Page 1: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each
Page 2: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

Oklahoma State Regents for Higher Education

Annual Campus Master Plan Submission Summary Form

June 12, 2013

Institution or Agency: The University of Oklahoma – 760

Total number of records submitted: 55 Total number of records requiring new State Dollars (long format): 11 Total number of “Self-funded” projects submitted: 44 Contact Person’s Name: Michael K. Moorman, Director Architectural and

Engineering Services Contact Person’s Phone Number: 405-325-6006 Please return this form to the attention of Sheri Mauck by June 12, 2013, or as soon as your institution completes the data entry of all projects. You may return the form by fax to (405) 225-9230, by email to [email protected] or by mail to 655 Research Parkway, Suite 200, Oklahoma City, OK 73104.

Page 3: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

THE UNIVERSITY OF OKLAHOMA May 9-10, 2013

15.0

AGENDA ITEM 15 ISSUE: CAMPUS MASTER PLAN OF CAPITAL IMPROVEMENT

PROJECTS – ALL ACTION PROPOSED:

President Boren recommends the Board of Regents approve the revised Campus Master Plan of Capital Improvement Projects for the Norman, Oklahoma City and Tulsa campuses of the University. BACKGROUND AND/OR RATIONALE:

The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each year an update of the Campus Master Plan of Capital Improvement Projects. Following approval by the State Regents at their June meeting, the Campus Master Plan will be submitted to the State Long Range Capital Planning Commission as required by statute. The Commission is charged with the responsibility of preparing a five-year State Capital Plan which is submitted in December of each year to the Governor, Speaker of the House of Representatives and President Pro-Tempore of the Senate.

The development of the Capital Improvement Plan for the Norman, Oklahoma City and Tulsa campuses has been completed following a review of current capital needs by executive officers. Attached for consideration and approval by the Board are prioritized project lists for each campus along with project descriptions providing additional information about each of the projects included in the plan. The projects for each campus are prioritized in groups as follows.

I. Highest priority projects for which State funding is requested;

II. Projects which are currently in planning, design or are under construction and for which funding has been identified in full or in part; and

III. High priority projects, funding not currently available.

New projects which have not previously been approved by the Board are shown in the

listings and descriptions in boldface type.

Page 4: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

1

CAMPUS MASTER PLAN OF CAPITAL IMPROVEMENT PROJECTS FOR THE NORMAN CAMPUS I. HIGHEST PRIORITY PROJECTS FOR WHICH STATE FUNDING IS REQUESTED, NORMAN CAMPUS Priority Estimated Number Project Name Total Cost 1 Hester Hall Renovation for College of International Studies $ 13,500,000 2 Fine Arts Center, Rupel Jones Theatre Renovation 5,000,000 3 Classroom Renovation and Improvements 3,000,000 4 Radar Innovations Laboratory 15,800,000 5 Campus Bicycle/Pedestrian Paths 2,000,000 6 Physical Sciences Center Life Safety Improvements 4,000,000 7 Bizzell Memorial Library, Neustadt Wing Lower Level 1 5,000,000 Renovation 8 Research Campus Infrastructure 5,000,000 9 Research and Instructional Equipment 4,000,000 10 Information Technology Improvements 6,000,000 11 Asset Preservation Projects – Level III 32,000,000 II. PROJECTS IN PLANNING, DESIGN OR CONSTRUCTION, FUNDING IDENTIFIED IN FULL OR IN PART, NORMAN CAMPUS Estimated Number Project Name Total Cost 12 Asset Preservation – Level II 13,000,000 13 Multi-Tenant Office Facility No. 4 at Research Campus 36,500,000 (Four Partners Place) 14 Multi-Tenant Office Facility No. 5 at Research Campus 28,000,000 (Five Partners Place) 15 Devon Energy Hall Clean Room 3,000,000 16 Jan Marie and Richard J. Crawford University Club Renovation 4,500,000 17 Scholars Walk/Asp Avenue Reconstruction 10,300,000

Page 5: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

2

18 Arezzo, Monastero Delle Clarisse di Santa Chiara 14,000,000 19 S. J. Sarkeys Complex, Huston Huffman Center Addition 15,000,000 and Locker Rooms Renovation 20 Utility Plant #4 73,000,000 21 Catlett Music Center, Paul F. Sharp Concert Hall Organ 16,000,000 22 Stephenson Life Sciences Research Center, Protein Production 700,000 Core Facility 23 Oklahoma Memorial Union Market 1,700,000 24 Oklahoma Memorial Union Technology Store 2,000,000 25 Acquisition of Property 10,000,000 26 Water Innovative Research Laboratory 15,000,000 27 Headington Hall Student Housing 75,000,000 28 Parking Expansion 5,000,000 29 Campus Streets and Drives 9,500,000 30 Max Westheimer Airport Improvements 13,400,000 31 Bud Wilkinson House/Wagner Dining Hall Renovations 14,000,000 32 Jimmie Austin OU Golf Club Improvements 6,000,000 33 Charlie Coe Golf Learning Center and Team Practice Facilities 4,000,000 34 Gaylord Family-Oklahoma Memorial Stadium Improvements, Phase VI 9,000,000 35 L. Dale Mitchell Baseball Park Expansion and Improvements 4,000,000 36 Softball Facility Expansion and Improvements 4,000,000 37 McCasland Field House Renovation and Improvements, Phase III 5,200,000 38 Varsity Rowing Practice Center 6,500,000 39 Boathouse 6,500,000 40 Emergency Repairs, Renovations and Equipment and 2,540,697 Technology Acquisitions, 2012-13 41 Emergency Repairs, Academic and Administrative Renovations, 1,842,930 and Equipment and Technology Acquisitions, 2013-2014

Page 6: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

3

III. HIGH PRIORITY PROJECTS, FUNDING NOT CURRENTLY AVAILABLE, NORMAN CAMPUS Estimated Number Project Name Total Cost 42 S. J. Sarkeys Complex Addition for Health and Exercise Science $ 10,000,000 43 Chemistry Building Renovation 10,000,000 44 Repository of Art, Public Affairs and History Collections 6,000,000 45 Cate Center Residence Halls Window Replacement 800,000 46 Biological Sciences Building 80,000,000 47 Life Sciences Center, Phase II 50,000,000 48 Armory Renovation 12,000,000 49 Multi-Tenant Light Industrial Facilities, Phase I 16,000,000 50 Kessler Farm Interdisciplinary Field Laboratory 3,000,000 51 Central Theatrical Set and Costume Design Facility 2,000,000 52 School of Art Facilities at Research Campus 10,900,000 53 College of Continuing Education Office Building 32,000,000 54 Fred Jones Art Center Renovation for the School of Art 8,000,000 55 University Research Campus-North Infrastructure Improvements 7,500,000

Page 7: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

4

CAMPUS MASTER PLAN OF CAPITAL IMPROVEMENT PROJECTS FOR THE OKLAHOMA CITY CAMPUS I. HIGHEST PRIORITY PROJECTS FOR WHICH STATE FUNDING IS REQUESTED, OKLAHOMA CITY CAMPUS Priority Estimated Number Project Name Total Cost 1 Campus Fire Sprinkler Systems $ 2,000,000 2 Academic and Administrative 4,426,000 Construction/Renovations 3 Academic and Administrative 21,774,000 Equipment 4 Campus ADA Improvements 872,000 II. PROJECTS IN PLANNING, DESIGN OR CONSTRUCTION, FUNDING IDENTIFIED IN FULL OR IN PART, OKLAHOMA CITY CAMPUS Estimated Number Project Name Total Cost

5 Peggy and Charles Stephenson Cancer Center $ 137,500,000 6 Harold Hamm Diabetes Center Renovation 2,500,000 7 Dentistry Curriculum Redesign & Patient Delivery 20,776,000 System Facilities Remodel, Phases I, II and III

8 Peggy and Charles Stephenson Cancer Center Phase I Clinical 1,128,000 Trials Expansion 9 Basic Sciences Education Building Air Entrainment Project 1,000,000 10 Rogers Building 5th Floor Remodel for IT Office Space 800,000 11 Asset Preservation Improvements 15,232,000 12 Research Park Acquisition 85,000,000 III. HIGH PRIORITY PROJECTS, FUNDING NOT CURRENTLY AVAILABLE, OKLAHOMA CITY CAMPUS Estimated Number Project Name Total Cost 13 Renovation of East and West Lecture Halls in the BSEB $ 1,000,000

Page 8: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

5

14 Public Health Auditorium Renovation 1,700,000 15 Operations Center 6,200,000 16 East Parking Structure 12,000,000 17 David L Boren Student Union 4th Floor Addition 3,000,000

18 Biomedical Sciences Building Laboratory Modernization Project 6,000,000

19 College of Nursing Building Updates 12,000,000 20 G. Rainey Williams Pavilion Renovation and Modernization 3,900,000

Page 9: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

6

CAMPUS MASTER PLAN OF CAPITAL IMPROVEMENT PROJECTS FOR THE TULSA CAMPUS I. HIGHEST PRIORITY PROJECTS FOR WHICH STATE FUNDING IS REQUESTED, TULSA CAMPUS Priority Estimated Number Project Name Total Cost 1 Academic and Administrative $ 2,405,000 Renovations & Equipment 2 Campus Infrastructure 7,511,000 Improvements II. PROJECTS IN PLANNING, DESIGN OR CONSTRUCTION, FUNDING IDENTIFIED IN FULL OR IN PART, TULSA CAMPUS Estimated Number Project Name Total Cost 3 Wayman Tisdale Specialty Health Clinic $18,700,000 4 Schusterman Center Clinic Outpatient Surgery Procedure Suite 300,000

5 OU Physicians Clinical Facilities 2,500,000

III. HIGH PRIORITY PROJECTS, FUNDING NOT CURRENTLY AVAILABLE, TULSA CAMPUS Estimated Number Project Name Total Cost

6 Digital Radiography (DR) Unit $ 93,000 7 Exterior Campus Enhancements 1,500,000 8 Simulation Center 3,750,000 9 Campus Parking Enhancements 400,000 10 Library Phase II 7,575,000 11 East Side Parking Facility 9,000,000

Page 10: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

7

CAMPUS MASTER PLAN OF CAPITAL IMPROVEMENT PROJECTS PROJECT DESCRIPTIONS, NORMAN CAMPUS: The following pages contain additional information about each of the capital projects contained in the preceding Campus Master Plan of Capital Improvements Projects for the Norman Campus. I. HIGHEST PRIORITY PROJECTS FOR WHICH NEW STATE FUNDING IS

REQUESTED, NORMAN CAMPUS 1 Hester Hall Renovation for College of International Studies: This project will provide

limited new construction and the total renovation of Hester Hall for the College of International Studies. The new construction will include an addition on the west façade of the three story element. This addition will become the front door of the College and house a two-story lobby, elevator and open stair. Two new stair towers will be constructed to improve building circulation and provide adequate emergency egress. The three-story element of the building will be renovated to house the Dean’s office, staff offices and a quiet study area on the first floor, with faculty offices and small conference and seminar rooms on the second and third floors. The one-story element will house International Student Services and Education Abroad as well as three classrooms, a seminar room, a formal conference room and the college living room. This project also will update the life safety, HVAC and electrical systems, renovate existing and add new restrooms, and improve accessibility. New windows will be installed and the existing brickwork will be tuckpointed to improve the appearance of the exterior. The estimated total project cost is $13,500,000, with new State funds requested.

2 Fine Arts Center, Rupel J. Jones Theatre Renovation: This project will include

renovation of interior spaces and the supporting mechanical and electrical systems necessary for the continued use of the Rupel Jones Theatre. Stage rigging and flooring will be refurbished, lighting and audio equipment will be upgraded, and curtains replaced. In addition, theatre seating will be replaced and other patron facilities renovated. The estimated total project cost is $5,000,000, with new State funds requested.

3 Classroom Renovation and Improvements: The University's Classroom Renovation Task

Force has recommended implementation of basic minimum standards for classroom configuration in order to address overcrowding and inadequate seating, and to provide the technology necessary for a quality teaching and learning environment. An aggressive program is underway to bring the current 140 centrally scheduled classrooms, comprising over 140,000 net square feet of space, up to the basic standards. This project will provide funding of $3,000,000 for renovations and instructional equipment in a number of classrooms identified as most critically in need of improvement. New State funds are requested.

4 Radar Innovations Laboratory: The Radar Innovations Laboratory will be located on the

University Research Campus south of One Partners Place and east of the National Weather Center. The approximately 36,000-gross-square-foot building will create open working space for research efforts pertaining to the design, assembly and testing of radar system components. The building will provide office space for 20 researchers and up to 60 graduate students, with supporting fabrication shops and test areas. Two anechoic chambers, one for low frequency research and one for high frequency research, will be

Page 11: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

8

installed within the test area. The estimated total project cost is $15,800,000, with new State funds requested.

5 Campus Bicycle/Pedestrian Paths: This project will provide funding of $2,000,000 for

implementation of a bicycle/multimodal transportation system throughout campus. When fully developed, this system will interconnect the campus community and link with the City of Norman beyond. New State funds are requested

6 Physical Sciences Center Life Safety Improvements: This project will include fire

sprinkler and alarms systems, emergency lighting, and other life safety improvements in several areas of the Physical Sciences Center. The estimated total project cost is $4,000,000, with new State funds requested.

7 Bizzell Memorial Library, Neustadt Wing Lower Level 1 Renovation: This project

involves a complete renovation and modernization of approximately 18,000 gross square feet on the Lower Level 1 of the 1983 Neustadt Wing addition. The design supports collaborative student learning spaces, creates classroom and changeable work space areas and includes a variety of individual and group study areas including seminar space, group meeting areas, computer laboratory and facility research areas. The existing Bookmark Café will be renovated and customer seating areas expanded. Restrooms on the floor will also be remodeled and made ADA compliant. The estimated total project cost is $5,000,000, with new State funds requested.

8 Research Campus Infrastructure: The University’s efforts to develop the Research

Campus continues. Some of the remaining infrastructure is in poor condition, and in many instances has been out of use for an extended period of time. The Master Plan for the area is being updated and will be implemented as new building projects are identified. The infrastructure improvements include utilities; site clearing; construction of roads, drives and parking; and information technology systems expansion. This project will provide additional funding of $5,000,000 to prepare the Research Campus for the next phase of development. New State funds are requested.

9 Research and Instructional Equipment: Funds are to be used to purchase new equipment

for teaching and research programs. Purchases are needed to replace, modernize and augment equipment used in classroom and laboratory instruction and in research programs. Part of the equipment will be used to support the teaching and research activities of newly hired faculty including some who will occupy endowed chairs. Funding in the amount of $4,000,000 is proposed from new State funds.

10 Information Technology Improvements: A number of information technology

improvements are needed to address data protection needs at the Norman campus. This project would modernize network security infrastructure by providing high performance firewalls, intrusion prevention systems, network access management, mobile device encryption, compliance management, and secure code analysis enabling the University to manage the risk of data loss and misuse of University resources. New State funds of $6,000,000 are requested.

11 Asset Preservation Projects – Level III: Capital requirements for the preservation of the

University’s facilities and infrastructure have been listed and categorized, including estimates of project costs. The work included in this group of asset preservation projects has been identified as Level III (i.e., condition will allow some further delay, however its delay will result in increased maintenance and operations costs). The projects include deferred maintenance projects, energy conservation work, new and upgraded elevators,

Page 12: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

9

lighting upgrades, roof repair and replacement projects, accessibility improvements, and utility upgrades. The estimated total cost for these projects is $32,000,000 with funding proposed from new State funds.

II. PROJECTS IN PLANNING, DESIGN OR CONSTRUCTION, FUNDING IDENTIFIED

IN FULL OR IN PART, NORMAN CAMPUS 12 Asset Preservation Projects – Level II: Capital requirements for the preservation of the

University’s facilities and infrastructure have been listed and categorized, including estimates of project costs. The work included in this group of asset preservation projects has been identified as Level II (i.e., condition will allow for only a short delay) and is critical in order for University departments to carry out their mission. The projects include deferred maintenance projects, roof repair and replacement projects, new and upgraded elevators, accessibility improvements, and utility upgrades. The estimated total cost for these projects is $13,000,000 with funding from institutional resources and general revenue bond proceeds.

13 Multi-Tenant Office Facility No. 4 at Research Campus (Four Partners Place): This

project will provide approximately 75,000 square feet of space, including general office space for University research programs and which may be leased to entities wishing to locate near other technology resources at the Research Campus. Also included in the new facility will be a Data Center which will consolidate the University’s high performance and mission critical computing assets into a dedicated and secure facility. The new Data Center is intended to house the equipment for the OU Supercomputing Center for Education & Research (OSCER), Department of Physics and Astronomy high energy physics research, and Information Technology’s Network Operations Center. Necessary infrastructure and parking areas associated with the new building will also need to be constructed as part of the project. The estimated total project cost is approximately $36,500,000 to be funded from general revenue bond proceeds.

14 Multi-Tenant Office Facility No. 5 at Research Campus (Five Partners Place): This new

four-story building will provide approximately 100,000 square feet of space, including general office space for University research programs and space which may be leased to entities wishing to locate at the Research Campus. Necessary infrastructure associated with the new building will also need to be constructed as part of the project. The estimated total project cost is approximately $28,000,000 to be funded from general revenue bond proceeds.

15 Devon Energy Hall Clean Room: This project will modify space in Devon Energy Hall

for research that can be conducted only in a highly clean environment. A clean room facility, operated as a University-wide shared resource, will provide capabilities that currently do not exist on campus. The availability of such a facility will substantially enhance opportunities for future research grant funding. The estimated total project cost is approximately $3,000,000 with funding from general revenue bond proceeds.

16 Jan Marie and Richard J. Crawford University Club Renovation: This project will

completely renovate the existing University Club space to make it more efficient, to provide additional and improved kitchen space permitting a larger variety of foods to be prepared and served to patrons, and to make significant improvements to the aesthetic design of the space. As a part of the project, public restrooms serving the club which are located off the adjacent public corridor will be renovated, as will the public corridor. Additionally, the Frontier Room, the Weitzenhoffer Room and the Heritage Room located across the corridor to the west of the club will be refurbished as a part of the

Page 13: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

10

project. The estimated total project cost is $4,500,000 with funding from private sources, general revenue bond proceeds and Section 13/New College funds.

17 Scholars Walk/Asp Avenue Reconstruction: This project will reconstruct VanVleet Oval

into a pedestrian mall north from Lindsey Street to tie into the Brooks Pedestrian Mall. The new mall, to be called Scholars Walk, will feature plaques recognizing the most outstanding honors received by the University’s graduates. The first two statues honoring the University’s most prominent faculty will also be included in this project. In addition, Asp Avenue between Brooks Mall and Lindsey Street will also be reconstructed to become a two-way street with on-street bus loading, staging, and parking as well as a cul-de-sac near Brooks Mall for a turn-around. To accommodate the anticipated improvements in these areas, it will be necessary to relocate the bus staging and transfer area from Asp Avenue and Brooks Street to a new location. Also, a portion of the Botany-Microbiology greenhouse facility will be demolished and the facility will be reconfigured. The estimated total project cost is $10,300,000, with funding to be provided from private sources, general revenue bond proceeds and Section 13/New College funds.

18 Arezzo, Monastero Delle Clarisse di Santa Chiara: This project involves the extensive

renovation of a former monastery in Arezzo, Italy, to create dormitory space for approximately 50 students in combinations of single and double occupancy rooms with bath facilities. The approximately 30,000-gross-square-foot building will also include three classrooms, a library, a dining facility and small kitchen. In addition, a faculty-in-residence apartment and limited administrative space will be created. The project will provide complete utility infrastructure including life safety systems. The exterior of the building will be restored and a new landscaped garden area will be created. Total costs for the renovation are anticipated to be approximately $14,000,000, with funding from private and discretionary resources.

