Overview of ODOT Construction
1
5 Regions
16 Construction Crews &17 Consultant REs
260 Full Time Inspectors
98 HQ Construction Staff
130 to 150 projects per year
$400M annual program20% state funded
How to Find Work?• Projects in Your Area• Doing Business with ODOT• Upcoming Projects and Bid Lettings
– ODOT eBIDS, these are projects in Oregon’s STIP, typically large in scale and sometimes complexity, Federal/State Funding mix
• Business Oregon/COBID– Subcontractors - work to expand your NAICS Codes
• ORPIN & OregonBuys– ORPIN/OregonBuys are small & often limited in
complexity, State Funded, Contract requirements similar to STIP projects
• Engage with:– AGC-Oregon, NMAC-Oregon, PDBG, APAO, OCAPA 2
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
ODOT Construction Milestones
& Process Checks
Plans, Specs & Estimates
Advertisement Bid Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Plans, Specifications and Estimate (PS&E)
• Final contract documents delivered to Office of Pre-Letting via ODOT Regions
• Quality control conducted prior to advertisement• Final quality control includes among other checks:
– Funding available for total construction project authorization
– Plans and specifications are complete– Permits are secured– Right of Way is certified– Legal sufficiency check
has been satisfied
4
Plans, Specs & Estimates
Advertisement Bid Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Plans, Specifications and Estimate (PS&E)
• Final Engineer’s Estimate (FEE) – ODOT’s internal cost estimate based on:
– Historic bid item costs– Material price trends– Presumption of the means & methods – Schedule completion dates, including interim milestones
• FEE does not include:– Anticipated items– Contingencies– Escalation (+ or -)
5
Plans, Specs & Estimates
Advertisement Bid Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Advertisement, Bid, & Award
• Advertisement 3 to 7 weeks depending on project size and complexity
• ODOT Resident Engineer (RE) takes lead role• During advertisement, contractor has opportunity
to ask for clarification and visit the project site • Select projects require mandatory pre-bid meeting• Bid dates are generally each Thursday, with 5 to 15
projects typically bid each month• Bid volume ranges from about 130 to 150 projects
in a typical year
6
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Advertisement, Bid & Award
• Each pre-qualified contractor submits bid based on:– Work described in the contract documents– Contractor’s understanding of the project requirements– Contractor’s means and methods– Price for each pay item– All pay items then add to a total bid cost
o Note: Total bid cost is based on estimated quantities and does not include items such as escalation, de-escalation, & performance pay factors
• Each contractor’s total bid cost is compared to other qualified bids and ODOT’s Engineer Estimate
• Lowest qualified total bid cost becomes apparent low bidder
7
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Advertisement, Bid, & Award
• ODOT Procurement Office (OPO) reviews bids for:– Required submittals received timely and meet contract
requirements
• If bid is deemed responsive, then the contract is awarded
• If bid is deemed non-responsive, then ODOT considers award to the next lowest responsive qualified bidder
• OPO provides Notice of Intent to Award
8
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Construction Authorization
• Construction authorization summarizes commitment of project budget, which generally includes:
– Contract Amount - bid items sum included in the Bid– Anticipated Items - potential items of Work such as:
o Railroad Flagging, Utility Connections, Public Information– Contingencies - 3.5% of Contract Amount, i.e. original bid:
o Funding for project quantity fluctuationo Performance pay factorso Changes in the Work
– Escalation (+ or -):o Not in project budgeto Fuel, Asphalt, & Steel
9
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Notice to Proceed
• Notice to Proceed will be issued within 5 Calendar Days after Contract is executed by ODOT
• Written Notice authorizing Contractor to begin Work• Pre-construction Conference will be held within 30
Calendar Days of the Notice to Proceed
10
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Pre-Construction Meeting
• ODOT RE contacts Contractor:– Schedules Pre-Construction Conference– Required to occur within 30 days of Notice to Proceed
• Contractor submits:– Project Schedule, Quality Control Plan, Traffic Control
Plan, Erosion & Sediment Control Plan; and Pollution Control Plan, among other required items
11
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Pre-Construction Meeting
• ODOT RE & Contractor discuss items such as: – Safety, key personnel, and major project elements– Communication channels– Documentation and payment requirements– Means and methods of contractor’s work
o Automated Machine Guidanceo Staging to accommodate all modes - rail, truck, bike,
pedestrian, ADA, auto, & special events– Utility or environmental concerns– Surveying
12
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
First Notification
• ODOT RE written Notification to Contractor• Contractor begins on-site Work• Provides Work start date for Contractor or their
