physical characterization of outfall pipeline discharges to the christina river … · 2020. 11....
TRANSCRIPT
PHYSICAL CHARACTERIZATION OF OUTFALL
PIPELINE DISCHARGES TO THE
CHRISTINA RIVER
AT
THE NEWPORT WORKS
NEWPORT, DELAWARE
FOR
CIBA-GEIGY CORPORATION
NEWPORT, DELAWARE
PREPARED BYH-4231 8. T. HUDSON ENGINEERS, INC.
800 COOPER STREETCAMDEN, NEW JERSEY 08102
S. T. HUDSON ENGINEERS INC.PROFESSIONAL ENGINEERS AND CONSULTANTS
May 19, 1991
CIBA-GEIGY CorporationJames & Water StreetsNewport, DE 19804
Attention: Mr. J. Kenneth TaftEnvironmental Specialist
Reference: Newport Works FacilityPhysical Characterization of Outfall Pipelineand Seep Discharges to the Christina RiverNewport, DE
Dear Mr. Taft:,
Complying with your request, S. T. Hudson Engineers, Inc. conducteda physical characterization of all exposed outfall pipelines andseeps along the Christina River at the Newport Works Facility.Also included is a detailed diver's inspection of the timber andconcrete seawall on the Christina River. The facility inspectionwas conducted from October 7, 1991 to October 21, 1991.
We have included in our report, photographs and the observedoutfall pipeline and seep plan C-1279, Rev. No. 2 of the NewportWorks Facility.
Should you have any questions regarding this report, we will bepleased to meet with you for discussion at your convenience.
V<
Manager, Environmental Services
RAL/em
Enclosures
H-4231
HUDSON SQUARE • 800 COOPER STREET • CAMDEN. NJ 08102 • 609-342-6600 • FAX
TABLE OF
PAGE NO.
INTRODUCTION 1
EXECUTIVE SUMMARY 3
SUMMARY OF FESTDINGS 10
A. SITE HISTORY 11
B. SURROUNDING SITE DESCRIPTION 15
C. MISCELLANEOUS OUTFALL PIPELINEINSPECTION 16
D. MISCELLANEOUS STRUCTURESINSPECTION 25
E. PERMUTED OUTFALL PIPELINEINSPECTION 27
F. SEEPS INSPECTION 33
G. DIVER'S INSPECTION OF THE TIMBERBULKHEAD AT BUILDING A-47 41
APPENDIX A - USGS QUADRANGLE LOCATIONMAP 44
APPENDIX B - SURVEY FIELD DATA 45
APPENDIX C - PHOTOGRAPHS
APPENDIX D - DRAWINGS
«i* <«.T!HHD!SOWEWGINEERS,INC.
INTRODUCTION
RR3i0350
INTRODUCTION
S. T. Hudson Engineers, Inc. was retained to conduct a physical
characterization of the outfall pipelines and seeps at the CIBA-
GEIGY Corp., Newport Works facility in Newport, Delaware.
The inspection of the outfall area along the Christina River was
performed from October 7 to October 21, 1991 and will be referred
to as the "Present" inspection.
This study was conducted to locate and describe each exposed
outfall pipeline and seep along the CIBA-GEIGY property on the
Christina River. A complete physical characterization of the
outfall pipelines and seeps including pipeline/seep location,
invert elevation, material of construction, description of effluent
and/or material discharged, if any, location of known manholes and
stormwater inlets has been summarized in this report.
Prior to performing the recent survey, S. T. Hudson Engineers, Inc.
conducted a survey of the subject area from May 2 through May 11,
1990. This survey and report concentrated on the physical
characterization of the exposed outfall pipelines found along the
Christina River. A hydrographic survey of the River was performed
as part of the scope of the survey. The report was issued August
20, 1990.
S.T. HUDSON ENGINEERS, INC.
The purpose of the present inspection was to identify all visible
outfall pipelines and seeps. All observed outfall pipelines and
seeps have been surveyed and a plan showing their location and
cross section have been plotted on S. T. Hudson Engineers, Inc.
Drawing C-1292,
A diver's inspection was performed at the timber crib wall along
the south side of Building A-47. Photographs of this area along
with the outfall pipelines and seeps are included in this report.
A H O I U 0 D C s.T. HUDSON ENGINEERS, INC.
EXECUTIVE SUMMARY
AR3I0353
EXECUTIVE SUMMARY
This report presents the findings of our visual site evaluation.
A thorough visual and physical characterization was made of the
river bank to locate and describe each exposed outfall pipeline and
seep.
A. Outfall Pipelines
A review of CIBA-GEIGY's Drawing entitled Newport Works Sewer
Map shows an extensive network of stormwater inlets, manholes
and outfalls. A total of twenty-six (26) outfall pipelines
(17 miscellaneous and 9 permitted) were found during our
visual inspection. Some of these lines have been abandoned,
rerouted and/or modified in the past according to CIBA-GEIGY.
Our investigation also included the tracing of selected
outfall pipelines back to its source by using a pipeline TV
camera, unless previously video taped or otherwise identified
by CIBA-GEIGY. The pipeline TV camera was operated by an
outside contractor selected by CIBA-GEIGY. The route of these
selected pipelines are plotted on S. T. Hudson Engineers, Inc.
Drawing C-1292, as observed by S. T. Hudson Engineers, Inc.
personnel during the tracing of the selected pipelines.
A R3 I U3 5^4 SJ. HUDSON ENGINEERS, INC
1. Miscellaneous Outfall Pipelines
Outfall OF-1 is shown on CIBA-GEIGY Drawing No. NPA-15302 as
a storm water outfall pipeline. OF-1 was not included in this
survey by the request of CIBA-GEIGY. According to CIBA-GEIGY
Outfall OF-1 has been plugged, abandoned and no flow was
observed from the pipeline.
Outfall OF-2 is the old 001 outfall pipeline which was
abandoned when the new 001 outfall was installed and connected
to the first manhole. The end of the pipe is sealed. This
information was supplied by CIBA-GEIGY.
Outfall (OF-3,/- TV inspection of the 8" diameter vitrified clay
pipe was limited to approximately 6' into the pipe due to
debris. No flow was observed.
Outfalls OF-4 & 5 - According to CIBA-GEIGY these Outfalls (6"
diameter metal pipes) were connected to reservoirs l and 2
respectively and have been plugged and abandoned.
Outfall OF-6 - This outfall was found plugged but a low flow
in the 12" diameter vitrified clay pipe was evident. Effluent
was white and clear with a strong kerosene like odor.
o
AR3 I 0355 S.T. HUDSON ENGINEERS, INC.
Outfall OF-7 - OF-7 outfall was not found after river bank
defoliation. A 3 ft. section of pipe was found lying into the
river bank. It was not connected to anything and was removed.
outfall F-y was cut-off at the low water elevation and
approximately 19 ft. section of the 12" diameter metal pipe
was removed from the river. This pipe went to Bldg. A-22
where the pipe was sealed with brick/concrete and filled with
debris. No flow was observed.
/ \Outfall (OF-9J - A 6" diameter metal pipe. No flow was observed
at this time. This pipe was previously flushed to 43' + .
