seiaapunjab.co.in of seac 78th meeting dt. 16.10...1 index item no. description page no. 78.01...

243
1 INDEX Item No. Description Page No. 78.01 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Bilaspur, Tehsil & Distt. Hoshiarpur by M/s Santokh Singh & Sons BKO, Village Bharta Khurad, Tehsil & District S.B.S. Nagar. 1-3 78.02 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Usmanpur, Tehsil Nawanshahr Distt. S.B.S. Nagar by M/s Anil Kumar BKO, Vill. Soeta, Tehsil & District S.B.S. Nagar. 4-6 78.03 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Bodal, Tehsil Dasuya, Distt. Hoshiarpur by M/s Ajmer Pal Singh BKO, Vill. Khera Kotli, P.O. Panwan, Tehsil Dasuya, Distt. Hoshiarpur. 7-9 78.04 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Begampur, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Arora Bricks Co., Village Karimpur Chahwala, Tehsil Balachaur, Distt. S.B.S. Nagar. 10-12 78.05 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Badallian, Tehsil Mukerian, Distt. Hoshiarpur by M/s Baba Beant Brick Mfg. Industry, Vill. Badalian Distt. Hoshiarpur. 13-15 78.06 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rakasan, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Bajaj Brick Co., Vill. Rurki Khurd, Tehsil Balachaur, Distt. S.B.S. Nagar. 16-18 78.07 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Badla, Tehsil Dasuya, Distt. Hoshiarpur by M/s Balaji Brick Industry, Vill. Sahu Da Pind, Tehsil Dasuya, Distt. Hosharpur. 19-21

Upload: truongtram

Post on 01-May-2018

213 views

Category:

Documents


1 download

TRANSCRIPT

1

INDEX

Item No.

Description Page No.

78.01 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Bilaspur, Tehsil & Distt. Hoshiarpur by M/s Santokh Singh & Sons BKO, Village Bharta Khurad, Tehsil & District S.B.S. Nagar.

1-3

78.02 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Usmanpur, Tehsil Nawanshahr Distt. S.B.S. Nagar by M/s Anil Kumar BKO, Vill. Soeta, Tehsil & District S.B.S. Nagar.

4-6

78.03 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Bodal, Tehsil Dasuya, Distt. Hoshiarpur by M/s Ajmer Pal Singh BKO, Vill. Khera Kotli, P.O. Panwan, Tehsil Dasuya, Distt. Hoshiarpur.

7-9

78.04 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Begampur, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Arora Bricks Co., Village Karimpur Chahwala, Tehsil Balachaur, Distt. S.B.S. Nagar.

10-12

78.05 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Badallian, Tehsil Mukerian, Distt. Hoshiarpur by M/s Baba Beant Brick Mfg. Industry, Vill. Badalian Distt. Hoshiarpur.

13-15

78.06 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rakasan, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Bajaj Brick Co., Vill. Rurki Khurd, Tehsil Balachaur, Distt. S.B.S. Nagar.

16-18

78.07 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Badla, Tehsil Dasuya, Distt. Hoshiarpur by M/s Balaji Brick Industry, Vill. Sahu Da Pind, Tehsil Dasuya, Distt. Hosharpur.

19-21

2

78.08 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. jandiali, Tehsil Banga & Distt. S.B.S. Nagar by M/s Baldev Singh Gurdeep Singh B.K.O., Vill. Jandialai, Distt. S.B.S. Nagar.

22-24

78.09 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rahon, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Davinder Kumar & Sons, Village Rahon Tehsil & Distt. S.B.S. Nagar.

25-27

78.10 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Ittian Tehsil Mukerian, Distt. Hoshiarpur by M/s Dev Ichha & Co., BKO, Namoli , Tehsil Mukerian, Distt. Hoshiarpur .

28-30

78.11 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Meharpatoli, Tehsil Dasuya, Distt. Hoshiarpur by M/s Dhir Brick Industry , Vill. Gagjalo, Tehsil Dasuya, Distt. Hoshiarpur.

31-33

78.12 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Badla, Tehsil Dasuya, Distt. Hoshiarpur by M/s Dhir Brick Kiln , Vill. Badla, Tehsil Dasuya, Distt. Hoshiarpur.

34-36

78.13 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Pallian Khurd, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s K.C. Bricks, Village Rahon, Tehsil & Distt. S.B.S. Nagar.

37-39

78.14 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rasulpur (Seota) & Usmanpur, Tehsil Nawanshar, Distt. S.B.S. Nagar by M/s K.K. Khosla Brick Industry BKO, Vill. Rasulpur (Seota), Tehsil & Distt. S.B.S. Nagar.

40-42

78.15 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Kot Ranjha, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Kamla Rani BKO, Village Musapur, Tehsil & Distt. S.B.S. Nagar.

43-45

78.16 Application for environmental clearance under EIA 46-48

3

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Musapur, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Kamla Rani BKO, Village Musapur, Tehsil & Distt. S.B.S. Nagar.

78.17 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Mallpur, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Kamla Rani BKO, Village Musapur, Tehsil & Distt. S.B.S. Nagar.

49-51

78.18 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rasulpur & Usmanpur, Tehsil Nawanshar, Distt. S.B.S. Nagar by M/s Kewal Kirshan Khosla BKO, Vill. Soeta, Tehsil & Distt. S.B.S. Nagar.

52-54

78.19 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Daffar, Tehsil Dasuya, Distt. Hoshiarpur by M/s Kiran Bala B.K.O., Vill. Daffar, Tehsil Dasuya, Distt. Hoshiarpur.

55-57

78.20 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Mehlanwali, Tehsil & Distt. Hoshiarpur by M/s Kirit Kiran Birck Industry, Vill. Mehatpur, Distt. Hoshiarpur.

58-60

78.21 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Passi Kandi, Tehsil Dasuya, Distt. Hoshiarpur by M/s Krishan Kumar BKO, Vill. Thiara, Distt. Hoshiarpur.

61-63

78.22 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Bassi Gulam Hussain, Tehsil Dasuya, Distt. Hoshiarpur by M/s Kundan Lal Murghai BKO, Vill. Adamwal, Tehsil & Distt. Hoshiarpur

64-66

78.23 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rahon, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Laroiya Brick Kiln, Village Chhokran, Tehsil & Distt. S.B.S. Nagar.

67-69

78.24 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rasulpur, Sahwajpur, Chhokran, Kotranja, Tehsil

70-72

4

Nawanshar, Distt. S.B.S. Nagar by M/s Loriya Brick Kiln, Vill. Chhokran, Tehsil & Distt. S.B.S. Nagar.

78.25 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Jugial Tehsil Dasuya, Distt. Hoshiarpur by M/s Laxmi Brick Industry, Vill. Jugial, Tehsil Dasuya, Distt. Hoshiarpur.

73-75

78.26 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Thiarray, Tehsil Dasuya, Distt. Hoshiarpur by M/s National Co-Operative Brick Kiln Industry, Vill. Dagan, Tehsil Mukerian, Distt. Hoshiarpur.

76-78

78.27 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Mehmdowal, Tehsil Garhsnkar, Distt. Hoshiarpur by M/s Parshotam Lal Bali BKO, Kaharpur, Tehsil Garhshanar, Distt. Hoshiarpur

79-81

78.28 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Railli, Tehsil Mukerian, Distt. Hoshiarpur by M/s Pawan Kumar BKO, Village Chak Bhian, Tehsil Mukerian, Hoshiarpur.

82-84

78.29 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Lalota, Tehsil Mukerian, Distt. Hoshiarpur by M/s Pawan Kumar Surinder Kumar BKO, Vill. Lalota, Tehsil Mukerian, Distt. Hoshiarpur.

85-87

78.30 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Ittian & Rally Tehsil Dasuya, Distt. Hoshiarpur by M/s Pooja Bricks Mfg. Industry, Village Talwara, Tehsil Mukerian, Distt. Hoshiarpur.

88-90

78.31 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Pallian, Bakhjlaur, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Pritpal Singh BKO, Village Sheikhupur, Tehsil & Distt. S.B.S. Nagar.

91-93

78.32 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Manan, Dhirowal Tehsil & Distt. Hoshiarpur by M/s Puri Birck Kiln Industry, Mehatpur, Una Road, Hoshiarpur.

94-96

5

78.33 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Mehamdowal Tehsil Garshankar, Distt. Hoshiarpur by M/s Rupica & Sandeep Bricks , Vill. Gohgroan Near Kalewal Bhagtan, Near Mahilpur, Distt. Hoshiarpur.

97-99

78.34 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Dollowal, Tehsil Mukerian, Distt. Hoshiarpur by M/s Sarswati Brick Mfg. Industries, Vill. Jeo Chak, Hoshiarpur.

100-102

78.35 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Dagan, Tehsil Mukerian, Distt. Hoshiarpur by M/s Shankar Enterprises BKO, Village Dagan, Tehsil Mukerian, Distt. Hoshiarpur.

103-105

78.36 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Ghorewaha, Tehsil Dasuya, Distt. Hoshiarpur by M/s Shiv Shakti Brick Indutry (Surinder Pal Brick Kiln, Vill. Nangal Farid, Hoshiarpur.

106-108

78.37 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Ittian, Tehsil Dasuya, Distt. Hoshiarpur by M/s Shiva Brick Industry, Vill. Ittian, Tehsil Dasuya, Distt. Hoshiarpur.

109-111

78.38 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rally, Mukerian, 0Hoshiarpur by M/s Shiva Krishna Gram Udyog, Vill. Dagan Tehsil Mukerian, Distt. Hoshiarpur.

112-114

78.39 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Gagsultan, Tehsil Dasuya, Distt. Hoshiarpur by M/s Sudesh Kumi BKO, Village Gagsultan, Teshil Dasuya, Distt. Hoshiarpur.

115-117

78.40 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Morian, Tehsil Dausya, Distt. Hoshiarpur by M/s Sukhdev Parshad Maini & Co. Vill. Rai Chak, Tehsil Dasuya , Distt. Hoshiarpur .

118-120

78.41 Application for environmental clearance under EIA 121-123

6

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Balagan, Tehsil Dasuya, Distt. Hoshiarpur by M/s Sukhdev Raj BKO, Vill. Balagan, Tehsil Dasuya, Distt. Hoshiarpur.

78.42 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Kahma, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Sukhvir Singh BKO, Village Kahma, Tehsil & Distt. S.B.S. Nagar.

124-126

78.43 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Sehrak Patti, Tehsil Dasuya, Distt. Hoshiarpur by M/s Trasem Lal & Co., Tehsil Dasuya, Distt. Hosharpur.

127-129

78.44 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Dollowal, Tehsil, Dasuya, Distt. Hoshiarpur by M/s Vasal & Co., BKO, Vill. Ghogra, Tehsil Dasuya, Distt. Hoshiarpur .

130-132

78.45 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Balagan, Tehsil Dasuya, Distt. Hoshiarpur by M/s Vipan Kumar BKO, Vill. Balagan, Tehsil Dasuya, Distt. Hoshiarpur.

133-135

78.46 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Tund, Tehsil Dasuya, Distt. Hoshiarpur by M/s Vishavkarma Brick Industry, Vill. Argowal, Tehsil Dasuya, Distt. Hoshiarpur

136-138

78.47 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Bhagroan, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Lucky Brick Kiln Industries Souna, Village & P.O. Langroya, Tehsil & Distt. District S.B.S. Nagar.

139-141

78.48 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Langroya, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Lucky Brick Kiln Industries Souna, Village & P.O. Langroya, Tehsil & Distt. District S.B.S. Nagar.

142-144

7

78.49 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Palli Jhikki, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s OPK Brick Industry, Vill. Palli Jhikki, Tehsil Nawanshahr, District S.B.S. Nagar.

145-147

78.50 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Talwandi Fattu, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Pawan Bhalla BKO, Vill. Gunachaur, Tehsil Nawanshahr, District S.B.S. Nagar.

148-150

78.51 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Soondh, Tehsil Banga, Distt. S.B.S. Nagar by M/s Sanjeev & Co. VPO, Godani, Tehsil Banga District, S.B.S. Nagar.

151-153

78.52 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Godani, Tehsil Banga, Distt. S.B.S. Nagar by M/s Sanjeev & Co. VPO, Godani, Tehsil Banga District, S.B.S. Nagar.

154-156

78.53 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Pallian Khurd, Tehsil Banga, Distt. S.B.S. Nagar by M/s Baranala Brick Kiln Industries, Vill. Barnala Kalan, Tehsil & District, S.B.S. Nagar.

157-159

78.54 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Sahiba Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Pawan Kumar BKO, Vill. Khurdan, Tehsil Balachaur, District, S.B.S. Nagar.

160-162

78.55 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Sarhala, Tehsil & Distt. Hoshiarpur by M/s Kamla Rani BKO, Vill. Sandhara, Hoshiarpur.

163-165

78.56 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Palli Jhikki, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s OP Kirpal BKO, Vill. Palli Jhikki, Tehsil & Distt. District S.B.S. Nagar.

166-168

78.57 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor

169-171

8

minerals (brick clay) in the revenue estate of Vill. Jalal Chak, Tehsil Dasuya, Distt. Hoshiarpur by M/s Sanjeev Kumar BKO, Village Balagan Tehsil Dasuya, District Hoshiarpur.

78.58 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Bohara, Tehsil Nawanshahr,Distt. S.B.S. Nagar by M/s Partapa Ram Duggal & Co. BKO, Vill. Garcha, Tehsil and Distt. S.B.S. Nagar.

172-174

78.59 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Ramrai Pur Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Baranala Brick Kiln Industries, Vill. Barnala Kalan, Tehsil & District, S.B.S. Nagar.

175-177

78.60 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Dharamkot, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s MRS Bricks, Vill. Malpur, Tehsil Nawanshahr, Distt. S.B.S. Nagar.

178-180

78.61 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Sahabpur, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Dharamvir Satish kumar BKO, Village Sanawa, Tehsil & Distt. S.B.S. Nagar.

181-183

78.62 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Jagtewal & Baggowal , Tehsil Balachaur, Distt. S.B.S. Nagar by M/s Dilbag Singh BKO, Vill. Malewal Kohlian, Tehsil Balachaur, Distt. S.B.S. Nagar.

184-186

78.63 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rasulpur Theh, Shehbazpur, & Alachaur, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s R.G. Bricks, Vill & P.O. Kulam, Tehsil & Distt. S.B.S. Nagar.

187-189

78.64 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Pharala, Tehsil & Distt. S.B.S. Nagar by M/s Bhagwati Bricks Co., Vill. Pharala, Tehsil & Distt. S.B.S. Nagar.

190-192

78.65 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor

193-195

9

minerals (brick clay) in the revenue estate of Vill. Ramgarh, Ranewal & Usmanpur , Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Anil Kumar & Son BKO, Vill. Usmanpur, Tehsil & Distt. S.B.S. Nagar.

78.66 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Sheikhupur , Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Pawan Bhalla BKO, Vill. Gunachaur, Teshil Nawanshahr, Distt. S.B.S. Nagar.

196-198

78.67 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Bohan, Tehsil & Distt. Hoshiarpur by M/s Bhole Shankar Bricks Industry, Vill. Barkia Tanoor, Tehsil & Distt. Hoshiarpur.

199-201

78.68 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Bohan, Tehsil & Distt. Hoshiarpur by M/s Surinder Singh & Bors. B.K.O., V& P.O. Changran, Tehsil & Distt. Hoshiarpur.

202-204

78.69 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Bakhlaur, Tehsil & Distt. S.B.S. Nagar by M/s Rana & Co. BKO, Vill. Mugal Kherabad & P.O. Bakhlaur, Tehsil & Distt. S.B.S. Nagar.

205-207

78.70 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Mehlanwali, Tehsil & Distt. Hoshiarpur by M/s Billa Brick Industry, Vill. Bassi Hast Khan, Tehsil & Distt. Hoshiarpur.

208-210

78.71 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Uchi Palli, Tehsil Nawanshahr Distt. S.B.S. Nagar by M/s O.P. Kirpal BKO, Palli Jhikki, Tehsil Nanwanshahr, Distt. S.B.S. Nagar.

