Planning New Construction

&

Major Ship Conversions

UsingUsing

PERCEPTION®

Page 2: Planning New Construction Major Ship Conversions Using

• Develop the Basic Product Structure• Hull Blocks, • Ship Zones, and • Equipment/Outfit Modules

Fundamental Project Tasks

• Identify Product Teams & Responsibilities

• Develop Manufacturing & Build Strategy

• Develop Management Strategy

• Execute the Plan

Page 3: Planning New Construction Major Ship Conversions Using

• Budgets (Labor & Material) & Schedules

Develop the

Production Management Plan

• Work Orders & Time Charging

• Material Control & Work Order Pallets

• Technical Packages for Production

• Tests & Quality Assurance

Page 4: Planning New Construction Major Ship Conversions Using

Develop the

Contract Management Plan

• Project Management Team

• Change Order Management

• Progress Milestones & Payment Management

Page 5: Planning New Construction Major Ship Conversions Using

Establish the Basic Building Plan

Product TeamsHull Block

Construction

PartsManufacturing

ZoneOutfit

Tests& Trials

Product Teams

EngineeringPlanning

PurchasingProduction

Page 6: Planning New Construction Major Ship Conversions Using

An integrated planning and resource

management system coordinates schedules and

tracks costs for

• Engineering,

• Purchasing & Deliveries,

• Inventory Control,

• Work Orders & Material Pallets,

• Trade Manpower,

• Subcontractors, and

• Shipyard Facilities.

Page 7: Planning New Construction Major Ship Conversions Using

Cost Estimating

Planning,

Budgeting & Scheduling

Labor & Manpower

Cost Management

Purchasing & Material

Cost ManagementCost Management Cost Management

Earned Value

Management Reporting

Cost Analysis

Page 8: Planning New Construction Major Ship Conversions Using

PERCEPTION Integrates the Shipyard

Business ProcessesBusiness Processes

Page 9: Planning New Construction Major Ship Conversions Using

PURCHASING

STORES

ENGINEERIN

G

PIPE SHOP

MACHINE

SHOP JOINER SHOP

SHEET

METAL SHOP

ELECTRICAL

SHOP

PREP & FAB

SUB-

ASSEMBLY

BLOCK

ASSEMBLY

PRE-OUTFIT

HOT

BLAST &

PAINT

PRE-OUTFIT

COLD

HULL BLOCK CONSTRUCTION

OUTFIT SHOPS

STEEL YARD

ERECTION

SITE

WET BERTH

INFORAMTIO

N SYSTEMS PLANNINGCONTRACT

ADMIN.

QUALITY

CONTROL

YARD

SERVICESSHIPYARD

ADMIN. FINANCE MARKETING

SUPPORT SERVICES YARD ADMINISTRATION

Page 10: Planning New Construction Major Ship Conversions Using

Planning and managing ship construction

requires careful coordination of a wide

variety of different resources & variety of different resources &

responsibilities.

Page 11: Planning New Construction Major Ship Conversions Using

• Engineering & technical development

• Purchasing & material control

• Subcontractors & vendors

• Production shops, trades & support services

• Hull erection sites and assembly areas• Hull erection sites and assembly areas

• Waterfront facilities & equipment

• Financial & project management services

• Classification societies & government authorities

• Ship owner representatives

Page 12: Planning New Construction Major Ship Conversions Using

Assembly operations are the most

significant cost drivers.

They are influenced by a very large degree

by when the assembly is performed.

Page 13: Planning New Construction Major Ship Conversions Using

Assembly on Outfit Unit

(most productive stage of construction)

Assembly on Hull Block

(more productive than on board ship)

Assembly on Board ship

(least productive stage of construction)

Page 14: Planning New Construction Major Ship Conversions Using

Primary Labor Costs: Assembly & Installation

Pe

rcen

t C

ost 300%

400%

Stages of ProductionParts Mfg On-Unit Ass'y On-Block Ass'y On-Board Ass'y

Pe

rcen

t C

ost

0%

100%

200%

Page 15: Planning New Construction Major Ship Conversions Using

Options for outfitting hull blocks:

1. "Stick" build outfit materials on block

2. Assemble outfit module in shop, then install

module on block.

Page 16: Planning New Construction Major Ship Conversions Using

"Stick" building outfit materials on block.

• Less productive work environment

than in shop.

• Few opportunities for repeatable

products cost savings.

Page 17: Planning New Construction Major Ship Conversions Using

Building outfit module in shop.

