onshore oil & gas order #1 blm/forest service final rule
TRANSCRIPT
![Page 1: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/1.jpg)
Onshore Oil & Gas Order #1
BLM/Forest Service Final Rule
![Page 2: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/2.jpg)
2
Onshore Oil & Gas Order #1
Ken McMurrough
NRS BLM, Colorado State Office
303-239-3642 (x3799 fax)
Hank Szymanski – 303-239-3797
![Page 3: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/3.jpg)
3
OverviewOnshore Oil & Gas Order No. 1
Authority
This rule, effective April 6, 2007, revised the existing OO#1 which supplemented primarily the federal regulations at 43 CFR 3162.3 and 3162.5.
Purpose - Approval of Operations of Federal and Indian Oil and Gas Leases
The purpose of OO#1 is to state the application requirements for the approval of all proposed oil and gas and service wells, certain subsequent well operations, and abandonment.
![Page 4: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/4.jpg)
4
OverviewOnshore Oil & Gas Order No. 1
Defines terms Components of APD Time line Approval requirements Split estate Indian leases Reclamation/Abandonment Appeals
![Page 5: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/5.jpg)
5
BackgroundReasons for Revision of Previous Order
Leasing Reform Act of 1987 Energy Policy Act of 2005 Update for Current Practices
– Split estate policy– Cultural & wildlife inventory– Right of Way coordination– Master development plans, directional drilling– Best Management Practices
![Page 6: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/6.jpg)
6
BackgroundStatus
Proposed rule – Published July 2005 Energy Policy Act – Signed August 2005 Further proposed rule – Published March 2006 Public comments – Received nearly 90 from
industry, interest groups and the public at large Final rule – March 7, 2007
![Page 7: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/7.jpg)
7
BackgroundMajor Revisions
Process time line– Section 366, Energy Policy Act of 2005
Requires compliance with applicable law
Define terms– Complete APD
Onsite inspection included Cultural & wildlife Inventories not included Geo-referenced well plat
![Page 8: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/8.jpg)
8
BackgroundMajor Revisions (continued)
Split estate– Operator provides SUPO & COAs to surface owner– Bond compensation for loss or damages for access based
on statutory requirements on patented lands (min $1000)
Onsite inspection– 15 day requirement eliminated– Onsite required for complete APD
Valid period for APD– Changed to 2 years with 2 year extension
![Page 9: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/9.jpg)
9
BackgroundControversial Issues
Time line– Onsite inspection required
Required for complete APD
– NEPA, NHPA, ESA compliance Potential delays – no definite time to process
– APD may be deferred or denied within 30 day after complete APD submittal
![Page 10: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/10.jpg)
10
BackgroundControversial Issues (continued)
Valid period for APD– 2 years with 2 year extension
Split estate– SUPO & COAs provided to surface owner– Good Faith Effort vs mandatory notification What is a “good faith effort”– Bonding for access Compensation based on loss or damages or
as required by specific statutory authority
![Page 11: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/11.jpg)
11
SpecificsDefinitions, New or Revised
Best Management Practices Casual Use COA Complete APD Days Emergency Repairs Geospatial Database Master Development Plan Onsite Inspection Private Surface Owner Reclamation Surface Managing Agency
![Page 12: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/12.jpg)
12
SpecificsGeneral
Read the preamble first if you have questions Early notification is new (initial planning
conference) & is voluntary, precede NOS Best Management Practices, something we
have been doing for decades, are strongly recommended
![Page 13: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/13.jpg)
13
SpecificsNotice Of Staking Option
Provides operator opportunity to gather information to address site-specific resource concerns while preparing the APD package.
10 days after receiving NOS, an onsite inspection will be scheduled to take place as soon as weather & conditions permit.
Minimum staking required: 1) center stake for proposed well, 2) 2 reference stakes, 3) flagged access centerline.
BLM will invite surface managing agency (SMA) and surface owner, if applicable.
