "Temporary Electrical Facilities."

2. Comply with NEMA, NECA, and UL standards and regulations for temporary electric service. Install

service in compliance with NFPA 70.

C. Inspections: Arrange for authorities having jurisdiction to inspect and test each temporary utility before

use. Obtain required certifications and permits.

1.4 PROJECT CONDITIONS:

A. Conditions of Use: Keep temporary services and facilities clean and neat in appearance. Operate in a safe

and efficient manner. Take necessary fire prevention measures. Do not overload facilities, or permit them

to interfere with progress. Do not allow hazardous, dangerous, unsanitary conditions, or public nuisances

to develop or persist on the Site.

PART 2 - PRODUCTS

2.1 MATERIALS AND EQUIPMENT:

A. Provide new or undamaged previously used materials and equipment in serviceable condition may be used.

Provide materials and equipment suitable for the use intended, of capacity for required usage, and meeting

applicable codes and standards.

B. Water: Provide potable water approved by local health authorities.

C. Electrical Outlets: Provide properly configured, NEMA-polarized outlets to prevent insertion of 110- to

120V plugs into higher voltage outlets. Provide receptacle outlets equipped with ground-fault circuit

interrupters, reset button, and pilot light for connection of power tools and equipment.

D. Electrical Power Cords: Provide grounded extension cords. Use hard-service cords where exposed to

abrasion and traffic. Provide waterproof connectors to connect separate lengths of electric cords if single

lengths will not reach areas where construction activities are in progress. Do not exceed safe length-

voltage ratio.

E. Fire Extinguishers: Provide hand-carried, portable, UL-rated, Class A fire extinguishers for temporary

offices and similar spaces. In other locations, provide hand-carried, portable, UL-rated, Class ABC, dry-

chemical extinguishers or a combination of extinguishers of NFPA-recommended classes for the exposures.

Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and size required by location

and class of fire exposure.

PART 3 - EXECUTION

3.1 TEMPORARY ELECTRICITY AND LIGHTING:

A. Service:

1. For each Site, arrange with the Owner and provide service required for power and lighting or furnish

on-site generation with periods of operation as specified or required.

2. The electric service shall be of sufficient capacity and characteristics for the various construction tools,

machinery, lights, heating and air conditioning, pumps, and other tools required by Contractor and his

Subcontractors.

3. Provide weatherproof, grounded, power distribution system sufficient to accommodate construction

operations requiring power, use of power tools, electrical heating, and lighting. Provide overload

Page 27: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Temporary Utilities and Facilities

Volume III-01560-24

protection. Locate multiple outlets spaced so that entire area of construction can be reached by power

tools on a single extension cord of 100-foot maximum length. Supply power for electric welding, if

any, from either temporary power distribution system or by engine-driven, power-generator sets at

Contractor's option.

4. Provide adequate artificial lighting for all areas of Work when natural light is not adequate for Work.

a. Sufficient light shall be provided for general construction areas, with additional sufficient lighting

for specific tasks and to meet safety requirements.

3.2 TEMPORARY TELEPHONE SERVICE:

A. General:

1. Arrange with telephone service company and provide mobile and fixed telephone service for use by

Contractor and so Contractor can be reached at construction Site during normal working hours.

3.3 TEMPORARY SANITARY FACILITIES:

A. Contractor-Furnished Facilities:

1. Furnish, install, and maintain temporary sanitary facilities for use through construction period.

Remove on completion of Work.

2. Provide for all construction workers under this Contract and representatives at the Site.

3. Provide toilet facilities of the chemical-aerated recirculation or combustion type, properly vented, fully

enclosed with a glass- fiber-reinforced polyester shell or similar nonabsorbent material, and

conforming to Part 1926 of the OSHA Standards for Construction.

4. Establish a regular collection of all sanitary and organic wastes.

B. Use of Existing Facilities:

1. Existing restrooms facilities are not available at the project site.

3.4 TEMPORARY CONSTRUCTION AIDS:

A. General:

1. Provide construction aids and equipment required by personnel and to facilitate the execution of the

Work; scaffolds, staging, ladders, stairs, ramps, runways, platforms, railings, hoists, cranes, chutes, and

other such facilities and equipment.

2. Materials may be new or used, must be suitable for the intended purpose, and meet the requirements of

applicable codes, regulations, and standards.

3.5 TEMPORARY SAFETY AND HEALTH:

A. General: Within 30 days of Notice to Proceed, Contractor shall develop safety and health programs for

personnel at Project Site as specified in GENERAL CONDITIONS.

3.6 TEMPORARY FIRE PROTECTION:

A. General:

1. Within 30 days of Notice to Proceed, Contractor shall develop a fire prevention and protection

program for all Work under this Contract.

2. The program shall comply with the applicable provisions for safety and protection as set forth in

DOCUMENT 00700 - GENERAL CONDITIONS and with applicable parts of the NFPA 10 and 241.

3. Locate fire extinguishers where convenient and effective for their intended purpose.

Page 28: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Temporary Utilities and Facilities

Volume III-01560-25

4. Store combustible materials in containers in fire-safe locations.

5. Maintain unobstructed access to fire extinguishers, fire hydrants, temporary fire protection facilities,

stairways, and other access routes for fighting fires.

6. Provide supervision of welding operations and similar sources of fire ignition.

7. Post warning and instructions at each extinguisher location, and instruct construction personnel on

proper use of extinguishers and other available facilities at Project Site.

8. Prohibit smoking in hazardous fire exposure areas and in underground excavations. “No Smoking”

signs shall be posted in these areas.

3.7 INSTALLATION AND REMOVAL:

A. Relocation: Relocate construction aids as required by progress of construction, by storage, or Work

requirements and to accommodate requirements of Owner and other Contractors at the Site.

B. Removal: Remove temporary materials, equipment, and services when construction needs can be met and

allowed by use of permanent construction, or at completion of the Project.

C. Repair: Clean and repair damage caused by installation or by use of temporary facilities.

1. Remove foundations and underground installations for construction aids.

2. Grade the areas of the Site affected by temporary installations to required elevations and clean the area.

END OF SECTION 01560

Page 29: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Equipment and Materials

Volume III-01600-26

DIVISION I - GENERAL REQUIREMENTS

SECTION 01600 - EQUIPMENT AND MATERIALS

PART 1 - GENERAL

1.1 SUMMARY:

A. This Section includes administrative and procedural requirements governing Contractor's selection of

products for use in the Project.

B. Related Sections: The following Sections contain requirements that relate to this Section:

1. For the applicability of industry standards to products specified:

2. For submittal of Contractor's construction progress schedule and the Submittal schedule: SECTIONS

01320 and 01330.

1.2 DEFINITIONS:

A. Definitions used in this Article are not intended to change the meaning of other terms used in these

Contract Documents, such as "specialties," "systems," "structures," "finishes," "accessories," and similar

terms. Such terms are self-explanatory and have well-recognized meanings in the construction industry.

1. "Products" are items purchased for incorporation in the Work, whether purchased for the Project or

taken from previously purchased stock. The term "product" includes the terms "Material,"

"Equipment," "system," and terms of similar intent.

a. "Named Products" are items identified by the manufacturer's product name, including make or

model number or other designation, shown or listed in the manufacturer's published product

literature, that is current as of the date of the Contract Documents.

2. "Materials" are products substantially shaped, cut, worked, mixed, finished, refined or otherwise

fabricated, processed, or installed to form a part of the Work.

3. "Equipment" is a product with operational or nonoperational parts, whether motorized, or manually

operated, that may require service connections, such as wiring or piping.

1.3 QUALITY ASSURANCE:

A. Source Limitations: To the fullest extent possible, provide products of the same kind from a single source.

1. When specified products are available only from sources that do not, or cannot, produce a quantity

adequate to complete Project requirements in a timely manner, consult with Engineer to determine the

most important product qualities before proceeding. Qualities may include attributes, such as visual

appearance, strength, durability, or compatibility. When a determination has been made, select

products from sources producing products that possess these qualities, to the fullest extent possible.

2. Where possible, provide products which match products already installed in the substation.

1.4 TRANSPORTATION AND SHIPMENT:

A. Shipment Preparation:

1. Contractor shall require manufacturers and Suppliers to prepare products for shipment in a manner to

facilitate unloading and handling, and to protect against damage, deterioration, or unnecessary

exposure to the elements in transit and storage. Provisions for protection shall include the following:

Page 30: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Equipment and Materials

Volume III-01600-27

a. Crates or other suitable packaging materials.

b. Covers and other means to prevent corrosion, moisture damage, mechanical injury, and

accumulation of dirt in motors, electrical equipment, and machinery.

c. Suitable rust-preventive compound on exposed machined surfaces and unpainted iron and steel.

d. Grease packing or oil lubrication in all bearings and similar items.

B. Marking: Each product item shall be tagged or marked as identified in the delivery schedule or on

Submittals. Complete packing lists and bills of material shall be included with each shipment. Each piece

of every item need not be marked separately, provided that all pieces of each item are packed or bundled

together and the packages or bundles are properly tagged or marked.

1.5 PRODUCT DELIVERY, STORAGE, AND HANDLING:

A. Deliver, store, and handle products according to the manufacturer's recommendations, using means and

methods that will prevent damage, deterioration, and loss, including theft.

1. Schedule delivery to minimize long-term storage at the Site and to prevent overcrowding of

construction spaces. Allow ample time to avoid delay of the Work.

2. Coordinate delivery with installation time to assure minimum holding time for items that are

flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

3. Deliver products to the Site in an undamaged condition in the manufacturer's original sealed container

or other packaging system, complete with labels and instructions for handling, storing, unpacking,

protecting, and installing.

4. Inspect products upon delivery to ensure compliance with the Contract Documents and to ensure that

products are undamaged and properly protected. Inspect shipment to assure:

a. Product complies with requirements of Contract Documents and reviewed Submittals.

b. Quantities are correct.

c. Containers and packages are intact and labels are legible.

d. Products are properly protected and undamaged.

5. Store products at the Site in a manner that will facilitate inspection and measurement of quantity or

counting of units. Mark deliveries of component parts of Equipment to identify the Equipment, to

permit easy accumulation of parts, and to facilitate inspection and measurement of quantity or counting

of units.

6. Store heavy Materials away from the Project structure in a manner that will not endanger the

supporting construction.

7. Store products subject to damage by the elements above ground, under cover in a weathertight

enclosure, and with ventilation adequate to prevent condensation. Maintain temperature and humidity

within range required by manufacturer's instruction.

B. Handling:

1. Provide equipment and personnel necessary, to unload and handle products, by methods to prevent

damage or soiling to products, or packaging.

2. Handle by methods to prevent bending or overstressing. Where lifting points are designated, lift

components only at those points.

3. Provide additional protection to surrounding surfaces as necessary to prevent damage.

C. Maintenance of Storage:

1. Inspect stored products on a scheduled basis.

2. Verify that storage facilities comply with manufacturer's product storage requirements, including

environmental conditions continually maintained.

3. Verify that surfaces of products exposed to elements are not adversely affected; that any weathering of

finishes is acceptable under requirements of Contract Documents.

Page 31: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Equipment and Materials

Volume III-01600-28

D. Protection after Installation: Provide substantial coverings as necessary to protect installed products from

damage from subsequent construction operations. Remove coverings when no longer needed or as

specified.

1.6 PRODUCTS FURNISHED BY OWNER:

A. Refer to Section 01610 for detailed listing and requirements for Owner Furnished Materials.

B. Contractor to install Owner Furnished Materials as indicated in the project documents.

C. Receipt and Unloading:

1. Items furnished by Owner for installation under this Contract, unless otherwise indicated within this

specification, will be delivered to the Site complete with packing lists and bills of material. Contractor

shall furnish receipts to shipper upon delivery.

2. The Equipment contractor will provide duplicate bills of material to Resident Project Representative's

office at the Site prior to the delivery of each shipment of Equipment and Material.

3. Contractor shall receive, check, unload, inventory, accept and store all Equipment and Materials

delivered to the Site per proper notice and in accordance with manufacturer's instructions. He shall

report any damage to Engineer prior to or during unloading, and advise Engineer of any shortage at

time of delivery. Engineer will verify such reports and so notify the Equipment contractor.

4. Contractor shall be responsible for proper location of trucks for unloading and all demurrage charges

and substantiated claims for damage to trucks resulting from unloading operations.

5. Contractor is responsible for insuring Owner furnished material against incidental damage.

PART 2 - PRODUCTS

2.1 PRODUCT SELECTION:

A. General Product Requirements: Provide products that comply with the Contract Documents, that are

undamaged and, unless otherwise specified or indicated, new at the time of installation.

1. Provide products complete with accessories, trim, finish, safety guards, and other devices and details

needed for a complete installation and the intended use and effect.

2. Where available, provide standard products of types that have been produced and used successfully in

similar situations on other projects.

3. Conform to applicable Specifications, codes, standards, and regulatory agencies.

4. Comply with size, make, type, and quality specified, or as specifically approved in writing by

Engineer.

5. Do not use products for any purpose other than that for which designed or are specified.

6. To the fullest extent possible, provide products of the same kind from a single source.

7. Where products are to match or replace existing materials installed, provide products of the same type

and model presently installed.

PART 3 - EXECUTION

3.1 INSTALLATION OF PRODUCTS:

A. Comply with manufacturer's instructions and recommendations for installation of products in the

applications indicated. Anchor each product securely in place except as required for proper movement and

performance, and accurately located and aligned with other Work.

Page 32: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Equipment and Materials

Volume III-01600-29

1. Handle, install, connect, clean, condition, and adjust products in accordance with such instructions and

in conformance with specified requirements. Should job conditions or specified requirements conflict

with manufacturer's instructions, consult with Engineer for further instructions.

B. Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time

of Substantial Completion.

END OF SECTION 01600

Page 33: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Owner Furnished Equipment and Materials

Volume III-01610-30

DIVISION I - GENERAL REQUIREMENTS

SECTION 01610- OWNER FURNISHED EQUIPMENT AND MATERIALS

PART 1 -

1.1 GENERAL

A. The equipment and materials described in this section will be furnished by the Owner under separate

specifications for installation by the Contractor.

B. All Owner furnished material are presently on order or on site. Anticipated deliveries are as noted in this

section.

C. The Contractor is responsible for the proper and successful installation of all materials in the Project

whether provided by the Owner or materials provided by the Contractor.

D. The Contractor is solely responsible for proper safe guarding, handling, transporting, and installation of

these materials. The Bidder shall provide and include in the Bid Proposal any and all costs associated with

receiving, storing, insuring against loss or damage, transporting, and handling the Owner Furnished

Materials.

E. The Contractor shall be responsible for loss or damage to all materials and all equipment on the site that are

required for his portion of the work until acceptance of the complete work by the Owner. Any lost or

damaged equipment or material under the responsibilities of the Contractor shall be promptly replaced by

the Contractor at his expense.

F. Except as indicated otherwise herein, all work, labor, and additional equipment required for complete

erection of the equipment, including receiving from the carrier, unloading, and storage prior to erection,

shall be provided by the Contractor. So as not to impede construction due to shortage of miscellaneous

materials, the Contractor will be responsible for obtaining minor material due to shortfalls.

G. All Owner furnished equipment and material shall be installed by the contractor in strict accordance with

the manufacturer’s installation instructions.

H. All equipment shall be adjusted and lubricated in accordance with the Manufacturer’s instructions, so that

it is left in a satisfactory operating condition. Extreme care shall be exercised in handling porcelain parts to

avoid chipping and breakage.

I. The following is a general description of the major Owner Furnished material types or groups that will be

installed in the substation. A summary of the Owner furnished materials is found at the end of this section.

PART 2 - MATERIALS

2.1 GENERAL

A. Material items that will be provided by the Owner.

2.2 DESCRIPTION

A. The material items to be Owner furnished are as follows:

Page 34: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powell Substation 21.6kV Switching Modification Project

Owner Furnished Equipment and Materials

Volume III-01610-31

1. 8- PME-10 Switch Gear. Delivery Date: March 15, 2016.

2. 8 – Fibercrete Pad Boxes Delivery Date: December 1, 2016

3. 1- Street Light. Delivery Date: On Hand

4. 3- Bus Supports/Riser Structural Steel; 3 Static Masts Structural Steel. Delivery Date: December 1,

2016.

5. 25kV Power Cable: On-Hand

2.3 INSTALLATION

A. The Contractor shall install the materials outlined above as shown in the drawings. The Contractor shall

make all electrical connections as indicated on the drawings, as specified and in accordance with the

manufacturer’s drawings and recommendations.

2.4 DELIVERY

A. The Contractor shall receive, store, and install all Owner furnished materials as indicated.

PART 3 - MATERIALS RECEIPT

3.1 A copy of the materials receipt will be required to be provided to the Owners Representative for all

materials received for use on the project.

PART 4 - OWNER FURNISHED MATERIAL VALUE

A. For insurance purpose (contractor furnished), the following is Owner furnished equipment/Material

value:

1. SCADA-READY PME -10’ s --- $90,000 per unit ( $720,000.00 total -- 8 units)

2. Structural Steel -- $42,000.00 Total

3. 25kV 500 MCM Power Cable – $3.50 per foot.

END OF SECTION 01610

Page 35: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises— Powell Substation 21.6kV Switching Modification Projectt

Contractor Furnished Equipment and Materials

Volume III-01630-32

DIVISION I - GENERAL REQUIREMENTS

SECTION 01630 - CONTRACTOR FURNISHED EQUIPMENT AND MATERIALS

PART 1 -

1.1 GENERAL

A. All the equipment and materials not indicated to be furnished by the Owner in Section 01610 but necessary

for project construction shall be furnished and installed by the Contractor.

B. Contractor is to furnish type and kind of material as indicated in the drawing set and as provided for in

these specifications. No substitutions are allowed unless approved in writing by the Owner or Owner's

Engineer.

C. The Contractor is responsible for all unlisted miscellaneous material necessary for project construction.

END OF SECTION 01630

Page 36: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises— Powel Substation 21.6kV Switching Modification Project

Substitutions

Volume III-01631-33

DIVISION I - GENERAL REQUIREMENTS SECTION 01631 - SUBSTITUTIONS PART 1 - GENERAL 1.1 SUMMARY:

A. This Section includes administrative and procedural requirements for handling requests for substitutions made after award of the Contract.

B. Related Work Specified Elsewhere:

1. Requirements for submitting Contractor's Construction Schedule and the Submittal Schedule:

SECTIONS 01320 and 01330. 2. Requirements governing Contractor's selection of products: SECTION 01600.

1.2 DEFINITIONS:

A. Definitions in this Article do not change or modify the meaning of other terms used in the Contract Documents.

B. Substitutions: Changes in products, Materials, Equipment, and methods of construction required by the

Contract Documents proposed by the Contractor after award of the Contract are considered to be requests for substitutions. The following are not considered to be requests for substitutions:

1. Substitutions requested during the bidding period, and accepted by Addendum prior to award of the

Contract, are included in the Contract Documents and are not subject to requirements specified in this Section for substitutions.

2. Revisions to the Contract Documents requested by Owner or Engineer. 3. Specified options of products and construction methods included in the Contract Documents.

1.3 SUBMITTALS:

A. Substitution Request Submittal: Engineer will consider written requests for substitution if received within 10 days after Notice to Proceed. Requests received more than 10 days after commencement of the Work will be rejected.

1. Submit 3 copies of each request for substitution for consideration. Submit requests in the form and

according to procedures required for Change Order proposals. 2. Identify the Equipment or Material, the fabrication, or installation method to be replaced in each

request. Include related Specification Section/Article and Drawing numbers. 3. Provide complete documentation showing compliance with the requirements for substitutions, and the

following information, as appropriate:

a. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate the proposed substitution.

b. A detailed comparison of significant qualities of the proposed substitution with those of the Work specified. Significant qualities may include elements such as performance, weight, size, durability, visual effect and available maintenance, repair, and replacement service.

c. Product data, including Drawings and descriptions of products and fabrication and installation procedures.

d. Samples, where applicable or requested. e. A statement indicating the substitution's effect on Contractor's Construction Schedule compared to

the schedule without approval of the substitution. Indicate the effect of the proposed substitution on the overall Contract Times.

Page 37: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises— Powel Substation 21.6kV Switching Modification Project

Substitutions

Volume III-01631-34

f. Cost information, including a proposal of the net change, if any, in the Contract Price. g. Whether or not incorporation or use of the substitute is subject to payment of any license fee or

royalty. h. The Contractor's certification that the proposed substitution conforms to requirements in the

Contract Documents, will perform adequately the functions and achieve the results called for by the general design, is similar in substance to that specified, and is suitable for same use as that indicated and specified.

i. The Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of the failure of the substitution to perform adequately.

4. Engineer's Action: If necessary, Engineer will request additional information or documentation for

evaluation within one week of receipt of a request for substitution. Engineer will notify Contractor of acceptance or rejection of the substitution within 1 week of receipt of the request, or one week of receipt of additional information or documentation, whichever is later. Acceptance will be in the form of an approved Submittal.

PART 2 - PRODUCTS 2.1 SUBSTITUTIONS:

A. Conditions: Engineer will receive and consider Contractor's request for substitution when one or more of the following conditions are satisfied, as determined by Engineer. If the following conditions are not satisfied, Engineer will return the requests without action except to record noncompliance with these requirements.

1. Revisions to the Contract Documents are not required. 2. Proposed changes are in keeping with the general intent of the Contract Documents. 3. The request is timely, fully documented, and properly submitted. 4. The specified product or method of construction cannot be provided within the Contract Time.

Engineer will not consider the request if the product or method cannot be provided as a result of failure to pursue the Work promptly or coordinate activities properly.

5. The request is directly related to an "or-equal" clause or similar language in the Contract Documents. 6. The requested substitution offers Owner a substantial advantage, in cost, time, energy conservation, or

other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Engineer for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.

7. The specified product or method of construction cannot receive necessary approval by a governing authority, and the requested substitution can be approved.

8. The specified product or method of construction cannot be provided in a manner that is compatible with other materials and where Contractor certifies that the substitution will overcome the incompatibility.

9. The specified product or method of construction cannot be coordinated with other materials and where Contractor certifies that the proposed substitution can be coordinated.

10. The specified product or method of construction cannot provide a warranty required by the Contract Documents and where Contractor certifies that the proposed substitution provides the required warranty.

11. Where a proposed substitution involves more than one prime contractor, each contractor shall cooperate with the other contractors involved to coordinate the Work, provide uniformity and consistency, and assure compatibility of products.

B. The Contractor's submittal and Engineer's acceptance of Shop Drawings, Product Data, or Samples for

construction activities not complying with the Contract Documents do not constitute an acceptable or valid request for substitution, nor do they constitute approval.

END OF SECTION 01631

Page 38: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powel Substation 21.6 kV Switching Modification Project

Contract Closeout

Volume III-01780-35

DIVISION I - GENERAL REQUIREMENTS

SECTION 01780 - CONTRACT CLOSEOUT

PART 1 - GENERAL

1.1 SUMMARY:

A. This Section includes administrative and procedural requirements for contract closeout including, but not

limited to, the following:

1. Inspection procedures.

2. Project record document submittal.

3. Submittal of warranties.

4. Final cleaning.

B. Closeout requirements for specific construction activities are included in the appropriate Sections.

C. Related Work Specified Elsewhere:

1. Prerequisites to Substantial Completion and Final Acceptance: GENERAL CONDITIONS.

2. Submittals: SECTION 01330.

3. Warranties: SECTION 01785.

1.2 SUBSTANTIAL COMPLETION:

A. Preliminary Procedures: Before requesting inspection for certification of Substantial Completion, complete

the following. List exceptions in the request.

1. In the application for the last payment, show 100% completion for the portion of the Work claimed as

completed.

2. Advise Owner of pending insurance changeover requirements.

3. Submit specific warranties, workmanship Bonds, maintenance agreements, final certifications, and

similar documents.

4. Obtain and submit releases enabling Owner unrestricted use of the Work.

5. Complete final cleanup requirements.

6. Touch up and otherwise repair and restore marred, exposed finishes.

B. Inspection Procedures: On receipt of a request for inspection, Engineer will either proceed with inspection

or advise Contractor of unfilled requirements. Engineer will prepare inspection or advise Contractor of

construction that must be completed or corrected.

1. Engineer will repeat inspection when requested and assured by Contractor that the Work is

Substantially Complete.

2. Results of the completed inspection will form the basis of requirements for final acceptance.

1.3 FINAL ACCEPTANCE:

A. Preliminary Procedures: Before requesting final inspection for certification of final acceptance and final

payment, complete the following. List exceptions in the request.

1. Submit the final payment request with releases and supporting documentation not previously submitted

and accepted. Include insurance certificates for products and completed operations where required.

2. Submit an updated final statement, accounting for final additional changes to the Contract Price.

Page 39: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powel Substation 21.6 kV Switching Modification Project

Contract Closeout

Volume III-01780-36

3. Submit a certified copy of Engineer's final inspection list of items to be completed or corrected,

endorsed and dated by Engineer. The certified copy of the list shall state that each item has been

completed or otherwise resolved for acceptance and shall be endorsed and dated by Engineer.

4. Submit consent of surety to final payment.

5. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

B. Reinspection Procedure: Engineer will reinspect the Work upon receipt of notice that the Work, including

inspection list items from earlier inspections, has been completed, except for items whose completion is

delayed under circumstances acceptable to Engineer.

1. Upon completion of reinspection, Engineer will prepare a certificate of final acceptance. If the Work

is incomplete, Engineer will advise Contractor of Work that is incomplete or of obligations that have

not been fulfilled but are required for final acceptance.

2. If necessary, reinspection will be repeated.

1.4 RECORD DOCUMENT SUBMITTALS:

A. General: Protect record documents from deterioration and loss in a secure, fire-resistant location. Provide

access to record documents for Engineer's reference during normal working hours.

B. Record Drawings: Maintain a clean, undamaged set of black line white-prints of Contract Drawings and

Shop Drawings. Mark the set to show the actual installation where the installation varies substantially from

the Work as originally shown. Mark which drawing is most capable of showing conditions fully and

accurately. Where Shop Drawings are used, record a cross-reference at the corresponding location on the

Contract Drawings. Give particular attention to concealed elements that would be difficult to measure and

record at a later date.

1. Record information concurrently with construction progress.

2. Mark record sets with red erasable pencil. Use other colors to distinguish between variations in

separate categories of the Work. Mark each document "PROJECT RECORD" in neat, large, printed

letters.

3. Mark new information that is important to Owner but was not shown on Contract Drawings or Shop

Drawings.

4. Note related Change Order numbers where applicable.

5. Organize record drawing sheets into manageable sets. Bind sets with durable-paper cover sheets; print

suitable titles, dates, and other identification on the cover of each set.

6. Include the following:

a. Depths of various elements of foundation in relation to finish datum.

b. Horizontal and vertical locations of underground utilities and appurtenances, referenced to

permanent surface improvements.

c. Location of internal utilities and appurtenances concealed in the construction, referenced to visible

and accessible features of construction.

d. Field changes of dimension and detail.

e. Changes made by Change Order or other Modifications.

f. Details not on original Contract Drawings.

C. Record Specifications: Maintain one complete copy of the Contract Documents including Addenda.

Include with the Contract Documents one copy of other written construction documents, such as Change

Orders and Modifications issued in printed form during construction.

1. Mark these documents to show substantial variations in actual Work performed in comparison with the

text of the Specifications and modifications.

2. Give particular attention to substitutions and selection of options and information on concealed

construction that cannot otherwise be readily discerned later by direct observation.

3. Note related record drawing information and product data.

Page 40: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powel Substation 21.6 kV Switching Modification Project

Contract Closeout

Volume III-01780-37

4. Upon completion of the Work, submit record Specifications to Engineer for Owner's records.

5. Include the following:

a. Manufacturer, trade name, catalog number, and Supplier of each product and item of Equipment

actually installed, particularly optional and substitute items.

b. Changes made by Addendum, Change Order, or other Modifications.

c. Related Submittals.

D. Record Product Data: Maintain one copy of each product data Submittal. Note related Change Orders and

markup of record drawings and Specifications.

1. Mark these documents to show significant variations in actual Work performed in comparison with

information submitted. Include variations in products delivered to the Site and from the manufacturer's

installation instructions and recommendations.

2. Give particular attention to concealed products and portions of the Work that cannot otherwise be

readily discerned later by direct observation.

3. Upon completion of markup, submit complete set of record product data to Engineer for Owner's

records.

E. Record Samples Submitted: Immediately prior to Substantial Completion, Contractor shall meet with

Engineer and Owner's personnel at the Project Site to determine which Samples are to be transmitted to

Owner for record purposes. Comply with Owner's instructions regarding packaging, identification, and

delivery to Owner.

F. Miscellaneous Record Submittals: Refer to other Specification Sections for requirements of miscellaneous

record keeping and Submittals in connection with actual performance of the Work. Immediately prior to

the date or dates of Substantial Completion, complete miscellaneous records and place in good order.

Identify miscellaneous records properly and bind or file, ready for continued use and reference. Submit to

Engineer for Owner's records.

G. Warranties and Bonds: Specified in Document 00700 - GENERAL CONDITIONS, SECTION 01330, and

SECTION 01785.

1.5 FINAL CLEANING:

A. General: The General Conditions require general cleaning during construction. Regular site cleaning is

included in SECTION 01530.

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or

unit to the condition expected in a normal, commercial building cleaning and maintenance program.

Comply with manufacturer's instructions.

1. Complete the following cleaning operations before requesting inspection for certification of

Substantial Completion.

a. Clean the site, including landscape development areas, of rubbish, litter, and other foreign

substances. Sweep paved areas broom clean; remove stains, spills, and other foreign deposits.

Rake grounds that are neither paved nor planted to a smooth, even-textured surface.

2. Remove temporary structures, tools, equipment, supplies, and surplus materials.

3. Remove temporary protection devices and facilities which were installed to protect previously

completed Work.

