Page 1: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

Opportunity Day Opportunity Day The 1The 1stst Quarter of 2009 Performance Quarter of 2009 Performance

Wednesday 27 May 2009 Wednesday 27 May 2009

1

Page 2: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

2

1st Quarter 2009 Operating Performance

MB % MB % MB %

Services Income 452.91 99.40% 111.57 99.61% 536.82 99.48%

Other Revenue 2.76 0.60% 0.44 0.39% 2.82 0.52%

Total Revenue 455.67 100.00% 112.01 100.00% 539.64 100.00%

Cost of Services -358.00 -78.57% -108.47 -96.84% -438.79 -81.31%

Gross Margin 94.91 20.83% 3.10 2.77% 98.02 18.16%

SG&A Int. -21.91 -4.81% -11.65 -10.40% -33.61 -6.23%

Allowance for Doubtful Debt 0.00 0.00% -38.25 -34.15% -38.25 -7.09%- Advance for Stung Meteuk

Project

Share of Loss from JV/Assoc. 0.00 0.00% 0.00% -2.92 -0.54%

EBT 75.76 16.63% -46.36 -41.39% 26.07 4.83%

TAX -19.50 -4.28% -0.04 -0.04% -19.50 -3.61%

Net Profit 56.26 12.35% -46.40 -41.42% 6.57 1.22%

Gross Profit Margin 20.96% 2.78% 18.26%

Net Profit Margin 12.35% -41.42% 1.22%

TRC Sahakarn Consolidated

1st Qtr 2009

1st Quarter 2009 Operating Performance

Page 3: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

3

Comparison with same period of last year

MB % MB % MB %

Services Income 536.82 99.48% 277.28 98.66% 259.54 93.60%

Other Revenue 2.82 0.52% 3.76 1.34% -0.94 -25.03%

Total Revenue 539.64 100.00% 281.05 100.00% 258.59 92.01%

Cost of Services -438.79 -81.31% -211.61 -75.30% 227.18 -107.36%

Gross Margin 98.02 18.16% 65.67 23.37% 32.36 49.27%

SG&A Int. -33.61 -6.23% -37.33 -13.28% -3.73 9.99%

Allowance for Doubtful Debt -38.25 -7.09% 0.00 0.00% 38.25 #DIV/0!

Share of Loss from JV/Assoc. -2.92 -0.54% -9.86 -3.51% -6.94 70.39%

EBT 26.07 4.83% 22.24 7.91% 3.83 17.21%

TAX -19.50 -3.61% -9.55 -3.40% 9.95 -104.20%

Net Profit 6.57 1.22% 12.69 4.52% -6.12 -48.25%

Gross Profit Margin 18.26% 23.68%

Net Profit Margin 1.22% 4.52%Debt to Equity (Time) 0.62 0.60

In case no allowance for doubtful debtAdd: Allowance for Doubtful Debt 38.25 7.09%Net Profit before

Extraordinary Item 44.82 8.31%

1st Qtr 2008

Consolidated

1st Qtr 2009

Consolidated Difference

Page 4: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

4

Project Name

Type

of

Works

Project Owner/

Client

Work Value

(MB)

Uncompleted

Work Value

(MB) Project Period

1. Hinkong Gas Pipeline E, P, C PTT Plc. 267.00 267.00

Apr 09 Jun 10

2. Bio Diesel Plant E, P, C Bangchak Bio fuel Co., Ltd. 757.00 274.03 Mar 08 June 09

3. PTTAR-Reformer Complex II Project H2 Line E, P, C PTT Aromatic and Refining Plc.

219.00 127.02 Sep 08 Sep 09

4. N/G Pipeline for 7 NGV Station ( Pack#5) E, P, C PTT Plc. 119.93 104.94 Jan 09 July 09

5. Bangchak Pipeline Reroute

Additional Work

E, P, C PTT Plc. 315.009.90

74.039.90

May 08 Mar 09

6. Construction of MRS and In-Line Block Valve, Suvanaphum - Payatai NGV. Pipeline Project

E, P, C PTT Plc. 185.00 61.32 Nov 06 Sep 07

7. Natural Gas Pipeline for small Industrial at Bang Pa-In state and existing area Ayudhya Province

E, P, C PTT Natural Gas Distribution

Co., Ltd.

135.99 40.60 May 08 Feb 09

8. Design & engineering for SPE II

Additional Work

E, P, C Siam Polyethylene Co., Ltd. 52.4130.80

5.5825.58

Apr 08 May 09

9. Supply and install fucture sleeve at corridor Pipeline

Project

Addtional Work

E, P, C Map Ta Phut Olefins Co., Ltd. 25.50

19.32

15.05

7.73

May 08 Nov 08

10. 1BCP-Main Outlet Pipe line to process E, P, C Bangchak Petroleum Co., Ltd. 14.80 9.62 Sep 08 Mar 09

10.2 BCP-Main Outlet Pipe line to process E, P, C PTT Plc. 12.24 7.95 Sep 08 Mar 09

11. Polishing Filter E, P, C RCR Engineering Co., Ltd. 42.48 11.89 Aug 08 Feb 09

12. CCC Interconnecting Pipeline Project E, P, C Map Ta Phut Olefins Co., Ltd.

Thai Polyethylene Co., Ltd.