![Page 14: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/14.jpg)
14
SpecificsGeneral
Geospatial database, required for well plat Operator must make a “Good Faith Effort” :
1) notify the private surface owner for access, 2) provide operator with SUPO & COA, 3) obtain surface access agreement
Casual Use further explained, includes surveying and staking
![Page 15: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/15.jpg)
15
Specifics9-point Drilling Plan
More complete casing and cementing information
Added language for directional drilling
![Page 16: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/16.jpg)
16
Specifics12-point Surface Use Plan
Geospatial data optional Additional staking required over that used for
an NOS Certify or Good Faith Effort made to get the
SUPO to the private surface owner (#11) Moved “Certification” out of SUPO, it now
stands alone as a required APD component
![Page 17: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/17.jpg)
17
SpecificsBonding
Bond increase and phased release (lease bond only) are now in the Order
BLM requires sufficient bond to restore surface adversely affected by lease operations after abandonment
Authority to require additional bond to be applied to off-lease facilities required to develop a lease
![Page 18: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/18.jpg)
18
SpecificsNOS Processing Time Line
Onsite scheduled within 10 days “List of Concerns” provided at onsite or within
7 days Submit APD within 60 days or NOS may be
returned
![Page 19: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/19.jpg)
19
SpecificsAPD Processing Time Line
10-Day letter for APD completeness notification Onsite scheduled within 10 days (unless NOS
onsite conducted) “Additional Deficiencies” provided at onsite 45 days to submit additional information 30 days for BLM decision after complete APD
submitted Decision to Approve, Defer, or Deny APD
![Page 20: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/20.jpg)
20
SpecificsAPD Permit Deferral
BLM will provide the operator a list of pending actions and a schedule for completion before final APD approval can be granted
BLM will inform the operator of the actions they could take to assist
The operator has 2 years to take the specified actions
BLM will approve the APD within 10 days after all actions are complete
![Page 21: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/21.jpg)
21
SpecificsAPD Approval
FS has NEPA responsibility on the Forest On the Forest, BLM should be a cooperating
agency (Co-lead) and adopt the NEPA analysis as a basis for its decision
On Indian lands, BLM may be a cooperating agency (Co-lead) OR may adopt the NEPA analysis prepared by the BIA
![Page 22: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/22.jpg)
22
SpecificsMaster Development Plans
Eliminated Master “Drilling” Plans Master development plan (MDP) for 2 or
more APDs with common drilling plan, SUPO and POD.
Subsequent APDs can reference the MDP for NEPA analysis
Each subsequent proposed well must have a survey plat and an APD Form (3160-3)
![Page 23: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/23.jpg)
23
SpecificsOperator Responsibilities
Section IV, General Operating Requirements Operator responsibilities discussed - includes requirements for :
• NEPA• General operations• Protecting cultural & historic resources• Protecting endangered species & their habitat• Surface protection• Safety• Completion reports
![Page 24: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/24.jpg)
24
SpecificsCompletion Reports
Well logs submitted in electronic format For directional wells be sure to report the
bottom hole lat/long locations (at top of production interval and at total depth)
![Page 25: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/25.jpg)
25
SpecificsPrivate Surface
Certify to BLM that a Good Faith Effort has been made to notify the private surface owner before entry
Certify to BLM that a surface use or access agreement has been reached or a Good Faith Effort made
Certify copy of SUPO & COA provided to private surface owner or a Good Faith Effort made
![Page 26: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/26.jpg)
26
SpecificsSubsequent Operations
NOI required for new construction, re-construction, or alterations that result in new disturbance.
If no existing approved plan exists, an NOI must be filed & approved by the BLM. New field inspection may be required & additional cultural or biological inventories may be required.
Split Estate - Operator must “certify” that “good faith effort” made to provide private surface owner a copy of any proposal for new surface disturbance.
![Page 27: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/27.jpg)
27
SpecificsWell Conversions
Order includes a more complete explanation of well conversions
Added a section on conversion to an injection well
![Page 28: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/28.jpg)
28
SpecificsWaivers, Exceptions, Modifications
Waiver – Permanent removal of lease stipulation. Exception – Case-by-case exemption from lease
stipulation. Modify – Permanent change to lease stipulation
Request should also include information to support that the stipulation no longer justified or the proposed operation would not cause unacceptable impacts.
![Page 29: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/29.jpg)
29
SpecificsAbandonment
6 months to complete earthwork (weather permitting) after well completion/plugging
May be difficult on multi-well pad An agreement between the SMA or private
surface owner and the operator necessary before assuming improvements (roads, pads, other)
![Page 30: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/30.jpg)
30
SpecificsAppeals
FS SUPO subject to FS appeal requirements BIA decisions subject to BIA appeal
requirements
![Page 31: Onshore Oil & Gas Order #1 BLM/Forest Service Final Rule](https://reader036.vdocuments.mx/reader036/viewer/2022062417/5516da4a55034643088b4630/html5/thumbnails/31.jpg)
31
Thoughts, Comments?
Onshore Oil and Gas Order Number 1, Approval of Operations
Federal Register, Volume 72, Page 10308-10338 (72FR10308), Wednesday, March 7, 2007
Effective May 7, 2007