office of the consumer grievances redressal forum … · 2018-04-13 · office complex (2nd floor),...
TRANSCRIPT
1
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 505 Date of Institution - 30.10.2013 Date of Order - 18.08.2015 In the matter Shri Deepak Gupta, House No.958, Sector-10, Panchkula.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.8 UT, Chandigarh.
……………….Respondents
Order
1. Shri Deepak Gupta, resident of House No.958, Sector-10, Panchkula through his
representation dated 30.10.2013 submitted that he has an electric connection at
House No. 4013, Mauli Jagran Complex since 2005. Against this DS connection,
the sundry charges of approximately Rs.25000/- was charged to him. On his
contacting the SDO ‘OP’ Sub Division No.8, he was informed that this amount was
on account of past arrears of the same premises. He stated that though he was
paying current bills, yet the supply was disconnected from time to time due to non
payment of sundry charges. The supply disconnected on 20.11.20`13 was restored
on 23.12.2013 after he deposited Rs.20,000/- with the department. On further
enquiry he was told by the Sub Division that amount pertains to year 2000 when the
premises was being used for commercial purposes and domestic misuse
commercial (DMC) tariff was levied. Then occupant did not pay the charges and his
connection was disconnected and meter was removed. The Complainant’s main
plea is that he got new connection in the year 2005 and at the time of release of
connection no such defaulting amount against the premises was conveyed.
2. The para-wise comments along with consumption data were called from the Nodal
Officer i.e. Executive Engineer, Electricity Operation Division No.2 vide letter dated
1.11.2013 with a copy to the complainant.
2
3. The Assistant Executive Engineer, ‘OP’ Sub Division No.8 vide his letter dated
3.12.2013 intimated as under:-
a) The electricity connection stands in the name of Shri Lal Chand and Shri Deepak
Gupta is not the consumer of the electricity department.
b) That one No. Electricity connection at the same premises was disconnected and
the defaulting amount of Rs.29,878/- has been transferred to new connection
being the same premises.
c) The said amount had been reflected in the Ledger for the period June 2006 to
August 2006.
d) The electricity supply was disconnected from time to time to recover the
defaulting amount and on the request of the consumer part payment was
accepted and electricity supply was restored.
e) He also supplied the consumption data of the existing connection.
4. The complaint was formally registered as Complaint No.505 was notified for hearing
on 1.1.2014, but neither the consumer nor the SDO attended. Subsequent hearing
was conducted on 28.1.2014 and was attended by the SDO only. In the next date of
hearing was 5.6.2014, again the complainant did not attend.
5. On the next date of hearing on 24.7.2014, the complainant as well as SDO attended
the hearing. The complainant submitted that he purchased the said house from
`Shri Lal Chand on General Power Attorney and the electricity connection was
applied in the name of original allotee i.e. Shri Lal Chand. At the time of release of
connection he was not conveyed (by the Sub Division) that any defaulting amount is
pending against this premises and thus he is not liable to pay this amount. The
concerned SDO on the other hand submitted that it was a new connection and was
released on the request of the consumer. Subsequently, the outstanding defaulting
amount was charged through sundry item to the consumer. He submitted that since
the connection is in the same name as such they are permitted by the Supply Code
Regulations to recover the defaulting amount. The Forum observed that the details
of the defaulting amount were not intimated by the Sub Division. The Forum,
therefore, called for certain information along with defaulting amount, Date of PDCO
etc. from the Nodal Officer vide letter dated 16.9.2014 and 26.11.2014. The
3
concerned SDO supplied the requisite details vide letter dated 18.9.2014 and
11.5.2015. From the details provided by the Sub Division it was noted that last bill
including current energy charges were issued for the period June to August 2001 as
Rs.20,210/-. Thereafter yearly interest/surcharge @ 10% per annum was levied and
thus defaulting amount of Rs.20,210/- in August 2001 became R.29,878/- in 2006.
6. The Case was then listed for hearing on 16.7.2015. The complainant, Xen. ‘OP”
Division No.2, SDO ‘OP’ Sub Division No.8 and RA were present. The complainant
as well as respondent Xen reiterated their earlier submissions. The complainant also
stated that he was issued no dues certificate at the time release of connection.
7. On Subsequent date of hearing on 18.8.2015, the Complainant only showed the
photo copy of Application Form submitted to the Sub Division for release of new
connection. The complainant submitted that he had already paid excess bill
through two instalments of Rs.20,000/- and Rs.10,000/- which were deposited under
protest.
8. The Nodal Officer informed that the consumer had not been paying the current bill
charges for the last two years or so.
9. Observations and decision by the Forum:
The Forum observed that the Sub Division can recover the defaulting amount in the
name of same consumer as per Regulations 9.2(10) of the Supply Code. In the
present case the premises is also same. However, the Sub Division should have
disconnected the supply on the first/ second default and should have made efforts to
recover the defaulting amount. It appears from the documents placed before the
Forum that such action was not taken by the Sub Division. The Forum considering
the request of the consumer not to recover at least the surcharge decides that only
principle amount of default i.e. Rs.20,210/- be recovered from the consumer instead
of Rs.29,878/- which grew on account of levy of interest on the principle amount. No
surcharge on this amount of Rs.20,210/- is to be levied till date of payment of this
amount. The surcharge on the current bills issued but not paid would, however, be
levied as per instructions. The consumer is also directed to pay the current cycle
charges simultaneously. While overhauling the amount it may be ensured that the
surcharge is levied only on the outstanding payment and not on full amount of bill
4
when part payment was made by the consumer. Compliance be reported within
twenty one days.
10. The SE/Electricity is also directed to re-iterate the provision of Supply Code to be
followed by the Nodal Officers in letter and spirits particularly w.r.t. disconnection of
electricity supply on default in payment of Electricity bills.
11. With the above observations, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
12. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
5
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 575 Date of Institution - 08.01.2014 Date of Order - 16.09.2015 In the matter the Registrar, Panjab University, Sector-14, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.4, UT, Chandigarh.
……………….Respondents
Order
1. The Registrar, Panjab University, Chandigarh approached the Forum vide letter
dated 19/20th December 2013, sent under Registered cover, which was received by
the Forum on 8.1.2014. The applicant stated that the electricity distribution system
in Panjab University is with Chandigarh Electricity Department. All the Electricity
connections have been released on LT side. The department and hostels of the
campus face various problems relating to electricity such as extension of load, low
voltage, electricity failures, frequent tripping and voltage fluctuations etc. Moreover,
a few new buildings come up in Sector-14 are lying unused due to non release of
electricity connections by the Electricity Department with the plea that total load of
buildings in the campus is more than 5 MW and needs to be clubbed and obtained
on 66 KV supply as per Hon’ble JERC Tariff Order dated 20.5.2010. The applicant
submitted that the Panjab University is not in a position to get the Power Connection
at 66 KV supply as the requisite power infrastructure is not ready. He apprised
following to the Forum:-
i) The Panjab University Board of Finance in its meeting held on 27.7.2011 has
sanctioned Rupees Six Crores funds for creating power infrastructure in first
phase.
6
ii) 1500 Sq. Yard of land has been kept reserved for creating 66 KV Grid Sub
Station Sector-14, Panjab University Campus, as shown in the Master Plan.
Additional land can also be allotted as per the requirement.
iii) The locations of existing and proposed Sub Stations would be as per
proposal marked in the attached Master Plan. These Sub Stations would be
connected through 5 Nos. 11 KV overhead/underground feeders from newly
proposed 66 KV Grid Sub Station to be installed in Panjab University
Campus, Sector-14, Chandigarh, as per Site Plan attached.
The applicant also mentioned that in view of non availability of manpower and
technical knowhow, the Panjab University requested Power Grid Corporation of
India (PGCI) and Bhakra Beas Management Board (BBMB) for executing the work
of 66 KV supply station on turnkey basis. In the meanwhile, following prayer was
made for utilizing the new buildings and one extended portion of the building that
urgently need power connections.
a) To release new connections to the newly constructed buildings on 440 Volts
supply to put the newly constructed buildings infrastructure in use immediately as
per existing practice. Panjab University, Chandigarh would pay the LT surcharge
till release of electricity connection on 66 KV lines.
b) To exclude the residences and shops from the load to be applied with
Chandigarh Electricity Department on 66 KV lines for an initial period of five
years as at present, Panjab University, Chandigarh does not have sufficient staff
strength and the infrastructure for same.
2. The complaint was forwarded to the Nodal Officer i.e. Additional Superintending
Engineer, Electricity Operation Division No.1 vide letter dated 5.2.2014 for
submitting parawise comments.
3. The concerned SDO ‘OP’ Sub Division No.4 through written submissions dated
24.2.2014 duly countersigned by the Additional Superintending Engineer, Elecy.
‘OP’ Division No.1 submitted that, the issue raised by the applicant does not fall
under the preview of the Forum as there is no provision in the notified Tariff
approved by the Hon’ble JERC for release of Electricity connection where the load is
more than 5 M.W and also the provision of LT surcharge. It was also advised that
7
applicant may seek the relief from the Hon’ble JERC by filing the petition before
them.
4. The complaint registered as Complaint No. 575 was listed for hearing on
5.11.2014, only SDO was present but the representative of the complainant did not
attend. The case was again notified for hearing on 23.12.2014 when the
representative of the complainant as well as SDO were present. The representative
of the complainant requested for release of connections at LT or at 11 KV but the
SDO objected stating that there is no such provision in the regulations. The
complainant was also requested to submit a definate time plan for getting the supply
at 66 KV as per the feedback from PGCIL.
5. On the next date of hearing on 16.9.2015, the representative of the complainant as
well as SDO along with his RA were present. The representative of the applicant
requested for release of connections of new buildings at LT or 11 KV. He also
agreed for laying a separate feeder from the Sub Station. To a query by the
Forum, the applicant stated that the present sanctioned load of Panjab University is
about 9 M.W and request for release of new/extended load has been made for
additional load of 3 M.W. With regard to setting up of 66 KV Substation it was
informed that applicant is already in contact with PGCIL for the same. The SDO
stated that present load of the Panjab University is being fed through two
independent feeders and three common feeder. As the total load is more than 5
M.W., as such the connection is required to be applied on 66 KV as per Tariff orders
issued by the Hon’ble JERC for the year 2014-15. The SDO also supplied a copy of
letter dated 27th Feb. 2015 written by the S.E. Electricity Operation U.T. to Panjab
University regarding installation of 66 KV Sub Station in Panjab University. In this
letter, the feeding arrangement of the proposed 66 KV sub station to be set up by
Panjab University was shared along with relevant details. The Panjab University
was also requested to submit drawings for the proposed 66 KV Sub Station along
with load flow study. SDO stated that drawings have not yet been submitted by the
applicant.
6. Observations and Decision by the Forum:
8
The Forum noted that the applicant was requesting for release of new
connection/extension of load to the existing connections at a lower voltage Than the
voltage level prescribed by the Hon’ble JERC. The Forum also observed that
release of connections at 400 Volt or even at 11 KV will attract higher losses. With
regard to complainant’s request for relaxing the voltage level for a period of 2 years
or so required for setting up of 66 KV Sub Station with payment of LT surcharge.
The Forum is of the view that it is beyond the Forum to allow such relaxations to the
regulation notified by the Hon’ble JERC. The applicant may approach the Hon’ble
JERC for the above relaxations.
7. With the above observations and decision, the complaint stands as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
9
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM
ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 653 Date of Institution - 23.02.2015
Date of Order - 16.07.2015 In the matter Shri Ram Paul, House No.1636, Mauli Jagran, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Ram Paul, House No.1636, Mauli Jagran, Vikas Nagar, Manimajra, Chandigarh
vide his complaint dated 23.2.2015 submitted that he received an inflated bill of his
domestic connection and requested for getting the same checked, stating that such
high consumption was not possible for his one room and kitchen set.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for examine and submit parawise comment/action taken
report along with consumption data for the last three years vide letter dated
24.2.2015.
3. The concerned AEE ‘OP’ Sub Division No.8 vide his letter dated 11.5.2015
submitted parawise reply duly counter signed by Xen. ‘OP’ Division No.2. He
submitted that the existing connection is under domestic category and on checking,
the load was found as 0.688 KW against the sanctioned load of 0.520 KW. The
working of the meter was also got checked and found O.K. He also supplied the
consumption data along with other relevant documents.
4. The case was formally registered as complaint No.653 and was listed for hearing on
16.7.2015 vide letter No. CGRF-653-656-505-660-659/2015/1029 dated
08.07.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.8 and to the complainant.
10
On the date of hearing, the complainant did not attend. The Nodal Officer Xen
‘OP’ Division No.2, AEE ‘OP’ Sub Division No.8 and RA of the Sub Division were
present.
During the hearing, the Nodal Officer stated that the consumption of 11341 units
during the period 8/2013 to 12/2013 could be possible on account of
accumulation of readings.
5. Observations of the Forum:
On critical analysis of the consumption details it was noted that current reading in
10/2013 was 17116 with previous reading in 8/2013 as 5802 thus recording the
consumption of 11314 units for 2 months. The bill was however prepared on
average considering the reading as inconsistent. The recorded reading in 12/13
was 17143 and 26266 on 5.2.2014 as per MCO dated 28.1.2014 with the meter
status as digit defective. The above details clearly established that the reading of
the meter had the tendency to jump. The Xen/AEE and RA also agreed with the
inference drawn by the Forum.
6. Decision:
The Nodal Officer is directed to get the account overhauled from the period 8/13
to 2/14 on the basis of consumption recorded during the corresponding year in
2012-13. Compliance be reported within twenty one days after the receipt of the
order failing which the Hon’ble JERC may impose penalty as per relevant rules
of Electricity Act 2003.
7. With the above directions, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
11
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 656 Date of Institution - 19.02.2015
Date of Order - 16.07.2015 In the matter Shri Mehar Din, House No.1052, Morigate, Manimajra, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Mehar Din, House No.1052, Morigate, Manimajra, Chandigarh through his
representation dated 19.2.2015 submitted that after receipt of bill of Rs. 4 lacs he
represented to the ‘OP’ Sub Division No.8 Manimajra that the high consumption
recorded by the meter was on account of reading jumping since his average
consumption was of the order of 500 to 600 units only.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 to examine and submit parawise comment/action taken
report along with consumption data for the last three years vide letter dated
24.2.2015.
3. The concerned AEE ‘OP’ Sub Division No.8 vide his letter dated 11.5.2015
submitted parawise reply duly counter signed by Xen. ‘OP’ Division No.2. He
stated that the connection was domestic and on checking the load was found as
2.670 KW against the sanctioned load of 0.240 KW. The working of the meter
was also got checked and found in order. He also supplied the consumption
data along with other documents.
4. The case was formally registered as complaint No.656 and was listed for hearing
on 16.7.2015 vide letter No. CGRF-653-656-505-660-659/2015/1029 dated
08.07.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.8 and to the complainant.
12
On the date of hearing, the complainant as well as Nodal Officer Xen ‘OP’
Division No.2, AEE ‘OP’ Sub Division No.8 and RA of the Sub Division were
present.
From the Consumption data supplied by the Sub Division, it was
noted that against the normal consumption of around 500 units per cycle, the
meter recorded consumption of 85940 units during the period March to May
2014. The respondent Xen ‘OP’ Division No.2 and AEE agreed that such high
consumption could be on account of meter jumping.
5. Decision:
The Nodal Officer is directed to get the meter replaced and overhaul the account
for the period March to May 2014 on the basis of consumption recorded during
the corresponding period (3/13 to 5/13) of the previous year. The surcharge is
also to be adjusted simultaneously. Compliance be reported within twenty one
days after the receipt of the order failing which the Hon’ble JERC may impose
penalty as per relevant rules of Electricity Act 2003.
6. With the above directions, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
13
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON, SH.G.D. SAINI MEMBER AND SH.RL MITTAL (OMBUDSMAN) MEMBER.
Complaint No. - 658 Date of Institution - 18.02.2015
Date of Order - 08.07.2015 In the matter Shri N.K. Gupta, House No.2211A, Sector 42-C, Chandigarh.
………………..Petitioner
Versus
1. The Additional Superintending Engineer, Elecy. Divn. No. 4, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No. 9, UT, Chandigarh.
……………….Respondents
Order
1. Shri N.K. Gupta, resident of House No.2211, Sector 42-C, Chandigarh vide his
complaint received in the office of CGRF on 18.2.2015 submitted that he made a
complaint about the working of his meter as faulty on 18.12.2013. The complaint
was disposed off by CGRF vide order dated 28.7.2014 in complaint No.522 on the
basis of report by concerned SDO ‘OP’ Sub Division No.9 about replacement of his
meter and overhauling of his account. He, however, came to know from the
electricity department that the meter of his neighbour was changed in February 2013
inadvertently and he was being billed on the basis of reading recorded by the
replaced meter which actually belonged to his neighbour House No.2210, Sector 42-
C, Chandigarh. The Sub Division after came to know of this mistake overhauled the
account and sent him a bill of Rs.36000/-.
2. The complaint was forwarded to the Nodal Officer i.e. Addl. Superintending
Engineer, Elecy. ‘OP’ Division No.4 to submit parawise comments vide letter dated
24.2.2015.
3. The concerned SDO ‘OP’ Sub Divn. No. 9 vide his reply dated 20.5.2015 submitted
the facts of the case as follows:-
a) As per order dated 28.7.2014 in Complaint No. 522 of the CGRF the
consumer account was overhauled for the period 10.5.2012 to 20.2.2013 on
14
the basis of consumption for the period 10.5.2011 to 10.5.2012 and
Rs.27117/- was refunded/adjusted vide sundry item dated 11.6.2014.
b) The MCO dated 18.2.2013 was issued to replace the defective energy meter
of the complainant.
c) Inadvertently energy meter of House No.2210A Sector 42-C was changed
and advice was sent to the Computer Centre in respect of account of the
complainant.
d) Subsequently when the fact of intermingling of reading of House No.2210A
and 2211A came to notice, the accounts of both the consumers were
overhauled on the basis of the readings recorded by their respective meters
and were settled through sundry charges/allowances.
e) On receiving the complaint from the complainant a check meter was installed
to check the working of the existing meter which was found to be 6.25% slow.
f) The disputed meter of the complainant was replaced on 24.3.2015.
He also supplied the consumption data of the meter for the last three years.
4. The case was formally registered as Complaint No.658 and was listed for hearing on
25.5.2015 vide letter dated 5.5.2015. A copy of the hearing notice was also sent to
the consumer as well as Nodal officer and SDO
5. The complainant as well as concerned SDO ‘OP’ Sub Division No.9 along with his
RA were present on 25.5.2015. The SDO submitted that in response to
complainant’s, first complaint dated 18.12.2013 (registered as Complaint No.522)
the meter of his neighbour was replaced by mistake which came to notice in the 3rd
quarter of 2014 and accordingly both the accounts was overhauled. The SDO was
directed to submit the consumption details along with readings of both the
consumers of House No.2210A and 2211A (Complainant), Sector 42-C, Chandigarh.
6. The SDO supplied the requisite consumptions vide his letter dated 29.5.2015.
7. The case was re-notified for hearing on 21.7.2015 but the hearing was preponed to
8.7.2015 on the request of the complainant. The applicant, RA and UDC of the
Sub Division No.9 were present. The RA stated that account of the complainant
was overhauled after it came to notice about intermingling of readings of both the
meters from the period 10.9.2012 to 22.9.2014 up to reading 46121 as recorded on
15
the meter. The meter was subsequently replaced on 24.3.2015 at reading of 48595
after meter was found to be slow by 6.25% on the basis of report of check meter.
The complainant, however, insisted that the meter was declared dead by the
department and therefore previous decision made by the CGRF should be continued
till the installation of new meter on 24.3.2015.
8. The Sub Division No.9 vide his letter dated 14th July 2015 submitted the written
statement in confirmation of the oral submissions made by the RA during the
hearing, as under:-
(a) The MCO No. 120/686 dated 18.2.2013 was issued to replace the defective
meter No. CHSE54002 installed at House No.2211A, Sector 42-C, Chandigarh.
(b) Inadvertently energy meter of House No.2210A, Sector 42-C, Chandigarh was
changed but advice was in respect of House No.2211A sent to the computer
centre.
(c) An amount of Rs.27117/- was refunded to the complainant (House No.2211A,
Sector 42-C, Chandigarh) after overhauling the account as per CGRF order in
complaint No.522.
(d) The fact of the wrong meter change came to notice when resident of House
No.2210A approached the Sub Division regarding inadequate billing. The Sub
Division Office again verified on 15.1.2015 and found that the energy meter
No.CHSE-54002 of the complainant was still existing at the site.
(e) The billing of the complainant was being done as per the consumption recorded
by the new installed meter of his neighbour.
(f) The consumer account of the complainant was again overhauled from the meter
readings 32000 to 47816 for Rs.8885 and Rs.27117/- which was earlier refunded
were again charged totalling to Rs.36002/-.
(g) The account of House No.2210A was also set right from the initial reading
amounting to Rs.50,020/- which was paid by the consumer.
(h) On the complainant of Shri N.K. Gupta a check meter was installed vide SJO
dated 23.2.2015 and the working of the disputed meter was found slow by
6.25%.
16
(i) Being a defective meter, the same was replaced on 24.3.2015 at meter reading
of 48595.
The SDO concluded the amount of Rs.36002/- charged to the consumer is
corrected and liable to be paid by him.
9. Views & Commentsof Nominated Member for CGRF of JERC 1. The whole story presented by the department is very confusing or may be it has been made very confusing.
Shri N.K. Gupta, resident of House No. 2211-A, Sector 42-C, Chandigarh had filed a complaint on dated 18.12.2013 regarding heavy amount of bills starting from the month of May 2012 (i.e. 10.5.2012). CGRF lodged this as Complaint No.522 and started its proceedings accordingly. In this complaint the Forum found out that the Consumer’s Meter was “Dead Stop” and there was an abrupt increase in the consumption from 10.5.2012 onwards as compared to the consumption for the past one year. The concerned SDO himself had replied that the consumer’s account was required to be overhauled on the basis of previous consumption as the meter was dead stop and was not showing correct readings. So , the Forum ordered to change the defective meter and to overhaul the account of the consumer from the period 10.5.2012 to 20.2.2013 (i.e. Date of MCO) on the basis of consumption for the period 10.5.2011 to10.5.2012, and ordered to refund/adjust an amount of Rs. 27,113/- to the Consumer, which was calculated on the basis of overhauling of the account and disposed of this ComplaintNo.522 vide order dated 28.7.2014.
2. But instead of complying with the order of the CGRF the Electricity Department charged the consumer an amount of Rs.36,002/- in the bill of dated 8.2.2015.
Electricity Department contended that vide the Meter change order No. 120/686 of dated 18.2.2013 which was issued to replace the defective meter of Shri N.K. Gupta it mistakenly changed Sh. N.K. Gupta’s neighbour’s electricity meter and informed wrongly to the Computer Cell that the electricity meter of Shri N.K. Gupta had been correctly changed. Department said that due to this reason the billing of Shri N.K. Gupta was being calculated as per the consumption of new meter installed on Shri N.K. Gupta’s Neighbour’s House and the billing of the neighbour was being done according to the consumption recorded by the meter installed at the premises of Shri N.K. Gupta. Department said they came to know about this discrepancy on dated 15.01.2015 and overhauled the account of the consumer (Shri N.K. Gupta) according to his meter’s readings for the period 10.9.2012 to 15.1.2015 and charged an amount of Rs.36,002/-. Department also refused from the earlier statement (Letter of SDO Memo. No. 1486 of dated 21.3.2014) regarding dead stop meter and contended that it was pertained to House No.2210, Sector 42 (Neighbour of Shri N.K. Gupta) and not to the complainant.