19 S. J. Sarkeys Complex, Huston Huffman Center Addition and Locker Rooms Renovation:

This project involves an approximately 20,000-gross-square-foot addition at Huston Huffman Center for expansion of the general recreation and exercise space in the facility. In addition, the existing men’s and women’s locker rooms would be renovated and modernized. The estimated total project cost is $15,000,000, with funding of $5,000,000 from general revenue bonds supported by student facility fees and $10,000,000 from other sources to be determined.

20 Utility Plant #4: This new utility plant is intended to augment the existing Chilled Water

Plants 1 and 2. With the rapid growth of the campus, the existing plants are nearing full capacity and can no longer be expanded due to site and piping limitations. The new plant was originally identified as a need in the 1997 Norman Campus Utilities Master Plan. The plant will be centrally located just north of the Huston Huffman Center, and will provide chilled water, steam and electricity for expanding campus facilities. The estimated total project cost is $73,000,000, with funding of $72,250,000 from University bond funds and $750,000 from chilled water assessment fees.

21 Catlett Music Center, Paul F. Sharp Concert Hall Organ: This project involves expansion

of the Paul F. Sharp Concert Hall and associated renovations needed to allow for the installation of the University’s Moller organ. Also included is the estimated cost to restore and install the organ (approximately $5,000,000). The estimated total cost is $16,000,000, with funding from private sources.

22 Stephenson Life Sciences Research Center, Protein Production Core Facility: The

renovation plan includes reconfiguration of a two-module laboratory area in the

Page 14: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

11

Stephenson Life Sciences Research Center, on the second floor adjacent to the Macromolecular X-ray and Crystallization Laboratory, creating a Protein Production Core Facility. The renovation for this new facility is associated with a National Institutes of Health grant received to establish a Center of Biomedical Research Excellence in Structural Biology. The reconfiguration will result in a secure stand-alone laboratory with central hallway access. An equipment alcove will be created with additional wall and floor space for laboratory equipment. Also, a number of modifications to existing lab modules adjacent to the PPCF and in other building locations will be made to accommodate the new faculty hired in association with a NIH grant and to relocate the displaced research groups. The estimated total cost for the project is $700,000 with funding provided from NIH grant funds ($220,000) and from the Office of the Vice President for Research ($480,000).

23 Oklahoma Memorial Union Market: This project involves renovation of the space

formerly occupied by Wendy’s to create a modern food services market, providing popular healthy meal, snack and beverage choices. The estimated total project cost is $1,700,000, with funding from Food Services.

24 Oklahoma Memorial Union Technology Store: This project involves renovation of

the space formerly occupied by the Union bookstore to create areas for computer and electronic device sales, accessory sales, support and service for devices. The project will include a training room for workshops and one-on-one training as well as open demonstration space to showcase innovative new technology for students and faculty. The estimated total project cost is $2,000,000, with funding from discretionary University resources.

25 Acquisition of Property: The project will allow the University to facilitate the

strategic and desirable acquisitions of real property as deemed necessary to support the mission of the University. The proposed total budget is $10,000,000, with funding from revenue bond proceeds and other sources.

26 Water Innovative Research Laboratory: The proposed new facility will serve as a

visible front door to the University’s water-related education, research and outreach programs, will showcase water conservation and expand community and global awareness. It will operate as center for collaborative investigative research, provide water-related public services and provide both student and public hands-on education and training. It is anticipated that the building may include offices, laboratories, laboratory support, a water quality testing facility, an active learning classroom, demonstration watershed, display and visualization technology, video-conferencing capabilities, and public learning spaces. The preliminary budget for total project costs is $15,000,000. Funding for preliminary planning and design has been identified from University sources.

27 Headington Hall Student Housing: The proposed new facilities will house students and

student athletes in a combination of two- and four-bed units totaling approximately 380 beds. The building is planned to be a mid-rise structure, with central dining, laundry facilities, computer labs, study rooms, and other support facilities on the ground floor. The project will also include a Faculty-In-Residence apartment. The total project cost is $75,000,000. Funding will be provided through a combination of private and other Athletics Department funds and revenue bonds.

28 Parking Expansion: This project provides ongoing funding for a number of parking lot

projects and includes demolition, site preparation and lot construction. The total project

Page 15: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

12

budget is $5,000,000 with funding from Parking and Transportation auxiliary funds and revenue bond funds.

29 Campus Streets and Drives: This project provides for the repair and resurfacing of a

variety of campus streets, drives, parking areas and other paved surfaces in need of refurbishment. The total project budget is $9,500,000 with funding from general revenue bond proceeds.

30 Max Westheimer Airport Improvements: This project provides for a variety of

improvements to the Max Westheimer Airport that will be required to support its continued maintenance and development. The anticipated work includes the following: (1) construct and light new (west) taxiway; (2) rehabilitate any and all airport pavements to include runways, taxiways, taxi-lanes, aprons and ramp areas (3) construct new air traffic control tower; (4) upgrade security camera system; (5) infrastructure development for north and/or south airport property; (6) update the airport master plan; (7) update the airport layout drawing; (8) expand Terminal Building parking; (9) reconstruct fuel lane and taxi lane adjacent to South Ramp; (10) improve drainage, (11) install/replace runway/taxiway lights and signs as necessary; and (12) other improvements and repairs. The estimated cost of these project elements is $13,400,000 to be funded from a combination of Federal Aviation Administration and Oklahoma Aeronautics Commission grants and airport auxiliary funds, as well as general revenue bonds.

31 Bud Wilkinson House/Wagner Dining Hall Renovation: A study has been

undertaken to assess the viability of repurposing these two buildings for other functions upon the relocation of student housing and dining to Headington Hall. The Athletic Academic Services program is proposed to be relocated from the second floor of the Gaylord Family-Oklahoma Memorial Stadium into Bud Wilkinson House. The existing 29,650 square foot building would be expanded to approximately 42,000 square feet to accommodate the program’s current and future academic needs. The facility would also feature a central stairway and elevator, new façade, and upgrades to restrooms and mechanical and electrical systems. Wagner Dining Hall is proposed to be renovated into a banquet facility for use by the University O-Club and would also serve as a central study hall for student athletes. The remodel would include new interior finishes in the dining area, new equipment designed for catered events in the kitchen, new restrooms, and new mechanical and electrical systems. The estimated total project cost is $14,000,000. Funding for preliminary planning has been identified from Athletics Department sources.

32 Jimmie Austin OU Golf Club Improvements: This project provides a variety of

improvements for the Jimmie Austin Golf Course. Improvements include a relocated maintenance facility, new clubhouse, residential cottages and various course and practice area renovations. Also included are much needed projects to upgrade the irrigation system infrastructure and to repair erosion problems in Bishop Creek and adjoining holes. The project will be developed incrementally over an extended time period. The initial project phase is estimated to cost approximately $6,000,000 with funding from private sources and general revenue bond proceeds.

33 Charlie Coe Golf Learning Center and Team Practice Facilities: The Athletic

Department has identified various team support areas that are needed at the Charlie Coe Golf Learning Center. The improvements include additional equipment storage and workout areas as well as improvement of the practice area. The estimated total project cost is $4,000,000, with funding to be provided from a combination of private and other Athletics Department funds.

Page 16: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

13

34 Gaylord Family Oklahoma Memorial Stadium Improvements, Phase VI: This project

will include continued renovations to the west mezzanine and refurbishment of the east side suites, the Santee Lounge and the Kerr McGee Stadium Club. Also included are maintenance, repairs, and improvements to the east stadium structure. The estimated total cost for the project is $9,000,000, with funding to be provided from Athletics capital funds.

35 L. Dale Mitchell Baseball Park Expansion and Improvements: The Athletic Department

has reviewed and identified the need for updates and improvements to spectator seating, fan amenities, and team facilities at L. Dale Mitchell Baseball Park, with an estimated total cost of $4,000,000, with funding to be provided from a combination of private and other Athletics Department funds.

36 Softball Facility Expansion and Improvements: The Athletic Department has reviewed

and identified the need for updates and improvements to spectator seating, fan amenities, team facilities, and parking expansion and other site improvements at the Softball Facility, with an estimated total cost of $4,000,000, with funding to be provided from a combination of private and other Athletics Department funds.

37 McCasland Field House Renovation and Improvements, Phase III: The primary elements

of this phase of the project are modifications for improved energy efficiency, including window and skylight replacement, and for improved accessibility, including walks and paving around the building’s exterior; structural repairs; roof replacement; and masonry restoration. The estimated total project cost for this phase is$5,200,000, with funding to be provided from a combination of private and other Athletics Department funds.

38 Varsity Rowing Practice Center: Plans call for construction of an approximately 24,000-

square-foot building to provide space to house indoor practice facilities for the women’s intercollegiate rowing team and to consolidate various Athletics Department storage needs. The rowing team facilities will include a rowing tank, team room and meeting spaces, a workout area, lockers/showers, and storage and laundry areas. The proposed new facility is estimated to require a total project budget of approximately $6,500,000, with funding to be provided from private funds within Athletics Department capital accounts.

39 Boathouse: The proposed new boathouse will be located in Oklahoma City near other

existing and future facilities on the Oklahoma River. The facility will include space for storage of shells, oars, ergometers, and other equipment; a changing/locker area with showers; a multi-purpose area for team meetings, workout, etc; a small training/treatment room; an entry lobby and hospitality area; restrooms for men and women; and access to the waterfront. The total estimated cost is $6,500,000, with funding from a combination of private funds and Athletics Department capital funds.

40 Emergency Repairs, Renovations, and Equipment and Technology Acquisitions,

2012-13: This project involves the expenditure of $2,540,697 in FY 2013 Section 13 and New College Funds for emergency repairs to various campus facilities, academic and administrative offices, classroom and laboratory renovations, and equipment and technology acquisitions. These project funds will allow for the implementation of projects as needed in support of a number of capital projects throughout the course of the fiscal year.

41 Emergency Repairs, Academic and Administrative Renovations, and Equipment

and Technology Acquisitions, 2013-14: This project involves the expenditure of

Page 17: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

14

$1,842,930 in FY 2014 Section 13 and New College Funds for emergency repairs to various campus facilities, academic and administrative offices, classroom and laboratory renovations, and equipment and technology acquisitions. These project funds will allow for the implementation of projects as needed in support of a number of capital projects throughout the course of the fiscal year.

III. HIGH PRIORITY PROJECTS, FUNDING NOT CURRENTLY AVAILABLE,

NORMAN CAMPUS 42 S. J. Sarkeys Complex Addition for Health and Exercise Science: This project will

consolidate Department of Health and Exercise Science faculty and students in one location with adequate space. The planned addition to the building will be sized to include approximately 19,550 gross square feet constructed to the south of the existing facility. The addition will provide new lab space, classrooms, and faculty offices, by expanding the existing basement and first floor. The project also includes modifications to the western façade that provides a new front entrance to the building off of Asp Avenue and ties the existing building into the new construction. The total estimated total project cost is $10,000,000.

43 Chemistry Building Renovation: As new facilities for the Department of Chemistry and

Biochemistry are constructed, spaces in existing facilities will be vacated and reprogrammed for other instructional and research uses. Renovation will be required to reconfigure space, upgrade building systems and improve accessibility. The estimated total project cost is approximately $10,000,000.

44 Repository of Art, Public Affairs and History Collections: This proposed new 15,000-

gross-square-foot facility would provide environmentally controlled warehouse space for storage of special arts and humanities collections. Possible building users would be the Carl Albert Center, Western History Collections, Gaylord College of Mass Communications and Journalism, Fred Jones Jr. Museum of Art and the Political Communications Center. The estimated total cost is $6,000,000.

45 Cate Center Residence Halls Window Replacement: New energy-efficient replacement

windows will be installed in Cate Center #2 and #3. In addition to providing energy cost savings, replacement of the windows will provide greater security and enhance the buildings’ appearance. The estimated total project cost is $800,000.

46 Biological Sciences Building: Many of the teaching and research facilities utilized by the

departments of Biology and Microbiology and Plant Biology, and the Oklahoma Biological Survey are outdated and insufficient to meet the needs of undergraduate teaching, research and current safety standards. In addition, the wide dispersal in multiple locations of the activities and faculty in the biological sciences is another significant impediment to accommodating dramatic growth in student numbers and the achievement of goals. The envisioned building would allow centralization of critical facilities and personnel. The plan would provide a new greenhouse and a superior learning environment for students including a new modern lecture hall, modernized research facilities, and open spaces for students, faculty and staff that will enhance opportunities for cross-disciplinary research collaborations and larger group projects. The estimated total project cost is $80,000,000.

47 Life Sciences Center, Phase II: This project will complete the program requirements

necessary to support the instructional and research activities of the Department of Chemistry and Biochemistry, and will ultimately consolidate and integrate the teaching

Page 18: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

15

and student services programs with the research programs to be constructed as Phase I. Phase II will contain approximately 100,000 gross square feet and will provide the department with state-of-the-art teaching laboratories for General, Analytical, Physical, Biological, Quantitative and Organic chemistry; teaching laboratory support and chemical stock room meeting the current life-safety requirements for storage and handling of hazardous materials; student advising and student services areas including an Information Commons, group study spaces and computer lab; and a 150-seat seminar auditorium. The project will also construct a parking structure. The estimated total project cost is $50,000,000.

48 Armory Renovation: This project, with an estimated project cost of $12,000,000, will

renovate the current Armory building to provide much needed and up-to-date classroom space required to teach classes in military science. The project will also make needed code, life safety and accessibility improvements to the building and update the building’s mechanical and electrical systems.

49 Multi-Tenant Light Industrial Facilities, Phase I: This project will provide high bay light

industrial space and office space for University research programs and which may be leased to entities wishing to locate near other technology resources at the University Research Campus. This phase will construct two pods, containing a total of approximately 73,000 gross square feet of space. Planning will include defined areas for additional pods. Necessary infrastructure and parking areas associated with the new buildings will also need to be constructed as part of the project. The estimated total project cost is approximately $16,000,000.

50 Kessler Farm Interdisciplinary Field Laboratory: Dr. Ed Kessler has deeded to The

University of Oklahoma approximately 350 acres of land southwest of Norman to be used as a field research facility. There have been numerous meteorological experiments on the farm over past years. This project is planned to construct a field laboratory building that will provide for preparation of samples prior to bringing them back to the Norman Campus. Also included is a subsequent phase will create a class and meeting area and temporary living quarters to allow researchers to stay at the laboratory while collecting specimens or data. The estimated total project cost is approximately $3,000,000.

51 Central Theatrical Set and Costume Design Facility: This project, with an estimated

project cost of $2,000,000, will construct a facility on the Research Campus which will house a central theatrical set and costume design facility for use by the University’s School of Drama and the Weitzenhoffer Department of Musical Theater.

52 School of Art Facilities at Research Campus: This project will provide improved

facilities for the School of Art and will be located adjacent to the School’s existing Ceramics Studio and Kiln Facility located at the Research Campus. Programs and functions currently utilizing space in the Fred Jones Jr. Memorial Art Center, the Charles M. Russell Center and two World War II vintage buildings at the University Research Campus-North would be consolidated in the new facility. Containing approximately 32,000 square feet of space with an associated project cost of approximately $10,900,000, this new facility would provide space for the School’s sculpture programs, graduate student and faculty studio spaces, and laboratory and studio spaces for the photography program.

53 College of Continuing Education Office Building: A new facility is proposed to replace

old and out-of-date facilities currently in use by the College of Continuing Education. A new building, to be located near existing CCE facilities, would provide expanded

Page 19: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

16

superior quality space to house the College’s programs. Approximately 150,000 gross square feet of flexible office space would provide areas for various program and administrative offices. Necessary infrastructure and a parking structure associated with the new building will also need to be constructed as part of the project. The estimated total project cost is approximately $32,000,000.

54 Fred Jones Art Center Renovation for the School of Art: This project will include

extensive renovation of interior spaces and the supporting mechanical, electrical, and computer and telecommunications systems necessary to modernize the art school facilities. In addition, the facility will be brought into compliance with current fire, life safety, and accessibility codes. Academic spaces for art instruction and other areas will be upgraded for current use and to meet current environmental isolation and health standards. Exterior repairs will be made to restore the building to good condition. The estimated project cost is $8,000,000.

55 University Research Campus-North Infrastructure Improvements: The establishment and

growth of the University Research Campus-North is dependent upon the development of an infrastructure foundation for the property. The University Research Campus-North is comprised of approximately 1,100 acres and organized into two basic elements: Swearingen Research Park and Max Westheimer Airport. This project involves the enhancement and addition to existing infrastructure systems on the east side of the property. Improvements include road construction and repair, street lighting and sidewalks, sewer mains, water distribution systems, storm water detention pond construction, perimeter and street landscaping, construction of primary entrances, and the demolition of several structures necessary to prepare sites for development. The estimated cost for these improvements totals $7,500,000.

Page 20: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

17

PROJECT DESCRIPTIONS, OKLAHOMA CITY CAMPUS: The following pages contain additional information about each of the capital projects contained in the preceding Campus Master Plan of Capital Improvements Projects for the Oklahoma City Campus. I. HIGHEST PRIORITY PROJECTS FOR WHICH NEW STATE FUNDING IS

REQUESTED, OKLAHOMA CITY CAMPUS 1 Campus Fire Sprinkler Systems: This project involves the installation of fire sprinkler

systems across the OUHSC campus including the Biomedical Sciences Building, Library and College of Public Health Building. At the time of their completion, several buildings on campus were not required by code to have full fire protection systems. The project includes the design and installation of fire sprinkler systems and upgrades to fire pumps as necessary. The estimated total project cost is $2,000,000, with funding proposed from new State or bond funds.

2 Academic and Administrative Construction/Renovations: This project involves academic

and administrative construction and renovation projects campus wide. Projects include, flooring for the College Pharmacy building, expansion of College of Pharmacy academic and faculty space, and renovation to student facilities, classrooms, support facilities, and laboratories in various campus buildings. The estimated total project cost is $4,426,000 with funding proposed from new State, grant, Section 13 and New College Funds, and/or department or institutional funds.

3 Academic and Administrative Equipment: This project involves the purchase of

academic and administrative equipment, including instructional, research and clinical equipment as well as moveable interior furnishings. The equipment is necessary to support the teaching, research and service missions of the Health Sciences Center. Equipment will be purchased for the Colleges of Allied Health, Public Health, Dentistry, Medicine, Nursing, and Pharmacy; for the Stanton L. Young Biomedical Research Center and the Information Technology department. The estimated total project cost is $21,774,000 with funding proposed from State, grant, Section 13 and New College Funds, and/or department or institutional funds.

4 Campus ADA Improvements: This project involves the completion of Americans with

Disabilities Act improvements. The priorities established under Phases VI-VIII will be completed and include parking and building access, interior pathways, signage, and other improvements. This will involve all campus facilities. The estimated total project cost is $872,000, with funding proposed from new State or Section 13 and New College Funds.

II. PROJECTS IN PLANNING, DESIGN OR CONSTRUCTION, FUNDING

IDENTIFIED IN FULL OR IN PART, OKLAHOMA CITY CAMPUS 5 Peggy and Charles Stephenson Cancer Center: This project involves the construction of

the Peggy and Charles Stephenson Cancer Center for adults and a separate facility for children at a total project cost of $137,500,000. The seven-story, 213,000 gross square feet adult facility is complete. Minor construction and installation of the Proton Therapy Center equipment and other minor purchases will be necessary using project funds through the Fall of 2013. The facility houses multi-disciplinary clinics, infusion center, space for clinical trials, Radiation Oncology including the Proton Therapy Center with two vaults (one shelled), imaging and related ancillary diagnostic and treatment services,

Page 21: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

18

patient education space, conference rooms, and building support spaces. The 24,600 gross square feet shelled space for the pediatric cancer facility at the OU Children’s Physicians Building is complete. Funding for the Peggy and Charles Stephenson Cancer Center includes bond proceeds supported by the State Tobacco Tax, State appropriations, 2005 OCIA Bond Issue and from private, University and/or other sources. The separately funded pediatric facility involves the use of State appropriated funds and departmental or other funds.

