valliammai engineering college semester/mc7401-resource...apply graphical method to solve the...
TRANSCRIPT
VALLIAMMAI ENGINEERING COLLEGE
SRM Nagar, Kattankulathur – 603 203
DEPARTMENT OF COMPUTER APPLICATIONS
QUESTION BANK
IV SEMESTER
MC 7401 – RESOURCE MANAGMENT TECHNIQUES
Regulation – 2013
Academic Year 2017 – 18
Prepared by
Mr. S. K. Saravanan, Assistant Professor/MCA
VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur – 603 203.
DEPARTMENT OF COMPUTER APPLICATIONS
QUESTION BANK
SUBJECT: MC 7401 – RESOURCE MANAGMENT TECHNIQUES
SEM / YEAR: IV / II
UNIT I - LINEAR PROGRAMMING MODELS
SYLLABUS : Mathematical Formulation - Graphical Solution of linear programming models – Simplex
method – Artificial variable Techniques- Variants of Simplex method
PART – A (2 Marks)
Q.No Questions BT Level Competence
1. What is infeasible solution? BTL1 Knowledge
2. Show some applications of Linear Programming Problem. BTL3 Application
3. What is Operation Research and Analyze its characteristics? BTL4 Analysis
4. What are the components of LPP? BTL4 Analysis
5. Define Convex Polygon. BTL1 Knowledge
6. What are the limitations of LPP? BTL2 Comprehension
7. What is linear programming problem? Describe its characteristics. BTL1 Knowledge
8. What is the mathematical model of linear programming? BTL1 Knowledge
9. Compare standard and canonical forms of LPP? BTL2 Comprehension
10. Discuss the characteristics of standard and canonical forms of LPP? BTL2 Comprehension
11. A firm manufactures two types of products A and B and sells them at profit
of Rs 2 on type A and Rs 3 on type B. Each product is processed on two
machines M1 and M2.Type A requires 1 minute of processing time on M1
and 2 minutes on M2 Type B requires 1 minute of processing time on M1
and 1 minute on M2. Machine M1 is available for not more than 6 hours 40
minutes while machine M2 is available for 10 hours during any working day.
Formulate the problem as a LPP so as to maximize the profit.
BTL3 Application
12. What is feasibility region? Is it necessary that it should always be a convex
set?
BTL4 Analysis
13. Define solution, feasible solution and optimal solution of LPP. BTL1 Knowledge
14. State the applications of linear programming. BTL3 Application
15. Devise the meaning of unbounded solution and Multiple Optimal solution. BTL5 Synthesis
16. Propose the meaning of slack and surplus variables. BTL5 Synthesis
17. How to resolve degeneracy in a LPP? BTL6 Evaluation
18. What is Simplex method? BTL1 Knowledge
19. Explain basic variable and non-basic variable in LP . BTL2 Comprehension
20. What do you think about unrestricted variable and artificial variable? BTL6 Evaluation
PART – B (13Marks)
1. Use Two – Phase simplex method to solve the following LPP.
Maximize Z = 3X1 + 2 X2
Subject to the constraints
2X1 + X2 ≤ 2
3X1 + 4X2 ≥ 12
X1, X2 ≥ 0
BTL3 Application
2. Use Big-M method to solve the following LPP.
Maximize Z = 3X1 - X2
Subject to the constraints
2X1 + X2 ≥ 2
X1 + 3X2 ≤ 3
X1, X2 ≥ 0
BTL3 Application
3. Solve by Big-M method.
Minimize Z = 2X1 + X2
Subject to the constraints
3X1 + X2 = 3
4X1 + 3X2 ≥ 6
X1 + 2X2 ≤ 3
X1, X2 ≥ 0
BTL3 Application
4. Solve the following LPP using Big-M method.
Maximize Z = 2X1 +3X2 + 4X3
Subject to the constraints
3X1 + X2 + 4X3 ≤ 600
2X1 + 4X2 + 2X3 ≥ 480
2X1 + 3X2 + 3X3 = 540
X1, X2, X3 ≥ 0
BTL3 Application
5. Apply Simplex method to solve the LPP
Maximize Z = 3X1 + 5X2
Subject to the constraints
3X1 + 2X2 ≤ 18
0 ≤ X1 ≤ 4, 0 ≤ X2 ≤ 6
BTL5 Synthesis
6. Use simplex method to solve the LPP.
Maximize Z = 4X1 + 10X2
Subject to the constraints
2X1 + X2 ≤ 50
2X1 + 5X2 ≤ 100
2X1 + 3X2 ≤ 90 and
X1, X2 ≥ 0.
BTL3 Application
7. i. Apply graphical method to solve the following LPP (10)
Maximize Z = 3X1 + 4X2
Subject to the constraints
X1 + X2 ≤ 450
2X1 + X2 ≤ 600
X1, X2 ≥ 0.
ii. Write the steps of graphical method. (3)
BTL5 Synthesis
8. Solve the LPP by graphical Method
Maximize Z = 3X1 + 5X2
Subject to the constraints
2X1 - X2 ≥ -2
2X1 + 3X2 ≥ 12
X1 ≤ 4
X2 ≥ 2 and X1, X2 ≥ 0.
BTL3 Application
9. i. A company produces refrigerator in Unit I and heater in Unit II. The two
products are produced and sold on a weekly basis. The weekly production
cannot exceed 25 in unit I and 36 in Unit II, due to constraints 60 workers
are employed. A refrigerator requires 2 man week of labour, while a heater
requires 1 man week of labour, the profit available is Rs. 600 per refrigerator
and Rs. 400 per heater. Formulate the LPP problem. (8)
ii. Solve the following LPP Graphically:
Minimize Z = 4X1 + 3X2
Subject to the constraints
X1 + 3X2 ≥ 9
2X1 + 3X2 ≥ 12
X1 + X2 ≥ 5
X1, X2 ≥ 0.
