paul learning_my pm notes
TRANSCRIPT
-
8/10/2019 Paul Learning_My PM Notes
1/32
How to study
1 Review Chapter Briefly
2 Create Chapter Outline (look up definitions w/page number)
3 Read Chapter Briefly (no notes)
4 Do some practice problems
5 Read chapter in depth and take notes
6 Re-do and do more practice problems7
04.21.13 Integrate
Make KAa connections,type notes, practice ITTOs and connections X
Read detailed ITTO list X
Read Outside Excel Notes Abhisheks version
Do practice questions
Look at Videos and take notes
Read PMBOK, Andy Crowe and Rita books
Go back and list highlighted notes
Practice Rita's process chart, formulas, and PMBOK chart
Do more practice questions
-
8/10/2019 Paul Learning_My PM Notes
2/32
Scope Time Cost Quality HR Comm Risk Procure
-
8/10/2019 Paul Learning_My PM Notes
3/32
INTEGRATION MANAGEMENT
Develop Project Charter (110/73)
Project Charter
Project Title and Description (What is the project)
Project Manager Assigned and Authority Level
Business Case
Resources PreassignedStakeholders
Stakeholder Requirements As Known
Product Description/Deliverables
Measurable Project Objective
Project Approval Requirements
High-Level Project Risks
Project Sponsors Authorizing This Project
Business Case (117/75)
Project Selection
1. Benefit measurement methods (Comparative approach)
Murder board (a panel of people who try to shoot down a new project idea)
Peer review
Scoring Models
Economic models for Project Selection
Present value (PV)
Net present value (NPV)
Internal rate of return (IRR)
Payback period
Cost benefit analysis
2. Constrained optimization methods (Mathematical approach)
Linear programmingInteger programming
Dynamic programming
Multi-objective programming
Economic Value Added (EVA)
Opportunity Cost
Sunk Costs
Law of Diminishing Returns
Working Capital
Depreciation
1. Straight Line Depreciation
2. Accelerated Depreciation
Constraints and Assumptions
Project Statement of Work (SOW) (123/75)
Charters with Work Under Contract
Enterprise Environmental Factors (123/14)
Project Management Information System (PMIS)
Organizational Process Assets (123/32)
Processes, Procedures, and Policies
Corporate Knowledge Base
-
8/10/2019 Paul Learning_My PM Notes
4/32
Historical Information
Lessons Learned
Develop Project Management Plan (124/78)
Management Plans
Project Management Plan
Baselines (Performance Measurement Baseline)
Requirements Management PlanChange Management Plan
Change Control System
Configuration Management Plan
Configuration management System
Process Improvement Plan
Project Documents (129/350)
Project Management Plan Approval
Kickoff Meeting
Direct and Manage Project Execution (130/83)
Monitor and Control Project Work (131/89)
Work Authorization System
Change Requests (132/92)
Corrective Action (132/92)
Preventive Action (134/92)
Defect Repair (135/92)
Perform Integrated Change Control (135/93)
Change Control Board (136/98)
Process for Making Changes (high level)
1. Evaluate the impact
2. Create options
3. Get the change request approved internally4. Get customer buy-in (if required)
Detailed Process for Making Changes
1. Prevent the root cause of changes
2. Identify change
3. Look at the impact of the change
4. Create a change request
5. Perform integrated change control
a. Assess the change
b. Look for options
c. The change is approved or rejected
d. Update the status of the change in the change control system
6. Adjust the project management plan, project documents, and baselines
7. Manage stakeholders' expectations by communicating the change to stakeholders
affected by the change
8. Manage the project to the revised project management plan and project
documents
Close Project or Phase (140/99)
Notes for overall trends within KA
-
8/10/2019 Paul Learning_My PM Notes
5/32
Project Charteris an input into Develop Project Management Plan (Planning).