6 Harold Hamm Diabetes Center Renovation: This project involves renovation of the

Harold Hamm Diabetes Center. The building was purchased in 2008 and is in need of renovation to accommodate the Harold Hamm Diabetes Center clinics. Previous phases have been completed renovating 9,400 square feet of clinical space on the 1st and 2nd floors. Current plans will renovate 12,100 square feet on the 1st and 3rd floors and improve the North entrance walkways and driveway. Additional phases will be planned in coordination with needs. The estimated total project cost is $2,500,000 with funding from State and/or other funds.

7 Dentistry Curriculum Redesign & Patient Delivery System Facilities Remodel, Phases I,

II and III: This project involves renovation and reconfiguration of the clinical and administrative areas of the Dental Clinical Sciences Building to be completed in three phases. This is in response to new accreditation standards that support a substantial redesign of the pre-doctoral curriculum and correlated patient care delivery system in the College of Dentistry. The current pre-doctoral curriculum is compressed, inflexible, complex and poorly sequenced. In addition, the current mechanism for screening and assigning patients, treatment planning cases, and providing care is inefficient and cumbersome for patients, students and faculty. In order to address a significant number of these issues, a substantial renovation and reconfiguration of administrative and clinical space is required, along with the purchase and/or replacement of equipment and furniture. Furthermore, areas of the first floor will be renovated to create additional classrooms and student locker and gathering areas. Phase I will renovate the clinical and teaching areas of the third floor and create additional classrooms and student locker and gathering areas on the first floor for approximately $12,100,000; Phase II will renovate the clinical and teaching areas of the second and fourth floors for approximately $4,102,000; and Phase III will renovate the faculty and administrative areas of the fifth floor for approximately $4,574,000. The estimated total project cost is $20,776,000.

8 Peggy and Charles Stephenson Cancer Center Phase I Clinical Trials Expansion:

This project involves the renovation of approximately 5,200 gross square feet to create additional space for the Phase I Clinical Trials on the third floor of the Peggy and Charles Stephenson Cancer Center. The current space for the Phase I Clinical Trials area is already at full capacity and additional space is needed to allow continued growth in the number of trials supported by the Peggy and Charles Stephenson Cancer Center. The estimated total project cost is $1,128,000 with funding from institutional funds.

9 Basic Sciences Education Building Air Entrainment Project: This project will correct

deficiencies associated with exhaust stacks located on the roof of the Basic Sciences Education Building (BSEB). The exhaust stacks on the roof of the BSEB may not properly prevent reentry of the exhausted gases from chemical and biological hoods and other sources. An architectural and engineering study recommended modifications and options that are currently under review. The total cost is estimated not to exceed $1,000,000 with funding proposed from new State, grant, Section 13 and New College Funds, and/or department or institutional funds.

Page 22: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

19

10 Rogers Building 5th Floor Remodel for IT Office Space: This project involves purchasing furniture and equipment to outfit the new office space on the 5th floor of the Rogers Building for Information Technology. Currently IT occupies office space in several locations across the campus. This project will address current space challenges and facilitate the consolidation of IT office space into a single location, fostering an improved collaborative environment to better serve the campus community. Specifically, this project brings IT Applications Services together with IT Operations, Engineering and Security. The estimated total project cost is $800,000.

11 Asset Preservation Improvements: This project involves deferred maintenance and

facility infrastructure improvements to protect the substantial capital assets of the Health Sciences Center. The project involves capital renewal in all major campus facilities, including subsystem repairs and replacements, upgrades to and/or replacement of existing elevators and air handlers, up-grade of fire alarm systems, replacement of the floor in the Stanton L. Young Biomedical Research Center North BSL3 lab, restroom remodels and upgrades, and containment and removal of asbestos. The estimated total cost is $15,232,000, with funding proposed from new State, bond, Section 13 and New College Funds, and/or institutional funds. A five year plan is being implemented to address high priority building improvements with Section 13 and New College Funds and institutional funds. This includes the use of $2,757,000 in previous years Section 13 and New College Funds.

12 Research Park Acquisition: This project is for the purchase of the Presbyterian

Health Foundation Research Park located west of Lincoln Boulevard between N.E. 8th Street and N.E. 4th Street. The purchase includes more than 700,000 square feet of modern biomedical research lab and office space supported by state-of-the-art communications and infrastructure systems. This transaction furthers the shared goal of the University and the Presbyterian Health Foundation to grow biomedical research in the State of Oklahoma to benefit healthcare across the State and nationwide. The University’s purchase of this property will establish a continuing affiliation dedicated to supporting biomedical research, enhancing the infrastructure available to support increasingly successful University research activities and will also support biomedical research companies in their efforts to commercialize new equipment and technologies. The estimated total project cost is $85,000,000, with funding from general obligation bonds and University funds.

III. HIGH PRIORITY PROJECTS, CURRENT FUNDING NOT AVAILABLE,

OKLAHOMA CITY CAMPUS 13 Renovation of East and West Lecture Halls in the BSEB: This project involves the

renovation of approximately 6,100 square feet of the East and West lecture halls at the Basic Sciences Education Building. The renovation of this space is required to be able to increase the medical school class size to 200 students per year. Work will include removing outdated and unnecessary projection booths, revising the ceiling, adding seating in the rear and front of each lecture hall and installing full fire sprinkler coverage in all areas involved in the renovation. Completion of this project will finalize the renovation of the Basic Sciences Education Building. The current estimated total project cost is $1,000,000 with funding proposed from State, grant, Section 13 and New College Funds, and/or department or institutional funds.

14 Public Health Auditorium Renovation: This project involves the renovation of 4,024

square feet of auditorium space in the College of Public Health Building. The 365 seat auditorium will provide state-of-the art distance education and audiovisual technical

Page 23: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

20

capability to support symposia and town hall meetings as the largest auditorium on the University of Oklahoma Health Sciences Center campus. Renovation will include seating, carpeting and fixtures. The estimated total project cost is $1,700,000.

15 Operations Center: This project involves the construction of a 42,100 gross square feet

facility. The facility will house OUHSC Operations, Site Support and related shops, Motor Pool, and other offices. These departments will be relocated from the old Service Center Building. The estimated total project cost is $6,200,000.

16 East Parking Structure: This project involves the construction of a 750 space parking

structure on the east side of the campus. The parking garage is necessary given new construction and growth of the campus. The estimated total project cost is $12,000,000.

17 David L Boren Student Union 4th Floor Addition: This project involves the construction

of a fourth floor addition consisting of approximately 12,000 gross square feet at the David L. Boren Student Union. The fourth floor addition will be constructed to accommodate additional student service’s needs. The estimated total project cost is $3,000,000. The funding involves the use of bond proceeds supported by a student facility fee.

18 Biomedical Sciences Building Laboratory Modernization Project: This project involves

the renovation of approximately 30,000 square feet in the Biomedical Sciences Building. The renovations will eliminate inefficient 1970’s design and construction features, including single pane exterior glazing, perimeter racetrack hallways, and non-modular laboratory design. The project will improve the energy efficiency of the building and provide much needed additional renovated laboratory space with increased space and operational efficiencies. The estimated total project cost is $6,000,000.

19 College of Nursing Building Upgrades: This project involves purchasing equipment,

desks, chairs, and cabling for the College of Nursing Building. These updates are necessary to provide Nursing students with an up-to-date learning environment in order to properly prepare the students of today for the career of tomorrow. All distance education rooms, classrooms and multimedia rooms in the College of Nursing Building are in need of permanent projection screens, fixed furniture with adequate electrical connections to power laptops, mounted projectors connected to lectern podiums, distance education equipment, cameras, and codecs. The estimated total project cost is $12,000,000.

20 G. Rainey Williams Pavilion Renovation and Modernization: This project involves

the renovation of approximately 129,000 square feet of academic office space and expansion and modernization of restrooms in the G. Rainey Williams Pavilion due to the age and condition of the current facility. The estimated total project cost is $3,900,000.

Page 24: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

21

PROJECT DESCRIPTIONS, TULSA CAMPUS: The following pages contain additional information about each of the capital projects contained in the preceding Campus Master Plan of Capital Improvements Projects for the University of Oklahoma - Tulsa Campus. I. HIGHEST PRIORITY PROJECTS FOR WHICH NEW STATE FUNDING IS

REQUESTED, TULSA CAMPUS 1 Academic and Administrative Renovations and Equipment: This project involves various

renovation projects and the purchase of equipment for the Schusterman Center. The project includes renovation for academic and administrative units, including the OU-Tulsa President’s Office, cafeteria remodeling, Innovations Commons, addition of a small kitchenette and for campus-wide Information Technology. Renovations and the acquisition of equipment will involve offices, research laboratories, and video technology. The estimated total cost is $2,405,000 in new State or other funds.

2 Campus Infrastructure Improvements: This project involves various physical plant

projects. They include replacement of 25 to 36-year-old, inefficient chillers that have reached their useful life expectancy. Additionally, the project includes replacement of the aging Uninterrupted Power Supply (UPS) that serves the network and telephone systems, roof replacement on several buildings, rebuilding of older PAUs (primary air units) in the main building, card key system upgrade, asbestos abatement, water pipe replacement, building pressurization and humidity control, covering switchyard and condition space, parking lots, replacing all windows in building 1 and carpet, replacing amplifiers and all smoke detectors and adding new ramps for ADA-compliancy. The estimated total cost is $7,511,000. Funding would be provided from bond issues or new State funds.

II. PROJECTS IN PLANNING, DESIGN OR CONSTRUCTION, FUNDING

IDENTIFIED IN FULL OR IN PART, TULSA CAMPUS 3 Wayman Tisdale Specialty Health Clinic: This project involves the construction of a

45,500 gross square feet building at an estimated total cost of $18,700,000. The clinic will be located in the North Tulsa area to expand medical care. The plan for the advanced outpatient health care facility will include urgent care, advanced MRI and CT services, and chemotherapy. The funding plan involves the use of $1,500,000 from 2006 SB 90XX, $2,875,000 from 2007 state legislation, $13,000,000 from private donations, $1,000,000 from an emergency medicine grant, and $325,000 in other funds.

4 Schusterman Center Clinic Outpatient Surgery Procedure Suite: This project involves an

interior remodel of approximately 3,000 square feet in the first floor of the Schusterman Center Clinic to create an outpatient surgery and endoscopy suite for minor outpatient surgical procedures. The estimated total project cost is $300,000 with funding from departmental funds.

5 OU Physicians Clinical Facilities: This project involves the renovation and

updating of clinical facilities and the furniture, fixtures, and equipment within these areas as needed from the wear of heavy patient traffic as well as clinical space usage being renovated due to a change in the clinical specialty needs. Clinical funds will be used to fund these projects as identified. The estimated total cost is $2,500,000 over 5 years.

Page 25: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

22

III. HIGH PRIORITY PROJECTS, CURRENT FUNDING NOT AVAILABLE, TULSA CAMPUS

6 Digital Radiography (DR) Unit: This project would purchase and install a digital

radiograph with a PACS unit in laboratory space allotted to the Department of Medical Imaging and Radiation Sciences, Tulsa, to replace an outdated unit. The radiography faculty use diagnostic radiographic units and phantoms to teach basic physics, positioning and techniques to students. The current laboratory has an outdated single unit. This unit does not have digital capabilities. Digital imaging is a standard format in the clinical affiliates of the program. A digital unit for teaching is needed to allow students to transition from laboratory practice to affiliate clinical practicum easier and successfully. The College of Allied Health in Tulsa is requesting an up-to-date integrated digital radiography (DR) unit to replace the current out dated unit. No additional shielding is required. The estimated total project cost is $93,000.

7 Exterior Campus Enhancements: This project involves a pedestrian pathway, exterior

signage, repaving of the east parking lot, cooling tower screen, and a landscape garden. The pedestrian pathway will provide safety improvement for access between the main building, Learning Center, and Schusterman Library. The estimated total project cost is $1,500,000.

8 Simulation Center: This project involves the development of 10,000 gross square feet for

a Simulation Center. The Simulation Center will allow for a complete range of simulations in multiple settings, including standardized patients, human patient simulators, task trainers, computer-based and web-based instruction, Virtual Reality Trainers, and other simulated environments. This will involve an integrated computer and video management system to allow for data collection and analysis for the simulated learning experiences. The Center will be used to educate third and fourth-year medical students, Physician Assistant students, residents, and students in nursing and pharmacy. The estimated total project cost is $3,750,000.

9 Campus Parking Enhancements: This project involves street and parking improvements.

Additional on-street and surface parking around campus will be provided, as well as necessary sidewalks and improved signage. Campus landscape beautification projects including tree replacements and additional benches as well as streetscape enhancements will be undertaken. The estimated total cost is $400,000 with funding from Foundation funds.

10 Library Phase II: Following the completion of the OU-Tulsa Schusterman Center Library

construction project in 2011, and keeping with the OU-Tulsa Campus Plan, an anticipated 20,000 square foot expansion of the original building would include many key features that were scaled back or eliminated from Phase I planning. These features would include additional learning clusters and Commons space for students; an information literacy computer lab to keep pace with the library’s expanding educational role on campus; an educational technology center to help faculty and students more fully adopt and better utilize distance education technologies; additional collections space for non-traditional and historic materials; additional group study and student conference rooms; individual study carrels; office space for traveling faculty from Norman and Oklahoma City; improved writing center facilities; and a full-featured library café and reading nook. The estimated total cost is $7,575,000.

11 East Side Parking Facility: This project involves the construction of a parking structure

with up to 500 spaces adjacent to the Learning Center and Library. This project is

Page 26: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

May 9-10, 2013

23

needed when all other new facilities, including the Library are completed. The estimated total project cost is $9,000,000.

Page 27: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each
Page 28: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0161

Printed: 06-17-2013

LONG-RANGE CAPITAL PLANNING COMMISSIONAGENCY SUMMARY BY PRIORITY

Fiscal Years 2015 through 2019

FY - 2015 Budget Request Capital Outlay Summary, Pg. 1

1

2

3

4

5

6

7

8

9

10

11

12

Hester Hall Renov, College Int'l Studies

Fine Arts Ctr, Rupel Jones Theatre Renov

Classroom Renovation and Improvements

Radar Innovations Laboratory

Campus Bicycle/Pedestrian Paths

Physical Sciences Ctr Life SafetyImprov

Bizzell Memorial Library, LL1 Renovation

Research Campus Infrastructure

Research and Instructional Equipment

Information Technology Improvements

Asset Preservation Projects - Level III

Asset Preservation Projects - Level II

760-0201

760-0078

760-0230

760-0301

760-0255

760-0268

760-0317

760-0124

760-0012

760-0020

760-0140

760-0139

0

0

0

0

0

0

0

0

0

0

0

0

13,500,000

5,000,000

3,000,000

15,800,000

2,000,000

4,000,000

5,000,000

5,000,000

4,000,000

6,000,000

32,000,000

0

0

0

0

0

0

0

0

0

0

0

0

13,000,000

Agency: University of Oklahoma

Priority Name of Project: Proj. #FederalFunds

OtherFunds

StateApprop

TotalProject

13,500,000

5,000,000

3,000,000

15,800,000

2,000,000

4,000,000

5,000,000

5,000,000

4,000,000

6,000,000

32,000,000

13,000,000

760

Page 29: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0161

Printed: 06-17-2013

LONG-RANGE CAPITAL PLANNING COMMISSIONAGENCY SUMMARY BY PRIORITY

Fiscal Years 2015 through 2019

FY - 2015 Budget Request Capital Outlay Summary, Pg. 2

13

14

15

16

17

18

19

20

21

22

23

24

25

Multi-Tenant Off Fac #4 at Res Campus

Multi-Tenant Off Fac #5 at Res Campus

Devon Energy Hall Clean Room

Crawford University Club Renovation

Scholars Walk/Asp Avenue Reconstruction

Arezzo, Monastero

Sarkeys Complex, Huffman Add/Locker Rms

Utility Plant #4

Catlett Music, Sharp Concert HallOrgan

Stephenson Life Sci, Protein ProdFac

Oklahoma Memorial Union Market

Oklahoma Memorial Union Technology Store

Acquisition of Property

760-0271

760-0304

760-0293

760-0305

760-0306

760-0308

760-0298

760-0251

760-0299

760-0324

760-0318

760-0319

760-0320

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

36,500,000

28,000,000

3,000,000

4,500,000

10,300,000

14,000,000

15,000,000

73,000,000

16,000,000

700,000

1,700,000

2,000,000

10,000,000

Agency: University of Oklahoma

Priority Name of Project: Proj. #FederalFunds

OtherFunds

StateApprop

TotalProject

36,500,000

28,000,000

3,000,000

4,500,000

10,300,000

14,000,000

15,000,000

73,000,000

16,000,000

700,000

1,700,000

2,000,000

10,000,000

760

Page 30: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0161

Printed: 06-17-2013

LONG-RANGE CAPITAL PLANNING COMMISSIONAGENCY SUMMARY BY PRIORITY

Fiscal Years 2015 through 2019

FY - 2015 Budget Request Capital Outlay Summary, Pg. 3

26

27

28

29

30

31

32

33

34

35

36

37

38

Water Innovative Research Laboratory

Headington Hall Student Housing

Parking Expansion

Campus Streets and Drives

Max Westheimer Airport Improv

Wilkinson House/Wagner Dining Hall Renov

Jimmie Austin OU Golf Club Improvements

Coe Golf Learning Ctr & Team Practice

Gaylord Fam Okla Mem Stadium Impr, Ph VI

L. Dale Mitchell Baseball Park Exp & Imp

Softball Facility Expansion & Improv

McCasland Field House Renov & ImpPh III

Varsity Rowing Practice Center

760-0321

760-0278

760-0241

760-0289

760-0033

760-0322

760-0309

760-0239

760-0310

760-0256

760-0257

760-0273

760-0311

0

0

0

0

10,720,000

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

15,000,000

75,000,000

5,000,000

9,500,000

2,680,000

14,000,000

6,000,000

4,000,000

9,000,000

4,000,000

4,000,000

5,200,000

6,500,000

Agency: University of Oklahoma

Priority Name of Project: Proj. #FederalFunds

OtherFunds

StateApprop

TotalProject

15,000,000

75,000,000

5,000,000

9,500,000

13,400,000

14,000,000

6,000,000

4,000,000

9,000,000

4,000,000

4,000,000

5,200,000

6,500,000

760

Page 31: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0161

Printed: 06-17-2013

LONG-RANGE CAPITAL PLANNING COMMISSIONAGENCY SUMMARY BY PRIORITY

Fiscal Years 2015 through 2019

FY - 2015 Budget Request Capital Outlay Summary, Pg. 4

39

40

41

42

43

44

45

46

47

48

49

50

51

52

Boat House

Emer Repair Renov Equip & Tech Acq 12-13

Emer Repair Renov Equip & Tech Acq 13-14

Sarkeys Complex, Health/Exercise Science

Chemistry Building Renovation

Repository of Collections

Cate Center Window Replacement

Biological Sciences Building

Life Sciences Center, Phase II

Armory Renovation

Multi-Tenant Light Industrial FacPh I

Kessler Farm Interdisciplinary Field Lab

Central Theatrical Set & Costume Design

School of Art Fac at Res Campus

760-0279

760-0312

760-0323

760-0302

760-0259

760-0303

760-0285

760-0292

760-0220

760-0270

760-0272

760-0249

760-0253

760-0236

0

0

0

0

0

0

0

0

0

0

0

2,950,000

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

6,500,000

2,540,697

1,842,930

10,000,000

10,000,000

6,000,000

800,000

80,000,000

50,000,000

12,000,000

16,000,000

50,000

2,000,000

10,900,000

Agency: University of Oklahoma

Priority Name of Project: Proj. #FederalFunds

OtherFunds

StateApprop

TotalProject

6,500,000

2,540,697

1,842,930

10,000,000

10,000,000

6,000,000

800,000

80,000,000

50,000,000

12,000,000

16,000,000

3,000,000

2,000,000

10,900,000

760

Page 32: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0161

Printed: 06-17-2013

LONG-RANGE CAPITAL PLANNING COMMISSIONAGENCY SUMMARY BY PRIORITY

Fiscal Years 2015 through 2019

FY - 2015 Budget Request Capital Outlay Summary, Pg. 5

53

54

55

College of Continuing Education Off Bldg

Fred Jones Art Ctr Renov-School of Art

Univ Research Campus-No. Infrastructure

760-0222

760-0077

760-0032

0

0

0

0

0

0

32,000,000

8,000,000

7,500,000

Agency: University of Oklahoma

Priority Name of Project: Proj. #FederalFunds

OtherFunds

StateApprop

TotalProject

32,000,000

8,000,000

7,500,000

760

13,670,000 643,713,627 95,300,000 752,683,627Totals:

Page 33: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each
Page 34: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 74 FY-2015 Budget Request

760 06-10-2013

760-0201 Hester Hall Renov, College Int'l Studies

729 Elm Ave

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Appropriated

30

1

Renovation

This project will provide limited new construction and the total renovation of Hester Hall for the College of International Studies. The new construction will include an addition on the west façade ofthe three story element. This addition will become the front door of the College and house a two-story lobby, elevator and open stair. Two new stair towers will be constructed to improve building circulation and provide adequate emergency egress. The three story element of the building will be

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 35: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 75 FY-2015 Budget Request

760 06-10-2013

760-0201 Hester Hall Renov, College Int'l Studies

renovated to house the Dean's office, staff offices and a quiet study area on the first floor, with faculty offices and small conference and seminar rooms on the second and third floors. The one-story element will house International Student Services and Education Abroad as well as three classrooms, a seminar room, a formal conference room and the college living room. This project also will update thelife safety, HVAC and electrical systems, renovate existing and add new restrooms, and improve accessibility. New windows will be installed and the existing brickwork will be tuckpointed to improve the appearance of the exterior.