Origin unknown.
Outfall OF-10 - The OF-10 outfall was sealed with concrete.
Outfall OF-11 - The outfall end of OF-11 (5'-0" diameter
reinforced concrete pipe) is located off of the CIBA-GEIGY
property but the storm water pipeline runs under the north-
eastern section of the plant and comes under the Amtrak
railroad tracks to the north. Effluent was clear with no
odor. CIBA-GEIGY has no contribution to this pipeline.
Outfall OF-12 - An 8" diameter zinc pipe is plugged. No flow
was present at this time.
, INC.
Outfall OF-13 - A 4" diameter metal pipe. It is not known at
this time where this pipe goes or the condition of the pipe.
No flow was present at this time.
Outfall \OF-14 - A 5"' diameter metal pipe with an obstruction
25'+ from the south end. No flow was observed.
Outfall QF-157- A 6" diameter cast iron pipe with an obstruc-
tion 45' + from the south end. No flow was observed.
Outfall OF-16 - A 24" diameter concrete pipe that is located
off of CIBA-GEIGY property. This pipe appears to collect
stormwater from James Street. Effluent found at the time of
the survey was clear with no odor.
Outfalir"OF-17 y- Located between OF-11 and OF-16. It is
assumed that this is an outfall due to the location of a
concrete end wall. This area has fill up to within 4"± of the
top of the wall, with heavy vegetation growth above the wall.
Partial digging at the face of the wall did not uncover a
pipe.
At this time our inspection cannot rule out the possibility of
the presence or absence of additional outfall pipelines that
may be below the mean low water line of the river or that may
be buried below the river bottom.
A R 3 I 0 3 5 7 S-T- HUDSON ENGINEERS, INC.
•
2. Permitted Outfall Pipelines
Nine (9) of the twenty-six (26) outfalls found have been
identified by CIBA-GEIGY as permitted outfall pipelines and
are shown on CIBA-GEIGY Drawing No. NPA-15302 entitled Newport
Works Sewer Map and S. T. Hudson Engineers, Inc. File #C-1292
dated 11/6/91, Drawings 1 through 5.
Out of the (9) permitted outfall pipelines, two (2) lines 004
and 007 are reported by CIBA-GEIGY to be plugged and aban-
doned.
Outfall 009 is a double chambered storm water outfall that
runs thru the eastern end of the plant and comes under the
Amtrak Railroad tracks from the north.
At the time of inspection, flow was observed at five
outfalls (001, 002, 006, 008 and 009) and no flow was observed /
at outfalls 003 and 005. Outfall 004 is cut-off at the low
water line. The effluent at Outfalls 001 and 006 was clear
with no odor. At Outfalls 008 and 009 clear flow was observed \,
but there appeared to be staining of the immediate area. /
Outfall 002 is not on Ciba-Geigy property.
S.T. HUDSON ENGINEERS, INC.
AR3I0358
B. Miscellaneous Structures
MS-1 appears to be an abandoned valve box structure with an
intake structure (MS-1A) approximately 25' outshore of MS-1.
MS-2 appears to be an abandoned river water intake structure,
however, this has not been confirmed.
MS-3 and MS-4 are both pump houses. MS-3 was abandoned when
MS-4 was installed. In addition, a 12" diameter river water
input line was installed in connection with MS-4. This line
supplies the three (3) reservoirs with river water. This
information was obtained from CIBA-GEIGY.
C. Seeps
Approximately twenty-six seeps were located at the time of
survey. The point of origin of these seeps is unknown. Some
seeps have color to the effluent, odor and/or have moderate to
heavy staining of the soil in the area of the seeps. Due to/
the makeup of the river bank, which appears to be old dis-
placed building structures and construction material, the1
location of the seeps could vary because of shifting of the,
river bank.
A R 3 I S.T. HUDSON ENGINEERS, INC.
J
•
D. Timber Bulkhead
The full length of the timber bulkhead (200') was inspected
and found to have horizontal timbers and vertical piles in
relatively good condition. Some loss of fill was found. The
construction joint between Building A-47 and the concrete
topping of the bulkhead is open 1-1/2" maximum for a length of
55 feet.
A R 3 I 0 3 6 Q S-T HUDSON ENGINEERS, INC.
SUMMARY OF FINDINGS
AR3I036I
SUMMARY OF FINDINGS
The intended purpose of this report section is to summarize the
findings of our site investigation. A request was made for a
physical characterization of the outfall pipelines, seeps and if
flow was observed coming from the outfall pipelines or seeps. A
total of 26 outfalls, 4 miscellaneous structures and 26 seeps were
located along the river bank.
10
H M 0 I U J 0 C s.T. HUDSON ENGINEERS, INC.
SITE HISTORY
flR3!0363
A. Site History
1. Location
The CIBA-GEIGY Newport Plant is part of the EPA designat-
ed E. I. DuPont de Nemours Co., Inc. - Newport Superfund
Site (the "Site"). The Site is located in Newport, New
Castle County, Delaware along the banks of the Christina
River, adjacent to Interstate 95 and Delaware Route 141.
The Site apparently consists of the E. I. DuPont de
Nemours Co., Inc. Holly Run Plant, the CIBA-GEIGY Newport
Plant, and two landfills along the north and south banks
of the Christina River. The North Landfill is a seven
acre parcel of land bounded to the north by the E. I.
DuPont de Nemours Co., Inc. Holly Run Plant and the CIBA-
GEIGY Newport Plant and to the south by the Christina
River. The south landfill is a 15 acre parcel of land
bounded to the north by the Christina River, to the south
and southwest by automobile salvage yards, and on the
east by Old Airport Road and Basin Road
11
. ~ * - S-T- HUDSON ENGINEERS, INC.AR3I036U
2. Past
The Site was originally owned by Henrik J.
Krebs from 1902 to 1929. Activities conducted
at the Site during this time included the
production of Lithopone, a white paint. In
1929, the Site was purchased by E. I. DuPont
de Nemours Co., Inc. which continued the
Lithopone production. Other activities initi-
ated during this time period included the
production of other lines of paint pigments
and chromium dioxide magnetic tape.
In 1984, CIBA-GEIGY bought the part of the
Site used to produce the paint pigments. The
remaining portion of the Site, the Holly Run
Plant and both landfills were retained by E.
I. DuPont de Nemours Co., Inc. The Holly Run
Plant continues to produce chromium dioxide
magnetic tape.
12
t
TA M U I U <3 0 t) S.T. HUDSON ENGINEERS, INC.
The two landfill areas were used primarily to
dispose of pigment muds; by-products of paint
production. Trash and such products as mag-
netic tape and thoriated nickel were also
disposed in the landfills. In 1973, the south
landfill was closed and capped with soil. In
1974, the north landfill was closed and capped
with clay. No landfilling has occurred at the
Site since 1974.
3. Present
The site consists of numerous buildings, which
include Manufacturing, Engineering, Milling,
Blending, Packaging and other such related
type buildings.
There are three fresh water reservoirs that
are used for fire fighting and other purposes.