3. So, whatever amount had been directed to refund in the final order of Complaint No.522, that all had been charged again by the department. On dated 27.1.2015, the consumer had sent a request letter to the CGRF and requested the Forum to ensure the compliance of its final order of Complaint No.522 as even after the passing of more than 6 months from the date of final order, no relief had been provided to him.
4. Directions to Comply: a) Consumer is being harassed form the month of May 2012.
Firstly from May 2012 (10.5.2012) to Feb. 2013 (20.2.2013) his meter readings showed a high inflation as compared to the consumption of previous years and after that he was informed that he was being charged on the basis of units consumed by his neighbour’s meter from 10.9.2012 to 15.1.2015 for period of almost 28 months. Consumer is suffering from the last more than 3 years.
17
b) The whole incident shows a huge carelessness on the part of electricity department. There are various things which look suspicious. I mean, the complaint of high bills were being made by the consumer (Shri N.K. Gupta) but the officials of the department were keep checking the Neighbour’s House. They firstly said that the meter of Shri Gupta was “Dead Stop” and later on they refused, and after that the meter change order was issued for changing the defective meter of Shri N.K. Gupta but the officials of the department changed the Neighbour’s meter and intimated to the Computer Cell that the meter of Shri N.K. Gupta has been correctly changed. And after that, on dated 15.1.2015 (almost after 28 months) the department awoke and came to know that Shri N.K. Gupta was being charged on the basis of Neighbour’s meter consumption and fined him an amount of Rs.36,002/-. The whole incident clearly shows that due to the miscalculations and Wrong workings of the department the consumer is suffering from the past 3 years and more.
c) Consumer had filed his original Complaint on 18.12.2013. His main grievance was high meter readings from May 2012 to Jan.2013 (i.e. 10.5.2012 to 10.1.2013). On 15.1.2015 the department overhauled the account of the consumer for the period 10.9.2012 to 15.1.2015 according to the consumption recorded by Shri N.K. Gupta’s meter. But this overhauling is also wrong because the meter of Shri N.K. Gupta (i.e. CHP-54002) was defective. Consumption pattern of Shri N.K. Gupta’s this meter clearly shows that the meter was not working properly. There are sudden high increases and decreases in the consumption pattern. Consumer had filed his complaint for high bills during the bill cycles of 10.5.2012 -10.7.2012, 10.7.2012 to 10.9.2012, 10.9.2012 to 10.11.2012, 10.11.2012 to 10.1.2013 ( i.e. Bill cycle from May/July 2012 to Nov./Dec. 2012).
Comparison of these above mentioned periods – consumption units with the previous year’s and future year’s consumption units clearly shows that the meter of the consumer was defective. For example InNov.2011, consumer’s consumption was only 664 units but for Nov. 2012 the meter of the consumer is showing consumption as of 2697 units and for Nov. 2013 it is showing consumption of just 393 units. So it is fluctuating-increasing and decreasing. This disorder is consumption pattern indicates that the meter was also defective. It was working sometimes slow and sometimes fast. The check meter Report of 23.2.2015 also says that the meter was not working accurately, it was working slow. But by this report we cannot rule out the possibility of it’s being running fast 3 years ago (i.e. 10.5.2012 – 10.1.2013) as there is a huge time gap between the disputed period and Check Meter Report. The maximum that we can take from check meter is that the meter was not working properly.
d) Firstly, it is to be noted that the consumer has not filed any new complaint. He has only sought the compliance of the order of CGRF in his earlier (himself filed) complaint No.522. The present complaint No.658 has not been filed by the consumer. CGRF cannot itself convert a request letter into a formal complaint without assent of the consumer. CGRF is not a Supreme Court or High Court, it is merely a quasi-Judicial body.
In Civil Cases, there has to be two parties (i.e. Petitioner and Respondent). Petitioner files the complaint and respondent replies. The case cannot go on if the petitioner withdraws the complaint and similarly the case does not become a formal complaint until someone (petitioner) files it. The present complaint 658 has been filed by no one. So, it is not proper, it does not has a proper base. The consumer had only sought the compliance of the order of CGRF is Complaint No.522 but the CGRF not only converted this request letter into a formal complaint but also has completely changed its earlier order in complaint No.522 which is completely against to the Principle of Laws.
18
In Indian Judicial System except the Supreme Court and
the High Courts no one has the power to review its earlier decisions. This is not only forbidden but also an offence of “Contempt of Court”.
In the complaint no. 658, both the parties to the complaint are
same, the subject matter of the complaint is also same as it was in Complaint No.522, just a new cover, “of The Name of Complaint No.658” has been put up as to purport it as a new complaint. But this will also amount to review/rectification in the original orders.
5. In the light of above mentioned Points. I recommend that as per Rules & Regulations of Electricity Act 2003 and Supply Code Regulations 2010, the ComplaintNo.658 is baseless, it is not maintainable. It should be dismissed. CGRF should not challenge the authority of Supreme Court/High Courts. “The order of the CGRF in Complaint No.522 should be implemented. The order of overhauling of the account of the consumer from the period 10.5.2012 to date of MCO on the basis of previous year’s consumption is correct and stands till today.” Department changed the meter of the consumer on dated 24.32015. So, now as per the order of the CGRF in Complaint No.522 the department shall have to do overhauling from 10.5.2012 to 24.3.2015 (i.e. up to the real MCO date of consumer) on the basis of previous year consumption.
(R L MITTAL)
MEMBER, CGRF
Observations of the Forum:
10. The Forum noted the facts of the case as under:-
i) Shri N.K. Gupta submitted a complaint to the Forum on 18.12.2013
submitting that his meter was not working properly and was giving higher
reading. As the main grievance was with regard to the consumption
recorded during the period May to July 2012, July to Sept. 2012 and from
September to Nov. 2012 as 2339, 2148 and 3604 units respectively. The
concerned SDO while submitting the comments stated that the meter of
the consumer was replaced on 26.2.2013 with the remarks that meter
dead stop. He suggested for overhauling the account of the consumer
from 10.5.2012 to 26.2.13 on the basis of previous period consumption
from 10.5.2011 to 10.5.2012 resulting into refund of Rs.27117/-.
ii) The Forum on the basis of written submissions of the SDO disposed off
the complaint after observing that the account of the consumer has been
overhauled for the disputed period vide order dated 28.7.2014 in
complaint No.522.
19
iii) Subsequently it came to the notice of the Sub Division that inadvertently
the meter of neighbour of Shri N.K. Gupta was replaced and the mistake
could not be detected as the readings of both the meters were in the
range of 32000. Thereafter the billing of both houses i.e. 2210A and
2211A were being done on the readings recorded by the meters of other
house. This continued till Jan. 2015 when the discrepancy was detected
and the account of both the consumers were overhauled. As amount of
Rs.36002/- was charged to the complainant through sundry charges. The
complainant then approached the Forum with the present complaint.
During the hearing and through written submissions, Sub Division
admitted their mistake and sated that the earlier report regarding dead
stop meter on the basis of which complaint No. 522 was disposed, was
pertaining to House No.2210 Sector 42 and not to the complainant.
iv) To ascertain the accuracy of the meter with regard to recording of higher
consumption, the Sub Division installed a check meter in series with the
disputed meter. It was, however, seen that meter was in fact found slow
by 6.25%.
v) The disputed meter has since been replaced on 24.3.2015 at the meter
reading of 48595.
vi) The Forum observed from the consumption data that the consumption
during winter season was in the range of 600 units where as the
consumption during the summer months was more than 2000 units per
billing cycle.
vii) The Sanctioned load of complainant is 10.340 KW inclusive 2 ACs of 1.5
ton capacity each which the complainant admitted were switched ‘ON’
only during the night hours.
11. Views & Decision by the Member & Chairman:
We do not agree with the views expressed by Shri R.L. Mittal at NP-6 of this
order that the present complaint No.658 is baseless and not maintainable and the
order of the CGRF in Complaint No.522 should be implemented.
20
As per the fact of the case and observions by the Forum the Complaint
No.522 was disposed off on the basis of facts placed before the Forum. The
orders of the Forum were implemented by the SDO and refund was allowed to the
complainant. However, subsequently new facts came to notice that the factual
position on the basis of which the decision in Complaint No.522 was taken were
totally different. Disputed meter of the complainant was not changed and was in
position till 24,3.2015 and was recording the consumption. On analysis of the
consumption data it was concluded that the consumption being recorded by the
meter was as per the connected load and as per its usage by the complainant.
The estimated consumption as per the connection load and usage of ACs during
night time as conveyed by the complainant was also found to be in the range of
consumption recorded by the meter. Subsequently on installation of check meter
it was established that in fact the meter was recording less consumption by 6.25%.
The above facts clearly support the registering of the present complaint as a
new complaint. The Ld. Member has given his decision in the last para at NP-6
that as per order of the CGRF in Complaint No.522 the department shall have to
do the overhauling from 10.5.12 to 24.3.2015 i.e. up to the real MCO date of
consumption on the basis of previous year consumption. The above decision
means review of the order in Complaint No.522 the representative of the Hon’ble
Commission who visited in June 2015 has strongly objected to the review of the
earlier orders by the Forum. Moreover the complainant in his Complaint submitted
on 18.2.2015 made a fresh complaint on the basis of new facts discovered
subsequently submitting that his meter which he contended were faulty was in
existence till March 2015 and thus the overhauling be done on the average worked
out till the period the meter was at his premises. However, on the basis of other
factors and analysis of the consumption the contention of the complainant that his
meter was faulty does not hold good and thus his prayer was not found to be
acceptable on merit.
12. Decision of the Forum:
i) On the basis of above facts it is seen that the consumption being recorded
by the meter of the complainant was certainly not on higher side. Ultimately
21
it was established in March 2015 after installation of check meter that in fact
the meter was recording less by 6.25% then the actual consumption.
ii) The estimated consumption taking the load factor of 30% and diversity factor
of 2 is 2233 units per billing cycle of 2 months. Otherwise also going by the
statement of the complainant that the ACs were switched ‘ON’ only during
slipping time, the estimated consumption by 2 ACs of 1.5 ton each (1.8 KW
each) taking conservatively as is 1512 units for a period of 2 months
assuming the ACs remains switched ‘ON’ for about 7 hours during night time
only. To this figures when the average consumption of 600 units is added
(when the ACs are not used) the estimated consumption is around 2100 units
for a period of 2 months.
iii) The Forum also noted that the consumption recorded during the summer
months was also 2000plus units and are matching with the estimated
consumption. Thus the apprehension of the complainant that the meter was
recording higher consumption does not stand on the basis of estimated
consumption as well as conclusion drawn about the working of the meter with
installation of check meter.
13. In view of above, the Forum agrees with the submissions made by the Sub Division
that the charging done by them on the basis of reading recorded by the meter is in
order. The Nodal officer is directed to overhaul the account on the basis of report of
check meter as per provisions laid down in the Supply Code if not done already.
Compliance be reported within a period of 21 days failing which the Hon’ble JERC
may impose the penalty as per the relevant sections of the Electricity Act 2003.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
14. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
22
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(G.D. SAINI) (R.K.ARORA) MEMBER, CGRF CHAIRPERSON, CGRF
23
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM
ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 659 Date of Institution - 16.02.2015
Date of Order - 16.07.2015 In the matter Shri Kishore Bansal, House No.5414/1, Manimajra Housing Complex, Manimajra, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Kishore Bansal, resident of House No. 5414/1, Modern Housing Complex,
Manimajra, Chandigarh through his representation dated 16.2.2015 submitted
that he received an inflated bill for Rs.9,71,030/- for the period 31/5/14 to 31/7/14
which he attributed could be due to jumping of meter reading.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 to examine and submit parawise comment/action
taken report along with consumption data for the last three years vide letter dated
19. 2.2015.
3. The concerned AEE ‘OP’ Sub Division No.8 vide his letter dated 11.5.2015
submitted parawise reply duly counter signed by Xen. ‘OP’ Division No.2. He
submitted that the connection was domestic and on checking the load was found
as 14.660 KW against the sanctioned load of 14.990 KW. The working of the
meter was also got checked and found O.K.. He also supplied the consumption
data.
4. The case was formally registered as complaint No.659 and was listed for
hearing on 16.7.2015 vide letter No. CGRF-653-656-505-660-659/2015/1029
dated 08.07.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub
Division No.8 and to the complainant.
24
On the date of hearing, Shri Harjinder Singh was present on behalf of Shri
Kishore Bansal. The Nodal Officer Xen ‘OP’ Division No.2, AEE ‘OP’ Sub
Division No.8 and RA of the Sub Division were also present.
He submitted that the disputed bill was for very high consumption
and it could be due to reading jumping. The Nodal Officer Xen ‘OP’ Division
No.2 and AEE agreed that such a high consumption of 81289 units against the
normal consumption in the range of 300 to 600 units could be on account of
meter jumping.
It was also observed that the subsequent consumption from Sept.
2014 to Jan. 2015 was also on higher side as compared to previous year
consumption.
Decision:
5. The Nodal Officer is directed to get the meter replaced and get the account
overhauled from July 2014 to till date of MCO on the basis of consumption
recorded in the previous year for the corresponding period. Compliance be
reported within twenty one days after the receipt of the order failing which the
Hon’ble JERC may impose penalty as per relevant rules of Electricity Act 2003.
6. With the above directions, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
25
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 660 Date of Institution - 16.02.2015
Date of Order - 16.07.2015 In the matter Shri Mohan Ram, House No.265/3, Gali No.11, Shanti Nagar, Manimajra, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Mohan Ram resident of House No.265/3, Gali No.11, Shanti Nagar,
Manimajra, Chandigarh through his representation dated 16.2.2014 submitted
that he received an inflated bill in the month of October 2014 with consumption
showing as 81968 units against his normal consumption. He challenged the bill
after depositing the requisite fee of Rs.10/- but he did not get any relief and
therefore approached the Forum.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 to examine and submit parawise comment/action taken
report along with consumption data for the last three years vide letter dated 19.
2.2015.
3. The concerned AEE ‘OP’ Sub Division No.8 vide his letter dated 11.5.2015
submitted parawise reply duly counter signed by Xen. ‘OP’ Division No.2. He
submitted that the connection was domestic and on checking the load was found
as 2.955 KW against the sanctioned load of 3.000 KW. The working of the meter
was also got checked and found O.K.. He also supplied the consumption data.
4. The case was formally registered as complaint No.660 and was listed for hearing
on 16.7.2015 vide letter No. CGRF-653-656-505-660-659/2015/1029 dated
08.07.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.8 and to the complainant.
26
On the date of hearing, the complainant as well as Nodal Officer Xen ‘OP’
Division No.2, AEE ‘OP’ Sub Division No.8 and RA of the Sub Division were
present.
The complainant reiterated his written submission that such a high
consumption could be on account of meter jumping. The respondent Xen ‘OP’
Division No.2 and AEE agreed that it could be case of jumping of meter.
Decision:
5. The Nodal Officer is directed to get the account overhauled of the complainant
for the disputed period on the basis of consumption recorded during the
corresponding period in the previous year. Compliance be reported within twenty
one days after the receipt of the order failing which the Hon’ble JERC may
impose penalty as per relevant rules of Electricity Act 2003.
6. With the above directions, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
27
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI , MEMBER AND
SH. R. L. MITTAL, OMBUDSMAN (RETD.), NOMINATED MEMBER. Complaint No. - 691 Date of Institution - 23.03.2015 Date of Order - 28.07.2015 In the matter of the Assistant Landscaping Officer, Hort. Sub Division No.2, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Electy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Electy. ‘OP’ Sub-Divn. No. 2, UT, Chandigarh.
……………….Respondents
Order
1. The Complainant submitted his complaint regarding disconnection of electricity
meter installed at Sukhna Tower due to non payment. It is further submitted that he
was regularly paying the electricity bill up to 12.7.2013. The Electricity department
has shown the arrear amounting to Rs.1,53,218/- in the recently bill received to the
department and the same amount was not related to the Horticulture Department.
With the request that the electricity department be directed for rectify the bill of
Horticulture department so that the Nursery/flower beds and horticulture related
works might not be suffered and the bills of disputed amount was also attached with
the complaint.
2. The representation was sent to the Nodal Officer, the Addl. Superintending
Engineer, Elecy. ‘OP’ Division No.1 for submitting parawise comments/action
taken report and along with consumption data for the last three years on the
representation, vide Memo.No. CGRF/Comp.-Misc./2014/59 dated 20.01.2014.
3. In view of this, the concerned SDO ‘OP’ Sub Division No.2 submitted his reply
vide Endst.No.456 dated 3.2.2014, SDO concerned submitted that a sum of
Rs.1,14,472/- was transferred to the account of the applicant bearing A/c No.
0342/000003X from A/c No. 0342/600840P being the same consumer. The
electricity meter of A/c No. 0342/600840P was removed on dated 3.12.2008 due
to non payment of electricity dues. The SDO concerned further submitted that
28
after the transfer of the amount the consumer stopped making the payment of
dues against existing account. At this position, electricity department has taken
the action and supply to the electricity of Meter No.CHEP-36814 bearing A/c
No.0342/000003X is also disconnected on dated 15.1.2014 at reading 062099.
At present a sum of Rs. 1,72,560/- was outstanding against the applicant
against A/c No.0342/000003X, so the action taken by the electricity department
was as per rules of the department. The SDO concerned also make the request
to the Forum to direct the complainant to make the payment at the earliest. SDO
concerned also attached the consumption data for the last three years with his
reply.
4. (i) The reply of A.L.O. Hort. Sub Divn.No.2 submitted secondary reply and
requested regarding his complaint vide Endst.No.188 dated 5.2.2014. The
complainant further submitted that after disconnection of A/c No. 0342/600840X
due to non payment, because the pending amount under this account was
merged in form of arrear with the account of 0342/000003X.
ii) The issue of delay payment under A/c No.0342/000003X cannot be
blamed upon this office as the delay was due to the procedural mistake of
merging the payments of different accounts. The complainant further raised the
points in view of the above, that the bill of A/c No. 0342/000003X might be
corrected and the amount of the arrear pertaining to the other account to avoid
delay in making the payment of the same and the complainant also requested for
revived of connection of account immediately, because this office was facing
problem of watering of the flower beds and plants at Sukhna Lake, Sector-6,
Chandigarh and this office has no concerned with the amount of the arrear of
Rs.1,60,768/- to this account related to A/c No. 0342/600840X.
5. The representation of the complaint was treated as formally as Complaint No.691
and the notice was issued to the concerned Nodal Officer with a copy to the
complainant fixing the case for consideration on dated 7.4.2015 vide this office
Memo. No. CGRF/Comp.-686-694/2015/325 dated 23.3.2015 and the same was
heard by the Forum. SDO was present but the complainant did not appear.
29
One more opportunity was given to the complainant to explain his position and
case was listed for hearing on 28.7.2015 vide letter No. CGRF/Comp-
746/747/748/691/023 dated 8.7.2015. On the date of hearing on 28.7.2015,
the complainant did not attend. The Xen ‘OP’ Division No.1 and SDO ‘OP’ Sub
Division No.2 were however, present.
6. Observations of the Forum:
After hearing the Xen ’OP’ Divn. No.1 and watching the complaint of the
consumer, Forum reached on the final decision that the amount pending in the
shape of arrear of Rs.1.60,768/- was related to A/c No/. 0342.600840X and the
same was merged in A/c No. 0342/000003X as both connections were in the
same nature.
7. Decision:
The Sub Regulation 10 of the Regulation 9.2 of Supply Code provides
disconnect ion of supply where any consumer having more than one connection
defaults in payment of dues relating to one of the connections.
Thus the action of Nodal Officer in transferring the defaulting amount of the
account of the same consumer and subsequently attending PDCO is as per
regulations.
8. With the above observations and directions, the case is dismissed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
9. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R.L. MITTAL) (G.D. SAINI) (R.K. ARORA) MEMBER,CGRF MEMBER, CGRF CHAIRPERSON, CGRF
30
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON AND SH.G.D. SAINI MEMBER
Complaint No. - 694 Date of Institution - 04.12.2014
Date of Order - 09.07.2015 In the matter Shri H.S. Mejie, House No.55, Sector-2, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 2, UT, Chandigarh.
……………….Respondents
Order
1. Shri H.S. Mejie, resident of House No.55, Sector-2, Chandigarh vide e-mail
received on 15 Jan. 2015 forwarded a copy of letter dated 17.9.2014 /4.12.2014
addressed to the SDO ‘OP’ Sub Division No.2 regarding high consumption being
recorded by the meter. It was stated that the meter is recording more
consumption then being actually used by them.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.1 for comments/action taken report along with
consumption data vide Memo. No. CGRF/Comp-Misc/2015/79 dated
09.02.2015. A copy of the letter was also forwarded to the complainant vide
Endst. No. CGRF/Comp-Misc/2015/80 dated 09.02.2015.
3. The Nodal Officer i.e. Xen ‘OP’ Division No.1 vide Memo. No. 2767 dated
11.3.2015 forwarded the reply submitted by AEE’OP’ Sub Division No.2 wherein
he submitted that in response to application by the consumer regarding the
excess bills, the electricity meter of the consumer was got checked from the JE
of his office. As per his report dated 5.12.2014, the meter working was found in
order and the above position was conveyed to the consumer on 29.12.2014.
Thereafter on another representation of the consumer, the check meter was
installed by the office itself and the result of the meter were found within
permissible limits. The complainant however, vide his letter dated 17.1.2015 to
31
the report of check meter and insisted that the meter be got tested in the Lab.
The consumption data was also enclosed.
4. The case was formally registered as complaint No.694 and was listed for hearing
on 14.5.2015. On the date of hearing both the consumer as well as SDO were
present. The consumer, however, showed his dis-satisfaction and insisted that
the meter got tested in the M&P Lab. The SDO stated that meter could not be
tested in the lab as the testing equipment was under re-caliberation.
5. Subsequently SDO vide his letter dated 15.6.2015 submitted that the electricity
meter was tested on 10.6.2015 in M&P Lab of the department in the presence of
the consumer and the working of the meter was found within permissible limits.
6. The case was again listed for hearing on 9.7.2015 vide letter dated 25.6.2015.
The representative of the complainant who attending the hearing was informed
by the SDO (during the hearing) that the report of check meter as well as testing
in M&P Lab established that the working of the meter is O.K. and therefore, bills
raised on the consumption recorded by the meter is in order. The representative
showed his satisfaction to the lab report. He, however, conveyed that the bills
were not being delivered in time. The SDO stated that the delivery of the bill was
assigned to the postal department and he will pull them in this regard.
7. With above observations that working of the meter is in order, the complaint
stands disposed. The Licensee is, however, directed to ensure that the bills are
delivered to the consumers by the postal department in time and give sufficient
time before the due date of the bill enabling them to make payment.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
32
8. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(G.D. SAINI) (R.K.ARORA) MEMBER,CGRF CHAIRPERSON, CGRF
33
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 708 Date of Institution - 19.02.2015
Date of Order - 10.08.2015 In the matter M/s B4 Solutions Pvt. Ltd. (Bharti Airtel), C-127, Phase 8, Industrial Area, Mohali
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No. 1 UT, Chandigarh.
……………….Respondents
Order
1. M/s B4 Solutions Pvt. Ltd., (Bharti Airtel) vide letter dated 13.2.2015 submitted that
during the period their meter remained defective w.e.f. May 2013 to July 2014, they
were charged consumption higher than the past average consumption. They
requested the concerned SDO for charging on the basis of average consumption but
SDO vide his letter dated 30.1.2015 stated that their meter was burning every year
and no proper reading record could be maintained. He also indicated the 2 months
readings recorded by the replaced meter to justify the consumption charged during
the meter remained defective.
2. The comments of the Nodal Officer i.e. Executive Engineer, Electricity Operation
Division No.1 were called vide this office Memo. No. CGRF/Comp-Misc./2015/136
dated 18.2.2015 along with consumption data for the last three years.
