offshore wind energy strategic environmental assessment (sea) phase 1 “progress and lessons”

Download Offshore Wind Energy Strategic Environmental Assessment (SEA) Phase 1 “Progress and Lessons”

If you can't read please download the document

Upload: hestia

Post on 09-Jan-2016

24 views

Category:

Documents


0 download

DESCRIPTION

Offshore Wind Energy Strategic Environmental Assessment (SEA) Phase 1 “Progress and Lessons” Mark Jennison and Trevor Baker BMT Cordah Ltd. Presentation Overview. Introduction to SEA Phase 1 SEA Approach Process and Work Programme Detailed Methodology Findings to date Lessons Learnt. - PowerPoint PPT Presentation

TRANSCRIPT

  • Offshore Wind EnergyStrategic Environmental Assessment (SEA)Phase 1

    Progress and Lessons

    Mark Jennison and Trevor BakerBMT Cordah Ltd.

  • Presentation Overview

    Introduction to SEAPhase 1 SEAApproachProcess and Work ProgrammeDetailed MethodologyFindings to dateLessons Learnt

  • Introduction to SEABasic Features:

    Tool/instrument to influence PPP processes by provision of environmental information;Earlier consideration of environmental issues (opportunities and risks);Better link to national and global issues (greenhouse gases);Identify preferred option from alternatives;Acquisition of key baseline data;Less resources and effort needed for EIAs; andProvides the context for decisions on individual projects.

  • SEA ApproachGoal: Provision of useful input to decision-making processBasic Guiding Principles:Following SEA Directive and draft ODPM guidanceConsideration of DTI SEA work for oil &gas activitiesGood international practice (IAIA, UN)

  • SEA ApproachSEA Directive Key Features:Plan and Programme Focus (not policy)Implemented during preparation process (alternatives)Scoping required to determine focus and content of Environmental Report (Directive includes biodiversity, health and cultural heritage)Draft and Final Environmental ReportsConsultations on draft plan/programme and Reports (decision input)Statement on use of Report in the decision

  • Strategic Areas

  • Phase 1 SEA ApproachProcess:

    Establish SEA Steering GroupEstablish SEA website as focus for awareness and consultationProvide overview of baseline situation, trends, problems and causesScope key issues and impactsDevelop scenarios for impact prediction (No wind farms, most likely, maximum credible)

  • Phase 1 SEA ApproachProcess:

    Impact prediction and evaluationCumulative impact analysis

  • Phase 1 SEA ApproachProcess:

    Identification of mitigation and enhancement measuresPreferred option/scenario identifiedPreparation of environmental management plan (mitigation and monitoring)

  • Phase 1 SEA ApproachEnvironmental Report:

    Information and advice pertaining to:Absolute constraintsRelative constraintsLowest level of constraintSignificance of environmental and socio-economic impacts from scenariosRecommendations for environmental management framework

  • Phase 1 SEA ApproachTimetable:Preparation of draft Environmental Report

    (To be issued at the end of April)

    ConsultationSummary of consultation responsesFinal document expected end of May

  • Phase 1 SEA ApproachMethodology and findings

    data collation and reviewquantitative data to GISconstraints mappingrisk based impact analysisscenario building

  • Risk-based impact analysisConsequence: effect of an activitys interaction with the natural and socio-economic environments

    Likelihood: probability that an activity will occur

    Risk = consequence x likelihood

  • Example assessment - noiseImpactLikelihoodConsequence RiskSeismic 5 3 15 (moderate)Construction* 5 1 5 (low)Operational * 5 3 15 (moderate)Decommissioning 3 5 15 (moderate)*Depends on type of noise and species

  • Socio-economic environment

  • Natural environment

  • Spatial analysis

    Table 1 Spatial analysis scoring for each socio-economic factor

    Factor

    Score

    Rationale

    Shipping

    0

    1

    2

    3

    Absent

    Low intensity (1-2500 hours per annum)

    Medium intensity (2500-7500 per annum)

    High intensity (7500-20000 per annum)

    Fishing effort

    0

    1

    2

    3

    None

    Low (1-500 hours in 2002)

    Medium (500-5000 hours in 2002)

    High (5000-15000 hours in 2002)

    Shellfishery areas

    0

    1

    2

    3

    Absent

    Unlicensed and unexploited beds [future resource]

    Licensed, but unexploited beds

    Licensed natural and farmed beds

  • Socio-economic environment

  • Natural environment

  • Constraints map - all data

  • Scenarios and time horizonsNo developmentLikely development Maximum development2010 and 2020

  • 2010within 12nm25004000beyond 12nm15003500Total40007500% UK supply48

    2020within 12nm37005000beyond 12nm650012000Total1020017000% UK supply1017Scenarioslikely max

  • Maximum credible development, 2020

  • Preliminary conclusionsData gaps: baseline information on birds, elasmobranchs, squid, fishing, recreational navigationData gaps: impacts on birds, cetaceans, elasmobranchs, seascape Number of constraints decline offshore

  • Lessons learntUnderstanding of SEA, (not a ramped up EIA or a substitute for EIA)Effectiveness of GISDifficulties in accessing data and information and in appropriate formatMix between issue focus and impact focusStakeholder interests very wide rangingEffective and appropriate consultation

  • Its a start

  • www.og.dti.gov.uk/offshore-wind-sea/