BTL3 Application
10.
i. A firm manufactures two types of products A and B and sells them at profit
of Rs 2 on type A and Rs 3 on type B. Each product is processed on two
machines M1 and M2.Type A requires 1 minute of processing time on M1
and 2 minutes on M2 Type B requires 1 minute of processing time on M1
and 1 minute on M2. Machine M1 is available for not more than 6 hours 40
minutes while machine M2 is available for 10 hours during any working day.
Formulate the problem as a LPP so as to maximize the profit.
(5)
ii. Solve the following LPP using Graphical Method
Max Z = 3x1 + 4 x 2
Subject to the constraints
5x1 + 4x2 ≤ 200, 3x1 + 5x2 ≤ 150
5x1 + 4x2 ≥ 100, 8x1 + 4x2 ≥ 80 and
x1, x2 ≥ 0 (8)
BTL3 Application
11. Solve the following LPP.
Minimize Z = 4X1 + 2X2
Subject to the constraints
3X1 + X2 ≥ 27
X1 + X2 ≥ 21
X1 + 2X2 ≥ 30
X1, X2 ≥ 0.
BTL3 Application
12. Apply graphical method to solve the LPP.
Maximize Z = X1 - 2X2
Subject to the constraints
-X1 + X2 ≤ 1
6X1 +4X2 ≥ 24
0 ≤ X1 ≤ 5, 2 ≤ X2 ≤ 4
BTL5 Synthesis
13. Solve the following LPP by simplex method.
Minimize Z = 8 X1 - 2X2
Subject to the constraints
-4X1 + 2X2 ≤ 1
5X1 - 4X2≤ 3
and X1, X2 ≥ 0.
BTL3 Application
14. Solve the following LPP.
Maximize Z = 5X1 + 6X2 + X3
Subject to the constraints
9X1 + 3X2 - 2X3≤ 5
4X1 + 2X2 - X3 ≤ 2
X1 - 4X2 + X3 ≤ 3
X1, X2, X3 ≥ 0.
BTL5 Synthesis
PART – C (15Marks)
1. i. Use the graphical method to solve the following LPP. (10)
Minimize Z = 20 X1 + 10X2
Subject to the constraints
X1 + 2X2 ≤ 40
3X1 + X2 ≥ 30 and
X1, X2 ≥ 0.
ii. Draw the flowchart for the Simplex method(Minimization case). (5)
BTL5 Synthesis
2. i. Use Simplex method to solve the LPP. (10)
Minimize Z = X1 - 3X2 + 2X3
Subject to the constraints
3X1 - X2 + 2X3 ≤ 7
-2X1 + 4X2 ≤ 12
-4X1 + 3X2 + 8X3 ≤ 10
X1, X2, X3 ≥ 0.
ii. Write the Simplex Algorithm (Maximization case). (5)
ii. Draw the flowchart for the Simplex method(Minimization case).
BTL3 Application
3. i. Use Big-M method to solve the following LPP.
Maximize Z = 2X1 + 4X2
Subject to the constraints
2X1 + X2 ≤ 18
3X1 + 2X2 ≥ 30
X1 + 2X2 = 26
X1, X2 ≥ 0
ii. Write the procedure of Big-M method.
(5)
(10) BTL3 Application
4. i. Use two-phase Simplex method to solve.
Maximize Z = 5X1 - 4X2 + 3X3
Subject to the constraints
2 X1 + X2 - 6X3 = 20
6 X1 + 5X2 + 10X3 ≤ 76
8 X1 - 3X2 + 6X3 ≤ 50
X1, X2, X3 ≥ 0
ii. Write the procedure of two-phase method.
(5)
(10) BTL3 Application
VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur – 603 203.
DEPARTMENT OF COMPUTER APPLICATIONS
QUESTION BANK
SUBJECT : MC 7401 – RESOURCE MANAGMENT TECHNICS
SEM / YEAR: IV / II
UNIT II - TRANSPORTATION AND ASSIGNMENT MODELS
SYLLABUS : Mathematical formulation of transportation problem- Methods for finding initial basic feasible
solution – optimum solution - degeneracy – Mathematical formulation of assignment models – Hungarian
Algorithm – Variants of the Assignment problem
PART – A (2 Marks)
Q.No Questions BT Level Competence
1. Define transportation problem and its basic purpose. BTL1 Knowledge
2. Define feasible solution & basic feasible solution in transportation problem. BTL1 Knowledge
3. Provide a definition for optimal solution and mathematical formation of
transportation problem.
BTL2 Comprehension
4. Obtain the initial solution for the transportation problem using least cost
method.
A B C SUPPLY
1 5
2 8
3 7
4 14
DEMAND 34
BTL4 Analysis
5. Can you provide the basic steps involved in solving a transportation
problem?
BTL2 Comprehension
6. What do you understand by degeneracy in a transportation problem? BTL4 Analysis
7. What are balanced & unbalanced transportation problems? BTL1 Knowledge
8. How do you convert an unbalanced transportation problem into a balanced BTL5 Synthesis
9. Describe how the profit maximization transportation problem can be
converted to an equivalent cost minimization transportation problem.
BTL1 Knowledge
10. Solve the assignment problem BTL3 Application
A B C D
I 20 25 22 28
II 15 18 23 17
III 19 17 21 24
IV 25 23 24 24
11. What differences exist between Transportation & Assignment Problem? BTL2 Comprehension
12. What are assignment problem and unbalanced assignment problem? BTL1 Knowledge
13. Define unbounded assignment problem and describe the steps involved in
solving it.