Water is supplied to the reservoirs by a
recently installed 12" input line which takes
its water from the Christina River.
13
A K«J I U 366 S.T. HUDSON ENGINEERS, INC,
The southern edge of the property lies along
approximately 1200 feet of the Christina
River. The grade of the facility is approx-
imately 20 feet above the mean high water
elevation of the river. The river bank from
outfall 002 to outfall OF-13 drops off sharply
at an approximate 1 to 1 slope to the river.
The river bank was partially defoliated in the
Spring of 1991. Drainage is generally to
southeast towards the river. The intertidal
zone in this area lies approximately on a
gentle 4 to 1 slope and is composed primarily
of river mud, silt, rip-rap and occasional
aquatic vegetation.
From outfall OF-13 to outfall OF-11, the river
bank is composed of a concrete seawall and
timber bulkhead. Depths in the river vary
from relatively shallow along the bank to
approximately 12 feet below mean low water at
the center of the river channel.
14
A K O I U 0 D / S.T. HUDSON ENGINEERS, INC.
SURROUNDING SITE DESCRIPTION
AR310368
IB. Surrounding Site Description
In general, the surrounding area is a combination of
industrial manufacturing, light commercial and residen-
tial. Bordering the northern perimeter of CIBA-GEIGY are
several railroad tracks which are part of the Amtrak
system. The southern perimeter is bordered by the
Christina River. The western perimeter is bordered by E.
I. DuPont de Nemours Co., Inc. The eastern perimeter is
bordered by James Street.
15
flR3IQ369 S.T. HUDSON ENGINEERS, INC.
MISCELLANEOUS OUTFALLPIPELINE INSPECTION
AR3I0370
C. Miscellaneous Outfall Pipeline Inspection
This summary includes the information from the 1990 S. T.
Hudson Engineers, Inc. survey and the present survey ("1991").
1. Outfall OF-1
1990 - Outfall OF-1 is an 18" diameter reinforced
concrete pipe which was found approximately 200 feet east
of the southwest property corner. Ciba-Geigy has
reported that the outfall discharges stormwater to a
swale. No flow was observed.
Present Survey - Outfall OF-1 was not included as part of
this inspection. According to CIBA-GEIGY, Outfall OF-1
has been plugged, abandoned and no flow was observed from
the pipeline.
2. Outfall OF-2
1990 - Outfall OF-2 is located along the river bank in
the intertidal zone. The pipe invert was below grade.
CIBA-GEIGY has reported that the outfall is the old 001
outfall line which has been abandoned.
16
N D Q i H Q "7 I S'T- HUDSON ENGINEERS, INC.A it J 1 U O / I
Present Survey - The opening of Outfall OF-2 is sealed.
The pipe invert is still below grade. Refer to Photo-
graph No. 1.
\
3. Outfall/OF-3)
1990 - Outfall OF-3 is an 8" diameter vitrified clay pipe
outfall which was found atop the river bank approximately
10 feet south of the fence line. No flow was observed.
Present Survey - There has been no change in this
outfall. TV inspection has found cracks, tree roots, and
pipe caulk/sealer laying in pipe. Depth of penetration
of camera was 6'+ due to these obstructions. The pipe
was found to terminate in the river bank. No flow was
observed. Refer to Photograph No. 2.
4. Outfall OF-4
1990 - Outfall OF-4 is a 6" diameter metal pipe that is
located in the intertidal zone next to the old abandoned
pump house (MS-3). CIBA-GEIGY has identified this
outfall as reservoir drain No. 2 and is reported to be
plugged at the reservoir. No flow was observed.
17
fl R 3 I 0 3 7 2 S'T HUDSON ENG'NEERS, INC.
Present Survey - There has been no change in this
outfall. Refer to Photograph No. 3.
5. Outfall OF-5
1990 - Outfall OF-5 is a 6" diameter metal pipe that is
located in the intertidal zone on the downstream side of
the old abandoned pump house (MS-3).
CIBA-GEIGY has identified this outfall as reservoir drain
No. 1 and is reported to be plugged at the reservoir. No
flow was observed.
Present Survey - There has been no change in this
outfall. Refer to Photograph No. 4.
6. Outfall OF-6
1990 - Outfall OF-6 is a 12" diameter vitrified clay pipe
located at about the mean high water line. A foamy white
and clear colored effluent was observed originating from
the outfall and the bank immediately adjacent to the
pipe. A strong kerosene-like odor was present.
18
A R 3 I 0 3 7 3 S>t HUDSON ENGINEERS, INC.
Present Survey - A plug consisting of a square metal
plate, concrete and timber wedges was found 1 ft. inside
the opening. This was removed. Another plug of the same
type was found 6 ft.± inside the opening. This was left
intact. A low flow of a white colored effluent with a
kerosene like odor is still present. Also, the pipe and
the soil around the opening are stained a blue and rust
color. Refer to Photograph No. 5.
7. Outfall OF-7
1990 - Outfall OF-7 located at the high water line is an
8" diameter metal pipe. No flow was observed.
Present Survey - After defoliation of the river bank the
only remnant of this outfall found was a 2 ft. 3 in.
length of broken pipe. The remainder of this outfall
could not be found after extensive probing of the river
bank in this area. May have been a misplaced pipe
section. Refer to Photograph No. 6.
19
A H 0 I U O / 4 s.T. HUDSON ENGINEERS, INC.
8. Outfall OF-8 NA/f*1990 - outfall OF-8 emerges from the bank at approxi-
mately the low water line. The bank is covered with rip-
rap in this area. The end of the outfall was not visible
at low tide.
Present Survey - This outfall pipe was cut-off at the low
water line and the outshore section of the metal pipe, 19
ft.+ long was removed from the river. TV inspection has
found the pipe decreases in size from a 12" diameter at
the river to an 8" diameter to a 6" diameter at Building
A-22. The 8" diameter section of pipe has numerous
cracks in it. The 6" diameter pipe at Building A-22 is
plugged and filled with debris. The 12" diameter section
is badly corroded with the bottom of the pipe corroded
through or missing. No flow was observed during the time
of the inspection. Refer to Photograph No. 7.
9. outfall OF-9
1990 - Outfall OF-9 located on the seawall is a 6"
diameter metal pipe, with no flow observed.
Present Survey - There has been no change- in this
outfall. Refer to Photograph No. 8.
20
A R 3 I 0375 S.T. HUDSON ENGINEERS, INC
10. Outfall OF-10
1990 - Outfall OF-10 is an 18" diameter corrugated metal
pipe located adjacent to Outfall 009. The pipe is
blocked with fill. No flow was observed.
Present Survey - There has been no change in this
outfall. Refer to Photograph No, 9.
11. outfall OF-ii
1990 - Outfall OF-11 is a 5'-0" diameter reinforced
concrete pipe located off the property and adjacent to
the downstream side of the James Street Bridge. The
effluent was clear with no apparent odor.
Present Survey - There has been no change in this
outfall. This pipe runs through CIBA-GEIGY property from
,/ the manhole at the railroad tracks on the north side of•-S." \Building A-23. A 12" to 15" lateral pipe was found 21' +
from the south end of the pipe. This lateral was dry.
