pmo update to prs troy anderson program management office march 23, 2006
TRANSCRIPT
PMO Update to PRS
Troy AndersonProgram Management Office
March 23, 2006
2
Project and PPL UpdateProject and PPL Update
SCR738 – Enhancement to FasTrak approved by Board to go into Execution phase New project budget = $2.5M Go Live scheduled for 6/17/2006
PRR502 – Aggregation of Combined Cycle Units Providing RRS going into Execution phase Go Live scheduled for 3/30
Many ERCOT projects accelerated in 2005 moved to Closing status
March PPL posted to ERCOT.com on 3/14
3
PMO Process ReviewPMO Process Review
Project Cost Estimates & Budgeting
Step 1 – Initial Project Idea Proposed— Impact Analysis provides budget range based on reviews
with Subject Matter Experts— “<$100k”, ”$100k-$500k”, “$500k-$1M”, “$1M-$3M”
Step 2 – Project Idea is Approved— Detailed Time & Cost Estimate is prepared by CART team— This estimate includes a 35% contingency due to high
level nature of project requirements— Project is added to division portfolio based on logical fit
and resource plans
4
PMO Process ReviewPMO Process Review
Project Cost Estimates & Budgeting (continued)
Step 3 – Project Initiation/Planning— CART initiates project based on resource plans— During Planning Phase, estimate is refined based on
detailed design work— Exit criteria for planning: project plan, resource plan, final
requirements, and revised budget
Step 4 – Project Requests Move to Execution— Request for final Execution budget is presented to
Strategic Review Team (SRT = ERCOT directors)— This estimate includes 10% contingency— If total project budget exceeds $1M, approval to proceed
by the Board of Directors is required— Any change to scope, schedule or budget requires an
approved change control— Change controls are approved by sponsor (and SRT and
Board of Directors, if necessary)
5
Monthly Project UpdatesMonthly Project Updates
Issue: Improved understanding of ERCOT projects is needed
Solution: Monthly PRS agenda item for a brief overview from one of the five ERCOT Program Areas Program Area representative(s) attend PRS Brief presentation with Q&A (15 minutes)
Schedule:Program Area
January IO IT Operations
February SO System Operations
March RO Retail Operations
April MO Market Operations
May CO Corporate Operations
June TBD
6
Questions?Questions?