3. The SDO ‘OP’ Sub Divn. No.1 vide his letter dated 3.3.2015 addressed to Xen of
Division No.1 submitted that since the meter of the complainant was burning every
year and the higher consumption was charged which whould be adjusted on the
basis of consumption recorded by the replaced meter by taking approval from the
competent authority. He supplied the consumption data for the last three years
along with MCOs..
34
4. The complaint was formally registered as Complaint No.708 and notice was issued
to the concerned Xen (Nodal Officer) with copy to the complainant fixing the case for
consideration on dated 23.4.2015 vide Memo. No. 549 dated 16.6.2014 with the
copy to the complainant. On the date of hearing, the complainant as well as Nodal
Officer i.e. Xen ‘OP’ Divn. No.1, SDO ‘OP Sub Divn. No.1 along with his RA were
present.
During the hearing, the Nodal Officer i.e. Xen. ‘OP’ Divn. No.1 desired to get the
load of the complainant checked to identify the reason of frequent burning of the
meter. The Forum gave permission and to submit the report in this regard.
The SDO ‘OP’ Sub Divn. No.1 vide his letter dated 20.5.2015 supplied up to date
consumption of account along with ECR and also stated that the meter was found
Dead Stop as per ECR.
5. The case was renotified for hearing on 10.8.2015 vide Memo. No.CGRF/Comp-
708/709/712 to 714/2015/1137 dated 24.7.2015 with a copy to the complainant. On
the date of hearing, the Complainant as well as SDO along with his RA were
present. The Forum observed that as per ECR report dated 12.5.2015 the meter
was found to be in working order.
6. Observations and Decision of the Forum:
On the basis of consumption data it was observed that the consumption recorded
by the meter prior to getting defective, is available for more than 6 months. The
Nodal Officer is therefore directed to overhaul the consumption during the disputed
period with the corresponding consumption recorded in the year 2013, for which the
meter was in working order. As the meter of the complainant is getting
burnt/becoming dead stop frequently, the Nodal Officer is also directed to shift the
meter outside the premises. The refund should be allowed to the complainant only
after the meter is shifted outside or complainant gives an undertaking in this regard.
As Per SDO & RA says that the consumer used the Electricity meter on
First/Second Floor for domestic use, if anything is found wrong the same may be
intimated to the Forum.
35
The penalty for excess load, if any, found during checking may also be imposed.
Compliance be reported within 21 days of issue of order failing which the Hon’ble
JERC may impose penalty as per relevant sections of Electricity Act 2003.
7. With the above observations and decision, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
36
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 712 Date of Institution - 19.02.2015
Date of Order - 10.08.2015 In the matter Shri Kuldip Singh Sabharwal, House No.704, First Floor, Sector 22-A, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No. 1 UT, Chandigarh.
……………….Respondents
Order
1. Shri Kuldip Singh Sabharwal, resident of House No.704, First Floor, Sector 22-A,
Chandigarh through his representation dated 19.2.2015 stated that he received a
bill dated 8.2.2015 for a consumption of 3509 units. He also stated that he is not
residing regularly in the house and live with his aged and ailing in-laws. He
apprehended that it is a case of technical defect/fault in the meter/wiring or an
irregularity committed by the ground floor resident to transfer his electricity
consumption to his account by manipulation as he is an employee of the electricity
department.
2. The comments of the Nodal Officer i.e. Executive Engineer, Electricity Operation
Division No.1 were called vide this office Memo. No. CGRF/Comp-Misc./2015/180
dated 24.2.2015 along with consumption data for the last three years.
3. The Nodal Officer vide his letter dated 31.3.2015 forwarded the reply submitted by
the concerned SDO ‘OP’ Sub Divn. No.1 that the electricity meter was got checked
through JE-II on 26.2.2015 and was found to be in working order. The connected
load was also found to be more than the sanctioned load. He contended that the bill
prepared for the period 10.11.2014 to 10.1.2015 was as per reading recorded by the
meter. He also supplied the consumption data long with report of J.E.
4. The complaint was formally registered as Complaint No.712 and notice was issued
to the concerned Xen (Nodal Officer) with copy to the complainant fixing the case for
37
consideration on dated 23.4.2015 vide Memo. No. 549 dated 16.6.2014 with the
copy to the complainant. On the date of hearing, the complainant as well as Nodal
Officer i.e. Xen ‘OP’ Divn. No.1, SDO ‘OP Sub Divn. No.1 along with his RA were
present.
In view of the submissions by the complaint as well as by the SDO it was felt that the
consumption for the last three years in respect of other two connections existing in
the premises be also analysed in view of the allegations by the complainant.
Accordingly SDO was directed to furnish the requisite data.
The SDO ‘OP’ Sub Division No.1 vide his letter 24.4.2015 supplied the consumption
data for the other two connections. It was observed that the consumption pattern of
other two connections was similar in the three years and further no appreciable
decrease in the consumption was observed during the disputed period. The
complainant subsequently through his letter dated 29.4.2015 reiterated his earlier
submissions.
The SDO ‘OP’ Sub Division No.1 in response to this office letter dated 30.4.2015
also submitted that the in view of the make of the meter installed at the premises of
complaint there is possibility of meter jumping as the complainant is not residing in
the house regularly.
5. The case was renotified for hearing on 10.8.2015 vide Memo. No.CGRF/Comp-
708/709/712 to 714/2015/1137 dated 24.7.2015 with a copy to the complainant. On
the date of hearing, the Complainant as well as SDO along with his RA were
present. Shri V.B. Khaana also attending the hearing along with complainant after
producing an authorised letter from the complainant. After observing the
consumption pattern of the complainant as well as of other two connections existing
in the house and the submissions made by the SDO , the Forum observed that this
could be a case of meter jumping. The Forum also noted that in some other cases
the meter jumping has come to notice of this particular make of the meter.
6. Decision of the Forum:
In view of the report given by the SDO that there is possibility of meter jumping,
the Forum agreed with the SDO’s submissions that it would be a case of meter
jumping. The Nodal Officer is, therefore, directed to overhaul the consumption of
38
the disputed period from 10.11.2014 to 10.1.2015 on the basis of average
consumption recorded during the period Nov. 2011 to Jan.2012, Nov. 2012 to Jan.
2013 and Jan. 2013 to Nov. 2014 in view of the fact that the disputed period is only
two months, the average on the basis of 6 month consumption is being worked out.
The disputed meter be also got replaced with a good quality meter. Compliance be
reported within 21 days of issue of order failing which the Hon’ble JERC may
impose penalty as per relevant section of Electricity Act 2003.
7. With the above observations and decision, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
39
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 713 Date of Institution - 13.02.2015 Date of Order - 10.08.2015 In the matter M/s Indus Tower (House No.1509, Sector 22-B), Chandigarh
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No. 1 UT, Chandigarh.
……………….Respondents
Order
1. M/s Indus Tower (House No.1509, Sector 22-B) Chandigarh vide letter dated
26.12.2014, submitted in the CGRF on 13.2.201, submitted that they received one
energy bill for the consumption from 14.6.2014 to 14.10.2014 for 33628 units. It
was also stated that from 14.8.2013 to 14.4.2014 they have paid high consumption
based bill of 86752 units i.e. 21688 units per bill for 4 cycles which was on higher
side as per the consumption recorded during the period December 2011 to
December 2013.
2. The comments of the Nodal Officer i.e. Executive Engineer, Electricity Operation
Division No.1 were called vide this office Memo. No. CGRF/Comp-Misc./2015/134
dated 18.2.2015 along with consumption data for the last three years.
3. The Nodal Officer i.e. Xen ‘OP’ Divn. No.1 vide his letter dated 31.3.2015
forwarded the reply submitted by the SDO ‘OP’ Sub Divn. No.1. The SDO
submitted that meter of the complainant was replaced on 13.5.2014 as the meter
was found burnt. He stated that the bills were issued for higher consumption (to be
adjusted subsequently) as it was apprehended that the connected load was more
than the sanctioned load. The consumption data was also supplied.
4. The complaint was formally registered as Complaint No.713 and notice was issued
to the concerned Xen (Nodal Officer) with copy to the complainant fixing the case for
40
consideration on dated 23.4.2015 vide Memo. No. 549 dated 16.6.2014 with the
copy to the complainant. On the date of hearing, the complainant as well as Nodal
Officer i.e. Xen ‘OP’ Divn. No.1, SDO ‘OP Sub Divn. No.1 along with his RA were
present.
During the hearing, the Nodal Officer i.e. Xen. ‘OP’ Divn. No.1 desired to get the
load of the complainant checked to identify the reason of frequent burning of the
meter. The Forum gave permission and to submit the report in this regard.
The SDO ‘OP’ Sub Divn. No.1 vide his letter dated 20.5.2015 supplied up to date
consumption of account along with ECR and also stated that the meter was found
defective as per ECR.
5. The case was re-notified for hearing on 10.8.2015 vide Memo. No.CGRF/Comp-
708/709/712 to 714/2015/1137 dated 24.7.2015 with a copy to the complainant. On
the date of hearing, the Complainant as well as SDO along with his RA were
present. The Forum observed that as per ECR report dated 12.5.2015 the meter
was found Dead Stop. Accordingly MCO dated 14.5.2015 was issued. The total
load was found to be 10.440 KW.
6. Observations and Decision of the Forum:
On the basis of consumption data it was observed that the consumption recorded
by the meter prior to getting defective, is available for more than 6 months. The
Nodal Officer is therefore directed to overhaul the consumption during the disputed
period with the corresponding consumption recorded in the year 2013, for which the
meter was in working order. As the meter of the complainant is getting
burnt/becoming dead stop frequently, the Nodal Officer is also directed to shift the
meter outside the preemies. The refund should be allowed to the complainant only
after the meter is shifted outside or complainant gives an undertaking in this regard.
As Per SDO & RA says that the consumer used the Electricity meter on
First/Second Floor for domestic use, if anything is found wrong the same may be
intimated to the Forum.
The penalty for excess load, if any, found during checking may also be imposed.
Compliance be reported within 21 days of issue of order failing which the Hon’ble
JERC may impose penalty as per relevant Sections of Electricity Act 2003.
41
7. With the above observations and decision, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
42
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 737 Date of Institution - 04.03.2015
Date of Order - 23.07.2015 In the matter Shri Chaman Lal, House No.242 PWT, Manimajra, U.T., Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Chaman Lal, resident of House No.242, PWT, Manimajra, Chandigarh vide his
representation dated 4.3.2015 submitted that though his average consumption is in
the range of 120 to 150 units per month, he received an abnormal bill for 30177
units during the period 18.10.2013 to 18.2.2014. He submitted an application for
challenging the bill and deposited the requisite fee. The Sub Division, however,
informed him that meter is working properly forcing him to approach the Forum.
2. The comments of the Nodal Officer i.e. Executive Engineer, Elecy. ‘OP’ Division
No.2 were called vide letter dated 11.3.2015 along with the consumption data for
the last three years.
3. The concerned AEE ‘OP’ Sub Division No.8 vide his letter dated 11.5.2015
submitted parawise reply duly counter signed by Xen. ‘OP’ Division No.2. He
submitted that the existing connection is under domestic category and the load
was found as 0.980 KW. The working of the meter was also checked and found
in order. He also supplied the consumption data of the complainant for the last
three years.
4. The case registered as complaint No.737, was listed for hearing on 23.7.2015
vide letter No. CGRF-737-738-740/2015/1035 dated 08.07.2015, a copy of
which was also sent to the SDO, Electy. ‘OP’ Sub Division No.8 and to the
complainant.
43
5. On the date of hearing, both the complainant as well as concerned SDO ‘OP’
Sub Division No.8 along with his RA were present. The complainant submitted
that high consumption could be on account of meter reading jumping. The
Forum from the consumption data concluded that against the normal
consumption in the range of 200 units, the consumption of 30177 with connected
load of less than is 1 KW was not possible and it could be a case of meter
reading jumping. The SDO along with his RA agreed.
6. The Forum therefore, directs the Nod
7. al Officer to overhaul the account of the disputed period on the basis of
corresponding consumption recorded in the previous year. Compliance be
reported within twenty one days after the receipt of the order failing which the
Hon’ble JERC may impose penalty as per relevant rules of Electricity Act 2003.
8. With the above directions, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
9. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
44
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 738 Date of Institution - 10.03.2014 Date of Order - 18.08.2015 In the matter Smt. Sunita Verma, House No. 556, Sector-8, Panchkula.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.8 UT, Chandigarh.
……………….Respondents
Order
1. Smt. Sunita Verma resident of House No.556, Sector-8, Panchkula vide her
representation dated 7.3.2014, received in the office on 10.3.2014, submitted that
she is owner of Shop No. 156/30, Rama Market, Manimajra along with other shop
in the vicinity which are let out to various tenants. A sum of Rs.2,14,087/- was
added in the bill issued against Shop No.156/30, Rama Market in the month of
Nov. 2013 . On enquiry from the SDO ‘OP’ Sub Division No.8 office it was revealed
that amount was pending for the Bill of Shop No.2366/1, Mariwala Town, Manimajra
which was let out to Shri Yogesh Soni with Registered Lease Deed from 1.1.2010
onwards. It was further sub let to Shri Pulkit . Complainant submitting that imposing
the sundry charges of Rs.2,14,087/- is illegal, arbitrary and against the law as the
disputed amount relates to the tenant and that the person cannot be punished for
the fault of another person. She also supplied the Power of Attorney that Shri Ashok
Kumar would represent her case before the Forum.
2. The comments of the Nodal Officer i.e. Executive Engineer, Electricity Operation
Division No.2 were called vide letter dated 10.3.2014 along with consumption data
with a copy to the complainant.
3. The Assistant Executive Engineer, ‘OP’ Sub Division No.8 vide his letter dated
5.6.2014 duly counter signed by the Nodal Officer i.e. Xen ‘OP’ Divn. No.2 submitted
parawise reply as under:-
45
a) That one of the connection in the name of the complainant was disconnected on
payment defaulter and the pending amount of Rs.2,14,087/- has been transferred
to another account of the same consumer.
b) Both these accounts stand in the name of Smt. Sunita Verma, the complainant.
c) The Electricity connection of the premises was disconnected on default and the
meter removed before transferring the defaulting amount.
The consumption data for the last three years was also supplied.
4. The complaint formally registered as Complaint No.738, was notified for hearing on
23.7.2015. The representative of the complainant submitted that transferring of
defaulting amount of the tenant to the owner against another account is not in order.
The SDO submitted that amount was transferred as per Regulations of the Supply
Code. The quoting the references/ regulations in support, the complainant as well
as SDO sought more time. It was decided to hold one more hearing on 18.8.2015 at
3.00 P.M.
5. On 18.8.2015, the representative of the complainant, Nodal Officer and the SDO OP’
Sub Division No.8 along with his RA were present. The representative of the
complainant again submitted that the defaulting amount of one connection can not
be transferred to another connection of the consumer. The Nodal Officer submitted
that as per Regulations 9.2(10) of the Supply Code the defaulting amount of one
connection can be transferred to another connection of the same consumer and thus
the levy of sundry charges are in order. The representative of the complainant
submitted that the sub division also failed to disconnect the electricity connection
immediately on default as per provisions and allowed the defaulting amount to grow
further.
6. The Forum observed that the provision in this regard existed in the Supply Code
Regulations and thus the action of the sub division in transferring the defaulting
amount is in order. The Forum, however, noted that the amount was allowed to be
accumulated and the connection was not disconnected immediately on first or
second default in payment. The Nodal Officer is directed to follow the
regulations/instructions meticulously in future. The S.E. Elecy. ‘OP’ Circle is also
46
directed to reiterate the instructions in this regard that the connection should be
disconnected on payment default strictly as per provisions of the Supply Code.
7. With the above observations, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
47
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 739 Date of Institution - 21.11.2013
Date of Order - 23.07.2015 In the matter Shri Bharat Bhushan Gupta, Principal, D.C Montessori School, Pocket No.2 & 3, Gobindpura, Near Modern Housing Complex, Manimajra, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Bharat Bhushan Gupta, Principl, D.C.Montessori School, Manimajra vide his
representation dated 21.11.2013 submitted that his load was checked by the
department and excess load of 23.209 KW was detected in the ECR dated
12.7.2013. He submitted that as per guidelines issued by the Hon’ble JERC no
penalty can be levied to the domestic category of consumer, if additional load is
detected. He prayed that the SDO ‘OP’ Sub Divn.No.8 be directed to exclude the
amount of sundry charges of his bill.
2. The complaint was forwarded to the Nodal Officer i.e. Executive Engineer, Elecy.
‘OP’ Division No.2 for submitting parawise comments vide letter dated
21.11.2013.
3. The concerned AEE ‘OP’ Sub Division No.8 vide his letter dated 12.02.2014
submitted that during the checking made vide ECR dated 12.7.2013, the excess
load was detected and thus the case was treated as unauthorised use of
electricity as per Electricity Supply Code Regulations 2010. Accordingly the
Assessment Notice on 7.8.2013 was issued for Rs.50,584/-. He also supplied
the consumption data for the last two years.
4. The case registered as complaint No.739 was listed for hearing on 23.7.2015
vide letter No. CGRF-737-738-740/2015/1035 dated 08.07.2015, a copy of
48
which was also sent to the SDO, Electy. ‘OP’ Sub Division No.8 and to the
complainant.
5. On the date of hearing, the representative of the complainant as well as
concerned SDO ‘OP’ Sub Division No.8 along with his RA were present. The
SDO submitted that amount raised by Sub Division on account of unauthorized
excess load was paid by the consumer and no amount is pending against them.
The complainant also confirmed that they have already made the payment of the
amount raised and have no grievances now with the department. It was also
conveyed that the load of the consumer had already been extended and released
at 11 K.V.
6. With the above observations, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
49
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 740 Date of Institution - 23.01.2015
Date of Order - 23.07.2015 In the matter Shri Sahai Jyoti, House No. 2026, Mauli Complex, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Sahai Jyoti, resident of House No. 2026, Mauli Complex, Chandigarh through e-
mail dated 23.1.2015 submitted that he had received last 2 bills with inflated amount.
“ The several reminder sent but no action was taken by the Sub Division. In spite of
his repeated oral complaints and Sub Division oral assurances gaveno concrete
action was taken yet to solve this problem. It is needed sad that Sub Division was
turned a deaf fear to his representation complaints followed by several reminders.
He has required for its efficiency should be taking so much time in doing the needful”
2. The e-mail was forwarded to the Nodal Officer i.e. Executive Engineer, Elecy.
‘OP’ Division No.2 for submitting action taken report on the same day.
Subsequently vide letter dated 9.2.2015 the same was confirmed with a copy to
the consumer.
3. The concerned AEE ‘OP’ Sub Division No.8 vide his letter dated 11.5.2015
submitted parawise reply duly counter signed by Xen. ‘OP’ Division No.2. He
submitted that the existing connection is under domestic category and load
when checked was found as 0.720 KW. The working of the meter was found
O.K. He also supplied the consumption data of the complainant. .
4. The case registered as complaint No.740 was listed for hearing on 23.7.2015
vide letter No. CGRF-737-738-740/2015/1035 dated 08.07.2015, a copy of
50
which was also sent to the SDO, Electy. ‘OP’ Sub Division No.8 and to the
complainant.
5. On the date of hearing, the complainant as well as concerned SDO ‘OP’ Sub
Division No.8 along with his RA were present. From the consumption data it
was noted that there was consumption of more than 1.5 lac units during the
period 10.2.2013 to 10.2.2014. This clearly pointed out that this much
consumption is not possible with the connected load of 0.7 KW. It was thus
concluded that it could be a case of reading jumping. The SDO and RA agreed.
6. The Nodal Officer is, therefore, directed to overhaul the account of the consumer
on the basis of past consumption of corresponding period for the period meter
remained defective. Compliance be reported within twenty one days after the
receipt of the order failing which the Hon’ble JERC may impose penalty as per
relevant rules of Electricity Act 2003.
7. With the above directions, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
51
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON AND SH.G.D. SAINI MEMBER
Complaint No. - 741 Date of Institution - 09.03.2015
Date of Order - 02.07.2015 In the matter Shri Harpal Sigh, House No.2689, Phase XI, Sector 65, Mohali.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Harpal Singh vide his letter dated 5.3.2015 received in the office of CGRF on
9.3.2015 submitted that he paid electricity bills of House No. 639 and shop No.640 in
Village Kishangarh on due date through separate cheques both dated 24.12.2014
amounting to Rs.7476/- and Rs.12688/- respectively. Though the cheques were
accepted by E-Sampark centre, he received subsequent bills with arrear of the
payment already made through cheques along with surcharge amount of Rs.341/-
and Rs.704/- respectively. He requested for refund of the surcharge amount.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for comments/action taken report vide Memo. No.
CGRF/Comp-Misc/2015/272 dated 11.03.2015. A copy of the letter was also
forwarded to the complainant vide Endst. No. CGRF/Comp-Misc,/2015/273-274
dated 11.03.2015.
3. The concerned AEE ‘OP’ Sub Division No.8 vide his Memo. No. 2399 dated
11.05.2015 submitted his reply duly countersigned by the Nodal Officer that the 2
Nos. Cheques through which payment of electricity charges were made i n the E-
Sampark Centre by the complainant were dishonoured as per copy of the
information received through concerned Xen. He attached the copy of the
same. Due to cheques getting dishonoured the arrears and surcharge were
levied in the subsequent bill.
52
4. The complaint was treated as a formal Complaint No.741 and was listed for
hearing on 2.7.2015 in CGRF Office vide Memo. No. CGRF/Comp-
620/763/764/765/2015/947 dated 26.6.2015 a copy which was also sent to the
complainant and SDO.
5. On the date of hearing, the complainant did not appear. The Nodal Officer, AEE
of ‘OP’ Sub Divn. No.8 and RA were present. The AEE submitted that the arrear
and surcharge was added in the subsequent bill due to reason that both the
cheques were dishonoured. The Forum observing that action by the Sub
Division was correct in levying surcharge/arrear on account of cheques getting
dishonoured, dismiss the complaint.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
` (G.D. SAINI) (R.K.ARORA) MEMBER,CGRF CHAIRPERSON, CGRF
53
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 742 Date of Institution - 31.12.2014
Date of Order - 04.08.2015 In the matter Air Mshl. P.S. Brar, House No.178/2 , Panchkula.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8 UT, Chandigarh.
……………….Respondents
Order
1. Air Mshl. P.S. Brar, resident of House No. 178/2, Panchkula submitted a complaint
received on 31.12.2014 stating that he had paid an amount of Rs.3,65,466/- for the
period Jan. 2013 to Jan 2014 for SCO No.45, Manimajra, Pocket 1, Chandigarh.
Despite the fact that the tenant vacated the premises in June 2013 without paying
any further dues after 21st Jan.2013. He admitted that no intimation was conveyed
to the department about the vacation of the premises of the tenant. The SCO was
again rented out on 19th April 2014, the billing during the entire period of SCO
remained vacant was issued on the basis of ‘N’ Code @ 7756 units per bill. He
requested for reviewing the rate of charge for the period SCO remained vacant. He
supplied the copy of Rent Agreement with the Ex-tenant and present tenant along
with copy of termination notice.
2. The comments of the Nodal Officer i.e. . Executive Engineer, Elecy. ‘OP’ Division
No.2 were called upon vide letter No.CGRF/Comp-Misc/2015/93 dated 9.2.2015 with
a copy to the complainant along with consumption data.
3. The concerned SDO ‘OP’ Sub Divn. No.8 submitted the reply duly counter signed
by the Xen ‘OP’ Division No.2 vide his letter No.2389 dated 11.5.2015. He stated
that the bills to the consumer with sanctioned load of 44.000 KW were issued on ‘D’
Code being meter defective w.e.f. 2/14 onward. He also confirmed that the
54
complainant had made all the payments up to December 2014. He also supplied the
consumption data for the last three years.