BTL1 Knowledge
14. Describe how a maximization problem is solved using assignment model. BTL4 Analysis
2 7 4
3 3 1
5 4 7
1 6 2
7 9 18
15. What do you understand by restricted assignment? How do you overcome
it?
BTL6 Evaluation
16. How do you identify alternative solution in assignment problem? BTL6 Evaluation
17. Illustrate the travelling salesman problem. BTL3 Application
18. Can you say how a minimization problem is solved using assignment model? BTL2 Comprehension
19. Can you propose which method is best for finding initial basic feasible
solution in transportation problem?
BTL5 Synthesis
20. Show the mathematical formulation of assignment model. BTL3 Application
PART – B (13Marks)
1. Good has to be transported from sources S1, S2 and S3 destinations D1, D2
and D3. The transportation cost per unit, capacities of the sources and
requirements of the destinations are given in the following table.
I II III SUPPLY
S1
S2
S3
DEMAND
Determine a transportation schedule so that cost is Minimum.
BTL5 Synthesis
2. Solve the following assignments problems
I II III IV V
A
B
C
D
E
BTL3 Application
3. Solve the TP where cell entries are unit costs. Use Vogel’s approximate
method to find the initial basic solution.
D1 D2 D3 D4 D5 AVAILABLE
O1 18
O2 17
O3 19
O4 13
O5 15
Required 16 18 20 14 14
BTL1 Knowledge
8 5 6 120
15 10 12 80
3 9 10 150
150 80 50
10 5 9 18 11
13 19 6 12 14
3 2 4 4 5
18 9 12 17 15
11 6 14 19 10
68 35 4 74 15
57 88 91 3 8
91 60 75 45 60
52 53 24 7 82
51 18 82 13 7
4. A small garments making units has five tailors stitching five different types
of garments all the five tailors are capable of stitching all the five types of
garments .The output per day per tailor and the profit(Rs.)for each type of
garments are given below.
1 2 3 4 5
A
B
C
D
E
PROFIT 2 3 2 3 4
Which type of garments should be assigned to which tailor in order to
maximize profit, assuming that there are no others constructs.
BTL4 Analysis
5. Solve the following TP to maximize profit
A B C D SUPPLY
1 100
2 30
3 70
DEMANDS 40 20 60 30
BTL3 Application
6. Five workers are available to work with the machines and respective cost
associated with each worker –machine assignments is given below. A sixth
machine is available to replace one of the existing machines and the
associated costs are also given below.
M1 M2 M3 M4 M5 M6
W1
W2
W3
W4
W5
Determine whether the new machine can be accepted and also determine
optimal assignments and the associated saving in cost
BTL6 Evaluation
7. Solve the following Transportation Problem
A B C D SUPPLY
30
I
40
II
30
III
20 20 25 35 100
DEMAND
BTL3 Application
7 9 4 8 6
4 9 5 7 8
8 5 2 9 8
6 5 8 10 10
7 8 10 9 9
40 25 22 33
44 35 30 30
38 38 28 30
12 3 6 - 5 8
4 11 - 5 - 3
8 2 10 9 7 5
- 7 8 6 12 10
5 8 9 4 6 -
15 18 22 16
15 19 20 14
13 16 23 17
8. Determine the IFBS using North-West Corner Rule and VAM
1 2 3 4 5
A
B
C
Demand
Supply
BTL3 Application
9. Solve the following assignment problem.
M1
J1
J2
J3
M2
M3
M4
BTL3 Application
10. Solve the following Transportation Problem. BTL3 Application
D1 D2 D3 D4 SUPPLY
S1 6 1 9 3 70
S2 11 5 2 8 55
S3 10 12 4 7 70
DEMANDS 85 35 50 45
11. Solve the following travelling salesman problem so as to minimize the cost
per cycle.
A B C D E
A
B
C
D
E
BTL3 Application
12. A Company has one surplus truck in each of the cities A,B,C,E&E and one
deficit truck in each of the cities 1,2,3,4,5&6. The distance between the
cities (in km) is shown in below matrix.
To Cities (Deficit)
1 2 3 4 5 6
From cities A 12 10 15 22 18 8 (Surplus)
B 10 18 25 15 16 12
C 11 10 3 8 5 9
D 6 14 10 13 13 12
E 8 12 11 7 13 10
Find the assignment of trucks from cities in surplus to cities in deficit so that
the distance covered these vehicles is minimum.
BTL5 Synthesis
2 11 10 3 7 4
1 4 7 2 1 8
3 9 4 8 12 9
3 3 4 5 6 21
18 24 28 32
8 13 17 18
10 15 19 22
- 3 6 2 3
3 - 5 2 3
6 5 - 6 4
2 3 6 - 6
3 3 4 6 -
13. Find the optimal solution of the following transportation problem.
Destination X Y Z SUPPLY
P 30
Origin Q 35
R 35
DEMAND 30 40 30
BTL3 Application
14. A Transport corporation has three vehicles in three cities. Each of
vehicles can be assigned to any of the four other cities. The distance
from one city to another as under : W X Y Z
A
B
C
You are required :
i. to assign a vehicle to a city in such a way that the total distance
travelled is minimized. (10)
ii. to build a mathematical model (3)
BTL5 Synthesis
PART – C (15Marks)
1. i. Solve the following Travelling Salesman Problem. (10)
To
P Q R S
A
From B
C
D
ii. Discuss the various degeneracy occur in Transportation problem and how to resolve it. (5)
BTL3 Application
2. i. Find an optimal solution to the following Transportation Problem. A B C SUPPLY
1 50
2 70
3 80
4 140
DEMAND 340 (10)
ii. Write the procedure for Modified Distribution Method (MODI) to
solve the Transportation problem. (5)
BTL3 Application
1 2 0
2 3 4
1 5 6
33 40 43 32
45 28 31 23
42 29 36 29
∞ 46 16 40
41 ∞ 50 40
82 32 ∞ 60
40 40 36 ∞
2 7 4
3 3 7
5 4 1
1 6 2
70 90 180
3. i. Consider the following profit matrix.