According to CIBA-GEIGY there are no CIBA-GEIGY catch
basins on this system. Refer to Photograph No. 10.
<»
21
AR3 I 0376 S.T. HUDSON ENGINEERS, INC.
,
D. Additional Miscellaneous Outfall Pipelines Observed During the
Present Survey
i rv Outfall OF-12
Outfall OF-12 is an 8" diameter zinc pipe located 6 feet
below the top of the river bank. This outfall reduces to
a 6" terracotta pipe approximately 4 feet from the
exposed end. No flow was observed. TV inspection has
found that the pipe decreases to a 4" diameter and is
plugged 22'± from the south end. Refer to Photograph
No. 11.
Outfall OF-13
Outfall OF-13 is a 4" diameter metal pipe located in the
tidal zone at the west end of the seawall. No flow was
observed. Interior of pipe was rust stained. Refer to
Photograph No. 12.
Outfall OF-14
Outfall OF-14 is a 5" metal pipe located at the high
water line west of outfall 006. No flow was observed.
The TV inspection found an obstruction in the pipe, 25
ft.± from the south end. 15 ft.+ from the south end,
22
"KJI0377 S.T.HUDSON ENGINEERS, INC.
roots were found in the pipe and at 18 ft.+ from the
south end the pipe diameter decreases and the camera
would not continue. Refer to Photograph No. 13.
Outfall OF-15
Outfall OF-15 is a 6" diameter cast iron outfall located
15 feet from the top of bank, west of the OF-3 outfall.
No flow was observed. This pipe was flushed with a high
pressure water hose 45 ft.± from the south end and hit an
obstruction. Roots were discovered in the pipe along
with debris. Refer to Photograph No. 14.
Outfall OF-16
Outfall OF-16 is a 24" diameter concrete outfall located
off the Ciba-Geigy property and 12 feet east of Outfall
OF-11. The effluent was clear with no apparent odor.
T.V. inspection found small debris 18 ft. to 23.7 ft.
south of manhole OF-16A. The T.V. camera was stopped
57.6' south of manhole OF-16A due to heavy debris.
Green dye was poured into the catch basin on James Street
under the railroad bridge and appeared at the river end
of the outfall. Refer to Photograph No. 15.
23
A R 3 I 0378 S'T- HUDSON ENGINEERS, INC.
Outfall OF-17
Outfall OF-17 is an outfall located directly adjacent to
OF-11 (off CIBA-GEIGY property) and is 100% covered by
fill. Only the top of an end wall structure is visible.
This structure is not on CIBA-GEIGY property. Excavation
of l'-6" to 2'-0" of sand fill did not expose any pipe.
Excavation was limited due to heavy vegetation and roots.
Refer to Photograph No. 16.
24
AH3I 0379 S.T. HUDSON ENGINEERS, INC.
MISCELLANEOUS STRUCTURES INSPECTION
flR3!0380
D. Miscellaneous Structures
1. Intake Box MS-1
1990 - This structure appears to be an abandoned river
water intake box. A l'-9" diameter flange was observed
inside of the box. This box lies outshore of the
abandoned pump house MS-3.
Present Survey - Valve Box MS-1 was measured to be 5'
long x 4' wide x 4' high. Upon further investigation by
our diver, an intake box, MS-1A (5'x4') was located
approximately 19 ft. outshore of MS-1. The valve box and
the intake box are connected by a 16" diameter pipe. MS-
1A is completely submerged at low tide. MS-1A and the
16" diameter pipeline were marked with buoys by the diver
for ease of locating them at a future date. Also, at the
time of this survey, a storage tank (3' diameter x 4'
long) was sitting inside of MS-1. Refer to Photograph
No. 2.
2. Intake Box MS-2
1990 - This structure also appears to be an abandoned
river water intake box. An elbow pipe connection was
observed just inshore of the box. This box lies outshore
of the abandoned pump house MS-3.
25
• p O j f| O Q I S.T. HUDSON ENGINEERS, INC.
Present Survey - There has been no change in this
structure. Refer to Photograph No. 3.
3. Abandoned Pump House MS-3
1990 - This structure is reported by CIBA-GEIGY to be the
old pump house which pumped river water to the reser-
voirs.
Present Survey - There has been no change in this
structure.
4. New Pump House MS-4
1990 - This structure is reported by CIBA-GEIGY to be the
new pump house that currently supplies the three reser-
voirs with river water. The 12" diameter river water
intake line was not observed at mean low water.
Present Survey - There has been no change in this
structure.
26
o
A R O I Q O Q g S.T. HUDSON ENGINEERS, INC.
PERMITTED OUTFALLPIPELINE INSPECTION
AR3I0383
E. Permitted Outfall Pipeline Inspection
All outfalls described below are reported by CIBA-GEIGY
to be permitted.
l. Outfall 001
1990 - Outfall 001 is located adjacent to a timber
stairway on the river bank. The outfall is a 24"
diameter reinforced concrete pipe. Flow was observed
during our inspection.
Present Survey - There has been no change in this
outfall. The flow observed during this inspection was
clear with no odor. Refer to Photograph No. 2.
Outfall 002
1990 - Outfall 002 is located just inside of the south-
western property line along the Christina River. The
outfall is a 24" diameter reinforced concrete pipe. Flow
was observed during our inspection.
Present Survey - There has been no change in this
outfall. It has been determined by our survey that this
27
H it J I U 0 0 4 s.T. HUDSON ENGINEERS, INC.
outfall is not located on CIBA-GEIGY property. This pipe
was inspected by TV camera from the manhole on Dupont
Property 162 ft..± south to the river bank and north 118
ft.+ to a sealed end at the CIBA-GEIGY property line.
The 162 ft. south section had rock debris, root infiltra-
tion and cracking. CIBA-GEIGY does not contribute to
this system. Refer to Photograph No. 1.
3 .\ Outfall 003
1990 - Outfall 003 is located above the mean high water
line. This outfall is a 12" diameter metal pipe with no
flow observed during our inspection.
Present Survey - The soil at the base of the pipe was
observed to have a rust colored stain. This pipe
decreases in size from a 12" diameter at the shoreline to
a 6" diameter in the plant. A second 12" diameter pipe
^ at the catch basin was filled with debris. The camera
stopped 32 ft.+ into the 6" diameter section due to
•—debris. Possible green dye or pigment was observed
during the T.V. inspection. Refer to Photograph No. 3.
28
<»
fflR3!0385 S.T. HUDSON ENGINEERS, INC.
.
Outfall 004n>t1990 - This line is reported by CIBA-GEIGY to be plugged
and abandoned. The end of the pipe was not visible at
mean low water.
Present Survey - This pipeline (8" diameter reinforced
rubber) was cutoff at the low water line and 30 ft. was
removed from the river. The diver reported that the
pipeline remaining in the river goes into the mud line
and it is assumed that it goes to the south side of the
Christina River. No flow was observed during our
inspection, however, the soil in the area of the outfall
is stained a blue color. Pentration of 38 ft.± with TV
camera found the pipe to have debris on the bottom with
a clear and glossy film on the inside. Laterals were
found at 12 ft.± and 22 ft.+ from south end of pipe.