4. Special Cleaning: Cleaning for specific units of Work is specified in applicable Sections of

Specifications.

Page 41: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises—Powel Substation 21.6 kV Switching Modification Project

Contract Closeout

Volume III-01780-38

C. Removal of Protection: Remove temporary protection and facilities installed for protection of the Work

during construction.

D. Compliance: Comply with regulations of authorities having jurisdiction and safety standards for cleaning.

Do not burn waste materials. Do not bury debris or excess materials on the Owner's property. Do not

discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from

the site and dispose of lawfully.

1. Extra materials of value remaining after completion of associated Work become Owner's property.

Dispose of these materials as directed by Owner.

E. Repairs:

1. Repair damaged protective coated surfaces.

2. Repair roads, walks, fences, and other items damaged or deteriorated because of construction

operations.

3. Restore all ground areas affected by construction operations.

END OF SECTION 01780

Page 42: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises— Powell Substation 21.6kV Switching Modification Project

Warranties

Volume III-01785-39

DIVISION I - GENERAL REQUIREMENTS

SECTION 01785 - WARRANTIES

PART 1 - SUMMARY

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for warranties required by the Contract

Documents, including manufacturers standard warranties on products and special warranties.

B. Related Sections: The following sections contain requirements that relate to this section:

1. Procedures for submitting warranties: SECTION 01330.

2. Contract closeout procedures: SECTION 01780.

C. Disclaimers and Limitations: Manufacturer’s disclaimers and limitations on product warranties do not

relieve Contractor of the warranty on the work that incorporates the products. Manufacturer’s disclaimers

and limitations on product warranties do not relieve suppliers, manufacturer’s, and subcontractors required

to countersign special warranties with Contractor.

1.2 DEFINITIONS

A. Standard product warranties are preprinted written warranties published by individual manufacturer’s for

particular products and are specifically endorsed by manufacturer to Owner.

B. Special warranties are written warranties required by or incorporated in the contract documents, either to

extend time limits provided by standard warranties or to provide greater rights for Owner.

1.3 WARRANTY REQUIREMENTS:

A. All equipment, materials and workmanship shall be warranted for a period of at least one (1) year after the

date of installation.

B. Related Damages and Losses: When correcting failed or damaged warranted construction, remove and

replace construction that has been damaged as a result of such failure.

C. Reinstatement of Warranty: When work is covered by a warranty has failed, and been corrected by

replacement or rebuilding, reinstate the warranty by written endorsement. The reinstated warranty shall be

equal to the original warranty with an equitable adjustment for depreciation.

D. Replacement Cost: Upon determination that Work covered by a warranty has failed, replace or rebuild the

work to an acceptable condition complying with requirements of the Contract Documents. Contractor is

responsible for the cost of replacing or rebuilding defective work regardless of whether Owner has

benefitted from use of the work through a portion of its anticipated useful service life.

E. Owner’s Recourse: Expressed warranties made to Owner are in addition to implied warranties and shall not

limit the duties, obligations, rights, or remedies.

1. Rejection of Warranties: Owner reserves the right to reject warranties and to limit selection to products

with warranties not in conflict with requirements of the contract documents.

F. Where the contract documents require a special warranty, or similar commitment on the work or part of the

work, Owner reserves the right to refuse to accept the work, until Contractor presents evidence required to

countersign such commitments are willing to do so.

Page 43: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises— Powell Substation 21.6kV Switching Modification Project

Warranties

Volume III-01785-40

1.4 SUBMITTALS

A. Submit written warranties to Engineer prior to the date certified for substantial completion. If the

Certificate of Substantial Completion designates a commencement date for warranties other than the Date

of Substantial Completion for the work, or a designated portion of the work, submit written warranties

upon request of Engineer.

1. When a designated portion of the work is completed and occupied or used by Owner, by separate

agreement with Contractor during the construction period, submit properly executed warranties to

Engineer within 15 days of completion of that designated portion of the work.

B. When the contract documents require Contractor, or Contractor and a Subcontractor, Supplier, or

manufacturer to execute a special warranty, prepare a written document that contains appropriate terms and

identification, ready for execution by required parties. Submit a draft to Owner, through Engineer, for

approval prior to final execution.

C. Form of Submittal: At final completion, compile 2 copies of each required warranty properly executed by

Contractor, or by Contractor, Subcontractor, Supplier, or Manufacturer. Organize the warranty documents

into an orderly sequence based on the table of contents of the contract documents.

D. Bind warranties and bonds in heavy-duty, commercial-quality, durable 3-ring, vinyl covered loose-leaf

binders, thickness as necessary to accommodate contents, and sized to receive 8 ½ by 11 inch paper.

1. Provide heavy paper dividers with celluloid covered tabs for each separate warranty. Mark the tab to

identify the product or installation. Provide a typed description of the product or installation, including

the name of the product, and the name, address, and telephone number of the installer.

2. Identify each binder on the front and spine with the typed or printed title “WARRANTIES,” and

required by SECTION 01330.

3. When warranted construction requires operation and maintenance manuals, provide additional copies

of each required warranty, as necessary, for inclusion in each required manual.

END OF SECTION 01785

Page 44: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

DIVISION 2

SITE WORK

Page 45: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Site Preparation and Grading

Volume III-02100-42

DIVISION 2 – SITE WORK

SECTION 02100 - SUBSTATION SITE PREPARATION AND GRADING

PART 1 - SCOPE

1.1. WORK INCLUDED

A. The work required under this section consists of all excavation, backfilling, grading, and related items

necessary to complete the work indicated on the drawings and as specified herein and generally listed.

B. Preparation and clearing of site area.

C. Grading of site and access road.

D. Construction and/or installation of culverts and other drainage structures and drainage ditches.

E. Surfacing of access road and station area.

1. The term "access roads" shall be defined as that part of the indicated roads inside or outside the fenced

enclosure of the substation and extending to the designated public thoroughfare. Road areas to include

all areas indicated in the drawings.

2. The term "station area" shall be defined as that part of the site in the fenced enclosure, plus the

immediate adjacent area surrounding the fenced enclosure as specified or indicated on the drawings.

F. Maintenance of all bench marks, monuments, or other reference points and replacement as directed if

disturbed or destroyed.

G. Excavation and backfill for concrete work, underground conduit, and ground grid.

PART 2 - MATERIALS

2.1. SUBGRADE FILL

A. Subgrade fill shall be free of roots and other organic matter, refuse, ashes, cinders, ice, frozen earth, or

other unsuitable material.

B. Fill material may be friable sandy or silty clay including rock containing fine material sufficient to provide

a dense mass free of voids and capable of satisfactory compaction. Maximum particle size shall not exceed

three inches.

C. Moisture content shall be optimum in accordance with ASTM D 1557.

D. Material containing gravel, stones, or shale particles greater in dimension than ½ of the depth of the layer to

be compacted is unacceptable.

E. Immediately prior to surfacing, the subgrade shall be shaped to the grade and cross section indicated on the

Drawings. The top 6 inches of the subgrade shall be compacted to 95 percent of the maximum dry density.

During compaction, the subgrade shall be ± 2 percent of the optimum moisture content as determined by

ASTM D1557. This operation shall include any scarifying, reshaping, and wetting required to obtain the

specified compaction. Soft, organic, and other unacceptable material shall be removed from the subgrade

and replaced with material meeting the requirements of the section titled "EARTHWORK AND

TRENCHING."

Page 46: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Site Preparation and Grading

Volume III-02100-43

F. Any deviation of the subgrade surface in excess of 1 inch, as indicated by a 16 foot straightedge or template

cut to typical section, shall be corrected by loosening, adding or removing material, reshaping, and

compacting.

2.2. CRUSHED ROCK

A. The crushed rock to be supplied shall meet the requirements of the American Association of State Highway

Officials Specifications for highway materials except as modified below. The sieve sizes listed for each

type of crushed rock are U.S. Standard and the percentage passing is by weight.

B. Surfacing: Crushed quarry rock, 1-1/2-inch to 3/8", meeting the following requirements:

1. Percentage of wear, Los Angeles Abrasion Test, shall not exceed 30.

2. Only quarry rock will be acceptable.

3. Gradation - as shown on drawings and paragraph 3.4.B of this section.

2.3. ACCESS ROAD SURFACING

A. Access road surfacing material shall be free of all foreign or organic material and shall consist of crushed

quarry rock of the following gradation:

Sieve Size Percent Passing by Weight

2

1 ½

1

3/4

½

3/8

No. 4

No. 30

No. 200

--

100

--

98

85

--

55

25

10

B. The Engineer may approve other gradations which have a record of satisfactory use in the local area.

C. Compaction of road base material should be completed in six inch layers and consolidated with moisture to

obtain maximum compaction.

PART 3 - WORKMANSHIP

3.1. SITE PREPARATION

A. Clearing and Grubbing

1. The site shall be cleared of rocks, boulders, trees, stumps, brush, and other vegetation.

2. Stones and boulders 6 inches or greater in the longest dimension shall be removed to a depth of 6

inches below finished subgrade in fill areas, on the access road, and in the fenced enclosure.

3. The site of all grading shall be stripped of sod to a depth of 6 inches or to such greater depth as may be

necessary to remove roots of grass and other vegetation.

4. The Contractor shall be responsible for disposal of all debris, resulting from site preparation

operations, including trees, brush, roots, and sod stripping. The Contractor shall dispose of all

materials in a manner acceptable to the Engineer and Owner.

Page 47: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Site Preparation and Grading

Volume III-02100-44

B. Grading of Substation Site and Access Roads

1. After the site has been satisfactorily cleared, the area indicated shall be graded to the subgrade section

as shown on the drawings.

2. The Contractor shall cut and fill as required to construct subgrades to the elevations and grades shown

on the drawings.

3. Remove all unsuitable material and replace with approved fill material, and perform all wetting,

drying, shaping, and compacting required to prepare a suitable subgrade.

4. Blasting will not be permitted.

5. Fill material shall be placed in layers not to exceed 8 inches and be compacted to a hard dense mass as

follows:

(a) Each lift or layer shall be compacted with a sheepsfoot roller conforming to the type used for

highway work with an approximate minimum weight of 90 pounds per linear inch of drum and a

minimum load on each sheepsfoot of 100 pounds of cross-sectional area of the sheepsfoot in

contact with the ground. The feet shall project not less than 7 inches from the face of the drum of

the roller.

(b) Water shall be added if necessary to obtain optimum moisture content for proper compaction.

(c) The sheepsfoot rolling of each layer or lift shall be continued until the "sheepsfoot" shall "walk

out" to the extent of at least ½ of their protruding length. The term "walk out" means the amount

of daylight beneath the sheepsfoot roller drum and the earth.

(d) Any material in the subgrade incapable of compaction to densities specified shall be removed and

replaced with acceptable fill material.

(e) After proper compaction, the graded area shall be shaped and fine graded to the section shown on

the drawings. The accumulation of loose material incidental to fine grading shall be incorporated

into the subgrade by means of a 5-ton pneumatic roller or other suitable means of compaction.

(f) Leave any borrow areas graded to drain and to present a neat appearance.

(g)

3.2. EXCAVATIONS FOR FOOTINGS AND OTHER CONCRETE WORK

A. The Contractor shall take precautions to ensure no damage to existing facilities or equipment, or to other

work.

B. Excavation shall include all materials found within the designated limits for excavation.

C. Excavate width adequately to permit efficient erection and removal of forms.

D. Trim to neat lines where details call for concrete to be deposited against earth.

E. Restore bottom of excavation to proper elevation with concrete in areas overexcavated.

F. Excavate by hand in areas where space and access will not permit use of machines.

G. Notify the Engineer immediately if suitable bearing is not encountered at the depth indicated on drawings.

Proceed as instructed by the Engineer.

H. Weight bearing surfaces shall be moistened with water and mechanically tamped firm and uniform.

I. Excavation for cable trenches and grounding materials shall be made in accordance with the drawings.

J. Rock excavation may require jackhammers or the use of rippers.

K. Blasting may be permitted only as approved in writing by the Owner and Engineer.

L. Control grading around excavations to prevent surface water from flowing into excavation areas.

Page 48: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Site Preparation and Grading

Volume III-02100-45

M. Drain or pump as required to continually maintaining excavated area free of water or mud from any source,

and discharging to approved drains or channels.

N. Remove subgrade material rendered unsuitable by excessive wetting and replace with approved backfill

material.

O. Waste materials, including excess materials unsuitable for use in backfilling, shall be disposed of by

hauling and removing such materials from the site.

3.3. BACKFILL OF EXCAVATIONS

A. Backfill material shall conform to the specifications of subgrade fill. After footings, concrete work, or

cable conduits are in place, the Contractor shall place backfill in accordance with the following:

1. Perform any wetting or drying of the backfill material as required and compact to obtain the specified

subgrade density.

2. Do not place backfill material on snow, ice, or frozen earth.

3. Backfill against concrete work only after concrete has attained 70 percent design strength.

4. Perform backfilling simultaneously on all sides of walled structures and only after construction of the

structure is complete.

5. Compaction material shall be placed in layers not exceeding 6 inches depth after compaction. Lift

materials shall be moistened and compacted to a density of 95 percent as determined by ASTM D1557.

6. Compact fill material with use of vibratory compactors or power tampers.

7. Avoid the use of heavy equipment adjacent to structures or concrete work.

3.4. SUBSTATION FINAL GRADE

A. A uniform layer of gravel surfacing shall be applied to the subgrade elevations after backfill of all

excavations is complete. The area to be covered shall include the fenced area, plus five (5) feet outside the

fence on all sides.

B. Materials used for crushed rock surfacing shall be composed of a layer four to six inches thick over the area

indicated on the drawings. The crushed rock layer will consist of the following: (AASHTO M147-65

Grade B)

Percent Passing by Weight Sieve Size

100

30-40

5-10

0

1-1/2"

1"

3/8"

No. 4

C. The final grade gravel surface shall be smoothed and compacted with a 5-ton pneumatic roller, steel drum

roller, or other means as approved by the Engineer to a hard, dense mass.

D. The layer shall be free of all foreign material.

E. A berm at least six inches above the initial surface grade and twelve inches wide shall be located one foot

inside the substation perimeter fence.

3.5. ACCESS ROAD SURFACING

Page 49: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Site Preparation and Grading

Volume III-02100-46

A. Prior to the placement of surfacing material, the roadbed shall be shaped and crowned for its full width to

the grade and section shown on the drawings with a crown as shown.

B. All exposed rock larger than 3 inches and any unstable soil shall be removed and replaced with acceptable

fill material.

C. The finished roadbed shall be smooth and uniform and shall be maintained in this condition until surfacing

material is placed.

D. The surfacing material shall be placed on the roadbed in sufficient quantities and uniformly spread to such

thickness and width that when the work is completed, the requirements of the typical cross-section for the

finished road are fulfilled and do not vary more than ½-inch from a template cut to the cross-section of the

road. The road grade parallel to the centerline shall not vary more than ½-inch from a 10-foot straightedge

applied at any location on the road. Variations in excess of the above shall be corrected by loosening,

adding or removing material, reshaping, and compacting.

E. Compacting shall be done at the optimum moisture content for compaction and shall be performed with a

5-ton pneumatic roller, a steel drum roller, or other means as approved by the Engineer.

END SECTION 02100

Page 50: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Chain Link Fence

Volume III-02200-47

DIVISION 2 – SITE WORK

SECTION 02200 - SUBSTATION CHAIN LINK FENCE

PART 1 - SCOPE

1.1. WORK INCLUDED

A. This section covers the work necessary for the material and installation/repair of the substation perimeter

chain link security fence.

1.2. The substation fence shall consist of woven steel fabric on steel posts. The fence shall be a minimum of 8

feet high with line posts no greater than 10 feet apart. More specific requirements are further described

under the Material and Erection sections of this Specification.

A. The primary components of the fence are:

1. Fabric

2. Line Posts

3. End and Corner Posts

4. Gate Posts

5. Top Rail

6. Barbed Wire

7. Extension Arms

8. Stretcher Bars

9. Post Braces

10. Tension Wire

11. Gate Frames

12. Hardware (Hinges, Latches, Stops, Keepers, Ties, Clips, Bands)

PART 2 - MATERIALS

2.1. HEIGHT

A. The overall fence shall stand 8 feet above grade when erected, including barbed wire. A combination of 7

feet of fence fabric and a 1 foot extension utilizing three strands of barbed wire.

2.2. FABRIC

A. The fabric for the fence shall be chain link heavily zinc-coated (galvanized) steel by hot-dip process after

weaving, 84 inches high, No. 9 USWG steel wire woven in a 2-inch mesh. The minimum breaking

strength of the wire shall be 1200 lbs. The sides of the mesh pattern shall be approximately 45 degrees to a

vertical line. Top and bottom selvages shall have a twisted and barbed finish, barbing to be done by cutting

wire on a bias, thus creating sharp points.

B. The fabric shall be galvanized in accordance with ASTM A392, Class II.

C. Wire pickets from which this fabric is made shall have a tensile strength of at least 70,000 pounds per

square inch, based on the cross-sectional area of the wire.

2.3. LINE, END, CORNER, PULL AND GATE POSTS

A. All posts shall be steel and conform to the sizes as listed for the specific type of application. Tubular

material should conform to ASTM A53 Grade B, for round shapes. Roll-formed sections shall meet the

Page 51: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Chain Link Fence

Volume III-02200-48

yield stress requirements of ASTM A36 as a minimum. All tubular posts shall be galvanized in accordance

with ASTM A120. Roll-formed sections shall be galvanized in accordance with ASTM A123.

B. LINE POSTS shall be 2-3/8 inch O.D. with a 0.154 inch wall thickness. Posts shall be of sufficient height

to; (a) accommodate a 7 foot fabric; (b) accommodate extension arms, and (c) be embedded 3 feet into the

concrete footing.

C. GATE POSTS for a 3 foot swing-gate shall be 2-7/8 inch O.D. with a 0.203 inch wall thickness. Posts

shall be of sufficient height to; (a) accommodate a 7 foot fabric; (b) accommodate extension arms, and (c)

be embedded 3 feet into the concrete footing.

D. END, CORNER, AND PULL POSTS shall be 2-7/8 inch O.D. with a 0.203 inch wall thickness. Posts

shall be of sufficient height to; (a) accommodate a 7 foot fabric; (b) accommodate extension arms or extend

1 foot extra, and; (c) be embedded 3 feet into the concrete footing.

E. GATE POSTS for a 20 foot double gate shall be 4 inch O.D. with a 0.226 inch wall thickness. Posts shall

be of sufficient height to; (a) accommodate a 7 foot fabric; (b) accommodate extension arms, and (c) be

embedded 3 feet into the concrete footing.

2.4. TOP RAIL

A. Top rails shall be round steel pipe or tubing galvanized in accordance with ASTM A120. The minimum

size shall not be less than 1-5/8 inch O.D. nor have a minimum wall thickness less than .138 inch. Lengths

should be a minimum of 20 feet. Provisions for adequately joining lengths together and securing to end or

corner posts shall be compatible for the physical size of the top rail. Couplings shall be of the outside

sleeve type, at least 16 inches in length. The top rail shall employ suitable fittings to allow for the

expansion and contraction of top rail, as recommended by the manufacturer. The top rail shall pass through

base of line post tops and form a continuous brace from end-to-end of each stretch of fence. The top rail

shall be securely fastened to terminal posts by pressed steel connections.

2.5. GATE FRAMES

A. Gate frames shall be constructed of tubular steel members which shall be welded at the joints. Additional

horizontal and vertical struts may be required to provide for a rigid gate panel allowing for no visible sag or

twist. Gate frames shall be made to have approximately 3 inch clearance above the road. The gate

location(s) shall be as shown on the Drawings.

B. Fabric for the gate panels shall be the same as the fence. Gate frame and bracing members shall not be less

than the structural equivalent of 2 inch O.D. standard pipe. Steel tension rods and turnbuckles may also be

utilized. Gate frame shall have provisions for three lines of barbed wire above fabric. All gate frame

material shall be hot-dip galvanized.

C. The 3 foot swing gate and the 20 foot double swing driveway gate(s) shall both have provisions for locking

closed and for securing the gate(s) in the open position (per plans).

2.6. BARBED WIRE

A. Barbed wire shall consist of two strands of No. 12-1/2 USWG steel wire with 4-point barbs at a maximum

spacing of 4 inches apart. The wire shall be galvanized after weaving in accordance with ASTM A121,

Class 3.

2.7. EXTENSION ARMS

A. The extension arms shall extend upward and outward from the fence at an angle of 45 degrees. Gate posts

shall have a ball top. Arms shall extend vertically on all gates and gate posts. There shall be provisions for

three equally spaced lines of barbed wire on the extended arms. The uppermost wire shall be

Page 52: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Chain Link Fence

Volume III-02200-49

approximately 1 foot vertically above the fabric. Barbed wires shall be securely fastened in slots by heavy

wire pins. Arms having projections to be bent down over barbed wires shall not be used.

B. The line post extension arms shall be made of pressed steel SAE 10.25. End and corner post arms shall be

of malleable iron and should be capable of supporting a downward force of 300 pounds. The extension

arms shall be galvanized in accordance with ASTM A153, Class B1.

2.8. STRETCHER BAR

A. Stretcher bars shall be galvanized steel bars not less than 1/4 inch x 3/4 inch. They shall be approximately

1 inch less than the fabric height.

B. The stretcher bar shall be used for securing the fabric to all terminal posts.

2.9. POST BRACES

A. Post braces are required at each gate, corner, pull and end post. It shall consists of a strut, which shall be 1-

5/8 inch O.D. with a minimum wall thickness not less than 0.138 inch, and a tension rod with turnbuckle.

The rod shall be steel and have a minimum diameter of 3/8 inch.

B. The strut shall be secured to the adjacent line post at approximately mid-height of the fabric. The tension

rod is also secured near this area on the line pole and is anchored near the base of the corner post (or gate,

pull or end post). Bracing members shall be all hot-dip galvanized per ASTM 153.

2.10. TENSION WIRE

A. Tension wire shall not be less than No. 7 USWG galvanized steel wire. Wire shall be interlaced at the

bottom of the fence fabric. Suitable attachments for the tension wire shall be provided.

2.11. HARDWARE

A. HINGES shall be heavy duty malleable iron ball-and-socket and allow 180 degree swing of all gate leaves.

The hinges shall not twist or turn under the action of the gate and shall provide ease of operation.

B. LATCHES, STOPS AND KEEPERS shall all be heavy duty construction of galvanized steel or malleable

iron. Latches shall have a heavy duty drop bar. The center stop shall be made to be cast in concrete and

engage the drop bar. A keeper shall be provided which will secure the free end of the gate in the open

position.

C. Hardware shall allow for gate operation from either side with provisions for securing with padlock.

Padlock will be accessible from both sides of the gate regardless of the latching arrangement.

D. BANDS, WIRE TIES AND CLIPS for securing fabric to top rails, line posts, terminal posts and tension

wires shall be galvanized steel and of adequate strength for the purpose intended.

2.12. INSULATED SECTION

A. Provided insulated fence sections as detailed in the drawings.

B. Insulated sections shall electrically isolate the substation fence system and ground grid from the existing

water treatment facility fencing.

C. The insulated section shall be a minimum of 10' in length to prevent a person from being able to touch both

the existing and substation fences at the same time.

Page 53: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Chain Link Fence

Volume III-02200-50

PART 3 - ERECTION

3.1. The fabric shall be placed on the outside of the posts, stretched taut and secured to the posts, top rail and

tension wire. The fabric shall be secured to the line posts with wire ties or metal bands at maximum

intervals of 14 in. The top and bottom edges shall be secured, respectively, to the top rail and tension wire

with wire ties not exceeding intervals of 24 inches.

3.2. Fabric for fencing shall all be either a left-hand or right-hand weave. Rolls of fabric shall be joined

together by weaving a single strand into the end of the roll to form a continuous piece.

3.3. The spacing of line posts (10 feet max.) shall in general be measured parallel to the ground. All posts shall

be placed in a vertical position with the strong axis parallel to the fabric.

3.4. All posts shall be set in holes and backfilled with concrete. Concrete shall have a minimum compressive

strength of 3000 psi at 28 days with a maximum size of aggregate of 1 inch. The concrete shall be well

worked (rodded) in the hole. The top of the backfill shall have a crown watershed finish.

3.5. The minimum diameter of holes for line posts shall be 18 inches and for terminal posts 20 inches.

3.6. The minimum depth of the holes shall be 3 feet for all posts in soil, all posts to extend a minimum of 2'-8

inch and 1'-8 inch into the hole respectively.

3.7. The fence shall be grounded in accordance with Section 16610 - Substation Grounding.

PART 4 - INSPECTION

4.1. The inspector shall review the fence installation to check the following:

A. Fence fabric and wires are properly tensioned in accordance with the Manufacturer's recommendations.

B. All gates, posts, braces and ties are sturdy and installed properly.

C. Compliance with material specifications.

4.2. Errors in the installation of the fence shall be corrected by the Contractor at no expense to the Owner as

directed by the Inspector and/or the Engineer.

END SECTION 02200

Page 54: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Earthwork and Trenching

Volume III-023200-51

DIVISION 2 – SITE WORK

SECTION 02300 - EARTHWORK AND TRENCHING

PART 1 -

1.1. GENERAL

A. This section covers general earthwork and includes preparation of the construction areas; removal and

disposal of debris; excavation and trenching; the handling, storage, transportation, and disposal of

excavated material; sheeting, shoring and projection work; preparation of subgrades; dewatering; protection

of adjacent construction; backfill; pipe embedment; construction of fills and embankments; surfacing and

grading; and other appurtenant work.

1.2. SHEETING AND SHORING

A. The stability of previously constructed structures and facilities shall not be impaired or endangered by

excavation work. Previously constructed structures and facilities include both structures and facilities

existing when this construction began and structures and facilities already provided under these

specifications.

B. Adequate sheeting and shoring shall be provided to protect and maintain the stability of previously

constructed structures and facilities and the sides of excavations until they are backfilled. Sheeting,

bracing, and shoring shall be designed and built to withstand all loads caused by earth movement or

pressure adjacent surcharges and shall maintain the shape of the excavation.

1.3. REMOVAL OF WATER

A. Adequate dewatering equipment shall be provided to remove and dispose of all surface and ground water

entering excavations and other parts of the work. Each excavation shall be kept dry. Ground water level

shall be maintained at least 12 inches below the bottom of each excavation. Dewatering shall continue

until the construction is no longer affected by ground or surface water.

B. Surface water shall be diverted and prevented from entering trenches.

1.4. BLASTING

A. Blasting is not anticipated to be used. However, if unknown situations occur during construction and

blasting is approved by the Owner and Engineer, the Contractor shall be responsible for all damage caused

by his blasting operations.

1.5. CLASSIFICATION OF EXCAVATED MATERIALS

A. No classification of excavated materials will be made. Excavation work shall include the removal and

handling of excavated materials regardless of the type, character, composition, or condition.

B. Rock that cannot be handled and compacted as earth shall be kept separate from other excavated materials

and shall not be mixed with backfill, fill or embankment materials.

1.6. FREEZING WEATHER RESTRICTIONS

A. Backfill and fill shall not be placed during freezing weather unless approved by the Engineer. Earth

material shall not be placed on frozen surfaces, and frozen materials, snow, or ice shall not be placed in any

fill or backfill.

Page 55: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Earthwork and Trenching

Volume III-023200-52

1.7. UNAUTHORIZED EXCAVATION

A. Material excavated below the bottom of concrete structures supported by the subgrade shall be replaced

with concrete placed monolithic with the concrete above. Material excavated below structures supported

on piers shall be replaced with crushed rock or gravel. The crushed rock or gravel shall be compacted to a

density equal to or greater than the density of the adjacent undisturbed soil.

1.8. TESTING

A. Laboratory testing shall be performed by a certified independent testing laboratory acceptable to the

Owner. Field sampling shall be performed by qualified personnel or the testing laboratory.

B. At least one field density determination shall be performed for each 2,000 cubic yards of compacted

material. Field samples shall be taken at locations selected by the Owner. If additional field control tests

are necessary, in the opinion of the Owner, such tests shall be made.

C. Maximum density for compacted sand and cohesive materials shall be determined in accordance with

ASTM D1557. The terms "maximum density" and "optimum moisture content" shall be as defined in

ASTM D1557.

D. Relative density for compacted crushed rock materials shall be determined in accordance with ASTM

D4253and D4254. The term "relative density" shall be as defined in ASTM D4354.

E. A copy of each test result shall be promptly furnished to the Owner.

1.9. SITE PREPARATION

A. Subgrades for permanent construction, including subgrades for fills and embankments, shall be stripped of

surface vegetation, sod, debris and organic topsoil. Surface vegetation shall be removed complete with

roots to a depth of not less than 6 inches below the ground surface.

B. All combustible and other waste materials shall be removed from the construction areas. Disposal shall be

as specified in Section 01110. Open burning is not permitted at the site.

1.10. ROADWAY ROADBEDS

A. Roadway and roadbed construction shall include excavation, subgrade preparation and construction of fills

and embankments. In excavated roadbed areas, overburden shall be removed and the subgrade shaped to

line, grade, and cross section. Compaction shall be to a depth of at least 6 inches and to at least 95 percent

of the maximum dry density. The material shall be placed at ± 2 percent of the optimum moisture content.

Compaction shall be determined by ASTM D1557. Soft, organic, and other unacceptable material shall be

removed from the subgrade and replaced. The replacement material shall meet the requirements of the

paragraph titled STRUCTURE BACKFILL.

B. Materials shall not be stored or stockpiled on subgrades.

1.11. FILLS AND EMBANKMENTS

A. Fills and embankments shall be constructed to lines and grades indicated on the Drawings.

1. Materials:

(a) To the maximum extent available, suitable materials obtained from excavation shall be used for

the construction of fills and embankments. Additional material shall be obtained from borrow

areas.