Programs of the College of International Studies have been located in a variety of locations on the Norman Campus. Consolidation in one building will provide opportunities for collaborative efforts andmake these types of initiatives easier to implement. Consolidation will also provide for more effective administration of the College.

This project will provide renovated space to meet the needs of the newly created College of International Studies. For the first time, all international programming, including the International and Area Studies academic program, education abroad, and International Student Services will be housed under one roof. A major priority of the University is internationalization of the University's curriculum and other offerings with the goal of producing students with a keen understanding of other cultures and points of view, necessary to succeed in the global environment of the 21st century.

No

Yes

Part 1 of the project was funded in 2005 from $2,730,463 in State Bonds.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

(con't)

Page 36: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 76 FY-2015 Budget Request

760 06-10-2013

760-0201 Hester Hall Renov, College Int'l Studies

Up-to-date equipment to be used for teaching will be available for use by students and faculty.

Educational programs will be adversely affected. If postponed, equipment and renovation will cost more due to inflation.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

Page 37: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 77 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0201 Hester Hall Renov, College Int'l Studies

11,200,000

11,200,000

8,600,000

700,000

1,900,000

11,200,000

2,300,000

2,300,000

500,000

1,700,000

100,000

2,300,000

0

0

0

0

13,500,000

0

0

0

0

0

0

0

0

13,500,000

1,200,000

10,300,000

2,000,000

13,500,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 38: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 78 FY-2015 Budget Request

760 06-10-2013

760-0201 Hester Hall Renov, College Int'l Studies

New State funds requested

Construction Manager, GMP - 05/01/2013

41,571

247.77

10,300,046.67

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 39: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 79 FY-2015 Budget Request

760 06-10-2013

760-0201 Hester Hall Renov, College Int'l Studies

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

a. Please give a dollar estimate of the annual operational savings generated by or increasesrequired by this project for the next five years.

Type of DollarSavings

State Dollars:

Federal Dollars:

Other Dollars:

Total:

Net Total:

FY - 2015 FY - 2016

FY - 2017 2018

2019 & Total

Type of Dollar

Increases

State Dollars:

Federal Dollars:

Ohter Dollars:

Total:

Page 40: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 80 FY-2015 Budget Request

760 06-10-2013

760-0201 Hester Hall Renov, College Int'l Studies

Economical building systems should result in more economical operation of this space. There are no additional operating costs associated with this project.

N/A

N/A

The renovation work will provide construction jobs for an approximately 20-month period. Architectural and engineering consultants will be selected to provide planning and documentation for the project. Audio/visual equipment and other furnishings will be purchased for the project.

Michael K. Moorman 4053256006

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

b. Explain changes in operating costs and number of state employees as a result of funding this project.

c. Will the agency be able to fund operating costs and employee increases without additional state

d. Explain the impact on state tax revenue or fee revenue, if any.

Detail the private sector economic impact or job creation for the area location of the project and/or the State. Specify both temporary jobs (e.g. Construction) and permanent jobs. Show how estimates were obtained.

Contact person: Contact phone number:

appropriations?

(Criteria D)

Page 41: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 81 FY-2015 Budget Request

760 06-10-2013

760-0201 Hester Hall Renov, College Int'l Studies

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Additional comments:

Page 42: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 82 FY-2015 Budget Request

760 06-10-2013

760-0201 Hester Hall Renov, College Int'l Studies

1 4

0 0

4 12

2 6

3 9

3 6

5 10

2 4

51

44.35

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Criteria/Rating ScaleScoreRange

Score A

Weight B

Total(A*B)

A. Overall fiscal impact/cost effectiveness 0 - 05 4

B. Legal obligation and mandates/addresses public

health/safety

0 - 05 4

C. Impact on service to the public 0 - 05 3

D. Economic impact/job creation -02 - 05 3

E. Urgency of maintenance needs/addresses public

health/safety

0 - 05 3

F. Whether prior phases have been funded or

partially funded

0 - 05 2

G. Departmental priority 01 - 05 2

H. Impact on the use of technology -02 - 05 2

Total Rating Points

Total Percentage Points (Total Rating Pts/115*100)

Page 43: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 41 FY-2015 Budget Request

760 06-10-2013

760-0078 Fine Arts Ctr, Rupel Jones Theatre Renov

563 Elm Avenue

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Appropriated

30

2

Renovation

This project will include renovation of interior spaces and the supporting mechanical and electrical systems necessary for the continued use of the Rupel Jones Theatre. Stage rigging and flooring will be refurbished, lighting and audio equipment will be upgraded, and curtains replaced. In addition, theatre seating will be replaced and other patron facilities renovated.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 44: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 42 FY-2015 Budget Request

760 06-10-2013

760-0078 Fine Arts Ctr, Rupel Jones Theatre Renov

Making Rupel Jones Theatre safe and bringing this heavily used facility to a higher standard vis-a-vis competing university facilities will bring an importantant advantage for the Weitzenhoffer College of Fine Arts' recruiting, teaching, and performance quality.Theatrical systems will be upgraded to a more professional and safe condition, including wiring and lighting, audio systems, stage lift hydraulics, stage rigging and stage floor. ADA and other code compliance items such as restrooms and elevators will be addressed. When funding allows, theatre seating and other theatre and lobby comfort and aesthetic improvements, including flooring and finisheswill be undertaken.

No

No

Yes. Current theatre technologies will be implemented (audio, intelligent lighting).

Educational programs will be adversely affected. If postponed, equipment and renovation will cost more due to inflation.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

Page 45: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 43 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0078 Fine Arts Ctr, Rupel Jones Theatre Renov

200,000

200,000

200,000

200,000

4,800,000

4,800,000

800,000

3,700,000

300,000

4,800,000

0

0

0

0

5,000,000

0

0

0

0

0

0

0

0

5,000,000

800,000

3,700,000

500,000

5,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 46: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 44 FY-2015 Budget Request

760 06-10-2013

760-0078 Fine Arts Ctr, Rupel Jones Theatre Renov

New State funds requested

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 47: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 45 FY-2015 Budget Request

760 06-10-2013

760-0078 Fine Arts Ctr, Rupel Jones Theatre Renov

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

a. Please give a dollar estimate of the annual operational savings generated by or increasesrequired by this project for the next five years.

Type of DollarSavings

State Dollars:

Federal Dollars:

Other Dollars:

Total:

Net Total:

FY - 2015 FY - 2016

FY - 2017 2018

2019 & Total

Type of Dollar

Increases

State Dollars:

Federal Dollars:

Ohter Dollars:

Total:

Page 48: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 46 FY-2015 Budget Request

760 06-10-2013

760-0078 Fine Arts Ctr, Rupel Jones Theatre Renov

There are no aditional operating costs associated with this project.

N/A

N/A

The renovation work will provide construction jobs for an approximate 12-month period. Architectural and engineering consultants will be selected to provide planning and documentation for the project. Equipment will be purchased for the project.

Michael K Moorman 4053256006

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

b. Explain changes in operating costs and number of state employees as a result of funding this project.

c. Will the agency be able to fund operating costs and employee increases without additional state

d. Explain the impact on state tax revenue or fee revenue, if any.

Detail the private sector economic impact or job creation for the area location of the project and/or the State. Specify both temporary jobs (e.g. Construction) and permanent jobs. Show how estimates were obtained.

Contact person: Contact phone number:

appropriations?

(Criteria D)

Page 49: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 47 FY-2015 Budget Request

760 06-10-2013

760-0078 Fine Arts Ctr, Rupel Jones Theatre Renov

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Additional comments:

Page 50: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 48 FY-2015 Budget Request

760 06-10-2013

760-0078 Fine Arts Ctr, Rupel Jones Theatre Renov

0 0

0 0

4 12

2 6

3 9

0 0

5 10

3 6

43

37.39

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Criteria/Rating ScaleScoreRange

Score A

Weight B

Total(A*B)

A. Overall fiscal impact/cost effectiveness 0 - 05 4

B. Legal obligation and mandates/addresses public

health/safety

0 - 05 4

C. Impact on service to the public 0 - 05 3

D. Economic impact/job creation -02 - 05 3

E. Urgency of maintenance needs/addresses public

health/safety

0 - 05 3

F. Whether prior phases have been funded or

partially funded

0 - 05 2

G. Departmental priority 01 - 05 2

H. Impact on the use of technology -02 - 05 2

Total Rating Points

Total Percentage Points (Total Rating Pts/115*100)

Page 51: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 99 FY-2015 Budget Request

760 06-10-2013

760-0230 Classroom Renovation and Improvements

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Appropriated

20

3

Renovation

The University's Classroom Renovation Task Force has recommended implementation of basic minimum standards for classroom configuration in order to address overcrowding and inadequate seating, and to provide the technology necessary for a quality teaching and learning environment. An aggressive program is underway to bring the current 140 centrally scheduled classrooms, comprising over 140,000 net square feet of space, up to the basic standards. This project will provide funding for

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 52: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 100 FY-2015 Budget Request

760 06-10-2013

760-0230 Classroom Renovation and Improvements

renovations and instructional equipment in a number of classrooms identified as most critically in need of improvement.

This project will address overcrowding, inadequate seating, and provide the technology necessary for a quality teaching and learning environment. An aggressive program is necessary to bring the current 131centrally scheduled classrooms, comprising over 120,000 net square feet of space, up to the basic standards. This project will begin that process. This project will help a number of schools and departments achieve goals identified in the University's Strategy for Excellence.

n/a

Yes

Section 13 and New College Funds and other University funds have been utilized for classroom renovations over the past several years. The 2005 State Bond provided $2,500,000.

Up-to-date equipment to be used for teaching will be available for use by students and faculty.

Educational programs will be adversely affected. If postponed, equipment and renovation will cost more due to inflation.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 53: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 101 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0230 Classroom Renovation and Improvements

0

0

1,550,000

1,550,000

500,000

1,000,000

50,000

1,550,000

1,450,000

1,450,000

400,000

1,000,000

50,000

1,450,000

0

0

3,000,000

0

0

0

0

0

0

0

0

3,000,000

900,000

2,000,000

100,000

3,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 54: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 102 FY-2015 Budget Request

760 06-10-2013

760-0230 Classroom Renovation and Improvements

New State funds requested

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 55: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 103 FY-2015 Budget Request

760 06-10-2013

760-0230 Classroom Renovation and Improvements

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

a. Please give a dollar estimate of the annual operational savings generated by or increasesrequired by this project for the next five years.

Type of DollarSavings

State Dollars:

Federal Dollars:

Other Dollars:

Total:

Net Total:

FY - 2015 FY - 2016

FY - 2017 2018

2019 & Total

Type of Dollar

Increases

State Dollars:

Federal Dollars:

Ohter Dollars:

Total:

Page 56: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 104 FY-2015 Budget Request

760 06-10-2013

760-0230 Classroom Renovation and Improvements

New lighting systems should result in more economical operation of classrooms. There are no additional operating costs associated with this project.

N/A

N/A

Renovation will provide construction jobs for an approximate 24-month period. Movable and scientific equipment and furnishings will be purchased for the project.

Michael K. Moorman 4053256006

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

b. Explain changes in operating costs and number of state employees as a result of funding this project.

c. Will the agency be able to fund operating costs and employee increases without additional state

d. Explain the impact on state tax revenue or fee revenue, if any.

Detail the private sector economic impact or job creation for the area location of the project and/or the State. Specify both temporary jobs (e.g. Construction) and permanent jobs. Show how estimates were obtained.

Contact person: Contact phone number:

appropriations?

(Criteria D)

Page 57: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 105 FY-2015 Budget Request

760 06-10-2013

760-0230 Classroom Renovation and Improvements

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Additional comments:

Page 58: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 106 FY-2015 Budget Request

760 06-10-2013

760-0230 Classroom Renovation and Improvements

2 8

0 0

5 15

1 3

3 9

3 6

5 10

4 8

59

51.30

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Criteria/Rating ScaleScoreRange

Score A

Weight B

Total(A*B)

A. Overall fiscal impact/cost effectiveness 0 - 05 4

B. Legal obligation and mandates/addresses public

health/safety

0 - 05 4

C. Impact on service to the public 0 - 05 3

D. Economic impact/job creation -02 - 05 3

E. Urgency of maintenance needs/addresses public

health/safety

0 - 05 3

F. Whether prior phases have been funded or

partially funded

0 - 05 2

G. Departmental priority 01 - 05 2

H. Impact on the use of technology -02 - 05 2

Total Rating Points

Total Percentage Points (Total Rating Pts/115*100)

Page 59: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 291 FY-2015 Budget Request

760 06-10-2013

760-0301 Radar Innovations Laboratory

Proposed new facility at Research Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

50

4

New

The Radar Innovations Laboratory will be located on the University Research Campus south of One Partners Place and east of the National Weather Center. The approximately 36,000-gross-square-foot building will create open working space for research efforts pertaining to the design, assembly and testing of radar system components. The building will provide office space for 20 researchers and up to 60 graduate students, with supporting fabrication shops and test areas. Two anechoic chambers, one

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 60: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 292 FY-2015 Budget Request

760 06-10-2013

760-0301 Radar Innovations Laboratory

for low frequency research and one for high frequency research, will be installed within the test area.

The Radar Innovations Laboratory will serve as the core facility for OU's growing radar program. Currently, 16 faculty members and over 60 students make up this active research center, who are currently spread across campus in several buildings. Bringing this vibrant ground together will greatly enhance collaboration, education, and will take the program to the national level in terms of overall prominence.

No

No

Yes, radar development involves in-depth design, fabrication, and test of complex electronics. The Radar Innovations Laboratory will provide the facilities necessary for such development, including sophisticated anechoic chambers, micro fabrication room, and extensive microwave test areas.

Based on a foundation in weather radar, The University of Oklahoma's overall radar program is now expanding into other areas of radar, including defense, security, and intelligence. With this investment, the program is on the verge of becoming a dominant force on the national stage. The timing is perfect to build this facility, and any delay would stifle the progress, especially in terms

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 61: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 293 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0301 Radar Innovations Laboratory

of recruiting excellent faculty and keeping top students in Oklahoma.

15,800,000

15,800,000

12,500,000

1,700,000

1,600,000

15,800,000

0

0

0

0

0

0

15,800,000

0

0

0

0

0

0

0

0

15,800,000

1,700,000

12,500,000

1,600,000

15,800,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

What is the effect of delaying this project or maintenance schedule? (Criteria E)

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

(con't)

Page 62: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 294 FY-2015 Budget Request

760 06-10-2013

760-0301 Radar Innovations Laboratory

New State funds requested

Construction Manager, GMP - 05/01/13

36,092

335.25

12,099,843.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 63: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 295 FY-2015 Budget Request

760 06-10-2013

760-0301 Radar Innovations Laboratory

0

374996

374996

0

393764

393764

0

1253475

1253475

0

0

0

2022235

0

0

0

2022235

2022235

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

a. Please give a dollar estimate of the annual operational savings generated by or increasesrequired by this project for the next five years.

Type of DollarSavings

State Dollars:

Federal Dollars:

Other Dollars:

Total:

Net Total:

FY - 2015 FY - 2016

FY - 2017 2018

2019 & Total

Type of Dollar

Increases

State Dollars:

Federal Dollars:

Ohter Dollars:

Total:

Page 64: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 296 FY-2015 Budget Request

760 06-10-2013

760-0301 Radar Innovations Laboratory

The radar program currently has several industry collaborations with companies such as EEC, Lockheed Martin, Raytheon, Weathernews, and CGI. This role of the University has been a priority and was one of the main reasons to expand the program into all applications of radar. It is important to evolve Oklahoma's economy into high technology, and radar is an area where a good foundation has been build and the pay off is beginning to be realized.

In addition, approximately $12 million of construction work will provide construction jobs for an approximate 12-month period. Architectural and engineering consultants will be selected to provide planning and documentation for the project.

Michael K. Moorman 4053256006

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

b. Explain changes in operating costs and number of state employees as a result of funding this project.

c. Will the agency be able to fund operating costs and employee increases without additional state

d. Explain the impact on state tax revenue or fee revenue, if any.

Detail the private sector economic impact or job creation for the area location of the project and/or the State. Specify both temporary jobs (e.g. Construction) and permanent jobs. Show how estimates were obtained.

Contact person: Contact phone number:

appropriations?

(Criteria D)

Page 65: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 297 FY-2015 Budget Request

760 06-10-2013

760-0301 Radar Innovations Laboratory

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Additional comments:

Page 66: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 298 FY-2015 Budget Request

760 06-10-2013

760-0301 Radar Innovations Laboratory

0 0

0 0

4 12

5 15

0 0

0 0

5 10

5 10

47

40.87

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Criteria/Rating ScaleScoreRange

Score A

Weight B

Total(A*B)

A. Overall fiscal impact/cost effectiveness 0 - 05 4

B. Legal obligation and mandates/addresses public

health/safety

0 - 05 4

C. Impact on service to the public 0 - 05 3

D. Economic impact/job creation -02 - 05 3

E. Urgency of maintenance needs/addresses public

health/safety

0 - 05 3

F. Whether prior phases have been funded or

partially funded

0 - 05 2

G. Departmental priority 01 - 05 2

H. Impact on the use of technology -02 - 05 2

Total Rating Points

Total Percentage Points (Total Rating Pts/115*100)

Page 67: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 155 FY-2015 Budget Request

760 06-10-2013

760-0255 Campus Bicycle/Pedestrian Paths

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Appropriated

20

5

This project will provide funding of $2,000,000 for implementation of a bicycle/multimodal transportation system throughout campus. When fully developed, this system will interconnect the campus community and link with the City of Norman beyond.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 68: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 156 FY-2015 Budget Request

760 06-10-2013

760-0255 Campus Bicycle/Pedestrian Paths

The safety of students, faculty/staff and visitors will be considerably enhanced by implementation of new bikeway facilities and programs which will decrease vehicle congestion and minimize conflicts between bicycles, pedistrians and vehicles. Pedestrian and bicycle travel will become easier, quicker and more convenient via a comprehensive set of non-motorized connections in and around the campus. Project should help to encourage walking and bicycling and curtail the need to construct new parking facilities. In addition, a healthier campus environment will result from improved air quality and a lowering of the overall level of noise.