211-213

78.72 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Kharderh, Tehsil & Distt. Hoshiarpur by M/s Billa Bricks Traders, Vill. Noorpur, Tehsil & Distt. Hoshiarpur.

214-216

78.73 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Bilaspur, Tehsil & Distt. Hoshiarpur by M/s Hari Darshan Singh BKO, Vill. Bassi Kikkran, Tehsil & Distt. Hoshiarpur.

217-219

10

78.74 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Seikhupur Bhag, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Jagdambey Brick Kiln, Village Majzara Kalan, Tehsil & Distt.S.B.S. Nagar.

220-222

78.75 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Jadla, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Jagdambey Brick Kiln, Village Majzara Kalan, Tehsil & Distt.S.B.S. Nagar.

223-225

78.76 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Kang, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Partapa Ram Duggal & Co. BKO, Vill. Garcha, Tehsil & Distt.S.B.S. Nagar.

226-228

78.77 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Atal Mazara, Tehsil Balachaur, Distt. S.B.S. Nagar by M/s Pawan Kumar BKO, Vill. Khurdan, Teshil Balachaur, Distt.S.B.S. Nagar.

229-231

11

12

Item No. 78.01 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Bilaspur, Tehsil & Distt. Hoshiarpur by M/s Santokh

Singh & Sons BKO, Village Bharta Khurad, Tehsil &

District S.B.S. Nagar.

It is submitted that M/s Santokh Singh & Sons BKO, Village Bharta

Khurad, Tehsil & District S.B.S. Nagar has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Bilaspur, Tehsil & Distt. Hoshiarpur. The

project is covered under category 1(a). The MoEF vigfde office memorandum

dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area of 1.82221 Hectares and is located in the revenue estate of Vill. Bilaspur, Tehsil & Distt. Hoshiarpur for manufacturing of bricks in the brick kiln located in the revenue estate of Village Bharta Khurad, Tehsil & District S.B.S. Nagar.

2. The mining of brick clay will be carried out at sites, the details of which are as under:

Site Hadbast No./

Khewat No.

/ Khatoni

Khasra No./ Total are of

site Lease Period

Site 1 170/189/264 24//17/2, 18, 24/1 3 years i.e. upto

08.10.2016

Site 2 170/177/245,

246

4/1, 4/10/5, 2/25/1, 11/1/1,

4/11/1/1

3 years i.e. upto

08.10.2016

Site 3 218/285/296 1//12/2, 13/2, 13/3, 14/1 3 years i.e. upto

08.10.2016

Site 4 170/ 335, 332, 333/ 454, 451, 452, 448,

449, 450

29//13/2/18//20, 21, 19//2, 3/ 8, 9, 10/2, 11/2, 12/2, 13/1, 15, 29//8/9/12/1, 3,

11/2, 12/1, 19//6, 17, 19//24, 25, 25//4, 1, 5/2, 29//3, 7//23, 1, 19//14,

23//21/2, 22/1, 23/2, 29//1, 2

3 years i.e. upto

08.10.2016

13

3. The expected cost of the project will be Rs. 6.00 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

14

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Santokh Singh & Sons BKO.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

15

Item No. 78.02 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Usmanpur, Tehsil Nawanshahr Distt. S.B.S. Nagar by

M/s Anil Kumar BKO, Vill. Soeta, Tehsil & District

S.B.S. Nagar.

It is submitted that M/s Anil Kumar BKO, Vill. Soeta, Tehsil &

District S.B.S. Nagar has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate Vill. Usmanpur, Tehsil Nawanshahr Distt. S.B.S. Nagar. The project

is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.3722 Hectares and is located in the revenue estate of Vill. Usmanpur,

Tehsil Nawanshahr Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Vill. Soeta, Tehsil & District

S.B.S. Nagar.

2. The mining of brick clay will be carried out at sites, the details of which are

as under:

Site Hadbast No./

Khewat No. / Khatoni

Khasra No./ Total are of site Lease

Period

Site 1 229/176/230 19/13, 18, 23/1 2 years i.e. upto

10.02.2015

Site 2 229/99/128 30/20/4, 21/1, 33/1/1/1 1 years i.e.

upto

02.07.2014

Site 3 229/219/292 19//14/1, 14/2/1, 17/1, 17/2/2,

24/1/1

2 years i.e.

upto

30.09.2015

3. The expected cost of the project will be Rs. 3.00 Lacs.

16

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred

17

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Anil Kumar BKO.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km of from boundary of the mining site.

Submitted a copy of letter no. 260 NS dated 30.09.213 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

18

Item No. 78.03 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Bodal, Tehsil Dasuya, Distt. Hoshiarpur by M/s Ajmer

Pal Singh BKO, Vill. Khera Kotli, P.O. Panwan, Tehsil

Dasuya, Distt. Hoshiarpur.

It is submitted that M/s Ajmer Pal Singh BKO, Vill. Khera Kotli, P.O.

Panwan, Tehsil Dasuya, Distt. Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Bodal, Tehsil Dasuya, Distt. Hoshiarpur.

The project is covered under category 1(a). The MoEF vide office memorandum

dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.5 Hectares and is located in the revenue estate of Vill. Bodal, Tehsil

Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Khera Kotli, P.O. Panwan, Tehsil

Dasuya, Distt. Hoshiarpur.

2. The mining of brick clay will be carried out at sites, the details of which are

as under:

Site Hadbast No./

Khewat No. /

Khatoni

Khasra No./ Total are of site Lease

Period

Site 1 93/815/892 1875, 1876, 1877

Total are of site= 0.5 Hectares

2 Years i.e. upto

21.08.2015

3. The expected cost of the project will be Rs. 3.50 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

19

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

c) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

d) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(g) Submitted

(h) Submitted

(i) Submitted

(j) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(k) Rs 25000/- will be incurred for implementation of EMP

20

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(l) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Ajmer Pal Singh BKO.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Both mining sites are within 01 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

21

Item No. 78.04 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Begampur, Tehsil Nawanshahr, Distt. S.B.S. Nagar by

M/s Arora Bricks Co., Village Karimpur Chahwala,

Tehsil Balachaur, Distt. S.B.S. Nagar.

It is submitted that M/s Arora Bricks Co., Village Karimpur

Chahwala, Tehsil Balachaur, Distt. S.B.S. Nagar has applied for obtaining

environmental clearance under EIA notification dated 14.09.2006 for mining of

minor minerals (brick clay) in the revenue estate Vill. Begampur, Tehsil

Nawanshahr, Distt. S.B.S. Nagar. The project is covered under category 1(a).

The MoEF vide office memorandum dated 24.06.2013 categorized the mining of

brick earth/clay as category B-2 for appraisal of the project proposal under EIA

Notification dated 14.06.2006. The details of the project proposal as per Form 1

and pre-feasibility report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.9319 Hectares out of which 1 site is 0.506 Hect and 2 site is 1.4259

Hectare and is located in the revenue estate of Vill. Begampur, Tehsil

Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Village Karimpur Chahwala,

Tehsil Balachaur, Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at two

sites, the details of which are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 244/322/420 28//12/2, 13 03.10.2013 to

02.09.2015

Site 2 244/255,259/314, 305

14//4, 5, 7, 8 03.10.2013 to

02.10.2015

3. The expected cost of the project will be Rs. 4.20 Lacs.

The other details of the project are as under:

22

1 Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

23

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Arora Bricks Co.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1258 dated 03.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km. from Balachaur Tehsil.

9. Mining site located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Both mining site within 1 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

Item No. 78.05 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Badallian, Tehsil Mukerian, Distt. Hoshiarpur by M/s

24

Baba Beant Brick Mfg. Industry, Vill. Badalian Distt.

Hoshiarpur.

It is submitted that M/s Baba Beant Brick Mfg. Industry, Vill.

Badalian Distt. Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Badallian, Tehsil Mukerian, Distt. Hoshiarpur. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 17 Kanal 17 Marlas and is located in the revenue estate of Vill.

Badallian, Tehsil Mukerian, Distt. Hoshiarpur for manufacturing of bricks in

the brick kiln located in the revenue estate of Vill. Badallian, Tehsil

Mukerian, Distt. Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./

Khewat No/

Khatoni

No.

Khasra No./ Total area of site Lease

Period

Site 1 360/15/24 3/116, Total area of site = 7 Kanal

17 Marlas

2 Years i.e.

upto

15.06.2015

3. The expected cost of the project will be Rs. 5.00 lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

25

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 25000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

26

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Baba Beant Brick Manf. Industry.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Mukerian, Dasuya & Hazipur of Distt. Hoshiarpur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

27

Item No. 78.06: Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Rakasan, Tehsil Nawanshahr, Distt. S.B.S. Nagar by

M/s Bajaj Brick Co., Vill. Rurki Khurd, Tehsil

Balachaur, Distt. S.B.S. Nagar.

It is submitted that M/s Bajaj Brick Co., Vill. Rurki Khurd, Tehsil

Balachaur, Distt. S.B.S. Nagar has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Rakasan, Tehsil Nawanshahr, Distt. S.B.S. Nagar.

The project is covered under category 1(a). The MoEF vide office memorandum

dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.4048 Hectares is located in the revenue estate of Vill. Rakasan, Tehsil

Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the brick

kiln located in the revenue estate of Vill. Rurki Khurd, Tehsil Balachaur,

Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 240/4/5 7//7

Total area of site = 0.4048

Hect.

30.07.2012 Till

extraction

3. The expected cost of the project will be Rs. 1.40 Lacs.

The other details of the project are as under:

1. Properly filled Form 1 & Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

28

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

c) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

d) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(g) Submitted

(h) Submitted

(i) Submitted

(j) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(k) Rs 50000/- will be incurred for implementation of EMP

(l) Farmer will be

29

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Bajaj Brick Co.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Nawanshahar Range

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

30

Item No. 78.07 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Badla, Tehsil Dasuya, Distt. Hoshiarpur by M/s Balaji

Brick Industry, Vill. Sahu Da Pind, Tehsil Dasuya,

Distt. Hosharpur.

It is submitted that M/s Balaji Brick Industry, Vill. Sahu Da Pind,

Tehsil Dasuya, Distt. Hosharpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Badla, Tehsil Dasuya, Distt. Hoshiarpur .

The project is covered under category 1(a). The MoEF vide office memorandum

dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.2140 Hectare and is located in the revenue estate of Vill. Badla, Tehsil

Dasuya, Distt. Hoshiarpur, for manufacturing of bricks in the brick kiln

located in the revenue estate of by Vill. Badla, Tehsil Dasuya, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoni No.

Khasra No./ Total area

of Site

Lease

Period

Site 1 626/1134,173/

1532, 217

74/15/2, 75//10/2, 75/11,

75/20.

Total area of Site =1.2140 Hectare

4 Years i.e. upto

31.03.2017

3. The expected cost of the project will be Rs. 5.40 lacs.

The other details of the project are as under:

1.

Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

31

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Not Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

to take care of the land after the expiry of the lease period.

32

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Balaji Brick Industry.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Mukerian, Dasuya & Hazipur of Distt. Hoshiarpur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

33

Item No. 78.08 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

jandiali, Tehsil Banga & Distt. S.B.S. Nagar by M/s

Baldev Singh Gurdeep Singh B.K.O., Vill. Jandialai,

Distt. S.B.S. Nagar.

It is submitted that M/s Baldev Singh Gurdeep Singh B.K.O., Vill.

Jandialai, Distt. S.B.S. Nagar. has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. jandiali, Tehsil Banga & Distt. S.B.S. Nagar. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 3.74 Hectares is located in the revenue estate of Vill. jandiali, Tehsil

Banga & Distt. S.B.S. Nagar for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Jandialai, Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of site Lease

Period

Site 1 2/270/318 39/14/, 39/15/1, 39//16/2 Ownership

Site 2 2/58/70 25//23/2/1, 32//3/2, Ownership

Site 3 2/92/87 32//13/2, 32//14/2, 32//17,

32//18

Total area of Site = 3.94

Hect.

Ownership

3. The expected cost of the project will be Rs. 15.00 Lacs.

The other details of the project are as under:

34

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 100000/- will be incurred for implementation of EMP

35

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? The project proponent shall submit an undertaking to the effect submit an undertaking to the effect that the total area of all borrowing / excavation sites including the area of the propose project within the radius of 500 m from the proposed area of borrowing/ excavation is less

than 5 hectares

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Baldev Singh Gurdeep Singh B.K.O.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Nawanshahar Range

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Application

The matter is placed before the SEAC for its consideration, please.

36

Item No. 78.09 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Rahon, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s

Davinder Kumar & Sons, Village Rahon Tehsil & Distt.

S.B.S. Nagar.

It is submitted that M/s Davinder Kumar & Sons, Village Rahon

Tehsil & Distt. S.B.S. Nagar has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Pallian Khurd, Tehsil Nawanshahr, Distt. S.B.S.

Nagar. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 2.2829 Hectares out of which 1 site is 1.01150 hectares , 2 Site is

0.8102 hectares, 3 Site is 0.2589 hectares, 4 site is 0.2023 hectares and

is located in the revenue estate of Vill. Rahon, Tehsil Nawanshahr, Distt.

S.B.S. Nagar for manufacturing of bricks in the brick kiln located in the

revenue estate of Village Rahon Tehsil & Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at four

sites, the details of which are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 223/75,519, 520, 36 /77,565, 566,

144

57//6/2, 16/1, 6/1/2, 15/1, 58/11, 19/4, 20/1, 32//21,

21/1, 58/1, 2, 9, 10/1

3 years i.e. upto

08.10.2016

Site 2 223/105, 106/1129, 1142

63//25/1, 62//21/1, 62//19, 20/1

Ownership

Site 3 63//16/1, 62//20/2, Ownership

Site 4 63//16/1, 62//20/2

Total area of both sites= 2.2829 Hectares

Ownership

37

3. The expected cost of the project will be Rs. 6.00

Lacs.

The other details of the project are as under:

1. Properly filled Form 1 & Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

38

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? The project proponent shall submit an undertaking to the effect submit an undertaking to the effect that the total area of all borrowing / excavation sites including the area of the propose project within the radius of 500 m from the proposed area of borrowing/ excavation is less

than 5 hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Davinder Kumar & Sons BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Nawanshahar Range

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

39

Item No. 78.10 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Ittian Tehsil Mukerian, Distt. Hoshiarpur by M/s Dev

Ichha & Co., BKO, Namoli , Tehsil Mukerian, Distt.

Hoshiarpur .

It is submitted that M/s Dev Ichha & Co., BKO, Namoli , Tehsil

Mukerian, Distt. Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Ittian Tehsil Mukerian, Distt. Hoshiarpur. The project

is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.0829 Hectares and is located in the revenue estate of Vill. Ittian Tehsil

Mukerian, Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of Village Namoli, Tehsil Dasuya, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at two sites, the details of which are as under:

Site Hadbast No./Khewat No./ Khatoni

No.

Khasra No./ Total area of site Lease Period

Site 1 229/45,124

/59,154

19//5, 19/6, 19//4/1,19//7/2/1. Total area of site = 1.0829

Hectares

27.09.2013 to

26.09.2014

3. The expected cost of the project will be Rs. 4.15 Lacs.

The other details of the project are as under:

1. Properly filled Form 1 Submitted

2. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

40

3. Proof of ownership of land/ Registered Lease

deed of mining area

Submitted

4. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

5. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

6. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

7. Environmental Management Plan indicating

the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the project

proponent will be responsible for

implementation of EMP and the

name of the person(s) responsible

for implementation of EMP.

e) Capital & recurring cost for the EMP

per year and the details of funds for

the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease

41

EMP after the lapse of the period for

which the project proponent is

responsible.

period.

8. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Dev Ichha & Co.

9. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km of from

boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

The matter is placed before the SEAC for its consideration, please.

42

Item No. 78.11 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Meharpatoli, Tehsil Dasuya, Distt. Hoshiarpur by M/s

Dhir Brick Industry , Vill. Gagjalo, Tehsil Dasuya, Distt.

Hoshiarpur.