Page 56: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Earthwork and Trenching

Volume III-023200-53

(b) Fill and embankment material shall be earth only and shall be free from rocks or stones larger than

6 inches in their greatest dimension, brush, stumps, logs, roots, debris, and organic or other

deleterious materials. No rocks or stones shall be placed in the upper 18 inches of any fill or

embankment. Rocks or stones within the allowable size limit may be incorporated in the

remainder of fills and embankments provided compaction requirements are met.

2. Subgrade Preparation:

(a) The subgrade shall be leveled and compacted. The subgrade surface shall be well bonded to the

previous layers of fill.

3. Placement and Compaction:

(a) Fill and embankment materials shall be placed in approximately horizontal layers not to exceed 8

inches in uncompacted thickness. Material deposited in piles or windrows shall be spread and

leveled before compaction.

(b) Each layer of material shall have the best practicable uniform moisture content required to obtain

the specified compaction. Water shall be added and worked into each layer using harrow, disk,

blade, or other acceptable equipment to provide uniform moisture content. Each layer shall be

thoroughly compacted to at least 95 percent of the maximum dry density. The material shall be

placed at ± 2 percent of the optimum moisture content as determined by ASTM D1557. If the

material fails to meet the specified density, compaction methods shall be altered.

4. Borrow Areas:

(a) Material necessary to complete fills and embankments shall be excavated from borrow areas and

hauled to the fill or embankment site. Additional borrow material will be available, if needed,

from the Owner or shall be furnished from an acceptable source.

(b) The location, size and shape of borrow areas shall be acceptable to the Owner. Borrow areas shall

be regular in shape, with finish graded surfaces when completed. Side slopes shall not be steeper

than three horizontal to one vertical and shall be uniform for its entire length.

1.12. STRUCTURE EXCAVATION

A. Excavation for structures shall be completed to the designated lines and elevations. Machine excavation

shall be controlled to prevent undercutting the subgrade elevations indicated on the drawings. Machinery

shall not be used within 5 feet of permanent structures and facilities. Only hand tools shall be used for

excavation around existing permanent structures and facilities.

B. Construction areas shall be kept as free as possible from obstructions. Work shall not interfere with the

transportation, storage, or handling of materials. Excavated materials that meet the specified requirements

may be used for the fills, embankments, and backfills.

C. Vertical faces of excavations shall not be undercut to provide for extended footings.

1.13. STRUCTURE AND TRENCH SUBGRADES

A. Subgrades for structures and the bottom of trenches shall be firm, dense, free from mud, thoroughly

compacted, and sufficiently stable to remain firm and intact. Compaction shall be to at least 95 percent of

the maximum dry density. The material shall be placed at ± 2 percent of the optimum moisture content as

determined by ASTM D1557.

B. Trench subgrades that run beneath roads or pass through structural backfill shall be compacted to at least 95

percent of the maximum dry density as determined by ASTM D1557. The moisture content shall be ±2

percent of optimum.

Page 57: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Earthwork and Trenching

Volume III-023200-54

C. Subgrades that are otherwise solid, but become mucky on top due to construction operations, shall be

stabilized by reinforcing them with one or more layers of crushed rock or gravel.

D. The finished elevation of stabilized structure subgrades shall not be above the subgrade elevations indicated

on the Drawings.

1.14. STRUCTURE BACKFILL

A. Backfill around and outside of structures shall be deposited in layers not to exceed 6 inches in uncompacted

thickness. Backfill shall be mechanically compacted to at least 95 percent of the maximum dry density.

The material shall be placed at ± 2 percent of the optimum moisture content as determined by ASTM

D1557. Compaction of structure backfill by rolling will be permitted provided the desired compaction is

obtained and damage to the structure is prevented. Compaction of structure backfill by inundation with

water will not be permitted.

B. Backfill materials shall be composed of earth only and shall not contain wood, grass, roots, broken

concrete, stones, trash or debris of any kind.

C. No tamped, rolled, or otherwise mechanically compacted backfill shall be deposited or compacted in water.

D. All backfill material shall consist of loose earth having a moisture content required to obtain the specified

density of the compacted soil. Moisture content shall be distributed uniformly. Water added for correction

of moisture content shall be distributed uniformly prior to compaction. Granular material shall be wet, not

just damp, when compacted.

E. Particular care shall be taken to compact structure backfill beneath drives, roads, or other surface

construction.

1.15. COMPACTED ROCK FILL

A. Compacted rock fill shall consist of crushed rock conforming to ASTM C33 with a gradation of 1 ½ inch to

½ inch. The rock fill shall be placed on undisturbed subgrade and compacted to not less than 70 percent

relative density as determined by ASTM D4253 and D4254. Compaction shall be performed with vibrating

mechanical compactors.

B. Crushed rock for compacted fill shall be handled and placed in a manner that will prevent segregation of

sizes. The fill material shall have the best practicable moisture content to achieve specified density. The

material shall be placed in horizontal layers not more than 6 inches in uncompacted thickness.

C. If concrete is to be placed on the compacted rock fill, the fill shall be finished with a thin layer of clean

concrete sand to fill all voids and interstices and to obtain the required subgrade elevation.

1.16. TRENCH BACKFILL

A. Trench backfill shall be compacted for the full depth of the trench.

B. Cohesive and sand backfill material shall be compacted to the specified densities as determined by ASTM

D1557. If crushed rock material is used, compaction shall be to 70 percent relative density as determined

by ASTM D4253 and D4254.

C. Compacted backfill material shall be either job excavated material or material furnished by the Contractor

from his own sources.

D. Backfill material shall be finely divided and free from debris, organic material, and stones larger than 3

inches in greatest dimension. Backfill shall be placed in uniform layers not exceeding 8 inches in

uncompacted thickness. Increased layer thickness may be permitted for noncohesive material if the

Page 58: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Earthwork and Trenching

Volume III-023200-55

specified compacted density is obtained. The method of compaction and the equipment used shall be

appropriate for the material being compacted. Trench backfill shall be compacted to not less than 95

percent of the maximum dry density.

E. Backfill for trenches traversing subgrades of roads, parking areas, underground electrical ducts and conduit,

and other facilities subject to damage by settlement shall be compacted to not less than 95 percent of the

maximum dry density.

F. Moisture content of backfill material shall be adjusted as required to obtain the specified density with the

compaction equipment used.

1.17. MAINTENANCE AND RESTORATION OF FILLS, EMBANKMENTS AND BACKFILLS

A. Fills, embankments and backfills that settle or erode before final acceptance of the work, shall be repaired.

The settled or eroded areas shall be filled, compacted, and graded to conform to the elevation indicated on

the Drawings or to the elevation of the adjacent ground surface. Damaged structures and other facilities

shall be repaired in a manner acceptable to the Owner.

B. Earth slopes of the roads constructed under this specification shall be maintained to the lines and grades

indicated on the Drawings until the final acceptance of the work.

1.18. FINAL GRADING

A. After all construction work has been completed, all ground surface areas disturbed by construction

operations shall be graded. The grading shall be finished to the contours and elevations indicated on the

Drawings, or if not indicated, to the matching contours and elevations of the original, undisturbed ground

surface. The final grading shall provide smooth uniform surfaces and effective drainage of the ground

areas.

1.19. DISPOSAL OF MATERIALS

A. Surplus earth and materials not suitable for the work shall be removed from the site in a manner and

disposed of properly. Disposal shall be in accordance with all federal, state and local requirements.

END SECTION 02300

Page 59: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

DIVISION 3

CONCRETE

Page 60: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Drilled Pier Foundations

Volume III-02380-57

DIVISION 3 – CONCRETE

SECTION 02380 – DRILLED PIER FOUNDATION

PART 1 - GENERAL

1.1 SCOPE

A. This Section covers furnishing all materials, accessories, tools, services, transportation, labor and

supervision required for the supply and installation of cast in place concrete.

B. This Section includes the following items;

1. Concrete for drilled piers

2. Reinforcement

3. Formwork

4. Embedded items, including anchors rods (bolts)

1.2 CONCRETE

A. Concrete shall be normal weight (145 pcf) ready-mix concrete with a compressive strength (f’c) of not

less than 4000 psi at 28 days.

1.3 DEFINITIONS

A. Engineer: Intermountain Consumer Professional Engineers, Inc. (“ICPE”)

1. 1145 East South Union Avenue

2. Midvale, Utah 84047

3. (801) 255-1111

B. Geotechnical Engineer: The specialized Engineering firm retained by the Owner or the Engineer with

the responsibilities of testing and investigation of soil characteristics and properties, providing pier

design values, recommendations and providing inspection of all phases of drilled pier construction.

C. Contractor: The organization contracted to perform the work governed by the drawings and this

Section. Contractor shall employ personnel experienced in the type of work to be performed, including

anticipated subsurface conditions and necessary specialized construction techniques.

D. Owner: Entity contracting or employing the Engineer and Contractor and owning all work completed

on the Project.

E. Owner’s Representative (OR): Owner, Engineer or person employed by the Owner to monitor and

inspect work indicated on the Drawings and in this Section on the Owner’s behalf.

F. Approval: Material or construction procedure to be approved by the Owner or Engineer prior to

incorporation into the Project.

1.4 QUALITY CONTROL

A. All work is subject to direction and approval by the Engineer and the Owner. Work not in compliance

to the Drawings or this Section shall be replaced or repaired as directed at no additional cost to the

Owner.

B. Materials called out on the Drawings and in this Section shall be placed as specified herein and per the

manufacturer’s recommendations. The Contractor shall notify the Engineer of discrepancies for

resolve.

Page 61: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Drilled Pier Foundations

Volume III-02380-58

C. Contract Drawings shall have precedence over Contract Specifications involving conflicting

information.

D. The Contractor shall facilitate inspections of the construction site and material source locations at any

time by the Owner, Engineer, Geotechnical Engineer or their representatives.

E. Cutting, patching or modifying any portion of completed work shall not be done unless approved.

F. The Contractor shall not give direction to the Geotechnical Engineer. However, for involvement by

the Geotechnical Engineer indicated in this Section the Contractor shall not proceed until the

Geotechnical Engineer indicates he has completed his responsibilities or the Contractor is directed to

proceed by the Engineer or Owner.

1.5 SUBMITTALS

A. Work and material indicated to be “approved” or “submitted for approval” shall be submitted with all

related pertinent information to the Engineer. Action on these items shall not be taken until directed by

the Engineer.

B. The following items shall be submitted unless indicated otherwise;

1. Design of concrete mixes in accordance with this Section and ACI 301, Chapter 3. List all

materials with their description, property values and a compliance statement or Standards stated in

this Section.

2. Reinforcing steel and embedded items, shop drawings, bar lists and bending and erection

drawings.

3. Test reports and material certifications as noted elsewhere in this Section and/or on the Drawings.

4. The final reinforcing steel and embedded item Shop Drawings shall be forwarded to the Engineer

when they are issued to the shop.

5. Placement procedure and protection plan for Hot and Cold Weather concrete placement under

conditions described in Para. 3.12 or 3.13.

6. Concrete curing method.

7. Certification specified in Para. 14 of ASTM C94.

8. Detailed procedure for placing concrete under water.

9. Detailed procedure for the placement and removal of casings.

10. Report of actual location, alignment, elevations and dimensions of drilled piers.

11. Report of actual material quantities for each pier.

12. Procedure for “Hot Weather” and “Cold Weather” concreting when conditions apply.

C. Substitute materials

1. Material description and properties for material intended for use other than those included in this

Section or the Drawings.

2. Substitute materials shall not be used without approval.

1.6 CODES AND STANDARDS

A. The following codes and standards of the latest revision shall be considered as part of this Section;

1. American Concrete Institute;

a. ACI 318, Building Code Requirements for Reinforced Concrete

b. ACI 211, Recommended Practice for Selecting Proportions for Normal and Heavy Weight

Concrete

c. ACI 301, Specification for Structural Concrete Buildings

d. ACI 304, Recommended Practice for Measuring, Mixing, Transporting and Placing Concrete

e. ACI 305, Recommended Practice for Hot Weather Concreting

f. ACI 306, Recommended Practice for Cold Weather Concreting

g. ACI 315, Manual of Standard Practice for Detailing Reinforced Concrete Structures

h. ACI 336, Suggested Design and Construction Procedures for Foundations

i. ACI 347, Recommended Practice for Concrete Formwork

Page 62: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Drilled Pier Foundations

Volume III-02380-59

2. American Society for Testing and Materials (ASTM), as noted

3. American Welding Society

a. D1.4, Structural Welding Code. Reinforcing Steel

b. D12.1, Recommended Practice for Welding Reinforcing Steel, Metal Inserts, and Connections in

Reinforced Concrete Construction

c. Concrete Reinforcing Steel Institute (CRSI), as noted

d. International Building Code. IBC

1.7 ADDITIONAL MATERIALS

A. Materials indicated on the Drawings that are not included in this Section shall be considered part of

this Section.

PART 2 - MATERIALS

2.1 CEMENT

A. Cement shall be Portland Cement conforming to ASTM C150, Type II or III cement unless indicated

otherwise on the Drawings.

2.2 WATER

A. Water used in mixing shall be clean and free from materials in amounts deleterious to concrete

conforming to ASTM C1602, “Standard Specification for Mixing Water Used in the Production of

Hydraulic Cement Concrete.”

2.3 ADMIXTURES

A. Admixtures shall conform to ASTM C494 “Chemical Admixtures for Concrete,” or improve properties

of the original design mix, or equal, or exceed ASTM C494, Type D.

B. Mineral

1. Fly Ash Pozzolan; Meet requirements of ASTM C618,Class F or C and with a loss of ignition

(LOI) of 3 percent maximum

C. Chemical

1. Admixture shall not contain calcium chloride nor shall calcium chloride.be used as an admixture.

All chemical admixtures used shall be from the same manufacturer.

2. Air entraining agents conforming to ASTM C260

3. Water reducing, retarding and accelerating admixture conforming to ASTM C494, Type D

4. High range water reducer admixture conforming to ASTM C494, Type F or G

5. Non-chloride accelerator admixture conforming to ASTM C494, Type C

2.4 AGGREGATE

A. Fine aggregate shall conform to ASTM C33, “Concrete Aggregates.”

B. Coarse aggregate shall conform to ASTM C33, “Concrete Aggregates,” with 1-1/2 inch to No. 4 size

gradation.

C. Aggregate shall have an expansion potential of less than 0.1% in accordance to AASHTO T 303 or the

concrete mix shall be tested and approved to have an expansion potential of less than 0.1% to provide

against ASR mitigation.

Page 63: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Drilled Pier Foundations

Volume III-02380-60

2.5 MIX DESIGN

A. Concrete shall meet the durability and quality requirements specified in ACI 318, Chapters 4 an 5 and

conform to ASTM C94.

B. The method of proportioning shall be in accordance with ACI 211.1.

C. The determination of the water-cement ratio to attain the required strength shall be in accordance with

ACI 301, Method 2 (for combinations of materials previously evaluated or to be established by trial

mixes), and with ACI 211.1. The water/cement ratio of the mix shall provide a compressive strength

25 percent greater than the strength specified. The maximum water/cement ratio (by weight) shall be

0.45 and the minimum cement content shall be 5-1/2 sacks per cubic yard.

D. Concrete shall have 3.5 to 6.5 percent air-entrainment.

E. The maximum slump of concrete shall be 5 inches.

F. The maximum amount of pozzolan that may be substituted for cement is 15 percent of the total design

cementitious weight.

2.6 REINFORCEMENT

A. Deformed Steel (Rebar)

1. Deformed reinforcing bars shall conform to ASTM A615, Grade 60, unless noted. Rebar shall be

tagged with mark number and size before shipment.

2. Rebar shall be detailed and fabricated in accordance to ACI 315.

3. Shop Drawings shall include complete placement drawings and bending schedules.

4. Cover for ties of rebar shall be fabricated as 3 inches from rebar face to the theoretical pier

perimeter.

2.7 FORMWORK

A. Design

1. Formwork shall be designed for loads and lateral pressures as outlined in ACI 347, chapter 1.

Formwork design and construction are the responsibility of the Contractor.

B. Forms

1. Forms shall be constructed of wood, steel, or other approved material. Material shall be chosen

based on strength and concrete finish requirements.

2.8 EMBEDDED ITEMS

A. Anchor rods (bolts)

1. Anchor rods shall conform to ASTM F1554, Grade 36, and be furnished with two heavy hex nuts

and one washer at the exposed end and one heavy hex nut at the embedded end. Anchor rod

threads shall be N.C. Class 1 fit. Welding shall comply with AWS recommended practice.

B. Embedded items shall be galvanized in accordance to ASTM A123, unless noted.

2.9 STEEL CASINGS

A. Steel casings shall conform to ASTM A252, Grade 2, ASTM A36, or ASTM A444 corrugated steel.

Design and construction of casings are the responsibility of the Contractor, unless noted.

1. Vertical joints in non-corrugated permanent casings shall be 100 percent penetration welds.

Page 64: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Drilled Pier Foundations

Volume III-02380-61

2. Hardened steel teeth for seating into rock on permanent casings shall be face welded with AWS

electrodes.

3. Steel casings shall be of sufficient strength to withstand handling stresses, concrete pressures and

surrounding earth or fluid pressures.

4. The outside diameter of casings shall be a minimum of the nominal outside diameter of the drilled

foundation shaft.

5. Where a casing is required only for safety during inspection or construction the wall thickness

shall be 1/4 inches minimum.

2.10 CURING AND CURING/SEALING COMPOUNDS

A. Curing compounds shall be a curing/sealing compound conforming to ASTM C309 with 30 percent

solids by weight. Accepted compounds are:

1. Kure-N-Seal 30 by Sonneborne (ChemRex Inc.)

2. Cure & Seal 31% by Seamons Corporation

3. Safe Cure & Seal 30 (J-19) by Dayton

2.11 GROUT

A. A sand-cement fluid grout mix design to fill voids around casings shall have a maximum sand- cement

ratio of 3 to 1.

B. Where indicated under base plates on the Drawings shall be one of the following non-shrink and non-

metallic grouts;

1. Master Flow 713 PLUS or 928 Grout by BASF Construction Chemicals

2. Five Star Special Grout by Five Star Products, Inc.

3. Sikagrout 328 Grout by Sika Concrete Restoration Systems

PART 3 - EXECUTION

3.1 PREPARATION

A. Prior to excavation the Contractor shall locate all existing underground utilities and investigate other

construction in the area to determine any conflicts with the work. The Contractor shall notify the

Engineer of any conflicts and shall not proceed until direction is given.

B. Transporting and handling equipment shall be clean and the areas where concrete is to be placed free

of obstructions.

3.2 EXCAVATION

A. Excavation of drilled piers shall be performed with a power auger foundation drilling rig designed for

that purpose. The Contractor shall contact the Engineer when the soil characteristics or water table

elevation does not represent the geotechnical report boring logs.

B. Excavate drilled piers to dimensions and required elevation and depth shown on the Drawings.

C. Construction methods shall be used to insure the pier is located properly and is plumb within

tolerances indicated in this Section. The excavated hole (shaft) shall be clean, straight and the

diameter indicated on the Drawings shall be maintained the entire length. Soil adjacent to the shaft and

near the surface shall not be disturbed. If soil is disturbed it shall be removed, replaced and compacted

as directed.

D. The Contractor shall grade the surface surrounding the pier with excavated material consistent to the

terrain contours and drainage as directed. Excess and material indicated to be removed from the site

shall be legally deposited.

Page 65: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Drilled Pier Foundations

Volume III-02380-62

E. The completed shaft shall have a flat, level bottom unless sloping rock is encountered. Sloping rock

may be stepped with surface slopes not greater than 10 degrees and step heights not exceeding one

quarter of the diameter of the bearing surface.

F. Drilling polymers may be used to facilitate excavation. The use shall comply with the manufacturer’s

recommendations and approved. Excess polymer shall collected and removed from the site unless

directed otherwise.

3.3 CASINGS

A. Provide a steel casing for shaft excavation where required for safety or to facilitate excavation due to

excessive water or non-cohesive soils..

B. When a casing is required for safety during an inspection or for workers safety during construction, it

shall be loose fitting and shall be removed immediately when the inspection and work is complete.

C. Unless otherwise specified a casing installed to facilitate construction may be removed or left in place

at the Contractor’s option. A placement procedure for casing use shall be approved prior to use.

D. The Geotechnical Engineer shall review the casing use procedure and provide inspection as he or the

Engineer deem necessary. Withdrawal of casings shall be made only as the shaft is being filled with

concrete. The static head of non-set concrete shall be sufficiently above ground water to prevent water

or caving soils from entering voids during casing removal.

E. During casing removal upward movement of the reinforcing steel shall not exceed 6 inches and

downward movement shall not exceed 6 inches per each 20 feet of shaft length.

F. When a casing is left in place fill annular voids between the casing and excavation with concrete or a n

approved sand-cement fluid grout.

3.4 REINFORCEMENT

A. Rebar splices shall be in accordance with ACI 318, Chapter 12. Deviations require approval.

B. At the time of placement rebar shall be free from loose, flaky rust, oil, grease, mud, or other coating,

including ice, that would negatively affect the bond. The use of heat to bend or straighten rebar is not

permitted without an approved procedure.

C. Rebar shall be accurately placed, securely tied at all intersections and splices with 18 gauge black

annealed wire and securely held in position during concrete placement using approved supports.

D. Tolerances, spacings, splice locations and concrete protection shall be the maximum spacing

conforming to the ACI 318, except tie cover in the shaft may be up to 6 inches from rebar face to pier

perimeter not counting space or distance due to over excavating of hole.

3.5 3.5 FORMWORK

A. Installation

1. Forms shall be constructed to the shape, line and grade required and shall be maintained

sufficiently rigid to prevent deformation under load, including placing and compaction of

concrete.

B. Earth Surfaces

1. Concrete may be placed directly against earth at the sides of excavations if they are clean cut and

stable at the time of placement.

Page 66: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Drilled Pier Foundations

Volume III-02380-63

C. Chamfers

1. Exposed corners of concrete shall have a 3/4 inch chamfer.

3.6 EMBEDDED ITEMS

A. Anchor Rods (Bolts)

1. Anchor rods shall be securely set plumb and true to the lines and grades shown on the Drawings.

Threads shall be protected with an oil or grease coating and encased in burlap or paper.

3.7 TOLERANCES

A. Anchor Rods

1. Location: +/- 1/8 inch at top of anchor and at concrete surface and 1/4 inch per 100 feet

accumulative

2. Projection plus 1 inch, minus 0 inch

3. Plum: +/- 1/16 inch/foot of anchor length

B. Pier Excavation

1. Location: Within 1/24 of the shaft diameter but not more than 3 inches Battered piers axis within 5

percent of indicated

2. Plumb: Maximum of 1.5 percent of the pier length and 12.5 percent of the shaft diameter, but not

more than 15 inches

3. Depth: minus 0 inch

C. Concrete

1. Top of pier elevation: plus 1 inch, minus 2 inches

3.8 CONCRETE MIXING

A. The mixing time shall comply with ACI 304, hot weather concreting shall comply with ACI 305 and

cold weather concreting shall comply with ACI 306.

B. Water in addition to the design amount shall not be added to batched concrete without approval. Water

added within the design limit at the site shall be incorporated with additional mixing as directed.

C. The minimum amount of concrete agitation shall be 70 revolutions. The maximum allowable time

between initial material charging in the mixing drum and concrete discharge at mean ambient

temperatures below 90 degrees F shall be 90 minutes or 300 drum rotations, whichever comes first.

Concrete not placed within these limits, within requirements of ACI 305 or 306, or after an initial set,

shall not be used. Tempering concrete is not permitted.

D. The slump may be increased to 6 inches where a casing is to be removed or for concrete pumping. ix

designs for pumped concrete shall be approved.

3.9 CONCRETE PLACEMENT

A. Conveying and placement of concrete shall comply with ACI 304. A copy of each concrete ticket shall

be given to the OR on site or submitted within 3 days.

B. There shall be no loose material or foreign material in the shaft when concrete is placed.

C. Reinforcement and anchor rods shall be placed and approved by the OR and the concrete immediately

placed. Non-cased or belled pier excavations shall not be left open over night without approval.

Page 67: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Drilled Pier Foundations

Volume III-02380-64

D. Concrete may free fall without containment 5'-0 maximum. Concrete may free fall greater distances

through a hopper or tremie located in the center of the pier or by equivalent means such that fall is

down the center of the shaft and the concrete does not hit the sides or rebar.

E. Concrete shall be placed in one continuous pour when possible. The Contractor may request placement

of construction joints with a submittal 3 working days prior to concrete placement. Before continuation

of concrete placement the existing joint surface shall be level, clean and roughened to remove laitance

and provide a profile amplitude of one inch.

F. The top 5 feet of each concrete pour shall be consolidated using a vibratory compactor. When a casing

is removed the consolidation shall be done after the casing removal.

G. A tremie pipe shall be used for placement of concrete under water. The water levels around casings

shall be balanced prior to concrete placement and the bottom end of the tremie shall remain below the

concrete surface after initial placement. Sheeting, casing, or polymer mud shall be used to retain the

sides of the shaft during concrete placement.

H. Effects of settling and shrinkage shall be considered by allowing one hour minimum to top out after

concrete placement.

3.10 CONCRETE FINISHING

A. Voids and honeycombing in formed concrete shall be filled with a 1 to 2 cement-sand mortar mix.

Form ridges and other projections shall be removed immediately after form removal.

B. The top of piers shall be screeded to the elevation indicated on the drawings.

C. Floating shall start as soon as the screeded surfaces have stiffened sufficiently. Floating shall be

performed as necessary to produce a smooth and even finish.

3.11 CURING AND SEALING

A. All concrete surfaces above grade shall be cured as soon as possible for 7 consecutive days. One or

more of the following methods shall be used unless indicated otherwise on the drawings:

1. Water curing by ponding or continuous wetting of sand or burlap.

2. Leaving the forms in place. If forms are removed prior to 7 days after concrete placement another

curing method shall be applied.

3. Curing compound applied in two applications in directions at 90 degrees to each other.

3.12 COLD WEATHER CONCRETE PLACEMENT

A. Sufficient protection against cold weather damage to concrete shall be made prior and during

placement. Cold weather concrete placement shall comply with the approved Contractor placement

procedure, ACI 306 and this Section.

B. Concrete placement temperature shall be above 50 degrees F and concrete shall be protected from

freezing within 7 days after placement when the 24 hour low temperature falls below 40 degrees F.

3.13 HOT WEATHER CONCRETING

A. Thorough preparation for protection against hot weather damage to concrete shall be made well in

advance. Hot weather concrete placement shall be performed above 85 degrees F and comply with the

approved Contractor placement procedure and with ACI 305.

B. The maximum concrete temperature at time of placement shall be limited in compliance with ACI 305,

Figure 2.1.5

Page 68: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Drilled Pier Foundations

Volume III-02380-65

C. One or more ingredients may be cooled to keep the concrete temperature from being excessive at

placement.

D. In place concrete shall be protected from wind and sun and shall be cured as soon as possible. An

evaporation retardant shall be sprayed on exposed surfaces if the air temperature is above 80 degrees F.

3.14 CHANGE ORDER WORK

A. The Contractor shall be compensated for work directed by the Owner/Engineer which is not included

in the scope of work as indicated in the drawings or this Section.

B. There shall be no additional compensation to the Contractor to correct or replace work which was not

completed per the drawings or this Section.

3.15 CLEAN UP

A. Forms, equipment, coatings, rubbish and other materials not part of the final work indicated on the

drawings shall be removed from the site and legally disposed after use is complete.

PART 4 - TESTING AND INSPECTION

4.1 INSPECTION

A. All forms, reinforcement, embedments, subgrade and anchor rods (bolts) shall be approved by the OR

before concrete is placed. If work is determined unsatisfactory all associated work shall not proceed

until corrected as directed.

B. Inspection of drilled piers shall include documentation of construction tolerances.

C. The Contractor shall notify the Engineer where soil characteristics or ground water elevation does not

represent the geotechnical report boring logs. The Geotechnical Engineer shall make a job site

inspection at his discretion or when directed by the Engineer.

4.2 TESTING

A. Handling, testing and acceptance of tests of concrete properties shall conform to ASTM C31, C39,

C94, C125, C138, C143, C172, C173, C192, C231, C470, C1064 and C1077.

B. An independent testing laboratory or the concrete supplier engaged by the Owner will be responsible

for the following:

1. Supplying test cylinder molds to the job-site and taking of samples.

2. Testing for air, slump, temperature, compressive strength and aggregate gradation.

3. Preparing test reports for the Owner, Engineer and Contractor.

C. The Contractor shall provide testing access and concrete for all tests.

D. Compressive test cylinders shall be prepared in sets of four for each test. Samples for each set shall be

obtained at the end of the chute or discharge line for pumped concrete and from the same batch of

concrete approximately midway through discharge. The minimum amount of sampling shall be as

follows:

1. At least one set of cylinders shall be obtained at the beginning of each pour and per 50 cubic yards

of concrete unless directed otherwise by the Engineer.

E. Test cylinder sets shall be dated, numbered consecutively, and identified as to location.

Page 69: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Drilled Pier Foundations

Volume III-02380-66

F. Cylinders shall be immediately stored under wet sand or burlap for about 24 hours after preparation.

All vibration or impact shall be avoided during this critical period.

G. After initial storage, the cylinders (still in their molds) shall be packed in sealed polyethylene bags, wet

sand or other resilient material for shipment to the testing laboratory.

H. Concrete slump tests shall be made in accordance with ASTM C 143 and shall be taken as necessary to

assure well-placed concrete.

I. In-Place Tests: Where questions exist as to the quality of the concrete placed the Engineer may require

tests per ASTM C42 or order a load test on structures as outlined in Chapter 20 of ACI 318.