No

Yes

University revenue bonds 2010, $580,000

No

Safety and health concerns associated with vehicle congestion will not be addressed.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 69: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 157 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0255 Campus Bicycle/Pedestrian Paths

150,000

150,000

110,000

40,000

150,000

1,850,000

1,850,000

1,400,000

450,000

1,850,000

0

0

0

0

2,000,000

0

0

0

0

0

0

0

0

2,000,000

0

1,510,000

490,000

2,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 70: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 158 FY-2015 Budget Request

760 06-10-2013

760-0255 Campus Bicycle/Pedestrian Paths

New State funds requested

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 71: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 159 FY-2015 Budget Request

760 06-10-2013

760-0255 Campus Bicycle/Pedestrian Paths

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

a. Please give a dollar estimate of the annual operational savings generated by or increasesrequired by this project for the next five years.

Type of DollarSavings

State Dollars:

Federal Dollars:

Other Dollars:

Total:

Net Total:

FY - 2015 FY - 2016

FY - 2017 2018

2019 & Total

Type of Dollar

Increases

State Dollars:

Federal Dollars:

Ohter Dollars:

Total:

Page 72: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 160 FY-2015 Budget Request

760 06-10-2013

760-0255 Campus Bicycle/Pedestrian Paths

NA

NA

NA

Approximately $1.5 million of work will provide construction jobs for an approximate 12-month period. Architectural and engineering consultants will be selected to provide planning and documentation for the project.

Michael K. Moorman 4053256006

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

b. Explain changes in operating costs and number of state employees as a result of funding this project.

c. Will the agency be able to fund operating costs and employee increases without additional state

d. Explain the impact on state tax revenue or fee revenue, if any.

Detail the private sector economic impact or job creation for the area location of the project and/or the State. Specify both temporary jobs (e.g. Construction) and permanent jobs. Show how estimates were obtained.

Contact person: Contact phone number:

appropriations?

(Criteria D)

Page 73: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 161 FY-2015 Budget Request

760 06-10-2013

760-0255 Campus Bicycle/Pedestrian Paths

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Additional comments:

Page 74: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 162 FY-2015 Budget Request

760 06-10-2013

760-0255 Campus Bicycle/Pedestrian Paths

2 8

0 0

3 9

2 6

4 12

4 8

5 10

0 0

53

46.09

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Criteria/Rating ScaleScoreRange

Score A

Weight B

Total(A*B)

A. Overall fiscal impact/cost effectiveness 0 - 05 4

B. Legal obligation and mandates/addresses public

health/safety

0 - 05 4

C. Impact on service to the public 0 - 05 3

D. Economic impact/job creation -02 - 05 3

E. Urgency of maintenance needs/addresses public

health/safety

0 - 05 3

F. Whether prior phases have been funded or

partially funded

0 - 05 2

G. Departmental priority 01 - 05 2

H. Impact on the use of technology -02 - 05 2

Total Rating Points

Total Percentage Points (Total Rating Pts/115*100)

Page 75: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 187 FY-2015 Budget Request

760 06-10-2013

760-0268 Physical Sciences Ctr Life Safety Improv

601 Elm Avenue

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Appropriated

25

6

Renovation

This project will include fire sprinkler and alarms systems, emergency lighting, and other life safetyimprovements in several areas of the Physical Sciences Center.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 76: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 188 FY-2015 Budget Request

760 06-10-2013

760-0268 Physical Sciences Ctr Life Safety Improv

The safety of students, faculty/staff and visitors to campus is paramount and will be addressed by lifesafety improvements in this high-rise building located in the central campus area.

Yes. Current Life Safety Code would require a building of this type to be fully sprinkled.

Yes

University revenue bond funds in the approximately amount of $240,000 were expended for fire sprinkler,fire alarm and emergency lighting in a portion of the building renovated in 2011/2012.

Yes. Advanced technology will for voice emergency notification in the building.

The high-rise building will remain unsprinkled.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 77: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 189 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0268 Physical Sciences Ctr Life Safety Improv

0

0

100,000

100,000

100,000

100,000

3,900,000

3,900,000

3,200,000

700,000

3,900,000

0

0

4,000,000

0

0

0

0

0

0

0

0

4,000,000

0

3,200,000

800,000

4,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 78: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 190 FY-2015 Budget Request

760 06-10-2013

760-0268 Physical Sciences Ctr Life Safety Improv

New State funds requested

University staff - 05/01/13

182,963

17.49

3,200,022.87

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 79: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 191 FY-2015 Budget Request

760 06-10-2013

760-0268 Physical Sciences Ctr Life Safety Improv

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

a. Please give a dollar estimate of the annual operational savings generated by or increasesrequired by this project for the next five years.

Type of DollarSavings

State Dollars:

Federal Dollars:

Other Dollars:

Total:

Net Total:

FY - 2015 FY - 2016

FY - 2017 2018

2019 & Total

Type of Dollar

Increases

State Dollars:

Federal Dollars:

Ohter Dollars:

Total:

Page 80: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 192 FY-2015 Budget Request

760 06-10-2013

760-0268 Physical Sciences Ctr Life Safety Improv

NA

NA

NA

Approximately $3.2 million of renovation work will provide construction jobs for an approximate 10-month period. Architectural and engineering consultants will be selected to provide planning and documentation for the project.

Michael K. Moorman 4053256006

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

b. Explain changes in operating costs and number of state employees as a result of funding this project.

c. Will the agency be able to fund operating costs and employee increases without additional state

d. Explain the impact on state tax revenue or fee revenue, if any.

Detail the private sector economic impact or job creation for the area location of the project and/or the State. Specify both temporary jobs (e.g. Construction) and permanent jobs. Show how estimates were obtained.

Contact person: Contact phone number:

appropriations?

(Criteria D)

Page 81: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 193 FY-2015 Budget Request

760 06-10-2013

760-0268 Physical Sciences Ctr Life Safety Improv

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Additional comments:

Page 82: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 194 FY-2015 Budget Request

760 06-10-2013

760-0268 Physical Sciences Ctr Life Safety Improv

2 8

3 12

4 12

1 3

4 12

3 6

5 10

2 4

67

58.26

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Criteria/Rating ScaleScoreRange

Score A

Weight B

Total(A*B)

A. Overall fiscal impact/cost effectiveness 0 - 05 4

B. Legal obligation and mandates/addresses public

health/safety

0 - 05 4

C. Impact on service to the public 0 - 05 3

D. Economic impact/job creation -02 - 05 3

E. Urgency of maintenance needs/addresses public

health/safety

0 - 05 3

F. Whether prior phases have been funded or

partially funded

0 - 05 2

G. Departmental priority 01 - 05 2

H. Impact on the use of technology -02 - 05 2

Total Rating Points

Total Percentage Points (Total Rating Pts/115*100)

Page 83: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 379 FY-2015 Budget Request

760 06-12-2013

760-0317 Bizzell Memorial Library, LL1 Renovation

401 W. Brooks Street

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

25

7

Renovation

This project involves a complete renovation and modernization of approximately 20,000 gross square feet on the Lower Level 1 of the 1983 Neustadt Wing addition. Seating capacity in the space will increase from 224 to approximately 525. The design includes creation of a variety of individual and group study areas including seminar space, group meeting areas, digital humanities laboratory, video creation lab and faculty research areas. The existing Bookmark Café will be renovated and expanded.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 84: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 380 FY-2015 Budget Request

760 06-12-2013

760-0317 Bizzell Memorial Library, LL1 Renovation

Restrooms on the floor will also be remodeled and made ADA compliant.

The project will modify the building in order to support collaborative student learning spaces, and creation of an innovative classroom and flexible work space areas. This initial renovation project will be the first step in modernizing the facility and its technology to make it more suitable for use by students and faculty.

The space to be renovated in LL1 currently provides 225 seats for student use. The reconfigured space, while gaining far greater flexibility, will provide support for about 400-425 students. More important than significantly increasing the number of seats, the project extends the ability of the library to support new learning modalities, namely student group and collaborative work. Additional benefit include: Community meeting room which can support lectures, symposia, etc., and thereby extend the Library's ability to engage our community as a part of being the "intellectual commons" of the university; digital scholarship lab which supports new cross-disciplinary work in the humanities and social sciences; and video conferencing capabilities to support collaboration with remote participants or groups.

No

Yes

A fire protection project totaling $4.7 million was completed in Bizzell Library in 2008.

Yes, the project will incorporate the latest in data, fiber and audio-video technologies for lecture rooms, group and individual study areas and for researchers. The 21st Century research library must

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

(con't)

Page 85: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 381 FY-2015 Budget Request

760 06-12-2013

760-0317 Bizzell Memorial Library, LL1 Renovation

support a wide spectrum of rapidly advancing technologies. The LL1 renovation is designed to begin toaddress the gap we experience today. The project advances the University Libraries ability to supportthe following:Improvements in current technology infrastructure (basic infrastructure);Collaborative group work equipmentDigital humanities laboratory developmentVisualization of geographical information systemsAudio recording roomsCollaborative classroomsVideo conferencing

Delaying ths project would compound the shortage of reader and study space in Bizzell. The facility experiences full utilization during the period prior to final examinations. Delaying the project would cause a loss of much needed momentum to promote the long-term vision to modernize the entire Library system at the University of Oklahoma.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 86: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 382 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0317 Bizzell Memorial Library, LL1 Renovation

5,000,000

5,000,000

3,000,000

1,300,000

700,000

5,000,000

0

0

0

0

0

0

5,000,000

0

0

0

0

0

0

0

0

5,000,000

1,300,000

3,000,000

700,000

5,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 87: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 383 FY-2015 Budget Request

760 06-12-2013

760-0317 Bizzell Memorial Library, LL1 Renovation

New State funds requested

Project Architects - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 88: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 384 FY-2015 Budget Request

760 06-12-2013

760-0317 Bizzell Memorial Library, LL1 Renovation

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

a. Please give a dollar estimate of the annual operational savings generated by or increasesrequired by this project for the next five years.

Type of DollarSavings

State Dollars:

Federal Dollars:

Other Dollars:

Total:

Net Total:

FY - 2015 FY - 2016

FY - 2017 2018

2019 & Total

Type of Dollar

Increases

State Dollars:

Federal Dollars:

Ohter Dollars:

Total:

Page 89: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 385 FY-2015 Budget Request

760 06-12-2013

760-0317 Bizzell Memorial Library, LL1 Renovation

N/A

N/A

N/A

The renovation work will provide construction jobs for an approximate 8-month period. Architectural and engineering consultants will provide planning and documentation for the project. Equipment and furnishings will be purchased for the project.

Michael K Moorman 4053256006

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

b. Explain changes in operating costs and number of state employees as a result of funding this project.

c. Will the agency be able to fund operating costs and employee increases without additional state

d. Explain the impact on state tax revenue or fee revenue, if any.

Detail the private sector economic impact or job creation for the area location of the project and/or the State. Specify both temporary jobs (e.g. Construction) and permanent jobs. Show how estimates were obtained.

Contact person: Contact phone number:

appropriations?

(Criteria D)

Page 90: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 386 FY-2015 Budget Request

760 06-12-2013

760-0317 Bizzell Memorial Library, LL1 Renovation

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Additional comments:

Page 91: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 387 FY-2015 Budget Request

760 06-12-2013

760-0317 Bizzell Memorial Library, LL1 Renovation

0 0

0 0

4 12

2 6

3 9

4 8

5 10

5 10

55

47.83

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Criteria/Rating ScaleScoreRange

Score A

Weight B

Total(A*B)

A. Overall fiscal impact/cost effectiveness 0 - 05 4

B. Legal obligation and mandates/addresses public

health/safety

0 - 05 4

C. Impact on service to the public 0 - 05 3

D. Economic impact/job creation -02 - 05 3

E. Urgency of maintenance needs/addresses public

health/safety

0 - 05 3

F. Whether prior phases have been funded or

partially funded

0 - 05 2

G. Departmental priority 01 - 05 2

H. Impact on the use of technology -02 - 05 2

Total Rating Points

Total Percentage Points (Total Rating Pts/115*100)

Page 92: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 49 FY-2015 Budget Request

760 06-10-2013

760-0124 Research Campus Infrastructure

University Research Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Appropriated

30

8

New

The University's efforts to develop the Research Campus continues. Some of the remaining infrastructure is in poor condition, and in many instances has been out of use for an extended period of time. The Master Plan for the area is being updated and will be implemented as new building projects are identified. The infrastructure improvements include utilities; site clearing; construction of roads, drives and parking; and information technology systems expansion.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 93: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 50 FY-2015 Budget Request

760 06-10-2013

760-0124 Research Campus Infrastructure

This project will allow critically needed research and teaching space to be constructed. Students and faculty will benefit from a much improved environment for learning and research that is being created at the University Research campus. Economic growth will be continue to be stimulated by development ofprivate and public facilities.

No

Yes

Approximately $20.5 million has been expended on University Research Campus infrastructure improvementsin Fiscal Years 2003 to 2011. Funding for this work was provided from University of Oklahoma sources including revenue bond funds, from a $1.25 million federal grant from the Economic Development Administration, and from 2005 State Bond funds. Additional infrastructure development also has been undertaken in order to connect newly constructed facilities with existing infrastructure systems.

Yes. Vital new facilities have recently been completed or are under construction at the Research Campus. The National Weather Ctr houses federal NOAA research programs as well as the University's meteorological research programs. The Stephenson Research & Technology Ctr has been designed to be a catalyst and showcase for modern cross-disciplinary research. Occupants of the building include OU's world-class faculty and program in gene sequencing and in functional genomics and the Okla Super Computer for Education and Research. Two facilities were recently completed, and a third is under construction, creating space leased to a private firms, e.g., one that utilizes and develops sophisticated weather information/analyses systems. The Stephenson Life Sciences Research Ctr is currently under construction. To support this growth, it is necessary that infrastructure be planned and constructed to provide utilities, roads, parking and telecommunications for the new facilities.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

Page 94: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 51 FY-2015 Budget Request

760 06-10-2013

760-0124 Research Campus Infrastructure

Development of the University Research Campus, which has been jump started by initial construction of the National Weather Center, the Stephenson Research and Technology Center and the Multi-tenant OfficeFacilities, will be delayed. It is extremely important that the momentum of this early development bemaintained in order to attract new technologies and economic enterprises to the state.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

What is the effect of delaying this project or maintenance schedule? (Criteria E)

Page 95: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 52 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0124 Research Campus Infrastructure

0

0

0

0

2,500,000

2,500,000

2,250,000

250,000

2,500,000

2,500,000

2,500,000

2,250,000

250,000

2,500,000

5,000,000

0

0

0

0

0

0

0

0

5,000,000

0

4,500,000

500,000

5,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 96: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 53 FY-2015 Budget Request

760 06-10-2013

760-0124 Research Campus Infrastructure

New State funds requested

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 97: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 54 FY-2015 Budget Request

760 06-10-2013

760-0124 Research Campus Infrastructure

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

a. Please give a dollar estimate of the annual operational savings generated by or increasesrequired by this project for the next five years.

Type of DollarSavings

State Dollars:

Federal Dollars:

Other Dollars:

Total:

Net Total:

FY - 2015 FY - 2016

FY - 2017 2018

2019 & Total

Type of Dollar

Increases

State Dollars:

Federal Dollars:

Ohter Dollars:

Total:

Page 98: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 55 FY-2015 Budget Request

760 06-10-2013

760-0124 Research Campus Infrastructure

N/A

N/A

New businesses located at the University Research Park should have a positive impact on state tax revenue.

The combination of technological advances from expanded public and private research and the associatedopportunities for employment, in conjunction with an increase in the number of graduates from high quality University programs, will enhance economic development within the State. A number of construction contracts will provide associated construction jobs. Engineering consultants will provide planning and documentation for the infrastructure projects.

Michael K Moorman 4053256006

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

b. Explain changes in operating costs and number of state employees as a result of funding this project.

c. Will the agency be able to fund operating costs and employee increases without additional state

d. Explain the impact on state tax revenue or fee revenue, if any.

Detail the private sector economic impact or job creation for the area location of the project and/or the State. Specify both temporary jobs (e.g. Construction) and permanent jobs. Show how estimates were obtained.

Contact person: Contact phone number:

appropriations?

(Criteria D)

Page 99: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 56 FY-2015 Budget Request

760 06-10-2013

760-0124 Research Campus Infrastructure

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Additional comments:

Page 100: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 57 FY-2015 Budget Request

760 06-10-2013

760-0124 Research Campus Infrastructure

3 12

0 0

4 12

5 15

3 9

4 8

5 10

5 10

76

66.09

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Criteria/Rating ScaleScoreRange

Score A

Weight B

Total(A*B)

A. Overall fiscal impact/cost effectiveness 0 - 05 4

B. Legal obligation and mandates/addresses public

health/safety

0 - 05 4

C. Impact on service to the public 0 - 05 3

D. Economic impact/job creation -02 - 05 3

E. Urgency of maintenance needs/addresses public

health/safety

0 - 05 3

F. Whether prior phases have been funded or

partially funded

0 - 05 2

G. Departmental priority 01 - 05 2

H. Impact on the use of technology -02 - 05 2

Total Rating Points

Total Percentage Points (Total Rating Pts/115*100)

Page 101: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 1 FY-2015 Budget Request

760 06-10-2013

760-0012 Research and Instructional Equipment

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Appropriated

10

9

Funds are to be used to purchase new equipment for teaching and research programs. Purchases are needed to replace, modernize and augment equipment used in classroom and laboratory instruction and inresearch programs. Part of the equipment will be used to support the teaching and research activitiesof newly hired faculty including some who will occupy endowed chairs.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 102: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 2 FY-2015 Budget Request

760 06-10-2013

760-0012 Research and Instructional Equipment

This project will replace, modernize and augment equipment used in classroom and laboratory instructionand in research programs. This equipment will help a number of schools and departments achieve goals identified in the University's Strategy for Excellence.

No

Yes

Section 13 and New College Funds in an annual amount of $300,000 or more have been allocated in severalrecent years for research and instructional equipment.

Up-to-date equipment to be used for teaching and research will be available for use by students and faculty.

Educational programs will be adversely affected. If postponed, equipment will cost more due to inflation.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

Page 103: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 3 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0012 Research and Instructional Equipment

0

0

0

0

0

0

4,000,000

4,000,000

4,000,000

4,000,000

4,000,000

0

0

0

0

0

0

0

0

4,000,000

4,000,000

0

0

4,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 104: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 4 FY-2015 Budget Request

760 06-10-2013

760-0012 Research and Instructional Equipment

New State funds requested

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 105: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 5 FY-2015 Budget Request

760 06-10-2013

760-0012 Research and Instructional Equipment

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

a. Please give a dollar estimate of the annual operational savings generated by or increasesrequired by this project for the next five years.

Type of DollarSavings

State Dollars:

Federal Dollars:

Other Dollars:

Total:

Net Total:

FY - 2015 FY - 2016

FY - 2017 2018

2019 & Total

Type of Dollar

Increases

State Dollars:

Federal Dollars:

Ohter Dollars:

Total:

Page 106: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 6 FY-2015 Budget Request

760 06-10-2013

760-0012 Research and Instructional Equipment

N/A

N/A

N/A

N/A

Michael K Moorman 4053256006

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

b. Explain changes in operating costs and number of state employees as a result of funding this project.

c. Will the agency be able to fund operating costs and employee increases without additional state

d. Explain the impact on state tax revenue or fee revenue, if any.

