panel 4 - 3 - risk-informed decision making approach for - nrc

14
Risk-Informed Decision Making Approach for Inflow Design Flood Selection and Accomodation for Dams Jason Hedien MWH January 30, 2013 RAC Engineers &Economists

Upload: others

Post on 09-Feb-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Risk-Informed Decision Making Approach for Inflow Design Flood Selection

and Accomodation for Dams

Jason Hedien MWH

January 30, 2013

RAC Engineers &Economists

RIDM for IDF Selection for Dams

• Presentation Outline

1. Background & Introduction 2. Context and Scope 3. Risk Assessment 4. Decisions Made (RIDM)

1. Background and Introduction

– Two run-of-river dams • Inflow = Outflow • No flood storage in reservoirs • Dams in series on same river

– Constructed for hydropower – Located in rural Midwest – Classified as high-hazard – Regulated by FERC – Existing dams would be

overtopped by PMF – Need to accommodate IDF – RIDM approach utilized

Presenter
Presentation Notes
Owner dam safety program: O&M program Surveillance and monitoring plan (instrumentation and inspections) Active and updated emergency action plans (EAP)

2. Context and Scope

• Context of Risk Assessment – Significant percentage of

population at risk around lakes – Flooding of dwellings around

lakes occurs with small increases in lake levels

– Significant difference in winter and summer populations

– Significant difference in winter and summer flood hydrographs

– Population impacted by floods before overtopping of dams

– Well functioning EAP

Presenter
Presentation Notes
Current capacity < PMF for warm and cold seasons

2. Context and Scope

• Scope of Risk Assessment

– Assess baseline risks (risks with dams in existing condition) (BRA)

– Identify risk reduction measures – Assess risk reduction measures (RRA) – Evaluate risk reduction measures relative to FERC IDF

definition

3. Risk Assessment

– Potential Failure Modes Analysis (PFMA) • Per FERC guidelines • Credible and Significant PFMs included in RA

– Flood-related – Focused on overtopping and erosion of embankments at dams

– Risk Assessment Workshop • Same participants as PFMA • Develop event tree & system response probabilities (SRP’s)

– Including a range of uncertainty – Spillway gate reliability and spillway plugging with debris

3. Risk Assessment

• Event Trees

.

.

.

AEP n -1 - A EP n

> AE P n

Spillway Clear

No Failure

Erosion exposes Shallow Section Core wall more than 15 ft deep

.

.

.

1. Annual Exceedance Probability

AEP 1 - A EP 2

AEP 2 - A EP 3

3. Spillway Clear / Plugged

Peak Reservoir Elevation

4. Peak Reservoir Elevation

2. Number of Spillway Gates Failing to Open

No Spillway Gate Fails

.

.

.

1 Gate Fails to open

5. Overtopping Erosion and Dam Failure

6. Core Wall Topples and Upstream Section Erodes and Location of Failure

30 ft wide

Erosion exposes Maximum Section Core wall more than 20 ft deep

Legend Expanded Chance Node Collapsed Chance Node Consequences Node

60 ft wide

90 ft wide

Spillway plugging - Case 1

Spillway plugging - Case 2

Insufficient Erosion

Overtopping Erosion

7. Initial Width of Core Wall Breach - Extent of Failure

8. Peak Discharge

No Failure Peak Discharge

Peak Discharge

Peak Discharge

Peak Discharge

Breach through Right Abutment

No Failure

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

0 0.5 1 1.5 2 2.5 3 3.5 4

Peak O vertopping Depth (ft)

Col

d &

War

m S

easo

n Pr

obab

ility

of C

orew

all F

ailu

re -

WIT

HO

UT

REB

AR

#1 #3 #4 #2 #5 Average

3. Risk Assessment

• System Response Probabilities

Individual & Group Estimates

3. Risk Assessment

• Estimating Consequences – Breach inundation runs – Affected structures – Population at risk – Life loss (LIFESim methodology by

Aboelata and Bowles)

Season

Peak Discharge at Norway (cfs)

Width of the first breach

(feet)Depth of

breaches (feet)Case (new numbering)