SUPPLY
1 150
2 200
3 125
DEMAND
Minimize the profit. (10)
ii. Write the procedure of Vogel’s Approximation method. (5)
BTL3 Application
4. i. Four jobs are to be done on four different machines. Assign the jobs
so as to maximize the total profit. (10)
ii. Draw the flowchart of Hungarian method. (5)
BTL3 Application
A B C D E
19 21 16 15 15
9 13 11 19 11
18 19 20 24 14
80 100 75 45 125
M1 M2 M3 M4
J1 15 11 13 15
J2 17 12 12 13
J3 14 15 10 14
J4 16 13 11 17
VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur – 603 203.
DEPARTMENT OF COMPUTER APPLICATIONS
QUESTION BANK
SUBJECT : MC 7401 – RESOURCE MANAGMENT TECHNICS
SEM / YEAR: IV / II
UNIT III - INTEGER PROGRAMMING MODELS
SYLLABUS : Formulation – Gomory’s IPP method – Gomory’s mixed integer method – Branch
and bound technique.
PART – A (2 Marks)
Q.No Questions BT Level Competence
1. State the Integer Programming Model. BTL1 Knowledge
2. Explain the characteristics of Integer programming problem. BTL4 Analysis
3. List some of the applications of Integer Programming. BTL3 Application
4. Define Mixed Integer Programming Problem. BTL2 Comprehension
5. What is Zero-one problem? BTL1 Knowledge
6. Write the differences between Pure & mixed integer programming. BTL2 Comprehension
7. Explain the importance of Integer Programming. BTL4 Analysis
8. Why not round off the optimum values instead of resorting to IP? BTL5 Synthesis
9. Write the difference between LPP and IPP. BTL2 Comprehension
10. What is cutting Plane method? BTL1 Knowledge
11. What do you think about search method? BTL6 Evaluation
12. Write about Branch and Bound Technique. BTL5 Synthesis
13. Construct the general format of IPP. BTL3 Application
14. Write the Gomory’s IPP method. BTL2 Comprehension
15. What is the purpose of Fractional cut constraints? BTL1 Knowledge
16. A manufacturer of baby dolls makes two types of dolls, doll X and doll Y.
Processing of these dolls is done on two machines A and B. Doll X requires 2
hours on machine A and 6 hours on Machine B. Doll Y requires 5 hours on
machine A and 5 hours on Machine B. There are 16 hours of time per day
available on machine A and 30 hours on machine B. The profit is gained on
both the dolls is same. Format this as IPP?
BTL3
Application
17. Explain Gomory’s Mixed Integer Method. BTL4 Analysis
18. What the geometrical meaning is of partitioned or branched the original
problem? BTL1 Knowledge
19. What is standard discrete programming problem? BTL1 Knowledge
20. How can you improve the efficiency of partitioned method? BTL6 Evaluation
PART – B (13Marks)
1. Solve the following mixed integer linear programming problem.
Maximize Z = X1 + X2
Subject to
2X1 + 5X2 ≤ 16
6X1 + 5X2 ≤ 30
X1, X2 ≥ 0 and X1 is integer.
BTL3 Application
2. Solve the following ILPP.
Maximize Z = 11X1 + 4X2
Subject to the constraints
-X1 + 2X2 ≤ 4
5X1 + 2X2 ≤ 16
2X1 - X2 ≤ 4
X1, X2 ≥ 0 and are non negative integers.
BTL3 Application
3. Solve the integer programming problem.
Maximize Z = 2X1 + 20X2 - 10X3
Subject to the constraints
2X1 + 20X2 + 4X3 ≤ 15
6X1 + 20X2 + 4X3 = 20
X1, X2, X3 ≥ 0 and are integers.
BTL3 Application
4. Explain the geometrical interpretation of Branch and Bound method by
solving the following Integer Linear Programming.
Maximize Z = X1 + X2
Subject to the constraints
3X1 + 2X2 ≤ 12
X2 ≤ 2
X1, X2 ≥ 0 and are integers.
BTL2 Comprehension
5. Solve the following mixed integer programming problem.
Maximize Z = 7X1 + 9 X2
Subject to the constraints
-X1 + 3X2 ≤ 6
7X1 + X2 ≤ 35
and X1, X2, ≥ 0, X1 is an integer.
BTL3 Application
6. Solve the following mixed integer programming problem.
Maximize Z = 4X1 + 6X2 + 2X3
Subject to the constraints
4X1 - 4X2 ≤ 5
-X1 + 6X2 ≤ 5
-X1 + X2 + X3 ≤ 5
and X1, X2, X3 ≥ 0, and X1 , X3 are integers.
BTL3 Application
7. Use Branch and bound algorithm to solve the following ILPP
Maximize Z = 3X1 + 4X2
Subject to the constraints
7X1 + 16X2 ≤ 52
3X1 - 2X2 ≤ 18
X1, X2 ≥ 0 and are integers.
BTL5 Synthesis
8. Apply Branch and bound algorithm to solve the following ILPP
Maximize Z = X1 + 4X2
Subject to the constraints
2X1 + 4X2 ≤ 7
5X1 + 3X2 ≤ 15
X1, X2 ≥ 0 and are integers.
