Infrastructure: Developing the Public-Private Partnership Model Where it Doesn’t Exist and Making it Work for You
Jay R. LindgrenJocelyn Knoll
2
In a time when state and local governments must balance shrinking revenue with deteriorating infrastructure, P3s have become a timely model for completing projects on time and on budget.
– A long-term performance-based contract between public sector and private sector to deliver public infrastructure
3
The Issue
• Not enough resources for current infrastructure needs– Increasing Spending Levels: How Much is
Enough?
• Changing demographics and market needs demand new infrastructure– Development Trends
– Diversity in America
4
Increasing Spending Levels: How Much Is Enough?
• Many groups claim that we are not spending enough. Comparisons of need differ based on what is being counted, but overall numbers are relatively consistent
American Society of Civil Engineers
Type $ billions annual spending
Roads 126
Bridges 9
Transit 21
Rail 13
Total 169
Note: Total government spending
American Association of State Highway and Transportation
Officials
Type $ billions annual spending
Highways 63
Transit 16
Freight 7
Intercity Passenger Rail
6
Total 91
Note: Federal government spending only
National Surface Transportation Revenue and Policy Study
Commission
Type $ billions annual spending
Highways & Bridges
130-166
Transit 14-18
Freight 5-7
Intercity Passenger Rail
7-9
Total 156-200
Note: Federal aid eligible roads only
5
Development TrendsUS Population 1900-2100
Source: All data from U.S. Bureau of the Census.Census Release NP-T1, "Annual Projections of the Total Resident Population as of JulyLowest, Middle, High Series: 1999 to 2100“,Population Estimates Program, Population Division, U.S. Census Bureau, Washington, D.C. 20233, February 14, 2000.
6
Diversity in AmericaDistribution of Households by Type: 1950 to 2000
7
New Demands: A More Urban Country
• Since 1956, we built 46,837 miles of Dwight Eisenhower National System of Interstate and Defense Highways at cost of $114 billion over35 years
• How to build the “urban half” of the system?
– Increasing demand
– Insufficient federal funding
– State transportation shortfalls
8
One Tool: P3s
• Public-Private Partnerships
– Accelerates infrastructure projects deemed impractical under traditional funding
– Well-developed international tool
– $200 billion capital available
9
Typical Models
• Build – Own – Transfer (“BOT”)
– Design, Build, Finance, Operate, Maintain
• Risk Shifting
• Performance-based Contracting
– Concessions
• “Privatization”
• Upfront fee in exchange for revenues
10
BOT: Advantages/Disadvantages
Pros
• Risk-sharing
• Innovation and efficiency
• Public liquidity
• Public focus on other core functions
• Decreased reliance on traditional funding
• International investment
Cons
• Long-term/complex contracts
• Loss of public control
• Potential higher user costs
• Risk of quality sacrifice in exchange for profits
• Impact on public jobs
• Loss of accountability
11
U.S. Examples
• Chicago Skyway - $1.8 billion (concession)
• Cincinnati Streetcar (BOT)
• British Columbia
– 75% of current infrastructure through P3s
– $3 out (??) $4 billion
12
Minnesota Roadblocks
We’ll consider . . .
• What is currently authorized
• What is currently prohibited
• What is necessary to achieve P3 goals
• Good models
13
Minnesota Roadblocks
What is currently authorized
• Local governments do not have inherent authority; authority must be expressly granted or implied from express grants.
• Mangold Midwest Co. v. Vill. of Richfield, 274 Minn. 347 (1966)
• Look to Minnesota Statutes for authority
14
Minnesota Roadblocks
What is currently authorized
• Local Road Authorities have power to retain private contractors to design, build, and maintain roads within their jurisdiction.
• E.g. Minn. Stat. § 163.02 (counties)
• Must follow public bidding process prior to awarding contract
• E.g. Minn. Stat. § 471.345.
15
Minnesota Roadblocks
What is currently authorized
• Implied authority to combine design, build & maintain into one contract?
“The awarding of a contract is an administrative act of discretion vested by the law in the governing authorities of the city. The courts cannot direct the authorities as to how they shall exercise that discretionary power nor direct to whom they must let a contract. They may only enjoin them from doing so illegally, which must include an arbitrary, capricious, or unreasonable exercise of power.”
• 33 Dunnell Minnesota Digest, § 12.01(b) (4th ed)
16
Minnesota Roadblocks
What is currently authorized
• Implied authority to combine design, build & maintain into one contract?– Must conform to bidding requirements, then
discretion re: methods and terms of contracting process.
– Must exercise discretion in a reasonable manner, not contrary to the public welfare, not unreasonable, arbitrary, or capricious.