• More productive work environment

• Opportunities for repeatable products cost savings.

Page 18: Planning New Construction Major Ship Conversions Using

Installing outfit module on block

(limited effort outside shop).

Net Cost Savings

Page 19: Planning New Construction Major Ship Conversions Using

Productivity of Assembly On-Block

also is dependent upon block size.

Page 20: Planning New Construction Major Ship Conversions Using

Productivity vs Block Size

Pro

du

cti

on

Co

st

100.00

120.00

140.00

160.00

Block Size (Tons)50 100 150 200 250 300 350 400 500 600 700 800 900 1000

Pro

du

cti

on

Co

st

40.00

60.00

80.00

Page 21: Planning New Construction Major Ship Conversions Using

The primary focus of planning must be to

organize all work activities to support the

major assembly operations:

•Outfit Units

•Hull Blocks

•On-Board Ship Outfit Zones

Page 22: Planning New Construction Major Ship Conversions Using

Equipment & Outfit

System Modules

Pre-Outfitted Hull Block

Construction

Planning, Integrating &

Managing Shipyard Resources

Shipyard Products

• Engineering

• Purchasing

• PlanningConstruction

On-Board Outfit Zones

• Parts Manufacturing

• Shipyard facilities

• Sub-Contractors

Page 23: Planning New Construction Major Ship Conversions Using

Develop the Performance

Management Plan

• Product Work Breakdown Structure (PWBS)

• Process Work Centers & Work Stations (Cost Codes)

• Systems Work Breakdown Structure (SWBS)

Page 24: Planning New Construction Major Ship Conversions Using

Product Work Breakdown Structure

PWBS

Services

Ship

BowEngineRoom

MidbodySternSuper

Structure

StructurePackage

Outfit UnitPackage

ServicesPackage

EnginePackage

Flat Panels CurvePanels

3-D Struct Shell

Block Block

Unit Module

Zone OutfitPackage

Page 25: Planning New Construction Major Ship Conversions Using

Ship

Ship Zone & Product Cost

Product Work Breakdown Structure

PWBS

Ship Zone &

Hull Block

Hull Unit &

Outfit Module

Assembly

Sub Assembly

Manufactured Parts

Components

Product CostManagement

Process CostManagement

Page 26: Planning New Construction Major Ship Conversions Using

Shipyard Process Cost Codes

Department

Shipyard Division

Project Total

Department

WORK ORDERS

TIME CHARGES

Work Center

Page 27: Planning New Construction Major Ship Conversions Using

Systems Work Breakdown Structure

SWBS

System

System Group

Project Total

System

Accounts

Systems-Based

WORK ORDERS

TIME CHARGES

Page 28: Planning New Construction Major Ship Conversions Using

Project Project

SWBS PWBS

Accounts

Group

Blocks

Zone

Assemblies

Mfg Process

Product &Process-Oriented

Work Orders

TIME CHARGES

WORK ORDERSDISTRIBUTEDWORK ORDERS

Automated Cost Allocation

Relating Process Costs

to

Ship System Costs

Via Allocated Distributed Work Orders

Page 29: Planning New Construction Major Ship Conversions Using

Develop the Build Strategy

• Production Engineering Plan

• Manufacturing & Assembly of Structural Parts Plan

• Manufacturing & Assembly of Outfit Systems Plan

• Hull Block Construction Erection Sequence Plan

• Assembly & Erection of Equipment & Outfit

Modules Plan

• On-Board Zone Outfit Plan

• Tests & Trials Plan

Page 30: Planning New Construction Major Ship Conversions Using

Plan Manufacturing & Assembly Processes

ENGINEER

PLAN

PREP FAB ASS'MP/O

HOTERECT

P/O

COLD

BLAST

PAINT

Pre-Outfitted Hull Block Construction

ENGINEER

PLAN

FAB ASS'M INSTALL TEST

Equipment & Outfit System Modules

Page 31: Planning New Construction Major Ship Conversions Using

Develop Erection

Sequence of Hull

Blocks & Equipment

Modules

Integrate with

On-Board Zone

Outfit, Tests &

Trials

Page 32: Planning New Construction Major Ship Conversions Using

Criteria for Maximizing Efficiency

•Maximize work during most productive stages of

construction (On-Unit & On-Block)

•Minimize work during less productive stages of

construction (On-Board)construction (On-Board)