4. The Complaint registered as 742 was notified for hearing on 2.7.2015, the
complainant did not attend. To give one more opportunity the case was renotified
for hearing on 4.8.2015 vide letter No. CGRF/Comp-
620/742/743/744/745/2015/1101 dated 20.7.2015 .
5. On the date of hearing, the complainant did not attend nor sent any intimation. The
Xen ‘OP’ Division No.2 , SDO ‘OP’ Sub Divn.No.8 along with his RA were present.
The Xen stated that the consumer was being served bill on average as the mater
was defective. But the complainant did not approach the Sub Division and was
making the payment. At this belated stage it is not possible to check the factual
position. The complainant in his complaint had also admitted that he was making
payment and the fact of SCO lying vacant was not conveyed to the electricity
department. SDO also stated that the defective meter of the complainant has since
been replaced. It has also been noted that from the consumption data that upto April
2014 the bills were issued @ 4756 units per bill which was reduced to 3880 units per
cycle w.e.f. April 2014 till Feb. 2015.
6. With the above observations that the consumer had been paying the bills as served
to him and did not being the position of vacancy of SCO to the notice of Sub
Division, the complaint is dimissed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
55
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 743 Date of Institution - 17.04.2015
Date of Order - 04.08.2015 In the matter Shri Sanjay Nagpal, 148/A, Village Mauli Jagran, U.T. Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8 UT, Chandigarh.
……………….Respondents
Order
1. Shri Sanjay Nagpal, vide his letter 17.4.2015 submitted that the bill for his house
148/A, Mauli Jagan, Chandigarh for the month of July 2013 was quite on high side
for which he challenged the bill by depositing R.250/- on 19.7.2013. The meter was
checked on 23.8.2013 with a report that the meter is jumping/digit defective. The
meter was subsequently replaced and thereafter the bills started to be issued on
consumption basis. On 9.2.2015 he received a letter from the Sub Division that
meter is working properly and showing the correct reading and no jumping of the
reading was found at the time of checking and demanding the amount raised for the
disputed period.
2. The complaint was forwarded to the Nodal Officer i.e. . Executive Engineer, Elecy.
‘OP’ Division No.2 to submit parawise comments vide letter No.CGRF/Comp-
Misc/2015/480 dated 27.04.2015 with a copy to the complainant along with
consumption data for the last three years.
3. The concerned SDO ‘OP’ Sub Divn. No.8 vide his letter No.2386 dated 11.5.2015
duly counter signed by the Xen ‘OP’ Division No.2 submitted the fact of the case.
a) The connected load was found to be 9.190 KW against the sanctioned load of
9.950 KW under domestic category though being used for commercial purpose .
b) The working of the meter found O.K.
c) He also supplied the consumption data of the consumer.
56
4. The Complaint registered as Complaint No.743 was notified for hearing on 2.7.2015.
The complainant did not attend. To give one more opportunity the case was re-
notified for hearing on 4.8.2015 vide letter No. CGRF/Comp-
620/742/743/744/745/2015/1101 dated 20.7.2015 .
5. On the date of hearing, the complainant as well as the Xen ‘OP’ Division No.2 , SDO
‘OP’ Sub Divn.No.8 along with his RA were present. The complainant submitted that
consumption from April to June 2014 was quite on higher side as per two past bills
which he attributed could be due to meter jumping. He also stated that the report by
the J.E on 24.9.2013 also pointed out that display of digit defective/seems to be
jumped.
6. The Xen stated that the working of meter was rechecked and found to be in order.
He also submitted that premises has 3 Spilt Air Conditioners of 1.5 Ton and as such
the consumption recorded during the summer months of May-June appears to be in
order. The SDO also supplied up to date consumption data and also that the meter
has since been replaced during the period 8/14 to 10/14.
7. Observations and decision by the Forum:
From the consumption data it was observed that for the period 4/13 to 6/13 the bill
was issued for a consumption of 3234 units on the basis of meter reading. The bills
in the past period were found to be in the range of 1000 to 1360 units. The report
dated 24.9.2013 regarding checking of meter was not found to be clear, as it has
been recorded: “Meter checked and working found”. Display of digit defective/seems
to be jump. Report already submitted vide verification Register No.355 dated
23.8.2013”.
The Forum observed that the premises has 3 ACs of 1.5 T i.e. 1.8 KW each. The
estimated consumption per Annum of the Supply Code works out as follows:-
Consumption per month= 1.8x3x40% x720 = 1555 Units per Month.
Thus estimated consumption of 3 ACs only for a billing cycle of 2 months is
1555x2=3110 units.
Further, from the analysis of the consumption data, it is noted that consumption
recorded during 4/15 to 6/15 with the replaced meter is 3432 units which is even
more than consumption recorded during the disputed period of 4/13 to 6/13. It was,
57
thus concluded that this much consumption during the summer months with 3 ACs
(at different floors of the house) is possible and thus the Forum did not find any merit
in the plea by the complainant that the consumption recorded during 4/13 to 6/13
was on account of meter jumping.
8. With the above observations, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
9. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
58
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 744 Date of Institution - 27.02.2015
Date of Order - 04.08.2015 In the matter Shri Shiv Sharan Dass Sharma, SCO No.833, NAC, Manimajra, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8 UT, Chandigarh.
……………….Respondents
Order
1. Shri Shiv Sharan Dass Sharma vide his complaint dated 27.2.2015 submitted that
though the second floor of SCO No.833 was lying vacant and there was no
consumption from 1.4.2013 onward, they received inflated bill. Prior to this meter
was dead and replaced by the department. He requested for getting the bill
corrected.
2. The comments of the Nodal Officer i.e. . Executive Engineer, Elecy. ‘OP’ Division
No.2 were called upon vide letter No.CGRF/Comp-Misc/2015/236 dated 4.3.2015
along with consumption data with a copy to the complainant
3. The concerned SDO ‘OP’ Sub Divn. No.8 submitted the reply duly counter signed
by the Xen ‘OP’ Division No.2 vide his letter No.2396 dated 11.5.2015. He
submitted that the electricity bills to the consumer have been issued on ‘D’ Code as
the meter was defective. Shri Shiv Dass Sharan Sharma submitted a request to his
office along with supporting documents regarding portion of SCO lying vacant. The
site was got verified by the concerned official on 11.3.2014 and account was
overhauled. He also supplied the consumption data along with supporting
documents.
4. The Complaint registered as 744 was notified for hearing on 2.7.2015, the
complainant did not attend. To give one more opportunity the case was re-notified
59
for hearing on 4.8.2015 vide letter No. CGRF/Comp-
620/742/743/744/745/2015/1101 dated 20.7.2015 .
5. On the date of hearing, the complainant as well as the Xen ‘OP’ Division No.2 , SDO
‘OP’ Sub Divn.No.8 along with his RA were present. The complainant reiterated his
written submission and stated that the average charged for the period floor remained
vacant was on higher side. He also intimated that the premises were again rented
w.e.f. Feb. 2014. The complainant also raised the issue that he had made part
payment but the surcharge has been levied on full amount of the bill rather than on
the arrear.
The SDO stated that earlier overhauling of the account was done on the basis of
documents submitted by the complainant after due verification. However, IA revised
the charges and accordingly same have been charged. He submitted that
complainant be asked to make the payment.
6. On the basis of above facts and the written submissions by the SDO that the
consumer had submitted requisite documents regarding vacancy of the premises to
the Sub Division which was also got verified and found to be correct, the Nodal
Officer is directed to overhaul the account on the basis of documents submitted by
the complainant to the Sub Division/verification by the Sub Division. The charging
done on the basis of internal audit is set aside. Further the surcharge should be
levied only on the arrear amount of the bill rather than full amount of the bill.
Compliance be reported within 21 days of issue of order failing which the Hon’ble
JERC may impose penalty as per relevant sections of Electricity Act 2003.
7. With the above observations, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
60
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
61
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 746 Date of Institution - 13.04.2015
Date of Order - 28.07.2015 In the matter Shri Prem Shanker, House No.3645, Mauli Jagran Complex, Chandigarh
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Prem Shanker, House No.3645, Mauli Jagran Complex Chandigarh through his
representation dated 13.4.2015 submitted that after receipt of inflated bill, he
represented to the ‘OP’ Sub Division No.8 Manimajra but no action was taken
forcing him to file an appeal with CGRF.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 to examine and submit parawise comment/action taken
report along with consumption data for the last three years vide letter dated
16.4.2015.
3. The concerned AEE ‘OP’ Sub Division No.8 vide his letter dated 11.5.2015
submitted parawise reply duly counter signed by Xen. ‘OP’ Division No.2. He
stated that the connection was domestic and on checking the load was found as
0.852 KW. The working of the meter was also got checked and found in order.
He also supplied the consumption data along with other documents.
4. The case formally registered as complaint No.746 was listed for hearing on
28.7.2015 vide letter No. CGRF-746/747/748/691/2015/1023 dated 08.07.2015,
a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division No.8 and to
the complainant.
62
On the date of hearing, the complainant as well as Nodal Officer Xen ‘OP’
Division No.2, AEE ‘OP’ Sub Division No.8 and RA of the Sub Division were
present.
From the Consumption data supplied by the Sub Division, it was
noted that against the normal consumption of around 150-500 units per cycle, the
meter recorded consumption of 8720 units during the period July to Sept. 2014.
The respondent Xen ‘OP’ Division No.2 and AEE agreed that such high
consumption could be on account of meter jumping. It was also submitted that
meter was of TG make and in no. of other cases, the cases of reading jumping,
have been reported of this Make of Meter.
5. Decision:
The Nodal Officer is directed to get the meter replaced and overhaul the account
for the period July to Sept. 2014 on the basis of consumption recorded during
the corresponding period of the previous year from 7/13 to 9/13. The surcharge
is also to be adjusted simultaneously. Compliance be reported within twenty one
days after the receipt of the order failing which the Hon’ble JERC may impose
penalty as per relevant rules of Electricity Act 2003.
6. With the above directions, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
63
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 747 Date of Institution - 25.3.2015
Date of Order - 28.07.2015 In the matter Shri Rajbir Singh, House No. 45/3. Shanti Nagar, Manimajra, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Rajbir Singh, House No.45/3, Shanti Nagar, Manimajra Chandigarh through his
representation dated 17.3.2015 received on 23.3.2015 submitted that after receipt
of inflated bill for the period 8/14 to 10/14, he represented to the ‘OP’ Sub Division
No.8 Manimajra for checking of the meter/connection of his bill but no action was
taken forcing him to file an appeal with CGRF.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 to examine and submit parawise comment/action taken
report along with consumption data for the last three years vide letter dated
25.3.2015
3. The concerned AEE ‘OP’ Sub Division No.8 vide his letter dated 11.5.2015
submitted parawise reply duly counter signed by Xen. ‘OP’ Division No.2. He
stated that the connection was domestic and on checking, the working of the
meter was also got checked and found in order. He also supplied the
consumption data along with connected documents.
4. The case formally registered as complaint No.747 was listed for hearing on
28.7.2015 vide letter No. CGRF-746/747/748/691/2015/1023 dated 08.07.2015,
a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division No.8 and to
the complainant.
64
On the date of hearing, the complainant as well as Nodal Officer Xen ‘OP’
Division No.2, AEE ‘OP’ Sub Division No.8 and RA of the Sub Division were
present.
The Executive Engineer ‘Op’ Division No.2 submitted that the
working of meter was found O.K. and further that on comparison of 6 months
consumption including the disputed period with corresponding period
consumption of previous year, no appreciable increase noticed. He attributed it
to the case of accumulation probably due to wrong (less) recording of reading in
Aug. 2013. The complainant on the other hand contended that the high
consumption was on account of meter reading jumping. He also raised the issue
of charging of higher slab charge and payment in lump sum with regard to the
submissions made by Xen that it could be a case of accumulation due to less
recording/punching of the reading.
5. Observations:
The Forum observed that the consumption during the period Feb.2013 to
Feb.2014 was 4906 units and for Feb. 2014 to Feb.2015 was 5513 units i.e.
upward variation of around 12%. It was also noted that meter was of “Saraf”
make which is considered to be good quality meter. The complaint also stated
that the same meter is in place today and the consumption is generally in order
after December 2014.
6. Decision:
On the basis of above observations that it could be a case of accumulation of
meter (not deliberate), the complaint is dismissed. However, the Nodal Officer is
directed to consider this consumption for the period from April to Oct. 2014 for
applying tariff slab. The complainant is also allowed to make the payment in two
instalments without levy of surcharge.
7. With the above directions, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
65
8. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
66
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 748 Date of Institution - 13.04.2015
Date of Order - 28.07.2015 In the matter Shri R.C. Goswai, House No.78, Bank Colony, Manimajra, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri R.C. Goswami, House No.78, Bank Colony, Manimajra, Chandigarh through his
representation dated 9.2.2015 submitted that after receipt of bill for the period 8/14
to 12/14 he represented to the ‘OP’ Sub Division No.8 Manimajra that the high
consumption recorded by the meter was on account of reading jumping or fast
running of the meter.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 to examine and submit parawise comment/action taken
report along with consumption data for the last three years vide letter dated
16.2.2015.
3. The concerned AEE ‘OP’ Sub Division No.8 vide his letter dated 14.5.2015
submitted parawise reply duly counter signed by Xen. ‘OP’ Division No.2. He
stated that the connection was domestic and on checking the load was found as
2.770 KW against the sanctioned load of 3.920 KW. The working of the meter
was also got checked and found in order. He also supplied the consumption
data along with other documents.
4. The case formally registered as complaint No.748 was listed for hearing on
28.7.2015 vide letter No. CGRF-746/747/748/691/2015/1023 dated 08.07.2015,
a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division No.8 and to
the complainant.
67
On the date of hearing, the complainant as well as Nodal Officer Xen ‘OP’
Division No.2, AEE ‘OP’ Sub Division No.8 and RA of the Sub Division were
present.
From the Consumption data supplied by the Sub Division, it was
noted that against the normal consumption of around 300-900 units per cycle, the
meter recorded consumption of 81334 units during the period August to
December 2014. The respondent Xen ‘OP’ Division No.2 and AEE agreed that
such high consumption could be on account of meter jumping.
5. Decision:
The Nodal Officer is directed to get the meter replaced and overhaul the account
for the period August to December 2014 on the basis of consumption recorded
during the corresponding period of the previous year from 8/13 to 12/13. The
surcharge is also to be adjusted simultaneously. Compliance be reported within
twenty one days after the receipt of the order failing which the Hon’ble JERC
may impose penalty as per relevant rules of Electricity Act 2003.
6. With the above directions, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
68
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON, SH.G.D. SAINI MEMBER
SH. R. L. MITTAL, OMBUDSMAN (RETD.), MEMBER Complaint No. - 749 Date of Institution - 05.5.2015
Date of Order - 16.06.2015 In the matter of Mrs. Sonika Kapoor, House No.1690, Sector 34-D, Chandigarh.
………………..Petitioner
Versus
1. The Addl. Superintending Engineer, Electy. ‘OP’ Divn. No. 4, UT, Chd. 2. SDO, Electy. ‘OP’ Sub-Divn. No. 9, UT, Chandigarh.
……………….Respondents
Order
1. Mrs. Sonika Kapoor, resident of House No.1690, Sector 34-D, Chandigarh vide her
applicant in dated 5.5.2015 submitted that she bought Flat No. 3326, Sector 50,
Chandigarh in 2012 and same was laying vacant till September 2013. In Jan. 2013,
she decided to sell off it, but the deal did not mature due to malafide intentions of
buyer. The case went to the court and after pursuance for one year, the final
decision was received in March 2014. Thereafter the flat was rented out in
September 2014. She also noted that the meter was found burnt and brought same
to the notice of SDO vide Mem. No. LK/2013/7358 dated 17.12.2014, the SDO
charged a sum of Rs.59,758/- on account of meter remaining burnt from 25.1.2012
to 25.9.2014. She met the concerned SDO but did not get the relief and thereafter
approached CGRF for settlement of the case. She attached transfer of allotment
letter, Agreement to sell, Legal Notice, the decision of the Court and the Notice
issued by the SDO.
2. The comments of the Nodal Officer i.e. Addl. Superintending Engineer, Elecy.
‘OP’ Division No.4 were called vide CGRF Memo. No. CGRF/Temp-
T 15/2015/577 dated 5.5.2015 along with consumption data with the directions to
freeze the sundry charges and accept the current amount of the bill w.e.f.
September 2014 onwards.
3. In response the concerned SDO ‘OP’ Sub Division No.9 vide Memo. No.2883
dated 21.5.2015 submitted that on receipt of information from the Consumer the
69
meter was got checked by the J.E. and was found burnt. The burnt meter was
replaced on 8.9.2014. Thereafter the consumer account was overhauled as per
Clause 8/.1(16) of Electricity Supply Code Regulation 2010 amended on
7.8.2013. As the available nominal consumption data was not sufficient and
commensurate with sanctioned load of 9.560 KW, the account was overhauled
from Jan.2012 to September 2014 on the basis of order dated 16.2.2000 by
taking 50 units Per KVA per month i.e. 500 units per month for 10 KW load. A
notice dated 17.12.2014 was served to the consumer for Rs.59,758/-. He also
submitted that consumer representation dated 13.01.2015 was examined by his
office and submitted that plea taken by the applicant could not be correct
regarding vacant house. He also attached 3 years consumption data of the
consumer.
4. The complaint was formally registered as Complaint No.749 and was notified for
hearing on 16.06.2015 vide Memo. No. CGRF/600/749/2015/821 dated 8.6.2015
a copy of which was also sent to the SDO, Elecy. ‘OP’ Sub Division No.9 and to
the complainant.
On the date of hearing, both the complainant and SDO along with his RA were
present. The complainant reiterated her written submission that the flat was
vacant from Jan.2012 to Sept. 2014 and charging on the basis of average
consumption or per KW consumption is not justified. The SDO, however,
submitted that in absence of unreliable consumption data charging has been
done at fixed units Per KW basis. He desired the complainant to submit the proof
regarding non-occupation of the flat. He suggested for submission of letter from
the water department in the support of the submission made by the complainant
in this regard.
5. Observation of the Forum:
From the consumption data supplied by the Sub Division, the Forum observed
that there was some consumption ranging from 2 units to 28 units in some of the
cycles during the period Jan.2012 to Sept. 2014 with the meter status Code Z i.e.
the working of the meter was being recorded as O.K. by the meter reader. The
MCO was affected on 8.9.2014 with the status of the meter as burnt and at
70
reading of 5460. The next 2 bills were issued on average basis (in consistent
reading.) The consumption of 2008 units was recorded from 8.9.21014 to
25.3.2015 . From the consumption data it is evident that the meter was recording
some consumption (ranging from 2 units to 28 units per cycle) with recording of
status Code as Z ( O.K.). From the documents attached with the representation,
it appears that the flat was vacant and thus the consumption was very less.
Conclusion:
The Forum on the basis of above observations, the Forum conclude that
charging @ 50 Units Per Month Per KW on the basis of instructions dated
16.2.2000 is not in order. The charging if any to be done has to be as per the
Supply Code Regulations. In the present case it appears that the flat was vacant
and meter was recording some consumption with Status Code as O.K. The
Forum does not considered the necessity of producing any proof such as letter
from the Water Department. The Forum therefore directs to the Nodal Officer to
overhaul the account from Jan.2012 to 8.9.2014 (Date of MCO with initiating
reading as 5056 and final reading as 5460 (as recorded on the MCO). The
amount of Rs.59,758/- already charged be reversed, the compliance be reported
within twenty days of issue of order failing which Penalty may be imposed by the
Hon’ble JERC as per relevant sections of the Electricity Supply Act, 2003.
6. With above directions, the complaint is considered as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R.L. MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
71
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON AND SH.G.D. SAINI MEMBER AND
Complaint No. - 758 Date of Institution - 26.3.2014 Date of Order - 11.09.2015 In the matter Shri Surinder Singh Saini on behalf of M/s Surinder Builders, SCO No.2, Sector 34, Chandigarh.
……………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 3, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.3, UT, Chandigarh.
……………….Respondents
Order
1. Shri Surinder Singh Saini on behalf of M/s Surinder Builders, SCO No.2, Sector 34-
C, Chandigarh vide his representation, received in the office of CGRF on 26.3.2014
under Registered cover, stated that they have received a notice from SDO ‘Elecy.
‘OP’ Sub Division No.3 for depositing a sum of Rs.1, 78,694/- on account of
defaulting amount of electricity connection in the year 1995. Further it was
submitted that no bill or letter has been received by them between the periods
1995 to 2014. The connection was released in 1995 and disconnected on
27.6.1997 and payments were made accordingly. The bill of Rs.38,448/-stated to
be issued by the Sub Division was not given to them at that time. It was also
mentioned that as per Section 56 of the Electricity Act no amount due from any
consumer shall be recoverable after a period of 2 years and thus Sub Division
cannot raise the claim after 19 years. It was prayed that notice for claim of
Rs.1,78,694/- be withdrawn.
2. In response to the Forum letter dated 11.4.2014, the Nodal Officer Xen. ‘OP’
Division No.3 vide letter dated 30.4.2014 forwarded the reply submitted by the
concerned SDO ‘OP’ Sub Division No.3 along with consumption data and other
related documents such as MCO, PDCO and A&A Form etc.s
3. The concerned SDO ‘OP’ Sub Division No.3 in his submissions stated that M/s
Surinder Builders was allotted the work of construction of 32 Nos. Government
72
Employees Houses in Sector 19-B, Chandigarh by the Executive Engineer, C.P.
Division No.4, Chandigarh. M/s Surinder Builders took a temporary electricity
connection on 4.10.1995. The electricity connection was disconnected vide PDCO
dated 27.6.1997. The SDO also supplied the details of bills raised to the consumer
and payment made as under:-
Period Old reading New reading
Units Bill amount Amount paid
4.10.1995 to 15.11.95
4 760 756 2082.00 Rs.2082/- R.No.251/1201 dt.31.3.96/
15.11.95 to 4.3.96
780 1517 757 2293/- Rs.2293/- R.No.237/1201 dt.6.5.1996
4.3.96 to 3.6.96 and 3.5.96 to 10.6.96
1517
5
4654
2464
3137
2459
15437/- Rs.15437/- R.No.274/1201 dt.11.8.96
10.6.96 to 3.5.97and 3.5.97 to 27.6.97
2464
1
4760
10000
2296
10000
42278/- Final bill Rs.42278/- not paid by the consumer which was prepared as per reading recorded on the meter.
The final bill of Rs.42,278/- not paid by the consumer has become
Rs.1,78,494/- with levy of annual surcharge @ 10%. The number of letters were
written to the consumer but no payment was made by them.
4. The case registered as complaint No. 758 was notified for hearing on 17.6.2015
vide letter No. 829-836 dated 9.6.2015. The consumer did not attend the hearing.
The Nodal Officer and concerned SDO were present. It was decided to give one
more opportunity. The case was again listing for hearing on 6.8.2015 vide letter
No.1110-13 dated 20.7.2015, the complainant again did not attend the hearing.
One more opportunity was given to the complainant and the case was listing for
hearing on 11.9.2015 vide letter dated 1381-86 dated 26.8.2015. Shri R.L. Mittal,
Member CGRF was on leave and did not attend the hearing on 11.9.2015. Only
SDO was present but the consumer neither attended the hearing nor sent any
message. The SDO submitted that complainant was also informed of the hearing
on telephone and was requested to attend the same.
73
5. The Forum observed that sufficient opportunities have been given to the
complainant but he failed to attend the hearing. He did not even care to inform the
Forum and the Forum, therefore, decide to proceed ex-parte.
