paart b
TRANSCRIPT
MBA Quality Management Project Part B
MGT 5534Team 1
Kelli BakerAJ DeCato
Mikel LozanoBrian RichardsonMadeline Russell
1
Table of Contents0.0 EXECUTIVE SUMMARY............................................................................................................3
1.0 INTRODUCTION.........................................................................................................................4
2.0 METHOD......................................................................................................................................62.1 DATA COLLECTION............................................................................................................................62.2 PARETO CHART.................................................................................................................................7
2.2.1 Pareto Chart Process................................................................................................................72.3 FISHBONE (ISHIKAWA) DIAGRAM......................................................................................................7
2.3.1 Fishbone Diagram Process.......................................................................................................72.4 BRAINSTORMING PROCESS.................................................................................................................82.5 TEAM 1 DEVELOPMENT......................................................................................................................8
3.0 RESULTS/RECOMMENDATIONS............................................................................................93.1 RESULTS............................................................................................................................................93.2 RECOMMENDATIONS........................................................................................................................10
4.0 CONCLUSION...........................................................................................................................114.1 PROJECT ACKNOWLEDGEMENT........................................................................................................114.2 RECOMMENDATION SOLUTION RECEIVED.......................................................................................114.3 PROCESS IMPLEMENTATION.............................................................................................................11
5.0 APPENDICES.............................................................................................................................12TABLE 1: CHECK SHEET 1......................................................................................................................12TABLE 2: CHECK SHEET 2.....................................................................................................................13TABLE 3: CHECK SHEET 3.....................................................................................................................14TABLE 4: NPS CHECK SHEET................................................................................................................15TABLE 5: TOTAL CHECK SHEET TALLY.................................................................................................16FIGURE 1: MLO CHECK SHEET PARETO CHART....................................................................................17FIGURE 2: FISHBONE DIAGRAM.............................................................................................................18
2
0.0 Executive Summary The Plan-Do-Check-Act (PDCA cycle) is a powerful quality tool used to help companies make
incremental process improvements. The PDCA cycle was used to help Idaho Central Credit
Union (ICCU) improve its online mortgage program. As the first half of the project focused on
the Plan portion of the PDCA cycle, the focus of the second half of the project will be on the Do-
Check-Act portions.
The planning phase developed a check sheet to determine what the largest issue the mortgage
program is facing. The cheek sheet was issued to the ICCU Internal Mortgage Loan Officers
(MLOs) for one month. The check sheets were then collected and the data was analyzed using a
Pareto Chart.
The Pareto Chart showed that members not understanding the timeline of the loan process was
the largest issue the MLOs faced. Given this information, Team 1 met with the MLOs again to
brainstorm the root cause. Team 1 used a fishbone diagram to facilitate this brainstorming
session. A fishbone diagram is a graphical representation of cause and effect. The MLOs then
ranked the possible causes, and the root cause was determined to be a lack of detailed and
upfront communications. From here several possible solutions were brainstormed and Team 1
made its recommendations:
ICCU should revise its checklist sent to members detailing the mortgage process.
ICCU should develop an internal checklist to prompt MLOs to use diverse
communication methods.
3
1.0 Introduction Every industry in the world is unique in that each possess its own unique culture, goals, and
collection of talents. However, one variable differentiates these industries from competitors and
allies alike, namely, their processes. A process can take on many different forms such as
procedure, method, practice or action, but, ultimately, its meaning boils down to one key aspect;
how operations are performed.
How does management treat employees? How do employees treat customers? How do
employees perform their work? These are just some of the concerns involved in an industry’s
process. Some organizations have a very inflexible process which take away employee freedom
in job performance by enforcing a strict set of rules and policies. Other organizations are far
more compassionate and implement incredibly favorable policies. Some policies include,
freedom in decision making, delegation of responsibilities, and even working harder than they
have to in order to make customers feel as though they are the most important person at that
time. ICCU is one of these organizations and Team 1, consisting of five graduate level students,
met with a team of ICCU MLOs, and their manager Ms. Lori Spanbauer, in an effort to take an
already incredible process and, potentially, make a great process even better.
During the first half of this project, Team 1 discussed with the Internal MLO team any issues
they were facing when dealing with their customers, online mortgage applicants, in order to gain
an understanding of ICCU’s process. A check sheet of the issues was created and delivered to the
MLOs which they then used to count how many times, within a month, those issues presented
themselves. This is where the second half of the project comes into play. The overall purpose of
this project is to create value for a company by helping them to understand the current issues,
4
within its process, and to understand the root cause of those issues. A series of quality tools
assisted in gaining this understanding.