END OF SECTION 02380

Page 70: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-67

DIVISION 3 – CONCRETE

SECTION 03300 - CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1. DESCRIPTION

A. This specification covers the furnishing of all material, equipment, accessories, tools, services,

transportation, labor, and supervision required for the supply and installation of cast in place concrete.

1.2. CONCRETE

A. Unless otherwise indicated, concrete shall be normal weight (145 pcf) ready-mixed concrete, conforming to

ASTM C94.

1.3. ITEMS INCLUDED

A. This specification includes the following items:

1. Concrete shown on the Drawings.

2. Reinforcement

3. Formwork

4. Embedded Items, including Anchor Bolts

1.4. COMPLIANCE SUBMITTALS

A. Submit concrete mix design, including technical information for all ingredients, reinforcement and

embedment shop drawings, accessories, technical data and any other submittals as specified in Section

16010 and as requested by the Engineer.

B. The concrete manufacturer shall certify that the concrete delivered conforms to the specification for Ready-

Mixed Concrete ASTM C94.

C. Information on materials to be used on the project that are in addition or as a substitute to materials

indicated in this Specification are to be approved by the Engineer prior to their use.

D. All ingredients and quantities in concrete mixes shall be listed in submittals with technical descriptions, test

reports and MSDS sheets for all admixtures. Concrete shall not be placed until all concrete mix submittals

are approved by the Engineer.

E. A certificate of compliance with the requirements of the Specification shall be submitted by the aggregate

supplier.

PART 2 - CODES AND STANDARDS

2.1. The following codes and standards of the latest revision shall be considered as part of this Specification:

A. American Concrete Institute, ACI 318, Building Code Requirements for Reinforced Concrete.

B. ACI 301, Specifications for Structural Concrete for Buildings.

C. ACI 304, Recommended Practice for Measuring, Mixing, Transporting and Placing Concrete.

Page 71: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-68

D. ACI 305, Recommended Practice for Hot Weather Concreting.

E. ACI 306, Recommended Practice for Cold Weather Concreting.

F. Detailing Manual and Commentary.

G. ACI 318, Building Code Requirements for Structural Concrete and Commentary.

H. ACI 347, Recommended Practice for Concrete Formwork.

I. American Society for Testing and Materials (ASTM), as noted.

J. American Welding Society D12.1, Recommended Practices for Welding Reinforcing Steel, Metal Inserts,

and Connections in Reinforced Concrete Construction.

K. American Welding Society D1.4, Structural Welding Code - Reinforcing Steel.

L. Concrete Reinforcing Steel Institute (CRSI), as noted.

M. International Building Code (IBC), 2012 Edition.

N. National Electrical Safety Code (NESC), latest Edition.

PART 3 - MATERIALS

3.1. CEMENT

A. Unless otherwise noted, all cement shall be Portland Cement conforming to ASTM C150, Type II or III

cement. All cement supplied shall be of one manufacturer unless indicated otherwise on the Drawings or

approved by the Engineer.

3.2. WATER

A. Water used in mixing shall be clean and free from deleterious amounts of acids, alkalis, organic matter, or

other impurities likely to be injurious to concrete. Water shall contain less than 650 milligrams per liter of

chlorides calculated as C1 and less than 1000 milligrams per liter of sulfates calculated as S04.

3.3. ADMIXTURES

A. Chemical Admixtures shall conform to "Chemical Admixtures for Concrete" (ASTM C 494) and shall not

be used unless prior approval in writing is obtained from the Construction Manager. Approved admixtures

shall maintain or improve the strength and/or durability of concrete of the original design mix. Admixtures

shall be used in strict accordance with the manufacturer's recommendations and shall be accompanied by

the services of the qualified field representative of the manufacturer to supervise the use thereof. A

certificate from an approved laboratory attesting that the admixture equals or exceeds ASTM C494, Type D

will be required.

B. Air Entraining Admixtures shall conform to "Specifications for Air-Entraining Admixtures for Concrete"

(ASTM C 260). Air content shall be determined in accordance with ASTM C231. The agent and the

cement proposed for use shall be selected well in advance of concrete placing. Approved air-entraining

admixtures are as follows:

1. Darex AEA (Grace Construction Materials)

2. Master Air VR 10 (Master Builders Co.)

3. Sika AER (Sika Chemical Corp.)

Page 72: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-69

C. The use of accelerators shall not be allowed unless approved by the Engineer.

D. Pozzolans

1. Fly Ash shall meet the requirements of ASTM C618, Class F or C, be from the same source for any

individual structure and have the following properties:

CLASS F CLASS C

(a) Loss of ignition 6% Max. 6% Max.

(b) SO3 Content 5% Max. 5% Max.

(c) Moisture Content 3% Max. 3% Max.

2. Silica Fume (Microsilica): Meeting the requirements of ASTM C1240.

(a) Force 10,000 by Grace

3.4. AGGREGATE

A. Aggregates shall conform to requirements of ACI 318, Section 3.3

B. Aggregates nonconforming to gradation requirements in this Specification but which produces concrete

with the required strength and conforms to all other requirements of this Specification, as verified by

testing or actual in service experience, may also be used. Where Type V cement is required, no carbonate

rocks such as limestone, calcite, dolomite, magnetite, sidenite, etc. shall be used. Coarse aggregate shall

meet the requirements of ASTM C33. The Coarse aggregate shall be uniformly graded as follows:

SIEVE PERCENT PASSING

1 1/2 inch

One inch

1/2 inch

No. 4

No.8

100

95 - 100

25 - 60

0 - 10

0 - 5

C. Fine aggregate shall meet the requirements of ASTM C33 and shall be uniformly graded as follows:

SIEVE PERCENT PASSING

3/8 inch

No. 4

No. 8

No. 16

No. 30

No. 50

No. 100

100

95 - 100

80 - 100

50 - 80

25 - 60

10 - 30

2 - 10

3.5. CONCRETE DURABILITY AND QUALITY

A. All concrete shall meet the durability and quality requirements specified in ACI 318, Chapters 4 and 5.

B. The 28 day compressive strength (f'c) of the concrete shall be not less than 4000 psi or as specified on the

drawings.

C. Method of proportioning shall be in accordance with ACI 211.1, "Recommended Practice for Selecting

Proportions for Normal and Heavy Weight Concrete."

Page 73: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-70

D. The determination of the water-cement ratio to attain the required strength shall be in accordance with ACI

301, Method 2 (For combinations of materials previously evaluated or to be established by trial mixes), and

with ACI 211.1. In addition, the maximum water-cement ratio (by weight) shall be 0.45 and the minimum

cement content shall be 5-1/2 sacks per cubic yard.

E. From the test results of the aforementioned procedures, a curve shall be plotted showing relationship

between the water-cement ratio and compressive strength, and the maximum water-cement ratio to be used

shall be the value shown by the curve to produce the strength a minimum of 25 percent greater than the

strength specified.

F. Calcium chloride, other salts and admixtures containing chlorides, or other salts, shall not be included in

the concrete design mix..

G. Concrete may contain a maximum of 15 percent pozzolans, by weight, as a substitute for cement in the

mix.

H. Unless otherwise noted or approved by the Engineer, all concrete shall be air-entrained. The air content

shall be as follows:

1. 6 to 10 percent for 3/8 inch maximum aggregate size

2. 5 to 9 percent for ½ inch maximum aggregate size.

3. 4 to 8 percent for 3/4 inch maximum aggregate size.

4. 3.5 to 6.5 percent for 1 inch maximum aggregate size.

5. 3 to 6 percent for 1-1/2 inch maximum aggregate size.

6. 2.5 to 5.5 percent for 2 inch maximum aggregate size.

I. The maximum slump shall be 4 inches prior to use of any water reducer admixture and 8 inches after a

water reducer admixture is added.

J. Mixing, transporting and placing concrete shall conform to applicable portions of ACI 211, ACI 212 and

ACI 304 and as specified herein. Concrete shall be agitated by at least 70 revolutions of the mixing drum

but not by more than 270 revolutions. Concrete shall be placed within 1 1/2 hours after the cement has

been added to the mix.

3.6. REINFORCEMENT

A. Deformed Bars

1. Reinforcing steel shall be new deformed bars and shall conform to ASTM A615 or ASTM A706,

Grade 60, unless noted otherwise. Bars shall be tagged with mark number and size before shipment.

Welded wire fabric shall conform to ASTM A185.

2. All reinforcing steel shall be new and free of deleterious material, such as grease, oil, paint, loose rust

and other similar contaminants, which would reduce the bond between the steel and concrete.

B. Coated Bars

1. If specified by the drawings, reinforcing bars shall be either galvanized or epoxy coated.

2. Galvanized coated reinforcement shall be Class I hot dipped after fabrication zinc coated in accordance

with ASTM 767. If the galvanized surface is damaged prior to placement of concrete, it shall be

repaired in accordance with ASTM A780.

3. Epoxy coated reinforcement shall be epoxy coated in accordance with ASTM A775. If the epoxy

surface is damaged prior to placement of concrete, it shall be repaired with "3M Scottcoat 306" in

accordance with manufacturer's specifications.

Page 74: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-71

C. Accessories

1. Accessories shall conform to CRSI “Manual of Standard Practice of Reinforced Concrete

Construction.” Include all devices necessary for proper placing, spacing, supporting, and fastening

steel reinforcement in place. Accessories shall be galvanized after fabrication if underside of concrete

will be exposed.

D. Concrete Squares (Precast Reinforcing Chairs)

1. Squares shall be approximately two inches square and of a thickness adequate to provide the cover for

the reinforcing steel as called for on the plans. The squares shall be made using a mixture of one part

Portland Cement to three parts sand (fine aggregate) and the tie wires shall be cast integrally with each

square.

3.7. FORM WORK

A. Design

1. Formwork shall be designed for loads and lateral pressures outlined in Chapter 1, Recommended

Practice for Concrete Formwork (ACI 347) and wind loads as specified by the controlling local

building code. Formwork design and construction are the responsibility of the Contractor.

B. Forms

1. Forms shall be constructed of wood, steel, or other approved material. Material shall be chosen based

on strength and concrete finish requirements.

3.8. EMBEDDED ITEMS

A. Anchor Bolts and Sleeves

1. Unless noted otherwise, anchor bolts shall conform to ASTM F1554 Grade 55 Steel as shown on the

Drawings. Sleeves, where indicated on the Drawings, shall be made with high impact plastic or

schedule 40 steel pipe with sleeve bottom closures of mild steel. Furnish each bolt with one heavy hex

nut and washer unless otherwise noted on the Drawings.

B. Embedded Metals

1. Curb angles, frames, beams, ducts, etc., shall be fabricated of ASTM A36 material, and shall have

anchors attached by welding at 24 inches maximum, unless noted on drawings.

2. The fabricated length of pipe sleeves shall be equal to the thickness of concrete they penetrate. Ends

of pipe sleeves shall be cut square and flush with the face of concrete. Unless otherwise specified or

shown on the Drawings, pipe sleeves shall be secured against movement by welding a ring or flange

around the outside midpoint of the sleeve.

C. Coatings

1. Embedded metal items shall be hot-dipped galvanized in accordance with ASTM A153, Grade 1,

unless otherwise noted on the Drawings.

3.9. JOINT SEALANT

A. Joint Sealant to be Sika-1a or approved equal unless indicated otherwise on the Drawings.

Page 75: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-72

3.10. ADHESIVE ANCHORS

A. Adhesive anchors to be Powers or Hilti System unless shown otherwise on the Drawings.

3.11. BONDING AGENT

A. Concrete bonding agent to be Weldcrete by Larsen Products or approved equal.

3.12. GROUT

A. Grout to be Master Flow 713 by Master Builders Co. or approved equal.

3.13. EVAPORATION RETARDANT

A. Evaporation retardant shall be Sure Film J-74 by Dayton Superior or Master Kure ER 50 by Master

Builders or approved equal.

3.14. CURING COMPOUNDS

A. Concrete surface curing compound and cure and seal compound shall be Kure-N-Seal 30 by Sonneborn or

Cure & Seal 31% by Symons, or approved equal.

PART 4 - EXECUTION

4.1. PREPARATION

A. In no case shall concrete be placed on muddy, spongy, or frozen subgrade.

B. All wood scraps and debris shall be removed from the areas in which concrete is to be placed.

C. All areas where concrete is to be placed shall be thoroughly cleaned to ensure proper placement and

bonding.

D. Forms and subgrade shall be wetted and all standing water removed prior to placing concrete.

E. All transporting and handling equipment shall be thoroughly cleaned.

4.2. FORMWORK

A. Installation

1. Forms shall be constructed to the shape, line, and grade required and shall be maintained sufficiently

rigid to prevent deformation under load, including placing and compacting of concrete. Set forms and

screens for floor and decks to provide uniform slopes to drains and positive drainage for exterior slabs

and steps. Forms shall be tight enough to prevent leakage of mortar. Formwork shall be secured to

prevent sagging, yielding, bulging, depressions, waves, or other defects in the finished work. Forms

shall be smooth and free from warp. Temporary openings shall be provided at base of column and

wall forms for cleaning and inspection. All debris including mud shall be removed before placing

concrete. Use of patented prefabricated panel sections for forming straight wall sections shall receive

prior approval of type and procedure including type of ties to be used. Lumber once used shall be

carefully cleaned and oiled before reuse. The top portion of all foundations shall be formed to a depth

of a minimum of 6" below subgrade. All exposed surfaces shall have a neat smooth finish.

Page 76: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-73

B. Earth Sides

1. Earth sides may be utilized if clean cut and stable at time of concrete placing. Earth must be

undisturbed or compacted to 95% density in accordance with ASTM D 1557, and free from surface

water.

C. Chamfering

1. Exposed corners of concrete shall have 3/4" x 45° chamfers unless otherwise shown on the Drawings.

D. Form Treatment

1. Board Forms: Keep wet previous to placing concrete; wet thoroughly just before placing.

2. Plywood Forms: For surfaces to be painted use silicone-type bondbreaker, Burke, West Chemical or

approved equal, applied in accordance with manufacturer's directions. Coat other surfaces with

approved stainless form oil, using minimum quantity required for satisfactory removal.

3. Metal Forms: Approved-type release compound, applied in accordance with manufacturer's directions.

E. Form Removal

1. Side forms of walls and beams can be removed after 1 to 3 days. Load-supporting forms and shoring

shall not be removed until after 7 days or two-thirds of designed 28 day compressive strength is

obtained or the 7-day test cylinders have been tested and results indicate an average strength adequate

to support the load imposed on the concrete. All forms shall be completely removed after setting of

concrete together with all temporary supports, etc., employed for construction purposes. Forms shall

be readily removable without hammering or prying against the concrete. Days having temperatures

below 40°F are not to be counted for form removal unless thermal protection for the concrete has been

provided. Concrete against forms removed prior to seven days after concrete placement shall be cured

in accordance to Paragraph 4.11.

4.3. REINFORCEMENT

A. Detailing and Fabrication

1. Reinforcing steel shall be detailed and fabricated in accordance with the ACI “Detailing Manual and

Commentary.” All bars shall be cold bent and continuous around corners.

2. The fabricating contractor shall prepare complete placing drawings and bending schedules. All

drawings, thus produced, shall be submitted to the Construction Manager for approval. Fabrication of

reinforcing steel shall not be started until Drawings have been approved by the Engineer.

B. Splicing

1. Bar splices shall be made in accordance with ACI 318 Chapter 12 unless noted otherwise on the design

drawings with a minimum splice of 48 times the bar diameter. Any deviation will require approval of

the Construction Manager.

2. When welded splices are specified on the design drawings, the welding shall conform to AWS D12.1

using ASTM A706 material. Welding of reinforcement is prohibited unless indicated on the Drawings

or approved by the Engineer.

3. Splices in welded wire fabric shall be made by lapping a minimum of one spacing of outermost cross

wires of each fabric sheet plus two inches.

C. Installation

1. Before being placed, reinforcing shall be free from loose flaky rust, oil, grease, mud, or other coating,

including ice that would reduce or destroy the bond. Reinforcement shall be accurately placed and

properly secured in position by precast concrete squares, metal chairs or spacers. The use of heat to

Page 77: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-74

bend or straighten reinforcing will be permitted only if the entire operation is approved by the

Construction Manager and Engineer. Tolerances, spacing, splices, and concrete protection to conform

with Chapter 7 and 12 of the ACI 318 Building Code.

2. Welding shall be done only where shown on the Drawings or approved by the Engineer conforming to

AWS D12.1.

3. Reinforcing steel shall be placed with minimum cover as indicated in ACI, Section 7.7, unless

otherwise shown on the Drawings.

4. With the exception of temperature reinforcement, which shall be tied to main steel, reinforcement shall

be accurately placed and securely tied at all intersections and splices with 18 gauge black annealed

wire, and shall be securely held in position during the placing of concrete by spacers, chairs, squares,

or other approved supports. Wire tie ends shall point away from the form. Unless otherwise indicated,

the number, type, and spacing of supports shall conform to ACI “Detailing Manual and Commentary.”

D. Slabs on Grade

1. Reinforcing for re-entrant corners and perimeter steel around the edge of each pouring unit shall be

provided using provided using ½" diameter (#4) deformed bars unless indicated otherwise on the

drawings. Bars used as dowels in joints shown on the Drawings shall be 5/8" diameter plain round

bars 2 feet long and spaced on 24" centers, unless otherwise indicated on the Drawings.

4.4. EMBEDDED ITEMS

A. No pours are to be made until all embedded items, anchor bolts, electrical conduits, steel frames, pipe

supports, etc., are properly positioned and secured. The Contractor shall be responsible for and coordinated

with other trades to obtain necessary data and information.

All sleeves, inserts, anchor bolts, waterstops, and other embedded items shall be positioned accurately and

supported against displacement.

B. Anchor Bolts

1. Anchor bolts shall be set true to the lines and grades shown on the Drawings and shall be set plumb

and be securely braced to prevent displacement during placing of concrete. Threads shall be protected

by coating with oil or grease and encasing them in burlap or paper. Upon completion of concrete

placement, bolts shall be rechecked for correct location and elevations. Should any bolt exceed

acceptable tolerances corrections directed by the Engineer shall be made at no additional cost to the

Owner.

2. Anchor Tolerances: Tolerance limits in setting anchors and anchor bolts at the surface of the concrete

and at the exposed end of bolt shall be as follows:

(a) Location, sleeved: 3/16 inch

(b) Location, unsleeved: 1/8 inch

(c) Projection: plus 1/4 inch, minus 0 inch

C. Embedded Metals

1. The fabricated length of pipe sleeves shall be equal to the thickness of concrete they penetrate. Ends

of pipe sleeves shall be cut square and flush with the face of concrete. Unless otherwise specified or

shown on the Drawings, pipe sleeves shall be secured against movement by welding a ring or flange

around the outside midpoint of the sleeve.

2. Ducts shall be fabricated as shown on the Drawings.

3. All embedded curb angles, beams, frames, pipe sleeves, etc. shall be set true to the lines and grades

shown on the Drawings. Embedded items shall be secured and braced to prevent shifting during

concrete placing. Where dissimilar metals are to be embedded in direct contact with one another, the

Page 78: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-75

contacting surfaces shall be heavily coated with bituminous mastic or other Engineer-approved surface

treatment to prevent galvanic coupling.

4.5. MIXING CONCRETE

A. The mixer and mixing time shall be in accordance with ACI 304. Hot weather concreting shall comply

with ACI 305, and cold weather concreting with ACI 306.

B. No additional water shall be added to batched concrete above the design amount without the permission of

the Engineer. Such water shall be incorporated by additional mixing equal to at least half of the total

mixing required for the batch. Any addition of water above that permitted by the limitation on specified

water-cement ratio, shall be accompanied by a quantity of cement sufficient to maintain the proper water-

cement ratio.

C. Concrete shall be mixed only in such quantities as required for immediate use. The maximum allowable

time between charging cement to the mixing drum and final concrete placement when the mean ambient

temperature is below 90°F shall be ninety (90) minutes or 300 drum revolutions, which ever comes first.

4.6. PLACING CONCRETE

A. Concrete shall not be placed prior to a recorded pre-placement inspection and/or authorization to proceed

by the Owners Representative.

B. The slump may be increased up to six (6) inches if concrete pumping is to be used. Pumping concrete and

the proposed mix design shall be approved by the Engineer.

C. Conveying and placing of concrete shall be in accordance with ACI 304.

D. Each days pour shall be properly scheduled to assure that concrete surfaces can be finished correctly and

the use of cold joints can be minimized.

E. Concrete shall be mechanically vibrated at regular intervals during concrete placement, except for slabs on

grade that are six (6) inches or less in thickness and drilled piers (cassons) below five (5) feet from the top

of the pier. Consolidation is not required below this elevation.

F. Concrete shall be placed in layers not over twenty four (24) inches deep. Each layer shall be consolidated

by mechanical internal-vibrating equipment in accordance with ACI 309 supplemented by hand spading,

rodding, and tamping to work concrete into all angles and narrow places. Duration of vibration shall be

limited to the time necessary to produce satisfactory consolidation without causing objectionable

segregation. Vibrators shall be applied vertically and at uniformly spaced points not farther apart than the

visible effectiveness of the machine. The vibrator shall not be inserted into lower courses that have begun

to set. Vibrators shall not be used to transport concrete inside forms. The use of form vibrators or form

tamping will not be permitted.

G. The free fall of concrete from the end of the spout or chute, or from a transporting vehicle, shall not exceed

ten (10) feet for thin walls (10 inches or less in thickness) nor more than six (6) feet for other types of

construction. Concrete shall not be permitted to hit obstructions while falling before reaching its intended

location.

H. A tremie with a flexible metal spout may be used when the distance through which concrete must be

dropped vertically exceeds the maximum specified above. Flexible metal spouts shall be composed of

conical sections not more than three feet long, with the diameter of the outlet and the taper of the various

sections such that the concrete will fill the outlet and be retarded in its flow.

I. Chutes, troughs, or pipes used as aids in placing concrete shall be arranged and used so the ingredients of

the concrete will not be separated. Chutes and troughs shall be of metal or metal-lined. When steep slopes

Page 79: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-76

are necessary, the chutes shall be equipped with baffle boards or a reversed section at the outlet. Open

troughs and chutes shall extend, if necessary, down inside the form or through holes left in the forms; or the

ends of such chutes shall terminate in vertical downspouts. All chutes, troughs, and pipes shall be kept

clean and free from coatings or hardened mortar by a thorough flushing with water before and after each

placement. Water used for flushing shall be discharged outside of the forms.

J. Concrete shall be deposited as nearly as possible to its final position and shall not flow farther laterally than

the overall finished concrete section depth. Each pour shall be completed in a continuous operation with no

interruptions in excess of forty-five (45) minutes. Each concrete layer shall be placed and compacted

before the preceding layer has taken initial set.

K. The placing sequence shall always be arranged to allow for the effects of settling and shrinkage. Walls and

columns bearing superimposed slabs or beams and walls over 10' - 0 high shall be allowed to settle 45

minutes before pouring slabs, beams or topping out. Laitance shall be removed before pouring

superimposed structural members.

L. Do not embed aluminum in concrete.

M. Do not use contaminated, deteriorated, or retempered concrete.

N. All materials shall be used in accordance with the manufacturers recommendations unless approved by the

Engineer.

O. Concrete that has not cured to an initial set shall be protected from precipitation to avoid excess water in

mix or unsatisfactory surface finish.

4.7. BONDING

A. The existing surfaces shall be thoroughly cleaned of all foreign material and laitance and roughened to a

1/4 inch high profile minimum before depositing new concrete on old concrete or against concrete which

has set.

B. Concrete surfaces existing prior to the start of the project shall be coated with a bonding agent before

coming into contact with new concrete.

4.8. JOINTS

A. Construction and control joints shall be placed where shown on the Drawings. Placement of construction

and control joints, when not shown on the Drawings, shall be in accordance with ACI 318, Chapter 6.4, and

approved by the Engineer.

B. Waterstops shall be installed as shown on the Drawings, forming a continuous diaphragm in each joint.

Support for waterstops shall be provided and waterstop material shall be protected from damage. Field

joints in waterstops shall be fabricated in accordance with manufacturer's instructions.

C. Saw cutting of control joints shall be done as soon as concrete hardens sufficiently (normally 4-12 hours)

so as not to be torn or damaged by the blade. Sawing shall not be done while concrete temperature is

falling. Control joints shall have a 1/4 inch wide opening minimum and be filled with sealant unless shown

otherwise on the Drawings.

D. One half of slab reinforcing shall be continued across control joints unless shown otherwise on the

Drawings. Keys shall be provided only if shown on the Drawings.

E. Construction joints shall not have joint material placed in them or otherwise be made to be flexible unless

located at control joints or indicated on the Drawings. When called for on the Drawings, the concrete

Page 80: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-77

surface forming construction joints shall be roughened uniformly to approximately 1/4 inch, and laitance,

loosened aggregate and damaged surface concrete shall be removed.

4.9. FORMED CONCRETE FINISHING

A. Form ties shall be broken back one (1) inch from the surface of the concrete. The remaining holes shall be

filled by seal patching using a 1- to -2 of cement-sand mix.

B. All voids and honeycomb areas in formed concrete shall be filled with a 1- to -2 cement-sand patch mix.

Form ridges and other projections shall be removed immediately after forms are removed. Exposed formed

concrete shall be rubbed with a carborundum brick prior to placing a thin cement grout coat as necessary to

produce a true, even and consistant surface. Grout shall extend at least three (3) inches below finished

backfill grade on grade walls.

C. Concrete surfaces left low for grouting shall be roughened to expose aggregate and all loose particles

removed. Anchor bolt threads shall be wire brushed and greased after concrete has set. One nut and

washer shall be placed on each bolt.

4.10. EXPOSED NON-FORMED CONCRETE FINISHING

A. Concrete slab surfaces shall be screeded to the elevations shown on the drawings. An evaporation retardant

shall be sprayed on the screeded surface in accordance to the manufacturer's directions if the air

temperature is expected to reach 80°F or above before cure is complete.

B. Floating the slab surface shall start as soon as the screeded surface has stiffened sufficiently. Floating shall

be performed as necessary to produce a smooth, even, textured finish. Floating shall be performed by hand

using wood floats, except where required for specified finish or interior surfaces, where magnesium tools

shall be used.

C. Slab surfaces shall be tested for accuracy with a straight edge after initial bullfloating or darbying is

completed. Any depressions shall be filled and high areas shall be cut down and reworked. Straight edge

testing and refloating shall continue until there are no deviations of more than 1/8 inch under a ten foot

straight edge.

D. Interior slabs and the top of equipment foundations shall be troweled, except as noted on drawings, or

specified otherwise. Steel troweling shall begin after straight edge testing is finished and while concrete is

still green, but sufficiently hardened to bear a person's weight without deep imprint. Steel troweling shall

produce a smooth troweled finish per ACI Standard 301, Section 11.7.3 "Trowel Finish". Time lapse and

number of trowelings to produce a hard surface will vary depending on weather conditions. The surface

shall not be over worked to prevent small, shallow “alligator” cracking.

E. Exterior slabs and other non-formed walking surfaces shall be broomed after final floating to provide a

nonskid surface. A soft bristled push broom shall be used in a swirling motion.

F. Nonslip surfaces indicated on the Drawings shall be provided by broadcasting not less than 1/4 pound per

square foot of abrasive aggregate, passing the No. 50 sieve, over the screeded and floated concrete surface.

Finishing shall then proceed immediately with a steel trowel. The abrasive aggregate shall pass the No 50

sieve and consist of not less than 55 percent aluminum-oxide or silicon-carbide abrasive ceramically

bonded together to form a homogeneous material that will be sufficiently porous to provide a good bond

with Portland cement. The aggregate shall have an abrasive hardness of not less than 40 as determined by

the test for wear resistance in the National Bureau of Standards Report BMS 98.

4.11. CURING AND SEALING

A. Exposed concrete may be cured by one of the following methods.

Page 81: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-78

1. Concrete shall be kept moist for seven days minimum for regular concrete and three days for high

early strength concrete. Formed surfaces shall be moist cured after the forms are removed until seven

days after placement for regular concrete and three days for high early strength concrete. Days having

temperatures below 40°F shall not be counted. Sealed moisture retaining cover may be used for

moisture cure.

2. Curing compounds may be used when meeting the following requirements

(a) Meets ASTM C 309 minimum requirements and stricter requirements stated in this specification.

(b) Thirty percent minimum solids by weight and applied at 200 square feet per gallon.

(c) Maximum moisture loss of 0.50 pounds/square yard in 72 hours per ASTM C 309 at 200 square

feet per gallon. This is less than the maximum allowed in ASTM C 309.

B. Steel troweled floor slabs, not covered with other materials shall receive a coat of "Cenco Seal 301" surface

hardener applied after all other equipment and work in the building has been installed and/or completed and

the floor has been thoroughly cleaned of all dust, dirt, masks, and foreign matter.

C. Floor surfaces designated to receive tile or other treatment shall not be treated with sealers or hardeners.

4.12. COLD WEATHER CONCRETING

A. Thorough preparation for protection against cold weather damage to concrete shall be made well in

advance. Cold weather concreting shall be performed in accordance with ACI 306.

B. Concrete shall be protected from freezing for not less than the first 7 days after placement.

C. No frozen materials shall be used.

D. Forms, reinforcements and fillers shall be free from frost.

E. At ambient temperatures below 40°F, maintain the concrete temperature at 60°F - 80°F just prior to

placement, and maintain the concrete temperature at 50°F minimum for five days after placement (regular

concrete), or at 50°F for three days after placement (high early strength concrete), or longer if determined

to be necessary by the Engineer.

F. Housings, coverings, or other protection shall remain in place for 24 hours after heating is discontinued.

4.13. HOT WEATHER CONCRETING

A. Thorough preparation for protection against hot weather damage to concrete shall be made well in advance.

Hot weather concreting shall be performed in accordance with ACI 305.