6. The Forum noted that the disputed amount was on account of a temporary
connection taken by the complainant in the year 1995 which was disconnected as
the consumer failed to make payment towards the last bill issued for the period
from 10.6.1996 to date of PDCO i.e. 27.6.1997. The defaulting amount as on
27.6.1997 attracted the surcharge @ 10% Per annum as per Supply Code
Regulations. Further the Licensee action of transferring the defaulting amount to
consumer’s other connection is also as per provision of the Supply Code
Regulations. With regard to submissions by the consumer that the amount cannot
be recovered after 2 years as per Electricity Act 2003, the Forum is of the view that
the disputed amount is a defaulting amount of the temporary connection taken by
the complainant and the same has now been transferred to his other account. The
provision of 2 years are applicable from the date of transferring of the amount.
There are number of judgements of the High Courts or Appellate Tribunal where it
has been concluded that limitation of 2 years would apply from the date when the
amount was first shown in the bill.
The limitation period of 2 years as per Section 56(2) of the Electricity Act 2003 are
applicable from the date of Notice in case the Electricity Department did not pursue
raise claim for this amount for a period of 2 years. The Notice was issued on
11.2.2014 and the complainant approached the Forum on 26.3.2014.
7. Decision by the Forum:
In view of above observations, Forum is of the view that the notice issued by the
Sub Division is in order and the consumer is liable to pay the amount demanded by
the Sub Division failing which the Nodal Officer may take further action as per
provisions of the Supply Code. Compliance be reported within 21 days failing which
the penalties may be imposed by Hon’ble JERC as per relevant sections of the
Electricity Act 2003.
74
8. With the above observations and directions, considers the complaint as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
9. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(G.D. SAINI) (R.K.ARORA) MEMBER,CGRF CHAIRPERSON, CGRF
75
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON AND SH.G.D. SAINI MEMBER
Complaint No. - 760 Date of Institution - 16.4.2015
Date of Order - 09.07.2015 In the matter Shri Amrit Lal Jain, House No.83, Sector 10-A, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 2, UT, Chandigarh.
……………….Respondents
Order
1. Shri Amrit Lal Jain, House No.83, Sector 10-A, Chandigarh made a representation
dated 15.4.2015, received in the office of CGRF on 16.4.2015. In his complaint he
submitted that for the meter installed at his premises he was receiving two bills, one
in the name of Smt. Padmawati and another bill in the name of Shir Himmat Singh.
The name of the consumer was got changed from Padmawati to Shri Himmat Singh
but the generation of the bill in the name of new name the bill in respect of old
name was also being issued simultaneously. The generation of two bills for the
same meter and for the same period of consumption has led to confusion. He
requested CGRF to look into the matter to clear the confusion.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.1 for comments/action taken report along with
submission of consumption data vide Memo. No. CGRF/Comp-T-5/2015/448
dated 21.04.2015. A copy of the letter was also forwarded to the complainant
vide Endst. No. CGRF/Comp-T-5/2015/449-450 dated 21.04.2015..
3. The Nodal Officer i.e. Xen ‘OP’ Division No.1 vide Memo. No. 9705 dated
19.5.2015 forwarded the reply submitted by AEE’OP’ Sub Division No.2. The
AEE submitted the details of three electricity connections in the premises, all in
the name of Shri Himmat Singh. He clarified that the electricity bill in the name of
Smt. Padamawati bearing A/c No. 102/1041/008304H for the period 12.7.2014 to
12.9.14, billing cycle/group 05/01 was issued as per actual consumption
76
recorded by the Meter No.CHSE-141124 i.e. 4533 units and the same was paid
by the consumer. As the owner of the premises, Sh.Himmat Singh applied for
change of name of the electricity connections vide A&A No. 73746, 73747 and
73748 dated 21.8.2014 which was effected on 9.9.2014, 19.9.2014 and
19.9.2014. Due to change of name two bills of the same Meter No.CHSE-
141124 were issued during cycle 06/01, 01/01 & 02/01 with different readings.
The new account allotted against old A/c No.1041/008304H is A/c
No.1041/008307Q. The wrong bills prepared against these accounts have been
revised and entry for adjustment of Rs.7106/- in the electricity bill bearing new
A/c No.1041/008307Q has been passed in the sundry charges and allowance
register. The advice for the same will be sent to computer and adjustment of
Rs.7106/- will appear in the next bill to be issued on 10.6.2015. The
consumption data for the last three years was also supplied .
4. The case was formally registered as complaint No.760 and was listed for hearing
on 9.7.2015 vide Memo. NO. 986 dated 25.6.2015. The complainant did not
attend the hearing on 9.7.2015. The SDO reiterated his written submissions that
the grievance of the complainant had already been redressed.
5. The Forum observing that the action has already been taken by the Sub Division
with regard to grievance of the consumer, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(G.D. SAINI) (R.K.ARORA) MEMBER,CGRF CHAIRPERSON, CGRF
77
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON AND SH.G.D. SAINI MEMBER
Complaint No. - 763 Date of Institution - 25.05.2015
Date of Order - 02.07.2015 In the matter Sh. Pardeep Mishra, Atta Chakki, Mauli Jagran, Manimajra, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Pradeep Mishra owner of Atta Chakki, Mauli Jagra, Manimajra, Chandigarh
through his representation dated 21.5.2015, received in CGRF Office on 25.5.2015
submitted that his electricity meter was burnt on 11.2.2015. Despite lodging of
complaint, the meter has not been replaced though a period of 3 months have
passed. He submitted that as per his understanding the meter is to be replaced
within 3 days.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for comments/action taken report vide Memo. No.
CGRF/Comp-T-29/2015/717 dated 28.05.2015. A copy of the letter was also
forwarded to the complainant vide Endst. No. CGRF/Comp-T-29/2015/718-719
dated 28.05.2015
3. The concerned AEE ‘OP’ Sub Division No.8 vide his Memo. No. 3473 dated
30.6.2015 submitted his reply ,duly countersigned by the Nodal Officer, that the
Atta Chakki connection having sanctioned load of 39.978 KW falls under Medium
Supply Category. The burnt meter of the complainant was replaced on
25.5.2015. With regard to issuance of the bills on average basis during the
period the meter remained burnt, he submitted that consumer’s account will be
overhauled accordingly subsequently.
78
4. The complaint was treated as a formal Complaint No.763 and was listed for
hearing on 2.7.2015 in CGRF Office vide Memo. No. CGRF/Comp-
620/763/764/765/2015/947 dated 26.6.2015 a copy which was also sent to the
complainant and SDO.
5. On the date of hearing, the consumer did not appear. The Nodal Officer, AEE
‘OP’ Sub Division No.8 and his RA were present. The AEE stated that the meter
has already been replaced on 25.5.2015 and thus grievances of the consumer
have been redressed. He attributed the delay in replacement of the meter due to
non available of LT CT meter in the Central Store.
6. The Forum observing that the grievances of the complainant had already been
redressed with replacement of meter, considers the complaint as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(G.D. SAINI) (R.K.ARORA) MEMBER,CGRF CHAIRPERSON, CGRF
79
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON AND SH.G.D. SAINI MEMBER
Complaint No. - 764 Date of Institution - 13.05.2015
Date of Order - 02.07.2015 In the matter Shri Pankesh Kumar on behalf of Shri Muni Ram, House No. 1252, Deep Complex, Hallomajra, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Shri Pankesh Kumar on behalf of Shri Muni Ram, House No.3242, Mauli Complex,
Mauli Jagran, Manimajra, Chandigarh through his complaint dated 11.5.2015
received in the CGRF Office on 13.5.2015 submitted that he was being charged in
excess on account of arrear which were already paid by him. He also raised that
ACD charges shown in the bill were more. He requested for rectification of his
accounts and to refund of excess charges for the period 20.12.2014 to 20.01.2015.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for comments/action taken report vide Memo. No.
CGRF/Comp-T-26/2015/658 dated 20.05.2015. A copy of the letter was also
forwarded to the complainant vide Endst. No. CGRF/Comp-T-26/2015/659-60
dated 20.05.2015
3. The concerned AEE ‘OP’ Sub Division No.8 vide his Memo. No. 2801 dated
01.6.2015 submitted his reply duly countersigned by the Nodal Officer that the
Electricity bill of the D.S. Consumer were issued on “ I “ Code- ‘Inconsistent
Reading’ and in the next bill issued from 20.9.14 to 20.1.2015 on consumption
basis, average bill issued on account of “ I “ Code was adjusted. With regard of
ACD charges, he stated that the same will be adjusted in the next bill.
4. The complaint was treated as a formal Complaint No.764 and was listed for
hearing on 2.7.2015 in CGRF Office vide Memo. No. CGRF/Comp-
80
620/763/764/765/2015/947 dated 26.6.2015 a copy which was also sent to the
complainant and SDO.
5. On the date of hearing, the complainant submitted that his previous bill was on
higher side. The AEE ‘OP’ Sub Division No.8 clarified that bill were issued on
average basis due to inconsistent reading. This average had already been
adjusted in the subsequent bills when the bill on reading were issued. The
complainant submitted that he had not received any such bill. The Xen ‘OP’
Division No.2 downloaded his bill from the internet and handed over the latest bill
with due date of July 2015. The amount of bill was around Rs.700/- including
arrear of Rs.300/- for the last bill. The complainant showed his satisfaction.
With regard to ACD charges the AEE assured him that the same will be worked
out on the basis of actual consumption.
6. The Forum observing that the grievances of the complainant had already been
redressed, considers the case as closed. The Nodal officer is however, directed
to recalculate the ACD as per actual consumption and report compliance within
21 days failing which the Hon’ble JERC may impose the penalty as per the
relevant sections of the Electricity Act 2003.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
` (G.D. SAINI) (R.K.ARORA) MEMBER,CGRF CHAIRPERSON, CGRF
81
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON AND SH.G.D. SAINI MEMBER
Complaint No. - 765 Date of Institution - 07.05.2015
Date of Order - 02.07.2015 In the matter of Ms Nutan Jain, House No.1813, Mohalla Arrorian, Manimajra, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No. 8, UT, Chandigarh.
……………….Respondents
Order
1. Ms. Nutan Jain resident of House No.1813, Mohalla Arrorian, Manimajra,
Chandigarh through her complaint dated 7.5.2015. (sent on e-mail) submitted
that the reading show in the Bill No.028248 does not coincide with the meter
reading. The bill shows reading from 12637 to 13791 with consumption as 1154
units where as the actual reading on 3.5.2015 stood as 12671. She requested
for correction of the bill.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for comments/action taken report after getting the
reading verified vide Memo. No. CGRF/Comp-T-19/2015/633 dated 18.05.2015.
A copy of the letter was also forwarded to the complainant vide Endst. No.
CGRF/Comp-T-19/2015/634-35 dated 18.05.2015
3. The concerned AEE ‘OP’ Sub Division No.8 vide his Memo. No. 2802 dated
1.6.2015 duly countersigned by Nodal Officer submitted that the bill of the
complainant was corrected after the official of his Sub Division verified the meter
reading on 13.5.2015 as 12811.
4. The complaint was treated as a formal Complaint No.765 and was listed for
hearing on 2.7.2015 vide Memo. No. CGRF/Comp-620/763/764/765/2015/947
dated 26.6.2015 a copy which was also sent to the complainant and AEE.
82
5. The complainant through her e-mail dated June 24, 2015 while acknowledging
letter dated 9.6.2015 of CGRF informed that her grievance has already been
resolved with the rectification of the disputed electricity bill. She expressed that
she will not be able to attend the hearing.
6. On the date of hearing, Nodal Officer Xen ‘OP’ Division No.2 and the AEE with
his RA were present but the complainant did not appear. The Forum observing
that the grievances of the consumer has already been redressed by the
concerned SDO for which the consumer has also conveyed her satisfaction,
considers the complaint as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(G.D. SAINI) (R.K.ARORA) MEMBER,CGRF CHAIRPERSON, CGRF
83
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 766 Date of Institution - 09.12.2013
Date of Order - 14.07.2015 In the matter Shri Anil Jain on behalf of M/s Anil Steel Industries, Site No.741, Industrial Area, Phase-II, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 5, UT, Chandigarh.
……………….Respondents
Order
1. Shri Anil Jain on behalf of M/s Anil Steel Industries, 741, Industrial Area Phase-II
Chandigarh vide his representation 4.12.2013 received in the office of CGRF on
09.12.2013 submitted that :-
a) The electricity department conducted a checking on his premises on
10.9.2011 and declared total load as 29.451 KW against the sanctioned
capacity of 15.833 KW. Thus 14 KW was found running unauthorised.
b) The electricity department issued a notice to deposit a sum of Rs.10,500/-
which was deposited by him on 27.9.2011. Subsequently inadvertently the
same amount of Rs.10500/- was again deposited on 1.12.2011.
c) He had already applied for extension of load of said premises from 16 KW to
49 KW vide application dated 10.11.2008 but the same was not sanctioned
due to non availability of suitable transformer.
d) After a gap of two years, the department again issued a notice on 25.10.2013
directing him to deposit a sum of Rs.47,776/- on account of same checking.
He raised the question of again asking him to deposit additional sum inspite
of the fact that the he had already applied for extension of load in the year
2008.
84
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 vide letter dated 10.12.2013 for submit para-wise
comments.
3. The concerned SDO ‘OP’ Sub Division No.5 vide his letter dated 10.1.2014
submitted parawise reply as under:-
a) Premises was checked on 10.9.2011 and load was detected as 29.451 KW
against the sanctioned load of 15.833 KW.
b) As per prevailing rules a notice was issued for depositing a sum of Rs.10500/-
c) He also informed that the consumer had applied for extension of load on
10.11.2008 and deposited the requisite fee of Rs.34800/- but the load could
not be released due to non availability of transformer.
d) The revised amount was charged on the basis of half margin by the Audit
Section as per Supply Code Regulations which was based on unauthorized
extension.
4. The concerned SDO subsequently through his submissions dated 14.4.2014 duly
countersigned by the Xen. ‘OP’ Division No.2 submitted that the present case
was covered under unauthorized use of electricity as per Section 126 of
Electricity Act and Instruction No.10.3 of Supply Code Regulations 2010. The
remedy for filing the appeal available under Section 127 in terms of notification
issued by the Chandigarh Administration on 11.7.2013 and the appeal is
therefore not maintainable before the Forum.
5. The reply received from the SDO was forwarded to the complainant for his
information and record.
6. The case was formally registered as complaint No.766 and was listed for hearing
on 14.7.2015 vide letter No. CGRF-633/766 to 776/2015/934-46 dated
26.6.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.5 and to the complainant. The AEE ‘OP’ Sub Division No.5 vide his letter
dated 13.7.2015 informed that the complainant has preferred to file a complaint
before the Permanant Lok Adalat, Sector 17 and the matter is pending till date.
7. The complainant did not attend the hearing. The Xen ‘OP’ Division No.2 stated
during the hearing that the complainant had moved the Permanent Lok Adalat.
85
8. The Forum observing that since the complainant had already filed an appeal with
the Permanent Lok Adalat, the Forum cannot take up the complaint. With the
above observations, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
9. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
86
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 767 Date of Institution - 21.01.2014
Date of Order - 14.07.2015 In the matter Shri Rajesh Saini, House No. 3872, Sector 47-D, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 5, UT, Chandigarh.
……………….Respondents
Order
1. Shri Rajesh Saini resident of House No.3872, Sector 47-D, Chandigarh through his
e-mail dated 17.1.2014 submitted that he was receiving bill on average basis though
his meter was in absolute working condition. He had approached concerned SDO in
this regard and J.E. of the Sub Division who visited in Jan.2014 informed that the
meter was in working condition. However, on 17.1.2014 the meter was changed in
his absence. He requested for overhauling of the account on the basis of actual
reading considering the meter working as O.K.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 vide letter dated 21.01.2014 for examining and
submission of para-wise comments along with consumption data for the last
three years.
3. The complainant through his e-mail dated April 27, 2014 informed that after the
special hearing of the complaint by the Forum on 14.4.2014, he contacted the
concerned SDO on 23.4.2014 who assured that the amount of Rs.1989/- excess
paid by him will be adjusted in the subsequent bill.
4. The case was formally registered as complaint No.767 and was listed for hearing
on 14.7.2015 vide letter No. CGRF-633/766 to 776/2015/934-46 dated
26.6.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.5 and to the complainant.
87
5. The Complainant’s brother came to the office in the Forenoon on the date of
hearing and showed his inability to attend the hearing scheduled for Afternoon.
He, however, showed his satisfaction to the action taken by the SDO in
redressing his grievance and submitted a letter in this regard. The Xen ‘OP’
Division No.2 and RA of the Sub Division No.5 attended the hearing in the
afternoon. The concerned AEE ‘OP’ Sub Division No.5 duly countersigned by
Xen through his written submissions stated that the working of the meter was
found O.K. and the premises was found lying vacant and thus the electricity was
being rarely used. Due to this fact the bills were issued on average considering
the meter as defective. He confirmed that the average bill raised under dispute
period were adjusted on the basis of final reading as on that date. He also
confirmed that the consumer is making the payment for the bills have served to
him on time to time and there is no dispute in any shape lying of the complainant.
6. With these observations that the complaint disputes had already been redressed
to his satisfaction, the complaint is considered as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
88
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 768 Date of Institution - 13.01.2014
Date of Order - 14.07.2015 In the matter Shri Anand Mohan Jagati, House No.199, Sector 48-A,Chandigarh
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 5, UT, Chandigarh.
……………….Respondents
Order
1. Shri Anand Mohan Jagati, resident of Flat No.199, Sector 48-A, Chandigarh
through his e-mail dated 9.1.2014 request for replacement of the existing fault
meter and also to get reviewed the abnormally high electricity bill for the period
June 2013 to January 2014. He stated that after his meter became faulty on
16.65.2014, average is being charged which he contended was on higher side.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for examine and for taking further action in the matter
vide letter dated 14.1. 2014 followed by reminder dated 19.6.2014.
3. The case was formally registered as complaint No.768 and was listed for hearing
on 14.7.2015 vide letter No. CGRF-633/766 to 776/2015/934-46 dated
26.6.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.5 and to the complainant.
4. On the date of hearing, the complainant did not attend. The Nodal Officer Xen
‘OP’ Division No.2 and RA of the concerned ‘OP’ Sub Division No.5 were
present. The RA stated that the issue raised by the complainant for charging
average during the dispute period was examined and was found be in order as
the same was charged on the basis of consumption of previous thre cycles. H
also informed that the meter was replaced during the period December 2013 to
Feb.2014 and the consumption being recorded by the new meter is in the same
89
range. It was also stated by him that the consumer is making payment of the bill
regularly. On the instance of consumer challenging the replaced meter. The
check meter was installed but the result showed that working of the meter was in
order. The written submissions duly signed by the AEE ‘OP’ Sub Division No.5
and counter signed by the Xen were also submitted along with consumption data
for the last three year.
From the consumption, it was observed that the range of units consumed
during the two months billing cycle was in the range of 1600 to 3300 units and
was matching with the consumption recorded by the previous meter which
became defective during the period June 2013 to August 2013.
5. With the above observations that defective meter has been replaced and
average charging (during the period the meter was defective) was in order, the
complaint is considered as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
90
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 769 Date of Institution - 09.09.2013
Date of Order - 14.07.2015 In the matter Shri Rajive Lochan Sharma, House No.1028, Sector 48-B, Chandigarh
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 5, UT, Chandigarh.
……………….Respondents
Order
1. Shri Rajiv Lochan Sharma resident of House No.1028, Sector 48-B, Popular
Society, Chandigarh through his e-mail dated 9.9.2013 submitted that his bill
dated 6.9.2013 showed the consumption of 1720 units which was very much on
higher side as compared to average consumption of 400 to 500 units. He also
submitted that reading on the electronic meter also appeared to be blurred and
was disappearing from the meter screen from time to time. He requested for
checking of the meter as well as review of the bill.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for calling parawise comments/action taken report
along with consumption data vide letter dated 10.9.2013 followed by reminder
dated 19.6.2014.
3. The case was formally registered as complaint No.769 and was listed for hearing
on 14.7.2015 vide letter No. CGRF-633/766 to 776/2015/934-46 dated
26.6.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.5 and to the complainant.
On the date of hearing, the complainant did not attend. The Nodal Officer Xen
‘OP’ Division No.2 and RA of the concerned ‘OP’ Sub Division No.5 were
present. The RA explained that the bill for the period 6/13 to 8/13 was issued on
wrong reading which was revised after verification. The meter was also got
91
checked and was replaced during the period 8/13 to 10/13 as display was found
defective. Thereafter the bill is being issued on reading and the consumer is
making the payment regularly.. The written submissions duly signed by the AEE
‘OP’ Sub Division No.5 and counter signed by the Xen were also submitted
wherein it was mentioned that display of the meter became defective and
accordingly the same was replaced. The period during which meter was
defective was revised on the basis of consumption recorded during the
corresponding period of previous year i.e. 6/12 to 8/12. The consumption data
for the two years were also supplied. The consistency between the consumption
of old and replaced meter was noted.
4. With the above observations that the action taken by the Sub Division and
charging was in order, the complaint is considered as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
5. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
92
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 770 Date of Institution - 03.07.2014
Date of Order - 14.07.2015 In the matter Col S.V.Patil, ESSCOT GREF, 507 SS & TC C/O 56 APO, Near Air Port Chowk, Behlana Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 5, UT, Chandigarh.
……………….Respondents
Order
1. Col S.V.Patil, ESSCOT GREF, 507 SS & TC C/O 56 APO, Near Air Port Chowk,
Behlana Chandigarh through his representation dated 3rd July 2014 submitted
that electricity bill for the month of June 2014 showed an amount of Rs.1,06,890/-
He stated that this amount was on higher side as compared with the bill amount
in the month of April and May 2014. He requested for reconciliation/verification
the correctness and issuance of fresh bill.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for calling parawise comments/action taken report
along with consumption data vide letter dated 03.04.2014 followed by reminder
dated 28.10.2014.
3. The case was formally registered as complaint No.770 and was listed for hearing
on 14.7.2015 vide letter No. CGRF-633/766 to 776/2015/934-46 dated
26.6.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.5 and to the complainant.
On the date of hearing, the complainant did not attend. The Nodal Officer Xen
‘OP’ Division No.2 and RA of the concerned ‘OP’ Sub Division No.5 were
present. The RA informed that the Sub Division could not find any
inconsistency/deficiency in the bill with regard to high consumption when
93
compared with the past bill(s). He stated that due to charging of ACD the
amount of bill during the period in dispute was higher than that of their average
amount which could have prompted the complainant to submit the Complaint.
The written submissions duly signed by the AEE ‘OP’ Sub Division No.5 and
counter signed by the Xen were also submitted giving the consumption for the
period July 2012 to March 2015. It was stated that the except for ACD charges
the sub division has not charged any amount in the bill and same was charged
as per provision contained in the JERC Supply Code Regulations and was in
order..
4. With the above observations the complaint is considered as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
5. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
94
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 771 Date of Institution - 06.06.2014
Date of Order - 13.07.2015 In the matter Shri Virender Kumar on behalf of Shri Rakesh Sharma, Floor No.181/32, Industrial Area, Phase –I, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 5, UT, Chandigarh.
……………….Respondents
Order
1. Shri Virender Kumar, Floor No.181/32, Industrial Area, Phase-I through his e-mail
dated 30th May 2014 enclosed the scaned copy of the bill with the request to get
the same checked and rectify.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 vide letter dated 9.6.2014 for examine and submit para-
wise comments. A reminder was also sent on 28.10.2014.
3. The case was formally registered as complaint No.771 and was listed for hearing
on 14.7.2015 vide letter No. CGRF-633/766 to 776/2015/934-46 dated
26.6.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.5 and to the complainant. The hearing notice was, however, returned back.