OPAs andEEFsare inputs into every IM KA, except EEFs are not in project closure
Project Management planbecomes an input into all Execution, M&C, and Closing
Processes
Project management plan updates andproject document updates are both outputs
found in all the Execution and M&C process groups
Approved Change request is an input into Execution, Change requestsare outputs
for Execution and M&C project work, but change requestsare inputs to PICC and
change request status updates is an output in PICC
Deliverablesare unique outputs for Execution, accepted deliverablesare input into
Closing and the final product, service or resulttransitionis an output in Closing
Work Performance Info (WPI)is an output in Execution and an Input into PICC
Expert judgementis a TT for all processes
PMISis a TT for Executioon
Chaange Control meetingsis a TT for PICC
Business Case, Project SOW, Contractare unique inputs into Develop Project
Charters
plan?
-
8/10/2019 Paul Learning_My PM Notes
6/32
Performance reportsare unique inputs into Monitor and control project work?
DMPE outpus Change requestsand WPIwhich become inputs into PICC, then
approved changed requests from PICC are input into DMPE
-
8/10/2019 Paul Learning_My PM Notes
7/32
Notes on individual KA processes
-
8/10/2019 Paul Learning_My PM Notes
8/32
Definitions for Process Group
-
8/10/2019 Paul Learning_My PM Notes
9/32
Develop Project CharterThe process of developing a document that formally
authorizes a project or a phase and documenting initial requirements that satisfy the
stakeholders needs and expectations.
Develop Project Management PlanThe process of documenting the actionsnecessary to define, prepare, integrate, and coordinate all subsidiary plans.
Direct and Manage Project ExecutionThe process of performing the work defined
in the project management plan to achieve the projects objectives.
Monitor and Control Project WorkThe process of tracking, reviewing, and
regulating the progress to meet the performance objectives defined in the project
management plan.
Perform Integrated Change ControlThe process of reviewing all change requests,
approving changes, and managing changes to the deliverables, organizational
process assets, project documents, and project management plan.
Close Project or PhaseThe process of finalizing all activities across all of the Project
Management Process Groups to formally complete the project or phase.
-
8/10/2019 Paul Learning_My PM Notes
10/32
-
8/10/2019 Paul Learning_My PM Notes
11/32
Notes from Practice Problems in Rita
-
8/10/2019 Paul Learning_My PM Notes
12/32
Definition of ITTOS
-
8/10/2019 Paul Learning_My PM Notes
13/32
Project Charter [Output/Input]. A document issued by the project initiator or sponsor that formally authorizes
the existence of a project, and provides the project manager with the authority to apply organizational resources
to project activities
Organizational Process Assets [Output/Input]. Any or all process related assets, from any or all of the
organizations involved in the project that are or can be used to influence the projects success. These process
assets include formal and informal plans, policies, procedures, and guidelines. The process assets also includethe organizations knowledge bases such as lessons learned and historical information.
Enterprise Environmental Factors [Output/Input]. Any or all external environmental factors and internal
organizational environmental factors that surround or influence the projects success. These factors are from any
or all of the enterprises involved in the project, and include organizational culture and structure, infrastructure,
existing resources, commercial databases, market conditions, and project management software
Project Management Plan [Output/Input]. A formal, approved document that defines how the project is
executed, monitored, and controlled. It may be a summary or detailed and may be composed of one or more
subsidiary management plans and other planning documents.
Approved Change Request [Output/Input]. A change request that has been processed through the integrated
change control process and approved.
Change Request. Requests to expand or reduce the project scope, modify policies, processes, plans, or
procedures, modify costs or budgets, or revise schedules.
now status of the processes from each knowledge area. It refers to what work has been completed, or how
much time has been elapsed, or the cost incurred, etc. It provides us information about the current status of the
project deliverables. This information is utilized in the creation of the Work Performance Measurements (WPM)
and the Performance Reporting.