BTL4 Analysis
9. Apply Branch and bound algorithm to solve the following ILPP
Maximize Z = 2X1 + 2X2
Subject to the constraints
5X1 + 3X2 ≤ 8
X1 + 2X2 ≤ 4
X1, X2 ≥ 0 and are integers
BTL4 Analysis
10. Using Gomory’s cutting plane method to solve the problem.
Maximize Z = 2X1 + 2X2
Subject to the constraints
5X1 + 3X2 ≤ 8
2X1 + 4X2 ≤ 8
X1, X2 ≥ 0 and are all integers.
BTL5 Synthesis
11. Describe the Branch and Bound Technique for Pure and Mixed IPP with
flowchart.
BTL1 Knowledge
12. i. Explain the Gomory’s Cutting Plane algorithms for Pure (All) IPP. (7)
ii. Explain the Gomory’s Cutting Plan algorithm for Mixed IPP. (6)
BTL2 Comprehension
13. Solve the following mixed integer problem.
Minimize Z = 10X1 + 9X2
Subject to the constraints
X1 ≤ 8
X2 ≤ 10
5X1 + 3X2 ≥ 45
X1, X2 ≥ 0, and X1 integer.
BTL3 Application
14. Solve the following mixed integer programming problem.
Maximize Z = X1 - 3X2
Subject to the constraints
X1 + X2 ≤ 5
-2X1 + 4X2 ≤ 11
X1, X2 ≥ 0 and and X2 is an integer.
BTL3 Application
PART – C (15 Marks)
1. Solve the following ILPP using Gomary’s Cutting Plane Method.
Maximize Z = X1 + X2
Subject to the constraints
2 X1+5X2 ≤ 16
6X1 +5 X2 ≤ 30
X1, X2 ≥ 0 and are integers.
BTL3 Application
2. Solve the following all-integer programming problem using the Branch and
Bound Method.
Miniimize Z = 3X1 + 2.5X2
Subject to the constraints
X1 + 2X2 ≥ 20
3X1 + 2X2 ≥ 50
X1, X2 ≥ 0 and are integers.
BTL3 Application
3. Solve the following mixed integer linear programming problem using
Gomarian’s cutting plane method.
Maximize Z = X1 + X2
Subject to the constraints
3 X1 + 2 X2 ≤ 5
X2 ≤ 2
X1, X2 ≥ 0 and X1 is an integer.
BTL3 Application
4. Solve the following mixed integer problem.
Maximize Z = -3X1 + X2 + 3 X3
Subject to
- X1 + 2X2 + X3 ≤ 4
2X2 + 1.5X3 ≤ 1
X1 - 3X2 + 2X3 ≤ 3
X1, X2 ≥ 0 and X3 non-negative integer.
BTL3 Application
VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur – 603 203.
DEPARTMENT OF COMPUTER APPLICATIONS
QUESTION BANK
SUBJECT : MC 7401 – RESOURCE MANAGMENT TECHNICS
SEM / YEAR: IV / II
UNIT IV - SCHEDULING BY PERT AND CPM
SYLLABUS : Network Construction – Critical Path Method – Project Evaluation and Review Technique – Resource Analysis in Network Scheduling
PART – A (2 Marks)
Q.No Questions BT Level Competence
1. What do you mean by project? Give an example. BTL6 Evaluation
2. What are the assumptions made in PERT calculations? BTL4 Analysis
3. What are the two basic planning and controlling techniques in a network? BTL4 Analysis
4. Write down the advantages of CPM and PERT techniques? BTL2 Comprehension
5. Differentiate between PERT and CPM. BTL2 Comprehension
6. Draw the network for the project whose activities with predecessor
relationship are given below :
A,C,D can start simultaneously. E > B,C; F,G > D; H,I >E,F; J > I, G; K> H; B > A;
BTL1 Knowledge
7. How does the PERT technique help a business manager in decision-making? BTL6 Evaluation
8. Can you write about activity & Critical Activities? BTL5 Synthesis
9. Define Dummy Activities and duration. BTL1 Knowledge
10. List three main managerial functions for any project. BTL4
11. What are float and slack? BTL1 Knowledge
12. Classify Crash time and Crash cost. BTL3 Application
13. Can you list the network construction steps? BTL3 Application
14. Define Optimistic time time estimate in PERT. BTL1 Knowledge
15. Show and define Pessimistic time estimate in PERT. BTL3 Application
16. How do you calculate most likely time estimation? BTL5 Synthesis
17. What is a parallel critical path? BTL1 Knowledge
18. Distinguish standard deviation and variance in PERT network? BTL2 Comprehension
19. Give the difference between direct cost and indirect cost. BTL2 Comprehension
20. What is meant by resource analysis? BTL1 Knowledge
PART – B (13Marks)
1. A project schedule has the following characteristics.
i. Construct Network diagram (3)
ii. Compute Earliest time and latest time for each event. (5)
iii. Find the critical path. Also obtain the Total float, Free float and slack time
and Independent float. (5)
BTL1 Knowledge
2. A small project is composed of seven activities whose time estimates are
listed in the table as follows:
i. Draw the network and find the project completion time. (7)
ii. Calculate the three floats for each activity. (6)
BTL3 Application
3. Calculate the total float, free float and independent float for the project
whose activities are given below:
Find the critical path also.
BTL1 Knowledge
4. Draw the network for the following project and compute the earliest and
latest times for each event and also find the critical path.
BTL6 Evaluation
Activity 1 – 2 1 – 3 2 – 4 3 – 4 3 – 5 4 – 9
Time 4 1 1 1 6 5
Activity 5 – 6 5 – 7 6 – 8 7 - 8 8 - 10 9 - 10
Time 4 8 1 2 5 7
Activity Preceding Activities Duration
A ---- 4
B ---- 7
C ---- 6
D A,B 5
E A,B 7
F C,D,E 6
G C,D,E 5
Activity 1 –2 1 – 3 1 – 5 2 – 3 2 – 4 3 – 4
Time 8 7 12 4 10 3
Activity 3 – 5 3 – 6 4 - 6 5 - 6
Time 5 10 7 4
Activity 1 – 2 1 – 3 2 – 4 3 – 4 4 – 5 4 – 6
Immediate
Predecessor --- --- 1 – 2 1 – 3 2 – 4
2 – 4 &
3 - 4
Time 5 4 6 2 1 7
Activity 5 – 7 6 – 7 7 - 8
Immediate
Predecessor 4 – 5 4 – 6
6 – 7 &
5 - 7
Time 8 4 3
5. The following table lists the jobs of a network with their time estimates:
i. Draw the project network. (4)
ii. Calculate the length and variance of the Critical Path. (3)
iii.What is the approximate probability that the jobs on the critical path will
be completed by the due date of 42 days? (3)
iv.What due date has about 90 % chance of being met? (3)
BTL5 Synthesis
6. A small project is composed of 7 activities, whose time estimates are listed
in the table below. Activities are identified by their beginning (i) and (j)
node numbers.
i. Draw the project network and identify all the paths through it. (5)
ii. Find the expected duration and variance for each activity. What is the
expected project length? (3)
ii. Calculate the variance and standard deviation of the project length.What
is the probability that the project will be completed at least 4 weeks earlier
than expected time? (5)
BTL2 Comprehension
7. Draw the network and determine the critical path for the given data.
Find the Total Float, Free Float and Independent float for the given data
BTL3 Application
Job(i, j)
Duration
Optimistic (to) Most likely(tm) Pessimistic (tp)
1 – 2 3 6 15
1 – 6 2 5 14
2 – 3 6 12 30
2 – 4 2 5 8
3 – 5 5 11 17
4 – 5 3 6 15
6 – 7 3 9 27
5 – 8 1 4 7
7 – 8 4 19 28
Job(i, j)
Duration
Optimistic (to) Most likely(tm) Pessimistic (tp)
1 – 2 1 1 7
1 – 3 1 4 7
1 – 4 2 2 8
2 – 5 1 1 1
3 – 5 2 5 14
4 – 6 2 5 8
5 – 6 3 6 15
Jobs 1 – 2 1 – 3 2 – 4 3 – 4 3 – 5 4 – 5 4 – 6 5 – 6
Duration 6 5 10 3 4 6 2 9
8. For the data given in the table below, draw the network, crash
systematically the activities and determine the optimal project duration and
cost. Indirect cot Rs. 70 per day
BTL6 Evaluation
9. The following table lists the jobs of a network along with their time
estimates.
Draw the network. Calculate the length and variance of the critical path and
find the probability that the project will be completed within 30 days
BTL3 Application
10. A project has the following activities and characteristics.
i. Find expected duration of each activity.
ii. Draw the project network and expected duration of the project.
iii. Find variances of activities on critical path and its standard deviation.
BTL4 Analysis
Activity) Normal Time
(days)
Cost Crash Time
(days)
Cost
1 – 2 8 100 6 200
1 – 3 4 150 2 350
2 – 4 2 50 1 90
2 – 5 10 100 5 400
3 – 4 5 100 1 200
4 – 5 3 80 1 100
Job(I, j)
Duration
Optimistic (to) Most likely(tm) Pessimistic (tp)
1 – 2 2 5 14
1 – 3 9 12 15
2 – 4 5 14 17
3 – 4 2 5 8
4 – 5 6 6 12
3 – 5 8 17 20
Activity
Estimated duration in days
Optimistic Most likely Pessimistic
1 – 2 2 5 8
1 – 3 4 10 16
1 – 4 1 7 13
2 – 5 5 8 11
3 – 5 2 8 14
4 – 6 6 9 12
5 – 6 4 7 10
11. Draw a network from the following activity and find a critical path and
duration of project.
BTL3 Application
Activity
1 –2 1 – 3 2 – 4
(Dummy)
2 – 7 3 – 4
(Dummy)
3 – 8 4 – 5
Time 3 8 0 1 0 2 4
12. The following information is available:
i. Draw the network and find the critical path.
ii. What is the peak requirement of Manpower? On which day(s) will this
occur?
iii. If the maximum labour available on any day is only 10, when can the
project be completed?
BTL4 Analysis
13. i. Explain the different phases of Network Analysis .
ii. Explain the Network components in detail with neat sketches.
(6)
(7)
BTL2 Comprehension
14. i. Describe the precedence relationship in detail with diagrams.
ii. Describe the different types of Floats and Slacks.
(6)
(7)
BTL1 Knowledge
PART – C (15Marks)
1. A project consists of a series or tasks labelled A, B,...H,I with the following
relationships (W < X , Y means D and Y cannot start until W is completed;
X,Y < W means W cannot start until both X and Y are completed). With this
notation, construct the network diagram having the following constraints:
A < D, E; B,D < F; C < G ; B < H; F, G < I
Find also the critical path of the project, when the time (in days) of each task
is as follows :
BTL1 Knowledge
5 – 6 6 – 7
(Dummy)
6 – 8
(Dummy)
7 - 9 8 - 9 9 -10 10 - 11
7 0 0 5 8 8 9
Activity No. of Days No. of men reqd. per day
A 1-2 4 2
B 1-3 2 3
C 1-4 8 5
D 2-6 6 3
E 3-5 4 2
F 5-6 1 3
G 4-6 1 8
Task A B C D E F G H I
Time 23 8 29 16 24 18 19 4 10
2. A project schedule ahs the following characteristics:
Construct a network and find critical path, total duration of the project and
various time estimates.
BTL3 Application
3. The following table gives the activities in a construction project and other
relevant information.
i. Draw a PERT diagram.
ii. Find the probability that the project will be completed in less than 60
days.
BTL6 Evaluation
4. The following project network and associated costs are given below:
i. Draw the network diagram
ii. What is the earliest the project can be completed? What is the lowest cost
for completing it in this time?
BTL4 Analysis
Activity 1 – 2 1 – 4 1 – 7 2 – 3 3 –6 4 – 5 4 – 8 5 – 6
Duration 3 2 1 3 2 4 6 5
Activity 6 – 9 7 – 8 8 – 9
Duration 4 4 5
Activity Optimistic Time
T1
Normal Time T2
Pessimistic Time
T3
1 – 2 30 44 54
1 – 3 8 12 16
2 – 3 1 2 3
2 – 4 2 3 5
3 – 4 8 10 12
4 – 5 14 22 25
Activity Predecess
or
Normal Crash
Tn (Days) Cn (Rs.) Tc(Days) Cc (Rs.)
A - 9 10 6 16
B - 8 9 5 18
C A 5 7 4 8
D A 8 9 6 19
E B 7 7 3 15
F C 5 5 5 5
G E,D 5 8 2 23
VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur – 603 203.
DEPARTMENT OF COMPUTER APPLICATIONS
QUESTION BANK
SUBJECT : MC 7401 – RESOURCE MANAGMENT TECHNICS
SEM / YEAR: IV / II
UNIT V - QUEUEING MODELS
SYLLABUS : Characteristics of Queuing Models – Poisson Queues - (M / M / 1) : (FIFO / ∞ /∞), (M / M / 1)
: (FIFO/ N / ∞), (M / M / C) : (FIFO / ∞ / ∞), (M / M / C) : (FIFO / N / ∞) models.
PART – A (2 Marks)
Q.No Questions BT Level Competence
1. Define Kendal’s notation for representing queuing models. BTL1 Knowledge
2. In a super market, the average arrival rate of customer is 5 in every 30
minutes following Poisson process. The average time is taken by the cashier
to list and calculate the customer’s purchase is 4.5 minutes; following
exponential distribution. What is the probability that the queue length
exceeds 5?
BTL5
Synthesis
3. Explain Queue discipline and its various forms. BTL4 Analysis
4. Distinguish between transient and steady state queuing system. BTL4 Analysis
5. Define steady state. BTL1 Knowledge
6. Define Jockeying. BTL1 Knowledge
7. If traffic intensity of M/M/I system is given to be 0.76, what percent of time
the system would be idle? BTL5 Synthesis
8. List the basic elements of queuing system. BTL2 Comprehensi
9. What do you meant by Balking and Reneging of customer behavior in a
queuing system? BTL2 Comprehension
10. What are the characteristics of queuing model? BTL2 Comprehension
11. Define Poisson process with its properties. BTL1 Knowledge
12. A two channel waiting line with Poisson arrival has a mean rate of 50 per
hour and exponential service with mean rate and 75 per hour for each
channel. Find the probability of empty system and the probability than an
arrival in the system will have to wait.
BTL4
Analysis
13. Customer arrives at a one-man barber shop according to a Poisson process
with a mean inter arrival time of 12 minutes. Customers spend a average of
10 minutes in the barber’s chain. What is the expected no of customers in
the barber shop and in the queue?
BTL6
Evaluation
14. Define pure birth process. BTL1 Knowledge
15. Write down the postulates of birth and death process? BTL3
16. What is the formula for the problem for a customer to wait in the system
under (m/m/1 : N/FCFS)? BTL1 Knowledge
17. What is “traffic intensity”? BTL3 Application
18. People arrive at a theatre ticket booth in Poisson distributed arrival rate of
25/hour. Service time is constant at 2 minutes. Calculate the mean? BTL6 Evaluation
19. Give the applications of Queuing Theory. BTL3 Application
20. State the operating characteristics of queuing system. BTL2 Comprehension
PART – B (13Marks)
1. A departmental store has a single cashier. During the rush hours customers
arrive at a rate of 20 customers per hour. The average number of
customers that can be processed by the cashier is 24 per hour. Assume
that the conditions for use of the single channel queuing model apply.
i. What is the probability that the cashier is idle? (2½)
ii. What is the average number of customers in the queuing system? (2½)
iii. What is the average time a customer spends in the system? (2½)
iv. What is the average number of customers in the queue? (3)
V. What is the average time a customer spends in the queue waiting for
service? (2½)
BTL1 Knowledge
2. A bank has two tellers working on savings accounts. The first teller handles
withdrawals only. The second teller handles depositors only. It has been
found that the service time distributions of both depositors and
withdrawals are exponential with a mean service time of 3 minutes per
customer. Depositors and withdrawers are found to arrive in a Poisson
fashion throughout the day with mean arrival rate of 16 and 14 per hour.
i. What would be the effect on the average waiting time for depositors and
withdrawers if each teller could handle both withdrawals and deposits? (7)
ii. What would be the effect if this could only be accomplished by increasing
the service time to 3.5 minutes? (6)
BTL5 Synthesis
3. At a certain filling station, customers arrive in a Poisson process with an
average time of 12 per hour. The time intervals between services follow
exponential distribution and as such the mean time taken to service a unit is
2 minutes. Evaluate:
(i). the probability that there is no customer at the counter. (2)
(ii). the probability that there are more than two customers at the counter. (2)
(iii). the probability that there is no customer to be served. (2)
(iv). the expected number of customers waiting in the system. (2)
(v). the expected number of customers in the waiting line. (2)
(vi). the expected time a customer spends in the system. (3)
BTL6 Evaluation
4. An insurance company has three claims adjusters in its branch office. People
with claims against the company are found to arrive in a Poisson fashion, at
an average rate of 20 per 8 hour day. The amount of time that an adjuster
with a claimant is found to have an exponential distribution, with mean
service time 40 minutes. Claimants are processed in the order of their
appearance.
i. How many hours a week an adjuster expected to spend with claimants? (7
ii. How much time, on the average, does a claimant spend in the branch
office?