Refer to Photograph No. 4.
5. Outfall 005
1990 - Outfall 005 is a 6" diameter metal pipe which lies
approximately 1" below mean low water. No flow was
observed during our inspection.
29
fl R 3 I 0 3 8 fi at H'UDSON ENG|NEERS' |NC-
Present Survey - This pipeline was cutoff in the tidal
zone and 26 ft. 6 inches of fiberglass pipe was removed
from the river. No flow at the new opening was observed
during our inspection. However, the soil in the area of
the new opening was stained a blue color with a kerosene
like odor. From the manhole (005) at the top of the bank
going south toward the river, root infiltration was found
at 31 ft.+. From the manhole north, the pipe was clean
for 50 ft. + , the maximum distance for the camera. From
the catch basin inshore of manhole (005) going south the
camera was stopped by debris 6 ft.+ from point of entry.
Refer to Photographs No. 5 & 6.
6. Outfall 006 &A>1990 - Outfall 006 located at approximately the mean low
water line is an 18" diameter reinforced concrete pipe.
A rust colored effluent was observed.
Present Survey - The flow observed during this inspection
was clear with no odor. Refer to Photographs No. 7.
7. Outfall 007
1990 - Outfall 007 located on the seawall is reported by
CIBA-GEIGY to be plugged and abandoned.
30
AR310387 S.T. HUDSON ENGINEERS, INC.
Present Survey - There has been no change in this
outfall. The location of the pipe's discharge is
completely filled with concrete. Refer to Photograph No.
8.
8. Outfall 008
1990 - Outfall 008 located on the seawall is a 12"
diameter vitrified clay pipe. Flow was observed during
the time of inspection.
Present Survey - The flow observed during this inspection
was clear with no odor, however, the concrete at the base
of the pipe opening is stained a rust color. Refer to
Photograph No. 9.
9. Outfall 009
1990 - Outfall 009 discharges into a concrete enclosed
trough. The outfall pipe was not found, however, flow
was observed into the trough at the time of inspection.
Present Survey - Outfall 009 is a concrete storm water
drainage trench made up of two (2) rectangular shaped
chambers with an overall dimension of 3'-4" high x 3'-0"
wide. Outfall 009 enters plant property from the Amtrack
31
A R 3 I 0 3 8 8 SJ' HUDSON ENGINEERS,INC-
Railroad tracks and terminates at the Christina River.
The flow observed during this inspection was clear with
no odor, however, the concrete at the base of the
opening was stained a rust color. The TV camera was
inserted into the west side catch basin, at the northeast
corner of Building A-23. Going in a northerly direction
the camera found two (2) lateral pipes, and the bottom
corner on the west side of the trench spalled. Camera
penetration in the northerly direction was stopped 54
ft.+ from point of insertion due to a depression or a
hole. Going south, a pipe with a low clear flow was
found at the top of the trench. Also, four (4) laterals
were found two (2) appeared dry and two (2) discharging
effluent into the trench. One (1) of these containing a
red fluid. Camera penetration stopped 189 ft.+ from
point of entry due to debris. Refer to Photograph No.
10.
32 °A R 3 I 0 3 8 9 S'T' HUDSON ENGINEERS, INC.
SEEPS INSPECTION
AR3I0390
F. Seeps (SP)
An inspection of the visible seeps along the bank of the
Christina River was conducted from October 7, 1991 to October
21, 1991. Twenty six (26) seeps were located and surveyed.
The amount of flow, color and odor observed varied from seep
to seep.
One consistent observation noted was that active probing
(insertion of a small steel rod) of the seeps resulted in
either an increase of water and/or colored effluent discharge
or the cessation of all discharge from that seep. In addi-
tion, several probes into areas of the bank without seeps
resulted in the discharge of water and/or colored effluent.
It would appear that the bank, water and colored effluent all
exist in a dynamic state.
1. Seep - OA
SP-OA - located west of the OF-13 outfall. A clear
flow with no odor was observed. The soil in this area
was stained a rust, red and blue color. Refer to
Photograph No. 1.
33
^ S.T. HUDSON ENGINEERS, INC.BR3I039I
2. Seep - OB
SP-OB - located west of Seep - OA. A low clear flow with
no odor was observed. The soil in this area was stained
a rust, red and blue color. Refer to Photograph No. 2.
3. Seep - 1
SP-1 - located west of Seep - OB. A low, clear flow with
no odor was observed. The soil in this area was stained
a rust and red color. Refer to Photograph No. 3.
4. Seep - 2
SP-2 - located west of Seep - 1. A low clear flow with
no odor was observed. The soil in the area was stained
a rust color. Refer to Photograph No. 4.
5. Seep - 3
SP-3 - located west of Seep - 2. A high clear flow with
no odor was observed. The soil in a 5'x5' area was
stained a rust color. Refer to Photograph No. 5.
34
A R 3 I 0 3 9 E1- HUDSON ENGINEERS, INC.
6. Seep - 4
SP-4 - located east of the 006 outfall and west of Seep -
3. A high flow with a white oily sheen and a kerosene
like odor was observed in a 5'x5' area. Refer to
Photograph No. 6.
7. Seep - 5
SP-5 - located east of the 006 outfall. A clear flow
with no odor was observed. Refer to Photograph No. 7.
Seep - 6
SP-6 - located east of the 006 outfall. A clear
flow with a kerosene like odor was observed. Soil in the
area is stained a red and blue color. Refer to Photo-
graph No. 8.
Seep ~ 7
SP-7 - located east of the 006 outfall. A clear
flow with a white oily sheen and a kerosene like odor was
observed. Soil in the area is stained a red and blue
color. Refer to Photograph No. 9.
35
S.T. HUDSON ENGINEERS, INC.
flR3!0393
10. Seep - 8
SP-8 - located west of the OF-8 outfall. A low flow was
observed with an oily like sheen on the soil in the
immediate area. Refer to Photograph No. 10.
11. Seep - 9
SP-9 - located west of the OF-8 outfall. A low flow was
observed with an oily like sheen on the soil in the
immediate area. Refer to Photograph No. 11.
12. Seep - 10
SP-10 - located west of the OF-8 outfall. A red colored
effluent flowing from the seep, with an oily like sheen
on the soil in the immediate area. Refer to Photograph
No. 12.
Seep - 11
SP-11 - located west of the OF-8 outfall. A clear
flow mixed with an oil like material and red pigment.
Also rust staining of the soil in the area. Refer to
Photographs No. 13 & 14.
36
5 R *^ I 0 Q L. S'T' HUDSON ENGINEERS, INC.
14. Seep - 12
SP-12 - located east of the 005 outfall and west of the
OF - 8 outfall. A red colored effluent was found flowing
from the seep. Refer to Photograph No. 15.
15. Seep - 13
SP-13 - located east of the 005 outfall. Low flow, soil
stained with an oily like white sheen in a 10' square
area. Refer to Photograph No. 16.
16. Seep - 14
SP-14 - located east of the 005 outfall. Low flow, soil
stained with a red and oily like sheen in a 10' square
area. Refer to Photograph No. 17.