It is submitted that M/s Dhir Brick Industry , Vill. Gagjalo, Tehsil

Dasuya, Distt. Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Meharpatoli, Tehsil Dasuya, Distt. Hoshiarpur. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.4 Heactares and is located in the revenue estate of Vill. Meharpatoli,

Tehsil Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick

kiln located in the revenue estate of Vill. Gagjalo, Tehsil Dasuya, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No/

Khatoni No.

Khasra No./ Total

area of site Lease Period

Site 1 177/156/194 6/20, 19

Total area of site = 0.4

Hectares

2 Years i.e.

26.09.2015

3. The expected cost of the project will be Rs. 4.00 Lacs.

The other details of the project are as under:

1. Properly filled Form 1 & Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

43

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 25000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

44

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Dhir Brick Industry.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

45

Item No. 78.12 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Badla, Tehsil Dasuya, Distt. Hoshiarpur by M/s Dhir

Brick Kiln , Vill. Badla, Tehsil Dasuya, Distt.

Hoshiarpur.

It is submitted that M/s Dhir Brick Kiln , Vill. Badla, Tehsil Dasuya,

Distt. Hoshiarpur has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Badla, Tehsil Dasuya, Distt. Hoshiarpur. The project is

covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.4 Hectares and is located in the revenue estate of Vill. Badla, Tehsil

Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Badla, Tehsil Dasuya, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at two

sites, the details of which are as under:

Site Hadbast No./ Khewat No/

Khatoni

Khasra No./ Total

area of Site Lease Period

Site 1 628/1106/1492 56/6. Total area of site =

0.4 Hectares

2 Years i.e. upto

26.09.2015

3. The expected cost of the project will be Rs. 5.00

Lacs.

The other details of the project are as under:

1. Properly filled Form 1 Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Submitted

3. Proof of ownership of land/ Registered Submitted

46

Lease deed of mining area

4. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

5. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

6. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

7. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 25000/- will be incurred for implementation of EMP

47

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

8. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Dhir Brick Kiln.

9. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

The matter is placed before the SEAC for its consideration, please.

48

Item No. 78.13 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Pallian Khurd, Tehsil Nawanshahr, Distt. S.B.S. Nagar

by M/s K.C. Bricks, Village Rahon, Tehsil & Distt.

S.B.S. Nagar.

It is submitted that M/s K.C. Bricks, Village Rahon, Tehsil & Distt.

S.B.S. Nagar. has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Village Rahon, Tehsil & Distt. S.B.S. Nagar. The project is

covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.63 Hectares out of which 1 site is 1.01959 hectares , 2 Site is 0.4046

hectares, 3 Site is 0.2114 hectares and is located in the revenue estate of

Vill. Pallian Khurd, Tehsil Nawanshahr, Distt. S.B.S. Nagar for

manufacturing of bricks in the brick kiln located in the revenue estate of

Village Rahon, Tehsil & Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 225/271/372,377,

378, 381

43//1/1, 13/8/2, 22//19/2, 6//24, 13/7/2, 13/3/1,

14/1/, 14/2, 18/1, 6//17/1,

17/2, 7//4 Min, 4 Min

3 years i.e. upto

09.10.2016

Site 2 5//12/2, 13/1, 14/1 3 years i.e.

upto

09.10.2016

Site 3 5//1, 12/3, 13/1, 14/1 3 years i.e.

upto

49

09.10.2016

3. The expected cost of the project will be Rs. 6.00 Lacs.

The other details of the project are as under:

1. Properly filled Form 1 & Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

50

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s K.C. Bricks.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Nawanshahar Range

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

51

Item No. 78.14 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Rasulpur (Seota) & Usmanpur, Tehsil Nawanshar,

Distt. S.B.S. Nagar by M/s K.K. Khosla Brick Industry

BKO, Vill. Rasulpur (Seota), Tehsil & Distt. S.B.S. Nagar.

It is submitted that M/s K.K. Khosla Brick Industry BKO, Vill.

Rasulpur (Seota), Tehsil & Distt. S.B.S. Nagar has applied for obtaining

environmental clearance under EIA notification dated 14.09.2006 for mining of

minor minerals (brick clay) in the revenue estate of Vill. Rasulpur (Seota) &

Usmanpur, Tehsil Nawanshar, Distt. S.B.S. Nagar. The project is covered under

category 1(a). The MoEF vide office memorandum dated 24.06.2013 categorized

the mining of brick earth/clay as category B-2 for appraisal of the project proposal

under EIA Notification dated 14.06.2006. The details of the project proposal as

per Form 1 and pre-feasibility report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.64082Hectares out of which 1 site is 0.1987 hectares , 2 Site is 0.4421

hectares and is located in the revenue estate of Vill. Rasulpur (Seota) &

Usmanpur, Tehsil Nawanshar, Distt. S.B.S. Nagar for manufacturing of

bricks in the brick kiln located in the revenue estate of Vill. Rasulpur

(Seota), Tehsil & Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 230/39/52 22//20

Total area of site =0.1987

hectares

2 Years i.e. upto

06.05.2015

Site 2 230/84/115 9//24/2, 22/3/2, 22//4

Total area of site =.4421

hectares

2 Years i.e. upto

06.09.2015

3. The expected cost of the project will be Rs. 4.92 Lacs.

52

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

c) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

d) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred

53

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? The project proponent shall submit an undertaking to the effect submit an undertaking to the effect that the total area of all borrowing / excavation sites including the area of the propose project within the radius of 500 m from the proposed area of borrowing/ excavation is less

than 5 hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s K.K. Khosla Brick Industry.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Nawanshahar Range

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

54

Item No. 78.15 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill. Kot

Ranjha, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s

Kamla Rani BKO, Village Musapur, Tehsil & Distt.

S.B.S. Nagar.

It is submitted that M/s Kamla Rani BKO, Village Musapur, Tehsil &

Distt. S.B.S. Nagar has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Kot Ranjha, Tehsil Nawanshahr, Distt. S.B.S. Nagar. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.4046 Hectares is located in the revenue estate of Vill. Kot Ranjha,

Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Village Mussapur, Tehsil & Distt.

S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./ Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 224/60,61/88, 99, 93, 98

18//9/2, 10/2, 11, 12/1, 12/2, 19/1, 20/1, 19//14/3, 15/1, 15/2, 16/1, 17/1/1,

17/2/1

3 years i.e. upto

09.10.2016

3. The expected cost of the project will be Rs. 1.15 Lacs.

The other details of the project are as under:

1. Properly filled Form 1 & Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

55

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

56

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Kamla Rani BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Nawanshahar Range

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

57

Item No. 78.16 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Musapur, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s Kamla Rani BKO, Village Musapur, Tehsil & Distt.

S.B.S. Nagar.

It is submitted that M/s Kamla Rani BKO, Village Musapur, Tehsil & Distt. S.B.S. Nagar has applied for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Musapur, Tehsil Nawanshahr, Distt. S.B.S. Nagar. The project is covered under category 1(a). The MoEF vide office memorandum dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for appraisal of the project proposal under EIA Notification dated 14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area of 3.1948 Hectares out of which 1 site is 0.5649 hectares, 2 site is 1.8207 hectares and 3 is 0.8092 hectares is located in the revenue estate of Vill. Musapur , Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the brick kiln located in the revenue estate of Village Mussapur, Tehsil & Distt. S.B.S. Nagar. The industry has also submitted undertaking that the Environmental clearance is being sought for site No. 1,2, & 5 and the distance between these three site is less than 01 km.

2. The mining of brick clay will be carried out at three sites, the details of

which are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of site Lease

Period

Site 1 116/613/770 1841, 1842, 3299,/1844, 1849, 1900, 1850, 1851

Ownership

Site 2 116/109,404, 479, 633,638 , 832 /144, 398, 605, 606, 608, 609, 794,

801, 1022

2111/1, 319, 315, 316, 317, 318, 322, 323, 433, 433, 432, 1911,

316, 2/1912, 1919, 1920, 1906/4, 2493, 1908/3, 321, 1910, 1921, 1931, 320, 2492, 1909, 1907/2,

1908/1, 2174/4, 2497, 2498, 2509, 2514, 2223, 2496, 2511, 2512,

2510, 2517/2, 2519, 2518, 2201, 2212, 2135, 2206, 2207, 2208,

2211, 2213, 2219, 2214

2 years i.e. upto

14.10.2013

Site 3 116/151/478 383/478, 151/191, 407, 408, 1460, Ownership

58

1417, 1458, 1459 Total area of both site = 3.1948

Hectare

3. The expected cost of the project will be Rs. 5.90 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of emergency such as accidents at

the site including fire.

d) For how long period the project proponent will be responsible for implementation

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

59

of EMP and the name of the person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the EMP per year and the details of

funds for the same.

f) Name of the individual persons / organization, who will be responsible for implementation of EMP after the lapse of the period for which the project proponent

is responsible.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Kamla Rani BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Nawanshahar Range

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Both mining sites are within 01 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

60

Item No. 78.17 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Mallpur, Tehsil Nawanshahr, Distt. S.B.S. Nagar by

M/s Kamla Rani BKO, Village Musapur, Tehsil & Distt.

S.B.S. Nagar.

It is submitted that M/s Kamla Rani BKO, Village Musapur, Tehsil &

Distt. S.B.S. Nagar has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Mallpur, Tehsil Nawanshahr, Distt. S.B.S. Nagar. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.4046 Hectares is located in the revenue estate of Vill. Mallpur, Tehsil

Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the brick

kiln located in the revenue estate of Village Mussapur, Tehsil & Distt. S.B.S.

Nagar.

2. The mining of brick clay will be carried out at site,

the details of which are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 170/176/244 12//23/3, 15//3/1, 85//3,

86//1, 24//23, 24/2

1½ years upto 14.05.2015

3. The expected cost of the project will be Rs. 1.15

Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

61

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of

62

for which the project proponent

is responsible.

the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Kamla Rani BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Nawanshahar Range

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

63

Item No. 78.18: Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rasulpur & Usmanpur, Tehsil Nawanshar, Distt. S.B.S. Nagar by M/s Kewal Kirshan Khosla BKO, Vill. Soeta,

Tehsil & Distt. S.B.S. Nagar.

It is submitted that M/s Kewal Kirshan Khosla BKO, Vill. Soeta, Tehsil & Distt. S.B.S. Nagar has applied for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rasulpur & Usmanpur, Tehsil Nawanshar, Distt. S.B.S. Nagar. The project is covered under category 1(a). The MoEF vide office memorandum dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for appraisal of the project proposal under EIA Notification dated 14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area of 2.73466 Hectares out of which 1 site is 0.7948 hectares , 2 Site is 0.8295 hectares and 3 site is 1.1102 hectares and is located in the revenue estate of Vill. Rasulpur & Usmanpur, Tehsil Nawanshar, Distt. S.B.S. Nagar for manufacturing of bricks in the brick kiln located in the revenue estate of Vill. Soeta, Tehsil & Distt. S.B.S. Nagar

2. The mining of brick clay will be carried out at three sites, the details of which are as under:

Site Hadbast No./ Khewat No./ Khatoi No.

Khasra No./ total area of site Lease

Period

Site 1 230/14/19 55/6, 54/10, 54/15, 16, 17/2, 25/1, 24/1, 19//6/2

Total area of site =0.7948

hectares

28.1.2010 to till

extraction

Site 2 229/529/661 14/2/2, 6/2, 19/15, 16, 17/2,

25/1, 24/1, 19//6/2

Total area of site =0.8295

hectares

05.12.2008 to till

extraction

Site 3 230/7/8 21/11, 12/1, 19/2, 20, 55/16

Total area of site = 1.1102

hectares

26.08.2011 to till

extraction

3. The expected cost of the project will be Rs. 4.91 Lacs.

64

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of emergency such as accidents at

the site including fire.

d) For how long period the project proponent will be responsible for implementation of EMP and the name of the person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

to take care of the land

65

f) Name of the individual persons / organization, who will be responsible for implementation of EMP after the lapse of the period for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? The project proponent shall submit an undertaking to the effect submit an undertaking to the effect that the total area of all borrowing / excavation sites including the area of the propose project within the radius of 500 m from the proposed area of borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Kewal Krishan Khosla BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Nawanshahar Range

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA notification dated 14.09.2013.

Both mining sites are within 01 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

66

Item No. 78.19 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Daffar, Tehsil Dasuya, Distt. Hoshiarpur by M/s Kiran

Bala B.K.O., Vill. Daffar, Tehsil Dasuya, Distt.

Hoshiarpur.

It is submitted that M/s Kiran Bala B.K.O., Vill. Daffar, Tehsil

Dasuya, Distt. Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Daffar, Tehsil Dasuya, Distt. Hoshiarpur. The project

is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 3.75 Acres and is located in the revenue estate of Vill. Daffar, Tehsil

Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Daffar, Tehsil Dasuya, Distt.

Hoshiarpur

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ Total

area of site

Lease

Period

Site 1 1/172/205 69//13/2, 69/14, 69/17, 69/18,

59//23/1

Half self own & half on lease.

Upto

26.09.2018

3. The expected cost of the project will be Rs. 4.96 Lacs.

The other details of the project are as under:

1

Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

67

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of emergency such as accidents at

the site including fire.

d) For how long period the project proponent will be responsible for implementation of EMP and the name of the person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the EMP per year and the details of

funds for the same.

f) Name of the individual persons / organization, who will be responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

68

EMP after the lapse of the period for which the project proponent

is responsible.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? The project proponent shall submit an undertaking to the effect submit an undertaking to the effect that the total area of all borrowing / excavation sites including the area of the propose project within the radius of 500 m from the proposed area of borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Kiran Kumar BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

69

Item No. 78.20 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Mehlanwali, Tehsil & Distt. Hoshiarpur by M/s Kirit

Kiran Birck Industry, Vill. Mehatpur, Distt. Hoshiarpur.

It is submitted that M/s Kirit Kiran Birck Industry, Vill. Mehatpur, Distt. Hoshiarpur has applied for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Mehlanwali, Tehsil & Distt. Hoshiarpur. The project is covered under category 1(a). The MoEF vide office memorandum dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for appraisal of the project proposal under EIA Notification dated 14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area of 0.8097 Hectares and both sites area are located in the revenue estate

of Vill. Mehlanwali, Tehsil & Distt. Hoshiarpur for manufacturing of bricks in the brick kiln located in the revenue estate of Vill. Mehatpur, Tehsil & Distt. Hoshiarpur.

2. The mining of brick clay will be carried out at two sites, the details of which are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ Total area of site

Lease Period

Site 1 344/213,511, 799, 941 /264, 519,

725, 1173

37//16/1, 43//19/1, 19/2/1, 20/1, 20/4, 20/5, 21/1/2, 22/1, 60//1/1, 43//20/3,

20/1, 20/2, 21/1/1, 21/2/1,1, 22/1/1/1, 22/1/2/1, 43//5/1, 19/2/2, 20/2, 20/6, 21/1/1, 21/2, 61//4/2/1, 7/1/2, 8/2,

9/2, 12/1, 62//14/2/1

24.02.2011 to

31.12.2016

Site 2 62//8/1, 8/2/1, 3/3

Total area of both sites = 0.8097 Hectares

18.05.2009 to

17.12.2015

3. The expected cost of the project will be Rs. 5.00 Lacs.

The other details of the project are as under:

1.

Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

70

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of emergency such as accidents at

the site including fire.

d) For how long period the project proponent will be responsible for implementation of EMP and the name of the person(s) responsible for implementation of EMP.

e) Capital & recurring cost for the EMP per year and the details of

funds for the same.

f) Name of the individual persons / organization, who will be responsible for implementation of EMP after the lapse of the period for which the project proponent

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 25000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

71

is responsible.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? The project proponent shall submit an undertaking to the effect submit an undertaking to the effect that the total area of all borrowing / excavation sites including the area of the propose project within the radius of 500 m from the proposed area of borrowing/ excavation is less than 5

hectares

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Kirit Kiran Birck Industry

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1262 dated 03.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife w i t h in 01 Km. from proposed site.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Both mining area within 01 km. periphery.

The matter is placed before the SEAC for its consideration, please.