One of these tools, as discussed in Part A of this project, is the PDCA cycle. The “planning”
phase took place during Part A, a plan was designed to assist ICCU to find its most frequent
issue. The remaining Do-Check-Act phases occurred within this part of the project. The “do”
phase of the cycle consisted of implementing the check sheet to the MLOs and allowing them to
collect data on the most recurring issue. The “check” phase of the cycle involved analyzing the
data collected by the MLOs in order to determine a trend in occurring processes. Finally, the
“act” phase of the cycle involved the brainstorming process, conducted with the MLOs and
Spanbauer, in order to determine the likely causes of the most frequent issue. In addition to the
PDCA cycle, the check sheet developed in Part A was issued to the MLOs and, using its
information, a Pareto Chart and fishbone diagram were created.
By utilizing these tools, an organization can gain an even deeper understanding of its issues and
can find ways to improve its process. However, Team 1 could only facilitate the discussion and
record information; the MLOs needed to discuss the effects of the issues in depth and analyze
possible causes on their own.
5
2.0 MethodDuring the “Do” phase of the PDCA cycle, Team 1 collected data from ICCU’s MLO team on
the frequency of issues. This data was used to create a Pareto chart to determine which issues are
causing most of the problem. Team 1 then focused on creating a fishbone diagram with the
MLOs in order to find possible root causes. An open communication methodology was used
throughout the process.
2.1 Data CollectionA check sheet of eight common concerns was formulated through Part A of the project. The
check sheet was issued to the four participating MLOs in direct contact with ICCU members.
They are also able to garner customer feedback through a Net Promoter Score (NPS), a phone
survey issued by an internal employee. The check sheet at Spanbauer’s desk was solely used for
the NPS feedback. The MLOs were informed that they would have the check sheet available for
one month and would be able to give a corresponding checkmark when an issue arose. Once a
week, Team 1 would ask the MLOs about the progress of the check sheets.
At the end of the 30 days Team 1 collected the check sheets. It was discovered that one of the
participants had lost his check sheet, believed to be accidentally thrown away a few weeks
before. If this would have been known, Team 1 could have supplied a new check sheet.
However, it was too late in the process so the information already collected would be used. The
amount of checks per participant varied in total from 2 to 31. Check sheets are shown in Tables 1
through 4.
6
2.2 Pareto ChartThe Pareto chart is a bar graph that visually depicts which situations are more significant. On
average a Pareto chart is useful to determine which problems or causes in a process needed to be
improved or investigated.
2.2.1 Pareto Chart ProcessThe Pareto chart was created to represent the data collected from the check sheets. A key aspect
of the Pareto chart is to show the largest set of responses which is the most important factor. The
process to create the Pareto Chart was through Excel. The check sheet issues and their
corresponding counts were shown as columns with the most frequent issues matching the largest
columns. Table 5 shows the variables entered into the Pareto chart, and the Pareto chart is
featured in Figure 1.
2.3 Fishbone Diagram A fishbone diagram identifies many possible causes for an effect or problem. It immediately
sorts ideas into useful and actionable categories.
2.3.1 Fishbone Diagram ProcessTo begin the process, Team 1 met with the MLOs. The Pareto chart determined that the most
frequent problem was that the member didn’t always understand the timeline of the process. This
was an effect listed on the fishbone diagram with a horizontal arrow pointing to it. Team 1
proceeded to create categories for possible causes shown as branches from the main arrow; the
outline resembled a fishbone (shown in Figure 2).
7
It was made clear to the MLOs that this was their time to brainstorm. During the open
brainstorming session, the MLOs came up with seven major categories of possible causes. Team
1 acted as facilitators throughout the process and asked some “why” questions to generate deeper
levels of causes. When the MLOs ran out of ideas, they were asked to assign points to their three
biggest causes. Their leading causes received five, three, and one point respectively. Each MLO
was able to assign points as they deemed fit.
2.4 Brainstorming ProcessAs mentioned, the initial brainstorming process for the development of the fishbone diagram
happened in a very open manner. In addition to this, the brainstorming process to discuss any
possible solutions was also very unguarded. Due to time constraints, Team 1 suggested that the
MLOs take a few hours, post fishbone diagram, to think about possible solutions, then would
meet again to brainstorm with the other MLOs.
2.5 Team 1 DevelopmentBy this time Team 1 felt comfortable with each other and was able to work entirely in the
performing phase of team development. Just as in Part A of the project, Team 1 met every
Monday night following class to discuss the project. Every member made it to all meetings with
the ICCU MLOs, however, only 1 member met with the MLOs on a weekly basis to minimize
any disruption. When it came time to write Part B, the sections were delegated to the person who
felt most comfortable in the section. The members of Team 1 have gained a strong understanding
of teamwork throughout the semester that can be carried on to other projects.