17. Seep - 15
SP-15 - located east of the 005 outfall. Low clear flow
was observed with the soil in the area stained a rust
color. Refer to Photograph No. 18.
37
H R 3 I 0 3 9 5 S-T- HUDSON ENGINEERS, INC.
18. Seeps - 16 & 17
SP-16, SP-17 are located approximately 2 ft. apart and
east of outfall 005. Both seeps have a low flow. The
soil in the area of the seeps is stained a rust color
with an oily sheen. Refer to Photographs No. 19 & 20.
19' Seep -18
SP-18 located east of outfall 005. When probed a high
flow of clear effluent mixed with a red colored fluid was
released. Further probing stopped this release. The
soil in this area is stained a rust color. Refer to
Photograph No. 18.
20. Seep - 19
SP-19 - located east of outfall 005. A low flow was
observed with an oily like sheen on top and the surround-
ing soil stained a rust color. Refer to Photograph No.
22.
38
fl R 3 I 0 3 9 fi S-T HUDSON ENGINEERS, INC.
21. Seep - 20
SP-20 - located east of outfall 005. A low flow was
observed with an oily like sheen on top and the surround-
ing soil stained a rust color. Refer to Photograph No.
23.
22. Seep - 21
SP-21 - located west of outfall 005. A low flow was
observed with an oily like sheen. The soil was stained
a red and blue color. Refer to Photograph No. 24.
Note: The soil from the tidal area to the top of the
bank was observed to have a blue color under the rocks
and surface debris.
23. Seeps 22. 23. 24
SP-22, SP-23, SP-24 are located west of outfall 004 and
east of outfall 003. A low flow was observed. The soil
was heavily stained a rust color with an oily like sheen
on top. Refer to Photographs No. 25 & 26.
• 39
A R 3 I 0 3 9 7<T 1UDSON ENGINEERS, INC.
24. Seep - 25
SP-25 is located west of outfall 004. A low flow was
observed. The soil was stained a rust color with an oily
sheen on top. Refer to Photograph No. 27.
25. Seep - 26
SP-26 is located west of outfall 004. A low flow was
observed. The soil was stained a rust color with an oily
sheen on top. Refer to Photograph No. 28.
26. Old Concrete Building Wall
This wall is located west of outfall 004 and is at the
low water line. There are five (5) seeps along the face
of wall with a low flow from the east seep only. At all
seep locations, the concrete wall is stained a rust
color. Refer to Photographs No. 29 & 30.
40
•
°A R 3 I 03 9^8 HUDSON ENGINEERS, INC.
DIVER'S SURVEY OF THE TIMBERBULKHEAD AT BUILDING A-47
flR3IQ399
.
DIVER'S SURVEY OF THE TIMBER BULKHEAD AT BUILDING A-47
The structure consists of horizontal timbers, approximately 33
timber piles and concrete topping which holds back rock and stone
fill along the outshore (river face) of Building No. A-47. There
are no signs of steel or timber tie backs or spur piles.
For the purpose of this survey the west corner of the timber
retaining wall is referenced as Station 0+00 and continues east for
approximately two hundred and four feet (Station 2+04).
We found that the horizontal timbers which span between the
vertical timber piles are of various sizes and are in relatively
good condition.
The bottom course of the horizontal timbers are fully exposed from
approximately Station 0+80 to 1+90. The diver/engineer noted that
the rock fill consisted of bricks and angular stones with little to
no fines. It was possible to probe behind the timbers up to 2
foot. The stone and brick fill is falling out from beneath the
bottom course from 0+80 to 1+20. The remaining areas of the timber
retaining wall have stone and brick piled against the timber
bulkhead covering most of the bottom course with no loose fill.
41
K R 3 I 0 fy 0 0 ST'HUDSON ENGINEERS, INC.
The thirty three (33) timber piles which appear to be retaining the
stone fill and horizontal timbers are rotted and split at the top
1 to 2 feet, the remainder of the piles are typically in fair
condition.
The concrete topping is cracked vertically and horizontally along
the sloping face and is generally in fair to poor condition along
the sloping face. The top surface of the concrete topping is in
good condition with minor hairline cracks.
The construction joint between the brick Building No. A-47 and the
concrete topping (Station 1+36 to 1+93) is separated 1 to 1-1/2
inches and probed from 5 to 12 inches in depth. There are two
outfalls, Outfall 008 at Station 0+71 and OF-9 at Station 1+27,
located along the timber retaining wall. Outfall 007 Station 0+30
has been sealed with concrete.
See attached sketch and photographs for conditions of the timber
bulkhead.
42
fl R 3 j 0 fy 0 ! S-T- HUDSON ENGINEERS, INC.
IRecommendations;
We do not recommend any repairs at this time, but annual inspec-
tions should be conducted to insure that conditions do not
deteriorate. Also, we recommend that a program be set up to
monitor any changes to the construction joint between Building A-47
and the concrete topping.
43
A it <J I U mj d s.T. HUDSON ENGINEERS, INC.
APPENDIX AUSGS QUADRANGLE LOCATION MAP
AH3!Ol»Ol»
9*4-&x&S%FUKreU -"-Hr S5 ^ BAN N.NG V ; F
?5tlt ,_ - iJ' ^ / ^ — • Campgiounds/'**55***" ^[c-•?—"—'. i.'5 U • u "iif "" f O«*" " i ' *' -^',;,•.-•:- .,.^?t:K>*v >. >"•"' •" -""'-ii—7 Tv-S--> Gf 'y0 ' ' ;."IjjJJ s jiA y S - "l ^.-?! -'" 5
J fgggjpatr390 -39''
S - ^ ^ ^ §
V .s- .__».,, <• —
• »\On1;. \• > V.- • I >• \ I* \ vs' .V- .1 I
\>-A I- iTisfe'" . v"
A.^LOCATION MAP ^ ///' / \•• -<x • , 4 // v ..••••/: A •.- \
APPENDIX B
SURVEY FIELD DATA
SURVEY FIELD DATA
A. MISCELLANEOUS OUTFALL PIPELINES
Present survey data unless otherwise noted.Note: Elevations are referenced to CIBA-GEIGY Plant Datum 0.0
(2.9' above mean low water)
O U T F A L L P I P E P I P ENO._____DIA. TYPE INVERT FLOW_______COMMENT________________
OF-1 18" RCP +5.4 No Not included as part of(1990) this inspection. (Outfall
sealed - CIBA-GEIGY).
OF-2 — —— Below — End of outfall is sealed.Grade
OF-3 8" VCP +19.1 No Outfall along top ofriver bank.
OF-4 6" MP +0.59 No Reservoir Drain #2.Reported plugged andabandoned.
OF-5 6" MP +1.4 No Reservoir Drain #1.Reported plugged andabandoned.
OF-6 12" VCP +3.4 Yes White and clear effluentobserved. Strongkerosene-like odor present.
OF-7 Section of pipe on river bank not connected.
OF-8 12" MP -2.4 — Pipe was cut off in tidalzone.
OF-9 6" MP +1.6 No Outfall in seawall. .