72

Item No. 78.21 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Passi Kandi, Tehsil Dasuya, Distt. Hoshiarpur by M/s

Krishan Kumar BKO, Vill. Thiara, Distt. Hoshiarpur.

It is submitted that M/s Krishan Kumar BKO, Vill. Thiara, Distt.

Hoshiarpur has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Passi Kandi, Tehsil Dasuya, Distt. Hoshiarpur. The project is

covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.3974 Hectare and is located in the revenue estate of Vill. Passi Kandi

Tehsil Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick

kiln located in the revenue estate of Vill. Thiara, Tehsil Dasuya, Distt.

Hoshiarpur

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./Khewat

No./

Khatoni No.

Khasra No./ Total area of site Lease Period

Site 1 159/ 169/233 15//17. Total area of site =

0.3974

30.09.2013 to

29.09.2018

3. The expected cost of the project will be Rs. 5.25 Lacs.

The other details of the project are as under:

1.

Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

73

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

74

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Krishan Kumar BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

75

Item No. 78.22 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Bassi Gulam Hussain, Tehsil Dasuya, Distt. Hoshiarpur

by M/s Kundan Lal Murghai BKO, Vill. Adamwal,

Tehsil & Distt. Hoshiarpur

It is submitted that M/s Kundan Lal Murghai BKO, Vill. Adamwal,

Tehsil & Distt. Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Bassi Gulam Hussain, Tehsil Dasuya, Distt.

Hoshiarpur. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 2 Acres and is located in the revenue estate of Vill. Bassi Gulam Hussain,

Tehsil Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick

kiln located in the revenue estate of Vill. Adamwal, Tehsil & Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./ Khatoi

No.

Khasra No./ Total area

of site

Lease

Period

Site 1 362/95/103 9/15/1/2, 7/2, 6/3, 7/2/2 Total area of site = 0.198

Hect.

3 years i.e. upto

04.08.2016

3. The expected cost of the project will be Rs. 3.80 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

76

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 10000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

77

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Kundan Lal Murghai.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

78

Item No. 78.23 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Rahon, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s

Laroiya Brick Kiln, Village Chhokran, Tehsil & Distt.

S.B.S. Nagar.

It is submitted that M/s Laroiya Brick Kiln, Village Chhokran, Tehsil

& Distt. S.B.S. Nagar has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Rahon, Tehsil Nawanshahr, Distt. S.B.S. Nagar. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.01 Hectares is located in the revenue estate of Vill. Rahon, Tehsil

Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the brick

kiln located in the revenue estate of Village Chhokran, Tehsil & Distt.

S.B.S. Nagar.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 223/518/564 57//6/2, 16/1, 6/1/2, 58//11, 19/4, 20/1, 32//21, 21/1,

58/1, 2, 9, 10/1

Total area of site = 1.01

Hect.

10.11.2011 till

extraction

3. The expected cost of the project will be Rs. 3.00 Lacs.

The other details of the project are as under:

79

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

80

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Laroiya Brick Kiln.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Nawanshahar Range

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Both mining sites are within 1 Km. periphery

The matter is placed before the SEAC for its consideration, please.

81

Item No. 78.24 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Rasulpur, Sahwajpur, Chhokran, Kotranja, Tehsil

Nawanshar, Distt. S.B.S. Nagar by M/s Loriya Brick

Kiln, Vill. Chhokran, Tehsil & Distt. S.B.S. Nagar.

It is submitted that M/s K.K. Khosla Brick Industry BKO, Vill. Rasulpur (Seota), Tehsil & Distt. S.B.S. Nagar has applied for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Rasulpur, Sahwajpur, Chhokran, Kotranja, Tehsil Nawanshar. The project is covered under category 1(a). The MoEF vide office memorandum dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for appraisal of the project proposal under EIA Notification dated 14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area of 1.40 Hectares out of which 1 site is 0.6069 hectares , 2 Site is 0.8092 hectares and is located in the revenue estate of Vill. Rasulpur, Sahwajpur, Chhokran, Kotranja, Tehsil Nawanshar for manufacturing of bricks in the brick kiln located in the revenue estate of Vill. Chhokran, Tehsil & Distt. S.B.S. Nagar. Earlier the industry has applied for 4 Number mining site and has now submitted undertaking that the Environmental Clearance is being sought for site No. 1 & 2 and distance between these 2 sites is less than 01 Km.

2. The mining of brick clay will be carried out at two sites, the details of which are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 230/105/140 54/12, 13/1, 18/3

Total area of site = 0.6069

hec.

1 Year i.e upto

30.03.2014

Site 2 227/1/2,1 1855/514/1, 518/1, 711, 1856/508, 1857/503, 1858/502, 1859/721

Total area of site = 0.8092

4 Years i.e. upto

05.07.2015

3. The expected cost of the project will be Rs. 7.10 Lacs.

The other details of the project are as under:

82

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan indicating the following:

e) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

f) Compliance of various environmental regulations.

c) Steps to be taken in case of emergency such as accidents at

the site including fire.

d) For how long period the project proponent will be responsible for implementation of EMP and the name of the person(s) responsible for implementation of EMP.

e) Capital & recurring cost for the EMP per year and the details of

funds for the same.

f) Name of the individual persons / organization, who will be

(m) Submitted

(n) Submitted

(o) Submitted

(p) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(q) Rs 50000/- will be incurred for implementation of EMP

(r) Farmer will be

responsible to take care of

83

responsible for implementation of EMP after the lapse of the period for which the project proponent is responsible.

the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? The project proponent shall submit an undertaking to the effect submit an undertaking to the effect that the total area of all borrowing / excavation sites including the area of the propose project within the radius of 500 m from the proposed area of borrowing/ excavation is less than 5

hectares

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Laroiya Brick Kiln.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Nawanshahar Range

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013.

Both mining sites are within periphery.

The matter is placed before the SEAC for its consideration, please.

84

Item No. 78.25 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Jugial Tehsil Dasuya, Distt. Hoshiarpur by M/s Laxmi

Brick Industry, Vill. Jugial, Tehsil Dasuya, Distt.

Hoshiarpur.

It is submitted that M/s Laxmi Brick Industry, Vill. Jugial, Tehsil

Dasuya, Distt. Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Jugial, Tehsil Dasuya, Distt. Hoshiarpur. The project

is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 4 Acre 1 Kanal 17 Marlas and is located in the revenue estate of Vill.

Jugial, Tehsil Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the

brick kiln located in the revenue estate of Vill. Jugial, Tehsil Dasuya, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at two

sites, the details of which are as under:

Site Hadbast No./Khewat No./ Khatoni

No.

Khasra No./ Total area of

site

Lease

Period

Site 1 369/60,139,201, 665/ 92,179,

242, 626

9//60/2, 9//6, 9//89/3, 9//120, 9//121, 9//121/2, 9//136,

9//1139/1, 9//141/2, 9//174, 9//175, 9//117, 9//134, 9//135, 9//138, 9//181, 9//1671/13/9/2,

9//117.

Total area of site = 4 Acre 1 Kanal 17 Marlas

Self owned

land

85

3. The expected cost of the project will be Rs. 7.55

Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

86

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Laxmi Birck Industry.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

The matter is placed before the SEAC for its consideration, please.

87

88

Item No. 78.26 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Thiarray, Tehsil Dasuya, Distt. Hoshiarpur by M/s

National Co-Operative Brick Kiln Industry, Vill. Dagan,

Tehsil Mukerian, Distt. Hoshiarpur.

It is submitted that M/s National Co-Operative Brick Kiln Industry,

Vill. Dagan, Tehsil Mukerian, Distt. Hoshiarpur has applied for obtaining

environmental clearance under EIA notification dated 14.09.2006 for mining of

minor minerals (brick clay) in the revenue estate of Vill. Thiarray, Tehsil Dasuya,

Distt. Hoshiarpur. The project is covered under category 1(a). The MoEF vide

office memorandum dated 24.06.2013 categorized the mining of brick earth/clay

as category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.62 Hectares and is located in the revenue estate of Vill. Thiarray,

Tehsil Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick

kiln located in the revenue estate of , Vill. Dagan, Tehsil Mukerian, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./Khewat

No./

Khatoni No.

Khasra No./ Total area of site Lease

Period

Site 1 169/46/57 9//1, 9//2, 9//9, 9//10. Total are

of site = 1.62 Hectares

1 Year i.e. upto

25.09.2014

3. The expected cost of the project will be Rs. 2.91 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

89

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 25000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

90

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s National Co-Operative Brick Kiln Industry

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

91

Item No. 78.27 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Mehmdowal, Tehsil Garhsnkar, Distt. Hoshiarpur by

M/s Parshotam Lal Bali BKO, Kaharpur, Tehsil

Garhshanar, Distt. Hoshiarpur

It is submitted that M/s Parshotam Lal Bali BKO, Kaharpur, Tehsil

Garhshanar, Distt. Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Mehmdowal, Tehsil Garhsnkar, Distt. Hoshiarpur. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.3477 Hectare and is located in the revenue estate of Vill. Mehmdowal,

Tehsil Garhsnkar, Distt. Hoshiarpur for manufacturing of bricks in the brick

kiln located in the revenue estate of Kaharpur, Tehsil Garhshanar, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ Total area

of site

Lease

Period

Site 1 320/33/39 9//16/1/18, 17/3 Total area of site = 0.3477

Hectare.

2 years i.e. upto

03.10.2015

3. The expected cost of the project will be Rs. 1.51 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

92

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 25000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

93

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Parshotam Lal Bali BKO

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1233 dated 03.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 KM.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

94

Item No. 78.28 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Railli, Tehsil Mukerian, Distt. Hoshiarpur by M/s

Pawan Kumar BKO, Village Chak Bhian, Tehsil

Mukerian, Hoshiarpur.

It is submitted that M/s Pawan Kumar BKO, Village Chak Bhian,

Tehsil Mukerian, Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Railli, Tehsil Mukerian, Distt. Hoshiarpur . The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.25 Hectares and is located in the revenue estate of Vill. Railli, Tehsil

Mukerian, Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of , Village Chak Bhian, Tehsil Mukerian,

Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./Khewat No./ Khatoni

No.

Khasra No./ Total site of area Lease

Period

Site 1 365/194/255 26//12, 20/2 1.5 Years i.e. upto

01.01.2015

3. The expected cost of the project will be Rs. 3.50 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

95

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 25000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

96

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Pawan Kumar BKO

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

97

Item No. 78.29 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Lalota, Tehsil Mukerian, Distt. Hoshiarpur by M/s

Pawan Kumar Surinder Kumar BKO, Vill. Lalota, Tehsil

Mukerian, Distt. Hoshiarpur.

It is submitted that M/s Pawan Kumar Surinder Kumar BKO, Vill.

Lalota, Tehsil Mukerian, Distt. Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Lalota, Tehsil Mukerian, Distt.

Hoshiarpur. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1 Acre 15 Kanal 13 Marlas and is located in the revenue estate of Vill.

Lalota, Tehsil Mukerian, Distt. Hoshiarpur for manufacturing of bricks in

the brick kiln located in the revenue estate of Vill. Lalota, Tehsil Mukerian,

Distt. Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat

No./ Khatoi No.

Khasra No./ Total

area of site

Lease

Period

Site 1 377/78,36/87,42 1567, 1568

Total Area of site 1 Acre 15 Kanal 13

Marlas

5 Years i.e. upto

26.09.2018

3. The expected cost of the project will be Rs. 3.50 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

98

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

99

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Pawan Kumar Surinder Kumar BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

100

Item No. 78.30 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Ittian & Rally Tehsil Dasuya, Distt. Hoshiarpur by M/s

Pooja Bricks Mfg. Industry, Village Talwara, Tehsil

Mukerian, Distt. Hoshiarpur.

It is submitted that M/s Pooja Bricks Mfg. Industry, Village Talwara,

Tehsil Mukerian, Distt. Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Ittian & Rally Tehsil Dasuya, Distt.

Hoshiarpur. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 2.10 Hectares out of which 1 site is 0.636 hectares and 2 site is 1.466

hectares and is located in the revenue estate of Vill. Ittian & Rally Tehsil

Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of Village Talwara, Tehsil Mukerian, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at two sites, the details of which are as under:

Site Hadbast No./Khewat

No./

Khatoni No.

Khasra No./ Total area of site Lease

Period

Site 1 365/98/137 31//17, 31//18/1, 31//23/2, 31//24, 30//3/2, 30//3/3. Total

area of site = 0.636 hectares

27.09.2013 to

26.09.2014

Site 2 223/123/15 19//13/1/3, 19//18/2, 19//19, 19//7/2/2, 19//8/1, 19//13/1/1

Total area of site = 1.466

hectares

27.09.2013 to

26.09.2014

3. The expected cost of the project will be Rs. 3.97 Lacs.

101

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred

102

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Pooja Bricks Mfg. Industry.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Both mining sites are within 01 Km. Periphery.

The matter is placed before the SEAC for its consideration, please.

103

Item No. 78.31 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Pallian, Bakhjlaur, Tehsil Nawanshahr, Distt. S.B.S.

Nagar by M/s Pritpal Singh BKO, Village Sheikhupur,

Tehsil & Distt. S.B.S. Nagar.

It is submitted that M/s Pritpal Singh BKO, Village Sheikhupur,

Tehsil & Distt. S.B.S. Nagar has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Pallian, Bakhjlaur, Tehsil Nawanshahr, Distt. S.B.S.

Nagar. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.5110 Hectares and is located in the revenue estate of Vill. Pallian,

Bakhjlaur, Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of

bricks in the brick kiln located in the revenue estate of Village Sheikhupur,

Tehsil & Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./Khewal No./ Khatoni

No.

Khasra No./ Total

area of site Lease Period

Site 1 199/106/138 55/11-20

Total area of site = 0.5110 Hect.

1 Year i.e. upto 01.05.2014

3. The expected cost of the project will be Rs. 3.20 Lacs.

The other details of the project are as under:

1. Properly filled Form 1 & Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

104

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

105

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Priptal Singh BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 260 NS dated 30.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

106

Item No. 78.32 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Manan, Dhirowal Tehsil & Distt. Hoshiarpur by M/s

Puri Birck Kiln Industry, Mehatpur, Una Road,

Hoshiarpur.

It is submitted that M/s Puri Birck Kiln Industry, Mehatpur, Una

Road, Hoshiarpur has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Manan, Dhirowal Tehsil & Distt. Hoshiarpur. The project is

covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

4. The mining of minor minerals (brick clay) will be carried out in a total area of 0.9999 Hectares out of which 1 site measuring 0.4470 hectares and 1 site measuring 0.5528 hectares is located in the revenue estate of Vill. Manan, Dhirowal Tehsil & Distt. Hoshiarpur for manufacturing of bricks in the brick kiln located in the revenue estate of Vill. Mehatpur, Una Road, Hoshiarpur

5. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./Khewal No./ Khatoni

No.

Khasra No./ Total

area of site Lease Period

Site 1 341/413,217

/494, 272

30//24/2, 46/3

total area of site

0.5528 hectares

2 Year i.e. upto

08.07.2015

Site 2 338/8,22/18,23 19//24/1, 25/1, 16/1

total area of site

0.4470 hectares

1 year i.e. upto

30.11.2013

6. The expected cost of the project will be Rs. 7.00

Lacs.

The other details of the project are as under:

107

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

g) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

h) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(s) Submitted

(t) Submitted

(u) Submitted

(v) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(w) Rs 25000/- will be incurred for implementation of EMP

108

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(x) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Puri Brick Kiln Industry.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1255 dated 03.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Both mining sites are within 01 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

109

Item No. 78.33 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Mehamdowal Tehsil Garshankar, Distt. Hoshiarpur by

M/s Rupica & Sandeep Bricks , Vill. Gohgroan Near

Kalewal Bhagtan, Near Mahilpur, Distt. Hoshiarpur.

It is submitted that M/s Rupica & Sandeep Bricks , Vill. Gohgroan

Near Kalewal Bhagtan, Distt. Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Mehamdowal Tehsil Garshankar, Distt.

Hoshiarpur . The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area of 1.5250 Hectare and is located in the revenue estate of Mehamdowal Tehsil Garshankar, Distt. Hoshiarpur for manufacturing of bricks in the brick kiln located in the revenue estate of Vill. Gohgroan Near Kalewal Bhagtan, Distt. Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are as under:

Site Hadbast No./

Khewat No./

Khatoni

No.