B. The maximum concrete temperature, at time of placement, shall be limited in accordance with ACI 305,

Figure 2.1.5. Provide protective measures approved by the Engineer and the Owners Representative in

advance of concrete placement. Among those protective measures consider the following:

1. Cool the concrete.

(a) One or more of the ingredients cooled to keep the temperature of the concrete from being

excessive at time of placement.

(b) Replacement of part of the mixing water with an equal weight of crushed ice is recommended for

effective cooling per ACI 305, figure 2.3.6.

2. Cover with an evaporative retarder.

3. Provide wind breaks.

4. Provide sun screens.

5. Place concrete when air temperature is near the lowest temperature reached in a 24 hour period.

Page 82: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-79

C. Concrete placement of slabs shall not be initiated when ambient conditions from wind and temperature may

produce an evaporation rate of mix water in excess of 0.10 lb/sq ft./hr. From exposed surfaces without the

use of an evaporation retardant or fogging (see Figure 1). If uncontrolled shrinkage cracking cannot be

prevented concrete shall not be placed.

4.14. PUMPED CONCRETE

A. The use of pumped concrete shall be approved in each case by the Owners Representative.

B. The proposed mix design for each class of concrete to be pumped shall be submitted and approved by the

Engineer prior to concrete placement.

PART 5 - TESTING AND INSPECTION

5.1. INSPECTION

A. All forms, reinforcement, and anchor bolts shall be inspected and approved by the Owners Representative

before concrete is placed. If work is found unsatisfactory, the work shall not proceed until all defects have

been remedied and approved by the Owners Representative. Such approval will in no way relieve the

Contractor of his obligation to produce finished concrete as required by the drawings and specifications.

5.2. TESTING

A. Testing and acceptance of tests of concrete shall be done in accordance with ASTM C31, C39, C94, C143,

C172, and C173, D75 and C136.

B. An independent testing laboratory engaged by the Contractor and approved by the Owners Representative.

The laboratory shall provide the following:

1. Supplying molds to the job-site and taking of cylinder samples.

2. Testing concrete samples taken for air, slump, temperature, compressive strength, aggregate gradation

and any other information request from the Owner.

3. Preparing test reports.

C. The Contractor shall supply concrete for all tests.

D. Concrete shall be sampled, cured, tested and accepted for compressive strength in accordance with ASTM

C172, C31, C39, and C94. Compressive test cylinders shall be prepared in sets of four (4) cylinders for

each test. Specimens for each set shall be obtained from the same batch of concrete after about one half of

the batch has been placed in the forms. The minimum rate of sampling shall be as follows:

1. Structures and Foundations

(a) One set per 75 cubic yards of concrete. At least one set shall be obtained for each structure or

foundation, except when placing a number of items, each smaller than 15 cubic yards, one set per

15 cubic yards shall suffice.

2. Floors and Slabs at Grade

(a) One set per 50 cubic yards of concrete.

3. Underground Duct Envelopes and Fireproofing

Page 83: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-80

(a) One set taken at the beginning of each day's concreting work. Subsequent testing may be

performed at the discretion of the Engineer.

4. All Other Concrete

(a) Same as Paragraph D.1.a. above.

E. Test cylinder sets shall be dated, numbered consecutively, and identified as to location.

F. All cylinders shall be immediately stored under wet sand or burlap for about 24 hours after preparation. All

vibration or impact shall be avoided during this critical period.

G. After initial storage, the cylinders (still in their molds) shall be packed in sealed polyethylene bags, wet

sand or other resilient material for shipment to the testing laboratory.

H. Concrete slump tests shall be made in accordance with ASTM C 143 and shall be taken as necessary to

assure well-placed concrete.

I. Engineer may require in-place tests per ASTM C42 or order a load test on structures as outlined in Chapter

20 of ACI 318, Building Code Requirements for Reinforced Concrete, where he questions the quality of the

concrete placed. The Contractor is not responsible for the costs of performing the tests unless the tests

indicate work by the Contractor was not in accordance with the Drawings or Specifications. The

Contractor shall replace or repair work not in accordance with the Drawings or Specifications as directed

by the Engineer and at no additional cost to the Owner.

J. All slump and cylinder test samples shall be taken from the end of the discharge line.

PART 6 - QUALITY OF CONSTRUCTION

6.1. Cutting, patching and repair of any portion of the work after it has been completed shall be done as

instructed by the Owners Representative.

6.2. Forms equipment, and other items required for construction shall be removed from the premises when they

are no longer needed. Rubbish and other materials not part of the final construction shall be removed on a

weekly basis maximum.

Page 84: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Cast-in-place Concrete

Volume III-03300-81

END OF SECTION 03300

FIGURE 1Source: PCA, Figure 11-6

Page 85: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

DIVISION 5

METALS

Page 86: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification Project

Substation Structures Erection

Volume III-05200-83

DIVISION 5 – METALS

SECTION 05200 - SUBSTATION STRUCTURES ERECTION

PART 1 - SCOPE

1.1. WORK INCLUDED

A. This section covers the work necessary for erecting all substation structures, and repairing any damage to

the protective coatings. Substation steel structures are provided by Owner.

1.2. GENERAL

A. The installation of the structures and the erection of the substation shall be in accordance with the outline

drawings and in accordance with the erection drawings. In the installation of the structures and other metal

work, only mechanics skilled in their various trades shall be employed. Special care shall be taken to

insure that all frames, trusses, columns, guides, and other fixed metal work are installed in their exact

position. Structures to be installed over embedded material and concrete shall be placed accurately and

shall be supported in a correct position of alignment and grade.

PART 2 - MATERIALS

2.1. GENERAL

A. The Contractor shall furnish all miscellaneous or any additional steel which does not appear on the

Drawings but are required to make the substation structures complete.

2.2. All erection shall be in accordance with the Thirteenth Edition of AISC.

PART 3 - WORKMANSHIP

3.1. INSTALLATION OF FABRICATED STRUCTURAL METALWORK

A. Structure installation includes miscellaneous drilling, adjustments, mounting holes, and touch-up

galvanizing/ painting to produce a complete steel structure system to accommodate all equipment, busses,

and materials.

B. All base plates shall be set level, in exact position, and shall be given full and even bearing.

C. Connection or erection bolts shall be entered clear to the head and installed with nuts to the inside of the

member. All bolts shall be ASTM A307. Nuts shall be Heavy Hex type, per ASTM A563 Grade A.

D. The structural nuts shall be tightened to a torque of 120 foot-pounds, and then locked into place with

hexagon Type MF locknuts.

E. All erection and equipment mounting bolts shall be provided with Type MF No. 1 locknuts. Nuts will be

on the inside face of the steel with adequate space provided between the locknut and the adjacent steel to

allow the use of socket type wrenches.

F. Beveled washers shall be used on sloping or beveled surfaces where required to provide a proper fit.

G. Only wrenches approved by the Engineer shall be used on the work, and the use of any wrench which may

deform the nut or cut or flake the cadmium plating will not be permitted.

Page 87: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification Project

Substation Structures Erection

Volume III-05200-84

H. A reasonable amount of drifting will be allowed in assembling, but reaming for mismatched holes will not

be permitted.

I. All structural metals shall be handled with care to avoid bending or damaging. Pieces bent in handling may

be used only if they are straightened to the satisfaction of the Engineer and Owner.

J. All structures shall be assembled, aligned and all bolts tightened and/or torqued as required by AISC code

of Standard Practice. After final tightening and before any apparatus is mounted on the structures, the

alignment will be checked by the Engineer. Structures must align within 1/500 of the span horizontally and

1/500 of the height from the top of the foundation to the connecting points of the supporting members of

the uppermost apparatus support.

K. Welding required for steel structure adjustment and miscellaneous additions and for connector installations

shall be performed by a certified welder. Certification shall be by American Testing Laboratories, Inc. or

Pittsburgh Testing Laboratory and shall be based on American Welding Society Standards.

L. Install commercially manufactured products in accordance with manufacturer's recommendations.

3.2. ANCHOR BOLTS

A. Place all anchor bolts accurately with templates at the time the concrete is placed.

3.3. PROTECTIVE COATING REPAIR

A. Repair all marred, scratched, or drilled steel surfaces as required by the Engineer.

B. Galvanizing repair material shall be in powder or stick form meeting requirements of MIL-P-21035 or

Federal Specification O-G-93 and shall be ZRC Zinc Compound, a product of Sealube Co.; AMCO

Galvanizing Compound, a product of American Solder and Flux Co., Inc.; or equal. Prepare surfaces and

apply repair material in conformance with the manufacturer's recommendation.

PART 4 - FINAL INSPECTION

4.1. Final inspection will be made by the Engineer who will mark and report all loose bolts and other errors in

erection. The Contractor shall be responsible to make sure that all bolts are in place and properly locked.

Inspection by Engineer shall not relieve Contractor of this responsibility.

4.2. Material on which painting has been damaged shall be repainted, unless in the opinion of the Engineer, the

damage is local and can be repaired by applying a coat of the original paint approved by the Engineer.

Where such repair is authorized, the damaged area shall be wiped clean and a cleaning solvent used in

conjunction with wire brushing to insure a proper metal base for the application of the paint. This shall be

done at no cost to the Owner.

4.3. Final inspection shall be made to verify that all equipment attached to the structures shall be made with

steel hardware specifically approved for the application.

4.4. Inspectors shall have full access to the work and shall have authority, subject to final decision of the

Engineer, to condemn and reject any defective work or material. Defective work as determined by the

Inspector and/or Engineer shall then be corrected at no cost to the Owner.

4.5. All work shall be equal to the best modern practice in the installation of materials of the types covered by

these specifications, not withstanding any omission from these specifications or drawings.

END SECTION 05200

Page 88: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

DIVISION 16

ELECTRICAL

Page 89: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Conduit and Accessories

Volume III-16110-86

DIVISION 16 – ELECTRICAL

SECTION 16110 - SUBSTATION CONDUIT & ACCESSORIES

PART 1 - GENERAL

1.1. SUMMARY:

A. The Contractor shall be responsible for providing the materials and installation and completion of conduit

systems at the substation.

B. This Section includes furnishing and installing all conduit, fittings, handholes, boxes, and accessories as

specified or indicated.

C. The Contract Drawings and conduit schedule define the size and type of each conduit. The specifications

define the type of all conduit.

D. Related Work Specified Elsewhere:

1. Site Work: DIVISION 2.

2. Concrete: DIVISION 3.

3. Wire, Cable and Accessories: DIVISION 16.

4. Power, Lighting and Control Devices: DIVISION 16.

1.2. REFERENCES

A. Applicable Standards: Shall be latest revisions, supplements, and amendments to the following:

1. American National Standards Institute (ANSI):

(a) C80.1 - Rigid Steel Conduit, Zinc Coated.

(b) C80.3 - Electrical Metallic Tubing, Zinc Coated.

(c) C80.5 - Rigid Aluminum Conduit.

2. American Society for Testing and Materials (ASTM):

(a) Al23 - Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.

(b) Al53 - Zinc Coating (Hot-Dip) on Iron and Steel Hardware.

(c) A307 - Carbon Steel Bolts and Studs, 60 000psi Tensile.

(d) A611 - Steel, Sheet, Carbon, Cold-Rolled, Structural Quality.

(e) A668 - Steel Forgings, Carbon and Alloy, for General Industrial Use.

(f) B241 - Aluminum and Aluminum-Alloy Seamless Pipe and Seamless Extruded Tube.

(g) F512 - Smooth-Wall Poly(Vinyl Chloride) (PVC) Conduit and Fittings for Underground

Installation.

3. Federal Specifications:

(a) W-C-1094A - Conduit and Conduit Fittings, Plastic, Rigid.

(b) WW-C-540A - Conduit, Metal, Rigid, (Electrical, Aluminum).

(c) WW-C-566C - Conduit, Metal, Flexible.

4. National Electrical Manufacturers Association (NEMA):

(a) FB 1 - Fittings, Cast Metal Boxes, and Conduit Bodies for Conduit and Cable Assemblies.

(b) TC 2 - Electrical Plastic Tubing (EPT) and Conduit (EPC-40 and EPC-80).

(c) TC 3 - PVC Fittings for Use with Rigid PVC Conduit and Tubing.

(d) TC 6 - PVC and ABS Plastic Utilities Duct for Underground Installation.

(e) TC 9 - Fittings for ABS and PVC Plastic Utilities Duct for Underground Installation.

Page 90: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Conduit and Accessories

Volume III-16110-87

5. National Fire Protection Association (NFPA):

(a) 70 - National Electrical Code.

6. Underwriters Laboratory (UL):

(a) 1 - Flexible Metal Conduit.

(b) 6 - Rigid Metal Conduit.

(c) 467 - Grounding and Bonding Equipment.

(d) 514A - Metallic Outlet Boxes.

(e) 514B - Fittings for Conduit and Outlet Boxes.

(f) 514C - Nonmetallic Outlet Boxes, Flush-Device Boxes, and Covers.

(g) 651 - Schedule 40 and 80 Rigid PVC Conduit.

(h) 651 A - Type EB and A Rigid PVC Conduit and HDPE Conduit.

(i) 797 - Electrical Metallic Tubing.

(j) 886 - Outlet Boxes and Fittings for Use in Hazardous (Classified) Locations.

1.3. COMPLIANCE SUBMITTALS

A. Submit as specified in DIVISION 1.

B. Include, but are not limited to, catalog cuts.

PART 2 - MATERIALS

2.1. ACCEPTABLE MANUFACTURERS

A. Rigid Steel Conduit:

1. Allied Tube and Conduit Corporation.

2. Robroy Industries, Pittsburgh Standard.

3. Triangle PWC, Inc.

B. Rigid Steel Conduit with Bonded Polyvinyl Chloride (PVC) Jacket:

1. Robroy Industries.

2. Triangle PWC, Inc. (KorKap).

3. Occidental Coating Company.

C. Electrical Metallic Tubing:

1. Allied Tube and Conduit Corporation.

2. Triangle PWC, Inc.

D. Rigid Nonmetallic Conduit:

1. Carlon Division, Lamson & Session Company.

2. Condux International, Inc.

E. Flexible Steel Conduit:

1. Anamet, Inc.

2. Electri-flex Company.

F. Flexible Fiber Optic Conduit:

Page 91: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Conduit and Accessories

Volume III-16110-88

1. Carlon "Optic-Gard/PE".

G. Conduit Fittings for Rigid Metallic Conduit:

1. Heavy-Duty Fittings:

(a) Appleton Electric Company.

(b) Crouse-Hinds Company.

(c) O-Z/Gedney Company.

2. Conduit Expansion Fittings:

(a) O-Z/Gedney Company.

H. Conduit Boxes for Rigid Metallic Conduit:

1. Hoffman Engineering Company.

I. Supports:

1. B-Line Systems, Inc.

2. GS Metals Corporation.

3. Power-Strut Division, Allied Tube and Conduit Corporation.

4. Russell Stoll, Electrical Products Division.

5. Unistrut Corporation.

J. Conduit Identification Tags: KC Plastic Laminating Company, Kansas City, Missouri.

K. Fireproof Coatings:

1. Carboline Company - Intumastic 285.

2. Flamemaster Corporation - Flamaster 77.

L. Penetration Sealers:

1. Dow Corning Corporation - Fire Stop Foam 2001.

2. Fireproof coatings listed above when applied as specified.

M. Damming Materials:

1. Boards: Thermal Ceramics - Firemaster Board.

2. Fiber: Thermal Ceramics - Firemaster Blanket or Fiber.

N. Paint and Coatings:

1. Supports:

(a) Rust-Oleum.

2. Rigid Steel Conduit:

(a) Kop-Coat, Carboline Company.

O. The Contractor shall furnish equipment and materials meeting the specified ratings and performance at the

altitude and ambient temperatures specified in DIVISION 1.

Page 92: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Conduit and Accessories

Volume III-16110-89

2.2. DESIGN REQUIREMENTS

A. Each length of conduit shall be furnished with coupling on one end and metal or plastic thread protector on

other end.

B. UL listed and labeled on each conduit length, fitting, and accessory.

C. Sizes of conduit, fittings, and accessories as indicated, specified, or required by applicable standards.

2.3. RIGID STEEL CONDUIT

A. Rigid steel conduits shall be constructed of mild ductile steel, circular in cross section with uniform wall

thickness sufficiently accurate to cut clean threads.

B. Each conduit length shall be threaded on both ends and threads protected by plastic thread protectors.

C. All scale, grease, dirt, burrs, and other foreign matter shall be removed from inside and outside of conduit

prior to application of coating materials.

D. Conduit shall be galvanized by the hot-dip process.

2.4. RIGID STEEL CONDUIT WITH BONDED POLYVINYL CHLORIDE (PVC) JACKET

A. Prior to application of PVC coating, rigid steel conduit interior and exterior surfaces shall be cleaned to

remove contaminates and treated with chromic acid to provide a suitable surface for bonding.

B. Adhesive shall be heat-polymerized, epoxy-acrylic with a thickness of approximately 0.5-mil thickness,

cured by heating the conduit.

C. Conduit shall be coated externally except for prethreaded ends with PVC to a nominal 40 mils, 0.035-inch

to 0.045-inch.

D. Coating shall be uniform around outside diameter and full length of the conduit.

E. Coating shall be bonded to surface of conduit with adhesion greater than the cohesive strength of the

coating.

F. Each coupling and fitting shall include a sleeve that overlaps the conduit.

G. The length of the overlapping sleeve shall equal the diameter of the conduit or 2 inches, whichever is less.

2.5. ELECTRICAL METALLIC TUBING

A. Electrical metallic tubing shall consist of high grade steel manufactured to standards which assure

maximum ductility.

B. The exterior shall be protected by the electro-galvanizing process and the interior surface shall be

uniformly coated with aluminum lacquer or enamel.

C. Final treatment of chromic acid shall be applied to galvanized surfaces to form a corrosion resistant coating

of zinc chromate.

D. Water tight compression-type fittings shall be used throughout.

E. Tubing shall be designed for interior applications only.

Page 93: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Conduit and Accessories

Volume III-16110-90

2.6. RIGID NONMETALLIC CONDUIT

A. Rigid nonmetallic conduit shall be fabricated from self-extinguishing high-impact polyvinyl chloride

designed for underground installations.

B. Fittings and accessories shall be fabricated from the same material as the conduit.

C. Solvent-cement-type joints shall be recommended by manufacturer.

D. Inside diameter shall be no less than that of rigid steel conduit.

E. Dielectric strength shall be a minimum of 400 volts per mil.

F. Schedule 40 PVC conduit is required for direct burial and concrete encased applications and must be rated

and labeled for use with 90-degree C rated conductors.

G. Type EPC schedule 40 heavy-wall rigid conduit shall conform to NEMA W-C-1094A Type II.

2.7. FLEXIBLE FIBER OPTIC CONDUIT

A. Flexible fiber optic conduit shall be liquid-tight with flexible polyethylene (PE) core and limited to fiber

optic cable applications only.

B. Conduit shall be orange in color.

2.8. FLEXIBLE STEEL CONDUIT

A. Flexible steel conduit liquid-tight with flexible galvanized-steel core and a polyvinyl chloride covering.

B. Conduit shall include spiral encased copper bonding conductors for conduit in sizes 1-1/4 inches and

smaller.

C. Covering shall be a special grade polyvinyl chloride (PVC) jacket, suitable for use in -50 degrees F through

220 degrees F areas and oil resistant applications.

2.9. CONDUIT FITTINGS FOR RIGID METALLIC CONDUIT

A. All types of fittings shall be heavy-duty cast malleable iron.

B. Fittings shall be mogul type for conduit sizes 1-1/2 inches and larger LBD or roller action type LB for right

angle fittings for conduit sizes 2 inches and larger.

C. Fittings shall include full-threaded hubs and rubber-gasketed covers.

D. Zinc, cadmium-plated, or bronze hardware, bolts, screws, and bushings shall be used for assembly.

E. Iron fittings shall be cadmium plated or galvanized.

F. Couplings and elbows shall be fabricated from the same material as the conduit and each treated as required

for the conduit.

G. Type EPC Schedule 40 heavy-wall rigid conduit shall conform to NEMA W-C-1094A Type II.

2.10. CONDUIT BOXES FOR RIGID METALLIC CONDUIT

A. Steel Boxes shall be electro-galvanized with galvanized steel covers

B. Cadmium-plated or bronze screws and bolts shall be used on all boxes.

Page 94: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Conduit and Accessories

Volume III-16110-91

C. For all boxes installed outdoors and in other areas subject to moisture, conduit entrances shall be threaded

or be waterproof hubs. Conduit boxes shall include provisions for mounting cable supports where

indicated, specified or as required by NEC.

D. Minimum gauge requirements shall be as follows:

No surface area exceeds No single

dimension exceeds Steel (MSG)

360 sq in 24 in 16

1,000 sq in 40 in 14

1,500 sq in 60 in 12

over 1,500 sq in over 60 in 10

1.1. SUPPORT SYSTEM

A. Galvanized steel conduit clamps shall be used to support all exposed metallic conduit and nonmagnetic

clamps shall be used to support nonmetallic conduits.

B. Supports shall be fabricated from structural steel or manufactured framing members equal to "Unistrut" P-

1000 series as manufactured by Unistrut Corporation unless otherwise indicated. Outdoor applications

shall use galvanized steel channel strut.

C. Support system shall include all necessary rods, anchors, inserts, clamps, spacers, shims, bolts and

miscellaneous steel with all members galvanized or cadmium-plated.

D. Where exposed to weather or high humidity, use noncorrodible, galvanized or cadmium-plated metal for

nuts, bolts, washers, shims, and other small accessories

PART 2 - EXECUTION

2.1. GENERAL REQUIREMENTS:

A. Location:

1. Install conduit as near as possible to the routing indicated. Work shall be performed in a professional

manner by craftsmen skilled in the particular trade. All work shall present a neat and finished

appearance. Engineer shall be notified of any deviations from indicated routing.

2. Shift locations as required to avoid interference with other equipment and piping being installed.

3. Where routing of conduit is not indicated, such as for lighting home run circuits and other systems

requiring small conduit runs, route conduit as specified subject to approval by Engineer.

B. Furnish conduit in sizes indicated. Where sizes are not indicated, do not use conduit smaller than 3/4-inch.

C. Size conduit in accordance with NEC requirements.

D. No conduits shall be routed through cable tray or cable trench openings in walls, floors, etc.

E. Seal around wire and cable and empty conduits in all equipment terminal cabinets and all conduits routed

through floors, walls and ceilings of control buildings with duct and conduit sealer.

F. Holes and Sleeves:

1. Unless indicated as being provided by others, provide through floors, walls, ceilings, and roofs as

necessary for conduit runs, including weatherproofing at outside walls and on roofs.

Page 95: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Conduit and Accessories

Volume III-16110-92

2. Furnish sleeves for all holes and forms for all openings in new work.

3. Core drill all holes in existing work using a dustless method. All core drilling locations shall be

approved by the Engineer before Work commences.

4. Seal all holes and slots in walls, floors and ceilings with penetration sealer.

(a) Silicone Foam: Dam penetration with specified fiber and/or board and fill to a depth of 6 inches.

(b) Coatings (Holes or Slots):

(1) Fill hole with specified fiber.

(2) Cut a ½-inch thick piece of the specified board large enough to cover the opening and overlap

the wall three to six inches.

(3) Attach board in at least two places.

(4) Apply coating 1/4-inch thick (wet) to board and the wall or floor three inches all around the

board.

G. Make connections including any required punching to boxes, panels and other equipment as follows:

1. Indoors: Double locknuts, one inside and one outside.

2. Outdoors: Use threaded conduit fittings or waterproof hubs.

H. Make connections to cable trays as follows:

1. Attach to tray with cable tray conduit clamps specifically designed for this application.

2. Attach to top of tray where tray covers are not required and to bottom of tray where covers are

required.

3. Do not cut or punch tray side rails to install conduit.

I. Terminate all conduit runs with insulated bushings where grounding is not required. Grounding bushings

shall be used at all equipment entrance locations.

J. Running threads will not be permitted.

K. Coat all field cut threads, scars, or wrench abrasions in galvanized conduit with one coat of zinc rich

coating at 3 mils dry:

1. Carboline 658.

2. Keeler & Long 7575.

3. Tnemec 90-94.

L. Do not exceed the following number of bends between cable pulling points:

Max Length of Run in Feet Max No. of 90 Degree Bends

0-49 4

50-99 3

100-149 2

150-199 1

M. Place drainage fittings or weep holes (for boxes only) at low points where moisture can collect, except in

hazardous areas.

N. Metallic conduit systems shall be electrically continuous in their entirety, with bonding jumpers provided

as required by NEC.

O. Provide suitable protection for conduit risers against damage during construction.

Page 96: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Conduit and Accessories

Volume III-16110-93

P. Cap all conduits after cleaning where conduits are to be left empty by this contract.

Q. Carefully ream ends of all conduit lengths after cutting to eliminate sharp burrs.

R. A mandrel of proper size shall be pulled through all conduit runs to ensure the conduits are free of debris

after installation. A pull wire or rope shall be left in all unused conduits to facilitate future installation of

cables. Clean out all conduit before pulling wire.

S. In finished rooms, install conduit concealed in walls, floors and above suspended ceilings (or in ceiling slab

where suspended ceiling is not specified).

2.2. EXPOSED INSTALLATION

A. All exposed conduits on substation structures shall be rigid galvanized steel.

B. Install in building interior spaces where specified or indicated.

C. Install above grade outdoors.

D. Install horizontal runs as high above floor as possible, and in no case lower than 7 feet above floor,

walkway, or platform in passage area.

E. Run conduit parallel or perpendicular to walls, ceilings, beams and columns unless indicated otherwise.

F. Route to clear all doors, windows, access wells and openings.

G. Group parallel runs in neatly aligned banks where possible with minimum of 1-inch clearance between

conduits.

H. Maintain 6-inch clearance between conduit and coverings on all hot lines; steam, hot water, etc.

I. Do not exceed a distance of 8 feet between supports on horizontal or vertical runs.

2.3. BURIED INSTALLATION

A. All subgrade conduit shall be rigid non-metallic schedule 40. Conduits extending above grade shall be

rigid galvanized steel (RGS). Rigid galvanized steel conduit shall extend 12" underground. Underground

rigid galvanized steel shall be PVC coated or wrapped with vinyl tape.

B. Install where specified or indicated.

C. Bury conduits a minimum of 24 inches below finish grade unless otherwise indicated. Underground

conduits for 15 kV power cables shall be installed a minimum of 42 inches below finish grade.

D. Before burying or trenching check with Engineer as to existing grade conditions and the possibility of

future coordination problems.

E. For all underground bends, the radius shall be as large as practical and no less than 30 inches. Shop or

factory bends may be used, provided they meet the requirements of these Specifications. All conduit and

conduit bends shall be free of flattening or cracks, and all cuts shall be made square with the inside of the

ends carefully reamed.

F. Slope conduits away from conduit risers where possible.

G. Use long radius bends at all risers unless otherwise indicated.

H. Provide wall entrance seals where conduit enters the building or subgrade walls/floors from exterior

underground.

Page 97: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Conduit and Accessories

Volume III-16110-94

I. Maintain 2-foot separation from underground piping.

J. Make all joints watertight after installation by coating all finished joints with Kop-Coat Bitumastic No. 50

waterproofing paint on galvanized conduit.

K. Cap ends of all conduit before backfilling.

L. After conduits have been installed in trench carefully backfill trench in layers of 4 to 8 inches of friable

sandy or silty clay containing fine material sufficient to provide a dense mass free of voids and capable of

satisfactory compaction and tamp each layer with a power tamp. Backfill material shall be free of roots or

other organic matter, refuse, ashes, cinder, frozen earth, or other unsuitable material.

2.4. RIGID STEEL CONDUIT

A. Install as specified or indicated.

B. Permitted for exposed, concealed, and cast-in-concrete applications.

C. Permitted for buried applications if encased with a minimum of 3 inches of concrete.

D. Use anti-seize compound on conduit threads.

E. Bend conduit per manufacturer's instructions.

2.5. RIGID STEEL CONDUIT (ELBOWS) WITH BONDED POLYVINYL CHLORIDE (PVC) JACKET

A. Install as indicated.

B. Permitted for buried application.

C. Tighten conduit with strap wrench and repair any damaged coating with a liquid patching compound as

recommended by manufacturer.

2.6. ELECTRICAL METALLIC TUBING

A. Install as specified or indicated.

B. Permitted for exposed and concealed applications with the following restrictions:

1. Use only for lighting and convenience power circuits.

2. For exposed applications use indoors only.

3. Install concealed in walls, floors, and above suspended ceilings where possible.

4. Do not use where conduit passes through floors or to support light fixtures.

5. Do not install in hazardous locations.

2.7. RIGID NONMETALLIC CONDUIT

A. Bury conduits at least 24 inches below finish grade unless indicated otherwise.

B. Make all joints watertight with cement compound furnished by conduit manufacturer.

C. Slope conduits away from conduit risers where possible.

D. Maintain 6-inch separation from underground piping.

E. After trench bottom has been finished to grade, lay conduit, then carefully backfill trench in layers of 4

inches to 8 inches of dry material, and tamp each layer with a power tamp.

Page 98: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Conduit and Accessories

Volume III-16110-95

2.8. FLEXIBLE STEEL CONDUIT

A. Install as specified or indicated. Other locations must be approved by the Engineer and Owner.

B. Permitted for exposed and concealed applications.

C. Do not install underground or cast-in-place concrete.

D. Install at all points of connection to equipment mounted on supports to allow for expansion and contraction.

E. Install at locations where rigid conduit connections are impractical.

F. Maximum length shall be six feet.

G. Install an external bonding jumper to conform to NEC on conduit sized 1-1/2 inches and larger.

H. Use for conduit expansion joints where practical.

2.9. CONDUIT FITTINGS: Install as specified, indicated, or necessary.

2.10. BOXES

A. Install boxes as specified, indicated, or as required by NEC.

B. Provide with 1/4-inch drain holes where installed at indoor termination of duct banks or outdoor conduit

run.

