page 2 - npv
DESCRIPTION
net present value - calculation sheetTRANSCRIPT
-
dieveluasimenggunakanmetodeNetPresentValue(NPV)LS S
ALTERNATIFA ABPWB = AB (P/A,i,n) + LS (P/F,i,n) + S (P/F,i,n)
= 250 (P/A,10,15) + 200 (P/F,10,7) + 300 (F/P,10,15)= 250 7,6061 + 200 0,5132 + 300 0,2394 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15= 2075,985 Juta
I ACPWC = I + AC (P/A,i,n)
= 500 + 150 (P/A,10,15)= 500 + 150 7,6061= 1640,915 Juta
NPV = PWB PWC= 2075,985 1640,92= 435,07
karenanilaiNPVlebihbesardari1makaAlternatifALAYAK
LS SALTERNATIFB ABPWB = AB (P/A,i,n) + LS (P/F,i,n) + S (P/F,i,n)
= 350 (P/A,10,15) + 150 (P/F,10,5) + 100 (F/P,10,15)= 350 7,6061 + 150 0,6209 + 100 0,2394 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15= 2779,21 Juta
I ACPWC = I + AC (P/A,i,n)
= 250 + 200 (P/A,10,15)= 250 + 200 7,6061= 1771,22 Juta
NPV = PWB PWC= 2779,21 1771,22= 1007,99
karenanilaiNPVlebihbesardari1makaAlternatifBLAYAK
LS SALTERNATIFC ABPWB = AB (P/A,i,n) + LS (P/F,i,n) + S (P/F,i,n)
= 400 (P/A,10,15) + 150 (P/F,10,8) + 250 (F/P,10,15)= 400 7,6061 + 150 0,4665 + 250 0,2394 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15= 3172,265 Juta
I ACPWC = I + AC (P/A,i,n)
-
= 800 + 100 (P/A,10,15)= 800 + 100 7,6061= 1560,61 Juta
NPV = PWB PWC= 3172,265 1560,61= 1611,655
karenanilaiNPVlebihbesardari1makaAlternatifCLAYAK
LS SALTERNATIFD ABPWB = AB (P/A,i,n) + LS (P/F,i,n) + S (P/F,i,n)
= 450 (P/A,10,15) + 300 (P/F,10,4) + 250 (F/P,10,15)= 450 7,6061 + 300 0,683 + 250 0,2394 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15= 3687,495 Juta
I ACPWC = I + AC (P/A,i,n)
= 850 + 200 (P/A,10,15)= 850 + 200 7,6061= 2371,22 Juta
NPV = PWB PWC= 3687,495 2371,22= 1316,275
karenanilaiNPVlebihbesardari1makaAlternatifDLAYAK
LS SALTERNATIFE ABPWB = AB (P/A,i,n) + LS (P/F,i,n) + S (P/F,i,n)
= 200 (P/A,10,15) + 100 (P/F,10,6) + 200 (F/P,10,15)= 200 7,6061 + 100 0,5645 + 200 0,2394 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15= 1625,55 Juta
I ACPWC = I + AC (P/A,i,n)
= 250 + 150 (P/A,10,15)= 250 + 150 7,6061= 1390,915 Juta
NPV = PWB PWC= 1625,55 1390,92= 234,635
karenanilaiNPVlebihbesardari1makaAlternatifELAYAK