Subcontractors, including:– Mobilization of equipment & resources– Aggregate source development, if any– Erection of a plant, if required – Other Contract items
13
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project Work – Delegation of Authority
• Oregon Transportation Commission (OTC) delegates certain authorities to ODOT
• Contract Administration Engineer has authority to approve:
– Contract Change Orders, Extra Work Orders, & State Force Orders
– Contract Time Adjustments– Progress & Final contract payments– Construction Claim settlements– Serves as Statewide Department of Justice (DOJ) Liaison
• RE obtains changes to Contract approvals
14
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project Work Authorities, Roles, & Responsibilities
• ODOT RE is responsible for:– Ensuring work is completed per Contract requirements– Providing certified staff to monitor the Work & document
compliance– Verifying quality of materials & workmanship– Performing measurement & payment for actual quantities
• ODOT RE has delegated authority to:– Suspend work and/or withhold payment for safety issues or
non-compliance– Remove unacceptable employees/subcontractors – Initiate Change Orders to modify, add, or delete Work
15
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project WorkRoles & Responsibilities
• Contractor is responsible to:– Coordinate with utilities and other contractors; – Provide notifications for traffic changes & Mobility Group;– Contact RE for any necessary clarification or interpretation
of the Contract; and – Promptly notify RE of any disagreements or disputes,
including disputed work, differing site conditions, or delays.
16
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project WorkRoles & Responsibilities
• Contractor must:– Provide ALL required paperwork and quality documentation– Comply with laws and permits– Schedule and control of means & methods– Provide materials, equipment, & labor– Manage subcontractors and suppliers– Satisfy labor law requirements; DBE, OJT, & TERO goals– Ensure quality workmanship– Perform materials testing (QC)– Other Contract obligations
17
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project Work – Inspection Activities
• ODOT RE staff:– Ensure contract compliance;– Record daily activities;– Take measurements & calculate payment quantities; – Conduct DBE Commercially Useful Function reviews; – Conduct labor compliance interviews;– Monitor contractor’s quality control testing;– Coordinate quality assurance testing;– Prepare monthly progress (pay) estimates;
o Construction Section processes monthly progress estimates for payment;
– Reject non-conforming Work; and– Provide Contract clarification.
18
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project Work – Prosecuting the Work
• Contractor submittals & notifications:– Weekly and monthly schedule updates;– Equipment lists & working drawings;– Daily traffic control & erosion control monitoring;– Quality control & conformance documentation;– Certified payrolls; and– Disagreements & disputes
o Delays to progresso Differing site conditionso Changed or extra work
19
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project Work – Prosecuting the Work
• ODOT submittals & notifications process:– Review, comment, or approve contractor submittals;– Review and respond to notices;
o Disagreements & disputeso Delays and/or differing site conditionso Changed or extra work
• Negotiate & prepare contract change orders for changes and/or unanticipated items; and
• Prepare extra work orders to perform workon a time-and-materialsbasis.
20
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project Work – Disagreements & Claims
• Contract is only between ODOT & Prime Contractor; • ODOT does not consider direct disagreements,
protests, or claims from subcontractors, suppliers, or any other entity not a party to the Contract;
• Contract disagreement, protest, & claims process; – Contractor raises disagreements or protest to RE for
resolution– If this discussion fails, then the contractor follows the
protest procedure
• Claims process has a tiered authority level structure, with the Contract Administration Engineer (CAE) having final approval authority; and
• CAE works with DOJ, may include litigation. 21
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project Work – Quality Assurance
• Contractor provides Quality Control testing;• ODOT checks contractor testing per our Quality
Assurance (QA) program;• QA program complies FHWA requirements; and• Success of ODOTs QA program is dependent on
three primary features:– Laboratory Certification– Technician Certification– Specific product testing
o Verification testingo Independent assurance
22
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project Work – Assurance
• CAE deploys Regional Assurance Specialists (RAS) to:– Provide ongoing quarterly review of project documentation
based on Contract requirements;– Provide final project documentation review & recommend
corrective actions if needed;– Recommend project documentation acceptance to CAE; and– Work toward statewide consistency in contract
administration processes, guidelines, & issue resolution.