C. Indoors, conform to NEMA Type 1 enclosure in all nonhazardous locations.

D. Outdoors, conform to NEMA Type 3R except in manholes and handholes NEMA Type 4.

E. Furnish 4-inch octagon or square boxes with raised simplex receptacle covers for fluorescent light fixture

outlets specified in DIVISION 7.

2.11. SUPPORTS

A. Construct with sufficient rigidity to hold all mounted equipment and material in permanent and neat

alignment.

B. A sufficient number of straps shall be used to firmly anchor all conduits, boxes, and fittings. Straps shall

be secured to the structures with welded unistrut or by drilling the steel and fastening the straps with

suitable self-tapping screws or a system similar to “power actuated fastening system” may be used.

C. Supports for the conduit are required within three feet of each outlet box, junction box, cabinet, or fitting.

For straight runs, supports are provided at least every eight feet.

D. Design to provide 1/4-inch space between equipment housings and walls or columns upon which they are

mounted.

E. Do not exceed load requirements in NEC and NEMA standards.

F. Paint all field cuts or welding of supports with one coat of zinc-rich coating at 3 mils dry:

1. Carboline 658.

2. Keeler & Long 7575.

3. Tnemec 90-94.

Page 99: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Conduit and Accessories

Volume III-16110-96

G. Use electro-galvanized steel conduit clamps and nonmagnetic conduit clamps to support electro-galvanized

steel conduit and nonmagnetic conduit respectively.

2.12. HOME RUNS: Where routine of conduit is not indicated. such as for lighting, convenience power, and

other systems, field route conduit as specified in this Division.

END OF SECTION 16110

Page 100: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Ductbanks

Volume III-16117-97

DIVISION 16 - ELECTRICAL

SECTION 16117 - DUCTBANKS

PART 1 - GENERAL

1.1 SUMMARY

A. The Contractor shall be responsible for duct bank installations. Refer to the Drawings for duck bank

requirements at the substation.

B. This Section includes the following:

1. Underground duct systems consisting of banks of nonmetallic ducts direct buried.

2. All necessary earth and rock excavation and backfill.

3. Removal and disposal of all excess excavation material.

C. Related Work Specified Elsewhere:

1. Site Preparation and Earthwork: SECTION 02100.

2. Conduit and Accessories: SECTION 16110.

3. Grounding: SECTION 16610.

4. Contract Documents: Powell Substation Drawing Sets.

1.2 COMPLIANCE SUBMITTALS

A. Submit as specified in DIVISION 1.

B. Include, but are not limited to, catalog cuts.

PART 2 - PRODUCTS

2.1 ACCEPTABLE MANUFACTURERS

A. Duct Spacers:

1. Carlon Electrical Products.

2. CertainTeed.

3. Formex.

4. Underground Devices, Inc.

5. Osborn Associates, Inc.

2.2 DAMPPROOFING: Kop-Coat Bitumastic Super Service Black.

2.3 "PULLING-IN" ROPE

A. Nylon or polypropylene.

B. Minimum breaking strength: 2,000 pounds.

PART 3 - EXECUTION

3.1 EXCAVATION: Perform excavations as specified in DIVISION 2.

3.2 INSTALLATION

A. Duct Banks:

1. Ducts:

a. Assemble as follows:

(1) Use spacers to maintain horizontal and vertical separation as indicated. Maximum

longitudinal distance between spacers for PVC duct shall be six feet.

Page 101: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Ductbanks

Volume III-16117-98

(2) Stagger joints in adjacent ducts.

(3) Make all joints watertight by application of joint sealer compound furnished by duct

manufacturer.

(4) Do not put reinforcing steel or other ferrous material between individual ducts.

(5) Do not install joints in the radius of duct bends.

b. Securely tie overall at five-foot intervals.

c. After assembly, align ducts so that they do not vary from the drawings more than four inches in

the horizontal or vertical plane.

d. Provide all duct bank terminations with end bells installed flush with face of concrete.

e. Cap ducts installed and not terminated for future extension by others and leave ready for said

extension.

3.3 CLEANING: Rod and clean all ducts with swabs and mandrels after installation of the duct bank. After

ducts are cleaned, plug each end of all ducts.

3.4 BACKFILLING

A. Backfill as specified in DIVISION 2.

END OF SECTION 16117

Page 102: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16120-99

DIVISION 16 - ELECTRICAL

SECTION 16120 - CONDUCTORS - CONTROL CABLES, LOW VOLTAGE CABLES, GROUND CABLES

AND ACCESSORIES

PART 1 - GENERAL

1.1 SUMMARY

A. The Contractor shall be responsible for furnishing all cables required for the Substation.

B. The Contractor shall be responsible for installing all cables for the substation.

C. This Division includes furnishing and installing (including terminations) of all 600 volt class electrical

wire, cable, connectors and accessories for the 48 volt DC, 240Y/120 volt AC auxiliary power distribution

and lighting systems, 600 volt class control and instrumentation wire and cable and ground cable as shown

by the Construction Drawings.

D. Related Work Specified Elsewhere:

1. Conduit and Accessories: Section16110.

2. Cable Trench: Section 16115

3. Substation Grounding: Section 16610

4. Power Switching Devices: Section 16450

5. Field Testing: Section 16700

6. Contract Documents: Volume IV (Drawings).

1.2 REFERENCES

A. Applicable Standards:

1. American Society for Testing and Materials (ASTM):

a. B3Soft or Annealed Copper Wire (Solid).

b. B8Concentric Lay-Stranded Copper Conductors, Hard, Medium-Hard, or Soft.

c. B33Tinned Soft or Annealed Copper Wire for Electrical Purposes.

d. B172Rope Lay Stranded Copper Conductors Having Bunch-Stranded Members, for Electrical

Conductors.

e. B189Lead-Coated and Lead-Alloy-Coated Soft Copper Wire for Electrical Purposes.

f. D752Heavy-Duty Black Polychloroprene Jacket for Wire and Cable.

g. D1350Construction of Rubber Insulated Wire and Cable.

h. D1047Polyvinyl Chloride Jacket for Wire and Cable.

i. D2219Polyvinyl Chloride Insulation for Wire and Cable, 60C̊ operation.

j. D2220Polyvinyl Chloride Insulation for Wire and Cable, 75C̊ operation.

2. Insulated Cable Engineers' Association (ICEA)

a. S-19-81Rubber-Insulated Wire and Cable for the Transmission and Distribution of Electrical

Energy.

b. S-61-402Thermoplastic-Insulated Wire and Cable for the Transmission and Distribution of

Electrical Energy.

c. S-66-524Cross-Linked Thermosetting Polyethylene-Insulated Wire and Cable for the

Transmission and Distribution of Electrical Energy.

d. S-68-516(Interim Standard NO.1): Ethylene-Propylene Rubber Insulation for Power Cables

e. S-19-81Vertical Flame Test on Individual Conductors with Flame-Retardant Cross-Linked

Polyethylene Insulation.

3. Underwriters' Laboratories, Inc. (UL)

a. UL-44Rubber-Insulated Wire and Cables.

Page 103: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16120-100

b. UL-83Thermoplastic-Insulated Wire.

c. UL-486Wire Connectors and Soldering Lugs.

d. UL-854Service Entrance Cables.

e. UL-1072Medium Voltage Power Cables.

f. UL-1277Electric Power and Control Tray Cables with Optional Optical Fiber Members.

4. Institute of Electrical and Electronic Engineers (IEEE):

a. 48Test Procedures and Requirements for High Voltage Alternating Current Cable Terminations.

b. 383Electrical Cable Tests,"Flame Test Portion for Power, Control, and Instrumentation Cables.

c. 404Cable Joints for Use with Extruded Dielectric Cable Rated 5,000 through 46,000 Volts, and

Cable Joints for Use with Laminated Dielectric Cable Rated 2,500 through 500,000 Volts.

5. National Electrical Manufacturers Association (NEMA)

a. WC3Rubber Insulated Wire and Cable for the Transmission and Distribution of Electrical Energy.

b. WC5Thermoplastic Insulated Wire and Cable for the Transmission and Distribution of Electrical

Energy.

c. WC7Cross-Linked-Thermosetting-Polyethylene Insulated Wire and Cable for the Transmission

and Distribution of Electrical Energy.

d. WC8Ethylene-Propylene-Rubber-Insulated Wire and Cable for the Transmission and Distribution

of Electrical Energy.

6. National Fire Protection Association (NFPA):

a. 70National Electrical Code.

B. Factory Tests:

1. Factory tests shall be conducted on wire and cable as specified on each individual wire and cable type

specification sheet contained in this Division.

2. Wire and cable certification sheets shall be submitted to the Engineer as specified on each individual

wire and cable specification sheet and in accordance with requirements in DIVISION 1.

C. The Contractor shall furnish equipment and materials meeting the specified ratings and performance at the

ambient temperature specified.

1.3 COMPLIANCE SUBMITTALS

A. Submittals as specified in Division 1 shall include, but not be limited to, the following for each wire and

cable type specified:

1. Cable manufacturer and cable specification sheets from the manufacturer including type of insulation

and thickness.

2. Dielectric strength and tests to which the cable will be subjected at the factory.

3. Outside diameter of the cable.

4. Current carrying capacity data.

5. Year of manufacture (not to exceed 2 years before cable is to be installed).

6. Data sheets for wire and cable accessories.

7. Cable manufacturer’s approval of splicing and terminating materials.

8. Cable manufacturer’s approval of pulling compounds.

9. Cable manufacturer’s installation requirements such as maximum pulling tensions, sidewall pressures,

minimum bending radii, etc.

B. The Contractor shall submit a test report certifying that all cables have been tested and shall submit a cable

schedule drawing listing the insulation strength for each cable.

C. Cable reels shall be stored and handled in a manner which will prevent physical damage to the cable.

Cable reels shall be stored on a hard surface to prevent contact between cable insulation and earth due to

sinking of the reel.

Page 104: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16120-101

PART 2 - PRODUCTS

2.1 ACCEPTABLE MANUFACTURERS

A. Wire and Cable: Acceptable manufacturers for each wire and cable type are:

1. Okonite Cable

2. Tamaqua Cable

3. Prysmian

B. Wire and Cable Accessories:

1. Cable Connectors:

a. AMP Special Industries.

b. Thomas and Betts Company, Inc.

c. Burndy.

2. Termination and Splice Kits:

a. Elastimold

b. Minnesota Mining and Manufacturing (3M)

c. Raychem

d. Joslyn

3. Tape and Insulation Putty: Minnesota Mining and Manufacturing (3M).

4. Cable Ties:

a. Thomas and Betts Company, Inc.

b. AMP Special Industries

c. Panduit Corporation

5. Cable Supports:

a. O.Z. Gedney Company

b. Hubbell, Kellem Grips

6. Terminal Blocks:

a. States Company

b. General Electric

7. Cable Identification Tags:

a. Allen Marking Products, Kansas City, Missouri

b. Specialaity Products Company, Rock Hill, South Carolina

c. Floy Tag and Manufacturing, Seattle, Washington

d. Thomas and Betts Company, Inc.

e. Panduit Corporation

2.2 WIRE AND CABLE

A. The Cable Schedule defines the type, size, end points and routing of each wire or cable (excluding lighting,

convenience power and grounding cables).

B. Lighting, convenience power and grounding cable requirements are indicated.

C. Wire and cable shall be furnished in accordance with the specification sheets at the end of this Section.

D. Contractor furnished wire, cables, and connectors for power, lighting, outlets, heating and ventilation

controls, and miscellaneous control in the control building and in the substation yard area shall be as

indicated on the drawings.

E. The Contractor shall determine the quantities of the various wire and cable required for the lighting system,

power, control and related conductor systems.

Page 105: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16120-102

F. The Contractor furnished wire and cable shall be all of the same specification, preferably all from the same

source, for the entire installation.

G. Cable reels shall be stored and handled in a manner which will prevent physical damage to the cable.

Cable reels shall be stored on a hard surface to prevent contact between cable insulation and earth due to

sinking of the reel.

2.3 CONNECTORS

A. General Requirements:

1. Designed and sized for specific cable being connected.

2. Solderless, pressure-type connectors constructed of non-corrodible tin plated copper.

3. Rated current carrying capacity equal to or greater than the cable being connected.

B. Power cable connectors:

1. Ring tongue, sized to match terminal stud size.

2. Vinyl pre-insulated ring tongue for wire sizes 12-2 AWG and uninsulated two-hole rectangular tongue

for wire sizes 1-750 kcmil.

3. Have insulation grip sleeve or ring to firmly hold to cable insulation.

4. Application tooling designed to crimp the wire barrel (conductor grip) and the insulation grip sleeve or

ring with a one-step crimp.

5. Application tooling shall be hydraulically operated for wire sizes 1-750 kcmil.

6. AMP Special Industries type PIDG Heavy-Duty for wire sizes 12-10 AWG, AMPLIBOND for wire

sizes 8-2 AWG and AMPOWER for wire sizes 1-750 kcmil, or approved equal by Thomas & Betts,

Panduit Corporation, or Burndy.

C. Control, instrument, and specialty cable connectors:

1. Sized to match terminal stud size.

2. Vinyl pre-insulated ring tongue type (spade lugs not permitted).

3. Have insulation grip sleeve to firmly hold to cable insulation.

4. Insulation grip sleeve shall be funneled to facilitate wire insertion and prevent turned back strands.

5. Application tooling designed to crimp the wire barrel (conductor grip) and the insulation grip sleeve

with a one step crimp.

6. AMP Special industries type PIDG for wire sizes 22-16 AWG and PIDG Heavy-Duty for wire sizes

14-10 AWG, or approved equal by Thomas & Betts, Panduit Corporation, or Burndy.

2.4 CABLE SUPPORTS

A. Type "R" wedging plug for cables in vertical conduit risers: O.Z. Gedney Company.

B. Kellum basket type wire mesh grip for cables in vertical tray or conduit risers.

2.5 CABLE TIES

A. Nylon self-locking type.

B. Have a normal service temperature range of -40 degrees C to 85 degrees C.

C. Be weather resistant for outdoor use.

D. Meet requirements of Military Standard MIL-S-23190D.

E. Be AMP Special Industries “AMP-TY”, Dennison Manufacturing Company “BAR-LOK”, Panduit

Corporation “PAN-TY” or Thomas and Betts “TY-RAP”.

2.6 TERMINAL BLOCKS SHALL BE OR HAVE:

A. Designed and sized for the cables being terminated.

B. Phenolic block rated 600 volts if mounted in terminal boxes; molded block rated 600 volts if mounted in

cabinets, panels, control boards, etc.

Page 106: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16120-103

C. Contacts shall be or have:

1. Tubular screw type contacts for power cables requiring no cable connectors.

2. Binding screw type contacts for power cables and current transformer circuits having ring tongue cable

connectors.

3. Strap screw type contacts for control and instrument cables having ring tongue cable connectors.

4. Rated current carrying capacity equal to or greater than the cable being terminated.

5. A marking strip with permanent circuit identifications.

6. Short circuit strips with one shorting screw for each terminal for current transformer circuits.

D. General Electric Type CR2960SY139 for power cables. Connection type KU or equal for control and

instrument cables. General Electric Type EB-27 for current transformer circuits.

2.7 CABLE IDENTIFICATION TAGS

A. Cable identification tags shall be one-inch, round hard, fiber type, white in color with cable number

stamped-on and filled with black ink or paint.

B. Acceptable manufacturers are as follows:

1. Okonite cable

2. Tamaqua cable

3. Prysmian

4. Carol

PART 3 - EXECUTION

3.1 GENERAL

A. Power (600 volts and below), control, instrument and specialty cable:

1. Install in conduit, duct, wireway, cable trench, or cable tray as indicated or specified.

2. Install complete as indicated and as recommended by manufacturer.

3. Install continuous between terminal points indicted without intermediate splices or taps unless

otherwise approved by the Engineer.

4. No splices shall be permitted in the CT secondary circuits, VT secondary circuits, or communication

grade circuits.

5. Make splices only in junction or terminal boxes. For control and instrument cables, splices shall be

made only on terminal blocks with marking strip. Maintain color coding on all splices. For power

cable 6 AWG and smaller, splices shall be made on terminal block. For power cable larger than 6

AWG, splices shall be made using compression-type connectors bolted together and covered with heat

shrink connector insulator. For shielded cables, shield continuity and isolation shall be maintained.

6. Do not subject cable to pulling tension in excess of manufacturer's recommendations. A calibrated

dynamo-meter shall be used to observe pulling loads.

7. Attach pulling grips over the cable sheath to prevent slopping the insulation.

8. Do not subject cable to bending radius of less than 8 times the cable outside diameter during or after

installation.

9. Install cable supports in vertical runs of conduit, at boxes and at terminations in equipment, and as

required to meet the intermediate support requirements of the NEC.

10. Install metallic barrier in all tray and boxes to separate power, control and instrumentation from low-

level signal (50 volts or less) instrumentation circuits where run in the same tray or box.

11. Secure with cable ties in cable tray risers at intervals not to exceed three feet.

12. Tie together with cable ties all single conductor cable on each individual circuit in each junction box,

equipment, or manhole, and in cable tray, at intervals not to exceed 6 feet.

13. Clamp, snub, and tie for proper support at each terminal block or connection so that any strain on the

cable will not be transmitted to the terminal connections.

14. Do not tie wires from different cables together.

Page 107: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16120-104

15. Attach a cable identification tag with a cable tie to each cable at termination or end points. Also,

provide cable identification every 75' of cable length and at trench intersection points when installed in

cable trench.

16. Terminate and ground control, instrument, and specialty cable shields as indicated and recommended

by the manufacturer of the equipment being connected.

17. Ground the cable shields, when provided, as indicated on the drawings.

18. Install ground cables as specified in Section 16610.

19. Connect all cables and wires for power equipment, lighting systems, outlets, wiring devices, control

devices, and miscellaneous equipment items for all yard equipment in accordance with Drawings and

as specified in Division 16.

20. A wire label shall be provided on each individual conductor at its termination point. Label shall

indicate cable number and conductor ID provided on the drawings.

B. Cable connection and terminations:

1. Make up clean and tight to assure a low-resistance joint.

2. Make terminations only in junction or terminal boxes, equipment, or other accepted enclosures and not

in conduit or cable tray.

3. Install connectors with tooling manufactured by the connector manufacturer. Tooling shall be equal to

AMP Special Industries, having die or piston stops to prevent over crimping and CERTI-CRIMP

cycling or pressure relief feature to prevent under crimping. The dies of all application tooling shall

provide dot or wire size coding for quality control verification.

4. Connect all power, control, metering, relaying, and communication cables to all terminal equipment

and termination panels in accordance with wiring termination Drawings and DC and AC schematic

Drawings to provide for a complete working wiring system.

C. Miscellaneous:

1. All spare and unused conductors shall be grounded with ring terminals at one end of the cable. The

spare conductors will be typically grounded at the equipment or junction boxes to a ground bar.

2. All direct-current circuits shall be installed with the positive and negative leads of a circuit in the same

cable.

3. AC and DC control circuits shall be run in separate cables.

4. Power circuits shall not be run in the same cables with AC or DC control circuits.

5. Wiring in cabinets and panels shall be arranged neatly. All cables entering cabinets and equipment

shall have an identification tag securely fastened to the conductor listing circuit number and function.

6. Cable shields are to be grounded at one end only. All cable shields will be grounded in the relay

panels.

3.2 FIELD TESTS

A. The Contractor must schedule cable testing with the Engineer and Owner prior to performance of tests.

B. Continuity checking of cables and wiring shall be made before any other tests, as indicated in Section

16700, are made on metering and station power equipment. This check shall be made by using low-voltage

continuity testing apparatus such as a buzzer or a flashlight. The wiring shall be checked against the

schematics and wiring diagrams at the same time the continuity tests are being made.

C. Perform insulation resistance and continuity testing of all power and control circuits below 600 volts with a

500-volt megohmeter. Prepare a written test report of the results and submit to the Engineer prior to final

inspection. Equipment which may be damaged during this test should be disconnected. Perform tests with

all other equipment connected to the circuit.

D. Circuits shall be energized only under the supervision of the Engineer and the Owner.

E. The Contractor shall provide assistance during all phases of field testing and commissioning portions of the

project.

END OF SECTION 16120

Page 108: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16126-105

DIVISION 16 - SECTION 16120

APPENDIX

ACP-1 WIRE AND CABLE SPECIFICATION SHEET - 600 VOLT SINGLE

CONDUCTOR - POWER CABLE

SCC-1 WIRE AND CABLE SPECIFICATION SHEET - 600 VOLT MULTIPLE

CONDUCTOR SHIELDED CONTROL CABLE

NSCC-1

CEV3

WIRE AND CABLE SPECIFICATION SHEET - 600 VOLT MULTI-

CONDUCTOR CONTROL CABLE

WIRE AND CABLE SPECIFICATION SHEET - 600 VOLT MULTI-

CONDUCTOR NON-SHIELDED CONTROL CABLE

BC1 WIRE AND CABLE SPECIFICATION SHEET - BARE COPPER GROUND

CABLE

Page 109: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16126-106

AND CABLE SPECIFICATION SHEET

ACP-1

600 VOLT - MULTIPLE CONDUCTOR - POWER CABLE

GENERAL REQUIREMENTS:

CONDUCTOR: CLASS B stranded annealed copper (ICEA S-66-524 Part 2).

INSULATION: CROSS-linked polyethylene "XLPE" (UL44 Part 18) and rated as Type XHHW-

2. Color coding shall be Method 1 E1(K1) and as shown in the following Table 1.

CABLE JACKET: : Heat, moisture and sunlight resistant, black (thermoplastic) chlorinated polyethylene

meeting the requirements of UL 1277. The thickness is in accordance with Table 11.25 of UL

1277.

IDENTIFICATION: SURFACE printing on the cable shall show manufacturer's name, insulation

type, number and size of conductors, jacket type, voltage rating, Underwriters Laboratories label

(UL) Oil Res II Sun Res Direct Burial and numbered footage markers.

SPECIFIC REQUIREMENTS:

TEMP. RATING: CABLE shall be suitable for operation under the following maximum conductor

temperatures:

90̊ C - Continuous, wet or dry locations

130̊ C - Emergency

250̊ C - Short Circuit

INSULATION THICKNESS:

Number of

Conductors

Conductor Size

(AWG or MCM)

Jacket Thickness

(Mils) (ICEA S-66-

524 Table 4-4)

2, 3 or 4 12 & 10 30

2, 3 or 4 8-2 45

2, 3 or 4 1-4/0 55

JACKET THICKNESS:

Calculated Diameter of

Cable Under Jacket

(inches)

Jacket Thickness (Mils)

(ICEA S-68-516

Table 4-5)

0.425 or less 45

0.426-0.700 60

0.701-1.500 80

1.501-2,500 110

2.501 or larger 140

FACTORY TESTS: ALL cable shall be tested In accordance with requirements of ICEA S-66-524.

All cable supplied shall meet the flame test requirements of UL1277 using a gas burner flame

source. Flame tests shall be performed on 3/C-12AWGand certified test reports shall be submitted

to the Engineer in triplicate.

Page 110: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16126-107

CERTIFICATION: CABLES shall be certified to be in conformance with all applicable requirements of

ICEA S-66-524.

GENERAL PRODUCT DESCRIPTION OF

Multi-Conductor 600 Volt, Shielded Tray Cable with

XLPE Insulated Circuit Conductors + Drain Wire (shielded)

with an Overall CPE Jacket

Table 1 (K1 Color Code)

Number &

Circuit Conductor

Size (awg)

Average

Insulation

Thickness (mils)

Average Jacket

Thickness (mils)

Nominal Cable

O.D. (in.)

Nominal Cable

Weight (lbs/kV) Color Code

2/C #12 30 60 0.45 150 Black, Red

2/C #10 30 60 0.45 160 Black, Red

4/C #12 30 60 0.520 188 Black, Red, White

and Green

4/C #10 30 60 0.580 250 Black, Red, White

& Green

4/C #8 45 60 0.735 385 Black, Red, white

& Green

7/C #12 30 60 0.610 284 Black, Red, White,

Green, Blue &

Orange

Wht/Blk

12/C #12 30 60 0.805 467 Black, Red,

White, Green,

Blue, Orange,

Wht/Blk,

Red/Blk,

Green/Blk,

Orange/Blk,

Blue/Blk,

Black/Wht

Page 111: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16126-108

WIRE AND CABLE SPECIFICATION SHEET

SCC-1

600 VOLT - MULTI-CONDUCTOR SHIELDED CONTROL CABLE

GENERAL REQUIREMENTS:

SCOPE: Multi-conductor, 600 volt, Tray Cable with cross-linked thermosetting polyethylene

(XLPE) insulated circuit conductors, a tinned copper drain wire, an aluminum/mylar shield, with

an overall thermoplastic chlorinated polyethylene (CPE) jacket. The cable is suitable for use in

cable trays, aerial or direct burial installations.

CONDUCTOR: CLASS B stranded annealed copper per ASTM B3 and ASTM B8.

INSULATION: CROSS-linked polyethylene "XLPE" (UL44 Part 18) and rated as Type XHHW2.

Color coding shall be Method 1 – E2 (K2) and as shown in the following Table 2.

CABLE SHIELD: Helically applied aluminized mylar or polyester tape and tinned copper drain wire.

CABLE JACKET: Heat, moisture and sunlight resistant, black (thermoplastic) chlorinated polyethylene

meeting the requirements of UL 1277. The thickness is in accordance with Table 11.25 of UL

1277.

IDENTIFICATION: SURFACE printing on the cable jacket shall show manufacturer's name,

cable type (TC), insulation type (XHHW-2), number and size of conductors, voltage rating,

Underwriters Laboratories label (UL). Oil Res II Sun Res, Direct Burial, and numbered footage

markers.

ASSEMBLY: The insulated circuit conductors are cabled together with flame resistant non-

hygroscopic fillers as needed. The cabled core shall be wrapped with a Mylar binder tape.

SPECIFIC REQUIREMENTS:

TEMP. RATING: CABLE shall be suitable for operation under the following maximum conductor

temperatures:

90̊ C - Continuous, wet or dry locations

INSULATION THICKNESS:

Conductor Size

(AWG)

Insulation

Thickness (Mils)

(UL44, Table 24.3)

14-9 30

16 25

FACTORY TESTS: ALL cable shall be tested in accordance with requirements of UL 1277.

CERTIFICATION: CABLES shall be certified to be in conformance with all applicable requirements of UL1277.

Page 112: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16126-109

SCC-1 (Cont.)

GENERAL PRODUCT DESCRIPTION OF

Multi-Conductor 600 Volt, Shielded Tray Cable with

XLPE Insulated Circuit Conductors + Drain Wire (shielded)

with an Overall CPE Jacket

Table 2 (K2 Color Code)

Number &

Circuit Conductor

Size (awg)

Average

Insulation

Thickness (mils)

Average Jacket

Thickness (mils)

Nominal Cable

O.D. (in.)

Nominal Cable

Weight (lbs/kV) Color Code

2/C #12 30 60 0.45 150 Black, Red

2/C #10 30 60 0.45 160 Black, Red

4/C #12 30 60 0.520 188 Black, Red, Blue

and Orange

4/C #10 30 60 0.580 250 Black, Red, Blue

and Orange

4/C #8 45 60 0.735 385 Black, Red, Blue

and Orange

7/C #12 30 60 0.610 284 Black, Red, Blue

Orange, Yellow,

Brown &

Red/Blk

12/C #12 30 60 0.805 467 Black, Red,

, Blue Orange,

Yellow, Brown &

Red/Blk,

Blue/Blk,

Orange/Blk,

Yellow/Blk,

Brown/Blk,

Black/Red

Page 113: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16126-110

WIRE AND CABLE SPECIFICATION SHEET

NSCC-1

600 VOLT - MULTI-CONDUCTOR UNSHIELDED CONTROL CABLE

GENERAL REQUIREMENTS:

SCOPE: Multi-conductor, 600 volt, Tray Cable with cross-linked thermosetting polyethylene

(XLPE) insulated circuit conductors, a tinned copper drain wire, an aluminum/mylar shield, with

an overall thermoplastic chlorinated polyethylene (CPE) jacket. The cable is suitable for use in

cable trays, aerial or direct burial installations.

CONDUCTOR: CLASS B stranded annealed copper per ASTM B3 and ASTM B8.

INSULATION: CROSS-linked polyethylene "XLPE" (UL44 Part 18) and rated as Type XHHW2.

Color coding shall be Method 1 – E2 (K2) and as shown in the following Table 3.

CABLE SHIELD: NA.

CABLE JACKET: Heat, moisture and sunlight resistant, black (thermoplastic) chlorinated polyethylene

meeting the requirements of UL 1277. The thickness is in accordance with Table 11.25 of UL

1277.

IDENTIFICATION: SURFACE printing on the cable jacket shall show manufacturer's name,

cable type (TC), insulation type (XHHW-2), number and size of conductors, voltage rating,

Underwriters Laboratories label (UL). Oil Res II Sun Res, Direct Burial, and numbered footage

markers.

ASSEMBLY: The insulated circuit conductors are cabled together with flame resistant non-

hygroscopic fillers as needed. The cabled core shall be wrapped with a Mylar binder tape.

SPECIFIC REQUIREMENTS:

TEMP. RATING: CABLE shall be suitable for operation under the following maximum conductor

temperatures:

90̊ C - Continuous, wet or dry locations

INSULATION THICKNESS:

Conductor Size

(AWG)

Insulation

Thickness (Mils)

(UL44, Table 24.3)

14-9 30

FACTORY TESTS: ALL cable shall be tested in accordance with requirements of UL 1277.