The complainant was contacted by the Chairman on his Mobile Number to
inform the date of hearing. The complainant informed that his concern was
regarding ACD charges. He was explained the method of levy of ACD charges
on the basis of 12 months consumption and also that same is adjusted on annual
basis and carries interest. He showed his satisfaction.
4. The Nodal Officer Xen ‘OP’ Division No.2 vide his letter dated 13.7.2015
supplied the reply mentioning that the ACD amount worked out was correct and
was restrictly as per Supply Code Regulations. He also supplied the
consumption data for two years in support.
95
5. On the date of hearing, the complainant did not attend. The Xen ‘OP’ Division
No.2 of the Sub Division was present. The RA explained that the ACD charged
in the bill was in order.
6. The Forum observing that the ACD charged was in order, considers the
complaint as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
96
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 772 Date of Institution - 28.10.2013
Date of Order - 14.07.2015 In the matter Shri Raju Thakur, House No.3269, Sector 47-D, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 5, UT, Chandigarh.
……………….Respondents
Order
1. Shri Raju Thakur, resident of House No.3269, Sector 47-D, Chandigarh though
his e-mail dated 25th October 2013 submitted that he received an electricity bill
amounting to Rs. 5000/- against his average monthly bill of Rs.600/-. He
requested for getting the matter looked into and refund of the extra amount.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 vide letter dated 29.10.2013 for examining and submit
para-wise comments. A reminder was also sent vide letter dated 19.6.2014 and
28.10.2014.
3. The case was formally registered as complaint No.772 and was listed for
hearing 14.7.2015 vide letter No. CGRF-633/766 to 776/2015/934-46 dated
26.6.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.5 and to the complainant.
4. The consumer did not attend the hearing. The SDO through his written
submissions supplied the consumption data and submitted that during the period
5/13 to 9/13 the bill for 4 months was sent to the consumer for 1703 units. An
allowance of Rs. 963/- for the bill issued on N Code during the period 5/13 to
7/13 was allowed in the bill. He also submitted that the consumer meter is till
date continuing and giving units. in normal manner and the consumer is making
97
payment for the bill rendered to him in time to time. The Xen ‘OP’ Division No.2
and RA present in the hearing reiterated the written submissions.
5. The Forum observing that disputed bill was issued for 4 months period due to
previous bill issued N Code on average basis which was also adjusted in the
disputed bill. The bill was found to be issued on reading and in order. With these
observations, the complaint stands dismissed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
98
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 773 Date of Institution - 26.05.2014
Date of Order - 14.07.2015 In the matter Smt. Suman Devi, Shop No.1955, Rehri Market, Phase-II, Ram Darbar, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 5, UT, Chandigarh.
……………….Respondents
Order
1. Smt. Suman Devi resident of House No.1448, Phase-I, Ram Darbar, Chandigarh
through her representation dated 16.5.2014 submitted that she was over charged
in the electricity bill for the period December 2013 to February 2014. The
consumption was less as the family was out for more than a month and shop was
locked. She requested for adjustment of the amount charged after verification.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for examine and for taking further action in the matter
vide letter dated 27.05. 2014 followed by reminder dated 28.10.2014.
3. The case was formally registered as complaint No.768 and was listed for hearing
on 14.7.2015 vide letter No. CGRF-633/766 to 776/2015/934-46 dated
26.6.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.5 and to the complainant.
On the date of hearing, the complainant did not attend. The Nodal Officer Xen
‘OP’ Division No.2 and RA of the concerned ‘OP’ Sub Division No.5 were
present. The RA explained that the meter became defective and the same was
replaced during the period June 2014 to August 2014. The written submissions
duly signed by the AEE ‘OP’ Sub Division No.5 and counter signed by the Xen
were also supplied. From the consumption data from 8/13 to 6/15 it was noted
that the meter became defective during the period December 2013 to Feb.2014
99
and average of 100 units was being charged during the period meter remained
defective till the replacement of the meter during the period June 2014 to August
2014. The Nodal Officer in the written submissions proposed that as the average
charged was quite on higher side as compared to the consumption recorded by
the replaced meter. It was proposed that the bill be revised on the basis of
consumption recorded by the replaced meter of one year of future consumption.
4. The Forum observed that the shop is in Rehri Market and may not use much
electricity and agrees with the proposal by the Nodal Officer that the account be
overhauled on the basis of one year consumption of the replaced meter. The
Nodal Officer to report compliance within 21 days of issue of order failing which
the Hon’ble JERC may impose penalty as per relevant rules of Electricity Act
2003.
5. With the above observations, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
100
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 774 Date of Institution - 16.05.2014
Date of Order - 14.07.2015 In the matter Shri Harjinder Dua, House No.2310 A, Sector 31-C, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 5, UT, Chandigarh.
……………….Respondents
Order
1. Shri Harjinder Dua, resident of House No.2310-A, Sector 31-C, Chandigarh
through his e-mail dated 16.5.2014 pointed out that his electricity bill was always
surpassing the figures of four digits inspite of carrying out all measures to utilize
minimum consumption. He stated that most of the time he remains out of station
duty and no appliances except for the AC in the peak of summer is being used.
He contended that the bill in the month of Feb. 2014 to March 2014 was on
higher side and requested for inspection of the meter/cables to check whether
any theft was being carried out.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for examine and submit para wise comments/action
taken report along with consumption data for the last three years vide letter dated
19.05. 2014 followed by reminder dated 28.10.2014.
3. The case was formally registered as complaint No.774 and was listed for hearing
on 14.7.2015 vide letter No. CGRF-633/766 to 776/2015/934-46 dated
26.6.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.5 and to the complainant.
On the date of hearing, the complainant did not attend. The Nodal Officer Xen
‘OP’ Division No.2 and RA of the concerned ‘OP’ Sub Division No.5 were
present. The RA during the hearing informed that the bill under dispute was
101
issued for 4 months period as the bill for previous cycle was issued on average
basis. The amount of average charged during previous bill were also adjusted in
the disputed bill. He also submitted that the consumer is now making the
payment of the bill regularly and there is no dispute. The written submissions
duly signed by the AEE ‘OP’ Sub Division No.5 and counter signed by the Xen
were also supplied. In the written submissions by the Sub Division. It was noted
from the consumption data that the consumption of the consumer was consistent
for the period of June 2013 to April 2014.
4. With the above observations and that the consumer is making the payment of
the bill regularly, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
5. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
102
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 775 Date of Institution - 29.01.2015
Date of Order - 14.07.2015 In the matter Shri Amit Kumar, House No.2433, Pushpac Society, Sector 48-C, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 5, UT, Chandigarh.
……………….Respondents
Order
1. Shri Amit Kumar, resident of House Npo.2433, Pushpac Society, Sector 48-C,
Chandigarh through his e-mail dated 29.1.2015 submitted that he had not
received the bill for the month of November to December 2014. On visiting E-
Sampark Centre he came to know that amount of his electricity bill was Nil.
Again for the month of Jan. & Feb. 2015 the amount of the bill was Nil. He stated
that he paid Rs.1269/- on 24.4.2014 and completed all the formalities for change
of name of the electricity bill in his name which was not upgraded till date.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for examine and to submit para wise comments/action
taken report along with consumption data for the last three years vide letter dated
09.02.2015.
3. The case was formally registered as complaint No.768 and was listed for hearing
on 14.7.2015 vide letter No. CGRF-633/766 to 776/2015/934-46 dated
26.6.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.5 and to the complainant.
On the date of hearing, the complainant did not attend. The Nodal Officer Xen
‘OP’ Division No.2 and RA of the concerned ‘OP’ Sub Division No.5 were
present. The RA during the hearing informed that the consumer had earlier made
a complaint which was disposed off vide Complaint No.586 by CGRF. With
103
regard to non issue of bill he attributed the same to the request made by the
complainant for change of name. He also confirmed that now bills are being
issued in his name and further that the amount standing at his credit in the old
Account No.205/4848/243301R has also been transferred to his new account.
The above was also confirmed through the written submissions duly signed by
the AEE ‘OP’ Sub Division No.5 and counter signed by the Xen ‘OP’ Division
No.2. In the written submission it was mentioned that now there is no dispute
with the complainant in any shape and he is regularly making the payment of
electricity bill being rendered to him.
4. With the above observations, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
5. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
104
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 776 Date of Institution - 15.05.2014
Date of Order - 14.07.2015 In the matter Shri Ram Panit, Jhuggi No.44, Colony No.4, Industrial Area, Phase_i, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 5, UT, Chandigarh.
……………….Respondents
Order
1. Shri Ram Panit, resident of Jhuggi No.44, Colony No.4, Industrial Area, Phase-
I, Chandigarh through his representation dated 15.5.2014 submitted that he
received a bill in Feb. 2013 amounting to Rs.88,879/- which was beyond his
capacity to pay. He requested for review of the bill as the same was high
considering his consumption.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.2 for examine and to submit para wise comments/action
taken report along with consumption data for the last three years vide letter dated
26.5.2014 followed by reminder dated 19.6.2014
3. The case was formally registered as complaint No.776 and was listed for hearing
on 14.7.2015 vide letter No. CGRF-633/766 to 776/2015/934-46 dated
26.6.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division
No.5 and to the complainant.
On the date of hearing, the complainant did not attend. The Nodal Officer Xen
‘OP’ Division No.2 and RA of the concerned ‘OP’ Sub Division No.5 were
present. The RA during the hearing stated that the complainant had a connection
in a Jhuggi No.44 which was disconnected w.e.f. 2013 and transferred to a
contractor along with other similar connections. He also stated that the
consumer is not making payment Nov. 2002. The bill was being issued on
105
average basis of around 400 units per billing cycle since 3/2008 to 11/2012 when
his meter became defective. The RA stated that average charged from the
complainant for the past period was certainly on higher side as compared to his
load/consumption. He agreed to reduce this average to 100 units per cycle
without levying any surcharge from the date when the same was started to be
charged. He also stated that his revision the bill of Rs.88,879/0 would reduced to
around Rs. 29,000/- with this revision of average. The written submissions duly
signed by the AEE ‘OP’ Sub Division No.5 and counter signed by the Xen ‘OP’
Division No.2 was also submitted.
4. The Forum observed that for a Jhuggi connection average charging @ 400 units
per billing cycle is certainly high and agreed to the proposal of the Sub Division
duly supported by the Nodal Officer to overhaul @ 50 units per month i.e.100 unit
per billing cycle without levy of any surcharge. The Forum also observed that the
letters being sent to the complainant was returned back undelivered. The Nodal
Officer is directed to get the account overhauled on the basis of average as 50
units per month and serve the revised bill to the complainant within a period of
21 days failing which the Hon’ble JERC may impose penalty as per relevant
rules of Electricity Act 2003.
5. With the above directions, complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
106
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 777 Date of Institution - 14.04.2045
Date of Order - 21.07.2015 In the matter Shri Raj Pal Singla on behalf of Shri Navneet Singla, Bay Shop No.391, Sector 44-D, Chandigarh.
………………..Petitioner
Versus
1. The Additional Superintending Engineer, Elecy. ‘OP’ Divn. No. 4, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 9, UT, Chandigarh.
……………….Respondents
Order
1. Shri Raj Pal Singla on behalf of owner of Bay Shop No.391, Sector 44-D,
Chandigarh submitted a complaint that the electricity supply was got
disconnected by the owner as per Supply Code Regulations in December 2013.
Subsequently the supply was restored on 12.9.2014 as per orders of the High
Court of Punjab & Haryana. On the directions of the High Court, the
Ombudsman allowed to Shri Vikas Deep Sharma of M/s Comfort Technologies
to get the new electricity connection released in their name after fulfilling the
formalities. The complainant stated that Shri Vikas Deep Sharma failed to
submit the requisite documents as per Supply Code Regulations and the Sub
Division was not disconnecting the supply and thus action against the Licensee
as per Section 142, 146 and 149 of the Electricity Act 2003 is required to be
taken.
2. The comments of the Nodal Officer Addl. Superintending Engineer, Elecy.’OP’
Division No.4 were called vide letter dated 30.4.2015 simultaneously fixing the
case for hearing on 25.5.2015.
3. The concerned SDO vide his letter dated 13.5.2015 submitted para-wise reply to
the complaint confirming that new connection could not be released in the name
of M/s Comfort Technologies as they failed to fulfil the requirements. He also
stated that connection could not be disconnected as per standing order of the
107
Ombudsman – “Licensee is ordered not to disconnect the supply till the
new connection is released)” for which clarification of the Ombudsman was
awaited.
4. On the date of hearing on 25.5.2015the complainant and the concerned SDO
along with his RA were present. The SDO informed that the connection was
disconnected on 14.5.2014 on the receipt of clarification from the Ombudsman.
The complainant desired to seek more information and submitted a paper
mentioning quarries.
5. The quarries were forwarded to the Nodal Officer for supplying parawise
details/information vide letter dated 30.4.2015.
6. The concerned SDO ‘OP’ Sub Division No.9 vide his letter dated 17.7.2015
submitted the requisite information/details as re quested by the complainant.
7. The case was listed for hearing on 21.7.2015, the complainant as well as SDO
along with his RA were present. During the hearing the complainant submitted
that he is not interested to pursue the case further, in view of the fact that the
delay in disconnection of the electricity supply in pursuance of Ombudsman
Orders when M/s Comfort Technologies failed to complete the formalities for
release of new connection was not to the account of the SDO.
8. The Forum observing that the connection stands disconnected and complainant
did not wish to pursue further, case is considers as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
9. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
108
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 778 Date of Institution - 18.05.2015 Date of Order - 25.08.2015 In the matter Shri Amit Julka, House No.209, Sector-8, Panchkula.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 4, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.9 UT, Chandigarh.
……………….Respondents
Order
1. Shri Amit Julka S/o Shri Tilak Raj Julka, resident of House No.209, Sector-8,
Panchkula through his e-mail dated 18.5.2015 submitted that he received a bill with
arrears of Rs.22836/- in respect of his Flat No.1024, Sector 51-B, Dayal Bagh
Co-operative Society, Chandigarh. When he contacted the Sub Division, he was
informed that disputed amount was on account of overhauling of his account for the
period meter remained defective from the period September 2012 to 9.4.2014, the
date of replacement of the meter. The complainant submitted that actual use of flat
started from 1.9.2013 when the flat was given on rent. Before 1.9.2013 the allotted
flat in 2011 was made in liveable position with loan taken from the Oriental Bank of
Commerce in March 2013. The complainant submitted that the charging of amount
prior to 1.9.2013 on the basis of worked out average was not justified as flat was
lying unoccupied.
2. The Executive Engineer, Electricity Operation Division No.4 was called upon to
submit para-wise comments along with consumption data on the representation vide
letter dated 20.5.2015.
3. The concerned SDO ‘OP’ Sub Division No.9 vide his letter dated 10.6.2015
submitted the para-wise comments. The SDO stated that the energy meter of the
complainant was replaced on 9.4.2014 as the same was found Dead stop/defective.
After replacement of the defective meter the account was overhauled as per Supply
109
Code Regulations 2010. He submitted that the consumer account was overhauled
for the period 23.1.2013 to 9.4.2014 (14.5 months) on the available base of
consumption recorded by new meter from 5/2014 to 11/2014 as the consumption
pattern for the previous period was not available.
4. The complaint formally registered as Complaint No.778 was listed for hearing on
21.7.2015. The complainant as well as SDO ‘OP’ Sub Division No.9 along with his
RA was present. On the request of SDO the complaint was re-notified for hearing
on 25.8.2014 vide letter No. 778/CG-1/CG-12/2015/1279 dated 10.8.2015. The
complainant and SDO along with his RA were present. On next date of hearing on
10.8.2015, the complainant reiterated his submissions that flat was allotted in 2nd
half of 2011 but was given on rent only on 11.9.2013 after making it in a liveable
condition.
5. The Forum from the consumption data supplied by the Sub Division noted that for
the period November 2011 to September 2013, the bills were issued on meter status
Code as ‘Z’ i.e. O.K. The consumption recorded during this period was only 26
units. Thereafter the meter becoming Dead Stop at reading of 35 and was replaced
on 9.4.2014. The Forum also observed that though the overhauled period was 14
months, the base for working out the average was 6 months which mostly included
the summer period. The SDO during hearing submitted that in the absence of past
consumption up to date future consumption was taken for overhauling of account.
6. Decision by the Forum:
The Forum from the consumption data noted that the meter might have become
Dead Stop during the month of May 2013 and thus overhauling of account prior to
May 2013 when bills were issued on reading with meter status as Okay is not in
order. For the period Jan. 2013 to May 2013 the meter was recording consumption
which also tallies with the statement of the complainant that the construction was
undertaken towards completion of the flat after March 2013. The Forum, therefore,
set aside the overhauling done by the Sub Division and directs the Nodal Officer to
get the account overhauled from 5/2013 to date of MCO 9.4.2014 afresh on the
basis of consumption recorded by the replaced meter for the corresponding period
110
i.e. May 2014 (MCO) to April 2015. Compliance be reported within 21 days after the
receipt of the order failing which the penalties may be imposed by Hon’ble JERC as
per relevant sections of the Electricity Act 2003.
7. With the above observations, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
111
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 779 Date of Institution - 28.5.2015 Date of Order - 12.08.2015 In the matter Shri Kamal Chandel, House No.581, Sector 11-B, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No. 2 UT, Chandigarh.
……………….Respondents
Order
1. Shri Kamal Chandel vide his e-mail dated 27.5.2015 submitted that electricity bill
dated 23.5.2015 for his house No. 581, Sector 11-B Chandigarh has the following
discrepancies. The meter was replaced in April 2015 and the consumption recorded
up to the meter replacement over and above. The already billed reading, was
around 100 units where as in the bill the consumption of old meter has been
mentioned as 638 units. He also submitted that his average consumption for two
month period is around 200 units.
2. The comments of the Nodal Officer i.e. Executive Engineer, Electricity Operation
Division No.1 were called vide letter dated 01.06.2015.
3. The Nodal Officer i.e. Xen ‘OP’ Divn. No.1 vide his letter dated 29.06.2015
forwarded the reply submitted by the AEE ‘OP’ Sub Divn. No.2 duly counter signed
by the Nodal Officer. The SDO submitted that consumer was served a bill for the
period 25.12.2014 to 25.02.2015 on premises locked basis (Average units.) The
next bill up to 25th April 2015 was issued on actual reading. Existing mechanical
meter was replaced with electronic meter on 20.4.2015. The advice for meter
change was sent to Computer Centre. The Computer Centre, however, did not
adjust the bill issued on average basis for the period 25.12.2014 to 25.2.2015. He
also submitted that the bill of the consumer has already been adjusted and
adjustment of Rs.1722/- has been made in Sundry Register which would be
112
reflected in the bill to be issued on 23.7.2015. The above was also intimated to the
consumer on his personal visit to the office. He also supplied the consumption data
long with copy of MCO.
4. The complaint was formally registered as Complaint No.779 and notice was issued
to the concerned Xen (Nodal Officer) with copy to the complainant fixing the case for
consideration on 12.8.2015 vide Memo. No.CGRF/Comp-690/692/761/703/779/1146
dated 24.7.2015. On the date of hearing on 12.8.2015, the complainant did not
attend. The concerned AEE ‘OP’ Sub Divn.No.2 informed that bill of the consumer
has already been corrected and refund allowed. Consumer was also intimated of
the same. He also submitted that consumer had already made full payment and
there is no default/dispute.
5. With the above observations that the grievance of the complainant has already been
redressed, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
113
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 780 Date of Institution - 18.5.2015 Date of Order - 10.08.2015 In the matter Shri Ashwani Kumar Anand, House No. 356, Sector 22-A, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No. 1 UT, Chandigarh.
……………….Respondents
Order
1. Shri Ashwani Kumar Anand, resident of House No. 356, Sector 22-A, Chandigarh
through his e-mail dated 18.5.2015 represented that in the bill issued on 9.5.2015
the existing ACD was shown as Rs.1320/- and the new calculated ACD as Rs.3664/-
He stated that in the bill dated 6.11.2013 old ACD was shown as Rs.1440/- and new
ACD as Rs.3948/-. The additional ACD demanded was paid in the next bill
6.1.2014. Thus he submitted that his old ACD should be corrected as Rs.3948/-
instead of Rs.1320/-. He also raised the issue of payment of interest on the ACD.
2. The comments of the Nodal Officer i.e. Executive Engineer, Electricity Operation
Division No.1 vide letter dated 20.5.2015..
3. The Nodal Officer i.e. Xen ‘OP’ Divn. No.1 vide his letter dated 8.7.2015
forwarded the reply submitted by the SDO ‘OP’ Sub Divn. No.1 wherein it was
stated that the amount of ACD has been corrected and he advice to the Incharge
Computer Cell has already been sent on 29.5.2015. He also confirmed that the
ACD has not yet been charged and only demand cum notice was sent to the
complainant in advance.
4. The complaint was formally registered as Complaint No.781 and notice was issued
to the concerned Xen (Nodal Officer) with copy to the complainant fixing the case for
consideration on 10.8.2015 vide Memo. No.CGRF/Comp-708/709/712 to
714/2015/1137 dated 24.7.2015.. On the date of hearing, SDO along with his RA
114
were present, the Complainant did not attend and through e-mail dated 8.8.2015
showed his inability to attend the hearing. He confirmed that in the latest bill dated
8.7.2015 the amount of old ACD has been correctly shown as Rs.3948/- against
Rs.1320/-. He, however, raised that the correct interest on the ACD for 2014-15 has
not been paid.
5. Observations and Decision of the Forum:
The Forum observed that necessary correction of the ACD amount has already
been done and correct amount reflected in the next billb. The Nodal Officer is
directed to ensure that the interest is also paid to the complainant on the actual
amount of the ACD available with the department. Compliance be reported within
21 days of issue of order failing which the Hon’ble JERC may impose penalty as per
relevant sections of Electricity Act 2003.
6. With the above observations and decision, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
115
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 781 Date of Institution - 25.5.2015 Date of Order - 10.08.2015 In the matter Shri Vijay Dabur, House No.470, Sector 22-A, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No. 1 UT, Chandigarh.
……………….Respondents
Order
1. Shri Vijay Dabur, resident of House No.470, Sector 22-A,Chandigarh through his e-
mail dated 25.5.2015 represented that in the bill issued on 9.5.2015 the existing
ACD was shown as Rs.960/- and the new calculated ACD as Rs.3092/- . He stated
that in the bill dated 6.11.2013 old ACD was shown as Rs.960/- and new ACD as
Rs.2910/-. The additional ACD demanded was paid in the next bill 6.1.2014. Thus
he submitted that his old ACD should be corrected as Rs.2910/- instead of Rs.960/-.
He also raised the issue of payment of interest on the actual ACD.
2. The comments of the Nodal Officer i.e. Executive Engineer, Electricity Operation
Division No.1 vide letter dated 28.5.2015..
3. The Nodal Officer i.e. Xen ‘OP’ Divn. No.1 vide his letter dated 8.7.2015
forwarded the reply submitted by the SDO ‘OP’ Sub Divn. No.1 wherein it was
stated that the amount of ACD has been corrected and the advice to the Incharge
Computer Cell has already been sent on 4.6.2015. He also confirmed that the ACD
has not yet been charged and only demand cum notice was sent to the complainant
in advance in the bill dated 9.5.2015.
4. The complaint was formally registered as Complaint No.713 and notice was issued
to the concerned Xen (Nodal Officer) with copy to the complainant fixing the case for
consideration on 10.8.2015 vide Memo. No.CGRF/Comp-708/709/712 to
714/2015/1137 dated 24.7.2015.. On the date of hearing, only SDO along with his
116
RA was present. The complainant did not attend.The SDO reiterated his written
submissions.