8
3.0 Results/Recommendations Throughout project Part B, Team 1 worked closely with ICCU’s MLOs in order to gain the best
possible results. Both teams understand that quality is important to achieve work that meets
organizational standards.
3.1 ResultsThe highest concern the MLOs were able to determine from the check sheet, was that the
members did not understanding the timeline of the overall loan process (see Table 5). This could
be attributed to many factors, however, from the fishbone diagram the leading cause was detailed
communication and expectations were not performed up front. Interestingly enough, the second
most frequent issue from the check sheet was members stating they had not received a copy of
the appraisal. This issue directly relates to the misunderstanding of the timeline as a whole as a
member had to wait for a document that they are supposed to receive.
ICCU is known for continuous improvement. This commitment has attributed to its overall
success through the years. Furthermore, members had been reporting not receiving their loan
documents in a timely manner before this quality project began. This practice had been more
widespread than simply the MLO member contact making ICCU select a new internal software
package that would handle document management differently, therefore, fixing this issue.
However, the program was not in the final selection stage until close to the end of this project.
While the document problem has been addressed, the largest issue is still the members not
understanding the timeline as a whole.
Through the construction of the fishbone diagram the MLOs highlighted the stem of the problem
at hand, the main proponent of the issue and any leading causes that could possibly contribute to
9
the problem. Figure 2 shows the entire fishbone diagram. Some of these issues include external
forces such as purchase contingencies, government restrictions such as tax implications and
TRID, and overall process understanding factors like jargon and uncommunicated delays. The
results of the fishbone diagram were mixed at first with no clear indication of the root cause.
However, a top reason eventually emerged when the MLOs assigned a point value system. The
top three causes remained after the points had been assigned from all MLOs and their manager.
Figure 2 represents all three causes and their respective votes.
3.2 RecommendationsDetailed communication and expectations upfront to the member was the root cause determined
by the MLO team. Currently the MLOs have a list in place to ensure each member understand
the necessary items and requirements of the process. This list is even sent to the member in an
email form to show what they will need and the general order of which things will happen. It is
recommended that this list be reviewed for accuracy against the average timeline for most
member loans. In addition, the MLO team should develop an internal checklist or form that
reminds them to notify the customer through multiple channels (ie. email, phone conversation,
letter) of the general timeline of the process based on the particular variables.
4.0 Conclusion Dr. Deming once said, “It is not enough to do your best; you must know what to do, and then do
your best.” ICCU is always looking for ways to continuously improve its process to better suit its
members and create fewer problems.
10
4.1 Project acknowledgement Overall the improvement project seemed to be well received by the MLOs at ICCU; there was
genuine excitement during the creation of the fishbone diagram. The end goal of a quality
improvement project is to improve customer satisfaction which will make the MLOs job easier.
The MLOs seem acutely aware of this fact, and as such they were very receptive to making a
process improvement. The quality improvement project provided strong evidence of
communication problems between the MLOs and the members of ICCU which was suspected
even before the project began.
4.2 Recommendation Solution Received The recommendations seem to be welcomed. Improving the existing checklist, the MLOs email
to members, seemed to be especially well received. It was actually close to a solution
brainstormed by the MLOs, to develop a letter that would explain in detail what the general
mortgage process and timeline is, as well as to develop more detailed letters for different type of
mortgages. Developing an internal checklist to help MLOs use diverse channels is essential to
improving communication. ICCU was quite receptive to developing this checklist.
4.3 Process Implementation Since ICCU has such a strong reputation for listening to employees and a high commitment to
customer service, the project’s recommendations will at least be taken into consideration. There
was also a great deal of enthusiasm for the project from Spanbauer. Given these facts, it is very
probable that most of the recommendations will be implemented to one degree or another.
11
5.0 AppendicesTable 1: Check sheet 1
12
Table 2: Check Sheet 2
13
Table 3: Check Sheet 3
14
Table 4: NPS Check Sheet
15
Table 5: Total Check Sheet TallyIssue Count
Member voiced concern about not understanding the timeline of the loan process. 14
Member stated that they have not received the appraisal 10
Member voiced concern about contact frequency during the loan process 7
Member confused about “Closing Costs” vs “Down Payment” 7
Member states it took too long to get contacted after the initial loan application 3
Member complained about receiving different information from other ICCU employees
3
Member voiced concern about not knowing the necessary information of loan process upfront.
1
Member expressed that they are not feeling value due to distance 1
16
Figure 1: MLO Check Sheet Pareto Chart
17
Figure 2: Fishbone Diagram
18