pacs ibdr 27/28 feb 2002 pacs cre1 pacs cre development ybe creten, patrick merken, jan putzeys, vic...

14
PACS CRE 1 PACS IBDR 27/28 Feb 2002 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

Upload: angelica-park

Post on 27-Dec-2015

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 1

PACS IBDR 27/28 Feb 2002

PACS CRE development

Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof

IMEC

Page 2: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 2

PACS IBDR 27/28 Feb 2002

Overview

• CRE and FEE design and design status• CRE/FEE Schedule and milestones• CRE and FEE Problems and possible solutions• PA/QA: AIV plan and activities• PA/QA: Key Inspection Points• Conclusions

Page 3: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 3

PACS IBDR 27/28 Feb 2002

CRE design and design status

• At IIDR:– CRE input stage in spec (in terms of gain/debiasing, noise

and power)

– smallest Cint not functional but solution identified

– linearity of output stage out of spec but solution identified on separate buffer

• QM CRE design iteration– CRE122000 linearity of output stage

– CRE032001 smallest Cint

– CRE102001 increased dynamic range

Page 4: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 4

PACS IBDR 27/28 Feb 2002

CRE design and design status (ctd)

• Status of CRE122000/CRE032001 – meet key CRE specifications:

• gain/debiasing, noise, power consumption

• linearity of output buffer

– do not meet• dynamic range (<2V, marginally

acceptable)• starting point of integration ramp

• smallest Cint linearity (“integrates”)

– results of IMEC confirmed by CSL

AVG slope @ 4K Vcascp = 3.0V Vcascn = 1.9V Outbias 10uA 4.1pF 2G/200mVExpected Slope : 1.3 V / 17 samples

2

2.5

3

3.5

4

4.5

5

0 5 10 15 20

0.00%

0.05%

0.10%

0.15%

0.20%

0.25%

Measured 02-10

lin trend

Non lin

Page 5: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 5

PACS IBDR 27/28 Feb 2002

CRE design and design status (ctd)

• Status of CRE102001:– in addition meets dynamic range requirement

– shows smallest Cint approaching linearity spec (absolute value tbc)

CRE032001 CRE102001

AC_ARRAY(10-2001) A1 Iin 0.02nA 0.1pF LvL 1.8V 4K

0.00

1.00

2.00

3.00

4.00

5.00

6.00

0 5 10 15 20

0.00%

0.50%

1.00%

1.50%

2.00%

2.50%

Page 6: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 6

PACS IBDR 27/28 Feb 2002

CRE Substrate design and design status

• QM_1 without shortcircuit resistors (baseline design)

• QM_2 model (featuring additional resistors)– Two production runs

• with BCB (adhesion deficient)• without BCB (_NB) to deliver sufficient assemblies

• QM_3 model made (to accommodate interface changes) – Available (no BCB version)

Page 7: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 7

PACS IBDR 27/28 Feb 2002

Harness Substrate design and design status

• Harness QM_1 (baseline design)• Harness QM_2 model (and QM_2NB without BCB)

• Harness QM_3 model in preparation = FM model additional reference lines and reduced (3) temperature

sensor connections ; FM harness substrates scheduled for April 2002

Page 8: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 8

PACS IBDR 27/28 Feb 2002

FEE status• Multiple FEE assemblies made

– QM_1 FEE delivered 6 July 2001 • 8 CRE082000 on QM_1 substrate delivered

– QM_2 FEE failed• 6 CRE032001 on QM_2 substrate shorted during bonding

– QM_2 FEE recovery• 3 CRE032001 on QM_2 substrate tested and delivered to MPE in November

2001• 3 CRE032001 on QM_2_NB substrate in stock (different R_mirror)• 13 CRE032001 on QM_2_NB assembled, tested and delivered to CSL

(December 2001)

– QM_3 FEE• 25 CRE102001 on QM_3 substrate (29 in process)• plan: phased assembly/test/delivery until Jan. 2002• 29 assembled in February 2002• Presently in test• Full delivery mid March 2002