Detail the private sector economic impact or job creation for the area location of the project and/or the State. Specify both temporary jobs (e.g. Construction) and permanent jobs. Show how estimates were obtained.

Contact person: Contact phone number:

appropriations?

(Criteria D)

Page 107: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 7 FY-2015 Budget Request

760 06-10-2013

760-0012 Research and Instructional Equipment

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Additional comments:

Page 108: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 8 FY-2015 Budget Request

760 06-10-2013

760-0012 Research and Instructional Equipment

2 8

0 0

3 9

0 0

3 9

3 6

5 10

4 8

50

43.48

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Criteria/Rating ScaleScoreRange

Score A

Weight B

Total(A*B)

A. Overall fiscal impact/cost effectiveness 0 - 05 4

B. Legal obligation and mandates/addresses public

health/safety

0 - 05 4

C. Impact on service to the public 0 - 05 3

D. Economic impact/job creation -02 - 05 3

E. Urgency of maintenance needs/addresses public

health/safety

0 - 05 3

F. Whether prior phases have been funded or

partially funded

0 - 05 2

G. Departmental priority 01 - 05 2

H. Impact on the use of technology -02 - 05 2

Total Rating Points

Total Percentage Points (Total Rating Pts/115*100)

Page 109: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 9 FY-2015 Budget Request

760 06-10-2013

760-0020 Information Technology Improvements

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Appropriated

10

10

A number of information technology improvements are needed to address data protection needs at the Norman campus. This project would modernize network security infrastructure by providing high performance firewalls, intrusion prevention systems, network access management, mobile device encryption, compliance management, and secure code analysis enabling the University to manage the riskof data loss and misuse of University resources.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 110: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 10 FY-2015 Budget Request

760 06-10-2013

760-0020 Information Technology Improvements

This project will help to accomplish one of the key goals identified by the University. It is necessaryto keep computer services and capabilities up to date to meet the academic and research requirements ofthe University. It is also neccessary to secure the University's data resources, including student andemployee personal data.

No

No

Project increases the technological capabilities of The University of Oklahoma enabling further securenetwork and wireless connection of computing resources and sharing of computer generated data. Equipment and systems will be purchased promoting private-sector development of advanced telecommunications and computing technologies.

Needed computer equipment and software will not be available to meet the academic and research needs of the University. Inflation will cause project costs to increase.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

Page 111: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 11 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0020 Information Technology Improvements

0

0

0

0

0

0

6,000,000

6,000,000

6,000,000

6,000,000

6,000,000

0

0

0

0

0

0

0

0

6,000,000

6,000,000

0

0

6,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 112: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 12 FY-2015 Budget Request

760 06-10-2013

760-0020 Information Technology Improvements

New State funds requested

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 113: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 13 FY-2015 Budget Request

760 06-10-2013

760-0020 Information Technology Improvements

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

a. Please give a dollar estimate of the annual operational savings generated by or increasesrequired by this project for the next five years.

Type of DollarSavings

State Dollars:

Federal Dollars:

Other Dollars:

Total:

Net Total:

FY - 2015 FY - 2016

FY - 2017 2018

2019 & Total

Type of Dollar

Increases

State Dollars:

Federal Dollars:

Ohter Dollars:

Total:

Page 114: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 14 FY-2015 Budget Request

760 06-10-2013

760-0020 Information Technology Improvements

N/A

N/A

N/A

Computer equipment will be purchased from vendors.

Michael K Moorman 4053256006

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

b. Explain changes in operating costs and number of state employees as a result of funding this project.

c. Will the agency be able to fund operating costs and employee increases without additional state

d. Explain the impact on state tax revenue or fee revenue, if any.

Detail the private sector economic impact or job creation for the area location of the project and/or the State. Specify both temporary jobs (e.g. Construction) and permanent jobs. Show how estimates were obtained.

Contact person: Contact phone number:

appropriations?

(Criteria D)

Page 115: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 15 FY-2015 Budget Request

760 06-10-2013

760-0020 Information Technology Improvements

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Additional comments:

Page 116: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 16 FY-2015 Budget Request

760 06-10-2013

760-0020 Information Technology Improvements

2 8

0 0

3 9

0 0

2 6

0 0

5 10

5 10

43

37.39

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Criteria/Rating ScaleScoreRange

Score A

Weight B

Total(A*B)

A. Overall fiscal impact/cost effectiveness 0 - 05 4

B. Legal obligation and mandates/addresses public

health/safety

0 - 05 4

C. Impact on service to the public 0 - 05 3

D. Economic impact/job creation -02 - 05 3

E. Urgency of maintenance needs/addresses public

health/safety

0 - 05 3

F. Whether prior phases have been funded or

partially funded

0 - 05 2

G. Departmental priority 01 - 05 2

H. Impact on the use of technology -02 - 05 2

Total Rating Points

Total Percentage Points (Total Rating Pts/115*100)

Page 117: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 66 FY-2015 Budget Request

760 06-11-2013

760-0140 Asset Preservation Projects - Level III

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Appropriated

30

11

Renovation

Capital requirements for the preservation of the University's facilities and infrastructure have been listed and categorized, including estimates of project costs. The work included in this group of asset preservation projects has been identified as Level III (i.e., condition will allow some further delay, however its delay will result in increased maintenance and operations costs). The projects include deferred maintenance projects, energy conservation work, new and upgraded elevators, lighting

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 118: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 67 FY-2015 Budget Request

760 06-11-2013

760-0140 Asset Preservation Projects - Level III

upgrades, roof repair and replacement projects, accessibility improvements, and utility upgrades.

Life safety, accessibility for disabled individuals, and user comfort (including enhanced lighting) will be addressed through implementation of this project.

Life safety code and ADA accessibility issues will be addressed.

No

Delay will result in increased maintenance and operations costs.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 119: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 68 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0140 Asset Preservation Projects - Level III

0

0

0

0

0

0

32,000,000

32,000,000

9,500,000

20,850,000

1,650,000

32,000,000

32,000,000

0

0

0

0

0

0

0

0

32,000,000

9,500,000

20,850,000

1,650,000

32,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 120: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 69 FY-2015 Budget Request

760 06-11-2013

760-0140 Asset Preservation Projects - Level III

New State funds requested

University staff and engineering consultant - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 121: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 70 FY-2015 Budget Request

760 06-11-2013

760-0140 Asset Preservation Projects - Level III

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

a. Please give a dollar estimate of the annual operational savings generated by or increasesrequired by this project for the next five years.

Type of DollarSavings

State Dollars:

Federal Dollars:

Other Dollars:

Total:

Net Total:

FY - 2015 FY - 2016

FY - 2017 2018

2019 & Total

Type of Dollar

Increases

State Dollars:

Federal Dollars:

Ohter Dollars:

Total:

Page 122: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 71 FY-2015 Budget Request

760 06-11-2013

760-0140 Asset Preservation Projects - Level III

N/A

N/A

N/A

Contracts and purchase orders will be awarded for purchase and installation of equipment. Engineeringconsultants will be selected to provide project documentation.

Michael K Moorman 4053256006

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Fiscal Impact: (Criteria A)

b. Explain changes in operating costs and number of state employees as a result of funding this project.

c. Will the agency be able to fund operating costs and employee increases without additional state

d. Explain the impact on state tax revenue or fee revenue, if any.

Detail the private sector economic impact or job creation for the area location of the project and/or the State. Specify both temporary jobs (e.g. Construction) and permanent jobs. Show how estimates were obtained.

Contact person: Contact phone number:

appropriations?

(Criteria D)

Page 123: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 72 FY-2015 Budget Request

760 06-11-2013

760-0140 Asset Preservation Projects - Level III

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Additional comments:

Page 124: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 73 FY-2015 Budget Request

760 06-11-2013

760-0140 Asset Preservation Projects - Level III

3 12

0 0

2 6

1 3

3 9

0 0

5 10

0 0

40

34.78

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Criteria/Rating ScaleScoreRange

Score A

Weight B

Total(A*B)

A. Overall fiscal impact/cost effectiveness 0 - 05 4

B. Legal obligation and mandates/addresses public

health/safety

0 - 05 4

C. Impact on service to the public 0 - 05 3

D. Economic impact/job creation -02 - 05 3

E. Urgency of maintenance needs/addresses public

health/safety

0 - 05 3

F. Whether prior phases have been funded or

partially funded

0 - 05 2

G. Departmental priority 01 - 05 2

H. Impact on the use of technology -02 - 05 2

Total Rating Points

Total Percentage Points (Total Rating Pts/115*100)

Page 125: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 58 FY-2015 Budget Request

760 06-11-2013

760-0139 Asset Preservation Projects - Level II

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

30

12

Renovation

Capital requirements for the preservation of the University's facilities and infrastructure have been listed and categorized, including estimates of project costs. The work included in this group of asset preservation projects has been identified as Level II (i.e., condition will allow for only a short delay) and is critical in order for University departments to carry out their mission. The projects include deferred maintenance projects, roof repair and replacement projects, new and upgraded

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 126: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 59 FY-2015 Budget Request

760 06-11-2013

760-0139 Asset Preservation Projects - Level II

elevators, accessibility improvements, and utility upgrades.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 127: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 60 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0139 Asset Preservation Projects - Level II

5,400,000

5,400,000

4,000,000

1,000,000

400,000

5,400,000

5300000

5,300,000

1,000,000

4,000,000

300,000

5,300,000

2,300,000

2,300,000

600,000

1,600,000

100,000

2,300,000

0

0

0

0

0

13,000,000

0

0

0

0

0

13,000,000

2,600,000

9,600,000

800,000

13,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 128: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 61 FY-2015 Budget Request

760 06-11-2013

760-0139 Asset Preservation Projects - Level II

Revolving funds and University revenue bond funds

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 129: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 203 FY-2015 Budget Request

760 06-10-2013

760-0271 Multi-Tenant Off Fac #4 at Res Campus

301 David L. Boren Blvd

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

50

13

New

This project will provide approximately 79,975 square feet of space, including general office space for University research programs and which may be leased to entities wishing to locate near other technology resources at the Research Campus. Also included in the new facility will be a Data Center which will consolidate the University's high performance and mission critical computing assets into a dedicated and secure facility. The new Data Center is intended to house the equipment for the OU

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 130: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 204 FY-2015 Budget Request

760 06-10-2013

760-0271 Multi-Tenant Off Fac #4 at Res Campus

Supercomputing Center for Education & Research (OSCER), Department of Physics and Astronomy high energy physics research, and Information Technology's Network Operations Center. Necessary infrastructure and parking areas associated with the new building will also need to be constructed as part of the project.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 131: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 205 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0271 Multi-Tenant Off Fac #4 at Res Campus

36,500,000

36,500,000

29,500,000

1,200,000

5,800,000

36,500,000

0

0

0

0

0

0

0

0

0

0

0

36,500,000

0

0

0

36,500,000

1,200,000

29,500,000

5,800,000

36,500,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 132: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 206 FY-2015 Budget Request

760 06-10-2013

760-0271 Multi-Tenant Off Fac #4 at Res Campus

University revenue bond funds

Actual construction contract - 05/01/13

79,975

368.86

29,499,578.50

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 133: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 315 FY-2015 Budget Request

760 06-10-2013

760-0304 Multi-Tenant Off Fac #5 at Res Campus

University Research Campus, proposed new facility

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

14

New

This new four-story building will provide approximately 100,000 square feet of space, including general office space for University research programs and space which may be leased to entities wishing to locate at the Research Campus. Necessary infrastructure associated with the new building will also need to be constructed as part of the project.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 134: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 317 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0304 Multi-Tenant Off Fac #5 at Res Campus

23,000,000

23,000,000

20,000,000

3,000,000

23,000,000

5,000,000

5,000,000

100,000

4,000,000

900,000

5,000,000

0

0

0

0

0

0

0

0

0

28,000,000

0

0

0

28,000,000

100,000

24,000,000

3,900,000

28,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 135: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 318 FY-2015 Budget Request

760 06-10-2013

760-0304 Multi-Tenant Off Fac #5 at Res Campus

University revenue bond funds

Construction Manager, GMP - 05/01/13

108,937

220.31

23,999,910.47

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 136: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 267 FY-2015 Budget Request

760 06-10-2013

760-0293 Devon Energy Hall Clean Room

110 W. Boyd Street

Norman

Statewide

44

16

3

8

Pending

50

15

Renovation

This project will modify space in Devon Energy Hall for research that can be conducted only in a highly clean environment. A clean room facility, operated as a University-wide shared resource, will provide capabilities that currently do not exist on campus. The availability of such a facility will substantially enhance opportunities for future research grant funding.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 137: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 269 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0293 Devon Energy Hall Clean Room

3,000,000

3,000,000

2,500,000

200,000

300,000

3,000,000

0

0

0

0

0

0

0

0

0

0

0

3,000,000

0

0

0

3,000,000

200,000

2,500,000

300,000

3,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 138: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 270 FY-2015 Budget Request

760 06-10-2013

760-0293 Devon Energy Hall Clean Room

University revenue bond funds

Actual construction contract - 05/10/13

3,000

833.33

2,499,990.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 139: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 323 FY-2015 Budget Request

760 06-10-2013

760-0305 Crawford University Club Renovation

900 Asp Avenue

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

30

16

Renovation

This project will completely renovate the existing University Club space to make it more efficient, toprovide additional and improved kitchen space permitting a larger variety of foods to be prepared and served to patrons, and to make significant improvements to the aesthetic design of the space. As a part of the project, public restrooms serving the club which are located off the adjacent public corridor will be renovated, as will the public corridor. Additionally, the Frontier Room, the

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 140: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 324 FY-2015 Budget Request

760 06-10-2013

760-0305 Crawford University Club Renovation

Weitzenhoffer Room and the Heritage Room located across the corridor to the west of the club will be refurbished as a part of the project.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 141: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 325 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0305 Crawford University Club Renovation

500,000

1,500,000

2,500,000

4,500,000

2,800,000

1,000,000

700,000

4,500,000

0

0

0

0

0

0

0

0

0

0

500,000

1,500,000

2,500,000

0

0

4,500,000

1,000,000

2,800,000

700,000

4,500,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 142: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 326 FY-2015 Budget Request

760 06-10-2013

760-0305 Crawford University Club Renovation

University revenue bond ($1,500,000), private funds ($500,000), Section 13/NC ($2,500,000)

Construction Manager, GMP - 05/01/13

10,000

280.00

2,800,000.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 143: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 331 FY-2015 Budget Request

760 06-11-2013

760-0306 Scholars Walk/Asp Avenue Reconstruction

Main Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

25

17

This project will reconstruct VanVleet Oval into a pedestrian mall north from Lindsey Street to tie into the Brooks Pedestrian Mall. The new mall, to be called Scholars Walk, will feature plaques recognizing the most outstanding honors received by the University's graduates. The first two statueshonoring the University's most prominent faculty will also be included in this project. In addition, Asp Avenue between Brooks Mall and Lindsey Street will also be reconstructed to become a two-way

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 144: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 332 FY-2015 Budget Request

760 06-11-2013

760-0306 Scholars Walk/Asp Avenue Reconstruction

street with on-street bus loading, staging, and parking as well as a cul-de-sac near Brooks Mall for aturn-around. To accommodate the anticipated improvements in these areas, it will be necessary to relocate the bus staging and transfer area from Asp Avenue and Brooks Street to a new location. Also,a portion of the Botany-Microbiology greenhouse facility will be demolished and the facility will be reconfigured.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 145: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 333 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0306 Scholars Walk/Asp Avenue Reconstruction

500,000

7,050,000

2,750,000

10,300,000

8,800,000

100,000

1,400,000

10,300,000

0

0

0

0

0

0

0

0

0

0

500,000

7,050,000

2,750,000

0

0

10,300,000

100,000

8,800,000

1,400,000

10,300,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 146: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 334 FY-2015 Budget Request

760 06-11-2013

760-0306 Scholars Walk/Asp Avenue Reconstruction

Private funds ($500,000), University revenue bond funds ($7,050,000), Section 13/NC funds ($2,750,000)

Project Construction Manager - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 147: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 339 FY-2015 Budget Request

760 06-12-2013

760-0308 Arezzo, Monastero

Via di San Domenico 78

Arezzo, Italy

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

18

Renovation

This project involves the extensive renovation of a former monastery in Arezzo, Italy, to create dormitory space for approximately 50 students in combinations of single and double occupancy rooms with bath facilities. The approximately 30,000-gross-square-foot building will also include three classrooms, a library, a dining facility and small kitchen. In addition, a faculty-in-residence apartment and limited administrative space will be created. The project will provide complete utility

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 148: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 340 FY-2015 Budget Request

760 06-12-2013

760-0308 Arezzo, Monastero

infrastructure including life safety systems. The exterior of the building will be restored and a newlandscaped garden area will be created.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 149: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 341 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0308 Arezzo, Monastero

2,650,500

1,549,500

4,200,000

3,200,000

1,000,000

4,200,000

6,500,000

6,500,000

700,000

4,800,000

1,000,000

6,500,000

3,300,000

3,300,000

800,000

1,700,000

800,000

3,300,000

0

0

0

0

0

0

2,650,500

0

0

0

11,349,500

14,000,000

1,500,000

9,700,000

2,800,000

14,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 150: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 342 FY-2015 Budget Request

760 06-12-2013

760-0308 Arezzo, Monastero

Private funds ($2,650,500), other University sources ($11,349,500)

University staff - 05/01/13

34,000

285.29

9,699,860.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 151: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 275 FY-2015 Budget Request

760 06-12-2013

760-0298 Sarkeys Complex, Huffman Add/Locker Rms

1401 Asp Avenue

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

30

19

Addition

This project involves an approximately 20,000-gross-square-foot addition at Huston Huffman Center for expansion of the general recreation and exercise space in the facility. In addition, the existing men's and women's locker rooms would be renovated and modernized.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 152: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 277 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0298 Sarkeys Complex, Huffman Add/Locker Rms

100,000

100,000

100,000

100,000

4,900,000

8,800,000

13,700,000

700,000

11,000,000

2,000,000

13,700,000

1,200,000

1,200,000

400,000

300,000

500,000

1,200,000

0

0

0

0

0

0

0

5,000,000

0

0

10,000,000

15,000,000

1,100,000

11,300,000

2,600,000

15,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 153: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 278 FY-2015 Budget Request

760 06-12-2013

760-0298 Sarkeys Complex, Huffman Add/Locker Rms

University revenue bond funds ($5,000,000), other University funds ($10,000,000)

University staff and Construction Manager - 05/01/13

20,000

565.00

11,300,000.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 154: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 139 FY-2015 Budget Request

760 06-10-2013

760-0251 Utility Plant #4

1330 Jenkins Avenue

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

50

20

New

This new utility plant is intended to augment the existing Chilled Water Plants 1 and 2. With the rapid growth of the campus, the existing plants are nearing full capacity and can no longer be expanded due to site and piping limitations. The new plant was originally identified as a need in the1997 Norman Campus Utilities Master Plan. The plant will be centrally located just north of the Huston Huffman Center, and will provide chilled water, steam and electricity for expanding campus

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 155: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 140 FY-2015 Budget Request

760 06-10-2013

760-0251 Utility Plant #4

facilities.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 156: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 141 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0251 Utility Plant #4

72,250,000

750,000

73,000,000

67,250,000

50,000

5,700,000

73,000,000

0

0

0

0

0

0

0

0

0

0

0

72,250,000

0

0

750,000

73,000,000

50,000

67,250,000

5,700,000

73,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 157: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 142 FY-2015 Budget Request

760 06-10-2013

760-0251 Utility Plant #4

University bond funds ($72,250,000) and utility infrastructure assessement on other construction projects ($750,000)

Actual construction contract - 05/01/13

40,000

1,656.25

66,250,000.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 158: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 283 FY-2015 Budget Request