No failure No failure NF130 20 NF2

120 20 NF330 15 NF4

120 15 NF5R. Embkmt. F 8.3 NF6

No failure No failure NF730 20 NF8

120 20 NF930 15 NF10

120 15 NF11R. Embkmt. F 8.3 NF12

No failure No failure NF1330 20 NF14

120 20 NF1530 15 NF16

120 15 NF17R. Embkmt. F 8.3 NF18

No failure No failure NF1930 20 NF20

120 20 NF2130 15 NF22

120 15 NF23R. Embkmt. F 8.3 NF24

No failure No failure NF2530 20 NF26

120 20 NF2730 15 NF28

120 15 NF29R. Embkmt. F 8.3 NF30

No failure No failure NF3130 20 NF32

120 20 NF3330 15 NF34

120 15 NF35R. Embkmt. F 8.3 NF36

No failure No failure NF3730 20 NF38

120 20 NF3930 15 NF40

120 15 NF41R. Embkmt. F 8.3 NF42

No failure No failure NF4330 20 NF44

120 20 NF4530 15 NF46

120 15 NF47R. Embkmt. F 8.3 NF48

39000

51000

War

m

39000

51000

Col

d

70000

90000

227600(PMF)

58200(PMF)

Flood Zone Rate of Life Loss (Range)

Rate of Life Loss (Average)

Safe 0 - <1% 0.02%

Compromised 0 – 50% 12%

Chance 50 – 100% 91.45%

3. Risk Assessment

• Tolerable Risks 1. F-N Charts (ANCOLD & HSE) 2. f-N Charts (Reclamation) 3. Summary Tables Rating Code Explanation

N-StrongL&S Strong justification for long- and short-term risk reduction measures

N Strong justification for long-term risk reduction measures

Y-ALARP? Diminished justification for long-term risk reduction measures, but ALARP (as low as reasonably practicable) still needs to be evaluated

Y Meets tolerable risk guideline and meets ALARP

3. Risk Assessment

• Risk Reduction Assessment – Improve warning & evacuation effectiveness (not explicitly

evaluated, but measures being implemented anyway) – Remove dams (not feasible) – Land acquisition (not feasible) – Improve gate reliability (not explicitly evaluated) – Trash/debris booms (not explicitly evaluated) – Raise embankment dams (not considered further) – Re-evaluate East Dam at Dam B to determine whether stability

improvements are needed – Add additional spillway capacity – Armor embankments – Do nothing (baseline case) – Appropriate changes to event tree inputs to represent each

alternative

Dam A Summary of Annual Probabilities of Failure

Alternative:

Description:

Discharge

(cfs):

Estimated Total Annual Probability of Failure

Baseline Case:

No Blockage &

100% Gate Reliability:

A Do nothing 39,000 1 in 700 1 in 1,300

B Provide functional flashboards on overflow spillway 43,700 1 in 1,400 1 in 2,800

C.0 Lower overflow spillway crest and add gates to pass additional flow over the overflow spillway

75,500 1 in 41,800 1 in 62,300

C.1 Lower overflow spillway crest and add gates 53,000 1 in 5,400 1 in 10,500

C.1R Same as C.1, but includes contribution of trash gate to overall discharge.

57,000 1 in 8,200 1 in 14,500

C.2 Lower overflow spillway crest and add gates 60,000 1 in 11,700 1 in 18,500

D Add gated spillway on left embankment and lower overflow spillway crest (maximize capacity through Dam A).

100,600 1 in 181,000 Not computed

E Armor left embankment and right rim 39,000 1 in 8,000,000 Not computed

3. Risk Assessment

4. Decisions Made

– Selected alternatives a result of RIDM – Alternative C.2 at Dam A:

• 60,000 cfs capacity ~ 103% warm PMF/27% cold PMF – Alternative B.2 at Dam B

• 65,000 cfs capacity ~ 108% warm PMF/28% cold PMF – Meet all tolerable risk guidelines – Spillway capacity additions accepted by FERC – Very low cost effectiveness for reducing life loss for risk

reduction alternatives (ALARP satisfied) – Alternatives in design and construction phase

END