Performance Reports [Output/Input].Documents and presentations that provide organized and summarizedwork performance information, earned value management parameters and calculations, and analyses of project
and approving
or rejecting those change requests. The roles and responsibilities of these boards are clearly defined and are
agreed upon by appropriate stakeholders. All change control board decisions are documented and
communicated to the stakeholders for information and follow-up actions
The business case or similar document provides the necessary information from a business standpoint to
determine whether or not the project is worth the required investment. Typically the business need and the cost-
benefit analysis are contained in the business case to justify the project. The requesting organization or
customer, in the case of external projects, may write the business case
The statement of work (SOW)is a narrative description of products or services to be delivered by the project.For internal projects, the project initiator or sponsor provides the statement of work based on business needs,
product, or service requirements. For external projects, the statement of work can be received from the
customer as part of a bid document, for example, request for proposal, request for information, request for bid,
Contract A contract is an input if the project is being done for an external customer.
-
8/10/2019 Paul Learning_My PM Notes
14/32
through 12 are integrated
to create the project management plan. Any baselines and subsidiary management plans that are an output
from other planning processes are inputs to this process. In addition, updates to these documents can
necessitate updates to the project management plan.
-
8/10/2019 Paul Learning_My PM Notes
15/32
-
8/10/2019 Paul Learning_My PM Notes
16/32
Notes for overall trends Outside KA
-
8/10/2019 Paul Learning_My PM Notes
17/32
-
8/10/2019 Paul Learning_My PM Notes
18/32
Notes for overall trends within KA Notes for overall trends within KA Definitions for Process Group
Project Charteris an input into Develop Project
Management Plan (Planning). Expert judgementis a TT for all processes
Develop Project CharterThe process of
developing a document that formally
authorizes a project or a phase anddocumenting initial requirements that satisfy
the stakeholders needs and expectations.
Project
issued b
formally
and provauthorit
project a
OPAs andEEFsare inputs into every IM KA,except EEFs are not in project closure PMISis a TT for Executioon
Develop Project Management PlanThe
process of documenting the actions necessary
to define, prepare, integrate, and coordinateall subsidiary plans.
Organiz
[Output
assets, f
involved
to influe
process
plans, po
process
knowledhistorica
Project Management planbecomes an input
into all Execution, M&C, and Closing Processes Chaange Control meetingsis a TT for PICC
Direct and Manage Project ExecutionThe
process of performing the work defined in the
project management plan to achieve the
projects objectives.
Enterpri
[Output
environ
organiza
surroun
These fa
enterpri
organiza
infrastru
databas
manage
Project management plan updates andproject
document updates are both outputs found in
all the Execution and M&C process groups
Business Case, Project SOW, Contractare
unique inputs into Develop Project Charters
Monitor and Control Project WorkThe
process of tracking, reviewing, and regulating
the progress to meet the performance
objectives defined in the project management
plan.
Project
A forma
how the
controll
and may
subsidia
planning
Approved Change request is an input into
Execution, Change requestsare outputs for
Execution and M&C project work, but change
requestsare inputs to PICC and change
request status updates is an output in PICC
Outputs from planning processesare unique
inputs in Develop project Management plan?
Perform Integrated Change ControlThe
process of reviewing all change requests,
approving changes, and managing changes
to the deliverables, organizational process
assets, project documents, and project
management plan.
Approve
change r
through
and app
-
8/10/2019 Paul Learning_My PM Notes
19/32
Work Performance Info (WPI)is an output in
Execution and an Input into PICC
DMPE outpus Change requestsand WPIwhich
become inputs into PICC, then approved
changed requests from PICC are input into
DMPE
Work Pe
raw data
that it is
from ea
work hahas bee
provides
status o
informa
Work Pe
the Perf
-
8/10/2019 Paul Learning_My PM Notes
20/32
Definition of ITTOS Notes for overall trends Outside KA
Performance Reports [Output/Input].
Documents and presentations that provide
organized and summarized work performance
information, earned value managementparameters and calculations, and analyses of
project work progress and status.
Develop Project Charteris an input into an
input into Scope KA (Collect Requirements &Define Scope) and Communication KA (Identify
Stakeholders).
Change Control meetings. A change control
board is responsible for meeting and reviewing
the change requests and approving
or rejecting those change requests. The roles
and responsibilities of these boards are clearly
defined and are agreed upon by appropriate
stakeholders. All change control board
decisions are documented and communicated
to the stakeholders for information and follow-up actions
Several management plans and documents
(from all KA's), baselines (scope, cost,
schedule) are input to create the Project
Management Plan[plan, define, collect,
develop, create]. The project management
planis an input for verify scope(s), control
(scope, schedule, cost), PQA, PQC, team(3) *,
DI, MSE. PMP Updatesare inputs for reporting
performance, monitor and control risks, andprocurement processes.
The business case or similar document
provides the necessary information from a
business standpoint to determine whether or
not the project is worth the required
investment. Typically the business need and
the cost-benefit analysis are contained in the
business case to justify the project. The
requesting organization or customer, in the
case of external projects, may write the
business case
Project doc updates are inputs for project
docs from DMPE.Deliverables from DMPEare
inputs into PQC, and WPIfrom DMPEare
inputs into control processes, quality
assurance, M&C risks, admin procurements
The statement of work (SOW)is a narrative
description of products or services to be
delivered by the project. For internal projects,
the project initiator or sponsor provides the
statement of work based on business needs,
product, or service requirements. For external
projects, the statement of work can be
received from the customer as part of a bid
document, for example, request for proposal,
request for information, request for bid, or as
part of a contract
Performance reports from the Report
Performance process are inputs into MCPW
and Project document updates from MCPW
become inputs into Project Documents
Contract A contract is an input if the project is
being done for an external customer.
The PMP was an input into several processes
dealing with verify scope(s), control (scope,
schedule, cost), PQA, PQC, MSE along with
PMP update was an input into M&C risks,
procurements (plan, conduct,admin). These
processes become inputs into PICC. And PICC
project doc updates is an input into project
documents, and change requests status
updates from PICCbecome inputs into PQC
and Administer procurements.
Outputs from Planning ProcessesOutputs
from many of the planning processes
-
8/10/2019 Paul Learning_My PM Notes
21/32
SCOPE MANAGEMENT
Product Scope (158/103)
Project Scope (158/103)
Scope Management Plan
The Scope Management Process
Collect Requirements (Planning) (160/105)
Reviewing Historical RecordsInterviewing
Focus Groups
Facilitated Workshops
Brainstorming
Nominal Group Technique
Delphi Technique
Mind Maps
Affinity Diagrams
Questionnaires and Surveys
Observations
Prototypes
Group Decision-Making
Requirements Documentation
Balancing Stakeholders' Requirements
Resolving Competing Requirements
Requirements Management Plan
Requirements Traceability Matrix
Define Scope (Planning) (167/112)
Product Analysis
Project Scope Statement
Create Work Breakdown Structure (WBS) (Planning) (168/116)WBS Dictionary
Scope Baseline
Verify Scope (Monitoring and Controlling) (176/123)
Control Scope (Monitoring and Controlling) (178/125)
-
8/10/2019 Paul Learning_My PM Notes
22/32
TIME MANAGEMENT
Schedule Management Plan (192/130)
Define Activities (Planning) (193/133)
Milestones
Sequence Activities (Planning) (194/136)
Methods to Draw Network Diagrams
Precedence Diagramming Method (PDM) or Activity-on-Node (AON)Finish-to-start (FS)
Start-to-start (SS)
Finish-to-finish (FF)
Start-to-finish (SF)
Graphical Evaluation and Review Technique (GERT)
Types of Dependencies
Mandatory Dependency (Hard Logic)
Discretionary Dependency (Preferred, Preferential, or Soft Logic)
External Dependency
Leads and Lags
Things About Estimating to Know for the Exam
Estimate Activity Resources (Planning) (198/141)
Estimate Activity Durations (Planning) (200/146)
How is Estimating Done?