Thai Industrial Gases Plc.

357.00 8.21 Apr 07 Mar 09

TRCTRC’s Projects on Hand as of 31 March 2009’s Projects on Hand as of 31 March 2009

Page 5: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

TRCTRC’s Projects on Hand as of 31 March 2009 ’s Projects on Hand as of 31 March 2009

Project Name

Type

of

Works

Project Owner/

Client

Work Value

(MB)

Uncompleted

Work Value

(MB) Project Period

13. N/G Pipeline for 5 NGV Station E, P, C PTT Plc. 121.80 4.87 Oct 08 Feb 09

14. Construction PHD Interconnecting Pipeline

Project

E, P, C Eastern Fluid Transport Co., Ltd.

91.75 4.59 Mar 08 Nov 08

15. PTT AMATA-Natural Gas Distribution Network E, P, C PTT Natural Gas Distribution

Co., Ltd.

7.63 2.29 July 08 Dec 08

16. Total Wp3 Wind Turbine Structural Support Frame

E, P, C TOTAL E&P Myanmar 1.73 0.21 Dec 08 Jan 09

Total 16 Projects 2,786.28

1,062.

41

5

Page 6: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

6

Project Name

Types

of

Works

Project Owner/

Client

Work Value

(MB)

Uncompleted Work Value

(MB) Project Period

1. Malibu Khao Tao Project (Condominium structure and architecture)

E,P,C

M Talay Co., Ltd.(Joint Venture of Maneeya Group and Mr. Pravit Maleenont)

371.96 229.91 Mar 08 Nov 09

2. Bangchak Bio Diesel Project P,C TRC Construction Plc. (The Owner: Bangchak Bio Fuel Co., Ltd.)

100.74 29.77 Sep 08 Mar 09

3. N/G Pipeline Project - Bangchak

E,P,C

TRC Construction Plc. (The Owner: Bangchak Petroleum Plc.)

14.06 9.14 Sep 08 Mar 09

4. N/G Pipeline Project - Bangchak

E,P,C

TRC Construction Plc. (The Owner: PTT Plc.)

11.63 7.56 Sep 08 Mar 09

5. Civil Construction of TPE/HDPE (Package 1)

E,P,C

Thai Polyethylene Co., Ltd.

36.53 2.66 May 08 Apr 09

Total 5 Projects 534.92 279.04

SKWSKW’s Projects on Hand as of 31 March 2009’s Projects on Hand as of 31 March 2009

TRC 16 Projects 1,062.41 MB

SKW 5 Projects 279.04 MB

Less 3 Join Projects (46.47) MB

Total Backlog 18 Projects 1,294.98 MB

1st Qtr Backlog Conclusion

+ Oman Project 800 M

(60% of USD 38 Million) 2,095 MB

Page 7: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

7

Projects from

Project Development and Investment Division

Page 8: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

Status Update

Region Project StatusThailand SPP Ladkrabang C.O.D 2012

Oman Petrogas Rima Contract value of USD 38 million. TRC is awarded

Namibia Desalination plant TRC consortium is one of the short listed

Cambodia Stung Meteuk Foreign investors show strong interests. The MoU is expected very shortly

Nigeria Amazon Energy as potential partner

The status of the projects are being monitoring closely

Page 9: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

Cambodia: Stung Meteuk

EGAT meeting on Power Development Plan and Power Purchase Program from Neighboring Countries

Negotiating with foreign investors, MoU is expected in a very near future

Page 10: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

Business Partner: CloughClough Highlight: Full Project Life Cycle Solutions Capability

10

JV Agreement is expected to be signed early of June The newly established JV company will lever TRC’s capability to venture to a new business segment (off-shore platform / off-shore piping) where margin is higher and competitors are less

Many opportunities in Thailand’s neighbor countries such as M-9 field in Myanmar, where PTTEP is the owner and the operation is expected to

commence soon

Page 11: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

Oman: Petrogas Rima Project

Scope of work:Engineering, Procurement, Construction, Load out, Transportation, and Hook-up of Production Flow Lines and Water Injection Flow Lines for Rima Satellites Small fields

Total of drilling well 72 wells

Distance between site 10-30 km. Contract value is USD 38 million

Page 12: Opportunity Day Opportunity Day The 1 st Quarter of 2009 Performance Wednesday 27 May 2009 1

Namibia: Desalination Plant in Swakopmund region

TRC and its Thai strategic partner as well as strategic Namibia partner formed a strong consortium to pursue this opportunity It is official that the consortium is short-listed (pre-qualified) to submit a full proposal in September ‘09 The desalination plant has a proposed capacity of 25 ml per day with full expansion of 80 ml per day utilizing R-O technology