5. Observations and Decision of the Forum:
The Forum observed that necessary correction of the ACD amount has already
been done and advice was conveyed to the Incharge Computer Cell. The Nodal
Officer is directed to ensure that the interest is also paid to the complainant on the
actual amount of the ACD available with the department. Compliance be reported
within 21 days of issue of order failing which the Hon’ble JERC may impose penalty
as per relevant sections of Electricity Act 2003.
6. With the above observations and decision, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
117
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 782 Date of Institution - 29.5.2015 Date of Order - 08.09.2015 In the matter Sister Gracy Joseph, Principal, St. Anne’s Convent School, Sector 32, Chandigarh.
……………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 3, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.6, UT, Chandigarh.
……………….Respondents
Order
1. The Principal, St. Anne’s Convent School, Sector 32, Chandigarh through
application dated 25.5.2015, received in the office of CGRF on 29.5.2015, submitted
that St. Anne’s Convent School is a religious unaided “Minority Educational Institute”
within the meaning of section 2(g) of the National Commission for Minor Educational
Institutions Act 2004 and the National Commission for Minor Educational Institutions,
Govt. of India vide F.No.1757 of 2006 dated 29.1.2007 has declared that school is a
Minority Educational Institution covered under Article 30 of the Constitution of India.
The school has not set up with any profit making motive and is not a commercial
establishment. The electricity connection to the school was being charged under DS
tariff till April 2013 where after the category has been changed to NRS. The
applicant submitted that School is recognized by Education Department, Chandigarh
Administration and as such the tariff applicability should be domestic supply as per
provisions in the tariff order issued by the Hon’ble JERC. The applicant prayed for
examining the points and correct the tariff category as DS w.e.f. May 2013 and
refund the excess charges charged on account of NRS tariff.
2. The para-wise comments were called from the Nodal Officer i.e. Executive Engineer,
Electricity Operation Division No.3 vide letter dated 1.6.2015 with a copy to the
complainant.
118
3. The concerned SDO ‘OP’ Sub Division No.6 vide his letter dated 26.6.2015
submitted para-wise comments.
The SDO submitted that the electricity bills were issued on DS tariff till 21.5.2013
where after the tariff category was converted to NRS during the billing period
30.5.2013 to 22.11.2013 as per Notification dated 23.5.2013 under intimation to the
applicant. The tariff category was changed as per Hon’ble JERC order for the year
2015-16 Clause 2 (b).
4. The Complaint registered as Complaint No. 782 was notified for hearing on
8.9.2015, vide letter No. 1337-43 dated 20.8.2015 . The representative of the
applicant as well as the concerned SDO were present. The SDO submitted that the
tariff category was changed as per Chandigarh Electricity Department Notification
dated 23.5.2013 where in it was provided that all Private Schools other than those
run by the Chandigarh Administration would be covered under NRS tariff.
5. Observations by the Forum:
The Forum has gone through the Tariff Order issued by the Hon’ble JERC for the
year 2013-14, 2014-15 and 2015-16 and has observed that the following provisions
exist in respect of Private Educational Institutions.
(i) Domestic Supply Applicability:
“Government recognized education institutions, viz schools, colleges
universities, ITI hostels, canteens, and residential quarters attached to the
educational institutions”
Notes:
iii. “Private Education Institutions not recognized by the Chandigarh
Administration shall be billed under Non Domestic Tariff.”
The Plain reading of the provisions with regard to applicability of the domestic
supply tariff points out that all Government Recognized Schools are to be covered
under DS Tariff. The Note under (iii) further clarified that the Private Educational
Institutions Not Recognized by the Chandigarh Administration shall be billed under
NRS tariff.
119
The SDO during hearing also stated that as per provisions in the tariff order for the
charitable organisations, the Schools is required to apply in a writing to the
Electricity Department along with a certificate with regard to institution registered
with the Income Tax Authorities under Section 80G, 80 GGA or 35 AC for
consideration for the tariff in the Domestic Category
The Forum do not agree with the submissions made by the SDO in this regard as
the provisions with regard to Private Schools recognized by the Chandigarh
Administration are amply clear in the tariff order issued by the Hon’ble JERC.
6. Decision:
In view of above, the Forum directs the Nodal Officer to change the category of the
applicant from NRS to DS w.e.f. 22.5.2013 and adjust the excess amount deposited
by the School Authorities in future bill. Compliance be reported within 21 days after
the receipt of the order failing which the penalties may be imposed by Hon’ble JERC
as per relevant sections of the Electricity Act 2003.
7. With the above observations and directions, considers the complaint as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
120
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 783 Date of Institution - 13.5.2015 Date of Order - 08.09.2015 In the matter Shri Charan Singh Virdi, Secretary, Punjab State Committee of Communist Party of India, Cheema Bhawan, Sector-30, Chandigarh.
……………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 3, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.6, UT, Chandigarh.
……………….Respondents
Order
1. The Secretary, Punjab State Committee of Communist Party of India through Shri
Charan Singh Virdi submitted an application dated 8.5.2015 to the CGRF for
withdrawal of notice dated 24.12.2014 issued by SDO and for refund Rs.1,92,242/-
deposited by them. The complainant stated that Communist Party of India has state
Head quarters in Cheema Bhawan, Sector 30-B, Chandigarh. They were making
the payment towards the electricity bills as being issued by the department regularly.
A notice dated 24.12.2014 was received from the SDO ‘OP’ Sub Division No.3
where in a sum of Rs.1,94,242/- was demanded towards sundry charges on
account of meter being Dead Stop for the period 10.12.2012 to 11.12.2014 on the
basis of overhauling. The complainant submitted that during the disputed period
they were being issued bills on the basis of average and the meter being Dead Stop
was not conveyed by the meter reader/department, it was responsibility of the Sub
Division to change the defective electricity meter well in time. The details of the bill
received on average and the amount paid by them was also provided by the
applicant. The applicant stated that adjustment of the bill issued on average basis
for the period about two years is not in order and prayed for setting aside the Notice
dated 24.12.2014 issued by the SDO and also adjustment of R.1,94.242/- already
deposited by them in response to the Notice.
121
2. The para-wise comments were called from the Nodal Officer i.e. Executive Engineer,
Electricity Operation Division No.3 vide letter dated 18.5.2015 with a copy to the
complainant.
3. The concerned SDO ‘OP’ Sub Division No.6 vide his letter dated 5.6.2015
submitted para-wise comments along with consumption data of the complainant and
basis of overhauling as well as copy of MCO.
The SDO stated that amount of Rs. 1,84,326/- was debited after overhauling the
account of the consumer from the period 10.12.2012 to 11.12.2014 when the meter
was dead stop. During the period meter was Dead Stop the bills were issued on
adhoc basis with meter Status Code as ‘D’ thus it was well within the knowledge of
Complainant that the bills were being issued on average basis due to defective/dead
stop meter. The payment of Rs.1,94,242/- deposited by the complainant also include
the current bill charges in addition to sundry charges of Rs.1,84,326/-. The account
has been overhauled @ 3047 units per month for the period 10.12.2012 to
11.12.2014 on the basis of consumption recorded during the period 6/2011 to
6/2012 with adjustment of adhoc amount already charged and paid by the
complainant for the bills issued on average basis. He also stated that the meter
could not be replaced earlier due to non availability of meters in the store.
4. The Complaint registered as 783 was notified for hearing on 8.9.2015, vide letter No.
1337-43 dated 20.8.2015. The complainant as well as the concerned SDO was
present. The complainant reiterated his written submissions that the adjustment of
bills already issued and paid by them is not justified. He specifically stated that it
was the responsibility of the department to replace the defective meter early so that
bills are issued to the consumer on consumption basis. Further the average being
charged to them during this period was not worked out correctly thereby demand of
lump sum heavy amount through notice. The SDO stated that the meter could not be
changed early as the same were not available in the store. With regard to less
average charging, he stated that average was being charged by computer. The
SDO also stated that overhauling done by the Sub Division is in order as the
average consumption recorded by the replaced meter is more than the base
calculated by the Sub Division for overhauling the account.
122
5. Observations and decision by the Forum:
The Forum after going through the consumption data, noted that the basis of
overhauling of the account and the charging of amount through Notice was required
to be calculated in view of following observations:-
a) The overhauling of the account has been done from 12/12 to 11/12/2014
whereas the meter become defective during the period 08/12 to 10/12 and thus
the overhauling of the account is to be done for 08/12 to 11/12/2014 instead of
12/12 to 11/12/2014 i.e. for 28 months.
b) The base for overhauling has been later as consumption recorded during the
period 06/11 to 06/12. The Forum noted that for the period 06/12 to 08/12, the bill
was issued with meter status code as ‘Z’. Thus this period also needs to be
included while working out the average for overhauling.
6. The Forum also observed that the sub division had allowed the continuation of
defective period for a much longer time. In case, the meters were not available in the
store, the option of asking the consumer to provide his own meter should have been
explored. Further the average being charged during the period was almost half of
the past consumption. Had the average been worked out correctly, the charging of
lump sum amount of 1.8 lac would not have arisen. In view of above observations,
the Forum directs the Nodal officer to recalculate the amount as per above
observations.
7. The Forum also directs the Electricity Department to arrange sufficient meters and
do not allow the defective meters to continue for such a long period. Further
directions needs to be issued to all the Nodal Officer that the average being charged
of defective/dead stop/burnt meters or premises locked cases should be reviewed at
regular intervals of 2/4 months in order to avoid shocks to the consumers when the
accounts are overhauled. Compliance be reported within 21 days after the receipt of
the order failing which the penalties may be imposed by Hon’ble JERC as per
relevant sections of the Electricity Act 2003.
123
8. With the above observations and directions, the complaint is considered as
disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
9. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
124
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 788 Date of Institution - 29.04.2015 Date of Order - 16.09.2015 In the matter Shri Sham Lal, House No.530B, T-24, Housing Board Dhanas, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.4, UT, Chandigarh.
……………….Respondents
Order
1. Shri Sham Lal, resident of House No.530B, Housing Board, Dhanas, Chandigarh
through his representation dated 29.4.2015 submitted that the bills prepared in the
past from July 2014 onward were on wrong readings (on higher side) where as
actual readings were less.
2. The complaint was forwarded to the Nodal Officer i.e. Executive Engineer, Electricity
Operation Division No.1 vide letter dated 15.5.2015 with the directions to submit
parawise reply. A reminder was also issued on 18.8.2015, as the Forum did not
receive the reply from the Nodal Officer in time.
3. The concerned SDO ‘OP’ Sub Division No.4 vide his letter dated 4.9.2015 submitted
that wrong reading bill of the complainant was issued for the period 20.11.2014 to
20.1.2015. The next bill was issued on average basis. He further submitted that the
wrong reading bill was revised by his office and sundry allowance advice for
RS.3434/- was sent which appeared in the consumer bills during the period March
2015 to May 2015. Simultaneously, the average bill issued on ‘I’ Code (Inconsistant
reading) was also adjusted by the computer and net bill of Rs.944/- was issued to
the consumer. The consumer paid the bill on 13.7.2015. A copy of the revised bill
was also submitted along with reply.
4. The complaint registered as Complaint No.788 was listed for hearing on
16.09.2015 vide letter No. 1388 dated 27.8.2015 with a copy to the complainant. The
125
notice was, however, returned undelivered with the remarks that no such house
number at Dhanas. An attempt was made to contact complainant on the mobile
number, mentioned in the complaint but the contact number was found to be not
valid number as per recorded message.
5. The Forum observing that the complaint has already been redressed, considers the
complaint as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
126
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 789 Date of Institution - 29.04.2015 Date of Order - 16.09.2015 In the matter the Senior Manager, Haryana Financial Corporation Bays Nos. 17,18 & 19, Sector 17-A, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.4, UT, Chandigarh.
……………….Respondents
Order
1. The Senior Manager, Haryana Financial Corporation, Bays No.17,18 & 19, Sector
17-A, Chandigarh vide letter dated 29.4.2015 stated that the electricity bills of his
office are not being received by them in time and they are facing lot of difficulty in
making the payment timely. He also submitted that the electricity bills for period
Jan.2015 onwards were not received as on date. He requested for delivery of bills
within time to avoid any type of inconvenience to pay in time.
2. The complaint was forwarded to the Nodal Officer i.e. Executive Engineer, Electricity
Operation Division No.1 vide letter dated 6.5.2015 for submitting parawise
comments, with a copy to the complainant. A reminder was also issued by the
Forum on 18.8.2015 to the Nodal Officer due to non receipt of reply with stipulated
time.
3. The Nodal Officer i.e. Executive Engineer, Elecy. ‘OP’ Division No.1 vide letter dated
3.9.2015 forwarded the reply submitted by the concerned SDO ‘OP’ Sub Division
No.4. wherein SDO submitted that the electricity bill of 4 Number Accounts were
distributed by the Post Office. The grievance of the consumer about late receipt of
bills has already been conveyed to the Post Master General, Sector -17,
Chandigarh vide letter dated 27.4.2015. The complainant was also informed vide
letter dated 6.5.2015 that the electricity bills can be downloaded directly from the
website of the Electricity department or duplicate copy can be had from his office or
127
e–Sampark Centres to avoid levy of late payment surcharges. The complainant
was also made aware of the Clause No.5 printed on the overleaf of the electricity bill
with regard to above. The Sub Division also enclosed a copy of the letter written to
the Post Master General and to the complainant.
4. The complaint registered as Complaint No. 789 was listed for hearing on
16.09.2015 vide letter No. 1388 dated 27.8.2015. Only SDO & RA were present, the
complainant did not attend.
5. The Forum observing that Post Master, Sector 17, Chandigarh has already been
advised by the Sub Division for late delivery of bills and further the complainant was
educated about obtaining the duplicate copy of the bill, considers the complaint as
disposed. The Nodal Officer is however, directed to ensure that bills to the
consumers are delivered in time and in future.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
128
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - 790 Date of Institution - 13.04.2015 Date of Order - 16.09.2015 In the matter the Manager, LIC, Jeevan Parkash, Sector 17-B, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.4, UT, Chandigarh.
……………….Respondents
Order
1. The Manager (Estate), LIC, Sector-17, Chandigarh vide his letters dated 13.4.2015,
28.4.2015 and 28.4.2015, complaint about late receipt of electricity bill against 3 No.
Accounts. The bills were received on 9.4.2015, 27.4.2015 and 13.4.2015 with due
date as 4.4.2015 and thus bills attracted late payment surcharges. It was requested
to issue correct bills for payment without late payment surcharges and adjust the
surcharge.
2. The complaint was forwarded to the Nodal Officer i.e. Executive Engineer, Electricity
Operation Division No.1 vide letter dated 18.5.2015 for submitting parawise
comments, with a copy to the complainant. A reminder was also issued by the
Forum on 18.8.2015 to the Nodal Officer due to non receipt of reply with stipulated
time.
3. The Nodal Officer i.e. Executive Engineer, Elecy. ‘OP’ Division No.1 vide letter dated
3.9.2015 forwarded the reply submitted by the concerned SDO ‘OP’ Sub Division
No.4. wherein SDO submitted that the electricity bills of 3 Number Accounts were
distributed by the Post Office. The grievance of the consumer about late receipt of
bills has already been conveyed to the Post Master General, Sector -17, Chandigarh
vide letter dated 27.4.2015. The complainant was also informed vide letter dated
7.5.2015 that the electricity bills can be downloaded directly from the website of the
Electricity department or duplicate copy can be had from his office or e–Sampark
129
Centres to avoid levy of late payment surcharges. The complainant was also made
aware of the Clause No.5 printed on the overleaf of the electricity bill with regard to
above. The Sub Division also enclosed a copy of the letter written to the Post
Master General and the complainant.
4. The complaint registered as Complaint No. 790 was listed for hearing on
16.09.2015 vide letter No. 1388 dated 27.8.2015. Only SDO & RA were present, the
complainant did not attend.
5. The Forum observed that no other consumer in the neighbourhood of the
complainant had complaint about receipt of bills after due date. Only M/s Haryana
Financial Corporation Ltd., Bays No. 17,18,19 & 20, Sector 17-A, has complained
about late delivery of bills but no after the due date was over. The consumers are
aware about the likely date of payment of bills. The complainant could have asked
for duplicate bills from the Sub Division as per printed clause No.5 on the overleaf of
the bill and as such their request for refund of the late payment surcharges is not
acceptable. The Nodal Officer is, however, directed to check that the electricity bills
are delivered to the consumer in future.
6. With the above observations and directions, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
130
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG 5of June 2015 Date of Institution - 17.06.2015
Date of Order - 30.07.2015 In the matter Shri Sukhdev Singh, House No.3031, Sector 20-D, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 3, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 6, UT, Chandigarh.
……………….Respondents
Order
1. Shri Sukhdev, resident of House No.3031, Sector 20-D, Chandigarh through his
representation dated 11.6.2015 received in the office on 16.6.2015 submitted that
the SDO ‘OP’ Sub Division No.6 sent him a bill of Rs.30,719/- which included sundry
charges of Rs.29,377/-. He desired detail of sundry charges levied for the period
4.6.12 to17.4.2015. He further submitted that he had been paying the electricity bills
regularly in the past as served to him by the electricity department. He submitted
that as discussed with SDO, he made a part payment of Rs.16000/- for the disputed
bill. He also indicated that details may be provided to him at an early date as he is in
the process of vacating the house.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.3 to submit parawise comment along with consumption data
for the last three years vide letter dated 26.6.2015.
3. In response to this office letter asking him for the fact of the case along with
consumption data, the concerned SDO ‘OP’ Sub Division No.6 vide his letter dated
14.7.2015 submitted the reply as under:-
i) That the meter of the complainant was replaced on 17.4.2014 being
defective.
ii) The Account of the consumer was overhauled for the period 4.6.2012 to
17.4.2014 (22.5 Months) on the basis of previous consumption.
131
iii) The present consumption by the replaced meter was also noted for one
year and was found to be higher than the base selected for charging.
iv) The charging was done as per Supply Code Regulations i.e. on the basis
of previous consumption.
He also stated that details of the sundry charges has already been
sent to the consumer and also supplied the consumption data of the
consumer for the period April 2011 to April 2015 along with other related
documents including copy of MCO.
4. The formally registered complaint was listed for hearing on 30.7.2015 vide letter No.
CGRF/Comp-CG5 & CG8/2015/1126 dated 21.7.2015, a copy of which was also
sent to the SDO, Electy. ‘OP’ Sub Division No.6 and to the complainant.
On the date of hearing, the complainant as well as concerned SDO ‘OP’
Sub Division No.6 were present. The complainant contested the levy of sundry
charges . The SDO stated that charges worked out by him were correct and as
per Supply Code Regulations.
5. Observations of the Forum:
From the Consumption data supplied by the Sub Division, it was
observed that though the bill for the period June 2012 to October 2013 were
issued on the basis of meter readings with meter status code as ‘Z’ i.e. O.K. yet
the consumption during this period was very very less such as 6 units for the
period August to October 2013, 39 Units for the period December 2012 to Feb.
2013 which the SDO attributed due to meter becoming defective after June 2012.
T3he consumption being recorded during the summer peak of June 2012 to Aug.
20012 as 325 units was nowhere in comparison to the corresponding period
consumption of 1306 units in 2011 or 1072 units in 2014, which clearly
established that the meter became defective somewhere in June 2012. The
complainant also admitted that the premises was not locked during any time of
this period and also they have one AC which is otherwise lying defective now.
The complainant also submitted that he has already shifted from the house to a
new premises of House No. 32, Sector 21-A, Chandigarh and the connection was
in the name of the owner.
132
6. Decision of the Forum:
On the basis of above observations and submissions by the SDO the Forum
reaches the conclusion that the meter might have become defective and started
recording less consumption w.e.f. June 2012. The recorded consumption
became less and less with passage of time and ultimately becoming 69 units
during June to August 2013, 6 units during August to October 2013 before
becoming ‘Dead Stop’ in October 2013. Thus the action taken by the SDO in
overhauling the account is correct. The SDO as well as complainant confirmed
that all the payment has been made and nothing is due.
7. With the above observations, complaint stands dismissed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
133
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG-6 of 2015 Date of Institution - 18.06.2015 Date of Order - 18.08.2015 In the matter Shri Harpal Singh, 289, Pipliwala Town, Manimajra, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 2, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.8 UT, Chandigarh.
……………….Respondents
Order
1. Shri Harpal Singh, resident of House No.289, Pipliwala Town, Manimajra,
Chandigarh vide his representation dated 17.6.2015 received in the office on
18.6.2015 submitted that generally he makes the payment of the electricity bill
through Cheque. However, on 15.6.2015 when he went to e-Sampark Centre for
making payment of electricity bill amount to Rs.11970/-, he was insisted upon to
make payment through demand draft as one of his cheque got bounced/ was
dishonoured in the past . He submitted that the payment by Demand Draft should
not be insisted.
2. The comments of the Nodal Officer i.e. Executive Engineer, Electricity Operation
Division No.2 were called vide letter dated 25.6.2015 with a copy to the
complainant.
3. The Nodal Officer vide his letter dated 30.6.2015 submitted that the matter relates to
generalised instructions of the Electricity Department and desired that the case be
dealt with the Commercial Section.
4. The formally registered complaint No. C-6 of 2015 was listed for hearing on
18.8.2015 vide letter No. CGRF/Comp-510/505/738/CG-3/CG-6/2015/1158 dated
24.7.2015, a copy of which was also sent to the SDO, Electy. ‘OP’ Sub Division No.8
and to the complainant.
134
5. On the date of hearing on 18.8.2015, the complainant, Nodal Officer and the SDO
OP’ Sub Division No.8 along with his RA and AEE (Commercial) of the Office of S.E.
Elecy. ‘OP’ Circle were present. Shri Pawan Kumar , AEE (Commercial) informed
that as per existing instructions whenever cheque is bounced/dishonoured, the
consumer is required to make the payment through Demand Draft only. He also
informed that the earlier limit for making payment by cash was Rs.10,000/- but
recently this limit has been raised to Rs.20,000/- per bill. The complainant on querry
by the Forum stated that his normal bill does not exceed Rs.20000/- and thus as per
his understanding he can make payment in cash. The Forum also noted that the
DD was being insisted as per the instructions of the Electricity Department.
6. With the above observations that the consumer got satisfied with the enhancement
of limit for payment of bill amount in cash, the consumer showed his satisfaction, the
complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
135
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG 8 of June 2015 Date of Institution - 25.06.2015
Date of Order - 30.07.2015 In the matter Smt. Surinder Kaur, House No. 2869/3, Sector 49-C, Chandigarh
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 3, UT, Chd. 2. AEE, Elecy. ‘OP’ Sub-Divn. No. 6, UT, Chandigarh.
……………….Respondents
Order
1. Smt. Surinder Kaur, resident of House No. 2869/3, Sector 49-C, Chandigarh vide
her application dated 25.6.2015 submitted that on receipt of high consumption bills
in 2011, she made a request to the concerned SDO for checking the meter as she
attributed high consumption to the case of jumping of reading. The bills were
however, paid. Disputed meter was changed in the Sub Division in December 2014
and now a bill of Rs.38,711/- has been sent to her. She stated that the overhauling
of the account on the basis of past consumption for which she suspected to be a
case of meter jumping, is not in order and account for the period meter remained
defective be overhauled on the basis of new consumption. She also requested to
stay the disputed amount.
2. The representation was forwarded to the Nodal Officer i.e. Executive Engineer,
Elecy. ‘OP’ Division No.3 to submit parawise comments along with consumption
data for the last three years vide letter dated 26.6.2015.
3. The concerned SDO ‘OP’ Sub Division No.6 vide his letter dated 9.7.2015 submitted
that dead stop electricity meter of the complainant was replaced on 12.12.2014.