One-Point Estimating
Analogous Estimating (Top-down)
Parametric Estimating
1. Regression analysis (scatter diagram)
2. Learning curve
Heuristics
Three-Point Estimating (PERT analysis, Program Evaluation and Review Technique)Reserve Analysis
Develop Schedule (Planning) (207/152)
Schedule Network Analysis
* Critical path method
* Schedule compression
* What-if scenario analysis
* Resource leveling
* Critical chain method
Critical Path Method*
Critical Path Method
Near-Critical Path
Float (Slack)
Total Float (slack)
Free Float (slack)
Project float (slack)
Using the Critical Path Method
Schedule compression*
Fast Tracking
Crashing
-
8/10/2019 Paul Learning_My PM Notes
23/32
What-if scenario analysis*
Monte Carlo Analysis
Resource leveling*
Critical chain method*
Project Schedule
Milestone Charts
Bar Charts (also called Gantt Charts)Understanding the Benefits of Different Formats
Schedule Baseline
Control Schedule (Monitoring and Controlling) (228/160)
Reestimating
-
8/10/2019 Paul Learning_My PM Notes
24/32
-
8/10/2019 Paul Learning_My PM Notes
25/32
Planned Value (PV)= As of Today,what is the estimatedvalue of the work plannedto be done?
Earned Value(EV) = As of Today,What is the estimatedvalue of the workactually accomplished?
Actual Cost (Total cost)(AC) = As of Today,what is the actualcost incurred for the workaccomplished?
Budget at Completion (the budget)(BAC)= How much did we BUDGETfor the TOTALproject effort?
EstimateatCompletion(EAC)= What do we currentlyexpectthe TOTALproject to cost (a forecast)?
EstimatetoComplete (ETC) = From this point on, how much MOREdo we expectit to cost to finishthe project
(a forecast)
VarianceatCompletion(VAC)= As of today,how much over or underbudget do we expect to be at the end of
the
project?
-
8/10/2019 Paul Learning_My PM Notes
26/32
-
8/10/2019 Paul Learning_My PM Notes
27/32
Earned
Value
C-E-A
S-E-P
E-A-C
1. CV = EV - AC
2. ETC = EAC - AC
3. VAC = BAC - EAC
4. CPI = EV / AC
5.
TCPI = (BAC -EV)/
(BAC -AC)
6. EAC = AC + Bottom UP ETC
7. EAC = AC +(BAC -EV)
8.
EAC = AC + (BAC-EV) /
(CPI x SPI)
9. EAC = BAC/CPI
10. SV = EV - PV
11. SPI = EV / PV
-
8/10/2019 Paul Learning_My PM Notes
28/32
-
8/10/2019 Paul Learning_My PM Notes
29/32
Cost Variance= Earned Value - Actual Cost
Estimate to Complete= Estimate at completion - Actual Cost
Variance at Completion= Budget at Completion -Estimate at Completion
Cost Performance Index= Earned Value / Actual Cost
To Complete Performance Index= (Budget at Completion - Earned Value)/(Budget atCompletion - Actual Cost)
Estimate at Completion= Actual Cost + Bottom up Estimate to Complete
Estimate at Completion= Actual Cost + (Budget at Completion - Earned Value)
Estimate at Completion= Actual Cost + (Budget at Completion - Earned Value) / (Cost
Performance Index x Schedule Performance Index)
Estimate at Completion= Budget at Completion / Cost Performance Index
Schedule Variance= Earned Value - Planned Value
Schedule Performance Index= Earned Value / Planned Value
-
8/10/2019 Paul Learning_My PM Notes
30/32
-
8/10/2019 Paul Learning_My PM Notes
31/32
As of today, what is the difference in the estimated value of the work actually accomplished and the actual cost
of the work actually accomplished? NEGATIVE is over budget; POSITIVE is under budget.
As of today, what is the difference in the currently expected cost of the total project and the actual cost of work
accomplished? How much MORE do we expect the project to cost to finish?
As of today, what is the difference in the Budget for the total project and the currently expected cost of the
total project?How much over and under budget will we be at the end of the project?
We are getting an estimated value of actual work accomplished out of this amount of actual cost for work
accomplished. Funds are or are not being used efficiently. CPI>1 good CPI
-
8/10/2019 Paul Learning_My PM Notes
32/32
H