• RAS reviews validates:– Quality & measurement for payment; and– FHWA Stewardship Agreement tied to federal funding.
23
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project Work – Labor Compliance
• RE monitors the Contractor & subcontractors :– Labor compliance; and– Certified payroll reports.
• RE conducts Commercially Useful Function (CUF) reviews to evaluate DBE Contract compliance:
• CUF review includes:– DBE Management;– DBE Equipment;– DBE Workforce;– DBE Materials; and– DBE Performance.
24
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Project Work – Get paid promptly!
• All parties comply with the Contract• Submit all contractually required documents
– Payroll, quality documents, and submittals
• Read and understand monthly progress payment– RE and Contractor should expedite reviews– Understand Materials-on-Hand (MOH) requirements
o Request made, securely stored, and protectedo Proof of payment to supplier within 30 days of
payment by ODOT
25
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
• Use electronic depositing your payment
• Call if in doubt, RE first, then CAE
Project work - Prompt Payment!
• Doc Express – Quick Overview & Payments Drawer– Drawer Z05 Payments
• Prompt Payment Issues– Prime Contractors
o Work through the RE first, then contact Contract Admin Engineer if needed.
– Subcontractors & supplierso Work through Prime Contractors first, then contact
RE, then Contract Admin Engineer if needed.
• Contacts if issues persist:– Chris Bucher PE, ODOT Contract Admin Engineer– Joe Squire PE, State Construction & Materials Engineer
26
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Second Notification
• End of Contract Time, bid item work is complete.• RE written acknowledgement to Contractor.• Second notification also lists:
– Date time charges stopped & liquidated damages for work not complete beyond specified contract completion date
– Submittals, required certifications, bills, warranties, certificate of insurance, & other required documentation.
– Development of corrective work item list (Punch List).– Equipment to be removed from the project site.– Starts 45-day period to file claims.
27
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Final Inspection
• Contractor notifies RE the project is complete.• RE has 15 calendar days to review project & notify
Contractor remaining Work. • Contractor has completed all Work & fulfilled
Contract as determined by the RE.
28
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Third Notification
• After final inspection, RE provides contractor written acknowledgement, subject to Final. Acceptance, the project completion date including:
– Submittal of all quality certifications, warranties, bills, forms, and documentation (labor compliance, civil rights documents, etc.).
– All minor corrective work completed.– De-mobilization.– Site clean-up.
29
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment
Final Acceptance / Final Payment
• Written acknowledgement RE:– Project has been completed per the Contract.– Exception - any latent defects & warranty obligations.
• 30 calendar days after Third Notification if Final Payment has not occurred, interest accrues on unpaid portion.
• Contractor has 30 days after final payment receipt to file claims of error in final quantities & amounts.
30
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance &Payment
How to Find Work?• Projects in Your Area• Doing Business with ODOT• Upcoming Projects and Bid Lettings
– ODOT eBIDS, these are projects in Oregon’s STIP, typically large in scale and sometimes complexity, Federal/State Funding mix
• Business Oregon/COBID– Subcontractors - work to expand your NAICS Codes
• ORPIN & OregonBuys– ORPIN/OregonBuys are small & often limited in
complexity, State Funded, Contract requirements similar to STIP projects
• Engage with:– AGC-Oregon, NMAC-Oregon, PDBG, APAO, OCAPA 31
Plans, Specs & Estimates
Advertisement, Bid, & Award
Notice to Proceed
Pre-Construction Meeting
First Notification
Project Work
Second Notification
Third Notification
Final Acceptance & Payment