Khasra No./ Total area of site Lease

Period

Site 1 320 26//3/2, 4/1, 7/1, 8/1/1, 8/2/1,

25//18/3, 18/2, 26//4/2

Total area of site = 1.5250 Hect.

2 Years

till

excavation

3. The expected cost of the project will be Rs. 4.50 Lacs. The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Lease deed of mining area

Submitted

110

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan indicating the following:

c) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

d) Compliance of various environmental regulations.

c) Steps to be taken in case of emergency such as accidents at

the site including fire.

d) For how long period the project proponent will be responsible for implementation of EMP and the name of the person(s) responsible for implementation of EMP.

e) Capital & recurring cost for the EMP per year and the details of

funds for the same.

f) Name of the individual persons / organization, who will be responsible for implementation of EMP after the lapse of the period for which the project proponent

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 25000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

111

is responsible.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Rupica & Sandeep Bricks.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1233 dated 03.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

112

Item No. 78.34 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Dollowal, Tehsil Mukerian, Distt. Hoshiarpur by M/s

Sarswati Brick Mfg. Industries, Vill. Jeo Chak,

Hoshiarpur.

It is submitted that M/s Sarswati Brick Mfg. Industries, Vill. Jeo

Chak, Hoshiarpur has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Dollowal, Tehsil Mukerian, Distt. Hoshiarpur. The project is

covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.3974 Hectare and is located in the revenue estate of Vill. Dollowal,

Tehsil Mukerian, Distt. Hoshiarpur for manufacturing of bricks in the brick

kiln located in the revenue estate of Vill. Jeo Chak, Hoshiarpur.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./

Khewat No./

Khatoni No.

Khasra No./ Total area of site Lease

Period

Site 1 188/19/40 9//3,4,5.

Total area of site = 0.3974 Hectare

17.06.2013 to

16.06.2015

3. The expected cost of the project will be Rs. 5.00 lacs.

The other details of the project are as under:

1. Properly filled Form 1.Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

113

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

114

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Sarswati Brick Manfg. Industries.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Mukerian, Dasuya & Hazipur of Distt. Hoshiarpur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

115

Item No. 78.35 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Dagan, Tehsil Mukerian, Distt. Hoshiarpur by M/s

Shankar Enterprises BKO, Village Dagan, Tehsil

Mukerian, Distt. Hoshiarpur.

It is submitted that M/s Shankar Enterprises BKO, Village Dagan,

Tehsil Mukerian, Distt. Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Dagan, Tehsil Mukerian, Distt.

Hoshiarpur. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.7511 Hectares and is located in the revenue estate of Vill. Dagan,

Tehsil Mukerian, Distt. Hoshiarpur for manufacturing of bricks in the brick

kiln located in the revenue estate of Vill. Dagan, Tehsil Mukerian, Distt.

Hoshiarpur

2. The mining of brick clay will be carried out at site, the details of which is as

under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ Total

area of site

Lease

Period

Site 1 290/22/32 23/5, 23//6, 23/7, 23//8 total area of

site = 0.7511

2 Years i.e upto

20.05.2015

3. The expected cost of the project will be Rs. 3.40 Lacs.

The other details of the project are as under:

1 Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

116

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

117

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? The project proponent shall submit an undertaking to the effect submit an undertaking to the effect that the total area of all borrowing / excavation sites including the area of the propose project within the radius of 500 m from the proposed area of borrowing/ excavation is less than 5 hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Shankar Enterprises BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

118

Item No. 78.36 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Ghorewaha, Tehsil Dasuya, Distt. Hoshiarpur by M/s

Shiv Shakti Brick Indutry (Surinder Pal Brick Kiln, Vill.

Nangal Farid, Hoshiarpur.

It is submitted that M/s Shiv Shakti Brick Indutry (Surinder Pal

Brick Kiln, Vill. Nangal Farid, Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Ghorewaha, Tehsil Dasuya, Distt.

Hoshiarpur . The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.6040 Hectare and is located in the revenue estate of Vill. Ghorewaha,

Tehsil Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick

kiln located in the revenue estate of Vill. Ghorewaha, Tehsil Dasuya, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at one sites, the details of which

are as under:

Site Hadbast No./

Khewat No./

Khatoni

No.

Khasra No./ Total area of site Lease

Period

Site 1 16/71/91 12/4, 12/7, Total area of site

=0.6040 Hectare

16.07.2013

to

16.07.2015

3. The expected cost of the project will be Rs. 2.00 lacs.

The other details of the project are as under:

119

1. Properly filled Form 1 Submitted

2. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

3. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

4. Status of mining at the site, if any, alongwith photographs from all the four sides

Not Submitted

5. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

6. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

7. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 25000/- will be incurred for implementation of EMP

120

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

8. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Shiv Shakti Brick Industry (Surinder Pal Brick Kiln).

9. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Mukerian, Dasuya & Hazipur of Distt. Hoshiarpur.

The matter is placed before the SEAC for its consideration, please.

121

Item No. 78.37 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Ittian, Tehsil Dasuya, Distt. Hoshiarpur by M/s Shiva

Brick Industry, Vill. Ittian, Tehsil Dasuya, Distt.

Hoshiarpur.

It is submitted that M/s Shiva Brick Industry, Vill. Ittian, Tehsil

Dasuya, Distt. Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Ittian, Tehsil Dasuya, Distt. Hoshiarpur. The project

is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 5 Acres 1 Kalan 11 Marlas and is located in the revenue estate of Vill.

Ittian, Tehsil Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the

brick kiln located in the revenue estate of Vill. Ittian, Tehsil Dasuya, Distt.

Hoshiarpur

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./

Khewat No./

Khatoni No.

Khasra No. / Total area of

Land

Lease

Period

Site 1 229/403, 409, 405/

524, 530,526

13//6/1, 13//24/1, 13//24/2, 13//25/1, 14//21/1, 17/1/1, 18//4/2, 18//5/1, 18//5/2,

17//21/1, 18//25/1, 18//25/2, 32//1/2, 14//20/1, 17//18/2, 17//13/1, 17//14/1, 17//14/2,

17//15, 17//6/2, 17//7/1, 18//2 Total area : 5 Acres 1 Kalan 11

Marlas

Ownership

122

3. The expected cost of the project will be Rs. 8.00 Lacs.

The other details of the project are as under:

1. Properly filled Form 1 Submitted

2. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

3. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

4. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

5. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

6. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

7. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible

123

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

8. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Shiva Brick Industries.

9. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

The matter is placed before the SEAC for its consideration, please.

124

Item No. 78.38 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Rally, Mukerian, 0Hoshiarpur by M/s Shiva Krishna

Gram Udyog, Vill. Dagan Tehsil Mukerian, Distt.

Hoshiarpur.

It is submitted that M/s Shiva Krishna Gram Udyog, Vill. Dagan

Tehsil Mukerian, Distt. Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Rally, Mukerian, Hoshiarpur . The project

is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 2 Hectare and is located in the revenue estate of Vill. Rally, Mukerian,

Hoshiarpur, for manufacturing of bricks in the brick kiln located in the

revenue estate of Vill. Rally, Mukerian, Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoni No.

Khasra No./ Total Area Lease

Period

Site

1

365/53,

135/73,182

8//18, 8//23, 22//15, 15//2,

7//20/2, 8//14/2, 8//15/2,

8//16 Total area of land = 2

Hectares

27.09.2013

to

26.09.2014

3. The expected cost of the project will be Rs. 3.60 lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

125

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Not Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 0.50 lacs will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

126

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Shiva Kirshna Gram Udyog.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Mukerian, Dasuya & Hazipur of Distt. Hoshiarpur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

127

Item No. 78.39 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Gagsultan, Tehsil Dasuya, Distt. Hoshiarpur by M/s

Sudesh Kumi BKO, Village Gagsultan, Teshil Dasuya,

Distt. Hoshiarpur.

It is submitted that M/s Sudesh Mukari BKO, Village Gagsultan,

Teshil Dasuya, Distt. Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Gagsultan, Tehsil Dasuya, Distt.

Hoshiarpur. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.7049 Hectares and is located in the revenue estate of Vill. Gagsultan,

Tehsil Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick

kiln located in the revenue estate of Vill. Gagsultan, Tehsil Dasuya, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at two sites, the details of which are as under:

Site Hadbast No./Khewat

No./ Khatoni No.

Khasra No./ Total area of site Lease

Period

Site 1 182/40/43 40//2, 40//3/1/2, 40//8/2, 40//9, 40/10, 40//11, 40//12, 40//13,

40/12, 40//15/4, 40//16

Total area of site = 0.7049

Hectares

Self owned land i.e.

upto

31.03.2015

3. The expected cost of the project will be Rs. 8.15 Lacs.

The other details of the project are as under:

128

1. Properly filled Form 1 & Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

129

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Sudesh Kumari BKO

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not applicable

The matter is placed before the SEAC for its consideration, please.

130

Item No. 78.40 Application for environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Morian, Tehsil Dausya, Distt. Hoshiarpur by M/s Sukhdev Parshad Maini & Co. Vill. Rai Chak, Tehsil

Dasuya , Distt. Hoshiarpur .

It is submitted that M/s Sukhdev Parshad Maini & Co. Vill. Rai Chak, Tehsil Dasuya , Distt. Hoshiarpur has applied for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate of Vill. Morian, Tehsil Dausya, Distt. Hoshiarpur. The project is covered under category 1(a). The MoEF vide office memorandum dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for appraisal of the project proposal under EIA Notification dated 14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area of 1.5946 Hectares and is located in the revenue estate of Vill. Morian, Tehsil Dausya, Distt. Hoshiarpur for manufacturing of bricks in the brick kiln located in the revenue estate of Vill. Rai Chak, Tehsil Dasuya , Distt. Hoshiarpur.

2. The mining of brick clay will be carried out at two sites, the details of which are as under:

Site Hadbast No./Khewat No./ Khatoni

No.

Khasra No./ Total area of

site

Lease

Period

Site 1 168/85/115,110 3//19/1, 3//20/3, 3//20/4, 3//21/1, 3//24/1, 2//13, 2//18,

2//23/1

Total area of site = 1.5946

27.09.2013 to

26.09.2014

3. The expected cost of the project will be Rs. 3.75 Lacs. The other details of the project are as under:

1. Properly filled Form 1 Submitted

2. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

3. Proof of ownership of land/ Registered Lease deed of mining area

Submitted

4. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

131

5. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

6. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

7. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of emergency such as accidents at the site including fire.

d) For how long period the project proponent will be responsible for implementation of EMP and the name of the person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the EMP per year and the details of

funds for the same.

f) Name of the individual persons / organization, who will be responsible for implementation of EMP after the lapse of the period for which the project proponent

is responsible.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

8. Whether the periphery of any other area of borrowing/excavation falls

Submitted an undertaking to the effect that there is no other

132

within a radius of 500 m from the

periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Sukhdev Parshad Maini& Co.

9. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

10 Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

133

Item No. 78.41 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Balagan, Tehsil Dasuya, Distt. Hoshiarpur by M/s

Sukhdev Raj BKO, Vill. Balagan, Tehsil Dasuya, Distt.

Hoshiarpur.

It is submitted that M/s Sukhdev Raj BKO, Vill. Balagan, Tehsil

Dasuya, Distt. Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Balagan, Tehsil Dasuya, Distt. Hoshiarpur. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1 acre 6 Kanal 1 Marla is located in the revenue estate of Vill. Balagan,

Tehsil Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick

kiln located in the revenue estate of Vill. Balagan, Tehsil Dasuya, Distt.

Hoshiarpur

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast

No./Khewat

No. /

Khatoni No.

Khasra No./ Total area of Site Lease

Period

Site 1 133/ 72, 70/

106, 103

3/2/1, 3/2/2, 8/1/1, 8/2/2, 7/1/1, 7/1/2, 7/1/3, 4/1, 4/2, 4/3, 5/2, 22/5/1, 21/1/1, ½ Total area of

Site = acre 6 Kanal 1 Marla

26.09.2013 to

25.09.2018

3. The expected cost of the project will be Rs. 3.55 Lacs.

The other details of the project are as under:

134

1 Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

135

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Sukhdev Raj BKO

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

136

Item No. 78.42 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Kahma, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s

Sukhvir Singh BKO, Village Kahma, Tehsil & Distt.

S.B.S. Nagar.

It is submitted that M/s Sukhvir Singh BKO, Village Kahma, Tehsil

& Distt. S.B.S. Nagar has applied for obtaining environmental clearance under

EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate Vill. Kahma, Tehsil Nawanshahr, Distt. S.B.S. Nagar. The project is

covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.2112 Hectares and is located in the revenue estate of Vill. Kahma,

Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Vill. Kahma, Tehsil Nawanshahr,

Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 112/610/756 10/9, 2, 8, 12, 26, 13, 19/1 14.03.2013 to till

extraction

3. The expected cost of the project will be Rs. 1.55 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

137

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

138

for which the project proponent

is responsible.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Sukhvir Singh BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 260NS dated 30.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

139

Item No. 78.43 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Sehrak Patti, Tehsil Dasuya, Distt. Hoshiarpur by M/s

Trasem Lal & Co., Tehsil Dasuya, Distt. Hosharpur.

It is submitted that M/s Trasem Lal & Co., Tehsil Dasuya, Distt.

Hosharpur has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Sehrak Patti, Tehsil Dasuya, Distt. Hoshiarpur . The project

is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area of

1Acre 6 Kanal and is located in the revenue estate of Vill. Sehrak Patti, Tehsil

Dasuya, Distt. Hoshiarpur, for manufacturing of bricks in the brick kiln located

in the revenue estate of M Vill. Sehrak Patti, Tehsil Dasuya, Distt. Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./ Khatoni

No.

Khasra No./ Total area of site Lease

Period

Site 1 626/718/1051,

1052

21/2, 1/2,22, 2/1, 2/2, Total Area

of Site =1Acre 6 Kanal

2 years i.e upto

28.05.2015

3. The expected cost of the project will be Rs. 5.00 lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

140

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Not Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

141

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Tarsem Lal & Co.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Mukerian, Dasuya & Hazipur of Distt. Hoshiarpur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

142

Item No. 78.44 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Dollowal, Tehsil, Dasuya, Distt. Hoshiarpur by M/s

Vasal & Co., BKO, Vill. Ghogra, Tehsil Dasuya, Distt.

Hoshiarpur .

It is submitted that M/s Vasal & Co., BKO, Vill. Ghogra, Tehsil

Dasuya, Distt. Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Dollowal, Tehsil, Dasuya, Distt. Hoshiarpur. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.8039 Hectare and is located in the revenue estate of Vill. Dollowal,

Tehsil, Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick

kiln located in the revenue estate of Vill. Ghogra, Tehsil, Dasuya, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are as under:

Site Hadbast No./Khewat No./ Khatoni

No.

Khasra No./ Total area of site Lease

Period

Site 1 188/26/50 6/16, 6/17, 6/24, 6/25, 6/18

Total area of site = 1.8039 Hect.

01.11.2012 to

30.10.2014

3. The expected cost of the project will be Rs. 8.75 Lacs.

The other details of the project are as under:

1.

Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

Submitted

2. Proof of ownership of land/ Registered Submitted

143

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

144

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Vasal & Co. BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

145

Item No. 78.45 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Balagan, Tehsil Dasuya, Distt. Hoshiarpur by M/s

Vipan Kumar BKO, Vill. Balagan, Tehsil Dasuya, Distt.

Hoshiarpur.

It is submitted that M/s Vipan Kumar BKO, Vill. Balagan, Tehsil

Dasuya, Distt. Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Balagan, Tehsil Dasuya, Distt. Hoshiarpur. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 2 Acres and is located in the revenue estate of Vill. Balagan, Tehsil

Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Balagan, Tehsil Dasuya, Distt.