OF-10 18" CMP +0.3 No Pipe was blocked withconcrete fill.
OF-11 5'-0" RCP +1.6 Yes The outfall was locatedoff of the Ciba-Geigyproperty adjacent the bridge.Effluent was clear incolor.
OF-12 8" Zinc +5.7 No Outfall along top ofriver bank.
OF-13 4" MP +1.8 No In tidal zone at westend of seawall.
45
aR3lOU07
SURVEY FIELD DATA
A. MISCELLANEOUS OUTFALL PIPELINES (Cont.)
OUTFALL PIPE PIPENO. DIA. TYPE INVERT FLOW_________COMMENT________________
OF-14 5" MP +2.7 No At high water line.
OF-15 6" CI +12.4 No Outfall along top ofriver bank.
OF-16 24" RCP +0.4 Yes Outfall located off theCiba-Geigy property. Effluentwas clear in color.
OF-17 —— —— ——— —— Assumed outfall location.(No pipe found)
46
flR3IOlf08
B. MISCELLANEOUS STRUCTURES
AREALOCATION
MS-1 Abandoned valve box (formally referred to as an intakebox) with l'-9" diameter blind flanged line exposed.
MS-1A Abandoned intake box approximately 19' outshore of MS-l.Connected to MS-1 by a 16" diameter pipe.
MS-2 Abandoned intake box. Elbow exposed at low tide.
MS-3 Abandoned Pump House.
MS-4 New Pump House.
47
SURVEY FIELD DATA
C. PERMITTED OUTFALL LINES
1990 survey data unless otherwise noted.Note: Elevations are referenced to CIBA-GEIGY Plant Datum 0.0
(2.9' above mean low water).
O U T F A L L P I P E P I P E "NO._____DIA. TYPE INVERT FLOW________COMMENT______________
001 24" RCP +0.4 Yes Clear effluent with noodor.
002 24" RCP +5.4 Yes This outfall is not onCiba-Geigy property.
003 12" MP +3.6 No Soil at base of pipe rustcolored.
004 8" Reinf. -2.1 No Reported plugged andRubber abandoned. End of outfall
visible below MLW bluestained soil. Pipe cut atbank and removed from river.Inv. elev. of removed section-2.06'.
005 6" Fiber- +2.1 No Approximately 27' of pipe(1991) glass cut and removed from river.
006 18" RCP - 1.9 Yes Clear and odorlesseffluent.
007 — —— ——— No Outfall on seawall filledand sealed with concrete.
008 12" VCP +2.6 Yes Located in the seawall.Clear effluent, pipestained a rust color.
009 — —— + 0.25 Yes Two (2) 3'x3' concretetroughs observed. Redstaining of concrete atopening.
48 A R 3 I O M O
D. Seeps (SP)
Present survey data.Note: Elevations are referenced to CIBA-GEIGY Plant Datum
o.o (2.9' above mean low water).
SPNO.______FLOW____ELEVATION________________COMMENT__________
SP-OA Yes + 0.3 Clear flow. Soil in areastained a rust, red & bluecolor.
SP-OB Yes - 0.5 Clear flow. Soil in areastained a rust, red & bluecolor.
SP-l Yes +0.5 Clear flow. Soil stainedrust and red.
SP-2 Yes + 1.1 Clear flow, soil rustcolored.
SP-3 Yes - 0.2 Large clear flow, ruststained soil.
SP-4 Yes +2.0 Large flow with while oilysheen and kerosene odor.
SP-5 Yes +2.5 Clear flow, no odor.
SP-6 Yes + 1.5 Clear flow, kerosene odor.Soil stained red and blue.
SP-7 Yes +1.5 Clear flow with white oilysheen, kerosene odor. Soilstained red and blue.
SP-8 Yes + 0.2 Oil like sheen on soil.
SP-9 Yes + 0.2 Oil like sheen on soil.
SP-10 Yes +0.2 Red colored effluent. Oillike sheen on soil.
SP-ll Yes +1.1 Large flow colored red. Oillike sheen on soil.
SP-12 Yes +0.6 Red colored effluent.
SP-13 Yes +2.7 Oil like sheen on soil.
SP-14 Yes +2.5 Oil like sheen on soil.
49
D. Seeps (SP) (Cont.)
SPNO.
SP-15
SP-16
SP-17
SP-18
SP-19
SP-20
SP-21
SP-22
SP-23
SP-24
SP-25
SP-26
FLOW ELEVATION
Yes +1.0
Yes +0.6
Yes +0.6
Yes +0.6
Yes +3.5
Yes +2.4
Yes +3.2
Yes +2.5
Yes +5.3
Yes +5.3
Yes +2.7
Yes +2 . 4
L
•COMMENT
Rust stained soil.
Rust stained soil.
Rust stained soil.
Large flow of clear effluentwith a red color fluid mixedin.
Soil stained a rust colorwith an oil like sheen.
Soil stained a rust colorwith an oil like sheen.
Effluent has oil like sheen,blue stained soil.
Soil heavily stained a rustcolor. ^ ^
Soil heavily stained a rust ^^^color.
Soil heavily stained a rustcolor.
Rust stained soil with oillike sheen.
Rust stained soil with oillike sheen.
UR3IOM2
APPENDIX CPHOTOGRAPHS
AR3IOIU3
PHOTOGRAPHS OF MISCELLANEOUSOUTFALLS OF-2 THRU OF-17
AR3IOMI*
1. Looking northwest at Outfall OF-2 (old 001).Note: End of pipe is sealed.
2. Looking north at Outfall OF-3.
A R 3 I O M 5 S.T. HUDSON ENGINEERS. iNC
3. Looking northwest at Outfall OF-4 located onupstream side of the old pumphouse.
4. Looking upstream at Outfall OF-5 located onthe downstream side of the old pumphouse.
S.T. HUDSON ENGINEERS, INC,
5. Looking north at Outfall OF-6.Note: The rust color stain of the river bankin front of the pipe.
AR3IOIH6ST HUDSON ENGINEERS, INC.
6. Outfall OF-7 - The only piece found after defoliation ofthe river bank and extensive probings.
7. Outfall OF-8 - Cut-off at low water line.
________________________________________________________A R 3 I 0 "4 I 7 S.T. HUDSON ENGINEERS, INC.
3. Outfall OF-9 located in the concrete and timber retainingwall.
9. Looking east at Outfall OF-10.Note: CMP sealed with concrete.
S.T. HUDSON ENGINEERS. INC.
f l R 3 I O U I 8
10. Looking northeast at Outfall OF-11 located onthe downstream side of the James St. Bridge.
11. Looking northwest at OF-12.
S.T. HUDSON ENGINEERS, INC.
,^
12. Looking north at OF-13 located at the upstreamend of the timber retaining wall.
flR3i S.T. HUDSON ENGINEERS. INC.
13. Looking northeast at Outfall OF-14,
14. Looking north at Outfall OF-15 located nearthe top of bank.
H H O 1 U 4 C I S.T. HUDSON ENGINEERS, INC.