Thereafter the account of the consumer was overhauled for the period 6.1.2013 to
12.12.2014 on the basis of previous consumption for the period March 2011 to
March 2012 @ 593 units per month and accordingly an amount of Rs.36094/- was
136
debited to the account of the complainant. He also supplied the copy of MCO as
well as consumption data for the last four years.
4. The formally registered complaint was listed for hearing on 30.7.2015 vide letter No.
CGRF/Comp-CG5 & CG8/2015/1126 dated 21.7.2015, a copy of which was also
sent to the SDO, Electy. ‘OP’ Sub Division No.6 and to the complainant.
On the date of hearing, the representative of the complainant as well as
concerned SDO ‘OP’ Sub Division No.6 were present. The representative of the
complainant submitted that they received an inflated bill in December 2011 which he
attributed to meter reading jumping and made a representation to the SDO on
8.11.2011. Though he paid the bills at that time he contended that average being
now charged on that basis (contested by him) is on higher side and not in order. He
prayed for charging on the basis of consumption recorded by the new meter. The
SDO submitted as the period of meter remaining defective was more than one year,
the base for charging has been taken as one year from 3/11 to 3/12. He submitted
that the meter was perfectly in working order during this period.
5. Observations:
The Forum observed that the overhauling was done by the SDO @ 593
units per month. The consumption after replacement of the meter was found to be
520 units during the period Jan to March 2015 and 530 units during the period Mach
2015 to May 2015. As the period was less than 6 months the current reading as on
date was asked which the SDO told as 4785. Thus it was observed that the present
meter recorded consumption of 4779 units from 12.2.2014 (Date of MCO with initial
reading 6) to 30.7.2015 in 7-1/2 months. The average consumption on the basis of
new meter was calculated as 637 units per month which was found to be more than
average charged by the SDO on the basis of past consumption.
6. Conclusion & Decision of the Forum:
On the basis of above, the Forum conclude that overhauling done by the SDO on
the basis of o ne year consumption is in order. The complainant agreed to the
inference drawn by the Forum. The complainant requested for allowing to make
the payment in instalments of Rs.6000/7000. The Forum agreed to the request
made by the representative of the complainant and directs the Nodal Officer to
137
recover the amount from the consumer in instalments without levy of surcharge
@ Rs.6000/- (as sundry amount is of the order of Rs.36000/-) bi-monthly in
addition to current bill charges. Compliance be reported within twenty one days
after the receipt of the order failing which the Hon’ble JERC may impose penalty
as per relevant rules of Electricity Act 2003.
7. With the above observations, complaint stands dismissed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
138
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG-10 of 2015 Date of Institution - 02.07.2015 Date of Order - 08.09.2015 In the matter Smt.Sham Rani Gupta, W/o Shri Vir Bhan Gupta, House No.4005, Sector 46-D, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 3, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.6, UT, Chandigarh.
……………….Respondents
Order
1. Smt. Sham Rani Gupta , resident of House No.4005, Sector 46-D, Chandigarh vide
her representation dated 2.7.2015 stated that she paid the electricity bill issued in
February 2015 up to reading 56950. However, the bill issued in April 2015 showed
the bill paid up to reading of 56229. Though in this bill electricity department charged
the bill of 791 units in excess, yet she paid the bill. Despite her representation to the
sub division, the next bill issued on 25.6.2015 was without adjustment.
2. The Executive Engineer, Electricity Operation Division No.3 was called upon to
submit parawise comments/action taken report on the representation vide letter No.
997-99 dated 6.7.2015 with a copy to the complainant.
3. The concerned SDO ‘OP’ Sub Division No.6 vide his letter dated 23.7.2015 informed
that the consumer had applied for change of name and deposited the bill in
December 2014. The new account No. was allotted and the bill for the period
December 2014 to March 2015 was issued showing the initial reading as 56229
instead of 56950. He further submitted that the bill has been corrected and an
amount of Rs.2914/- has been credited to the new consumer account to be reflected
in the next bill.
4. The complaint registered as Complaint No.CG-10 of 2015 was listed for hearing on
08.09.2015 vide letter No. 1336 dated 20.8.2015. The consumer did not attend.
The SDO reiterated his written submissions
139
5. The Forum observing that the SDO had already taken corrective action and the
excess payment made by the consumer might have been reflected in the last bill
issued in August 2015, considers the complaint as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
140
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG 11 Date of Institution - 07.07.2015
Date of Order - 14.07.2015 In the matter Shri Vipul Dubey, House No.226C, Sector 51A, Chandigarh.
………………..Petitioner
Versus
1. The Additional Superintending Engineer, Elecy. ‘OP’ Divn. No. 4 UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No. 9, UT, Chandigarh.
……………….Respondents
Order
1. Shri Vipul Dubey through his e-mail dated July 7, 2015 submitted that current bill
for his Account No. 409/5142/0226COK was received in torn condition and he
fail to understand the details. He was also unable to review the bill online. He
requested for issuance of duplicate bill.
2. The Nodal Officer i.e. Addl. Superintending Engineer, Elecy. ‘OP’ Division No.4
was directed to ensure deliver of duplicate bill to the consumer latest by 10th July
2015 vide letter dated 7.7.2015.
3. The SDO delivered a duplicate bill to the complainant by hand on 9th July 2015
and confirmed the same to the Forum.
4. The complainant through e-mail dated 7.7.2015 was also conveyed and he
confirmed the receipt of the bill stating that issue had been resolved.
5. With the above observations that grievance of the consumer had already been
redressed with the quick action taken by the SDO ‘OP’ Sub Division No.9. The
prompt action by the SDO ‘OP’ Sub Divn. No. 9 is appreciated.
141
6. With the above observation, complaint stands disposed
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
7. A copy of this order be placed on the main file for record. One copy be sent to
the office of XEN being the Nodal Officer with a copy to the consumer for
compliance wherever required. File be consigned to the record room after
having it properly numbered and indexed.
(RL MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
142
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG-12 of 2015 Date of Institution - 09.07.2015 Date of Order - 25.08.2015 In the matter Shri Lokesh Vasudeva, House No.1017/2, Sector 45-B, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 4, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.9 UT, Chandigarh.
……………….Respondents
Order
1. Shri Lokesh Vasudeva, resident of House No.1017/2, Sector 45-B, Chandigarh
through his e-mail dated 8.7.2015 requested for arranging duplicate copies of
electricity bills for the last 3 cycles stating that same have not been received by him.
He also stated that he was ,however, regularly making the payment for electricity
bills at nearby e-Sampark on employee’s verbal communication.
2. The Executive Engineer, Electricity Operation Division No.4 was called upon to
submit parawise comments/action taken report on the representation vide letter
dated 9.7.2015 with a copy to the complainant.
3. The concerned SDO ‘OP’ Sub Division No.9 vide his letter dated 16.7.2015 supplied
the copies of duplicate bills of last 3 cycles to the complainant. The copy of the
above letter was also endorsed to CGRF in compliance to its direction. A copy of
the account statement electricity/water bills showing the payments made by the
consumer was also supplied. It was noted that the consumer was making the
payment regularly.
4. The complaint registered as Complaint No.CG-12 of 2015 was listed for hearing
on 25.8.2014 vide letter No. 778/CG-1/CG-12/2015/1279 dated 10.8.2015. The
consumer through e-mail dated 25.8.2015 showed his inability to attend the hearing
due to other commitments. He, however, showed his concern about the payment of
Rs.309/- made at Sector 43 Sampark Centre on 2nd May 2015 as the same was not
143
reflected in the last bill with due date as 8.6.2015. The SDO along with his RA
present, during the hearing submitted that payment of Rs.309/- is reflected in the
credit of the complainant and would be adjusted in the subsequent bill.
5. The Forum observing that the grievance of the complainant for supply of duplicate
copy of bills is already been redressed considers the complaint as disposed. The
Nodal officer is, however, directed to ensure
i) Delivery of bill to the complainant before the due date in future.
ii) The credit of payment Rs.309/- is reflected in the next bill.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
144
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG-17 of 2015 Date of Institution - 20.07.2015 Date of Order - 01.09.2015 In the matter Shri Vinod Joshi, House No.3203-G, Sector 40-D, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 4, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.10, UT, Chandigarh.
……………….Respondents
Order
1. Shri Vinod Joshi, resident of House No.3203-G, Sector 40-D, Chandigarh through
his representation dated 20.7.2015 complained about non receipt of his electricity bill
since Jan. 2015. He stated that he had made many requests by visiting personally
to the Electricity office but could not get the desired response during the period of
last six months.
2. The Executive Engineer, Electricity Operation Division No.4 was called upon to
submit parawise comments/action taken report on the representation vide letter No.
1121-22 dated 21.7.2015 with a copy to the complainant.
3. The concerned SDO ‘OP’ Sub Division No.10 vide his letter dated 28.7.2015
submitted that the consumer applied for an electric connection but due to clerical
oversight wrong Account number was assigned resulting into delay in issuance of
the bill. He also submitted that to avoid inconvenience to the applicant, necessary
verification was got done and bill up to meter reading 1025 was prepared manually
and handed over to the consumer. The consumer also made payment of this
manual bill amounting to Rs.1267/- on 24.7.2015. The SDO stated that Master File
is being sent to the Computer Centre on 31.7.2015 for creating a new account and
issuance of computerized bill.
4. The complaint registered as Complaint No.CG-17 of 2015 was listed for hearing
on 01.09.2015 vide letter No. 1332 dated 20.8.2015. The consumer as well as
145
concerned SDO ‘OP’ Sub Divn. No.10 was present. The complainant reiterated his
written submissions and stated that the Sub Division staff handled his application in
a casual manner as the address was mentioned wrongly and also that in the manual
bill, meter rent were charged though the meter was supplied by him.
The SDO was directed to get the computerized bill issued from the date of
application and also to adjust the payment of Rs.1267/- paid by the applicant
towards the manual bill. The SDO was also directed to ensure that the address is
correctly printed on the bill and the meter rental are not levied. The SDO should
also get the old account overhauled simultaneously, if required.
In view of above, the Nodal Officer is directed to ensure that the grievances
pointed out by the complainant are suitably addressed and correct computerized bill
is rendered to him. Compliance be reported immediately on issuance of the
computerized bill to the complainant failing which the penalties may be imposed by
Hon’ble JERC as per relevant sections of the Electricity Act 2003.
5. With above directions, the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
146
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG-19 of 2015 Date of Institution - 23.7.2015 Date of Order - 16.09.2015 In the matter Smt. Jaspreet Grewal, resident of House No.536A, Side Gate, Sector 16-D, Chanigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.4, UT, Chandigarh.
……………….Respondents
Order
1. Smt. Jaspreet Grewal, resident of House No. 536-A, Side Gate, Sector 16-D,
Chandigarh through e-mail dated 23.7.2015 in occupation of the back half of House
No.536, Sector 16-D, Chandigarh with postal address as House No.536-A, Side
Gate, Sector 16-D, Chandigarh. For the last 2 years she had not received the bills in
time due to improper billing address. She prayed for correction of the mailing
address on the bill. She also offered to avail the facility of SMS alert on her Mobile
No.9815631655.
2. The complaint was forwarded to the Nodal Officer i.e. Executive Engineer, Electricity
Operation Division No.1 vide letter dated 23.7.2015 for submitting parawise
comments, with a copy to the complainant. A reminder was also issued by the
Forum on 18.8.2015 to the Nodal Officer for submission of the reply.
3. The Nodal Officer i.e. Executive Engineer, Elecy. ‘OP’ Division No.1 vide letter dated
4.9.2015 forwarded the reply submitted by the concerned SDO ‘OP’ Sub Division
No.4. SDO in his reply stated that the amendment in the billing address has been
made by his office by adding the words “Side Gate” in the billing address of the
consumer and necessary advice for the same was sent to the Computer on
1.9./2015. With necessary changes to be reflected in the next bill of the consumer.
The SDO also submitted that the electricity bill of the consumer for the period April
147
2015 to June 2015 was negative with Rs.3527/- standing at the credit of the
consumer.
4. The complaint registered as Complaint No.CG-19 of 2015 was listed for hearing
on 16.09.2015 vide letter No. 1388 dated 27.8.2015. The complainant was informed
through e-mail on 15.9.2015 while forwarding the reply furnished by the Sub Division
for information and further action.
5. The complainant was also informed on telephone about the date of hearing. The
complainant assured her satisfaction to the action taken by the Sub Division. She
also informed that in respect of water bills to incorporate full mailing address to the
water department instead of printing full name started printing initial only in view of
the limit of the characters.
6. On the date of hearing SDO and RA were present but the consumer did not attend.
The Nodal Officer is directed to ensure that correct mailing address is printed on the
electricity bills and also that in case limit to the number of characters her name may
be abbreviated instead of mentioning full name. Compliance be reported
immediately on issuance of the bill with correct mailing address.
7. With above directions, the complaint stands as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
148
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG-20 of 2015 Date of Institution - 23.07.2015 Date of Order - 08.09.2015 In the matter Smt. Jaswant Kaur, House No.1559, Sector 49-B, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 3, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.6, UT, Chandigarh.
……………….Respondents
Order
1. Mrs. Jaswant Kaur, presently residing in of House No.745, Swastik Vihar, Zirakpur,
Punjab vide her representation dated 23.7.2015 submitted that she is owner of Flat
No. 1559, Pushpac Complex, Sector 49, Chandigarh. For the last two years she is
not residing at the flat but living with her daughter in Zirakpur due to medical
reasons. She was paying the electricity bills as received but the bill dated
21.5.2015 included an amount of Rs.36515/- on account of average charged for a
period of nearly 1-1/2 years.
2. The Executive Engineer, Electricity Operation Division No.3 was called upon to
submit parawise comments/action taken report on the representation vide letter No.
1155-57 dated 24.7.2015 with a copy to the complainant.
3. The concerned SDO ‘OP’ Sub Division No.6 vide his letter dated 4.8.2015 submitted
para-wise comments along with consumption data for the last three years. The SDO
stated that the meter got burnt and same was replaced on 20.2.2015. The account
of the consumer was overhauled for the period the meter remained burnt (from
20.4.2014 to 20.2.2015) on the basis of past consumption for the period 4/2013 to
4/2014 @ 903 units per month. With regard to premises remaining locked the SDO
submitted that the complainant had neither submitted any applications to the sub
division in this regard nor any application for visiting her son in France/U.S
149
4. The complaint registered as Complaint No.CG-20 of 2015 was listed for hearing on
08.09.2015 vide letter No. 1336 dated 20.8.2015. The consumer as well as
concerned SDO was present. The complainant stated that charging for the period
when she was not residing on the basis of past consumption is not justified. She also
submitted a certificate signed by the neighbours stating that she was not staying in
the flat for nearly past two years
5. Observations by the Forum:
From the consumption data, Forum observed that last bill issued on meter status as
‘OK’ was up to August 2014 where after the bills were being issued on average
basis with meter status code as “burnt’ till 20.2.2015 when the meter was replaced.
Thus the overhauling of the account overhauled for the period April 2014 to August
2014 is not in order when the bills were issued on reading.
6. Decision:
The Forum on the basis of above observations directs the Nodal Officer to overhaul
the account from August 2014 to 20.2.2015 on the basis of consumption recorded
during the corresponding period during the year 2013-14. The earlier charging done
by the SDO is set aside. Compliance be reported within 21 days after the receipt of
the order failing which the penalties may be imposed by Hon’ble JERC as per
relevant sections of the Electricity Act 2003.
7. With the above observations and directions, considers the complaint as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
8. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
150
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG-21 of 2015 Date of Institution - 29.07.2015 Date of Order - 18.09.2015 In the matter Shri Avnish Kumar Chhibba, House No.2166/3, Sector 45-C, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 4, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.9, UT, Chandigarh.
……………….Respondents
Order
1. Shri Avnish Kumar Chhibba, resident of House No.2166/3, Sector 45-C, Chandigarh
through his e-mail dated 29.7.2015 submitted that he got excess electricity bill due to
error in meter reading. The new reading was shown as 5971 units where as on
actual checking the reading was found to be 3195.7 on 28.7.2015.
2. The comments of the Nodal Officer i.e. Executive Engineer, Elecy. ‘OP’ Division
No.4 were called vide letter dated 30.7.3015 with a copy to the complainant. In the
mean time, the complainant sent another e-mail on 26.8.2015. A reminder was
issued to the Nodal officer vide letter dated 27.8.2015 for submission of comments.
The case was also notified for hearing on 18.9.2015.
3. The concerned SDO ‘OP’ Sub Division No.9 vide his letter dated 02.09.2015
submitted that the reply of the first notice of the Forum dated 30.7.2015 was
submitted on 14.8.2015.
4. The complaint registered as Complaint No.CG-31 of 2015 was listed for hearing
on 18.09.2015, The complainant did not attend. Only SDO along with his RA were
present in the hearing informed that the bill of the consumer for the period 19.2.2015
to 20.6.2015 was rectified up to meter reading 3522 after the reading was got
checked/verified by his office. He also stated that refund of RS.12552/- has been
allowed to the consumer through sundry allowance to be reflected in the next billing
cycle. The SDO also supplied copy of the letter dated 14.8.2015 which was not
151
received by the Forum. The Forum also observed that the reply by the Sub Division
was sent to the Xen as well as to the Complainant.
5. The complaint is considered as disposed as the Sub Division had already rectified
the bill as per complaint made by Shri Avnish Kumar Chibba.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
152
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG-30 of 2015 Date of Institution - 20.08.2015 Date of Order - 15.09.2015 In the matter Shri Gurinder Soni, House No.3434, Top Floor, Sector 38-D, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 4, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.10, UT, Chandigarh.
……………….Respondents
Order
1. Shri Gurinder Soni through e-mail dated 20.8.2015 submitted that he lives in House
No.3434, Top Floor, Sector 38-D, Chandigarh and paying the electricity and water
bills in time. For the last 4 months he did not receive any water or electricity bill. He
tried to contact the Complaint number or helpline number and also visited the
website in engineering.gov.in to view his bill but in vain.
2. The complaint was forwarded to the Nodal Officer i.e. Executive Engineer,
Electricity Operation Division No.4 vide letter dated 21.8.2015 with the directions to
ensure delivery of duplicate bill to the consumer latest by 26th August 2015. The
Forum through return e-mail dated 21.8.2015 also requested the complainant to
contact the Sampark Centre for making the payment of the electricity bill.
3. The concerned SDO ‘OP’ Sub Division No.10 through his written submissions dated
25.8.2015 informed that the complainant was contacted on his mobile on 24.8.2015
by the A.R.A. of his office. The Complainant informed that he had received
electricity bill through Postal Department. The applicant was also told to visit the Sub
Division during working hours for training him for downloading electricity bill form the
website of the department to avoid any inconvenience in the future.
4. The complaint registered as Complaint No.CG-30 of 2015 was listed for hearing
on 15.09.2015 vide letter No. 1401-03 dated 27.8.2015. The complainant did not
attend. The concerned SDO ‘OP’ Sub Divn. No.10 along with his RA were present.
153
The SDO stated that consumer had confirmed the receipt of the bills, which was also
conveyed to the Forum through written submissions dated 25.8.2015 and as such
the complaint be considered as disposed.
5. The Forum observing that the grievances of the consumer has already been
resolved, considers the complaint stands disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
6. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
154
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG-32 of 2015 Date of Institution - 25.08.2015 Date of Order - 16.09.2015 In the matter Mrs. Santosh Bajaj, W/o Late Shri K.C. Bajaj, House No.3235, Sector 15-D, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 1, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.4, UT, Chandigarh.
……………….Respondents
Order
1. Mrs. Santosh Bajaj, resident of House No. 3235, Sector 15-D, Chandigarh through
e-mail dated 25.8.2015, stated that she applied for a new Three Phase connection
and along with enhancement of load of 2 existing connections on 15.6.2015. The
Electricity ‘OP’ Sub Division No.4 when contacted informed non availability of cables
and asked for provide the cables for herself for release of connections. Thereafter,
she approached the Forum for issuing advise to the Sub Division to arrange the
cables and to release the connection expeditiously.
2. The comments of the Nodal Officer i.e. Executive Engineer, Elecy. ‘OP’ Division o.1
were called vide letter dated 26.8.2015 by 1.9.2015. The hearing of the case was
simultaneously fixed for 16.9.2015, with a copy to the complainant.
3. The complaint registered as Complaint No.CG-32 of 2015 was listed for hearing at
the time of calling comments on 16.09.2015 vide letter No. 1375-77 dated
26.8.2015. On the date of hearing, the SDO along with his RA were present. The
complainant did not attend. The SDO submitted that the connections have already
been released on 31.8.2015. He also handed over the written submissions along
with the copies of the SCO during hearing. The SDO in his written statement also
stated that consumer’s that she was asked to provide her own cable is wrong. A
letter signed by the consumer stated that her grandson met some person outside the
office who told him about the non availability of the cable was also enclosed with the
155
written submissions. The complainant also stated that the connections have been
released and she has no pending complaint against the department.
4. The Forum observing that the grievance of the consumer has already been
redressed, considers the complaint as disposed.
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
5. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
156
OFFICE OF THE CONSUMER GRIEVANCES REDRESSAL FORUM ROOM NO. 531, 5TH FLOOR, UT SECTT. BUILDING
UT, CHANDIGARH-160009
BEFORE ER. R.K. ARORA, CHAIRPERSON SH.G.D. SAINI MEMBER AND SH. R L MITTAL, OMBUDSMAN (RETD.), MEMBER.
Complaint No. - CG-37 of 2015 Date of Institution - 02.09.2015 Date of Order - 18.09.2015 In the matter Shri Balkar Singh, House No.1486, MIG Flats, Sector 61, Chandigarh.
………………..Petitioner
Versus
1. The Executive Engineer, Elecy. ‘OP’ Divn. No. 4, UT, Chd. 2. SDO, Elecy. ‘OP’ Sub-Divn. No.9, UT, Chandigarh.
……………….Respondents
Order
1. Shri Balkar Singh through his e-mail dated September 2, 2015 submitted that street
light on Pole opposite House No. 1486, MIG Flats, Sector 61, Chandigarh was not
working for the last 15 days. He lodged 3 complaints at the Electricity Complaint
Centre Sector 43 on 22.8.2015, 30.8.2015 and 1.9.2015 but no action was taken by
the Sub Division.
2. The comments of the Nodal Officer i.e. Executive Engineer, Elecy. ‘OP’ Division
No.4 were called vide letter dated 3.9.2015 with a copy to the complainant.
3. The SDO ‘OP’ Sub Division No.9 vide his letter dated 8.9.2015 addressed to the
Nodal Officer with a copy to the Forum as well as to the complainant informed that
the complaint was got checked by JE Street light wo reported on 8.9.2015 that
street light point at Pole No.34 near House No. 1485-86, Sector 61 was set right.
4. The complaint registered as Complaint No.CG-37 of 2015 was listed for hearing
on 18.09.2015.. On the date of hearing, the SDO along with his RA were present.
The complainant did not attend. The SDO stated that the street light has already
been set right as per the complaint of the consumer. The Forum observing that the
grievance of the complainant has been redressed, considers the complaint
disposed.
157
“The Complainant, if aggrieved, by non-redressal of his grievance by the Forum may make a representation/appeal against this order, before the Electricity Ombudsman for JERC for the State of Goa and UTs, “Vanijya Nikunj”, HSIIDC Office Complex (2nd Floor), Udyog Vihar, Phase-V, Gurgaon- 122016 (Haryana), Phone No.0124-2340954, Mob: 09871588333, E-mail id- [email protected] within one month from the date of receipt of this order.”
5. A copy of this order be placed on the main file for record. One copy be sent to the
office of XEN being the Nodal Officer with a copy to the consumer for compliance
wherever required. File be consigned to the record room after having it properly
numbered and indexed.
(R L MITTAL) (G.D. SAINI) (R.K.ARORA) MEMBER, CGRF MEMBER,CGRF CHAIRPERSON, CGRF
158