Hoshiarpur

2. The mining of brick clay will be carried out at site, the details of which is as

under:

Site Hadbast No./ Khewat

No./ Khatoi No. Khasra No. Lease

Period

Site 1 109/7/8 1567, 1568

Total Area 2 Acres

03.06.2013 to

02.06.2014

3. The expected cost of the project will be Rs. 5.50 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

146

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

147

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Vipin Kumar BKO

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

148

Item No. 78.46 Application for environmental clearance under

EIA notification dated 14.09.2006 for mining of

minor minerals (brick clay) in the revenue estate

of Vill. Tund, Tehsil Dasuya, Distt. Hoshiarpur by

M/s Vishavkarma Brick Industry, Vill. Argowal,

Tehsil Dasuya, Distt. Hoshiarpur

It is submitted that M/s Vishavkarma Brick Industry, Vill. Argowal,

Tehsil Dasuya, Distt. Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Tund, Tehsil Dasuya, Distt. Hoshiarpur.

The project is covered under category 1(a). The MoEF vide office memorandum

dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 2 Acres and is located in the revenue estate of Vill. Tund, Tehsil

Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Argowal, Tehsil Dasuya, Distt.

Hoshiarpur

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat

No./ Khatoi No.

Khasra No./ Total

area of site

Lease

Period

Site 1 14/10/12 1048/78 = total area

0.8017 Hectare

1 year i.e. upto

31.01.2014

3. The expected cost of the project will be Rs. 3.80 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

149

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

150

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Vishavkarma Brick Industry.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013.

Not Applicable

The matter is placed before the SEAC for its consideration, please.

151

Item No. 78.47 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Bhagroan, Tehsil Nawanshahr, Distt. S.B.S. Nagar by

M/s Lucky Brick Kiln Industries Souna, Village & P.O.

Langroya, Tehsil & Distt. District S.B.S. Nagar.

It is submitted that M/s Lucky Brick Kiln Industries Souna, Village

& P.O. Langroya, Tehsil & Distt. District S.B.S. Nagar has applied for obtaining

environmental clearance under EIA notification dated 14.09.2006 for mining of

minor minerals (brick clay) in the revenue estate of Vill. Bhagroan, Tehsil

Nawanshahr, Distt. S.B.S. Nagar. The project is covered under category 1(a). The

MoEF vide office memorandum dated 24.06.2013 categorized the mining of brick

earth/clay as category B-2 for appraisal of the project proposal under EIA

Notification dated 14.06.2006. The details of the project proposal as per Form 1

and pre-feasibility report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.8096 Hectares and is located in the revenue estate of Vill. Bhagroan,

Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Village & P.O. Langroya, Tehsil &

Distt. District S.B.S. Nagar.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 139/274,358, 279, 192/ 350, 457,

358, 242

13//16, 17, 18, 14, 60/456, 13//23, 24, 25/1, 26//5 Min,

5 Min

Total area of site – 0.8096

Hect

1year i.e. upto

01.08.2014

3. The expected cost of the project will be Rs. 1.75 Lacs.

152

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 25000/- will be incurred for implementation of EMP

153

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Lucky Brick Kiln Industries Souna.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 260 Ns dated 30.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in 01 Km. from boundary of mining site.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

154

Item No. 78.48 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Langroya, Tehsil Nawanshahr, Distt. S.B.S. Nagar by

M/s Lucky Brick Kiln Industries Souna, Village & P.O.

Langroya, Tehsil & Distt. District S.B.S. Nagar.

It is submitted that M/s Lucky Brick Kiln Industries Souna, Village

& P.O. Langroya, Tehsil & Distt. District S.B.S. Nagar has applied for obtaining

environmental clearance under EIA notification dated 14.09.2006 for mining of

minor minerals (brick clay) in the revenue estate of Vill. Langroya, Tehsil

Nawanshahr, Distt. S.B.S. Nagar. The project is covered under category 1(a). The

MoEF vide office memorandum dated 24.06.2013 categorized the mining of brick

earth/clay as category B-2 for appraisal of the project proposal under EIA

Notification dated 14.06.2006. The details of the project proposal as per Form 1

and pre-feasibility report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.63 Hectares out of which 1 site is 1.01959 hectares , 2 Site is 0.4046

hectares, 3 Site is 0.2114 hectares and is located in the revenue estate of

Vill. Langroya, Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing

of bricks in the brick kiln located in the revenue estate of Village & P.O.

Langroya, Tehsil & Distt. District S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 137/21/22 8/24/2, 24/3, 25/1, 11/4/1/1,

11/4/1/1

5 years i.e. upto

14.09.2014

3. The expected cost of the project will be Rs. 1.75 Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

155

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 25000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

156

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Lucky Brick Kiln Industries Souna.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in Nawanshahr Range.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

157

Item No. 78.49 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill. Palli

Jhikki, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s

OPK Brick Industry, Vill. Palli Jhikki, Tehsil

Nawanshahr, District S.B.S. Nagar.

It is submitted that M/s OPK Brick Industry, Vill. Palli Jhikki, Tehsil

Nawanshahr, District S.B.S. Nagar. has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Palli Jhikki, Tehsil Nawanshahr, Distt.

S.B.S. Nagar. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.2856 Hectares and is located in the revenue estate of Vill. Palli Jhikki,

Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Vill. Palli Jhikki, Tehsil

Nawanshahr, Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 109/75/136 54//3/3, 4/1, 7, 8/1, 57//6/3,

13/6, 14/1

Total area of site = 0.2856 Hect.

4years i.e. upto

14.09.2017

3. The expected cost of the project will be Rs. 1.75 Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

158

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 30000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

159

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s OPK Brick Industry.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 260 NS dated 30.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in 01 km. from the mining site.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

160

Item No. 78.50 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Talwandi Fattu, Tehsil Nawanshahr, Distt. S.B.S.

Nagar by M/s Pawan Bhalla BKO, Vill. Gunachaur,

Tehsil Nawanshahr, District S.B.S. Nagar.

It is submitted that M/s Pawan Bhalla BKO, Vill. Gunachaur, Tehsil

Nawanshahr, District S.B.S. Nagar has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Talwandi Fattu, Tehsil Nawanshahr,

Distt. S.B.S. Nagar. The project is covered under category 1(a). The MoEF vide

office memorandum dated 24.06.2013 categorized the mining of brick earth/clay

as category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

4. The mining of minor minerals (brick clay) will be

carried out in a total area of 0.42988 Hectares and is located in the

revenue estate of Vill. Palli Jhikki, Tehsil Nawanshahr, Distt. S.B.S. Nagar

for manufacturing of bricks in the brick kiln located in the revenue estate of

Vill. Palli Jhikki, Tehsil Nawanshahr, Distt. S.B.S. Nagar.

5. The mining of brick clay will be carried out at site,

the details of which are as under:

Site Hadbast No./ Khewat No./ Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 191/-/35,36 166/12/2, 19, 20, 21/1, 9/2/1, 9/3, 12/1

Total area of site = 0.42988

Hectares

2years i.e. upto

28.08.2015

6. The expected cost of the project will be Rs. 2.55

Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

161

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

c) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

d) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

(g) Submitted

(h) Submitted

(i) Submitted

(j) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(k) Rs 50000/- will be incurred for implementation of EMP

162

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(l) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Pawan Bhalla BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in Nawanshahr Range.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

163

Item No. 78.51 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Soondh, Tehsil Banga, Distt. S.B.S. Nagar by M/s

Sanjeev & Co. VPO, Godani, Tehsil Banga District,

S.B.S. Nagar.

It is submitted that M/s Sanjeev & Co. VPO, Godani, Tehsil Banga

District, S.B.S. Nagar has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Soondh, Tehsil Banga, Distt. S.B.S. Nagar. The project is

covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 2.4288 Hectares and is located in the revenue estate of Vill. Soondh,

Tehsil Banga, Distt. S.B.S. Nagar for manufacturing of bricks in the brick

kiln located in the revenue estate of VPO, Godani, Tehsil Banga District,

S.B.S. Nagar.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./ Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 28/253/283 43//14, 43//15, 43/16, 43/17, 43/18, 43/24, 43/25,

43/26, 50//4, 50//5/1

Total area of site = 2.4288

Hectares

3years i.e. upto

31.12.2016

3. The expected cost of the project will be Rs. 2.50 Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

164

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

165

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Sanjeev & Co.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in Nawanshahr Range.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

166

Item No. 78.52 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Godani, Tehsil Banga, Distt. S.B.S. Nagar by M/s

Sanjeev & Co. VPO, Godani, Tehsil Banga District,

S.B.S. Nagar.

It is submitted that M/s Sanjeev & Co. VPO, Godani, Tehsil Banga

District, S.B.S. Nagar has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Godani, Tehsil Banga, Distt. S.B.S. Nagar. The project is

covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.2144 Hectares and is located in the revenue estate of Vill. Godani,

Tehsil Banga, Distt. S.B.S. Nagar for manufacturing of bricks in the brick

kiln located in the revenue estate of VPO, Godani, Tehsil Banga District,

S.B.S. Nagar.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 25/160/188 33

Total area of site = 1.2144

Hectares

5 years i.e. upto

29.06.2018

3. The expected cost of the project will be Rs. 2.30 Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

167

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

e) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

f) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(m) Submitted

(n) Submitted

(o) Submitted

(p) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(q) Rs 50000/- will be incurred for implementation of EMP

(r) Farmer will be responsible to take care of the land after the expiry of the lease period.

168

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Sanjeev & Co.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in Nawanshahr Range.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

169

Item No.78.53 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Pallian Khurd, Tehsil Banga, Distt. S.B.S. Nagar by M/s

Baranala Brick Kiln Industries, Vill. Barnala Kalan,

Tehsil & District, S.B.S. Nagar.

It is submitted that M/s Baranala Brick Kiln Industries, Vill.

Barnala Kalan, Tehsil & District, S.B.S. Nagar has applied for obtaining

environmental clearance under EIA notification dated 14.09.2006 for mining of

minor minerals (brick clay) in the revenue estate of Vill. Pallian Khurd, Tehsil

Banga, Distt. S.B.S. Nagar. The project is covered under category 1(a). The MoEF

vide office memorandum dated 24.06.2013 categorized the mining of brick

earth/clay as category B-2 for appraisal of the project proposal under EIA

Notification dated 14.06.2006. The details of the project proposal as per Form 1

and pre-feasibility report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.9178 Hectares and is located in the revenue estate of Vill. Pallian

Khurd, Tehsil Banga, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Vill. Barnala Kalan, Tehsil &

District, S.B.S. Nagar.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 225/81/84 10/4/2/2, 7, 8/2, 13, 14, 27

Total area of site = 0.9178

Hectares

2 years i.e. upto

09.04.2015

3. The expected cost of the project will be Rs. 2.00 Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

170

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

171

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Barnala Brick Kiln Industries.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in Nawanshahr Range.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

172

Item No. 78.54 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Sahiba Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s

Pawan Kumar BKO, Vill. Khurdan, Tehsil Balachaur,

District, S.B.S. Nagar.

It is submitted that M/s Pawan Kumar BKO, Vill. Khurdan, Tehsil

Balachaur, District, S.B.S. Nagar has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Sahiba Tehsil Nawanshahr, Distt. S.B.S.

Nagar. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.8092 Hectares and is located in the revenue estate of Vill. Sahiba

Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Vill. Khurdan, Tehsil Balachaur,

District, S.B.S. Nagar.

2. The mining of brick clay will be carried out at sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 237/223/309 30//1, 2/1, 9/2, 10/1, 10/2

Total area of site = 0.8092

Hectares

1 years i.e. upto

06.03.2014

3. The expected cost of the project will be Rs. 2.60 Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

173

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 30000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

174

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Pawan Kumar BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1259 dated 03.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in 01 Km. Thesil Balachaur

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

175

Item No. 78.55 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Sarhala, Tehsil & Distt. Hoshiarpur by M/s Kamla Rani

BKO, Vill. Sandhara, Hoshiarpur.

It is submitted that M/s Kamla Rani BKO, Vill. Sandhara,

Hoshiarpur has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Sarhala, Tehsil & Distt. Hoshiarpur. The project is covered

under category 1(a). The MoEF vide office memorandum dated 24.06.2013

categorized the mining of brick earth/clay as category B-2 for appraisal of the

project proposal under EIA Notification dated 14.06.2006. The details of the

project proposal as per Form 1 and pre-feasibility report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.2483 Hectares and is located in the revenue estate of Vill. Sandhara,

Hoshiarpur for manufacturing of bricks in the brick kiln located in the

revenue estate of Vill. Sandhara, Hoshiarpur.

2. The mining of brick clay will be carried out at sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 104/247,266/415,

435 178,179, 180

Total area of site = 0.2483

Hect.

1 years i.e. upto

05.06.2014

3. The expected cost of the project will be Rs. 2.50 Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

176

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

177

is responsible.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Kamla Rani BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1293 dated 04.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary within 01 Km periphery of mining site.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

178

Item No. 78.56 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill. Palli

Jhikki, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s

OP Kirpal BKO, Vill. Palli Jhikki, Tehsil & Distt. District

S.B.S. Nagar.

It is submitted that M/s OP Kirpal BKO, Vill. Palli Jhikki, Tehsil &

Distt. District S.B.S. Nagar has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Palli Jhikki, Tehsil Nawanshahr, Distt. S.B.S. Nagar.

The project is covered under category 1(a). The MoEF vide office memorandum

dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.4905 Hectares and is located in the revenue estate of Vill. Palli Jhikki,

Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Vill. Palli Jhikki, Tehsil & Distt.

District S.B.S. Nagar.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 109/75/136,137 54//3/3, 4/1, 7, 8/1,

57//6/3, 13/6, 14/1

Total area of site – 0.4905 Hect.

4years i.e. upto

01.09.2017

3. The expected cost of the project will be Rs. 2.50 Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

179

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 30000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

180

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s OP Kirpal BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in 01 Km. from boundary of mining site.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

181

Item No. 78.57 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill. Jalal

Chak, Tehsil Dasuya, Distt. Hoshiarpur by M/s

Sanjeev Kumar BKO, Village Balagan Tehsil Dasuya,

District Hoshiarpur.

It is submitted that M/s Sanjeev Kumar BKO, Village Balagan

Tehsil Dasuya, District Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Jalal Chak, Tehsil Dasuya, Distt.

Hoshiarpur. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 3 Acres and is located in the revenue estate of Vill. Jalal Chak, Tehsil

Dasuya, Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Balagan, Tehsil Dasuya, Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 184/65,64/79,77 8//22, 23, 24/1, 11//3

Total area of site – 3 Acres

1 year i.e. upto

14.10.2014

3. The expected cost of the project will be Rs. 9.00 Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

182

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 20000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

183

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Sanjeev Kumar BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1193 dated 27.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in Tehsil Dasuya, Mukerian & Tanda.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

184

Item No. 78.58 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Bohara, Tehsil Nawanshahr,Distt. S.B.S. Nagar by M/s

Partapa Ram Duggal & Co. BKO, Vill. Garcha, Tehsil

and Distt. S.B.S. Nagar.

It is submitted that M/s Partapa Ram Duggal & Co. BKO, Vill.

Garcha, Tehsil and Distt. S.B.S. Nagar has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Bohara, Tehsil Nawanshahr,Distt. S.B.S.

Nagar. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.3186 Hectare out of which 1 is 0.1042 Hectare, 2 is 1.2144 Hectare

and is located in the revenue estate of Vill. Bohara, Tehsil

Nawanshahr,Distt. S.B.S. Nagar for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Garcha, Tehsil and Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 176/86/274 12//18, 23 2 year i.e. upto

07.06.2015

Site 2 176/17/28,31 17/5, 6, 15/1, 4/2, 7/1

Total area of Both of sites =1.3186 Hectare

4 Years i.e. upto

30.09.2017

3. The expected cost of the project will be Rs. 2.80 Lacs.

185

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

186

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Partapa Ram Duggal & Co. BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 260 NS dated 30.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in 01 Km. radius.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

187

Item No. 78.59 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Ramrai Pur Tehsil Nawanshahr, Distt. S.B.S. Nagar by

M/s Baranala Brick Kiln Industries, Vill. Barnala Kalan,

Tehsil & District, S.B.S. Nagar.

It is submitted that M/s Baranala Brick Kiln Industries, Vill.