760 06-11-2013

760-0299 Catlett Music, Sharp Concert Hall Organ

500 W. Boyd Street

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

21

Addition

This project involves expansion of the Paul F. Sharp Concert Hall and associated renovations needed toallow for the installation of the University's Moller organ.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 159: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 285 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0299 Catlett Music, Sharp Concert Hall Organ

200,000

200,000

200,000

200,000

10,000,000

10,000,000

8,000,000

2,000,000

10,000,000

5,800,000

5,800,000

300,000

4,000,000

1,500,000

5,800,000

0

0

0

0

0

0

16,000,000

0

0

0

0

16,000,000

300,000

12,000,000

3,700,000

16,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 160: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 286 FY-2015 Budget Request

760 06-11-2013

760-0299 Catlett Music, Sharp Concert Hall Organ

Private funds

University staff and project architects - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 161: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 436 FY-2015 Budget Request

760 06-11-2013

760-0324 Stephenson Life Sci, Protein Prod Fac

101 Stephenson Parkway

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

30

22

Renovation

The project includes reconfiguration of a two-module laboratory area in the Stephenson Life Sciences Research Center, on the second floor adjacent to the Macromolecular X-ray and Crystallization Laboratory, creating a Protein Production Core Facility. The renovation for this new facility is associated with a National Institutes of Health grant received to establish a Center of Biomedical Research Excellence in Structural Biology. The reconfiguration will result in a secure stand-alone

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 162: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 437 FY-2015 Budget Request

760 06-11-2013

760-0324 Stephenson Life Sci, Protein Prod Fac

laboratory with central hallway access. An equipment alcove will be created with additional wall and floor space for laboratory equipment. Also, a number of modifications to existing lab modules adjacent to the PPCF and in other building locations will be made to accommodate the new faculty hiredin association with a NIH grant and to relocate the displaced research groups.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 163: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 438 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0324 Stephenson Life Sci, Protein Prod Fac

700,000

700,000

550,000

25,000

125,000

700,000

0

0

0

0

0

0

0

0

0

0

0

0

0

0

700,000

700,000

25,000

550,000

125,000

700,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 164: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 439 FY-2015 Budget Request

760 06-11-2013

760-0324 Stephenson Life Sci, Protein Prod Fac

Grant funds ($220,000), VP for Research funds ($480,000)

Construction Manager, GMP - 05/01/13

4,030

136.47

549,974.10

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 165: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 388 FY-2015 Budget Request

760 06-11-2013

760-0318 Oklahoma Memorial Union Market

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

15

23

Renovation

This project involves renovation of the space formerly occupied by Wendy's to create a modern food services market, providing popular healthy meal, snack and beverage choices.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 166: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 390 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0318 Oklahoma Memorial Union Market

1,700,000

1,700,000

1,300,000

200,000

200,000

1,700,000

0

0

0

0

0

0

0

0

0

0

0

0

0

0

1,700,000

1,700,000

200,000

1,300,000

200,000

1,700,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 167: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 391 FY-2015 Budget Request

760 06-11-2013

760-0318 Oklahoma Memorial Union Market

Food Services funds

University staff - 05/01/2013

4,000

325.00

1,300,000.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 168: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 396 FY-2015 Budget Request

760 06-12-2013

760-0319 Oklahoma Memorial Union Technology Store

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

15

24

Renovation

This project involves renovation of the space formerly occupied by the Union bookstore to create areasfor computer and electronic device sales, accessory sales, support and service for devices. The project will include a training room for workshops and one-on-one training as well as open demonstration space to showcase innovative new technology for students and faculty.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 169: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 398 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0319 Oklahoma Memorial Union Technology Store

2,000,000

2,000,000

1,100,000

450,000

450,000

2,000,000

0

0

0

0

0

0

0

0

0

0

0

0

0

0

2,000,000

2,000,000

450,000

1,100,000

450,000

2,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 170: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 399 FY-2015 Budget Request

760 06-12-2013

760-0319 Oklahoma Memorial Union Technology Store

Discretionary University resources

Construction Manager, GMP - 05/01/2013

5,264

208.97

1,100,018.08

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 171: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 404 FY-2015 Budget Request

760 06-11-2013

760-0320 Acquisition of Property

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

25

The project will allow the University to facilitate the strategic and desirable acquisitions of real property as deemed necessary to support the mission of the University.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 172: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 406 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0320 Acquisition of Property

7,200,000

7,200,000

7,200,000

7,200,000

2,800,000

2,800,000

2,800,000

2,800,000

0

0

0

0

0

0

0

0

0

7,200,000

0

0

2,800,000

10,000,000

0

0

10,000,000

10,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 173: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 407 FY-2015 Budget Request

760 06-11-2013

760-0320 Acquisition of Property

University revenue bonds ($7,200,000); other discretionary University funds ($2,800,000)

University staff - 05/01/2013

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 174: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 412 FY-2015 Budget Request

760 06-11-2013

760-0321 Water Innovative Research Laboratory

University Research Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

26

New

The proposed new facility will serve as a visible front door to the University's water-related education, research and outreach programs, will showcase water conservation and expand community and global awareness. It will operate as center for collaborative investigative research, provide water-related public services and provide both student and public hands-on education and training. It is anticipated that the building may include offices, laboratories, laboratory support, a water quality

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 175: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 413 FY-2015 Budget Request

760 06-11-2013

760-0321 Water Innovative Research Laboratory

testing facility, an active learning classroom, demonstration watershed, display and visualization technology, video-conferencing capabilities, and public learning spaces.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 176: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 414 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0321 Water Innovative Research Laboratory

800,000

800,000

200,000

600,000

800,000

14,200,000

14,200,000

1,700,000

11,500,000

1,000,000

14,200,000

0

0

0

0

0

0

0

0

0

14,200,000

0

0

800,000

15,000,000

1,700,000

11,700,000

1,600,000

15,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 177: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 415 FY-2015 Budget Request

760 06-11-2013

760-0321 Water Innovative Research Laboratory

University staff - 05/01/2013

40,000

292.50

11,700,000.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 178: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 227 FY-2015 Budget Request

760 06-11-2013

760-0278 Headington Hall Student Housing

100 East Lindsey

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

50

27

New

The proposed new facilities will house students and student athletes in a combination of two- and four-bed units totaling approximately 380 beds. The building is planned to be a mid-rise structure, with central dining, laundry facilities, computer labs, study rooms, and other support facilities on the ground floor. The project will also include a Faculty-In-Residence apartment.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 179: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 229 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0278 Headington Hall Student Housing

27,085,000

40,000,000

7,915,000

75,000,000

53,500,000

5,000,000

16,500,000

75,000,000

0

0

0

0

0

0

0

0

0

0

27,085,000

40,000,000

0

0

7,915,000

75,000,000

5,000,000

53,500,000

16,500,000

75,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 180: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 230 FY-2015 Budget Request

760 06-11-2013

760-0278 Headington Hall Student Housing

Private funds ($27,085,000), University revenue bond funds ($40,000,000), Athletics funds ($7,915,000)

Construction Manager lump sum contract - 05/01/13

232,000

230.60

53,499,200.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 181: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 123 FY-2015 Budget Request

760 06-11-2013

760-0241 Parking Expansion

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

15

28

This project provides ongoing funding for a number of parking lot projects and includes demolition, site preparation and lot construction.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 182: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 125 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0241 Parking Expansion

1,000,000

1,000,000

800,000

200,000

1,000,000

1,000,000

1,000,000

2,000,000

1,700,000

300,000

2,000,000

2,000,000

2,000,000

1,600,000

400,000

2,000,000

0

0

0

0

0

0

0

3,000,000

0

0

2,000,000

5,000,000

0

4,100,000

900,000

5,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 183: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 126 FY-2015 Budget Request

760 06-11-2013

760-0241 Parking Expansion

University parking auxiliary revenues ($2,000,000), and University bond funds ($3,000,000)

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 184: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 251 FY-2015 Budget Request

760 06-11-2013

760-0289 Campus Streets and Drives

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

15

29

This project provides for the repair and resurfacing of a variety of campus streets, drives, parking areas and other paved surfaces in need of refurbishment.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 185: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 253 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0289 Campus Streets and Drives

3,000,000

3,000,000

2,500,000

500,000

3,000,000

3,500,000

3,500,000

2,920,000

580,000

3,500,000

3,000,000

3,000,000

2,500,000

500,000

3,000,000

0

0

0

0

0

0

0

9,500,000

0

0

0

9,500,000

0

7,920,000

1,580,000

9,500,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 186: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 254 FY-2015 Budget Request

760 06-11-2013

760-0289 Campus Streets and Drives

University revenue bond funds

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 187: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 25 FY-2015 Budget Request

760 06-11-2013

760-0033 Max Westheimer Airport Improv

1700 Lexington Avenue

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

25

30

This project provides for a variety of improvements to the Max Westheimer Airport that will be required to support its continued maintenance and development. The anticipated work includes the following: (1) construct and light new (west) taxiway; (2) rehabilitate any and all airport pavementsto include runways, taxiways, taxi-lanes, aprons and ramp areas (3) construct new air traffic control tower; (4) upgrade security camera system; (5) infrastructure development for north and/or south

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 188: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 26 FY-2015 Budget Request

760 06-11-2013

760-0033 Max Westheimer Airport Improv

airport property; (6) update the airport master plan; (7) update the airport layout drawing; (8) expand Terminal Building parking; (9) reconstruct fuel lane and taxi lane adjacent to South Ramp; (10)improve drainage, (11) install/replace runway/taxiway lights and signs as necessary; and (12) other improvements and repairs.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 189: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 27 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0033 Max Westheimer Airport Improv

3,200,000

800,000

4,000,000

3,100,000

500,000

400,000

4,000,000

2,400,000

600,000

3,000,000

300,000

2,300,000

400,000

3,000,000

2,400,000

600,000

3,000,000

300,000

2,300,000

400,000

3,000,000

2,720,000

680,000

3,400,000

300,000

2,250,000

850,000

3,400,000

0

0

10,720,000

0

0

0

0

0

2,680,000

13,400,000

1,400,000

9,950,000

2,050,000

13,400,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 190: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 28 FY-2015 Budget Request

760 06-11-2013

760-0033 Max Westheimer Airport Improv

Federal Aviation Administration and Oklahoma Aeronautics Commission grants with matching University auxiliary funds (5-20%)

University staff and Airport Engineers - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 191: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 420 FY-2015 Budget Request

760 06-11-2013

760-0322 Wilkinson House/Wagner Dining Hall Renov

1225 S. Jenkins Ave

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

25

31

Renovation

A study has been undertaken to assess the viability of repurposing these two buildings for other functions upon the relocation of student housing and dining to Headington Hall. The Athletic AcademicServices program is proposed to be relocated from the second floor of the Gaylord Family-Oklahoma Memorial Stadium into Bud Wilkinson House. The existing 29,650 square foot building would be expandedto approximately 42,000 square feet to accommodate the program's current and future academic needs.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 192: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 421 FY-2015 Budget Request

760 06-11-2013

760-0322 Wilkinson House/Wagner Dining Hall Renov

The facility would also feature a central stairway and elevator, new façade, and upgrades to restroomsand mechanical and electrical systems. Wagner Dining Hall is proposed to be renovated into a banquet facility for use by the University O-Club and would also serve as a central study hall for student athletes. The remodel would include new interior finishes in the dining area, new equipment designed for catered events in the kitchen, new restrooms, and new mechanical and electrical systems.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 193: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 422 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0322 Wilkinson House/Wagner Dining Hall Renov

700,000

700,000

500,000

200,000

700,000

10,300,000

10,300,000

1,000,000

8,000,000

1,300,000

10,300,000

3,000,000

3,000,000

500,000

1,800,000

700,000

3,000,000

0

0

0

0

0

0

0

0

0

0

14,000,000

14,000,000

1,500,000

10,300,000

2,200,000

14,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 194: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 423 FY-2015 Budget Request

760 06-11-2013

760-0322 Wilkinson House/Wagner Dining Hall Renov

Athletics Department funds

University staff and architectural consultant - 05/01/2013

37,000

278.38

10,300,060.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 195: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 347 FY-2015 Budget Request

760 06-11-2013

760-0309 Jimmie Austin OU Golf Club Improvements

1 Par Drive

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

32

New

This project provides a variety of improvements for the Jimmie Austin Golf Course. Improvements include a relocated maintenance facility, new clubhouse, residential cottages and various course and practice area renovations. Also included are much needed projects to upgrade the irrigation system infrastructure and to repair erosion problems in Bishop Creek and adjoining holes. The project will bedeveloped incrementally over an extended time period.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 196: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 349 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0309 Jimmie Austin OU Golf Club Improvements

1,000,000

2,800,000

3,800,000

3,000,000

200,000

600,000

3,800,000

1,000,000

1,200,000

2,200,000

200,000

1,800,000

200,000

2,200,000

0

0

0

0

0

0

0

0

2,000,000

4,000,000

0

0

0

6,000,000

400,000

4,800,000

800,000

6,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 197: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 350 FY-2015 Budget Request

760 06-11-2013

760-0309 Jimmie Austin OU Golf Club Improvements

University revenue bond ($4,000,000), private funds ($2,000,000)

Project architects and University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 198: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 115 FY-2015 Budget Request

760 06-11-2013

760-0239 Coe Golf Learning Ctr & Team Practice

4 Par Drive

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

25

33

Renovation

The Athletic Department has identified various team support areas that are needed at the Charlie Coe Golf Learning Center. The improvements include additional equipment storage and workout areas as wellas improvement of the practice area.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 199: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 117 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0239 Coe Golf Learning Ctr & Team Practice

2,500,000

2,500,000

2,000,000

100,000

400,000

2,500,000

1,500,000

1,500,000

100,000

1,000,000

400,000

1,500,000

0

0

0

0

0

0

0

0

4,000,000

0

0

0

0

4,000,000

200,000

3,000,000

800,000

4,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 200: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 118 FY-2015 Budget Request

760 06-11-2013

760-0239 Coe Golf Learning Ctr & Team Practice

Private funds to be raised and/or other Athletic Department funds

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 201: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 355 FY-2015 Budget Request

760 06-11-2013

760-0310 Gaylord Fam Okla Mem Stadium Impr, Ph VI

180 W. Brooks

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

50

34

Renovation

This project will include continued renovations to the west mezzanine and refurbishment of the east side suites, the Santee Lounge and the Kerr McGee Stadium Club. Also included are maintenance, repairs, and improvements to the east stadium structure.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 202: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 357 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0310 Gaylord Fam Okla Mem Stadium Impr, Ph VI

9,000,000

9,000,000

5,600,000

1,250,000

2,150,000

9,000,000

0

0

0

0

0

0

0

0

0

0

9,000,000

0

0

0

0

9,000,000

1,250,000

5,600,000

2,150,000

9,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 203: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 358 FY-2015 Budget Request

760 06-11-2013

760-0310 Gaylord Fam Okla Mem Stadium Impr, Ph VI

Private funds

Construction Manager, Lump Sum Price - 05/01/13

15,500

361.29

5,599,995.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 204: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 163 FY-2015 Budget Request

760 06-11-2013

760-0256 L. Dale Mitchell Baseball Park Exp & Imp

401 West Imhoff Road

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

30

35

Renovation

The Athletic Department has reviewed and identified the need for updates and improvements to spectatorseating, fan amenities, and team facilities at L. Dale Mitchell Baseball Park.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 205: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 165 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0256 L. Dale Mitchell Baseball Park Exp & Imp

1,750,000

1,750,000

1,250,000

200,000

300,000

1,750,000

0

0

1,000,000

1,250,000

2,250,000

200,000

1,650,000

400,000

2,250,000

0

0

0

0

0

0

2,750,000

0

0

0

1,250,000

4,000,000

400,000

2,900,000

700,000

4,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 206: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 166 FY-2015 Budget Request

760 06-11-2013

760-0256 L. Dale Mitchell Baseball Park Exp & Imp

Private funds and Athletics Department funds

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 207: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 171 FY-2015 Budget Request

760 06-11-2013

760-0257 Softball Facility Expansion & Improv

2500 South Jenkins Ave

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

30

36

Renovation

The Athletic Department has reviewed and identified the need for updates and improvements to spectatorseating, fan amenities, team facilities, and parking expansion and other site improvements at the Softball Facility.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 208: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 173 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0257 Softball Facility Expansion & Improv

1,000,000

3,000,000

4,000,000

3,300,000

300,000

400,000

4,000,000

0

0

0

0

0

0

0

0

0

0

1,000,000

0

0

0

3,000,000

4,000,000

300,000

3,300,000

400,000

4,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 209: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 174 FY-2015 Budget Request

760 06-11-2013

760-0257 Softball Facility Expansion & Improv

Private funds and Athletics Department funds

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 210: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 219 FY-2015 Budget Request

760 06-11-2013

760-0273 McCasland Field House Renov & Imp Ph III

151 W. Brooks

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

30

37

Renovation

The primary elements of this phase of the project are modifications for improved energy efficiency, including window and skylight replacement, and for improved accessibility, including walks and paving around the building's exterior; structural repairs; roof replacement; and masonry restoration.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 211: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 221 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0273 McCasland Field House Renov & Imp Ph III

5,200,000

5,200,000

4,100,000

50,000

1,050,000

5,200,000

0

0

0

0

0

0

0

0

0

0

5,200,000

0

0

0

0

5,200,000

50,000

4,100,000

1,050,000

5,200,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 212: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 222 FY-2015 Budget Request

760 06-11-2013

760-0273 McCasland Field House Renov & Imp Ph III

Private funds

Actual construction contract - 05/01/13

53,770

76.25

4,099,962.50

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 213: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 363 FY-2015 Budget Request

760 06-12-2013

760-0311 Varsity Rowing Practice Center

500 G.T. Blankship Blvd

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

50

38

New

Plans call for construction of an approximately 24,000-square-foot building to provide space to house indoor practice facilities for the women's intercollegiate rowing team and to consolidate various Athletics Department storage needs. The rowing team facilities will include a rowing tank, team room and meeting spaces, a workout area, lockers/showers, and storage and laundry areas.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 214: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 365 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0311 Varsity Rowing Practice Center

1,500,000

5,000,000

6,500,000

4,900,000

500,000

1,100,000

6,500,000

0

0

0

0

0

0

0

0

0

0

1,500,000

0

0

0

5,000,000

6,500,000

500,000

4,900,000

1,100,000

6,500,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 215: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 366 FY-2015 Budget Request

760 06-12-2013

760-0311 Varsity Rowing Practice Center

Athletics Department funds and private gifts

Construction contract awarded - 05/01/13

22,000

222.73

4,900,060.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 216: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 235 FY-2015 Budget Request

760 06-11-2013

760-0279 Boat House

Proposed New Facility on the Oklahoma River

Oklahoma City

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

39

New

The proposed new boathouse will be located in Oklahoma City near other existing and future facilities on the Oklahoma River. The facility will include space for storage of shells, oars, ergometers, and other equipment; a changing/locker area with showers; a multi-purpose area for team meetings, workout,etc; a small training/treatment room; an entry lobby and hospitality area; restrooms for men and women; and access to the waterfront.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 217: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 237 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-11-2013

760-0279 Boat House

1,400,000

1,400,000

1,000,000

400,000

1,400,000

1,600,000

3,500,000

5,100,000

500,000

3,800,000

800,000

5,100,000

0

0

0

0

0

0

0

0

3,000,000

0

0

0

3,500,000

6,500,000

500,000

4,800,000

1,200,000

6,500,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 218: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 238 FY-2015 Budget Request

760 06-11-2013

760-0279 Boat House

Private funds ($3,000,000), and Athletics Department funds ($3,500,000)

Project architect and University staff - 05/01/13

16,000

300.00

4,800,000.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 219: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 371 FY-2015 Budget Request