•Maximize work under cover

•Maximize access to work

•Minimize material handling

•Minimize non-productive activities

Page 33: Planning New Construction Major Ship Conversions Using

•Maximize productivity of available manufacturing

processes

•Ensure all necessary resources are readily available

at work times scheduled

•drawings,

•materials,

•tools & facilities, and

•manpower

•Exploit benefits of engineering, material and

production standards

Page 34: Planning New Construction Major Ship Conversions Using

Maximize Productivity of Available

Manufacturing Processes

Efficiency Lost From Process Interruption

100

120

Pro

cess C

ost

Per

Un

it

0

20

40

60

80

0 20 40 60

Units Produced

Pro

cess C

ost

Per

Un

it

Pro

du

ced

Interrupted Process

Un-Interrupted Process

Page 35: Planning New Construction Major Ship Conversions Using

Develop Material Management

Plan to Support Production

•Purchase Order Management

•Sub-Contract Management

•Warehouse & Inventory Management

•Production Work Order Kitting Management

Page 36: Planning New Construction Major Ship Conversions Using

Managing Material

From Engineering to Production

Life CycleMaterial

PERCEPTION

MATERIALREQUISITIONS

PURCHASING

RECEIVING

INSPECTING

WAREHOUSING

KITTING

ISSUES TOPRODUCTION

ControlPLANNED

REQUIREMENTS

OPTIONALCAD INTERFACE

ACTUAL USAGE

EXCESS STORESHISTORICAL RECORDS

VENDOR INVOICESCUSTOMER BILLINGS

Interface With AccountingSystems

Page 37: Planning New Construction Major Ship Conversions Using

Packaging Work for Stages of

Construction

ASSEMBLY

SUB-ASSEMBLYSUB-ASSEMBLY

PRODUCTSTAGE

ASSEMBLYLEVEL WORKORDER PALLET

WORK ORDERMATERIALKITS

COMPONENT

COMPONENT MFG

COMPONENT

COMPONENT MFG

COMPONENT

GROUP MFG

COMPONENT

RAW MATERIALS:

• Direct Purchase Material

• General Stock Material

• Owner Furnished Material

• Manufactured Parts

BILL OF MATERIALREQUISITION ITEM

PURCHASE ORDER ITEM

MFGLEVELWORKORDERPALLET

CAD

Page 38: Planning New Construction Major Ship Conversions Using

Develop Production Work Orders

Process Sequence: Pre-Outfitted Hull Block ConstructionLOFT

PLAN

PREP FAB ASS'MP/O

HOTERECT

P/O

COLD

BLAST

PAINT

Process Sequence: Outfit Fabricate & Install

Engineering

Specificat ions

Production

Drawings

Shop

Fabricat ion

Component

Installation

System

Tests

Process Sequence: Outfit Fabricate & Install

Rip-Out Repair Re-Install Test

Process Sequence: Repair & Install

Page 39: Planning New Construction Major Ship Conversions Using

A Work Order

A work order is a distinct and definable unit of work that can be definable unit of work that can be started and completed without significant interruption under the direction of a single work center.

Page 40: Planning New Construction Major Ship Conversions Using

Size of Work Orders

The size of work orders will vary, depending on scope.

Generally, large work orders are more difficult to manage than smaller work orders.

Large work orders that are open and in-process for a long period of time always collect more costs than necessary. Actual progress is impossible to measure.

However, work orders too small also are difficult to manage. They require more overhead to plan and manage. They increase opportunities for time charge errors.

Page 41: Planning New Construction Major Ship Conversions Using

A good rule of thumb for new

construction work orders:

Average 250 man-hours of laborAverage 250 man-hours of labor

Average 2 weeks duration

Page 42: Planning New Construction Major Ship Conversions Using

Time Charging

PERCEPTION provides functions for PERCEPTION provides functions for entering and validating authorized work order time charges

Page 43: Planning New Construction Major Ship Conversions Using

The recording of time charges against

authorized work orders is of major

importance to the shipyard.

Correct and complete time charging against

contracts is often the basis by which the

shipyard bills its customers. shipyard bills its customers.

Without accurate and timely information,

billings can be incomplete or late causing

considerable problems with the ability of the

shipyard to make a profit.

Page 44: Planning New Construction Major Ship Conversions Using

Completing Work Orders

Every work order should be authorized so

that it can be completed without undue

delay.delay.

PERCEPTION provides a formal closing

out procedure that indicates to the system

that the work order is finished.