Barnala Kalan, Tehsil & District, S.B.S. Nagar has applied for obtaining

environmental clearance under EIA notification dated 14.09.2006 for mining of

minor minerals (brick clay) in the revenue estate of Vill. Ramrai Pur Tehsil

Nawanshahr, Distt. S.B.S. Nagar. The project is covered under category 1(a). The

MoEF vide office memorandum dated 24.06.2013 categorized the mining of brick

earth/clay as category B-2 for appraisal of the project proposal under EIA

Notification dated 14.06.2006. The details of the project proposal as per Form 1

and pre-feasibility report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.0180 Hectares out of which 1 site is 0.1632 Hectare, 2 site is 0.4048

Hectares and is located in the revenue estate of Vill. Ramrai Pur Tehsil

Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the brick

kiln located in the revenue estate of Vill. Barnala Kalan, Tehsil & District,

S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 155/143,160/198,

89

397, 398, 399, 400, 401,

402

3 years i.e. upto

09.10.2016

Site 2 155/143/198 326, 327, 328, 329, 330, 344

Total area of site = 1.0180

Hectares

3 years i.e. upto

09.10.2016

3. The expected cost of the project will be Rs. 1.75 Lacs.

188

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

189

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Barnala Brick Kiln Industries.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in Nawanshahr Range.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

190

Item No. 78.60 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Dharamkot, Tehsil Nawanshahr, Distt. S.B.S. Nagar by

M/s MRS Bricks, Vill. Malpur, Tehsil Nawanshahr,

Distt. S.B.S. Nagar.

It is submitted that M/s MRS Bricks, Vill. Malpur, Tehsil

Nawanshahr, Distt. S.B.S. Nagar has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Dharamkot, Tehsil Nawanshahr, Distt.

S.B.S. Nagar. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.3540 Hectare and is located in the revenue estate of MRS Bricks, Vill.

Malpur, Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks

in the brick kiln located in the revenue estate of Vill. Malpur, Tehsil

Nawanshahr, Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 168/99/131 2318/1-1847, 2318/1-1847,

2318/1-1847, 2318/1-1847

Total area of sites =0.3540 Hectare

1 year i.e. upto

09.10.2014

3. The expected cost of the project will be Rs. 1.85 Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

191

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 30000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

192

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s MRS Bricks.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in 01 Km. radius.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

193

Item No. 78.61 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Sahabpur, Tehsil Nawanshahr, Distt. S.B.S. Nagar by

M/s Dharamvir Satish kumar BKO, Village Sanawa,

Tehsil & Distt. S.B.S. Nagar.

It is submitted that M/s Dharamvir Satish kumar BKO, Village

Sanawa, Tehsil & Distt. S.B.S. Nagar has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Sahabpur, Tehsil Nawanshahr, Distt.

S.B.S. Nagar. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.1416 Hectare and is located in the revenue estate of Vill. Sahabpur,

Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Village Sanawa, Tehsil & Distt.

S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 153/85,86,88/ 107, 108, 109, 112, 113, 114,

116, 115

587, 579, 825, 581, 576, 585, 586, 588, 589, 590, 583, 577,

578, 50, 582

Total area of site = 1.1416

Hect.

5 years i.e. upto

28.05.2016

3. The expected cost of the project will be Rs. 4.80 Lacs.

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

194

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

195

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of

borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Dharamvir Satish Kumar BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 260 NS dated 30.03.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in 01 Km. radius.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

196

Item No. 78.62 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Jagtewal & Baggowal , Tehsil Balachaur, Distt. S.B.S.

Nagar by M/s Dilbag Singh BKO, Vill. Malewal Kohlian,

Tehsil Balachaur, Distt. S.B.S. Nagar.

It is submitted that M/s Dilbag Singh BKO, Vill. Malewal Kohlian,

Tehsil Balachaur, Distt. S.B.S. Nagar has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Jagtewal & Baggowal , Tehsil Balachaur,

Distt. S.B.S. Nagar. The project is covered under category 1(a). The MoEF vide

office memorandum dated 24.06.2013 categorized the mining of brick earth/clay

as category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.19352 Hectare and is located in the revenue estate of Vill. Jagtewal

& Baggowal , Tehsil Balachaur, Distt. S.B.S. Nagar for manufacturing of

bricks in the brick kiln located in the revenue estate of Vill. Malewal

Kohlian, Tehsil Balachaur, Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at two sites, the details of which

are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 207/16/25 9//12, 9//19

4 years i.e. upto

01.09.2017

Site 2 409/16/16 69//21, 69//22, 70//25, 72//1, 72//2

Total area of both site 1.19352

1 Years i.e. upto

15.07.2014

3. The expected cost of the project will be Rs. 4.80 Lacs.

197

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 30000/- will be incurred for implementation of EMP

198

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Dilbag Singh BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1258 dated 03.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife sanctuary in 01 Km. radius.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Both mining site are within 01 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

199

Item No. 78.63 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Rasulpur Theh, Shehbazpur, & Alachaur, Tehsil

Nawanshahr, Distt. S.B.S. Nagar by M/s R.G. Bricks,

Vill & P.O. Kulam, Tehsil & Distt. S.B.S. Nagar.

It is submitted that M/s R.G. Bricks, Vill & P.O. Kulam, Tehsil &

Distt. S.B.S. Nagar has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate Vill. Rasulpur Theh, Shehbazpur, & Alachaur, Tehsil Nawanshahr,

Distt. S.B.S. Nagar. The project is covered under category 1(a). The MoEF vide

office memorandum dated 24.06.2013 categorized the mining of brick earth/clay

as category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 2.2264 Hectares out of which 1 site is 0.6072 Hect, 2 site is 0.8096

Hectare and 3 site is 0.8096 Hectare is located in the revenue estate of Vill.

Rasulpur Theh, Shehbazpur, & Alachaur, Tehsil Nawanshahr, Distt. S.B.S.

Nagar for manufacturing of bricks in the brick kiln located in the revenue

estate of Vill. & P.O. Kulam, Tehsil & Distt. S.B.S. Nagar. The industry has

also submitted undertaking that the mining site located at (Alachour,

Rasulpur and Shehbazpur) not located more than 1 Km. distance.

2. The mining of brick clay will be carried out at three sites, the details of

which are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of site

Lease Period

Site 1 230/156/196 22/21/1, 3//16/2, 17/2/, 24,

25, 24//4/1, 5/1

3 years i.e. upto

09.10.2015

Site 2 227/153/203,205 2500/0, 5, 250/1/7, 14, 2297/9, 6, 2298/10, 8,

2299/8, 1919/4, 1920/7,

1921/660

3 years i.e. upto

09.10.2015

200

Site 3 131/356/484 2625/22, 2626/22, 2625/22

Total area of site =

2.2264 Hect.

3 years i.e. upto

09.10.2015

3. The expected cost of the project will be Rs. 4.50 Lacs.

The other details of the project are as under:

1. Properly filled Form 1 &Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

(a) Submitted

(b) Submitted

(c) Submitted

201

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? If not, submit an undertaking to the effect that there is no other area of borrowing/excavation within a radius of 500 m from the proposed area of borrowing / excavation.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s R.G. Bricks.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1258 dated 03.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km. from Balachaur Tehsil.

9. Mining sites located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

Boths mining sites are within 01 km. periphery.

The matter is placed before the SEAC for its consideration, please.

202

Item No. 78.64 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Pharala, Tehsil & Distt. S.B.S. Nagar by M/s Bhagwati

Bricks Co., Vill. Pharala, Tehsil & Distt. S.B.S. Nagar.

It is submitted that M/s Bhagwati Bricks Co., Vill. Pharala, Tehsil &

Distt. S.B.S. Nagar has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate Vill. Pharala, Tehsil & Distt. S.B.S. Nagar. The project is covered

under category 1(a). The MoEF vide office memorandum dated 24.06.2013

categorized the mining of brick earth/clay as category B-2 for appraisal of the

project proposal under EIA Notification dated 14.06.2006. The details of the

project proposal as per Form 1 and pre-feasibility report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 2.1338 Hectares out of which 1 site is 0.9108 Hect and 2 site is 0.7590,

3 site is 0.0592, 4 site is 0.4048 Hectare and is located in the revenue

estate of Vill. Pharala, Tehsil & Distt. S.B.S. Nagar for manufacturing of

bricks in the brick kiln located in the revenue estate of Vill. Pharala, Tehsil

& Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at four sites, the details of

which are as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of site

Lease Period

Site 1 18/858/1075 96//9/13, 96//11/13, 96//12/2, 96//12/2, 96//12/8, 96//9/13,

96//12/2, 96//12/5, 96//12/8

2 years i.e. upto

01.08.2015

Site 2 18/856, 2, 3/2303, 2304, 1055, 1056

92//22/2/2, 97//2/1, 97//2/2, 97//2/2, 97//2/3, 97//3/6

10 Years i.e. upto

18.11.2018

Site 3 18/524/688 91//20/2/3, 91//20/5/, 15/2,

92//16/2/1

2 years i.e. upto

31.03.2015

Site 4 18/60/105 99//2/1, 99//2/2, 99//3/1,

99//3/2

1 year i.e. upto

10.09.2014

203

3. The expected cost of the project will be Rs. 4.45 Lacs.

The other details of the project are as under:

1 Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

c) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

d) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

(g) Submitted

(h) Submitted

(i) Submitted

(j) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

204

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(k) Rs 50000/- will be incurred for implementation of EMP

(l) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Bhagwati Brick Co.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining site located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

All mining sites are within 1 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

205

Item No. 78.65 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Ramgarh, Ranewal & Usmanpur , Tehsil Nawanshahr,

Distt. S.B.S. Nagar by M/s Anil Kumar & Son BKO, Vill.

Usmanpur, Tehsil & Distt. S.B.S. Nagar.

It is submitted that M/s Anil Kumar & Son BKO, Vill. Usmanpur,

Tehsil & Distt. S.B.S. Nagar has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate Vill. Ramgarh, Ranewal & Usmanpur , Tehsil Nawanshahr,

Distt. S.B.S. Nagar. The project is covered under category 1(a). The MoEF vide

office memorandum dated 24.06.2013 categorized the mining of brick earth/clay

as category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area of 2.6818 Hectares and is located in the revenue estate of Vill. Ramgarh, Ranewal & Usmanpur, Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the brick kiln located in the revenue estate of Vill. Usmanpur, Tehsil & Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at four sites, the details of which are as under:

Site Hadbast No./ Khewat No./ Khatoi No.

Khasra No./ total

area of site Lease Period

Site 1 152/32/39 4/21, 22, 7/1/1, ½, 10/1,

2 years i.e. upto 09.10.2015

Site 2 152/31/38 6/13/3, 5/13/5, 14/1, 14/3, 15/2, 16, 17

18/1

2 years i.e. upto

09.10.2015

Site3 152/31/38 5/13/3, 5//13/5, 14/1, 14/3, 15/2, 16, 17,

18/1

2 years i.e. upto

09.10.2015

Site 4 233/211/238 3/1/1/2, 10/2/1, 4/6/1 2 years i.e. upto 09.10.2015

Site 5 229/299/391, 392 19//23/2, 24/2, 28//3/2/2, 4/1

2 years i.e. upto 09.10.2015

206

3. The expected cost of the project will be Rs. 4.50 Lacs.

The other details of the project are as under:

1 Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

207

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Anil Kumar & Sons BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining site located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

All mining sites are within 1 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

208

Item No. 78.66 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Sheikhupur , Tehsil Nawanshahr, Distt. S.B.S. Nagar

by M/s Pawan Bhalla BKO, Vill. Gunachaur, Teshil

Nawanshahr, Distt. S.B.S. Nagar.

It is submitted that M/s Pawan Bhalla BKO, Vill. Gunachaur, Teshil

Nawanshahr, Distt. S.B.S. Nagar has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate Vill. Sheikhupur , Tehsil Nawanshahr, Distt.

S.B.S. Nagar. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area of 1.56782 Hectares and is located in the revenue estate of Vill. Sheikhupur , Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the brick kiln located in the revenue estate of Vill. Gunachaur, Teshil Nawanshahr, Distt. S.B.S. Nagar .

2. The mining of brick clay will be carried out at site, the details of which are as under:

Site Hadbast No./ Khewat No./ Khatoi No.

Khasra No./ total area of site Lease

Period

Site 1 182/170,177,187,367/240,

252,258, 517

19//15, 16, 29, 12//9/1, 29, 19//6, 7, 14, 25, 20//2, 8 Min, 11/3, 12/3 Min, 19/1 Min 19/1 Min, 9//23/1, 20//12/3 Min,

20//8, 9/1, 9/4, 9/2, 11/2, 12/2, 19//4/1,4/2, 5, 17, 2//1, 3,

12//19, 25//2/1 min, 2/1min, 20//21/1min, 25//1 min, 26//5

min, 25//1min, 26//5 min, 25//10/1, 20//21/3, 179, 159,

20//21/3, 179, 159, 20//13, 17, 18, 22/2, 23/1, 158, 180, 181,

25//26

5 years i.e. 15.01.2018

3. The expected cost of the project will be Rs. 3.50 Lacs.

209

The other details of the project are as under:

1 Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

e) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

f) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

(m) Submitted

(n) Submitted

(o) Submitted

(p) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

210

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(q) Rs 50000/- will be incurred for implementation of EMP

(r) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area of borrowing/excavation falls within a radius of 500 m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such borrowing/excavation sites? The project proponent shall submit an undertaking to the effect submit an undertaking to the effect that the total area of all borrowing / excavation sites including the area of the propose project within the radius of 500 m from the proposed area of borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Pawan Bhalla BKO.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 260NS dated 30.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining site located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

All mining sites are within 1 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

211

Item No. 78.67 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Bohan, Tehsil & Distt. Hoshiarpur by M/s Bhole

Shankar Bricks Industry, Vill. Barkia Tanoor, Tehsil &

Distt. Hoshiarpur.

It is submitted that M/s Bhole Shankar Bricks Industry, Vill. Barkia Tanoor, Tehsil & Distt. Hoshiarpur has applied for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay) in the revenue estate Vill. Bohan, Tehsil & Distt. Hoshiarpur. The project is covered under category 1(a). The MoEF vide office memorandum dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for appraisal of the project proposal under EIA Notification dated 14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area of 1.56782 Hectares and is located in the revenue estate of Vill. Bohan, Tehsil & Distt. Hoshiarpur for manufacturing of bricks in the brick kiln located in the revenue estate of Vill. Barkia Tanoor, Tehsil & Distt. Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of site

Lease Period

Site 1 295/197, 248, 276, 311, 312, 315, 316, 360, 387, 417, 494, 694, 741,781/3,212, 266, 294, 329, 330, 333, 334, 386, 413, 443, 541, 704, 812,

863.

44//6/2, 44//15/1, 38//23/2, 38//23/8, 38//23/4, 44//2/2, 44//14, 44//3/2, 38//13/1,

38//18/4, 38/23/2, 38//24/1, 38/13/2, 38//23/5, 38/23/6,

38//23/9, 38//23/10, 38//24/2, 38//25/1,

38//25/2, 44//4/2, 44//17

Ownership upto 3

years

3. The expected cost of the project will be Rs. 3.00 Lacs.

The other details of the project are as under:

212

1 Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

213

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Bhole Shankar Bricks Industry, Vill. Barkia, Tanoor, Tehsil & Distt. Hoshiarpur.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1322 dated 08.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining site located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

All mining sites are within 1 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

214

Item No. 78.68 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Bohan, Tehsil & Distt. Hoshiarpur by M/s Surinder

Singh & Bors. B.K.O., V& P.O. Changran, Tehsil & Distt.

Hoshiarpur.

It is submitted that M/s Surinder Singh & Bors. B.K.O., V& P.O.