Page 9: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 9

PACS IBDR 27/28 Feb 2002

Schedule and MilestonesID Task Name Duration Start Finish

1 Start project #### Fri 9/1/00 Fri 9/1/00

2 FEE QM (Phase I) #### Fri 9/1/00 Fri 9/28/01

3 Design FEE QM #### Fri 9/1/00 Tue 10/31/00

4 Manufacture FEE QM #### Tue 10/31/00 Sat 12/30/00

5 Evaluation/Test FEE QM #### Sat 12/30/00 Wed 2/28/01

6 First FEE QM available #### Wed 2/28/01 Wed 2/28/01

7 Redesign FEE QM #### Tue 10/31/00 Mon 1/29/01

8 Manufacture FEE QM #### Mon 1/29/01 Fri 3/30/01

9 Evaluation/Test FEE QM #### Fri 3/30/01 Tue 5/29/01

10 FEE QM available #### Tue 5/29/01 Tue 5/29/01

11 ECP: QM_2 substrate redesign #### Tue 5/29/01 Mon 9/3/01

12 Milestone after ECP1 #### Fri 9/28/01 Fri 9/28/01

13 Detector Test Feedback #### Wed 2/28/01 Tue 8/14/01

14 Review and Acceptance all Phase I deliverables#### Tue 8/14/01 Tue 8/14/01

15 FEE PFM (Phase II) / FM (Phase III) #### Wed 2/28/01 Fri 4/11/03

16 Design FEE PFM #### Wed 2/28/01 Tue 7/3/01

17 ECP2: circuit redesign #### Mon 6/25/01 Fri 9/28/01

18 Manufacture FEE PFM #### Fri 9/28/01 Fri 11/23/01

19 ECP2: QM_3 assembly and gradual delivery #### Sun 12/2/01 Fri 2/15/02

20 Evaluation/Test FEE PFM #### Fri 11/23/01 Sat 3/2/02

21 Review and Acceptance Phase II #### Sat 3/2/02 Sat 3/2/02

22 Milestone after ECP2 #### Fri 3/15/02 Fri 3/15/02

23 ECP3: Design FEE FM #### Thu 7/11/02 Tue 10/29/02

24 Manufacture/pretest FEE FM #### Tue 10/29/02 Thu 2/6/03

25 Pretest FEE FM #### Thu 2/6/03 Mon 4/7/03

26 FEE FM available #### Fri 4/11/03 Fri 4/11/03

27 Review and Acceptance Phase III #### Fri 4/11/03 Fri 4/11/03

28 FEE FS (Phase IV) #### Fri 4/11/03 Wed 10/8/03

29 Manufacture FEE FS #### Fri 4/11/03 Thu 7/10/03

30 FEE FS available #### Thu 7/10/03 Thu 7/10/03

31 Evaluation/Test FEE FS #### Thu 7/10/03 Wed 10/8/03

32 Review and Acceptance Phase IV #### Wed 10/8/03 Wed 10/8/03

9/1

2/28

5/29

9/28

8/14

3/2

3/15

4/11

4/11

7/10

10/8

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32001 2002 2003 2004

Delayed start date TBC

M1 met

M2 met

M3 met 12/2001

M4 moves to 03/2002

M5 moves to 04/2003

Page 10: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 10

PACS IBDR 27/28 Feb 2002

Schedule: Implications of FM delivery date

11/04/036/02/0329/10/0211/07/02

CREFM design

1 monthCRE

pretest

2 monthsFEE

assembly/test

today

• Counting back from FM delivery date

Answers needed to several questions !- absolute value Cint and background- Iout and Coutput adapation/redesign- latch-up tests on 12 modules- QM test results

06/01/03

FM tapeout

2 monthsCRE

production

Page 11: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 11

PACS IBDR 27/28 Feb 2002

(Possible+Encountered) Problems and possible solutions

Componentaffected

Problemdescription

Possible solutions

FEE Bond strength onunpassivated MCM

Al vs Au bond wiresDestructive test on additional modules

CRE Radiation tolerancetesting

- Gamma and protons tested at RT- Cryogenic irradiation setup in progress (testing at LLN

and ESTEC)- Indirect evidence: scaled technologies are more rad-

tolerant

CRE Absolute value ofCint

Design iteration if needed

CRE Parasitic Cpara atdetector input andInput leakage current

Known after detector integrationInput bond pad with reduced ESD

Page 12: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 12

PACS IBDR 27/28 Feb 2002

PA/QA: AIV and Test plan

• A general overview of the manufacturing of the FEE and Harness substrates: document PACS-IM-PL-001.

• Incoming inspection of parts and materials which are used during the manufacturing/assembly of the FEE and Harness substrates: document PACS-IM-PL-002.

• The assembly of the FEE substrates: document PACS-IM-PL-004 (draft).

• Verification of the performance of the FEE: document PACS-IM-PR-001.

• Critical items list: input provided

• FMECA: input provided

Page 13: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 13

PACS IBDR 27/28 Feb 2002

PA/QA: AIV and Key Inspection Points

• FEE: each FEE is tested at room temperature and at 4 Kelvin. This test will indicate any error in bonding, resistor value, electrical connectivity, etc.

• Harness substrate: Each harness substrate will be visually

inspected before packaging (‘packing’).

Visual inspection

Substratemanufacturing flow

Functional Tests

FEE assembly

Packing

IC manufacturingflow

Harness Substrate

Packing

KIP

KIP

Page 14: PACS IBDR 27/28 Feb 2002 PACS CRE1 PACS CRE development Ybe Creten, Patrick Merken, Jan Putzeys, Vic Fonderie, Chris Van Hoof IMEC

PACS CRE 14

PACS IBDR 27/28 Feb 2002

Conclusions• FEE deliveries

– 3 FEE on QM_2 delivered for detector tests

– 13 FEE on QM_2NB delivered for module tests

– 25 FEE on QM_3 delivery pending (assembled and partially tested/accepted)

• ‘Forced’ delay in start of FEE FM design. No ‘idle time’ due to this delay:– design/test:

• of QM FEE in sufficient detail

• for correction/change of Cint

– assembly/inspection: • destructive bond-strength testing on spare FEE modules

• ECP for modified CRE substrate and harness substrate

– verification: cryogenic radiation setup and testing

• AIV and test plans available