Page 45: Planning New Construction Major Ship Conversions Using

From completed work orders,

PERCEPTION measures, tracks

and forecasts cost variances

automatically.

Page 46: Planning New Construction Major Ship Conversions Using

Work orders that are held up for

QA inspections may have a QA &

Pick Up work order created, with

appropriate budget, that allows

the bulk of the work to be closed

out.

Page 47: Planning New Construction Major Ship Conversions Using

Suggestion: Work orders that

require additional scope of work

due to short-comings of

preceding work orders should

be reimbursed with budget be reimbursed with budget

transferred from those earlier

work orders.

Page 48: Planning New Construction Major Ship Conversions Using

PERCEPTION offers 4 Primary Types of

Work Orders for Different Operations

Requirements

•Discrete Work Order•Discrete Work Order

•Distributed Work Order

•Time-Phased Work Order

•Process Work Order

Page 49: Planning New Construction Major Ship Conversions Using

1. The discrete work order identifies work that

can be catalogued easily within a given work

breakdown structure.

The discrete work order identifies work that

ultimately produces a definable interim or end

product.product.

Equipment & Outfit System Modules

Page 50: Planning New Construction Major Ship Conversions Using

2. The distributed work order identifies work across

multiple elements of the work breakdown structure.

The distributed work order is useful for collecting

costs by unit module, ship zone or group

manufacturing process and allocating the costs

automatically to individual ship systems.

• Potable Water System

• Sanitary Waste System

• HVAC

• Foundations

Page 51: Planning New Construction Major Ship Conversions Using

The time-phased

work order

3. The time-phased work order identifies a level of

effort activity that has no clear end product.

Examples include supervision and shipyard support

services.

Time-Phased CurvesMixed Library

120.0%work order

manages time

charge budgets on

a monthly basis

with no changes

in the work order

charge number.

-20.0%

0.0%

20.0%

40.0%

60.0%

80.0%

100.0%

0% 20% 40% 60% 80% 100% 120%

Fraction of Total Duration

Fra

cti

on

of

To

tal

Bu

dg

et

Exp

en

ded

Support Services

Packages

Page 52: Planning New Construction Major Ship Conversions Using

4. The process work order measures actual

production rates for specific manufacturing

processes. Performance is measured not only in

terms of labor hours and costs against budgets, but

also in terms of planned versus actual production

throughput units of measure (feet of weld, tons of

steel, etc.).steel, etc.).

The system generates forecasts of these throughput

rates as learning becomes evident and efficiency

improves.

Manufacturing Process

Work Packages

Page 53: Planning New Construction Major Ship Conversions Using

Managing the Project Execution

• Time Charging Procedures

• Material Issue Procedures

• Technical Package Issue Procedures• Technical Package Issue Procedures

• Budgets & Integrated Schedules

• Performance Reporting

Page 54: Planning New Construction Major Ship Conversions Using

Tracking Performance CostsTracking Performance Costs

Page 55: Planning New Construction Major Ship Conversions Using

Tracking ProgressTracking Progress

Page 56: Planning New Construction Major Ship Conversions Using

Tracking & Forecasting Tracking & Forecasting

Schedule VarianceSchedule Variance

Page 57: Planning New Construction Major Ship Conversions Using

Tracking & Forecasting Tracking & Forecasting

OverOver--Budget/Savings VarianceBudget/Savings Variance

Page 58: Planning New Construction Major Ship Conversions Using

Tracking Cost/1% ProgressTracking Cost/1% Progress

Page 59: Planning New Construction Major Ship Conversions Using

Tracking Performance Indexes

Page 60: Planning New Construction Major Ship Conversions Using

Tracking Material CostsTracking Material Costs

Page 61: Planning New Construction Major Ship Conversions Using

On-Line Cost & Schedule Status Reporting

Page 62: Planning New Construction Major Ship Conversions Using

Hard Copy Cost & Schedule Status Reporting

Page 63: Planning New Construction Major Ship Conversions Using

Tracking Manpower Requirements

•As Planned in Baseline

•As Currently Planned

•As Actually Expended To Date

•As Forecast to Complete

Manpower can be evaluated by WBS, by shipyard work

center, for one project or across multiple projects.

The analysis can combine current back-log with

proposed new work.

Page 64: Planning New Construction Major Ship Conversions Using

Tracking Manpower Requirements

(Planned Vs Actual Vs Forecast)

Page 65: Planning New Construction Major Ship Conversions Using

New Work Manpower Modeled On Top

Of Active Work Manpower