Changran, Tehsil & Distt. Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate Vill. Bohan, Tehsil & Distt. Hoshiarpur. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.56782 Hectares and is located in the revenue estate of Vill. Bohan,

Tehsil & Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of V& P.O. Changran, Tehsil & Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 295/129,738,864, 974, 81, 641, 864, 1076, 8/140, 809,

955, 1069, 91,

693, 954, 119

37//19, 37//20, 38/24/2, 38//25/1, 38//25/2, 44//4/2,

38//6, 38//7/1, 38/15, 37//11, 37//10, 38//18/1, 38/18/2, 38/18/3, 38/7/1,

38//17, 38/16

Ownership land

sufficient

for 3 years

3. The expected cost of the project will be Rs. 4.00 Lacs.

The other details of the project are as under:

215

1 Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

216

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Surinder Singh & Bros. B.K.O.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1329 dated 08.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining site located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

All mining sites are within 1 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

217

Item No. 78.69 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Bakhlaur, Tehsil & Distt. S.B.S. Nagar by M/s Rana &

Co. BKO, Vill. Mugal Kherabad & P.O. Bakhlaur, Tehsil

& Distt. S.B.S. Nagar.

It is submitted that M/s Rana & Co. BKO, Vill. Mugal Kherabad &

P.O. Bakhlaur, Tehsil & Distt. S.B.S. Nagar has applied for obtaining

environmental clearance under EIA notification dated 14.09.2006 for mining of

minor minerals (brick clay) in the revenue estate Vill. Bakhlaur, Tehsil & Distt.

S.B.S. Nagar. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.3156 Hectares and is located in the revenue estate of Vill. Bakhlaur,

Tehsil & Distt. S.B.S. Nagar for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Mugal Kherabad & P.O. Bakhlaur,

Tehsil & Distt. S.B.S. Nagar.

2. The mining of brick clay will be carried out at site, the details of which are

as under:

Site Hadbast No./ Khewat No./

Khatoi No.

Khasra No./ total area of

site

Lease

Period

Site 1 324, 144/ 397,

398, 182

42//19, 17, 19, 2, 3/1, 3/25, 7, 9/1, 3, 22/2, 23, 24/1,

42/4/1, 49//9, 11, 12, 13, 14, 48//6/1, 1, 6/2, 49/4, 42//12,

14, 24, 48//5/2

3 years i.e. upto

08.07.2016

Site 2 324/396, 397, 398, 399, 400,

401, 402

42/2, 3/1, 3/2, 7, 9/1, 33//22/2, 23, 24/1, 42//4/1,

9, 11, 12, 13

3 years i.e. upto

08.07.2016

3. The expected cost of the project will be Rs. 3.50 Lacs.

The other details of the project are as under:

218

1 Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

c) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

d) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(g) Submitted

(h) Submitted

(i) Submitted

(j) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(k) Rs 50000/- will be incurred for implementation of EMP

219

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(l) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Rana & Co.

8. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining site located more than 1 Km. apart are to be considered as different block/ cluster clearance under EIA

notification dated 14.09.2013

All mining sites are within 1 Km. periphery.

The matter is placed before the SEAC for its consideration, please.

220

Item No. 78.70: Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Mehlanwali, Tehsil & Distt. Hoshiarpur by M/s Billa

Brick Industry, Vill. Bassi Hast Khan, Tehsil & Distt.

Hoshiarpur.

It is submitted that M/s Billa Brick Industry, Vill. Bassi Hast Khan,

Tehsil & Distt. Hoshiarpur. has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Mehlanwali, Tehsil & Distt. Hoshiarpur . The project

is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 3.206 Hectares and is located in the revenue estate of Vill. Mehlanwali,

Tehsil & Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Bassi Hast Khan, Tehsil & Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at sites, the details of which are

as under:

Site Hadbast No./

Khewat No. /

Khatoni

Khasra No./ Total are of site Lease

Period

Site 1 344/77, 362, 39, 76/113, 439, 48,

113, 112

102//5/3, 16, 103//5, 6, 7, 8, 103//15, 16, 104//11, 12, 19, 20,

21, 22, 23, 108//2/1, 3, 103//9, 10, 11,12,13, 19, 20

5 years i.e. upto

05.09.2018

3. The expected cost of the project will be Rs. 4.00 Lacs.

The other details of the project are as under:

221

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

222

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Bill Brick Industry.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km of from boundary of the mining site.

Submitted a copy of letter no. 629 dated 08.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

223

Item No. 78.71 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill. Uchi

Palli, Tehsil Nawanshahr Distt. S.B.S. Nagar by M/s

O.P. Kirpal BKO, Palli Jhikki, Tehsil Nanwanshahr,

Distt. S.B.S. Nagar.

It is submitted that M/s O.P. Kirpal BKO, Palli Jhikki, Tehsil

Nanwanshahr, Distt. S.B.S. Nagar has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Uchi Palli, Tehsil Nawanshahr Distt.

S.B.S. Nagar . The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.015 Hectares and is located in the revenue estate of Vill. Uchi Palli,

Tehsil Nawanshahr Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Vill. Palli Jhikki, Tehsil

Nanwanshahr, Distt. S.B.S.

2. The mining of brick clay will be carried out at sites, the details of which are

as under:

Site Hadbast No./

Khewat No. /

Khatoni

Khasra No./ Total are of site Lease

Period

Site 1 110/5,397/

5,6 7, 505

37//5/1, 5/2, 5/3, 36//2/1, 2/2,

1, 10, 9/1

1 Years i.e. upto

31.03.2014

Site 2 110/244/301 22//11/2, 19/8, 20 2 years i.e. upto

30.06.2015

3. The expected cost of the project will be Rs. 3.25 Lacs.

The other details of the project are as under:

224

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 30000/- will be incurred for implementation of EMP

225

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s OP Kirpal BKO.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

226

Item No. 78.72 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Kharderh, Tehsil & Distt. Hoshiarpur by M/s Billa

Bricks Traders, Vill. Noorpur, Tehsil & Distt.

Hoshiarpur.

It is submitted that M/s Billa Bricks Traders, Vill. Noorpur, Tehsil &

Distt. Hoshiarpur has applied for obtaining environmental clearance under EIA

notification dated 14.09.2006 for mining of minor minerals (brick clay) in the

revenue estate of Vill. Kharderh, Tehsil & Distt. Hoshiarpur . The project is

covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.248 Hectares and is located in the revenue estate of Vill. Kharderh,

Tehsil & Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Noorpur, Tehsil & Distt. Hoshiarpur.

2. The mining of brick clay will be carried out at sites, the details of which are

as under:

Site Hadbast No./

Khewat No. /

Khatoni

Khasra No./ Total are of site Lease

Period

Site 1 98/35,36/

54,55 6//14/2, 6//17/1 1 year i.e.

upto

01.02.2014

3. The expected cost of the project will be Rs. 2.00 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

227

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land after the expiry of the lease period.

228

EMP after the lapse of the period

for which the project proponent

is responsible.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Bill Bricks Traders.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1320 dated 08.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in Tehsil Dasuya, Mukerian & Hajipur.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

229

Item No. 78.73 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Bilaspur, Tehsil & Distt. Hoshiarpur by M/s Hari

Darshan Singh BKO, Vill. Bassi Kikkran, Tehsil & Distt.

Hoshiarpur.

It is submitted that M/s Hari Darshan Singh BKO, Vill. Bassi

Kikkran, Tehsil & Distt. Hoshiarpur has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Bilaspur, Tehsil & Distt. Hoshiarpur. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.291 Hectares and is located in the revenue estate of Vill. Bilaspur,

Tehsil & Distt. Hoshiarpur for manufacturing of bricks in the brick kiln

located in the revenue estate of Vill. Bassi Kikkran, Tehsil & Distt.

Hoshiarpur.

2. The mining of brick clay will be carried out at sites, the details of which are

as under:

Site Hadbast No./

Khewat No. /

Khatoni

Khasra No./ Total are of site Lease Period

Site 1 356/297, 20,

19/378, 58, 56

5//23/1, 8//9/2, 15//1, 9//3/1, 7/2/2, 8/2, 11/1, 12/2, 13/1, 13/2,

14/1, 17/4/1, 18/1, 18/2, 18/3, 19/2, 22//1/1, 8,9, 19, 21//5/1

5 year i.e. upto

03.07.2018

3. The expected cost of the project will be Rs. 3.00 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

230

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

231

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

to take care of the land after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Hari Darshan Singh BKO.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 1327 dated 08.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

232

Item No. 78.74 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Seikhupur Bhag, Tehsil Nawanshahr, Distt. S.B.S.

Nagar by M/s Jagdambey Brick Kiln, Village Majzara

Kalan, Tehsil & Distt.S.B.S. Nagar.

It is submitted that M/s Jagdambey Brick Kiln, Village Majzara

Kalan, Tehsil & Distt.Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Seikhupur Bhag, Tehsil Nawanshahr, Distt. S.B.S.

Nagar. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 1.8207 Hectares and is located in the revenue estate of Vill. Seikhupur

Bhag, Tehsil Nawanshahr for manufacturing of bricks in the brick kiln

located in the revenue estate of Village Majzara Kalan, Tehsil &

Distt.S.B.S. Nagar..

2. The mining of brick clay will be carried out at sites, the details of which are

as under:

Site Hadbast No./

Khewat No. / Khatoni

Khasra No./ Total are of site Lease

Period

Site 1 235/134/174, 175

19//24/2, 25/2, 22//4, 6/1, 7/1, 23//10/1

3 year i.e. upto

31.08.2016

3. The expected cost of the project will be Rs. 5.90 Lacs. The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered

Lease deed of mining area

Submitted

233

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible

to take care of the land after the expiry of the lease period.

234

is responsible.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Jagdambey Brick Kiln.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

235

Item No. 78.75 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Jadla, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s

Jagdambey Brick Kiln, Village Majzara Kalan, Tehsil &

Distt.S.B.S. Nagar.

It is submitted that M/s Jagdambey Brick Kiln, Village Majzara

Kalan, Tehsil & Distt.Hoshiarpur has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Jadla, Tehsil Nawanshahr, Distt. S.B.S. Nagar. The

project is covered under category 1(a). The MoEF vide office memorandum dated

24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.66304 Hectares and is located in the revenue estate of Vill. Jadla,

Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Village Majzara Kalan, Tehsil &

Distt.S.B.S. Nagar.

2. The mining of brick clay will be carried out at sites, the details of which are

as under:

Site Hadbast No./

Khewat No. /

Khatoni

Khasra No./ Total are of site Lease

Period

Site 1 146/533/613 49//24/7, 25, 21, 73//1, 10/1,

74//4, 5, 6

3 years i.e. upto

28.02.2016

3. The expected cost of the project will be Rs. 5.90 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

236

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

237

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Jagdambey Brick Kiln.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 6121 dated 07.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

238

Item No. 78.76 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill.

Kang, Tehsil Nawanshahr, Distt. S.B.S. Nagar by M/s

Partapa Ram Duggal & Co. BKO, Vill. Garcha, Tehsil &

Distt.S.B.S. Nagar.

It is submitted that M/s Partapa Ram Duggal & Co. BKO, Vill.

Garcha, Tehsil & Distt.S.B.S. Nagar has applied for obtaining environmental

clearance under EIA notification dated 14.09.2006 for mining of minor minerals

(brick clay) in the revenue estate of Vill. Kang, Tehsil Nawanshahr, Distt. S.B.S.

Nagar. The project is covered under category 1(a). The MoEF vide office

memorandum dated 24.06.2013 categorized the mining of brick earth/clay as

category B-2 for appraisal of the project proposal under EIA Notification dated

14.06.2006. The details of the project proposal as per Form 1 and pre-feasibility

report are as under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.2074 Hectares and is located in the revenue estate of Vill. Kang,

Tehsil Nawanshahr, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Vill. Garcha, Tehsil & Distt.S.B.S.

Nagar.

2. The mining of brick clay will be carried out at sites, the details of which are

as under:

Site Hadbast No./

Khewat No. /

Khatoni

Khasra No./ Total are of site Lease

Period

Site 1 169/151/161 6//3/8 2 years i.e. upto

21.09.2015

3. The expected cost of the project will be Rs. 45000/-.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

239

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 50000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

240

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Partapa Ram Duggal & Co.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 260 NS dated 30.09.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.

241

Item No. 78.77 Application for environmental clearance under EIA

notification dated 14.09.2006 for mining of minor

minerals (brick clay) in the revenue estate of Vill. Atal

Mazara, Tehsil Balachaur, Distt. S.B.S. Nagar by M/s

Pawan Kumar BKO, Vill. Khurdan, Teshil Balachaur,

Distt.S.B.S. Nagar.

It is submitted that M/s Pawan Kumar BKO, Vill. Khurdan, Teshil

Balachaur, Distt.S.B.S. Nagar has applied for obtaining environmental clearance

under EIA notification dated 14.09.2006 for mining of minor minerals (brick clay)

in the revenue estate of Vill. Atal Mazara, Tehsil Balachaur, Distt. S.B.S. Nagar.

The project is covered under category 1(a). The MoEF vide office memorandum

dated 24.06.2013 categorized the mining of brick earth/clay as category B-2 for

appraisal of the project proposal under EIA Notification dated 14.06.2006. The

details of the project proposal as per Form 1 and pre-feasibility report are as

under:

1. The mining of minor minerals (brick clay) will be carried out in a total area

of 0.4046 Hectares and is located in the revenue estate of Vill. Atal Mazara,

Tehsil Balachaur, Distt. S.B.S. Nagar for manufacturing of bricks in the

brick kiln located in the revenue estate of Vill. Khurdan, Teshil Balachaur,

Distt.S.B.S. Nagar.

2. The mining of brick clay will be carried out at sites, the details of which are

as under:

Site Hadbast No./

Khewat No. /

Khatoni

Khasra No./ Total are of site Lease Period

Site 1 236/

143/ 231 44, 45, 983/48 3 years i.e.

upto

31.07.2016

3. The expected cost of the project will be Rs. 2.30 Lacs.

The other details of the project are as under:

1. Properly filled Form 1. Pre-feasibility report as per Ministry of Environment & Forests, Circular dated 30.12.2010.

Submitted

2. Proof of ownership of land/ Registered Submitted

242

Lease deed of mining area

3. Status of mining at the site, if any, alongwith photographs from all the four sides

Submitted

4. 500 meter radius map of the area from periphery of project site clearly indicating the physical features

Submitted

5.. Site-cum-location plan of the mining site indicating the hadbast number, khasra number and khewat/khatoni number etc on aksh chhajra map.

Submitted

6. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.

b) Compliance of various environmental regulations.

c) Steps to be taken in case of

emergency such as accidents at

the site including fire.

d) For how long period the

project proponent will be

responsible for implementation

of EMP and the name of the

person(s) responsible for

implementation of EMP.

e) Capital & recurring cost for the

EMP per year and the details of

funds for the same.

f) Name of the individual persons /

organization, who will be

(a) Submitted

(b) Submitted

(c) Submitted

(d) Applicant will be responsible for implementation of EMP till the expiry of the lease period.

(e) Rs 30000/- will be incurred for implementation of EMP

(f) Farmer will be responsible to take care of the land

243

responsible for implementation of

EMP after the lapse of the period

for which the project proponent

is responsible.

after the expiry of the lease period.

7. Whether the periphery of any other area

of borrowing/excavation falls within a

radius of 500 m from the periphery of this

area borrowing/excavation or not? If yes,

how much is the total area of all such

borrowing/excavation sites? The project

proponent shall submit an undertaking to

the effect submit an undertaking to the

effect that the total area of all borrowing

/ excavation sites including the area of

the propose project within the radius of

500 m from the proposed area of

borrowing/ excavation is less than 5

hectares.

Submitted an undertaking to the effect that there is no other brick earth mining operations carried out within a radius of 500 m from the proposed mining sites of the M/s Pawan Kumar BKO.

8.. Certificate of Deptt. of Forests & Wildlife Preservation to the effect that there is no boundary of National Park & Wildlife within a radius of 1.0 km

of from boundary of the mining site.

Submitted a copy of letter no. 3305 dated 03.10.2013 from Deptt. of Forests, wherein, it has mentioned that there is no boundary of National Park & Wildlife in 01 Km.

9. Mining sites located more than 1 Km.

apart are to be considered as different

block/ cluster clearance under EIA

notification dated 14.09.2013

Not Applicable

The matter is placed before the SEAC for its consideration, please.