CERTIFICATION: CABLES shall be certified to be in conformance with all applicable requirements of UL1277.

Page 114: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16126-111

NSCC-1 (cont.)

GENERAL PRODUCT DESCRIPTION OF

Multi-Conductor 600 Volt, Unshielded Tray Cable with

XLPE Type XHHW2 Insulated Circuit Conductors

with an Overall CPE Jacket

Table 3 (K2 Color Code)

Number &

Circuit Conductor

Size (awg)

Average

Insulation

Thickness (mils)

Average Jacket

Thickness (mils)

Nominal Cable

O.D. (in.)

Nominal Cable

Weight (lbs/kV) Color Code

2/C #12 30 60 0.41 150 Black, Red

2/C #10 30 60 0.45 160 Black, Red

4/C #12 30 60 0.470 188 Black, Red, Blue

and Orange

4/C #10 30 60 0.560 250 Black, Red, Blue

and Orange

4/C #8 45 60 0.70 385 Black, Red, Blue

and Orange

7/C #12 30 60 0.590 284 Black, Red, Blue

Orange, Yellow,

Brown &

Red/Blk

12/C #12 30 60 0.77 467 Black, Red,

, Blue Orange,

Yellow, Brown &

Red/Blk,

Blue/Blk,

Orange/Blk,

Yellow/Blk,

Brown/Blk,

Black/Red

12/C #14 30 60 0.77 467 Black, Red,

, Blue Orange,

Yellow, Brown &

Red/Blk,

Blue/Blk,

Orange/Blk,

Yellow/Blk,

Brown/Blk,

Black/Red

Page 115: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16126-112

WIRE AND CABLE SPECIFICATION SHEET

BC1

BARE COPPER GROUND CABLE

GENERAL REQUIREMENTS:

Annealed, uncoated, bare copper (ASTM B3).

SPECIFIC REQUIREMENTS:

1. Solid in sizes 4 AWG and smaller.

2. Class B stranded in sizes 2 AWG and larger (ASTM B8).

Page 116: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16126-113

SECTION 16126 - POWER CABLE INSTALLATION METHODS

PART 1 - EXECUTION

1.1 GENERAL

A. Install electric conductors and cables as indicated, in compliance with manufacturer's written instructions,

applicable requirements of NEC and NECA's "Standards of Installation"", and in accordance with

recognized industry practices.

B. Cables shall not be pulled into plastic conduit until all conduit joints made using plastic conduit cement

have been allowed to dry for at least ½ hour.

C. When pulling cables into conduit, the pulling line used shall have a safe working load rating (minimum)

equal to the maximum allowable pulling line tensions for the type and size of cables being pulled as

recommended by the manufacturer. Cables shall be pulled into conduit with a pulling eye attached to the

cable conductor or a pulling grip placed over the cable sheath, insulation or jacket.

D. When cables are pulled into straight conduit runs, the pulling line tension shall not exceed the values shown

in the manufacturer's shop drawings.

E. When cables are pulled into conduit runs including bends or sweeps, the maximum pulling line tension

shall not exceed 300 times the radius of curvature of the bend or sweep with the smallest radius expressed

in feet.

1.2 CABLES PULLING IN CONDUIT

A. Whenever possible, pull cables so that bends in the conduit into which the cables are to be pulled are

nearest to the feed-in end. This will result in minimum tension on the cables.

B. On long pulls, the pull-out location should be rigged whenever possible, so that an adequate amount of

cable for splicing and racking may be pulled into the manhole without the necessity of taking hitches on the

cable sheath or jacket.

C. In highly congested switchgear or where cables must be bent sharply to permit pulling, use a feed-in tube

for pulling in cables. This will reduce pulling tensions and prevent damage to the cables being pulled and

to other adjacent cables.

D. Before making a pull, conduits should be clear and free of dirt, rocks, etc.

E. When pulling three single conductor cables in one conduit, consideration should be given to the possibility

of the cables jamming, particularly at bends. This possibility occurs when the sum of the outside diameters

of the three cables approximately equals the inside diameter of the conduit they are to be pulled into. When

the possibility of jamming exists, pulling tension should be continuously monitored to ensure that damage

to the cables, should they jam, will be kept to a minimum.

F. Wire rope shall be used to pull cables in nonmetallic conduits unless all bends in the conduits are

constructed using a bent length of steel conduit or steel conduit elbows. Installation methods which

eliminate damaged to the conduit and associated elbows shall be used.

G. Do not pull cable into duct or conduit until factory test reports of cable have been approved.

H. Cables may be pulled by direct attachment to conductors or by use of basket weave pulling grip applied

over cables. Attachment to pulling device shall be made through approved swivel connection. Cable may

Page 117: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Conductors - Control Cables, Low Voltage Cables,

Ground Cables And Accessories

Volume III-16126-114

be pulled by using basket weave pulling grip, provided the pulling force does not exceed limits

recommended by manufacturer; if pulling more than one cable, bind them together with friction tape before

applying the grip. For long pulls requiring heavy pulling force, use pulling eyes attached to conductors.

I. Do not exceed manufacturer's recommendations for maximum allowable pulling tension, side wall

pressure, and minimum allowable bending radius. In all cases, pulling tension applied to the conductors

shall be limited to 0.008 lbs. per circular mil of conductor cross-section area.

J. Pull in cable from the end having the sharpest bend; i.e. bend shall be closest to reel. Keep pulling tension

to minimum by liberal use of lubricant, and turning of reel, and slack feeding of cable into duct entrance.

Employ not less than one man at reel and one in pullhole during this operation.

K. For training of cables, minimum bend radius to inner surface of cable shall be 15 times cable diameter.

L. Where cable is pulled under tension over sheaves, conduit bends, or other curved surfaces, make minimum

bend radius 50% greater than specified above for training.

M. Use only wire and cable pulling compound recommended by the specific cable manufacturer, and which is

listed by UL. Pulling compound shall be used liberally (at both ends of the pull) to minimize any damage

to the conduit system and cables and to keep pulling tensions to a minimum.

N. Seal all cable ends unless splicing is to be done immediately.

O. Train and support all cables in manholes, pullholes, concrete trenches, and similar locations by cable racks

and secure to rack insulators with nylon cord and self-locking nylon cable ties.

1.3 AFTER INSTALLATION TESTING

A. After installation and before the operating test on connection to the existing system, the cable shall be given

a high potential test.

B. Test all cable per ICEA Standards. Notify Owner's representative of proposed date of test sufficiently in

advance so that arrangements can be made for the Engineer and the Owner's personnel to witness the test.

C. Test the conductor for continuity with all equipment disconnected.

D. Submit three (3) copies of test, properly labeled, to the Engineer of review. Include all necessary test

information such as cable system identification, ambient temperature, weather conditions, current, voltage,

cable length, size, etc.

1.4 CABLE PHASING

A. Each cable shall be properly "phased" to assure proper connection to the system.

B. Supply all equipment needed to make phasing checks.

C. Notify the Engineer and the Owner sufficiently in advance of making phase checks to allow for

arrangements to be made for the witnessing of the tests.

D. Make necessary changes to cable connection points, as determined by phasing checks, and reverify phasing

after any cable changes.

END SECTION 16126

Page 118: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Lighting and Low Voltage Power

Volume III-16445-115

DIVISION 16 - ELECTRICAL

SECTION 16445 - LIGHTING AND LOW-VOLTAGE POWER

PART 1 - GENERAL

1.1. SUMMARY

A. This Section covers the furnishing and installation of lighting materials and equipment complete as

indicated on the Drawings and specified herein.

1. Exterior lighting systems.

2. Luminaries and fixtures.

3. Receptacle power systems.

4. All necessary mounting, wiring, and accessories.

B. Related Work Specified Elsewhere:

1. Conductors: Section 16120.

2. Conduit and Accessories: Section 16110

3. Project Documents: Volume IV (Drawings).

1.2. REFERENCES:

A. Applicable Standards

1. American National Standards Institute (ANSI)

(a) C78 Series

(1) Incandescent Lamps.

(2) Electric Discharge Lamps (Fluorescent).

(3) Electric Discharge Lamps (HID).

(b) C81 Series - Electric Lamp Base and Holders.

(c) C82 Series - Lamp Ballasts

2. National Fire Protection Association (NFPA).

(a) 70 – National Electric Code (NEC).

(b) 101 - Life Code.

B. Acceptable Manufacturers:

1. Lamps:

(a) Holophane.

2. Switches:

(a) Bryant Electric Company.

(b) Leviton MFG. Co. Inc.

(c) Hubell Inc.

(d) Pass & Seymour Inc.

(e) Arrow Hart, Div. Crouse-Hinds Co.

3. Luminaries and Fixtures: As specified for each type.

Page 119: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Lighting and Low Voltage Power

Volume III-16445-116

4. Receptacles – Miscellaneous single and duplex; Straight-Blade and locking:

(a) Arrow-Hart, Div. Crouse-Hinds Co.

(b) Bryant Electric Company.

(c) Hubbell Inc.

(d) Leviton MFG. Co. Inc.

C. The Contractor shall furnish equipment and materials meeting the specified ratings and performance at the

altitude and ambient temperatures specified in DIVISION 1.

1.3. COMPLIANCE SUBMITTALS:

A. Submit as specified in Division 1.

B. Information for each light fixture, switch, receptacle, etc.

C. In the event of a proposed substitution of the lighting specified, the Contractor shall submit the following

information to the engineer for approval before an order is placed for such fixtures.

1. A complete fixture description.

2. A complete set of photometrics for proposed fixture.

3. If required by Engineer, operating sample units of fixture proposed as substitute to those specified.

PART 2 - MATERIALS

2.1. GENERAL REQUIRMENTS

A. All equipment and materials to bear UL label and conform to applicable standards specified.

B. All materials and devices shall be in accordance with the applicable requirements of the Federal

Occupational Safety and Health Standards (OSHA).

C. All necessary wiring and accessories for complete installation.

D. Systems:

1. 120-V, single-phase, 2-wire system.

2.2. SUBSTATTION YARD LUMINAIRE:

A. Rated 120 volt, 60 hertz, ac

B. Heavy-duty, LED, per material list.

C. Weatherproof, aluminum housing with Alzak aluminum reflector, top and bottom.

D. Optical assembly shall be shock and impact resistant.

E. Ballast assembly, suitable for +/- 5 percent fluctuation at rated voltage.

F. Bracket arm assembly with common mounting for luminaire and ballast assemblies.

2.3. SWITCHES:

A. All single-pole or three-way switches as indicated.

B. Surface-Mounted, Tumbler, Self-Grounding, Heavy-Duty Switches:

1. Rated 20 amperes at 120V, ac.

Page 120: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Lighting and Low Voltage Power

Volume III-16445-117

2. Gray toggle.

3. FS and FD single or multiple gang boxes.

4. Stainless-steel cover plates with matching countersunk screws.

5. Locations as indicated.

6. Leviton Manufacturing Company "Industrial" specification grade.

2.4. RECEPTACLES:

A. Straight blade, duplex.

1. Rated 20 amperes at 125V ac, 2 pole, 3 wire, grounding type.

2. Polarized, parallel blade, arc resistant, specification grade, NEMA Reference 5-20R.

3. Ivory.

4. FD malleable-iron single box surface-mount enclosure.

5. Stainless steel cover, brushed satin finish, with matching countersunk screws.

6. Leviton Manufacturing Company No. 8300-I or approved equal receptacle.

2.5. FIXTURE SUPPORTS

A. All lighting fixture supports, hangers, clamps, and fasteners required shall be furnished

2.6. RACEWAY

A. All exterior lighting raceway fittings shall be as specified in Section 16110.

PART 3 - ERECTION

3.1. INSTALLATION:

A. Fixtures

1. Each complete fixture shall be secured to its support assembly. This work includes but is not limited

to all special drilling, assembling, disassembling, reassembling, and wiring.

2. Fixture maintenance shall be continuous until the date of commercial operation. All fixtures shall be

cleaned immediately prior to the Contractor leaving the jobsite unless otherwise directed by the

Owner.

3. Location.

(a) Fixture locations indicated on the Drawings are approximate and shall be coordinated with other

work in the same area to prevent interference between lighting fixtures and or other equipment.

Any fixture shall be relocated if, after installation, it is found to interfere with other equipment

or is so located to prevent its practical and intended use. No fixture shall be located to prevent

the full use of any access way.

4. Alignment.

(a) Fixtures installed in rows shall be carefully aligned vertically and horizontally. Lighting

fixtures and outlets boxes, mounted on building steel, shall be centered on the beam flanges or

webs, except where deviations are required to avoid interference with piping or miscellaneous

steel.

5. Mounting.

(a) Provide fixture mounting as indicated for all substation luminaries.

B. Luminaries:

Page 121: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Lighting and Low Voltage Power

Volume III-16445-118

1. Install as indicated including fuses and all necessary mounting and supporting materials.

2. Maintain the lighting system throughout the construction period including replacement of burned out

lamps, repair of un-operable fixtures as directed by the Engineer.

3. Prior to final acceptance, lighting system shall be fully checked. At this time, all defective lighting

fixtures, ballasts, lamps, etc., shall be repaired or replaced.

C. Switches:

1. Mount 4'-6" above floor, walkways, or finished grade unless otherwise indicated including all

necessary mounting and supporting materials.

2. Install close to frame on lock or latch side when located near doors.

3. Flush mount in finished areas and surface mount in all other areas unless otherwise indicated.

4. Install weatherproof switches outdoors or as indicated.

D. Receptacles:

1. Install as specified or indicated including all mounting and supporting materials.

2. Install flush-mount receptacle outlets 1'-0" above floor in finished rooms except as otherwise indicated.

3. Install surface mount receptacle outlets 3'-0" above floor in all other areas except as otherwise

indicated. Use FS and FD boxes.

4. Shift-location if necessary to avoid interference with other apparatus or material.

E. Wiring:

1. Each conduit shall contain not more than one conductor of each phase and one or more neutrals as

necessary.

2. Each receptacle circuit shall have an identified neutral and identified grounding conductor.

3. Use circuit numbers as indicated.

4. Use cable as specified for lighting and receptacle circuits.

5. Do not use wire smaller than No. 12 AWG.

6. Contractor shall size and install proper wire size, as required, such that the voltage drop from the

power or lighting panel to the farthest light fixture or receptacle does not exceed 5 percent. Contractor

shall be required to rewire circuits which exceed 5 percent.

7. Splice in boxes only with twist-on electrical connectors, pre-insulated closed end splices with free

expanding spring to apply strong uniform holding power on all wire combinations. Acceptable

manufacturers are as follows:

(a) Minnesota Mining and Manufacturing (3M) Scotchlok.

(b) Buchanan B Cap Connectors.

8. Install all lighting circuits in field routed conduit systems as specified in DIVISION 6.

9. Install emergency lighting circuits in a separate conduit system.

3.2. FIELD TESTING: Specification in Section 16700.

END SECTION 16445

Page 122: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Major Substation Equipment

Volume III-16510-119

DIVISION 16 - ELECTRICAL

SECTION 16510 – INSTALLATION OF MAJOR SUBSTATION EQUIPMENT

PART 1 - GENERAL

1.1 DESCRIPTION

A. This Division includes Contractor requirements for the unloading, moving, storage, transport, installation,

and necessary field assembly of equipment and materials furnished by the Owner. Quantity and delivery

date are as indicated.

1. Materials will be delivered to the Project sites or Materials Receiving and Storage Yard (Page Electric

Utility warehouse located next to the project site) at the location of Page Electric Utility offices. The

Contractor is responsible for transport of equipment that is received at Page Eclectic Utility warehouse.

B. Related Work Specified Elsewhere:

1. Substation Grounding: Section 16610.

2. Field Testing: Section 16700.

3. Contract Documents: Project Drawing Sets.

PART 2 - PRODUCTS

2.1 EQUIPMENT AND MATERIALS: Provide all equipment and materials required for the installation of

major substation equipment.

2.2 RECEIVING, STORAGE AND TRANSPORT OF MATERIALS:

A. General:

1. Receipt of Materials:

a. Unload all equipment promptly when delivered and pay all demurrage charges and claims from

damage to cars or vehicles resulting from Contractor's unloading operations. The Contractor shall

be responsible for the proper location of trucks for unloading.

b. Inspect all equipment and material for damage and check against shipping receipts for any missing

parts. Inform the Engineer of any shortages or damaged materials at the time of delivery. Report

obvious shipping damage immediately to the Owner Repersentative. Note the damage on the

shipping company's forms before accepting shipment.

c. Prepare material receipts on standard forms as furnished by the Engineer.

d. The Contractor shall dispose of all nonreturnable gas bottles.

B. Medium-Weight Equipment Receiving:

1. Use cranes or fork lifts of sufficient size to prevent overloading of lifting equipment. Do not load

rigging in excess of its recommended safe working load. When fork lifts are used, line the forks so

that equipment finishes will not be marred.

2. Rigging equipment shall be inspected prior to use and during its use to assure safety. If found

defective, the rigging equipment shall be replaced.

3. Use lifting hooks, eyes, etc., if provided on the equipment for lifting.

4. Use rope or synthetic webbing for slinging.

C. Material Storage:

1. Equipment and materials shall be placed in storage areas as designated.

2. Storage areas shall be divided into lots for the storage of each particular substation's materials.

3. Materials shall be stored such that materials being used first will not have to be lifted over materials

which will be used later.

4. As much as possible, all parts for a particular piece of equipment shall be stored in one location.

5. Deliver all spare or extra parts to the Owner's warehouse at the Newport Substation and store as

directed by the Engineer at the end of the job.

Page 123: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Major Substation Equipment

Volume III-16510-120

D. Material protection as specified in DIVISION 1.

PART 3 - EXECUTION

3.1 GENERAL:

A. Install equipment and materials completely as specified and as required for operation and continuous

service at the locations shown on the Drawings.

B. Include assembly of all shipping sections and miscellaneous items of equipment shipped unassembled as

received from the manufacturer.

C. Install at times as required to meet the specified construction schedule and as necessary to move equipment

into place without delaying erection of structures. Do not place equipment onto concrete foundations until

minimum concrete compressive strength requirements are met as follows:

1. Structure foundations shall be cured at least 7 days and shall have a concrete compressive strength

greater than 70 percent of the specified minimum 28-day strength prior to the installation of structures.

2. Equipment foundations shall be cured at least 14 days and shall have a concrete compressive strength

greater than 85 percent of the specified minimum 28-day strength prior to the installation of

equipment.

3. Structure foundations shall be cured at least 28 days and shall have a concrete compressive strength

greater than or equal to 100 percent of the specified minimum 28-day strength prior to attaching wires

to structures on these foundations.

D. Include any disassembly and reassembly of any parts or sections of equipment made necessary by

obstructions or other limitations encountered in moving equipment to the final location indicated.

E. Conform exactly to the manufacturers recommendation in all respects. Any conflict between the Contract

Drawings and Specifications and the manufacturer's written or verbal recommendations shall be referred to

the Engineer for final decision.

F. Provide all openings in floors, walls, roofs, and other structures necessary for complete equipment

installation and connection unless such openings are specifically noted on the Drawings or reference

drawings as being provided by others.

G. Paint all non-galvanized steel supporting material with one coat of red lead chromate primer and two finish

coats of fast drying enamel of color selected by the Engineer.

H. Include leveling, shimming, anchoring to floor or foundations with bolts or cinch anchors, and any

necessary grouting.

I. Include receiving, caring for, and finally delivering to Owner's storage, all tools, maintenance devices, and

other accessories furnished with the equipment.

J. Include removing and replacing any covers, bus and wiring connections, etc., whenever and for whatever

number of times it is directed by the Engineer for inspection or testing.

K. Restore all equipment to a "factory clean" condition before final acceptance is made.

3.2 RS PAD MOUNT SWITCHGEAR

A. Inspection, Handling and Installation.

1. Examine Each PME-10 for external evidence of damage at receipt. If there is visible damage notify

Page Utility.

2. The contractor is responsible for handling and installation in accordance with the Manufactures

Installation Bulletin 666-505 ( Bulletin provided with each unit).

3. The Contractor is responsible for installation of PME-10 Mounting boxes/pedestal. Boxes to be

mounted on properly compacted soils and in accordance with Manufactures requirements.

4. Contractor is responsible to achor the pad mounted gear to foundation box pad.

Page 124: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Major Substation Equipment

Volume III-16510-121

5. The contractor is responsible for pad mount gear 25kV cable interconnection.

6. The contractor is responsible for pad mount switchgear grounding.

7. Connect all external and internal wiring circuits, including control, power.

8. The Contractor is responsible to anchor the pad mounted gear to foundation pad.

3.3 SUBSTATION EQUIPMENT AND MATERIALS:

A. General:

1. This Contract will perform all receiving, storing, assembling, and installation of all insulators, bus

materials connectors, disconnect switches, equipment, etc., as indicated by the Drawings and Bills of

Material and directed by the Engineer in order to place the equipment in complete working order.

2. The attachment hardware is to be furnished and installed by this Contract.

B. Equipment Assembly:

1. Install conduit risers complete to equipment enclosures.

C. Substation Bus Assembly

1. General

a. The Contractor shall install all of the substation buswork.

b. Buses, jumpers, insulation, connectors and other hardware shall be installed in accordance with the

applicable Drawings. Clearance and spacing shall be equal to or greater than NEMA Standard

SG-6, "Recommended Spacing and Clearances." All conductors at joints and fittings shall be

cleaned and free of foreign matter.

c. Maintain proper phasing of buses and connections as indicated. Install phase identification plates

as specified.

2. Strain and Jumper Buses

a. Strain and jumper buses shall be installed in accordance with Drawings, manufacturer's

recommendations and the Engineer's requirements.

b. Jumpers and buses shall be smoothly formed, and adjacent runs shall be similarly and

symmetrically shaped to provide a uniform and pleasing appearance throughout.

c. Stranded conductor shall be installed without twists or kinks and shall be handled to avoid

abrasions or other damage. No splices shall be allowed in overhead strain buses.

d. All strain buses and incoming line conductors shall be sagged according to values supplied be the

Engineer and at the direction of the Engineer. Phase conductors and shield wires shall be installed

such that maximum tension shall not exceed those indicated on the Drawings. All strain buses and

incoming lines shall be terminated on the structures and not on equipment bases.

e. Install complete termination of incoming transmission lines at the substation structures.

D. Substation Connectors Assembly

1. Welded Electrical Connections

a. Welded fillings shall be used for electrical connections as shown on the drawings.

b. All bolts shall be properly tightened by alternately tightening the nuts with a torque wrench until

the torque values recommended by the manufacturer are reached. Threads shall not be over-

stressed. Bolts in clamps over stranded conductor shall be tightened enough to flatten the lock

washers, but not enough to deform or damage conductor.

c. The Contractor shall obtain the chart of bolt torque recommendations from the manufacturer and

make it available to the Engineer during construction.

d. Connections of each type shall be made per the following instructions:

(1) Aluminum-to-aluminum connections:

(a) Clean contact areas of conductors and fittings to remove oxide.

(b) Completely coat these contact areas with a liberal amount of corrosion inhibitor.

(c) Abrade these contact areas through the grease with a stiff wire brush. CAUTION - Do

not remove grease.

Page 125: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Major Substation Equipment

Volume III-16510-122

(d) Add more compound and make connections. Alternately tighten nuts with a torque

wrench until the recommended torque values are obtained. Use caution in tightening

lubricated bolts.

(e) Do not remove excess compound that squeezes out of connection, since this helps prevent

the entrance of moisture and dirt.

(2) Aluminum-to-copper connections: When making the following connections, place the

aluminum conductor above the copper conductor:

(a) Connecting tin-plated copper or bronze terminal connector or pad to aluminum terminal

pad:

1) Prepare the aluminum pad as follows: (1) Clean contact area to remove oxide; (2)

completely coat the contact area with a liberal amount of corrosion inhibitor; (3)

abrade the contact area through the corrosion inhibitor with a stiff wire brush.

CAUTION - Do not remove grease.

2) Do not abrade or wire brush the plated fittings. A few light rubs with fine steel wool

before greasing is sufficient.

3) Grease contact surfaces of the copper or bronze connector with corrosion. inhibitor,

adding more inhibitor to the aluminum contact.

4) Make connections.

(3) Connecting aluminum terminal with bonded copper contact on tongue to bronze or copper

pad:

(a) Clean contact areas.

(b) Grease with corrosion inhibitor.

(c) Make connection.

(4) Connecting aluminum pad to copper or bronze pad, using bimetallic transition plate:

(a) Prepare aluminum, pad, and the aluminum side of the transition plate as described in

above.

(b) Clean the contact areas of the bronze or copper pad and the copper side of the transition

plate.

(c) Grease the surfaces of the bronze or copper pad and the copper side of the transition plate

with corrosion-inhibiting compound.

(d) Add more corrosion-inhibiting compound to the aluminum contact surfaces.

(e) Make the connections with the aluminum side of the contact plate in contact with the

aluminum pad, and the copper side of the contact plate in contact with the copper pad.

e. Provision shall be made for connecting the copper ground cable to all lightning arrester grounds,

structures and electrical equipment cases and/or neutral connections. Adequately fasten the

grounding cable to the various structural members to give a neat appearance and as approved by

the Engineer.

f. On long cable runs along horizontal structural members, clamp type connectors shall be spaced at

no more than 2'-0" center-to-center. On long cable runs along vertical structural members, clamp

type connectors shall be spaced at not more than 4'-0" center-to-center.

2. Compressions Connectors

a. Compression connectors shall be installed in strict accordance with the manufacturer's

recommendations.

b. Use an ample amount of corrosion-inhibiting compound.

c. The connector shall be the proper size to fit the cable as recommended by the manufacturer.

d. Tools and dies of the proper size and type as recommended by the connector manufacturer shall be

used for installation.

3. Jumpers and Taps

a. Jumpers and vertical cable taps shall be installed of such length and form as to maintain proper

clearance from surrounding objects.

b. Jumpers shall be neat but shall have enough "slack" to allow for movement during a seismic event.

Page 126: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Major Substation Equipment

Volume III-16510-123

E. Insulator Assembly

1. All insulators and bushings shall be cleaned of oil, dirt, paper, tape or other foreign materials. Any

insulator or bushing having the surface glaze damaged in any way shall not be installed.

2. The Contractor shall be responsible for providing any miscellaneous hardware that is required for a

complete insulation system to the substation structures. Miscellaneous hardware can include nuts,

eyebolts, shackles, clevis-pieces, etc. The Contractor shall furnish such miscellaneous hardware to

complete the insulation system in conformance with the Drawings.

3. All insulators are to be inspected for damage prior to energizing the substation.

END OF SECTION 16510

Page 127: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

High Voltage Buss, Insulators, Connectors,

Material and Hardware

Volume III-16520-124

DIVISION 16 - ELECTRICAL

SECTION 16520 - HIGH VOLTAGE BUS, INSULATORS, CONNECTORS, MATERIALS AND HARDWARE

PART 1 - GENERAL

1.1 SUMMARY

A. This Division includes the individual specifications and requirements for high-voltage bus, insulators,

connectors, structures, materials, and hardware to be furnished and installed by this Contract at the

substations.

B. Items to be furnished under this Division include, Aluminum Conductor Steel Reinforced (ACSR), shield

wire, electrical pad connection bolt and welded assemblies, equipment mounting bolt assemblies,

suspension insulators, bus support insulators, bus fittings and hardware, conductor connectors, clamps and

fittings, grounding studs, stud connectors, transmission line fittings, miscellaneous steel structures, etc., as

required. Quantities shall be as indicated and/or as required for a complete installation.

C. The Contractor shall furnish equipment and materials meeting the specified ratings and performance in

accordance with the specified standards.

D. Related Work Specified Elsewhere:

1. Installation of Major Substation Equipment: Section 16510.

2. Contract Documents: Project Drawing Sets.

1.2 REFERENCES:

A. Design, construct, test, and assemble all equipment and materials in conformance with the latest revisions

and supplements of all applicable ANSI, NEMA, IEEE, ASTM, OSHA, NESC, NEC, and UBC standards

including, but not limited to, the following:

B. Acceptable manufacturers are listed separately with each item of equipment and material. Other

manufacturers than those listed may be employed with the approval of the Engineer, and if the item to be

furnished conforms with this specification.

C. Experience:

1. The manufacturer of each item of equipment or material furnished shall be regularly engaged in the

fabrication of the item and it shall have an acceptable history of satisfactory, reliable service in outdoor

substation use for a period of at least three years under comparable environmental conditions.

2. Newly-developed equipment with less than three years actual service will be considered from

established manufacturers only if it has been adequately tested, meets the requirements of this contract,

and is approved by the Engineer.

1.3 COMPLIANCE SUBMITTAL:

A. Submit as specified in DIVISION 1.

B. For each item, furnish the following types of drawings:

1. Furnish drawings necessary for design, erection, installation, and operation of all equipment and

materials furnished including, but not limited to, the following:

a. Rigid bus plan indicating bus lengths and coupler locations, complete with bill of material item

numbers.

b. Complete bill of material including item numbers and manufacturers' catalog numbers.

c. Complete drawings and descriptive bulletins for installation, adjustment, testing, maintenance, and

operation of all equipment including bus weldments, connectors, insulators, fittings, etc.

d. General outline drawings and nameplate.

e. Drawings showing additional detail if requested by the Engineer or otherwise required for

installation and maintenance.

Page 128: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

High Voltage Buss, Insulators, Connectors,

Material and Hardware

Volume III-16520-125

2. Standard drawings of equipment which do not indicate clearly the exact size, model number, and

optional items to be furnished will be returned to the Contractor for this information before review by

the Engineer.