BTL5 Synthesis
5. A supermarket has two girls at the counters .The customers arrive in an
poisson fashion at the rate of 12 per hour .The service time for each
customer is exponential with mean 6 minutes. Find
i. The probability that an arriving customer has to wait for service
ii. The average number of customer in the system and
iii. The average time spent by a customer in the supermarket
BTL4 Analysis
6. An airport emergency medical facility has a single paramedic and room for
a total of three patients, including the one being treated. Patients arrive
with an exponentially distributed inter arrival time with a mean of one
hour. Service time is exponentially distribute with a mean of 30 minutes.
i.What percentage of the time is the paramedic busy? (7)
ii. How many patients on average are refused entry in a 24 hour day? (3)
iii. What is the average number of patients in the facility at any given time?
(3)
BTL4 Analysis
7. i. Explain the fundamental components of a queuing process. (9)
ii. Write the conditions for single channel queuing model. (4)
BTL2 Comprehension
8. Draw the basic structures of Queuing Models and explain the various
processes. (13)
BTL1 Knowledge
9. Arrivals of a telephone booth are considered to be Poisson with an average
time of 10 minutes between one arrival and the next. The length of phone
call is assumed to be distributed exponentially, with mean 3 minutes.
i. What is the probability that a person arriving at the booth will have to wait?
(5)
ii. The telephone department will install a second booth when convinced that
an arrival would expect waiting for at least 3 minutes for a phone call. By
how much should the flow of arrivals increase in order to justify a second
booth? (6)
iii. What is the average length of the queue that forms from time to time?
(4)
BTL1 Knowledge
10. A branch of a national bank has only one typist. Since the typing work varies
in length, the typing rate is randomly distributed approximating Poisson
distribution with mean rate of 8 letters per hour. The letter arrives at a rate
of 5 per hour during the entire 8 hour work day. If the typewrite is valued at
Rs.1.50 per hour. Determine equipment utilization, the present time an
arriving letter has to wait, average system time and average idle time cost of
the typewriter per day.
BTL6 Evaluation
11. Ships arrive at a port at the rate of one in every 4 hours with exponential
distribution of inter arrival times. The time a ship occupies a berth for
unloading has exponential distribution with an average of 10 hours. If the
average delays of ships waiting for berths is to be kept below 14 hours. How
many berths should be provided at the port?
BTL3 Application
12. Obtain the steady state difference equations for the queuing model
(M/M/1) : (FCFS/N/∞) with usual nota0ons and solve them for P0 and Pn.
Also find the average number of units in the system and average queue
length.
BTL1 Knowledge
13. A T.V repairman finds that the time spent on his jobs has an exponential
distribution with mean 30 minutes. If he repairs sets in the order in which
they came in,and if they arrival of sets is approximately Poisson with the
average rate of 10per 8-hour day, what is repairman 's expected idle time
each day? How many jobs are ahead of the average set just brought in?
BTL3 Application
14. A factory has five machines. On an average there are two machine
breakdowns every 5 weeks .Assuming the repairing capacity is one machine
a week, the repairing time being exponential distributed ,determine
i. The probability that the service facility will be idle
ii. The probability that there shall be exactly 3 machines to be, and being
repaired
iii. The excepted number of the queue,
iv. The excepted time a machine waiting to be queue to be repaired ,and
v. The excepted time machine shall wait in the queue to be repaired, and
vi. The excepted time that a machine shall spend in the system-ie waiting for
and getting repaired
BTL3 Application
PART – C (15Marks)
1. A tailor specializes in ladies dresses .The number if customers approaching
the tailor appear to be Poisson distributed with a mean of 6 customers per
the hour .The tailor attends the customers on the first come first served -
basis and the customers wait, it the need be. The tailor can attend the
customers at an average rate of 10 customers per hour with the service time
exponentially distributed.
i. Find the probability of the number of arrivals (0 through 5) during
(a) a 15 minutes interval and (b) a 30 minute interval
ii. The utilization parameter
iii. The probability that the queuing system is idle
iv. The average time that the tailor is free on an 10 hour working day
BTL1 Knowledge
2. Past records indicated that of the five machine that a factory owns,
breakdown occurs at random and the average time between the breakdown
is 2 days .Assuming that the repairing capacity of the workman is one
machine a day and the repairing is distributed exponentially ,determine the
following
i. The probability that the service facility will be idle
ii. The probability of various numbers of machine (0 through 5)to be and
being repaired
iii. The excepted length of the queue
iv. The Excepted number of machine waiting to be and being repaired
v. The excepted time that a machine shall wait in the queue to be repaired.
vi. The excepted time that a machine will be in the system
BTL3 Application
3. A tax consulting firm has three counters in its office to receive people who
have problems concerning their income, wealth and sales taxes .On the
average 48 persons arrive in an 8 hour in a day. Each tax advisor spends 15
minutes on an average on an arrival. If the arrivals are poissonly distributed
and service times are according to exponential distribution. Find
i. The average number if customers in the system
ii. Average number of customers waiting to be srved
iii. Average time a customer spends in the systems
BTL4 Analysis
4. Let there be an automobile inspection situation with three inspection stalls.
Assume that cars wait in such a way that when a stall becomes vacant. The
car at the of the line pulls up to it. The station can accommodate almost four
cars waiting (seven in station) at one time. The arrival pattern is poisson
with a mean of one car every minute during the peak hours. The service
time is exponential with a mean 6 minutes. Find the average number of
customers in the system during the peak hours, the average waiting time
and the average number per hour that cannot enter the station because of
full capacity.
BTL6 Evaluation