15. Looking north at Outfall OF-16.Note the low flow coming from pipe.
s s &.&s *-
16. OF-17 assumed location of outfall. Note concrete endwall, with heavy vegetation above and Outfall OF-16immediately upstream (indicated by arrow).
; HUDSON ENGINEERS, INC.
1
PHOTOGRAPHS OF MISCELLANEOUS STRUCTURES
1. Overall photo of MS-1 and MS-2 looking upstream.
M O I U 4 2 fy S,T. HUDSON ENGINEERS. INC.
2. MS-1 - Looking downstream.Note: The cylindrical tank inside the valvebox is not part of the structure.
H ft 0 I U 4 L. 0 S-T HUDSON ENGINEERS, INC.
.f : •;>
3. MS-2 - Looking downstream.
S.T. HUDSON ENGINEERS. INC.
PHOTOGRAPHS OF PERMITTED OUTFALLS
AR3IOi*27
1. Looking north at Outfall 002 which is not on Ciba-Geigyproperty.
2. Looking northeast at Outfall 001.Note the clear effluent from the pipeline.
AR3 101*28 3.T. HUDSON ENGINEERS. INC.
3. Looking north at Outfall 003.Note: The rust stained soil below the pipe.
A R 3 1 0 2 9 S'T- HUDSON ENGINEERS, INC.
4. Outfall 004 - looking downstream at the 30'+length of reinforced rubber pipe removed fromthe river. Note: Concrete anchor.
flflO I UHJU S.T. HUDSON ENGINEERS. INC.
5. Outfall 005 - Looking at the 26'-6" of fiberglasspipe removed from the river.
6. Looking northwest at Outfall 005.
5 R 3 1 0 fy 3 I S-T HUDSON ENGINEERS, INC.
7. Looking upstream at Outfall 006. Located in the tidalarea.
8. Looking downstream at Outfall 007. This outfall islocated on the south side of Building A-47. Pipe hasbeen sealed with concrete,
S.T. HUDSON ENGINEERS. INC,
5R3IOU32
9. Outfall 008 located in the timber/concrete retaining wallon the south side of Bldg. A-47. Note: The rust coloredflow from the pipe.
10. Outfall 009 located on the west side of the James StreetBridge. Note: The red stain on the concrete.
10^ ,HUDSON ENGINEERS, INC.
PHOTOGRAPHS OF SEEPS (SP)
. • j *- - ••
i, SP-OA - Note: Clear continuous effluent and thestal.ned soil ,
S.T. HUDSON ENGINEERS. INC.
2. SP-OB - Note: Clear effluent and the stained soilin the area,
3 IQkJb S.T. HUDSON ENGINEERS. INC,
3. SP-1 - Note; The low clear flew.
DSON ENGINEERS. INC.
SP-2 - Looking north,
P. HUDSON ENGINEERS. INC,
5. SP-3 - Looking north. Clear effluent visible.
S.T, HUDSON ENGINEERS, INC.
6. SP-4 - Looking north. A high steady flow with a whiteoily sheen and a kerosene like odor was found.
A n J j 0 fy 4 0 S-T HUDSON ENGINEERS. INC.
7. SP-5 - A clear flow without an odor was found,
]S,T. HUDSON ENGINEERS, INC.
SP-6 - Looking west. Clear flow with a kerosene likeodor. The soil was stained red and blue.
9. SP-7 - Looking north.
H it U i U 4s(f ffiJDSON ENGINEERS, INC.
10. SP-8 - Note: The oily sheen of the effluent.
11. SP-9 - Looking west.
S.T. HUDSON ENGINEERS. INC.
12. SP-10 ~ Mote the reel colored effluent with an oily likesheen.
13. SP-11 - Note the clear colored effluent mixed with an oillike material.
14. SP-11 - A clear effluent with traces of red pigment andoil with a rust staining of the soil was observed.
AR3IOH5 S.T. HUDSON ENGINEERS. ' C
15. SP-12 - Note the red colored effluent.
16. SP-13 - Note the oily like sheen on effluent.
S.T. HUOSCM ENGINEERS. NC
17. SP-14 - Note the oily Like sheen on the effluent.
r, HUDSON ENGINEERS. INC.
-; .
18, SP-15 - Low clear flow with rust stained soil.
19, SP-16 - Low flow, rust colored soil with an oily sheen.
S.T. HUDSON ENGINEERS, iNC
20. SP-17 - Low flow seep with rust colored soil withand oily like sheen,
21. SP-18 - Low flow seep rust colored soil with an oilysheen.
S.7. HUDSON ENGINEERS 'NC
22, SP-19 - Rust stained soil with an oily like sheen.
S.T. HUDSON ENGINEERS :NC
23. SP-20 - Rust stained soil with an oily like sheen,
UT3T0THF S.T, HUDSON ENGINEERS, INC.
24. SP-21 - Soil stained a rust and blue color with an oilylike sheen.
S T. HODSOfJ ENGiNEEPS INC
25. SP-22, 23, 24 - Soil with a heavy rust stain and an oilylike sheen.
>.T HUDSON ENGINEERS, INC.
W i-j&nSF* snBt ifcfrV • - .S* ^^ ' • jt >~v • *S
26, SP-24 - A close up showing the rust colored soil
S.T. HUDSON ENGiNeERS, 1NC
^
27. SP-25 - Soil with a rust color and an oily like sheen.
28. SP-26 - Located downstream of the 003 outfallNote the rust colored soil.
S.T. HUDSON ENGINEERS. INC.
29. Concrete Foundation Wall - Effluent flowing from down-stream corner of wall. Note: Rust colored concrete andsoil.
30. Concrete Foundation Wall - Multiple seeps in concretewall. Heaviest seeps at the upstream and downstreamcorners.
S.T. HUDSON ENGINEERS, INC
INSPECTION OF THE TIMBER BULKHEADAT BUILDING A-47
1. Photograph looking upstream. Station 0+00 to 1+35.Note: Absence of rock fill at bottom of wall startingat Station 0+80+.
2. Photograph looking north. Station 1+40 to 2+04.Note: Numerous surface cracks on sloping partof concrete topping.
S r HUDSON ENGINEERS. INC.
Photograph looking downstream at Station 0+10+.Note: Uneven horizontal timbers. Weathered re-placement timber piles and old rotted and brokentimber piles.
4. Photograph looking downstream at Station 0+38,Note: Gap where the bottom horizontal timberis moving outshore.
S.r HUDSON SNGINEEPS iNC-
5. South face of Building A-47 looking upstream,Note: Gap between concrete topping and thebuilding.
timwenr S.T. HUDSON ENGINEERS INC.
6. South face of Building A-47 looking downstreamat Station 1+85 showing gap of I" vide and 12"deep between the building and the concretetopping.
" HUDSON £NG!M£=RS. NC
DRAWINGS
AR3I01+62
UNSCANNED ITEM(S)
ONE OR MORE OF THE FOLLOWING ITEMS MAY BE ASSOCIATEDWITH THIS DOCUMENT:
PHOTOGRAPHSDRAWINGS
OVERSIZED MAPSROLLED MAPS
PLEASE CONTACT THE CERCLA RECORDS CENTER TO VIEW THEITEM(S)