1.4 ACCEPTABLE MANUFACTURERS OR APPROVED EQUAL:

A. Suspension and Bus Insulators :

1. NGK-Locke.

2. Lapp (porcelain station post).

3. Sediver.

4. Reliable.

B. Conductor:

1. Alcoa.

2. Anderson (Hubbell).

C. Tubular and Stranded Aluminum Bus Connectors - Weldments:

1. Sefcor.

2. Anderson (Hubbell).

3. Burndy.

4. Alcoa.

5. Gibbons.

6. Frankel

7. Royal

8. Continental

D. All Other Equipment and Materials:

1. Manufacturers meeting the requirements and standards of the items specified.

PART 2 - PRODUCTS

2.1 GENERAL

A. All insulators and bushings shall be clean of oil, dirt, paper, tape or other foreign materials. Any new or

reused insulator or bushing having the surface glaze damaged in any way shall not be installed.

B. The Contractor shall be responsible for providing any miscellaneous hardware that are missing and

necessary to install a complete insulation system to the substation structures. Miscellaneous hardware can

include nuts, eyebolts, shackles, clevis-pieces, etc. The Contractor shall not delay the project on the basis

of miscellaneous materials that are missing. The Contractor shall furnish such miscellaneous hardware to

complete the insulation system in conformance with the Drawings.

2.2 BUS INSULATORS:

A. The bus insulators shall be of the type and kind as indicated on the project drawing sets.

PART 3 - EXECUTION

3.1 GENERAL

A. The Contractor shall furnish and install all material required to complete the work specified herein. The

Contractor shall become thoroughly familiar with the specified work requirements and determine for

themselves the exact quantities necessary to complete the work.

B. The Contractor shall provide Burndy “Penatrox A” electrical joint compound or an equivalent preparation

as a corrosion-inhibitor on all electrical connections.

C. All nuts, bolts, and washers shall be cadmium plated, brass, or stainless steel as required. Aluminum is not

acceptable.

Page 129: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

High Voltage Buss, Insulators, Connectors,

Material and Hardware

Volume III-16520-126

3.2 STRAIN BUS:

A. Provide jumpers as indicated, constructed with 795 kcmil, bare ACSR.

B. Provide static (overhead ground) wires constricted with 3/8" extra high-strength grade galvanized steel.

3.3 CONNECTORS AND FITTINGS:

A. The Contractor shall furnish and install all connectors and fittings to completely erect the substation and

connect all materials and equipment that are listed in the drawing material lists. The Contractor shall

furnish and install all material not listed in the Bill of Material but required to complete the work specified

herein. The Contractor shall become thoroughly familiar with the specified work requirements and

determine for themselves the exact quantities necessary to complete the work.

B. The Contractor shall provide “Penatrox A” electrical joint compound or an equivalent preparation as a

corrosion-inhibitor on all electrical connections.

C. Strain or deadend clamps shall be of forged steel, galvanized, and shall be complete with galvanized wye-

clevis-eye fittings; and the assembly shall have mechanical strength of not less than 15,000 pounds.

D. Insulator assembly hardware shall be malleable iron or forged steel, galvanized, and shall have a

mechanical strength of not less then 15,000 pounds.

E. Connectors shall be of the following types:

1. Proper size and design to assure permanent, secure, low-resistance connections.

2. Weldment types for aluminum tubing connections and puddle-weld type for aluminum cable

connections. Do not mix types of connections for aluminum tubing. Use all weldment type

connections for aluminum tubing.

3. Use tubular aluminum internal type splicing sleeves for splices in aluminum tubing.

4. For connections between aluminum tubing and cable, use a tubing-to-terminal pad connector and a

cable-to-terminal pad connector.

5. Furnish flexible terminal type where tubing connections are made to bushing studs, breakers, switches,

and other equipment, as indicated. Use expansion-type connectors with internal ball-type alignment

guides, utilizing laminated shunts oriented horizontally.

6. For electrical pad connections, provide stainless steel hex-bolts, hex-nuts, flat washers, and Belleville

washers. Belleville washers shall have a minimum compression rating of 4,000 pounds. Bolt lengths

shall be sized to provide minimal projection beyond hexnut to prevent excessive noise due to corona,

but entire hexnut must be engaged.

7. All dead-end fittings for stranded aluminum conductor shall be tubular compression type fittings. In

no case shall any type of stranded aluminum conductor be used with bolted or clamp-type fittings,

except for through-type connections to surge arresters on transformers, and at other locations indicated.

Furnish 5 percent extra dead-end body filler plugs for each type used.

8. Stranded and tubular copper bus work, where used, shall have connectors and fittings with a minimum

of four bolts or two "U" bolts on each side of each joint.

9. All connections between stranded aluminum conductors and equipment stud terminals shall be made

with a stud-to-pad type stud connector and a cable-to-pad type conductor termination.

10. Fittings shall develop the full strength of the conductor, and shall be capable of carrying the full

current capacity of the conductor.

11. Fittings for shield wire dead ends shall be compression type with bolted jumper connection.

12. Furnish "Alcoa Filler Compound" for application in conductor dead-end bodies and Alcoa No. 3

Electrical Joint Compound (Alnox), or approved equal for aluminum connections. Furnish 5 percent

overage of all filler compounds furnished.

13. Bus support clamps for rigid bus shall be fixed or slip type as required to firmly support the bus but

allow for temperature expansion and contraction.

14. Provide bolted ground connector and flexible type grounding jumper for operating handles of

disconnect switches.

15. All transformer and power circuit breaker stud connectors shall be tinned bronze material.

16. All compression tees are to be open type compression run and 4-hole NEMA pad tap.

17. Where indicated, furnish bundled jumpers.

18. For disconnect switch connections, provide NEMA type terminal pad connectors with at least four

bolts.

Page 130: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

High Voltage Buss, Insulators, Connectors,

Material and Hardware

Volume III-16520-127

19. It shall be the Contractor's responsibility to furnish all materials so as to have mechanical and electrical

ratings, types, sizes, etc., coordinate with adjacent hardware and fittings.

20. All hardware furnished shall be static-free type.

21. Provide ground jumper direct from switch-operator ground pad to ground connector on operating

handle or mechanism of switch. A direct ground connection from the ground grid is also to be made to

the switch-operator pad.

22. Provide wire guides and bundle conductor spacers as required and indicated to maintain adequate

clearance and support on cable jumpers, connections, and overhead lines.

23. Provide all equipment mounting bolts and hardware to meet ASTM A307. Insulator cap screws shall

be sized to provide maximum thread engagement without exceeding tapped hole depth of casting. All

connections shall include properly sized hex-bolt, hex-nut where applicable, flat washer and lock

washer.

END OF SECTION 16520

Page 131: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Grounding

Volume III-16610-128

DIVISION 16 – ELECTRICAL

SECTION 16610 - SUBSTATION GROUNDING

PART 1 - SCOPE

1.1. WORK INCLUDED

A. This section covers the work necessary to completely install the station electrical grounding system in the

substation yard to achieve an earth-to-grid resistance of 1.0 ohm or less. Grounding shall include a

complete buried system and a grounding system for all switches, shield wires, lightning arresters, reclosers,

circuit breakers, regulators, meter cabinets, potential transformers, power transformers, structures, fence,

control building, panels, switch platforms and other appropriate equipment. The drawings and

specifications show the grounding system expected to achieve the required resistance. Should further

modifications be required the Contractor shall make such modifications (i.e., add ground rods and/or cross

grid) as directed by the Engineer. Additional material and labor for work not shown on the drawings but

required by the Engineer shall be provided on a unit price basis.

PART 2 - MATERIALS

2.1. GENERAL

A. The Contractor shall furnish all ground materials also all other incidental items not specifically listed on the

drawings, but required to make the station grounding system complete. The Contractor shall provide all

labor, tools, and equipment necessary to excavate for and install the station grounding system as shown on

the drawings and specified herein.

2.2. GROUND RODS

A. Provide copper-clad steel ground rods not less than 3/4-inch diameter and 10 feet long.

2.3. GROUND CONDUCTORS

A. Provide #4/0 bare stranded soft drawn copper ground conductor as indicated in the drawings.

2.4. GROUND CONNECTIONS

A. Provide exothermic connections or compression connectors as indicated in the drawings, or approved

equal.

PART 3 - WORKMANSHIP

3.1. GENERAL

A. Except where specifically indicated otherwise, ground all exposed noncurrent-carrying metallic parts of

electrical equipment, raceway systems, and the neutral of all wiring systems in strict accordance with the

NEC, state, and other applicable laws and regulations.

B. Make connections of any grounding conductors to circuits 20 amps or above by a solderless terminal and a

5/16-inch minimum bolt tapped to the motor frame or equipment housing. Ground connections to motors

by fastening the terminal to a grounded connection box. Connect junction boxes to the equipment

grounding system with grounding clips mounted directly on the box or with 3/8-inch machine screws.

Completely expose bare metal at grounding conductor connection points so that good metal-to-metal

contact is made.

Page 132: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Grounding

Volume III-16610-129

C. Metal sheathing and any exposed metal vertical structural elements of buildings shall be grounded. Metal

fences enclosing the substation yard area shall be grounded in accordance with the fence grounding details.

Any metal equipment platforms which support electrical equipment shall be bonded. Provide good

electrical contact between metal frames and railings supporting, receptacles, pull cabinets, etc., and metallic

raceways carrying circuits to these devices.

3.2. BELOW GROUND INSTALLATION

A. The grounding grid shall be installed at a depth of 18 inches below subgrade and located as shown on the

drawings. The ground bus shall be buried outside the fence 36 inches from the fence. At conductor

crossings care shall be exercised so that the crossed-over cable is not damaged. Damaged cable shall be

replaced with new cable. Labor and material costs of replacing damaged cable shall be completely borne

by the Contractor.

B. In addition to the perimeter ground grid, all gates shall be enclosed by a loop ground bus within 18 inches

of the opening radius (inside) of the gate. Refer to the Grounding general location plan drawing.

C. Grounding conductors shall be straight and free from kinks, breaks, and other damage after installation.

Conductors shall be thoroughly cleaned prior to making connections.

D. All intersections of cables shall be connected together. All taps and ground rods shall be connected with

separate connectors to the main ground grid.

E. All junctions and splices shall be made at ground rods wherever reasonably possible.

F. Connections shall be of the compression type and shall be installed in accordance with the manufacturer's

recommendations utilizing tools recommended. All dirt shall be removed from the splice area, and care

shall be taken to ensure the conductors are clean and dry just prior to making the connection.

G. All equipment and all steel structures shall be connected to the ground system. This also includes all

panels, junction boxes, and auxiliary equipment.

H. All taps, junctions and splices shall be left uncovered until inspected and approved by the Engineer.

I. The ground grid shall be left uncovered until ground resistance measurements have been made by the

Contractor and witnessed by the Engineer.

J. After installing the ground conductor, the trench shall be backfilled with earth or other low resistivity

backfill material. Do not backfill with sand, gravel, or crushed rock. The backfill shall be thoroughly

compacted.

3.3. ABOVEGROUND INSTALLATION

A. All equipment shall be grounded as indicated on the detailed grounding drawings and specified herein.

Any additional holes required for making connections or securing cable fasteners to the structures shall be

made at the expense of the Contractor. Holes drilled in the structures, to fasten ground cables, shall be

treated to prevent rusting or other structure damage. All unpainted or ungalvanized metal surfaces

remaining after the ground connection has been made shall be restored to their original finish.

B. The Contractor shall neatly train conductors to equipment along the face of the footing or structural steel,

following all surfaces closely to the point of connection. Conductors running to equipment shall be

supported and secured with cable fasteners at intervals no greater than 5 feet.

C. Remove paint, rust or other non-conducting material from the contact surfaces before making any ground

connections.

Page 133: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Substation Grounding

Volume III-16610-130

D. The reclosers, transformers, regulators, and other major equipment shall be grounded through their ground

pads with two-bolt connectors. Each major equipment item shall have at least two ground pad type

connections and shall be attached to the main ground grid at a minimum of two locations.

E. All metal conduits shall be bonded to the ground grid as shown on the grounding detail drawings.

F. Connections of ground conductors to the equipment shall be made with two-hole bolt-on bar lugs, unless

otherwise specified, and connected in accordance with the manufacturer's recommendations.

G. Compression connections shall be installed in strict accordance with manufacturer's recommendations,

using tools and dies of proper size and type.

3.4. GROUND RODS

A. Typical Installation: Ground rods shall be driven vertically the full length of the rod until its top is at least

14 inches below the subgrade elevation.

3.5. FIELD TESTS

A. Using a test method approved by the Engineer, test the ground resistance of the grounding system in the

Engineer's presence. Should grounding system modifications be required due to high earth-to-grid

resistance, retest after such modifications are made.

B. Provide copies of reports of all grounding system tests to the Engineer.

3.6. FINAL INSPECTION

A. The Engineer shall review the complete buried ground system and the Contractor shall perform such

ground resistance measurements as may be required. The ground grid shall be covered only upon approval

of the Engineer.

B. Errors in the installation of the ground system shall be corrected by the Contractor at no expense to the

Owner as directed by the Engineer.

END SECTION 16610

Page 134: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Field Testing

Volume III-16700-131

DIVISION 16 - ELECTRICAL

SECTION 16700 – FIELD TESTING

PART 1 - GENERAL

1.1 DESCRIPTION

A. This Division covers the field testing of substation equipment and electrical systems installed or

constructed by this Contract. It is the intent of this specification that field testing by this Contract be

extensive and complete as specified to provide positive assurance of totally correct installation and

operation of equipment. The Contractor will be required to furnish the services of a testing company to

perform, but not be limited to, the tests contained in this DIVISION.

B. As a part of the Contractor’s proposal, the Contractor shall submit the name of its subcontractor, along with

a listing of equipment to be used by the subcontractor for functional checkout and equipment testing and

relay testing.

C. Testing shall include, but is not limited to, the following:

1. Test all wire, cable, electrical equipment, and systems installed or connected by this Contract to assure

proper installation, adjustment, setting, connection, and functioning in accordance with the Drawings,

these specifications, relay settings to be supplied by the Engineer, and the manufacturer's

recommendations.

2. Furnish all qualified personnel, supervision, and labor required for, and incidental to, testing.

3. Furnish all test equipment, qualified personnel, labor, and materials including special equipment

required for testing of all protective relays.

D. Checkout of electrical construction shall include, but not be limited to the following items in addition to the

checkout work described in other sections of these Specifications.

1. General equipment check per manufacturer recommendations and as approved by the Engineer.

2. Inspect for physical, electrical, and mechanical conditions.

3. Field wiring and grounding system verification.

4. Conductor insulation tests and Bus High-Pot test.

5. Minor corrections to factory wiring

6. Electrical equipment adjustments.

7. Exercise all active components.

8. Inspect all indicating devices for proper operation.

9. Test all electrical and mechanical interlock systems for proper operation and sequencing.

10. Inspect all bus connections including connection tightness utilizing a torque wrench.

1.2 QUALIFICATIONS:

A. Qualifications of Testing Contractor

1. The testing Contractor shall have a minimum of five (5) uninterrupted years of experience in the

inspection, testing, calibration, and startup of electrical apparatus, devices, schemes, systems, controls,

interlocks, etc. Specific experience shall include electrical power generation, transmission,

distribution, substations, and industrial power utilization equipment.

2. The Contractor shall be corporately independent of the electrical equipment manufacturers, suppliers

and installers of the equipment.

3. The Contractor shall utilize only full-time employees who are regularly engaged in electrical power

systems testing. Electrically unskilled employees shall not perform or assist in testing of any kind.

4. The Contractor shall have a registered professional electrical engineer on staff as a full time employee.

5. The testing agency shall be an independent testing agency and shall not be affiliated with an

engineering or construction company.

B. Qualification of Contractor Personnel:

1. Classifications:

Page 135: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Field Testing

Volume III-16700-132

a. Field Service Engineers Classification: A field service engineer classification requires a BSEE

degree in electrical engineering and 5 years of actual test experience required.

b. Senior Technician: A senior technician classification requires a two year degree or equivalent

technical education in an electrical and/or electronic curriculum. In addition to education, a

minimum of 6 years actual test experience is required.

c. Technician: A technician classification has the same general educational requirements as a senior

technician. In addition to education, a minimum of 3 years of actual test experience is required.

d. Junior Technician: A junior technician classification has the same general educational

requirements as a senior technician, but requires less than 3 years actual test experience.

2. Experience on both new and existing energized power and control system installations.

3. Proficient in reading all types of electrical power and control systems drawings including system

coordination data.

4. An in depth understanding of power and control system design, including metering and protective

relaying schemes.

5. Successful completion of training which covers all elements of inspections, tests, and calibration of

electrical power systems in which the technician will be engaged.

6. Proficient in the use of test equipment and devices ordinarily used for inspections, tests, and calibration

of electrical power systems apparatus, including the interpretation of resultant test data.

7. Safety considerations applicable to the work being performed.

C. Test Reports:

1. Submit final test reports in quantities as specified in DIVISION 1 to the Engineer for approval. After

final approval, these will be distributed by the Engineer.

2. Maintain a written record of all tests showing date, personnel making test, equipment or material

tested, tests performed, and results. A copy of these reports shall be submitted to the Engineer weekly.

3. Notify Engineer two weeks prior to commencement of all testing.

4. The Engineer may provide test report forms for some tests. Fill out these forms as the tests are

completed in accordance with the above when supplied. When forms are not provided, the Contractor

may use his standard test forms.

PART 2 - PRODUCTS

2.1 REQUIREMENTS:

A. The testing firm shall furnish to the project all test equipment necessary for testing as specified herein.

The test equipment shall be supplied on an as-needed basis for use by the testing firm field service

personnel only.

B. The accuracy of all test equipment utilized by the testing firm for testing, calibrating, and in the evaluation

of all electrical apparatus, devices, systems. and controls shall be certified traceable to the National Bureau

of Standards (NBS). Each applicable piece of test equipment shall have a calibration tag which indicates

last date of calibration and calibration due date.

C. The testing firm shall utilize testing and calibrating standards of a higher degree of accuracy than that of the

device being tested.

2.2 EQUIPMENT:

A. The testing contractor shall furnish all test equipment required for complete testing and calibration of the

specified electrical power system apparatus, devices, and controls. The testing contractor shall submit a list

showing the proposed test equipment, along with the manufacturer, date, and model number of the

equipment.

PART 3 - EXECUTION

3.1 GENERAL REQUIREMENTS:

A. The testing company employed by the Contractor shall perform the following:

Page 136: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Field Testing

Volume III-16700-133

1. Be personally present on the jobsite during the testing of all wiring, controls and systems furnished,

installed, or connected by this contract and until they are all in complete and satisfactory operation and

the substation is in full operation.

2. Perform and direct the complete program of testing specified herein.

3. Personally check all wiring installed by this contract for proper connection according to the diagrams

shown in the plans, connection diagrams to be furnished later by the Engineer, and on the

manufacturer's shop drawings.

B. The Contractor shall perform all tests recommended by the equipment manufacturer including tests as

stated herein unless specifically waived by Engineer.

C. The Contractor shall include all additional tests issued by Engineer that are deemed necessary because of

field conditions, to determine that equipment and material and systems meet requirements of Contract

Documents.

D. The Contractor shall be responsible for all damage to equipment or material due to improper test

procedures or test apparatus handling.

E. After completion of testing and checkout of equipment, wiring, and other items associated with individual

systems, and believing a system to be ready for operation, the Contractor shall notify the Engineer who,

along with the Owner, will witness a final operational test of each individual system to be installed by this

Contract.

F. Upon testing, any deviations from these specifications and/or manufacturer’s specifications will be

recorded and included in the test report, reported to the Engineer, and corrective action shall be taken.

G. Connections shall not be made or testing done on existing equipment, facilities, circuits, or systems without

receiving proper authorization from the Owner and the Engineer. The Owner reserves the right to have

personnel present when connections are made or testing is done on any piece of equipment installed or

tested by this contract. Scheduling for such work shall be through the Engineer, subject to the Owner’s

approval. Work may be rescheduled at the Owner's discretion.

H. All test procedures, equipment, temporary circuits, etc., shall be designed and utilized to minimize danger

to testing technicians and surrounding personnel; i.e., current transformer temporary test circuits utilizing

alligator clips will not be permitted. The Contractor shall furnish and use safety devices such as rubber

gloves and blankets, provide protective screens and barriers, yellow tape, danger signs, to adequately

protect and warn all personnel in the vicinity of the tests.

PART 4 - TESTING

4.1 TESTS: The following are general test procedures to be used as specified on equipment indicated in

Section 4.2.

A. Insulation Resistance (Megger) Test:

1. Perform insulation resistance tests on equipment as specified in Section 4.2.

a. Apply voltage as-shown in the table below for 1 minute.

b. Resistance values at the end of one minute should be as shown.

c. Determine the values with all switchboards, panelboards, fuse holders, switches, and overcurrent

devices in place. Do not connect motors and transformers during meggering.

d. Megger wire and cable after installation, not on the cable reel.

e. Determine allowable procedures for this test from manufacturer's instructions for circuits

connected to solid state and microprocessor based equipment.

f. Determine allowable procedures for this test from manufacturer's instructions for solid state and

microprocessor based equipment.

Maximum Rating of

Equipment in Volts

Minimum

Test Voltage, dc in Volts

Recommended Minimum

Insulation Resistance in Megohms

250 500 25

600 1,000 100

5,000 2,500 1,000

Page 137: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Field Testing

Volume III-16700-134

8,000 2,500 2,000

15,000 2,500 5,000

25,000 5,000 20,000

35,000 15,000 100,000

46,000 15,000 100,000

69,000 15,000 100,000

B. Grounding Tests:

1. Perform ground tests prior to static wire attachment to line dead-end towers, or disconnect static

jumpers for insulated static wire installations.

2. Measure ground system resistance at each riser in the presence of the Engineer using the three-point

method (with electrodes diagonal to the grid) with a commercial test instrument approved by the

Engineer for the test.

3. Record results on forms provided and notify Engineer if any reading exceeds 1 ohm.

4. Test at least three of each type of ground connection and not less than 25 percent of all ground

connections.

5. Test the substation grid resistance to "remote" earth using the 3 point method in the following manner:

a. Extend an insulated conductor to a current electrode, 1000 feet diagonally away from one comer

of the substation grid.

b. Extend potential electrode to 800 feet from the corner of the substation fence and record

resistance.

c. Relocate potential electrode 50 feet closer to the substation corner and repeat test, continue in a

like manner for ground tests until a distance of 200 feet away from the substation grid is reached

for the potential electrode.

d. Record results on forms provided and notify the Engineer of the results.

e. Additional lead lengths may be required due to ground grid size and layout.

4.2 EQUIPMENT TESTS:

A. PME -10 Pad Mounted Switchgear:

1. Inspect pad mount gear cabinet and cable grounding.

2. Inspect 25kV Cable terminations and cable tagging.

3. Inspect and verify 120 volt cabling to control cabinet.

4. Preform Operational tests in accordance with Manufactures recommendation.

5. See manufacture bulletin on dielectric test restrictions.

B. Cable, 600-Volt and Below:

1. Verify cables terminated in accordance with Contract Drawings.

2. Verify tightness of connections and inspect compression connectors.

3. Perform insulation resistance test as specified in 4.l.A.

a. Test each conductor to ground and to all other conductors in cable (and shield, if applicable).

4. Perform continuity tests on all wiring to verify proper operation of all controls, as specified in 4.4.

C. Power Panels, ac and dc:

1. Inspect panels and circuit breakers. Verify nameplate data and compare to Contract Drawings and

Specifications.

2. Visually inspect all circuit breakers for correct mounting and operate manually. Clean out all ducts.

3. Verify proper grounding and test in accordance with 4.l.C.

4. Perform molded-case circuit breaker trip tests as follows:

a. Inject 3 times and 10 times rated current into each breaker and record trip time of circuit breakers.

Page 138: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Field Testing

Volume III-16700-135

b. Check results versus circuit breaker TC curves and notify Engineer of any discrepancies.

5. Check for proper current rating to circuit connected.

6. Verify proper operation of ground detector on all GFI breakers.

D. Field wiring checkout

1. The Contractor shall perform, a complete de-energized check of all field wiring installed under these

specification after installation and connection to verify conformance with the Drawings, shop prints,

and schematic wiring diagrams; to assure proper phasing and polarity of all power conductors; and to

confirm that cable shields are grounded at the points indicated on the Drawings and only at the points

indicated on the Drawings. These checks shall include but not be limited to the following.

a. Performance of continuity test to verify that each circuit installed or modified under this

Specification originates and terminated at the locations designated by the circuit list, Drawings, or

shop prints. Conformance or circuit terminations with connection diagrams shall be visually

checked.

b. Meggering or high potential testing shall be performed on all power, lighting, and control

conductors. Meggering shall not be performed with cable connected to protection devices or

equipment.

2. Check cable color coding and cable tagging for conformance to Drawings.

3. 25 kV Cables

a. Inspect exposed sections for physical damage.

b. Verify cable is supplied and connected in accordance with single-line diagram.

c. Inspect for shield grounding, cable support, and termination.

d. Visually inspect jacket and insulation condition.

e. Perform cable dielectric tests.

4.3 AUXILIARY EQUIPMENT ENERGIZATION: (600-V and below)

A. General:

1. Auxiliary equipment shall include equipment and materials necessary for the following:

a. 120/240V 1-phase station service power.

b. 48V dc power.

c. All power circuits connected to the power panels.

2. The Engineer shall be advised two weeks prior to the energization of this equipment. This equipment

may be energized from the backup or emergency source upon the concurrence of the Engineer.

3. The Contractor will be deemed to have concluded all testing and checkout of equipment prior to

energization. Preliminary test reports are required to be submitted to the Engineer prior to the

energization of the equipment.

4. Check all circuit connections immediately prior to energization.

5. Megger all circuits phase-to-phase, phase-to-around, wire-to-wire, or wire-to-ground immediately

preceding energization to assure temporary grounds have been removed.

6. Energize equipment one stage, section, circuit, or piece at a time to minimize damage upon equipment

failure and to aid in locating trouble areas.

7. Verify proper voltage levels, current levels, phasing, and rotation after each energization step. If

necessary, make corrections before proceeding to the next step.

8. Record all measurements and tests for future reference.

B. Lighting:

1. Test all systems for proper operation and correct phasing prior to final acceptance.

2. Test emergency lighting prior to final acceptance.

3. Make any possible adjustments to lighting at night to provide best light distribution in the substation

area.

Page 139: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Field Testing

Volume III-16700-136

4.4 ENERGIZATION PROCEDURE:

A. Coordination:

1. Initial Energization Procedure will be submitted to the Owners Representative at least two (2) weeks

prior to energization for approval and comments. Comments are to be returned to the Owners

Representative within one (1) week. If deemed necessary by the Engineer, a meeting will be held on

site prior to the energization date to discuss any details of the energization procedure.

2. Those to be present are as follows:

a. Owner, or his authorized representative.

b. Manufacturer's field representatives, as required by the Owner.

c. Contractor with following personnel:

(1) Craft labor for switching, removing grounds, etc.

(2) Testing personnel.

3. Responsibilities of those present during energization are as follows:

a. Owner:

(1) Witness initial energization or operation of equipment.

(2) Obtain and hold work clearances on existing facilities to allow final permanent connections to

be made by the Contractor. Owner may stop work from proceeding if such work, in his

estimation, will cause his system to operate unsatisfactorily or to drop load.

(3) Ensure that the initial energization procedure is followed.

(4) Provide test load with backup source for load tests and checks. It is realized that the test load

may be dropped during load testing.

(5) Perform switching procedures for energization in coordination with Contractor and Engineer.

b. Manufacturer's field representative:

(1) Perform or witness final tests on equipment.

(2) State in writing equipment is ready for energization.

(3) Witness initial energization.

c. Contractor:

(1) Perform all labor associated with clearing new bus equipment, etc., required to allow initial

energization.

(2) Make final connections as required for initial energization.

(3) Perform all work as specified, in existing facilities as required for initial energization. Do not

proceed with work in existing facilities until clearances have been given or obtained by the

Owner for the specific work at hand.

(4) Coordinate with the Engineer to obtain the required clearances.

(5) Witness initial energization of equipment.

(6) Perform all testing and/or corrective work required during initial energization.

(7) Be responsible for the installation of all equipment and materials installed under this Contract.

(8) Assure that the initial energization procedure is followed.

d. Owners Representative.

(1) Witness initial energization or operation of equipment.

(2) Coordinate with the Owner to obtain required work clearances.

(3) Coordinate with the Contractor to schedule completion of testing and construction to prepare

for initial energization.

(4) Coordinate with manufacturer's field representatives when their presence is required for initial

energization.

(5) Assure that the initial energization procedure is followed.

4. Initial Energization Procedure may be amended when required by field conditions and with the consent

of the Owner, Construction Manager, Contractor, and the Engineer.

5. Contractor shall provide testing personnel during energization of substation equipment as required.

Page 140: Powell Subs tation 21.6 witching Modificat roject · 2017. 1. 25. · 4. Receive, handle, and unload Materials at the delivery point, including uncrating and storage. 5. Promptly

Intermountain Consumer Professional Engineers, Inc.

Page Utility Enterprises: Powell Substation 21.6kV Switching Modification

Field Testing

Volume III-16700-137

B. Insulation Tests before Energizing:

1. Inspect bus arrangement for compliance with Drawings.

2. Examine bus and supports for defects, such as cracked welds, chipped porcelain, etc.

3. Check tightness of accessible bolted joints by using calibrated torque wrench.

4. Megger each high voltage bus or cable, or other major item of equipment just before it is energized

each time during construction, see PME manufactures dielectric test restrictions.

5. Megger between each phase and ground and between all phases and record.

C. Phasing and Synchronizing:

1. Maintain correct phasing on all circuits and buses. Substation buses and connections shall have

phasing as shown on the Drawings. Make phasing tests on all circuits that can be energized from two

or more sources to prevent paralleling of sources out of phase.

2. Phasing tests shall be made with the Owner’s representative present.

END SECTION 16700