17
Minnesota Roadblocks
What is currently authorized
• Implied authority to combine design, build & maintain into one contract?– Argument: By combining the contractual
obligations to design, build and maintain into a single procurement process which comports in all respects with the applicable contracting procedures, a local road authority may use and combine these private initiative variants.
18
Minnesota Roadblocks
What is currently authorized
• Certain Toll Facilities– Since 1993, Minnesota Statutes have permitted
local road authorities to enter into agreements with private operators to develop, finance, design, construct, improve, own, and operate a toll facility for roads and bridges within the road authority’s jurisdiction.
• Minn. Stat. §§ 160.84–160.93
19
Minnesota Roadblocks
What is currently authorized
• Certain Toll Facilities– Toll Facilities = “a bridge, causeway, or tunnel,
and its approaches; a road street, or highway; an appurtenant building, structure, or other improvement; land lying within applicable rights-of-way; and other appurtenant rights or hereditaments that together comprise a project for which a road authority or private operator is authorized to develop, finance, design, operate and impose tolls.”
• Minn. Stat. § 160.84
20
Minnesota Roadblocks
What is currently authorized
• Certain Toll Facilities– NOTE: An important element of the definition of
“toll facility” is the ability of the road authority or the private operator to impose tolls.
21
Minnesota Roadblocks
What is currently prohibited
• 2008 Transportation Finance Bill (passed over Governor veto)
• New provision restricting local road authorities from imposing new tolls on existing highways or using existing highways as toll facilities.
• Now road authorities may not limit operation of commercial motor vehicles to a toll facility or a tolled portion of a highway.
– Minn. Stat. § 160.845(b)
22
Minnesota Roadblocks
What is currently prohibited
• Three exceptions to ban on new toll facilities:
1.Toll facilities or HOV lanes constructed, converted, or established before 9/1/07
2.Any additional lane added to a highway after 9/1/07 (including price dynamic shoulder lane, HOV lane, or high-occupancy toll lane)
3.Any other general purpose lane that adds capacity
23
Minnesota Roadblocks
What is currently prohibited
• Also in 2008 Transportation Finance Bill:“A road authority may not sell, lease, execute a development agreement for a BOT facility or a BTO facility that transfers an existing highway lane, or otherwise relinquish management of a highway, if the highway is retained or utilized by the buyer, lessor, or operator for highway purposes.”
• Minn. Stat. § 160.98
• Aimed to prevent “privatization” of State’s roads and bridges
24
Minnesota Roadblocks
What is currently prohibited
• 2008 Minnesota Law, Key Terms– “BOT facility” = “a build-operate-transfer toll
facility developed, designed, constructed, improved, rehabilitated, and operated by a private operator who holds title to the facility subject to a development agreement providing that title will be transferred to the road authority on expiration of an agreed term.”
25
Minnesota Roadblocks
What is currently prohibited
• 2008 Minnesota Law, Key Terms– “BTO facility” = “a build-transfer-operate toll
facility developed, financed designed, constructed improved, or rehabilitated by a private operator who: (1) transfer any interest it may have in the toll facility to the road authority before operation begins; and (2) operates the toll facilities for an agreed term under a lease, management, or toll concession agreement.”
26
Minnesota Roadblocks
What is currently prohibited
• 2008 Minnesota Law, Key Terms– “Highway” includes all kinds of highways and
roads and the bridges or other structures thereon which form part of the same
– “Road Authority” applies to state, county, and city-level authorities.
• New law applies to all roads and bridges owned or managed by any road authority in the State.
27
Minnesota Roadblocks
• What is necessary to achieve P3 goals
• Dialogue
– ULI/RCM “Connecting Infrastructure, Transportation and Land Use Initiative
• Legislation
28
Minnesota Roadblocks
Good models
• Minnesota’s procurement laws specifically permit private ownership and operation of water and wastewater treatment plants.
• Citing the public benefits of faster construction, lower cost, and efficiency, the law permits privatization of facilities for the prevention, control and abatement of water pollution and the furnishing of potable water. – Minn. Stat. §§ 471.371 and 471A.01.
29
Minnesota Roadblocks
Good models
• ABA’s 2007 Model Code for Public Infrastructure Procurement
– design – bid – build
– design – build
– design – build – operate – maintain
– design – build – finance – operate – maintain
30
Resources
• Dorsey's Infrastructure Practice Group: http://www.dorsey.com/infrastructure/
• The National Council for Public-Private Partnerships: http://www.ncppp.org/
• The Institute for Public-Private Partnerships, Inc.: http://www.ip3.org
• U.S. DOT publication, “An Update on the Burgeoning Private Sector Role in U.S. Highway and Transit Infrastructure” (July 18, 2008):http://www.fhwa.dot.gov/reports/pppwave/ppp_innovation_wave.pdf
• British Columbia’s P3 agency: http://www.partnershipsbc.ca/index.html