parallel runway design and construction at cancún ... · sat in cancún area - 3 days @ 3 km/hr...

57
g Parallel Runway Design and Construction at Cancún International Airport, Mexico George Nowak, P.Eng. SWIFT Conference, Montreal September 17, 2015

Upload: others

Post on 23-May-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

Parallel Runway Design and Construction at Cancún International Airport, Mexico

George Nowak, P.Eng.

SWIFT Conference, Montreal

September 17, 2015

Page 2: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gPresentation Outline

Cancún and New Runway Geometry

Runway Elevation and Drainage Criteria

Surface and Subsurface Conditions

Runway Subgrade (Cenote) Repair

Runway Pavement Design

Embankment Fill and Construction

Runway Construction and Completion Photos

Page 3: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

Cancún and New Runway Geometry

Page 4: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

Mexico

Quintana Roo

Cancún

CUN:

Over 18 million Pax

Projected in 2015

15% Annual Growth

City: 700,000+

Page 5: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gCancún and Airport Location

Hotel Zone

City

Airport

Page 6: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gNew Runway 12L-30R and X-over Twy

12L

30R

4660 ft

Page 7: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gRunway Length Analysis : 9200ft (2800m)

Cancún

Page 8: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gNew Runway Geometry

- ICAO Aerodrome Standards (DGAC Mexico)

T3T2

11,483 ft (3,550m)

9,186 ft (2,800 m)

Page 9: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

Taxiway FBridge

23 ft (7 m) fillMax 1.5% slope

Page 10: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

Runway Elevation and Drainage Criteria

Page 11: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gDesign Storm

/ Runway Design Elevation

Wilma - Category 5

Mexico hit on Oct. 21, 2005

Sat in Cancún area - 3 Days @

3 km/hr

24-63” (600-1600 mm) rainfall

Design Elevation of 4.26m ASL

– no flooding on existing

runway

Ground elevation varies from

1.2 to 5.8 m ASL in runway

area

Cancún

Eye over Cozumel

Page 12: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gRunway/Taxiway Drainage Design

No Stormwater Piping except to drain confined pavement areas

No Ditches – water table usually at +0.5m to +1.0m ASL

Cancún Aquifer provides drinking water to surrounding areas and City

Drainage (infiltration) Wells drain into Cancun Aquifer – need more drainage?- then add some more wells

Drainage wells typically 30m deep with infiltration rates about 285 gallons/min (18 liters/sec)

Page 13: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

Surface and Subsurface Conditions

Page 14: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gClearing and Residual Topsoil

Page 15: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gRunway Strip After Clearing

Page 16: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gGeotechnical Profile

Airport Geology

– Limestone coral Basement Rock (>1200m)

– Karst Development (Sinkholes = “Cenotes” )

– Deposits of weathered limestone/coral (Locally called “Sascab”)

– Limited Topsoil and Fill

Page 17: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gTypical Rock Core

Page 18: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gSinkholes (Cenotes)

Page 19: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gCenote Mapping and Repair

Three Basic Types

– Open Basin

– Deeper Cavern

– Hidden

Mapping Done by Client after clearing and topsoil removal – 134 found in Runway and Taxiway Areas

Repair Techniques by Client – perfected during Terminal 3 apron construction

Page 20: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gRisk Assessment

Page 21: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gLargest Basin Cenote

– 43 ft. (13m) dia.

Fish – cenotes interconnected

Page 22: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gCavern Type Cenote in Rwy Area

Page 23: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gHidden Cenotes – How Big?

12”

Page 24: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

Drill perimeter to delineate and excavate– achieving one metre rock face depth

Page 25: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

Runway Subgrade (Cenote) Repair

Page 26: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gTypical Cenote Repair Technique

Page 27: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gCenote manual cleaning

Page 28: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gLean concrete to seal rock fill and cenote perimeter water channels

Page 29: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gCenote Backfill to Subgrade Level

Page 30: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gWhat about the “Unmapped” Cenotes?

How to find hidden caverns with NO surface indication?

Tried geophysics (electrical resistivity) on T3 apron – very poor correlation.

Page 31: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gProofrolling with

50 Ton 4-Wheel Roller

Page 32: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gRunway Subgrade after

Cenote Repairs

246 ft (75m)

Page 33: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

Pavement and Embankment Design

Page 34: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gPavement Design

Flexible Design only considered as per contract (existing runway is flexible)

Compared FAA (LEDFAA 1.3) and FAARFIELD(beta version at the time) and Transport Canada methods

24 pavement sections considered in analysis (variations on arr/dep traffic and minimum thicknesses)

Use T3 apron “Sascab” k and CBR values (lowest CBR is 35+ and plate load tests show conservative k of 87 MN/m3 (320 pci))

Note: Software does not accept more than 30 for CBR Subgrade input

Page 35: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gRunway/Taxiway Pavement Layers

5” (125 mm) HMA

6” (150 mm) CTB (4” calculated)

6” (150 mm) Crushed Granular Base (4” calculated)

100% Modified Proctor Compaction 40” (1000 mm) below finished surface

95% Modified Proctor Compaction below 40”

Subgrade Formation CBR 35% (28.5% used)

Expected service life 40 years on structure (CDF) = remaining 40 years of 50 year concession.

Page 36: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gRunway/Taxiway

Earthwork Quantities

“Fill” project – 95% Fill/ 5% Cut based on design elevation/drainage criteria

Imported “rock” and “Sascab” fill from local quarries

Approximately 1.4 million C.Y. earthworks

Page 37: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gTypical Runway Fill Section

Sascab

“Rock” Fill/Sascab

Page 38: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

Embankment Fill Properties and Construction

(Sascab and Rockfill)

Page 39: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gWhat is “Sascab”?

Decomposed limestone (from freshwater migration and deposition of fine CaCO3 )

Light brown silty sand or sandy silt and gravel that is highly cementitious in its natural state

Used historically by Mayans (200-900 AD) as mortar and now as building and paving material (engineered fill) due to cementitious properties when re-compacted

Page 40: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gNatural Sascab on Site

Page 41: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gSascab “Fill” Quarry Face

Face Excavated with Front-end Loader

Page 42: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gTypical Sascab

Engineering Properties

LAB CBR

Page 43: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gField CBR –

Truck gets elevated!

Page 44: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

“Rockfill” Breakdownand Compaction

Page 45: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

g

Runway Embankment Completion

Page 46: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gNew Runway/Taxiway April/2008

Page 47: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gTaxiway F/Links to T3 Apron

Page 48: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gInfiltration Wells

Rapid Exit

Runway

Page 49: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gRunway/Rapid-Exit/Taxiway F

Page 50: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gNorth Bridge Abutment

and Taxiway F

Page 51: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gRunway 30R Approach – July 2008

Page 52: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gCTB Construction

Page 53: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gCrossover Taxiway and Bridge

Page 54: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gExisting/New Rwy and New ATCT

Page 55: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gRunway Open – October 20, 2009

Page 56: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gCancún 2015

Page 57: Parallel Runway Design and Construction at Cancún ... · Sat in Cancún area - 3 Days @ 3 km/hr 24-63” (600-1600 mm) rainfall Design Elevation of 4.26m ASL –no flooding on existing

gThank You!