760 06-10-2013

760-0312 Emer Repair Renov Equip & Tech Acq 12-13

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

15

40

Renovation

This project involves the expenditure of $2,540,697 in FY 2013 Section 13 and New College Funds for emergency repairs to various campus facilities, academic and administrative offices, classroom and laboratory renovations, and equipment and technology acquisitions. These project funds will allow forthe implementation of projects as needed in support of a number of capital projects throughout the course of the fiscal year.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 220: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 373 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0312 Emer Repair Renov Equip & Tech Acq 12-13

2,540,697

2,540,697

1,290,697

1,250,000

2,540,697

0

0

0

0

0

0

0

0

0

0

0

0

2,540,697

0

0

2,540,697

1,250,000

1,290,697

0

2,540,697

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 221: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 374 FY-2015 Budget Request

760 06-10-2013

760-0312 Emer Repair Renov Equip & Tech Acq 12-13

FY13 Section 13 and New College Funds

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 222: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 428 FY-2015 Budget Request

760 06-12-2013

760-0323 Emer Repair Renov Equip & Tech Acq 13-14

Norman Campus

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

10

41

Renovation

This project involves the expenditure of $1,842,930 in FY 2014 Section 13 and New College Funds for emergency repairs to various campus facilities, academic and administrative offices, classroom and laboratory renovations, and equipment and technology acquisitions. These project funds will allow forthe implementation of projects as needed in support of a number of capital projects throughout the course of the fiscal year.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 223: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 430 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0323 Emer Repair Renov Equip & Tech Acq 13-14

1,842,930

1,842,930

842,930

1,000,000

1,842,930

0

0

0

0

0

0

0

0

0

0

0

0

1,842,930

0

0

1,842,930

1,000,000

842,930

0

1,842,930

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 224: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 431 FY-2015 Budget Request

760 06-12-2013

760-0323 Emer Repair Renov Equip & Tech Acq 13-14

FY 14 Section 13 and New College Funds

University staff - 05/01/2013

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 225: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 299 FY-2015 Budget Request

760 06-12-2013

760-0302 Sarkeys Complex, Health/Exercise Science

1401 Asp Avenue

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

42

Addition

This project will consolidate Department of Health and Exercise Science faculty and students in one location with adequate space. The planned addition to the building will be sized to include approximately 19,550 gross square feet constructed to the south of the existing facility. The additionwill provide new lab space, classrooms, and faculty offices, by expanding the existing basement and first floor. The project also includes modifications to the western façade that provides a new front

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 226: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 300 FY-2015 Budget Request

760 06-12-2013

760-0302 Sarkeys Complex, Health/Exercise Science

entrance to the building off of Asp Avenue and ties the existing building into the new construction.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 227: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 301 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0302 Sarkeys Complex, Health/Exercise Science

100,000

100,000

100,000

100,000

9,900,000

9,900,000

700,000

7,500,000

1,700,000

9,900,000

0

0

0

0

0

0

0

0

0

0

0

0

10,000,000

10,000,000

700,000

7,500,000

1,800,000

10,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 228: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 302 FY-2015 Budget Request

760 06-12-2013

760-0302 Sarkeys Complex, Health/Exercise Science

Funds to be determined

Consultant and University staff - 05/01/13

20,000

375.00

7,500,000.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 229: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 179 FY-2015 Budget Request

760 06-12-2013

760-0259 Chemistry Building Renovation

620 Parrington Oval

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

25

43

Renovation

As new facilities for the Department of Chemistry and Biochemistry are constructed, spaces in existingfacilities will be vacated and reprogrammed for other instructional and research uses. Renovation will be required to reconfigure space, upgrade building systems and improve accessibility.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 230: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 181 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0259 Chemistry Building Renovation

0

0

0

0

200,000

200,000

200,000

200,000

9,800,000

9,800,000

1,000,000

7,300,000

1,500,000

9,800,000

0

0

0

0

0

0

0

0

10,000,000

10,000,000

1,000,000

7,300,000

1,700,000

10,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 231: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 182 FY-2015 Budget Request

760 06-12-2013

760-0259 Chemistry Building Renovation

Source of funds is to be identified

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 232: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 307 FY-2015 Budget Request

760 06-10-2013

760-0303 Repository of Collections

Proposed new facility

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

44

New

This proposed new 15,000-gross-square-foot facility would provide environmentally controlled warehousespace for storage of special arts and humanities collections. Possible building users would be the Carl Albert Center, Western History Collections, Gaylord College of Mass Communications and Journalism, Fred Jones Jr. Museum of Art and the Political Communications Center.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 233: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 309 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0303 Repository of Collections

0

0

50,000

50,000

50,000

50,000

5,950,000

5,950,000

200,000

4,000,000

1,750,000

5,950,000

0

0

0

0

0

0

0

0

0

0

6,000,000

6,000,000

200,000

4,000,000

1,800,000

6,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 234: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 310 FY-2015 Budget Request

760 06-10-2013

760-0303 Repository of Collections

Source of funds to be determined

University staff - 05/01/13

15,000

266.67

4,000,050.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 235: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 243 FY-2015 Budget Request

760 06-12-2013

760-0285 Cate Center Window Replacement

316-330 Cate Center Drive

Norman

Statewide

44

16

4

8

Pending

Self Funded

25

45

Renovation

New energy-efficient replacement windows will be installed in Cate Center #2 and #3. In addition to providing energy cost savings, replacement of the windows will provide greater security and enhance the buildings' appearance.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 236: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 245 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0285 Cate Center Window Replacement

0

0

800,000

800,000

650,000

150,000

800,000

0

0

0

0

0

0

0

0

0

0

0

0

800,000

800,000

0

650,000

150,000

800,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 237: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 246 FY-2015 Budget Request

760 06-12-2013

760-0285 Cate Center Window Replacement

Source of funds is to be identified

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 238: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 259 FY-2015 Budget Request

760 06-10-2013

760-0292 Biological Sciences Building

Proposed new facility

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

46

New

Many of the teaching and research facilities utilized by the departments of Biology and Microbiology and Plant Biology, and the Oklahoma Biological Survey are outdated and insufficient to meet the needs of undergraduate teaching, research and current safety standards. In addition, the wide dispersal in multiple locations of the activities and faculty in the biological sciences is another significant impediment to accommodating dramatic growth in student numbers and the achievement of goals. The

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 239: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 260 FY-2015 Budget Request

760 06-10-2013

760-0292 Biological Sciences Building

envisioned building would allow centralization of critical facilities and personnel. The plan would provide a new greenhouse and a superior learning environment for students including a new modern lecture hall, modernized research facilities, and open spaces for students, faculty and staff that will enhance opportunities for cross-disciplinary research collaborations and larger group projects.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 240: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 261 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0292 Biological Sciences Building

0

0

0

0

0

0

80,000,000

80,000,000

5,000,000

56,000,000

19,000,000

80,000,000

0

0

0

0

0

0

0

0

80,000,000

80,000,000

5,000,000

56,000,000

19,000,000

80,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 241: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 262 FY-2015 Budget Request

760 06-10-2013

760-0292 Biological Sciences Building

Source of funds is to be identified

University staff - 05/01/13

112,000

500.00

56,000,000.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 242: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 83 FY-2015 Budget Request

760 06-10-2013

760-0220 Life Sciences Center, Phase II

University Research Campus, proposed new facility

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

47

New

This project will complete the program requirements necessary to support the instructional and research activities of the Department of Chemistry and Biochemistry, and will ultimately consolidate and integrate the teaching and student services programs with the research programs to be constructed as Phase I. Phase II will contain approximately 100,000 gross square feet and will provide the department with state-of-the-art teaching laboratories for General, Analytical, Physical, Biological,

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 243: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 84 FY-2015 Budget Request

760 06-10-2013

760-0220 Life Sciences Center, Phase II

Quantitative and Organic chemistry; teaching laboratory support and chemical stock room meeting the current life-safety requirements for storage and handling of hazardous materials; student advising andstudent services areas including an Information Commons, group study spaces and computer lab; and a 150-seat seminar auditorium. The project will also construct a parking structure.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 244: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 85 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0220 Life Sciences Center, Phase II

0

0

0

0

0

0

50,000,000

50,000,000

3,000,000

36,000,000

11,000,000

50,000,000

0

0

0

0

0

0

0

0

50,000,000

50,000,000

3,000,000

36,000,000

11,000,000

50,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 245: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 86 FY-2015 Budget Request

760 06-10-2013

760-0220 Life Sciences Center, Phase II

Source of funds is to be identified

Project architect - 05/01/13

100,000

360.00

36,000,000.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 246: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 195 FY-2015 Budget Request

760 06-12-2013

760-0270 Armory Renovation

290 West Brooks Street

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

25

48

Renovation

This project will renovate the current Armory building to provide much needed and up-to-date classroomspace required to teach classes in military science. The project will also make needed code, life safety and accessibility improvements to the building and update the building's mechanical and electrical systems.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 247: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 197 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0270 Armory Renovation

0

0

0

0

50,000

50,000

50,000

50,000

11,950,000

11,950,000

20,000

9,000,000

2,930,000

11,950,000

0

0

0

0

0

0

0

0

12,000,000

12,000,000

20,000

9,000,000

2,980,000

12,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 248: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 198 FY-2015 Budget Request

760 06-12-2013

760-0270 Armory Renovation

Source of funds is to be identified

Feasibility study by on-call architectural consultant - 05/01/13

39,000

230.76

8,999,640.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 249: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 211 FY-2015 Budget Request

760 06-10-2013

760-0272 Multi-Tenant Light Industrial Fac Ph I

University Research Campus, proposed new facility

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

49

New

This project will provide high bay light industrial space and office space for University research programs and which may be leased to entities wishing to locate near other technology resources at the University Research Campus. This phase will construct two pods, containing a total of approximately 73,000 gross square feet of space. Planning will include defined areas for additional pods. Necessary infrastructure and parking areas associated with the new buildings will also need to be

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 250: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 212 FY-2015 Budget Request

760 06-10-2013

760-0272 Multi-Tenant Light Industrial Fac Ph I

constructed as part of the project.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 251: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 213 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0272 Multi-Tenant Light Industrial Fac Ph I

0

0

200,000

200,000

200,000

200,000

2,800,000

2,800,000

300,000

2,000,000

500,000

2,800,000

13,000,000

13,000,000

300,000

10,800,000

1,900,000

13,000,000

0

0

0

0

0

0

0

0

16,000,000

16,000,000

600,000

12,800,000

2,600,000

16,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 252: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 214 FY-2015 Budget Request

760 06-10-2013

760-0272 Multi-Tenant Light Industrial Fac Ph I

Source of funds is to be identified

Feasibility study by architect and University staff - 05/01/13

73,000

175.34

12,799,820.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 253: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 131 FY-2015 Budget Request

760 06-10-2013

760-0249 Kessler Farm Interdisciplinary Field Lab

18388 190th Street

Purcell

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

50

New

Dr. Ed Kessler has deeded to The University of Oklahoma approximately 350 acres of land southwest of Norman to be used as a field research facility. There have been numerous meteorological experiments on the farm over past years. This project is planned to construct a field laboratory building that will provide for preparation of samples prior to bringing them back to the Norman Campus. Also included is a subsequent phase will create a class and meeting area and temporary living quarters to

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 254: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 132 FY-2015 Budget Request

760 06-10-2013

760-0249 Kessler Farm Interdisciplinary Field Lab

allow researchers to stay at the laboratory while collecting specimens or data.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 255: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 133 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0249 Kessler Farm Interdisciplinary Field Lab

50,000

50,000

50,000

50,000

1,550,000

1,550,000

200,000

1,100,000

250,000

1,550,000

1,400,000

1,400,000

150,000

1,050,000

200,000

1,400,000

0

0

0

0

2,950,000

0

0

0

0

0

50,000

3,000,000

350,000

2,150,000

500,000

3,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 256: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 134 FY-2015 Budget Request

760 06-10-2013

760-0249 Kessler Farm Interdisciplinary Field Lab

National Science Foundation and other research grants

Project architect - 05/01/13

7,600

230.26

1,749,976.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 257: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 147 FY-2015 Budget Request

760 06-12-2013

760-0253 Central Theatrical Set & Costume Design

University Research Campus, proposed new facility

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

51

New

This project will construct a facility on the Research Campus which will house a central theatrical set and costume design facility for use by the University's School of Drama and the Weitzenhoffer Department of Musical Theater.

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Page 258: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 149 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0253 Central Theatrical Set & Costume Design

0

0

0

0

0

0

2,000,000

2,000,000

200,000

1,500,000

300,000

2,000,000

0

0

0

0

0

0

0

0

2,000,000

2,000,000

200,000

1,500,000

300,000

2,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 259: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 150 FY-2015 Budget Request

760 06-12-2013

760-0253 Central Theatrical Set & Costume Design

Source of funds is to be determined

University staff - 05/01/13

8,500

176.47

1,499,995.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 260: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 107 FY-2015 Budget Request

760 06-12-2013

760-0236 School of Art Fac at Res Campus

University Research Campus, proposed new facility

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

52

New

This project will provide improved facilities for the School of Art and will be located adjacent to the School's existing Ceramics Studio and Kiln Facility located at the Research Campus. Programs andfunctions currently utilizing space in the Fred Jones Jr. Memorial Art Center, the Charles M. Russell Center and two World War II vintage buildings at the University Research Campus-North would be consolidated in the new facility. Containing approximately 32,000 square feet of space, this new

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 261: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 108 FY-2015 Budget Request

760 06-12-2013

760-0236 School of Art Fac at Res Campus

facility would provide space for the School's sculpture programs, graduate student and faculty studio spaces, and laboratory and studio spaces for the photography program.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 262: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 109 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0236 School of Art Fac at Res Campus

0

0

0

0

0

0

10,900,000

10,900,000

1,500,000

8,200,000

1,200,000

10,900,000

0

0

0

0

10,900,000

0

0

0

0

10,900,000

1,500,000

8,200,000

1,200,000

10,900,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 263: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 110 FY-2015 Budget Request

760 06-12-2013

760-0236 School of Art Fac at Res Campus

Private funds to be raised

University staff - 05/01/13

32,000

256.25

8,200,000.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 264: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 91 FY-2015 Budget Request

760 06-12-2013

760-0222 College of Continuing Education Off Bldg

Norman Campus, proposed new building

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

50

53

New

A new facility is proposed to replace old and out-of-date facilities currently in use by the College of Continuing Education. A new building, to be located near existing CCE facilities, would provide expanded superior quality space to house the College's programs. Approximately 150,000 gross square feet of flexible office space would provide areas for various program and administrative offices. Necessary infrastructure and a parking structure associated with the new building will also need to be

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 265: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 92 FY-2015 Budget Request

760 06-12-2013

760-0222 College of Continuing Education Off Bldg

constructed as part of the project.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 266: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 93 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-12-2013

760-0222 College of Continuing Education Off Bldg

0

0

0

0

14,500,000

14,500,000

11,000,000

3,500,000

14,500,000

17,500,000

17,500,000

1,500,000

12,500,000

3,500,000

17,500,000

0

0

0

0

0

0

0

0

32,000,000

32,000,000

1,500,000

23,500,000

7,000,000

32,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 267: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 94 FY-2015 Budget Request

760 06-12-2013

760-0222 College of Continuing Education Off Bldg

Source of funds is to be identified

University staff - 05/01/13

94,000

250.00

23,500,000.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 268: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 33 FY-2015 Budget Request

760 06-10-2013

760-0077 Fred Jones Art Ctr Renov-School of Art

520 Parrington Oval

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

30

54

Renovation

This project will include extensive renovation of interior spaces and the supporting mechanical, electrical, and computer and telecommunications systems necessary to modernize the art school facilities. In addition, the facility will be brought into compliance with current fire, life safety,and accessibility codes. Academic spaces for art instruction and other areas will be upgraded for current use and to meet current environmental isolation and health standards. Exterior repairs will

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 269: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 34 FY-2015 Budget Request

760 06-10-2013

760-0077 Fred Jones Art Ctr Renov-School of Art

be made to restore the building to good condition.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 270: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 35 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0077 Fred Jones Art Ctr Renov-School of Art

0

0

0

0

600,000

600,000

600,000

600,000

7,400,000

7,400,000

900,000

6,200,000

300,000

7,400,000

0

0

0

0

0

0

0

0

8,000,000

8,000,000

900,000

6,200,000

900,000

8,000,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 271: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 36 FY-2015 Budget Request

760 06-10-2013

760-0077 Fred Jones Art Ctr Renov-School of Art

Source of funds is to be identified

University staff - 05/01/13

71,000

87.32

6,199,720.00

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total:

Page 272: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 17 FY-2015 Budget Request

760 06-10-2013

760-0032 Univ Research Campus-No. Infrastructure

University Research Campus-North

Norman

Statewide

44

16

4

8

Educational Facilities

Pending

Self Funded

30

55

The establishment and growth of the University Research Campus-North is dependent upon the developmentof an infrastructure foundation for the property. The University Research Campus-North is comprised of approximately 1,100 acres and organized into two basic elements: Swearingen Research Park and Max Westheimer Airport. This project involves the enhancement and addition to existing infrastructure systems on the east side of the property. Improvements include road construction and repair, street

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

** Items with(Criteria_) after them are used to complete the Criteria/Rating Scale.**

Location of Project

Address:

City:

County(ies) to be served:

Legislative District numbers: House -

Senate -

Congressional District number:

Sub-State Planning District number:

Type of Project:

Project Status:

Funding Type:

What is the useful life of this project in years:

Agency's priority number for project: (Criteria G)

Type of building construction:

Description of project and justification:

Page 273: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 18 FY-2015 Budget Request

760 06-10-2013

760-0032 Univ Research Campus-No. Infrastructure

lighting and sidewalks, sewer mains, water distribution systems, storm water detention pond construction, perimeter and street landscaping, construction of primary entrances, and the demolition of several structures necessary to prepare sites for development.

No

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Description of project and justification:

How will this project benefit those served by your agency? (Criteria C)

Are there legal obligations or mandates? (Criteria B)

Is this a request to supplement previous funding for this project: (Criteria F)

If yes, indicate the source and amount of funding and the year(s) it was provided:

Does this project involve technological advancement? How? (Criteria H)

What is the effect of delaying this project or maintenance schedule? (Criteria E)

(con't)

Page 274: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 19 FY-2015 Budget Request

2014 2015 2016

2017 2018

2019

760 06-10-2013

760-0032 Univ Research Campus-No. Infrastructure

500,000

500,000

350,000

150,000

500,000

2,000,000

2,000,000

1,850,000

150,000

2,000,000

2,000,000

2,000,000

1,850,000

150,000

2,000,000

3,000,000

3,000,000

2,650,000

350,000

3,000,000

0

0

0

0

0

0

0

0

7,500,000

7,500,000

0

6,700,000

800,000

7,500,000

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

PROJECT SOURCES AND USES OF FUNDS (estimates should cover entire cost of project) (Criteria A)

Expeditures

thru 6 -Source of Funds:

State Approp.

G.O. Bonds

Federal/Matching

Gifts/Donations

Revenue Bonds

Section 13

Revolving Funds

Section 13 Offset

Other

Total Sources

Project Costs:

Equipment

Construction

Other

Total Costs

FY - FY -

FY -

& Totals

Page 275: Oklahoma State Regents for Higher Education f… · The Oklahoma State Regents for Higher Education have requested that each institution in the State system submit in June of each

BRR0160

Printed: 06-17-2013 Capital Outlay Project

Capital Outlay, Pg. 20 FY-2015 Budget Request

760 06-10-2013

760-0032 Univ Research Campus-No. Infrastructure

Source of funds is to be identified

University staff - 05/01/13

Agency: University of Oklahoma Last Changed:

Project Number: Project Name:

Describe source of funds used or to be used on the previous table. (Explain whether G.O. or revenue bondproceeds are from existing or proposed issues, what will be the source of revenue to repay the bonds, and identify "Other" sources)(Criteria A)

Cost Estimate Information:

a. What is the source and date of your cost estimate? (e.g. Engineering Study - 12/3/90)

b. What is the square footage?

c. What is the cost per square foot?

d. Total: