Our Legacy of Neglect:The Longfellow Bridge and The Cost

of Deferred Maintenance

(Photo by Christopher Penler)

Page 2: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

The Longfellow Bridge Today

• The bridge was constructed out of granite and steel in 1906, using methods which are now outdated.

• The bridge carries over 49,500 vehicles per day plus an estimated 97,000 daily MBTA Red Line transit passengers.

Page 3: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Deterioration of the Bridge

• Some of the original deck sections contain large rust holes ( with 100% section loss) and the arch ribs also have heavy rusting and section loss.

• The stringers, floor beams and posts are rated as “4-Poor”, on a scale of 1 to 9 (1-imminent failure to 9-excellent).

The most recent inspection of the bridge was done in September 2006.

Page 4: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

• The substructure consists of the 10 granite piers in the river and the 2 abutments.

• The pier walls have random areas of cracked and missing mortar joints. Four of the piers have vertical cracks extending down through four courses of granite block and some have vertical cracks extending all the way down to the water line.

Deterioration of the Bridge

Page 5: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Maintenance History of the Longfellow

• The 1959 project included some structural repairs and replacements and cost an estimated $2M.

• The 2003 project included structural repairs, graffiti removal, sidewalk repairs and lighting, at a cost of $3.2M.

The Longfellow has undergone two repair projects since 1907; first in 1959, then again in 2003.

Page 6: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Construction and Maintenance Spending

• Based on the ENR Construction Cost Index, the 1959 rehabilitation would be equivalent to $19.7M and 2002 rehabilitation equivalent to $3.8M in 2007 dollars.

• Thus the historical spending to date is $272.5M.

Date Cost Cost (2007 $)

Initial Construction 1907 $2.6M $249.0M

First Rehab 1959 $2.0M $19.7M

Second Rehab 2002 $3.2M $3.8M

Total Historical Cost to Date $272.5M

Page 7: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

• Costs may escalate based on engineering findings.

• Symptomatic of a larger problem: Commonwealth’s assets suffer from a maintenance backlog in the tens of billions of dollars.

Fixing the Longfellow Bridge could cost up to $200 million, or more…

• We lack a comprehensive, state-wide system to manage assets, as well as the funding and political will to properly maintain our assets. There is nothing to stop the problem from growing worse.

Page 8: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

The Cost of Longfellow’s Deferred Maintenance

• In January 2006, the Executive Office of Transportation, stated that “[t]he current $70 million price tag could rise to $100 million.”

• Currently, the official Massachusetts Highway Department estimate is $180 million.

• Transportation Finance Commission, issued on March 28, 2007, estimated repair costs at $200 million.

• Findings of engineering study may radically escalate this estimate.

Page 9: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

A New Bridge? With an approximate total cost of $480 million (historical cost + estimated cost of repairs), a new replacement bridge begins to appear economically rational, but unreasonable due to the bridge’s significance.

After the existing bridge has been rebuilt or repaired, will we again let it deteriorate without proper maintenance, or will it be properly maintained?

Page 10: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Asset Life-Cycle

0

20

40

60

80

100

120

0 20 40 60 80 100 120

Time

Asset

Co

nd

itio

nAcceptable Condition Level

Lack of Maintenace Results in

"Run To Ground"

Poor Condition

Good Condition

Maintenance Restores

Asset Condition

Ref. Reece, GASB , Maze

•Maintenance can restore the condition of an asset before its condition reaches the inflection point and begins to decline rapidly.

•The effect of not maintaining an asset is called “running to ground”.

•It is expected that there is a 40 percent drop in quality over 75 percent of an asset’s lifetime, then a more precipitous drop in the final quarter of the asset’s life.

Page 11: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

What Could Have Been Done• The Longfellow Bridge

suffered from a lack of annual maintenance compounded over many years.• Major repairs were

undertaken in 1959 and lesser repairs in 2002, but years of neglect have caught up with the structure.

• The following three scenarios evaluate different levels of investment in maintenance that could have been implemented upon completion of the bridge.

Page 12: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Scenario 1

• If an investment of 1 percent each year in maintenance was made that would be equivalent to a total of $62.7 million in today’s dollars.

• With the addition of a projected $80 million in current rehabilitation costs (equal to 40% of the estimate), the total savings (relative to the actual scenario) would be approximately $80 million.

Invest 1 percent of the bridge’s capital cost each year in a maintenance program.

Page 13: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Scenario 2

• By investing 2.5 percent each year in maintenance that would be equivalent to a total of $156.8 million in today’s dollars.

• With the addition 20% of the rehab cost, the total savings would be $26.7

million.

Invest 2.5 percent of the bridge’s capital cost each year in a maintenance program

Page 14: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Scenario 3: Reality

• Capital depreciation is assumed to be 100 percent of the rehabilitation cost, currently set at $200 million. The total cost to keep the bridge in good repair is $223.5 million

• But these cost estimates mask the reality of the bridge’s poor condition

Actual Scenario: No annual maintenance program, but a major rehabilitation in 1959 followed by lesser repairs in 2002.

Page 15: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Maintenance Scenarios

(% asset value on Maintenance; $M)

Scenario 1

(1%)

Scenario 2

(2.5%)

Scenario 3

(Actual)

Maintenance Cost $62.7M $156.8M $23.5M

Current Cost to Rehab

$80.0M $40.0M $200.0M

Total Cost to Return Bridge to Good Repair

$142.7M $196.8M $223.5M

Savings from Maintenance

$80.8M $26.7M N/A

Page 16: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Statewide Backlog of Deferred Maintenance

•Total depreciated value of state assets at $24.9 billion in June 2006. •Our study estimates a deferred maintenance backlog of at least $17 billion.•This deferral of maintenance is caused by:

•Unwillingness to prioritize maintenance over new projects

•Diffusion of responsibility for assets across the public sector

•Incentives that discourage spending on maintenance

Page 17: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Maintenance BacklogsEntity Citation Backlog Estimate

($B) Mass Highway - Pavement MHD 5 Year Pavement

Condition Tables $6.2

MBTA April 2007 PMT Advisory Board Meeting

$2.7

UMASS Amherst UMASS 2007 Financial Indicators Report

$1.6

DCR 11/12/06 Boston Globe Article $1.3 State and Community Colleges 11/06 Roadmap $1.2 Remainder of UMASS (Boston, Dartmouth, Lowell, Worcester)

UMASS 2007 Financial Indicators Report

$1.1

Mass Highway - Bridges 10/06 Performance Report $1.0 County Sheriffs Author’s Estimate >$1.0 Trial Court Gienapp Design Associates

6/26/07 Report $.5

Mass Pike - Bridges 5/15/07 Press Report $.4 Other – MWRA, Massport, RTAs, Steamship Authority

Unknown

Total Maintenance Backlog At least $17 billion

Page 18: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Disincentives for Maintenance

• Due to the current system, any maintenance spending from an agency’s operating budget results in a reduction of funds available for programs.

• By neglecting maintenance (and potentially running assets to failure), operating funds can be maximized.• The eventual failure of the building-related assets will result in an

emergency disbursement of capital funds, which come from DCAM’s budget and will not impact the agency’s operating budget.

Page 19: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Current Asset Management The Commonwealth does not have

overarching systems in place to:• Adequately inventory assets

• Assess their condition

• Estimate the cost of deferred maintenance

•DCR now utilizes FAMIS, the Facility Administration and Maintenance Information System, for their own assets, with the exception of major bridges including the Longfellow.

•Longfellow will become part of the PONTIS bridge maintenance system includes data and analytical models for an inventory of the state's bridges.

Page 20: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Options for Improving Maintenance • The lines of responsibility for maintenance

should be clarified.• The DCAM should be empowered to fulfill its

statutory ability to monitor the maintenance of non-transportation, non-park assets.

• A report should be issued yearly on the status of assets by department, including maintenance progress and funding.

• The Governor’s Office and the Executive Office of Administration and Finance should highlight the importance of maintenance to program managers and reward them and their programs for improvements in maintenance practices.

Page 21: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Conclusions• The lack of maintenance, and its

resultant cost, on the Longfellow is symptomatic of a problem that stretches across the assets owned by the Commonwealth.

• We lack a centralized system to comprehensively manage our assets.

• There is no state-wide plan in place to stop the problem from growing worse.

• A regular program of maintenance would have extended the bridge’s useful service life and lowered overall rehabilitation costs.

Page 22: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Recommendations• Only build new structures and expand the

transportation network with a comprehensive life-cycle management plan in place.

• The Executive Office of Administration and Finance should prepare a report on asset conditions, condition trends, maintenance efforts and maintenance plans for each department and authority by asset class and actively reward those agencies that are addressing the problem.

• Each state agency should include in its annual operating budget an amount equal to 2 percent of replacement value for such capital asset

Page 23: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)

Recommendations•A Commonwealth Facilities Maintenance Reserve Fund should be established, beginning with only 0.1 percent of the general fund in the first year and rising 0.1 percent per year to 1 percent of the general fund in the 10th year

•The Commonwealth and its political subdivisions should consider utilizing the GASB 34 “Modified Approach” to promote active asset management.

•The Governor should establish general principles for infrastructure maintenance to be followed by all state infrastructure agencies

•Governor should charge the Executive Office of Transportation and Public Works, and the Division of Capital Asset Management with responsibility for establishing a process to more fully develop and oversee maintenance and reporting guidelines

Page 24: Our Legacy of Neglect: The Longfellow Bridge and The Cost of Deferred Maintenance (Photo by Christopher Penler)